1 Detailed Project Budget *Packet must include Attachment A and Attachment B* Kit Carson School District R1 2/23/2018 Total Project Cost: 32,135, Division of Public School Capital Construction Assistance Colorado Department of Education 1580 Logan St., #310 Denver, CO 80203

2 Design/ Consulting Fees City and Planning Fees Sub Architectural/ Design Fees Architectural 1,955, % of estimated construction cost of 23 million Structural Mechanical Electrical Landscape Design Code and Accessibility Review Interiors Printing/ Reimbursables/ Mileage 40, D Modeling/ Computer Animation/ Model Acoustical Design Lighting Design Food Service Design Health Dept. Review 2, Historical Reviews Civil Engineering Drainage Study Zoning PUD Special Use Permit Costs Colorado Geological Survey Transportation Improvement Plan Traffic Study/Parking High Performance Energy Modeling 25, High Performance Commissioning (CxA) 200, LEED/CHPS Design & Coordination 15, LEED/CHPS Certification 10, Project Management/ Owners Representative 345, % of estimated construction cost of 23 million Design Fees Subtotal 2,592, Preliminary Development Plan (PDP) Official Development Plan (ODP) Amendment to PDP of ODP Rezoning Fee (if applicable) Public RightofWay Easement Vacation Park Development Fees Street Excavation Permit enter in any clarifying statements here CDE CCA Detailed Project Budget Attachment A "Project Soft Costs" Page 1 of 6

3 Submittal Fees Sub City Planning Fees Subtotal enter in any clarifying statements here Utility and Development Costs Site Survey and Soils Report Water Tap and Development Review Assessments Well Permits (water) Fire Protection Water Tap Fire Hydrants Water Reserve for Fire Protection Water Tap Fees 20, Existing Water Tap Credits Special Metro Districts Sanitary Sewer Review and Assessment Septic System/ Leach Fields Metro District County (as applicable) City 5, State (as applicable) Storm Sewer Utility Services Utility Extensions 25, Gas 25, Fuel Storage/ Propane/ Wood? Electric 50, Phase Power Phone Cabling Cable Television Cabling City Traffic Impact Fee City Development Excise Tax Metro District Fees Street Lighting Fees *Not to be included in grant application Traffic Control Devices *Not to be included in grant application Extraordinary Offsite Utility Costs Utility & Development Costs Subtotal 125, Site Survey 15, CDE CCA Detailed Project Budget Attachment A "Project Soft Costs" Page 2 of 6

4 Material Testing/ 3rd Party Inspections Environmental Sub Geo Technical Report 15, Site Survey and Soils Report Subtotal 30, Caisson Inspection Soils Compaction 35, Rebar Inspection 20, Concrete Testing 20, Steel Welds & Bolted Connections 25, Asphalt Testing 20, Spray Fireproofing Material Testing Subtotal 120, ACM Abatement 150, Block Filler Underground Tanks/Contaminated Soils Lead CFCs Storm Water Management State Demolition Permit State Fugitive Dust Permit Animal Removal/Relocation Endangered Species Act Environmental/Hazmat/Testing Subtotal 150, enter in any clarifying statements here *Included but not limited to the noted below. Additional Costs * The owner is tax exempt Builder's Risk Insurance (If by owner) Leasing Fees Rental costs during construction Legal Fees 10, Finance Costs Moving & Relocating Costs 30, Land Purchase Site Development Colo. Dept. of Transportation Costs CDE CCA Detailed Project Budget Attachment A "Project Soft Costs" Page 3 of 6

5 Building Systems Infrastructure (by owner) Sub Easement Dedications Construction Loan Interest Additional Costs Subtotal 40, Sound System/Audiovisual/TVDVD Included with Hard Costs Telecommunications Included with Hard Costs Phone Systems Cabling Included with Hard Costs Data Systems Cabling Included with Hard Costs Equipment 35, Telephone system Security Systems Included with Hard Costs Fire Alarm System Included with Hard Costs Building Systems Subtotal 35, enter in any clarifying statements here Furniture/ Fixtures and Equipment *Items may or may not be included with the grant application, to be reviewed. Window Coverings Included with Hard Costs Parking Lot Signage Included with Hard Costs Permanent Interior Signage Included with Hard Costs Interior Plaque Included with Hard Costs Permanent Exterior Signage Included with Hard Costs Monument Signage Included with Hard Costs Technology Computers/Laptops/Tablets 125, Projection Equipment 20, Smart boards, LED Touch Screens, Etc. 50, School Desks/ Tables/ Chairs 320, Cafeteria Chairs and Tables 40, Office Furniture 50, Office Equipment Display Cases Included with Hard Costs Marker & Tack Boards Included with Hard Costs Foodservice Equipment Included with Hard Costs Indoor Sports Equipment Included with Hard Costs Bleachers Included with Hard Costs Scoreboards Included with Hard Costs CDE CCA Detailed Project Budget Attachment A "Project Soft Costs" Page 4 of 6

6 Site Furnishings Sub Site Furniture 15, Outdoor Sports Equipment Included with Hard Costs Playground Equipment Included with Hard Costs Project Furniture/ Fixtures and Equipment Subtotal 620, SOFT COST TOTAL 3,712,500 enter in any clarifying statements here Permits, Taxes, Bonds Building Construction Cost Direct Cost of Work by Division HARD COST *Public School Facilities are tax exempt Building, Mechanical, Plumbing, Electrical Permit Fees Included with Hard Costs Plan Review Fee (State) 15, Fire Department Review Fee 5, State Inspections by 3rd Party Storm Water Permit Fees Land Disturbance Fee Permits, Taxes, Bonds Subtotal 20, Cost per SF Division 1 General Requirements , Division 2 Sitework ,191, Division 3 Concrete , Division 4 Masonry , Division 5 Metals ,698, Division 6 Woods & Plastics , Division 7 Thermal / Moisture Protection ,244, Division 8 Doors & Windows ,061, Division 9 Finishes ,211, Division 10 Specialties , Division 11 Equipment , Division 12 Furnishings , Division 13 Special Construction , Division 14 Conveying Systems CDE CCA Detailed Project Budget Attachment A "Project Soft Costs" Page 5 of 6 Totals

