Payment Terms: Entitlement, Timing and Security

Size: px
Start display at page:

Download "Payment Terms: Entitlement, Timing and Security"

Transcription

1 Payment Terms: Entitlement, Timing and Security Introduction: Progress Payments and Final Payment Payments to construction subcontractors can be divided into two categories: progress payments and final payment. Progress payments are designed to supply the funds "necessary for the agreed performance," 1 so subcontractors can pay for labor and materials as the project progresses. Final payment, on the other hand, is a special case. This is because in most circumstances a subcontractor s acceptance of a payment that is designated as final payment constitutes the subcontractor's waiver of all outstanding claims, 2 including claims for unpaid, extra work. Another difference between progress payments and final payment is retainage. 3 "Retainage" is an agreed percentage that is withheld from progress payments, but which is ordinarily paid as part of the final payment, or immediately before final payment when the project is substantially complete. Amounts of Payments The amount of each progress payment that is made under a lump sum construction contract is ordinarily determined by comparing the actual work that has been performed to a schedule of values that apportions the total, lump-sum contract amount among separately identifiable stages of work, according to their relative values. 4 The seller is commonly entitled to submit applications for progress payments at periodic intervals (e.g. monthly) or to submit applications as certain milestones in construction are reached. To encourage advance procurement of materials and equipment, construction contracts typically allow the seller to apply for payment for materials and equipment stored at the construction site or some other agreed location. 5 The buyer is then entitled to inspect the work and delivered materials that underlie the application, to verify that the work has been properly performed, and that materials have been suitably stored and insured, before making payment. 1 Manganaro Corp. v. HITT Contracting,193 F.Supp.88, 97 (D.D.C. 2002). 2 See ASA s Payment Advocacy Year ( PAY! ) white paper for February 2003: Final Payment. 3 See ASA s white paper for July 2009: Retainage. 4 Frontloading and backloading occur when the relative values of the work are skewed so that the seller is either paid too much up front (frontloading), or too little until the end (backloading). Backloading is a way to disguise retainage. See ASA s white paper for July 2009: Retainage. 5 Guideline on Payment for Stored Materials and Equipment, Guidelines for a Successful Construction Project, Associated General Contractors of America, ASA, Associated Specialty Contractors, published at See also ASA s Payment Advocacy Year (PAY!) August 2003 white paper, Stored Materials. 1

2 A buyer of construction services ordinarily reserves the right, in the written contract, to withhold, or reduce the amounts of, payments otherwise due to the seller, based on dissatisfaction with the services that the seller has provided. In addition, the buyer frequently reserves the right to take set-offs against its payments to the seller to remedy defects in the work performed by the seller. In other words, buyers reserve contractual rights to backcharge the seller for the cost to hire another contractor to perform remedial work. Unfortunately, buyers of construction services often withhold payments for reasons that (1) the seller cannot control, and (2) have nothing to do with a seller s performance of its contract obligations. Subcontractors can mitigate the chances of unwarranted backcharges by insisting on contract terms that require their general contractor to provide them with notice of any claimed defects in their work before the general contractor incurs any backcharges. These terms should also afford subcontractor with a reasonable opportunity to avoid backcharges by commencing corrections on its own. These types of clauses should not be objectionable and maintain your ability to control your own work. In addition, it is always wise to insist on contract language that requires that any actual backcharges be billed promptly enough to permit verification and thus ensure authenticity and reasonableness of the charges. 6 Payment Timing and Entitlement: Pay-when-Paid and Pay-if-Paid Payment timing terms that are considered typical in the construction industry pose such extraordinary credit risks for subcontractors that it can be difficult for credit managers and other objective observers to understand how these objectionable terms have become so entrenched. A. Pay-When-Paid" vs. Pay-if-Paid Contracts Construction subcontracts typically provide that the general contractor s payments are not due and owing to the subcontractor until the general contractor actually receives payment from its customer (an upper-tier contractor or the project owner). These clauses are known as pay-when-paid clauses because they require the general contractor to pay only when it is paid. Pay-when-paid terms present extraordinary credit risks because the subcontractor who signs on to them accepts the risk that a party over whom it has no control, and with whom it has no direct communications, will fail to make payments in a timely fashion. Agreeing to pay-when-paid terms will be inevitable in many cases, considering that that the very 6 For example, the A subcontract requires the buyer to provide written compilations to the Subcontractor of services and materials provided and charged for such services and materials no later than the fifteenth day of the following month at

3 purpose of progress payments is to supply the funds needed to finance a lengthy schedule of performance. B. The Risks Involved With Accepting Conditional Payment Terms The fact that a construction buyer will not, in most cases, be able to afford to pay its subcontractor-seller until it receives payment from its own customer may be a sufficient reason to justify the use of pay-when-paid payment terms, but only where they do not shift the risk of total nonpayment to the subcontractor-seller. That fact does nothing, however, to alleviate the credit risk taken by the subcontractor-seller. To the contrary, the inability of the subcontractor s customer to afford to pay for construction services with its own resources which is always implied when pay-whenpaid or pay-if-paid terms are proposed clearly magnifies the subcontractor s own credit risks. One example of the extraordinary risk imposed by pay-when-paid terms flows from the fact that the subcontractor-seller necessarily has imperfect information about the precise time when the buyer receives payment from its customer. As a result, the subcontractor is left in the position of taking the general contractor s word about when its payments are actually due or past due! Moreover, the general contractor s need to push for timely payments from its own customer is necessarily eased when it is entitled to extend the time for its own payments to its lower-tiers. In other words, pay-when-paid terms reduce the general contractor/ buyer s natural incentives to ensure regular cash flow from its customer for the project. However, where the seller is a construction subcontractor who must (1) pay labor costs according to a strict payroll schedule, and (2) pay suppliers as well, the subcontractorseller s costs for late payments will far exceed the cost exposure of upper-tier contractors, who will only be exposed to the extent of their ordinary overhead costs. A payment delay of even a single day has much larger costs for a subcontractor who has to tap lines of credit, and pay interest on the borrowed funds, in order to keep current on its own accounts payable. What happens to the seller if the buyer is never paid by its customer? Although paywhen-paid terms pose extraordinary credit risks, in an overwhelming majority of jurisdictions, payment in accordance with a pay-when-paid clause must still be made within a reasonable time, even where the buyer never receives payment from its own customer. Payment terms that do clearly and unambiguously shift the risk of owner nonpayment are often called pay-if-paid terms to distinguish them from other paywhen-paid terms. 7 7 See, e.g., Farnsworth, E. Allan, Contracts, 3rd Edition (1999),

4 The distinction between a "pay-when-paid" and "pay-if-paid" clause is important. A payif-paid clause will clearly and unambiguously shift the risk of project owner nonpayment to the subcontractor. 8 The "pay-when-paid" clause will merely allow the general contractor-buyer additional time to make payment, but will not completely absolve it of responsibility to pay its subcontractors if payment from above does not come. In other words, even if the ultimate customer (i.e., the project owner) never makes a payment, the construction subcontractors who perform the work and supply the materials will still generally be entitled to be paid by the contractors who are their direct customers, unless the payment terms clearly and unambiguously shift the risk of owner (or upper-tier contractor) nonpayment to the subcontractor. C. Conditional Payment Terms and Late Payment Provisions Subcontractors are creditors, because they provide labor and materials on credit for a promise of future payment. As creditors, construction subcontractors should give careful consideration to the credit risks that they accept, and whether those risks can be ameliorated by terms providing for interest on late payments, costs of collection, and appropriate security. To collect interest on a late payment, for example, the contract should not only provide for a reasonable rate of interest, but also a way to determine when payment is late. Paywhen-paid terms, which require the buyer to make payment in a reasonable time, will almost never be considered late except in extreme circumstances, as where a monthly payment is several months overdue. As a practical matter, however, a monthly payment will have to be at least several months past due to be worth the cost of attempting to collect the accrued interest, and so that risk may be acceptable. Pay-if-paid terms, however, pose the risk that payment for services properly rendered will never, ever be due, and thus, never late. The effect can be similar in regard to security for payment. Can a mechanic s lien, or a claim against a payment bond, be used to secure a payment that is not, and may never, actually be due? Many jurisdictions recognize that a project owner should not be permitted to assert its own failure to pay for services it has received as a defense to the assertion of liens against the improved property, 9 and others have recognized that payment bond sureties should 8 Koch v. Construction Technology, 924 S.W.2d 68 (Tenn. 1996) (ASA appeared as amicus curiae). An excellent state-by-state summary of conditional payment laws prepared by Kegler, Brown, Hill and Ritter, Contingent Payment Clauses in the 50 States (2008 ed.), appears in the members-only section of the ASA Web site ( 9 See, e.g., Kansas Fairness in Private Construction Contract Act 3(c) (SB-33 (2005)) effective July 1,

