SPP REPORT ON TLR EVENTS FROM FEBRUARY 13 MARCH 4, 2002
|
|
- Edward Richard
- 6 years ago
- Views:
Transcription
1 SPP REPORT ON TLR EVENTS FROM FEBRUARY 13 MARCH 4, 2002 On seven occasions between February 13 and March 4, 2002, SPP initiated a TLR on the MorStiSooNor flow gate, #5067, that included firm service curtailments. In response to NERC reporting requirements, SPP prepared a report on these events addressing thirteen bullet points associated with an initial investigation. The following is the report submitted by SPP for the February 13-March 4 MorStiSooNor TLR events addressing each of those points. 1. Description of purpose/cause of curtailment The purpose of these TLRs initiated by SPP between February 13, 2002 and March 4, 2002 was to relieve the Morrison Tap-Stillwater 138 kv line (Monitored Element) of excessive flows that would have resulted from an unexpected loss of the Spring Creek- Northwest 345 kv line (Contingency Element). This facility is modeled as a flow gate labeled MorStiSooNor (flow gate # 5067) in the IDC for which an Outage Transfer Distribution Factor is calculated based on the loss of the Contingency Element. 2. Facility/flow gate limitations and flows at the time the TLR was initiated. The Monitored Element has an emergency rating of 191 MVA based on a wave trap limitation. In each of the TLR events, the calculated post-contingency flow on the Monitored Element had either exceeded, or was expected to exceed, the 191 MVA line rating. 3. TLR levels, timing and relief requested amounts Attachment A contains the NERC TLR Procedure Logs for the February 13-March 4 TLR events on the MorStiSooNor flow gate. These logs contain timing of TLR actions, TLR levels, and the number, priority and amount of curtailments. All times are in CST. Please note that the log for February 27 indicates that while a TLR was issued, the NNL calculation within the IDC was not functioning during the event. The NNL responsibility for OG&E was estimated based on previous experience with this flowgate. Estimates indicated that WFEC s NNL responsibility was less than 1 MW. Since this was an estimate and it was very small, WFEC was not requested to provide NNL relief during this event. 4. Transmission and Generation outages or changes from prediction that may have contributed. On January 30, 2002 a major ice storm hit south central Kansas and north central Oklahoma. Ice accumulations of 6 inches were recorded in some areas of this region. The electric systems of American Electric Power (AEP), Oklahoma Gas & Electric (OG&E), Western Farmers Electric Cooperative (WFEC) and Westar (WR) suffered significant damage resulting in numerous transmission line outages. During the TLR events covered in this report, kv lines and as many as kv lines in this area were out-of-service due to the ice storm. These lines are listed in Attachment B.
2 SPP Report on TLR Events on February 13-March 4, 2002 Most of these facilities were in an area north and west of a line running from Oklahoma City, OK to Tulsa, OK. This area is shown in a map in Attachment C. Three of the 345 kv lines terminated at OG&E s Woodring substation and included a major tie to Westar to the north and a critical line to OG&E s Sooner Plant (1,020 MW of generating capacity) to the east. Approximately 650 structures were down in these three lines alone. With the Sooner-Woodring line out, Sooner s only remaining 345 kv outlet was the Sooner-Spring Creek-Northwest 345 kv line. A 336 MW IPP, OneOk, is located at the Spring Creek station. Given this configuration, if the Spring Creek- Northwest 345 kv line trips, all of the Sooner generation and the OneOk generation is rerouted to the 138 kv system around Sooner. This system is not capable of handling this amount of generation with all 138 kv lines in the area in-service. With several 138 kv facilities in the area out-of-service, overloading is exacerbated. OneOk has a firm point-to-point transmission reservation out of OG&E, but since the bulk of OG&E s generation is south of the MorStiSooNor flowgate, the impact of this transaction on the flow gate is less than the 5% threshold according to TDF calculations by the IDC. Therefore any transaction utilizing this reservation does not show up in the IDC Adjust Lists. However, OneOk is included in the list of generators impacting the flowgate more than 5% in the Control Area NNL Responsibility table in the IDC. Thus whenever OneOk utilizes its firm service reservation, the post-contingency flow on the flowgate is projected to exceed the rating of the monitored element forcing a Level 5 TLR. 5. Procedures implemented prior to curtailment. Recognizing the situation, OG&E shut down Sooner 2 prior to February 13 in an effort to limit loading on the flowgate. A scheduled maintenance outage for Sooner 2 was subsequently accelerated in order to take advantage of this forced reduction. The output of Sooner 1 is adjusted continuously to maintain flow gate loading below its rating. 6. Complete Transaction Curtailment lists & comparison to IDC Transaction Lists both before and after curtailment. Attachment D contains the Congestion Management Reports including the initial and subsequent TLR Level 5 curtailment lists and the control area NNL responsibilities issued by the IDC for relief on the MorStiSooNor flow gate for the events of February 13 through March Known transactions not in the IDC & actions taken. SPP assumed that all transactions were in the IDC and was not aware of any transactions flowing that were not in the IDC. 8. SCIS or other system messages No additional messaging for this TLR was posted other than that through the IDC. SPP 2 4/12/02