7 Sub Division 15 Mechanical ,448, Division 16 Electrical ,689, Single Scope Lump Sum Bid (use if no divisions provided) Subtotal for Direct Cost of Work ,001, Contingencies in Escalation 8.00% 1,840,160 Hard Costs Construction Contingency 4.00% 920,080 Subtotal for Direct and Indirect Cost of Work ,762, General Liability Insurance 1.00% 257, Fees, Insurance, Builder's Risk Insurance 0.50% 128, and Bonds Fees for Overhead and Profit 3.00% 772, Performance and Payment Bonds 0.50% 128, Total Construction Hard Costs ,050, Owner's Contingency on Construction 5.00% 1,352, Building Construction Costs Subtotal 28,402, Other Costs Not Listed Above Please list: 1) 2) 3) 4) 5) 6) 7) Excluded Items Subtotal HARD COST TOTAL 28,422, enter in any clarifying statements here PROJECT SUMMARY Cost Totals Cost Per Sq. Ft. Soft Cost Total Hard Cost Total 3,712, ,422, TOTAL PROJECT COST 32,135, CDE CCA Detailed Project Budget Attachment A "Project Soft Costs" Page 6 of 6

City of Los Altos. Civic Center Master Plan Council Meeting. March 24, 2015

City of Los Altos. Civic Center Master Plan Council Meeting. March 24, 2015 City of Los Altos Civic Center Master Plan Council Meeting March 24, 2015 Agenda Context, Purpose, Intended Results Final Site Design Concept Cost Model & Budget Data Review Council Input Needed Context

More information

Educational & Performing Arts Center: Downriver Campus

Educational & Performing Arts Center: Downriver Campus Educational & Performing Arts Center: Total Estimated Project Construction Cost: $ 18.04 million Groundbreaking: September 2006 Percentage Completed: 100 percent Anticipated Completion Date: Completed

More information

CAPITAL PROJECT PROCESS

CAPITAL PROJECT PROCESS CAPITAL PROJECT PROCESS May 2009 GETTING STARTED What is a project? A project is defined as all work (maintenance & repair or renovation) that requires 5,000 or more in time and materials and/or is sufficiently

More information

Letter of Instructions

Letter of Instructions Letter of Instructions Trade Contractor Prequalification Statement Please complete the following and return at your earliest convenience by email to prequal@chanen.com. 1. Trade Contractor Prequalification

More information

INVENTRUST PROPERTIES VENDOR TRADE CODES INSURANCE REQUIREMENTS

INVENTRUST PROPERTIES VENDOR TRADE CODES INSURANCE REQUIREMENTS To determine the levels of insurance coverage that will be required, consult your Service Agreement, or note by the description below Please contact the Risk Department if you have any questions reguarding

More information

Contents. Ballot Measure Full Text Ballot Proposition Tax Rate Statement Impartial Analysis Statement in Favor of Measure...

Contents. Ballot Measure Full Text Ballot Proposition Tax Rate Statement Impartial Analysis Statement in Favor of Measure... Contents Ballot Measure... 2 Full Text Ballot Proposition... 3 Tax Rate Statement... 6 Impartial Analysis... 7 Statement in Favor of Measure... 8 Ballot Measure EXHIBIT A HANFORD ELEMENTARY SCHOOLS REPAIR

More information

1. CALL TO ORDER AND RECOGNITION OF A QUORUM

1. CALL TO ORDER AND RECOGNITION OF A QUORUM Mesa Union School District Agenda for the Special Board Meeting of the Board of Trustees to be held on Thursday, May 3, 2018, at 6:00 p.m. in the School Multi-Purpose Room located at 3901 North Mesa School

More information

VENDOR PREQUALIFICATION FORM

VENDOR PREQUALIFICATION FORM VENDOR PREQUALIFICATION FORM Date: Please complete this form and return to Rockford Construction via e mail (prequal@rockfordconstruction.com) or fax (1 616 285 8423 must include the 1 616). Name of Company

More information

Solicitation/Proposal/Award (Construction) PROPOSAL

Solicitation/Proposal/Award (Construction) PROPOSAL SOLICITATION: PL-K-REC-09-001-17-011, Amendment #03. Solicitation/Proposal/Award (Construction) PROPOSAL Offerors shall enter in the space below a Total Lump Sum Cost Proposal. A. Total Lump Sum Cost Proposal:

More information

Backlog Reduction Plan

Backlog Reduction Plan 2003-2013 Executive Summary proposes to achieve reductions in our facilities maintenance backlog by documenting and completing backlog projects on a priority basis and by minimizing or eliminating future

More information

APPENDIX A FULL TEXT OF BOND MEASURE

APPENDIX A FULL TEXT OF BOND MEASURE APPENDIX A FULL TEXT OF BOND MEASURE INTRODUCTION To repair aging classrooms / leaky roofs / old facilities, and provide a safe, quality learning environment for current and future students, shall Grass

More information

The Beverly Middle School Flexible Learning Academy

The Beverly Middle School Flexible Learning Academy Transformative Learning Through Architecture The Beverly Middle School Flexible Learning Academy Flexible Classroom Studios FLEXIBLE ACADEMY Flexible Configurations Flexible Support Exhibits Cross Discipline

More information

REQUEST FOR PROPOSALS. Construction Related Services Retainer Contract

REQUEST FOR PROPOSALS. Construction Related Services Retainer Contract REQUEST FOR PROPOSALS Construction Related Services Retainer Contract ISSUE DATE: July 3, 2014 CLOSING DATE: August 31, 2016 CLOSING TIME: 5:00 PM Pacific Time {00312821;1} TABLE OF CONTENTS Page Section

More information

PROJECT TIMELINE *

PROJECT TIMELINE * NAME OF HERITAGE PLACE: PREPARED BY: DURATION OF PROJECT: START DATE (ENTIRE PROJECT): DDMMYYYY END DATE (ENTIRE PROJECT) : DDMMYYYY PROJECT TIMELINE 20162017* Please provide your project timeline, including