5 not be permitted to assert the owner s nonpayment as a defense. 10 In many other jurisdictions, however, these questions are unsettled and may be resolved against the interests of subcontractors. Subcontractors who inform themselves about local laws in order to fully understand the credit risks posed by the payment terms of their proposed subcontracts will make much smarter business decisions. Payment Timing and Entitlement: Final Payment For construction subcontractors who specialize in work completed early in the project schedule, the release and payment of retainage always constitutes final payment because progress payments covering the entirety of their work will have been received well in advance of project completion. For later-finishing subcontractors, however, final payment may occur after release of retainage, because many construction contracts provide for release of most retainage upon the occurrence of substantial completion 11 of the project, subject to withholding of a smaller balance for completion of punch-list items (uncompleted or improperly completed project items). Amounts withheld from the release of retainage at substantial completion are generally a multiple of the estimated reasonable value of the punch-list items. 12 In such cases, final completion, and thus final payment, occurs after the punch-list and other close-out items (such as delivery of manufacturers warranties and maintenance instructions) are completed. Still, many general contractors and later-finishing subcontractors nonetheless associate release of retainage with final payment because many construction contracts provide that no retainage will be released until final completion, notwithstanding the earlier occurrence of substantial completion which is often combined with owner occupancy of the project. When retainage and change order approvals are withheld until final completion, a large fund remains after the substantial completion and owner occupancy of the project, which may potentially be used as leverage to unfairly resolve meritorious claims for extra work properly performed, for delay claims, and for other claims, often at the expense of faultless subcontractors who have properly completed their work. 10 See, e.g., Moore Brothers Co. v. Brown & Root, Inc., 207 F.3d 717 (4th Cir. 2000). 11 Commonly, substantial completion occurs when the owner can occupy and use the project improvements as intended. See, e.g., A at 9.8.1, DBIA 535 (1998) at , ConsensusDOCS 200 (2007) at See, e.g., AOD Form 2002GC (2002) at (menu allows retainage to be release at substantial completion less 200% of the reasonable value of remaining items, or release of ¾ of remaining retainage, or release of no retainage until final completion). 5

6 Whatever definition of final payment is used for a particular project, the risks of delay or non-receipt of final payment extend well beyond the ordinary risks of creditworthiness, miscommunication, or even outright dishonesty that may be associated with progress payments. Industry Practices on Payment Timing and Entitlement Industry payment practices are increasingly the subject of legal restrictions imposed by state legislation, suggesting that payment abuse in the construction industry is extensive. Public procurement laws, for example, usually address not only payment by public entities to prime contractors, but also payments by prime contractors to their subcontractors. Model contract documents published by industry trade associations vary widely in the way they address subcontractor payment concerns, suggesting broad differences of opinion on the proper treatment of subcontractor payment provisions. 1. Public Procurement Public procurement laws reveal that pay-when-paid terms for progress payments are common in the construction industry. Retainage, where it is still used on public construction projects, is normally held until final acceptance and not released upon substantial completion. Final payment may still be hostage to final settlement of all claims made by the public contractor. Federal procurement laws divide payments under construction contracts into progress payments and final payments. 13 Progress payments are required, by the federal Prompt Payment Act, to be made by a federal agency to a prime contractor on a construction projects within fourteen (14) days of the agency s receipt of a proper invoice from the construction contractor. 14 A proper invoice must include all the information and substantiating documentation required by regulation or by the contract, 15 but the federal agency is required to return any invoice that is not a proper invoice within seven (7) days after receipt specifying the reasons that the invoice is not a proper invoice, or else the fourteen (14) day period for timely payment is shortened by one day for each day the agency s response is overdue. 16 Contractors that fail to make timely payment face automatic interest penalties. 17 The federal Prompt Payment Act also imposes requirements on public contractors to pay their subcontractors promptly. It mandates that any construction contract awarded by federal agency must require the prime contractor to include a payment clause in any subcontract it awards obligating the prime contractor to make payment to the CFR (a)(1)(i) and (a)(1)(ii) U.S.C. 3903(a)(6) U.S.C. 3901(a)(3) U.S.C. 3903(a)(7) U.S.C. 3902, 3903(a)(6). 6

7 subcontractor within seven days of the prime contractor s receipt of payment. If it does not do so, the prime contractor must pay interest penalties. 18 The law also requires the prime contractor to pass along the same mandate to its subcontractors, so that each lowertier subcontractor or supplier will also be entitled to payment within seven days of its customer s receipt of payment. 19 Final payment on a federal construction project is made after completion and acceptance of all work and release of all claims against the Government, 20 requirements which essentially incorporate the state law concept of an accord and satisfaction at the time of final payment. Release of retainage and final payment are not interrelated on federal construction as with other projects. As a practical matter, the practice of holding retainage on federal construction projects has effectively ended. This is because retainage cannot be held on federal procurement contracts without cause, and should not be used as a substitute for good contract management by the contracting officer. 21 And general contractors cannot hold retainage because they are forbidden from requesting payment by the government for any amount to be withheld from a subcontractor. 22 Federal construction contracts may, however, provide for government use and possession of all or part of project improvements prior to completion. In such cases the contracting officer is responsible for furnishing a list of items of work remaining to be performed or corrected. 23 While the federal procurement rules avoid the terms substantial completion and punch-list, they nonetheless follow the general practice of using catch-all language to avoid binding the project owner, by providing that failure of the Contracting Officer to list any item of work on the punch-list "shall not relieve the Contractor of responsibility for complying with the terms of the contract. Final payment, then, is not tied to the punch-list, which is susceptible to being supplemented by additional punch-lists. However, the federal procurement rules are sensitive to at least some of the problems of the rolling punch-list, where they provide that the contractor is relieved of any responsibility for loss or damage to the work resulting from the Government s possession or use. 24 The practice of holding final payment hostage to settlement of outstanding, unapproved change orders should be less of a problem for subcontractors on federal projects because federal procurement regulations forbid contracting officers from directing or encouraging U.S.C. 3905(b) U.S.C. 3905(c) CFR (a)(1)(ii); see also 48 CFR (a)(3)(iii) (interest penalties not authorized for final payment where the amount is subject to further contract settlement actions ) CFR CFR (h) CFR , (a) CFR (b). 7

8 contractors to perform extra work without written change orders, 25 and changes cannot generally be requested without certification of funding. 26 Of course, contractors and contracting officers may disagree whether a change has occurred and whether a price adjustment is appropriate, 27 and so it is certainly possible for final payment to be delayed pending resolution of a dispute over changes and extras on a federal project. Nonetheless, recourse to contract appeals boards, and the general prohibition against arbitrary or capricious action by agency personnel under the Administrative Procedures Act, should provide some measure of relief against any opportunistic behavior at the time of final payment. Moreover, the contracting officer will not have any direct profit motive to engage in opportunistic attempts to underpay contractors. The District of Columbia and 49 states have also enacted prompt payment laws setting deadlines for payment of public construction contractors (only New Hampshire has no prompt payment law). Most are less generous than the federal law to public contractors in that they afford public agencies with considerably more than 14 days to pay. Deadlines of 30 or 45 days to pay public contractors on state jobs are not uncommon, and few states permit even longer delays. All but 10 of those 49 states with prompt payment legislation applicable to public procurement include deadlines for paying subcontractors. Only 6 of the 39 states with deadlines for paying subcontractors on public projects lack deadlines for paying lower-tier subcontractors. State procurement laws generally permit state public entities to hold retainage until final acceptance. Many of those laws do, however, permit the contractor to substitute securities for retainage, which earn interest for the benefit of the contractor. A few states have gone beyond the substitution of securities and directly require retained funds to be deposited in an account which earns interest for the benefit of the contractor and subcontractors Model Contract Forms Standard forms for prime contracts published by construction industry trade associations generally contemplate a monthly payment schedule, while standard form subcontracts published by the American Institute of Architects (AIA), ConsensusDOCS, and the Design-Build Institute of America (DBIA), all incorporate pay-when-paid payment CFR (a)(3) CFR In rare circumstances where certification of fund availability is not required, the contract must state that the government has no legal liability for work performed absent future appropriation, and so payment for the extra work still cannot be held hostage pending resolution of other claims. 48 CFR , See, e.g., 48 CFR (contractor must notify the Government in writing as soon as possible when it believes it has been asked to perform extra work amounting to a change). 28 See A Guide to Passing Retainage Reform in Your State, Appendix A ( Summary of Retainage Laws in the Fifty States ) (ASA, 2007). 8