3 SPP Report on TLR Events on February 13-March 4, State Estimator snapshots and security analysis including any contingency analysis or stability analysis along with any other recorded data indicating need for Transmission Loading Relief Attachment E contains screen prints of Flowgate Detail from the SPP EMS used to monitor post-contingency flows on the SPP flow gates. These particular prints were made as each TLR Level 5 was being taken. Only one of the prints, associated with the 1723 event on February 13, 2002, indicates that the flow gate loading was clearly beyond its emergency limit of 191 MVA. (The EMS time stamps are in CST.) This is because the TLR was not issued during this event until after the IPP s firm transaction had started to ramp in. Subsequent TLRs, except for the 0623 event on February 27, 2002, were declared in anticipation of the firm transaction starting thus preventing the overload of the flow gate and an emergency redispatch of generation in OG&E. The screen prints for February 13 contain some hand written values. This is because the display had not been updated to coincide with a change in the contingent element brought about by system topology following the ice storm. Note the change in the contingent element and the monitored element calculation between the screen prints taken on February 13 and those taken on February 15 which reflect the changes. Note also that the display became fully operational by the time the 0916 print was taken on the 15 th. Results from other periodic analyses of pre-contingency and post-contingency flows from the EMS can be found in the NERC TLR Procedure Logs in Attachment A. 10. ATC limitations before, during and after the TLR event. The MorStiSooNor flow gate had not experienced any heavy loading or low ATCs prior to the transmission outages caused by the ice storm. 11. Description of actions taken to avoid future curtailments Although there wasn t much that could have been done to prevent the ice storm related outages that brought on this series of Level 5 TLRs, OG&E, WFEC and Westar have done a commendable job of repairing and returning facilities to service. Work continues on a daily basis to ensure that all repairs are completed and the facilities returned to service before the summer peak season. 12. Re-dispatch actions taken. As mentioned previously OG&E assumed the burden of redispatching its Sooner generation to prevent overloading on the flow gate. This ultimately led to OG&E accelerating a maintenance outage on Sooner 2 to take advantage of the forced downtime. Additional redispatch action was not taken until the Level 5 TLRs were issued as covered in Item 13 below. 13. If firm transaction curtailment took place, description of Transactional Contribution Factor calculation and results as well as how necessary relief was obtained through network service and native load contribution. SPP used the Transactional Contribution Factor (TCF) calculation process explained in the Parallel Flow Calculation Procedure Reference Document to determine the amount of relief required by native load and network service. The actual calculation was SPP 3 4/12/02
4 SPP Report on TLR Events on February 13-March 4, 2002 performed using the IDC. The results of the calculations are shown in Attachment D, the IDC Congestion Management Reports (CMR), for the events of February 13 March 4. In each report the Control Area NNL Responsibility table details the relief to be provided by NNL. The summary of all curtailments, NNL responsibilities and pointto-point service, can be found in the Next Hour Reallocation/Reload Report or the Current Hour Transactions Curtailment List of each Level 5A or 5B, respectively, CMR. For each event, results indicated that generators serving native load or providing network service in the OG&E, WFEC and WR control areas contributed to the postcontingency loading on the Monitored Element. The curtailment prescriptions for each TLR issuance on each day are summarized in Attachment F. The table indicates the time of issue, a breakdown of the relief and how much NNL relief was actually provided by each control area. Because the impacting generators in the WR control area were not on-line during these events, WR was relieved of any NNL responsibility. OG&E and WFEC provided the native load and network service relief assigned to them by redispatch as noted in the attachment. WFEC was not asked to provide NNL relief during the February 28 event due to oversight on the part of the SPP Reliability Authority. SPP 4 4/12/02
5 NERC TRANSMISSION LOADING RELIEF (TLR) PROCEDURE LOG FILE SAVED AS: O:\SECURITY\SECURITY DOCUMENTS\NERC TLR Log\SPP_2002 INCIDENT : SPP_ DATE: 2/13/2002 IMPACTED SECURITY COORDINATOR : SPP ID NO: 5067 I N I T I A L C O N D I T I O N S The Sooner-Woodring 345 kv and other 138 kv lines in the vicinity of Sooner remain out-of-service due the ice storm of January 30, 2002 Limiting Flowgate (LIMIT) Rating Contingent Flowgate (CONT.) ODF Morrison Tap - Stillwater 138 kv line 191 Sooner - Northwest 345 kv 45% TLR Levels Priorities NX Next Hour Market Service 0: TLR Incident Canceled NS Service over secondary receipt and delivery points 1. Notify Security Coordinators of potential problems. NH Hourly Service 2: Halt additional transactions that contribute to the overload ND Daily Service 3a and 3b: Curtail transactions using Non-firm Transmission Service NW Weekly Service 4. Reconfigure to continue firm transactions if needed. NM Monthly Service 5a and 5b: Curtail Transactions using Firm Transmission Service. NN Non-firm imports for native load and network customers from 6: Implement emergency procedures. non-designated network resources F Firm Service T L R A C T I O N S TLR 3,5 TLR 3,5 LIMIT CONT. LEVEL TIME Priority NO. TX MW Present Post-Cont. Present C O M M E N T S A B O U T A C T I O N S Curtail Curtail Flow Flow Flow 5B Issued TLR Level 5B, OG&E and WFEC redispatched generation to relieve flowgate loading Reissued TLR as Level 5A, released some redispatch OG&E and WFEC 5A A Reissued TLR Leve 5A, released additional redispatch Reissued TLR as Level 0
6 NERC TRANSMISSION LOADING RELIEF (TLR) PROCEDURE LOG FILE SAVED AS: O:\SECURITY\SECURITY DOCUMENTS\NERC TLR Log\SPP_2002 INCIDENT : SPP_ DATE: 2/15/2002 IMPACTED SECURITY COORDINATOR : SPP ID NO: 5067 I N I T I A L C O N D I T I O N S The Sooner-Woodring 345 kv and other 138 kv lines in the vicinity of Sooner remain out-of-service due the ice storm of January 30, 2002 Limiting Flowgate (LIMIT) Rating Contingent Flowgate (CONT.) ODF Morrison Tap - Stillwater 138 kv line 191 Sooner - Northwest 345 kv line 45% TLR Levels Priorities NX Next Hour Market Service 0: TLR Incident Canceled NS Service over secondary receipt and delivery points 1. Notify Security Coordinators of potential problems. NH Hourly Service 2: Halt additional transactions that contribute to the overload ND Daily Service 3a and 3b: Curtail transactions using Non-firm Transmission Service NW Weekly Service 4. Reconfigure to continue firm transactions if needed. NM Monthly Service 5a and 5b: Curtail Transactions using Firm Transmission Service. NN Non-firm imports for native load and network customers from 6: Implement emergency procedures. non-designated network resources F Firm Service T L R A C T I O N S TLR 3,5 TLR 3,5 LIMIT CONT. LEVEL TIME Priority NO. TX MW Present Post-Cont. Present C O M M E N T S A B O U T A C T I O N S Curtail Curtail Flow Flow Flow Issued TLR Level 5A, OG&E and WFEC redispatched generation to relieve flowgate loading in anticipation of firm transaction scheduled to start at A A Reissued TLR as Level 5A, redispatch held at previous hour's level Reissued TLR as Level 0 Issued TLR Level 5A, OG&E and WFEC redispatched generation to relieve flowgate loading in anticipation of firm transaction scheduled to start at A Reissued TLR as Level 0
