Goals, Objectives, and Policies Capital Improvements Element

Size: px
Start display at page:

Download "Goals, Objectives, and Policies Capital Improvements Element"

Transcription

1 Goals, Objectives, and Policies Capital Improvements Element Background Pursuant to Chapter (3)(a), F.S. and Sections 9J-5.016(3) (a), (b), and (c), F.A.C., the following represents the goals, objectives and policies of Capital Improvements Element. In addition to statutory requirements, the Goals, Objections, and Policies were developed in keeping with the character, conditions, both environmental and social, and desires of the community. These goals, objectives and policies are intended to establish the long-term end for the timely and efficient provision of public facilities through the use of sound fiscal policies. Implementation Unless otherwise stated, the implementation of objectives and associated policies contained in this section shall be through the development, adoption, and application of regulations set forth in the City s Code of Ordinances. Goals, Objectives, and Policies GOAL CIE 1: The City shall maintain a Capital Improvements Program to provide needed public facilities and services to its citizens in a manner that protects investments in existing facilities, maximizes the use of existing facilities and promotes orderly, compact growth. Capital Improvements Prioritization Objective CIE 1.1: Use the Capital Improvements Element as a capital facility management tool to correct existing deficiencies, accommodate desired future growth, replace worn out or obsolete facilities, and organize capital expenditures. A financially feasible program of capital improvements will be implemented Policy CIE 1.1.1: The City shall include all projects of $25,000 or larger, identified in the other elements of this comprehensive plan as necessary to maintain the adopted levels of service, implement a City program or initiative or correct existing deficiencies in the five-year Capital Improvements Plan. Policy CIE 1.1.2: The City Commission shall continue to evaluate and rank, in order of priority, projects proposed for inclusion in the City s five-year LOS-Related Schedule of Capital Improvements. Capital Improvements shall be programmed consistent with available revenues in the major areas of Transportation, Water/Sewer, Stormwater, and Parks. Policy CIE 1.1.3: As part of its annual budget process, the City shall update the five year LOS-Related Schedule of Capital Improvements to: a. reflect existing and projected capital needs in accordance with adopted level of service standards; b. reflect the elimination, deferral, or delay of construction of any facilities or service; and c. assess capital project costs against projected revenues and expenditures. Policy CIE 1.1.4: Proposed capital improvement projects shall be evaluated and ranked in order of priority according to the following guidelines: Page 8-1

2 a. Project is needed to eliminate a proven or obvious hazard to public health and safety; b. Project is needed to fulfill a legal commitment by the City; c. Project is needed to preserve, maintain, refurbish, or achieve full use of existing facilities; d. Project will provide or bring an existing facility up to an adopted level of service; e. Project will increase efficiency or use of existing facilities, prevents or reduces future improvement cost, or provides service to all residents equitably; f. Project will increase the economic base or quality of life of the residents; g. Budget impact of project, both capital and operating, and financial feasibility of project will be considered to assure financial feasibility; h. Project will be reviewed for consistency with plans of other agencies having responsibility for public facilities within the jurisdiction; and i. Project involves a public-private partnership. Policy CIE 1.1.5: The City shall continue to seek to secure grants or private funds to finance needed capital improvements. Policy CIE 1.1.6: Should a public referendum be utilized to provide for funding for any capital project identified in this Comprehensive Plan and should such referendum fail, the City shall utilize other fiscally sound funding alternatives as listed in the City s fiveyear LOS-Related Schedule of Capital Improvements or amend this element accordingly. Should any project funding be dependent on any other outside source, such as a developer s agreement or funding from another government entity, such funding must be guaranteed in the form of a development agreement or interlocal agreement before that project can be included within the first three years in such Schedule as committed funding. Projects that are dependent upon future funding that are planned but not committed may be placed in years four or five of such Schedule, but funding must be committed to such projects prior to their inclusion in years one through three or such projects must be delayed to year four or five, or removed from the Schedule. Policy CIE 1.1.7: Corrections and modifications to the City s five-year LOS-Related Schedule of Capital Improvements concerning costs; revenue sources; or acceptance of facilities pursuant to dedications which are consistent with the plan may be accomplished by ordinance and shall not be deemed to be amendments to the local comprehensive plan. A copy of the ordinance shall be transmitted to the state land planning agency. An amendment to the comprehensive plan is required to update the schedule on an annual basis or to eliminate, defer, or delay the construction for any facility listed in the 5-year schedule. Capital Improvements element amendment require only a single public hearing before the governing board which shall be an adoption hearing as described in Section (7), Fla. Stat. and are not subject to the requirements of Section (3)-(6), Fla. Stat. Policy CIE 1.1.8: The City of Dade City adopts Table CIE-1: Adopted: 05/08/01 Page 8-2

3 Project Funding FY FY Total Spending Potable Water Capital Improvements Orange Valley Supply Well Tank Hill Pumping Station Utility Revenues, - $ 715, Penny For Pasco Total Project - $ 715, $ 715,000 State Revolving - - $1,700, Loan Fund Total Project - - $1,700, $1,700,000 St. Joe Developer $346,000 - Distribution Main Contribution Total Project $346,000 $346,000 Extension CR 535 Main Developer $234,000 (Lakeland Contribution $234,000 Hwy) Total Project $234,000 Morningside Developer $244,000 Drive Contribution $244,000 Distribution Total Project $244,000 Main Project Funding FY FY Total Spending US 301 Developer $450,000 - McDonald Contribution $450,000 Clinton Connector Total Project $450,000 - Total s $ 715,000 $1,700,000 $450,000 $824,000 $3,689,000 Stormwater Management Capital Improvements Beauchamp Ponds Stormwater Construction Downtown Stormwater Design Project Stormwater Construction Project Penny for Pasco $110, Total Project $110, $110,500 SWFWMD $1,150,000 Grant. SR :Loan Fund - $1,150, $2,300,000 Total Project - $2,300,000 Stormwater Fees - - $ 120,000 - $120,000 Total Project - - $ 120,000 - $120,000 SWFWMD $2,300,000 - Grant Total Project $2,300,000 - $ 240,000 $2,300,000 Total s $110,500 $2,300,000 $120,000 2,300,000 $120,000 $4,950,500 Pavement Mgt/Roadway Capital Improvements Pavement Resurfacing St. Joe Roundabout Penny for Pasco $316,403 $200,000 $200,000 $200,000 $200,000 General Fund $200,000 Total Project $516,403 $200,000 $200,000 $200,000 $200,000 FDOT Lap Funds - - $325, Transportation - - $325, Impact Fee Total Project - - $650, $1,316,403 $ 650,000 Page 8-3

