Condor Gold plc. ( Condor or the Company ) Whittle Consulting s Optimisation Study Significantly Enhances Economics

Size: px
Start display at page:

Download "Condor Gold plc. ( Condor or the Company ) Whittle Consulting s Optimisation Study Significantly Enhances Economics"

Transcription

1 Condor Gold plc 7 th Floor 39 St. James s Street London SW1A 1JD Telephone Fax: am on 20 October 2015 Condor Gold plc ( Condor or the Company ) Whittle Consulting s Optimisation Study Significantly Enhances Economics Condor (AIM:CNR), is pleased to announce the results from Whittle Consulting Limited s ( Whittle ) Enterprise Optimisation study on La India Project, Nicaragua (the Study ). The optimisation involves the application of advanced analytical techniques to construct a model of the operation from the ore bodies through mining and ore treatment processes to products sold to the market with a view to maximising a project s economics. The study used the reserves/resources and technical studies used in the NI compliant Pre-Feasibility Study ( PFS ) and Preliminary Economic Assessments ( PEA ) produced by independent mineral resource and mining consultants SRK Consulting Limited ( SRK ) in December Highlights of Optimisation Study: 22% increase in average gold production for the first 5 years, ranging from 91,000 oz to 165,000 oz gold per annum across three production scenarios The object of the optimisation is to bring forward future cashflows 29% increase to 866k oz gold from 674k oz gold of contained gold of Indicated ounces only in the base case La India open pit, as the pit pushes deeper 29% increase to 1,066k oz gold from 827k oz gold contained gold of Indicated and Inferred ounces within La India open pit + two feeder pits 18% increase to 1,544k oz gold from 1,313 oz gold of contained gold of Indicated and Inferred within all pits and underground The model shows payback improves to 2-3 production years across three production scenarios The recovered gold over life of mine ranges from 796,000 oz to 1,437,000 oz gold across the 3 production scenarios AlI in sustaining cash costs remain under US$700 per oz gold for all production scenarios Mark Child CEO comments: The results of the optimisation study are extremely positive. Indicated ounces of gold within the main La India open pit increase by 29% to 866k oz gold as the pit pushes deeper. Contained gold within the pit shells increases 29% to 1,066k oz gold for the main pit and feeder pits. The annual gold production for the first 5 years increases on average 22% and ranges from 91,000 oz gold to 165,000 oz gold per annum versus the PFS and PEA studies. All in sustaining cash costs remain 1

2 under US$700 per oz gold. The recovered gold over life of mine ranges from 796,000 oz to 1,437,000 oz gold. The average pay back of upfront capital costs is between two and three production years, highlighting the outstanding economics and versatility of La India Project. The optimisation study commenced in May 2015 to maximise the economics for four production scenarios at La India Project by bringing forward future cashflows and increasing production ounces. The main optimisation mechanisms applicable to the La India Project are: variable cut-off grade, stockpile use, grind-throughput-recovery, optimised pit and phasing, and multi-mine scheduling Background Whittle Consulting s (Whittle) Enterprise Optimisation is an integrated approach to maximising the economics of a mining business by simultaneously optimizing 10 different mechanisms across the mining value chain. Condor commissioned the independent optimisation study in May 2015 to investigate strategic options to improve project economics. The Study is a strategic planning tool and is not NI compliant. However, Whittle is the recognised world leader in a specialist field of maximising the economics of a mine and has completed work for major mining companies: Rio Tinto, Anglo American, Kinross, AngloGold Ashanti, Barrick, Xstrata, Vale. Four production scenarios were assessed, based on the study methodology employed by SRK and Condor. The PFS case includes measured and indicated material only from the La India open pit, with a processing capacity of 0.8 million tonnes per annum (mtpa) or 2,200 tonnes per day (tpd). The PEA 1.0 case also includes the La India open pit inferred material, with a process capacity of 1.0 mtpa or 2,800tpd The PEA 1.2 case includes all of the La India open pit material, and also includes material from two nearby smaller pits, America and Central Breccia. The processing capacity for this case is 1.2 mtpa or 3,300tpd. This is known as scenario A in the SRK reports. The PEA 1.6 case adds underground mining from La India and America, over and above the material in PEA 1.2. The processing capacity for this case is 1.6 mtpa or 4,400tpd. This is known as scenario B in the SRK reports. Validation runs for each case were produced. Optimised runs were generated using multi-mine scheduling, fully variable cut-off grade and stockpiling. Reduced capacity cases were run, also optimised for schedule, cut-off grade and stockpiling. Grind-throughput-recovery relationships were developed for the La India open pit material, and this methodology was used to further optimize the schedule for all cases. Pit and Phase optimisation was completed on the La India pit using the Enterprise Optimisation economics. The optimised cases were developed from work done from May 2015 through to September The gold price for this work is $1,250 per troy ounce, and the silver price is $19.75/troz in order to have a like for like comparison with the PFS and PEAs. Metal recoveries were based on the PFS and PEA work completed in late The Enterprise Optimisation methodology included the Grind-Throughput-recovery (GTR) work being isolated to La India Vein Set only due to limited metallurgical data on the America and Central Breccia. Similar results may be recognized when data is collected and assessed for the America and Central Breccia open pit and underground material. It is important to note that the 1.0 mtpa case does not have a PFS/PEA study equivalent, nor corresponding pit designs, so there 2

3 is no comparison data. In these cases, improvements are measured against the initial Enterprise Optimisation calibration runs. Table 1. Comparison of optimisation production scenarios to PFS and PEAs La India - PFS La India All Open Pits All Open Pits + UG Open Pit - PFS IND Only Open Pit IND+INF PEA-A IND+INF PEA-B IND+INF PFS Whittle EO Whittle EO PEA A Whittle EO PEA A Whittle EO Nominal Processing Plant capacity tpd 2,200 2,800 3,300 4,400 Nom. Capacity in M-tpa Contained gold koz ,066 1,313 1,554 Recovered gold koz ,203 1,437 1 st 5 years avg. production gold p.a. koz Production improvement 1 st 5 years 20% n/a 25% 20% The initial optimised schedule for the PFS 0.8 mtpa / 2,200 tpd case, utilizing fully variable cut-off grade and a maximum of 1.5 mt of stockpiling. The grind-throughput-recovery methodology improves economics over the prior case due to faster/coarser grinding and reduced costs. The Enterprise Optimisation net value economics generate a larger pit and higher early value phases. Whilst this exercise did generate a larger pit with more ounces, it should be stressed that this is not at a PFS level of study. The PEA 1.2 A case, includes all Measured, Indicated &Inferred material from all three pits, with a nominal processing capacity of 1.2 mtpa (3,300 tpd). There are two cut-off grade and stockpile optimised Prober schedules for reduced processing rates. Cut-off grade and stockpiling improves economics over the PEA A case, and GTR adds to the economics. Overall, the Enterprise Optimisation methodology significantly improved cashflows for the PEA A 1.2. The PEA 1.6 B case includes all of the open pit material available, plus a scoping study view of underground resource from the La India and America deposits, with a nominal processing capacity of 1.6 mtpa / 4400 tpd. For the PEA 1.6 B case, the cut-off grade and stockpile schedule improves economics over the base, and the GTR case adds ounces. The GTR approach had less impact in this case as only the La India material has sufficient information for GTR analysis. With the addition of the Central Breccia (CBZ) material, the America pit material, and the higher grade underground material, there is proportionally less material eligible for this methodology. The Enterprise Optimised economics-base pit and phase optimisation generated significant cashflow. Outcomes This Enterprise Optimisation Study developed the optimised schedules through variable cut-off grade, stockpile capacity, grind-throughput-recovery, multi-mine scheduling, and optimised pit and phasing. Significant outcomes of this process include: 1. An optimised schedule utilizing fully variable cut-off grade with stockpiling adds significantly to greater production ounces and enhanced cashflow in all cases. 3

