Volume 1 - Contract Data Parts 1 and 2. for the. Edge Lane West Highway and Environmental Improvement Scheme

Size: px
Start display at page:

Download "Volume 1 - Contract Data Parts 1 and 2. for the. Edge Lane West Highway and Environmental Improvement Scheme"

Transcription

1 Volume 1 - for the Edge Lane West Highway and Environmental Improvement Scheme July 2009

2 EDGE LANE WEST HIGHWAY AND ENVIRONMENTAL IMPROVEMENT SCHEME CONTRACT DATA PARTS 1 AND 2 Volume 1 - Issue No 1 Issue Status Author Date Check Date Authorised Date 01 Issued for Tender MA 30/06/09 RF 30/06/09 CJF 04/06/09 02 Issued for ECI 03 Issued for Construction Edge Lane West CD Pt1and2 Volume 1 (Rev 3)

3 EDGE LANE WEST HIGHWAY AND ENVIRONMENTAL IMPROVEMENT SCHEME ECI - DOCUMENTS Volume 1 Conditions of Contract Volume 2 Site Information Pre-Construction Information Pack Project Risk Register Strategic Programme Volume 3 Works Information Bill of Principal Quantities Drawings Specification Statutory Undertakers Schedule Images Library CD Pt 1-2 Volume 1 (Rev 3) i

4 1. General CONTRACT DATA PART ONE DATA PROVIDED BY THE EMPLOYER Content Page 1.1 Conditions of Contract Works description Employer Project Manager Quantity Surveyor Supervisor CDM Coordinator Adjudicator Nomination Body Works Information Site Information Boundaries of the site Language of this contract Law of this contract Period for reply Pre- Construction Information Pack Amendments to the Conditions of Contract Additions to Conditions of Contract Project Risk Register Contractor's Main Responsibilities 2.1 Liability for defects due to Contractor's design Considerate Constructor's Scheme Forecasts of Actual Costs Early Warnings and Compensation Event Notifications Time 3.1 Starting date Possession date Completion date Taking over of works Submission of first programme Submission of revised programmes Delay damages for whole of the works Testing and Defects 4.1 Defects date Defect correction period Landscape Maintenance Period...4 CD Pt 1-2 Volume 1 (Rev 3) ii

5 5. Payment 5.1 Currency of this contract Assessment interval Payments period Interest rate Retention amount Contract Bond Amount Exchange Rates Schedule of Assessment dates Compensation Events 6.1 Place where weather recorded Weather measurements Weather Data Title 7.1 Title Risks and Insurance 8.1 Minimum insurance for third party risks Minimum insurance for Contractor's employees Minimum insurance for Non Recoverable RTA Minimum Insurance for Contractor s All Risk Additional Employer's risks Contractor s Liability Duration of Liability after Completion Performance against Key Performance Indication Additional Insurance Disputes and Termination 9.1 Disagreement over adjudicator Adjudication procedure Schedule of Drawings and Standard Details...8 CD Pt 1-2 Volume 1 (Rev 3) iii

6 Contract Data Part 1 (Data Provided by the Employer) 1. General 1.1 The conditions of contract are the NEC3 New Engineering and Construction Contract ((Third edition issued June 2005) as amended by: Main Payment Option B (Priced Contract with Bill of Quantities) ECC Secondary Options T (Changes in the Law) M (Contractor's Liability for Design) G (Performance Bond) P (Retention Bond) R (Delay Damages) U (CDM Regulations) W1 (Dispute Resolution) Y (UK) 2 (published by the ICE April 1998), Z Clauses and As modified within the Contract Agreement dated..tbc. between Liverpool City Council and the preferred contractor and hereafter referred to as the Conditions of Contract'. 1.2 The Works are the Edge Lane West (ELW) Highways and Environmental Improvement Scheme, and comprise the demolition of residential and business properties, various accommodation works including works to listed properties, coordination and diversion of all statutory undertakers apparatus, extensive temporary traffic management plans and traffic regulation orders, junction improvement at the Holt Road/ Durning Road Junction, Marmaduke Street/ Jubilee Drive Junctions and at Hall Lane/ Edge Lane Junction, upgrade existing crossing at Dorothy Street, construction of new central reservation along the entire route, construction of School Lane access road, carriageway re-construction, closure of redundant accesses and side roads, new communal square, carriageway resurfacing, footway refurbishment, installation of new lighting column, installation new advance directional signage, new carriageway markings, soft landscaping, and public artwork. 1.3 The Employer is Liverpool City Council Municipal Buildings, Dale Street, Liverpool, L69 2DH and is represented by Mr Robert Dunn 1

7 1.4 The Project Manager is Mouchel c/o 2020 Liverpool West House Mercury Court Tithebarn Street Liverpool L2 2QP and is represented by Mr Chris Founds The Project Manager delegates all of his actions to the Supervisor except for the actions required by the following conditions : 14.2 (Delegations) 17.1 (Instruction to resolve ambiguities or inconsistencies) 19.1 (Instruction to resolve illegal or impossible requirements) 20.3 (Issue of Works Information) 44.2 (Acceptance of Defects) 60.1(1) (Changes to the Works Information) 62.3 (Acceptance of Quotations for Compensation Events) 65.1 (Implementation of Compensation Events) 65.4 (Implementation of Compensation Events) 1.5 The Quantity Surveyor and Cost Consultant is Davis Langdon LLP Cunard Building Water Street Liverpool L3 1J R 1.6 The Supervisor is Mouchel c/o 2020 Liverpool West House Mercury Court Tithebarn Street Liverpool L2 2QP 1.7 The CDM Coordinator is Mouchel c/o 2020 Liverpool West House Mercury Court Tithebarn Street Liverpool and is represented by Mr Terry McVey and is represented by TBC. 2

8 L2 2QP 1.8 The Adjudicator nominating body is and is represented by Mr Daniel Blakeley The Institution of Civil Engineers One Great George Street Westminster London SW1P 3AA 1.9 The Works Information is provided in Volumes 2 and 3, and provided as the Specification and Drawings at the Tender Stage Supplementary Site Information, Ground Investigation and Statutory Undertakers diversions are contained within Volume The boundaries of the site are shown in Drawing No /ELW/100/02/ The language of this contract is English The law of the contract is the law of England and Wales. Dispute resolution for the contract is arbitration The period of reply is 7 days The Pre- Construction Information Pack is issued by the CDM Coordinator Amendments to the Conditions of Contract are as listed in the Schedule of Amendment in the Contract Agreement Additions to the Conditions of Contract are as listed in the Schedule of Amendment in the Contract Agreement The Project Risk Register is located in Volume 2 2. The Contractor's Main Responsibilities 2.1 The Contractor's liability for Defects due to his design that are not listed on the Defects Certificate is unlimited. 2.2 The Contractor submits to the Project Manager a copy of the Construction Industry Board's registration certificate within 28 days of the Contract Date confirming registration of the Site under the Considerate Constructor's Scheme. 2.3 The Contractor prepares forecasts of Actual Cost for the works at intervals no longer than 4 weeks. 2.4 The Contractor is required to arrange Early Warning and Compensation 3

9 Event meetings at intervals no longer than 2 weeks. 3. Time 3.1 The starting date of the Contract Period is TBC. 3.2 The possession dates are: Part of the Site... Date 3.3 The Completion Date for the whole of the works is 3.4 The Employer is not willing to take over the Works before the Completion Date. 3.5 The Contractor is to submit a first programme for acceptance within 2 weeks of the Contract Date. 3.6 The Contractor submits a revised Programme at intervals no longer than 4 weeks 3.7 Delay damages for Completion of the whole of the works are per day. 4. Testing and Defects 4.1 The defects date is 52 weeks after the Completion Date for the whole of the works with the exception of Thin wearing course systems exceeding 40mm thickness to Clause 942, which will have a defects date of 36 months after completion. 4.2 The defects correction period is 4 weeks. 4.3 The landscaping defects and aftercare requirements will include all soft landscaping and tree planting within the works and will be maintained for a period of 156 weeks (3 years) after the Completion Date for the whole of the works. The landscape aftercare requirements are detailed in Volume Payment 5.1 The currency of this contract is sterling ( ). 5.2 The assessment interval is 4 weeks. 5.3 The period within which payments are to be made is 28 days. 4

10 5.4 The interest rate is 3% per annum above the rate of the Bank of England. 5.5 The retention free amount is NIL. The retention percentage amount is 5 %. 5.6 The amount of the guarantee bond is 10% of the contract sum. 5.7 Exchange rates are those published in the Financial Times on the Contract Award Date. 5.8 A schedule of Assessment Dates is to be agreed between the Project Manager and the Contractor. 6. Compensation Events 6.1 The place where weather is to be recorded is the nearest Meteorological Station, located at Liverpool Sandon Dock. 6.2 The weather measurements to be recorded for each calendar month are the cumulative rainfall (mm) the number of days with rainfall more than 5mm the number of days with minimum air temperature less than 0 degrees Celsius the number of days with snow lying at 08:00 hours GMT and these measurements: working hours with windspeed exceeding 60km/hr 6.3 The weather data are the records of past weather measurements for each calendar month which were recorded at Liverpool City Centre (Sandon Dock) and Crosby Marina and which are available from The Met Office Fitzroy Road Exeter Devon EX1 3PB Tel: or at 7. Title Refer to the Contract Agreement and Schedule of Amendments 8. Risks and insurance 8.1 The amount of the minimum limit of indemnity for insurance in respect of loss of or damage to property (except the Works, Plant and Materials and Equipment) and liability for bodily injury to or death of a person (not an 5