More information

TOWN OF WOODWAY FEE SCHEDULE PAGE 1 EFFECTIVE APRIL 18, 2017

TOWN OF WOODWAY FEE SCHEDULE PAGE 1 EFFECTIVE APRIL 18, 2017 TOWN OF WOODWAY FEE SCHEDULE EFFECTIVE APRIL 18, 2017 A. BUILDING/PERMIT FEES FEE 1-A. Building Permit Fee, Based on Total Total Value Fee Valuation (includes swimming pools $1 to $2,000 $85 game courts,

More information

Job Status Report w/hours 09/24/08

Job Status Report w/hours 09/24/08 Cost-To-Complete Job# = 186 Sample Company 2005 Job Status Report w/hours 186 Williams Post Office 1 General Requirements 1000.000 Budget 926 69,942 69,942 57 % 50 % 39,565 9,187 GENERAL REQUIREMENTS Cost

More information

Provide a lump sum cost for Pre-Construction Services as described in the RFP Scope of Work and the associated AIA agreement documents:

Provide a lump sum cost for Pre-Construction Services as described in the RFP Scope of Work and the associated AIA agreement documents: Proposal Pricing Form for Construction Management (CM) Services for the Waterbury Municipal Complex Waterbury, Vermont. To William A. Shepeluk, Town Manager The Town of Waterbury, Vermont 51 South Main

More information

City of Brea COUNCIL COMMUNICATION

City of Brea COUNCIL COMMUNICATION City of Brea COUNCIL COMMUNICATION Agenda Item. TO: FROM: Honorable Mayor and City Council Members City Manager DATE: 06/16/2015 SUBJECT: CONSIDERATION OF BREA DOWNTOWN SUPERBLOCK PARKING STRUCTURE RECOMMENDATION

More information

Release Date: January 3, 2019 Due Date: January 17, 2019

Release Date: January 3, 2019 Due Date: January 17, 2019 SAN JUAN SCHOOL DISTRICT REQUEST FOR BID CONSTRUCTION OF NEW BLUFF ELEMENTARY SCHOOL AND NEW MONTEZUMA CREEK ELEMENTARY GYM Release Date: January 3, 2019 Due Date: January 17, 2019 I. GENERAL A. Intent

More information

GENERAL ADMINISTRATION AND CORPORATE SERVICES (Administration/Corporate/Finance Departments)

GENERAL ADMINISTRATION AND CORPORATE SERVICES (Administration/Corporate/Finance Departments) This document is provided as a comparison document for reference only. The years noted are based on the assumption that changes were considered for most or all sections of a respective bylaw, although

More information

Self-Help Public Charter School Loan Application

Self-Help Public Charter School Loan Application Self-Help Public Charter School Loan Application Thank you for your interest in Self-Help. We have been a charter school lender since 1997 and look forward to using our experience to serve your school.

More information

CITY-TIF COMMISSION EXPENSES Cost Description Project Cost Data Reimbursable From Public Funds Developer Equity COST TIF Super TIF State TIF CID SCTC PRIVATE I. Legal $ 750,000 $ 750,000 $ - $ - $ - $

More information

EXHIBIT A CITY OF OLDSMAR PERMIT, INSPECTION AND PLANS EXAMINATION FEE SCHEDULE

EXHIBIT A CITY OF OLDSMAR PERMIT, INSPECTION AND PLANS EXAMINATION FEE SCHEDULE 1. Building Permit EXHIBIT A CITY OF OLDSMAR PERMIT, INSPECTION AND PLANS EXAMINATION FEE SCHEDULE a. This fee schedule is applicable to all building permits issued by the City of Oldsmar, Building Division

More information

Sisseton-Wahpeton Oyate Community Justice and Rehabilitation Center

Sisseton-Wahpeton Oyate Community Justice and Rehabilitation Center December 13, 2016 (Final Draft) December 13, 2016 (Final Draft) Prepared by: EKM&P, Inc. John T. Milosovich jtmilo@ekmp.com Office: (303)926-8375 Cell: (303) 549-1562 Copyright 2016 These have been developed

More information

TOWN OF BERTHOUD SCHEDULE OF RATES, CHARGES AND FEES 2018

TOWN OF BERTHOUD SCHEDULE OF RATES, CHARGES AND FEES 2018 PLANNING & BUILDING DEPARTMENTS BUILDING PERMIT FEES PERMIT FEE PLAN REVIEW FEE Residential Construction 50% of Permit Fee + Electrical Non Residential Construction 65% of Permit Fee + Electrical Accessory

More information

City of New Smyrna Beach Permit Fee Schedule

City of New Smyrna Beach Permit Fee Schedule Fifty percent of the permit fee will be paid in advance for plan review and shall not be eligible for refund. ALL PERMITS ARE CHARGED A STATE OF FLORIDA SURCHARGE OF 2.5% OR $4.00 WHICH EVER IS GREATER.

More information

Ballot Measures-T Section

Ballot Measures-T Section T, Westminster School District Classroom Improvement Measure To upgrade aging schools and improve the quality of education with funding that cannot be taken by the State; provide heating, ventilation and

More information

PROJECT BUDGET PRESENTATION

PROJECT BUDGET PRESENTATION PROJECT BUDGET PRESENTATION Monomoy Regional High School Building Committee Meeting June 19, 2012 Project Features Serves 700 Students Grades 8-12 8 th Grade Wing located near main entrance 168,000 GSF

More information

NOTICE TO TAXPAYERS. The Notice to Taxpayers is available online at or by calling (888)

NOTICE TO TAXPAYERS. The Notice to Taxpayers is available online at   or by calling (888) Prescribed by the Department of Local Government Finance Approved by the State Board of Accounts NOTICE TO TAXPAYERS Budget Form No. 3 (Rev. 2018) Print 8/9/2018 12:12:13 PM The Notice to Taxpayers is

More information

INSPECTION SERVICES DIVISION FEE SCHEDULE

INSPECTION SERVICES DIVISION FEE SCHEDULE BUILDING INSPECTION SERVICES DIVISION FEE SCHEDULE Effective January 1, 2017 ** To calculate fees for building projects use the higher of the fees by valuation or square footage ** New Buildings, Additions

More information

Status: Structural steel installation complete at primary building. Observatory construction underway. Central Plant modifications are complete.

