REALISEGRID. Final Conference. Brussels, May TSO incentivization policies for cross-border transmission development

Size: px
Start display at page:

Download "REALISEGRID. Final Conference. Brussels, May TSO incentivization policies for cross-border transmission development"

Transcription

1 REALISEGRID Final Conference Brussels, May 2011 TSO incentivization policies for cross-border transmission development M. Urbani - OME G. Migliavacca and A. L Abbate - RSE

2 Outline Background Building cross-border interconnections in Europe: goals and barriers Regulation of transmission investment : regulated approaches and merchant lines option RES and grid infrastructure Cross-border transmission investments: costs, benefits, incentives and Policy recommendations TSOs and financial markets 2

3 Background The electricity sector liberalization has modified the European energy panorama: unbundling - markets integration - new firm strategies TSOs (natural monopoly): asnew companies in a regulated environment, some of them have been privatized and in case of stock companies, they need to make profits. The regulator has to enforce a planning investment policy favouring the social welfare achievement. The increasing penetration of variable generation obliges to rethink the whole European transmission system: huge investments required to intensify European coordination A regulatory framework should be then implemented to provide TSOs with clear incentive schemes in order to foster a pan- European transmission development. 3

4 Cross-border Interconnections in Europe: Policy Goals The trade-off is between minimizing network costs (investing efficiently for meeting reliability standards) and making additional investments for facilitating: Competition and RES integration 4

5 Cross-border Interconnections Investments: Main drawbacks 5

6 Transmission Investments Regulation: Regulatory Approaches 6

7 Regulated Investments: Cost of Service Regulation Financial risk very small Advantageous with major investment and economic uncertainties No incentives to reduce costs No incentive to invest if the rate-of-return is too low Risk of overinvestment Asymmetry of information 7

8 Regulated Investments: Incentive Regulation Incentive to promote efficiency Inconvenient with long-term and lumpy investments No incentive if the performance index does not reflect real costs Risk of underinvestment 8

9 Merchant transmission investments Merchant lines will not be an "alternative" to regulated investments as they represent a limitation to the market liberalization and a ultima ratio (Art. 17, Reg. 714/2009). It will be less expensive for the network users as a whole to pay the cost of the line than to pay the congestion rent (CEER, 2004) Profit-driven investors will have an incentive to maximize profits rather than welfare (Joskow &Tirole, 2005). There is a risk that the construction of a merchant line prevents the one of a regulated line. However, without a certain remuneration incentive scheme, an unregulated investor could be more enticed to invest in a crossborder merchant line than a TSO in a regulated asset, especially when the lumpiness is significant. An increase of merchant interconnectors (especially HVDC) has been recorded in Europe in the latest years. In some cases the exemption has been granted for the starting years (7-10 years e.g.), before making the interconnector a regulated asset (e.g. Estlink 1). 9

10 RES and grid infrastructure RES connection cost allocations: from deep to super-shallow Super-shallow grid integration charging policy option has been developed in the GreenNet-Europe projects recently for large scale offshore-wind farms 10

11 RES and grid infrastructure If grid related cost of RES integration are allocated to TSOs, a re-design of financial RES support instruments should be envisaged (e.g. like feed-in tariffs) 11

12 Cross-border Network Investments: Costs & Benefits 12

13 Cost-benefit analysis and Incentives 13

14 Policy Recommendations: cost-benefit KPI Also, national regulators should recognize extra-territorial costs in their Regulatory Asset Base (regulatory gap). Such approach would minimize the TSOs investment risk. 14

15 Cost-benefit analysis and cross-border incentives TSOs are not motivated to build new cross-border links in situations in which: 1. they operate a power exporting system, where the local customers could see a reduction of their social welfare. This reduction could be compensated either via cross-subsidization between importing and exporting countries (less probable) or via welfare transfer from producers to consumers of the exporting country. On the other side, in an importing system, there is always a social welfare increase. In the coupling of two systems, one importing and one exporting, there is always a global social welfare increase. 2. they operate the power system of a transited country (or area). An extensive concept of the Inter-TSO Compensation (ITC) would then be necessary. Cross-border incentives and the related KPI can be crucial elements for stimulating trans-national investments 15

16 Policy Recommendations: Towards a new ITC mechanism? The present formulation of ITC significantly deviates from a truly cost-reflective scheme and does not send good incentives A new ITC (or just a stricter interpretation of Art.13-6, Reg. 714/2009) covering investment costs and not only operative ones, could be a suitable solution: 1) for creating a broader regional and pan-european consensus 2) for allocating costs between regions in a standardized way 3) for balancing incentivization drivers for CBT investments Art.13-6: The costs incurred as a result of hosting cross border flows shall be established on the basis of the forward looking long run average incremental costs, taking into account losses, investments in new infrastructure ( ) 3 March 2011 ENTSO-E puts in place an enduring ITC but incentives remain weak. 16

17 Policy Recommendations: TSOs proactive behavior In a liberalized power market, transmission and generation investments are decoupled, thus the investments coordination is more difficult, especially between two different countries. EC coordinators approach: successful but not enough. Literature (Glachant & Rious, 2010) suggests to anticipate the transmission infrastructure construction for facilitating new generation development, minimizing social costs and attracting market entries. Proactive TSO s behavior is risky and uncertain as the demand forecasting is, but could create a virtuous circle, avoiding congestion increase during the period of construction/connection and reducing social welfare losses EU is expected to establish guidelines on maximum delays in the national procedures. 17

18 Policy Recommendations: the hybrid solution 18

19 TSOs and financial issues 19

20 The de-bottlenecking problem: a wider view 7. Act on public opinion and on compensation policy (bottomup) 8. Boost TSO investment optimality 1. Build-up new infrastructure 2. Anticipate needs in the planning 6. Reform the electricity market 5. Refurbish the existing infrastructure 3. Speed up and harmonize legal procedures (top-down) 4. Facilitate merchant investment wherever convenient 20

