SPP s Regional Review of SPP-MISO Coordinated System Plan Recommended Interregional Projects

Size: px
Start display at page:

Download "SPP s Regional Review of SPP-MISO Coordinated System Plan Recommended Interregional Projects"

Transcription

1 SPP s Regional Review of SPP-MISO Coordinated System Plan Recommended Interregional Projects January 4, 2016 SPP Interregional Relations

2 Table of Contents Executive Summary... 2 Introduction... 5 Stakeholder Involvement... 5 Assumptions Development... 6 Model Development...6 Economic Model...6 Power Flow Model...7 Constraint Assessment...7 Metrics... 7 APC...7 Avoided or Delayed Reliability Project Cost...8 Mitigation of Transmission Outage Costs...8 Wheeling Through and Out Revenue...8 Cost Estimates... 9 Analysis Results... 9 Alto Series Reactor...9 Metric Results Project Recommendations & Approvals Rebuild South Shreveport to Wallace Lake...11 Metric Results Project Recommendation and Approvals Elm Creek NSUB 345 kv...12 Metric Results Project Recommendation and Approvals Reliability Assessment Conclusion

3 Executive Summary In its Regional Review process, SPP evaluated three potential Interregional Projects which were recommended by the SPP-MISO Joint Planning Committee (JPC) from the SPP-MISO Coordinated System Plan (CSP) study. These potential Interregional Projects are: 1. Series Reactor on Alto-Swartz 115kV (Alto Series Reactor); 2. Rebuild Southwest Shreveport Wallace Lake 138 kv (Southwest Shreveport); and 3. Elm Creek NSUB 345 kv (Elm Creek). The purpose of the Regional Review is to utilize SPP s own regional planning models and benefit metrics to estimate the benefits to the SPP region from the potential Interregional Projects identified in the CSP. At their June 2015 meeting, the Economic Studies Working Group (ESWG) approved a study scope for the Regional Review for SPP staff to use a Business-as-Usual future. SPP utilized the 2015 ITP10 Future 1 model as the starting point for the Regional Review model. This model was then updated to include model enhancements that were identified in the latter stages of the 2015 ITP10, the CSP, and additional stakeholder review. The Regional Review scope described utilizing four benefit metrics to evaluate the potential Interregional Projects: Adjusted Production Cost; Avoided or Delayed Reliability Project Cost; 2

4 Mitigation of Transmission Outage Cost; and Increased Wheeling Through and Out Revenue. SPP performed a 40-year financial analysis of the potential Interregional Projects to determine the total present value of the estimated benefits that could be attributed to SPP. The cost for the two potential Interregional Projects within SPP, Southwest Shreveport and Elm Creek, were estimated using SPP s regional project cost estimation process. These costs were study level estimates with a plus/minus degree of accuracy of 30%. The cost for the project within MISO, the Alto Series Reactor, was estimated using MISO s regional project cost estimate process and also was an estimate of plus/minus 30%. Only the proportion of each project s cost that would be paid by SPP, as determined through the CSP analysis, was considered when comparing the costs to the estimated SPP benefits. Should the potential Interregional Projects be approved, SPP would be responsible for 14% of the cost of the Alto Series Reactor, 20% of Southwest Shreveport, and 80% of Elm Creek. Those percentages were calculated in the CSP. SPP s evaluation of the Alto Series Reactor determined that this potential Interregional Project does not provide benefit to SPP. While SPP was only projected to be allocated 14% of the cost, which amounts to $1.27 million over 40 years, SPP s 40-year APC benefit was estimated to be negative $8.73 million based on the results of SPP s Regional Review. Additionally this project does not provide benefits from the other three metrics: Increased Wheeling Through and Out Revenue, Mitigation of Transmission Outage Cost, and Avoided or Delayed Reliability Project. SPP staff recommended that the Alto Series Reactor not be approved as an Interregional Project. In October 2015 the SPP Board of Directors (Board) voted to not approve this project as an Interregional Project. SPP s evaluation of South Shreveport determined that this potential Interregional Project is estimated to provide significant benefits to SPP. SPP was projected to be allocated 20% of the cost, which amounts to $6.38 million over 40 years. SPP s 40-year APC benefit is estimated to be $39 million resulting in an APC-only B/C ratio of 6.2. This potential Interregional Project also was expected to provide Avoided or Delayed Reliability Project benefit of $31.9 million and Mitigation of Transmission Outage Cost benefits of $4.4 million, resulting in total 40-year benefits of $75.7 million and a B/C ratio of Categories Values APC $ 39,328,392 Wheeling $ - Trans Outages $ 4,444,108 Reliability $ 31,898, Yr PV Benefits $ 75,671, Yr PV Cost $ 6,379,772 NPV $ 69,291,589 B/C Ratio Even if SPP were responsible for a significantly higher percentage of the cost, this project would still be cost effective for SPP. Based on the results of the Regional Review, SPP staff recommended that this project be approved as an Interregional Project. In October 2015, the Board voted to approve South Shreveport as an Interregional Project. If this project were to be 3

5 approved by the MISO Board of Directors as well it would move forward as an Interregional Project. SPP s evaluation of Elm Creek determined that this potential Interregional Project is estimated to provide benefits to SPP. Benefits for this project are substantially less than what was calculated in the CSP. The primary driver for the benefit difference is the 2015 ITP10 approval of the voltage conversion for Iatan Stranger 161 kv to 345 kv. Due to the timing of when the Iatan Stranger voltage conversion was approved, this project was not included in the CSP study but was included in SPP s Regional Review. SPP s 40-year APC benefit is estimated to be $190 million. This potential Interregional Project also provides Mitigation of Transmission Outage Cost benefits of $21.4 million and Wheeling Through and Out Revenue benefit of $8.3 million. The total 40-year benefit to SPP is $219 million, resulting in a 40-year B/C ratio of Categories Values APC $ 189,646,497 Wheeling $ 8,335,167 Trans Outages $ 21,430,054 Reliability $ - 40-Yr PV Benefits $ 219,411, Yr PV Cost $ 193,479,100 NPV $ 25,932,619 B/C Ratio 1.13 While the estimated B/C ratio of 1.13 is greater than 1, SPP staff recommended that Elm Creek not be approved as an Interregional Project. This recommendation is based on SPP staff s analysis that most of the estimated benefit from the Elm Creek project is driven by an increase in coal generation, and given the uncertainty due to the Clean Power Plan, SPP staff was not confident that the benefits would have a high likelihood of materializing under a carbon constrained future. Additionally, SPP s Regional Review analysis shows that the Elm Creek project is not projected to have an annual B/C ratio greater than 1.0 until SPP staff s conclusion to not recommend approval of the proposed Elm Creek Interregional Project and continuing to evaluate this project until there is more certainty represents a noregrets approach. In October 2015 the Board voted to not approve this project as an Interregional Project. Of the three potential Interregional Projects resulting from the CSP, only South Shreveport was approved by the Board as an Interregional Project. In order for an Interregional Project to move forward it must also be approved by the MISO Board of Directors. MISO staff has informed SPP staff that the MISO Board of Directors does not plan to take any action on these projects at this time. 4

