Emergency Works Bespoke Application

Size: px
Start display at page:

Download "Emergency Works Bespoke Application"

Transcription

1 Appendix 2 A January 2018 P Murphy Senior Investment Advisor System Design and Delivery NZ Transport Agency Private Bag PALMERSTON NORTH 4442 Dear Paul Emergency Works Bespoke Application The Gisborne District Council (Council) wishes to apply for an emergency works - Bespoke application and asks that the Transport Agency considers the following: 1. The scope of the bespoke application to include Cyclones Debbie and Cook and the July 2017 rainfall event for a total of $9.1m. 2. The costs associated with repairs to the network are listed under One Network Roading Classifications and identified forestry routes below. Cyclones Debbie and Cook and July 2017 Event ONRC Category Total Identified Forestry Routes Alternative Route for SH2 Arterial $0 $0 $0 Primary Collector $240,000 $80,000 $0 Secondary Collector $2,138,647 $1,301,992 $454,000 Low Volume $3,299,271 $1,557,426 $0 Access $3,431,172 $664,000 $0 Total $9,109,090 $3,603,418 $454, Council seeks the following relief: 1) The repairs for roads leading to identified forests routes at 100% FAR to a total of $3,603,418. 2) The repairs for Tiniroto Road which is an alternative route when SH2 is closed at 100% FAR to a total of $454,000. 3) The remaining $5,051,672 would be at the enhanced FAR of 83%. 4) The bespoke agreement to commence at the date of the agreement for a period of two years. 5) To keep the scope of this application open until the end of this financial year 2017/18 to cover any future emergency events. PO Box 747 Gisborne 4040 New Zealand PHONE FAX gdc.govt.nz

2 2 Council has submitted an enhanced local road maintenance programme as part of the Draft Regional Land Transport Plan (RLTP) which includes an increased emergency works and local roads maintenance allocation. To fund the local share the impacts will be: To set rates take increases at 5% per annum for the first six years, reducing to 4% from the seventh year. To extend Council s historically low debt levels in line with debt levels of other councils to enable funding of critical activities and infrastructure. This indicates Council s long term financial commitment to supporting its future roading infrastructure needs but the bespoke application will address the immediate crisis. This investment will be viewed as value for money because deferring emergency works repairs until the next RLTP may see more of the network degrade at a faster rate and require a larger investment to reinstate it. This approach also provides a best for customer outcome. I would welcome meeting with you again to discuss this proposal and to present our submission to the Transport Agency. Please feel free to give me a call. For your information Council will also be making two other funding requests: cost scope adjustment to the Gisborne Regional Land Transport Plan an application to accelerate the transition of its revised FAR. I look forward to discussing this further. Yours sincerely Dave Hadfield General Manager Tairāwhiti Roads

3 1. BACKGROUND The Gisborne District Council (Council) seeks a bespoke arrangement for hardship reasons under the definition of a series of large events. The purpose of the request will minimise the impact of impending rate increases on the community and deliver safe roads for heavy transport users. Over the last 18 months the Gisborne District had four emergency works applications funded by the Transport Agency. A summary of the approved applications are funded below: $ 1) Gisborne rain event 8 July ,979,220 2) September ,980,952 3) Cyclones Debbie and Cook ,809,090 4) 21 September 2015 rain event 580,765 Total Approved $12,350,027 In July 2017, the district had another severe weather event causing damage to the value of $3.3m. The application will be submitted in February 2018 and if it is approved the total emergency work costs over the last two financial years would total $15.3m or specifically for 2017/18 to $10.1m. The 2017/18 emergency works total costs and potential Funding Assistance Rates (FAR) is tabled below. Activities FAR Total Cost Transport Agency September $835,321 $526,252 $309,069 Cyclones Debbie and Cook 63 $924,279 $582,296 $341,983 Cyclones Debbie and Cook 83 $4,884,811 $4,054,393 $830,488 Gisborne rain event 8 July $205,000 $170,150 $34,850 July 2017 Rainfall event 83 $3,300,000 $2,739,000 $561,000 Totals $10,149,411 $8,072,091 $2,077,320 Council has reached the point where it cannot afford its local share (even with the enhanced FAR) and has stopped further repair works. Council acknowledges this strategy has significant risk. With the impending winter more road closures are inevitable, levels of service will falter and stakeholders like the forestry industry will be severely impacted. President of the New Zealand Forest Owners Association Peter Clark said There is real concern in the forest industry that some roads will be closed because of their state, and that would be highly disruptive for everyone getting trees out of the forest. One of the recommendations of the latest NZ Transport Agency Investment Audit Report confirmed that some improvements are needed in how we manage the network. Council is following accepted practice in network management. However we are concerned that the increase in heavy vehicles associated with forestry operations will negatively impact the condition of the network and present a risk to the Agency s investment.

4 2 Forestry operations in the Gisborne region are expected to nearly double from 2.5 million tonnes to 4.5 million tonnes in the near future. The majority of this harvesting will begin on local roads before joining the state highway network en route to processing sites. Our field inspection found a number of low volume roads where traffic, especially heavy vehicles associated with forestry activities, had increased markedly to the point the pavements were in distress and presented a safety risk to users. Non-forestry roads, sealed and unsealed, were generally found to be in good condition. This is the rationale for the 100% FAR for identified forestry routes. Tiniroto Road is an alternative route when there are road closures on SH2 between Wairoa and Gisborne and that is why it is proposed that this also be funded at 100% FAR. The remaining emergency works were defined under the One Network Roading Classifications to provide benchmarking if the Transport Agency receives any future bespoke applications from other councils. The district also had an abnormal autumn/winter for March July 2017 that required additional maintenance requirements for the network, refer rainfall figures below. This removed Council s ability to reduce roading maintenance in other work categories to fund the emergency works repairs. Council has submitted an enhanced roading programme as part of the Draft Regional Land Transport Plan , which includes an increase in its emergency works allocation. Therefore, we are confident that we can manage an ongoing series of events in the future if this programme is adopted.

5 3 2. EMERGENCY WORKS EXPENDITURE BEYOND COUNCIL S ABILITY TO RAISE LOCAL SHARE 2.1 Operational Position Council s Assets & Infrastructure Committee considered Report Cyclones Debbie & Cook Emergency Works at its meeting on 30 November The report stated that the existing $2m budget for emergency works had been exhausted. Several options were provided to the Committee but the following option one was adopted. The following explains what Option one is: Staying within Council s existing 2017/18 budget where possible (current operational position). Due to the financial shortfall, all flood damage work has now placed on hold, tenders withdrawn and contractors decommissioned. The remaining storm damaged sites will either be cordoned off or have more permanent fencing installed to make them safe. Council will complete a total of $2.9m repairs this financial year but will then have to stop further repairs as it will not have enough local share to complete the work. The rate impact of the events is detailed below. Emergency Works Total Cost Transport Agency Totals $10,149,411 $8,072,091 $2,077,320 For the 2015/18 National Land Transport Programme, Council has rated the following: Year FAR Annual Budget Transport Agency 2017/18 63% $2,000,000 $1,260,000 $740,000 Even with the enhanced FAR this leaves Council with a deficit of $1,337,320 which is equivalent to a 2.05% rates rise for Gisborne District residents. To complete the 2016/17 emergency works repairs and with the enhanced FAR Council had a local share deficit of $732,388 for the emergency works category. (Details are provided in Appendix 1). 2.2 Hardship The rating provision of subsidised local roads and emergency reinstatement is tabled below: Rates Funding Source Categories of Rateable Land Weightings Capital Value Revenue (excl. GST) Millions Provision of Roads and Residential/lifestyle 1 $3,467,102 Footpaths Industrial and Commercial 2 $966,318 Horticulture and Pastoral 1.5 $2,479,099 Forestry 5 $1,042,255 Sub Total $7,954,774 Unformal Annual General Charge $1,776,226 Total $9,731,000

