1 NATIONAL ENERGY BOARD IN THE MATTER OF the National Energy Board Act, R.S.C. 1985, c. N-7, as amended, and the Regulations made thereunder; AND IN THE MATTER OF an application by Enbridge Pipelines Inc. for the Line 10 Westover Segment Replacement Project; AND IN THE MATTER OF Hearing Order OH and NEB File No. OF-Fac-Oil-E WRITTEN EVIDENCE of the Copetown Landowners Group 1. The Copetown Landowners Group ( CLG ) consists of landowners whose properties are situated on or near the route deviation proposed by Enbridge Pipelines Inc. ( Enbridge ) for its Line 10 Westover Segment Replacement Pipeline in the Copetown, Ontario area. The proposed deviation would avoid Enbridge s existing Line 10 and Line 11 pipeline corridor that runs through two area golf courses. 2. CLG members own properties in four locations directly affected by the proposed route deviation: Landowner(s) Property Address Property Identifier Number(s) Ontario Inc. (Gowland Farms) Andrew Guiducci and Julia Guiducci John Neeb and Terri Neeb Sian McGregor nd Conc. Rd. W., RR1, Lynden, ON nd Conc. Rd. W., RR1, Lynden, ON 2525 Governors Rd., RR2, Lynden, ON 2532 Governors Rd., RR2, Lynden, ON LT LT LT LT LT 3. Other CLG members own residential properties in the close vicinity of the proposed route deviation: Landowner(s) Kelly Van Heurn and Tom Van Heurn Property Address 150 Orkney Road, Lynden, ON

2 CLG Written Evidence June 20, Paul Fiorentino and Martha Fiorentino Ian Flatt and Evelyn Flatt Ron Thomson and Nellie Thomson Eric Schmidt and Anne Schmidt Mark Crowther and Roberta Crowther Jean Griffin and Patrick Griffin nd Conc. Rd. W., RR1, Lynden, ON nd Conc. Rd. W., RR1, Lynden, ON nd Conc. Rd. W., RR1, Lynden, ON nd Conc. Rd. W., RR1, Lynden, ON nd Conc. Rd. W., RR1, Lynden, ON nd Conc. Rd. W., RR1, Lynden, ON 4. No CLG members own lands located along the existing Enbridge Line 10 and Line 11 corridor. 5. CLG s members are opposed to Enbridge s proposed route deviation in their area and will request that the NEB reject the proposed route deviation. The NEB should only approve Enbridge s Line 10 Westover Segment Replacement Project on the basis that it must follow Enbridge s existing Line 10 and Line 11 corridor in the Copetown area. 6. Enbridge has an existing, long-established corridor for its Line 10 and Line 11 pipelines and is capable of installing and operating its proposed Line 10 replacement pipeline in or along the same corridor. Use of the proposed deviation route in the Copetown area will result in unwarranted and unjustifiable negative environmental and socio-economic impacts. 7. Enbridge has also requested that its project be exempt from the requirement to file a Plan, Profile and Book of Reference so as to deprive landowners affected by the project of the right to require detailed route hearings Enbridge has confirmed that it is seeking an order of the NEB in the current hearing process approving the final detailed route for its project. 8. CLG opposes Enbridge s exemption request and opposes Enbridge s request that the NEB approve the final detailed route for its project on the basis of its Section 58 Application to the NEB. 9. If the NEB decides to approve the general route of the proposed Line 10 replacement pipeline with the route deviation in the Copetown area, CLG will request in the alternative that the NEB reject Enbridge s exemption request so that CLG landowners will have the opportunity to require detailed route hearings for their properties for the determination of the best possible detailed route of the pipeline and the most appropriate methods and timing of construction of the pipeline.

3 CLG Written Evidence June 20, CLG applied for and received an award of participant funding for this hearing process. However, the participant funding award is not sufficient to cover CLG s anticipated legal and expert consultant costs. In contrast, landowners may be reimbursed for their actual costs reasonably incurred in connection with a detailed route hearing. Enbridge Route Deviation 11. Since filing its Section 58 Application with the NEB in December, 2015, Enbridge has made multiple changes to its proposed route for the Line 10 replacement pipeline. CLG understands the currently proposed route to be the one set out in the mapping provided by Enbridge dated April 29, Excerpts from Enbridge Route Map dated April 29, 2016 Attachment When Enbridge disclosed that it had made changes to its proposed route in its Additional Evidence filing on April 18, 2016, CLG s counsel wrote to counsel for Enbridge to request that updated Environmental Alignment Sheets be provided. To date, no updated Alignment Sheets have been provided to CLG or filed with the NEB. 13. Enbridge is proposing to construct a 20 inch diameter oil pipeline through and near CLG member properties within a permanent 10 metre wide easement. To CLG s understanding, there are currently no pipeline easements crossing these properties. 14. The 10 metre wide permanent easement proposed by Enbridge is designed to accommodate the Line 10 replacement pipeline and future pipelines that may be proposed by Enbridge. Enbridge has already replaced a segment of its Line 11 pipeline. If the route deviation in the Copetown area is approved by the NEB and a new Enbridge pipeline corridor is established, any future Enbridge pipeline, including any Line 11 replacement pipeline, will follow the new corridor in the Copetown area. 15. The form of easement agreement proposed by Enbridge for this project provides for multiple pipelines to be installed and operated within the proposed permanent easement, and provides that Enbridge will have a right of ingress and egress over the entire property affected by the easement. 16. In the proposed easement agreement, Enbridge also reserves to itself sole discretion over the disposition of any pipeline that is removed from service. Enbridge would have the contractual option to release its easement and walk away from any pipeline it has installed.

4 CLG Written Evidence June 20, In addition to the 10 metre wide permanent easement being proposed by Enbridge for the CLG properties for the Line 10 replacement pipeline (and the associated temporary work space during the construction period), CLG properties would also be subject to the restrictions imposed by Section 112 of the NEB Act that go beyond the boundary of the pipeline easement. The restricted area has measured 30 metres (100 feet) from the edge of the easement and may extend beyond the boundaries of the properties on which the actual easement is located. 18. If the route deviation is approved, all CLG landowners and their properties will be negatively affected by Enbridge s construction and operation of its Line 10 replacement pipeline both now and into the future. The negative impacts of pipeline construction and operation on residences and on agricultural operations are well-established and identified and acknowledged by Enbridge in its application and evidence. Gowland Farms Property Tracts 23 and Gowland Farms owns the two parcels of land designated by Enbridge as Tracts 23 and 24 for its project. The parcels comprise a farm measuring about 200 acres in size that was purchased by Gowland Farms in or about Excerpt from Enbridge Section 87 Notice (Map) Attachment 2 The farm has an extensive systematic tile drainage system (composed mainly of clay tile) and irrigation system. The farm was previously owned by Gordon Forth Farms Limited and was used for the production of broccoli under the brand name, Barry Brand Iced Broccoli. 21. Aerial Photograph of farm showing tile runs Attachment 3 Clay Tile System Drawing Attachment 4 Photographs of farm showing proposed pipeline route Attachment 5 Barry Brand Iced Broccoli Trademark Information Attachment 6 Although Gowland Farms is currently growing corn on the property, the farm is capable of producing premium value vegetable crops such as broccoli. Gowland Farms will consider returning to the production of vegetable crops on the property in the future. All of the buildings and infrastructure used by Gordon Forth Farms Limited for broccoli production remain in place. 22. At present there is no pipeline crossing the Gowland Farms property. Enbridge proposes to install and operate its Line 10 replacement pipeline on a diagonal line through the middle of the farm. The proposed construction and establishment of the pipeline will

5 CLG Written Evidence June 20, irreparably disturb the tile drainage and irrigation system on the property and will permanently impair the soils and their productivity. 23. Gowland Farms also rents the cultivated land owned by Hydro One Networks Inc. ( HONI ) adjacent to the Gowland Farms property on the east side (designated as Tract 22 by Enbridge). Enbridge s proposed route deviation crosses that farm as well. In addition to HONI s transmission towers and lines, there are three gas pipelines located on that property that would be crossed by Enbridge s Line 10 replacement pipeline. HONI Parcel Register for Tract 22 Property Attachment 7 PIN Map showing HONI property and adjacent properties Attachment 8 PIN Map showing intersection of adjacent affected properties Attachment 9 Drainage Diagram showing intersection of affected properties Attachment 10 Guiducci Property Tract Andrew and Julia Guiducci own the property designated as Tract 27 for its project. They purchased the 103-acre property in 2011 through their company and are currently building a house on the property where they will reside. 25. Enbridge s originally proposed deviation route ran directly through the west side of the property, including the provincially significant wetland located on the property. 26. Original Enbridge Section 87 Notice Attachment 11 Enbridge recently changed its proposed route so as to cross the wetland primarily on the properties located to the west of the Guiducci property. However, the Line 10 replacement pipeline would still run through the front of the Guiducci property and immediately adjacent to its west boundary. The proposed route still runs through the centre of the same wetland that is located on the Guiducci property. 27. Revised Enbridge Section 87 Notice Attachment 12 PIN Map showing Guiducci Property Attachment 13 Guiducci Property Photographs Attachment 14 Guiducci Ducks Unlimited Wetland Project Map Updated Attachment 15 Grand Valley Conservation Authority Map Attachment 16 The proposed route will run through the hazelnut tree field planted at the front of the Guiducci property. This is a test plot as future expansion is being considered. It takes five years to reach hazelnut production; the currently planted trees are in the third year. Pipeline construction through this area will set back these plans. 28. There is also tile drainage located on the property that will be affected by any pipeline construction and operation.

