The World Bank Kabul Urban Transport Efficiency Improvement Project (P131864)
|
|
- Alisha Carson
- 5 years ago
- Views:
Transcription
1 Public Disclosure Authorized SOUTH ASIA Afghanistan Transport & Digital Development Global Practice Recipient Executed Activities Investment Project Financing FY 2014 Seq No: 8 ARCHIVED on 09-Feb-2018 ISR31139 Implementing Agencies: Ministry of Finance, Islamic Republic of Afghanistan, Kabul Municipality (KM) Public Disclosure Authorized Key Dates Key Project Dates Bank Approval Date:03-Apr-2014 Planned Mid Term Review Date:30-Jun-2016 Original Closing Date:31-Dec-2019 Project Development Objectives Effectiveness Date:11-Apr-2014 Actual Mid-Term Review Date:01-Aug-2017 Revised Closing Date:31-Dec-2019 Public Disclosure Authorized Project Development Objective (from Project Appraisal Document) Improve road condition and traffic flows on selected corridors of Kabul city. Has the Project Development Objective been changed since Board Approval of the Project Objective? No PHRPDODEL Components Name Road infrastructure:(cost $68.94 M) Capacity Building:(Cost $13.71 M) Public Disclosure Authorized Project Management Support:(Cost $7.85 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Substantial Substantial Implementation Status and Key Decisions 2/9/2018 Page 1 of 10
2 Project implementation is proceeding broadly in line with the plans and schedules. Overall progress towards achievement of Project Development Objectives (PDO) is rated Satisfactory (S), while Implementation Progress (IP) is still rated Moderately Satisfactory (MS). The project implementation arrangements are mostly in place and functioning. The detailed implementation progress and key issues related to implementation of the three project s components and activities are as follow: Component A. Road Infrastructure (US$68.94 million): This component finances the improvement of 32 km of roads in four priority corridors of Kabul city, and reconstruction of 6.5 km of Wazir Abad drainage canal. As of December 21, 2017, all major works contracts are awarded. Out of 9 civil works contracts, six road infrastructure contracts have been completed for a total of 19.3 km, and roads are opened to the traffic. 2 contracts are under implementation, and the final one is in the contract signing stage. Component B. Capacity Building (US$13.71 million): This component provides technical assistance to KM in various areas. The team's assessment during the MTR shows that most of the activities under this component are delayed. The team had detailed discussions with KM and has agreed on time bound actions for the procurement of all consultancies under the project. Component C. Project Management Support (US$7.85 million). Under this component, the project finances consultancy services to enhance KM s human resource capacity for KUTEI s implementation. KM has mobilized a fully functional Project Management Unit (PMU) for the implementation of the project. The team consists of individual local and international consultants and KM civil servants. KUTEI/KM has prepared and is implementing a comprehensive on the job training plan. The project Mid Term review was carried out over the period of August 01 - September 15, The summary of findings are as follows: Financial Management. An FM review was carried out, covering aspects of budgeting, accounting, funds flow, record management, internal controls, reporting, internal and external audits, and staffing. The project has fully designed financial management arrangements in place. Social and Environmental Safeguards. The compliances on social and environmental safeguards management are satisfactory. KUTEI has made significant progress with regards to land/assets documentation, compensation to Project Affected Persons (PAPs), GRM functionality and quality of social safeguards instruments. Environmental and Social Management Plans (ESMPs) and Abbreviated Resettlement Action Plans (RAPs) for project affected parcels have been prepared. KUTEI also made substantial progress in timely conducting and updating the Environmental and Social Impact Assessment (ESIA) and prepared the subsequent safeguards documents. The documents are cleared by the National Environmental Protection Agency (NEPA). Nevertheless, it is noted that, the health, safety and hygiene issue at subproject sites have not received adequate attention. It was agreed that KUTEI will ensure that contractors will improve physical condition of subproject sites. 2/9/2018 Page 2 of 10
3 2/9/2018 Page 3 of 10
4 2/9/2018 Page 4 of 10
