1 BUILDING CONDITION ASSESSMENT A Comprehensive Approach in Energy and Facility Management
2 Presentation Outline Page Nadine International Company Profile.. 3 FCI -Industry Preferred Formula FCI -Other Formula for the FCI Calculation. 5 Deferred Maintenance Deficiencies Defined... 6 Current Replacement Value Defined Why FCI?. 8 Strategic Asset Management & Capital Renewal Plan 9 Why BCA? Building Condition Assessment (BCA) 12 BCA Approach, Detailed and Intrusive Audit. 13 BCA Radio Frequency Identification Device (RFID) 14 BCA Approach, Detailed and Intrusive Audit 15 & 16 BCA Reports 17 Basic BCA Reports, Part I Life Cycle Cost Chart 18 Basic BCA Reports, Part II Annual Expenditures Chart 19 Basic BCA Reports, Part II Equipment Database 20 How BCA Provides Quality and Accuracy 21 & 22 Strategic Asset Management & Capital Renewal Plan. 23 Operations 24 Budgets and Funding. 24 Job Costing and Project Tracking 26 Work Orders Demand & Corrective. 27 Strategy. 28 Reserve Fund Planning 29 Risk Management. 31 Capital Renewal Needs 32 Planned Preventive Maintenance 34 Validation & Summary 36 Analysis. 37 Prioritizing Repairs/Replacement/Upgrades 38 Case Study ABC Long Term Care (LTC)
3 Nadine International Company Profile Multi-Discipline Consulting Engineering Firm ISO 9001 Certified A One Stop Shop for Engineering Services Registrations: - Association of Professional Engineers of Ontario - Consulting Engineers of Ontario - Consulting Engineers of Canada - Ministry of Municipal Affairs and Housing - Winner of 2008 Consulting Engineers of Ontario Award 3
4 FACILITY CONDITION INDEX (FCI) Industry Preferred Formula FCI = total cost of existing repairs or deferred maintenance (DM) current replacement value (CRV) X 100 Good Good Fair Poor... 5% 10% Greater than 10% 4
5 FACILITY CONDITION INDEX (FCI) Other Formula for the FCI Calculation FCI=(1 - Total Deficiencies Replacement Costs ) X 100 Good Good Fair Poor
6 Deferred Maintenance Deficiencies Defined The total dollar amount of existing major maintenance repairs and replacement, identified by a comprehensive Building Condition Assessment of building, grounds, fixed equipment, and infrastructure needs. It does not include projected maintenance and replacements, or other types of work, such as program improvements or new construction; these items are viewed, as separate capital needs. 6
7 Current Replacement Value Defined - Current Replacement Value (CRV) is defined as the total amount of expenditure in current dollars required to replace the asset - Meet the current acceptable standards of construction, and comply with regulatory requirements. - CRV is not the Insurance Replacement Value, Book Value, or the Market Value 7
8 Why FCI? Strategic Asset Management Tool Building / Facility Performance Indicator Useful tool for setting renewal priorities Useful tool for the allocation of funding and resources Benchmark to compare conditions of a group of facilities, or portfolio 8
9 Strategic Asset Management & Capital Renewal Plan Asset Management & Capital Renewal Plan FCI BCA Analysis Strategy Operations 9
10 Strategic Asset Management & Capital Renewal Plan Strategy ASSET ASSET MANAGEMENT MANAGEMENT & CAPITAL CAPITAL RENEWAL RENEWAL PLAN PLAN Operations Reserve Fund Planning Risk Management FACILITY FACILITY CONDITION CONDITION INDEX INDEX (FCI) (FCI) Budgets & Funding Capital Renewal Needs Planned PM ANALYSIS ANALYSIS Job Costing & Project Tracking Work Orders Validation & Summary BUILDING CONDITION ASSESSMENT BUILDING CONDITION ASSESSMENT 10
11 Why BCA? BCA is a comprehensive condition inspections, generally performed every three (3) years, and used to assess the performance of a system, subsystem or component. In addition to providing a detailed inventory, short/long term replacement strategies, and life cycle costs, Building Condition Assessment (BCA) provides a key data for Accurate Facility Condition Index (FCI) calculations, and energy savings. What do you own? What is it worth? What is its condition? What is the remaining service life? What are the project priorities? What is the deferred maintenance, repairs, replacements, and upgrades required? Is the asset energy efficient? 11
12 Building Condition Assessment (BCA) - BCA provides an accurate data for FCI Calculations - Establishes the baseline conditions for the building and its systems - Identifies, classifies and prioritizes building deficiencies - Recommends corrective action for each deficiency - Estimates cost for proposed corrective actions - Maintains building condition and cost data current - Identify and prioritize the necessary short and long term maintenance and repair requirements - Better allocation of the funding - Identifies areas of energy saving - Assessment performed by professional architects and engineers (with/or without RFID) 12
13 BCA Approach, Detailed and Intrusive Audit Preliminary Site Audit: - Review drawings and Annual Inspection Reports - Review existing documentation (Studies, Reports, etc.) - Interview Building Management Staff a) Interview Checklist b) Equipment History c) Performance d) Future Planning - Digital pictures - Install Radio Frequency Identification (RFID) tags (recommended) 13
14 BCA Radio Frequency Identification Device (RFID) RFID tagging will help reduce the FCI in the following ways: - Reduce the cost of future BCA - Improve Asset Management - Reduce operating/maintenance expenditures - Improve tracking of assets, asset condition, repairs and upgrades - Integration with Computerized Maintenance Managements Systems (CMMS) will provide better control over FCI across the portfolio - Improve the quality of the strategic decision making, due to the accurate and current data 14
15 BCA Approach, Detailed and Intrusive Audit Detailed Audit: - Visual Inspection of the entire building Intrusive Assessment: a) Review existing documentation b) Conduct Inspection as per Checklists c) Open the equipment panels d) Conduct performance tests e) Record actual condition of the equipment f) Take digital picture of the deficiencies g) Identify opportunities for improvements (Energy Efficiency, accessibility, Codes, etc.) 15