6 CLG Written Evidence June 20, Andrew Guiducci first learned of Enbridge s proposed project in the summer of 2013 and attended Enbridge open houses related to the project. He expressed his concerns about the proposed route deviation to Enbridge personnel, including at the August, 2013 open house. At that time, Enbridge personnel advised Andrew Guiducci that, in spite of Enbridge s project mapping that showed the route deviation in the Copetown area, Enbridge s primary option for the Line 10 replacement pipeline was to horizontal bore it through the two golf courses (Copetown Woods and Flamborough Hills) adjacent to the existing Line 10 and Line 11 corridor. 30. Andrew Guiducci August 12, 2013 Letter Attachment 17 Hamilton Spectator Article dated August 29, 2013 Attachment 18 The owner of the Copetown Woods golf course also supported the routing of the Line 10 replacement pipeline along the existing corridor through the golf course. 31. In 2015, Enbridge s land agent, Glen Beach, was still telling Andrew Guiducci that Enbridge s primary option for the Line 10 replacement pipeline was to follow the existing Line 10 and Line 11 corridor through the two golf courses. 32. Andrew Guiducci June 29, Correspondence Attachment 19 However, following discussions with Glen Beach in the summer of 2015, Andrew and Julia Guiducci were served with a Section 87 Notice by Enbridge that confirmed that Enbridge s true plan was to install its Line 10 replacement pipeline following the route deviation around the golf courses and through the Guiducci property. Neeb Property Tract John and Terri Neeb own the 67-acre property designated by Enbridge as Tract 34 for its project. They purchased the property in Enbridge Section 87 Notice Attachment 20 PIN Map showing Neeb Property Attachment 21 The Neebs residence is located on the property. They have previously grown vegetables on the farm, including potatoes, but currently grow corn and soybeans. The cultivation of premium value vegetable crops remains an option. 35. Due to the location of the property, surface water from nearly 200 acres of land, including the land surrounding the Neeb property, drains through the Neeb property. A series of tile drains and grassed waterways have been developed to provide for this drainage.

7 CLG Written Evidence June 20, Neeb Soil Sampling Map Attachment 22 Neeb Drainage Diagram Attachment 23 Enbridge has proposed to install its Line 10 replacement pipeline right through the middle of the Neeb farm, which will irreparably disturb the drainage system on the property and will permanently impair the soils and their productivity. 37. Photos of Neeb Property Attachment 24 Due to the configuration of the farm, construction by Enbridge will also cut off access to some of the fields. McGregor Property Tract Sian McGregor owns the property designated by Enbridge as Tract 36 for its project. She purchased the property in 2002 and lives there with her family. The McGregor property is located on the south side of Governor s Road directly across from the Neeb property. 39. Original Enbridge Section 87 Notice Attachment 25 Revised Enbridge Section 87 Notice Attachment 26 PIN Map showing McGregor property Attachment 27 Sian McGregor has plans to develop a landscape construction and nursery stock business on the property. Presently, the cultivated land on the property is rented by John Neeb for cash crop production. 40. Photographs of McGregor Property Attachment 28 Enbridge construction will cut off access to the two west fields on the McGregor property, and will irreparably disturb the drainage system (clay tile) on the property and permanently impair the soils and their productivity. 41. McGregor Farm soil map Attachment 29 There is also a provincially significant wetland located on the McGregor property directly adjacent to Enbridge s proposed deviation route. Grand Valley Conservation Authority Map Attachment 30 Golf Course Impacts 42. Enbridge has proposed to install and operate its Line 10 replacement pipeline through the CLG properties in order to avoid using its existing Line 10 and Line 11 corridor through the two Copetown-area golf courses: Copetown Woods Golf Course and Flamborough Hills Golf Course. CLG understands that Enbridge s primary reason for

8 CLG Written Evidence June 20, avoiding the existing corridor is that construction through the existing corridor will be more expensive than construction along the route deviation. 43. However, the environmental and socio-economic impacts of construction along the existing corridor through the golf courses will be significantly less than the impacts associated with construction and operation of the Line 10 replacement pipeline on the route deviation through the CLG properties and other affected properties. 44. Enbridge has extensive experience in constructing and operating oil pipelines through golf courses, including Line 10 and Line 11 through the Copetown Woods and Flamborough Hills golf courses. Enbridge has on several recent projects submitted environmental assessments and mitigation plans to the NEB dealing specifically with the mitigation of impacts of pipeline construction and operation on golf courses. 45. Excerpts from Terrace Phase I ESEIA Attachment 31 Excerpts from Terrace Phase I As-Built Env. Report Attachment 32 Excerpts from Alberta Clipper ESA Attachment 33 Excerpts from Alberta Clipper EPP Attachment 34 Excerpts from Edmonton to Hardisty ESA Attachment 35 Enbridge already has easement agreements providing permanent easement rights for multiple pipelines on the two golf course properties. The Flamborough Hills golf course was developed in the early 1960s around the time that Enbridge (the then Interprovincial Pipe Line Company) developed its Line 10 pipeline. The easement agreement for the Flamborough Hills property was modified from the standard form to specify that compensation would be payable for damages related to golf course facilities. 46. The Flamborough Hills golf course was already in place when Enbridge (the then Interprovincial Pipe Line Company) planned and constructed its Line 11 pipeline through the property in the early 1970s. 47. The Copetown Woods golf course was constructed after both the Line 10 and Line 11 pipelines were already in place. The golf course was specifically designed to accommodate the Enbridge pipelines as well as the HONI transmission corridor and the three adjacent gas pipelines. 48. The golf course is owned by and was developed by Gordon Forth, the former owner of the Gowland Farms property. He formerly grew broccoli on the farm where the golf course is now located, but developed the golf course there because it was challenging to

9 CLG Written Evidence June 20, grow broccoli and vegetables on the property due to soil conditions (in contrast to the Gowland Farms property where vegetables continued to be grown). Copetown Woods Golf Course History from Website Attachment Enbridge has sufficient room within its existing permanent easement through the golf courses for the installation of its proposed Line 10 replacement pipeline. Enbridge has the necessary easement rights to remove the existing Line 10 pipeline and replace it in the same location. Alternatively, Enbridge can install the replacement Line 10 pipeline within the 6.1 metre area between Line 11 and the eastern edge of Enbridge s easement. 50. If the replacement Line 11 pipeline is located 3 metres away from Line 11 (which is the same separation distance that exists between Line 10 and Line 11 currently), there will be the same amount of space between the replacement Line 10 and the eastern edge of the easement as there is between the existing Line 10 and the western edge of the easement. It is apparent that Enbridge (then Interprovincial Pipe Line Company) designed the Line 10 and Line 11 corridor to accommodate a third pipeline on the western side of Line 11 in the area of the two golf course properties. 51. To the extent that additional permanent easement is required for the Line 10 replacement pipeline, Enbridge can take that additional easement from the golf course properties. 52. To the extent that Enbridge chooses to avoid open trench construction on the golf course properties (although that was the method used for construction of the existing Line 10 and Line 11 pipelines, and was the method of construction used by Enbridge on the recent projects for which golf course environmental assessments and mitigation plans were submitted to the NEB), Enbridge is capable of horizontally boring or horizontally direct drilling ( HDD ) the line through the golf courses. 53. To the extent that Enbridge wishes to avoid the impact of HDD on the properties that lie to the north of the Copetown Woods golf course and to the south of the Flamborough Hills golf course, the areas to be used for the HDD can be restricted to the golf course properties themselves. 54. For the Copetown Woods golf course, lands to be used for any HDD construction would be restricted to the south side of the 2 nd Concession Road West. Any part of the Line 10 replacement pipeline that cannot be installed through HDD can be installed using the traditional open trench method.