6 Introduction The purpose of the MISO-SPP Coordinated System Plan (CSP) study was to jointly evaluate seams transmission issues and identify transmission solutions that efficiently address the identified issues to the benefit of both MISO and SPP. This study incorporated an evaluation of economic seams transmission issues and an assessment of potential reliability violations. At the completion of the CSP study, the SPP-MISO Joint Planning Committee (JPC) produced a draft report. The report documented all aspects of the study including: transmission issues evaluated; analyses; potential transmission solutions; and the recommended Interregional Projects with the associated interregional cost allocation. Taking into consideration the recommendation of the Interregional Planning Stakeholder Advisory Committee (IPSAC), the JPC met and voted to recommend three potential Interregional Projects. On the JPC s June 29, 2015 conference call, the JPC voted to recommend the following potential Interregional Projects: 1. Series Reactor on Alto-Swartz 115kV (Alto Series Reactor); 2. Rebuild Southwest Shreveport Wallace Lake 138 kv (Southwest Shreveport); and 3. Elm Creek NSUB 345 kv (Elm Creek). The SPP Regional Review officially began once the projects were recommended by the JPC. The SPP Regional Review methodology, posted on the SPP website 1, provides guidance on the development of the study scope. The study scope was drafted by SPP staff and approved by the ESWG at their June 2015 meeting. Stakeholder Involvement While stakeholder involvement in the CSP primarily occurred at the joint IPSAC meetings, SPP s Regional Review is driven by SPP s regional stakeholder process. Since the three recommended Interregional Projects were recommended to address economic issues, the Economic Studies Working Group (ESWG) was identified as being the primary group responsible for overseeing SPP s Regional Review study. The ESWG approved the scope for the Regional Review study at their June 2015 meeting. The model for use in the Regional Review study was approved by the ESWG at their August 2015 meeting after being reviewed and updated by stakeholders over the course of several weeks. While the ESWG was the primary SPP stakeholder group driving SPP s Regional Review study, the Transmission Working Group (TWG) was also involved. The TWG approved an updated constraint assessment at their July meeting to be used in SPP s Regional Review. The TWG also reviewed the results of the reliability no-harm analysis and the reliability benefit metric

7 Other SPP working groups were provided updates on the Regional Review study as it was in process, such as the Cost Allocation Working Group (CAWG), the Seams Steering Committee (SSC), and the Markets and Operations Policy Committee (MOPC). Both the ESWG and the TWG reviewed the final results compiled by SPP staff. The TWG voted to approve the results of the no-harm analysis and the reliability benefit metric at their September 2015 meeting. The ESWG was responsible for providing a recommendation to the MOPC and voted to recommend Elm Creek and Southwest Shreveport for approval as Interregional Projects at their September 2015 meeting. The SSC also voted to express their desire that Southwest Shreveport be approved as an Interregional Project. Assumptions Development The Regional Review methodology states that the latest or current ITP10 model(s) and assumptions from the business as usual future will be used unless the ESWG determines that adjustments are needed due to a significant change in expected conditions. The ESWG agreed with using Future 1 from the 2015 ITP10 as the base for all assumptions in the Regional Review 2. One deviation from those assumptions was that the ESWG directed SPP staff to use the hurdle rates identified in the CSP to perform the APC analysis. The transmission topology in SPP s Regional Review model was updated from what was used in the CSP and the 2015 ITP10 to include stakeholder feedback that was provided during the development of the 2017 ITP10 models. Additionally, SPP staff updated the models to include the transmission projects which were approved by the Board in January 2015 which were not included in the CSP models. Model Development The models used in the Regional Review differ from those used in the CSP. The Regional Review models are built under the purview of the SPP stakeholder process rather than the interregional process utilized in the CSP. Additionally, the Regional Review model is 12 months newer than the CSP model which resulted in the Regional Review model including updated topology and generation assumptions that were not known when the CSP model was built. These model updates contributed to the difference in results between the CSP and the SPP Regional Review. Economic Model Two economic models were used in the Regional Review study: a 2019 model and a 2024 model. Since 2024 is the study year for the CSP and 2024 is assumed to be the in-service date for the projects, the 2024 model was the primary model used in the project evaluation. The 2019 model 2 The 2015 ITP10 scope includes details on the assumptions. 6

8 was utilized for the Adjusted Production Cost (APC) 40-year financial analysis to extrapolate data points beyond the 2024 model year. The economic model was based upon what was used in the CSP. The CSP model already included the 2015 ITP10 data. Updates were made to this model based on the assumptions approved by the ESWG in the Regional Review Scope and other stakeholder feedback. Once the economic model for SPP s Regional Review was developed it was reviewed by the ESWG. The model was endorsed by the ESWG at their July 9, 2015 meeting. Power Flow Model A power flow model was utilized to perform a no-harm evaluation and to calculate the avoided or delayed reliability project cost and increased wheeling through and out revenues benefit metrics. The 2015 ITP power flow model was updated to include recently approved transmission projects and other enhancements as provided by stakeholders. Constraint Assessment The 2015 ITP10 constraint list was used as the starting point for SPP s Regional Review constraint list. Since the transmission topology in the power flow model was updated to incorporate transmission projects approved in January 2015, an additional constraint analysis was performed to determine if additional constraints should be modeled. Two hours, one peak and one non-peak hour, were evaluated, and the additional constraints that were identified were added to the constraint list. This revised constraint list was provided to stakeholders and approved by the TWG at their July 2015 meeting. Metrics The scope identified four metrics to be used to calculate SPP benefit: 1. Adjusted Production Cost (APC); 2. Avoided or delayed reliability project cost; 3. Mitigation of transmission outage costs; and 4. Increased wheeling through and out revenues. APC APC is a measure of the impact on production cost savings, considering purchases and sales of energy between each area of the transmission grid. The calculation, performed on an hourly basis, is summarized in the following figure. 7

9 APC captures the monetary cost associated with fuel prices, run times, grid congestion, and unit operating costs, energy purchases, energy sales, and other factors that directly relate to energy production by generating resources in the SPP footprint. Additional transmission projects aim to relieve system congestion and reduce costs through a combination of a more economical generation dispatch, more economical purchases, and optimal revenue from sales. To calculate benefits over the expected 40-year life of the projects 3, two years were analyzed, 2019 and 2024, and the APC savings were calculated accordingly for these years. The calculated APC benefits are extrapolated for the initial 20-year period based on the slope between the two points and assumed to grow at an inflation rate of 2.5% per each year after that up to year 40. Each year s benefit was then discounted to 2019 using an 8% discount rate and a 2.5% inflation rate from 2019 back to The sum of all discounted benefits was presented as the Net Present Value (NPV) benefit. Avoided or Delayed Reliability Project Cost To calculate the avoided or delayed reliability project cost benefit a power flow analysis is performed to determine whether the potential Interregional Project replaces an SPP regional reliability project. The value of this benefit metric is calculated as the 40-year cost of the replaced SPP regional reliability project(s). Mitigation of Transmission Outage Costs The standard production cost simulations used to estimate APC savings assume that transmission lines and facilities are available during all hours of the year, and thereby ignore the added congestion-relief and production cost benefits of new transmission facilities during the planned and unplanned outages of existing transmission facilities. To estimate the incremental savings associated with the mitigation of transmission outage costs, the production cost simulations can be augmented for a realistic level of transmission outages. Due to the significant effort that would be needed to develop these augmented models, and as was done in the 2015 ITP10, the findings from the SPP Regional Cost Allocation Review (RCAR) study were used to estimate this benefit metric for the potential Interregional Projects. In the RCAR analysis, adding a subset of historical transmission outage events to the production cost simulations increased the APC savings by 11.3%. This 11.3% is applied to the APC benefit to estimate the Mitigation of Transmission Outage Costs benefit. Wheeling Through and Out Revenue Increasing Available Transfer Capability (ATC) with a neighboring region improves import and export opportunities for the SPP footprint. Increased interregional transmission capacity that allows for increased through and out transactions may also increase SPP wheeling revenues. 3 The SPP OATT requires that the potential Interregional Projects be evaluated using a 40-year financial analysis. 8