5 Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance -- High High Macroeconomic -- Substantial Substantial Sector Strategies and Policies -- Substantial Substantial Technical Design of Project or Program -- Moderate Moderate Institutional Capacity for Implementation and Sustainability -- High Substantial Fiduciary -- High High Environment and Social -- Moderate Moderate Stakeholders -- Low Low Other -- Moderate Moderate Overall -- Substantial Substantial Results Project Development Objective Indicators 2/9/2018 Page 5 of 10
6 PHINDPDOTBL Average vehicle speed on the selected corridors in the off-peak time. (Kilometers, Custom) Value Date 30-Apr Apr Aug Dec-2019 The actual vehicle speed along 14 roads are determined during off peak hours after completion. The current average speed is 35km/hr which means speed has improved by 17km/hr. Due to unavailability of sufficient information during project appraisal, the team did not specify the end target, but clearly, the project investment has had significant improvement on average vehicle speed. This is the latest data available from the actual survey carried out by KUTEI during August The frequency of the data is before and after the project intervention. PHINDPDOTBL Number of people in urban areas provided with access to all-season roads within a 500 meter range under the project (Number, Custom) Value , , Date 01-Sep Apr Aug Dec-2019 In 2013, a total of 58,977 people living in a range of 500m along 5 roads of the project did not have access to an all-season road. After completion of these roads, it is anticipated that 58,977 people will have access to an all-season road. This is the latest data available from the actual survey carried out by KUTEI during August The frequency of the data is before and after the project intervention. PHINDPDOTBL Fair and above surface condition of major urban road network improved (Percentage, Custom) Value Date 31-Oct Apr Apr Mar-2019 A survey was conducted by Operations and Maintenance Department of Kabul Municipality in 2013/2014. A total of 289 km of roads were classified as trunk roads. The total of 244.2km of Kabul city's trunk roads were identified to be in "Fair to Better" condition, so the baseline 2/9/2018 Page 6 of 10
7 PHINDIRITBL PHINDIRITBL percentage of these roads was calculated as 84% in Assuming that all roads that were in "Fair or Better" condition in 2014 will still be in "Fair to Better" condition by end of KUTEI project in December 2019, it is anticipated that the percentage of Kabul City's trunk roads network in "Fair to Better" condition will increase by 10%. This is the latest data available from the actual survey carried out by KUTEI during August The frequency of the data is before and after the project intervention. Overall Detailed comments have been provided under every each PDO indicators. Intermediate Results Indicators All O&M equipments purchased, installed and KM staffs are capable to operate and maintain the equipment (Yes/No, Custom) Value N N N Y Date 31-Dec Apr Dec Jun-2018 As part of improving the O&M productivity, KUTEI will procure equipment for KM s O&M directorate to strengthen implementation capacity. KM s O&M director presented a new list of O&M equipment, which was reviewed and approved in principle by the Bank team. The procurement will start soon. Roads rehabilitated, Non-rural (Kilometers, Custom) Value Date 30-Jan Apr Dec Jun-2016 The project financed 32km roads in eight lots. Six roads have been completed so far for a total of 19.3 km and two lots are under implementation, and expected to be completed by the end of /9/2018 Page 7 of 10
8 PHINDIRITBL PHINDIRITBL PHINDIRITBL Road rehabilitated by KM Dept of Works and Maintenance (Kilometers, Custom Supplement) Value Junction channelization along 4 selected corridors (Number, Custom) Value Date 31-Dec Apr Dec May-2019 KM will finalize selection of the four intersections for junction channelization from the 20 most problematic intersections already identified. KM will prepare ToRs for consultants to develop detailed designs and bid documents, and send to the Bank for review by February 28, High volume public transport feasibility study and business plan finalized and ready for implementation (Yes/No, Custom) Value N N N Y Date 31-Dec Apr Dec Jun-2016 The public transport feasibility study is already financed by KM from its internal resources, while the project will finance the business plan and detailed engineering design for one or two potential public transport service corridors. Overall Detailed comments have been provided under every each intermediate indicators. 2/9/2018 Page 8 of 10
9 Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P TF Effective USD % Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P TF Effective 11-Apr Apr Apr Dec Dec-2019 Cumulative Disbursements Restructuring History There has been no restructuring to date. Related Project(s) 2/9/2018 Page 9 of 10