4 Sidewalks Penny for Pasco $40, Total Project $40, $ 40,000 Total s $556,403 $ 200,000 $850,000 $200,000 $200,000 $ 2,006,403 Wastewater Capital Improvements Liftstation Rehabilitation (Phase 1B) JDR Forcemain Connection Rehabilitation of Existing Capacity at Wastewater Treatment Plant (1.5MGD) State Revolving Loan Total Project Penny For Pasco Total Project State Revolving Loan Fund $1,633, $1,633, $75, $75,000 $2,045, $ $1,633,000 $ 75,000 $ 2,045,000 Total Project $2,045, Construct Master Sewer Impact $1,185,300 $1,185,300 Pump Station Fee Total Project $1,185,300 Total s 3,678,000 $1,260,300 $4,938,300 Park System Capital Improvements Mickens Field Penny for $110, Improvements Pasco $110,000 Total Project $110, Price Park Penny for $90, Improvements Pasco $ 90,000 Total Project $90, Hardy Trail Extension Developer Contribution $150,000 FDOT Enhanced Funds - $800, $ 950,000 Total Project - $800, $150,000 Watson Park Penny for $50, $50,000 Improvements Pasco Beauchamp SWFWMD - - $500,000 - Stormwater Penny for $75, Pasco $575,000 Total Project $75, $500,000 - Total s $325,000 $800,000 $500,000 $150,000 $1,775,000 TOTAL CAPITAL COSTS $4,669,903 $4,015,000 $2,670,000 $3,450,000 $2,479,300 $17,284,203 Adopted: 05/08/01 Page 8-4

5 Budgetary Policy Objective CIE 1.2: Through the budgetary process, manage future debt in a manner to that maintains the integrity of its City fiscal resources. Policy CIE 1.2.1: The City shall confine long-term borrowing to capital improvements too large to be financed from current revenues. Policy CIE 1.2.2: The City will ensure that any bonds issued will be structured to be paid back within a period not to exceed the expected useful life of the capital project unless the project is mandated by a regulatory agency. Policy CIE 1.2.3: Where possible, special assessment, revenue, or other self-supporting bonds will be used instead of general obligation bonds. Policy CIE 1.2.4: Prior to the adoption of any impact fees or special assessments, the City Commission shall assess whether the associated capital improvement benefits the entire community or only one area or sector of the community. If found to be of benefit to only one area or sector of the community, the impact fee or special assessment shall be applied to that one area or sector only. Policy CIE 1.2.5: Total debt service for general obligation debt will not exceed 10 percent of net operating revenues. Levels of Service Objective CIE 1.3: Manage the land development process so that public facility needs created by previously issued development orders or future development do not exceed the funding abilities of the City. Policy CIE 1.3.1: The City shall implement a concurrency management system to ensure that at the time a development order is issued adequate facility capacity is available or will be available when needed to serve the development, or as otherwise provided for in Rule 9J , FAC. Policy CIE 1.3.2: The adopted levels of service standards for public facilities within the jurisdiction of the City of Dade City shall be those adopted in the Transportation, Public Facilities, and Recreation/Open Space elements of this Plan. Policy CIE 1.3.3: Development orders issued prior to adoption of the EAR-based amendments on May 8, 2001, shall be presumed to have adequate public facility services consistent with the level of service standards contained herein. Facility s and Development Objective CIE 1.4: Future development shall bear a proportionate cost of facility improvements necessitated by the development to maintain adopted level of service standards. Page 8-5

6 Consistency Policy CIE 1.4.1: The City shall assess new developments a pro rata share of the costs to provide public facility improvements to maintain adopted level of service standards. Policy CIE 1.4.2: Through the building permit process, the City shall coordinate with Pasco County, the Pasco County MPO, and the Florida Department of Transportation to ensure that public facility improvement projects located within the City are funded in a fiscally equitable manner apportioning the costs among those who are responsible for it. Objective CIE 1.5: Maintain adopted level of service standards as specified in the individual elements of this Comprehensive Plan and meet existing and future facility needs by coordinating land use decisions and available or projected fiscal resources with the LOS- Related Schedule of Capital Improvements. Policy CIE 1.5.1: The City shall use fiscal policies to direct expenditures for capital improvements that recognize and are consistent with the policies of the other comprehensive plan elements. Adopted: 05/08/01 Page 8-6

Capital Improvements

Capital Improvements Capital Improvements CAPITAL IMPROVEMENT ELEMENT GOAL 7-1: PROVIDE & MAINTAIN PUBLIC FACILITIES AND SERVICES Provide and maintain public facilities and services which protect and promote the public health,

More information

TABLE OF CONTENTS LIST OF TABLES

TABLE OF CONTENTS LIST OF TABLES TABLE OF CONTENTS A. GOALS, OBJECTIVES, AND POLICIES... 3 B. SUMMARY... 17 LIST OF TABLES Table IX 1: City of Winter Springs Five-Year Schedule of Capital Improvements (SCI) FY 2013/14-2017/18... 11 Table

More information

CAPITAL IMPROVEMENTS ELEMENT:

CAPITAL IMPROVEMENTS ELEMENT: CAPITAL IMPROVEMENTS ELEMENT: Goals, Objectives and Policies Goal 1. The provision of needed public facilities in a timely manner, which protects investments in existing facilities, maximizes the use of

More information

ORDINANCE NO

ORDINANCE NO ORDINANCE NO. 4-217 AN ORDINANCE OF THE CITY OF SEMINOLE, FLORIDA, AMENDING THE CITY OF SEMINOLE COMPREHENSIVE PLAN, GOALS OBJECTIVES AND POLICIES OF THE CAPITAL IMPROVEMENTS ELEMENT; REPEALING THE PUBLIC