10 The 2015 ITP10 analysis estimated the impact of ATC on selling wheeling services. Those results reflected that every MW of increased ATC would result in an annual benefit of $37,500. This analysis was leveraged to calculate the Wheeling Through and Out Revenue benefit for the potential Interregional Projects in SPP s Regional Review. Each potential Interregional Project was evaluated to determine its impact on ATC. The metric was calculated by multiplying the MW increase in ATC by $37,500. To determine the 40-year benefit of this metric an annual growth rate of 2.5% was used to account for inflation. Cost Estimates The project cost estimates from the CSP were used in SPP s Regional Review of the potential Interregional Projects. These cost estimates were developed utilizing the assumptions MISO and SPP use in their respective regional cost estimation processes. If the project was geographically located within MISO s footprint, MISO s project cost estimates were utilized. If the project was geographically located within SPP s footprint, SPP s project cost estimates were utilized. These cost estimates are study level estimates (+/-30%). SPP s portion of each potential Interregional Project were determined based on SPP s proportion of APC benefits identified in the CSP. Project Total E&C Cost SPP Portion of E&C Cost Alto Series $5,287,929 $740,310 Reactor Shreveport $18,553,018 $3,710,604 Elm Creek $140,664,160 $112,531,328 Alto Series Reactor Analysis Results The Alto Series Reactor project adds a 10% reactor on 100 MVA base in series with the Alto Swartz 115 kv line. The reactor is to be normally bypassed, and un-bypassed post-contingency for critical contingencies such as a loss of Baxter Wilson Perryville 500 kv. The Alto-Swartz 115 kv line with which the reactor would be placed in series is located in North Central Northwest Louisiana. In the CSP this project was proposed to relieve congestion on the Swartz Alto 115 kv flowgate. 9

11 Metric Results While the results of the CSP demonstrated that this project provided benefit to both SPP and MISO, SPP s Regional Review results show that the Alto Series Reactor is estimated to provide negative APC benefits to SPP. The benefit results when calculating the other three metrics also show that this project does not provide benefit to SPP. Categories 40-YR PV APC ($8,733,712) Wheeling $0 Trans Outages $0 Reliability $0 40-Yr PV Benefits ($8,733,712) 40-Yr PV Cost $1,272,841 Project Recommendations & Approvals Due to the negative benefit calculated for the SPP region, SPP staff recommended to the SPP Markets and Operations Policy Committee (MOPC) that this project not be approved as an Interregional Project. The MOPC made a recommendation to the Board to not approve the Alto Series Reactor as an Interregional Project. At the October Board meeting the Board voted in agreement with the MOPC to not approve the Alto Series Reactor as an Interregional Project. 10

12 Rebuild South Shreveport to Wallace Lake The South Shreveport project proposes rebuilding the existing 11 mile South Shreveport to Wallace Lake 138 kv line with CSRT/TW conductor along with upgrades at the South Shreveport and Wallace Lake substations. The South Shreveport Wallace Lake 138 kv line is located in Northwestern Louisiana. This project was proposed to relieve congestion on the South Shreveport Wallace Lake 138 kv flowgate. Metric Results APC The South Shreveport project s impact was primarily on congestion on the South Shreveport Wallace Lake flowgate. This reduction in congestion was the primary driver for the APC benefits. South Shreveport was estimated to provide significant APC benefits to SPP of almost $40 million over 40 years. Using only the APC benefit metric the B/C ratio would still be over 6. Transmission Outages The Transmission Outage benefit for South Shreveport is $4,444,108 which was calculated by multiplying the estimated APC benefit by 11.3%. 11

13 Avoided or Delayed Reliability Project Cost The South Shreveport project addresses a reliability issue identified in the 2015 ITP10. When Fort Humbug Trichel Street 138 kv is taken out of service, South Shreveport Wallace Lake 138 kv is forecast to be overloaded. The 2015 ITP10 identified the South Shreveport upgrade as being the most cost effective solution to address this potential reliability issue. Approving the Interregional Project South Shreveport would result in recalling the SPP regional version of the project. The avoided or delayed reliability project cost benefit is equal to the cost of the South Shreveport project, $31,898, Total Benefits The benefits estimated for SPP far exceed the cost assigned to SPP with a Net Present Value of over $69 million and a B/C ratio of These results also indicate that under any interregional cost allocation scenario SPP s B/C ratio would be greater than 1. Categories 40-YR PV APC $ 39,328,392 Wheeling $ - Trans Outages $ 4,444,108 Reliability $ 31,898, Yr PV Benefits $ 75,671, Yr PV Cost $ 6,379,772 NPV $ 69,291,589 B/C Ratio Project Recommendation and Approvals Due to the significant value this project provides to the SPP region, SPP staff recommended to the SPP Markets and Operations Policy Committee (MOPC) that this project be approved as an Interregional Project. The MOPC made a recommendation to the Board to approve South Shreveport as an Interregional Project. At the October Board meeting the Board voted in agreement with the MOPC to approve South Shreveport as an Interregional Project. This project would become an approved SPP-MISO Interregional Project if the MISO Board were to approve the project. Elm Creek NSUB 345 kv The proposed Elm Creek NSUB 345 kv transmission line is a new transmission project heading north from an Elm Creek 345 kv substation in North Central Kansas (Cloud County) to a new 345 kv substation that taps the existing Mark Moore Pauline 345 kv line. This 4 Note that this value is higher than the cost SPP would pay for this project as an Interregional Project since there would not be cost sharing of the regional version of the project. 12

14 project has an estimated length of 78 miles. The Elm Creek 345 kv substation is being built as a part of the SPP Elm Creek Summit 345 kv project that was approved in the 2012 SPP ITP10. That project has an expected in-service date of This project was proposed to relieve congestion on the Northeast to Charlotte 161 kv flowgate. Metric Results APC The Elm Creek project s impact was greater than just the congestion relief on the Northeast to Charlotte flowgate. In addition, Elm Creek also provided significant congestion relief on Gentleman to Redwillow, Tecumseh Hill Transformer, S1221 to S1255, Iatan to Stranger, and Cooper South flowgates. One major impact on the APC benefits of this project is the inclusion of the 2015 ITP10 Iatan to Stranger project, which is identified on the map above. That project is a voltage conversion from the current 161 kv to 345 kv. The Iatan to Stranger project also addresses congestion on Northeast to Charlotte and was not in the CSP models due to the timing of its approval by the Board in January Including this project in the model greatly reduces the benefits attributable to Elm Creek. Elm Creek is estimated to provide over $189 million in APC benefit over 40 years. 13

15 Transmission Outages The Transmission Outage benefit for Elm Creek is $21,430,054 which was calculated by multiplying the estimated APC benefit by 11.3%. Increased Wheeling Through and Out Revenues Elm Creek is the only potential Interregional Project recommended from the CSP that is estimated to provide increased wheeling through and out revenues benefit as it is the only project that increases ATC. Elm Creek increases SPP s ATC by 15.9 MW which results in an annual benefit value of $596,250. Over 40 years the present value is $8,335,167. Total Benefits The estimated benefits calculated for SPP exceed the cost assigned to SPP with a Net Present Value of almost $26 million and a B/C ratio of Categories 40-YR PV APC $ 189,646,497 Wheeling $ 8,335,167 Trans Outages $ 21,430,054 Reliability $ - 40-Yr PV Benefits $ 219,411, Yr PV Cost $ 193,479,100 NPV $ 25,932,619 B/C Ratio 1.13 Project Recommendation and Approvals While the 40-Year B/C ratio is greater than 1.0, SPP staff recommended to the SPP Markets and Operations Policy Committee (MOPC) that this project not be approved as an Interregional Project. This recommendation is based on SPP staff s analysis that most of the estimated benefits of the Elm Creek project is driven by an increase in coal generation, and given the uncertainty due to the Clean Power Plan SPP staff was not confident that the benefits would have a high likelihood of materializing under a carbon constrained future. 14

16 Generation Change (MWh) 150, ,000 50, , , , , , , ,000 CC ST Gas ST Coal CT Gas IC Gas Additionally, the Elm Creek project is not estimated to have an annual B/C ratio greater than 1.0 until 2035 which indicates that there is little to no harm in deferring approval of the project and reevaluating it in a later study. 15