11 employee of the Contractor) caused by activity in connection with this contract for any one event is 10,000, unlimited. 8.2 The amount of the minimum limit of indemnity for insurance in respect of death of or bodily injury to employees of the Contractor arising out of and in the course of their employment in connection with this contract for any one event shall comply with the statutory requirements of the law. 8.3 The minimum limit of indemnity for insurance in respect of damage to the works due to non recoverable Road Traffic Accident for any one event is 10, unlimited. 8.4 The amount of the minimum limit of indemnity for Contractors All Risks insurance is the price of the work to date. 8.5 The Employer does not provide any of the insurances stated in the Insurance Table. 8.6 The Contractor s total liability to the Employer for all matters arising under or in connection with this contract, other than excluded matters is limited to the price of work to date. 8.7 The end of liability date is 12 months after the completion of the whole of the works 8.8 A report of performance against each Key Performance Indicators is provided at intervals of 3 months 8.9 The additional conditions of contract are as listed in Part 3 of the Schedule of Amendments 9. Disputes and termination 9.1 The body which will choose a new adjudicator if the Parties cannot agree a choice is the Institution of Civil Engineers. 9.2 The Adjudicator is the person appointed as follows: a) In the event that a first dispute is referred to adjudication, the referring Party at the same time applies to the Institution of Civil Engineers to appoint an Adjudicator. b) The application to the Institution includes a copy of this definition of the Adjudicator. c) The referring Party pays the administrative charge made by the Institution. d) The person appointed is also the Adjudicator for later disputes. e) Guidance Notes on the Appointment of an Adjudicator. 6

12 Applications to the Institution are only accepted if made on ICE Form AdjICE. The form assumes that there is a formal 'Notice of Adjudication' which is attached to the application. The NEC contracts do not require any specific formalities to be followed. It is suggested that a covering letter be sent with the application form. The ICE Dispute Administration service can be contacted as follows: Dispute Administration Service The Institution of Civil Engineers One Great George Street Westminster London SW1P 3AA Telephone: Fax:

13 Schedule A Drawings and Standard Details Size Number rev Title Scale Status July 09 Series 100: Preliminaries Statutory Undertakers Works A Scottish Power - LV, HV and 33KV proposed 1:500 Complete /ELW/100/01 alterations Sheet 1 of 2. A Scottish Power - LV, HV and 33KV proposed 1:500 Complete /ELW/100/02 alterations Sheet 2 of /ELW/100/03 A Scottish Power -132KV Sheet 1 of 2. 1:500 Complete /ELW/100/04 A Scottish Power -132KV Sheet 2 of 2. 1:500 Complete A Cable and Wireless - proposed alterations 1:500 Complete /ELW/100/05 Sheet 1 of 2. A Cable and Wireless - proposed alterations 1:500 Complete /ELW/100/06 Sheet 2 of 2. A British Telecom - proposed alterations Sheet 1 1:500 Complete /ELW/100/07 of 2. A British Telecom - proposed alterations Sheet 2 1:500 Complete /ELW/100/08 of /ELW/100/09 A Energis Sheet 1 of 1. 1:500 Complete A National Grid - proposed alterations Sheet 1 of 1:500 Complete /ELW/100/10 2. A National Grid - proposed alterations Sheet 2 of 1:500 Complete /ELW/100/11 2. A United Utilities Water - proposed alterations 1:500 Complete /ELW/100/12 Sheet 1 of 2. A United Utilities Water - proposed alterations 1:500 Complete /ELW/100/13 Sheet 2 of /ELW/100/14 A United Utilities Sewers Sheet 1 of 2. 1:500 Complete /ELW/100/15 A United Utilities Sewers Sheet 2 of 2. 1:500 Complete /ELW/100/16 A WATC - proposed alterations Sheet 1 of 2. 1:500 Complete /ELW/100/17 B WATC - proposed alterations Sheet 2 of 2. 1:500 Complete /ELW/100/18 A Telewest - proposed alterations Sheet 1 of 2. 1:500 Complete /ELW/100/19 A Telewest - proposed alterations Sheet 2 of 2. 1:500 Complete A Combined Statutory Undertakers Services 1:500 Complete /ELW/100/20 Plan Sheet 1 of 2 A Combined Statutory Undertakers Services 1:500 Complete /ELW/100/21 Plan Sheet 2 of 2 A Bus Shelters - existing and proposed locations 1:500 Not Finalised /ELW/100/22 Sheet 1 of 2 A Bus Shelters - existing and proposed 1:500 Not Finalised /ELW/100/23 locations Sheet 2 of 2 A3 A Layout of Statutory Undertakers Services in N.T.S Complete /ELW/100/24 New Footway 3m Wide. A3 A Layout of Statutory Undertakers Services in N.T.S Complete /ELW/100/25 New Footway 5m Wide. Series 100/02: Preliminaries General Details /ELW/100/02/01 C General Arrangement 1:1000 Complete /ELW/100/02/02 B Site Extent and Limitations on Use 1:1000 Complete A Topographical Survey and Site Investigation 1:500 Not Finalised /ELW/100/02/03 Details Sheet 1 of 2 A Topographical Survey and Site Investigation 1:500 Not Finalised /ELW/100/02/04 Details Sheet 2 of 2 Series 100/03: Preliminaries Setting Out Details /ELW/100/03/01 A MX Setting Out Details 1:1000 Not Started 8

14 Size Number rev Title Scale Status July /ELW/100/03/02 A MX Proposed Surface Contours Sheet 1 of 2 1:500 Not Finalised /ELW/100/03/03 A MX Proposed Surface Contours Sheet 2 of 2 1:500 Not Finalised /ELW/100/03/04 A Proposed Cross Sections Sheet 1 of 6 1:200 Not Finalised /ELW/100/03/05 A Proposed Cross Sections Sheet 2 of 6 1:200 Not Finalised /ELW/100/03/06 A Proposed Cross Sections Sheet 3 of 6 1:200 Not Finalised /ELW/100/03/07 A Proposed Cross Sections Sheet 4 of 6 1:200 Not Finalised /ELW/100/03/08 A Proposed Cross Sections Sheet 5 of 6 1:200 Not Finalised /ELW/100/03/09 A Proposed Cross Sections Sheet 6 of 6 1:200 Not Finalised Series 100/04: - Accommodation Works /ELW/100/04/01 B Plan Showing Accommodation Works 1:1000 Complete /ELW/100/04/02 C Varies Revisions Boundary Treatment to 91 Edge Lane reqd /ELW/100/04/03 A Varies Revisions Boundary Treatment to 99 Edge Lane reqd /ELW/100/04/04 C Boundary Treatment to 115 Edge Lane Varies Revisions /ELW/100/04/05 A Boundary Treatment to 145 Edge Lane Varies reqd Revisions reqd /ELW/100/04/06 A Boundary Treatment to The Hindu Centre Varies Complete Series 200: Site Clearance /ELW/200/01 B Site Clearance Details Sheet 1 of 2 1:500 Complete /ELW/200/02 B Site Clearance Details Sheet 2 of 2 1:500 Complete A0 A Marmaduke St / Jubilee Dr Traffic Signals Site 1:200 Complete /ELW/200/03/01 Clearance A /ELW/200/03/02 A Dorothy Street Puffin Site Clearance 1:200 Complete B Durning Road / Holt Road Traffic Signals Site 1:200 Complete /ELW/200/03/03 Clearance A /ELW/200/05/01 A Current Level of Property Acquisitions NTS Complete A /ELW/200/05/02 A Highway Demolition Areas NTS Complete Series 300: Fencing, Gates and Stiles /ELW/300/01 B Fencing and Gates 1:500 Complete Series 400: Road Restraint Systems (Vehicle and Pedestrian) A /ELW/400/01 A Pedestrian Guardrail Detail Complete A /ELW/400/02 A Marmaduke St / Jubilee Dr Pedestrian 1:200 Complete Guardrail A /ELW/400/03 A Dorothy Street Puffin Pedestrian Guardrail 1:200 Complete A /ELW/400/04 A Durning Road / Holt Road Pedestrian Guardrail 1:200 Complete Series 500: Drainage and Service Ducts /ELW/500/01 A Highway Drainage Layout Sheet 1 of 2 1:500 Complete /ELW/500/02 A Highway Drainage Layout Sheet 2 of 2 1:500 Complete /ELW/600/03 A Highway Drainage Construction Details Not Finalised Series 600: Earthworks /ELW/600/01 A Earthworks Details Sheet 1 of 2 1:500 Complete /ELW/600/02 A Earthworks Details Sheet 2 of 2 1:500 Complete /ELW/600/03 A Typical Earthworks Cross Sections 1:50 Not Finalised Series 700: Pavements /ELW/700/01 C Pavement Details Sheet 1 of 2 1:500 Complete /ELW/700/02 C Pavement Details Sheet 2 of 2 1:500 Complete A /ELW/700/03 A Marmaduke St / Jubilee Dr HFS 1:200 Complete /ELW/700/04 A Dorothy Street Puffin HFS 1:200 Complete A /ELW/700/05 A Durning Road / Holt Road HFS 1:200 Complete A /ELW/700/03 A School Lane Speed Hump Detail Not Finalised Series 1100: Kerbing, Footways and Paved Areas /ELW/1100/01 C Kerbing and Footway Details Sheet 1 of 2 1:500 Complete 9