10 There are no related projects. 2/9/2018 Page 10 of 10
Public Disclosure Copy
Public Disclosure Authorized EUROPE AND CENTRAL ASIA Armenia Energy & Extractives Global Practice Recipient Executed Activities Investment Project Financing FY 2015 Seq No: 1 ARCHIVED on 24-Sep-2015 ISR20717
More informationPublic Disclosure Copy
Public Disclosure Authorized EUROPE AND CENTRAL ASIA Georgia Transport & ICT Global Practice IBRD/IDA Investment Project Financing FY 2015 Seq No: 6 ARCHIVED on 11-Sep-2017 ISR28869 Implementing Agencies:
More informationPublic Disclosure Copy
Public Disclosure Authorized EUROPE AND CENTRAL ASIA Georgia Transport & ICT Global Practice IBRD/IDA Investment Project Financing FY 2015 Seq No: 5 ARCHIVED on 09-Feb-2017 ISR25380 Implementing Agencies:
More informationPublic Disclosure Copy
Public Disclosure Authorized EAST ASIA AND PACIFIC Indonesia Social, Urban, Rural and Resilience Global Practice Global Practice IBRD/IDA Investment Project Financing FY 2012 Seq No: 12 ARCHIVED on 08-Dec-2017
More informationPublic Disclosure Copy
Public Disclosure Authorized EUROPE AND CENTRAL ASIA Serbia Transport Global Practice IBRD/IDA Specific Investment Loan FY 2013 Seq No: 4 ARCHIVED on 24-Jun-2015 ISR17421 Implementing Agencies: Public
More informationPublic Disclosure Copy
Public Disclosure Authorized EAST ASIA AND PACIFIC Indonesia Social, Urban, Rural and Resilience Global Practice Global Practice IBRD/IDA Specific Investment Loan FY 2012 Seq No: 8 ARCHIVED on 14-Dec-2015
More informationThe World Bank Palestinian Recovery & Development Plan MDTF (P110690)
Public Disclosure Authorized MIDDLE EAST AND NORTH AFRICA West Bank and Gaza Recipient Executed Activities Adaptable Program Loan FY 2008 Seq No: 6 ARCHIVED on 21-Mar-2017 ISR27335 Implementing Agencies:
More informationRoad Sector Development Project (P149322)
Public Disclosure Authorized EUROPE AND CENTRAL ASIA Ukraine Transport & Digital Development Global Practice IBRD/IDA Investment Project Financing FY 2016 Seq No: 6 ARCHIVED on 20-Jun-2018 ISR32806 Implementing
More informationDebt Management Strengthening Programme at Ministry of Finance, Government of Pakistan (P161451)
SOUTH ASIA Pakistan Macroeconomics, Trade and Investment Global Practice Recipient Executed Activities Investment Project Financing FY 2017 Seq No: 2 ARCHIVED on 27-Jun-2018 ISR33129 Implementing Agencies:
More informationPublic Disclosure Copy
Public Disclosure Authorized AFRICA Liberia Transport & ICT Global Practice IBRD/IDA Specific Investment Loan FY 2011 Seq No: 11 ARCHIVED on 10-Nov-2016 ISR24991 Implementing Agencies: Infrastructure Implementation
More informationPublic Disclosure Copy
Public Disclosure Authorized EAST ASIA AND PACIFIC Indonesia Water Global Practice IBRD/IDA Specific Investment Loan FY 2012 Seq No: 7 ARCHIVED on 19-Jun-2015 ISR19914 Implementing Agencies: Ministry of
More informationThe World Bank Indonesia Infrastructure Guarantee Fund Project (P118916)
Public Disclosure Authorized EAST ASIA AND PACIFIC Indonesia Finance & Markets Global Practice IBRD/IDA Investment Project Financing FY 2013 Seq No: 10 ARCHIVED on 24-Dec-2017 ISR31037 Implementing Agencies:
More informationPublic Disclosure Copy
Public Disclosure Authorized LATIN AMERICA AND CARIBBEAN Brazil Agriculture Global Practice IBRD/IDA Specific Investment Loan FY 2012 Seq No: 9 ARCHIVED on 29-Feb-2016 ISR22351 Implementing Agencies: SEDAR
More informationPublic Disclosure Copy
Public Disclosure Authorized EUROPE AND CENTRAL ASIA Uzbekistan Water Global Practice IBRD/IDA Investment Project Financing FY 2013 Seq No: 11 ARCHIVED on 12-Jan-2018 ISR30620 Implementing Agencies: Republic
More informationThe World Bank Urban Transport Corridor Development in Surabaya - RETF (P147893)
Public Disclosure Authorized EAST ASIA AND PACIFIC Indonesia Social, Urban, Rural and Resilience Global Practice Global Practice Recipient Executed Activities Investment Project Financing FY 2014 Seq No:
More informationThe World Bank Building a Modern Fiscal System Technical Assistance (P154694)
Public Disclosure Authorized EAST ASIA AND PACIFIC China Macro Economics & Fiscal Management Global Practice IBRD/IDA Investment Project Financing FY 2016 Seq No: 2 ARCHIVED on 15-Jun-2017 ISR26699 Implementing
More informationThe World Bank Albania-Enhancing Quality of Financial Reporting (EQ-FINREP) (P152567)
EUROPE AND CENTRAL ASIA Albania Governance Global Practice Recipient Executed Activities Investment Project Financing FY 2015 Seq No: 2 ARCHIVED on 17-Oct-2017 ISR29727 Implementing Agencies: Key Dates
More informationThe World Bank Bangladesh Ghorashal Unit 4 Repowering Project (P128012)
