SECTION SUPPLEMENTARY CONDITIONS

Size: px
Start display at page:

Download "SECTION SUPPLEMENTARY CONDITIONS"

Transcription

1 SECTION SUPPLEMENTARY CONDITIONS PART 1 GENERAL 1.01 GENERAL CONDITIONS A. The Supplementary Conditions modify, delete and/or add to the General Conditions, AIA Document A201/Cma, Construction Management Edition, 1992 Edition, Articles 1 through 14, are hereby incorporated as the General Conditions of this Contract. Where any Article, paragraph, or subparagraph in the General Conditions is supplemented by one of the following paragraphs, the provisions of such Article, paragraph, or subparagraph shall remain in effect and the supplemental provisions shall be considered as added thereto. Where any Article, paragraph, or subparagraph in the General Conditions is not supplemented, amended, voided or superseded by any of the following paragraphs, the provisions of such Article, paragraph or subparagraph not so amended, voided or superseded shall remain in effect. Amendments are as follows: 1.02 INCONSISTENCY A. Add the following to Subparagraph 1.2.3: If there is an inconsistency in the quality or quantity of Work required by the Contract Documents, either the greater quality or quantity of Work indicated shall be provided in accordance with the Architect s interpretation, and no change in the Contract Sum will be permitted STANDARD SPECIFICATIONS A. Add the following to Paragraph 1.2: Where a reference in the Contract Documents to a Federal Specification, American National Standards Institute standard, American Society of Testing Materials standard or other standard, the edition and amendments current as of the date of this Project Manual shall apply. However, no provision of a referenced standard, manual, code shall change the duties and responsibilities of the Owner, Architect, Construction Manager or Contractor from those set for in the Contract Documents ADMINISTRATION OF THE CONTRACT A. Add the following to Paragraph 2.2: The duties, responsibilities and limitations of authority of the Architect and the Construction Manager as the Owner s representatives during construction as set forth in the Contract Documents will not be modified or extended without written consent of the Owner and the Architect or the Owner and the Construction Manager, as applicable, which will be shown to the Contract OVERTIME WORK A. Add the following to Subparagraph 3.4: If the Contract Documents require work to be performed after regular working hours or if the Contractor elects to perform work after regular working hours, the additional cost of such work shall borne by the Contractor Construction Issue 1 Supplementary Conditions

2 1.06 SUBSTITUTIONS A. Add the following to Paragraph 3.5: The Contractor shall be responsible for the costs of additional work and changes required to incorporate substitute materials, product or equipment approved during the bidding period into the Project including all such work and changes performed under other contracts Each material, product or item of equipment shall be of the same manufacture throughout the Project, unless otherwise specified Substitutions made without written approval may be subject to removal and replacement with approved materials and equipment at the Contractor s expense, including all associated expenses CUTTING AND PATCHING OF WORK A. Change Subparagraph to read as follows: The Contractor shall be responsible for all cutting, fitting, and patching of materials normally included as part of his work that may be required to complete the Work or make its several parts fit together properly, except as otherwise specifically provided in the Contract Documents. Where cutting and patching is required to surrounding areas and materials not normally part of the Contractor s Work, this cutting and patching shall be the responsibility of other respective Contractors. Similarly, if the work of other Contractor s requires cutting and patching of this Contractor s materials, then this Contractor shall be responsible. B. Add the following to Paragraph Cutting shall be accurately located and neatly done. Unnecessary cutting should be avoided Patching shall be done by skilled mechanics experienced in the particular type of work involved. Patching work shall conform to the standards of the Specifications where applicable, and where not specified, work shall conform to the highest standards of the trade. Finished patching work shall be acceptable to the contractor whose work has been patched The Contractor shall leave all holes, chases and other openings in his Work required by other separate contractors for the installation of their work, provided such openings are accurately located by the party requiring them before the execution of the Contractor s Work. The Contractor shall afford other separate contractors a reasonable opportunity to locate such openings VERIFICATION OF FIELD CONDITIONS A. Add the followings to Article 3: 3.19 VERIFICATION OF FIELD CONDITIONS The Contractor shall take field measurements and verify field conditions and shall carefully compare such field measurements and conditions with the Contract Documents and any Shop Drawings and Product Data before commencing any Work. Any error, inconsistency or omission shall be reported to the Architect at once No change in the Contact Sum will be allowed an account of minor differences between actual field conditions and the Contract Documents Construction Issue 2 Supplementary Conditions