15 Size Number rev Title Scale Status July /ELW/1100/02 C Kerbing and Footway Details Sheet 2 of 2 1:500 Complete /ELW/1100/02/01 A Marmaduke Street Junction Kerbing and Not Finalised Footway Details /ELW/1100/02/02 A Dorothy Street Puffin Crossing - Kerbing and Not Finalised Footway Details /ELW/1100/02/03 A Durning Road Junction Kerbing and Footway Not Finalised Details /ELW/1100/03/01 A Footway Crossover FC01 (Typical) Property 1:25 Complete Nos 73 to /ELW/1100/03/02 A Footway Crossover FC02 Property No 91 1:25 Not Finalised /ELW/1100/03/03 A Footway Crossover FC03 Property Nos 99 1:25 Not Finalised and /ELW/1100/03/04 A Footway Crossover FC04 TA Centre Adj No 1:25 Not Finalised /ELW/1100/03/05 A Footway Crossover FC05 TA Centre Corner 1:25 Not Finalised Botanic Rd /ELW/1100/03/06 A Footway Crossover FC06 Botanic Park 1:25 Not Finalised Entrance /ELW/1100/03/07 A Road Crossing RC01 Adjacent Property No 1:25 Not Finalised 10A /ELW/1100/03/08 A Road Crossing RC02 (Typical) - Flaxman 1:25 Complete Street /ELW/1100/03/09 A Entry Treatment ET01 Adelaide Road 1:25 Not Finalised /ELW/1100/03/10 A Entry Treatment ET02 (Typical) Leopold 1:25 Complete Road /ELW/1100/03/11 A Entry Treatment ET03 Empress Road 1:25 Not Finalised /ELW/1100/03/12 A Side Road SR01 School Lane West Junction 1:25 Not Finalised /ELW/1100/03/13 A Side Road SR02 (Typical) School Lane 1:25 Complete South Junction /ELW/1100/03/14 A Private Access PA01 (Typical) Property Nos 1:25 Complete 126 / /ELW/1100/03/15 A Private Access PA02 Property No 134 1:25 Not Finalised /ELW/1100/03/16 A Private Access PA03 Property No 265 1:25 Not Finalised /ELW/1100/03/17 A Redundant Access RA01 (Typical) Quorn 1:25 Complete Street /ELW/1100/03/18 A Redundant Access RA02 Adderley Street 1:25 Not Finalised /ELW/1100/03/19 A Redundant Access RA03 Dorothy Street 1:25 Not Finalised Series 1200: Traffic Signs and Road Markings /ELW/1200/01/01 A Traffic Signs and Road Markings Sheet 1 of 1:500 Complete /ELW/1200/01/02 A Traffic Signs and Road Markings Sheet 1 of 1:500 Complete 2 A /ELW/1200/03/01 B Marmaduke St / Jubilee Dr Traffic Signals 1:200 Not Finalised Road Markings A /ELW/1200/03/02 A Dorothy Street Puffin Traffic Signals Road 1:200 Not Finalised Markings A /ELW/1200/03/03 B Durning Road / Holt Road Traffic Signals Road Markings 1:200 Not Finalised Series 1200: Traffic Signals A /ELW/1200/02/01 B Marmaduke St / Jubilee Dr Traffic Signals 1:200 Complete General Arrangement A /ELW/1200/02/02 B Dorothy Street Puffin Traffic Signals General 1:200 Complete Arrangement A /ELW/1200/02/03 B Durning Rd / Holt Rd Traffic Signals General 1:200 Complete 10

16 Size Number rev Title Scale Arrangement A /ELW/1200/02/04 B Marmaduke St / Jubilee Dr Traffic Signals Signal Layout Status July 09 1:200 Complete A /ELW/1200/02/05 A Dorothy Street Puffin Signal Layout 1:200 Complete A /ELW/1200/02/06 B Durning Rd / Holt Rd Traffic Signals Signal 1:200 Complete Layout A /ELW/1200/02/07 B Marmaduke St / Jubilee Dr Traffic Signals 1:200 Not Finalised Detector Loops A /ELW/1200/02/08 B Dorothy Street Puffin Detector Loops 1:200 Not Finalised A /ELW/1200/02/09 B Durning Rd / Holt Rd Traffic Signals Detector 1:200 Not Finalised Loops A /ELW/1200/02/10 B Marmaduke St / Jubilee Dr Traffic Signals 1:200 Not Finalised Ducting & Chambers /ELW/1200/02/11 B Dorothy Street Puffin Ducting & Chambers 1:200 Not Finalised A /ELW/1200/02/12 B Durning Rd / Holt Rd Traffic Signals Ducting & Chambers 1:200 Not Finalised Series 1300: Street Lighting A /ELW/1300/01 A Street Lighting Site Clearance 1:500 Not Finalised A /ELW/1300/02 A Proposed Street Lighting 1:500 Complete /ELW/1300/03 B Proposed Street Lighting (School Access Road) Series 1700: Structural Concrete /ELW/1700/01 A School Lane Retaining Wall Plan and Typical Section /ELW/1700/02 A School Lane Retaining Wall Long and Cross Sections Series 3000: Landscape and Ecology /ELW/3000/01 B Public Realm & Landscape General Arrangements 1:500 Complete Varie s Varie s 1: /ELW/3000/02 A Tree Pit and Planting Details Varie s Not Finalised Not Finalised Complete Complete 11

17 Edge Lane West - Highways and Environmental Improvement Scheme CONTRACT DATA PART TWO - DATA PROVIDED BY THE CONTRACTOR 1.1 The Contractor is Name. Address Line 1. Address Line 2. Represented by 1.2 The Direct fee percentage is.% 1.3 The subcontracted fee percentage is.% 1.4 The working areas are the Site and.. [Note: the Contractor s head office or other premises as an additional area are not permitted include these costs under (1.2) above]. 1.5 The Contractor's key persons together with CVs (no longer than 1 A4 page), are as follows: Contractor's Director... Contractor s Commercial Director... Contractor s Project Manager... Contractor s Commercial Manager... Managing/ Lead Quantity Surveyor... Engineer(s) Contractor's Site Agent Contractor's Site Safety Officer... Contractor's Planner... Contractor's Deputy Site Safety Officer... *Contractor's Quality Manager... Contractor's Traffic Safety and Control Officer... Contractor's Deputy Traffic Safety and Control Officer... Contractor's Designer... Contractor's General Foreman... (* include/delete as required) I

18 1.6 The Works information for the Contractor s design is in The programme identified in the Contract Data is 1.9 We confirm that the adjudicator's appointment as set out in Contract Data Part One *is acceptable *is not acceptable Our proposed names of Subcontractors, their experience and qualifications, and areas of work envisaged are given in Annex A. [Note: include one Subcontractor only for each area of work]. We confirm that we are registered under the Inland Revenue's Construction Industry Scheme. We hold the following valid type certificate: Details of our insurance policies held or proposed to meet the full requirements of this contract are given in the Quality Submission. We confirm that any excess included in our insurance policies does not exceed the permitted limits as follows: (a) for insurance risks relating to loss of or damage to the works, plant and materials, as follows: (b) for all other insurance risks relating to loss of or damage to equipment and property, bodily injury or death to the Contractor's employees and bodily injury or death to third parties, as follows: 1.12 The quality statement is in a separate section marked Quality Statement We confirm that a parent company guarantee [*is not necessary for this contract.] [*will be provided within 14 days of the Contract Date]. 2. Data for Schedule of Cost Components 2.1 The hourly rates for Actual Cost of manufacture and fabrication outside the Working Areas are: Category of employee Hourly rate Senior Engineer Engineer Technician Skilled Labour Semi Skilled Labour 2.2 The percentage for manufacture and fabrication overheads is...% 1. The hourly rates for Actual Cost of design outside the Working Areas are: II