9 terms. Retainage is required to be released upon substantial completion under some, but not all, standard forms of general conditions, and some, but not all, of the forms have a mechanism for the contractor to preserve outstanding claims at the time of final payment. Model prime contracts ordinarily require the prime contractor to submit an application for payment a specified number of days in advance of each scheduled payment to permit review, either by setting the number of days in the general conditions, or by requiring the parties to fix a particular number in a separate agreement document. They generally also require payment of interest on late payments. A. The ConsensusDOCS and Payment Terms The ConsensusDOCS form contracts are endorsed by the ASA and embody the best practices of the construction industry. Payment terms and interest payments are addressed in the ConsensusDOCS 200 (2007), which: provides for a monthly application for payment no later than the day of the calendar month; requires payment within twenty (20) days or written notice of deficiencies; and provides for late payment interest at the statutory rate at the place of the Project. 29 The ConsensusDOCS contract forms are distinguished by the ASA's endorsement and the ability to consider them together with subcontract forms published by the same group. The ConsensusDOCS Standard Form of Agreement and General Conditions Between Owner and Contractor expressly provides that a contractor can preserve its right to assert claims for additional money after receipt of final payment if it provides written notice and identification of unsettled claims with its application for final payment. 30 In addition, the ConsensusDOCS 750, Standard Form of Agreement between Contractor and Subcontractor, states that final payment does not relieve the Contractor for claims made in writing by the Subcontractor. 31 The ConsensusDOCS general contract expressly provides for release of retainage upon substantial completion, less a sum equal to two hundred percent (200%) of the estimated cost of completing or correcting remaining items. The ConsensusDOCS subcontract form allows for line-item release of retainage to early-finishing subcontractors, if the 29 ConsensusDOCS 200 (2007) 9.2.1, 9.3, ConsensusDOCS 200 (2007) at ConsensusDOCS 750 (2007) at

10 Subcontract Documents [elsewhere] provide for reduction of retainage at a specified percentage of completion. 32 If the owner retains all retainage until substantial completion, then the general contractor s payment to the subcontractor will be similarly delayed, even under the ConsensusDOCS, but final payment to the subcontractor shall be made within seven (7) days after receipt by the Contractor of final payment from the Owner for such Subcontract Work. 33 B. The Other Trade Association Forms Treatment of Payments/Interest Industry treatment of terms regarding payments and interest on late payments is as follows for the other (non-consensusdocs) forms: The EJCDC C-700 (2002) requires (1) the contractor to submit its payment application [a]t least 20 days before the date established in the Agreement for each progress payment and (2) the engineer, as the owner s agent, to within 10 days after receipt "either indicate in writing a recommendation or payment or return the Application to Contractor indicating in writing the Engineer s reasons for refusing to recommend payment. 34 The EJCDC C-700 does not set an interest rate for late payments, but also does not disclaim any existing right to claim statutory interest. In fact, it provides that where the Contractor stops work for nonpayment it may insist on payment of interest before starting work again. 35 The A , requires payment applications to be submitted 10 days before the payment date, gives the architect seven days to approve the application or provide notice of deficiencies to the contractor, and for interest at the legal rate on late payments. 36 The DBIA 535 (1998) refers to monthly progress payments, requires applications for payment to be submitted [o]n or before the date established in the Agreement. The DBIA 535 also requires the owner to give notice of deficiencies at least five days before the payment due date. If such payment is not made, interest will be assessed at the rate set forth in the Agreement ConsensusDOCS 750 (2007) at 8.2.2; also provides that the Contractor shall incorporate the Subcontractor s application for final payment into the Contractor s next application for payment to the Owner. 33 ConsensusDOCS 750 (2007) at EJCDC C-700 (2002) A.1, B EJCDC C-700 (2002) B. 36 A , 9.4.1, DBIA 6.2, 6.2.1, 6.3.1,

11 The AOD 2002GC, published by the Associated Owners and Developers, provides that Contractor may submit to Owner an itemized Application for Payment on or before the day of the month for the period ending on the day of the month. The 2002GC further requires that the owner provide notice of deficiencies at or before the time payment is due, and provides that any sums withheld shall become due within days after all reasons for withholding such sum have been removed. 38 The AOD form provides a 30-day grace-period before late payment interest, at a rate to be inserted by the parties, begins to accrue. 39 The CMAA A-3 (2005) requires payment applications to be submitted at least five (5) days before each progress payment is scheduled. But it also gives the construction manager fourteen (14) days to examine the application and send notice of deficiencies to the contractor. 40 The CMAA form provides for interest on late payments at the legal rate. 41 As for treatment of final payment in standard forms, when a contract is silent on the subject of a contractor s or subcontractor s right to pursue claims after final payment is received, any such claims may be waived by operation of state law upon acceptance of final payment. It is perhaps unsurprising, then, that the model contract form published by one association of project owners is silent on the effect of final payment as a waiver of claims. 42 The form essentially relies on the default legal rule of accord and satisfaction without employing a so-called red-flag explicitly providing for waiver of all claims on final payment. The same form, unsurprisingly, also omits any mention of release of retainage on substantial completion, although it does allow for owner occupancy of the project at that time. 43 Thus, the document leaves the entire fund of retainage for use as leverage to resolve all claims favorably to the owner in exchange for final payment. The standard form contract published by AOD provides a menu for the parties providing a choice between release of retainage upon substantial completion, 44 or upon final 38 AOD 2002GC 6.4.1, 6.5.3, AOD 2002GC CMAA A-3 (2005) , CMAA A-3 (2005) COAA Document B-200GC (2000) at Final Payment. 43 COAA Document B-200GC (2000) at AOD Form 2002GC (2002) The user has a choice between release of 75% of the retainage, or release of all retainage less 200% of the reasonable value of uncompleted work, where substantial completion is used as the benchmark. 11

12 completion. 45 The contract form expressly permits the contractor to preserve previously asserted claims. 46 The standard general contract form published by the Construction Management Association of America (CMAA) expressly provides that acceptance of final payment constitutes a waiver of all claims by the Contractor against the Owner. 47 The document is intended for use when the owner has hired a construction manager to serve as its agent to manage the construction project using another CMAA form, 48 and appears to put the leverage in the owner s hands with regard to final payment. The CMAA form document does not mention releasing retainage on substantial completion, even though it permits owner use and occupancy of the project. 49 The entire fund of retained money thus appears to, under the CMAA documents, remain in the owner s hands until final payment. C. ConsensusDOCS and DBIA Documents on Retainage and Claims after Final Payment The ConsensusDOCS 200 form makes an innovative attempt to tie release of retainage to the completion of punch-list items, by providing that the owner "shall pay the Contractor monthly the amount retained for unfinished items as each item is completed. 50 Standard forms published by DBIA permit both the design-builder and its subcontractors to preserve claims previously asserted in writing and remaining unsettled at the time of payment. The DBIA s Standard Form of General Conditions of Contract Between Owner and Design-Builder requires the design-builder to provide the project owner with a written release at the end of the project, expressly waiving, upon receipt of final payment, all claims except those claims previously made in writing to Owner and remaining unsettled at the time of final payment. 51 The DBIA documents similarly require general contractors and subcontractors working under the design-builder to provide written releases before final payment, and also allow claims against the designbuilder to be preserved if previously made in writing. 52 The DBIA documents provide for release of retainage to the design builder upon substantial completion. 53 Those working under the design-builder can expect their 45 AOD Form 2002GC (2002) AOD Form 2002GC (2002) CMAA A-3 (2005) at The document s first sentence provides that it is to be used in connection with the CMAA Document A CMAA A-3 (2005) at , , ConsensusDOCS 200 (2007) at DBIA 535 (1998) at DBIA 555 (DB-GC contract) (1999) at ; DBIA 560 (DB DB subcontract) (1999) at ; DBIA 570 (DB-nonDB subcontract) (2001) at DBIA 535 (1998) at 6.6.2, less an amount equal to the reasonable value of all remaining or incomplete items of Work. 12