16 BCA Approach, Detailed and Intrusive Audit Intrusive Audit: - Conduct Inspections as per Checklists - Infrared Scanning of the Electrical Panels: a) Radiometer b) Graphic profile of the terminal c) Determine trouble spots - Generator Test: a) Generator run test - Chain Drag Test: a) Underground parking garage floor slab b) Damaged areas are identified and quantified 16
17 BCA Reports Projected annual/overall sustainment costs based on the condition of the facility Condition analysis spreadsheets Capital Planning Analysis spreadsheet Deferred Maintenance data Cash flow analysis Reserve fund analysis Individual Uniformat II component, and total portfolio reporting for user-defined periods Capability to relate actual work performed to projected budgets for each Uniformat II component, or by portfolio. 17
18 Basic BCA Reports Part I Life Cycle Cost Chart Uniformat Code Component Name Description Observations Recommendations Uniformat Categories Cost Allowance Service/Actual and Remaining Life Scope of Work Quantities/Units Rates Photos/Attachments Percentage of quantity scheduled Estimated future cost 18
19 Basic BCA Reports Part II Annual Expenditures Chart Uniformat Code Budget Cycles Annual Projections 19
20 Basic BCA Reports Part III Equipment Database Equipment Naming Convention Equipment Name Manufacturer s Name Service Life Equipment Location Installation Date Model/Serial # Capacity Power Supply 20
21 BCA How BCA Provides Quality and Accuracy Use comprehensive Checklists to ensure a thorough Assessment Interview appropriate Property Management Staff to gather information on: - Equipment History - Performance - Future Planning Conduct detailed intrusive Assessments by specialized professionals to obtain: - Accurate information for developing Scope of Work, and reliable business case Identify deficiencies with respect to applicable Codes, Standards, and Manufacturer s recommendations 21
22 BCA How BCA Provides Quality and Accuracy Analyze deficiencies and make sound Engineering recommendations Apply Good Engineering Practice Ensure proposed upgrades are in line with Client s Corporate Objectives 22
23 Strategic Asset Management & Capital Renewal Plan Strategy ASSET ASSET MANAGEMENT MANAGEMENT & CAPITAL CAPITAL RENEWAL RENEWAL PLAN PLAN Operations Reserve Fund Planning Risk Management FACILITY FACILITY CONDITION CONDITION INDEX INDEX (FCI) (FCI) Budgets & Funding Capital Renewal Needs Planned PM ANALYSIS ANALYSIS Job Costing & Project Tracking Work Orders Validation & Summary BUILDING CONDITION ASSESSMENT BUILDING CONDITION ASSESSMENT 23
24 OPERATIONS Budgets and Funding - Multiyear Capital Plan - Based on BCA or SWOT (Strength, Weakness, Opportunities and Threats) Analysis - Gap Analysis (Funding/Needs) - Long Term Service and Replacement Issues - Setting priorities from funding 24
25 Strategic Asset Management & Capital Renewal Plan Strategy ASSET ASSET MANAGEMENT MANAGEMENT & CAPITAL CAPITAL RENEWAL RENEWAL PLAN PLAN Operations Reserve Fund Planning Risk Management FACILITY FACILITY CONDITION CONDITION INDEX INDEX (FCI) (FCI) Budgets & Funding Capital Renewal Needs Planned PM ANALYSIS ANALYSIS Job Costing & Project Tracking Work Orders Validation & Summary BUILDING CONDITION ASSESSMENT BUILDING CONDITION ASSESSMENT 25
26 OPERATIONS Job Costing and Project Tracking - Based on accurate information from BCA - Class D Estimate - Includes Contingencies - Life Cycle Costs 26
27 Strategic Asset Management & Capital Renewal Plan Strategy ASSET ASSET MANAGEMENT MANAGEMENT & CAPITAL CAPITAL RENEWAL RENEWAL PLAN PLAN Operations Reserve Fund Planning Risk Management FACILITY FACILITY CONDITION CONDITION INDEX INDEX (FCI) (FCI) Budgets & Funding Capital Renewal Needs Planned PM ANALYSIS ANALYSIS Job Costing & Project Tracking Work Orders Validation & Summary BUILDING CONDITION ASSESSMENT BUILDING CONDITION ASSESSMENT 27
28 Strategic Asset Management & Capital Renewal Plan Strategy ASSET ASSET MANAGEMENT MANAGEMENT & CAPITAL CAPITAL RENEWAL RENEWAL PLAN PLAN Operations Reserve Fund Planning Risk Management FACILITY FACILITY CONDITION CONDITION INDEX INDEX (FCI) (FCI) Budgets & Funding Capital Renewal Needs Planned PM ANALYSIS ANALYSIS Job Costing & Project Tracking Work Orders Validation & Summary BUILDING CONDITION ASSESSMENT BUILDING CONDITION ASSESSMENT 28
29 STRATEGY Reserve Fund Planning - Have the management policies shortened the life of the building? - Have the unfunded liability been identified? - Are any parts of the building reaching, or have reached functional obsolescence? - Have the depreciated value of physical deterioration, and obsolescence been identified? - Has the quality of the original construction been assessed against life cycle and the gap identified? 29
30 Strategic Asset Management & Capital Renewal Plan Strategy ASSET ASSET MANAGEMENT MANAGEMENT & CAPITAL CAPITAL RENEWAL RENEWAL PLAN PLAN Operations Reserve Fund Planning Risk Management FACILITY FACILITY CONDITION CONDITION INDEX INDEX (FCI) (FCI) Budgets & Funding Capital Renewal Needs Planned PM ANALYSIS ANALYSIS Job Costing & Project Tracking Work Orders Validation & Summary BUILDING CONDITION ASSESSMENT BUILDING CONDITION ASSESSMENT 30
31 STRATEGY Risk Management - Is the present condition of the assets? a) Acceptable b) Below Standard c) Well below Standard d) Will likely fail imminently e) Has failed - What will happen if this asset Fails? a) No Risk b) Local Inconvenience c) Significant Inconvenience d) Critical or Life Safety - What would happen if the Repair is delayed? a) No Significance b) Reduction in efficiency c) Deterioration of the Asset d) Major deterioration of the Asset 31
32 Strategic Asset Management & Capital Renewal Plan Strategy ASSET ASSET MANAGEMENT MANAGEMENT & CAPITAL CAPITAL RENEWAL RENEWAL PLAN PLAN Operations Reserve Fund Planning Risk Management FACILITY FACILITY CONDITION CONDITION INDEX INDEX (FCI) (FCI) Budgets & Funding Capital Renewal Needs Planned PM ANALYSIS ANALYSIS Job Costing & Project Tracking Work Orders Validation & Summary BUILDING CONDITION ASSESSMENT BUILDING CONDITION ASSESSMENT 32