21 Lack of cross-border infrastructure: some final considerations A new regulatory approach that balances short-term and long-term interests is needed, because incentives for efficient network operation do not necessarily also provide incentives for new long-term investments. Short-term tariff reductions (politically envisaged) push TSOs to less invest in expensive long-term investments as this would raise the asset base on which most tariffs are calculated. Only 25% of all congestion revenues earned in the period has been reinvested in interconnectors, the rest has been allocated to lower tariffs in the short-term. As congestion is often driven by price differences, alleviating congestion may increase the price in the low-price region. Regulators at this losing side of the interconnector might oppose such an investment: national vs. European interests. ACER can only propose or sort disputes, but today should be able to pass new regulations to guarantee pan-eu interests. Social costs of excess capacity are much smaller than the costs of under capacity, don t forgetting benefits: Competition, RES, Reliability 21 21

22 Acknowledgements J. Kappauf (OME), H. Auer (EEG), G. Lettner (EEG), I. Losa (RSE) and M. Osthues (TUDO) co-authors of D3.6.2 President Dobbeni (ENTSO-E) Professor Glachant and V. Rious (FSR) X. Gallet, G. de Saint-Martin (RTE-I) C. Vergine, P. Antonelli, A. Sallati (TERNA) K. Jansen, M. van der Meijden (TenneT) K. Reich, O. Wadosch (Verbund-APG) 22

23 Thank you for your attention REALISEGRID 23

REALISEGRID. WP3 Final Workshop. Rome - 31 March TSO incentivization policies for cross-border transmission development

REALISEGRID. WP3 Final Workshop. Rome - 31 March TSO incentivization policies for cross-border transmission development REALISEGRID WP3 Final Workshop Rome - 31 March 2011 TSO incentivization policies for cross-border transmission development WP3.6 ongoing results OME & RSE Outline Background Building cross-border interconnections

More information

COMMISSION REGULATION (EU)

COMMISSION REGULATION (EU) 24.9.2010 Official Journal of the European Union L 250/5 COMMISSION REGULATION (EU) No 838/2010 of 23 September 2010 on laying down guidelines relating to the inter-transmission system operator compensation

More information

Draft. COMMISSION REGULATION (EU) No /

Draft. COMMISSION REGULATION (EU) No / EN EN EN EUROPEAN COMMISSION Brussels, C(2010) XXX final Draft COMMISSION REGULATION (EU) No / of on laying down guidelines relating to the inter-transmission system operator compensation mechanism and

More information

Austrian Power Grid Comments to ACER consultation

Austrian Power Grid Comments to ACER consultation Austrian Power Grid Comments to ACER consultation Austrian Power Grid (APG) welcomes the invitation to respond to the Public Consultation on Assessment of the Annual Cross-Border Infrastructure Compensation

More information

Draft Outline of the 2016 Work Programme

Draft Outline of the 2016 Work Programme Draft Outline of the 2016 Work Programme This document presents an outline of the tasks that the Agency plans to perform in 2016. As such, it focuses primarily on the external deliverables the Agency expects

More information

REQUEST FOR AMENDMENT BY ALL REGULATORY AUTHORITIES AGREED AT THE ENERGY REGULATORS FORUM ON

REQUEST FOR AMENDMENT BY ALL REGULATORY AUTHORITIES AGREED AT THE ENERGY REGULATORS FORUM ON REQUEST FOR AMENDMENT BY ALL REGULATORY AUTHORITIES AGREED AT THE ENERGY REGULATORS FORUM ON ALL TSO s PROPOSAL FOR CONGESTION INCOME DISTRIBUTION METHODOLOGY 24.01.2017 I. Introduction and legal context

More information

The North Seas Countries Offshore Grid Initiative

The North Seas Countries Offshore Grid Initiative The North Seas Countries Offshore Grid Initiative Deliverable 1 - final report This report identifies areas where the incompatibility of national market and regulatory regimes acts as a barrier to coordinated

More information

Impact of Wind Energy Support Schemes on the Development of an Offshore Grid in the North Sea

Impact of Wind Energy Support Schemes on the Development of an Offshore Grid in the North Sea 1 Paper No: 14PESGM0689 Impact of Wind Energy Support Schemes on the Development of an Offshore Grid in the North Sea Shahab Shariat Torbaghan, Dr. Madeleine Gibescu, Prof. Mart van der Meijden (TU Delft)

More information

Allegato A. Summary WHEREAS... 3 GENERAL PROVISIONS Article 1 Subject matter and scope Article 2 Definitions... 4

Allegato A. Summary WHEREAS... 3 GENERAL PROVISIONS Article 1 Subject matter and scope Article 2 Definitions... 4 Greece-Italy TSOs proposal for methodology for redispatching and countertrading cost-sharing in accordance with Article 74 of the Commission Regulation (EU) 2015/1222 of 24 July 2015 establishing a Guideline

More information

The North Seas Countries Offshore Grid Initiative

The North Seas Countries Offshore Grid Initiative The North Seas Countries Offshore Grid Initiative NSCOGI 2013/2014 progress report August 2014 1 Objectives of the North Seas Countries Offshore Grid Initiative In December 2012, Ministers of the North

More information

INVESTING IN LONG-TERM EUROPE:

INVESTING IN LONG-TERM EUROPE: INVESTING IN LONG-TERM EUROPE: RE-LAUNCHING FIXED, NETWORK AND SOCIAL INFRASTRUCTURE Conference Organized In Association With The Italian EU Presidency ROMA, 12 Dicembre 2014 Italian Energy Price Evolution

More information

Proposal for Multiple NEMO Arrangements (MNA) for the Belgian bidding zone in accordance with Article 45 and Article 57 of the Commission Regulation