13 retainage with final payment provided Design-Builder has received such retained amounts from Owner. 54 Otherwise, those working under the design-builder should still expect payment within ten (10) days after Design-Builder s receipt of final payment from Owner on account of Subcontractor s Final Application for Payment. 55 D. The AIA Documents on Claims after Final Payment and the Release of Retainage The AIA s A prevents waiver of claims previously made in writing and identified by that payee as unsettled at the time of final Application for Payment. 56 The A201 states that such claims are preserved after Acceptance of final payment by the Contractor, a Subcontractor or material supplier. While this is good, the AIA s A subcontract form does not directly address the issue of waiver on final payment. This means that subcontractors who use the A must ensure that the term incorporating the A by reference 57 is unadulterated to be certain that previously asserted claims will not be waived by acceptance of final payment. The A provides for release of retainage to the general contractor on substantial completion. 58 The A subcontract form provides for release of retainage to the subcontractor as soon as the subcontractor s work is substantially complete, if line-item release of retainage is permitted by the contract documents. 59 Otherwise, the subcontractor can expect payment of any owner-withheld retainage whenever it is received by the general contractor State Regulation of Private Payment Arrangements Timing and release of payments for private construction projects are increasingly the subject of state regulation. In 2002, for example, Missouri enacted a 10 percent limit on privately held retainage. 61 The law imposes a trust on retained funds for the benefit of the general contractor, subcontractors and suppliers, and also requires that contractors and subcontractors be permitted to substitute securities in lieu of retainage. A 2001 enactment in New Mexico requires both public and private retainage to be held in an escrow account with investment income inuring to the benefit of contractors and subcontractors DBIA 555 (1999) at 7.3.1; DBIA 560 (1999) at 7.3.1; DBIA 570 (2001) at DBIA 570 (2001) at 7.5.1; and see DBIA 555 (1999) at 7.6.1, DBIA 560 (1999) at A at A at A at 9.8.5, adjusted for Work that is incomplete or not in accordance with the requirements of the Contract Documents. 59 A at A at HB 1403, 91 st General Assembly, Missouri Revised Statutes HB 320 (2001) Retainage Act. 13

14 ASA maintains up-to-date resources detailing state restrictions on payment and retainage in its Guide to Passing a Prompt Pay Law in Your State and its Guide to Passing Retainage Reform in Your State, which are maintained as resources for legislative advocacy at the statement government level. Security for Payments: Trust Fund Terms, Liens and Bonds Project owners who are concerned that unpaid subcontractors may file mechanic s liens against their property can take steps when they request bids from prime contractors to increase the risk to the prime contractor for failure to pay subcontractors. One measure owners can implement is to insert "trust language" in the prime contract. This language will make the prime contractor a trustee of the funds it receives from the owner for the benefit of the subcontractors who are performing the work. As a trustee, the prime contractor cannot fail to pass payments through to subcontractors without subjecting itself to claims for breach of trust, punitive damages, and, in many states, criminal liability. Moreover, funds held by the prime contractor as a trustee are protected from the prime contractor s other creditors in the event of the prime contractor s bankruptcy. As one can imagine, a prime contract with trust language in it provides powerful protections to lower-tier subcontractors. For more details on imposing trust protections for subcontractor payments, see ASA s October 2003 Payment Advocacy Year (PAY!) white paper, Trust Funds. Another measure project owners can implement is to require the successful bidder to provide a payment bond. A payment bond is a guarantee provided by a surety of the prime contractor s obligations to pay its subcontractors. A list of sureties from whom the federal government will accept payment bonds for federal construction projects as required by the Miller Act (40 U.S.C et seq.) is published annually in U.S. Treasury Department Circular 570, which is available on the Internet at State government also all have their own, statutory bonding requirements for construction projects, called Little Miller Acts. For state-by-state details on state Little Miller Acts, read Lien and Bond Claims in the 50 States, available from the Foundation for the American Subcontractors Association ( If the owner does not act to impose a trust on funds paid to the prime contractor or to require payment bonds subcontractors must generally rely on statutorily-created liens against the project owner s property to secure their payments, commonly called mechanic s liens or construction liens. The rules for preserving and asserting a subcontractor s right to a mechanic s lien are as variable as the laws of the 50 states that provide for mechanic s liens. Subcontractors 14

15 should make themselves aware of the project owner s actual ownership interest in the property to be improved, as they may find themselves with a lien against a leasehold interest, rather than a lien against the equitable ownership interest in the improved real estate. For state-by-state details on mechanic s lien laws, read Lien and Bond Claims in the 50 States, also available from In addition to a mechanic s liens, construction contractors might also seek to obtain a lien against improvements they affixes to real estate through a fixture filing under Article 9 of the Uniform Commercial Code. A fixture filing lien may entitle the secured party to go back onto the land and repossess items that it has affixed to the real estate. For most construction contractors, a fixture filing would be inferior to a mechanic s lien because the lien of a fixture filing extends only to the particular piece of property that could be repossessed, rather than to the real estate itself. In addition, the provisions the Uniform Commercial Code that allow for fixture filing contain an exception for ordinary building materials incorporated into an improvement on land, as well as providing that the fixture-filing lien will, in most cases, be subordinate to a construction mortgage. 63 Finally, the financing statement that must be recorded in the land records to create the lien may require a signature from the debtor owning the real estate in order to impart record notice to creditors and purchasers, unlike a mechanic s lien, which requires no such signature. Not surprisingly, most debtors are unlikely to be particularly helpful to creditors seeking to lien their property. Thus, the lien laws of greatest importance to construction contractors and subcontractors are mechanics lien laws. Conclusion Issues about payment, payment timing, and payment security are fundamental credit issues that are central to the health of any business. In the contraction context, these issues are particularly critical to the survival of construction businesses which provide large amounts of labor and material on credit, for a promise of payment in the future. Subcontractors must identify, and recognize the differences between the kinds of payment arrangements that: (a) they consider acceptable; (b) are poor credit risks; and (c) are red flags indicating financial trouble is ahead. In taking these steps, and being aware of the best practices endorsed by the ASA and reflected in the 2007 ConsensusDOCS, subcontractors can better protect themselves from unpleasant and unnecessary payment risks. 63 UCC Article 9. 15

Contingent Payment Frequently Asked Questions

Contingent Payment Frequently Asked Questions August 2015 Contingent Payment Frequently Asked Questions Subcontractors continue to report that one of the most objectionable subcontract provisions they face is a clause that legally prevents them from

More information

Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project

Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project Document A105 2007 Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project AGREEMENT made as of the in the year (In words, indicate day, month and year.) BETWEEN

More information

Standard Form of Agreement Between Design-Builder and Contractor. The Design-Builder has entered into a Design-Build Contract with the Owner dated:

Standard Form of Agreement Between Design-Builder and Contractor. The Design-Builder has entered into a Design-Build Contract with the Owner dated: Document A142 2014 Standard Form of Agreement Between Design-Builder and Contractor AGREEMENT made as of the day of in the year (In words, indicate day, month and year.) BETWEEN the Design-Builder: (Name,

More information

WESTERN RIVERSIDE COUNCIL OF GOVERNMENTS EQUIPMENT PURCHASE AGREEMENT

WESTERN RIVERSIDE COUNCIL OF GOVERNMENTS EQUIPMENT PURCHASE AGREEMENT WESTERN RIVERSIDE COUNCIL OF GOVERNMENTS EQUIPMENT PURCHASE AGREEMENT This Equipment Purchase Agreement ( Agreement ) is entered into this day of, 20, by and between the Western Riverside Council of Governments,

More information

The Toler Firm LLC A Construction Law Firm Timothy N. Toler September 23, 2015

The Toler Firm LLC A Construction Law Firm Timothy N. Toler September 23, 2015 The Toler Firm LLC A Construction Law Firm Timothy N. Toler September 23, 2015 Negotiating 8 Key Contract Clauses from the Contractor s Perspective (Part 1 of 2) 1 This is the first of a two-part overview

More information

Construction Law Survival Manual. Credit Management Contract Terms.

Construction Law Survival Manual. Credit Management Contract Terms. 1 Credit Management Contract Terms Presented by James D. Fullerton www.fullertonlaw.com JFullerton@FullertonLaw.com James D. Fullerton Fullerton & Knowles, P.C. 12642 Chapel Rd. Clifton, VA 20124 (703)

More information

SAMPLE DOCUMENT SUBCONTRACT AGREEMENT

SAMPLE DOCUMENT SUBCONTRACT AGREEMENT SUBCONTRACT AGREEMENT THIS SUBCONTRACT, made this day of by and between (hereinafter "Contractor"), with an office and principal place of business at and (hereinafter "Subcontractor") with an office and

More information

Contractor for any and all liability, costs, expenses, fines, penalties, and attorney s fees resulting from its failure to perform such duties.