3 1.09 AWARDS OF SUBCONTRACTS AND OTHER CONTRACTS FOR PORTIONS OF WORK A. Add the following to Paragraph 5.2: The Contractor s responsibility to furnish materials, products and equipment in conformance with the requirements of the Contract Documents shall no be changed or limited by the Owner s or Architects lack of reasonable objection to any selected Subcontractor, person or entity PERFORMANCE AND PAYMENT BONDS A. Add the following to paragraph 11.4: The Owner reserves the right to require Performance on L & M Payment Bonds from any Contractor. Do not include costs for these bonds in any bid proposal TESTS A. Delete the last sentence of Subparagraph and add the following:.1 Where proof of compliance with the requirements of Contract Documents such as manufacturer s certificates, manufacturer s tests, independent laboratory tests and inspections and other data is required by the Contract Documents before materials, products or equipment may be used in the Work, the Contractor shall bear all costs for such certificates, tests, inspections, and other data..2 Where preliminary tests and inspections for design purposes such as concrete mix designs are required by the Contract Documents, the Contractor shall bear all costs for such tests and inpections..3 The Owner will pay for all other laboratory tests, inspections, and approvals required by the Contract Documents. The Owner will select an independent testing agency to perform such tests, inspections, and approvals. The Contractor, at his expense, shall furnish all samples and materials to be tested, and deliver the samples and materials to the testing agency. B. Delete the last sentence to Subparagraph and substitute the following: The Cost of such special inspection, testing or approval shall be paid as provided in Subparagraph C. Delete Subparagraph , and substitute the following: Reports of tests, inspections and approvals performed by the independent testing agency selected by the Owner in accordance with Clause shall be submitted to the Architect, the Construction Manager and the Contractor and promptly delivered by him to the Construction Manager. D. Add the following to paragraph 13.5: The Contractor shall make all arrangements, furnish all samples and materials to be tested, and do all related work necessary for the inspections, tests and approvals required under Subparagraphs and If after the commencement of the Work the Architect determines that any of the Work requires special inspection, testing or approval which Subparagraph does not included, he may, upon written authorization from the Owner, in lieu of the procedure specified in Subparagraph , secure the services of an independent testing agency to perform such tests, inspections and approvals. The Contractor, at his expense, shall make all arrangements, furnish all samples and materials to be tested, and deliver the samples and materials to the testing agency. Reports of such tests, inspections and approvals shall be submitted to the Architect, the Construction Manager and the Contractor. The Contractor or the Onwer shall bear the costs of such tests as provided in Subparagraph Construction Issue 3 Supplementary Conditions

4 1.12 USE OF OCCUPANCY PRIOR TO SUBSTANTIAL COMPLETION A. Add the following to Article 9: 9.11 USE OR OCCUPANCY PRIOR TO SUBSTANTIAL COMPLETION The Owner shall have the right to install his furnishings and equipment within the Project prior to substantial completion of the Work. Such installation shall not constitute occupancy or use by the Owner The Owner shall have the right to use or occupy the Project, or a portion thereof, prior to substantial completion of the Work under the following conditions:.1 The Owner shall give the Contractor at least ten days prior written notice of his intention to use or occupy the Project, or a portion thereof. Prior to use or occupancy, the Architect accompanied by the Owner and the Contractor shall agree in writing on their individual responsibilities for security, maintenance, heat, utilities, damage to the Work and insurance for the area to be used or occupied..2 The insurance company or companies providing the property insurance shall consent to the use of occupancy by endorsement prior to such use or occupancy..3 After occupancy, the Owner will allow the Contractor reasonable access to the occupied area to complete and correct the Work..4 Any claims for an adjustment in the Contract Sum or an extension of the Contract Time because of the Owner s occupancy shall be made in writing to the Architect through the Construction Manager prior to such use or occupancy..5 The Contractor shall not be held responsible for any damage to the occupied part of the Project resulting from the Owner s use or occupancy..6 Use or occupancy by the Owner shall not be deemed to constitute a waiver of existing claims in behalf of the Owner or Contractor against each other PROGRESS AND COMPLETION A. Add the following to Subparagraph 8.2.2: The progress of the work shall conform to the Project Construction Schedule prepared by the Construction Manager DAMAGES FOR DELAY A. Add the following to Article 8: 8.4 DAMAGES FOR DELAY The Contractor shall be responsible for damages incurred by the Owner and any separate contractors for delay resulting from the Contractor s failure to complete the Work within the Contract Time or resulting from the progress of the Work failing to conform to the Contractor s progress schedule CONTRACTOR S LIABILITY INSURANCE A. Add the following to Article 11: Worker s Compensation and Employer s Liability Insurance..1 Worker s Compensation insurance shall be as required by law and shall include an All States or Universal Endorsement Construction Issue 4 Supplementary Conditions