Status: Structural steel installation complete at primary building. Observatory construction underway. Central Plant modifications are complete. Page 1 of 11 FACILITIES PLAN STATUS REPORT June 22, 2015 SADDLEBACK COLLEGE 1. SCIENCES BUILDING Project Budget: $52,234,000 $8,308,000 $67,358,000 State Match: $36,564,000 ($36,564,000) - Basic Aid Allocation:

More information

FACILITIES PLAN STATUS REPORT July 21, 2014 SADDLEBACK COLLEGE 1. SCIENCES BUILDING

FACILITIES PLAN STATUS REPORT July 21, 2014 SADDLEBACK COLLEGE 1. SCIENCES BUILDING Page 1 of 11 FACILITIES PLAN STATUS REPORT July 21, 2014 SADDLEBACK COLLEGE 1. SCIENCES BUILDING Project Budget: $52,234,000 $8,308,000 $67,358,000 State Match: $36,564,000 ($36,564,000) - Basic Aid Allocation:

More information

Town of Middleton Salt Storage Building Pioneer Road Pioneer Lands Town of Middleton Dane County, WI 53562

Town of Middleton Salt Storage Building Pioneer Road Pioneer Lands Town of Middleton Dane County, WI 53562 Town of Middleton Salt Storage Building Pioneer Road Pioneer Lands Town of Middleton Dane County, WI 53562 1 T100 PROJECT LOCATION MAP Scale: NTS N Revisions: No. Date: Description: Scale As Indicated

More information

City and County of Denver. Construction Contractors Tax Seminar

City and County of Denver. Construction Contractors Tax Seminar City and County of Denver Construction Contractors Tax Seminar Construction Contractors Resources Denver Revised Municipal Code (DRMC) Treasury Tax Rule # 5 Rules Regarding The Assessment and Collection

More information

Anson County Early College High

Anson County Early College High NC School District/040 Anson County/High School Anson County Early College High Final Campus Assessment Report March 11, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary

More information

Code Reference: Section , F.S. Chapter ; FS Section ; Responsible Dept.: Community Development/Building Division

Code Reference: Section , F.S. Chapter ; FS Section ; Responsible Dept.: Community Development/Building Division Building Construction Permit Fees 322100 Building Division 341910 Planning Division 341940 Harbor/Code Division 322200/322300 Surcharge Building Permit Fees The governing bodies of local governments may

More information

NEWTON PARISH REPLACEMENT RESERVE REPORT 2008 REPLACEMENT RESERVE REPORT FY CAS, Inc MILLER ~ DODSON ASSOCIATES. Community Management by:

NEWTON PARISH REPLACEMENT RESERVE REPORT 2008 REPLACEMENT RESERVE REPORT FY CAS, Inc MILLER ~ DODSON ASSOCIATES. Community Management by: REPLACEMENT RESERVE REPORT 2008 NEWTON PARISH NEWTON PARISH REPLACEMENT RESERVE REPORT FY 2008 Community Management by: CAS, Inc Mr. Dan Quartermane 1930 N. Salem Street, Suite 101 Apex, NC 27523 919-367-7711

More information

CAPITAL PROJECT BUDGET REPORTING FORM

CAPITAL PROJECT BUDGET REPORTING FORM CAPITAL PROJECT BUDGET REPORTING FORM TYPE BUDGET: PROJECT NAME: 3rd REVISED FINAL FLORICULTURE GREENHOUSE APPROVED APPROVED APPROVED APPROVED APPROVED APPROVED PROPOSED REVISED REVISED REVISED REVISED

More information

REPLACEMENT RESERVE REPORT FY 2010 WOODWIND ASSOCIATION. N & H Enterprises MILLER ~ DODSON ASSOCIATES. Community Management by:

REPLACEMENT RESERVE REPORT FY 2010 WOODWIND ASSOCIATION. N & H Enterprises MILLER ~ DODSON ASSOCIATES. Community Management by: REPLACEMENT RESERVE REPORT FY 2010 WOODWIND ASSOCIATION WOODWIND ASSOCIATION REPLACEMENT RESERVE REPORT FY 2010 Community Management by: N & H Enterprises PO Box 5539 Greenville, SC 29607 864-467-1600

More information

Oceanside Gateway Business Park O. A.

Oceanside Gateway Business Park O. A. Operating Budget-Final Parcel Parcel Address Parcel / Bldg / Unit Sq. Ft. % of project Total Monthly Assessment Total Quarterly Assessment PSF/Mo. 1 Hamann Co 33,100 6.78% $ 1,735 $ 5,205 $ 0.052 2-1 BP

More information

CONTRACTOR QUALIFICATION FORM

CONTRACTOR QUALIFICATION FORM CONTRACTOR QUALIFICATION FORM Please TYPE or print in all blanks accurately, provide attachments and fax, mail or e-mail to: INTEGRITY CONSTRUCTION SERVICES, LLC. 829 WEST MAIN STREET, SUITE C GAYLORD,

More information

Contents Ballot Measure... 2 Full Text Ballot Proposition... 3 Tax Rate Statement... 7 Impartial Analysis... 8 Statement in Favor of Measure...