Proposal for Multiple NEMO Arrangements (MNA) for the Belgian bidding zone in accordance with Article 45 and Article 57 of the Commission Regulation Proposal for Multiple NEMO Arrangements (MNA) for the Belgian bidding zone in accordance with Article 45 and Article 57 of the Commission Regulation (EU) 2015/1222 of 24 July 2015 establishing a Guideline

More information

Mr Alberto Pototschnig, Director ACER. CC: Dr Klaus-Dieter Borchardt, Director Internal Energy Market DG ENER European Commission

Mr Alberto Pototschnig, Director ACER. CC: Dr Klaus-Dieter Borchardt, Director Internal Energy Market DG ENER European Commission Mr Alberto Pototschnig, Director ACER CC: Dr Klaus-Dieter Borchardt, Director Internal Energy Market DG ENER European Commission Mr Laurent Schmitt, Secretary General ENTSO-E 14 June 2017 Dear Alberto,

More information

Draft Outline of the 2019 Work Programme

Draft Outline of the 2019 Work Programme Draft Outline of the 2019 Work Programme This document presents an outline of the tasks the Agency plans to perform in 2019. As such, it focuses primarily on the external deliverables the Agency expects

More information

29 June 2016 Disclaimer This explanatory document is submitted by all TSOs to all NRAs for information and clarification purposes only accompanying the All TSOs proposal for methodology for congestion

More information

CID Methodology Explanatory note

CID Methodology Explanatory note 29 June 2016 Disclaimer This explanatory document is submitted by all TSOs to all NRAs for information and clarification purposes only accompanying the All TSOs proposal for methodology for congestion

More information

AGENCY FOR THE COOPERATION OF ENERGY REGULATORS (ACER): QUOI DE NEUF AFTER THE COMMISSION S PROPOSAL FOR A RECAST OF THE REGULATION ON ACER

AGENCY FOR THE COOPERATION OF ENERGY REGULATORS (ACER): QUOI DE NEUF AFTER THE COMMISSION S PROPOSAL FOR A RECAST OF THE REGULATION ON ACER AGENCY FOR THE COOPERATION OF ENERGY REGULATORS (ACER): QUOI DE NEUF AFTER THE COMMISSION S PROPOSAL FOR A RECAST OF THE REGULATION ON ACER PROF. DR. MARIA MENG-PAPANTONI PANTEION UNIVERSITY-ATHENS VISITING

More information

GB TSOs Intraday proposal for arrangements concerning more than one Nominated Electricity Market Operator (NEMO) in the GB Bidding Zone in accordance

GB TSOs Intraday proposal for arrangements concerning more than one Nominated Electricity Market Operator (NEMO) in the GB Bidding Zone in accordance GB TSOs Intraday proposal for arrangements concerning more than one Nominated Electricity Market Operator (NEMO) in the GB Bidding Zone in accordance with Article 57 of the Commission Regulation (EU) 2015/1222

More information

A Contestable Approach to Financing Critical Interconnection Across Europe at the Scale and Pace Needed

A Contestable Approach to Financing Critical Interconnection Across Europe at the Scale and Pace Needed A Contestable Approach to Financing Critical Interconnection Across Europe Summary Phil Baker September 2015 A robust and secure transmission network, with strong interconnection between Member States,

More information

APPROVAL BY ALL CONCERNED CCR HANSA AUTHORITIES

APPROVAL BY ALL CONCERNED CCR HANSA AUTHORITIES APPROVAL BY ALL CONCERNED CCR HANSA AUTHORITIES OF CCR HANSA TSO PROPOSAL FOR CCR HANSA REGIONAL REQUIREMENTS TO HARMONISED ALLOCATION RULES IN ACCORDANCE WITH ARTICLE 52 OF THE COMMISSION REGULATION (EU)

More information

7 April ENTSO-E AISBL Avenue de Cortenbergh Brussels Belgium Tel Fax www. entsoe.

7 April ENTSO-E AISBL Avenue de Cortenbergh Brussels Belgium Tel Fax www. entsoe. All TSOs Proposal for a Congestion Income Distribution (CID) methodology in accordance with Article 73 of the Commission Regulation (EU) 2015/1222 of 24 July 2015 establishing a Guideline on Capacity Allocation

More information

TSOs perspective of the CACM requirements. Athanasios Troupakis Market Advisor ENTSO-E

TSOs perspective of the CACM requirements. Athanasios Troupakis Market Advisor ENTSO-E TSOs perspective of the CACM requirements Athanasios Troupakis Market Advisor ENTSO-E Energy Community Secretariat Energy Community Secretariat Table of contents 1. Introductory remarks 2. Elements of

More information

Security of Supply. Walter Boltz. 8 th EU/US Roundtable. CEER Vice President, Gas Working Group Chair October 2010, Berlin

Security of Supply. Walter Boltz. 8 th EU/US Roundtable. CEER Vice President, Gas Working Group Chair October 2010, Berlin Security of Supply Walter Boltz CEER Vice President, Gas Working Group Chair 8 th EU/US Roundtable 25-27 October 2010, Berlin Agenda Framework for Investment Planning and Security of Supply in the European

More information

ENTSO-E recommendations for Market Design Trilogue negotiations

ENTSO-E recommendations for Market Design Trilogue negotiations ENTSO-E recommendations for Market Design Trilogue negotiations ENTSO-E congratulates the Bulgarian Presidency, the European Parliament and the European Commission on the successful conclusion of the first

More information

2011 Work Programme of the Agency for the Cooperation of Energy Regulators

2011 Work Programme of the Agency for the Cooperation of Energy Regulators of the Cooperation of Regulators 21 September 2010 TABLE OF CONTENTS 1 INTRODUCTION 3 1.1 Foreword 3 1.2 Presentation 5 2 PERFORMANCE INDICATORS 10 2.1 Regulatory topics 10 2.2 Administrative topics 13

More information

The current ETSO ITC Model and possible development

The current ETSO ITC Model and possible development The current ETSO ITC Model and possible development 1. Summary The present model for inter-tso compensation for transit (ITC) was introduced in 2002 and has been modified step-by-step from year to year.