10 CLG Written Evidence June 20, PIN Map showing Enbridge crossing of 2 nd Conc. Rd. W. Attachment 37 For the Flamborough Hills golf course, lands to be used for any HDD construction would be restricted to the north side of the CNR tracks. Alternatively, the Line 10 replacement pipeline south of the CNR tracks (which form the southern boundary of the Flamborough Hills golf course property) could be re-routed slightly to the west to avoid any impact on the residential house and workshop that are located directly adjacent to the existing Line 10 and Line 11 corridor. There is sufficient room to the west and possibly to the east of the existing corridor in which Enbridge can construct its proposed pipeline. 56. Enbridge Line 10 Operation and Maintenance Notification Attachment 38 Also, it is not likely that the construction of the Line 10 replacement pipeline through the golf courses (whether by open trench, boring or HDD) will have any significant impact on the golf course properties or their operations. 57. There are already two Enbridge pipelines located within the golf courses and the courses have been designed to accommodate those pipelines. 58. Flamborough Hills consists of three 9-hole courses and even if construction took place during the golfing season, no fewer than 11 holes and the driving range could remain open for use. 59. Flamborough Hills Course Layout from Facebook Page Attachment 39 Copetown Woods was constructed after Line 10 and Line 11 were already in place, and its course accommodates the pipeline corridor. TransCanada has as recently as 2005 undertaken work through the golf course and filed impact mitigation information with the NEB. 60. Golf Course Planning Documentation submitted to City of Hamilton Attachment 40 TransCanada 2005 Cathodic Protection Program Attachment 41 In any event, Enbridge is proposing late Fall and Winter construction as it has done in previous projects to avoid conflict with golf course operations entirely. There appears to be no reason why the same mitigation measures cannot mitigate impacts to the golf courses from Enbridge s proposed Line 10 replacement pipeline.

11 CLG Written Evidence June 20, Collins Farm Produce 61. In its alternative route analysis narrative for the Copetown area, Enbridge has suggested that the route deviation is necessary not only to avoid the golf courses, but also to avoid negative impacts on the nearby Collins Farm Produce operation. 62. However, it does not appear that installation of the Line 10 replacement pipeline along the existing Line 10 and Line 11 corridor through the Collins Farm Produce property (owned by J. Collins & Sons Limited and Charles John Collins, which is designated by Enbridge as Tract 18 for its project) would have any significant impact on the Collins Farm Produce property or business. The property appears to be used mainly for the production of soybeans, not vegetable crops. 63. Photos showing Enbridge easement through Collins Farm Produce Attachment 42 PIN Map showing Collins Farm Produce property Attachment 43 Rather than following the existing Line 10 and Line 11 corridor that runs almost entirely on a straight line down the side of the property, Enbridge has proposed to veer off on a diagonal line across the Collins Farm Produce property. The route deviation then crosses over into the property owned by Joseph Betzner and Terry Betzner (designated by Enbridge as Tract 21 for its project). From there, the route deviation crosses the HONI property through to the Gowland Farms property. 64. PIN Map showing Betzner property Attachment 44 As with the golf course properties, Enbridge already has permanent easement rights to install multiple pipelines on the Collins Farm Produce and Betzner properties. 65. Parcel Register for Collins Farm Produce property Attachment 45 Enbridge Easement Agreement for Collins Farm Produce property Attachment 46 Parcel Register for Betzner property Attachment 47 Enbridge has also obtained option agreements for the Collins Farm Produce and Betzner properties for the Line 10 Replacement pipeline. 66. Notice of Enbridge Option for Collins Farm Produce Property Attachment 48 Notice of Enbridge Option for Betzner property Attachment 49 Enbridge can construct and operate its Line 10 replacement pipeline within or immediately adjacent to the existing Line 10 and Line 11 corridor on the Collins Farm Produce and Betzner properties.

12 CLG Written Evidence June 20, Alternatively, if a route deviation on the Collins Farm Produce property is necessary to mitigate project impacts on the Collins Farm Produce property and business, Enbridge can restrict its route deviation to that property. Rather than veering westward toward the Betzner, HONI and Gowland Farms properties, Enbridge s Line 10 replacement pipeline can be routed back eastward to the existing Line 10 and Line 11 corridor. OEB Guidelines for Construction 68. Rather than proposing to construct its Line 10 replacement pipeline along the existing and previously disturbed Line 10 and Line 11 corridor in the Copetown area, Enbridge proposes to install and operate its new pipeline through prime agricultural lands, including the CLG properties, where there are no pipelines currently in place. 69. Enbridge s proposal is contrary to the Environmental Guidelines for the Location, Construction and Operation of Hydrocarbon Pipelines and Facilities in Ontario, which provide at Section 4.3.5: (a) (b) (c) (d) The disruption of farmlands by pipelines and related facilities should be minimized. Accordingly, the use of the lowest capability agricultural land is preferred. Pipeline and facilities siting should avoid disruption of prime agricultural lands. If it is essential that the route or site traverse prime agricultural lands, all reasonable efforts to parallel property lines and other rights-of-way should be made. Diagonal field severance should be avoided. Environmental Guidelines, 2011 Attachment 50 Greenbelt Plan Enbridge s proposed route deviation is also contrary to Ontario s Greenbelt Plan, which applies to the Copetown area. 71. Section of the Greenbelt Plan 2005 provides that, for lands falling within the Protected Countryside, the location and construction of infrastructure and expansions, operations and maintenance are subject to:

13 CLG Written Evidence June 20, (a) (b) (c) Planning, design and construction practices shall minimize, wherever possible, the amount of the Greenbelt, and particularly the Natural Heritage System, traversed and/or occupied by such infrastructure. Where practicable, existing capacity and coordination with different infrastructure services is optimized so that the rural and existing character of the Protected Countryside and the overall urban structure for southern Ontario established by Greenbelt and any provincial growth management initiatives are supported and reinforced. New or expanding infrastructure shall avoid key natural heritage features or key hydrologic features unless need has been demonstrated and it has been established that there is no reasonable alternative. Greenbelt Plan 2005 Attachment Enbridge has indicated that its project includes route deviations totaling 13 km in length. Whereas its current Line 10 pipeline runs approximately 32 km in length in a single corridor, Enbridge s project as proposed would result in a total length of 45 km in multiple connected corridors. 73. And Enbridge s proposed route deviation in the Copetown area is designed to run directly through or directly adjacent to multiple provincially significant wetlands and other natural heritage systems. 74. Enbridge s route deviations for its Line 10 replacement pipeline project would result in the unnecessary and wasteful creation of a third major utility corridor in the Copetown area (in addition to the existing Enbridge corridor and the HONI/gas pipeline corridor). 75. In contrast, Enbridge s environmental assessment in support of its recent Line 11 replacement pipeline project found that the best option was to follow Enbridge s existing Line 10 and Line 11 corridor. Enbridge Line 11 ESA Attachment Jim Harris, the owner of the Knollwood Golf Course, an intervenor in the NEB hearing process, made a presentation to the City of Hamilton Council opposing the creation of new corridors by Enbridge in contravention of the Greenbelt Plan. As requested, the City of Hamilton has filed a letter with the NEB stating its opposition to the creation of a new corridor.

14 CLG Written Evidence June 20, Minutes of Presentations to City of Hamilton Council Attachment 53 City of Hamilton Report PED15208/LS15036) Attachment 54 Mr. Harris has had much recent experience with Enbridge construction operations through his golf course. A few years ago, Enbridge conducted a series of pipeline maintenance digs on the Knollwood Golf Course property and had in place agreements with the golf course concerning the mitigation of impacts. Enbridge Letter to NEB re maintenance operations Attachment 55 Additional CLG Written Evidence 78. In addition to the written evidence above, CLG will be filing with the NEB expert written evidence prepared by the firm of Hardy Stevenson and Associates with respect to routing of the proposed Enbridge Line 10 replacement pipeline. 79. CLG also reserves its right to file additional written evidence in respect of any further information request responses provided by Enbridge in connection with CLG s pending motion or any further evidence filed by Enbridge, as permitted by the NEB.