Contents Ballot Measure... 2 Full Text Ballot Proposition... 3 Tax Rate Statement... 7 Impartial Analysis... 8 Statement in Favor of Measure... Contents Ballot Measure... 2 Full Text Ballot Proposition... 3 Tax Rate Statement... 7 Impartial Analysis... 8 Statement in Favor of Measure... 10 Ballot Measure EXHIBIT B MEASURE Y (ABBREVIATED FORM)

More information

AIA Document A101 TM 2017 Exhibit A

AIA Document A101 TM 2017 Exhibit A AIA Document A101 TM 2017 Exhibit A Insurance and Bonds This Insurance and Bonds Exhibit is part of the Agreement, between the Owner and the Contractor, dated the day of «November» in the year «2017» (In

More information

TOWN OF PERINTON FEE SCHEDULE 2018 DEPARTMENT OF PUBLIC WORKS PERMIT & INSPECTION FEES. $60 per inspection / $150 per re-inspection

TOWN OF PERINTON FEE SCHEDULE 2018 DEPARTMENT OF PUBLIC WORKS PERMIT & INSPECTION FEES. $60 per inspection / $150 per re-inspection TOWN OF PERINTON FEE SCHEDULE 2018 DEPARTMENT OF PUBLIC WORKS PERMIT & INSPECTION FEES Sewer Connection Fees Town Sewer District Entrance Fee Town Out-of-District Fee Monroe County Pure Waters Connection

More information

CITY OF SONOMA 2017 FEE SCHEDULE INDEX EFFECTIVE FEBRUARY 13, 2017

CITY OF SONOMA 2017 FEE SCHEDULE INDEX EFFECTIVE FEBRUARY 13, 2017 ADMINISTRATION CA-00 Copy fee - ALL DEPARTMENTS - Unless specific document copy fee is stated. This applies to all printed material i.e. Development Code, General Plan, Minutes, Staff Reports, Agendas

More information

PROJECT FEASIBILITY REPORT CHECKLIST

PROJECT FEASIBILITY REPORT CHECKLIST THE FEASIBILITY PROCESS PROJECT FEASIBILITY REPORT CHECKLIST The Project Feasibility Report is conducted to determine the parameters of time, cost and quality of a proposed capital building project that

More information

Racine Event Center & Hotel. RDA & Committee of the Whole Meeting Tuesday, June 27

Racine Event Center & Hotel. RDA & Committee of the Whole Meeting Tuesday, June 27 Racine Event Center & Hotel RDA & Committee of the Whole Meeting Tuesday, June 27 Agenda o o o o o o Team introductions What the event center and hotel will do for our city? The schedule/process What will

More information

**REVISED BID PRICE FORM** October 24, 2018

**REVISED BID PRICE FORM** October 24, 2018 **REVISED BID PRICE FORM** October 24, 2018 (Date) TO: RE: CHARLESTON COUNTY PARK AND RECREATION COMMISSION (CCPRC) 861 RIVERLAND DRIVE CHARLESTON, SC 29412 INVITATION FOR BID WANNAMAKER COUNTY PARK DOG

More information

MUROC JOINT UNIFIED SCHOOL DISTRICT KERN COUNTY NORTH EDWARDS, CALIFORNIA

MUROC JOINT UNIFIED SCHOOL DISTRICT KERN COUNTY NORTH EDWARDS, CALIFORNIA KERN COUNTY NORTH EDWARDS, CALIFORNIA FINANCIAL AND PERFORMANCE AUDIT JUNE 30, 2018 TABLE OF CONTENTS JUNE 30, 2018 PAGE INTRODUCTORY SECTION TABLE OF CONTENTS i FINANCIAL SECTION INDEPENDENT AUDITOR'S

More information

Integrating Green Building Measures into Capital Planning for HUD Assisted and Public Housing Programs

Integrating Green Building Measures into Capital Planning for HUD Assisted and Public Housing Programs Building Bridges to Net Zero Integrating Green Building Measures into Capital Planning for HUD Assisted and Public Housing Programs Evolution of HUD's Green Capital Needs Assessment, and the new CNA etool

More information

Reserve Fund Study My Condominium Plan

Reserve Fund Study My Condominium Plan Reserve Fund Study My Condominium Plan 12 3456 Number of Units 36 Number of Buildings 1 Building Construction 21 Contact Ima Happy Position(s) President Contact Phone 43.555.4321 Report Date August 8,

More information

McPherson Contractors, Inc.

McPherson Contractors, Inc. McPherson Contractors, Inc. Construction Manager Manual Bishop Professional Development Center Bid Package #3 *****FROM***** McPherson Contractors, Inc. 3501 SW Fairlawn Rd., Suite 100 Topeka, Kansas 66614

More information

2014 Reserve Study. The Bear Creek Crossing Owner's Association, Inc. Bear Haven Way Sevierville, Tennessee Report No: 2921 Version 2

2014 Reserve Study. The Bear Creek Crossing Owner's Association, Inc. Bear Haven Way Sevierville, Tennessee Report No: 2921 Version 2 2014 Reserve Study The Bear Creek Crossing Owner's Association, Inc. Bear Haven Way Sevierville, Tennessee 37862 Report No: 2921 Version 2 For the Period From: January 1, 2014 To: December 31, 2014 TABLE

More information

CHAPTER 3-1 FEE SCHEDULE

CHAPTER 3-1 FEE SCHEDULE CHAPTER 3-1 FEE SCHEDULE Sections: 3-1-1 FEE SCHEDULE (A) Administrative Fees Cable Television System Permit Application $ 2,000.00 9-9-4(A)(1) MC Carnival License $ 250.00 per day 5-1-1(C) MC False Alarms

More information

UNINCORPORATED CAPITAL

UNINCORPORATED CAPITAL UNINCORPORATED CAPITAL The total funding to be appropriated for the unincorporated capital program in FY13 is $13,665,000. This reflects funds committed to drainage, pavement, sidewalk, and other infrastructure

More information

March 21, REQUEST FOR PROPOSAL ARCHITECTURAL / ENGINEERING SERVICES For Department of Public Works Operations Center

March 21, REQUEST FOR PROPOSAL ARCHITECTURAL / ENGINEERING SERVICES For Department of Public Works Operations Center March 21, 2018 REQUEST FOR PROPOSAL ARCHITECTURAL / ENGINEERING SERVICES For Department of Public Works Operations Center 1. INTRODUCTION The City of Jackson is interested in receiving proposals from architects

More information

SUMMARY OF PROPOSED PROJECT

SUMMARY OF PROPOSED PROJECT SOUTH CAROLINA JOBS-ECONOMIC DEVELOPMENT AUTHORITY APPLICATION FOR INDUSTRIAL REVENUE BOND FINANCING Under the Provisions of The South Carolina Jobs-Economic Development Authority Act Name and Address

More information

INSURANCE SCHEDULE F

INSURANCE SCHEDULE F Trade Contractors, Subcontractors or Sub-Subcontractors INSURANCE SCHEDULE F Class A: Asbestos Removal Asphalt Paving Concrete Construction Managers Cranes Culverts Decking Demolition Deconstruction Earthwork

More information

POSITIVE RESPONSE: Nebraska811 does not respond to the excavator or mark lines on behalf of any utility.