More information

CAPITAL IMPROVEMENTS ELEMENT

CAPITAL IMPROVEMENTS ELEMENT [COMPREHENSIVE PLAN] 2025 INTRODUCTION EXHIBIT F CAPITAL IMPROVEMENTS ELEMENT A primary purpose of the Capital Improvements Element (CIE) is to assess and demonstrate the financial feasibility of the Clay

More information

1. identifies the required capacity of capital improvements to serve existing and future development based on level-of-service (LOS) standards;

1. identifies the required capacity of capital improvements to serve existing and future development based on level-of-service (LOS) standards; DIVISION 4.200 CAPITAL IMPROVEMENTS ELEMENT SECTION 4.201 INTRODUCTION The purpose of the Capital Improvements Element (CIE) is to tie the capital improvement needs identified in the other elements to

More information

PALM BEACH COUNTY CAPITAL IMPROVEMENT PROGRAM

PALM BEACH COUNTY CAPITAL IMPROVEMENT PROGRAM Palm Beach County (the County) provides the needed and desired urban services to the public. In order to provide these services, the County must furnish and maintain capital facilities and equipment, such

More information

Chapter Ten, Capital Improvements Element City of St. Petersburg Comprehensive Plan

Chapter Ten, Capital Improvements Element City of St. Petersburg Comprehensive Plan CAPITAL IMPROVEMENTS ELEMENT Sections: 10.1 INTRODUCTION 10. 2 GOALS, OBJECTIVES AND POLICIES ISSUE: Construction of needed improvements ISSUE: Adequate provision of public facilities ISSUE: Public expenditure

More information

CAPITAL IMPROVEMENTS ELEMENT

CAPITAL IMPROVEMENTS ELEMENT Goals, Objectives and Policies CAPITAL IMPROVEMENTS ELEMENT GOAL 9.1.: USE SOUND FISCAL POLICIES TO PROVIDE ADEQUATE PUBLIC FACILITIES TO ALL RESIDENTS WITHIN THE CITY. FISCAL POLICIES MUST PROTECT INVESTMENTS

More information

TABLE OF CONTENTS INTRODUCTION... 1 CAPITAL IMPROVEMENTS INVENTORY AND ANALYSIS... 1 DEFINITIONS... 2 DATA INVENTORY... 23

TABLE OF CONTENTS INTRODUCTION... 1 CAPITAL IMPROVEMENTS INVENTORY AND ANALYSIS... 1 DEFINITIONS... 2 DATA INVENTORY... 23 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 Chapter 8 TABLE OF CONTENTS INTRODUCTION... 1 CAPITAL IMPROVEMENTS INVENTORY AND

More information

CAPITAL IMPROVEMENTS ELEMENT

CAPITAL IMPROVEMENTS ELEMENT GOALS, OBJECTIVES AND POLICIES Goal 1.0.0. To annually adopt and utilize a 5-Year Capital Improvements Program and Annual Capital Budget to coordinate the timing and to prioritize the construction and

More information

CAPITAL IMPROVEMENTS ELEMENT

CAPITAL IMPROVEMENTS ELEMENT CAPITAL IMPROVEMENTS ELEMENT INTRODUCTION The purpose of the Capital Improvements Element is to consider the need for and the location of public facilities in order to encourage the efficient use of such

More information

AGENDA REPORT. DATE: November 27, City Commission. Kim D. Leinbach, Interim City Manager

AGENDA REPORT. DATE: November 27, City Commission. Kim D. Leinbach, Interim City Manager AGENDA REPORT DATE: November 27, 2017 TO: FROM: SUBJECT: City Commission Kim D. Leinbach, Interim City Manager Set a public hearing to consider the adoption of the annual update of the 5-Year Schedule

More information

Nassau County 2030 Comprehensive Plan. Capital Improvements Element (CI) Goals, Objectives and Policies. Goal

Nassau County 2030 Comprehensive Plan. Capital Improvements Element (CI) Goals, Objectives and Policies. Goal (CI) Goal Based on the premise that existing taxpayers should not have to bear the financial burden of growth-related infrastructure needs, Ensure the orderly and efficient provision of infrastructure

More information

The $1.620 million Commercial Container Acquisition CIP project is planned through Solid Waste funds.

The $1.620 million Commercial Container Acquisition CIP project is planned through Solid Waste funds. I. CAPITAL IMPROVEMENTS ELEMENT INTRODUCTION The intent of the capital improvements element is to provide a component that outlines principles for construction, extension, or increase in capacity of public

More information

CAPITAL IMPROVEMENTS ELEMENT GOALS, OBJECTIVES, AND POLICIES

CAPITAL IMPROVEMENTS ELEMENT GOALS, OBJECTIVES, AND POLICIES CAPITAL IMPROVEMENTS ELEMENT GOALS, OBJECTIVES, AND POLICIES Goal 9 The City shall ensure adequate and timely public facilities and infrastructure capacity to accommodate existing and future residents

More information

Pinellas County Capital Improvement Program, FY2011 Through FY2016 INTRODUCTION AND BACKGROUND

Pinellas County Capital Improvement Program, FY2011 Through FY2016 INTRODUCTION AND BACKGROUND Introduction to the Six-Year Capital Improvement Program (CIP) The Pinellas County Capital Improvement Program (CIP) is a comprehensive six-year plan of proposed capital projects, intended to identify

More information

CHAPTER 9 CAPITAL FACILITIES ELEMENT

CHAPTER 9 CAPITAL FACILITIES ELEMENT Town of La Conner Comprehensive Plan Capital Facilities Element CHAPTER 9 CAPITAL FACILITIES ELEMENT Introduction The Capital Facilities Element sets policy direction for determining capital improvement

More information

CAPITAL IMPROVEMENTS. City of St. Augustine Comprehensive Plan EAR-Based Amendments

CAPITAL IMPROVEMENTS. City of St. Augustine Comprehensive Plan EAR-Based Amendments CAPITAL IMPROVEMENTS City of St. Augustine Comprehensive Plan EAR-Based Amendments CAPITAL IMPROVEMENTS ELEMENT CI Goal 1 The City shall manage its financial resources to adequately provide public facilities

More information

CAPITAL IMPROVEMENTS ELEMENT GOALS, OBJECTIVES AND POLICIES. Goal 1: [CI] (EFF. 7/16/90)