4 2. The permitted maximum stockpile capacity of 1.5Mt should be utilized, and additional stockpile capacity may increase cashflows and production ounces 3. The grind size-throughput-recovery (GTR) methodology adds significant improved cashflow and production ounces to the project in all cases where it can be utilized. 4. Modification of the ultimate pit and phase selection based on the methodology presented here increases cashflows significantly in all cases, partially due to incorporating additional tonnes and ounces. 5. The theory of constraints indicates using US Dollar per kilowatt hour as the limiting factor in the business system will improve value. The Enterprise Optimised pit and phase optimisation based on this, combined with cut-off and GTR optimisation adds significantly to enhanced economics of the project. 6. When additional mining material is added, processing capacity may not necessarily need to be increased. The Enterprise Optimisation methodology as applied in this study was able to pull cash flow forward. Conclusion Overall, the independent optimisation analysis conducted by Whittle clearly demonstrates the potential to unlock substantial additional production ounces and cashflows from the La India Project. Across 3 production scenarios, the model shows production ounces and cashflows could be increased substantially. The payback on upfront capital costs reduces to between two to three production years, and gold production increases on average 22% for the first 5 years. Whittle s study is a strategic planning tool, which is used to maximise the economics, ahead of a build decision and can often form part of a more detailed Definitive/Bankable Feasibility Study. It should be noted that Whittle s study is not NI compliant and would require re-generation of the PFS and PEAs to confirm the improvements. Whittle Consulting Limited Whittle Consulting s ( approach to Enterprise Optimisation involves the application of advanced analytical techniques to construct a model of the operation from the ore bodies through mining and ore treatment processes to products sold to the market. Once modelled, a powerful mathematical optimiser is applied to manipulate the variables which are regarded as negotiable, to develop long-term plans that excel in terms of a wide range of economic and other operational and business criteria. All the mechanisms required for this study have been implemented before most of them on a routine basis. Because Condor is in an Offer Period as defined under the Takeover Code, any NPV numbers have to be provided by an Independent Valuer for the purposes of Rule 29 of the Takeover Code. Whittle, who were retained before the Offer Period, has acted as an independent optimisation consultant and not as an Independent Valuer and therefore NPV numbers are excluded from this announcement. The Company will consider releasing NPV figures in due course and if then in an Offer Period, fully in accordance with the requirements of Rule 29. Whittle s Enterprise Optimisation study on Condor was prepared by Richard Peevers (B.A. (Geology), MBA (Finance), M.Eng. (Civil), Registered Professional Civil Engineer California). Richard holds degrees in geology, engineering, and business administration and has managed copper, gold, borate, and nickel optimisation studies for Whittle Consulting. 4

5 Competent Person s Declaration Information in this announcement that relates to the project evaluation, Preliminary Feasibility Study, engineering and mine planning is based on information compiled and/or reviewed by Gerald David Crawford, the Chief Operating Officer, who is a Registered Professional Engineer in the states of Colorado and Nevada and member of the Society of Mining, Metallurgy and Exploration, and a mining engineer with 38 years of experience in the design and evaluation of precious and base metal mineral resources. Mr. Crawford is a full-time employee of Condor Gold plc and has sufficient experience which is relevant to the mining method and type of deposit under consideration, and to the type of activity which he is undertaking to qualify as a Qualified Person as defined under Canadian NI Mr. Crawford consents to the inclusion in the announcement of the matters based on their information in the form and context in which it appears and confirms that this information is accurate and not false or misleading. Technical Glossary $/kwhr CBZ CDR COG Constraint Enterprise Optimisation GTR LP mtpa NPV Dollars per kilowatt-hour, one means of optimizing mill throughput. Mills are frequently a bottleneck / constraint in improvement of net present value Central Breccia deposit, a near surface inferred resource located bout 2km to the northeast of the La India Pit Whittle s abbreviation for the Condor project Cut-off Grade - a grade of gold in ore that segregates ore from waste or stockpile material. One of the variables that Prober manipulates to improve NPV A term from Linear Programming, any attribute of a cash flow and operating cost model that serves to limit increases in the net present value of the system Enterprise Optimisation - Whittle terminology for 'Whole Mine' optimisation Grind- Throughput- Recovery- - Prober optimisation of the grind size, gold recovery and mill throughput variables in the EO process Linear Programming - A mathematical technique used to optimize a process subject to a set of constraints Million tonnes per annum (metric tonnes) Net Present Value P&P Pit and Phase - Whittle optimisation of the ultimate pit shell and all contained phases to achieve maximum NPV using EO net value economics PEA Preliminary Economic Assessment - A conceptual-level study used to demonstrate basic economic viability under Canadian National Instrument PFS Preliminary Feasibility Study - Overall economic accuracy of +/- 25% Prober The proprietary software package used by Whittle Consulting Ltd. to implement Enterprise Optimisation Stockpile A means of controlling the grade of material sent through the mill, whereby higher grades are given preferential treatment, particularly when a surplus of ore is available within any mining period. 5

6 Theory of All production processes are limited by any number of factors, such as Constraints advance rate within the mine, truck capacity, or power that can be applied through the SAG mill (for example). Prober uses these constraints to eliminate unworkable scenarios, solving for the maximum NPV achievable within the constraints tr.oz Troy Ounce, standard transaction unit for gold and silver sales, at grams per troy ounce. UG Validation Run Underground Mining The initial test of the Whittle cash flow model and fixed-mining Prober run that ensures that pre-optimisation economics calculated by Whittle agree with existing PFS and PEA results - Ends - For further information please visit or contact: Condor Gold plc Beaumont Cornish Limited Numis Securities Limited Farm Street Media Mark Child, Executive Chairman and CEO +44 (0) Roland Cornish and James Biddle +44 (0) John Prior and James Black +44 (0) Simon Robinson +44 (0) Luc English, Country Manager Nicaragua About Condor Gold plc: Condor Gold plc was admitted to AIM on 31 st May The Company is a gold exploration and development company with a focus on Central America. Condor completed a Pre-Feasibility Study (PFS) and two Preliminary Economic Assessments (PEA) on La India Project in Nicaragua in December The PFS details an open pit gold mineral reserve of 6.9M tonnes at 3.0g/t gold for 675,000 oz gold producing 80,000 oz gold p.a. for 7 years. The PEA for the open pit only scenario details 100,000 oz gold production p.a. for 8 years whereas the PEA for a combination of open pit and underground details 140,000 oz gold production p.a. for 8 years. La India Project contains a total attributable mineral resource of 18.4Mt at 3.9g/t for 2.33M oz gold and 2.68M oz silver at 6.2g/t to the CIM Code. In El Salvador, Condor has an attributable 1,004,000 oz gold equivalent at 2.6g/t JORC compliant resource. The resource calculations are compiled by independent geologists SRK Consulting (UK) Limited for Nicaragua and Ravensgate and Geosure for El Salvador. Consent by Whittle Consulting Whittle Consulting hereby accepts responsibility for the information extracted from the Enterprise Optimisation study prepared for the Company dated 19 October 2015 (and which study adopted the economic and other technical assumptions provided by Condor Gold plc and SRK Consulting (UK) Limited) as contained in this announcement. Furthermore, Whittle Consulting consents to the use of its name in this announcement. 6