POSITIVE RESPONSE: Nebraska811 does not respond to the excavator or mark lines on behalf of any utility. ONE CALL 101 POSITIVE RESPONSE: Nebraska811 does not respond to the excavator or mark lines on behalf of any utility. Every utility that receives a locate request must respond to the excavator by either

More information

SUBDIVISION IMPROVEMENTS AGREEMENT

SUBDIVISION IMPROVEMENTS AGREEMENT SUBDIVISION IMPROVEMENTS AGREEMENT THIS AGREEMENT, made between GLEN DEVELOPMENT COMPANY, hereinafter called the "Subdivider," and El Paso County by and through the Board of County Commissioners of El

More information

City of Hanover 2018 Fee Schedule

City of Hanover 2018 Fee Schedule City of Hanover 2018 Fee Schedule CITY HALL RENTAL FEES: Community Room: No Alcohol Under 100 People Over 100 People Damage Deposit $ 200.00 $ 200.00 Rental Fee $ 125.00 $ 150.00 Community Room: With Alcohol

More information

One and two family residences... $ Mobile Homes... $73.73 Commercial Building... $ All other miscellaneous applications... $44.

One and two family residences... $ Mobile Homes... $73.73 Commercial Building... $ All other miscellaneous applications... $44. EXHIBIT "A" BUILDING PERMITS, HOUSING CODE AND MOBILE HOME PERMIT FEES Page 1 of 9 I. APPLICATION FEES (Non-refundable) One and two family residences... $147.59 Mobile Homes... $73.73 Commercial Building...

More information

BID TABULATION PAGE 1 OF 6

BID TABULATION PAGE 1 OF 6 BID TABULATION PAGE 1 OF 6 BID PRE-BID ESTIMATE R.G. Huston Company, Inc. Kopplin & Kinas Co., Inc. Cottage Grove, WI Green Lake, WI NO. DESCRIPTION OF WORK QUANT. UNITS UNIT PRICE AMOUNT UNIT PRICE AMOUNT

More information

CITY OF NORMANDY PARK ADOPTED FEE SCHEDULE

CITY OF NORMANDY PARK ADOPTED FEE SCHEDULE CITY OF NORMANDY PARK ADOPTED FEE SCHEDULE Effective January 2018 Page 1 Table of Contents General Government and Miscellaneous 3 Page City Clerk 5 Business License Community Development 6 Finance 15 Animal

More information

DeKalb County School District/Middle Schools Chapel Hill Middle Final School Assessment Report May 20, 2016

DeKalb County School District/Middle Schools Chapel Hill Middle Final School Assessment Report May 20, 2016 DeKalb County School District/Middle Schools Chapel Hill Middle Final School Assessment Report May 20, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 3 School Condition

More information

RESERVESTUDYUPDATE. The Villas at Blackberry Run Dallas, GA. Prepared for:

RESERVESTUDYUPDATE. The Villas at Blackberry Run Dallas, GA. Prepared for: RESERVESTUDYUPDATE Dallas, GA Prepared for: THE VILLAS AT BLACKBERRY RUN HOME OWNERS ASSOCIATION, INC. Carl Swanson-President Prepared by: CRITERIUM-CARUSO ENGINEERS 1065 POWERS PLACE, SUITE B ALPHARETTA,

More information

RESOLUTION NO A RESOLUTION OF THE CITY OF NEWPORT REVOKING ALL PRIOR FEE RESOLUTIONS AND ADOPTING A NEW FEE SCHEDULE.

RESOLUTION NO A RESOLUTION OF THE CITY OF NEWPORT REVOKING ALL PRIOR FEE RESOLUTIONS AND ADOPTING A NEW FEE SCHEDULE. RESOLUTION NO. 01152019 A RESOLUTION OF THE CITY OF NEWPORT REVOKING ALL PRIOR FEE RESOLUTIONS AND ADOPTING A NEW FEE SCHEDULE. WHEREAS, the City of Newport has adopted a fee schedule, and WHEREAS, it

More information

City of Hanover 2019 Fee Schedule

City of Hanover 2019 Fee Schedule City of Hanover CITY HALL RENTAL FEES: Complete payment is due 60 days prior to event. Community Room: No Alcohol Damage Deposit $ 200.00 Rental Fee $ 200.00 Community Room: With Alcohol Damage Deposit

More information

DeKalb County School District/Elementary Schools Dunwoody Elementary Final School Assessment Report May 19, 2016

DeKalb County School District/Elementary Schools Dunwoody Elementary Final School Assessment Report May 19, 2016 DeKalb County School District/Elementary Schools Dunwoody Elementary Final School Assessment Report May 19, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 4 School Condition

More information

SANTA ANA COLLEGE FACILITIES COMMITTEE MEETING MAY 15, 2018

SANTA ANA COLLEGE FACILITIES COMMITTEE MEETING MAY 15, 2018 FACILITIES COMMITTEE MEETING MAY 15, 2018 1 PROJECTS Dunlap Hall Renovation - Completed Central Plant & Infrastructure - Completed Johnson Student Center Johnson Demolition Science Center & Building J

More information

Fee Schedule. Effective January 1, Administrative Services/All Departments: COPYING OF RECORDS