CAPITAL IMPROVEMENTS ELEMENT GOALS, OBJECTIVES AND POLICIES. Goal 1: [CI] (EFF. 7/16/90) CAPITAL IMPROVEMENTS ELEMENT GOALS, OBJECTIVES AND POLICIES Goal 1: [CI] (EFF. 7/16/90) To use sound fiscal policies to provide adequate public facilities concurrent with, or prior to development in order

More information

CAPITAL BUDGET AND MULTI-YEAR CAPITAL PLAN SECTION 1 INTRODUCTION INTRODUCTION. Purpose of the Capital Improvement Plan

CAPITAL BUDGET AND MULTI-YEAR CAPITAL PLAN SECTION 1 INTRODUCTION INTRODUCTION. Purpose of the Capital Improvement Plan INTRODUCTION Purpose of the Capital Improvement Plan The Multi-Year Capital Plan (the Capital Improvement Plan or CIP) is an official statement of public policy regarding long-range physical development

More information

CAPITAL IMPROVEMENT ELEMENT Inventory Analysis

CAPITAL IMPROVEMENT ELEMENT Inventory Analysis CAPITAL IMPROVEMENT ELEMENT Inventory Analysis 2.191 INTRODUCTION The principal purpose of this element is to identify the capital improvements that are needed to implement the comprehensive plan and ensure

More information

8. CAPITAL IMPROVEMENT ELEMENT Goals, Objectives, and Policies

8. CAPITAL IMPROVEMENT ELEMENT Goals, Objectives, and Policies 8. Goals, Objectives, and Policies GOAL 8-1: TO USE SOUND FISCAL POLICIES TO PROVIDE PUBLIC FACILITIES AND SERVICES CONCURRENT WITH DEVELOPMENT/REDEVELOPMENT IN ORDER TO ACHIEVE AND MAINTAIN ADOPTED STANDARDS

More information

This page intentionally blank. Capital Facilities Chapter Relationship to Vision. Capital Facilities Chapter Concepts

This page intentionally blank. Capital Facilities Chapter Relationship to Vision. Capital Facilities Chapter Concepts This page intentionally blank. Capital Facilities Chapter Relationship to Vision Vision County Government. County government that is accountable and accessible; encourages citizen participation; seeks

More information

Capital Improvements Element

Capital Improvements Element [This page intentionally left blank.] Table of Contents I. Purpose... CIE-1 II. Inventory... CIE-1 Public Health and Public Education Facilities... CIE-1 Needs Derived from Other Elements... CIE-2 Financial

More information

Policy CIE The following are the minimum acceptable LOS standards to be utilized in planning for capital improvement needs:

Policy CIE The following are the minimum acceptable LOS standards to be utilized in planning for capital improvement needs: Vision Statement: Provide high quality public facilities that meet and exceed the minimum level of service standards. Goals, Objectives and Policies: Goal CIE-1. The City shall provide for facilities and

More information

2025 Comprehensive Plan for the City of Temple Terrace Florida. Capital Improvements. Adopted by City Council June 30, 2009

2025 Comprehensive Plan for the City of Temple Terrace Florida. Capital Improvements. Adopted by City Council June 30, 2009 2025 Comprehensive Plan for the City of Temple Terrace Florida Capital Improvements Adopted by City Council June 30, 2009 Effective Date September 22, 2009 THIS PAGE INTENTIONALLY BLANK Comprehensive Plan

More information

City Services Appendix

City Services Appendix Technical vices 1.0 Introduction... 1 1.1 The Capital Facilities Plan... 1 1.2 Utilities Plan... 2 1.3 Key Principles Guiding Bremerton s Capital Investments... 3 1.4 Capital Facilities and Utilities Addressed

More information

2025 COMPREHENSIVE PLAN PASCO COUNTY, FLORIDA CHAPTER 11 TABLE OF CONTENTS

2025 COMPREHENSIVE PLAN PASCO COUNTY, FLORIDA CHAPTER 11 TABLE OF CONTENTS CHAPTER 11 TABLE OF CONTENTS GOALS, OBJECTIVES, AND POLICIES 11-1 CAPITAL IMPROVEMENTS GOALS, OBJECTIVES, AND POLICIES 11-1 Goal CIE 1: Timely and Efficient Provision of Adequate Public Facilities Through

More information

TOWN OF CARY CAPITAL IMPROVEMENTS BUDGET OVERVIEW FOR FISCAL YEAR 2015

TOWN OF CARY CAPITAL IMPROVEMENTS BUDGET OVERVIEW FOR FISCAL YEAR 2015 TOWN OF CARY CAPITAL IMPROVEMENTS BUDGET OVERVIEW FOR FISCAL YEAR 2015 The Capital Improvements Budget/Plan Process Each year, staff prepares a capital improvements budget and a long range capital improvements

More information

13.0 Capital Improvements

13.0 Capital Improvements 13.0 Capital Improvements Goal 1: To Provide Capital Facilities to Meet the Space Needs of the University on a Continuing Basis as the Needs are Identified. Objective 1.1: Provide a schedule of capital

More information

Vision, Mission, Values and Critical Success Factors

Vision, Mission, Values and Critical Success Factors Approved Budget Vision, Mission, Values and Critical Success Factors The City of Tallahassee, through workshops, surveys and commission retreats has developed the following vision, mission, and target

More information

C APITA L IMPRO VEMENTS S CHEDULE (FIGURE CI-14)

C APITA L IMPRO VEMENTS S CHEDULE (FIGURE CI-14) August 20, 2018 Staff Report to the Municipal Planning Board G M P 2 0 1 8-1 0 0 2 0 I TEM 6 S U M M A RY Applicant City of Orlando Requested Actions 1. Amend Figure CI-14 and Policy 2.2.30 of the Capital

More information

Chapter 5: Cost and Revenues Assumptions

Chapter 5: Cost and Revenues Assumptions Chapter 5: Cost and Revenues Assumptions Chapter 5: Cost and Revenues Assumptions INTRODUCTION This chapter documents the assumptions that were used to develop unit costs and revenue estimates for the

More information

ARTICLE 8.6 PROPORTIONATE FAIR-SHARE PROGRAM [Enacted by Ord /5/06]