19 Category of Employee Hourly Rate The hourly rates for Actual Cost of Site Employees: Category of Employee Hourly Rate The percentage for design overheads is % 2.6 The categories of employees whose travelling expenses to and from the Working Areas are included in the Actual Cost are The percentage for Working Area Overheads is....% (i) (ii) Please note that the Shorter Schedule of Cost Components is used for the assessment of Compensation Events Please note for the purposes of Assessments, the Working Area Overhead is not required 2.8 The percentage for people overheads is...% 2.9 The published list of Equipment is the last edition of the list published by the Civil Engineering Contractor's Association The percentage for adjustment for listed Equipment is... % [Insert either a "+" or a "-" figure] 2.11 The rates of other Equipment are: Equipment size or capacity rate 2.12 The hourly rate for Defined Cost of design outside the Working Areas are Category of employee hourly rate III

20 2.13 The percentage for design overheads is % 2.14 The categories of design employees whose travelling expenses to and from the Working Areas are included in Defined Cost are Annex A NAMED SUBCONTRACTORS [Note: include one subcontractor only for each area of work] Note: All sub contractors will be subject to the approval of the Project Manager IV

21 PRICING DATA (Data provided by the Contractor) 1 Bill of Principal Quantities 2 Priced Construction Risk Register 3 Programme 4 ECI Technical Query Register (To be developed) 5 Staff Fee Schedule for Stage 2 Works V

22 CONTRACTORS QUALITY STATEMENT (Data provided by the Contractor) Contents Part I: Quality Submission requirements Part II: Questionnaire on Health and Safety PART I: QUALITY SUBMISSION REQUIREMENTS Where the contractor s Tender Quality Statement does not satisfy the elements listed below, use the following as the framework for the Quality Plan Please provide the following information in the numbered format required below: Section 1 - PROPOSED CONTRACT MANAGEMENT STRUCTURE 1.1 Provide details of your proposed organisation structure for this contract to include Contractor Director, Contract Manager and those nominated roles within Contract Data Part 2. Provide CVs for all personnel. Section 2 - PROPOSED CONTRACT EXECUTION 2.1 Method Statement: Provide a method statement for the works that describes the approach to this contract and the methodology to be employed, including proposals for mitigating any identified risks. This should include type and availability of resources and plant to be utilised and any innovative ideas of significance to the timely and cost effective completion of the works. 2.2 Proposed Use of Sub-Contractors: Procedures and criteria for selection and management of those sub-contractors proposed for this contract as per Contract Data Part Outline Programme: An outline programme including level of resources for each activity in accordance with Numbered Appendix 1/13 in Works Information. 2.4 Environmental Management Proposals: Proposals for environmental management of the works to mitigate the impact of the works on workers, adjoining neighbours and the public against dust, noise and vibration. Include draft dust management and noise management plans. 2.5 Quality Plan: Proposed outline quality plan in accordance with Numbered Appendix 1/24 in the Works Information 2.6 Use of Local Labour: Proposals for the Contractors approach and commitment within this contract to the use of local labour recruitment, and/or creation of training opportunities. 2.7 Community Liaison and Stakeholder Management: Proposals for stakeholder management, community liaison, public relations and liaison procedures with VI

23 the Project Manager, Supervisor, Employer, in accordance with Clause 172AR of the Contract. ; 2.8 Measurement and Agreement of the Works: Proposals for the measurement and agreement of the works. Proposals for the timely close-out and completion of the works and commitment to achieving agreement of the Final Account. (No longer than 4 A4 pages) 2.9 Health and Safety: Responses to the questionnaire on health and safety as set out at Annex C Insurances: Details of insurance policies held or proposed meeting requirements stated in the Insurance Table within clause 84 of ECC and the Contract Data must be submitted. PART II: QUESTIONNAIRE ON HEALTH AND SAFETY FOR THE PURPOSES OF CONSTRUCTION (DESIGN AND MANAGEMENT) REGULATIONS 2007 PROJECT SPECIFIC Written statements are required on the following:- (a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) What is your technical and managerial approach for dealing with the significant and unusual hazards and risks identified in the Pre-construction Information Pack issued with the tender documents? Confirm that appropriate provision has been made in your tender for all the items listed in Part III of this Questionnaire. Induction training for new starters, tool-box talks and other training for special risk situations, etc. Maintenance of safe systems of work, including whether there are written risk assessments and method statements. Work equipment. Personal protective equipment. Adequate and appropriate plant, including arrangements for inspection and testing. Control of substances hazardous to health, including correct identification, assessment, storage and handling in accordance with COSHH Regulations. Protection of the workforce and the public against vibration, dust and noise. Manual handling, including assessing ergonomics of workplace layouts and work activities. First-aid, including provision of trained first aiders and the keeping of documented medical records. VII

24 (l) (m) (o) (p) (q) Reporting accidents and incidents in conformance with the requirements of the Reporting of Injuries, Diseases and Dangerous Occurrences Regulations 1989 (RIDDOR) and the keeping of proper records related thereto. Suitable and sufficient accident investigation procedures. Arrangements for visitors to the site. Provision of welfare, messing, washing and drying facilities in accordance with the Construction (Health, Safety and Welfare) Regulations Complying with the Working Time Regulations 1998 with particular reference to any night working. NON-PROJECT SPECIFIC Responses are required to the following questions in respect of your company's organisation and management: (a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) Provide evidence of the company's commitment to and policy on health and safety. What arrangements are there for keeping that policy under regular review? Which senior director is named as being responsible and has the company's policy statement been signed by him? What are the management arrangements for delegating responsibility to named individuals? Provide evidence that you have clear and detailed working methods for achieving the company's policy objectives. What is the system and responsibility for reporting health and safety matters within your company? What cooperation and involvement is expected of employees, subcontractors and the self employed? What procedures are there for safety inspections and audits? What is the employee training programme? What trade union or employee safety structure is in operation? What is the system for control of subcontractors? VIII

TRANSNET NATIONAL PORTS AUTHORITY RFP NUMBER TNPA 541 DESCRIPTION OF THE WORKS: PORT OF RICHARDS BAY - CONSTRUCTION OF PORT ENTRANCES AND ACCESS ROADS

TRANSNET NATIONAL PORTS AUTHORITY RFP NUMBER TNPA 541 DESCRIPTION OF THE WORKS: PORT OF RICHARDS BAY - CONSTRUCTION OF PORT ENTRANCES AND ACCESS ROADS C1.2 Contract Data Part one - Data provided by the Employer Clause Statement Data 1 General The conditions of contract are the core clauses and the clauses for main Option B: Priced Contract with Bill

More information

CONTRACT DATA. Part one Data provided by the Employer CONTRACT DATA PART 1

CONTRACT DATA. Part one Data provided by the Employer CONTRACT DATA PART 1 CONTRACT DATA Part one Data provided by the Employer Statements given in all contracts Completion of the data in full, according to the Options chosen, is essential to create a complete contract. 1 General

More information

CAMBRIDGESHIRE GUIDED BUSWAY OPERATIONS POLICY

CAMBRIDGESHIRE GUIDED BUSWAY OPERATIONS POLICY CAMBRIDGESHIRE GUIDED BUSWAY OPERATIONS POLICY Page 1 of 7 CGB OPERATIONS POLICY Contents: 1. Introduction 2. Contents 3. General Policy 4. Safety Inductions 5. Access 6. Requirements and Restrictions

More information

Professional Services Contract

Professional Services Contract Professional Services Contract Revising the programme 32 32.1 The Consultant shows on each revised programme. the actual progress achieved on each operation and its effect upon the timing of the reing

More information

Conditions of Contract for PLANT and Design-Build

Conditions of Contract for PLANT and Design-Build Conditions of Contract for PLANT and Design-Build FOR ELECTRICAL AND MECHANICAL WORKS AND FOR BUILDING AND ENGINEERING WORKS DESIGNED BY THE CONTRACTOR General Conditions 1st Edition 1999 FEDERATION INTERNATIONALE

More information

Council Assets REGENT STREET CHIPPENDALE NSW Commissioned by LAING O'ROURKE. Report prepared by JOHN MAGLIS

Council Assets REGENT STREET CHIPPENDALE NSW Commissioned by LAING O'ROURKE. Report prepared by JOHN MAGLIS Council Assets 56-64 REGENT STREET CHIPPENDALE NSW 2008 DILAPIDATION REPORT Commissioned by LAING O'ROURKE Report prepared by JOHN MAGLIS 0414 885 748 TYRRELLS PROPERTY INSPECTIONS PTY LIMITED Inspection

More information

PREQUALIFICATION QUESTIONNAIRE

PREQUALIFICATION QUESTIONNAIRE PREUALIFICATION UESTIONNAIRE 1.0 COMPANY DETAILS 1.1 Please complete the company details below: Company: Post Code: Tel: E-mail Contact: Title: CRN: Fax: Website: 1.2 Does this Company have a Parent Company

More information

KIER CONSTRUCTION LIMITED. Trading as Kier Construction-Eastern NEC3 SUBCONTRACT CAMBRIDGESHIRE COUNTY COUNCIL FRAMEWORK - OPTION [A, B, C, D, E]

KIER CONSTRUCTION LIMITED. Trading as Kier Construction-Eastern NEC3 SUBCONTRACT CAMBRIDGESHIRE COUNTY COUNCIL FRAMEWORK - OPTION [A, B, C, D, E] KIER CONSTRUCTION LIMITED Trading as Kier Construction-Eastern NEC3 SUBCONTRACT CAMBRIDGESHIRE COUNTY COUNCIL FRAMEWORK - OPTION [A, B, C, D, E] Originator: [insert] Approved for issue: [insert] Sub-contract

More information

Peter Kerrigan CONTRACTING ON NEC 3 ENGINEERING CONSTRUCTION CONTRACT OPTION A - AN INTRODUCTION.