33 Strategic Asset Management & Capital Renewal Plan Strategy ASSET ASSET MANAGEMENT MANAGEMENT & CAPITAL CAPITAL RENEWAL RENEWAL PLAN PLAN Operations Reserve Fund Planning Risk Management FACILITY FACILITY CONDITION CONDITION INDEX INDEX (FCI) (FCI) Budgets & Funding Capital Renewal Needs Planned PM ANALYSIS ANALYSIS Job Costing & Project Tracking Work Orders Validation & Summary BUILDING CONDITION ASSESSMENT BUILDING CONDITION ASSESSMENT 33
34 STRATEGY Planned Preventive Maintenance Establish a reasonable set of Planned Preventive Maintenance procedures to keep the asset base to an acceptable level Develop an internal and external process to perform these tasks Evaluate the effects of the Preventive Maintenance Program 34
35 Strategic Asset Management & Capital Renewal Plan Strategy ASSET ASSET MANAGEMENT MANAGEMENT & CAPITAL CAPITAL RENEWAL RENEWAL PLAN PLAN Operations Reserve Fund Planning Risk Management FACILITY FACILITY CONDITION CONDITION INDEX INDEX (FCI) (FCI) Budgets & Funding Capital Renewal Needs Planned PM ANALYSIS ANALYSIS Job Costing & Project Tracking Work Orders Validation & Summary BUILDING CONDITION ASSESSMENT BUILDING CONDITION ASSESSMENT 35
36 STRATEGY Validation & Summary Are the Capital Projects, Planned Maintenance and Emergency Repairs keeping the Assets at the acceptable level? Is there a process to validate the BCA information, and the ongoing maintenance projects for the assets? 36
37 Strategic Asset Management & Capital Renewal Plan Strategy ASSET ASSET MANAGEMENT MANAGEMENT & CAPITAL CAPITAL RENEWAL RENEWAL PLAN PLAN Operations Reserve Fund Planning Risk Management FACILITY FACILITY CONDITION CONDITION INDEX INDEX (FCI) (FCI) Budgets & Funding Capital Renewal Needs Planned PM ANALYSIS ANALYSIS Job Costing & Project Tracking Work Orders Validation & Summary BUILDING CONDITION ASSESSMENT BUILDING CONDITION ASSESSMENT 37
38 ANALYSIS Prioritizing Repairs/Replacement/Upgrades Priority 1 Immediate Safety, Building Code, Accreditation Immediate/Critical: Priority 2: Short term deficiencies, correct within 1 to 2 years Potentially Critical: Priority 3: Long term deficiencies correct within 3 to 5 years Necessary / May become critical: Priority 4: Improvements required to improve the performance Potentially Critical: of the building and its systems Priority 5: New code requirements, to be addressed in any Current Code major renovation Compliance: 38
39 Strategic Asset Management & Capital Renewal Plan Strategy ASSET ASSET MANAGEMENT MANAGEMENT & CAPITAL CAPITAL RENEWAL RENEWAL PLAN PLAN Operations Reserve Fund Planning Risk Management FACILITY FACILITY CONDITION CONDITION INDEX INDEX (FCI) (FCI) Budgets & Funding Capital Renewal Needs Planned PM ANALYSIS ANALYSIS Job Costing & Project Tracking Work Orders Validation & Summary BUILDING CONDITION ASSESSMENT BUILDING CONDITION ASSESSMENT 39
40 FACILITY CONDITION INDEX (FCI) Case Study ABC LTC 40
41 FCI - Case Study ABC LTC Current Replacement Value (CRV) ABC LTC Building Type: 2 North Pole Avenue, Canada Long Term Care Centre with Face Brick & Concrete Block Back-up / Bearing Walls Floor Area (SM): 13,481 Gross Floor Area (SM): 11,352 Cost Per Square Meter: $3, Cost Per Square Foot: $ Building Cost: $42,773, Description Cost Per S.M. Cost A Substructure $ $1,430, BShell $ $7,882, C Interiors $ $6,927, D Services $1, $12,562, E Equipment & Furnishings $79.28 $900, Sub-Total $2, $29,703, Contractor Fees (General Conditions, Overhead, Profit) - 18% $ $5,346, Architectural, Engineering, Project Management, and Building Permit Fees - 15% $ $4,455, User Fees - 3% $78.50 $891, Contingency - 8% $ $2,376, CURRENT REPLACEMENT VALUE (CRV): $3, $42,773,
42 FCI - Case Study ABC LTC Current Replacement Value (CRV) A - Substructure 2 North Pole Avenue, Canada Building Type: Long Term Care Centre with Face Brick & Concrete Block Back-up / Bearing Walls Floor Area (SM): 13,481 Gross Floor Area (SM): 11,352 Cost Per Square Meter: $3, Cost Per Square Foot: $ Building Cost: $42,773, Description Cost Per S.M. Cost A Wall Foundations - General $25.77 $292, A Perimeter Drainage $6.30 $71, A Slab on Grade $53.48 $607, A Basement Excavation $10.71 $121, A Basement Walls $29.77 $338, A Substructure $ $1,430,
43 FCI - Case Study ABC LTC Current Replacement Value (CRV) B -Shell 2 North Pole Avenue, Canada Building Type: Long Term Care Centre with Face Brick & Concrete Block Back-up / Bearing Walls Floor Area (SM): 13,481 Gross Floor Area (SM): 11,352 Cost Per Square Meter: $3, Cost Per Square Foot: $ Building Cost: $42,773, Description Cost Per S.M. Cost B Floor Construction $ $1,654, B Roof Construction $ $1,909, B Exterior Walls $ $2,756, B Exterior Windows $59.66 $677, B Exterior Doors $10.36 $117, B Roof Coverings $66.42 $754, B Roof Openings $1.10 $12, BShell $ $7,882,
44 FCI - Case Study ABC LTC Current Replacement Value (CRV) C - Interiors 2 North Pole Avenue, Canada Building Type: Long Term Care Centre with Face Brick & Concrete Block Back-up / Bearing Walls Floor Area (SM): 13,481 Gross Floor Area (SM): 11,352 Cost Per Square Meter: $3, Cost Per Square Foot: $ Building Cost: $42,773, Description Cost Per S.M. Cost C Partitions $ $1,701, C Interior Doors $ $1,876, C Fittings $13.48 $153, C Stair Construction $33.69 $382, C Wall Finishes $77.42 $878, C Floor Finishes $87.76 $996, C Ceiling Finishes $82.66 $938, C Interiors $ $6,927,
45 FCI - Case Study ABC LTC Current Replacement Value (CRV) D - Services Description Cost Per S.M. Cost D Elevators and Lifts $43.00 $488, D Plumbing Fixtures $ $2,965, D Domestic Water Distribution $11.31 $128, D Sanitary Waste $6.17 $70, D Rain Water Drainage $6.17 $70, D Energy Supply $38.71 $439, D Heat Generating Systems $85.16 $966, D Cooling Generating Systems $ $2,197, D Distribution Systems $23.19 $263, D Terminal & Package Units $38.71 $439, D Controls & Instrumentation $7.74 $87, D Sprinklers $54.00 $613, D Standpipes $11.00 $124, D Electrical Service/Distribution $38.52 $437, D Lighting and Branch Wiring $ $1,968, D Communications and Security $ $1,145, D Other Electrical Systems $13.85 $157, D Services $1, $87,346,
46 FCI - Case Study ABC LTC Current Replacement Value (CRV) E Equipment & Furnishings Building Current Replacement Value (CRV) Estimate Name: ABC (Long Term Care Centre) 2 North Pole Avenue, Canada Building Type: Long Term Care Centre with Face Brick & Concrete Block Back-up / Bearing Walls Floor Area (SM): 13,481 Gross Floor Area (SM): 11,352 Cost Per Square Meter: $3, Cost Per Square Foot: $ Building Cost: $42,773, Description Cost Per S.M. Cost E Other Equipment $79.28 $900, E Equipment & Furnishings $79.28 $900,