7 NERC TRANSMISSION LOADING RELIEF (TLR) PROCEDURE LOG FILE SAVED AS: O:\SECURITY\SECURITY DOCUMENTS\NERC TLR Log\SPP_2002 INCIDENT : SPP_ DATE: 2/27/2002 IMPACTED SECURITY COORDINATOR : SPP ID NO: 5067 I N I T I A L C O N D I T I O N S The Sooner-Woodring 345 kv and other 138 kv lines in the vicinity of Sooner remain out-of-service due the ice storm of January 30, 2002 Limiting Flowgate (LIMIT) Rating Contingent Flowgate (CONT.) ODF Morrison Tap-Stillwater 138kv line 191 Sooner-Northwest 345kv line 45% TLR Levels Priorities NX Next Hour Market Service 0: TLR Incident Canceled NS Service over secondary receipt and delivery points 1. Notify Security Coordinators of potential problems. NH Hourly Service 2: Halt additional transactions that contribute to the overload ND Daily Service 3a and 3b: Curtail transactions using Non-firm Transmission Service NW Weekly Service 4. Reconfigure to continue firm transactions if needed. NM Monthly Service 5a and 5b: Curtail Transactions using Firm Transmission Service. NN Non-firm imports for native load and network customers from 6: Implement emergency procedures. non-designated network resources F Firm Service T L R A C T I O N S TLR 3,5 TLR 3,5 LIMIT CONT. LEVEL TIME Priority NO. TX MW Present Post-Cont. Present C O M M E N T S A B O U T A C T I O N S Curtail Curtail Flow Flow Flow 5A , Issued TLR Level 5A, OG&E redispatched generation to relieve flowgate loading in anticipation of firm transaction scheduled to start at IDC did not provide NNL responsibilities, therefore redispatch amounts were estimated. 5A Reissued TLR Level 5A, OG&E continues to redispatch generation to relieve flowgate loading in anticipation of firm transaction scheduled to run at IDC did not provide NNL responsibilities, therefore redispatch amounts were estimated Reissued TLR as level 0
8 NERC TRANSMISSION LOADING RELIEF (TLR) PROCEDURE LOG FILE SAVED AS: O:\SECURITY\SECURITY DOCUMENTS\NERC TLR Log\SPP_2002 INCIDENT : SPP_ DATE: 2/28/2002 IMPACTED SECURITY COORDINATOR : SPP ID NO: 5067 I N I T I A L C O N D I T I O N S The Sooner-Woodring 345 kv and other 138 kv lines in the vicinity of Sooner remain out-of-service due the ice storm of January 30, 2002 Limiting Flowgate (LIMIT) Rating Contingent Flowgate (CONT.) ODF Morrison Tap - Stillwater 138 kv line 191 Sooner - Northwest 345 kv line 45% TLR Levels Priorities NX Next Hour Market Service 0: TLR Incident Canceled NS Service over secondary receipt and delivery points 1. Notify Security Coordinators of potential problems. NH Hourly Service 2: Halt additional transactions that contribute to the overload ND Daily Service 3a and 3b: Curtail transactions using Non-firm Transmission Service NW Weekly Service 4. Reconfigure to continue firm transactions if needed. NM Monthly Service 5a and 5b: Curtail Transactions using Firm Transmission Service. NN Non-firm imports for native load and network customers from 6: Implement emergency procedures. non-designated network resources F Firm Service T L R A C T I O N S TLR 3,5 TLR 3,5 LIMIT CONT. LEVEL TIME Priority NO. TX MW Present Post-Cont. Present C O M M E N T S A B O U T A C T I O N S Curtail Curtail Flow Flow Flow Issued TLR Level 5B, OG&E redispatching generation to relieve overload on 5B flowgate Reissued TLR as Level 0 5A 0809 Issued Preliminary TLR Level 5A 5A , Reissued TLR as Level 5A Final -- OKGE redispatched generation in anticipation of firm transaction scheduled to start at Reissued TLR as Level 0
9 NERC TRANSMISSION LOADING RELIEF (TLR) PROCEDURE LOG FILE SAVED AS: O:\SECURITY\SECURITY DOCUMENTS\NERC TLR Log\SPP_2002 INCIDENT : SPP_ DATE: 3/4/2002 IMPACTED SECURITY COORDINATOR : SPP ID NO: 5067 I N I T I A L C O N D I T I O N S The Sooner-Woodring 345 kv and other 138 kv lines in the vicinity of Sooner remain out-of-service due the ice storm of January 30, 2002 Limiting Flowgate (LIMIT) Rating Contingent Flowgate (CONT.) ODF Morrison Tap-Stillwater 138kv line 191 Sooner-Northwest 345kv line 45% TLR Levels Priorities NX Next Hour Market Service 0: TLR Incident Canceled NS Service over secondary receipt and delivery points 1. Notify Security Coordinators of potential problems. NH Hourly Service 2: Halt additional transactions that contribute to the overload ND Daily Service 3a and 3b: Curtail transactions using Non-firm Transmission Service NW Weekly Service 4. Reconfigure to continue firm transactions if needed. NM Monthly Service 5a and 5b: Curtail Transactions using Firm Transmission Service. NN Non-firm imports for native load and network customers from 6: Implement emergency procedures. non-designated network resources F Firm Service T L R A C T I O N S TLR 3,5 TLR 3,5 LIMIT CONT. LEVEL TIME Priority NO. TX MW Present Post-Cont. Present C O M M E N T S A B O U T A C T I O N S Curtail Curtail Flow Flow Flow 5A Issued Preliminary TLR Level 5A in anticipation of firm transaction starting at Redispatch required to prevent flowgate overloading. 5A Reissued TLR as Level 5A Final, requested redispatch by OG&E and WFEC generation Reissued TLR as Level 0, EES curtailed transaction that was firm in SPP as non-firm transaction in EES for TLR on Weber-Richard flowgate. Issued TLR Level 5A in anticipation of firm transaction starting at OG&E and WFEC requested to redispatch to prevent flowgate overloading. 5A A Reissued TLR Level 5A, relieved some redispatch by OG&E and WFEC generation 5A Reissued TLR Level 5A, relieved additional redispatch by OG&E and WFEC generation Reissued TLR as Level 0, firm transaction scheduled to end at 1000
10 Transmission Line Outages Caused by the Ice Storm 345 kv Neosho-Rose Hill (WR) Woodring-Cimarron (OG&E) Woodring-Sooner (OG&E) Woodring-Wichita (OG&E/WR) 138 kv Altoona-Butler (WR) Clinton Junction-Weatherford Junction (CSWS) Cow Creek-Morrison Tap (OG&E) Dover-Okeene (WFEC) Hennessey-Dover (WFEC) Hydro-Weatherford (WFEC) Jensen Road-Weatherford Junction (CSWS) Otter-Woodring (OG&E) Sara-Cimarron (OG&E) Waukomis Tap-South 4 th Street (OG&E) Waukomis Tap-Woodring (OG&E) Woodring-Cottonwood Creek (OG&E)