6 4 Using the current FAR, Council will require an additional $1,337,320 to complete the repair work. This represents an additional 13% of the total annual roading rates. (This excludes the local share deficit of $732,388 for 2016/17 financial year). This series of events is causing a different type of crisis. The emergency works roading deficits are ever increasing and therefore Council is unable to maintain levels of services for heavy transport users. Council s 2017/18 Annual Plan had the total rates of $54.4m plus GST ($62.5m), which covers both regional and territorial responsibilities. Emergency Total Rates Total Roading rates % Pre Event % Post % Increase in Works millions Event local share Totals $54.4 $9,731, The increases in local share required to reinstate the transport network as a percentage of the local authority revenue is 2.46%. This is similar to and ranges around 2.3% to 4% for previously approved bespoke applications for Whanganui, Rangitikei and South Taranaki District Councils. 3. LOCAL ROADS MAINTENANCE PROGRAMME Council submitted its final Draft Regional Land Transport Plan bid in December While not pre-empting the national moderation process, the bespoke criteria requires the estimated annual emergency works local share by applying the policy over the next three years relative to Council s local roads maintenance programme and its annual revenue. The information is supplied but conditional on the following: This does not pre-empt the outcomes of the Draft Regional Land Transport Plan and Draft Long Term Plan. Council will also be applying for an application to accelerate the transition of its revised FAR. 3.1 Proposed Emergency Works Allocations Council will be implementing several measures to rectify the emergency works and other network issues as part of the Draft Regional Land Transport Plan Council s Activity Management Plan (AMP) reflects the expenditure over the last three National Land Transport Programmes (NLTP).

7 5 Council will be seeking an increase from $2.0m to $3.0m per year to adjust expenditure levels with operational spends. The present and future allocations are tabled below. RLTP FAR Actual Emergency Works Allocations Transport Agency 2015/16 61% $2,000,000 $1,220,000 $780, /17 62% $2,000,000 $1,240,000 $760, /18 63% $2,000,000 $1,260,000 $740,000 Draft RLTP FAR Proposed Transport Agency 2021 Emergency Works Allocations 2018/19 64% $3,000,000 $1,920,000 $1,080, /20 65% $3,000,000 $1,950,000 $1,050, /21 66% $3,000,000 $1,980,000 $1,020, Proposed Local Roads Maintenance Allocations Council will be seeking an enhanced programme the details are tabled below: RLTP FAR Annual Budget Transport Agency 2015/16 61% $17,196,000 $10,489,560 $6,706, /17 62% $17,995,998 $11,157,518 $6,838, /18 63% $17,596,002 $11,085,481 $6,510,520

8 6 Draft RLTP FAR Annual Budget Transport Agency 2018/19 64% $25,529,000 $16,338,560 $9,190, /20 65% $25,772,000 $16,751,800 $9,020, /21 66% $25,513,000 $16,838,580 $8,674,420 The information shows the substantial future investment that Council (in partnership with the Transport Agency) is proposing to invest to meet the present and future needs of the network. 3.3 Existing and Future Gisborne District Council s 2017/18 Annual Plan had the total rates of $54.4m plus GST ($62.5m). The proposed rate take for 2019/20 will be $57m. This is subject to Long Term Plan (LTP) approval. 3.4 Financial Position and the Ability to Raise Rates At its meeting on 25 January 2018, Council considered Report Draft Financial Strategy for Consultation. This report outlines Council s financial vision for the next ten years and the impacts on rates, debt, levels of service and investments. Key recommendations in the strategy are to: focus Council expenditure firmly on critical infrastructure and services that are core Council activities set rates take increases to a maximum of 5% per annum for the first six years of the LTP, with the potential to reduce this to as low as 4% from the seventh year extend Council s historically low debt levels in line with debt levels of other councils to enable funding of critical activities and infrastructure

9 7 ensure that those who benefit from the services and infrastructure Council provides pay the costs associated with the provision of those services and infrastructure increase the focus on securing funding from alternative revenue streams (other than rates). The strategy shows that Council is seriously addressing its investment with its core activities (not just roading related) and is confident that we can manage an ongoing series of events if this programme is adopted. The bespoke application will enable Council to get through this recovery process until the LTP and NLT are adopted. Points of the Financial Strategy which are relevant to the bespoke application are: Roading Debt Levels and Emergency Events Council s opening debt leading into the LTP is higher than was forecasted. It is higher mostly due to unplanned roading expenditure that occurred in the financial year ending 30 June Roading overspends resulted in a $4.6m deficit in the roading activity, and as such have led to a higher opening debt position for Council. Over the course of the LTP, the operational overspend in 2016/17 will be rated to be paid back in the form of principal repayments made on internal loans. It is expected that Council will need to review its roading budget in particular and increase its bid to the Transport Agency to better provide for this in the coming years. The frequency of these weather events and the damage they cause is forecast to continue. Grant funding and alternative income streams thus become critical to help fund those projects that are not core infrastructure but still meet the needs of the community. Rates Affordability and Debt Given the demographic projections for Te Tairāwhiti, Council needs to be aware of the pressures on the community in terms of rates affordability. An ageing and working population, with largely static incomes, is not well placed to absorb significant rates increases. Over the last ten years Council has tried to keep rates increases to a minimum. Holding rates increases at 2% is not sustainable and will not help fund core infrastructure or maintain levels of services at current levels. A significant increase in core infrastructure costs and a tougher regulatory environment means it is vital that Council looks to other avenues to raise funds rather than through rates. Current projections suggest rates increases of 4.5% 6% pa plus growth is proposed for the LTP. Council needs to continue to operate within a fiscal envelope that meets our needs over the next ten years and matches the community s ability to pay. Social Deprivation Index The district scores highly on the social deprivation index. Income levels are below national medians, with a median household weekly income of $1,400 in 2017 for both Hawkes Bay and Gisborne combined, compared to $1,578 nationally. This highlights rates affordability as a particular concern and focus for Council.