Public Disclosure Authorized SOUTH ASIA Bangladesh Energy & Extractives Global Practice IBRD/IDA Investment Project Financing FY 2016 Seq No: 3 ARCHIVED on 24-Apr-2017 ISR27761 Implementing Agencies: Public
More informationPublic Disclosure Copy
SOUTH ASIA India Finance & Markets Global Practice IBRD/IDA Financial Intermediary Loan FY 2013 Seq No: 8 ARCHIVED on 11-Nov-2016 ISR25496 Implementing Agencies: National Housing Bank, National Housing
More informationPublic Disclosure Copy. Implementation Status & Results Report CAPE VERDE - Recovery and Reform of the Electricity Sector Project (P115464)
Public Disclosure Authorized AFRICA Cabo Verde Energy & Extractives Global Practice IBRD/IDA Specific Investment Loan FY 2012 Seq No: 10 ARCHIVED on 23-Oct-2017 ISR29430 Implementing Agencies: Unidade
More informationThe World Bank Transport Connectivity and Asset Management Project (P132833)
Public Disclosure Authorized SOUTH ASIA Sri Lanka Transport & ICT Global Practice IBRD/IDA Specific Investment Loan FY 2016 Seq No: 2 ARCHIVED on 30-Jan-2017 ISR26613 Implementing Agencies: Public Disclosure
More informationPublic Disclosure Copy. East-West Roads Project (Almaty-Korgos Section): Western Europe - Western China International Transit
Public Disclosure Authorized East-West Roads Project (Almaty-Korgos Section): Western Europe - Western China International Transit Corridor EUROPE AND CENTRAL ASIA Kazakhstan Transport & ICT Global Practice
More informationThe World Bank Municipal Services Improvement (P096481)
Public Disclosure Authorized EUROPE AND CENTRAL ASIA Macedonia, former Yugoslav Republic of Urban Development Global Practice IBRD/IDA Specific Investment Loan FY 2009 Seq No: 15 ARCHIVED on 15-Jun-2015
More informationWest Bank and Gaza: Finance for Jobs (P151089)
MIDDLE EAST AND NORTH AFRICA West Bank and Gaza Finance & Markets Global Practice Special Financing Investment Project Financing FY 2016 Seq No: 1 ARCHIVED on 18-Apr-2016 ISR23000 Implementing Agencies:
More informationPublic Disclosure Copy
Public Disclosure Authorized EAST ASIA AND PACIFIC Indonesia Social, Urban, Rural and Resilience Global Practice Global Practice IBRD/IDA Specific Investment Loan FY 2013 Seq No: 9 ARCHIVED on 22-Jun-2017
More informationThe World Bank Transport Connectivity and Asset Management Project (P132833)
SOUTH ASIA Sri Lanka Transport & ICT Global Practice IBRD/IDA Specific Investment Loan FY 2016 Seq No: 3 ARCHIVED on 31-Aug-2017 ISR29065 Implementing Agencies: Democratic Socialist Republic of Sri Lanka,
More informationJordan Ozone Depleting Substances HCFC Phase-Out Project (ODS3) (P127702)
Public Disclosure Authorized Public Disclosure Copy MIDDLE EAST AND NORTH AFRICA Jordan Environment & Natural Resources Global Practice Montreal Protocol Specific Investment Loan FY 2013 Seq No: 9 ARCHIVED
More informationPublic Disclosure Copy
Public Disclosure Authorized AFRICA Senegal Transport & Digital Development Global Practice IBRD/IDA Investment Project Financing FY 2017 Seq No: 2 ARCHIVED on 21-May-2018 ISR32084 Implementing Agencies:
More informationMozambique -Roads and Bridges Management and Maintenance Program - Phase II (P083325)
AFRICA Mozambique Transport & Digital Development Global Practice IBRD/IDA Investment Project Financing FY 2007 Seq No: 24 ARCHIVED on 29-Aug-2018 ISR33744 Implementing Agencies: ROAD FUND (Fundo de Estradas),
More informationPublic Disclosure Copy. Implementation Status & Results Report Federally Administered Tribal Areas (FATA) Governance and Policy Program (P156412)
SOUTH ASIA Pakistan Governance Global Practice Recipient Executed Activities Investment Project Financing FY 2017 Seq No: 1 ARCHIVED on 06-Apr-2017 ISR27349 Implementing Agencies: Economic Affairs Division,
More informationThe World Bank Indonesia Power Transmission Development Project (P117323)
Public Disclosure Authorized EAST ASIA AND PACIFIC Indonesia Energy & Extractives Global Practice IBRD/IDA Specific Investment Loan FY 2011 Seq No: 7 ARCHIVED on 07-Jul-2015 ISR18557 Implementing Agencies:
More informationPublic Disclosure Copy
SOUTH ASIA Bangladesh Financial Management Global Practice Recipient Executed Activities Technical Assistance Loan FY 2011 Seq No: 4 ARCHIVED on 26-Feb-2015 ISR18034 Implementing Agencies: Key Dates Key
More informationPublic Disclosure Copy. Implementation Status & Results Report FATA Rural Livelihoods and Community Infrastructure Project (RLCIP) (P126833)
SOUTH ASIA Pakistan Agriculture and Rural Development Global Practice Recipient Executed Activities Specific Investment Loan FY 2012 Seq No: 7 ARCHIVED on 08-May-2015 ISR19105 Implementing Agencies: FATA
More informationThe World Bank Indonesia Power Transmission Development Project (P117323)