Peter Kerrigan CONTRACTING ON NEC 3 ENGINEERING CONSTRUCTION CONTRACT OPTION A - AN INTRODUCTION. CONTRACTING ON NEC 3 ENGINEERING CONSTRUCTION CONTRACT OPTION A - AN INTRODUCTION Peter Kerrigan LL.B (HONS), FRICS, FCIARB, BARRISTER www.kerrigans.net 1 Course Content Introduction and overview of ECC

More information

Employer s agent services

Employer s agent services Corporate Professional Local Employer s agent services For use with the RICS Standard form of consultant s appointment and RICS Short form of consultant s appointment The mark of property professionalism

More information

ENGINEERING AND CONSTRUCTION CONTRACT

ENGINEERING AND CONSTRUCTION CONTRACT THE NEC 3RD EDITION ENGINEERING AND CONSTRUCTION CONTRACT INTRODUCTION AND CRITICAL APPRAISAL For the HKIS March 23 rd 2010 Ian Heaphy Agenda Engineering and Construction Contract 3rd Edition: Aim of Presentation

More information

AGREEMENT AND CONDITIONS OF SUB-CONTRACT (DOMESTIC)

AGREEMENT AND CONDITIONS OF SUB-CONTRACT (DOMESTIC) AGREEMENT AND CONDITIONS OF SUB-CONTRACT (DOMESTIC) FOR USE IN CONJUNCTION WITH THE FORMS OF MAIN CONTRACT FOR PUBLIC WORKS ISSUED BY THE OFFICE OF GOVERNMENT PROCUREMENT, DEPARTMENT OF PUBLIC EXPENDITURE

More information

SUB CONTRACTOR INDUCTION PACK

SUB CONTRACTOR INDUCTION PACK REQUIREMENTS FOR WORKING ON ROYAL MAIL PREMISES 1. INTRODUCTION AND PURPOSE This document sets out the arrangements that Royal Mail Property & Facilities Solutions Limited and Royal Mail [hereinafter jointly

More information

Risk Assessment Procedure

Risk Assessment Procedure 1. Introduction Risk Assessment Procedure 1.1 The Management of Health and Safety at Work Regulations 1999 set out general duties which apply to employers and are aimed at improving health and safety management.

More information

MAJ Developments (UK) Ltd CONTRACTORS PRE-QUALIFICATION QUESTIONNAIRE (PQQ)

MAJ Developments (UK) Ltd CONTRACTORS PRE-QUALIFICATION QUESTIONNAIRE (PQQ) MAJ Developments (UK) Ltd CONTRACTORS PRE-QUALIFICATION QUESTIONNAIRE (PQQ) In accordance with the requirements of the Health and Safety at Work etc. Act 1974, Management of Health and Safety at Work Regulations

More information

Occupational Safety & Health Policy & Guidelines for Contractors

Occupational Safety & Health Policy & Guidelines for Contractors Occupational Safety & Health Policy & Guidelines for Contractors Occupational Safety & Health Policy & Guidelines for Contractors Table of Contents Forward..1 Introduction... 1 Policy.1 City of Kalamunda

More information

2 nd Edition September 2005 (Second Edition of CIDB document 1020)

2 nd Edition September 2005 (Second Edition of CIDB document 1020) Supply of Goods (Short Contract) 2 nd Edition September 2005 (Second Edition of CIDB document 1020) CIDB Supply of Goods (Short Contract) September 2005, Second Edition of CIDB document 1020 SUPPLY OF

More information

The NEC 3 Engineering and Construction Contract

The NEC 3 Engineering and Construction Contract The NEC 3 Engineering and Construction Contract The NEC 3 Engineering and Construction Contract A Commentary Second Edition Brian Eggleston CEng, FICE, FIStructE, FCIArb Blackwell Science 2006 Brian Eggleston

More information

NEC3 ECC target contract option principles and innovative applications

NEC3 ECC target contract option principles and innovative applications INFRASTRUCTURE NEC3 ECC target contract option principles and innovative applications INTRODUCTION ISO 6707-2, Building and civil engineering Vocabulary Part 2: Contract terms, defines a target cost contract

More information

City of Portsmouth Portsmouth, New Hampshire Department of Public Works

City of Portsmouth Portsmouth, New Hampshire Department of Public Works RFP# 10-07 City of Portsmouth Portsmouth, New Hampshire Department of Public Works MARKET STREET BICYCLE AND PEDESTRIAN PATH BETWEEN MICHAEL SUCCI DRIVE AND THE NH PORT AUTHORITY REQUEST FOR PROPOSAL Sealed

More information

L E I A CONDITIONS OF CONTRACT

L E I A CONDITIONS OF CONTRACT Lift and Escalator Industry Association L E I A CONDITIONS OF CONTRACT for the manufacture, supply, installation, modernisation and repair of LIFTS JANUARY 2010 33-34 Devonshire Street, London W1G 6PY

More information

The Landscape Consultant s Appointment

The Landscape Consultant s Appointment The Landscape Consultant s Appointment The Landscape Institute 33 Great Portland Street London W1W 8QG Tel: +44 (0)20 7299 4500 Fax: +44 (0)20 7299 4501 Email: mail@landscapeinstitute.org Web: www.landscapeinstitute.org

More information

Course agenda. Course agenda. NEC3: Introduction to the Engineering and Construction Contract (ECC)

Course agenda. Course agenda. NEC3: Introduction to the Engineering and Construction Contract (ECC) NEC3: Introduction to the Engineering and Construction Contract (ECC) Course agenda Welcome and Introductions Session 1 elearning review Session 2 the ECC system and contract strategy the Options Session

More information

Special Conditions, Regulations and Instructions for Right of Way Permit Applications

Special Conditions, Regulations and Instructions for Right of Way Permit Applications Special Conditions, Regulations and Instructions for Right of Way Permit Applications The Department of Environmental Services (DES) issues public right of way (PROW) permits to contractors with a valid

More information

1997 Part 2. Document B141. Standard Form of Architect's Services: Design and Contract Administration TABLE OF ARTICLES

1997 Part 2. Document B141. Standard Form of Architect's Services: Design and Contract Administration TABLE OF ARTICLES TM Document B141 Standard Form of Architect's Services: Design and Contract Administration 1997 Part 2 TABLE OF ARTICLES 2.1 PROJECT ADMINISTRATION SERVICES 2.2 SUPPORTING SERVICES 2.3 EVALUATION AND PLANNING

More information

Contractor Safety Plan

Contractor Safety Plan Contractor Safety Plan INSTRUCTIONS Scope This form is to be completed by the contractor that has been identified as a major contract. This Plan expires at the completion of the contract work or 12 months

More information

TENDER FOR THE TOWNSHIP OF SEVERN

TENDER FOR THE TOWNSHIP OF SEVERN TENDER FOR THE TOWNSHIP OF SEVERN Contract No. PW2017-1O 1 Page S Contract No. PW2017-1O The Corporation of the Township of Severn Tender Closing Date is February 17, 2017 at 10:00 a.m. Local Time Lowest

More information

Guideline Scope of Services and Tariff of Fees for Persons Registered in terms of the Engineering Profession Act, 2000, (Act No.

Guideline Scope of Services and Tariff of Fees for Persons Registered in terms of the Engineering Profession Act, 2000, (Act No. Page 1 BOARD NOTICE 30 OF 2007 Engineering Council of South Africa Guideline Scope of Services and Tariff of Fees for Persons Registered in terms of the Engineering Profession Act, 2000, (Act No.46 of

More information

Health & Safety Policy

Health & Safety Policy Health & Safety Policy K4S Security Ltd Imperial Office 2a Heigham Road East Ham London E6 2JG Registered Company Number: 09646212 Policy Date: 12 April 2018 1/14 Contents Page 1.0 General Statement of

More information

The City of Roanoke is currently soliciting bid proposals for fire lane striping for all City owned facilities with fire lanes.

The City of Roanoke is currently soliciting bid proposals for fire lane striping for all City owned facilities with fire lanes. Request for Proposal (RFP) The City of Roanoke is currently soliciting bid proposals for fire lane striping for all City owned facilities with fire lanes. Bids are due January 4, 2018 at 12:00 pm CST.