17 The ESWG made an alternative proposal to MOPC which recommended the approval of Elm Creek as an Interregional Project. Ultimately the MOPC recommended to the Board to not approve Elm Creek as an Interregional Project. At the October Board meeting the Board voted in agreement with the MOPC to not approve Elm Creek as an Interregional Project. Reliability Assessment A no-harm reliability assessment was performed using an updated version of the 2015 ITP10 models. The updates to the model included adding the transmission projects approved by the Board in January The assessment concluded that the three potential Interregional Projects did not create any potential reliability issues. Conclusion SPP s Regional Review analysis results demonstrated that South Shreveport would provide significant benefits to SPP with an estimated B/C ratio of over 11. Even under alternative interregional cost allocation scenarios with MISO, SPP s B/C ratio is greater than 1 and would be considered cost effective. The Alto Series Reactor provided negative benefits to the SPP region in the Regional Review analysis and for this reason the SPP Board voted to not approve the Alto Series Reactor. While the B/C ratio for Elm Creek was greater than the required 1.0 SPP staff recommended, and the SPP Board voted in agreement, that this project should not be approved as an Interregional Project at this time but should instead be further evaluated in future studies. While the SPP Board approved South Shreveport as an Interregional Project the project will not move forward unless approved by the MISO Board of Directors. MISO has informed SPP that the MISO Board of Directors does not plan to vote on any of the three potential Interregional Projects. 16

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION ) ) ) ) ) ) ) ) ) ) ) DIRECT TESTIMONY WILLIAM A. GRANT. on behalf of

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION ) ) ) ) ) ) ) ) ) ) ) DIRECT TESTIMONY WILLIAM A. GRANT. on behalf of BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION IN THE MATTER OF SOUTHWESTERN PUBLIC SERVICE COMPANY S APPLICATION FOR REVISION OF ITS RETAIL RATES UNDER ADVICE NOTICE NO., SOUTHWESTERN PUBLIC SERVICE

More information

Cost Allocation Principles for Seams Transmission Expansion Projects

Cost Allocation Principles for Seams Transmission Expansion Projects Cost Allocation Principles for Seams Transmission Expansion Projects SPP s seams agreements currently contain requirements for SPP to develop coordinated system plans with its neighbors. The extent and

More information

Seams Cost Allocation: A Flexible Framework to Support Interregional Transmission Planning (Summary of Final Report)

Seams Cost Allocation: A Flexible Framework to Support Interregional Transmission Planning (Summary of Final Report) Seams Cost Allocation: A Flexible Framework to Support Interregional Transmission Planning (Summary of Final Report) Presented at: SPP RSC Quarterly Meeting Presented by: Johannes Pfeifenberger Delphine

More information

Costs and Revenue Offsets Item # Description

Costs and Revenue Offsets Item # Description Item # CUS-13 Costs and Description Total Cost Allocation - Total cost (PV of 40-year ATRR's ) are listed as $7,382M on ESWG slide 3. Could we get a breakdown (listing) of how this total was determined.

More information

SPP-AECI Joint Projects

SPP-AECI Joint Projects SPP-AECI Joint Projects 1 Morgan Transformer Project Addition of a new 400 MVA 345/161 kv Transformer at AECI s Morgan substation and an uprate of the 161 kv line between Morgan and Brookline Located in

More information

New Member Cost Allocation Review Process. Prepared by: COST ALLOCATION WORKING GROUP

New Member Cost Allocation Review Process. Prepared by: COST ALLOCATION WORKING GROUP New Member Cost Allocation Review Process Prepared by: COST ALLOCATION WORKING GROUP TABLE OF CONTENTS 1. HISTORY AND BACKGROUND... 1 2. PURPOSE / GOAL STATEMENT... 3 3. OVERVIEW OF PROCESS... 3 4. NEW

More information

Regional Cost Allocation Review (RCAR II) July 11, 2016 SPP Regional Cost Allocation Review Report for RCAR II

Regional Cost Allocation Review (RCAR II) July 11, 2016 SPP Regional Cost Allocation Review Report for RCAR II Regional Cost Allocation Review (RCAR II) July 11, 2016 SPP Regional Cost Allocation Review Report for RCAR II 1 Table of Contents EXECUTIVE SUMMARY...5 BACKGROUND...7 SECTION 1: OVERVIEW OF THE RARTF

More information

October 8, SPP Regional Cost Allocation Review Report

October 8, SPP Regional Cost Allocation Review Report Regional Cost Allocation Review October 8, 2013 SPP Regional Cost Allocation Review Report 1 Table of Contents EXECUTIVE SUMMARY...5 BACKGROUND...7 SECTION 1: OVERVIEW OF THE RARTF AND RCAR REVIEW...8

More information

EIPC Roll-Up Report & Scenarios

EIPC Roll-Up Report & Scenarios EIPC Roll-Up Report & Scenarios Zach Smith Director, Transmission Planning New York Independent System Operator IPTF/EGCWG/ESPWG Meeting January 6, 2014 2013 New York Independent System Operator, Inc.

More information

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION SOUTHWESTERN PUBLIC SERVICE COMPANY S UNOPPOSED RESPONSE TO STAFF S COMMENTS

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION SOUTHWESTERN PUBLIC SERVICE COMPANY S UNOPPOSED RESPONSE TO STAFF S COMMENTS BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION IN THE MATTER OF SOUTHWESTERN ) PUBLIC SERVICE COMPANY S 2018 ) INTEGRATED RESOURCE PLAN FOR ) NEW MEXICO. ) CASE NO. 18-00215-UT ) SOUTHWESTERN PUBLIC

More information

TABLE OF CONTENTS ARTICLE ONE: RECITALS... 5 ARTICLE TWO: ABBREVIATIONS, ACRONYMS, AND DEFINITIONS... 6 ARTICLE THREE: OPERATING COMMITTEE...

TABLE OF CONTENTS ARTICLE ONE: RECITALS... 5 ARTICLE TWO: ABBREVIATIONS, ACRONYMS, AND DEFINITIONS... 6 ARTICLE THREE: OPERATING COMMITTEE... TABLE OF CONTENTS ARTICLE ONE: RECITALS... 5 ARTICLE TWO: ABBREVIATIONS, ACRONYMS, AND DEFINITIONS... 6 2.1 Abbreviations and Acronyms... 6 2.2 Definitions... 7 2.3 Rules of Construction... 10 ARTICLE

More information

MISO PJM IPSAC. December 2, Revised December 22, PJM IPSAC Meeting, December 2,

MISO PJM IPSAC. December 2, Revised December 22, PJM IPSAC Meeting, December 2, MISO PJM IPSAC December 2, 2016 Revised December 22, 2016 1 Agenda 2 TMEP Final JOA Language Recommended TMEPs Order No. 1000 Compliance Filing Generation Deactivation JOA Language PJM Proposal Window

More information

BEFORE THE MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS 600 North Robert Street St. Paul, MN 55101

BEFORE THE MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS 600 North Robert Street St. Paul, MN 55101 BEFORE THE MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS 00 North Robert Street St. Paul, MN 1 FOR THE MINNESOTA PUBLIC UTILITIES COMMISSION th Place East, Suite 0 St Paul MN 1-1 IN THE MATTER OF THE APPLICATION

More information

SPP PLANNING AND COST ALLOCATION OVERVIEW

SPP PLANNING AND COST ALLOCATION OVERVIEW Benefit/Cost Ratio Primer 101 for the Regional Allocation Review Task Force August 4, 2011 1 SPP PLANNING AND COST ALLOCATION OVERVIEW 2 1 Transmission = 10% Retail Electricity Rates Transmission enables

More information

BEFORE THE MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS 600 North Robert Street St. Paul, MN 55101

BEFORE THE MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS 600 North Robert Street St. Paul, MN 55101 BEFORE THE MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS 00 North Robert Street St. Paul, MN 1 FOR THE MINNESOTA PUBLIC UTILITIES COMMISSION th Place East, Suite 0 St Paul MN 1-1 IN THE MATTER OF THE APPLICATION