Public Disclosure Authorized EAST ASIA AND PACIFIC Indonesia Energy & Extractives Global Practice IBRD/IDA Investment Project Financing FY 2011 Seq No: 13 ARCHIVED on 28-Dec-2017 ISR30911 Implementing
More informationInnovative Access to Finance (P147183)
Public Disclosure Authorized EUROPE AND CENTRAL ASIA Turkey Finance, Competitiveness and Innovation Global Practice IBRD/IDA Investment Project Financing FY 2015 Seq No: 7 ARCHIVED on 07-Mar-2018 ISR31622
More informationThe World Bank Bangladesh Ghorashal Unit 4 Repowering Project (P128012)
Public Disclosure Authorized SOUTH ASIA Bangladesh Energy & Extractives Global Practice IBRD/IDA Investment Project Financing FY 2016 Seq No: 4 ARCHIVED on 01-Dec-2017 ISR30202 Implementing Agencies: Government
More informationThe World Bank Nigeria - Public/Private Partnership Program (P115386)
AFRICA Nigeria Finance & Markets Global Practice IBRD/IDA Adaptable Program Loan FY 2011 Seq No: 11 ARCHIVED on 03-Jan-2017 ISR25243 Implementing Agencies: Ministry of Finance Key Dates Key Project Dates
More informationZambia Kafue Town - Muzuma - Victoria Falls Regional Transmission Line Reinforcement Project
Public Disclosure Authorized Zambia Kafue Town - Muzuma - Victoria Falls Regional Transmission Line Reinforcement Project (P124351) AFRICA Africa Energy and Mining Global Practice IBRD/IDA Specific Investment
More informationPublic Disclosure Copy
AFRICA Western Africa Finance, Competitiveness and Innovation Global Practice IBRD/IDA Investment Project Financing FY 2018 Seq No: 2 ARCHIVED on 11-Jun-2018 ISR32159 Implementing Agencies: CRRH, BOAD,
More informationThe World Bank Burkina Faso Donsin Transport Infrastructure Project (P120960)
Public Disclosure Authorized AFRICA Burkina Faso Transport & ICT Global Practice IBRD/IDA Investment Project Financing FY 2013 Seq No: 11 ARCHIVED on 29-Dec-2017 ISR30740 Implementing Agencies: MOAD, Government
More informationPublic Disclosure Copy. Implementation Status & Results Report QUALISUS-REDE Brazil Health Network Formation and Quality Improvement Project (P088716)
LATIN AMERICA AND CARIBBEAN Brazil Health, Nutrition and Population Global Practice IBRD/IDA Adaptable Program Loan FY 2009 Seq No: 11 ARCHIVED on 21-Jan-2015 ISR17508 Implementing Agencies: Ministry of
More informationPublic Disclosure Copy
Public Disclosure Authorized EAST ASIA AND PACIFIC China Transport Global Practice IBRD/IDA Specific Investment Loan FY 2010 Seq No: 6.0 ARCHIVED on 21-Nov-2014 ISR16536 Implementing Agencies: Wuhan Urban
More informationThe World Bank Nigeria - Public/Private Partnership Program (P115386)
AFRICA Nigeria Finance & Markets Global Practice IBRD/IDA Adaptable Program Loan FY 2011 Seq No: 12 DRAFT ISR29127 Implementing Agencies: Ministry of Finance, Ministry of Finance Key Dates Key Project
More informationKey Dates. Project Development Objectives. Components. Overall Ratings. Implementation Status and Key Decisions
Public Disclosure Authorized AFRICA Africa Water Global Practice IBRD/IDA Investment Project Financing FY 2015 Seq No: 3 ARCHIVED on 27-Jun-2016 ISR22945 Implementing Agencies: Zambezi River Authority
More informationThe World Bank Pacific Islands Regional Oceanscape Program - Tuvalu (P151780)
Public Disclosure Authorized EAST ASIA AND PACIFIC Tuvalu Environment & Natural Resources Global Practice IBRD/IDA Investment Project Financing FY 2015 Seq No: 6 ARCHIVED on 08-Dec-2017 ISR30682 Implementing
More informationPublic Disclosure Copy
EAST ASIA AND PACIFIC Indonesia Social, Urban, Rural and Resilience Global Practice Global Practice Recipient Executed Activities Technical Assistance Loan FY 2013 Seq No: 4 ARCHIVED on 28-Dec-2015 ISR21722
More informationPublic Disclosure Copy
Public Disclosure Authorized EAST ASIA AND PACIFIC Indonesia Public Private Partnership Global Practice Recipient Executed Activities Investment Project Financing FY 2016 Seq No: 2 ARCHIVED on 29-Jun-2017
More informationPublic Disclosure Copy
Public Disclosure Authorized LATIN AMERICA AND CARIBBEAN Argentina Social Protection & Labor Global Practice IBRD/IDA Specific Investment Loan FY 2009 Seq No: 14 ARCHIVED on 16-Jun-2016 ISR23892 Implementing
More informationPublic Disclosure Copy
AFRICA Uganda Transport Global Practice IBRD/IDA Specific Investment Loan FY 2010 Seq No: 10 ARCHIVED on 24-Feb-2015 ISR17943 Implementing Agencies: Uganda National Roads Authority Key Dates Key Project
More informationPublic Disclosure Copy
Public Disclosure Authorized EUROPE AND CENTRAL ASIA Turkey Finance & Markets Global Practice IBRD/IDA Investment Project Financing FY 2013 Seq No: 8 ARCHIVED on 16-Oct-2017 ISR29893 Implementing Agencies:
More informationThe World Bank. Ghana: Energy Development and Access Project (P074191) Key Dates. Project Development Objectives. Components