5 .2 Employer s Liability Insurance shall be written for not less that $100,000 each accident General Liability Insurance..1 General Liability Insurance shall be written on a Comprehensive General Liability form and shall include coverages for premises and operations, independent contractors, usual personal injury, completed operations, contractual and other coverage s indicated below. This insurance shall be written for not less than the following limits of liability: Bodily Injury Liability $1,000,000 each occurrence $1,000,000 aggregate Property Damage liability $1,000,000 each occurrence $1,000,000 aggregate Personal Injury Liability $1,000,000 each person aggregate $1,000,000 general aggregate.2 In lieu of liability for Bodily Injury Liability and Property Damage Liability required under Clause above, the insurance may be written for a single limit of liability for bodily injury and property damage of not less than $1,000,000 each occurrence/$1,000,000 aggregate. The aggregate limit shall apply only to Bodily Injury Liability under Completed Operations coverage and to Property Damage Liability..3 Property Damage Liability coverage shall include coverage for hazards of explosion, collapse and damage to underground property (XCU)..4 The policy shall include a Broad Form Property Damage Coverage Endorsement..5 Personal Injury Liability coverage shall provide coverage for Group A, B, and C offenses. The employment exclusion shall be deleted..6 Completed Operations coverage shall be maintained in effect during construction and for a period of not less that one year after the Date of Substantial Completion of the Work..7 Contractual Liability Insurance shall insure the Contractor s obligations under Paragraph 4.18 and shall conform to the requirements of Minnesota Statues Section Automobile Liability Insurance.1 Automobile Liability form and shall cover owned, non-owned and hire vehicles. This insurance shall be written for not less than the following limits of liability: Bodily Injury Liability Property Damage Liability $1,000,000 each person $1,000,000 each occurrence $1,000,000 each occurrence Public Liability Insurance shall be arranged either under Comprehensive General Liability and Comprehensive Automobile Liability policies written for the full limits Construction Issue 5 Supplementary Conditions

6 required under Subparagraphs and above, or a combination of underlying Comprehensive Liability policies written for lesser limits with the remaining limits provided by an Excess or Umbrella Liability policy. If an Excess or Umbrella Liability policy is used, the total limits provided shall be not less than the sum of the Bodily Injury Liability and the Property Damage Liability limits for one occurrence specified in Clause above The Contractor shall be responsible for all deductibles and retentions which may apply to any of the insurance coverage s required by this Paragraph All policies shall provide that the Insurance company shall give the Owner, the Architect, the Construction Manager, the Contractor, and any other named insured thirty days prior written notice of cancellation, non-renewal or any material change in the policy, and insurance certificates shall so state Subparagraphs through establish minimum insurance requirements, and it is the sole responsibility of the Contractor to purchase and maintain additional insurance that may be necessary in connection with the Work The Contractor shall not commence the Work until he has obtained the required insurance and such insurance has been approved by the Owner in writing..1 The Contractor shall submit the original and two duplicate copies of the Owners and Contractors Protective Liability Insurance policy to the construction Manager for the review and approval of the Owner..2 The Contractor shall submit three copies of Certificates of Insurance for all other coverage s to the construction Manager for the review and approval of the Owner. The certificates shall be on CICC Form 701, Rev. Jan or AIA Document G705, Nov Edition All policies shall be open to inspection by the Owner, and copiers of policies shall be submitted to the Owner upon written request PROPERTY INSURANCE A. Delete Paragraph 11.3, and substitute the following: The Owner shall purchase and maintain property insurance upon the entire Work at the site. This insurance shall be written by an insurance company satisfactory to the Contractor and any separate contractors. The insurance shall be written in an amount of not less than the total of the contract sums of all separate contractors The Insurance required by Subparagraph shall be written on a Builders Risk completed value basis form and shall provide Multiple Peril coverage. A Multiple peril Endorsement which provides coverage substantially equal to that provided by the St. Paul Insurance Companies Contractor s All Risk Form, Form 19622, Rev. 2-70, shall be added to the fire policy The policy may contain a deductible of not more than $1,000 which applies to each loss If payments are to be made for materials or equipment stored off the site or in a transit pursuant to Subparagraph , and such materials or equipment ar not covered by the property insurance obtained pursuant to this Paragraph 11.3, the Contractor shall effect and maintain similar property insurance on such material and equipment Construction Issue 6 Supplementary Conditions