More information

NTTG REGIONAL TRANSMISSION PLAN. December 30, 2015

NTTG REGIONAL TRANSMISSION PLAN. December 30, 2015 NTTG 2014-2015 REGIONAL TRANSMISSION PLAN December 30, 2015 1 Table of Contents Executive Summary... 3 Introduction... 3 The Northern Tier Transmission Group... 3 Participating Utilities... 4 Purpose of

More information

CAWG MEETING July 25, 2007 Marriott Country Club Plaza Kansas City, MO 11:00 am 5:00 pm AGENDA

CAWG MEETING July 25, 2007 Marriott Country Club Plaza Kansas City, MO 11:00 am 5:00 pm AGENDA CAWG MEETING July 25, 2007 Marriott Country Club Plaza Kansas City, MO 11:00 am 5:00 pm AGENDA 1. Introductions 11:00-11:10 2. STEP Screen to Portfolio Transition 11:10 12:00 Discussion lead by Charles

More information

Mountain West Transmission Group (MWTG) Introduction and Process

Mountain West Transmission Group (MWTG) Introduction and Process Mountain West Transmission Group (MWTG) Introduction and Process October 13 Denver, CO October 16 Little Rock, AR 2 Agenda Overview of SPP Overview of the MWTG Members SPP Process New Member Integration

More information

Southwest Power Pool s Balanced Portfolio Approach for Economic Upgrades

Southwest Power Pool s Balanced Portfolio Approach for Economic Upgrades Southwest Power Pool s Balanced Portfolio Approach for Economic Upgrades Presentation by Michael Proctor Chief Economist, Missouri PSC Harvard Electricity Policy Group Chicago, Illinois October 2, 2008

More information

ITP Evaluation Process Plan

ITP Evaluation Process Plan ITP Evaluation Process Plan HVDC Conversion Project The goal of the coordinated Interregional Transmission Project (ITP) evaluation process is to achieve consistent planning assumptions and technical data

More information

FTR Credit Requirements Prevailing Flow Paths Affected by Transmission System Upgrades

FTR Credit Requirements Prevailing Flow Paths Affected by Transmission System Upgrades FTR Credit Requirements Prevailing Flow Paths Affected by Transmission System Upgrades Hal Loomis Manager, Credit Markets & Reliability Committee December 7, 2017 Credit Risk Exposure Issue Description

More information

SPP REPORT ON TLR EVENTS FROM FEBRUARY 13 MARCH 4, 2002

SPP REPORT ON TLR EVENTS FROM FEBRUARY 13 MARCH 4, 2002 SPP REPORT ON TLR EVENTS FROM FEBRUARY 13 MARCH 4, 2002 On seven occasions between February 13 and March 4, 2002, SPP initiated a TLR on the MorStiSooNor flow gate, #5067, that included firm service curtailments.

More information

Memo to the MOPC and Board of Directors Highway-Byway Cost Allocation

Memo to the MOPC and Board of Directors Highway-Byway Cost Allocation Memo to the MOPC and Board of Directors Highway-Byway Cost Allocation SPP believes that the proposed Highway-Byway cost allocation methodology will promote new transmission construction by allocating:

More information

MISO Planning Process. May 31, 2013

MISO Planning Process. May 31, 2013 MISO Planning Process May 31, 2013 MISO Planning Objectives Fundamental Goal The development of a comprehensive expansion plan that meets reliability needs, policy needs, and economic needs MISO Board

More information

February 23, 2015 VIA ELECTRONIC FILING

February 23, 2015 VIA ELECTRONIC FILING February 23, 2015 VIA ELECTRONIC FILING The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: Southwest Power Pool, Inc., Docket

More information

SPP TLR (TEMPORARY

SPP TLR (TEMPORARY SPP TLR 5 Investigation Report Flowgate 15369 (TEMPORARY 11) Plant X Sundown 230 kv Line for the Loss of Tolk Yoakum 230 kv Line TLR Level 5: February 1, 2009 Report Issued: March 11, 2009 1. Description

More information

Rate Schedules and Seams Agreements Tariff

Rate Schedules and Seams Agreements Tariff Rate Schedules and Seams Agreements Tariff Southwest Power Pool Rate Schedules and Seams Agreements Tariff Document Generated On: 8/20/2015 Southwest Power Pool - Rate Schedules and Seams Agreements Tariff

More information

Long Term Access Goal Final Report Update

Long Term Access Goal Final Report Update Long Term Access Goal 2007-09 Final Report 2008-10 Update SME Version of Presentation for ATC Board of Directors Meeting December 14, 2009 2007-09 and 2008-10 Long Term Goals Access (10%) Reduce congestion

More information

Regional Transmission Organization Frequently Asked Questions

Regional Transmission Organization Frequently Asked Questions 1. The CRA analysis showed greater trade benefits to the Entergy region from joining SPP rather than joining MISO. Did Entergy re-do the CRA analysis? No. The CRA analysis was a key component of the Entergy

More information

10-YEAR COSTS AND BENEFITS TO SPP MEMBERS OF INTEGRATING MOUNTAIN WEST TRANSMISSION GROUP Quantitative Analysis of Costs and Benefits

10-YEAR COSTS AND BENEFITS TO SPP MEMBERS OF INTEGRATING MOUNTAIN WEST TRANSMISSION GROUP Quantitative Analysis of Costs and Benefits 10-YEAR COSTS AND BENEFITS TO SPP MEMBERS OF INTEGRATING MOUNTAIN WEST TRANSMISSION GROUP Quantitative Analysis of Costs and Benefits Published on March 19, 2018 By SPP Staff REVISION HISTORY DATE OR VERSION

More information

Southwest Power Pool, Inc. Policy Recommendation for the SPP Board of Directors and Members Committee. March 6, 2018 Mountain West Transmission Group

Southwest Power Pool, Inc. Policy Recommendation for the SPP Board of Directors and Members Committee. March 6, 2018 Mountain West Transmission Group Southwest Power Pool, Inc. Policy for the SPP Board of Directors and Members Committee Policy Area #1 DC Ties March 6, 2018 Mountain West Transmission Group SPP and MWTG anticipate that incorporating the

More information

Alberta Utilities Commission

Alberta Utilities Commission Alberta Utilities Commission In the Matter of the Need for 138 kv and 240 kv Transmission System Development in the Red Deer Region And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1,

More information

The cost allocation principles and methodologies in this Attachment Y cover only

The cost allocation principles and methodologies in this Attachment Y cover only 31.5 Cost Allocation and Cost Recovery 31.5.1 The Scope of Attachment Y Cost Allocation 31.5.1.1 Regulated Responses The cost allocation principles and methodologies in this Attachment Y cover only regulated

More information

Cost Allocation for Transmission Infrastructure

Cost Allocation for Transmission Infrastructure USAID/NARUC East Africa Regional Regulatory Partnership Exchange: Cost Allocation for Transmission Infrastructure Andrew Greene Massachusetts Dept. of Public Utilities Energy Facilities Siting Board Dar

More information

Benefits Determination and Cost Allocation

Benefits Determination and Cost Allocation Benefits Determination and Cost Allocation Johannes Pfeifenberger Transmission Executive Forum West 2012 Meeting Public Policy Objectives through Transmission Investment San Diego, CA October 22, 2012

More information

RR16 - Page 1 of

RR16 - Page 1 of DOCKET NO. APPLICATION OF SOUTHWESTERN PUBLIC SERVICE COMPANY FOR AUTHORITY TO CHANGE RATES PUBLIC UTILITY COMMISSION OF TEXAS DIRECT TESTIMONY of ARTHUR P. FREITAS on behalf of SOUTHWESTERN PUBLIC SERVICE

More information

Alberta Utilities Commission

Alberta Utilities Commission Alberta Utilities Commission In the Matter of the Need for the Grizzly Bear Creek Wind Power Plant Connection And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities

More information

SPP New Member Communication and Integration Process. Mountain West Transmission Group. Background Information October 2017

SPP New Member Communication and Integration Process. Mountain West Transmission Group. Background Information October 2017 1 SPP New Member Communication and Integration Process Mountain West Transmission Group Background Information October 2017 Contents Introduction... 2 1. Westside Tariff Design... 2 2. Operational Provisions...