Fee Schedule. Effective January 1, Administrative Services/All Departments: COPYING OF RECORDS Fee Schedule Effective January 1, 2019 Administrative Services/All Departments: COPYING OF RECORDS 8½ x 11 black and white $0.25 per page 8½ x 11 color $0.50 per page 8½ x 14 or 11 x 17 black and white

More information

CONVENIENCE STORE QUICK APPLICATION WITH AND WITHOUT GAS PUMPS

CONVENIENCE STORE QUICK APPLICATION WITH AND WITHOUT GAS PUMPS CONVENIENCE STORE QUICK APPLICATION WITH AND WITHOUT GAS PUMPS Binding subject to any additional information when required by IIC. Agency Agency Contact Email: Effective Date Expiration Date: Years in

More information

CITY OF MISSION VIEJO PUBLIC WORKS FEE SCHEDULE

CITY OF MISSION VIEJO PUBLIC WORKS FEE SCHEDULE CITY OF MISSION VIEJO PUBLIC WORKS FEE SCHEDULE GENERAL INSTRUCTIONS 1. This pamphlet lists services available or required to process your project and fees or charges for these services. 2. Fees or deposits

More information

PROFESSIONAL SERVICES CONSULTANT TYPE OF RETAINER AGREEMENT UNIVERSITY OF ILLINOIS

PROFESSIONAL SERVICES CONSULTANT TYPE OF RETAINER AGREEMENT UNIVERSITY OF ILLINOIS PROFESSIONAL SERVICES CONSULTANT TYPE OF RETAINER AGREEMENT UNIVERSITY OF ILLINOIS THIS AGREEMENT, made and entered into in the City of, State of Illinois, as of the date of the last signature of the parties

More information

Laurel Hill Elementary

Laurel Hill Elementary NC School District/830 Scotland County/Elementary School Laurel Hill Elementary Final Campus Assessment Report March 11, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary

More information

Status: Structural steel installation underway at primary building. Observatory construction underway.

Status: Structural steel installation underway at primary building. Observatory construction underway. Page 1 of 11 FACILITIES PLAN STATUS REPORT March 30, 2015 SADDLEBACK COLLEGE 1. SCIENCES BUILDING Project Budget: $52,234,000 $8,308,000 $67,358,000 State Match: $36,564,000 ($36,564,000) - Basic Aid Allocation:

More information

GLOBAL Solution Partners, LLC - Toll free phone and fax: (844)

GLOBAL Solution Partners, LLC - Toll free phone and fax: (844) GLOBAL Solution Partners, LLC info@globalreservestudies.com - Toll free phone and fax: (844) 477-7883 - www.globalsolutionpartners.com Funding Reserve Analysis for Oak Crest Farms November 2, 2016 Page

More information

TAUSSIG. Annual Report Fiscal Year City of Irvine Community Facilities District No (Great Park) & Associates, Inc.

TAUSSIG. Annual Report Fiscal Year City of Irvine Community Facilities District No (Great Park) & Associates, Inc. DAVID TAUSSIG & Associates, Inc. Annual Report Fiscal Year 2014-2015 City of Irvine Community Facilities District No. 2013-3 (Great Park) October 27, 2015 Public Finance Public Private Partnerships Urban

More information

Residential Permit Fee Schedule

Residential Permit Fee Schedule l home Residential Permit Fee Schedule City of Shenandoah 29955 I-45 North Shenandoah, Texas 77381 281-298-5522 New Residential Home Building Permit (includes all sub-contractors fees, plan review, and

More information

Albany Unified School District Measure E Citizens Oversight Committee

Albany Unified School District Measure E Citizens Oversight Committee Measure E Citizens Oversight Committee AGENDA Meeting on: Thursday, October 21, 2010 Meeting Location: AUSD District Office Conference Room Meeting Time: 5:00 p.m. 1. Opening Business a. Call to Order

More information

Town Square Redevelopment. Phase I Contract Discussion

Town Square Redevelopment. Phase I Contract Discussion Town Square Redevelopment Phase I Contract Discussion Date: June 8, 2017 Current Estimated Schedule Draft RFQ Review September 20, 2016 Final RFQ Publication October 10, 2016 Part I Team Shortlist January

More information

NATOMAS UNIFIED SCHOOL DISTRICT CONTRACT FOR ARCHITECTURAL SERVICES FOR ( )

NATOMAS UNIFIED SCHOOL DISTRICT CONTRACT FOR ARCHITECTURAL SERVICES FOR ( ) NATOMAS UNIFIED SCHOOL DISTRICT CONTRACT FOR ARCHITECTURAL SERVICES FOR ( ) THIS AGREEMENT is entered into this day of, 2014, between the, NATOMAS UNIFIED SCHOOL DISTRICT of the County of Sacramento, California,

More information

CITY OF ELKO BID TABULATION * RE-BID* FOR Sports Complex April 4, 2018

CITY OF ELKO BID TABULATION * RE-BID* FOR Sports Complex April 4, 2018 CITY OF ELKO BID TABULATION * RE-BID* FOR Sports Complex 2017-2018 April 4, 2018 Great Basin Engineering CLEARING EARTHWORK 1 337.01200 Mobilization @ Per Lump Sum 1 LS $445,350.00 $ 445,350.00 $481,768.00

More information

CITY OF JENKS COMMERCIAL BUILDING PERMIT P.O. Box N. Elm Jenks, OK 74037(918)

CITY OF JENKS COMMERCIAL BUILDING PERMIT P.O. Box N. Elm Jenks, OK 74037(918) CITY OF JENKS COMMERCIAL BUILDING PERMIT P.O. Box 2007 211 N. Elm Jenks, OK 74037(918) 299-5883 CERTIFICATE OF OCCUPANCY: DATE RECEIVED: BUILDING ADDRESS: LOT: BLOCK: ADDITION: SECTION: TOWNSHIP: RANGE:

More information

TOWN OF JUNO BEACH 340 Ocean Drive Juno Beach, FL Phone: (561) Fax: (561)