More information

UNDERGROUND SERVICE STRIKES

UNDERGROUND SERVICE STRIKES UNDERGROUND SERVICE STRIKES GUIDELINES FOR CONSTRUCTION COMPANIES An underground service strike can lead to injury or loss of life and the costs to your business can be substantial. This short guide is

More information

2016 CDM Smith All Rights Reserved July 2016 SECTION SAFETY, HEALTH, AND EMERGENCY RESPONSE

2016 CDM Smith All Rights Reserved July 2016 SECTION SAFETY, HEALTH, AND EMERGENCY RESPONSE PART 1 GENERAL 1.01 SCOPE OF WORK SECTION 01 11 01 SAFETY, HEALTH, AND EMERGENCY RESPONSE A. Pursuant to Section 107 of the Contract Work Hours and Safety Standards Act and DOL Regulations set forth in

More information

CORK COUNTY COUNCIL. Senior Resident Engineer Road Construction Supervision

CORK COUNTY COUNCIL. Senior Resident Engineer Road Construction Supervision CORK COUNTY COUNCIL Senior Resident Engineer Road Construction Supervision QUALIFICATIONS 1. Character Candidates shall be of good character. 2. Health Canidates shall be in a state of health such as would

More information

Control of Cranes, Hoists and Elevated Work Platforms on Public Roads in Waterford

Control of Cranes, Hoists and Elevated Work Platforms on Public Roads in Waterford Direction in the Control of Cranes, Hoists and Mobile Elevated Work Platforms on Public Roads in Waterford Legal Background In accordance with Section 101D Road Traffic Act, 1961 (Subsection 2) as inserted

More information

Ebbsfleet Development Corporation

Ebbsfleet Development Corporation Title of paper Finance and Operations Report as at 31 March 2018 Presented by Sub-committee Gerard Whiteman, Director of Finance Not applicable Purpose of Paper and Executive Summary An update on EDC budgets,

More information

Contractor Information

Contractor Information Contractor Information Contractor Induction Program Table of Contents Introduction... 1 Contractor Occupational Safety and Health Management Systems... 2 Safety Orientation Sessions for Contractors Employees...

More information

Section 7. General Conditions of Contract for the Procurement of Works

Section 7. General Conditions of Contract for the Procurement of Works Section 7. General Conditions of Contract for the Procurement of Works Table of Clauses A. General...3 1. Definitions...3 2. Interpretation...5 3. Language and Law...5 4. Project Manager s Decisions...5

More information

Transnet Freight Rail E.4E Transnet (August 2006) A Division of Transnet Ltd. TRANSNET LIMITED (Registration no. 1990/000900/06) PRIEVIEW COPY ONLY

Transnet Freight Rail E.4E Transnet (August 2006) A Division of Transnet Ltd. TRANSNET LIMITED (Registration no. 1990/000900/06) PRIEVIEW COPY ONLY TRANSNET LIMITED (Registration no. 1990/000900/06) SAFETY ARRANGEMENTS AND PROCEDURAL COMPLIANCE WITH THE OCCUPATIONAL HEALTH AND SAFETY ACT (ACT 85 OF 1993) AND APPLICABLE REGULATIONS 1. General 1.1 The

More information

Asbestos Management. Date of Approval: Date for Next Scheduled Review: Review Body: Equality Impact Assessment Complete: Policy Published on Web:

Asbestos Management. Date of Approval: Date for Next Scheduled Review: Review Body: Equality Impact Assessment Complete: Policy Published on Web: Asbestos Management Policy Title: Policy Author: Date of Approval: Date for Next Scheduled Review: Review Body: Asbestos Management Diane Hendry MC Equality Impact Assessment Complete: Policy Published

More information

NZS 3915:2005 AMENDMENTS. No. Date of issue Description Entered by, and date

NZS 3915:2005 AMENDMENTS. No. Date of issue Description Entered by, and date NZS 3915:2005 COMMITTEE REPRESENTATION This Standard was prepared by Technical Committee P 3915 for the Standards Council established under the Standards Act 1988. Peter Fehl New Zealand Contractors Federation

More information

2 The Contractor s main responsibilities

2 The Contractor s main responsibilities Core Clauses 2 The Contractor s responsibilities Providing the Service 20 20.1 The Contractor Provides the Service in accordance with the Service Information. 20.2 In Providing the Service, the Contractor

More information

WORK IN OR ABOUT QR PROPERTY

WORK IN OR ABOUT QR PROPERTY SYSTEMS AND CAPABILITY TECHNICAL REQUIREMENT NO: MCE-SR-002 ISSUE: Revision E DATE: 22-12-2009 PAGE: 1 of 12 WORK IN OR ABOUT QR PROPERTY ISSUE DATE DESCRIPTION / REASON Initial 05.03.1997 Revision A 14.05.1997

More information

CHARTERED INSTITUTE OF ARBITRATORS NEC compensation events A process for all eventualities? April 21 st 2016

CHARTERED INSTITUTE OF ARBITRATORS NEC compensation events A process for all eventualities? April 21 st 2016 CHARTERED INSTITUTE OF ARBITRATORS NEC compensation events A process for all eventualities? April 21 st 2016 SARAH KELLERMAN PARTNER m +44 (0) 7810 850 387 e sarah.kellerman@arcadis.com Arcadis Arcadis,

More information

Skip Permit Application Form

Skip Permit Application Form Skip Permit Application Form Roads Department, Civic Offices, Dungarvan, Co. Waterford. Ph: 0761 10 2020; email: contact@waterfordcouncil.ie; www.waterfordcouncil.ie Please note that all applications for

More information

Cork County Council. Resident Technician/Clerk of Works Road Construction Supervision

Cork County Council. Resident Technician/Clerk of Works Road Construction Supervision Cork County Council Resident Technician/Clerk of Works Road Construction Supervision Qualifications 1. Character Each candidate must be of good character. 2. Health Each candidate must be in a state of

More information

DIVISION 1 - GENERAL REQUIREMENTS SECTION APPLICATIONS FOR PAYMENT

DIVISION 1 - GENERAL REQUIREMENTS SECTION APPLICATIONS FOR PAYMENT DIVISION 1 - GENERAL REQUIREMENTS SECTION 01027 APPLICATIONS FOR PAYMENT I. GENERAL This section specifies administrative and procedural requirements governing Contractor Applications For Payment. II.

More information

Occupational Health and Safety Act, Major Hazard Installation Regulations

Occupational Health and Safety Act, Major Hazard Installation Regulations Occupational Health and Safety Act, 1993 Major Hazard Installation Regulations The Minister of Labour has, after consultation with the Advisory Council for Occupational Health and Safety, under section

More information

Minimum SHE Requirements for Construction Related RFQ projects

Minimum SHE Requirements for Construction Related RFQ projects 1. SCOPE OF WORK: Repairing the Palisade Fence at Olifantsvlei Village 2. PURPOSE The aim of the SHE specification is to ensure that any contractor which is appointed by Johannesburg Water to conduct any

More information

ITW LTD T/A AVERY WEIGH-TRONIX SAFETY, HEALTH AND ENVIRONMENTAL INFORMATION

ITW LTD T/A AVERY WEIGH-TRONIX SAFETY, HEALTH AND ENVIRONMENTAL INFORMATION ITW LTD T/A AVERY WEIGH-TRONIX SAFETY, HEALTH AND ENVIRONMENTAL INFORMATION January 2018 1 Introduction We recognize that as a customer of Avery Weigh-Tronix, you require details of our management of safety,

More information

NEC4 Engineering and Construction Contract review of changes from NEC3

NEC4 Engineering and Construction Contract review of changes from NEC3 Here is a review from GMH Planning Ltd of the significant changes within the NEC4 ECC contract compared to that of the NEC3 version. We have not identified every single change, but picked out the main

More information

WRITTEN AGREEMENT FOR OCCUPATIONAL HEALTH AND SAFETY

WRITTEN AGREEMENT FOR OCCUPATIONAL HEALTH AND SAFETY WRITTEN AGREEMENT FOR OCCUPATIONAL HEALTH AND SAFETY In accordance with the provisions of Section 37(2) of the Occupational Health and Safety Act No. 85 of 1993 Entered into and between Tongaat Hulett

More information

Control of Asbestos Regulations 2012 (SI 2012 No. 632)

Control of Asbestos Regulations 2012 (SI 2012 No. 632) Control of Asbestos Regulations 2012 (SI 2012 No. 632) Part 1: Preliminary Part 1 covers commencement, interpretation and application. 2: Interpretation This contains a number of definitions. Of particular

More information

A UNIQUE AND COMPREHENSIVE INSURANCE SCHEME FOR THE ELECTRICAL INDUSTRY

A UNIQUE AND COMPREHENSIVE INSURANCE SCHEME FOR THE ELECTRICAL INDUSTRY .. A UNIQUE AND COMPREHENSIVE INSURANCE SCHEME FOR THE ELECTRICAL INDUSTRY PROPOSAL FORM Camberford Law plc Innovative Insurance solutions Since 1958 Insurance Brokers Underwriting Agents Authorised and