7 Disclaimer Neither the contents of the Company's website nor the contents of any website accessible from hyperlinks on the Company's website (or any other website) is incorporated into, or forms part of, this announcement. Whittle Consulting is acting exclusively for Condor Gold plc and no one else in connection with the Enterprise Optimisation study and will not be responsible to anyone other than Condor Gold plc for providing the protections afforded to clients of Whittle Consulting. Neither Whittle Consulting nor any of its affiliates owes or accepts any duty, liability or responsibility whatsoever (whether direct or indirect, whether in contract, in tort, under statute or otherwise) to any person who is not a client of Whittle Consulting in connection with this Announcement, any statement contained herein, or otherwise. Beaumont Cornish Limited, which is authorised and regulated in the United Kingdom by the Financial Conduct Authority, is acting exclusively as Rule 3 adviser to Condor Gold plc and no one else in connection with the Strategic Review (leading to an Offer Period) (the Strategic Review ) and will not be responsible to anyone other than Condor Gold plc for providing the protections afforded to clients of Beaumont Cornish Limited nor for providing advice in relation to the Strategic Review. Neither Beaumont Cornish Limited nor any of its affiliates owes or accepts any duty, liability or responsibility whatsoever (whether direct or indirect, whether in contract, in tort, under statute or otherwise) to any person who is not a client of Beaumont Cornish Limited in connection with this Announcement, any statement contained herein, the Strategic Review or otherwise. The Directors of the Company accept responsibility for the contents of this announcement. A copy of this announcement will be posted to Shareholders and made available, subject to certain restrictions relating to persons resident in restricted jurisdictions, on Condor Gold's website ( under the "Investor Relations" section no later than 12 noon on 21 October

CONDOR GOLD. Mines and Money Conference. 1 st to 3 rd December 2015 CONDOR GOLD PLC

CONDOR GOLD. Mines and Money Conference. 1 st to 3 rd December 2015 CONDOR GOLD PLC CONDOR GOLD Mines and Money Conference 1 st to 3 rd December 2015 DISCLAIMER This written presentation (the "Slides") has been prepared by Condor Gold plc (the "Company"). The Slides are the sole responsibility

More information

Condor Gold plc. ( Condor, Condor Gold or the Company ) Condor Gold plc announces its unaudited results for the three months ended March 31, 2018

Condor Gold plc. ( Condor, Condor Gold or the Company ) Condor Gold plc announces its unaudited results for the three months ended March 31, 2018 Condor Gold plc 7th Floor 39 St. James s Street London SW1A 1JD Telephone +44 020 74932784 Fax: +44 020 74938633 May 15, 2018 Condor Gold plc ( Condor, Condor Gold or the Company ) Condor Gold plc announces

More information

CONDOR GOLD RECEIVES ENVIRONMENTAL PERMIT TO CONSTRUCT AND OPERATE A NEW MINE AT LA INDIA PROJECT, NICARAGUA

CONDOR GOLD RECEIVES ENVIRONMENTAL PERMIT TO CONSTRUCT AND OPERATE A NEW MINE AT LA INDIA PROJECT, NICARAGUA Condor Gold plc 7th Floor 39 St. James s Street London SW1A 1JD Telephone +44 020 74932784 Fax: +44 020 74938633 6 August 2018 Condor Gold plc ( Condor, Condor Gold or the Company ) CONDOR GOLD RECEIVES

More information

CONDOR GOLD. Proactive Investors Presentation 29 th June 2017 CONDOR GOLD PLC

CONDOR GOLD. Proactive Investors Presentation 29 th June 2017 CONDOR GOLD PLC CONDOR GOLD Proactive Investors Presentation 29 th June 2017 Disclaimer This written presentation (the "Slides") has been prepared by Condor Gold plc (the "Company") and is the sole responsibility of the

More information

News Release. B2Gold Corp. Announces Positive Results from the Preliminary Economic Assessment for the Gramalote Project in Colombia

News Release. B2Gold Corp. Announces Positive Results from the Preliminary Economic Assessment for the Gramalote Project in Colombia News Release B2Gold Corp. Announces Positive Results from the Preliminary Economic Assessment for the Gramalote Project in Colombia Vancouver, March 12, 2014 B2Gold Corp. (TSX: BTO, NYSE MKT: BTG, NSX:

More information

NOVEMBER NYSE American: PZG

NOVEMBER NYSE American: PZG NOVEMBER 2017 NYSE American: PZG This Presentation contains forward-looking statements within the meaning of applicable securities laws relating to Paramount Gold Nevada Corp. ( Paramount, we, us, our,

More information

CONDOR GOLD PLC Report and Accounts Year ended 31 December Company number:

CONDOR GOLD PLC Report and Accounts Year ended 31 December Company number: Report and Accounts Year ended 31 December 2016 Company number: 05587987 CONTENTS OF THE FINANCIAL STATEMENTS TABLE OF CONTENTS Page Highlights 2 Chairman s Statement 3 6 Strategic Report 7 9 Project Overview

More information

MEDIA RELEASE OCEANAGOLD UPDATES DIDIPIO NI TECHNICAL REPORT

MEDIA RELEASE OCEANAGOLD UPDATES DIDIPIO NI TECHNICAL REPORT MEDIA RELEASE 30 October 2014 OCEANAGOLD UPDATES DIDIPIO NI 43-101 TECHNICAL REPORT (All figures in US Dollars unless otherwise stated) (MELBOURNE) OceanaGold Corporation (TSX/ASX/NZX: OGC) (the Company

More information

For personal use only. Drilling at Torrecillas July 2011

For personal use only. Drilling at Torrecillas July 2011 Drilling at Torrecillas July 2011 Mundo Mineracao Ltda - Overview Presentation December 2012 1 Disclaimer & Forward-Looking Statements Competent Person s Statement The information in this report that relates

More information

Corporate Presentation December 5, 2017

Corporate Presentation December 5, 2017 Corporate Presentation December 5, 2017 Cautionary Statements Cautionary Note Regarding Forward Looking Statements: Statements made regarding matters which are not historical facts, such as statements

More information

Acacia Mining plc (formerly African Barrick Gold plc) LSE: ACA. ( Acacia or the Company ) Approval of Gokona Underground project at North Mara

Acacia Mining plc (formerly African Barrick Gold plc) LSE: ACA. ( Acacia or the Company ) Approval of Gokona Underground project at North Mara 27 November 2014 Acacia Mining plc (formerly African Barrick Gold plc) LSE:ACA ( Acacia or the Company ) Approval of Gokona Underground project at North Mara Total production of 450,000 ounces over a 5