CERTIFICATE OC-56. IN THE MATTER OF the National Energy Board Act (NEB Act) and the regulations made thereunder; and

CERTIFICATE OC-56. IN THE MATTER OF the National Energy Board Act (NEB Act) and the regulations made thereunder; and CERTIFICATE IN THE MATTER OF the National Energy Board Act (NEB Act) and the regulations made thereunder; and IN THE MATTER OF the Canadian Environmental Assessment Act (CEA Act), as amended and the regulations

More information

The Bison Pipeline Project. Public Disclosure Document

The Bison Pipeline Project. Public Disclosure Document The Bison Pipeline Project Public Disclosure Document Who is involved with the Bison project? Bison Pipeline Ltd. (Bison Pipeline), a wholly owned subsidiary of BC Gas Inc., has released a public disclosure

More information

6.0 MONITORING AND CONTINGENCY PLANS

6.0 MONITORING AND CONTINGENCY PLANS 6.0 MONITORING AND CONTINGENCY PLANS 6.1 MONITORING The primary objective of compliance and effects monitoring is to confirm whether mitigation and protective measures are effectively implemented and to

More information

CERTIFICATE OC-063. IN THE MATTER OF the National Energy Board Act (NEB Act) and the regulations made thereunder; and

CERTIFICATE OC-063. IN THE MATTER OF the National Energy Board Act (NEB Act) and the regulations made thereunder; and BEFORE the Board on 19 April 2016. CERTIFICATE IN THE MATTER OF the National Energy Board Act (NEB Act) and the regulations made thereunder; and IN THE MATTER OF an application dated 5 November 2014 under

More information

Enbridge Energy, Limited Partnership and Enbridge Pipelines (Southern Lights) L.L.C. Routing Permit for a Crude Oil Pipeline. Alberta Clipper Project

Enbridge Energy, Limited Partnership and Enbridge Pipelines (Southern Lights) L.L.C. Routing Permit for a Crude Oil Pipeline. Alberta Clipper Project Routing Permit for a Crude Oil Pipeline Alberta Clipper Project MPUC Docket No. PL9/PPL-07-361 November 18, 2009 Docket No. PL9/PPL-07-361 November 18, 2009 REVISED Mile Post 893 Deviation Request Enbridge

More information

2014 ABAER 007. Inter Pipeline Ltd. Application for a Pipeline Licence Edmonton/Fort Saskatchewan Area. June 23, 2014

2014 ABAER 007. Inter Pipeline Ltd. Application for a Pipeline Licence Edmonton/Fort Saskatchewan Area. June 23, 2014 2014 ABAER 007 Inter Pipeline Ltd. Application for a Pipeline Licence Edmonton/Fort Saskatchewan Area June 23, 2014 ALBERTA ENERGY REGULATOR Decision 2014 ABAER 007: Inter Pipeline Ltd., Application for

More information

Good afternoon, For further details regarding the Don River Replacement Project, please refer to the attached project description.

Good afternoon, For further details regarding the Don River Replacement Project, please refer to the attached project description. Filed: 2018-07-04, EB-2018-0108, Exhibit F, Tab 1, Schedule 1, Attachment 1, Page 1 of 9 From: To: Cc: Subject: Date: Attachments: Stephanie Allman "emma.sharkey@ontario.ca" "zora.crnojacki@oeb.ca" Enbridge

More information

CANADIAN OCCIDENTAL PETROLEUM LTD. & MR. A. POFFENROTH LICENCE NO , PIPELINE NO. 12 Decision DELACOUR AREA Applications No.

CANADIAN OCCIDENTAL PETROLEUM LTD. & MR. A. POFFENROTH LICENCE NO , PIPELINE NO. 12 Decision DELACOUR AREA Applications No. ALBERTA ENERGY AND UTILITIES BOARD Calgary Alberta CANADIAN OCCIDENTAL PETROLEUM LTD. & MR. A. POFFENROTH LICENCE NO. 26758, PIPELINE NO. 12 Decision 97-11 DELACOUR AREA Applications No. 960925 1 INTRODUCTION

More information

GLNG PROJECT - ENVIRONMENTAL IMPACT STATEMENT

GLNG PROJECT - ENVIRONMENTAL IMPACT STATEMENT 7 Values and Management of Impacts J:\Jobs\42626220\07 Deliverables\EIS\FINAL for Public Release\7. Values and Management of Impacts\7-12 Visual Amenity\07 12 Visual Amenity (Section 7.12) FINAL PUBLIC.doc

More information

Report to: Development Services Committee Date: June 26, 2017

Report to: Development Services Committee Date: June 26, 2017 SUBJECT: New Provincial Plans Release of the 2017 Growth Plan, Greenbelt Plan and Oak Ridges Moraine Conservation Plan PREPARED BY: Policy and Research, Planning and Urban Design REVIEWED BY: Marg Wouters,

More information

LETTER DECISION. File OF-Fac-OtherComm-H October 2016

LETTER DECISION. File OF-Fac-OtherComm-H October 2016 LETTER DECISION File OF-Fac-OtherComm-H109-2016-01 01 31 October 2016 Mr. Shawn Gowrie Regulatory Technician Husky Oil Operations Limited Box 6525, Station D 707 8 th Avenue SW Calgary, AB T2P 3G7 Facsimile

More information

ATCO Gas and Pipelines Ltd. (South)

ATCO Gas and Pipelines Ltd. (South) Decision 22634-D01-2017 Southwest Calgary Connector Pipeline Project August 9, 2017 Alberta Utilities Commission Decision 22634-D01-2017 Southwest Calgary Connector Pipeline Project Proceeding 22634 Application

More information

Applying for a Kinder Morgan Canada. Proximity Permit. Design and Construction Guidelines CANADA

Applying for a Kinder Morgan Canada. Proximity Permit. Design and Construction Guidelines CANADA Applying for a Kinder Morgan Canada Proximity Permit Design and Construction Guidelines CANADA A Guide to Applying for a Kinder Morgan Canada Proximity Permit Kinder Morgan Canada operates the Trans Mountain

More information

ATCO Gas and Pipelines Ltd. (South)

ATCO Gas and Pipelines Ltd. (South) Decision 3421-D01-2015 Northeast Calgary Connector Pipeline January 16, 2015 The Alberta Utilities Commission Decision 3421-D01-2015: Northeast Calgary Connector Pipeline Application 1610854 Proceeding

More information

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND ORDER EB UNION GAS LIMITED

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND ORDER EB UNION GAS LIMITED Commission de l énergie de l Ontario DECISION AND ORDER UNION GAS LIMITED Application for approval to construct a natural gas pipeline in the City of Greater Sudbury BEFORE: Lynne Anderson Presiding Member

More information

AltaLink Management Ltd.

AltaLink Management Ltd. Decision 22025-D03-2017 Red Deer Area Transmission Development Amendment Application June 8, 2017 Decision 22025-D03-2017 Red Deer Area Transmission Development Amendment Application Proceeding 22025 Applications

More information

RE: PROPOSED MANAWATU DISTRICT PLAN CHANGE 55 HEARINGS

RE: PROPOSED MANAWATU DISTRICT PLAN CHANGE 55 HEARINGS 30 November 2016 File: 13/134 DDI: 09 917 4305 Email: kblair@burtonconsultants.co.nz Manawatu District Council Private Bag 10 001 FEILDING 4743 Attention: Hearing Committee: Plan Change 55 By email only:

More information

SAN DIEGO LAFCO MINUTES OF THE REGULAR MEETING JULY 7, 2003

SAN DIEGO LAFCO MINUTES OF THE REGULAR MEETING JULY 7, 2003 SAN DIEGO LAFCO MINUTES OF THE REGULAR MEETING JULY 7, 2003 There being a quorum present, the meeting was convened at 9:00 a.m. by Chairwoman Dianne Jacob. Also present were: Regular Commissioners Councilmember

More information

NATIONAL ENERGY BOARD HEARING ORDER OH TRANSCANADA KEYSTONE PIPELINE GP LTD. ( KEYSTONE ) KEYSTONE XL PIPELINE APPLICATION

NATIONAL ENERGY BOARD HEARING ORDER OH TRANSCANADA KEYSTONE PIPELINE GP LTD. ( KEYSTONE ) KEYSTONE XL PIPELINE APPLICATION File OF-Fac-Oil-T-00-0 0 NATIONAL ENERGY BOARD HEARING ORDER TRANSCANADA KEYSTONE PIPELINE GP LTD. ( KEYSTONE ) KEYSTONE XL PIPELINE APPLICATION WRITTEN EVIDENCE OF ENBRIDGE PIPELINES INC. ( ENBRIDGE )

More information

2.1 THE PUBLIC INTEREST STANDARD APPLIES TO TRANSFER APPLICATIONS

2.1 THE PUBLIC INTEREST STANDARD APPLIES TO TRANSFER APPLICATIONS Energy East Pipeline Ltd. CA PDF Page 1 of 8 Section 2 2.0 REGULATORY STANDARDS Past NEB decisions indicate that the regulatory standards to be considered and applied in applications for leave to transfer

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PennEast Pipeline Company, LLC ) Docket Nos. CP15-558-000 and CP15-558-001 MOTION FOR A STAY PENDING REHEARING SUBMITTED BY THE

More information

Edmonton to Hardisty Pipeline Project - Certificate OC-062 and Order XO-E A3V9D6 Adobe Pg 4

Edmonton to Hardisty Pipeline Project - Certificate OC-062 and Order XO-E A3V9D6 Adobe Pg 4 Edmonton to Hardisty Pipeline Project Section 52 - Condition # 9 OC-062 Hearing Order - OH-001-2013 Section 52 Commitments Tracking Table as of July 13, 2018 Enbridge Pipelines Inc. - Edmonton to Hardisty

More information

CITY OF PITT MEADOWS

CITY OF PITT MEADOWS RECOMMENDATIONS: THAT Council: CITY OF PITT MEADOWS COUNCIL IN COMMITTEE REPORT To: Chief Administrative Officer File No: From: Acting Director of Bylaw/Policy No: 2635- Operations and 2013 Development