More information

1st Qua u r a ter e M e M e e t e in i g 2nd Qua u r a ter e M e M e e t e in i g

1st Qua u r a ter e M e M e e t e in i g 2nd Qua u r a ter e M e M e e t e in i g 2012 SERTP Welcome SERTP 2012 First RPSG Meeting & Interactive Training Session 1 2012 SERTP The SERTP process is a transmission planning process. Please contact the respective transmission provider for

More information

April 6, 2018 VIA OVERNIGHT MAIL. Sheri Young, Secretary of the Board National Energy Board th Avenue SW Calgary, Alberta T2R 0A8

April 6, 2018 VIA OVERNIGHT MAIL. Sheri Young, Secretary of the Board National Energy Board th Avenue SW Calgary, Alberta T2R 0A8 !! April 6, 2018 VIA OVERNIGHT MAIL Sheri Young, Secretary of the Board National Energy Board 517 10 th Avenue SW Calgary, Alberta T2R 0A8 Re: North American Electric Reliability Corporation Dear Ms. Young:

More information

Information Document Available Transfer Capability and Transfer Path Management ID # R

Information Document Available Transfer Capability and Transfer Path Management ID # R Information Documents are not authoritative. Information Documents are for information purposes only and are intended to provide guidance. In the event of any discrepancy between an Information Document

More information

December 9, City of Farmington Integrated Resource Planning (IRP)

December 9, City of Farmington Integrated Resource Planning (IRP) December 9, 2016 City of Farmington Integrated Resource Planning (IRP) Restricted Siemens AG 2013 All rights reserved. Answers for infrastructure and cities. Pace Global Disclaimer This Report was produced

More information

SPP TLR (TEMPORARY

SPP TLR (TEMPORARY SPP TLR 5 Investigation Report Flowgate 15613 (TEMPORARY 20) Sikeston Idalia 161 kv Line for the Loss of New Madrid Tipton 161 kv Line TLR Level 5: February 12, 2009 Report Issued: March 11, 2009 1. Description

More information

MISO PJM IPSAC. August 26, PJM IPSAC Meeting, August 26,

MISO PJM IPSAC. August 26, PJM IPSAC Meeting, August 26, MISO PJM IPSAC August 26, 2016 1 Agenda 2 Targeted Market Efficiency Project (TMEP) Study TMEP Proposed JOA Language FERC EL13-88 Filings IPSAC Work Schedule 2 3 Targeted Market Efficiency Project Study

More information

April 24, 2015 VIA ELECTRONIC FILING

April 24, 2015 VIA ELECTRONIC FILING April 24, 2015 VIA ELECTRONIC FILING The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: Southwest Power Pool, Inc., Docket No.

More information

Wairakei Ring Investment Proposal. Project Reference: CTNI_TRAN-DEV-01. Attachment A GIT Results

Wairakei Ring Investment Proposal. Project Reference: CTNI_TRAN-DEV-01. Attachment A GIT Results Wairakei Ring Investment Proposal Project Reference: CTNI_TRAN-DEV-01 Attachment A GIT Results December 2008 Document Revision Control Document Number/Version 001/Rev A Description Wairakei Ring Investment

More information

ATC Customer Benefit Metric

ATC Customer Benefit Metric ATC Customer Benefit Metric Marty Smith ATC Economic Planning April 5, 2012 Helping to keep the lights on, businesses running and communities strong Background ATC has used the Customer Benefit (CB) Metric

More information

Transmission Investment Trends and Planning Challenges

Transmission Investment Trends and Planning Challenges Transmission Investment Trends and Planning Challenges Presented at: EEI Transmission and Wholesale Markets School Presented by: Johannes Pfeifenberger Madison, WI August 8, 2012 Copyright 2012 The Brattle

More information

MISO Cost Allocation Response. RECBWG February 15, 2018

MISO Cost Allocation Response. RECBWG February 15, 2018 MISO Cost Allocation Response RECBWG February 15, 2018 MISO Cost Allocation Response: February 2018 Context The overall objective of the MISO transmission cost allocation methodology is to align who pays

More information

SPP s Operating Region

SPP s Operating Region SPP s Operating Region Current 77,366 MW of generating capacity 46,136 MW of peak demand 48,930 miles transmission: 69 kv 12,569 miles 115 kv 10,239 miles 138 kv 9,691 miles 161 kv 5,049 miles 230 kv 3,889

More information

Monthly State of the Market Report October 2010

Monthly State of the Market Report October 2010 Monthly State of the ket Report ober 20 Published ember 15, 20 Table of Contents Executive Summary...2 Metrics...3 Figure 1 SPP EIS Price Contour Map...3 Figure 2 Congestion by Shadow Price Impact ober

More information

Northern Tier Transmission Group Cost Allocation Principles Work Group. Straw Proposal. May 29, 2007

Northern Tier Transmission Group Cost Allocation Principles Work Group. Straw Proposal. May 29, 2007 Northern Tier Transmission Group Cost Allocation Principles Work Group Straw Proposal May 29, 2007 NTTG Cost Allocation Principles and Process page 1 INTRODUCTION This paper makes a strawman proposal responsive

More information

SPP Reserve Sharing Group Operating Process

SPP Reserve Sharing Group Operating Process SPP Reserve Sharing Group Operating Process Effective: 1/1/2018 1.1 Reserve Sharing Group Purpose In the continuous operation of the electric power network, Operating Capacity is required to meet forecasted

More information

Lower Voltage Interregional Economic Projects. RECBWG April 18, 2018

Lower Voltage Interregional Economic Projects. RECBWG April 18, 2018 Lower Voltage Interregional Economic Projects RECBWG April 18, 2018 Interregional Gaps & Inconsistencies 1. No tariff defined cost allocation for sub 345 kv economic projects with PJM 2. Economic projects

More information

Monthly State of the Market Report November 2010

Monthly State of the Market Report November 2010 Monthly State of the ket Report ember 20 Published ember 17, 20 Table of Contents Executive Summary...2 Metrics...3 Figure 1 SPP EIS Price Contour Map...3 Figure 2 Congestion by Shadow Price Impact ember

More information

PJM SERTP Planning Process Overview

PJM SERTP Planning Process Overview PJM SERTP Planning Process Overview Order 1000 Biennial Regional Transmission Plan Review Meeting Presentation 1 of 2 May 8 th, 2018 Georgia Power Corporate Headquarters Atlanta, GA PJM SERTP Interregional

More information

2011 IRP Public Input Meeting. October 5, Pacific Power Rocky Mountain Power PacifiCorp Energy

2011 IRP Public Input Meeting. October 5, Pacific Power Rocky Mountain Power PacifiCorp Energy 2011 IRP Public Input Meeting October 5, 2010 Pacific Power Rocky Mountain Power PacifiCorp Energy Agenda Morning Session IRP Schedule Update Energy Gateway Transmission Construction Update and Evaluation

More information

PROJECT COST TASK FORCE. June 2, 2011

PROJECT COST TASK FORCE. June 2, 2011 PROJECT COST TASK FORCE June 2, 2011 Table of Contents Introduction...3 RSC Motion 1...3 Problem Summary...3 RSC Motion 4...3 Problem Summary...3 Project Tracking Current Process...4 PCTF Recommendations...4

More information

Transmission System Expansion Cost Allocation Alternatives for Renewable Resources. Cost Allocation Working Group March 26, 2008 OG&E Ver 2 3/20/8