Public Disclosure Authorized AFRICA Ghana Energy & Extractives Global Practice IBRD/IDA Investment Project Financing FY 2008 Seq No: 19 ARCHIVED on 29-Jun-2018 ISR32934 Implementing Agencies: Electricity
More informationPublic Disclosure Copy. Implementation Status & Results Report Pacific Regional Connectivity Program 2:Palau-FSM Connectivity Project (P130592)
Public Disclosure Authorized EAST ASIA AND PACIFIC Micronesia, Federated States of Transport & ICT Global Practice IBRD/IDA Investment Project Financing FY 2015 Seq No: 4 ARCHIVED on 06-Jun-2017 ISR28080
More informationPublic Disclosure Copy
AFRICA Uganda Transport & ICT Global Practice IBRD/IDA Specific Investment Loan FY 2010 Seq No: 11 ARCHIVED on 17-Aug-2015 ISR20352 Implementing Agencies: Uganda National Roads Authority (UNRA) Key Dates
More informationKey Dates. Project Development Objectives. Components. Overall Ratings. Implementation Status and Key Decisions
Public Disclosure Authorized LATIN AMERICA AND CARIBBEAN Brazil Transport & ICT Global Practice IBRD/IDA Specific Investment Loan FY 2010 Seq No: 12 ARCHIVED on 20-Jun-2016 ISR23360 Implementing Agencies:
More informationPublic Disclosure Copy
Public Disclosure Authorized EAST ASIA AND PACIFIC Myanmar Energy & Extractives Global Practice IBRD/IDA Investment Project Financing FY 2014 Seq No: 5 ARCHIVED on 06-Jan-2016 ISR21425 Implementing Agencies:
More informationPublic Disclosure Copy. Implementation Status & Results Report Dominican Republic DRM Development Policy Loan with a Cat DDO (P159351)
LATIN AMERICA AND CARIBBEAN Dominican Republic Social, Urban, Rural and Resilience Global Practice Global Practice IBRD/IDA Development Policy Lending FY 2018 Seq No: 1 ARCHIVED on 26-Jan-2018 ISR31220
More informationThe World Bank Second Karnataka State Highway Improvement (P107649)
Public Disclosure Authorized SOUTH ASIA India Transport & ICT Global Practice IBRD/IDA Specific Investment Loan FY 2011 Seq No: 10 ARCHIVED on 31-Jul-2015 ISR18834 Implementing Agencies: Karnataka Road
More informationPublic Disclosure Copy
Public Disclosure Authorized EUROPE AND CENTRAL ASIA Poland Water Global Practice IBRD/IDA Investment Project Financing FY 2007 Seq No: 20 ARCHIVED on 07-Dec-2017 ISR30355 Implementing Agencies: Republic
More informationThe World Bank Jamaica Strategic Public Sector Transformation (P146688)
Public Disclosure Authorized LATIN AMERICA AND CARIBBEAN Jamaica Governance Global Practice IBRD/IDA Investment Project Financing FY 2015 Seq No: 7 ARCHIVED on 28-Jun-2018 ISR32761 Implementing Agencies:
More informationKey Dates. Global Development Objectives. Components. Overall Ratings
Public Disclosure Authorized AFRICA Cameroon Environment & Natural Resources Global Practice Global Environment Project Specific Investment Loan FY 2012 Seq No: 10 ARCHIVED on 19-Apr-2017 ISR27535 Implementing
More informationPublic Disclosure Copy
Public Disclosure Authorized AFRICA Ghana Finance & Markets Global Practice IBRD/IDA Adaptable Program Loan FY 2012 Seq : 7 ARCHIVED on 27-Aug-2015 ISR20184 Implementing Agencies: Public Investment Department,
More informationThe World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report
Public Disclosure Authorized Public Disclosure Copy EAST ASIA AND PACIFIC China Energy & Extractives Global Practice IBRD/IDA Financial Intermediary Loan FY 2008 Seq No: 11 ARCHIVED on 16-Dec-2015 ISR21909
More informationBangladesh Insurance Sector Development Project (P156823)
SOUTH ASIA Bangladesh Finance, Competitiveness and Innovation Global Practice IBRD/IDA Investment Project Financing FY 2017 Seq No: 4 ARCHIVED on 11-Oct-2018 ISR34079 Implementing Agencies: PEOPLE'S REPUBLIC
More informationThe World Bank Water Resources and Irrigation Sector Management Program 2 (P114348)
Public Disclosure Authorized EAST ASIA AND PACIFIC Indonesia Water Global Practice IBRD/IDA Adaptable Program Loan FY 2011 Seq No: 9 ARCHIVED on 24-Jun-2016 ISR23824 Implementing Agencies: Public Disclosure
More informationThe World Bank Research and Innovation in Science and Technology Project (P121842)
Public Disclosure Authorized EAST ASIA AND PACIFIC Indonesia Education Global Practice IBRD/IDA Specific Investment Loan FY 2013 Seq No: 7 ARCHIVED on 07-Dec-2016 ISR25509 Implementing Agencies: Ministry
More informationPublic Disclosure Copy
LATIN AMERICA AND CARIBBEAN Honduras Energy & Extractives Global Practice Recipient Executed Activities Technical Assistance Loan FY 2014 Seq No: 1 ARCHIVED on 16-Oct-2015 ISR20092 Implementing Agencies:
More informationTR Third Access to Finance for SMEs (SME III) (P130864)
EUROPE AND CENTRAL ASIA Turkey Finance, Competitiveness and Innovation Global Practice IBRD/IDA Investment Project Financing FY 2013 Seq No: 9 ARCHIVED on 17-Oct-2018 ISR34297 Implementing Agencies: T.