More information

ENVIRONMENTAL ASSESSMENT ACT SECTION 9 NOTICE OF APPROVAL TO PROCEED WITH THE UNDERTAKING

ENVIRONMENTAL ASSESSMENT ACT SECTION 9 NOTICE OF APPROVAL TO PROCEED WITH THE UNDERTAKING ENVIRONMENTAL ASSESSMENT ACT SECTION 9 NOTICE OF APPROVAL TO PROCEED WITH THE UNDERTAKING RE: An Environmental Assessment for the Easterly Extension of the 407 Transportation Corridor Proponent: EA File

More information

City of Kingston Information Report to Rural Advisory Committee Report Number RAC

City of Kingston Information Report to Rural Advisory Committee Report Number RAC To: From: Resource Staff: City of Kingston Information Report to Rural Advisory Committee Report Number RAC-14-006 Chair and Members of the Rural Advisory Committee Cynthia Beach, Commissioner, Corporate

More information

ENBRIDGE PIPELINES (VIRDEN) INC. Proposed NGL Injection Station and Connecting Pipeline W1M to W1M Near Cromer, Manitoba

ENBRIDGE PIPELINES (VIRDEN) INC. Proposed NGL Injection Station and Connecting Pipeline W1M to W1M Near Cromer, Manitoba ENBRIDGE PIPELINES (VIRDEN) INC. Proposed NGL Injection Station and Connecting Pipeline 06-20-09-28 W1M to 03-20-09-28 W1M Near Cromer, Manitoba Manitoba Innovation, Energy and Mines Project Application

More information

Filed: , EB /EB , Exhibit JT1.21, Attachment 1, Page 1 of November 2017

Filed: , EB /EB , Exhibit JT1.21, Attachment 1, Page 1 of November 2017 Filed: 2018-04-04, EB-2017-0306/EB-2017-0307, Exhibit JT1.21, Attachment 1, Page 1 of 9 22 November 2017 The New Enbridge SLIDE 2 Filed: 2018-04-04, EB-2017-0306/EB-2017-0307, Exhibit JT1.21, Attachment

More information

an Inspector appointed by the Secretary of State for Communities and Local Government

an Inspector appointed by the Secretary of State for Communities and Local Government Appeal Decisions Site visit made on 25 November 2014 by R J Marshall LLB DipTP MRTPI an Inspector appointed by the Secretary of State for Communities and Local Government Decision date: 23 January 2015

More information

PUBLIC INFORMATION MEETING

PUBLIC INFORMATION MEETING PUBLIC INFORMATION MEETING Draft Local Official Plan Amendment Coleraine West Employment Area and Secondary Plan File: POPA 14-03 July 9, 2014 7:00 p.m. Caledon Council Chambers Purpose of Presentation

More information

PATRICK ENGINEERING & SURVEYING

PATRICK ENGINEERING & SURVEYING PATRICK ENGINEERING & SURVEYING Patrick L. Brown, R.C.E. 18067 2110 Main Street, Suite A Post Office Box 442 Julian, California 92036 Office (760) 765-1343/Fax (760) 765-2081 E-mail: patrickeng@sbcglobal.net

More information

District of Maple Ridge Telecommunication Antenna Structures Siting Protocols (V2)

District of Maple Ridge Telecommunication Antenna Structures Siting Protocols (V2) District of Maple Ridge Telecommunication Antenna Structures Siting Protocols (V2) Purpose: The purpose of the Telecommunication Antenna Structures Siting Protocols is to establish procedural standards

More information

National Energy Board. Reasons for Decision. Murphy Oil Company Ltd. OH March Application

National Energy Board. Reasons for Decision. Murphy Oil Company Ltd. OH March Application C A N A D A National Energy Board Reasons for Decision Murphy Oil Company Ltd. OH-1-84 March 1985 Application National Energy Board Reasons for Decision In the Matter of Murphy Oil Company Ltd. Application

More information

Discussion Paper: DAMAGE PREVENTION FRAMEWORK FOR FEDERALLY REGULATED POWER LINES

Discussion Paper: DAMAGE PREVENTION FRAMEWORK FOR FEDERALLY REGULATED POWER LINES Discussion Paper: DAMAGE PREVENTION FRAMEWORK FOR FEDERALLY REGULATED POWER LINES Discussion Paper: Damage Prevention Framework for Federally Regulated Power Lines Introduction Bill C-69, which creates

More information

LOWELL CHARTER TOWNSHIP PLANNING COMMISSION PUBLIC HEARING AND REGULAR MEETING October 9, 2006

LOWELL CHARTER TOWNSHIP PLANNING COMMISSION PUBLIC HEARING AND REGULAR MEETING October 9, 2006 LOWELL CHARTER TOWNSHIP PLANNING COMMISSION PUBLIC HEARING AND REGULAR MEETING PRESENT: Blumm, Batchelor, Simmonds, Clements and Sanford ABSENT: None TOWNSHIP PLANNER: Tim Johnson CITIZENS IN ATTENDANCE:

More information

RE: Bolton Residential Expansion Analysis Review of SGL Response to Comments

RE: Bolton Residential Expansion Analysis Review of SGL Response to Comments May 24, 2016 Karen Bennett, MCIP, RPP, Associate Glen Schnarr & Associates Inc. 10 Kingsbridge Garden Circle, Ste.700 Mississauga, ON, L5R 3K6 Dear Ms Bennett: RE: Bolton Residential Expansion Analysis

More information

THUNDERBIRD ENERGY CORP. (formerly MBA RESOURCES CORP.) SIX MONTHS ENDED JULY 31, 2006 MANAGEMENT DISCUSSION AND ANALYSIS

THUNDERBIRD ENERGY CORP. (formerly MBA RESOURCES CORP.) SIX MONTHS ENDED JULY 31, 2006 MANAGEMENT DISCUSSION AND ANALYSIS 1. REPORT DATE AND DESCRIPTION OF BUSINESS The following Management s Discussion and Analysis ( MD&A ) is prepared as of September 25, and should be read in conjunction with the unaudited financial statements

More information

Pipeline Application

Pipeline Application Pipeline Application Crude Oil Pipeline From 12-30-001-25 W1M to 13-17-009-28 W1M And NGL Pipeline From 12-30-001-25 W1M to 13-17-010-28 W1M Southwestern Manitoba Manitoba Innovation, Energy and Mines

More information

NOTICE OF REVISED APPLICATION

NOTICE OF REVISED APPLICATION Ontario Energy Board Commission de l énergie de l Ontario EB-2012-0451 NOTICE OF REVISED APPLICATION Enbridge Gas Distribution Inc. has requested to revise its application for approval to build two segments

More information

CITY OF EDMONTON ANNEXATION APPLICATION APPENDIX 7.0 FISCAL IMPACT ANALYSIS

CITY OF EDMONTON ANNEXATION APPLICATION APPENDIX 7.0 FISCAL IMPACT ANALYSIS CITY OF EDMONTON ANNEXATION APPLICATION APPENDIX 7.0 FISCAL IMPACT ANALYSIS MARCH 2018 Fiscal Impact Analysis of the City of Edmonton s Proposed Annexation Submitted to: City of Edmonton - Sustainable

More information

Gov's Planning Estimates Project Title Rank Fund Project Requests for State Funds

Gov's Planning Estimates Project Title Rank Fund Project Requests for State Funds This document is made available electronically by the Minnesota Legislative Reference Library as part of an ongoing digital archiving project. http://www.leg.state.mn.us/lrl/lrl.asp Water and Soil Resources

More information

Request for Decision STAFF REPORT. Recommendation. Applicant: Location: Application: Proposal: Presented To: Planning Committee

Request for Decision STAFF REPORT. Recommendation. Applicant: Location: Application: Proposal: Presented To: Planning Committee Request for Decision Application for rezoning in order to permit a lot addition to PIN 73366-0188, the abutting property owner s land, Fairbank Road North, Whitefish - Nellie & James Langdon Presented

More information

AMADOR COUNTY PLANNING COMMISSION MINUTES SUMMARY MINUTES OF TAPE RECORDED MEETING MAY 13, :00 P.M. PAGE 1 OF 4

AMADOR COUNTY PLANNING COMMISSION MINUTES SUMMARY MINUTES OF TAPE RECORDED MEETING MAY 13, :00 P.M. PAGE 1 OF 4 MAY 13, 2014 7:00 P.M. PAGE 1 OF 4 The Planning Commission of the County of Amador met at the County Administration Center, 810 Court Street, Jackson, California. The meeting was called to order at 7:00

More information

Metrolinx-City of Toronto-Toronto Transit Commission Master Agreement for Light Rail Transit Projects