10 8 Supporting Maori Economic Development Gisborne has the highest proportion of Māori of all regions, with 49% identifying as Māori in the 2013 census compared to 16% nationally. Key legislation governing Council s functions emphasise the significance of Māori cultural values in resource management and participation in decision-making. The district also has a high proportion of Māori land comprising approximately 18% of the district s land area, which continues to have its challenges in terms of productivity and development. Debt from unpaid rates on Māori land continues to be an issue even though we have a high uptake of landowners utilising whenua rahui and other support mechanisms. Council needs to continue to support the development of Māori land to help grow whanau and hapū, encourage economic growth and in turn help grow the Council s rates revenue base. 4. CONTINUE TO PROVIDE APPROPRIATE LEVELS OF SERVICE ON ITS NETWORK OVER THE NEXT THREE YEARS The inability to repair the network is causing considerable strain with stakeholders. The following is an extract from the Gisborne Herald dated August Roads Crisis Too Big For Us The forestry industry says the region s roading crisis is too big for Council and Tairāwhiti Roads to handle alone. A new report entitled Roads in Crisis prepared by Eastland Wood Council (EWC), in association with Federated Farmers, forestry owners and forestry management companies, calls for a joint approach to improving the roads and suggests the Government should be approached to take charge. The region s roads have become a problem that exceeds the role and responsibility of Tairāwhiti Roads and Gisborne District Council to make change. It is paramount that others step in to assist the process, the report says. It points out that forestry, trucking and farming operations are all affected by the region s poor roads. This is a major regional and national problem that requires the council, Tairawhiti Roads, and the forestry and farming sectors, along with central government, to start the process of solving this with appropriate collaboration of stakeholders. EWC chief executive Prue Younger said it was important to note that the report was not about throwing stones but about recognising the scale and urgency of the problem. We want to collaborate to find the solutions and work as a region to support an approach to central government to make that change to the process. Ms Younger said it was now time to act and for the industry to drive a collaborative approach to change the roading crisis. A successful bespoke application will assist the recovery process with stakeholders.

11 9 4.2 Further Mitigation Measures During the 2016/17 financial year the Council could have closed roads (leading to forests) using its existing Traffic and Parking Bylaw but our legal and consultation processes with stakeholders were not ready at the time. Council s Assets & Infrastructure Services Committee has asked staff to reconsider this option leading to the 2018 winter season as a tool to ensure budgets are kept to the NLTP allocations. President of the New Zealand Forest Owners Association Peter Clark said There is real concern in the forest industry that some roads will be closed because of their state, and that would be highly disruptive for everyone getting trees out of the forest. We intend to report back to the Assets & Infrastructure Committee in March 2018 to determine if this option can be implemented. 5. INTERVENTION HIERARCHY 5.1 Local Roads Maintenance Allocation The hierarchy encourages that reinstatement and maintenance activities should take priority over improvements. These series of events combined with an abnormal 2017/18 winter and high export prices for logs has placed pressure on the unsealed network. Council s objective is to meet its 2017/18 local roads maintenance allocation of $17.59m as any increase has local share consequences. One of the recommendations of the latest Investment Audit Report confirmed that some improvements are needed in how we manage the network. Council is following accepted practice in network management. However we are concerned that the increase in heavy vehicles associated with forestry operations will negatively impact the condition of the network and present a risk to the Agency s investment. Forestry operations in the Gisborne region are expected to nearly double from 2.5 million tonnes to 4.5 million tonnes in the near future. The majority of this harvesting will begin on local roads before joining the state highway network on route to processing sites. Our field inspection found a number of low volume roads where traffic, especially heavy vehicles associated with forestry activities, had increased markedly to the point the pavements were in distress and presented a safety risk to users. Non forestry roads, sealed and unsealed, were generally found to be in good condition. Therefore the ability to reduce local maintenance roads expenditure to offset additional emergency works is limited. There is very little risk to the Transport Agency that Council would implement a limited pull back on maintenance if a bespoke agreement is granted. There is a strong demand from stakeholders to ensure minimum levels of service are maintained (refer to Section 4 Appropriate Levels of Service).

12 Capital versus Operational Costs The Gisborne NLTP has several improvements for 2017/18 in progress. WC Activity Total Cost Progress 324 HPMV bridge strengthening $260,000 Tenders closed construction to proceed in February required for continued forestry harvests. 324 Streetlight upgrade to LED $300,000 Project 80% complete. 341 Minor Improvements $1,200,792 Projects at different construction phases but under way. 357 Resilience Improvements $540,000 Projects 50% complete, required to alleviate future emergency works 452 Walking and Cycling Improvements $2,274,778 Design phase underway, driver is the Crown funds of $355k have to be spent this financial. Part of project will be delivered in 2018/19. Total $5,779,762 The improvements are essential for the: heavy transport industry to maintain momentum gaining electricity savings to lower ongoing maintenance costs reduce our increasing deaths and serious accidents on the network alleviate the scale of future emergency works applications Crown funds for walking and cycling projects have to be allocated this financial. The deferring of improvements to pay for operational activities (like emergency works) is not straightforward as one activity may be funded through loans, the other depreciation. Unfortunately they are not transferable. 6. TIME FRAME AND PROGRAMMING As discussed previously all works have been placed on hold and sites made safe with the appropriate traffic management in place. This strategy can suffice in the short term but during another emergency event more damage can occur further increasing the repair value. The high risk sites as determined by the maintenance network team have been made safe. The regulatory environment has become tougher. Council released its Proposed Gisborne Regional Freshwater Plan in Emergency works repairs that were permitted now require a resource consent. For the 2017/18 emergency event we now require 36 resource consents to complete works near waterways and/or in land overlays which are susceptible to erosion. Though we have put on hold on any further works, we are still processing the consents for these sites. Staff are applying for a global consent for any future emergency events but it does put further delays to implementing repairs so our preference is that the bespoke agreement date start at the date of the agreement.

13 11 Under the current policy the enhanced FAR stop at the end of the corresponding financial year. Our bespoke application would ask that this continue as part of any successful agreement to allow for the large number of repairs to complete balanced against available resources. 7. SHORT TERM ENHANCED EMERGENCY WORKS FAR The policy allows for front-loading arrangements with Council s local share likely to be delayed and spread over an extended period. Council s preference is not to adopt this option as we still have to manage future emergency events under the existing policy. A frontloading arrangement could see Council having to find the local share to pay its share of the arrangement plus fund subsequent repairs. Council has submitted an enhanced local roads maintenance and improvement programme as part of the Draft RLTP and if successful will assist the recovery process. Our preference is for a short term enhanced emergency works FAR over a two year period. 8. INTEGRATED TRANSPORT PRIORITY PLAN (ITPP) AND STATE HIGHWAY BUSINESS CASES Council would like to acknowledge the effort the Transport Agency staff have invested in these planning documents. There is a risk that this short term relief package may be dismissed as long-term remedies will be included in these documents. The planning documents may be completed within two years, the actual physical delivery of works is still uncertain.

14 APPENDIX /17 YEAR - EMERGENCY WORKS FINANCIALS Event FAR Total Cost Transport Agency Council Rates Total Claim to Date September $3,980,952 $3,264,381 $716,571 $3,145,631 Gisborne Region Rain Event 8 July 2016 Gisborne Region Rain Event 8 July 2016 Rain event of 21 September $595,385 $488,216 $107,169 $595, $1,178,835 $730,878 $447,957 $1,178, $580,765 $360,074 $220,691 $580,765 Total Emergency Works $6,335,937 $4,843,549 $1,492,388 $5,500,616 For the 2015/18 National Land Transport Programme, Council rated the following: Year FAR Annual Budget Transport Agency 2016/17 62% $2,000,000 $1,240,000 $760,000 Even with the enhanced FAR Council had a local share deficit of $732,388 for emergency works category which it had to pay as part of the 2016/17 roading overspend. This is equivalent to a 1.1% rates rise for Gisborne District residents.