More information

RESPONSE TO ACER'S CONSULTATION ON TARIFFS

RESPONSE TO ACER'S CONSULTATION ON TARIFFS RESPONSE TO ACER'S CONSULTATION ON TARIFFS Question 1: What other issues should be dealt with in this Framework Guideline? What is the evidence for including these issues? Please provide justification.

More information

Capacity Allocation and Congestion Management (CACM) Code Overview

Capacity Allocation and Congestion Management (CACM) Code Overview Capacity Allocation and Congestion Management (CACM) Code Overview Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size

More information

Can The EU Be An Example To Turkish Electricity Market Liberalisation?

Can The EU Be An Example To Turkish Electricity Market Liberalisation? Can The EU Be An Example To Turkish Electricity Market Liberalisation? Istanbul Energy Day 8 September 2015 Dr. Jan Haizmann Managing Director CORREGGIO CONSULTING Introduction Dr. Jan Haizmann Academia

More information

Offshore transmission investments How to regulate these investments? Who should act?

Offshore transmission investments How to regulate these investments? Who should act? Offshore transmission investments How to regulate these investments? Who should act? North Seas Countries Offshore Grid Initiative (NSCOGI) Copenhagen, 18-19 April 2012 Leonardo Meeus (Florence School

More information

Content Abbreviations Article 1 Article 2 Article 3 Article 4 Article 5 Article 6 Article 7 Article 8 Article 9 Article 10 Article 11 Article 12

Content Abbreviations Article 1 Article 2 Article 3 Article 4 Article 5 Article 6 Article 7 Article 8 Article 9 Article 10 Article 11 Article 12 All TSOs proposal for common settlement rules applicable to all intended exchanges of energy as a result of the reserve replacement process, frequency restoration process with manual and automatic activation

More information

Paving the way to a a meshed offshore grid Recommendations for an efficient policy and regulatory framework

Paving the way to a a meshed offshore grid Recommendations for an efficient policy and regulatory framework Downloaded from orbit.dtu.dk on: Apr 04, 2019 Paving the way to a a meshed offshore grid Recommendations for an efficient policy and regulatory framework Bergaentzlé, Claire; Hoffrichter, Albert; Isojärvi,

More information

South East Europe Electricity Market options paper

South East Europe Electricity Market options paper EUROPEAN COMMISSION DIRECTORATE-GENERAL FOR ENERGY AND TRANSPORT DIRECTORATE C - Conventional Energies Electricity & Gas Brussels, 5 December 2005 DG TREN/C2/MS South East Europe Electricity Market options

More information

Explanatory document for the Nordic synchronous area proposal for limits for the exchange of FCR between the TSOs in accordance with Article 163(2)

Explanatory document for the Nordic synchronous area proposal for limits for the exchange of FCR between the TSOs in accordance with Article 163(2) Explanatory document for the Nordic synchronous area proposal for limits for the exchange of FCR between the TSOs in accordance with Article 163(2) of the Commission Regulation (EU) 2017/1485 of 2 August

More information

BETTER EUROPEAN STAKEHOLDER WORKSHOP. Results from the EC project RES Support Schemes and Cooperation Mechanisms in Europe

BETTER EUROPEAN STAKEHOLDER WORKSHOP. Results from the EC project RES Support Schemes and Cooperation Mechanisms in Europe BETTER EUROPEAN STAKEHOLDER WORKSHOP Results from the EC project RES Support Schemes and Cooperation Mechanisms in Europe Malte Gephart 08/10/2014 Content Project overview Current status of Cooperation

More information

EUROPEA U IO. Brussels, 12 June 2009 (OR. en) 2007/0198 (COD) PE-CO S 3651/09 E ER 173 CODEC 704

EUROPEA U IO. Brussels, 12 June 2009 (OR. en) 2007/0198 (COD) PE-CO S 3651/09 E ER 173 CODEC 704 EUROPEA U IO THE EUROPEA PARLIAMT THE COU CIL Brussels, 12 June 2009 (OR. en) 2007/0198 (COD) PE-CO S 3651/09 ER 173 CODEC 704 LEGISLATIVE ACTS A D OTHER I STRUMTS Subject: REGULATION OF THE EUROPEAN PARLIAMENT

More information

The Road to the I-SEM

The Road to the I-SEM The Road to the I-SEM 1 Agenda Development of power markets in Ireland and Northern Ireland Development of power markets across Europe Market coupling explained The road to the I-SEM The elements of the

More information

Offshore Grid Development in Germany

Offshore Grid Development in Germany Offshore Grid Development in Germany Hamburg, 26 September 2017 Lukas Wienholt Federal Maritime and Hydrographic Agency Content of Presentation I. Current status of offshore wind energy in the German North

More information

EAI Response to ACER Consultation on Forward Risk-Hedging Products and Harmonisation of Long-Term Capacity Allocation Rules

EAI Response to ACER Consultation on Forward Risk-Hedging Products and Harmonisation of Long-Term Capacity Allocation Rules Version 1.0 ACER Consultation on Forward Risk-Hedging Products and Harmonisation of Long-Term Capacity Allocation Rules EAI Response to ACER Consultation on Forward Risk-Hedging Products and Harmonisation

More information

Content Abbreviations Article 1 Article 2 Article 3 Article 4 Article 5 Article 6 Article 7 Article 8 Article 9 Article 10 Article 11 Article 12

Content Abbreviations Article 1 Article 2 Article 3 Article 4 Article 5 Article 6 Article 7 Article 8 Article 9 Article 10 Article 11 Article 12 All TSOs proposal for common settlement rules applicable to all intended exchanges of energy as a result of the reserve replacement process, frequency restoration process with manual and automatic activation