Metrolinx-City of Toronto-Toronto Transit Commission Master Agreement for Light Rail Transit Projects STAFF REPORT ACTION REQUIRED Metrolinx-City of Toronto-Toronto Transit Commission Master Agreement for Light Rail Transit Projects Date: October 23, 2012 To: From: Wards: City Council City Manager All

More information

Attention: Ms. Chantal Briand, Regulatory Drafting Specialist Ms. Rebecca Vanderspiegel, Regulatory Development Specialist

Attention: Ms. Chantal Briand, Regulatory Drafting Specialist Ms. Rebecca Vanderspiegel, Regulatory Development Specialist Power Line Damage Prevention Project Team National Energy Board Suite 210, 517 Tenth Avenue SW Calgary, Alberta T2R 0A8 PLdamagepreventionregs@neb-one.gc.ca BY E-MAIL Attention: Ms. Chantal Briand, Regulatory

More information

Zoning Board of Appeals TOWN OF BRUNSWICK 336 Town Office Road Troy, New York 12180

Zoning Board of Appeals TOWN OF BRUNSWICK 336 Town Office Road Troy, New York 12180 Zoning Board of Appeals TOWN OF BRUNSWICK 336 Town Office Road Troy, New York 12180 MINUTES OF THE BRUNSWICK ZONING BOARD OF APPEALS MEETING HELD SEPTEMBER 17, 2018 PRESENT were MARTIN STEINBACH, CHAIRMAN,

More information

3 YORK REGION 2031 POPULATION AND EMPLOYMENT FORECASTS

3 YORK REGION 2031 POPULATION AND EMPLOYMENT FORECASTS 3 YORK REGION 2031 POPULATION AND EMPLOYMENT FORECASTS The Planning and Economic Development Committee recommends: 1. Receipt of the presentation by Paul Bottomley, Manager, Growth Management Economy and

More information

AGREED STATEMENT OF FACTS

AGREED STATEMENT OF FACTS IN THE PROVINCIAL COURT OF ALBERTA CRIMINAL DIVISION Between HER MAJESTY THE QUEEN and MCCOLMAN & SONS DEMOLITION LTD. AGREED STATEMENT OF FACTS SUMMARY OF THE CHARGES 1. The company has pled guilty to

More information

Breezy Hill Farm Leasing Opportunity

Breezy Hill Farm Leasing Opportunity Breezy Hill Farm Leasing Opportunity Lease offering Breezy Hill Farm is a 23-acre farm located in Homeworth, Ohio in Columbiana County. The farm was acquired by Phil and Mindy Bartholomae in the fall of

More information

Wetlands Board Hearing Procedures

Wetlands Board Hearing Procedures Wetlands Board Hearing Procedures The Virginia Beach Wetlands Public Hearing is held at 10:00 a.m. in the Council Chamber of the City Hall Building, Municipal Center. A staff briefing is held at 8:30 a.m.

More information

CITY OF HAMILTON PLANNING AND ECONOMIC DEVELOPMENT DEPARTMENT Growth Management Division

CITY OF HAMILTON PLANNING AND ECONOMIC DEVELOPMENT DEPARTMENT Growth Management Division CITY OF HAMILTON PLANNING AND ECONOMIC DEVELOPMENT DEPARTMENT Growth Management Division TO: Mayor and Members General Issues Committee COMMITTEE DATE: June 20, 2018 SUBJECT/REPORT NO: WARD(S) AFFECTED:

More information

REGIONAL EVALUATION FRAMEWORK 1.0 INTRODUCTION 2.0 PURPOSE 3.0 DEFINITIONS. Edmonton Metropolitan Region Planning Toolkit

REGIONAL EVALUATION FRAMEWORK 1.0 INTRODUCTION 2.0 PURPOSE 3.0 DEFINITIONS. Edmonton Metropolitan Region Planning Toolkit Edmonton Metropolitan Region Planning Toolkit Re-imagine. Plan. Build. Edmonton Metropolitan Region Growth Plan 1.0 INTRODUCTION On October 26, 2017, the Government of Alberta approved the Edmonton Metropolitan

More information

Edmonton Subdivision and Development Appeal Board

Edmonton Subdivision and Development Appeal Board Edmonton Subdivision and Development Appeal Board Churchill Building 10019-103 Avenue NW Edmonton, AB T5J 0G9 Phone: 780-496-6079 Fax: 780-577-3537 Email: sdab@edmonton.ca Web: www.edmontonsdab.ca Notice

More information

KITTITAS RECLAMATION DISTRICT RESOLUTION NO

KITTITAS RECLAMATION DISTRICT RESOLUTION NO KITTITAS RECLAMATION DISTRICT RESOLUTION NO. 2010-002 WHEREAS, the Kittitas Reclamation District previously adopted Article 13 for the purpose of establishing a policy for land reclassification and surrender

More information

Two Models of Corridor Planning The Edmonton Transportation Utility Corridor (TUC) and Northeast Penetrator Corridor (NEPC)

Two Models of Corridor Planning The Edmonton Transportation Utility Corridor (TUC) and Northeast Penetrator Corridor (NEPC) Two Models of Corridor Planning The Edmonton Transportation Utility Corridor (TUC) and Northeast Penetrator Corridor (NEPC) Presented by Lyle Markovich RPP MCIP, Director, Land Planning to Edmonton Region

More information

Article 23-6 FLOODPLAIN DISTRICT

Article 23-6 FLOODPLAIN DISTRICT AMENDING THE CODE OF THE CITY OF PITTSFIELD CHAPTER 23, ZONING ORDINANCE SECTION I That the Code of the City of Pittsfield, Chapter 23, Article 23-6 Floodplain District, shall be replaced with the following:

More information

COVENTRY PLANNING AND ZONING COMMISSION MINUTES REGULAR MEETING MONDAY, AUGUST 27, 2018

COVENTRY PLANNING AND ZONING COMMISSION MINUTES REGULAR MEETING MONDAY, AUGUST 27, 2018 COVENTRY PLANNING AND ZONING COMMISSION MINUTES REGULAR MEETING MONDAY, AUGUST 27, 2018 CALL TO ORDER By: Jobbagy Time: 7:02 p.m. Place: Conference Room B ROLL CALL: PRESENT ABSENT REGULAR MEMBERS: Steven

More information

Enbridge Battle Sands 594S Substation Connection Needs Identification Document

Enbridge Battle Sands 594S Substation Connection Needs Identification Document APPENDIX C AESO PIP Enbridge Battle Sands 594S Substation Connection Needs Identification Document 1.0 Participant Involvement Program (PIP) From June to October 2015, the AESO conducted a Participant

More information

Addendum No. 1 RFP for Residential Subdivision Design Services Questions and Answers to Date and Revision of Project Boundaries Date: January 19, 2017

Addendum No. 1 RFP for Residential Subdivision Design Services Questions and Answers to Date and Revision of Project Boundaries Date: January 19, 2017 Addendum No. 1 RFP for Residential Subdivision Design Services Questions and Answers to Date and Revision of Project Boundaries Date: January 19, 2017 City of Moose Jaw The following addendum (Addendum

More information

The Regional Municipality of Halton. Chair and Members of the Planning and Public Works Committee

The Regional Municipality of Halton. Chair and Members of the Planning and Public Works Committee The Regional Municipality of Halton Report To: From: Chair and Members of the Planning and Public Works Committee Mark G. Meneray, Commissioner, Legislative & Planning Services and Corporate Counsel Date:

More information

Alberta Electric System Operator, AltaLink Management Ltd. and ENMAX Power Corporation. Foothills Area Transmission Development

Alberta Electric System Operator, AltaLink Management Ltd. and ENMAX Power Corporation. Foothills Area Transmission Development Decision 2013-087 Alberta Electric System Operator, AltaLink Management Ltd. and ENMAX Power Corporation Foothills Area Transmission Development March 12, 2013 The Alberta Utilities Commission Decision

More information

ADMINISTRATIVE APPEAL DECISION APPROVED GEOGRAPHIC JURISDICTION FOR DAVENPORT PROPERTY SAN FRANCISCO DISTRICT. File number 20651N.