More informationThe World Bank KI: Telecommunications and ICT Development Project (P126324)
Public Disclosure Authorized EAST ASIA AND PACIFIC Kiribati Transport & ICT Global Practice IBRD/IDA Technical Assistance Loan FY 2013 Seq No: 6 ARCHIVED on 27-Aug-2015 ISR20341 Implementing Agencies:
More informationPublic Disclosure Copy
EAST ASIA AND PACIFIC China Energy & Extractives Global Practice IBRD/IDA Investment Project Financing FY 2011 Seq No: 12 ARCHIVED on 27-Nov-2017 ISR28052 Implementing Agencies: Ministry of Fiance, Shandong
More informationPublic Disclosure Copy
Public Disclosure Authorized SOUTH ASIA India Water Global Practice IBRD/IDA Specific Investment Loan FY 2010 Seq No: 14 ARCHIVED on 14-Sep-2016 ISR24822 Implementing Agencies: Telangana State Irrigation
More informationThe World Bank NP: Strengthening the Office of the Auditor General (P127040)
Public Disclosure Authorized SOUTH ASIA Nepal Financial Management Global Practice Recipient Executed Activities Specific Investment Loan FY 2012 Seq No: 3 ARCHIVED on 20-Feb-2015 ISR18017 Implementing
More informationThe World Bank Ghana - PPP Project (P125595)
Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized AFRICA Ghana Finance & Markets Global Practice IBRD/IDA Adaptable Program Loan FY 2012
More informationThe World Bank Governance and Policy Program for Khyber Pakhtunkhwa (KP) (P156410)
SOUTH ASIA Pakistan Governance Global Practice Recipient Executed Activities Investment Project Financing FY 2017 Seq No: 1 ARCHIVED on 18-Aug-2017 ISR29255 Implementing Agencies: Economic Affairs Division,
More informationImplementation Status & Results Report Niger Disaster Risk Management and Urban Development Project (P145268)
Public Disclosure Authorized AFRICA Niger Social, Urban, Rural and Resilience Global Practice Global Practice IBRD/IDA Investment Project Financing FY 2014 Seq No: 8 ARCHIVED on 04-Apr-2018 ISR30085 Implementing
More informationMyanmar Southeast Asia Disaster Risk Management Project (P160931)
Public Disclosure Authorized EAST ASIA AND PACIFIC Myanmar Social, Urban, Rural and Resilience Global Practice Global Practice IBRD/IDA Investment Project Financing FY 2017 Seq No: 3 ARCHIVED on 26-Aug-2018
More informationThe World Bank Kenya Cash Transfer for Orphans and Vulnerable Children (P111545)
Public Disclosure Authorized AFRICA Kenya Social Protection & Labor Global Practice IBRD/IDA Specific Investment Loan FY 2009 Seq No: 17 ARCHIVED on 21-Jun-2017 ISR28380 Implementing Agencies: Ministry
More informationThe World Bank. Key Dates. Project Development Objectives. Components. Overall Ratings. Implementation Status and Key Decisions
Public Disclosure Authorized Public Disclosure Copy AFRICA South Sudan Health, Nutrition & Population Global Practice Special Financing Emergency Recovery Loan FY 2012 Seq No: 7 ARCHIVED on 23-Dec-2015
More informationPublic Disclosure Copy. Implementation Status & Results Report Improving Maternal and Child Health through Integrated Social Services (P123706)
Public Disclosure Authorized LATIN AMERICA AND CARIBBEAN Haiti Health, Nutrition & Population Global Practice IBRD/IDA Investment Project Financing FY 2013 Seq No: 10 ARCHIVED on 29-Jun-2018 ISR32902 Implementing
More informationSOUTH-WEST ROADS: WESTERN EUROPE-WESTERN CHINA INTERNATIONAL TRANSIT CORRIDOR (CAREC 1B & 6B) (P099270)
Public Disclosure Authorized SOUTH-WEST ROADS: WESTERN EUROPE-WESTERN CHINA INTERNATIONAL TRANSIT CORRIDOR EUROPE AND CENTRAL ASIA Kazakhstan Transport & ICT Global Practice IBRD/IDA Specific Investment
More informationThe World Bank Egypt National Railways Restructuring Project (P101103)
Public Disclosure Authorized MIDDLE EAST AND NORTH AFRICA Egypt, Arab Republic of Transport Global Practice IBRD/IDA Specific Investment Loan FY 2009 Seq No: 14 ARCHIVED on 19-Mar-2015 ISR18375 Implementing
More informationThe World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report
Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized AFRICA Nigeria Governance Global Practice IBRD/IDA Specific Investment Loan FY 2012 Seq
More informationThe World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report
Public Disclosure Authorized EAST ASIA AND PACIFIC Vietnam Transport Global Practice IBRD/IDA Specific Investment Loan FY 2008 Seq No: 12 ARCHIVED on 24-Feb-2015 ISR18063 Implementing Agencies: Hanoi Urban
More informationPublic Disclosure Copy
Public Disclosure Authorized AFRICA Senegal Transport & ICT Global Practice IBRD/IDA Investment Project Financing FY 2017 Seq No: 1 ARCHIVED on 01-Nov-2017 ISR29876 Implementing Agencies: Ministry of Economy,
More informationThe World Bank. Ghana: Energy Development and Access Project (P074191) Key Dates. Project Development Objectives. Components