More information

Traffic Impact Analysis Guidelines Methodology

Traffic Impact Analysis Guidelines Methodology York County Government Traffic Impact Analysis Guidelines Methodology Implementation Guide for Section 154.037 Traffic Impact Analysis of the York County Code of Ordinances 11/1/2017 TABLE OF CONTENTS

More information

Annex A. ERM Approved Inspection Authority, Certificates of Accreditation

Annex A. ERM Approved Inspection Authority, Certificates of Accreditation Annex A ERM Approved Inspection Authority, Certificates of Accreditation Annex B Major Hazard Installation Legislation Government Gazette REPUBLIC OF SOUTH AFRICA Regulation Gazette No. 7122 Vol. 433

More information

TERMS AND CONDITIONS

TERMS AND CONDITIONS BACKGROUND (A) ARTROOMSFAIR Ltd is the Organiser of ARTROOMS - INTERNATIONAL CONTEMPORARY ART FAIR ( EVENT ). (B) ARTROOMS INTERNATIONAL CONTEMPORARY ART FAIR will take place at MELIA WHITE HOUSE HOTEL

More information

GASCADE Gastransport GmbH HSE-GUIDELINE-CONTRACTORS. Version 5 Status: 15th May 2017

GASCADE Gastransport GmbH HSE-GUIDELINE-CONTRACTORS. Version 5 Status: 15th May 2017 GASCADE Gastransport GmbH HSE-GUIDELINE-CONTRACTORS Version 5 Status: 15th May 2017 CONTENT 1. Preamble... 2. Scope... 3. General requirements, access, intoxicants... 4. Responsibility / organisation /

More information

NEC3 ECC Introductory Training

NEC3 ECC Introductory Training NEC3 ECC Introductory Training John Rayner House Keeping and Safety Fire Alarm Toilets Mobile phones Please remember to switch all mobile phones to silent 1 Introductions John Rayner Name: NEC3 Knowledge:

More information

TERMS AND CONDITIONS

TERMS AND CONDITIONS BACKGROUND (A) ARTROOMSFAIR Ltd is the Organiser of ARTROOMS - INTERNATIONAL CONTEMPORARY ART FAIR ( EVENT ). (B) ARTROOMS INTERNATIONAL CONTEMPORARY ART FAIR will take place at MELIA WHITE HOUSE HOTEL

More information

SAN JOSE EVERGREEN COMMUNITY COLLEGE DISTRICT DOCUMENT SPECIAL CONDITIONS

SAN JOSE EVERGREEN COMMUNITY COLLEGE DISTRICT DOCUMENT SPECIAL CONDITIONS DOCUMENT 00 73 10 SPECIAL CONDITIONS 1 Application of Special Conditions. These Special Conditions are part of the Contract Documents for the Work generally described as: EVC Campus Water Service Replacement

More information

Original prepared by: István TAMÁS Tel.: 6138

Original prepared by: István TAMÁS Tel.: 6138 1/5 Date of change: 01.02.2018 Checked by: András GAZDAG Approved by: Tibor SZIGETI Objective: Tel.: 6978 Tel.: 6016 Annexes: (part of the present directive) The mandatory use of the safety foot protection

More information

Construction Management Approach based on FIDIC Conditions of Contract for Construction, st Edition. Dr. Munther M.

Construction Management Approach based on FIDIC Conditions of Contract for Construction, st Edition. Dr. Munther M. Construction Management Approach based on FIDIC Conditions of Contract for Construction, 1999 1st Edition Dr. Munther M. Saket March 2015 1 Traditional Construction Contracts Owner of a construction project

More information

3 OUR INSTALLERS 4 OUR RESPONSIBILITY

3 OUR INSTALLERS 4 OUR RESPONSIBILITY NPOWER SALE TERMS & CONDITIONS FOR NEST THERMOSTAT 1 OUR CONTRACT These Terms & Conditions apply to the Contract between you and us. Please read them carefully. Words which appear in bold type throughout

More information

New Terminology. References to. The main theme of NEC4 is that it represents an evolution rather than a revolution in thinking

New Terminology. References to. The main theme of NEC4 is that it represents an evolution rather than a revolution in thinking New Terminology The main theme of NEC is that it represents an evolution rather than a revolution in thinking References to project participants as him and his actions are now stated in a neutral voice

More information

TOWN OF TIBURON ENCROACHMENT PERMIT APPLICATION EP Number:

TOWN OF TIBURON ENCROACHMENT PERMIT APPLICATION EP Number: TOWN OF TIBURON ENCROACHMENT PERMIT APPLICATION EP Number: APPLICATION DATE: ADDRESS OF WORK OR ENCROACHMENT: CROSS STREET: STARTING DATE: APN: - - No. Street City/Township ESTIMATED COST: $ COMPLETION

More information

CENTRAL GOLDFIELDS SHIRE COUNCIL TENDER G CIVIL & TRAFFIC ENGINEERING CONSULTANCY SERVICES

CENTRAL GOLDFIELDS SHIRE COUNCIL TENDER G CIVIL & TRAFFIC ENGINEERING CONSULTANCY SERVICES 0 CENTRAL GOLDFIELDS SHIRE COUNCIL TENDER G530-09 CIVIL & TRAFFIC ENGINEERING CONSULTANCY SERVICES 1 TABLE OF CONTENTS Page No. 1. NOTICE TO TENDERERS AND GENERAL CONDITIONS OF TENDERING...3 2. SCHEDULE

More information

A. Letter of Acceptance

A. Letter of Acceptance A. Letter of Acceptance [letterhead paper of the Employer] [insert date] To: [insert name and address of the Contractor] Subject: [Notification of Award Contract No] This is to notify you that your Bid

More information

Contractor Guidelines

Contractor Guidelines Contractor Guidelines This Guideline has been written to detail the minimum expectations with regards to contractor safety at Sodexo business units. It is the responsibility of the contractor to understand

More information

RISK ASSESSMENT POLICY

RISK ASSESSMENT POLICY RISK ASSESSMENT POLICY Scope of the Policy The academy s Governors are committed to promoting the safety and welfare of all members of its community. Governors priority lies in ensuring that all operations

More information

ADDENDUM NUMBER 01 TO THE BID DOCUMENTS. BID NUMBER: G Math and Science Building Exterior Stair Lighting #32107 Evergreen Valley College

ADDENDUM NUMBER 01 TO THE BID DOCUMENTS. BID NUMBER: G Math and Science Building Exterior Stair Lighting #32107 Evergreen Valley College SAN JOSE EVERGREEN COMMUNITY COLLEGE DISTRICT ADDENDUM NUMBER 01 TO THE BID DOCUMENTS To all general contract bidders of record on the Bid Proposal: BID NUMBER: G2010.0189 Math and Science Building Exterior

More information

CORK COUNTY COUNCIL. Resident Executive Engineer Road Construction Supervision QUALIFICATIONS

CORK COUNTY COUNCIL. Resident Executive Engineer Road Construction Supervision QUALIFICATIONS 1. Character CORK COUNTY COUNCIL Resident Executive Engineer Road Construction Supervision Candidates must be of good character. 2. Health QUALIFICATIONS Candidates shall be in a state of health such as

More information

AH: STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION AND IMPROVEMENT WOPKS SCC.1

AH: STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION AND IMPROVEMENT WOPKS SCC.1 COMPLIANCE TO CONDITIONS OF CONTRACT - SCC.1(Renovation) Please indicate clearly below your compliance to each clause of the Conditions of Contract. Where you are not in agreement, you should give your

More information

Request for Proposals Installation of Pavilions

Request for Proposals Installation of Pavilions Request for Proposals Installation of Pavilions The Jefferson County Parks and Recreation Commission is now accepting proposals for the installation of three (3) pavilions at James Hite Park located at

More information

The following amendments have been made to the June 2005 edition deleted: and of notified early warning matters

The following amendments have been made to the June 2005 edition deleted: and of notified early warning matters AMENDMENTS JUNE 2006 The following amendments have been made to the June 2005 edition. Page Clause Line 10 32.1 4 deleted: and of notified early warning matters 59 Contract Data Part one, 1. 3 added, (with

More information

AMENDMENTS APRIL 2013

AMENDMENTS APRIL 2013 AMENDMENTS APRIL 2013 The following amendments have been made to the December 2009 edition. Full details of all amendments are available on www.neccontract.com. Page Clause Line 11 40.1 1 replace: The

More information

[Project Name] NZTA Contract No. [Contract Number] Conditions of Contract

[Project Name] NZTA Contract No. [Contract Number] Conditions of Contract [Project Name] NZTA Contract No. [Contract Number] DOCUMENT CHANGE FORMAT CODES This proforma document provides the basis for the development of physical works contract

More information

Railroad DOT Mitigation Strategies (R16) Master Project Agreement

Railroad DOT Mitigation Strategies (R16) Master Project Agreement Railroad DOT Mitigation Strategies (R16) Master Project Agreement The master project agreement includes standard legal provisions that are common to nearly all projects and incorporates them into one overall

More information

This policy aims to ensure the health, safety and welfare of contractors working on UEL premises and those affected by their work.