Transmission System Expansion Cost Allocation Alternatives for Renewable Resources. Cost Allocation Working Group March 26, 2008 OG&E Ver 2 3/20/8 Transmission System Expansion Cost Allocation Alternatives for Renewable Resources Cost Allocation Working Group March 26, 2008 OG&E Ver 2 3/20/8 Page 1 Why Page 2 Page 1 of 11 Basic Principles Wind generation

More information

Renewable Generation, Transmission and the Energy Marketplace

Renewable Generation, Transmission and the Energy Marketplace Renewable Generation, Transmission and the Energy Marketplace Portfolio Development and Business Case October 25, 2012 Overview Multi Value Projects reflect the transformation of the MISO planning process

More information

EIPC GAS-ELECTRIC SYSTEM INTERFACE STUDY

EIPC GAS-ELECTRIC SYSTEM INTERFACE STUDY EIPC GAS-ELECTRIC SYSTEM INTERFACE STUDY Status Update Mark Babula Principal Engineer System Planning ISO New England Inc. NPCC Governmental/Regulatory Affairs Advisory Group December 3, 2013 Table of

More information

Informational Filing of Midwest Independent Transmission System Operator, Inc. s Independent Market Monitor

Informational Filing of Midwest Independent Transmission System Operator, Inc. s Independent Market Monitor Potomac Economics, Ltd. 9990 Fairfax Boulevard, Suite 560 Telephone: 703-383-0720 Fairfax, Virginia 22030 Facsimile: 703-383-0796 Honorable Kimberly D. Bose, Secretary Federal Energy Regulatory Commission

More information

Stakeholder Comment Matrix Harry Allen-Eldorado 500 kv line project December 12, 2014

Stakeholder Comment Matrix Harry Allen-Eldorado 500 kv line project December 12, 2014 The ISO received comments on the CAISO economic analysis results stakeholder meeting discussion held on November 20, 2014 1 from the following: 1. Bay Area Municipal Transmission group (BAMx) 2. California

More information

Estimating Capacity Benefits of the AC Transmission Public Policy Projects

Estimating Capacity Benefits of the AC Transmission Public Policy Projects Memorandum TO: NYISO Board of Directors FROM: David B. Patton and Pallas LeeVanSchaick DATE: RE: Estimating Capacity Benefits of the AC Transmission Public Policy Projects A. Introduction In the second

More information

2014 BUDGET PREPARED BY ACCOUNTING DEPARTMENT

2014 BUDGET PREPARED BY ACCOUNTING DEPARTMENT 2014 BUDGET PREPARED BY ACCOUNTING DEPARTMENT October 29, 2013 Southwest Power Pool Board of Directors RE: 2014 Budget Hello. The following presentation incorporates detailed financial information for

More information

Southwest Power Pool SEAMS STEERING COMMITTEE MEETING February 5, 2015 AEP Office, Dallas, TX MINUTES

Southwest Power Pool SEAMS STEERING COMMITTEE MEETING February 5, 2015 AEP Office, Dallas, TX MINUTES Southwest Power Pool SEAMS STEERIN COMMITTEE MEETIN February 5, 2015 AEP Office, Dallas, T MINUTES Agenda Item 1 Administrative Items Seams Steering Committee (SSC) Chair Paul Malone, NPPD, called the

More information

Southwest Power Pool SEAMS STEERING COMMITTEE MEETING July 8, 2014 Conference Call MINUTES

Southwest Power Pool SEAMS STEERING COMMITTEE MEETING July 8, 2014 Conference Call MINUTES Southwest Power Pool SEAMS STEERING COMMITTEE MEETING July 8, 2014 Conference Call MINUTES Agenda Item 1 Administrative Items Seams Steering Committee (SSC) Chair Paul Malone, NPPD, called the meeting

More information

COMMENTS OF NV ENERGY LOCAL MARKET POWER MITIGATION ENHANCEMENTS DRAFT FINAL PROPOSAL DATED JANUARY 31, 2019 CAISO STAKEHOLDER PROCESS

COMMENTS OF NV ENERGY LOCAL MARKET POWER MITIGATION ENHANCEMENTS DRAFT FINAL PROPOSAL DATED JANUARY 31, 2019 CAISO STAKEHOLDER PROCESS COMMENTS OF NV ENERGY LOCAL MARKET POWER MITIGATION ENHANCEMENTS DRAFT FINAL PROPOSAL DATED JANUARY 31, 2019 CAISO STAKEHOLDER PROCESS February 8 th, 2019 NV Energy appreciates the opportunity to comment

More information

Cost Allocation Reform Update

Cost Allocation Reform Update Cost Allocation Reform Update Regional Expansion Criteria and Benefits Working Group May 18, 2017 Conditions Precedent for Regional Transmission Investment 1. Increased consensus regarding the issue(s)

More information

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION ) ) ) ) ) ) ) ) ) ) ) DIRECT TESTIMONY RUTH M. SAKYA. on behalf of.

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION ) ) ) ) ) ) ) ) ) ) ) DIRECT TESTIMONY RUTH M. SAKYA. on behalf of. BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION IN THE MATTER OF SOUTHWESTERN PUBLIC SERVICE COMPANY S INTERIM REPORT ON ITS PARTICIPATION IN THE SOUTHWEST POWER POOL REGIONAL TRANSMISSION ORGANIZATION,

More information

153 FERC 61,249 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER REJECTING TARIFF REVISIONS. (Issued November 30, 2015)

153 FERC 61,249 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER REJECTING TARIFF REVISIONS. (Issued November 30, 2015) 153 FERC 61,249 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Norman C. Bay, Chairman; Cheryl A. LaFleur, Tony Clark, and Colette D. Honorable. Southwest Power Pool,

More information

Project Cost Review Process. SPP Project Cost Working Group

Project Cost Review Process. SPP Project Cost Working Group Project Cost Review Process SPP Project Cost Working Group Revision History Date or Version Number Author Change Description Comments PCWG Initial Draft 6/28/2012 PCWG Sub-group Edited by sub-group 7/31/2012

More information

NORTHEASTERN ISO/RTO PLANNING COORDINATION PROTOCOL DESIGNATION OF FILING PARTY

NORTHEASTERN ISO/RTO PLANNING COORDINATION PROTOCOL DESIGNATION OF FILING PARTY NORTHEASTERN ISO/RTO PLANNING COORDINATION PROTOCOL DESIGNATION OF FILING PARTY The Northeastern ISO/RTO Planning Coordination Protocol among PJM Interconnection, L.L.C. ( PJM ), the New York Independent

More information

Posting Date: 08/01/2015 Gentry Crowson, Market Forensics

Posting Date: 08/01/2015 Gentry Crowson, Market Forensics VRL Analysis Posting Date: 08/01/2015 Gentry Crowson, Market Forensics 2 Contents Executive Summary... 3 Background... 6 Analysis of OC Breach Characteristics in the Marketplace... 8 VRL Yearly Analysis

More information

ITC Holdings Corp. Investor Meetings. January 2015

ITC Holdings Corp. Investor Meetings. January 2015 ITC Holdings Corp. Investor Meetings January 2015 Safe Harbor Language & Legal Disclosure This presentation contains certain statements that describe our management s beliefs concerning future business

More information

Information Document FAC-008-AB-3 Facility Ratings ID # RS

Information Document FAC-008-AB-3 Facility Ratings ID # RS Information Documents are not authoritative. Information Documents are for information purposes only and are intended to provide guidance. In the event of any discrepancy between an Information Document

More information

Generation Retirement Scenario

Generation Retirement Scenario Generation Retirement Scenario Special Reliability Assessment December 18, 2018 NERC Report Title Report Date I Table of Contents Preface... iii Executive Summary... v Key Findings... vii Recommendations...