More information

Viviane Illegems European Market Integration

Viviane Illegems European Market Integration Introduction of the allocation of Financial Transmission Rights (FTRs) Options instead of Physical Transmission Rights with UIOSI (Use It or Sell It) for long term transmission rights on Belgian Borders

More information

ENTSO-E Network Code on Electricity Balancing

ENTSO-E Network Code on Electricity Balancing Annex II to Recommendation of the Agency for the Cooperation of Energy Regulators No 03/2015 of 20 July 2015 on the Network Code on Electricity Balancing Proposed amendments to the Network Code ENTSO-E

More information

BRIEF POLICY. First series of cross-border cost allocation decisions for projects of common interest: Main lessons learned

BRIEF POLICY. First series of cross-border cost allocation decisions for projects of common interest: Main lessons learned ISSN 1977-3919 ISBN 978-92-9084-245-3 DOI 10.2870/579216 FLORENCE SCHOOL OF REGULATION Issue 2015/01 February 2015 First series of cross-border cost allocation decisions for projects of common interest:

More information

ACER. Congestion income distribution methodology. in accordance with Article 73 of the Commission Regulation

ACER. Congestion income distribution methodology. in accordance with Article 73 of the Commission Regulation Annex I Capacity Allocation and Congestion Management in accordance with Article 73 of the Commission Regulation (EU) 2015/1222 of 24 July 2015 establishing a Guideline on Congestion income distribution

More information

EFET Proposal on Regional Independent System Operator (R_ISO) A CEER Response Paper

EFET Proposal on Regional Independent System Operator (R_ISO) A CEER Response Paper EFET Proposal on Regional Independent System Operator (R_ISO) A CEER Response Paper Ref. C08-GWG-42-03 6 February 2008 Council of European Energy Regulators ASBL 28 rue le Titien, 1000 Bruxelles Arrondissement

More information

Wind power and the power market

Wind power and the power market Wind power and the power market Sascha T. Schröder EWEA2012 Pre-Conference Grid Seminar by the Danish Wind Industry Association April 15 th, 2012 Outline Wind power remuneration in power markets Power

More information

European transmission tariff structures Cambridge Economic Policy Associates

European transmission tariff structures Cambridge Economic Policy Associates European transmission tariff structures Cambridge Economic Policy Associates 24 March 2015 Cambridge Economic Policy Associates (CEPA) We are an economic and financial policy consulting business Our energy

More information

DEFINITION AND PRACTICAL APPLICATION OF KEY PERFORMANCE INDICATORS TO SUPPORT EUROPEAN GRID OPERATORS TO ENABLE THE ENERGY POLICY GOALS

DEFINITION AND PRACTICAL APPLICATION OF KEY PERFORMANCE INDICATORS TO SUPPORT EUROPEAN GRID OPERATORS TO ENABLE THE ENERGY POLICY GOALS DEFINITION AND PRACTICAL APPLICATION OF KEY PERFORMANCE INDICATORS TO SUPPORT EUROPEAN GRID OPERATORS TO ENABLE THE ENERGY POLICY GOALS Gareth BISSELL, Carlos COSTA Michele DE NIGRIS, Ilaria LOSA Massimiliano

More information

NOTE OF DG ENERGY & TRANSPORT ON DIRECTIVES 2003/54-55 AND REGULATION 1228\03 IN THE ELECTRICITY AND GAS INTERNAL MARKET

NOTE OF DG ENERGY & TRANSPORT ON DIRECTIVES 2003/54-55 AND REGULATION 1228\03 IN THE ELECTRICITY AND GAS INTERNAL MARKET NOTE OF DG ENERGY & TRANSPORT ON DIRECTIVES 2003/54-55 AND REGULATION 1228\03 IN THE ELECTRICITY AND GAS INTERNAL MARKET THIS DOCUMENT IS NOT BINDING ON THE COMMISSION EXEMPTIONS FROM CERTAIN PROVISIONS

More information

regulation Policy Brief 26 November 2014

regulation Policy Brief 26 November 2014 Fostering Electricity transmission investments to achieve Europe s energy goals: Towards a future-looking regulation Policy Brief 26 November 2014 Executive Summary A strong and secure transmission network

More information

18 April 2016 Draft for consultation

18 April 2016 Draft for consultation All TSOs proposal for intraday cross-zonal gate opening and gate closure times in accordance with Article 59 of Commission Regulation (EU) 2015/1222 of 24 July 2015 establishing a guideline on capacity

More information

Tackling uncertainty in developing gas infrastructure in South East Europe. Michael Thomadakis Member of the Board, RAE GREECE

Tackling uncertainty in developing gas infrastructure in South East Europe. Michael Thomadakis Member of the Board, RAE GREECE Tackling uncertainty in developing gas infrastructure in South East Europe Michael Thomadakis Member of the Board, RAE GREECE The Southern Gas Corridor-PCI list The vicious circle of the SEE gas markets

More information

Wholesale Electricity Market Monitoring Report for the Energy Community Contracting Parties and Georgia

Wholesale Electricity Market Monitoring Report for the Energy Community Contracting Parties and Georgia Wholesale Electricity Market Monitoring Report for the Energy Community Contracting Parties and Georgia Reporting Period 2014 Publication date April 2016 Contents Contents... 1 List of Tables... 2 List

More information

SUMMARY OF THE ASSESSMENT OF THE COMMENTS FROM THE PUBLIC CONSULTATION OF REGARDING PRICE OF THE SERVICES OF ACCESS TO INTERCONNECTION LINES

SUMMARY OF THE ASSESSMENT OF THE COMMENTS FROM THE PUBLIC CONSULTATION OF REGARDING PRICE OF THE SERVICES OF ACCESS TO INTERCONNECTION LINES SUMMARY OF THE ASSESSMENT OF THE COMMENTS FROM THE PUBLIC CONSULTATION OF REGARDING PRICE OF THE SERVICES OF ACCESS TO INTERCONNECTION LINES 1 Estonian Competition Authority, November 16, 2015 (Estonian

More information

Economic Assessment of a hypothetical interconnector RO-BG. László Szabó REKK SEERMAP Electricity Network Assessment workshop Athens, 6-8 March.