This policy aims to ensure the health, safety and welfare of contractors working on UEL premises and those affected by their work. HR Services UEL Health and Safety Handbook Contractor Health and Safety Management Policy This policy is a sub-policy of the main University Health and Safety Policy Statement Introduction The University

More information

Cosmos Projects - Standard Terms and Conditions of Sub-Contract

Cosmos Projects - Standard Terms and Conditions of Sub-Contract Cosmos Projects - Standard Terms and Conditions of Sub-Contract These standard terms and conditions shall apply to any Sub Contract between Cosmos Projects Limited ( CPL ) and any Sub-Contractor following

More information

The following amendments have been made to the June 2005 edition deleted: and of notified early warning matters

The following amendments have been made to the June 2005 edition deleted: and of notified early warning matters AMENDMENTS JUNE 2006 The following amendments have been made to the June 2005 edition. Page Clause Line 10 32.1 4 deleted: and of notified early warning matters 17 70.4 2 otherwise inserted after stated

More information

Work Health and Safety Conditions

Work Health and Safety Conditions Work Health and Safety Conditions Table of Contents PURPOSE AND SCOPE... 1 RESPONSIBILITIES... 1 DEFINITIONS, ABBREVIATIONS AND ACRONYMS... 1 GENERAL WH&S & ELECTRICAL SAFETY REQUIREMENTS... 1 Compliance...

More information

Request for Proposal for Engineering Services. January 10, 2017 Sue Howard Closing Date: January 17,

Request for Proposal for Engineering Services. January 10, 2017 Sue Howard Closing Date: January 17, Request for Proposal for Sue Howard Closing Date: January 17, 2017 Email: sue.howard@wetaskiwin.ca Contents Purpose... 3 Background... 3 Terms of Reference... 4 1. General... 4 2. Key Dates... 5 Scope

More information

Policy for Occupational Health, Safety and Environment Requirements for Contracted Construction and Maintenance Work

Policy for Occupational Health, Safety and Environment Requirements for Contracted Construction and Maintenance Work Policy for Occupational Health, Safety and Environment Requirements for Contracted Construction and Maintenance Work Policy Statement Rationale Construction and Maintenance work undertaken by contracted

More information

CHECKLIST FOR CONSTRUCTION STAGING PLAN IN CORAL GABLES

CHECKLIST FOR CONSTRUCTION STAGING PLAN IN CORAL GABLES CHECKLIST FOR CONSTRUCTION STAGING PLAN IN CORAL GABLES _ A Construction Staging Plan is required prior to permit issuance for all commercial and multi-family residential projects. It is intended to reduce

More information

HSE MANUAL. PO Box 14659, Zayed bin Sultan Street, Al Ain, U.A.E.., Tel: , Fax

HSE MANUAL. PO Box 14659, Zayed bin Sultan Street, Al Ain, U.A.E.., Tel: , Fax HSE MANUAL PO Box 14659, Zayed bin Sultan Street, Al Ain, U.A.E.., Tel: 03-7640177, Fax 03-7640188 HSE 1 Health and Safety Policy Statement 1.0 The policy is to ensure, as far as is reasonably practicable,

More information

The consultant s team for construction supervision and benefits monitoring will include:

The consultant s team for construction supervision and benefits monitoring will include: TERMS OF REFERENCE FOR CONSULTING SERVICES FOR CENTRAL ASIA ROAD LINKS PROJECT: CONSTRUCTION SUPERVISION SERVICES FOR LOT 1: ISFANA- KAIRAGACH, LOT 2: BATKEN KYZYL-BEL, BATKEN ROUNDABOUT KM 248. Background

More information

Standard Form of Agreement Between Owner and Architect for a Federally Funded or Federally Insured Project

Standard Form of Agreement Between Owner and Architect for a Federally Funded or Federally Insured Project Document B108 2009 Standard Form of Agreement Between Owner and Architect for a Federally Funded or Federally Insured Project AGREEMENT made as of the in the year (In words, indicate day, month and year.)

More information

Health and Safety Procedure: Risk Assessment. 1. Introduction

Health and Safety Procedure: Risk Assessment. 1. Introduction Health and Safety Procedure: Risk Assessment 1. Introduction 1.1. The purpose of this Procedure is to set out the London School of Economics (hereafter the School or LSE) arrangements for undertaking risk

More information

MEMORANDUM OF UNDERSTANDING

MEMORANDUM OF UNDERSTANDING MEMORANDUM OF UNDERSTANDING THE INSTALLATION AND REPAIR OF FIRE HYDRANTS AND THE USE OF WATER FOR FIREFIGHTING PURPOSES Kent and Medway Towns Fire Authority /Folkestone and Dover Water Services 1 Introduction

More information

SECTION NR 2 - PRELIMINARIES AND GENERAL CONDITIONS

SECTION NR 2 - PRELIMINARIES AND GENERAL CONDITIONS SECTION NR 2 - PRELIMINARIES AND GENERAL CONDITIONS SECTION NR 2 - PRELIMINARIES AND GENERAL CONDITIONS A10 PROJECT PARTICULARS 110 THE PROJECT Nature: Demolition of former probation centre Location: 14

More information

Decision by Richard Dent, a reporter appointed by the Scottish Ministers

Decision by Richard Dent, a reporter appointed by the Scottish Ministers Directorate for Planning and Environmental Appeals Appeal Decision Notice T: 01324 696 400 F: 01324 696 444 E: dpea@scotland.gsi.gov.uk Decision by Richard Dent, a reporter appointed by the Scottish Ministers

More information

CODE OF PRACTICE FOR SUBCONTRACTORS

CODE OF PRACTICE FOR SUBCONTRACTORS CODE OF PRACTICE FOR SUBCONTRACTORS Introduction Competence Quality Management Considerate Constructors Scheme Site Induction Safe Systems of Work Tools and Equipment Personal Protective Equipment Environmental

More information

Conditions of Contract

Conditions of Contract Conditions of Contract Request for Quotation (RFQ) RFQ Title RFQ Number Level 1 Essential Energy Works for the Warialda Truck Wash GWY_1819_Q03 Issue Date 21st December 2018 This document contains the

More information

BROCKWOOD PARK SCHOOL & INWOODS SMALL SCHOOL

BROCKWOOD PARK SCHOOL & INWOODS SMALL SCHOOL BROCKWOOD PARK SCHOOL & INWOODS SMALL SCHOOL RISK ASSESSMENT POLICY Last Review Date August 2018 Policy endorsed by Policy is maintained by ISI reference The Trustees, Principal & Inwoods Head Teacher

More information

CIOB TIME AND COST MANAGEMENT CONTRACT SUBCONTRACT APPENDICES 2015 EDITION

CIOB TIME AND COST MANAGEMENT CONTRACT SUBCONTRACT APPENDICES 2015 EDITION CIOB TIME AND COST MANAGEMENT CONTRACT 06 SUBCONTRACT APPENDICES 2015 EDITION CIOB TIME AND COST MANAGEMENT CONTRACT 06 SUBCONTRACT APPENDICES 2015 EDITION 1 NAMING The Subcontract is formally called the

More information

NEC4 ENGINEERING & CONSTRUCTION CONTRACT

NEC4 ENGINEERING & CONSTRUCTION CONTRACT 1. Introduction 1.1 This paper provides an overview of the NEC Engineering & Construction Contract summarising the key features and structure of the NEC family of contracts. The NEC4 (4 th Edition) box

More information

Town of South Bruce Peninsula. Tender PW Resurfacing of D Line

Town of South Bruce Peninsula. Tender PW Resurfacing of D Line Town of South Bruce Peninsula Tender PW 17-14 Resurfacing of D Line Town of South Bruce Peninsula Tender PW 17-14 Resurfacing of D Line The Town of South Bruce Peninsula is requesting tenders for the resurfacing

More information

MDB Harmonised Particular Conditions

MDB Harmonised Particular Conditions FIDIC Plant and Design-Build Contract MDB Harmonised Particular Conditions 1. Introduction There is a need for FIDIC to provide sample Particular Conditions that render the General Conditions of the 1st

More information

Webinar - The Project Manager in the NEC4 ECC: What s new and different?

Webinar - The Project Manager in the NEC4 ECC: What s new and different? Webinar - The Project Manager in the NEC4 ECC: What s new and different? 17 th May 2017 Q&A session This document provides answers to the questions submitted during the webinar. The webinar can be viewed

More information

DEVELOPMENT PERMIT APPLICATION CHECKLIST New: Commercial Industrial Institutional - Multiple Family Residential

DEVELOPMENT PERMIT APPLICATION CHECKLIST New: Commercial Industrial Institutional - Multiple Family Residential FOR OFFICE USE ONLY 5 St. Anne Street St. Albert, AB T8N 3Z9 Phone: (780) 459-1642 Fax: (780) 458-1974 Project: Address: Date: File No.: DEVELOPMENT PERMIT APPLICATION CHECKLIST New: Commercial Industrial

More information