47 FCI - Case Study ABC LTC Annual Estimated Expenditures/Total Cost of Existing Repairs UNIFORMAT CODE 2011 A -Substructure $ 117, B - Shell $ 340, C -Interiors $ 445, D- Services $ 522, E- Equipment & Furnishings $ 205, G- Site Work $ 573, H- General Requirements $ 160, Annual Estimated Expenditures / Total Cost of Existing Repairs $ 2,363,
48 FCI - Case Study ABC LTC FCI Calculations total cost of existing repairs current replacement value FCI = X 100 ABC LTC $ FCI = 2,363, $42,773, X 100 = 5.53% As per standard industry norms, the 5.53% is classified as a FAIR Facility Condition Index. 48
49 FCI - Case Study ABC LTC Graphical Presentation FCI poor 10% 5% 0% ABC LTC FCI = 5.53% fair good YEAR
50 FCI - Case Study ABC LTC Annual Estimated Expenditures from 2010 BCA ( ) UNIFORMAT CODE A -Substructure $ 117, $ - $ - $ - $ - B - Shell $ 340, $ - $ 340, $ - $ - C -Interiors $ 445, $ 59, $ 59, $ 161, $ 59, D- Services $ 522, $ 180, $ 205, $ 110, $ 487, E- Equipment & Furnishings $ 205, $ - $ - $ 7, $ - G- Site Work $ 573, $ - $ - $ - $ - H- General Requirements $ 160, $ - $ - $ 60, $ - Annual Estimated Expenditures $ 2,363, $ 239, $ 605, $ 338, $ 546,
51 FCI - Case Study ABC LTC Annual Estimated Expenditures from 2010 BCA ( ) UNIFORMAT CODE A -Substructure $ - $ - $ - $ - $ - B - Shell $ - $ - $ - $ - $ - C -Interiors $ 59, $ 155, $ 59, $ 59, $ 155, D- Services $ 1,491, $ - $ - $ 400, $ 60, E- Equipment & Furnishings $ 29, $ - $ - $ 30, $ - G- Site Work $ 189, $ - $ - $ - $ - H- General Requirements $ - $ - $ 60, $ - $ - Annual Estimated Expenditures $ 1,769, $ 155, $ 119, $ 489, $ 215,
52 FCI - Case Study ABC LTC Annual Estimated Expenditures from 2010 BCA Ten (10) Years Graphical Presentation $ 2,500,000 $2,363, $ 2,000,000 $1,769, $ 1,500,000 Ser ies1 Ser ies2 $ 1,000,000 $ 500,000 $605, $546, $338, $239, $489, $155, $215, $119, $
53 FCI - Case Study ABC LTC Funding Option I - Keep current FCI stable at 5.53% - The red line in the following chart assumes that there will be no spending in 2011 YEAR ESTIMATED EXPENDITURE FUNDING FCI 2011 $2,363, $ $239, $239, $605, $605, $338, $338, $546, $546, $1,769, $1,769, % 2017 $155, $155, $119, $119, $489, $489, $215, $215,
54 FCI - Case Study ABC LTC Funding Option I Graphical Presentation Current FCI 5.53% $2,500,000 $2,000,000 $1,500,000 $1,000,000 $500,000 $
55 FCI - Case Study ABC LTC Funding Option II - No funding in 2011, 2012, 2013, 2014, 2015, 2016, and The FCI increases to 14.07% in A funding of $6,018, in 2017, and $119, in 2018 will be required to reduce the FCI to 0.28% in 2018 YEAR Estimated Expenditure Funding 2011 $ 2,363, $ % Fair 2012 $ 239, $ % Fair 2013 $ 605, $ % Fair 2014 $ 338, $ % Fair 2015 $ 546, $ % Fair 2016 $ 1,769, $ % Poor 2017 $ 155, $ 6,018, % Poor 2018 $ 119, $ 119, % Good 2019 $ 489, $ % Good 2020 $ 215, $ % Good FCI 55
56 Thank you. 56
Backlog Reduction Plan
2003-2013 Executive Summary proposes to achieve reductions in our facilities maintenance backlog by documenting and completing backlog projects on a priority basis and by minimizing or eliminating future
More informationDeKalb Elementary School of the Arts at Terry Mills
DeKalb County School District/Elementary Schools DeKalb Elementary School of the Arts at Terry Mills Final School Assessment Report May 19, 2016 PARSONS School Assessment Report Table of Contents School
More informationRonald E. McNair Discovery Learning Academy
DeKalb County School District/Elementary Schools Ronald E. McNair Discovery Learning Academy Final School Assessment Report May 20, 2016 PARSONS School Assessment Report Table of Contents School Executive
More informationWilliam Bradley Bryant Center
DeKalb County School District/Education Other William Bradley Bryant Center Final School Assessment Report May 19, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 4 School
More informationRobert Shaw Theme Elementary
DeKalb County School District/Elementary Schools Robert Shaw Theme Elementary Final School Assessment Report May 20, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 4 School
More informationDeKalb County School District/Elementary Schools Dunwoody Elementary Final School Assessment Report May 19, 2016
DeKalb County School District/Elementary Schools Dunwoody Elementary Final School Assessment Report May 19, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 4 School Condition
More informationNC School District/430 Harnett County/Middle School Highland Middle Final Campus Assessment Report March 11, 2017
NC School District/430 Harnett County/Middle School Highland Middle Final Campus Assessment Report March 11, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary 5 Campus Dashboard
More informationDeKalb County School District/High Schools Druid Hills High Final School Assessment Report May 19, 2016
DeKalb County School District/High Schools Druid Hills High Final School Assessment Report May 19, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 5 School Condition Summary
More informationPleasantdale Elementary
DeKalb County School District/Elementary Schools Pleasantdale Elementary Final School Assessment Report May 20, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 5 School
More informationHarnett Central High
NC School District/430 Harnett County/High School Harnett Central High Final Campus Assessment Report March 11, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary 6 Campus
More informationAnson County Early College High
NC School District/040 Anson County/High School Anson County Early College High Final Campus Assessment Report March 11, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary
More informationSagamore Hills Elementary
DeKalb County School District/Elementary Schools Sagamore Hills Elementary Final School Assessment Report May 20, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 4 School
More informationStone Mountain Middle