11 PDF created with FinePrint pdffactory trial version
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59 MorStiSooNor TLR NNL Relief Date Issue Relief NNL Relief Time Non-firm Firm NNL Total CA Contribution Provided 2/13/ : OG&E WFEC : OG&E WFEC : OG&E WFEC /15/2002 6: OG&E WFEC : OG&E WFEC : OG&E WFEC /27/02 1 8: OG&E : OG&E /28/2002 6: OG&E WFEC : OG&E WFEC /4/02 2 6: OG&E WFEC : OG&E WFEC : OG&E WFEC NNL responsibilities not calculated by the IDC 2 - Level 5 TLR initially issued at 0504 but reissued as a Level 0 at 0542 because of tag adjustments
SPP TLR (TEMPORARY
SPP TLR 5 Investigation Report Flowgate 15369 (TEMPORARY 11) Plant X Sundown 230 kv Line for the Loss of Tolk Yoakum 230 kv Line TLR Level 5: February 1, 2009 Report Issued: March 11, 2009 1. Description
More informationSPP TLR (TEMPORARY
SPP TLR 5 Investigation Report Flowgate 15613 (TEMPORARY 20) Sikeston Idalia 161 kv Line for the Loss of New Madrid Tipton 161 kv Line TLR Level 5: February 12, 2009 Report Issued: March 11, 2009 1. Description
More informationWECC Guideline: UNSCHEDULED FLOW REDUCTION GUIDELINE
The content of this document is an excerpt of the WECC Unscheduled Flow Mitigation Plan Document posted on www.wecc.biz. Introduction WECC : UNSCHEDULED FLOW REDUCTION GUIDELINE The combination of Scheduled
More informationIntroduction to IDC Factors
Introduction to IDC Factors TDF Transfer Distribution Factor GSF Generation Shift Factor LSF Load Shift Factor GLDF Generation-to-Load Distribution Factor LODF Line Outage Distribution Factor PTDF & OTDF
More informationSPP s Regional Review of SPP-MISO Coordinated System Plan Recommended Interregional Projects
SPP s Regional Review of SPP-MISO Coordinated System Plan Recommended Interregional Projects January 4, 2016 SPP Interregional Relations Table of Contents Executive Summary... 2 Introduction... 5 Stakeholder
More informationWestern Interconnection Unscheduled Flow Mitigation Plan, (WIUFMP)
Western Interconnection Unscheduled Flow Mitigation Plan, (WIUFMP) Purpose: The purpose of the Western Interconnection Unscheduled Flow Mitigation Plan (WIUFMP) is to mitigate flows on Qualified Paths
More informationMonthly State of the Market Report October 2010
Monthly State of the ket Report ober 20 Published ember 15, 20 Table of Contents Executive Summary...2 Metrics...3 Figure 1 SPP EIS Price Contour Map...3 Figure 2 Congestion by Shadow Price Impact ober
More informationCURTAILMENT OF TRANSMISSION AND ENERGY
CURTAILMENT OF TRANSMISSION AND ENERGY In this Section: Overview Scheduling Limit (SL) Curtailment Priority - Transmission Curtailment Priority - Energy Curtailment Process Curtailment of Losses Reloads
More informationSPP Reserve Sharing Group Operating Process
SPP Reserve Sharing Group Operating Process Effective: 1/1/2018 1.1 Reserve Sharing Group Purpose In the continuous operation of the electric power network, Operating Capacity is required to meet forecasted
More informationTABLE OF CONTENTS ARTICLE ONE: RECITALS... 5 ARTICLE TWO: ABBREVIATIONS, ACRONYMS, AND DEFINITIONS... 6 ARTICLE THREE: OPERATING COMMITTEE...
TABLE OF CONTENTS ARTICLE ONE: RECITALS... 5 ARTICLE TWO: ABBREVIATIONS, ACRONYMS, AND DEFINITIONS... 6 2.1 Abbreviations and Acronyms... 6 2.2 Definitions... 7 2.3 Rules of Construction... 10 ARTICLE
More informationStandard MOD Flowgate Methodology
A. Introduction 1. Title: Flowgate Methodology 2. Number: MOD-030-1 3. Purpose: To increase consistency and reliability in the development and documentation of transfer capability calculations for short-term
More informationSPP s Operating Region
SPP s Operating Region Current 77,366 MW of generating capacity 46,136 MW of peak demand 48,930 miles transmission: 69 kv 12,569 miles 115 kv 10,239 miles 138 kv 9,691 miles 161 kv 5,049 miles 230 kv 3,889
More informationMarket Monitoring Unit. State of the Market Fall 2018
State of the ket Fall 20 published uary 16, 2019 TABLE OF CONTENTS Table of contents... i List of figures... ii 1. ket highlights...1 2. Load and resources...3 2.1 Load... 3 2.2 Resources... 4 2.3 External
More informationMonthly State of the Market Report November 2010
Monthly State of the ket Report ember 20 Published ember 17, 20 Table of Contents Executive Summary...2 Metrics...3 Figure 1 SPP EIS Price Contour Map...3 Figure 2 Congestion by Shadow Price Impact ember
More informationFebruary 23, 2015 VIA ELECTRONIC FILING
February 23, 2015 VIA ELECTRONIC FILING The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: Southwest Power Pool, Inc., Docket
More informationA. Introduction. Standard MOD Flowgate Methodology
A. Introduction 1. Title: Flowgate Methodology 2. Number: MOD-030-3 3. Purpose: To increase consistency and reliability in the development and documentation of transfer capability calculations for short-term
More informationInformation Document Available Transfer Capability and Transfer Path Management ID # R
Information Documents are not authoritative. Information Documents are for information purposes only and are intended to provide guidance. In the event of any discrepancy between an Information Document
More informationPROJECT COSTS, ECONOMICS, AND OTHER PUBLIC INTEREST CONSIDERATIONS
Filed: September, 00 EB-00-0 Schedule Page of PROJECT COSTS, ECONOMICS, AND OTHER PUBLIC INTEREST CONSIDERATIONS This set of exhibits describes the costs of the proposed facilities and the economics of
More informationMemo to the MOPC and Board of Directors Highway-Byway Cost Allocation
Memo to the MOPC and Board of Directors Highway-Byway Cost Allocation SPP believes that the proposed Highway-Byway cost allocation methodology will promote new transmission construction by allocating:
More information130 FERC 61,033 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. [Docket No. RM ]
130 FERC 61,033 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION [Docket No. RM10-9-000] Transmission Loading Relief Reliability Standard and Curtailment Priorities (Issued January 21, 2010)
More informationMarket Monitoring Unit. State of the Market Fall 2017
State of the ket 20 published uary 22, 2018 TABLE OF CONTENTS List of figures... i 1. ket performance highlights... 1 2. Prices and market costs... 3 3. Demand, generation and unit commitment... 21 4.