7 Each separate contractor shall be responsible for any deductible which applies to loss of his work. Where a signal deductible applies to loss of the work of several separate contractors, the cost of the deductible shall be prorated among the separate contractors according to the proportionate loss of each contractor The Owner, the Architect, the Engineers and any other consultants, the Construction Manager, all separate contractors, by name, and all subcontractors categorically, shall be named insured Any insured loss shall be adjusted with the named insured and payable to the named insured, as their interests may appear, subject to the requirements of any applicable mortgage clause The policy shall be endorsed to permit occupancy of the premises by the Owner The policy shall be endorsed to specifically permit the waiver of subrogation specified in Subparagraph below The policy shall be endorsed to provide that the insurance company shall give the Owner, the Architect, the Construction Manager, the Contractors and any other named insured thirty days prior written notice of cancellation, non-renewal or any material change in the policy If the Contractor requests in writing that insurance for risks other than those described in Subparagraph or other special hazards be included in the property insurance policy, the Owner shall, if possible, include such insurance, and the cost thereof shall be charged to the Contractor by Change Order The Contractor shall not commence the Work until the Owner has obtained the property insurance required by this Paragraph 11.3 and such insurance has been approved by the contractor in writing. No other separate contractor shall commence his work until he has approved the insurance in writing..1 The Owner shall submit two complete copies of the property insurance policy plus one additional copy for each contractor to the Construction Manager for review and approval of the contractors..2 Upon approval, the Owner shall file a Memorandum of Insurance with each additional named insured If the Owner does not intend to purchase the property insurance required by this Paragraph 11.3, he shall inform the Architect and the Contractor in writing prior to commencement of the Work. The Contractor may then effect insurance which will protect the interests of himself, his Subcontractors and the Subsubcontractors in the Work, and by appropriate Change Order, the thereof shall be charged to the Owner. If the contractor is damaged by failure of the Owner to purchase or maintain such insurance and so to notify the Contractor, then the Owner shall bear all reasonable costs properly attributable thereto All policies shall be open to the inspection of the named insured, and certified copies of policies shall be furnished to any of the named insured at their requests Property Insurance shall be continuous, and the property insurance required by this Paragraph 11.3 shall not be permitted to lapse until the Owner has purchased permanent property insurance on the Project The Owner and the contractor waive all rights against (1) each other and the Subcontractors, Sub-subcontractors, agents and employees each of the other, and (2) the Architect, the Construction Manager and separate contractors, if any, and their subcontractors, sub-subcontractors, agents and employees, for damages caused by fire or other perils to the extent covered by insurance obtained pursuant to this Paragraph 11.3 or any other property insurance Construction Issue 7 Supplementary Conditions