Contractor for any and all liability, costs, expenses, fines, penalties, and attorney s fees resulting from its failure to perform such duties. SUBCONTRACT AGREEMENT THIS SUBCONTRACT, made this day of, 20 by and between (hereinafter "Contractor"), with an office and principal place of business at and (hereinafter "Subcontractor") with an office

More information

AN ANALYSIS OF ARIZONA PROMPT PAYMENT STATUTES

AN ANALYSIS OF ARIZONA PROMPT PAYMENT STATUTES AN ANALYSIS OF ARIZONA PROMPT PAYMENT STATUTES GUY W. BLUFF, ESQ. I. ARIZONA S PROMPT PAYMENT STATUTES 3 A. The General Rule 4 B. Objections Must be In Writing and Specific 6 II. SUMMARY OF STATUTORY AND

More information

Standard Form of Agreement Between Contractor and Subcontractor

Standard Form of Agreement Between Contractor and Subcontractor Document A401 2007 Standard Form of Agreement Between Contractor and Subcontractor AGREEMENT made as of the in the year (In words, indicate day, month and year.) day of BETWEEN the Contractor: (Name, legal

More information

AIA Document A101 TM 2007

AIA Document A101 TM 2007 AIA Document A101 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum AS MODIFIED BY OWNER AGREEMENT made as of the day of in the year (In words,

More information

Document A Standard Form of Agreement Between Contractor and Subcontractor

Document A Standard Form of Agreement Between Contractor and Subcontractor Document A401 2017 Standard Form of Agreement Between Contractor and Subcontractor AGREEMENT made as of the day of in the year (In words, indicate day, month and year.) BETWEEN the Contractor: (Name, legal

More information

SHORT FORM STANDARD SUBCONTRACT. This Agreement is made this day of, 20, between

SHORT FORM STANDARD SUBCONTRACT. This Agreement is made this day of, 20, between SHORT FORM STANDARD SUBCONTRACT This Agreement is made this day of, 20, between (Contractor) and (Subcontractor). The work described in Section I below shall be performed in accordance with the prime contract

More information

AIA Document A201 TM 1997

AIA Document A201 TM 1997 AIA Document A201 TM 1997 General Conditions of the Contract for Construction for the following PROJECT: (Name and location or address): Project University of Maine at Farmington THE OWNER: (Name and address):

More information

White Paper on Project Financing

White Paper on Project Financing White Paper on Project Financing Published by American Subcontractors Association, Inc. Foundation of the American Subcontractors Association, Inc. 1004 Duke Street Alexandria VA 22314-3588 (703) 684-3450

More information

ARTICLE 1 ARTICLE 3 CONTRACTOR THE SUBCONTRACT DOCUMENTS ARTICLE 2 MUTUAL RIGHTS AND RESPONSIBILITIES

ARTICLE 1 ARTICLE 3 CONTRACTOR THE SUBCONTRACT DOCUMENTS ARTICLE 2 MUTUAL RIGHTS AND RESPONSIBILITIES ARTICLE 1 THE SUBCONTRACT DOCUMENTS 1.1 The Subcontract Documents consist of (1) this Agreement; (2) the prime Contract, consisting of the Agreement between the Owner and Contractor and the other Contract

More information

Document A Exhibit A

Document A Exhibit A Design-Build Amendment Document A141 2014 Exhibit A This Amendment is incorporated into the accompanying AIA Document A141 2014, Standard Form of Agreement Between Owner and Design-Builder dated the day

More information

Document A General Conditions of the Contract for Construction, Construction Manager as Adviser Edition

Document A General Conditions of the Contract for Construction, Construction Manager as Adviser Edition Document A232 2009 General Conditions of the Contract for Construction, Construction Manager as Adviser Edition for the following PROJECT: (Name, and location or address) THE CONSTRUCTION MANAGER: (Name,

More information

Document A101 TM. Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum

Document A101 TM. Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum Document A101 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum AGREEMENT made as of the day of in the year (In words, indicate day, month and

More information

RENOVATION LOAN AGREEMENT

RENOVATION LOAN AGREEMENT THIS IS A MODEL DOCUMENT FOR USE IN FANNIE MAE RENOVATION LOAN TRANSACTIONS. THIS FORM IS PROVIDED AS AN EXAMPLE AND HAS NOT BEEN EVALUATED FOR VALIDITY AND ENFORCEABILITY IN ANY JURISDICTION. LENDERS

More information

Avoiding Common Payment Pitfalls for Subcontractors: A Primer on Federal Contracting Payment Remedies

Avoiding Common Payment Pitfalls for Subcontractors: A Primer on Federal Contracting Payment Remedies Avoiding Common Payment Pitfalls for Subcontractors: A Primer on Federal Contracting Payment Remedies Shoshana E. Rothman BrigliaMcLaughlin, PLLC April 2017 Seminar Goals: 1. Understand key contract clauses

More information

AIA Document A201 TM 1997

AIA Document A201 TM 1997 AIA Document A201 TM 1997 General Conditions of the Contract for Construction for the following PROJECT: (Name and location or address): A201 conversion Michigan State University East Lansing, MI THE OWNER:

More information

AIA Document A101 TM 2007

AIA Document A101 TM 2007 AIA Document A101 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum AGREEMENT made as of the day of in the year (In words, indicate day, month

More information

FINISHING CONTRACTORS ASSOCIATION

FINISHING CONTRACTORS ASSOCIATION FINISHING CONTRACTORS ASSOCIATION GETTING PAID IN TROUBLED TIMES: IMPORTANT CONTRACTUAL ISSUES It is more important than ever for subcontractors to do everything they can to ensure their rights to payment.

More information

IFB F B-WING RENOVATIONS IFB F C OFFICES BUILD OUT. Addendum 3

IFB F B-WING RENOVATIONS IFB F C OFFICES BUILD OUT. Addendum 3 JUNE 23, 2016 ATTENTION ALL PROPONENTS: IFB F2015017 B-WING RENOVATIONS IFB F2015007 9C OFFICES BUILD OUT Addendum 3 The purpose of this Amendment is to advise all offertories of the following: 1. In Project

More information

Document A101 TM. Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum

Document A101 TM. Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum Document A101 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum AGREEMENT made as of the day of in the year (In words, indicate day, month and

More information

Document A401 TM. Standard Form of Agreement Between Contractor and Subcontractor

Document A401 TM. Standard Form of Agreement Between Contractor and Subcontractor Document A401 TM 2007 Standard Form of Agreement Between Contractor and Subcontractor AGREEMENT made as of the day of in the year (In words, indicate day, month and year.) BETWEEN the Contractor: (Name,

More information

Construction Management Contract This agreement is made by (Contractor) and (Owner) on the date written beside our signatures.

Construction Management Contract This agreement is made by (Contractor) and (Owner) on the date written beside our signatures. Construction Management Contract This agreement is made by (Contractor) and (Owner) on the date written beside our signatures. Contractor Address Address City, Zip Work Phone Number: Cell Phone Number:

More information

MASTER SUBCONTRACT AGREEMENT

MASTER SUBCONTRACT AGREEMENT MASTER SUBCONTRACT AGREEMENT This Master Subcontract Agreement ( Subcontract ), made this day of, 20 by and between (hereinafter "Contractor"), with an office and principal place of business at and (hereinafter

More information

Chapter 7 Bonds, Insurance, and Taxes

Chapter 7 Bonds, Insurance, and Taxes Sam Chapter 7 Bonds, Insurance, and Taxes Section 1 Bonds.................................................................. 191 7.1.1 General......................................................... 191

More information

General Conditions for Construction GCC201. Contract Type: Document No. for the following PROJECT: (Name and location or address) EXAMPLE

General Conditions for Construction GCC201. Contract Type: Document No. for the following PROJECT: (Name and location or address) EXAMPLE Page 1 of 37 for the following PROJECT: (Name and location or address) EXAMPLE THE OWNER: (Name and address) Example, THE ARCHITECT: (Name and address) TABLE OF ARTICLES 1 GENERAL PROVISIONS 2 OWNER 3

More information

3.1.2 The Contractor shall perform the Work in accordance with the Contract Documents.

3.1.2 The Contractor shall perform the Work in accordance with the Contract Documents. the portion of the Work affected by a material change. After the Owner furnishes the evidence, the Owner shall not materially vary such financial arrangements without prior notice to the Contractor. 2.2.2

More information

ADDENDUM TO AGCC3. Unless otherwise stated, the contract price includes all taxes.

ADDENDUM TO AGCC3. Unless otherwise stated, the contract price includes all taxes. ADDENDUM TO AGCC3 This is an Addendum to the AGCC3 Long Form Standard Subcontract and shall amend and modify the Subcontract and any Contract Documents. 1. Section 3: Add the following language: Unless

More information

CONSTRUCTION CONTRACT RIDER

CONSTRUCTION CONTRACT RIDER CONSTRUCTION CONTRACT RIDER In connection with the work at, Massachusetts (the Development ) to be performed by (the Contractor ) pursuant to the Construction Contract dated, 20 between the Contractor

More information

SECTION SUPPLEMENTARY CONDITIONS

SECTION SUPPLEMENTARY CONDITIONS SECTION 00800 SUPPLEMENTARY CONDITIONS PART 1 GENERAL 1.01 GENERAL CONDITIONS A. The Supplementary Conditions modify, delete and/or add to the General Conditions, AIA Document A201/Cma, Construction Management

More information

Document A101 TM. Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum

Document A101 TM. Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum Document A101 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum AGREEMENT made as of. (Date of issuance of Owner s Purchase Order) BETWEEN the

More information

Document A101 TM. Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum

Document A101 TM. Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum Document A101 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum AGREEMENT made as of the day of in the year (In words, indicate day, month and

More information

WHEN CAN YOU STOP WORK FOR NONPAYMENT?