Economic Assessment of a hypothetical interconnector RO-BG. László Szabó REKK SEERMAP Electricity Network Assessment workshop Athens, 6-8 March. Economic Assessment of a hypothetical interconnector RO-BG László Szabó REKK SEERMAP Electricity Network Assessment workshop Athens, 6-8 March. 2017 1 Outline Introduction Economic vs financial focused

More information

Business Process. BP_SO_13.1 Interim Long-Term Coordinated Capacity Calculation

Business Process. BP_SO_13.1 Interim Long-Term Coordinated Capacity Calculation Business Process BP_SO_13.1 Interim Long-Term Coordinated Capacity Calculation EirGrid and SONI support the provision of information to the marketplace by publishing operational data, processes, methodologies

More information

Panel Discussion: " Will Financial Globalization Survive?" Luzerne, June Should financial globalization survive?

Panel Discussion:  Will Financial Globalization Survive? Luzerne, June Should financial globalization survive? Some remarks by Jose Dario Uribe, Governor of the Banco de la República, Colombia, at the 11th BIS Annual Conference on "The Future of Financial Globalization." Panel Discussion: " Will Financial Globalization

More information

EU Harmonisation of Maintenance Publications at Interconnections Points

EU Harmonisation of Maintenance Publications at Interconnections Points EU Harmonisation of Maintenance Publications at Interconnections Points Provision of Maintenance Information at Interconnection Points - EU Harmonisation Background: European Regulation EC 715/2009 puts

More information

FORTUMS RESPONSE TO ACER CONSULTATION ON FORWARD RISK-HEDGING PRODUCTS AND HARMONISATION OF LONG-TERM CAPACITY ALLOCATION RULES

FORTUMS RESPONSE TO ACER CONSULTATION ON FORWARD RISK-HEDGING PRODUCTS AND HARMONISATION OF LONG-TERM CAPACITY ALLOCATION RULES 1 (5) FORTUMS RESPONSE TO ACER CONSULTATION ON FORWARD RISK-HEDGING PRODUCTS AND HARMONISATION OF LONG-TERM CAPACITY ALLOCATION RULES General comments Fortum welcomes the consultation by ACER on Forward

More information

Brexit: potential impacts on energy markets and regulation

Brexit: potential impacts on energy markets and regulation Brexit: potential impacts on energy markets and regulation November 2016 Overview This briefing note reviews the possible impacts of the UK s Brexit vote on energy regulation in the UK, in two scenarios:

More information

Intermediate Deliverable - Economic framework for offshore grid planning

Intermediate Deliverable - Economic framework for offshore grid planning Intermediate Deliverable - Economic framework for offshore grid planning PROMOTioN Progress on Meshed HVDC Offshore Transmission Networks Mail info@promotion-offshore.net Web www.promotion-offshore.net

More information

Comments on CEPA s draft conclusions in relation to European transmission tariffs

Comments on CEPA s draft conclusions in relation to European transmission tariffs July 2015 Frontier Economics 1 ACER commissioned CEPA to review harmonisation of transmission tariffs in Europe, and specifically to: assess whether increased harmonisation of electricity transmission

More information

Workshop on Regional Electricity Trade and Market Development

Workshop on Regional Electricity Trade and Market Development Workshop on Regional Electricity Trade and Market Development Cross-border Electricity Trade and Tariffs April 23, 2014 Cross-border Electricity Trade (CBT) Flows within which part of the transmission

More information

Guidelines for improvement network regulation for enhancing the share of DG DSO revenues and incentives to integrate DG

Guidelines for improvement network regulation for enhancing the share of DG DSO revenues and incentives to integrate DG Guidelines for improvement network regulation for enhancing the share of DG DSO revenues and incentives to integrate DG DG-GRID Workshop, Madrid, April 12, 2007 Objectives Development of guidelines for

More information

ERGEG Public Consultation on Guidelines on Transmission Tarification 1. - Evaluation of the Comments Received

ERGEG Public Consultation on Guidelines on Transmission Tarification 1. - Evaluation of the Comments Received ERGEG Public Consultation on Guidelines on Transmission Tarification 1 - Evaluation of the Comments Received - 18-07-2005 INTRODUCTION This document contains the evaluation by ERGEG of the comments received

More information

EU Electricity Market & System: What s new with 4 th Package? Lodz, EEM18

EU Electricity Market & System: What s new with 4 th Package? Lodz, EEM18 EU Electricity Market & System: What s new with 4 th Package? Lodz, EEM18 Jean-Michel Glachant Director Florence School of Regulation European University Institute (Florence, Italy) EU I know, You know

More information

The voice of the energy industry. Brexit & the future EU-UK energy relationship

The voice of the energy industry. Brexit & the future EU-UK energy relationship The voice of the energy industry Brexit & the future EU-UK energy relationship February 2018 Executive Summary Energy UK was pleased to see the negotiations on the UK s departure from the European Union

More information

We appreciate your feedback

We appreciate your feedback Publishing date: 05/09/2012 Document title: We appreciate your feedback Please click on the icon to take a 5 online survey and provide your feedback about this document Draft Framework Guidelines on rules

More information

3 rd Technical Workshop: Gas Market Design and Natural Gas Transmission Grid Codes