Roading and Footpaths Group

Roading and Footpaths Group Roading and Footpaths Group Roading Council maintains and manages the local roading network including roads, street lighting and signage. Community Outcome A Safe and Healthy District Roading contributes

More information

Financial Strategy. What is Council s financial strategy?

Financial Strategy. What is Council s financial strategy? Financial Strategy Having a financial strategy is one of the key tools to the Council achieving its vision for the future. It is a new requirement under the amendments to the Local Government Act 2002.

More information

TŌ TĀTOU ROHE ME TE ANGA WHAKAMUA OUR DISTRICT OUR DIRECTION

TŌ TĀTOU ROHE ME TE ANGA WHAKAMUA OUR DISTRICT OUR DIRECTION TŌ TĀTOU ROHE ME TE ANGA WHAKAMUA OUR DISTRICT OUR DIRECTION Our District 28 Our District We are a region of firsts locally, nationally and globally. The Gisborne District (which is also a region) covers

More information

Section 4c. Our services: Land transport

Section 4c. Our services: Land transport Section 4c Our services: Land transport Land transport LAND TRANSPORT Local roads and footpaths Bridges Road safety Amenities Contribution to public transport Cycle ways Our land transport activity is

More information

Significant Forecasting Assumptions

Significant Forecasting Assumptions Summary of s The following general and financial s are assumed for the life of this Long Term Plan (2018-28). Level Consequence General s 1 Population Change Medium Low Minor 2 Household Change Medium

More information

EXPLAINED. Your Rates

EXPLAINED. Your Rates Your Rates EXPLAINED 2018-2019 The Horizons Region extends over 22,200km2 - from Ruapehu in the north and Horowhenua in the south, to Whanganui in the west and Tararua in the east, and has a population

More information

Significant Forecasting Assumptions

Significant Forecasting Assumptions Significant Forecasting Assumptions Council has made the following significant assumptions in preparing the Ashburton District Council Long Term Plan 2015-2025. Most of these assumptions have been identified

More information

20. FUNDING SOURCES AND FINANCIAL FORECASTS

20. FUNDING SOURCES AND FINANCIAL FORECASTS 20. FUNDING SOURCES AND FINANCIAL FORECASTS 20.1 FUNDING SOURCES This section provides forecasts of anticipated revenue and expenditure for the next 10 years. The main sources of funds for land transport

More information

State Highway Annual Plan Instructions Manual. 1. Purpose. 2. Document Information. 3. Amendment and Review Strategy. 4.

State Highway Annual Plan Instructions Manual. 1. Purpose. 2. Document Information. 3. Amendment and Review Strategy. 4. System Design and Delivery Date of Issue: July 2018 State Highway Annual Plan Instructions Manual Manual Owner: Sponsor Endorsement: Principal Asset Management Advisor Liane Powell (Operational Policy,

More information

POPULATION GROWTH. Steady and moderate growth of 1.7% a year to 2018, slowing to 0.6% a year out to 2048 MITGATING FACTORS (IF APPLICABLE)

POPULATION GROWTH. Steady and moderate growth of 1.7% a year to 2018, slowing to 0.6% a year out to 2048 MITGATING FACTORS (IF APPLICABLE) POPULATION GROWTH Steady and moderate growth of 1.7% a year to 2018, slowing to 0.6% a year out to 2048 ALTERNATIVES IMPACT LIKELIHOOD OVERALL RISK REASONS AND FINANCIAL EFFECT That the population growth

More information

Government Policy Statement on land transport 2018 release for public engagement

Government Policy Statement on land transport 2018 release for public engagement In Confidence Office of the Minister of Transport Chair, Cabinet Economic Development Committee Government Policy Statement on land transport 2018 release for public engagement Proposal 1. This paper seeks

More information

Development Contributions Policy 2018: Springvale Urban Expansion Area and Otamatea West

Development Contributions Policy 2018: Springvale Urban Expansion Area and Otamatea West Development Contributions Policy 2018: Urban Expansion Area and West 1 P a g e Development Contributions Policy 2018: Urban Expansion Area and West Originator: Damien Wood, Development Engineer Contact

More information

33. Government financial support to local authorities

33. Government financial support to local authorities 33. Government financial support to local authorities Summary Specific government financial support to local authorities during or after an emergency is based on a range of mandates, criteria, and triggers,

More information

Regulatory Impact Analysis: Cost Recovery Impact Statement - Overview of Required Information 1

Regulatory Impact Analysis: Cost Recovery Impact Statement - Overview of Required Information 1 ACC Levies for 2019/20 and 2020/21 Cost Recovery Impact Statement Agency Disclosure Statement This Cost Recovery Impact Statement has been prepared by the Ministry of Business, Innovation and Employment.

More information

2018 Long Term Plan Financial forecasting assumptions

2018 Long Term Plan Financial forecasting assumptions 2018 Long Term Plan Financial forecasting assumptions Forecasting assumption Risk Likelihood of occurrence Projected price change factors Forecast financial information That actual price changes vary Medium

More information

Financial information

Financial information Financial information 135 Significant forecasting assumptions and risks Greater Wellington Draft Long-Term Plan 2012-22 These prospective financial statements were authorised for issue by the Council on

More information

NATIONAL LAND TRANSPORT PROGRAMME / INformation sheet / october 2012

NATIONAL LAND TRANSPORT PROGRAMME / INformation sheet / october 2012 NATIONAL LAND TRANSPORT PROGRAMME 2012 15 / INformation sheet / october 2012 Creating transport solutions for a thriving New Zealand The NZ Transport Agency Board has adopted the 2012 15 National Land

More information

DRAFT STRATEGIC ENVIRONMENTAL ASSESSMENT SCREENING REPORT. Climate Change Sectoral Adaptation Plan for Flood Risk Management ( )

DRAFT STRATEGIC ENVIRONMENTAL ASSESSMENT SCREENING REPORT. Climate Change Sectoral Adaptation Plan for Flood Risk Management ( ) Office of Public Works DRAFT STRATEGIC ENVIRONMENTAL ASSESSMENT SCREENING REPORT Climate Change Sectoral Adaptation Plan for Flood Risk Management (2014-2019) Determination of the need for strategic environmental

More information

Keeping. on track K E E P I N G O N T R A C K K E Y I S S U E S : C O N S U L T A T I O N D O C U M E N T. Key issues

Keeping. on track K E E P I N G O N T R A C K K E Y I S S U E S : C O N S U L T A T I O N D O C U M E N T. Key issues LONG TERM PLAN 2018-2028 Keeping K E E P I N G on track C O N S U L T A T I O N D O C U M E N T O N T R A C K Long Consultation Term Plan Document 2018-2028 K E Y I S S U E S : Earthquake debt Earthquake-prone

More information

Pre-Election Report. July 2016 Clare Hadley, Chief Executive

Pre-Election Report. July 2016 Clare Hadley, Chief Executive Pre-Election Report July 2016 Clare Hadley, Chief Executive This document constitutes the pre-election report for the purposes of Section 99A of the Local Government Act 2002 Contents Contents... 2 Introduction...