WHEN CAN YOU STOP WORK FOR NONPAYMENT? WHEN CAN YOU STOP WORK FOR NONPAYMENT? PLANNING AHEAD When an owner or general contractor has not paid a roofing contractor the sums it is owed under the contract, the roofing contractor is faced with

More information

Revenue Recognition: Construction Industry Supplement

Revenue Recognition: Construction Industry Supplement Revenue Recognition: Construction Industry Supplement Table of Contents BACKGROUND & SUMMARY... 4 SCOPE... 5 THE REVENUE RECOGNITION MODEL... 5 STEP 1 IDENTIFY THE CONTRACT WITH A CUSTOMER... 6 Collectibility...

More information

AGC TEXT COPY THE ASSOCIATED GENERAL CONTRACTORS OF AMERICA AGC DOCUMENT NO. 603 STANDARD SHORT FORM AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR

AGC TEXT COPY THE ASSOCIATED GENERAL CONTRACTORS OF AMERICA AGC DOCUMENT NO. 603 STANDARD SHORT FORM AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR THE ASSOCIATED GENERAL CONTRACTORS OF AMERICA AGC DOCUMENT NO. 603 STANDARD SHORT FORM AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR (Where Contractor Assumes Risk of Owner Payment) The original text

More information

STANDARD SUBCONTRACT AGREEMENT FOR BUILDING CONSTRUCTION

STANDARD SUBCONTRACT AGREEMENT FOR BUILDING CONSTRUCTION STANDARD SUBCONTRACT AGREEMENT FOR BUILDING CONSTRUCTION THIS AGREEMENT made at Columbus, Ohio on by and between Lincoln Construction, Inc., hereinafter referred to as the Contractor, and, hereinafter

More information

THE SURETY & FIDELITY ASSOCIATION OF AMERICA MEMORANDUM

THE SURETY & FIDELITY ASSOCIATION OF AMERICA MEMORANDUM THE SURETY & FIDELITY ASSOCIATION OF AMERICA MEMORANDUM TO: FROM: RE: Government Affairs Advisory Committee Daniel Wanke Contract Surety Legislation DATE: June 3, 2016 There are 11 states and the District

More information

Document A401 TM. Standard Form of Agreement Between Contractor and Subcontractor

Document A401 TM. Standard Form of Agreement Between Contractor and Subcontractor Document A401 TM 2017 Standard Form of Agreement Between Contractor and Subcontractor AGREEMENT made as of the day of in the year (In words, indicate day, month and year.) BETWEEN the Contractor: (Name,

More information

SUMMARY OF MECHANICS LIEN LAW FOR TEXAS. With Changes for 2012

SUMMARY OF MECHANICS LIEN LAW FOR TEXAS. With Changes for 2012 SUMMARY OF MECHANICS LIEN LAW FOR TEXAS With Changes for 2012 Section Contents Pre-lien Notice(s) Name of Notice Who Must Use This Notice When How to Serve Verified or notarized? Section Contents Mechanic

More information

SECTION 8 - MEASUREMENT AND PAYMENT TABLE OF CONTENTS

SECTION 8 - MEASUREMENT AND PAYMENT TABLE OF CONTENTS SECTION 8 - MEASUREMENT AND PAYMENT TABLE OF CONTENTS Section Page 8-1 BASIS AND MEASUREMENT OF PAYMENT QUANTITIES... 8-1 8-1.01 Unit Price Contracts... 8-1 8-1.02 Lump Sum or Job Contracts... 8-1 8-1.03

More information

Trade Association Form Subcontracts: The Good, The Not So Bad, And the Ugly

Trade Association Form Subcontracts: The Good, The Not So Bad, And the Ugly KILLER CONTRACT CLAUSES Donald W. Gregory, Esq. KEGLER, BROWN, HILL & RITTER Attorneys & Counselors at Law 65 E. State Street, Suite 1800 Columbus, OH 43215 (614) 462-5400 Trade Association Form Subcontracts:

More information

GENERAL: WITNESSETH: That the said Contractor and the said District, for consideration hereinafter named agree as follows: DESCRIPTION OF WORK:

GENERAL: WITNESSETH: That the said Contractor and the said District, for consideration hereinafter named agree as follows: DESCRIPTION OF WORK: GENERAL: This Contract made and entered into this day of, 2013, by and between the Sundown Sanitary Sewer District, hereinafter called "District", and, hereinafter called "Contractor", duly authorized

More information

TEXAS MECHANIC S LIEN LAW

TEXAS MECHANIC S LIEN LAW TEXAS MECHANIC S LIEN LAW 2018-2019 Go to: Texas Mechanics Lien Forms More Info: www.nationallienlaw.com Section Contents Pre-lien Notice(s) Name of Notice Who Must Use This Notice When How to Serve Verified

More information

SECTION 8 - MEASUREMENT AND PAYMENT TABLE OF CONTENTS

SECTION 8 - MEASUREMENT AND PAYMENT TABLE OF CONTENTS SECTION 8 - MEASUREMENT AND PAYMENT TABLE OF CONTENTS Section Page 8-1 BASIS AND MEASUREMENT OF PAYMENT QUANTITIES... 8.1 8-1.01 Unit Price Contracts... 8.1 8-1.02 Lump Sum or Job Contracts... 8.1 8-1.03

More information

Document A201 TM 2007 SP

Document A201 TM 2007 SP AIA Document A201 TM 2007 SP General Conditions of the Contract for Construction, for use on a Sustainable Project for the following PROJECT: (Name and location or address) THE OWNER: (Name, legal status

More information

Standard Form of Agreement Between Contractor and Subcontractor

Standard Form of Agreement Between Contractor and Subcontractor Standard Form of Agreement Between Contractor and Subcontractor GENERAL TERMS AND CONDITIONS ARTICLE 1 THE SUBCONTRACT DOCUMENTS 1.1 The Subcontract Documents consist of (1) these General Terms and Conditions,

More information

AGREEMENT FOR ENGINEERING SERVICES (AHTD VERSION COST PLUS FEE) JOB NO. FEDERAL AID PROJECT ( FAP ) NO. JOB TITLE PREAMBLE

AGREEMENT FOR ENGINEERING SERVICES (AHTD VERSION COST PLUS FEE) JOB NO. FEDERAL AID PROJECT ( FAP ) NO. JOB TITLE PREAMBLE AGREEMENT FOR ENGINEERING SERVICES (AHTD VERSION COST PLUS FEE) JOB NO. FEDERAL AID PROJECT ( FAP ) NO. JOB TITLE PREAMBLE THIS AGREEMENT, entered into this day of, by and between the Arkansas State Highway

More information

STATE OF COLORADO BUILDING EXCELLENT SCHOOLS TODAY SUBLEASE OF MORGAN COUNTY SCHOOL DISTRICT RE-3. by and between

STATE OF COLORADO BUILDING EXCELLENT SCHOOLS TODAY SUBLEASE OF MORGAN COUNTY SCHOOL DISTRICT RE-3. by and between KR draft 12/16/14 After recording return to: Michael R. Johnson Kutak Rock LLP 1801 California Street, Suite 3000 Denver, Colorado 80202 STATE OF COLORADO BUILDING EXCELLENT SCHOOLS TODAY SUBLEASE OF MORGAN

More information

Document A101. Standard Form of Agreement Between Owner and Contractor where the basis of payment is a STIPULATED SUM

Document A101. Standard Form of Agreement Between Owner and Contractor where the basis of payment is a STIPULATED SUM TM Document A101 1997 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a STIPULATED SUM AGREEMENT made as of the day of March in the year of 2007 (In words, indicate

More information

Managing design professional risks arising out of the Prime/Subcontractor relationship

Managing design professional risks arising out of the Prime/Subcontractor relationship Managing design professional risks arising out of the Prime/Subcontractor relationship June 22, 2017 Gail S. Kelley P.E., Esq., LEED AP J. Kent Holland, J.D. ConstructionRisk, LLC Copyright Information

More information

SUPPLEMENTARY AND SPECIAL TERMS AND CONDITIONS FOR MINOR PROJECTS

SUPPLEMENTARY AND SPECIAL TERMS AND CONDITIONS FOR MINOR PROJECTS SUPPLEMENTARY AND SPECIAL TERMS AND CONDITIONS FOR MINOR PROJECTS HCPS STANDARDS DOC. No.: 01015 APPLICATION: ELEMENTARY, MIDDLE AND HIGH SCHOOL DATE OF ISSUE: 04-04-14 - Revised paragraph 13.10.1 to increase

More information

MANITOBA HOUSING SUPPLEMENTAL CONDITIONS CONTRACT #: XXXX GENERAL

MANITOBA HOUSING SUPPLEMENTAL CONDITIONS CONTRACT #: XXXX GENERAL GENERAL 1. Stipulated Price Contract CCDC2-2008 2. CCDC2-2008 Supplemental Conditions The Construction Contract for this project is the standard Construction Document- CCDC2 2008, Stipulated Price Contract.