DeKalb County School District/Middle Schools Stone Mountain Middle Final School Assessment Report May 20, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 4 School Condition
More informationLaurel Hill Elementary
NC School District/830 Scotland County/Elementary School Laurel Hill Elementary Final Campus Assessment Report March 11, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary
More informationBob Mathis Elementary
DeKalb County School District/Elementary Schools Bob Mathis Elementary Final School Assessment Report May 19, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 4 School Condition
More informationMountain Heritage High
NC School District/995 Yancey County/High School Mountain Heritage High Final Campus Assessment Report March 12, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary 7 Campus
More informationHarnett Central Middle
NC School District/430 Harnett County/Middle School Harnett Central Middle Final Campus Assessment Report March 11, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary 5 Campus
More informationPinebrook Elementary
NC School District/300 Davie County/Elementary School Pinebrook Elementary Final Campus Assessment Report March 10, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary 6 Campus
More informationDavie County Early College High
NC School District/300 Davie County/High School Davie County Early College High Final Campus Assessment Report March 10, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary
More informationCentral Davie Academy
NC School District/300 Davie County/High School Central Davie Academy Final Campus Assessment Report March 10, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary 4 Campus
More informationDeKalb County School District/Middle Schools Peachtree Middle Final School Assessment Report May 20, 2016
DeKalb County School District/Middle Schools Peachtree Middle Final School Assessment Report May 20, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 3 School Condition
More informationAnderson Creek Primary
NC School District/430 Harnett County/Elementary School Anderson Creek Primary Final Campus Assessment Report March 11, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary
More informationMartin Luther King Jr. High
DeKalb County School District/High Schools Martin Luther King Jr. High Final School Assessment Report May 19, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 4 School Condition
More informationDeKalb County School District/Middle Schools Chapel Hill Middle Final School Assessment Report May 20, 2016
DeKalb County School District/Middle Schools Chapel Hill Middle Final School Assessment Report May 20, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 3 School Condition
More informationNC School District/520 Jones County/Elementary School Trenton Elementary Final Campus Assessment Report March 11, 2017
NC School District/520 Jones County/Elementary School Trenton Elementary Final Campus Assessment Report March 11, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary 4 Campus
More informationNC School District/430 Harnett County/Elementary School Gentry Primary Final Campus Assessment Report March 11, 2017
NC School District/430 Harnett County/Elementary School Gentry Primary Final Campus Assessment Report March 11, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary 6 Campus
More informationLafayette Elementary
NC School District/430 Harnett County/Elementary School Lafayette Elementary Final Campus Assessment Report March 11, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary 5
More informationWilliam Ellis Middle
NC School District/300 Davie County/Middle School William Ellis Middle Final Campus Assessment Report March 10, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary 5 Campus
More informationBill Asdal. Asdal Builders, llc IBS Orlando
Bill Asdal Asdal Builders, llc Bill@asdalcompanies.com www.asdalbuilders.com IBS - 2007 - Orlando A Professional is. Someone who works ON their company not just in it. Setting the overview: Where is your
More informationIntegrating Green Building Measures into Capital Planning for HUD Assisted and Public Housing Programs
Building Bridges to Net Zero Integrating Green Building Measures into Capital Planning for HUD Assisted and Public Housing Programs Evolution of HUD's Green Capital Needs Assessment, and the new CNA etool
More informationFacility Condition Assessment Report. Coast Community College District
Facility Condition Assessment Report Coast Community College District February 28, 2003 Introduction To help document the need for funding the necessary replacement and upgrading of facilities within California
More informationEstimate Considerations. Estimate Considerations
Estimate Considerations Estimate Considerations Every estimate, whether it is generated in the conceptual phase of a project or at bidding time, must consider a number of issues Project Size Project Quality
More informationNC School District/430 Harnett County/Elementary School Coats Elementary Final Campus Assessment Report March 11, 2017
NC School District/430 Harnett County/Elementary School Coats Elementary Final Campus Assessment Report March 11, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary 5 Campus
More informationCAPITAL FUNDING SUMMARY
CAPITAL SUMMARY SCC (School Consolidation Capital ) CAPITAL : B19 -December 1, Specifically to address a school board s excess capacity : B11 -May 26, Opportunity to identify most urgent & pressing accommodations
More informationMocksville Elementary
NC School District/300 Davie County/Elementary School Mocksville Elementary Final Campus Assessment Report March 10, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary 5 Campus
More informationSubject: Capital Reserve Expenditure Guidelines. *incl. former OCHAP/CSHP Peel Access to Housing (PATH)
HIP Housing In Peel Subject: Capital Reserve Expenditure Guidelines Date: August 1, 2012 Applicable To The information contained in this document applies to the following: Municipal & Private Non- Federal
More informationCAPITAL RESERVE STUDY
CAPITAL RESERVE STUDY FOR THE HIALEAH CONDOMINIUM WILDWOOD CREST, NEW JERSEY Project Number: 12-1066 W:\2012\12-1066\CORR\12-1066v1.doc Date: March 29, 2013 Table of Contents Section Page Executive Summary...