More information

TUNKILLIA GOLD PROJECT

TUNKILLIA GOLD PROJECT TUNKILLIA GOLD PROJECT Positive Scoping Study establishes that Mungana (ASX: MUX) can become costcompetitive gold producer in South Australia Highlights Technical and economic assessment provides confidence

More information

Spanish Mountain Gold Announces Results of New PEA for the First Zone

Spanish Mountain Gold Announces Results of New PEA for the First Zone 1120-1095 West Pender Street Vancouver, British Columbia, V6E 2M6 Tel: 604.601.3651 April 10, 2017 Spanish Mountain Gold Announces Results of New PEA for the First Zone VANCOUVER, B.C. Spanish Mountain

More information

Shanta Gold Limited. ("Shanta Gold", Shanta or the "Company") Singida NPV and Project Update

Shanta Gold Limited. (Shanta Gold, Shanta or the Company) Singida NPV and Project Update 5 December 2018 Shanta Gold Limited ("Shanta Gold", Shanta or the "Company") Singida NPV and Project Update Shanta Gold (AIM: SHG), the East Africa-focused gold producer, developer and explorer, is pleased

More information

MEDIA RELEASE. OCEANAGOLD HAILE OPTIMISATION STUDY DELIVERS ENHANCED VALUE (All financial figures in US Dollars unless otherwise stated)

MEDIA RELEASE. OCEANAGOLD HAILE OPTIMISATION STUDY DELIVERS ENHANCED VALUE (All financial figures in US Dollars unless otherwise stated) MEDIA RELEASE 26 June 2017 OCEANAGOLD HAILE OPTIMISATION STUDY DELIVERS ENHANCED VALUE (All financial figures in US Dollars unless otherwise stated) (MELBOURNE) OceanaGold Corporation (TSX/ASX: OGC) (the

More information

October 01, 2018 News Release Release #

October 01, 2018 News Release Release # October 01, 2018 News Release Release #17-2018 Monument s Fourth Quarter and Fiscal 2018 Results Gross Revenue of $19.25 Million and Cash Cost of US$753/Oz Vancouver, B.C., October 01, 2018, Monument Mining

More information

QUARTERLY REPORT OCTOBER TO DECEMBER 2014

QUARTERLY REPORT OCTOBER TO DECEMBER 2014 QUARTERLY REPORT OCTOBER TO DECEMBER 2014 Highlights Outlook for March Quarter 2015 TUNGSTEN & MOLYBDENUM Molyhil NT Revised feasibility study completed demonstrating robust economics Continue off-take

More information

Corvus Gold Announces Maiden Resource for Mother Lode Deposit, Nevada

Corvus Gold Announces Maiden Resource for Mother Lode Deposit, Nevada Suite 1750, 700 West Pender St. Vancouver, British Columbia CANADA V6C 1G8 TSX: KOR OTCQX: CORVF Tel: (604) 638-3246 Toll Free: 1-844-638-3246 info@corvusgold.com www.corvusgold.com NR18-15 September 18,

More information

Detour Gold Updates Life of Mine Plan for Detour Lake

Detour Gold Updates Life of Mine Plan for Detour Lake February 4, 2012 NEWS RELEASE Detour Gold Updates Life of Mine Plan for Detour Lake Detour Gold Corporation (TSX: DGC) ( Detour Gold or the Company ) is pleased to announce an updated life of mine plan

More information

Orezone Announces Positive Preliminary Economic Assessment

Orezone Announces Positive Preliminary Economic Assessment Orezone Announces Positive Preliminary Economic Assessment January 22, 2014 - Orezone Gold Corporation (ORE:TSX) is pleased to announce the results of an independent Preliminary Economic Assessment (the

More information

COPPER SHINES BRIGHTLY FOR MCEWEN MINING - ENHANCED ECONOMICS OF LOS AZULES

COPPER SHINES BRIGHTLY FOR MCEWEN MINING - ENHANCED ECONOMICS OF LOS AZULES COPPER SHINES BRIGHTLY FOR MCEWEN MINING - ENHANCED ECONOMICS OF LOS AZULES $2.2 Billion After-Tax NPV@8 and IRR of 20. 3.6 Year Payback at $3.00/lb. Copper and 36 Year Mine Life 45 Million lbs. Average

More information

Bellhaven Receives Favourable Preliminary Economic Assessment for its 100%- Controlled La Mina Gold-(Copper, Silver) Project, Colombia

Bellhaven Receives Favourable Preliminary Economic Assessment for its 100%- Controlled La Mina Gold-(Copper, Silver) Project, Colombia Bellhaven Receives Favourable Preliminary Economic Assessment for its 100%- Controlled La Mina Gold-(Copper, Silver) Project, Colombia PEA Study Highlights La Mina as One of the Lowest Cost Gold Development

More information

For personal use only

For personal use only TUJUH BUKIT PROJECT INDONESIA HEAP LEACH OPERATION ON OXIDE RESOURCE DELIVERS ROBUST PRELIMINARY ECONOMIC ASSESSMENT RESULTS ANNUAL GOLD PRODUCTION - 143,000 OUNCES CASH COSTS - US$376 PER OUNCE (AFTER

More information

Marathon Gold Announces Substantial Improvements in Updated PEA with 44% Increase in Recovered Gold, at the Valentine Lake Gold Camp, Newfoundland

Marathon Gold Announces Substantial Improvements in Updated PEA with 44% Increase in Recovered Gold, at the Valentine Lake Gold Camp, Newfoundland Marathon Gold Announces Substantial Improvements in Updated PEA with 44% Increase in Recovered Gold, at the Valentine Lake Gold Camp, Newfoundland TORONTO, ON October 30, 2018 - Marathon Gold Corporation

More information

Argonaut Gold Announces Updates on the Magino and San Agustin Projects. Magino Metallurgical Column Test Work Shows Results of up to 70% Recovery

Argonaut Gold Announces Updates on the Magino and San Agustin Projects. Magino Metallurgical Column Test Work Shows Results of up to 70% Recovery Argonaut Gold Announces Updates on the Magino and San Agustin Projects Magino Metallurgical Column Test Work Shows Results of up to 70% Recovery The San Agustin Preliminary Economic Assessment Results

More information

SANDSTORM GOLD ROYALTIES RELEASES HOD MADEN PFS AND INCREASES PRODUCTION GUIDANCE

SANDSTORM GOLD ROYALTIES RELEASES HOD MADEN PFS AND INCREASES PRODUCTION GUIDANCE PRESS RELEASE SANDSTORM GOLD ROYALTIES RELEASES HOD MADEN PFS AND INCREASES PRODUCTION GUIDANCE Vancouver, British Columbia June 26, 2018 Sandstorm Gold Ltd. (dba Sandstorm Gold Royalties, Sandstorm or

More information

Golden Star Announces Wassa Mine Feasibility Study Results

Golden Star Announces Wassa Mine Feasibility Study Results Golden Star Announces Wassa Mine Feasibility Study Results TORONTO March 26, 2014 - Golden Star is pleased to announce the results of its Feasibility Study on the development of an underground mining operation

More information

The New Leader in Global Copper

The New Leader in Global Copper The New Leader in Global Copper May 15, 2013 Global Diversified Cautionary Note Regarding Forward-Looking Statement Certain statements and information contained in this presentation, including all statements

More information

Exeter Secures Second Water Source Outlines Pathway for First Stage Development of Caspiche Oxides