More information

SUBCONTRACT FOR BUILDING CONSTRUCTION

SUBCONTRACT FOR BUILDING CONSTRUCTION SUBCONTRACT FOR BUILDING CONSTRUCTION TABLE OF ARTICLES 1. AGREEMENT 2. SCOPE OF WORK 3. SCHEDULE OF WORK 4. CONTRACT PRICE 5. PAYMENT 6. CHANGES, CLAIMS AND DELAYS 7. CONTRACTOR'S OBLIGATIONS 8. SUBCONTRACTOR'S

More information

APPENDIX D PAGE 1 of 9. A. ACCESS TO RECORDS AND REPORTS 49 U.S.C. 5325; 18 CFR (i); 49 CFR

APPENDIX D PAGE 1 of 9. A. ACCESS TO RECORDS AND REPORTS 49 U.S.C. 5325; 18 CFR (i); 49 CFR PAGE 1 of 9 Federal Transit Administration (FTA) Required Clauses for Operations Contracts under the 2011 Section 5310 Purchase of Service Contract for the Southeast NH RCC through COAST A. ACCESS TO RECORDS

More information

CITY OF EAST POINT BID NO BID TITLE: CONTRACT FOR CONSTRUCTION AND INCORPORATED GENERAL CONDITIONS

CITY OF EAST POINT BID NO BID TITLE: CONTRACT FOR CONSTRUCTION AND INCORPORATED GENERAL CONDITIONS CITY OF EAST POINT BID NO. 2017- BID TITLE: Revised 12/05/2014 TABLE OF CONTENTS Page # ARTICLE I THE CONTRACT AND THE CONTRACT DOCUMENT... 1 1.1 The Contract... 1 1.2 The Contract Documents... 1 1.3 Entire

More information

ACA UNIFORM TERMS AND CONDITIONS

ACA UNIFORM TERMS AND CONDITIONS ACA UNIFORM TERMS AND CONDITIONS ARIZONA COMMERCE AUTHORITY (ACA) UNIFORM TERMS AND CONDITIONS 1. Definition of Terms As used in this Solicitation and any resulting Contract, the terms listed below are

More information

Webinar: Making the Right Choices in Government Contracting Part 3

Webinar: Making the Right Choices in Government Contracting Part 3 Public Contracting Institute LLC Webinar: Making the Right Choices in Government Contracting Part 3 Presented by Richard D. Lieberman, FAR Consultant, Website: www.richarddlieberman.com. Email rliebermanconsultant@gmail.com.

More information

Construction Law: Greensboro Builders Association Remodelers Counsel

Construction Law: Greensboro Builders Association Remodelers Counsel Construction Law: Greensboro Builders Association Remodelers Counsel February 25, 2010 J. Patrick Haywood Carruthers & Roth, P.A. 235 N. Edgeworth Street Greensboro, NC 27401 Direct Line: (336) 478-1177

More information

Standard Form of Agreement Between OWNER AND CONSTRUCTION MANAGER Construction Manager At-Risk

Standard Form of Agreement Between OWNER AND CONSTRUCTION MANAGER Construction Manager At-Risk CMAA Document CMAR-1 Standard Form of Agreement Between OWNER AND CONSTRUCTION MANAGER Construction Manager At-Risk 2004 EDITION This document is to be used in connection with CMAA Standard Form of Contract

More information

DOCUMENT SUPPLEMENTARY CONDITIONS

DOCUMENT SUPPLEMENTARY CONDITIONS 1.1 GENERAL CONDITIONS DOCUMENT 007300 SUPPLEMENTARY CONDITIONS A. The Supplementary Conditions modify, delete and/or add to the General Conditions, AIA Document A201/Cma, Construction Management Edition,

More information

FEDERAL EMERGENCY MANAGEMENT AGENCY S GRANT PROGRAM REQUIREMENTS FOR PROCUREMENT CONTRACTS

FEDERAL EMERGENCY MANAGEMENT AGENCY S GRANT PROGRAM REQUIREMENTS FOR PROCUREMENT CONTRACTS FEDERAL EMERGENCY MANAGEMENT AGENCY S GRANT PROGRAM REQUIREMENTS FOR PROCUREMENT CONTRACTS I. DEFINITIONS A. Agreement means the agreement between City and Contractor to which this document (Federal Emergency

More information

U.S. DEPARTMENT OF HOMELAND SECURITY'S URBAN AREAS SECURITY INITIATIVE GRANT PROGRAM REQUIREMENTS FOR PROCUREMENT CONTRACTS

U.S. DEPARTMENT OF HOMELAND SECURITY'S URBAN AREAS SECURITY INITIATIVE GRANT PROGRAM REQUIREMENTS FOR PROCUREMENT CONTRACTS U.S. DEPARTMENT OF HOMELAND SECURITY'S URBAN AREAS SECURITY INITIATIVE GRANT PROGRAM REQUIREMENTS FOR PROCUREMENT CONTRACTS I. DEFINITIONS A. Agreement means the agreement between City and Contractor to

More information

FIRM FIXED PRICE TERMS AND CONDITIONS AES-1 Applicable to Architect-Engineering Services Contracts INDEX CLAUSE NUMBER TITLE PAGE

FIRM FIXED PRICE TERMS AND CONDITIONS AES-1 Applicable to Architect-Engineering Services Contracts INDEX CLAUSE NUMBER TITLE PAGE Applicable to Architect-Engineering Services Contracts INDEX CLAUSE NUMBER TITLE PAGE 1. DEFINITIONS 1 2. COMPOSITION OF THE ARCHITECT-ENGINEER 1 3. INDEPENDENT CONTRACTOR 1 4. RESPONSIBILITY OF THE ARCHETECT-ENGINEER

More information

Washington University in St. Louis

Washington University in St. Louis Washington University in St. Louis Construction Terms and Conditions A. AGREEMENT. The Purchase Order, these Terms and Conditions, any special conditions, Owner s Policies, Design Standards and Insurance

More information

Master Securities Loan Agreement

Master Securities Loan Agreement Master Securities Loan Agreement 2017 Version Dated as of: Between: and 1. Applicability. From time to time the parties hereto may enter into transactions in which one party ( Lender ) will lend to the

More information

7 Bonds, Insurance and Taxes

7 Bonds, Insurance and Taxes Purchasing Manual 7 Bonds, Insurance and Taxes 7 Bonds, Insurance and Taxes........................................... 251 7.1 Bonds..........................................................................

More information

7 Bonds, Insurance, and Taxes

7 Bonds, Insurance, and Taxes Bonds, Insurance, and Taxes 7.1.1.b 7 Bonds, Insurance, and Taxes 7.1 Bonds 7.1.1 General 7.1.1.a 7.1.1.b Guidelines. Bonds (other than bonds required for construction contracts) (see 7.1.2.a) and performance

More information

Participating Dealer Financing Agreement with Collins Community Credit Union

Participating Dealer Financing Agreement with Collins Community Credit Union Participating Dealer Financing Agreement with Collins Community Credit Union THIS AGREEMENT ( Agreement ) is entered into between, hereinafter referred to as Dealer, and Collins Community Credit Union,

More information

GENERAL CONDITIONS. of the CONTRACT FOR CONSTRUCTION. for the ARCHDIOCESE OF CHICAGO. for SOLE SOURCE CONTRACTS. (2004 Archdiocese Edition)

GENERAL CONDITIONS. of the CONTRACT FOR CONSTRUCTION. for the ARCHDIOCESE OF CHICAGO. for SOLE SOURCE CONTRACTS. (2004 Archdiocese Edition) Document #: 861154 GENERAL CONDITIONS of the CONTRACT FOR CONSTRUCTION for the ARCHDIOCESE OF CHICAGO for SOLE SOURCE CONTRACTS (2004 Archdiocese Edition) 86 Document #: 861161 TABLE OF CONTENTS ARTICLE

More information

SUBCONTRACT (SHORT FORM)

SUBCONTRACT (SHORT FORM) SUBCONTRACTOR: PHONE SUBCONTRACT (SHORT FORM) PROJECT: LOCATION: This agreement is made and effective, by and between SUN CONSTRUCTION & FACILITY SERVICES, INC. (Contractor) and (Subcontractor) which are