3 rd Technical Workshop: Gas Market Design and Natural Gas Transmission Grid Codes 3 rd Technical Workshop: Gas Market Design and Natural Gas Transmission Grid Codes Regulatory Framework & Incentives for Infrastructure Development Sergio Ascari VIS Consultants Gas Advisor, Florence School

More information

EVALUATION OF INVESTMENTS IN ELECTRICITY AND GAS TRANSMISSION NETWORKS

EVALUATION OF INVESTMENTS IN ELECTRICITY AND GAS TRANSMISSION NETWORKS Unofficial English version Methodology and criteria for evaluating investments in electricity and gas infrastructure projects (article 13(6) of Regulation (EU) No 347/2013 of the European Parliament and

More information

The TSO side of pan-european XBorder trading in high frequencies: The Role of Scheduling. Michael Schaefer Project Manager, Amprion System Operation

The TSO side of pan-european XBorder trading in high frequencies: The Role of Scheduling. Michael Schaefer Project Manager, Amprion System Operation The TSO side of pan-european XBorder trading in high frequencies: The Role of Scheduling Michael Schaefer Project Manager, Amprion System Operation Diploma in Information Science & Advanced Postgraduate

More information

South East Europe Regional Electricity Market. Belgrade, 01 November 2007

South East Europe Regional Electricity Market. Belgrade, 01 November 2007 South East Europe Regional Electricity Market Belgrade, 01 November 2007 1 Main Purpose of the presentation Brief info on the energy sector of the Western Balkans about the present energy situation in

More information

Introduction to transmission network assessment methodology: the ENTSO-E CBA methodology and the PCI selection process.

Introduction to transmission network assessment methodology: the ENTSO-E CBA methodology and the PCI selection process. Introduction to transmission network assessment methodology: the ENTSO-E CBA methodology and the PCI selection process Péter Kaderják SEERMAP training March 7, 2017 Athens, Greece Overview The policy context

More information

Vision. A A a. Possible offshore development Phase 1 Phase 2 Phase januar

Vision. A A a. Possible offshore development Phase 1 Phase 2 Phase januar Offshore grid developments 20 jan. 2011 Kjartan Hauglum, Statnettt tt Phase 1 Phase 2 Phase 3 A A a Vision Possible offshore development 2020-2040 24. januar 2011 2 Statnetts mission towards 2030 -To build

More information

Cross-border exchange and sharing of generation reserve capacity

Cross-border exchange and sharing of generation reserve capacity Cross-border exchange and sharing of generation reserve capacity Fridrik Mar Baldursson, Reykjavik University Ewa Lazarczyk, Reykjavik University Marten Ovaere, KU Leuven Stef Proost, KU Leuven ference,

More information

Strategy & Targets

Strategy & Targets 2013 2016 Strategy & Targets March 13 th, 2013 snam.it Playing a Leading Role in Integrating the European Gas Market Carlo Malacarne Chief Executive Officer 2 Key Priorities of a Sustainable Growth Strategy

More information

Conclusions of the European Council discussions on energy infrastructure issues

Conclusions of the European Council discussions on energy infrastructure issues Conclusions of the European Council discussions on energy infrastructure issues Slovenia Overall support for the regulation as this will allow to tackle the known problems regarding infrastructure The

More information

Economic Assessment of a hypothetical interconnector RO-BG

Economic Assessment of a hypothetical interconnector RO-BG Economic Assessment of a hypothetical interconnector RO-BG László Szabó REKK SEERMAP Electricity Network Assessment workshop Tirana, 14-16 December. 2016 1 Outline Introduction Economic vs financial focused

More information

Spurring Growth of Renewable Energies in MENA through Private Sector Investment

Spurring Growth of Renewable Energies in MENA through Private Sector Investment MENA-OECD Business Council: Task Force on Energy and Infrastructure WORKING PAPER PRESENTING THE PRIVATE SECTOR S VIEW Spurring Growth of Renewable Energies in MENA through Private Sector Investment Agenda

More information

ACER s functions and responsibilities in the European Union

ACER s functions and responsibilities in the European Union ACER s functions and responsibilities in the European Union Alberto Pototschnig Director Orkumál og EES-samningurinn. Hver eru áhrif þriðja orkupakkans? University of Reykjavik 13 August 2018 The internal

More information

WORKSHOP. Building a European energy infrastructure selecting and implementing projects of common interest

WORKSHOP. Building a European energy infrastructure selecting and implementing projects of common interest DIRECTORATE GENERAL FOR INTERNAL POLICIES POLICY DEPARTMENT A: ECONOMIC AND SCIENTIFIC POLICY WORKSHOP Building a European energy infrastructure selecting and implementing projects of common interest Brussels,

More information

Connecting Europe Facility:

Connecting Europe Facility: Cyprus Oct 2013 S. Committee Development & Business Environment Connecting Europe Facility: Initial provisions Council and European Parliament agreement Brussels, 10 July 2013 Aris Chatzidakis 24-10-2013

More information

Regulatory framework for crossborder redispatching and countertrading

Regulatory framework for crossborder redispatching and countertrading Regulatory framework for crossborder redispatching and countertrading Joint Task Force ACER ENTSO-E 1 OUTLINE The need for an efficient and coordinated redispatch measures framework Current situation:

More information

Grid Investments from a Nordic Perspective

Grid Investments from a Nordic Perspective Grid Investments from a Nordic Perspective NordREG recommendations 1 Background and task As one of the challenges for the further development of the Nordic electricity market has in the last few years

More information

CLEAN ENERGY FOR ALL EUROPEANS

CLEAN ENERGY FOR ALL EUROPEANS CLEAN ENERGY FOR ALL EUROPEANS Stepping Up Regional Cooperation Kristina Jankovich DG ENER B2 LEGISLATIVE PACKAGE IMPLEMENTING THE ENERGY UNION STRATEGY AN ENERGY UNION BASED ON 5 MUTUALLY SUPPORTIVE AND