TOWN OF JUNO BEACH 340 Ocean Drive Juno Beach, FL Phone: (561) Fax: (561) OFFICE USE ONLY: TOWN OF JUNO BEACH 340 Ocean Drive Phone: (561) 656-0302 Fax: (561) 775-0812 Date: Permit #: Tracking #: Application for Building Permit & Certificate of Occupancy Job Address: Property

More information

Subject: Addendum No. 1 Project #C CCE Parking Lot Replacement Phase 2 Robert Bishop Drive 4380 Richmond Road, Highland Hills, Ohio 44122

Subject: Addendum No. 1 Project #C CCE Parking Lot Replacement Phase 2 Robert Bishop Drive 4380 Richmond Road, Highland Hills, Ohio 44122 Addendum No. 1 Page One To: From: All Plan Holders of Record CT Consultants, Inc. Gene E. Arters, P.E. on behalf of Cuyahoga Community College Subject: Addendum No. 1 Project #C20166009 CCE Parking Lot

More information

DeKalb County School District/High Schools Druid Hills High Final School Assessment Report May 19, 2016

DeKalb County School District/High Schools Druid Hills High Final School Assessment Report May 19, 2016 DeKalb County School District/High Schools Druid Hills High Final School Assessment Report May 19, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 5 School Condition Summary

More information

Subcontractor Questionnaire

Subcontractor Questionnaire Subcontractor Questionnaire Please complete and submit the following questionnaire to be considered for bidding work with SDV. Please fax the following additional items with your completed questionnaire

More information

TAUSSIG. Annual Report Fiscal Year City of Irvine Community Facilities District No (Great Park) & Associates, Inc.

TAUSSIG. Annual Report Fiscal Year City of Irvine Community Facilities District No (Great Park) & Associates, Inc. DAVID TAUSSIG & Associates, Inc. Annual Report Fiscal Year 2016-2017 City of Irvine Community Facilities District No. 2013-3 (Great Park) September 26, 2017 Public Finance Public Private Partnerships Urban

More information

LETTER OF INTENT FOR: HERITAGE HILLS COMMUNITY

LETTER OF INTENT FOR: HERITAGE HILLS COMMUNITY LETTER OF INTENT FOR: HERITAGE HILLS COMMUNITY January 5, 205 2 Partially Completed Single Family Lots (65' x 5' typical) 46 Completed Townhome Pads (22' x 50' typical) Sale. This letter of intent outlines

More information

19th & Barker Roundabout / Waterline Improvement Project No. 56-CP12-901(C) Cost Breakdown

19th & Barker Roundabout / Waterline Improvement Project No. 56-CP12-901(C) Cost Breakdown 19th & Barker Roundabout / Waterline Improvement Project No. 56CP12901(C) Cost Breakdown Engineering Fees: Original Contract $ 71,861.00 Additional Services $ 8,744.00 Waterline Contract $ 17,500.00 TOTAL

More information

Facilities Management and Planning Organizational Review Phase II Update

Facilities Management and Planning Organizational Review Phase II Update MEMORANDUM Office of College Services DATE: September 3, 2013 TO: CC: FROM: SUBJECT: President Mary Spilde, Vice President Brian Kelly Facilities Management & Planning Organizational Review Team Jennifer

More information

SUPPLEMENTAL QUESTIONNAIRE Artisan Contractors

SUPPLEMENTAL QUESTIONNAIRE Artisan Contractors SUPPLEMENTAL QUESTIONNAIRE Artisan Contractors GENERAL INFORMATION Applicant Name: Mailing Address: Location Address (if different from above): Website Address: Date Business Started Has applicant changed

More information

Fee Schedule for 2017

Fee Schedule for 2017 EXHIBIT A Fee Schedule for GENERAL CITY ADMINISTRATIVE FEES Business Licenses Neighborhood Business License Neighborhood Business License - Initial Application Neighborhood Business License - Annual Renewal

More information

Brookwood Homeowners Association, Inc.

Brookwood Homeowners Association, Inc. RESERVE STUDY Full Study Brookwood Homeowners Association, Inc. Published - February 05, 2013 Browning Reserve Group / Emmett, ID 83617 Office (208) 365-0977 Tony@BrowningRG.com / www.browningrg.com Browning

More information

ADDENDUM NO. 3 to the PREQUALIFICATION DOCUMENTS AUGUST 26, 2011

ADDENDUM NO. 3 to the PREQUALIFICATION DOCUMENTS AUGUST 26, 2011 ADDENDUM NO. 3 to the PREQUALIFICATION DOCUMENTS AUGUST 26, 2011 HOUSING 4: THE SUMMITS PROJECT NO. 906270 CAMPUS, MERCED CALIFORNIA A. BID SUBMISSION DEADLINE: [The deadline for submitting prequalification

More information

City of Beaumont Fee Schedule

City of Beaumont Fee Schedule City of Beaumont Fee Schedule Any fees not included in this Fee Schedule will be calculated based on actual costs to provide the service. PLANNING FEES Agricultural Preserve $ 400.00 Amendments: General

More information

BUSINESS EQUIPMENT TAX REIMBURSEMENT

BUSINESS EQUIPMENT TAX REIMBURSEMENT Property Tax Relief Programs Business Equipment / Maine Revenue Services Property Tax Division October 2013 http://www.state.me.us/revenue/propertytax/propertytaxbe nefits/bete.htm Reimbursement Program

More information

PROFESSIONAL RESERVE STUDY

PROFESSIONAL RESERVE STUDY PROFESSIONAL RESERVE STUDY Heritage Park 3208-52 nd Place NE, Tacoma, WA 98422 For: Heritage Park Homeowners Association c/o Juanita Carbaugh, Property Manager HOA Community Solutions 5500 Olympic Drive,

More information

City of La Verne Cost Allocation Study

City of La Verne Cost Allocation Study HF&H Consultants Presentation Outline Study Purpose Current Overhead Cost Allocations Administrative Operational Potential Enterprise Reimbursements Public Safety Governmental Facilities Capital Right-of-Way

More information