More information

ENERGY EFFICIENCY CONTRACTOR AGREEMENT

ENERGY EFFICIENCY CONTRACTOR AGREEMENT ENERGY EFFICIENCY CONTRACTOR AGREEMENT 2208 Rev. 2/1/13 THIS IS AN AGREEMENT by and between PUBLIC UTILITY DISTRICT NO. 1 OF SNOHOMISH COUNTY (the District ) and a contractor registered with the State

More information

Standard Form of Agreement Between. Owner and Design-Builder Cost Plus Fee with an Option for a Guaranteed Maximum Price

Standard Form of Agreement Between. Owner and Design-Builder Cost Plus Fee with an Option for a Guaranteed Maximum Price November 3, 2014 Standard Form of Agreement Between Owner and Design-Builder Cost Plus Fee with an Option for a Guaranteed Maximum Price This document has important legal consequences. Consultation with

More information

STANDARD CONTRACT EXECUTION FORMS

STANDARD CONTRACT EXECUTION FORMS THE BIDDING AND CONTRACT PROVISIONS Document Section 00 50 00 - Standard Contract Execution Forms (Standard Contract Set) STANDARD CONTRACT EXECUTION FORMS 1. EXECUTION OF THE AGREEMENT 1.1 Extraneous

More information

4. CARGO PREFERENCE REQUIREMENTS 46 U.S.C CFR

4. CARGO PREFERENCE REQUIREMENTS 46 U.S.C CFR FEDERAL CLAUSES 4. CARGO PREFERENCE REQUIREMENTS 46 U.S.C. 1241 46 CFR Part 381 Applicability to Contracts: The Cargo Preference requirements apply to all contracts involving equipment, materials, or commodities

More information

AIA Document B141 TM 1997 Part

AIA Document B141 TM 1997 Part 1 AIA Document B141 TM 1997 Part Standard Form of Agreement Between Owner and Architect with Standard Form of Architect's Services TABLE OF ARTICLES 1.1 INITIAL INFORMATION 1.2 RESPONSIBILITIES OF THE

More information

ATTACHMENT E BILLING PROCEDURES

ATTACHMENT E BILLING PROCEDURES Job Name Job Location SWINERTON Job No. IF CHECKED, TEXTURA IS NOT USED ON THIS PROJECT A. Progress Payments ATTACHMENT E BILLING PROCEDURES All billings for work performed during the period of the 1st

More information

CITY UNIVERSITY CONSTRUCTION FUND GUIDELINES FOR PROCUREMENT CONTRACTS (as amended through June 23, 2016)

CITY UNIVERSITY CONSTRUCTION FUND GUIDELINES FOR PROCUREMENT CONTRACTS (as amended through June 23, 2016) CITY UNIVERSITY CONSTRUCTION FUND GUIDELINES FOR PROCUREMENT CONTRACTS (as amended through June 23, 2016) Section A. Introduction These Guidelines set forth the operative policy and instructions of the

More information

MANDATORY GENERAL TERMS AND CONDITIONS:

MANDATORY GENERAL TERMS AND CONDITIONS: MANDATORY GENERAL TERMS AND CONDITIONS: A. PURCHASING MANUAL: This solicitation is subject to the provisions of the College s Purchasing Manual for Institutions of Higher Education and their Vendors and

More information

OSE FORM 812 STANDARD SUPPLEMENTARY CONDITIONS

OSE FORM 812 STANDARD SUPPLEMENTARY CONDITIONS OSE FORM 812 STANDARD SUPPLEMENTARY CONDITIONS OWNER: PROJECT NUMBER: PROJECT NAME: 1 GENERAL CONDITIONS The General Conditions of the Contract for Construction, AIA Document A201, 2007 Edition, Articles

More information

BETWEEN name. address. AND name (hereinafter called the Subcontractor ) address

BETWEEN name. address. AND name (hereinafter called the Subcontractor ) address AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR CONTRACTOR S COPY SUBCONTRACT NO. Alberta Standard Construction Subcontract THIS AGREEMENT made this day of, A.D. 20 BETWEEN name (hereinafter called the

More information

DOUKPSC04 Rev Feb 2013

DOUKPSC04 Rev Feb 2013 DOUKPSC04 Purchasing Standard conditions for the Purchase of Consultancy Services 1 DEFINITIONS In the Contract (as hereinafter defined) the following words and expressions shall have the meanings hereby

More information

Document A Standard Abbreviated Form of Agreement Between Owner and Contractor

Document A Standard Abbreviated Form of Agreement Between Owner and Contractor Document A104 2017 Standard Abbreviated Form of Agreement Between Owner and Contractor AGREEMENT made as of the day of in the year (In words, indicate day, month and year.) BETWEEN the Owner: (Name, legal

More information

ARTICLE 8 - OWNER S RESPONSIBILITIES

ARTICLE 8 - OWNER S RESPONSIBILITIES properly integrate with such other work. Contractor shall not endanger any work of others by cutting, excavating, or otherwise altering their work and will only cut or alter their work with the written

More information

Subcontract Agreement

Subcontract Agreement S THIS AGREEMENT made as of the day of, 2012 BETWEEN the Contractor: TCL Partners 5212 123 rd Place SE Everett, WA 98208 and the For the Following Project: The Architect for the Project: The Contractor

More information

Purchase Order Terms and Conditions Commercial Contracts

Purchase Order Terms and Conditions Commercial Contracts 1. ACCEPTANCE: Purchase Order Terms and Conditions This purchase order represents Company's offer to purchase the goods or services ordered strictly in accordance with its stated terms and conditions.

More information

SMALL SERVICE, REHABILITATION, OR CONSTRUCTION AGREEMENT

SMALL SERVICE, REHABILITATION, OR CONSTRUCTION AGREEMENT SMALL SERVICE, REHABILITATION, OR CONSTRUCTION AGREEMENT (This Agreement shall be utilized for any service, rehabilitation, or construction project when funding sources contain no additional restrictions

More information

Project # and Name Subcontract Firm Name Subcontract #: Appendix F - Subcontract Terms and Conditions

Project # and Name Subcontract Firm Name Subcontract #: Appendix F - Subcontract Terms and Conditions ARTICLE 1 - SUBCONTRACTOR'S WORK AND SCHEDULE 1.1 WORK: Subcontractor agrees to furnish all supervision, labor, materials, tools, equipment, services, storage, and whatever else is required to perform

More information

AIA Document A133 TM 2009

AIA Document A133 TM 2009 AIA Document A133 TM 2009 Standard Form of Agreement Between Owner and Construction Manager as Constructor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price

More information

Risk Identification & Contract Risk Management

Risk Identification & Contract Risk Management Risk Identification & Contract Risk Management In the world of geospatial Presenters Bob Hanson Senior Vice President, Michael Baker International Geospatial Practice Leader 717 221-2005 rhanson@mbakerintl.com

More information

AIA Document A103 TM 2007

AIA Document A103 TM 2007 AIA Document A103 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is the Cost of the Work plus a fee without a Guaranteed Maximum Price AGREEMENT made as of the

More information

General Contract Conditions for Small Construction/Development Contracts

General Contract Conditions for Small Construction/Development Contracts General Contract Conditions for Small Construction/Development Contracts U.S. Department of Housing and Urban Development Office of Public and Indian Housing OMB Approval No. 2577-0157 (exp. 3/31/2020)

More information

Educational Use Only S A M P L E S A M P L E

Educational Use Only S A M P L E S A M P L E CONSENSUSDOCS 750 STANDARD FORM OF AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR This document was developed through a collaborative effort of entities representing a wide cross-section of the construction

More information

CONSTRUCTION CONTRACT EXAMPLE

CONSTRUCTION CONTRACT EXAMPLE P a g e 1 CONSTRUCTION CONTRACT EXAMPLE THIS AGREEMENT, made and entered into this date, by and between, hereinafter called CONTRACTOR, and NPC QUALITY BURGER, INC., hereinafter called OWNER. IT IS HEREBY

More information

SAMPLE SPECIFICATION SECTION SALES AND USE TAX SAVINGS

SAMPLE SPECIFICATION SECTION SALES AND USE TAX SAVINGS SAMPLE SPECIFICATION SECTION SALES AND USE TAX SAVINGS GENERAL DESCRIPTION A. PURPOSE: The Owner,, is a Tax Exempt Instrumentality of the State of Alabama. As such, it is authorized to and desires to enter

More information

ConsensusDocs 750 vs. AIA A : Which is Best For You?

ConsensusDocs 750 vs. AIA A : Which is Best For You? ConsensusDocs 750 vs. AIA A401 2007: Which is Best For You? Presented for the AGC NE Building Chapter by Kory George and Brian Koerwitz Woods & Aitken LLP Omaha, Lincoln, Denver, Washington D.C. kgeorge@woodsaitken.com

More information