Exeter Secures Second Water Source Outlines Pathway for First Stage Development of Caspiche Oxides For Immediate Release: NR 17-01 Exeter Secures Second Water Source Outlines Pathway for First Stage Development of Caspiche Oxides Vancouver, B.C., January 17, 2017: Exeter Resource Corporation (NYSE-MKT:XRA,

More information

OSISKO UPDATES CANADIAN MALARTIC MINE PLAN

OSISKO UPDATES CANADIAN MALARTIC MINE PLAN OSISKO UPDATES CANADIAN MALARTIC MINE PLAN Average Annual Gold Production of 610,000 ounces at US$516 per ounce (2014 2018) Average Annual Gold Production of 597,000 ounces at US$525 per ounce Life of

More information

Whittle Consulting Pty Ltd Strategic Mine Planning Specialists

Whittle Consulting Pty Ltd Strategic Mine Planning Specialists Whittle Consulting Pty Ltd Strategic Mine Planning Specialists www.whittleconsulting.com.au Cut-off Grade Optimisation Gerald Whittle and Jeff Whittle - Feb 07. Intro Whilst processing all material above

More information

For personal use only

For personal use only Sandfire Resources NL ABN 55 105 154 185 Level 2, 31 Ventnor Ave, West Perth Western Australia 6005 Phone: +61 8 6430 3800 Fax: +61 8 6430 3849 Email: info@sandfire.com.au Web: www.sandfire.com.au ASX/Media

More information

First Quarter 2012 Results

First Quarter 2012 Results AGNICO-EAGLE MINES LIMITED First Quarter 2012 Results April 2012 Forward Looking Statements The information in this document has been prepared as at April 27, 2012. Certain statements contained in this

More information

Dalradian Resources Reports Positive Preliminary Economic Assessment for the Curraghinalt Gold Project in Northern Ireland

Dalradian Resources Reports Positive Preliminary Economic Assessment for the Curraghinalt Gold Project in Northern Ireland 2012 No. 12 TSX: DNA Dalradian Resources Reports Positive Preliminary Economic Assessment for the Curraghinalt Gold Project in Northern Ireland TORONTO, ONTARIO - (Marketwire - July 25, 2012) - Dalradian

More information

Avnel Gold Reports that Indicated Resources Increased 55% to 2 Million Ounces at the Kalana Main Project

Avnel Gold Reports that Indicated Resources Increased 55% to 2 Million Ounces at the Kalana Main Project Avnel Gold Reports that Indicated Resources Increased 55% to 2 Million Ounces at the Kalana Main Project ST. PETER PORT, GUERNSEY, October 15, 2014 Avnel Gold Mining Limited ( Avnel Gold or the Company

More information

How Life of Mine and Budgets are Developed Toronto February 14, 2014 agnicoeagle.com

How Life of Mine and Budgets are Developed Toronto February 14, 2014 agnicoeagle.com How Life of Mine and Budgets are Developed Toronto February 14, 2014 FORWARD LOOKING STATEMENTS The information in this document has been prepared as at February 12, 2014. Certain statements contained

More information

2017Year End Conference Call

2017Year End Conference Call COPPER MOUNTAIN MINING A Canadian Copper/Gold Producer TSX:CMMC 2017Year End Conference Call Support Slides February 20, 2018 1 This presentation contains forward-looking statements. These forward-looking

More information

Turquoise Hill files 2016 Oyu Tolgoi Technical Report

Turquoise Hill files 2016 Oyu Tolgoi Technical Report October 21, 2016 Press release Turquoise Hill files 2016 Oyu Tolgoi Technical Report VANCOUVER, CANADA Turquoise Hill Resources today filed an updated compliant independently-prepared technical report

More information

POSITIONING FOR SUSTAINABLE GROWTH

POSITIONING FOR SUSTAINABLE GROWTH POSITIONING FOR SUSTAINABLE GROWTH Island Gold Mine Expansion Case PEA May 29, 2017 TSX NYSE : RIC RICHMONT MINES FORWARD-LOOKING STATEMENTS Safe Harbor Statement & Cautionary Note to U.S. Investors Concerning

More information

KINROSS GOLD CORPORATION

KINROSS GOLD CORPORATION April 1 2014 KINROSS GOLD CORPORATION Results of the Tasiast feasibility study 1 1 CAUTIONARY STATEMENT ON FORWARD-LOOKING INFORMATION All statements, other than statements of historical fact, contained

More information

NEWS RELEASE. Preliminary Economic Assessment of Block 14 Strong Economics at US$1,200/oz

NEWS RELEASE. Preliminary Economic Assessment of Block 14 Strong Economics at US$1,200/oz Orca Gold Inc., 2000-885 West Georgia St., Vancouver, B.C., V6C 3E8, Canada Tel: +1 604 689 7842 Fax: +1 604 689 4250 NEWS RELEASE Preliminary Economic Assessment of Block 14 Strong Economics at US$1,200/oz

More information

FORWARD LOOKING STATEMENTS

FORWARD LOOKING STATEMENTS FORWARD LOOKING STATEMENTS We are in the mineral exploration and development business. It is inherently risky, and all potential investors should be keenly aware of this. This presentation contains forward-looking

More information

McEWEN MINING ANNOUNCES POSITIVE FEASIBILTY STUDY FOR EL GALLO PHASE II, MEXICO

McEWEN MINING ANNOUNCES POSITIVE FEASIBILTY STUDY FOR EL GALLO PHASE II, MEXICO McEWEN MINING ANNOUNCES POSITIVE FEASIBILTY STUDY FOR EL GALLO PHASE II, MEXICO TORONTO, ONTARIO - (September 10, 2012) - McEwen Mining Inc. (NYSE: MUX) (TSX: MUX) is pleased to announce results of the

More information

Nusantara Resources Low cost gold development + Exploration

Nusantara Resources Low cost gold development + Exploration Martin Pyle Mike Spreadborough Boyke Abidin Rob Hogarth Craig Smyth C o r p o r a t Capital Structure ASX Code: NUS Shares 97.5 m. Options 37.4 m.av $0.42 Price $ 0.345 Market Cap $ 34 m. Cash (est Dec

More information

LEAGOLD FILES UPDATED TECHNICAL REPORT FOR LOS FILOS GOLD MINE, INCREASING RESERVES BY 59% TO 2.7 MILLION OUNCES GOLD

LEAGOLD FILES UPDATED TECHNICAL REPORT FOR LOS FILOS GOLD MINE, INCREASING RESERVES BY 59% TO 2.7 MILLION OUNCES GOLD News Release TSX: LMC March 8, 2018 LEAGOLD FILES UPDATED TECHNICAL REPORT FOR LOS FILOS GOLD MINE, INCREASING RESERVES BY 59% TO 2.7 MILLION OUNCES GOLD Vancouver, March 8, 2018 Leagold Mining Corporation

More information

Tepal Gold/Copper Project

Tepal Gold/Copper Project Tepal Gold/Copper Project Developing Mexico s Next Porphyry Belt CORPORATE PRESENTATION April 2017 Forward-Looking Statements Cautionary Statement on Forward-Looking Information & Statements This presentation

More information

ATLANTIC ANNOUNCES STRATEGIC INVESTMENT IN VELOCITY MINERALS LTD.