Public Disclosure Authorized Public Disclosure Copy AFRICA Ghana Energy & Extractives Global Practice IBRD/IDA Specific Investment Loan FY 2008 Seq No: 17 ARCHIVED on 29-Jun-2017 ISR28824 Implementing
More informationPublic Disclosure Copy
Public Disclosure Authorized LATIN AMERICA AND CARIBBEAN Argentina Environment & Natural Resources Global Practice IBRD/IDA Adaptable Program Loan FY 2009 Seq No: 17 ARCHIVED on 29-Jun-2017 ISR27259 Implementing
More informationThe World Bank Emergency 2007 Cyclone Recovery and Restoration Project (P111272)
Public Disclosure Authorized SOUTH ASIA Bangladesh Social, Urban, Rural and Resilience Global Practice Global Practice IBRD/IDA Emergency Recovery Loan FY 2009 Seq No: 14 ARCHIVED on 31-Dec-2015 ISR21491
More informationMicroSmall&Medium Enterprise and Large Enterprise Supply Chain Finance (P157691)
EUROPE AND CENTRAL ASIA Turkey Finance, Competitiveness and Innovation Global Practice IBRD/IDA Investment Project Financing FY 2016 Seq No: 6 ARCHIVED on 26-Nov-2018 ISR34378 Implementing Agencies: Türkiye
More informationPublic Disclosure Copy. Implementation Status & Results Report Uganda Reproductive, Maternal and Child Health Services Improvement Project (P155186)
Public Disclosure Authorized AFRICA Uganda Health, Nutrition & Population Global Practice IBRD/IDA Investment Project Financing FY 2017 Seq No: 3 ARCHIVED on 20-Dec-2017 ISR30454 Implementing Agencies:
More informationThe World Bank Egypt National Railways Restructuring Project (P101103)
Public Disclosure Authorized MIDDLE EAST AND NORTH AFRICA Egypt, Arab Republic of Transport & Digital Development Global Practice IBRD/IDA Investment Project Financing FY 2009 Seq No: 21 ARCHIVED on 05-Jun-2018
More informationResults-Based Rural Water Supply and Sanitation Under the National Target Program (P127435)
Public Disclosure Authorized EAST ASIA AND PACIFIC Vietnam Water Global Practice Requesting Unit: EACVF Responsible Unit: GWA02 IBRD/IDA Program-for-Results Financing FY 2013 Team Leader(s): Lilian Pena
More informationThe World Bank Egypt National Railways Restructuring Project (P101103)
Public Disclosure Authorized MIDDLE EAST AND NORTH AFRICA Egypt, Arab Republic of Transport & ICT Global Practice IBRD/IDA Specific Investment Loan FY 2009 Seq No: 16 ARCHIVED on 12-Jan-2016 ISR22382 Implementing
More informationState Owned Financial Institutions Reform Project (P156837)
EUROPE AND CENTRAL ASIA Serbia Finance, Competitiveness and Innovation Global Practice IBRD/IDA Investment Project Financing FY 2018 Seq No: 2 ARCHIVED on 12-Dec-2018 ISR34752 Implementing Agencies: Republic
More informationMozambique -Roads and Bridges Management and Maintenance Program - Phase II (P083325)
AFRICA Mozambique Transport & ICT Global Practice IBRD/IDA Adaptable Program Loan FY 2007 Seq No: 22 APPROVED ISR29261 Implementing Agencies: Key Dates Key Project Dates Bank Approval Date:23-May-2007
More informationThe World Bank Egypt National Railways Restructuring Project (P101103)
Public Disclosure Authorized MIDDLE EAST AND NORTH AFRICA Egypt, Arab Republic of Transport & ICT Global Practice IBRD/IDA Specific Investment Loan FY 2009 Seq No: 19 ARCHIVED on 08-Jun-2017 ISR28299 Implementing
More informationThe World Bank Mozambique Public Financial Management for Results Program (P124615)
Public Disclosure Authorized AFRICA Mozambique Governance Global Practice IBRD/IDA Program-for-Results FY 2014 Seq No: 6 ARCHIVED on 29-Jun-2017 ISR28952 Implementing Agencies: Ministry of Economy and
More informationPublic Disclosure Copy
Public Disclosure Authorized AFRICA Burkina Faso Social Protection & Labor Global Practice IBRD/IDA Investment Project Financing FY 2014 Seq No: 10 ARCHIVED on 23-Dec-2017 ISR29874 Implementing Agencies:
More informationPublic Disclosure Copy
Public Disclosure Authorized AFRICA Ethiopia Finance & Markets Global Practice IBRD/IDA Investment Project Financing FY 2016 Seq No: 2 ARCHIVED on 18-Nov-2016 ISR25624 Implementing Agencies: National Bank
More informationPublic Disclosure Copy
Public Disclosure Authorized SOUTH ASIA India Governance Global Practice IBRD/IDA Investment Project Financing FY 2016 Seq No: 1 ARCHIVED on 06-May-2016 ISR23129 Implementing Agencies: Department of Public
More informationThe World Bank. Key Dates. Project Development Objectives. Components. Overall Ratings. Public Disclosure Authorized
Public Disclosure Authorized Public Disclosure Copy AFRICA Ethiopia Social Protection & Labor Global Practice IBRD/IDA Sector Investment and Maintenance Loan FY 2013 Seq No: 12 ARCHIVED on 09-Oct-2015
More informationPublic Disclosure Copy
Public Disclosure Authorized MIDDLE EAST AND NORTH AFRICA Morocco Energy and Mining Global Practice IBRD/IDA Specific Investment Loan FY 2008 Seq No: 12 ARCHIVED on 17-Jun-2015 ISR19641 Implementing Agencies:
More information