ADMINISTRATIVE APPEAL DECISION APPROVED GEOGRAPHIC JURISDICTION FOR DAVENPORT PROPERTY SAN FRANCISCO DISTRICT. File number 20651N. ADMINISTRATIVE APPEAL DECISION APPROVED GEOGRAPHIC JURISDICTION FOR DAVENPORT PROPERTY SAN FRANCISCO DISTRICT File number 20651N April 29, 2003 Review Officer: Douglas R. Pomeroy, U.S. Army Corps of Engineers,

More information

MINUTE ORDER COUNTY COMMISSIONERS PUBLIC HEARING MINUTES SEPTEMBER 8, 2015

MINUTE ORDER COUNTY COMMISSIONERS PUBLIC HEARING MINUTES SEPTEMBER 8, 2015 MINUTE ORDER COUNTY COMMISSIONERS PUBLIC HEARING MINUTES SEPTEMBER 8, 2015 CALL TO ORDER: Chair Kelly called the Bonner County Commissioners hearing to order at 3:00 p.m. in the 3rd floor BOCC meeting

More information

REGULAR MEETING JULY 16, 2018 MINUTES

REGULAR MEETING JULY 16, 2018 MINUTES MASON COUNTY PLANNING ADVISORY COMMISSION MASON COUNTY COMMUNITY SERVICES 615 W. ALDER STREET, SHELTON, WA 98584 Meetings held at: Commissioners Chambers 411 N. 5 th Street Shelton, WA 98584 REGULAR MEETING

More information

Ron Maxwell, Code Enforcement Officer. Joe Ardieta, Vanguard (Coast Professional)

Ron Maxwell, Code Enforcement Officer. Joe Ardieta, Vanguard (Coast Professional) on 10/03/16 Town of Geneseo Planning Board Meeting Minutes September 12, 2016 7:00 8:55 PM Members Present: Charles Maxwell David Woods Robert Lennington Darcy Young Bob Irwin Robert Harris Excused: Dwight

More information

Trust Fund 2009 Work Program

Trust Fund 2009 Work Program Trust Fund 2009 Work Program Date of Report: May 8, 2009 Date of Next Progress Report: Dec. 1, 2009 Date of Work Program Approval: Project Completion Date: June 30, 2011 I. PROJECT TITLE: Minnesota s Habitat

More information

The National Energy Board and The TransCanada Alberta System Questions and Answers

The National Energy Board and The TransCanada Alberta System Questions and Answers The National Energy Board and The TransCanada Alberta System Questions and Answers www.neb-one.gc.ca Message from the Chair of the National Energy Board Dear Landowner: As Chair of the National Energy

More information

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND ORDER EB UNION GAS LIMITED. BEFORE: Susan Frank Presiding Member

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND ORDER EB UNION GAS LIMITED. BEFORE: Susan Frank Presiding Member Commission de l énergie de l Ontario DECISION AND ORDER UNION GAS LIMITED Application for leave to construct a natural gas transmission pipeline and associated facilities in the Town of Lakeshore and the

More information

IN THE MATTER OF the Ontario Energy Board Act, 1998,S.O.1998, c. 15 (Schedule B) pursuant to section 90(1);

IN THE MATTER OF the Ontario Energy Board Act, 1998,S.O.1998, c. 15 (Schedule B) pursuant to section 90(1); Ontario Energy Board Commission de l Énergie de l Ontario EB-2010-0302 IN THE MATTER OF the Act, 1998,S.O.1998, c. 15 (Schedule B) pursuant to section 90(1); AND IN THE MATTER OF an application by Enbridge

More information

Board of Variance Minutes

Board of Variance Minutes Board of Variance Minutes City Manager's Board Room City Hall 14245-56 Avenue Surrey, B.C. MONDAY, AUGUST 27, 2001 Time: 9:00 a.m. Present: Chairperson - M. Cooper D. Cutler J. Grenier Absent: B. Dack

More information

Supplementary Development Contributions Scheme - Cobh/Midleton - Blarney Suburban Rail Project

Supplementary Development Contributions Scheme - Cobh/Midleton - Blarney Suburban Rail Project Adopted by Council on 23 rd February, 2004. Supplementary Development Contributions Scheme - Cobh/Midleton - Blarney Suburban Rail Project Under Section 49 of the Planning & Development Act, 2000 Section

More information

TOWN OF DUCK PLANNING BOARD REGULAR MEETING. The Planning Board for the Town of Duck convened at the Duck Meeting Hall on Wednesday, August 14, 2013.

TOWN OF DUCK PLANNING BOARD REGULAR MEETING. The Planning Board for the Town of Duck convened at the Duck Meeting Hall on Wednesday, August 14, 2013. TOWN OF DUCK PLANNING BOARD REGULAR MEETING August 14, 2013 The Planning Board for the Town of Duck convened at the Duck Meeting Hall on Wednesday, August 14, 2013. Present were: Chair Joe Blakaitis, Vice-Chair

More information

ABBOTSFORD. Sa '~A COUNCIL REPORT. Report No. PDS Date: February 11, 2016 File No: /14

ABBOTSFORD. Sa '~A COUNCIL REPORT. Report No. PDS Date: February 11, 2016 File No: /14 Sa '~A ABBOTSFORD Report No. PDS 028-2016 COUNCIL REPORT EXECUTIVE COMMITTEE Date: February 11, 2016 File No: 3220-20/14 To: From: Subject: Mayor and Council Phil Blaker, Director, Building and Development

More information

DECISION AND ORDER ON PHASE 1

DECISION AND ORDER ON PHASE 1 Commission de l énergie de l Ontario DECISION AND ORDER ON PHASE 1 HYDRO ONE NETWORKS INC. Leave to construct a new transmission line and facilities in the Windsor-Essex Region, Ontario. Before: Ken Quesnelle

More information

ADMINISTRATIVE APPEAL DECISION JURISDICTIONAL DETERMINATION MR. MARTIN KNAPPE FILE NUMBER WILMINGTON DISTRICT. DATE: June 16, 2008

ADMINISTRATIVE APPEAL DECISION JURISDICTIONAL DETERMINATION MR. MARTIN KNAPPE FILE NUMBER WILMINGTON DISTRICT. DATE: June 16, 2008 ADMINISTRATIVE APPEAL DECISION JURISDICTIONAL DETERMINATION MR. MARTIN KNAPPE FILE NUMBER 2006-32700-128 WILMINGTON DISTRICT DATE: June 16, 2008 Review Officer: Michael F. Bell, US Army Corps of Engineers,

More information

DRAFT Tier 2 Compliance Letter Guide

DRAFT Tier 2 Compliance Letter Guide DRAFT Tier 2 Compliance Letter Guide November 05, 2018 Title: Number: AEP, Land Policy, 2018, No. # Program Name: Land Conservation and Reclamation Policy Section; Land Policy Branch Effective Date: January

More information

Britannia Village Flood Control Project

Britannia Village Flood Control Project Britannia Village Flood Control Project Summary of Background Information February 2011 Contents 1) Flood Risks in the Village 2) Alternative Flood Risk Management Approaches Status Quo The Proposed Remedial

More information

SOUTH NORTHAMPTONSHIRE COUNCIL STATEMENT OF CASE ON BEHALF OF THE LOCAL PLANNING AUTHORITY

SOUTH NORTHAMPTONSHIRE COUNCIL STATEMENT OF CASE ON BEHALF OF THE LOCAL PLANNING AUTHORITY SOUTH NORTHAMPTONSHIRE COUNCIL STATEMENT OF CASE ON BEHALF OF THE LOCAL PLANNING AUTHORITY Appeal by Mrs. S Biddle against the decision by South Northamptonshire Council to refuse planning permission for

More information

ADMINISTRATIVE APPEAL DECISION CLEAN WATER ACT Mendenhall PROPERTY Tenedor, LLC Utah County, Utah SACRAMENTO DISTRICT FILE NUMBER SPK

ADMINISTRATIVE APPEAL DECISION CLEAN WATER ACT Mendenhall PROPERTY Tenedor, LLC Utah County, Utah SACRAMENTO DISTRICT FILE NUMBER SPK ADMINISTRATIVE APPEAL DECISION CLEAN WATER ACT Mendenhall PROPERTY Tenedor, LLC Utah County, Utah SACRAMENTO DISTRICT FILE NUMBER SPK-2006-50413 DATE: March 28, 2008 Review Officer: Thomas J. Cavanaugh,

More information

1. Call to Order The Presiding Officer calls the statutory public meeting to order and leads those present in a moment of contemplation.

1. Call to Order The Presiding Officer calls the statutory public meeting to order and leads those present in a moment of contemplation. Special Council Meeting Monday, April 30, 2018 7:00 PM Zima Room, Library and Cultural Centre, 425 Holland Street West, Bradford Agenda A meeting of Special Council of The Corporation of the Town of Bradford

More information

THE TWENTY-FOURTH MEETING OF THE PLANNING COMMITTEE OF THE CITY OF GREATER SUDBURY COUNCILLOR LYNNE REYNOLDS PRESIDING

THE TWENTY-FOURTH MEETING OF THE PLANNING COMMITTEE OF THE CITY OF GREATER SUDBURY COUNCILLOR LYNNE REYNOLDS PRESIDING THE TWENTY-FOURTH MEETING OF THE PLANNING COMMITTEE OF THE CITY OF GREATER SUDBURY Committee Room C-11 Tuesday, February 15, 2005 Tom Davies Square Commencement: 4:50 p.m. Adjournment: 6:25 p.m. COUNCILLOR

More information

1. CALL TO ORDER The meeting was called to order at 7:05 p.m.

1. CALL TO ORDER The meeting was called to order at 7:05 p.m. 1 1 1 3 3 0 2 The Lindon City held a regularly scheduled meeting on Tuesday, June, 1 at 7:00 p.m. at the Lindon City Center, City Council Chambers, 0 North State Street, Lindon, Utah. REGULAR SESSION 7:00

More information

Midway City Council 15 January 2019 Regular Meeting. Ordinance / Transmission Lines

Midway City Council 15 January 2019 Regular Meeting. Ordinance / Transmission Lines Midway City Council 15 January 2019 Regular Meeting Ordinance 2019-02 / Transmission Lines CITY COUNCIL MEETING STAFF REPORT DATE OF MEETING: January 15, 2018 NAME OF APPLICANT: Midway City AGENDA ITEM:

More information

Ṡtandard Energy Inc.