ATLANTIC ANNOUNCES STRATEGIC INVESTMENT IN VELOCITY MINERALS LTD. ATLANTIC ANNOUNCES STRATEGIC INVESTMENT IN VELOCITY MINERALS LTD. January 17, 2019 Canadian dollars unless otherwise noted Vancouver, British Columbia Atlantic Gold Corporation (TSX-V: AGB) ("Atlantic"

More information

Corporate Update. June 2013

Corporate Update. June 2013 Corporate Update June 2013 FORWARD LOOKING STATEMENTS The information in this document has been prepared as at June 5, 2013. Certain statements contained in this document constitute forwardlooking statements

More information

AGNICO-EAGLE MINES LIMITED. Corporate Update. May 2012

AGNICO-EAGLE MINES LIMITED. Corporate Update. May 2012 AGNICO-EAGLE MINES LIMITED Corporate Update May 2012 Forward Looking Statements The information in this document has been prepared as at May 16, 2012. Certain statements contained in this document constitute

More information

Allied Nevada Announces Improved Mine Plan and Economics for Hycroft Mill Expansion With 77% IRR and $2.7 Billion NPV

Allied Nevada Announces Improved Mine Plan and Economics for Hycroft Mill Expansion With 77% IRR and $2.7 Billion NPV Allied Nevada Gold Corp. 9790 Gateway Drive Suite 200 Reno, NV 89521 USA NEWS RELEASE Allied Nevada Announces Improved Mine Plan and Economics for Hycroft Mill Expansion With 77% IRR and $2.7 Billion NPV

More information

May 31, 2017 News Release SILVER STANDARD FORMS JOINT VENTURE WITH GOLDEN ARROW AND FILES TECHNICAL REPORT FOR THE CHINCHILLAS PROJECT

May 31, 2017 News Release SILVER STANDARD FORMS JOINT VENTURE WITH GOLDEN ARROW AND FILES TECHNICAL REPORT FOR THE CHINCHILLAS PROJECT May 31, 2017 News Release 17 18 SILVER STANDARD FORMS JOINT VENTURE WITH GOLDEN ARROW AND FILES TECHNICAL REPORT FOR THE CHINCHILLAS PROJECT VANCOUVER, B.C. -- Silver Standard Resources Inc. (NASDAQ: SSRI)

More information

SCOTGOLD RESOURCES LIMITED

SCOTGOLD RESOURCES LIMITED SCOTGOLD RESOURCES LIMITED Proactive Investor Forum Presentation London 12 January 2017 Disclaimer This presentation is provided for the sole purpose of providing preliminary technical, financial and other

More information

MIDWAY ANNOUNCES SIGNIFICANT UPGRADE IN RESOURCE AND 2014 BUDGET INCREASE AT SPRING VALLEY PROJECT, NEVADA

MIDWAY ANNOUNCES SIGNIFICANT UPGRADE IN RESOURCE AND 2014 BUDGET INCREASE AT SPRING VALLEY PROJECT, NEVADA MIDWAY ANNOUNCES SIGNIFICANT UPGRADE IN RESOURCE AND 2014 BUDGET INCREASE AT SPRING VALLEY PROJECT, NEVADA August 12, 2014 Denver, Colorado Midway Gold Corp. ("Midway" or the "Company") (MDW:TSX, MDW:NYSE-

More information

PLATFORM FOR GROWTH. BMO Global Metals & Mining Conference. February 25 28, 2018

PLATFORM FOR GROWTH. BMO Global Metals & Mining Conference. February 25 28, 2018 PLATFORM FOR GROWTH BMO Global Metals & Mining Conference February 25 28, 2018 FORWARD-LOOKING STATEMENT Certain statements contained herein may constitute forward-looking statements (or forward-looking

More information

KBL Mining Limited (ASX: KBL) Presentation May 2015 Resources Investment Symposium BROKEN HILL

KBL Mining Limited (ASX: KBL) Presentation May 2015 Resources Investment Symposium BROKEN HILL KBL Mining Limited (ASX: KBL) Presentation May 2015 Resources Investment Symposium BROKEN HILL Disclaimer This presentation and these materials (together the Presentation ) has been prepared by KBL Mining

More information

Filo del Sol Pre-Feasibility Study Results Webcast & Conference Call Presentation January 15, 2019

Filo del Sol Pre-Feasibility Study Results Webcast & Conference Call Presentation January 15, 2019 Filo del Sol Pre-Feasibility Study Results Webcast & Conference Call Presentation January 15, 2019 Cautionary Note Regarding Forward-Looking Statements Certain statements made and information contained

More information

Africa Projects February 2016

Africa Projects February 2016 Africa Projects Cautionary statement Cautionary statement regarding forward looking statements: This presentation contains forward-looking statements within the meaning of Section 27A of the Securities

More information

Q P R E S T E A P E A R E S U L T S

Q P R E S T E A P E A R E S U L T S Q 4 2 0 1 4 P R E S T E A P E A R E S U L T S 1 1. 1 4 DISCLAIMER AND OTHER MATTERS SAFE HARBOR: Some statements contained in this presentation are forwardlooking statements within the meaning of the Private

More information

INVESTOR PRESENTATION March 2017

INVESTOR PRESENTATION March 2017 INVESTOR PRESENTATION March 2017 1 1 Overview 100% owner of Big Springs Gold Project, north-east Nevada, USA 1 Mil ounce resource Fully permitted to commence mining operations Low capex requirement Mining

More information

For personal use only

For personal use only ASX Announcement 29 January 2014 Quarterly Activities Report December 2013 Project geologists inspecting new drill core from the Natougou Gold Project. Orbis Gold Limited ACN 120 212 017 ASX Code : OBS

More information

For personal use only

For personal use only 25 July 2013 ASX Code: BAB, AIM Code: BGL QUARTERLY ACTIVITY REPORT FOR THE THREE MONTHS ENDED 30 JUNE 2013 Highlights Exploration and Resource Development Resources upgraded at the Gryphon and Edwards

More information

TRANSATLANTIC MINING - NI AND PRELIMINARY ECONOMIC ASSESSMENT ALDER GULCH PROJECT US GRANT MINE

TRANSATLANTIC MINING - NI AND PRELIMINARY ECONOMIC ASSESSMENT ALDER GULCH PROJECT US GRANT MINE TRANSATLANTIC MINING - NI 43-101 AND PRELIMINARY ECONOMIC ASSESSMENT ALDER GULCH PROJECT US GRANT MINE 12 th December 2016 TSX Venture Exchange Vancouver, British Columbia Trading Symbol: TCO Transatlantic

More information

PRESS RELEASE TSX NYSE: RIC

PRESS RELEASE TSX NYSE: RIC PRESS RELEASE TSX NYSE: RIC Richmont Mines Reports Strong Results from the Island Gold Mine Expansion Case Preliminary Economic Assessment Positive First Step in a Multi-Phased Transformation of the Island

More information

The New Leader in Global Copper. June, 2013

The New Leader in Global Copper. June, 2013 The New Leader in Global Copper June, 2013 Cautionary Note Regarding Forward-Looking Statement Certain statements and information contained in this presentation, including all statements that are not historical