ARTICLE 8.6 PROPORTIONATE FAIR-SHARE PROGRAM [Enacted by Ord /5/06] ARTICLE 8.6 ARTICLE 8.6 PROPORTIONATE FAIR-SHARE PROGRAM [Enacted by Ord. 74-06 12/5/06] (A) Purpose and Intent: The purpose of this section is to establish a method whereby the impacts of development

More information

Capital Improvements Element. Goals, Objectives and Policies

Capital Improvements Element. Goals, Objectives and Policies VIII. Goals, Objectives and Policies Amendments: Ordinance 2014-11, Adopted December 9, 2014 Ordinance 2016-5, Adopted January 12, 2016 Ordinance 2017-1, Adopted January 10, 2017 VIII. GOAL VIII-1: GLADES

More information

Capital Improvements i

Capital Improvements i CAPITAL IMPROVEMENTS TABLE OF CONTENTS I. INTRODUCTION...1 II. INVENTORY OF PUBLIC FACILITY NEEDS...1 A. Capital Needs Derived from Other Elements...1 B. Cost Estimates for Identified Capital Needs...2

More information

Year /2015. Year /2016. Tuskawilla 8 $ 567,000 $ - $ 300,000 $ - $ - $ 867,000 FLUE 1.3.1; CIE 1.3.3; IE IV.A.1.5; HE 1.

Year /2015. Year /2016. Tuskawilla 8 $ 567,000 $ - $ 300,000 $ - $ - $ 867,000 FLUE 1.3.1; CIE 1.3.3; IE IV.A.1.5; HE 1. Table IX1: City of FiveYear Schedule of Capital (SCI) FY 2013/2014 PARKS & RECREATION Magnolia Park CF305 & Description / Justification acreage for active recreation []. (Years 15) 10 $ 1,217,125 $ $ $

More information

CHAPTER 11. CAPITAL FACILITIES PLAN ELEMENT

CHAPTER 11. CAPITAL FACILITIES PLAN ELEMENT CHAPTER 11. CAPITAL FACILITIES PLAN ELEMENT 11.1 INTRODUCTION A is one of eight elements required by the Growth Management Act (GMA) to be included in Yakima County s comprehensive plan. The reason for

More information

Introduced by the Council President at the request of the Joint. Planning Committee & substituted by the Land Use and Zoning Committee:

Introduced by the Council President at the request of the Joint. Planning Committee & substituted by the Land Use and Zoning Committee: Substituted //0 Introduced by the Council President at the request of the Joint Planning Committee & substituted by the Land Use and Zoning Committee: ORDINANCE 0--E AN ORDINANCE AMENDING CHAPTER, ORDINANCE

More information

In FY , the following projects will be actively under design or construction:

In FY , the following projects will be actively under design or construction: PASCO COUNTY FISCAL YEAR 216-22 CAPITAL IMPROVEMENT PLAN INTERNAL SERVICES The Pasco County Board of County Commissioners has a broad responsibility to provide equipment, buildings, and other facilities

More information

Working with Proportionate Fair-Share

Working with Proportionate Fair-Share Working with Proportionate Fair-Share December 2006 Presented by the Florida Department of Transportation Working with Proportionate Fair-Share Volume 1, December 2006 Presented by the Florida Department

More information

Working with Proportionate Fair-Share

Working with Proportionate Fair-Share Working with Proportionate Fair-Share Final Volume 1, December 2006 Presented by the Florida Department of Transportation Table of Contents MPO RSI Metropolitan Planning Organization Roadway Segment Improvement

More information

Item Amend Capital Improvements Element

Item Amend Capital Improvements Element Item 05-15 Amend Capital Improvements Element CHAPTER 15 CAPITAL IMPROVEMENTS ELEMENT Page 1 of 38 CHAPTER 15 CAPITAL IMPROVEMENTS ELEMENT A. OVERVIEW The Capital Improvements Element is essentially the

More information

Pasco County Fiscal Year 2016 Proposed Fiscal Plan. Debt Service

Pasco County Fiscal Year 2016 Proposed Fiscal Plan. Debt Service Mission Statement Proposed Fiscal Plan This section displays the annual cost of payments on debt issued to the Board of County Commissioners (BCC) under various funds. uses Municipal Revenue Bonds as a

More information

TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M. To: Council Members AGENDA ITEM 5J

TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M. To: Council Members AGENDA ITEM 5J TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M To: Council Members AGENDA ITEM 5J From: Date: Subject: Staff September 18, 2009 Council Meeting Local Government Comprehensive Plan Review

More information

Georgetown Planning Department Plan Annual Update: Background

Georgetown Planning Department Plan Annual Update: Background 2030 Plan Annual Update: 2014 Background The 2030 Comprehensive Plan was unanimously adopted by City Council on February 26, 2008. The Plan was an update from Georgetown s 1988 Century Plan. One of the

More information

Chapter VIII. General Plan Implementation A. INTRODUCTION B. SUBMITTAL AND APPROVAL OF SUBSEQUENT PROJECTS C. SPHERE OF INFLUENCE

Chapter VIII. General Plan Implementation A. INTRODUCTION B. SUBMITTAL AND APPROVAL OF SUBSEQUENT PROJECTS C. SPHERE OF INFLUENCE Chapter VIII General Plan Implementation A. INTRODUCTION This chapter presents a variety of tools available to the (City) to help build the physical city envisioned in Chapter III. While the Modesto provides

More information

C APITA L IMPRO VEMENTS S CHEDULE (FIGURE CI-14)

C APITA L IMPRO VEMENTS S CHEDULE (FIGURE CI-14) August 15, 2017 Staff Report to the Municipal Planning Board G M P 2 0 1 7-0 0 0 1 7 I TEM 3 S U M M A RY Applicant City of Orlando Requested Actions 1. Amend Figure CI-14 and Policy 2.2.30 of the Capital

More information

DEVELOPMENT PHILOSOPHY

DEVELOPMENT PHILOSOPHY County Administrator Joseph Kernell jkernell@greenvillecounty.org (864) 467-7105 www.greenvillecounty.org May 16, 2017 Dear Chairman Kirven and Members of County Council: I am pleased to present Greenville

More information

ADOPTED CAPITAL IMPROVEMENTS PROGRAM BY DEPARTMENT FY 2009/10 to FY 2014/15. Year /11. Year /10. Ranking Score