Ṡtandard Energy Inc. Decision 2009-059 Ṡtandard Energy Inc. Application for Two Well Licences Grande Prairie Field October 6, 2009 ENERGY RESOURCES CONSERVATION BOARD Decision 2009-059:, Grande Prairie Field October 6, 2009

More information

Village of Lansing Planning Board Meeting February 26, 2013

Village of Lansing Planning Board Meeting February 26, 2013 Village of Lansing Planning Board Meeting February 26, 2013 1 2 3 4 5 6 7 8 9 10 11 12 13 The meeting of the was called to order at 7:35 P.M. by Chairman Mario Tomei. Present at the meeting were Planning

More information

DIRECTIONAL DRILLING. BSA AGM Presentation, 13 th October Peter Shannon, Legal Partner

DIRECTIONAL DRILLING. BSA AGM Presentation, 13 th October Peter Shannon, Legal Partner DIRECTIONAL DRILLING BSA AGM Presentation, 13 th October 2015 Peter Shannon, Legal Partner Directional Drilling The original CSG projects concentrated on vertical wells with a typical well spacing of 750

More information

MINUTES PLANNING COMMISSION. REGULAR MEETING November 6, : 00 P. M.

MINUTES PLANNING COMMISSION. REGULAR MEETING November 6, : 00 P. M. MINUTES PLANNING COMMISSION REGULAR MEETING November 6, 2018 6: 00 P. M. CALL TO ORDER The regular meeting of the Planning Commission of the City of Highland was called to order at 6: 00 p. m. by Chair

More information

Notice of Decision. Construct exterior alteration to an existing Semi-detached House on Lot 42 (Driveway extension, 2.44metres x 6.0metres).

Notice of Decision. Construct exterior alteration to an existing Semi-detached House on Lot 42 (Driveway extension, 2.44metres x 6.0metres). 10019 103 Avenue NW Edmonton, AB T5J 0G9 P: 780-496-6079 F: 780-577-3537 sdab@edmonton.ca edmontonsdab.ca Date: September 7, 2018 Project Number: 284417740-001 File Number: SDAB-D-18-131 Notice of Decision

More information

Decision by Richard Dent, a reporter appointed by the Scottish Ministers

Decision by Richard Dent, a reporter appointed by the Scottish Ministers Directorate for Planning and Environmental Appeals Appeal Decision Notice T: 01324 696 400 F: 01324 696 444 E: dpea@scotland.gsi.gov.uk Decision by Richard Dent, a reporter appointed by the Scottish Ministers

More information

STATEMENT OF REBUTTAL EVIDENCE OF SAM BERNARD LE HERON

STATEMENT OF REBUTTAL EVIDENCE OF SAM BERNARD LE HERON In the matter of the Resource Management Act 1991 And In the matter of the Ruakura Variation to the Hamilton Proposed District Plan STATEMENT OF REBUTTAL EVIDENCE OF SAM BERNARD LE HERON On behalf of Hamilton

More information

ACTON COUNTRY Mobilehome Park

ACTON COUNTRY Mobilehome Park ACTON COUNTRY Mobilehome Park Investment Offering Eric Coulsell Listing Broker 949-383-0813 cell BRE License # 01465230 Eric@Calcomadvisors.com Property Photos Investment Narrative California Commercial

More information

Chairman John England called the June 12, 2008 regular meeting of the Planning Commission to order at 7:30 P.M.

Chairman John England called the June 12, 2008 regular meeting of the Planning Commission to order at 7:30 P.M. AT A MEETING OF THE MIDDLESEX COUNTY PLANNING COMMISSION HELD ON THURSDAY, JUNE 12, 2008 IN THE BOARDROOM OF THE HISTORIC COURTHOUSE, SALUDA, VIRGINIA: Present: John England, Chairman, Saluda District

More information

BEFORE THE CORPORATION COMMISSION OF THE STATE OF OKLAHOMA INTERIM ORDER

BEFORE THE CORPORATION COMMISSION OF THE STATE OF OKLAHOMA INTERIM ORDER r a BEFORE THE CORPORATION COMMISSION OF THE STATE OF OKLAHOMA APPLICANT : ST. MARY LAND & EXPLORATION COMPAN Y RELIEF SOUGHT : LOCATION EXCEPTION ) ) LEGAL DESCRIPTION : THE E/2 OF SECTION 17, ) TOWNSHIP

More information

an Inspector appointed by the Secretary of State for Communities and Local Government

an Inspector appointed by the Secretary of State for Communities and Local Government Appeal Decision Hearing held on 8 April 2014 Site visit made on 8 April 2014 by Anthony Lyman BSc(Hons) DipTP MRTPI an Inspector appointed by the Secretary of State for Communities and Local Government

More information

Walton Ontario. Third Quarter Report 2013 For the three and nine months ended September 30, 2013 and September 30, 2012

Walton Ontario. Third Quarter Report 2013 For the three and nine months ended September 30, 2013 and September 30, 2012 Walton Ontario Land L.P. 1 Third Quarter Report 2013 For the three and nine months ended 2013 and 2012 Table of Contents CEO Message to Unitholders Management s Discussion and Analysis Financial Statements

More information

Charges schemes. New connections and developer services charges scheme 2019/2020 Page 1 of 64

Charges schemes. New connections and developer services charges scheme 2019/2020 Page 1 of 64 s schemes Page 1 of 64 United Utilities Water Limited has published four charges schemes for 2019/2020 charging year. They include the charges to be paid for services provided by us in the course of carrying

More information

I Te Koti Taiao o Aotearoa Ōtautahi Rohe ENV-2018-CHC-

I Te Koti Taiao o Aotearoa Ōtautahi Rohe ENV-2018-CHC- In the Environment Court of New Zealand Christchurch Registry I Te Koti Taiao o Aotearoa Ōtautahi Rohe ENV-2018-CHC- Under In the matter of Between the Resource Management Act 1991 (RMA) An appeal under

More information

FINAL TECHNICAL MEMORANDUM AWD FLOWS THROUGH FLOOD DAMAGE REDUCTION AREA July 16, 2012

FINAL TECHNICAL MEMORANDUM AWD FLOWS THROUGH FLOOD DAMAGE REDUCTION AREA July 16, 2012 FINAL TECHNICAL MEMORANDUM AWD-00002 FLOWS THROUGH FLOOD DAMAGE REDUCTION AREA July 16, 2012 Table of Contents TABLE OF CONTENTS Table of Contents... 1 Executive Summary... 2 1 Objective... 4 2 Study Approach...

More information

George Casey U.S. Army Corps of Engineers, New York District 26 Federal Plaza New York, New York June 2017

George Casey U.S. Army Corps of Engineers, New York District 26 Federal Plaza New York, New York June 2017 The Wetland Trust, 4729 State Route 414, Burdett, NY 14818 607-765-4780 www.thewetlandtrust.org Peter J. Krakowiak U.S. Army Corps of Engineers, Buffalo District Biologist, Regulatory Branch 1776 Niagara

More information

NOTICE OF MEETING SHEBOYGAN COUNTY PLANNING, RESOURCES, AGRICULTURE AND EXTENSION COMMITTEE

NOTICE OF MEETING SHEBOYGAN COUNTY PLANNING, RESOURCES, AGRICULTURE AND EXTENSION COMMITTEE NOTICE OF MEETING SHEBOYGAN COUNTY PLANNING, RESOURCES, AGRICULTURE AND EXTENSION COMMITTEE November 14, 2017 4:15 P.M. UW Extension Office UW Sheboygan Campus 5 University Drive Sheboygan, WI Room 5024

More information

Apr. 21, 2009 Ontario Municipal Board Commission des affaires municipales de l Ontario

Apr. 21, 2009 Ontario Municipal Board Commission des affaires municipales de l Ontario ISSUE DATE: Apr. 21, 2009 Ontario Municipal Board Commission des affaires municipales de l Ontario IN THE MATTER OF subsection 53(19) of the Planning Act, R.S.O. 1990, c. P.13, as amended Appellant: Applicant:

More information