More information

Southland District Council. Pre-Election Report

Southland District Council. Pre-Election Report Southland District Council Pre-Election Report Chief Executive s Introduction Welcome to Southland District Council s first Pre-Election Report. The purpose of this report is to provide information to

More information

RE: PROPOSED MANAWATU DISTRICT PLAN CHANGE 55 HEARINGS

RE: PROPOSED MANAWATU DISTRICT PLAN CHANGE 55 HEARINGS 30 November 2016 File: 13/134 DDI: 09 917 4305 Email: kblair@burtonconsultants.co.nz Manawatu District Council Private Bag 10 001 FEILDING 4743 Attention: Hearing Committee: Plan Change 55 By email only:

More information

CORPORATE ASSUMPTIONS

CORPORATE ASSUMPTIONS of Minor and short term population changes have minimal impact on Council. Usually Resident Population (URP) of the district will continue to decline at a rate of approximately 0.02% per annum. (Source:

More information

Section D: Financial Information

Section D: Financial Information The Shearer Statue Section D: Financial Information This section provides the Financial Strategy, details on the financial implications of the Plan, including estimated expenditure, revenue and public

More information

Significant forecasting assumptions LTP 2018 V2 12 February 2018

Significant forecasting assumptions LTP 2018 V2 12 February 2018 Significant forecasting assumptions LTP 2018 V2 12 February 2018 Introduction In preparing forecasts, both financial and non-financial, there is a need to provide assumptions to address the uncertainties

More information

SUSTAINABLE LAND USE INITIATIVE (SLUI)

SUSTAINABLE LAND USE INITIATIVE (SLUI) Report No. 17-125 Information Only - No Decision Required SUSTAINABLE LAND USE INITIATIVE (SLUI) 1. PURPOSE 1.1. This report is to update Members about progress on Council s Sustainable Land Use Initiative

More information

Significant Forecasting Assumptions

Significant Forecasting Assumptions Significant Forecasting Assumptions In preparing this Long Term Plan it was necessary for Council to make a number of assumptions about the future. The following tables identify those forecasting assumptions

More information

AGE ACTION IRELAND STRATEGIC PLAN

AGE ACTION IRELAND STRATEGIC PLAN AGE ACTION IRELAND STRATEGIC PLAN 2016-2018 FEBRUARY 2016 Contents Introduction... 3 Our Vision... 4 Our Mission... 4 Our Core Values... 5 Achievements... 6 Development of the 2016-2018 Strategic Plan...

More information

RIMS Risk Guide Implementation

RIMS Risk Guide Implementation Case Study RIMS Risk Guide Implementation Initiative number 2014_06 May 2014 Version No Date Item Affected Description of Change 1 11/04/14 All Document Created 2 17/06/14 All Final Executive Summary The

More information

Report to COUNCIL for noting

Report to COUNCIL for noting 15/362 Subject: Chief Executive s Activity Report: September 2015 Prepared by: Judy Campbell (Chief Executive) Meeting Date: 8 October 2015 Report to COUNCIL for noting SUMMARY Attached is my report for

More information

Aurora Energy Limited

Aurora Energy Limited Aurora Energy Limited Statement of Intent for the year ending 30 June 2016 CONTENTS Page 1 INTRODUCTION... 1 2 STRATEGIC DIRECTION... 1 2.1 Vision... 1 2.2 Mission... 1 2.3 Corporate Goals... 1 2.4 Specific

More information

WELLINGTON CITY COUNCIL POLICY ON UNDERGROUNDING OF OVERHEAD CABLES

WELLINGTON CITY COUNCIL POLICY ON UNDERGROUNDING OF OVERHEAD CABLES WELLINGTON CITY COUNCIL POLICY ON UNDERGROUNDING OF OVERHEAD CABLES CONTENTS Foreword 3 Summary of Council Policy 3 Introduction 5 Definitions 5 Policy Objectives 5 Undergrounding Principles 5 Cost and

More information

Harden Contributions Plan for Heavy Haulage Developments. Adopted by Council Resolution No. 277/11/11 16 th November, Prepared by.

Harden Contributions Plan for Heavy Haulage Developments. Adopted by Council Resolution No. 277/11/11 16 th November, Prepared by. Harden Contributions Plan for Heavy Haulage Developments Adopted by Council Resolution No. 277/11/11 16 th November, 2011 Prepared by newplan Urban Planning Solutions ABN 16 113 272 705 Member of the Planning

More information

Financial Strategy Rautaki Pūtea

Financial Strategy Rautaki Pūtea FOR CONSULTATION Financial Strategy Rautaki Pūtea SUPPORTING THE LONG TERM PLAN 2018-28 CONSULTATION DOCUMENT Financial Strategy Note: The information in this strategy has been drafted to support the proposed

More information

RESPONSIBLE MINISTER FOR MINISTRY OF TRANSPORT: Minister of Transport

RESPONSIBLE MINISTER FOR MINISTRY OF TRANSPORT: Minister of Transport Vote Transport APPROPRIATION MINISTER(S): Minister of Transport (M72) APPROPRIATION ADMINISTRATOR: Ministry of Transport RESPONSIBLE MINISTER FOR MINISTRY OF TRANSPORT: Minister of Transport THE ESTIMATES

More information

Auckland Transport Alignment Project. Revenue and Expenditure Report

Auckland Transport Alignment Project. Revenue and Expenditure Report Auckland Transport Alignment Project Revenue and Expenditure Report Contents 1. Introduction... 3 2. Approach... 3 3. Expenditure... 5 3.1. Historic transport expenditure 2001-2015... 5 3.2. Expenditure

More information

Strategic Performance Framework

Strategic Performance Framework Strategic Performance Framework Overview The strategic performance framework is a list of Key Performance Indicators (KPIs), which enable the Council to report how successful it has been in delivering

More information

HAVE YOUR SAY CONSULTATION DOCUMENT ON THE ANNUAL PLAN CARTERTON DISTRICT COUNCIL ISSN

HAVE YOUR SAY CONSULTATION DOCUMENT ON THE ANNUAL PLAN CARTERTON DISTRICT COUNCIL ISSN CONSULTATION DOCUMENT HAVE YOUR SAY ON THE ANNUAL PLAN 2017-2018 CARTERTON DISTRICT COUNCIL ISSN 1171 7459 FROM HIS WORSHIP THE MAYOR The biggest issue facing us now is finding a way to eventually discharge

More information

Financial Strategy. Forecast Revenue. Rates revenue

Financial Strategy. Forecast Revenue. Rates revenue Financial Strategy Council has adopted a set of funding and financial policies to provide predictability and certainty about sources and levels of funding. The Council intends to manage its financial dealings

More information

Managing the Impact of Weather & Natural Hazards. Council Best Practice natural hazard preparedness

Managing the Impact of Weather & Natural Hazards. Council Best Practice natural hazard preparedness Managing the Impact of Weather & Natural Hazards Council Best Practice natural hazard preparedness The Impact of Natural Hazards on Local Government Every year, many Australian communities suffer the impact

More information

14 March 2017 Corporate Report Format

14 March 2017 Corporate Report Format 14 March 2017 Corporate Report Format To the Chair and Members of Cabinet APPROVAL TO ENTER INTO A FUNDING AGREEMENT WITH SHEFFIELD CITY REGION TO BE ABLE DRAW DOWN SCRIF APPROVED FUNDING FOR THE DELIVERY

More information

achieving results in the public sector Kāpiti Coast District Council Financial Investigation of a Kāpiti Coast Unitary April 2013

achieving results in the public sector Kāpiti Coast District Council Financial Investigation of a Kāpiti Coast Unitary April 2013 AUCKLAND SYDNEY BRISBANE PERTH Kāpiti Coast District Council Financial Investigation of a Kāpiti Coast Unitary achieving results in the public sector TABLE OF CONTENTS 1. INTRODUCTION... 1 2. METHODOLOGY...