More informationPeak Reliability SUMMARY DOCUMENT FOR STAKEHOLDER COMMENT. ECC Final State Design. Jeremy West. Manager, Interconnection Reliability Initiatives
Peak Reliability SUMMARY DOCUMENT FOR STAKEHOLDER COMMENT ECC Final State Design Jeremy West Manager, Interconnection Reliability Initiatives November 22, 2017 Vancouver, Washington Loveland, Colorado
More informationWholesale Energy Markets Overview. Jeff Klarer Market Strategist
Wholesale Energy Markets Overview Jeff Klarer Market Strategist Wisconsin Electric Utility Fuel Rules (PSC-116) Fuel Cost Components Fuel for generation (coal, natural gas, uranium, etc.) Energy market
More informationApril 6, 2018 VIA OVERNIGHT MAIL. Sheri Young, Secretary of the Board National Energy Board th Avenue SW Calgary, Alberta T2R 0A8
!! April 6, 2018 VIA OVERNIGHT MAIL Sheri Young, Secretary of the Board National Energy Board 517 10 th Avenue SW Calgary, Alberta T2R 0A8 Re: North American Electric Reliability Corporation Dear Ms. Young:
More informationPJM & MISO Assumptions and Criteria for Testing of New Resources
& Assumptions and Criteria for Testing of New Resources 1 Introduction These slides provide a description and comparison of the assumptions and criteria used by and during the study of customer proposed
More informationRate Schedules and Seams Agreements Tariff
Rate Schedules and Seams Agreements Tariff Southwest Power Pool Rate Schedules and Seams Agreements Tariff Document Generated On: 8/20/2015 Southwest Power Pool - Rate Schedules and Seams Agreements Tariff
More informationCAWG MEETING July 25, 2007 Marriott Country Club Plaza Kansas City, MO 11:00 am 5:00 pm AGENDA
CAWG MEETING July 25, 2007 Marriott Country Club Plaza Kansas City, MO 11:00 am 5:00 pm AGENDA 1. Introductions 11:00-11:10 2. STEP Screen to Portfolio Transition 11:10 12:00 Discussion lead by Charles
More informationTransmission Reliability Margin Implementation Document (TRMID) Revised 6/8/2012 Ver 2.0
Transmission Reliability Margin Implementation Document (TRMID) Revised 6/8/2012 Ver 2.0 Table of Contents Process Details... 3 Purpose... 3 User Requirements... 3 Process... 3 Process Overview... 3 Calculation
More informationNTTG REGIONAL TRANSMISSION PLAN. December 30, 2015
NTTG 2014-2015 REGIONAL TRANSMISSION PLAN December 30, 2015 1 Table of Contents Executive Summary... 3 Introduction... 3 The Northern Tier Transmission Group... 3 Participating Utilities... 4 Purpose of
More informationCOLUMBIAGRID GEOMAGNETIC DISTURBANCE DRAFT STUDY REPORT
COLUMBIAGRID GEOMAGNETIC DISTURBANCE DRAFT STUDY REPORT (NERC Standard TPL-007-1) Revision 1 February 1, 2018 ColumbiaGrid 8338 NE Alderwood Road, Suite 140 Portland, OR 97220 www.columbiagrid.org (503)
More informationImplementation of BAL Dede Subakti
Implementation of BAL-002-2 Dede Subakti Agenda Background information Impact assessment Issue statement Implementation options Request for comments Page 2 Background Information NERC BAL-002-2 was approved
More informationCost Allocation Principles for Seams Transmission Expansion Projects
Cost Allocation Principles for Seams Transmission Expansion Projects SPP s seams agreements currently contain requirements for SPP to develop coordinated system plans with its neighbors. The extent and
More informationStochastic Loss of Load Study for the 2011 Integrated Resource Plan
November 18, 2010 Stochastic Loss of Load Study for the 2011 Integrated Resource Plan INTRODUCTION PacifiCorp evaluates the desired level of capacity planning reserves for each integrated resource plan.
More informationBEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION SOUTHWESTERN PUBLIC SERVICE COMPANY S UNOPPOSED RESPONSE TO STAFF S COMMENTS
BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION IN THE MATTER OF SOUTHWESTERN ) PUBLIC SERVICE COMPANY S 2018 ) INTEGRATED RESOURCE PLAN FOR ) NEW MEXICO. ) CASE NO. 18-00215-UT ) SOUTHWESTERN PUBLIC
More informationSPP PLANNING AND COST ALLOCATION OVERVIEW
Benefit/Cost Ratio Primer 101 for the Regional Allocation Review Task Force August 4, 2011 1 SPP PLANNING AND COST ALLOCATION OVERVIEW 2 1 Transmission = 10% Retail Electricity Rates Transmission enables
More informationPosting Date: 08/01/2015 Gentry Crowson, Market Forensics
VRL Analysis Posting Date: 08/01/2015 Gentry Crowson, Market Forensics 2 Contents Executive Summary... 3 Background... 6 Analysis of OC Breach Characteristics in the Marketplace... 8 VRL Yearly Analysis
More informationAlberta Utilities Commission
Alberta Utilities Commission In the Matter of the Need for 138 kv and 240 kv Transmission System Development in the Red Deer Region And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1,
More informationA Tutorial on the Flowgates versus Nodal Pricing Debate. Fernando L. Alvarado Shmuel S. Oren PSERC IAB Meeting Tutorial November 30, 2000
A Tutorial on the Flowgates versus Nodal Pricing Debate Fernando L. Alvarado Shmuel S. Oren PSERC IAB Meeting Tutorial November 30, 2000 PSERC IAB Meeting, November 2000 Objectives 1. Understand the relationship
More informationTransmission Reliability Margin Implementation Document (TRMID)
Page 1 of 10 TRANS Standard Validation Date 03-10-2017 Review Frequency 1 year Validated By Marshalia Green Effective Date 03/31/2017 Level of Use: Responsible Execu. Approved by: Page 2 of 10 Revision
More informationBackground Information:
Project 2010-14.1 Balancing Authority Reliability-based Control BAL-002-2 Disturbance Control Performance - Contingency Reserve for Recovery from a Balancing Contingency Event Please do not use this form
More informationPOWER SYSTEM NOT IN A SECURE OPERATING STATE IN VICTORIA ON 15 JUNE 2016 REVIEWABLE OPERATING INCIDENT REPORT UNDER THE NATIONAL ELECTRICITY RULES
POWER SYSTEM NOT IN A SECURE OPERATING STATE IN VICTORIA ON 15 JUNE 2016 REVIEWABLE OPERATING INCIDENT REPORT UNDER THE NATIONAL ELECTRICITY RULES Published: November 2016 INCIDENT CLASSIFICATIONS Classification
More informationWECC Process for Risk-Based Compliance Oversight Inherent Risk Assessment and Compliance Oversight Plan
WECC Process for Risk-Based Compliance Oversight Inherent Risk Assessment and Compliance Oversight Plan WECC Entity Oversight Effective Date: April 1, 2017 155 North 400 West, Suite 200 Salt Lake City,
More informationYear Assessment Preliminary Study Design
2015 10-Year Assessment Preliminary Study Design October 15, 2014 Stakeholder and Customer Webcast atcllc.com Purpose Solicit pre-study Comments 2015 Assessment Process 2015 Assessment Assumptions Public
More informationTransmission Loss Factor Methodology
Transmission Loss Factor Methodology Discussion Paper Operations & Reliability Draft February 9, 2005 Table of Contents 1. Introduction...3 1.1 Legislative Direction.....3 1.2 Goal and Objectives... 3
More informationTUCSON ELECTRIC POWER COMPANY. Transmission Reliability Margin Implementation Document (TRMID)
A UniSource Energy Company TUCSON ELECTRIC POWER COMPANY Transmission Reliability Margin Implementation Document (TRMID) Approved by: Effective Date: /c Version 1 Based on North American Electric Reliability
More informationNPCC Regional Reliability Reference Directory # 5 Reserve
NPCC Regional Reliability Reference Directory # 5 Task Force on Coordination of Operations Revision Review Record: December 2 nd, 2010 October 11 th, 2012 Adopted by the Members of the Northeast Power
More informationSPP New Member Communication and Integration Process. Mountain West Transmission Group. Background Information October 2017
1 SPP New Member Communication and Integration Process Mountain West Transmission Group Background Information October 2017 Contents Introduction... 2 1. Westside Tariff Design... 2 2. Operational Provisions...
More informationRegulatory Status Report
FERC or State Jurisdiction: FERC EL13-88 EL16-91 Northern Indiana Public Service Company's ("NIPSCO") Complaint Against the Midcontinent Independent System Operator, Inc. ("MISO") and PJM Interconnection,
More informationSouthwest Power Pool s Balanced Portfolio Approach for Economic Upgrades
Southwest Power Pool s Balanced Portfolio Approach for Economic Upgrades Presentation by Michael Proctor Chief Economist, Missouri PSC Harvard Electricity Policy Group Chicago, Illinois October 2, 2008
More informationProcedure for ERO Support of Frequency Response and Frequency Bias Setting Standard
Procedure for ERO Support of Frequency Response and Frequency Bias Setting Standard NERC Report Title Report Date I Table of Contents Preface... iii Introduction...iiv Chapter 1: Event Selection Process...
More informationNew Member Cost Allocation Review Process. Prepared by: COST ALLOCATION WORKING GROUP
New Member Cost Allocation Review Process Prepared by: COST ALLOCATION WORKING GROUP TABLE OF CONTENTS 1. HISTORY AND BACKGROUND... 1 2. PURPOSE / GOAL STATEMENT... 3 3. OVERVIEW OF PROCESS... 3 4. NEW
More informationWestern Area Power Administration-Rocky Mountain Region
Western Area Power Administration-Rocky Mountain Region Revision Date CURRENT BUSINESS PRACTICES Effective Date: October 1, 2017 Business Practices Revision Table (Changes to the business rules for this
More informationStandard Development Timeline
Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft
More informationT-D Interconnections: Best Value Planning White Paper January 2016
T-D Interconnections: Best Value Planning White Paper Updated January 2016 1. Purpose This paper defines the process and criteria that together constitute joint best value planning (BVP) between ATC and
More informationREPORT TO THE PUBLIC UTILITIES BOARD
REPORT TO THE PUBLIC UTILITIES BOARD CURTAILABLE RATE PROGRAM APRIL 1, 2011 MARCH 31, 2012 JULY 2012 TABLE OF CONTENTS Page No. SUMMARY... 1 BACKGROUND... 1 PERFORMANCE FOR 2011/12... 3 Curtailment Options...3
More informationApril 24, 2015 VIA ELECTRONIC FILING
April 24, 2015 VIA ELECTRONIC FILING The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: Southwest Power Pool, Inc., Docket No.
More informationEIPC Roll-Up Report & Scenarios
EIPC Roll-Up Report & Scenarios Zach Smith Director, Transmission Planning New York Independent System Operator IPTF/EGCWG/ESPWG Meeting January 6, 2014 2013 New York Independent System Operator, Inc.
More informationFive-Minute Settlements Education
Five-Minute Settlements Education Disclaimer PJM has made all efforts possible to accurately document all information in this presentation. The information seen here does not supersede the PJM Operating
More informationWASN Operations Business Procedure OASIS COVER PAGE
No. COVER PAGE This page will be removed when final document is posted Western Area Power Administration Sierra Nevada Region () Business Practice/ covering Sierra Nevada Regional procedures is being updated.