More informationBody Corporate ten year maintenance plan example for South Africa
Body Corporate ten year maintenance plan example for South Africa Prepared by: Date: This plan covers the period of ten years from.. Building details & report inputs Supplied information Building name
More informationCAPITAL PROJECT PROCESS
CAPITAL PROJECT PROCESS May 2009 GETTING STARTED What is a project? A project is defined as all work (maintenance & repair or renovation) that requires 5,000 or more in time and materials and/or is sufficiently
More informationReserve Analysis Report
Reserve Analysis Report Parkway Towers 1155 Ash St Denver, CO 80220 Level I Study with Site Inspection Fiscal Year End Date: 12/31/2014 8597 Via Mallorca Suite E La Jolla, CA 92037 Phone: 858-764-1895
More informationReserve Studies Turnover Reports Insurance Appraisals
Reserve Studies Turnover Reports Insurance Appraisals Dear Board Members, Managers and Unit Owners, For twenty years we having been serving community associations throughout Florida and the Southeast United
More informationConstruction to Permanent Loan Forms
Construction to Permanent Loan Forms Table of Contents Form A - Builder Acceptance Checklist and Questionnaire Form completed by builder for Builder Acceptance by the Lender. Form B - Builder s Letter
More informationREQUEST FOR QUALIFICATIONS ARCHITECTURAL SERVICES FOR DOUGLAS CITY HALL RENOVATIONS DOUGLAS, WYOMING
REQUEST FOR QUALIFICATIONS ARCHITECTURAL SERVICES FOR DOUGLAS CITY HALL RENOVATIONS DOUGLAS, WYOMING Request for Qualifications (RFQ) due: 3:00pm local time, August 17, 2018 Page 1 of 8 Section One Introduction
More informationLilesville Elementary
NC School District/040 Anson County/Elementary School Lilesville Elementary Final Campus Assessment Report March 11, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary 4 Campus
More information2009/10 Capital Plan. Capital Plan Instructions
2009/10 Capital Plan Capital Plan Instructions January 2009 2009/10 CAPITAL PLAN - CAPITAL PLAN INSTRUCTIONS TABLE OF CONTENTS Part I - OVERVIEW 1. Introduction 1 2. Capital Funding 2 3. Capital Cost Drivers
More informationArizona Nevada Texas Utah New Mexico
Arizona Nevada Texas Utah New Mexico 9/12/2016 Summit Park HOA Regarding: Fiscal Year beginning 1/1/2017 Level II Capital Replacement Reserve Study We are pleased to submit this Level II Reserve Study
More information1 Integrated Planning & Public Works
1 Integrated Planning & Public Works STAFF REPORT Building Standards Title: Building Standards 2016 Fees and Charges Report Number: IPPW2015-111 Author: Lynn Balfour Meeting Type: Finance & Strategic Planning
More informationResidential Construction Guide.
Residential Construction Guide. for Builders and Mortgage Brokers MARCH 2018 British Columbia Brokerage #X022176 Alberta Brokerage #MW-1411086 ON Brokerage #12560 Admin #12500 page 3 construction guide
More informationDeveloper Project Guidelines
Developer Project Guidelines The Texas A&M University System Office of Facilities Planning and Construction November 04, 2015 Introduction The purpose of these guidelines is to explain the Office of Facilities
More informationReserve Fund Study Planning
Reserve Fund Study Planning What is a reserve fund and why is it important? The study evaluates the amount of money in the reserve fund to see it is sufficient to cover the repair and replacement of common
More informationThe Pillar Blueprint A FRAMEWORK FOR CONSTRUCTION FINANCING. Solution Based Lender
A FRAMEWORK FOR CONSTRUCTION FINANCING Solution Based Lender What is the Pillar Blueprint? The primary goal of the Pillar Blueprint is to provide competitive, flexible mortgages for those planning on building
More informationBUILDING CONDITION ASSESSMENTS EXECUTIVE SUMMARY
BUILDING CONDITION ASSESSMENTS EXECUTIVE SUMMARY for at Civic Centre 902 7 Avenue Canmore, Alberta Prepared for Dave Hubman Supervisor of Facilities CCIG Project No: T146434CA CCIG Contacts: Deirdre Roe,
More informationFacility Condition Assessment. Facility Condition Assessment 8/13/2013 AGENDA
AGENDA benefits & limitations Rod Moore, RA, LEED AP, PMP Georgia Tech Benjamin Dutton, FFB, MCIOB, MRICS Faithful+Gould GT Facilities GT Program What is GT FCA Deliverables How GT uses FCA Information
More informationREVIEW OF DEFERRED MAINTENANCE IN THE COMMONWEALTH FINAL REPORT DECEMBER 2005
REVIEW OF DEFERRED MAINTENANCE IN THE COMMONWEALTH FINAL REPORT DECEMBER 2005 EXECUTIVE SUMMARY The Commonwealth of Virginia has a $1.626 billion deferred maintenance backlog for 5,269 of the 10,449 buildings
More informationORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 2/15/2013 BUILDING SURVEY DATE
0807 3502 SOUTH FIRST STREET CHAMPAIGN, ILLINOIS SYSTEM CONDITION INDEX.771 PRIMARY BUILDING USE BUILDING SURVEY TEAM BUILDING SYSTEM REPLACEMENT COST $ 347,400 LABORATORY BUILDING GROSS SQUARE FEET 16,986
More informationAsset Management Plan
Asset Management Plan FACILITIES November 26, 2013 Asset Management Plan Introduction The Facility Asset Management Plan focuses on the major costs of maintaining or improving facilities for the next 30
More informationSummary of Depreciation Report. 888 Beach Avenue Strata Plan LMS 712 Halsall Project 213vA040A Vancouver, BC
G Summary of Depreciation Report 888 Beach Avenue Strata Plan LMS 712 Halsall Project 213vA040A Vancouver, BC Presented by Kevin Grasty, P.Eng., LEED AP Ed Watson, B.Sc.(Eng.) Halsall Associates November
More informationMASSHOUSING REPLACEMENT RESERVE DISBURSEMENT GUIDELINES
MASSHOUSING REPLACEMENT RESERVE DISBURSEMENT GUIDELINES The Replacement Reserve escrow account is generally used to fund the replacement of building components considered to be capital items as well as
More informationRESERVE FUND STUDY. Reserve Fund Study
RESERVE FUND STUDY Reserve Fund Study The reserve fund study for the condominium corporation is prepared in a format to be presented to the Condominium Corporation s Board of Directors or for use in delayed
More informationEducational & Performing Arts Center: Downriver Campus
Educational & Performing Arts Center: Total Estimated Project Construction Cost: $ 18.04 million Groundbreaking: September 2006 Percentage Completed: 100 percent Anticipated Completion Date: Completed
More informationWestmount Place Renovations Policy
Conditions Precedent to the Implementation of Renovations 1. Condominium Bylaws and Regulations No renovations or modifications shall be implemented without authorization of the Board of Directors. All
More informationReserve Fund Study My Condominium Plan
Reserve Fund Study My Condominium Plan 12 3456 Number of Units 36 Number of Buildings 1 Building Construction 21 Contact Ima Happy Position(s) President Contact Phone 43.555.4321 Report Date August 8,
More informationCITY OF FORT PIERCE BUILDING DEPARTMENT
CITY OF FORT PIERCE BUILDING DEPARTMENT APPLICATION FOR DETERMINATION OF SUBSTANTIAL IMPROVEMENT This is a request for determination by the City s Floodplain Administrator as to whether or not the project
More informationStatus: Structural steel installation complete at primary building. Observatory construction underway. Central Plant modifications are complete.