More information

ASSESSMENT REPORT FOR ANNUAL PLAN 17/18 DIFFERENCES FROM YEAR 3 OF THE LTP

ASSESSMENT REPORT FOR ANNUAL PLAN 17/18 DIFFERENCES FROM YEAR 3 OF THE LTP ASSESSMENT REPORT FOR ANNUAL PLAN 17/18 DIFFERENCES FROM YEAR 3 OF THE LTP 2015-25 SIGNIFICANT OR MATERIAL? In order to determine if consultation is required on the Annual Plan 2017/18 Council must assess

More information

Christchurch City Council Draft Annual Plan 2016/17 and Proposed Amendments to the Long-term Plan (Draft) Council Consideration Draft

Christchurch City Council Draft Annual Plan 2016/17 and Proposed Amendments to the Long-term Plan (Draft) Council Consideration Draft Christchurch City Council Draft Annual 2016/17 and Proposed Amendments to the Long-term 2015-2025 (Draft) Council Consideration Draft Please note: This document contains the Council consideration draft

More information

Report to COUNCIL Workshop for discussion

Report to COUNCIL Workshop for discussion Subject: Prepared by: Revenue & Finance Policy Commercial & Business Activities Mike Drummond (Group Manager Corporate Services) Meeting Date: Workshop 29 July 2011 Report to COUNCIL Workshop for discussion

More information

Overview of PADR process

Overview of PADR process SECTION 3 Overview of PADR process PADR is a methodology for use at community level. It involves active engagement, with the community, in a process to explore the risks they face and the factors contributing

More information

Performance Management. Framework

Performance Management. Framework Management Framework Section Two Supporting Information LTP 2015-25 Structure of Groups of Activities Council carries out a number of activities or functions in order to meet it statutory responsibilities

More information

Audit Engagement Letter: Audit of the consultation document and Long-Term Plan for the period commencing 1 July 2018

Audit Engagement Letter: Audit of the consultation document and Long-Term Plan for the period commencing 1 July 2018 31 Amesbury Street PO Box 149, Palmerston North 4440 11 December 2018 Phone: 04 496 3099 Andy Watson Rangitikei District Council Private Bag 1102 Marton 4741 Dear Andy Audit Engagement Letter: Audit of

More information

Revenue and Financing Policy 2018

Revenue and Financing Policy 2018 Revenue and Financing Policy 2018 Greater Wellington Regional Council Contents Core provisions... 2 1. Introduction... 2 2. Considerations for this policy... 2 3. Valuation system... 2 Equalised capital

More information

Report to COUNCIL for decision

Report to COUNCIL for decision 13/345 Subject: Statement of Proposal Remission of selected rates 2013/2014 Prepared by: Fiona Scragg (Senior Rates Officer) Meeting Date: 5 September 2013 Report to COUNCIL for decision SUMMARY The rates

More information

Funding assistance rates (FAR) review Background document

Funding assistance rates (FAR) review Background document Funding assistance rates (FAR) review Background document our purpose creating transport solutions for a thriving new zealand NZ Transport Agency (NZTA) Published November 2012 ISBN 978-0-478-39498-6 (print)

More information

Upper Tukituki Flood Control Scheme. Asset Management Plan. October 2017 HBRC Plan Number 4559 HBRC Report Number AM 15-04

Upper Tukituki Flood Control Scheme. Asset Management Plan. October 2017 HBRC Plan Number 4559 HBRC Report Number AM 15-04 Upper Tukituki Flood Control Scheme Asset Management Plan October 2017 HBRC Plan Number 4559 HBRC Report Number AM 15-04 Asset Management Group Technical Report ISSN 1174 3085 Engineering Section Upper

More information

In Confidence. Office of the Minister of Commerce and Consumer Affairs Chair, Cabinet Economic Growth and Infrastructure Committee

In Confidence. Office of the Minister of Commerce and Consumer Affairs Chair, Cabinet Economic Growth and Infrastructure Committee In Confidence Office of the Minister of Commerce and Consumer Affairs Chair, Cabinet Economic Growth and Infrastructure Committee Approval to release discussion paper Review of Consumer Credit Regulation,

More information

Road Assets & Expenditure

Road Assets & Expenditure Report on Local Government Road Assets & Expenditure 2013/14 walga.asn.au REPORT ON LOCAL GOVERNMENT ROAD ASSETS & EXPENDITURE 2013/14 Acknowledgements A special note of appreciation is extended to Clive

More information

APPROPRIATION MINISTER(S): Minister for Climate Change (M12), Minister for the Environment (M29)

APPROPRIATION MINISTER(S): Minister for Climate Change (M12), Minister for the Environment (M29) Vote Environment APPROPRIATION MINISTER(S): Minister for Climate Change (M12), Minister for the Environment (M29) APPROPRIATION ADMINISTRATOR: Ministry for the Environment RESPONSIBLE MINISTER FOR MINISTRY

More information

our city our future DRAFT RESOURCING STRATEGY July 2014 FOR PUBLIC EXHIBITION 4 August - 15 September 2014

our city our future DRAFT RESOURCING STRATEGY July 2014 FOR PUBLIC EXHIBITION 4 August - 15 September 2014 our city our future SUSTAINABLE BLUE MOUNTAINS FOR PUBLIC EXHIBITION 4 August - 15 September 2014 DRAFT RESOURCING STRATEGY 2014-2024 July 2014 Including three possible options for Resourcing Our Future

More information

TE TOHATOHA PŪTEA OUR FINANCES

TE TOHATOHA PŪTEA OUR FINANCES TE TOHATOHA PŪTEA OUR FINANCES 7 Gisborne District Annual Report 25/ Contents Page Our Finances Our Finances Statement of Compliance and Responsibility 77 Statement of Comprehensive Income for the year

More information

Accounting policies. 1. Reporting entity

Accounting policies. 1. Reporting entity Accounting policies 1. Reporting entity Taupō District Council (TDC) is a Local Authority under Schedule 2, Part 2 of the Local Government Act 2002. The Council has not presented group prospective financial

More information

Part three POLIcies and other information

Part three POLIcies and other information Part three POLIcies and other information Policies Policies The following policies form part of the Long Term Council Community Plan (LTCCP). However, rather than include them in their entirety in the