More information

NEWS RELEASE GREAT PANTHER SILVER REPORTS POSITIVE PRELIMINARY ECONOMIC ASSESSMENT FOR THE CORICANCHA MINE

NEWS RELEASE GREAT PANTHER SILVER REPORTS POSITIVE PRELIMINARY ECONOMIC ASSESSMENT FOR THE CORICANCHA MINE May 31, 2018 For Immediate Release NEWS RELEASE TSX: GPR NYSE AMERICAN: GPL GREAT PANTHER SILVER REPORTS POSITIVE PRELIMINARY ECONOMIC ASSESSMENT FOR THE CORICANCHA MINE Potential for Average Annual Production

More information

International Tower Hill Mines Announces Livengood Gold Project Feasibility Study Results

International Tower Hill Mines Announces Livengood Gold Project Feasibility Study Results 1177 West Hastings Street Suite 2300 Vancouver, BC Canada V6E 2K3 www.ithmines.com NR13-07 July 23, 2013 International Tower Hill Mines Announces Livengood Gold Project Feasibility Study Results Vancouver,

More information

CANADA S INTERMEDIATE GOLD PRODUCER LOM Presentation / Workshop 25 January 2016

CANADA S INTERMEDIATE GOLD PRODUCER LOM Presentation / Workshop 25 January 2016 CANADA S INTERMEDIATE GOLD PRODUCER 1 2016 LOM Presentation / Workshop 25 January 2016 Forward Looking Information This presentation contains certain forward-looking information and statements as defined

More information

2014 First Quarter Highlights

2014 First Quarter Highlights News Release B2Gold Reports First Quarter 2014 Gold Production and Revenue. Otjikoto Mine Construction Remains on Track for Completion in the Fourth Quarter of 2014. Vancouver, April 30, 2014 B2Gold Corp.

More information

Candelaria Gold & Silver Stream

Candelaria Gold & Silver Stream Candelaria Gold & Silver Stream October 6, 2014 Cautionary Statement Forward-Looking Statements This presentation contains forward looking information and forward looking statements within the meaning

More information

Panda Hill Niobium Project. January 2014

Panda Hill Niobium Project. January 2014 Panda Hill Niobium Project January 2014 ASX Capital Structure Issued Shares* 128,675,017 Unlisted options (May 2016 at 26.7c) 7,687,500 Listed options (January 2015 at 26.7c) 15,962,506 Total Options 23,650,006

More information

URSA Major Minerals Incorporated Press Release UMJ TSX March 2, 2012 URSA Major Minerals and Prophecy Platinum sign business combination agreement

URSA Major Minerals Incorporated Press Release UMJ TSX March 2, 2012 URSA Major Minerals and Prophecy Platinum sign business combination agreement URSA Major Minerals Incorporated Press Release UMJ TSX March 2, 2012 URSA Major Minerals and Prophecy Platinum sign business combination agreement Ursa Major Minerals Incorporated ("Ursa") (TSX: UMJ) and

More information

GROWTH THROUGH CASH FLOW. Q Results 3 August 2017

GROWTH THROUGH CASH FLOW. Q Results 3 August 2017 GROWTH THROUGH CASH FLOW 2017 Results 3 August 2017 2 DISCLOSURES Forward Looking Statements: There are risks associated with an investment in the shares of Centamin. Recipients of this presentation should

More information

Stock Symbol: AEM (NYSE and TSX) For further information: Investor Relations (416)

Stock Symbol: AEM (NYSE and TSX) For further information: Investor Relations (416) Stock Symbol: AEM (NYSE and TSX) For further information: Investor Relations (416) 947-1212 (All amounts expressed in U.S. dollars unless otherwise noted) AGNICO-EAGLE FILES NEW TECHNICAL REPORT ON GOLDEX

More information

September 2014 Quarterly Results

September 2014 Quarterly Results September 2014 Quarterly Results Sandeep Biswas Managing Director and Chief Executive Officer 21 October 2014 Disclaimer Forward Looking Statements These materials include forward looking statements. Often,

More information

For Immediate Release Date: July 4, 2017 # ORVANA PROVIDES UPDATE ON DON MARIO OPERATION; ANNOUNCES US$11.3 MILLION DEBT FINANCING

For Immediate Release Date: July 4, 2017 # ORVANA PROVIDES UPDATE ON DON MARIO OPERATION; ANNOUNCES US$11.3 MILLION DEBT FINANCING For Immediate Release TSX:ORV Date: July 4, 2017 #07-2017 ORVANA PROVIDES UPDATE ON DON MARIO OPERATION; ANNOUNCES US$11.3 MILLION DEBT FINANCING TORONTO, ONTARIO, July 4, 2017 - Orvana Minerals Corp.

More information

A PROFITABLE, GROWTH-ORIENTED, INTERMEDIATE GOLD PRODUCER DECEMBER 2014

A PROFITABLE, GROWTH-ORIENTED, INTERMEDIATE GOLD PRODUCER DECEMBER 2014 A PROFITABLE, GROWTH-ORIENTED, INTERMEDIATE GOLD PRODUCER DECEMBER 2014 1 Cautionary Statement This presentation includes certain forward-looking statements within the meaning of applicable securities

More information

TAMPIA GOLD PROJECT FEASIBILITY STUDY

TAMPIA GOLD PROJECT FEASIBILITY STUDY TAMPIA GOLD PROJECT FEASIBILITY STUDY DEVELOPING A NEW GOLD MINE EXPLORING A POTENTIAL NEW GOLD FIELD ASX:EXU 1 TAMPIA GOLD PROJECT Western Australian gold explorer focused on developing the shallow high

More information

THE ELEMENTS OF VALUE CREATION. Revised Prefeasibility Study Results. Dumont Nickel Project May 14, 2012

THE ELEMENTS OF VALUE CREATION. Revised Prefeasibility Study Results. Dumont Nickel Project May 14, 2012 THE ELEMENTS OF VALUE CREATION Revised Prefeasibility Study Results Dumont Nickel Project May 14, 2012 Disclaimer Cautionary Statements Concerning Forward Looking Statements This presentation contains

More information

For further information: Investor Relations (416)

For further information: Investor Relations (416) For further information: Investor Relations (416) 947-1212 (All amounts expressed in U.S. dollars unless otherwise noted) AGNICO EAGLE COMPLETES UPDATED NI 43-101 TECHNICAL REPORT ON THE MELIADINE GOLD

More information

Minera IRL Announces Successful Feasibility Study for Don Nicolas Project in Argentina

Minera IRL Announces Successful Feasibility Study for Don Nicolas Project in Argentina Minera IRL Announces Successful Feasibility Study for Don Nicolas Project in Argentina London and Toronto, 14 February 2012: Minera IRL Limited ( Minera IRL or the Company ), (TSX:IRL) (AIM:MIRL) (BVL:MIRL),

More information

December Developing Copper, Zinc and Gold Deposits on the Asmara Project, Eritrea. November 2010

December Developing Copper, Zinc and Gold Deposits on the Asmara Project, Eritrea. November 2010 November 2010 December 2013 Underground workings at Debarwa copper-gold deposit Developing Copper, Zinc and Gold Deposits on the Asmara Project, Eritrea Eritrea and the Asmara Project Sudan Zara Bisha