8 applicable to the Work, except such rights as they may have to the proceeds of such insurance. Should the Owner upon terminating of the property insurance obtained pursuant to this Paragraph 11.3, neglect, fail or refuse to purchase and maintain permanent property insurance on the Project, the Owner waives all rights against the Contractor, separate contractors, if any, the Architect and their subcontractors, sub-subcontractors, agents and employees for damages to his properties from any perils insured under the terminated property insurance policy The Owner or the contractor, as appropriate, shall require of the Architect, the Construction Manager, separate contractors, Subcontractors and Sub-subcontractors by appropriate agreements, written where legally required for validity, waivers similar to those contained in Subparagraph , each in favor of all other parties enumerated in Subparagraph BOILER AND MACHINERY INSURANCE A. Add the following to Article 11: The Owner shall purchase and maintain such boiler and machinery insurance as may be required by the Contract Documents or by law. This insurance shall include the interests of the Owner and the Contractor, Subcontractors and Sub-subcontractors in the Work. The waiver of subrogation specified in Subparagraph above shall also apply to damages covered by this insurance CHANGES IN THE WORK A. Add the following to paragraph 7.1: The cost or credit to the Owner resulting for a Change in the Work shall be determined in one or more of the following ways..1 By mutual acceptance of a lump sum properly itemized and supported by sufficient substantiating data to permit evaluation. A lump sum for an increase in the Contract Sum may contain a reasonable allowance for overhead and profit. No allowance for overhead and profit will be allowed if the change results in a net decrease in cost. When both additions and credits covering related Work or substitutes are involved in any one change, the allowance for overhead and profit shall be figured on the basis of net increase, if any..2 By unit prices stated in the Contract Documents or subsequently agreed upon. Unit process shall cover all of the Contractor s costs for labor, materials, equipment and related services including such costs for subcontracted work, and the Contractor s overhead and profit..3 By cost to be determined in a manner agreed upon by the parties and a mutually acceptable fixed or percentage fee..4 By the method provided in Subparagraph and The cost of a change determined under the methods in Clauses and shall include all costs directly related to the change, and the Contractor shall itemize these cots and provide Construction Issue 8 Supplementary Conditions

9 appropriate supporting data as may be necessary to establish their correctness. All indirect costs whether incurred on or off site shall be included in the Contractor s overhead..6 In the case of Work authorized under Clauses and 7.1.5, a reasonable allowance for overhead profit shall not be more than ten percent (10%) of the net cost of Work accomplished by the Contractor s own forces and five percent (5%) of the cost of Work accomplished by Subcontractors. Subcontractors may add an allowance of not more than ten percent (10%) of the net cost of the Work accomplished by their own forces to cover their overhead and profit TERMINATION BY OWNER A. Change Subparagraph to read as follows: If the Contractor persistently or repeatedly refuses or fails, except in cases for which extension of time is provided, to supply enough properly skilled workmen or proper materials, or if he fails to make prompt payment to Subcontractors or for materials or labor, or persistently disregards laws, ordinances, rules, regulations or orders of any public authority having jurisdiction, or otherwise is guilty of a substantial breach of a provision, then the Owner, upon certification by the Architect that sufficient cause exists to justify such action, may, without prejudice to any right or remedy and after giving the Contractor and surety, if any, three (3) days written notice, terminate the employment of the materials, equipment, tools, construction equipment and machinery thereon owned by the Contractor and may finish the Work by whatever method he may deem expedient. END OF SECTION Construction Issue 9 Supplementary Conditions

DOCUMENT SUPPLEMENTARY CONDITIONS

DOCUMENT SUPPLEMENTARY CONDITIONS 1.1 GENERAL CONDITIONS DOCUMENT 007300 SUPPLEMENTARY CONDITIONS A. The Supplementary Conditions modify, delete and/or add to the General Conditions, AIA Document A201/Cma, Construction Management Edition,

More information

Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project

Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project Document A105 2007 Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project AGREEMENT made as of the in the year (In words, indicate day, month and year.) BETWEEN

More information

ARTICLE 1 ARTICLE 3 CONTRACTOR THE SUBCONTRACT DOCUMENTS ARTICLE 2 MUTUAL RIGHTS AND RESPONSIBILITIES

ARTICLE 1 ARTICLE 3 CONTRACTOR THE SUBCONTRACT DOCUMENTS ARTICLE 2 MUTUAL RIGHTS AND RESPONSIBILITIES ARTICLE 1 THE SUBCONTRACT DOCUMENTS 1.1 The Subcontract Documents consist of (1) this Agreement; (2) the prime Contract, consisting of the Agreement between the Owner and Contractor and the other Contract

More information

ADDENDUM TO STANDARD FORM OF AGREEMENT BETWEEN OWNER AND CONTRACTOR FOR A RESIDENTIAL OR SMALL COMMERCIAL PROJECT AIA DOCUMENT A

ADDENDUM TO STANDARD FORM OF AGREEMENT BETWEEN OWNER AND CONTRACTOR FOR A RESIDENTIAL OR SMALL COMMERCIAL PROJECT AIA DOCUMENT A ADDENDUM TO STANDARD FORM OF AGREEMENT BETWEEN OWNER AND CONTRACTOR FOR A RESIDENTIAL OR SMALL COMMERCIAL PROJECT AIA DOCUMENT A105-2007 The following addendum modifies or supplements the standard form