ADOPTED CAPITAL IMPROVEMENTS PROGRAM BY DEPARTMENT FY 2009/10 to FY 2014/15. Year /11. Year /10. Ranking Score FY to FY Department: PARKS & RECREATION 305-65000-70008 Magnolia Park CF-305 & Outdoor amphitheatre furthers the network of public green spaces that form the framework for the Town and promotes & expands

More information

RESOLUTION NO. 14-R-

RESOLUTION NO. 14-R- RESOLUTION NO. 14-R- A RESOLUTION OF THE BOARD OF COUNTY COMMISSIONERS OF MARION COUNTY, FLORIDA DIRECTING AND AUTHORIZING THE ACQUISITION OF SUBSTANTIALLY ALL OF THE REAL AND PERSONAL PROPERTY COMPRISING

More information

This page intentionally left blank

This page intentionally left blank 197 This page intentionally left blank 198 Capital Improvement Program PROCEDURE Each year the Capital Improvement Program (CIP) is prepared from project requests submitted by the various departments.

More information

Chapter 4 Capital Facilities 2 3

Chapter 4 Capital Facilities 2 3 Draft March 0 0 Chapter Four Capital Facilities Introduction Capital facilities as defined here, and for purposes of the plan, include facilities owned by Whatcom County and other public entities. Capital

More information

INTRODUCTION. Introduction Page 1 of 5. G:\Comp\Adopted Comprehensive Plans\15. Cylce 16-2 and 16-3\Elements not changed\_d. Introduction.

INTRODUCTION. Introduction Page 1 of 5. G:\Comp\Adopted Comprehensive Plans\15. Cylce 16-2 and 16-3\Elements not changed\_d. Introduction. INTRODUCTION Page 1 of 5 G:\Comp\Adopted Comprehensive Plans\15. Cylce 16-2 and 16-3\Elements not changed\_d..doc INTRODUCTION In 1985 the State Legislature passed Florida's Growth Management Act. Officially

More information

GOVERNMENTAL CAPITAL

GOVERNMENTAL CAPITAL GOVERNMENTAL CAPITAL Governmental Capital refers to that portion of the six year Capital Improvement Program which is not funded by the County's Enterprise Operations. Funding sources include: Transportation

More information

Fully Utilized Transportation Funding Sources

Fully Utilized Transportation Funding Sources Ad valorem Taxes Fully Utilized Transportation ing Sources Statutory Ad Valorem Taxes Section 9, Article VII, Florida Constitution has the current authority to levy up to 0.5 mills and is currently levying

More information

Georgetown Planning Department Plan Annual Update: Background

Georgetown Planning Department Plan Annual Update: Background 2030 Plan Annual Update: 2013 Background The 2030 Comprehensive Plan was unanimously adopted by City Council on February 26, 2008. The Plan was an update from Georgetown s 1988 Century Plan. One of the

More information

Chapter 4 Capital Facilities 2 3

Chapter 4 Capital Facilities 2 3 January, 0 0 0 0 Chapter Four Capital Facilities Introduction Capital facilities as defined here, and for purposes of the plan, include facilities owned by Whatcom County and other public entities. Capital

More information

Technical Report No. 4. Revenue and Costs

Technical Report No. 4. Revenue and Costs Technical Report No. 4 Revenue and Costs Technical Report No. 4 REVENUE AND COSTS PASCO COUNTY METROPOLITAN PLANNING ORGANIZATION 8731 Citizens Drive New Port Richey, FL 34654 Ph (727) 847-8140, fax (727)

More information

TOWN OF CARY CAPITAL IMPROVEMENTS BUDGET MESSAGE FOR FISCAL YEAR 2014

TOWN OF CARY CAPITAL IMPROVEMENTS BUDGET MESSAGE FOR FISCAL YEAR 2014 TOWN OF CARY CAPITAL IMPROVEMENTS BUDGET MESSAGE FOR FISCAL YEAR 2014 Mayor Weinbrecht and Members of Council: The recommended capital improvements budget for the fiscal year of July 1, 2013 to June 30,

More information

Pinellas County, Florida Board of County Commissioners

Pinellas County, Florida Board of County Commissioners Pinellas County, Florida Board of County Commissioners FY2014 FY2023 Capital Improvement Program Kenneth T. Welch, Chairman Karen Williams Seel, Vice Chairman Charlie Justice, Board Member Susan Latvala,

More information

DEBT SERVICE REQUIREMENTS

DEBT SERVICE REQUIREMENTS DEBT SERVICE REQUIREMENTS BACKGROUND In North Carolina, an agency known as the Local Government Commission, the LGC, oversees local government bonded debt. The LGC must approve all bonded debt of local

More information

County-wide Planning Policies

County-wide Planning Policies Kittitas County County-wide Planning Policies Last amended on April 16, 2013 Ordinance No. 2013-005 KITTITAS COUNTY - COUNTY-WIDE PLANNING POLICIES PREAMBLE TO THE COUNTY-WIDE PLANNING POLICIES These Planning

More information

Capital Improvements Data and Analysis Report

Capital Improvements Data and Analysis Report Capital Improvements Data and Analysis Report Introduction The Capital Improvements Data and Analysis Report summarizes the existing and projected needs for City-provided capital facilities identified

More information

City of Lake Wales 5 Year Capital Improvement Plan FY 2018/ /23. Content. City of Lake Wales

City of Lake Wales 5 Year Capital Improvement Plan FY 2018/ /23. Content. City of Lake Wales City of Lake Wales 5 Year Capital Improvement Plan FY 08/9-0/3 Content City of Lake Wales Page 0 Central Ave. W. P.O. Box 30 Summary Memo Lake Wales, FL 33859-30 Ordinance 07-7 3 Phone (863) 678-48 Cost

More information

FY 2015 Operating and Capital Budget Union County, NC

FY 2015 Operating and Capital Budget Union County, NC 1 County Services Public Hearing Tonight s Meeting Public Hearing Concerning the Proposed FY 2015 Operating and Capital Budget for County Services Including the proposed County Ad Valorem Tax Rate of 30.64

More information

Pinellas County Bonded Debt. Last ten years (dollars in thousands)

Pinellas County Bonded Debt. Last ten years (dollars in thousands) DEBT SERVICE Debt Service Costs include the annual payments of interest, principal and other fees on long term bond indebtedness. This section includes the budgeted debt service for obligations which provide