More informationWECC Criterion TPL-001-WECC-CRT-3.1
WECC Criterion TPL-001-WECC-CRT-3.1 A. Introduction 1. Title: Transmission System Planning Performance 2. Number: TPL-001-WECC-CRT-3.1 3. Purpose: To facilitate coordinated near-term and long-term transmission
More informationNERC TPL Standard Overview
NERC TPL-001-4 Standard Overview Attachment K Quarter 3 Stakeholder s Meeting September 29, 2016 1 Background New NERC TPL Standard 2016 TPL Plan and Status Update 2015 Planning Assessment Results Compliance
More informationFTR Credit Requirements Prevailing Flow Paths Affected by Transmission System Upgrades
FTR Credit Requirements Prevailing Flow Paths Affected by Transmission System Upgrades Hal Loomis Manager, Credit Markets & Reliability Committee December 7, 2017 Credit Risk Exposure Issue Description
More informationTerms, Conditions and Methodologies on Cross-Zonal Capacity Calculation, Provision and Allocation within the Baltic States and with the 3 rd Countries
Terms, Conditions and Methodologies on Cross-Zonal Capacity Calculation, Provision and Allocation within the Baltic States and with the 3 rd Countries Among: AS Augstsprieguma tīkls Elering AS LITGRID
More informationPROPOSAL FOR COST ESTIMATION REVIEW PROCESS FOR SPP TRANSMISSION
PROPOSAL FOR COST ESTIMATION REVIEW PROCESS FOR SPP REGIONALLY FUNDED TRANSMISSION Presented on behalf of SPP s Transmission Owners SPP Strategic Planning Committee Meeting December 3, 2010 REGIONALLY
More informationRSC Workshop on the Integration of WAPA, Basin, Heartland. April 4, 2014
RSC Workshop on the Integration of WAPA, Basin, Heartland April 4, 2014 AGENDA I. Impact of IS Joining SPP II. Cost Allocation III. Potential Clarification to RSC Bylaws IV. SPP Bylaw and Membership Agreement
More informationReducing Contingency-based Windfarm Curtailments through use of Transmission Capacity Forecasting
Reducing Contingency-based Windfarm Curtailments through use of Transmission Capacity Forecasting Doug Bowman Southwest Power Pool Jack McCall Lindsey Manufacturing Co. Minnesota Power Systems Conference
More informationAlberta Utilities Commission
Alberta Utilities Commission In the Matter of the Need for the Grizzly Bear Creek Wind Power Plant Connection And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities
More informationCONTROL AREA SERVICES AND OPERATIONS TARIFF OTTER TAIL POWER COMPANY
Otter Tail Power Company Original Sheet No. 1 CONTROL AREA SERVICES AND OPERATIONS TARIFF OTTER TAIL POWER COMPANY Otter Tail Power Company Substitute Original Sheet No. 2 Superseding Original Volume No.
More informationContingency Reserve Cost Allocation. Draft Final Proposal
Contingency Reserve Cost Allocation Draft Final Proposal May 27, 2014 Contingency Reserve Cost Allocation Draft Final Proposal Table of Contents 1 Introduction... 3 2 Changes to Straw Proposal... 3 3 Plan
More informationLong Term Access Goal Final Report Update
Long Term Access Goal 2007-09 Final Report 2008-10 Update SME Version of Presentation for ATC Board of Directors Meeting December 14, 2009 2007-09 and 2008-10 Long Term Goals Access (10%) Reduce congestion
More information1st Qua u r a ter e M e M e e t e in i g 2nd Qua u r a ter e M e M e e t e in i g
2012 SERTP Welcome SERTP 2012 First RPSG Meeting & Interactive Training Session 1 2012 SERTP The SERTP process is a transmission planning process. Please contact the respective transmission provider for
More informationMISO PJM IPSAC. December 2, Revised December 22, PJM IPSAC Meeting, December 2,
MISO PJM IPSAC December 2, 2016 Revised December 22, 2016 1 Agenda 2 TMEP Final JOA Language Recommended TMEPs Order No. 1000 Compliance Filing Generation Deactivation JOA Language PJM Proposal Window
More informationProcedure for ERO Support of Frequency Response and Frequency Bias Setting Standard
Procedure for ERO Support of Frequency Response and Frequency Bias Setting Standard I Table of Contents Preface... iii Introduction...iiv Chapter 1: Event Selection Process... 1 Event Selection Objectives...
More informationITP Evaluation Process Plan
ITP Evaluation Process Plan HVDC Conversion Project The goal of the coordinated Interregional Transmission Project (ITP) evaluation process is to achieve consistent planning assumptions and technical data
More informationTransmission Formula Rate Annual Customer Meeting. June 2017
American Electric Power Transmission Formula Rate Annual Customer Meeting Public Service Company of Oklahoma Southwestern Electric Power Company June 2017 2017 Annual Update Internet Posting http://www.aep.com/about/codeofco
More informationEXCERPTS from the SAMS-SPCS SPS Technical Reference
Problem Statement The existing NERC Glossary of Terms definition for a Special Protection System (SPS or, as used in the Western Interconnection, a Remedial Action Scheme or RAS) lacks clarity and specificity
More informationNevada Power & Sierra Pacific Power d/b/a NV Energy Stakeholders Planning Input Meeting July
Nevada Power & Sierra Pacific Power d/b/a NV Energy Stakeholders Planning Input Meeting July 2012 1 1. Welcome Introductions 2. IRP filing and results Update on Loads and Resources Renewable Transmission
More informationBC HYDRO REAL TIME OPERATIONS OPERATING ORDER 1T 61
BC HYDRO REAL TIME OPERATIONS OPERATING ORDER 1T 61 BC HYDRO OPERATING RESERVE AND NWPP RESERVE SHARING PROCEDURES Supersedes 1T-61 issued 26 September 2011 Review Year: 2018 Original signed by Brett Hallborg
More informationEffective for SERC Region applicable Registered Entities on the first day of the first calendar quarter after approved by FERC.