More information

Ireland in the wider European energy market

Ireland in the wider European energy market Ireland in the wider European energy market MOP Breakfast Briefing Stephen Woodhouse 24 March 2011 Pöyry what do we do? 3 7000 employees across 49 countries Pöyry Management Consulting, Energy Europe s

More information

PCI status, its benefits and obligations

PCI status, its benefits and obligations PCI status, its benefits and obligations Meeting of the Regional Groups of the four Gas Priority Corridors; 30 May 2017 Adam Romanowski, DG B1 Climate, and Trans-European Networks Policies Foundations

More information

Introduction to Power Exchanges

Introduction to Power Exchanges For Public Use Introduction to Power Exchanges Presented by: Mr. S.K. Ray on behalf of IEX In this presentation Introduction to Indian Power Markets Power Exchange functioning and Market Snapshot International

More information

Fostering Electricity transmission investments to achieve Europe s energy goals: Towards a future-looking regulation

Fostering Electricity transmission investments to achieve Europe s energy goals: Towards a future-looking regulation Fostering Electricity transmission investments to achieve ENTSO-E Working Group Economic Framework 26 November 2014 Content Executive Summary... 2 Introduction... 2 1. The Investment Challenge... 3 2.

More information

NordREG Activities 2008

NordREG Activities 2008 NordREG Activities 2008 NordREG Activities 2008 NordREG c/o Norwegian Water Resources and Energy Directorate P.O. Box 5091, Majorstua N-0301 Oslo Norway Telephone: +47 22 95 95 95 Telefax: +47 22 95 90

More information

Realising the benefits of European market integration

Realising the benefits of European market integration 1 EUROPEAN MARKET INTEGRATION THE REGULATORY ASSISTANCE PROJECT (RAP) MAY 2018 Realising the benefits of European market integration Philip Baker, Michael Hogan, and Christos Kolokathis Enhanced market

More information

CROSS BORDER CAPACITY ALLOCATION FOR THE EXCHANGE OF ANCILLARY SERVICES

CROSS BORDER CAPACITY ALLOCATION FOR THE EXCHANGE OF ANCILLARY SERVICES CROSS BORDER CAPACITY ALLOCATION FOR THE EXCHANGE OF ANCILLARY SERVICES A POSITION PAPER BY THE ENTSO-E ANCILLARY SERVICES WORKING GROUP JANUARY 2012 Purpose & objectives of the paper This paper further

More information

Trading across borders - The key to manage portfolios at a regional scale

Trading across borders - The key to manage portfolios at a regional scale Trading across borders - The key to manage portfolios at a regional scale Jérôme Le Page Manager for European Electricity Markets EFET European Federation of Energy Traders Energy Community Secretariat

More information

Intermediate report: Financing framework for meshed offshore grid investments

Intermediate report: Financing framework for meshed offshore grid investments Intermediate report: Financing framework for meshed offshore grid investments PROMOTioN Progress on Meshed HVDC Offshore Transmission Networks Mail info@promotion-offshore.net Web www.promotion-offshore.net

More information

ACER 2 nd Annual Conference Roundtable: The infrastructure challenge 17 May, 14:00 15:10 Grand Union Hotel, Ljubljana

ACER 2 nd Annual Conference Roundtable: The infrastructure challenge 17 May, 14:00 15:10 Grand Union Hotel, Ljubljana Ref.: 13GIE076 May 2013 ACER 2 nd Annual Conference Roundtable: The infrastructure challenge 17 May, 14:00 15:10 Grand Union Hotel, Ljubljana Roundtable: The Infrastructure Challenge Moderator: Piotr Wozniak

More information

LONG-TERM TRANSMISSION NETWORK EXPANSION PLANNING CONSIDERING THE ECONOMIC CRITERIA AND THE FLOW-BASED MARKET MODEL

LONG-TERM TRANSMISSION NETWORK EXPANSION PLANNING CONSIDERING THE ECONOMIC CRITERIA AND THE FLOW-BASED MARKET MODEL Milan Vukasovic 1, Oliver John 2, Nenad Stefanovic 3 LONG-TERM TRANSMISSION NETWORK EXPANSION PLANNING CONSIDERING THE ECONOMIC CRITERIA AND THE FLOW-BASED MARKET MODEL 1 VERBUND-Austrian Power Grid AG,

More information

The Model of Implicit Capacity Allocation in the Baltic States

The Model of Implicit Capacity Allocation in the Baltic States The Model of Implicit Capacity Allocation in the Baltic States This document describes a model of implicit allocation of gas transmission capacity in the Baltic States. Implicit capacity allocation is

More information

Possible market model for crossborder intraday trading

Possible market model for crossborder intraday trading Possible market model for crossborder intraday trading Belpex Users Group 29 January 2008 Linking partners in power Context Intraday trading is becoming increasingly important Within CWE region several

More information

Winter Academy 2018 Trading, Sales and Financing in the European Energy Market and Industry Functioning of the European Power Exchange

Winter Academy 2018 Trading, Sales and Financing in the European Energy Market and Industry Functioning of the European Power Exchange Winter Academy 2018 Trading, Sales and Financing in the European Energy Market and Industry Functioning of the European Power Exchange Patrick Adigbli, Head of Public & Regulatory Affairs, EPEX SPOT 1

More information

IU TSOs proposal for fallback procedures in accordance with Article 44 of the Commission Regulation (EU) 2015/1222 of 24 July 2015 establishing a

IU TSOs proposal for fallback procedures in accordance with Article 44 of the Commission Regulation (EU) 2015/1222 of 24 July 2015 establishing a IU TSOs proposal for fallback procedures in accordance with Article 44 of the Commission Regulation (EU) 2015/1222 of 24 July 2015 establishing a Guideline on Capacity Allocation and Congestion Management

More information