Page 1 of 11 FACILITIES PLAN STATUS REPORT June 22, 2015 SADDLEBACK COLLEGE 1. SCIENCES BUILDING Project Budget: $52,234,000 $8,308,000 $67,358,000 State Match: $36,564,000 ($36,564,000) - Basic Aid Allocation:
More informationBuilding Permit Fees
Permit Center 210 Lottie Street, Bellingham, WA 98225 Phone: (360) 778-8300 Fax: (360) 778-8301 TTY: (360) 778-8382 Email: permits@cob.org Web: www.cob.org/permits Building Permit Fees This handout includes
More informationREPLACEMENT RESERVE GUIDE
CANADA MORTGAGE AND HOUSING CORPORATION REPLACEMENT RESERVE GUIDE What is the Replacement Reserve? The replacement reserve is a fund kept by each housing sponsor under the terms of its operating agreement
More information- RS. D e sig n atio n
ALEXANDER LIU CAI - RS Reserve D e sig n atio n Specialist Sample Table Of HOA Contents Project Table of Contents Page Preface i Executive Summary 1 Membership Disclosure Summary 2 Disclosure Statement
More informationIntroduction to Capital Planning Management Systems
Introduction to Capital Planning Management Systems Scottish Healthcare Conference 2013 Michael Kwok, P.Eng. MBA Senior Vice President, Professional Services Ray Dufresne, AIA Vice President, Consulting
More informationFinal Report. Capital Plan Building Condition and Energy Assessments Khyber Building 1588 Barrington Street Halifax, Nova Scotia
Capital Management Engineering Limited EMPOWERING OUR CLIENTS WITH KNOWLEDGE 5531 Cornwallis Street, Halifax, NS, Canada B3K 1B3 Phone: 902 429 4412 Fax: 902 423 4945 Final Report Capital Plan Building
More informationWelcome to Northwest and congratulations on your decision to build a new home.
Welcome to Northwest and congratulations on your decision to build a new home. Let s Get Started Welcome to Northwest and congratulations on your decision to build your new home! Please take some time
More informationRestructuring of the Heritage Property Tax Rebate Program
STAFF REPORT ACTION REQUIRED Restructuring of the Heritage Property Tax Rebate Program Date: May 28, 2014 To: From: Wards: Reference Number: Toronto Preservation Board Planning and Growth Management Committee
More informationSocial Housing Administration Directive No
Regional Municipality of Halton Social Housing Administration Directive No. 06-05 Date: August 30, 06 To: Federally-Funded Social Housing Providers subject to Operating Agreements under Section 95 of the
More informationTown of Middleton Salt Storage Building Pioneer Road Pioneer Lands Town of Middleton Dane County, WI 53562
Town of Middleton Salt Storage Building Pioneer Road Pioneer Lands Town of Middleton Dane County, WI 53562 1 T100 PROJECT LOCATION MAP Scale: NTS N Revisions: No. Date: Description: Scale As Indicated
More informationRESERVE STUDY LEVEL I - Full Reserve Study. ABC Condominium Association, Inc.
Insurance Appraisals Reserve Studies Wind Mitigation RESERVE STUDY LEVEL I - Full Reserve Study Prepared for: ABC Condominium Association, Inc. For the period of January 1, 214 - December 31, 214 71 Enterprise
More informationRelease Date: January 3, 2019 Due Date: January 17, 2019
SAN JUAN SCHOOL DISTRICT REQUEST FOR BID CONSTRUCTION OF NEW BLUFF ELEMENTARY SCHOOL AND NEW MONTEZUMA CREEK ELEMENTARY GYM Release Date: January 3, 2019 Due Date: January 17, 2019 I. GENERAL A. Intent
More informationCottonwoods at Vine. Reserve Study. October 2012
Reserve Study October 2012 Tab Table of Contents Reserve Study Analysis Executive Summary... Remaining Useful Life Analysis... Reserve Study Schedule... Annual Expenditures... Funding Plan Summary... Percentage
More informationOur Focus: Your Future
Town of Fort Erie Infrastructure Services Our Focus: Your Future Prepared for Council-in-Committee Report No. IS-53-07 Agenda Date November 19, 2007 File No. 220102 Subject 5 YEAR FACILITY CONDITION STATUS
More informationNCAHMA Spring Underwriting Forum April 7-8, 2010 Physical Needs Assessments
NCAHMA Spring Underwriting Forum April 7-8, 2010 Physical Needs Assessments 1. What is a CNA? Presentation by: Thomas E. Fielder Phone: 859-276-0000 / tfielder@fieldergroup.com a) Comprehensive review
More informationFacility Condition Assessment Report 2010 Limited Scope Update
PARSONS Ferris State University Facility Condition Assessment Report 2010 Limited Scope Update April 25, 2011 Table of Contents Objectives and Approach... 1 Objectives... 3 Approach... 3 Summary of Findings...