More information

Nevada Power & Sierra Pacific Power d/b/a NV Energy Stakeholders Planning Input Meeting July

Nevada Power & Sierra Pacific Power d/b/a NV Energy Stakeholders Planning Input Meeting July Nevada Power & Sierra Pacific Power d/b/a NV Energy Stakeholders Planning Input Meeting July 2012 1 1. Welcome Introductions 2. IRP filing and results Update on Loads and Resources Renewable Transmission

More information

Alberta Utilities Commission

Alberta Utilities Commission Alberta Utilities Commission In the Matter of the Need for the Jenner Wind Energy Connection And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities Commission Act,

More information

Filed with the Iowa Utilities Board on May 31, 2017, E STATE OF IOWA DEPARTMENT OF COMMERCE UTILITIES BOARD

Filed with the Iowa Utilities Board on May 31, 2017, E STATE OF IOWA DEPARTMENT OF COMMERCE UTILITIES BOARD STATE OF IOWA DEPARTMENT OF COMMERCE UTILITIES BOARD IN RE: MIDAMERICAN ENERGY IN RE: DOCKET NOS. E-22269, E-22270, AND E-22271 DOCKET NO. E-22279 (consolidated) ITC MIDWEST LLC BRIEF BY THE MIDCONTINENT

More information

Comments of PacifiCorp on the Consolidated EIM Initiatives

Comments of PacifiCorp on the Consolidated EIM Initiatives Comments of PacifiCorp on the Consolidated EIM Initiatives Submitted by Company Date Submitted Christine Kirsten christine.kirsten@pacificorp.com 916-207-4693 PacifiCorp June 30, 2017 Introduction PacifiCorp

More information

FIRST QUARTERLY PROJECT TRACKING REPORT 2018 January 2018

FIRST QUARTERLY PROJECT TRACKING REPORT 2018 January 2018 FIRST QUARTERLY PROJECT TRACKING REPORT 2018 January 2018 CONTENTS Executive Summary... 3 NTC Project Summary... 5 NTC Issuance... 7 NTC Withdraw... 7 Completed Projects... 8 Project status summary...

More information

Cost Estimation for Regional Transmission Overlay Study (RTOS)

Cost Estimation for Regional Transmission Overlay Study (RTOS) Cost Estimation for Regional Transmission Overlay Study (RTOS) Purpose & Key Takeaways Purpose: To provide detail for MISO s cost estimation approach Key Takeaways: Planning-Level and Scoping-Level MISO

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 36. Congestion Revenue Rights... 3 36.1 Overview Of CRRs And Procurement Of CRRs... 3 36.2 Types Of CRR Instruments... 3 36.2.1 CRR Obligations... 3 36.2.2 CRR Options... 3 36.2.3 Point-To-Point

More information

History of Cost Allocation within MISO RECB TF. January 29, 2015

History of Cost Allocation within MISO RECB TF. January 29, 2015 History of Cost Allocation within MISO RECB TF January 29, 2015 Cost Allocation FERC Orders, Filings, and Rulings Cost allocation for MISO began with Order 2003 which instituted a pro forma Generator Interconnection

More information

T-D Interconnections: Best Value Planning White Paper January 2016

T-D Interconnections: Best Value Planning White Paper January 2016 T-D Interconnections: Best Value Planning White Paper Updated January 2016 1. Purpose This paper defines the process and criteria that together constitute joint best value planning (BVP) between ATC and

More information

Market Monitoring Unit. State of the Market Fall 2017

Market Monitoring Unit. State of the Market Fall 2017 State of the ket 20 published uary 22, 2018 TABLE OF CONTENTS List of figures... i 1. ket performance highlights... 1 2. Prices and market costs... 3 3. Demand, generation and unit commitment... 21 4.

More information

APPENDIX B: WHOLESALE AND RETAIL PRICE FORECAST

APPENDIX B: WHOLESALE AND RETAIL PRICE FORECAST Seventh Northwest Conservation and Electric Power Plan APPENDIX B: WHOLESALE AND RETAIL PRICE FORECAST Contents Introduction... 3 Key Findings... 3 Background... 5 Methodology... 7 Inputs and Assumptions...

More information

Standard Development Timeline

Standard Development Timeline PRC 012 2 Remedial Action Schemes Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

More information

WECC Process for Risk-Based Compliance Oversight Inherent Risk Assessment and Compliance Oversight Plan

WECC Process for Risk-Based Compliance Oversight Inherent Risk Assessment and Compliance Oversight Plan WECC Process for Risk-Based Compliance Oversight Inherent Risk Assessment and Compliance Oversight Plan WECC Entity Oversight Effective Date: April 1, 2017 155 North 400 West, Suite 200 Salt Lake City,

More information

Supplemental Report on the NCTPC 2006 Collaborative Transmission Plan

Supplemental Report on the NCTPC 2006 Collaborative Transmission Plan Supplemental Report on the NCTPC 2006 Collaborative Transmission Plan 04/26/07 Table of Contents I. Executive Summary...3 II. Introduction...4 III. 1,200 MW Resource Supply Option Study Increased Imports

More information

PRC Remedial Action Schemes

PRC Remedial Action Schemes PRC-012-2 Remedial Action Schemes A. Introduction 1. Title: Remedial Action Schemes 2. Number: PRC-012-2 3. Purpose: To ensure that Remedial Action Schemes (RAS) do not introduce unintentional or unacceptable

More information

PJM & MISO Assumptions and Criteria for Testing of New Resources

PJM & MISO Assumptions and Criteria for Testing of New Resources & Assumptions and Criteria for Testing of New Resources 1 Introduction These slides provide a description and comparison of the assumptions and criteria used by and during the study of customer proposed

More information

ITC Holdings Corp. Investor Meetings. March 2015

ITC Holdings Corp. Investor Meetings. March 2015 ITC Holdings Corp. Investor Meetings March 2015 Safe Harbor Language & Legal Disclosure This presentation contains certain statements that describe our management s beliefs concerning future business conditions

More information

Transmission Loss Factor Methodology

Transmission Loss Factor Methodology Transmission Loss Factor Methodology Discussion Paper Operations & Reliability Draft February 9, 2005 Table of Contents 1. Introduction...3 1.1 Legislative Direction.....3 1.2 Goal and Objectives... 3

More information

COLUMBIAGRID GEOMAGNETIC DISTURBANCE DRAFT STUDY REPORT

COLUMBIAGRID GEOMAGNETIC DISTURBANCE DRAFT STUDY REPORT COLUMBIAGRID GEOMAGNETIC DISTURBANCE DRAFT STUDY REPORT (NERC Standard TPL-007-1) Revision 1 February 1, 2018 ColumbiaGrid 8338 NE Alderwood Road, Suite 140 Portland, OR 97220 www.columbiagrid.org (503)

More information

Both the ISO-NE and NYISO allow bids in whole MWh increments only.

Both the ISO-NE and NYISO allow bids in whole MWh increments only. Attachment D Benchmarking against NYISO, PJM, and ISO-NE As the CAISO and stakeholders consider various design elements of convergence bidding that may pose market manipulation concerns, it is useful to

More information

Strategic Planning Committee Task Force Clean Power Plan Meeting No. 03 December 4, 2015

Strategic Planning Committee Task Force Clean Power Plan Meeting No. 03 December 4, 2015 Strategic Planning Committee Task Force Clean Power Plan Meeting No. 03 December 4, 2015 Southwest Power Pool SPCTF CLEAN POWER PLAN Friday, December 4, 2015 AEP Office, Dallas, Texas MINUTES Agenda Item

More information

Expenditure Forecast Methodology

Expenditure Forecast Methodology Forecast Methodology Regulatory Control Period 2018-19 to 2022-23 Version 1.0 Security Classification: Public ElectraNet Corporate Headquarters 52-55 East Terrace, Adelaide, South Australia 5000 PO Box

More information

Stochastic Loss of Load Study for the 2011 Integrated Resource Plan

Stochastic Loss of Load Study for the 2011 Integrated Resource Plan November 18, 2010 Stochastic Loss of Load Study for the 2011 Integrated Resource Plan INTRODUCTION PacifiCorp evaluates the desired level of capacity planning reserves for each integrated resource plan.

More information