Effective Date Effective for SERC Region applicable Registered Entities on the first day of the first calendar quarter after approved by FERC. Introduction 1. Title: Automatic Underfrequency Load Shedding
More informationIntegrated Marketplace Member-Facing Reports Inventory
Integrated Marketplace Member-Facing s Inventory July 3, 2012 Revision History Date or Version Number Author Change Description Comments 7/3/2012, version 1.0 Annette Holbert Initial Draft Compilation
More informationPUC DOCKET NO. PUBLIC UTILITY COMMISSION OF TEXAS APPLICATION OF SOUTHWESTERN ELECTRIC POWER COMPANY
PUBLIC UTILITY COMMISSION OF TEXAS APPLICATION OF SOUTHWESTERN ELECTRIC POWER COMPANY FOR CERTIFICATE OF CONVENIENCE AND NECESSITY AUTHORIZATION AND RELATED RELIEF FOR THE WIND CATCHER ENERGY CONNECTION
More informationTRIP OF MULTIPLE TRANSMISSION ELEMENTS IN THE SOUTHERN NSW AREA, 11 FEBRUARY 2017
TRIP OF MULTIPLE TRANSMISSION ELEMENTS IN THE SOUTHERN NSW AREA, 11 FEBRUARY 2017 REVIEWABLE OPERATING INCIDENT REPORT UNDER THE NATIONAL ELECTRICITY RULES Published: 15 September 2017 INCIDENT CLASSIFICATIONS
More informationSignificant negative consequences of the proposed standard include but are not limited to: 1) The proposed language moves this project from being a
or group. (28 Responses) Name (13 Responses) Organization (13 Responses) Name (15 Responses) Lead Contact (15 Responses) Contact Organization (15 Responses) Question 1 (28 Responses) Northeast Power Coordinating
More informationStandard Market Design: FERC Process and Issues
Standard Market Design: FERC Process and Issues Richard O Neill and Udi Helman Division of the Chief Economic Advisor, Office of Markets, Tariffs and Rates Federal Energy Regulatory Commission IEEE PES
More informationBEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION ) ) ) ) ) ) ) ) ) ) ) DIRECT TESTIMONY WILLIAM A. GRANT. on behalf of
BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION IN THE MATTER OF SOUTHWESTERN PUBLIC SERVICE COMPANY S APPLICATION FOR REVISION OF ITS RETAIL RATES UNDER ADVICE NOTICE NO., SOUTHWESTERN PUBLIC SERVICE
More informationBoard of Public Utilities Prepared Testimony of Lori Austin September, 2010
Board of Public Utilities Prepared Testimony of Lori Austin September, 2010 Q: Please state your name and your business address. A: My name is Lori Austin, 540 Minnesota Avenue, Kansas City, KS 66101.
More informationTRIP OF VALES POINT 330 KV MAIN BUSBAR ON 27 JULY 2017 REVIEWABLE OPERATING INCIDENT REPORT UNDER THE NATIONAL ELECTRICITY RULES
TRIP OF VALES POINT 330 KV MAIN BUSBAR ON 27 JULY 2017 REVIEWABLE OPERATING INCIDENT REPORT UNDER THE NATIONAL ELECTRICITY RULES Published: 26 September 2017 INCIDENT CLASSIFICATIONS Classification Detail
More informationFIRST QUARTERLY PROJECT TRACKING REPORT 2018 January 2018
FIRST QUARTERLY PROJECT TRACKING REPORT 2018 January 2018 CONTENTS Executive Summary... 3 NTC Project Summary... 5 NTC Issuance... 7 NTC Withdraw... 7 Completed Projects... 8 Project status summary...
More informationBEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION ) ) ) ) ) ) ) ) ) ) ) DIRECT TESTIMONY RUTH M. SAKYA. on behalf of.
BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION IN THE MATTER OF SOUTHWESTERN PUBLIC SERVICE COMPANY S INTERIM REPORT ON ITS PARTICIPATION IN THE SOUTHWEST POWER POOL REGIONAL TRANSMISSION ORGANIZATION,
More informationAC TRANSMISSION PUBLIC POLICY TRANSMISSION NEEDS PROJECT SOLICITATION Response due April 29, 2016
10 Krey Boulevard Rensselaer, NY 12144 AC TRANSMISSION PUBLIC POLICY TRANSMISSION NEEDS PROJECT SOLICITATION Response due April 29, 2016 Dear NYISO Stakeholder or Interested Party: February 29, 2016 With
More information2011 IRP Public Input Meeting. October 5, Pacific Power Rocky Mountain Power PacifiCorp Energy
2011 IRP Public Input Meeting October 5, 2010 Pacific Power Rocky Mountain Power PacifiCorp Energy Agenda Morning Session IRP Schedule Update Energy Gateway Transmission Construction Update and Evaluation
More informationAEPTCo - SPP Formula Rate Projected NITS Rates Page: 1 of 69
AEPTCo SPP Formula Rate Projected NITS Rates Page: 1 of 69 AEP Transmission Formula Rate Template Utilizing FERC Form 1 Data.. For rates effective July 1, 2015 SPP Zone 1 Projected AEP Revenue Requirements
More informationWhirlwind AA-Bank RAS Modifications
Whirlwind AA-Bank RAS Modifications Edison Team Members: Adrian Franco Electric System Planning Bill Zhang - Protection Engineering Obinna Obah - Power System Controls Hans Bakker - Communications Presentation
More informationAEPTCo - SPP Formula Rate Projected NITS Rates Page: 1 of 69
Projected NITS Rates Page: 1 of 69 AEP Transmission Formula Rate Template Utilizing FERC Form 1 Data For rates effective July 1, 2016 SPP Zone 1 Projected AEP Revenue Requirements OKTCo Annual SWTCo Annual
More informationPRC Remedial Action Schemes
PRC-012-2 Remedial Action Schemes A. Introduction 1. Title: Remedial Action Schemes 2. Number: PRC-012-2 3. Purpose: To ensure that Remedial Action Schemes (RAS) do not introduce unintentional or unacceptable
More informationOperations Manager Responsible for the TRMID for the WAPA-RMR Transmission Operator (TOP) function.
1.0 PURPOSE This document serves to promote the consistent and reliable calculation, verification, preservation, and use of Transmission Reliability Margin (TRM) to support analysis and system operations.
More informationStandard INT Interchange Initiation and Modification for Reliability
A. Introduction 1. Title: Interchange Initiation and Modification for Reliability 2. Number: INT-010-2 3. Purpose: To provide guidance for required actions on Confirmed Interchange or Implemented Interchange
More informationGATE 3 FREQUENTLY ASKED QUESTIONS
GATE 3 FREQUENTLY ASKED QUESTIONS Latest Update May 2013 SECTION 2 - GATE 3 CONSTRAINT ANALYSIS, CONSTRAINT REPORTS, CONSTRAINTS AND CURTAILMENT 1. What are constraints and curtailment? 2. What is the
More informationBC HYDRO REAL TIME OPERATIONS OPERATING ORDER 7T 18. BC - US INTERCONNECTION Supersedes 7T-18 issued 15 December 2015
BC HYDRO REAL TIME OPERATIONS OPERATING ORDER 7T 18 BC - US INTERCONNECTION Supersedes 7T-18 issued 15 December 2015 Review Year: 2019 APPROVED BY: Original signed by: Paul Choudhury General Manager, Real
More informationAPPENDIX B: WHOLESALE AND RETAIL PRICE FORECAST
Seventh Northwest Conservation and Electric Power Plan APPENDIX B: WHOLESALE AND RETAIL PRICE FORECAST Contents Introduction... 3 Key Findings... 3 Background... 5 Methodology... 7 Inputs and Assumptions...
More information