More information

TERREBONNE PARISH CONSOLIDATED GOVERNMENT INSURANCE REQUIREMENTS CONTRACTORS

TERREBONNE PARISH CONSOLIDATED GOVERNMENT INSURANCE REQUIREMENTS CONTRACTORS TERREBONNE PARISH CONSOLIDATED GOVERNMENT INSURANCE REQUIREMENTS CONTRACTORS ARTICLE 5- Bonds and Insurance 5.1 PERFORMANCE AND OTHER BONDS: 5.1.1 CONTRACTOR shall furnish performance and payment Bonds,

More information

5.0 TERREBONNE PARISH CONSOLIDATED GOVERNMENT, DEFINED.

5.0 TERREBONNE PARISH CONSOLIDATED GOVERNMENT, DEFINED. ARTICLE 5 - Bonds and Insurance 5.0 TERREBONNE PARISH CONSOLIDATED GOVERNMENT, DEFINED. For the purposes of this Article, the terms Terrebonne Parish Consolidated Government, TPCG, and OWNER shall include,

More information

Subcontract Agreement

Subcontract Agreement S THIS AGREEMENT made as of the day of, 2012 BETWEEN the Contractor: TCL Partners 5212 123 rd Place SE Everett, WA 98208 and the For the Following Project: The Architect for the Project: The Contractor

More information

AIA Document A201 TM 1997

AIA Document A201 TM 1997 AIA Document A201 TM 1997 General Conditions of the Contract for Construction for the following PROJECT: (Name and location or address): Project University of Maine at Farmington THE OWNER: (Name and address):

More information

SUPPLEMENTARY AND SPECIAL TERMS AND CONDITIONS FOR MINOR PROJECTS

SUPPLEMENTARY AND SPECIAL TERMS AND CONDITIONS FOR MINOR PROJECTS SUPPLEMENTARY AND SPECIAL TERMS AND CONDITIONS FOR MINOR PROJECTS HCPS STANDARDS DOC. No.: 01015 APPLICATION: ELEMENTARY, MIDDLE AND HIGH SCHOOL DATE OF ISSUE: 04-04-14 - Revised paragraph 13.10.1 to increase

More information

Amount of Contract work per the plans and specifications for project. Specifications Attached. Plans Attached

Amount of Contract work per the plans and specifications for project. Specifications Attached. Plans Attached Sample Company 2005 XXXX Main St Anywhere CA 99999 800 555-5555 SUBCONTRACT Contract#: 921 Contract Date: 08/20/2008 SUBCONTRACTOR: Baxter Heating & Cooling 4320 Eucalyptus Way Santa Rosa CA 95401 PROJECT:

More information

AIA Document A201 TM 1997

AIA Document A201 TM 1997 AIA Document A201 TM 1997 General Conditions of the Contract for Construction for the following PROJECT: (Name and location or address): A201 conversion Michigan State University East Lansing, MI THE OWNER:

More information

(I) (We) understand that any alteration/strike out of the Contract/Bidding Requirements or Special Provisions pages will void my bid.

(I) (We) understand that any alteration/strike out of the Contract/Bidding Requirements or Special Provisions pages will void my bid. To the Board of County Commissioners of Olmsted County, Minnesota: Bidders: In accordance with the advertisement of Olmsted County inviting proposals for the furnishing and application of dust control

More information

ANNEX A Standard Special Conditions For The Salvation Army

ANNEX A Standard Special Conditions For The Salvation Army ANNEX A Standard Special Conditions For The Salvation Army TO BE ATTACHED TO AIA B101-2007 EDITION ABBREVIATED STANDARD FORM OF AGREEMENT BETWEEN OWNER AND ARCHITECT 1. Contract Documents. This Annex supplements,

More information

Standard Form of Agreement Between Contractor and Subcontractor

Standard Form of Agreement Between Contractor and Subcontractor Standard Form of Agreement Between Contractor and Subcontractor GENERAL TERMS AND CONDITIONS ARTICLE 1 THE SUBCONTRACT DOCUMENTS 1.1 The Subcontract Documents consist of (1) these General Terms and Conditions,

More information

STATE OF VERMONT STANDARD FORM. GENERAL CONDITIONS FOR F P R DESIGN BUILD CONTRACTS (March 2017)