More information

Re: Senate Inquiry - Credit and financial services targeted at Australians at risk of financial hardship

Re: Senate Inquiry - Credit and financial services targeted at Australians at risk of financial hardship Nov 8, 2018 (Uploaded via APH website) Senate Standing Committees on Economics PO Box 6100 Parliament House Canberra ACT 2600 Re: Senate Inquiry - Credit and financial services targeted at Australians

More information

AMP2016. i t r i g e s t. c o w w w. p u b l i c s e c t o r d i g e s t. c o m. The 2016 Asset Management Plan for the Township of Hamilton

AMP2016. i t r i g e s t. c o w w w. p u b l i c s e c t o r d i g e s t. c o m. The 2016 Asset Management Plan for the Township of Hamilton AMP2016 i t r i g e s t. c o w w w. p u b l i c s e c t o r d i g e s t. c o m The 2016 Asset Management Plan for the Township of Hamilton SUBMITTED BY THE PUBLIC SECTOR DIGEST INC. (PSD) WWW.PUBLICSECTORDIGEST.COM

More information

Coversheet: Increasing the minimum wage

Coversheet: Increasing the minimum wage Coversheet: Increasing the minimum wage Advising agencies Decision sought Proposing Ministers Ministry of Business, Innovation and Employment Increasing the Minimum Wage Minister for Workplace Relations

More information

Hawke s Bay Regional Council s Long Term Plan Part 3 30 Year Infrastructure Strategy

Hawke s Bay Regional Council s Long Term Plan Part 3 30 Year Infrastructure Strategy Hawke s Bay Regional Council s Long Term Plan 2015-25 Part 3 30 Year Infrastructure Strategy HBRC s 30 Year Infrastructure Strategy Contents Section 1 - Introduction... 1 Section 2 Significant Infrastructure...

More information

Long Term Plan

Long Term Plan s Long Term Plan 2018 2028 Volume 1 Volume 1 Overview including community outcomes and detailed financial information 2 Detailed Council activities activity plans and performance framework 3 Infrastructure

More information

Cabinet Committee on State Sector Reform and Expenditure Control STAGE 2 OF TRANSFORMING NEW ZEALAND S REVENUE SYSTEM

Cabinet Committee on State Sector Reform and Expenditure Control STAGE 2 OF TRANSFORMING NEW ZEALAND S REVENUE SYSTEM Cabinet Committee on State Sector Reform and Expenditure Control In Confidence Office of the Minister of Revenue STAGE 2 OF TRANSFORMING NEW ZEALAND S REVENUE SYSTEM Proposal 1. This paper provides an

More information

PEOPLE PLAN PROGRESS. Our Achievements

PEOPLE PLAN PROGRESS. Our Achievements Our Achievements Our Achievements (service performance reporting) In the statements of service performance there are references to an Annual Survey. This survey was undertaken by Key Research and the sample

More information

LTP Committee 7 June 2018

LTP Committee 7 June 2018 1 LTP Committee 7 June 2018 Issues and Options Re-budgets Internal submissions 2 Contents page Topic and number Description Issue no. Page 1 Key Proposals (01) Walking and Cycling 01 5 2 Key Proposals

More information

STATEMENT OF CORPORATE INTENT April 2018 Electra Group

STATEMENT OF CORPORATE INTENT April 2018 Electra Group STATEMENT OF CORPORATE INTENT April 2018 Electra Group Electra Group Statement of Corporate Intent Page 1 of 11 ELECTRA GROUP STATEMENT OF CORPORATE INTENT APRIL 2018 1. Business mission The mission of

More information

a. Options for managing any equity shares the Government takes in projects through the Fund

a. Options for managing any equity shares the Government takes in projects through the Fund implementation of the Fund (e.g. to reflect potential changes in the role of Senior Regional Officials). I also recommend that the RED Delegated Ministers be similarly authorised to make small scale changes

More information

WE ARE MORE THAN JUST NUMBERS

WE ARE MORE THAN JUST NUMBERS WE ARE MORE THAN JUST NUMBERS 23 WE ARE MORE THAN JUST NUMBERS Unfortunately when it comes to public interest in Local Government, much of it revolves around the figures. A number of commentators have

More information

Vote Primary Industries and Food Safety

Vote Primary Industries and Food Safety Vote Primary Industries and Food Safety APPROPRIATION MINISTER(S): Minister of Agriculture (M2), Minister for Biosecurity (M7), Minister for Food Safety (M33), Minister of Forestry (M35), Minister of Fisheries

More information

The City of Owen Sound Asset Management Plan

The City of Owen Sound Asset Management Plan The City of Owen Sound Asset Management Plan December 013 Adopted by Council March 4, 014 TABLE OF CONTENTS 1 EXECUTIVE SUMMARY... 1 INTRODUCTION....1 Vision.... What is Asset Management?....3 Link to

More information

Welcome to. Dorchester Finance. Your Finance. Your Way

Welcome to. Dorchester Finance. Your Finance. Your Way Welcome to Dorchester Finance Your Finance. Your Way We d like to say... Thank you for choosing Dorchester Finance. Every year we provide New Zealander s just like you with trusted financial solutions.

More information

Report to FINANCE & MONITORING Committee for decision

Report to FINANCE & MONITORING Committee for decision 11/360 Subject: Prepared by: NZ Local Government Funding Agency Mike Drummond (Group Manager Corporate Services) Meeting Date: 16 June 2011 Report to FINANCE & MONITORING Committee for decision SUMMARY

More information

Proposed Waikato Regional Plan Change 1: Waikato and Waipa River Catchments

Proposed Waikato Regional Plan Change 1: Waikato and Waipa River Catchments To: Submission on: Waikato Regional Council Private Bag 3038 Waikato Mail Centre Hamilton 3240 Proposed Waikato Regional Plan Change 1: Waikato and Waipa River Catchments Date: Submission by: Sally Millar

More information

Historic Environment Scotland

Historic Environment Scotland Historic Environment Scotland Page 1 of 7 Asset management plan for the properties in the care of Scottish Ministers - interim statement. September 2015 Page 2 of 7 Purpose and Scope This document sets

More information

B.29[17m] Reflections from our audits: Investment and asset management

B.29[17m] Reflections from our audits: Investment and asset management B.29[17m] Reflections from our audits: Investment and asset management Cover artwork acknowledgement: Painting 502, 1963, Waikanae, by Walter Honour. Purchased 1968. Te Papa. CC BY-NC-ND licence. Te Papa

More information

Otorohanga District Council Summary Annual Report for the year ended 30 June 2016

Otorohanga District Council Summary Annual Report for the year ended 30 June 2016 Otorohanga District Council Summary Annual Report for the year ended COMMENTS FROM THE MAYOR AND THE CHIEF EXECUTIVE The 2015/16 year was another year of steady performance by Council. Whilst there were

More information

$1.4m favourable over budget

$1.4m favourable over budget ASSETS AND INFRASTRUCTURE REPORT April 2018 EXECUTIVE SUMMARY COMMITTEE EXECUTIVE SUMMARY Lifelines has been focussed on capital works delivery. The construction season has been challenging due to wet