More information

Mobility Fee Study. Brad Thoburn. State Transportation Development Administrator Florida Department of Transportation. June 9,2010

Mobility Fee Study. Brad Thoburn. State Transportation Development Administrator Florida Department of Transportation. June 9,2010 Mobility Fee Study Brad Thoburn State Transportation Development Administrator Florida Department of Transportation June 9,2010 The Florida Community Renewal Act Senate Bill 360 (2009) the state shall

More information

Capital Facilities Element 2/15/2016

Capital Facilities Element 2/15/2016 Capital Facilities Element 2/15/2016 Capital Facilities This Capital Facilities Element has been developed in accordance with Section 36.70A.070 of the Growth Management Act to address the capital facilities

More information

Budget in Brief Proposed City Commission Budget FY 2017

Budget in Brief Proposed City Commission Budget FY 2017 City of Treasure Island Budget in Brief Proposed City Commission Budget FY 2017 Where charm meets contemporary All Funds Budget Summary Total Proposed Budget Budget % Fund FY 2016 FY 2017 Change General

More information

How did we get here?

How did we get here? MOBILITY FEES How did we get here? ULI Report (2008): The County should conduct long-range concurrency studies for each of the five market areas linked to a defined concurrency fee schedule specific to

More information

ORGANIZATION OF PASCO COUNTY

ORGANIZATION OF PASCO COUNTY ORGANIZATION OF PASCO COUNTY Organization of Pasco County Pasco County Government has been organized according to the Council Administrator form of government since 1973. As such, the Board of County Commissioners

More information

Fairfax County Federation of Citizens Associations Resolution Fairfax County Advertised FY 2006 Budget (Membership approved 3/31/05)

Fairfax County Federation of Citizens Associations Resolution Fairfax County Advertised FY 2006 Budget (Membership approved 3/31/05) Fairfax County Federation of Citizens Associations Resolution Fairfax County Advertised FY 2006 Budget (Membership approved 3/31/05) Background The County Executive s proposed FY 2006 Budget Plan totals

More information

ASSET MANAGEMENT PLAN. HEMSON C o n s u l t i n g L t d. 30 Saint Patrick Street, Suite 1000 Toronto, ON, M5T 3A3

ASSET MANAGEMENT PLAN. HEMSON C o n s u l t i n g L t d. 30 Saint Patrick Street, Suite 1000 Toronto, ON, M5T 3A3 ASSET MANAGEMENT PLAN C o n s u l t i n g L t d. 30 Saint Patrick Street, Suite 1000 Toronto, ON, M5T 3A3 March 2017 TABLE OF CONTENTS EXECUTIVE SUMMARY... 1 A. STATE OF THE LOCAL INFRASTRUCTURE... 1 B.

More information

CAPITAL IMPROVEMENT PLAN

CAPITAL IMPROVEMENT PLAN CAPITAL IMPROVEMENT PLAN Algoma Township 1 P a g e Table of Contents Title Page 1 Table of Contents 2 Chapter 1 Executive Summary Overview 3 The Capital Improvement Plan 3 Organization 4 Project Prioritization

More information

Fiscal Year 2016 and Beyond: Balancing Revenue with Community Expectations

Fiscal Year 2016 and Beyond: Balancing Revenue with Community Expectations Fiscal Year 2016 and Beyond: Balancing Revenue with Community Expectations St. Johns County Board of County Commissioners Special Meeting January 27, 2015 Michael D. Wanchick St. Johns County Administrator

More information

Audited Financial Statements And Other Financial Information. City of Clinton, North Carolina. As of June 30, 2016

Audited Financial Statements And Other Financial Information. City of Clinton, North Carolina. As of June 30, 2016 Audited Financial Statements And Other Financial Information City of Clinton, North Carolina As of June 30, 2016 City Council Members Mr. Lew Starling, Mayor Ms. Maxine Harris, Mayor Pro-Tem Mr. Steve

More information

Mobility Fee Legislation

Mobility Fee Legislation Mobility Fee Legislation The Joint Report contains three recommended legislative options for mobility fees: 1. Require mobility fees statewide by a date certain 2. Require mobility fees in DULA counties

More information

INTRODUCTION TO CAPITAL IMPROVEMENTS PROGRAMMING

INTRODUCTION TO CAPITAL IMPROVEMENTS PROGRAMMING INTRODUCTION TO CAPITAL IMPROVEMENTS PROGRAMMING Jerry Hiebert, AICP (Updated by V. Rosales, AICP in 2007) Planners often hear the complaint that their plans sit on shelves gathering dust and are not implemented

More information

CITY OF ROSEBURG, OREGON TABLE OF CONTENTS ENTERPRISE FUNDS

CITY OF ROSEBURG, OREGON TABLE OF CONTENTS ENTERPRISE FUNDS TABLE OF CONTENTS ENTERPRISE FUNDS Storm Drainage Fund... 121-124 Off Street Parking Fund... 125-126 Airport Fund... 127-131 Water Service Fund... 132-145 STORM DRAINAGE FUND CURRENT OPERATIONS This fund

More information

Ten-Year Capital Improvement Program (CIP)

Ten-Year Capital Improvement Program (CIP) Ten-Year Capital Improvement Program (CIP) 1 Introduction to CIP Buildings, infrastructure, technology, and major equipment are the physical foundation for providing services to constituents. Capital planning

More information

DEVELOPMENT PHILOSOPHY The recommended budget aligns the County s resources with the Council s identified governing priorities:

DEVELOPMENT PHILOSOPHY The recommended budget aligns the County s resources with the Council s identified governing priorities: County Administrator Joseph Kernell jkernell@greenvillecounty.org (864) 467-7105 www.greenvillecounty.org May 19, 2015 Dear Chairman Taylor and Members of County Council: I am pleased to present Greenville

More information

Stormwater System Development Charges

Stormwater System Development Charges Methodology Report Stormwater System Development Charges Prepared For City of Springfield April 20, 2009 GALARDI CONSULTING, LLC PAGE 1 OF 9 SECTION 1 Introduction Oregon legislation establishes guidelines