More information

SUITE WEST HASTINGS STREET VANCOUVER, BC V6C 2W2 CANADA TEL: FAX: November 12, 2009

SUITE WEST HASTINGS STREET VANCOUVER, BC V6C 2W2 CANADA TEL: FAX: November 12, 2009 SUITE 900-999 WEST HASTINGS STREET VANCOUVER, BC V6C 2W2 CANADA TEL: 604.684.8894 FAX: 604.688.2180 FOR IMMEDIATE RELEASE November 12, 2009 #09-36 Capstone Reports Strong Third Quarter and Year-to-Date

More information

For personal use only

For personal use only Company Presentation The year Northern Star catches up with its peers as a gold mid- cap producer April 2012 Disclaimer Competent Persons Statements The information in this announcement that relates to

More information

For personal use only

For personal use only INDEPENDENCE GROUP NL PETER BRADFORD, MANAGING DIRECTOR AND CEO Australian Nickel Conference 20 October 2016 Cautionary statements & disclaimer This presentation has been prepared by Independence Group

More information

Shanta Gold Limited ("Shanta Gold", Shanta or the "Company") Q PRODUCTION & OPERATIONAL UPDATE

Shanta Gold Limited (Shanta Gold, Shanta or the Company) Q PRODUCTION & OPERATIONAL UPDATE 19 July 2018 Shanta Gold Limited ("Shanta Gold", Shanta or the "Company") Q2 2018 PRODUCTION & OPERATIONAL UPDATE Shanta Gold (AIM: SHG), the East Africa-focused gold producer, developer and explorer,

More information

Media Announcement (For Immediate Release)

Media Announcement (For Immediate Release) LionGold Corp Ltd (Incorporated in Bermuda) 59 Mohamed Sultan Road Sultan Link 02-08 Singapore 238999 Tel: (65) 6690 6860 Fax: (65) 6690 6844 info@liongoldcorp.om www.liongoldcorp.com Media Announcement

More information

First Six Months a Success Exploration Looking Good. May 2016

First Six Months a Success Exploration Looking Good. May 2016 First Six Months a Success Exploration Looking Good May 2016 Disclaimer Forward Looking Statements These materials include forward looking statements. Forward looking statements inherently involve subjective

More information

Côté Gold Project Feasibility Study Conference Call

Côté Gold Project Feasibility Study Conference Call Côté Gold Project Feasibility Study Conference Call November 2, 2018 l TSX: IMG l NYSE: IAG l Cautionary Statement All information included in this presentation whether in narrative or chart form, including

More information

MCEWEN MINING REPORTS 2017 FULL YEAR AND Q4 RESULTS

MCEWEN MINING REPORTS 2017 FULL YEAR AND Q4 RESULTS MCEWEN MINING REPORTS 2017 FULL YEAR AND Q4 RESULTS TORONTO, February 22, 2018 - (NYSE: MUX) (TSX: MUX) today reported fourth quarter and full year results for the period ended December 31, 2017. For the

More information

Morila our company maker in a post mining legacy. Chiaka Berthe

Morila our company maker in a post mining legacy. Chiaka Berthe Morila our company maker in a post mining legacy Chiaka Berthe Investor Days November 2016 Morila history 2002 Morila Produces 1.05Moz of gold 2008 Randgold took over Morila operatorship 2000 AngloGold

More information

NEWS RELEASE JANUARY 29, 2015

NEWS RELEASE JANUARY 29, 2015 NEWS RELEASE 15-02 JANUARY 29, 2015 PILOT GOLD ANNOUNCES REVISED PRELIMINARY ECONOMIC ASSESSMENT FOR HALILAGA COPPER-GOLD PORPHYRY PROJECT Project Generates After-tax 43.1% IRR and US$474 Million NPV 7%

More information

Enterprise Optimisation

Enterprise Optimisation Enterprise Optimisation G Whittle 1 ABSTRACT Enterprise Optimisation is a methodology for increasing the value of mining and mineral processing operations through better long-term planning decisions. It

More information

Alecto Minerals plc / EPIC: ALO / Market: AIM / Sector: Exploration & Development. Alecto Minerals plc ( Alecto or the Company )

Alecto Minerals plc / EPIC: ALO / Market: AIM / Sector: Exploration & Development. Alecto Minerals plc ( Alecto or the Company ) 29 September 2015 Alecto Minerals plc / EPIC: ALO / Market: AIM / Sector: Exploration & Development Alecto Minerals plc ( Alecto or the Company ) Scoping Study Demonstrates Robust Economics for a Joint

More information

20% Increase in T3 Feasibility Study Plant Throughput to 3Mtpa

20% Increase in T3 Feasibility Study Plant Throughput to 3Mtpa 10 August 2018 ASX: MOD 20% Increase in T3 Feasibility Study Plant Throughput to 3Mtpa T3 plant throughput capacity increased to 3Mtpa, a 20% increase to the PFS Base Case Sedgman appointed as Feasibility

More information

A Canadian Focused Gold Producer

A Canadian Focused Gold Producer A Canadian Focused Gold Producer CORPORATE PRESENTATION Denver Gold Forum September 2018 1 Cautionary statements ALL AMOUNTS IN U.S. DOLLARS UNLESS OTHERWISE STATED CAUTIONARY NOTE REGARDING FORWARD-LOOKING

More information

A Z E R B A I J A N G O L D, C O P P E R A N D S I L V E R P R O D U C E R

A Z E R B A I J A N G O L D, C O P P E R A N D S I L V E R P R O D U C E R A Z E R B A I J A N G O L D, C O P P E R A N D S I L V E R P R O D U C E R A C A S H G E N E R A T I V E M I N I N G B U S I N E S S P R O A C T I V E I N V E S T O R S E V E N I N G F E B R U A R Y 2

More information

SILVER PRODUCER STRENGTH UPSIDE PRIMARY SILVER PRODUCER. Primary Silver Producer 55% Ag, 36% Au, 9% Pb-Zn

SILVER PRODUCER STRENGTH UPSIDE PRIMARY SILVER PRODUCER. Primary Silver Producer 55% Ag, 36% Au, 9% Pb-Zn PRIMARY SILVER PRODUCER SILVER Primary Silver Producer 55% Ag, 36% Au, 9% Pb-Zn PRODUCER Two 100% owned mines in Mexico Unhedged Ag & Au STRENGTH Strong balance sheet; no debt $21.8 M cash, $38.2 M working

More information

All amounts are in US dollars, unless otherwise indicated.

All amounts are in US dollars, unless otherwise indicated. TSX: IMG NYSE: IAG NEWS RELEASE IAMGOLD S FEASIBILITY STUDY FOR BOTO GOLD DELIVERS SIGNIFICANTLY IMPROVED PROJECT ECONOMICS 23% After-tax Internal Rate of Return Payback 3.4 years Net Present Value $261

More information

November 28, 2018 News Release Release #

November 28, 2018 News Release Release # November 28, 2018 News Release Release #21-2018 Monument Reports First Quarter Fiscal 2019 Results Gross Revenue of $5.53 Million and Cash Cost of US$617/Oz Vancouver, B.C., November 28, 2018, Monument

More information

AZUMAH MINING LEASES GRANTED

AZUMAH MINING LEASES GRANTED AZUMAH MINING LEASES GRANTED WA GOLD PROJECT, GHANA ASX & Media Release ASX Code AZM 28 th July 2014 Perth-based gold explorer and developer Azumah Resources Limited (ASX:AZM) (Azumah or the Company) is

More information