More informationITEM 7 ESTIMATED INITIAL INVESTMENT. YOUR ESTIMATED INITIAL INVESTMENT FOR A SHOPPING MALL FOOD COURT LOCATION (Single Unit) Method of Payment
ITEM 7 ESTIMATED INITIAL INVESTMENT SHOPPING MALL FOOD COURT LOCATION (Single Unit) Initial Franchise Fee 1 $30,000 Lump Sum At Signing of Franchise Agreement Travel and Living Expenses While Training
More informationREPLACEMENT RESERVE REPORT FY 2016
REPLACEMENT RESERVE REPORT FY 2016 VILLAS AT PARKWOOD ESTATES VILLAS AT PARKWOOD ESTATES REPLACEMENT RESERVE REPORT FY 2016 Community Management by: Community Management Professionals, LLC Beth Maurer
More informationPrepared for: VILLAGE AT HIGHLANDS OWNERS ASSOCIATION CROZET, VA. Prepared by:
RESERVE FUND STUDY THE VILLAGE AT HIGHLANDS CROZET, VA 22932 Prepared for: VILLAGE AT HIGHLANDS OWNERS ASSOCIATION CROZET, VA C/O ASSOCIA COMMUNITY GROUP 1828 PAVILION CIRCLE CHARLOTTESVILLE, VA 22911
More informationBuilding Division Fees 2018
Building Division Fees 2018 Permit Administration A permit administration fee of $45.00 shall be assessed for each permit. Staff Consultation Fee $75.00 Administration Determination $90.00 / hour; $23.00
More informationTreetop Condos West Linn, Oregon Account 2015 On Site Update -- Version 1 October 07, 2014
West Linn, Oregon Account 2015 On Site Update -- Version 1 October 07, 2014 The Management Trust - Northwest P.O. Box 23099 Tigard, OR 97281 Phone: 503-670-8111 Toll Free: 877-852-8100 Fax: 503-670-0775
More informationKansas Home Inspectors Registration Board
Agency 130 Kansas Home Inspectors Registration Board Articles 130-1. REGISTRATION, RENEWAL, AND EXAMINATION. 130-2. FEES. 130-3. EDUCATION PROGRAMS. 130-4. CODE OF ETHICS AND STANDARDS OF PRACTICE. 130-5.
More informationLevel 3 Reserve Study without a Site a Site Visit Visit
Level 3 Reserve Study without a Site a Site Visit Visit We offer two types of reports for a Level 3 Reserve Study with a Site Visit, RS-3 - Standard Reserve Study without a site visit SMRS-3 - Statutory
More informationONTARIO RENOVATES
ONTARIO RENOVATES - 2018 INFORMATION SHEET The Ontario Renovates programs, Investment in Affordable Housing [IAH-E] and Social Infrastructure Fund [SIF], are Ministry of Housing (MHO) programs for low
More informationChapter. Acquisition of Leased Office Space
Chapter Acquisition of Leased Office Space All of the audit work in this chapter was conducted in accordance with the standards for assurance engagements set by the Canadian Institute of Chartered Accountants.
More information2014 Reserve Study. The Bear Creek Crossing Owner's Association, Inc. Bear Haven Way Sevierville, Tennessee Report No: 2921 Version 2
2014 Reserve Study The Bear Creek Crossing Owner's Association, Inc. Bear Haven Way Sevierville, Tennessee 37862 Report No: 2921 Version 2 For the Period From: January 1, 2014 To: December 31, 2014 TABLE
More informationFHA Renovation Loan Program, or 203K
FHA Renovation Loan Program, or 203K The Federal Housing Administration (FHA), which is part of the Department of Housing and Urban Development (HUD), administers various single family mortgage insurance
More informationResidential Permits R-2, R-3, R-4, and U Occupancies 2018 Building Permit Valuation/Fee Schedule
Residential Permits R-2, R-3, R-4, and U Occupancies 2018 Building Permit Valuation/Fee Schedule The base valuation to determine permit fees for residential buildings and additions are based on a dollar
More informationRESERVESTUDYUPDATE. The Villas at Blackberry Run Dallas, GA. Prepared for:
RESERVESTUDYUPDATE Dallas, GA Prepared for: THE VILLAS AT BLACKBERRY RUN HOME OWNERS ASSOCIATION, INC. Carl Swanson-President Prepared by: CRITERIUM-CARUSO ENGINEERS 1065 POWERS PLACE, SUITE B ALPHARETTA,
More informationRESERVE FUND STUDY. Hill & Associates Ltd. Member APEGNB July 2014
2014 RESERVE FUND STUDY Hill & Associates Ltd. Member APEGNB July 2014 Reserve Fund Study Prepared for Bobak Place Townhome Condominiums Prepared by Hill & Associates Ltd. Consulting Professional Engineers
More informationComprehensive Reserve Fund Study and Building Condition Assessment for Wellington Standard Condominium Corporation No. 149
Comprehensive Reserve Fund Study and Building Condition Assessment for Wellington Standard Condominium Corporation No. 149 820 Gartshore Street Fergus, Ontario Report Prepared for the Board of Directors
More informationSOMERSET CREEK STANDARD LEVEL 3 RESERVE STUDY UPDATE WITHOUT A SITE VISIT. With funding recommendations for the 2019 fiscal year
SOMERSET CREEK Bellevue, Washington STANDARD LEVEL 3 RESERVE STUDY UPDATE WITHOUT A SITE VISIT With funding recommendations for the 2019 fiscal year Issued April, 2018 Next Update: Level 2 by April, 2019
More informationUse of State and District Construction Funds
8 Use of State and District Construction Funds Through its long-range planning process, the district has met its facilities needs without issuing significant debt. To improve cost efficiency, however,
More informationQUICK GUIDE. An Introduction to COPE Data. Copyright 2017 AssetWorks Inc. All Rights Reserved. For more information visit,
QUICK GUIDE An Introduction to COPE Data An Introduction to COPE Data The collection of COPE data is important for organizations. It s four data categories construction, occupancy, protection, and exposure
More informationOntario Universities Facilities Condition Assessment Program
Ontario Universities Facilities Condition Assessment Program As of May 2014 Prepared by the Task Force of the Council of Senior Administrative Officers and the Ontario Association of Physical Plant Administrators
More informationSs. Francis & John Strategic Planning Committee
Ss. Francis & John Strategic Planning Committee Town Hall Meeting April 28, 2015 2 Agenda Update on Debt Reduction Update on One in Faith in Mission Expansion/Facilities Committee Report Questions Saint
More informationCOUNCIL ORDER No
SAFETY CODES COUNCIL #1000, 10665 Jasper Avenue N.W., Edmonton, Alberta, Canada, T5J 389 Tel: 780-413-0099 I 1-888-413-0099 Fax: 780-424-5134 I 1-888-424-5134 www.safetycodes.ab.ca COUNCIL ORDER No. 0015428
More information