More information

City of Prince Albert YEAR STRATEGIC PLAN

City of Prince Albert YEAR STRATEGIC PLAN 5 City of Prince Albert YEAR STRATEGIC PLAN 2015-2020 City of Prince Albert Introduction Members of City Council, along with Senior Administration, attended a two-day Strategic Planning Session for the

More information

Carroll County Maryland. Community Investment Plan Request Fiscal Years

Carroll County Maryland. Community Investment Plan Request Fiscal Years Carroll County Maryland Community Investment Plan Request Fiscal Years 2019-2024 PRODUCED BY The Department of Management and Budget Ted Zaleski... Director Deborah Effingham... Chief, Bureau of Budget

More information

MDE FINANCIAL ASSISTANCE FOR CHASEPEAKE BAY WATERSHED IMPLEMENTATION PLAN CAPITAL PROJECTS

MDE FINANCIAL ASSISTANCE FOR CHASEPEAKE BAY WATERSHED IMPLEMENTATION PLAN CAPITAL PROJECTS MDE FINANCIAL ASSISTANCE FOR CHASEPEAKE BAY WATERSHED IMPLEMENTATION PLAN CAPITAL PROJECTS Jag Khuman, Director Maryland Water Quality Financing Administration MDE Key Water Quality Financing Programs

More information

FINANCIAL PERFORMANCE OBJECTIVES

FINANCIAL PERFORMANCE OBJECTIVES ORANGE WATER AND SEWER AUTHORITY FINANCIAL MANAGEMENT POLICY JANUARY 26, 2012 SUMMARY The purpose of this document is to describe a comprehensive and systematic approach to strategic financial planning,

More information

Glossary Candidate Roadway Project Evaluation Form Project Scoring Sheet... 17

Glossary Candidate Roadway Project Evaluation Form Project Scoring Sheet... 17 Kitsap County Public Works Transportation Project Evaluation System 2017 Table of Contents Introduction... 1 Four-Tier system... 4 Tier 1 - Transportation Improvement Program (TIP)... 4 Tier 2 Prioritized

More information

Proposed Budget (as of September 15, 2016)

Proposed Budget (as of September 15, 2016) CITY OF ORLANDO OPERATING AND CAPITAL IMPROVEMENT BUDGETS Vision Statement: Orlando is an international city, which uses its diversity, amenities and economy to provide a high quality of life. Mission

More information

SECTION DESCRIPTION PAGE I. BUDGET INTRODUCTION... 1 II. FINAL OPERATING BUDGET... 2 III. GENERAL FUND 001 DESCRIPTIONS... 3

SECTION DESCRIPTION PAGE I. BUDGET INTRODUCTION... 1 II. FINAL OPERATING BUDGET... 2 III. GENERAL FUND 001 DESCRIPTIONS... 3 2018 SECTION DESCRIPTION PAGE I. BUDGET INTRODUCTION... 1 II. FINAL OPERATING BUDGET... 2 III. GENERAL FUND 001 DESCRIPTIONS... 3 IV. SCHEDULE OF ANNUAL ASSESSMENTS... 5 Background Information The Cypress

More information

PROPOSED 2018 BUDGET MESSAGE

PROPOSED 2018 BUDGET MESSAGE PROPOSED 2018 BUDGET MESSAGE August 15, 2017 Honorable Mayor and Town Council Members, Budgets reflect priorities. On behalf of Town staff, I am pleased to submit the Proposed 2018 Budget to Town Council

More information

Quigley Canyon Ranch Cost/Benefit Study Update

Quigley Canyon Ranch Cost/Benefit Study Update Quigley Canyon Ranch Cost/Benefit Study Update April 26, 2012 RICHARD CAPLAN & ASSOCIATES Mayor Fritz Haemmerle Hailey City Council 115 Main Street Hailey, ID 83333 April 26, 2012 Dear Mayor Haemmerle

More information

Capital Improvements Data; and Capital Improvements Analysis; and Capital Improvements Goal, Objectives and Policies

Capital Improvements Data; and Capital Improvements Analysis; and Capital Improvements Goal, Objectives and Policies 10.0 CAPITAL IMPROVEMENTS (UPDATE) 10.1 INTRODUCTION The CAPITAL IMPROVEMENTS element is required to be included within the Comprehensive Plan per requirements of State planning law and rule criteria.

More information

ARLINGTON COUNTY, VIRGINIA

ARLINGTON COUNTY, VIRGINIA ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of July 22, 2008 DATE: July 15, 2008 SUBJECT: Approval of Resolutions and Questions to include in the 2008 Bond Referenda C. M. RECOMMENDATION:

More information

Debt Table of Contents

Debt Table of Contents Debt Debt Table of Contents Debt Management & Policy... 205 Outstanding Debt Summary... 206 General Debt Service Outstanding Debt By Type... 207 Legal Debt Margin for General Obligation... 207 Principal

More information

CITY OF FEDERAL WAY 2017/2018 ADOPTED BUDGET

CITY OF FEDERAL WAY 2017/2018 ADOPTED BUDGET I. OPERATING BUDGET A. OVERALL BUDGET POLICIES 1. The budget should be a performance, financing and spending plan agreed to by the Mayor, City Council, and Department Directors. It should contain information

More information

GOAL 1: Protect coastal resources and human life and limit public expenditures in areas that are subject to destruction by natural disasters..

GOAL 1: Protect coastal resources and human life and limit public expenditures in areas that are subject to destruction by natural disasters.. GOALS, OBJECTIVES, AND POLICIES GOAL 1: Protect coastal resources and human life and limit public expenditures in areas that are subject to destruction by natural disasters.. OBJECTIVE 1.1: The City will

More information

Highlights from the Proposed Budget Fiscal Year

Highlights from the Proposed Budget Fiscal Year Highlights from the Proposed Budget Fiscal Year 2018-2019 City of Plant City Florida Budget Highlights KEY BUDGET HIGHLIGHTS: This budget is a responsible, proactive spending plan that will benefit Plant

More information

APPENDIX TABLE OF CONTENTS

APPENDIX TABLE OF CONTENTS APPENDIX TABLE OF CONTENTS Glossary... K-3 Budget Policies... K-11 Basis of Accounting Financial Statements... K-17 Basis of Accounting Budget... K-17 Budget Process... K-17 Budgetary Control and Adjustments...

More information