More information

Central Plains Water Limited Annual Report For the year ended 30 June 2018

Central Plains Water Limited Annual Report For the year ended 30 June 2018 CENTRAL PLAINS WATER Annual Report Central Plains Water Ltd, Level 1B, 2 Barry Hogan Place, Christchurch PO Box 9424, Tower Junction Ph (03) 982 4267 Contents Page Chairmans' review 2 Directors' report

More information

Impacts from the July 8, 2013 Storm Event on the City of Toronto

Impacts from the July 8, 2013 Storm Event on the City of Toronto STAFF REPORT ACTION REQUIRED Impacts from the July 8, 2013 Storm Event on the City of Toronto Date: September 10, 2013 To: From: Wards: Executive Committee City Manager All Reference Number: SUMMARY The

More information

Report to COUNCIL for decision

Report to COUNCIL for decision 18 098 Title: Section: Prepared by: Fees and Charges for Regional Compliance Monitoring and Science Strategic Planning and Environmental Services Yvette Kinsella (Acting Strategic Planning Manager) and

More information

Report of Housing and Environment Lead Commissioner

Report of Housing and Environment Lead Commissioner Performance and Contract Management Committee 11 June 2014 Title NSL Contract Performance and other parking related issues Report of Housing and Environment Lead Commissioner Wards All Status Public Enclosures

More information

Revenue and Financing Policy

Revenue and Financing Policy It is likely that in the future other relationship agreements will be required for Council to enter into in a post treaty settlement environment especially for those Tangata Whēnua/Māori not covered by

More information

Scottish Canals Asset Management Strategy

Scottish Canals Asset Management Strategy Scottish Canals Asset Management Strategy 2018-2030 Scottish Canals Asset Management Strategy 2018-2030 Executive Summary Scottish Canals is responsible for five historic canals that form a network covering

More information

NZ Transport Agency Boardroom, 50 Victoria Street, Wellington

NZ Transport Agency Boardroom, 50 Victoria Street, Wellington Board Meeting Minutes Date & time Location Board Membership Apologies NZTA staff in attendance Guests 7 July 2017, 9.00am 2.00pm NZ Transport Agency Boardroom, 50 Victoria Street, Wellington Chris Moller

More information

Powys County Council. Highway Asset Management Plan. Working Document Page 1

Powys County Council. Highway Asset Management Plan. Working Document Page 1 Powys County Council Highway Asset Management Plan 2017 Working Document Page 1 Foreword This plan sets out the council s strategy for the management of the council s highway asset for the future. It has

More information

Greater Wellington Regional Council Revenue and Financing Policy Statement of Proposal 1

Greater Wellington Regional Council Revenue and Financing Policy Statement of Proposal 1 Revenue and Financing Policy Statement of Proposal 1 (Greater Wellington) proposes to change our Revenue and Financing Policy. The purpose of the changes is to make the funding policies more transparent,

More information

Funding Fire and Emergency Services for all New Zealanders PUBLIC CONSULTATION

Funding Fire and Emergency Services for all New Zealanders PUBLIC CONSULTATION Funding Fire and Emergency Services for all New Zealanders PUBLIC CONSULTATION A public consultation paper on the setting of the rates of levy on contracts of fire insurance for the 2017/18 financial year

More information

7.0 RISK MANAGEMENT. Table of Contents

7.0 RISK MANAGEMENT. Table of Contents Section 7 Risk Management 7.0 RISK MANAGEMENT Table of Contents 7.0 RISK MANAGEMENT... 1 7.1 Risk Management Process... 2 7.2 Audit and Risk Committee... 2 7.3 Risk Management Charter... 3 7.4 Council

More information

Otorohanga District Council Summary Annual Report for the year ended 30 June 2015

Otorohanga District Council Summary Annual Report for the year ended 30 June 2015 Otorohanga District Council Summary Annual Report for the year ended COMMENTS FROM THE MAYOR AND THE CHIEF EXECUTIVE Council continues to generally operate in a very lean and efficient mode, made possible

More information

Finance Terms and Conditions

Finance Terms and Conditions Finance Terms and Conditions Welcome to Oxford Finance We know you re unique. That s why we have real people assessing real finance needs. Contact Us For any enquiries on your loan, or to update your details,

More information

Financial Performance

Financial Performance Financial Performance Statement of Comprehensive Revenue and Expense For the year ended 30 June Note Budget Revenue Rates, excluding targeted rates for water supply 4 57,758 57,786 54,146 57,740 54,146

More information

Hawke s Bay Airport Limited Statement of Intent

Hawke s Bay Airport Limited Statement of Intent Hawke s Bay Airport Limited Statement of Intent For the year ended 30 June 2018 and the two following years. 1.0 Governance Governance sits with the Board of Directors of Hawke s Bay Airport Limited, which

More information

NEW ZEALAND EMISSIONS TRADING SCHEME REVIEW 2015/16 SUBMISSION BY METHANEX NEW ZEALAND LIMITED (OTHER MATTERS)

NEW ZEALAND EMISSIONS TRADING SCHEME REVIEW 2015/16 SUBMISSION BY METHANEX NEW ZEALAND LIMITED (OTHER MATTERS) Level 3, 36 Kitchener Street PO Box 4299, Shortland Street 1140 Auckland, New Zealand T: (09) 356 9300 F: (06) 356 9301 29 April 2016 NZ ETS Review Consultation Ministry for the Environment PO Box 10362

More information

GUNDAGAI SHIRE COUNCIL

GUNDAGAI SHIRE COUNCIL GUNDAGAI SHIRE COUNCIL Contributions Plan in accordance with Section 94 of the Environmental Planning & Assessment Act 1979 Development generating heavy vehicle usage of local roads June 2015 Date of Adoption:

More information

Department of the Auditor General. Highlights

Department of the Auditor General. Highlights Department of the Auditor General The Pennsylvania Turnpike s financial obligation under Act 44 is unsustainable, causing the deterioration of the financial condition of the Turnpike, while placing an

More information

SUBJECT: A $NZ2 BILLION AND 17,000 NEW JOBS MISSED OPPORTUNITY

SUBJECT: A $NZ2 BILLION AND 17,000 NEW JOBS MISSED OPPORTUNITY Tuesday 20 th August, 2013 Hon. Minister Tim Groser Minister for Climate Change Parliament Buildings Wellington SUBJECT: A $NZ2 BILLION AND 17,000 NEW JOBS MISSED OPPORTUNITY E te Minita, tena koe Thank

More information

Interim Report Review of the financial system external dispute resolution and complaints framework

Interim Report Review of the financial system external dispute resolution and complaints framework EDR Review Secretariat Financial System Division Markets Group The Treasury Langton Crescent PARKES ACT 2600 Email: EDRreview@treasury.gov.au 25 January 2017 Dear Sir/Madam Interim Report Review of the

More information

Policy Implementation for Enhancing Community. Resilience in Malawi

Policy Implementation for Enhancing Community. Resilience in Malawi Volume 10 Issue 1 May 2014 Status of Policy Implementation for Enhancing Community Resilience in Malawi Policy Brief ECRP and DISCOVER Disclaimer This policy brief has been financed by United Kingdom (UK)

More information