STATE OF VERMONT STANDARD FORM. GENERAL CONDITIONS FOR F P R DESIGN BUILD CONTRACTS (March 2017) STATE OF VERMONT STANDARD FORM GENERAL CONDITIONS FOR F P R DESIGN BUILD CONTRACTS (March 2017) The following general conditions are for use with DESIGN BUILD construction contracts with the State of Vermont,

More information

SUBCONTRACTOR AGREEMENT

SUBCONTRACTOR AGREEMENT SUBCONTRACTOR AGREEMENT THIS AGREEMENT MADE THIS DAY OF IN THE YEAR OF 2016 (In words, indicate day, month and year) BETWEEN DeWitt & Associates, Inc. 1256 South Barnes Springfield, Missouri 65804 AND:

More information

INSURANCE EXHIBIT TO CONSTRUCTION AGREEMENT Insurance Requirements Owner Controlled Insurance Program

INSURANCE EXHIBIT TO CONSTRUCTION AGREEMENT Insurance Requirements Owner Controlled Insurance Program *THIS INSURANCE EXHIBIT IS SUBJECT TO FINAL UPDATE BASED ON QUOTE NEGOTIATIONS AND DECISION BY OWNER TO IMPLEMENT THE OCIP PROGRAM FOR THIS PROJECT IT IS BEING PROVIDED FOR INFORMATION ONLY, TO PROSPECTIVE

More information

Standard Form of Agreement Between Contractor and Subcontractor

Standard Form of Agreement Between Contractor and Subcontractor Document A401 2007 Standard Form of Agreement Between Contractor and Subcontractor AGREEMENT made as of the in the year (In words, indicate day, month and year.) day of BETWEEN the Contractor: (Name, legal

More information

SECTION AGREEMENT BETWEEN OWNER AND CONTRACTOR

SECTION AGREEMENT BETWEEN OWNER AND CONTRACTOR Montgomery County Public Schools Facilities Guide DIVISION 0 - CONDITIONS OF THE CONTRACT SECTION 00500 - AGREEMENT BETWEEN OWNER AND CONTRACTOR The provisions of the following Agreement Between Owner

More information

Document A201 TM. General Conditions of the Contract for Construction. (Name and location or address)

Document A201 TM. General Conditions of the Contract for Construction. (Name and location or address) Document A201 TM 2007 General Conditions of the Contract for Construction for the following PROJECT: (Name and location or address) THE OWNER: (Name, legal status and address) Case Western Reserve University

More information

SUPPLEMENTARY CONDITIONS

SUPPLEMENTARY CONDITIONS SUPPLEMENTARY CONDITIONS Instructions for Use The A.I.A. A201-1997, General Conditions of the Contract for Construction, with Additions and Deletions by Michigan State University, along with the Supplementary

More information

CONSTRUCTION CONTRACT EXAMPLE

CONSTRUCTION CONTRACT EXAMPLE P a g e 1 CONSTRUCTION CONTRACT EXAMPLE THIS AGREEMENT, made and entered into this date, by and between, hereinafter called CONTRACTOR, and NPC QUALITY BURGER, INC., hereinafter called OWNER. IT IS HEREBY

More information

AIA Document A101 TM 2007

AIA Document A101 TM 2007 AIA Document A101 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum AGREEMENT made as of the day of in the year (In words, indicate day, month

More information

TERREBONNE PARISH CONSOLIDATED GOVERNMENT MINIMUM INSURANCE REQUIREMENTS PROFESSIONAL SERVICES (ARCHITECTS, ENGINEERS, CONSULTANTS, ETC.

TERREBONNE PARISH CONSOLIDATED GOVERNMENT MINIMUM INSURANCE REQUIREMENTS PROFESSIONAL SERVICES (ARCHITECTS, ENGINEERS, CONSULTANTS, ETC. TERREBONNE PARISH CONSOLIDATED GOVERNMENT MINIMUM INSURANCE REQUIREMENTS PROFESSIONAL SERVICES (ARCHITECTS, ENGINEERS, CONSULTANTS, ETC.) STANDARD FORM OF AGREEMENT BETWEEN OWNER AND CONSULTANT FOR PROFESSIONAL

More information

Document A201 TM 2007 SP

Document A201 TM 2007 SP AIA Document A201 TM 2007 SP General Conditions of the Contract for Construction, for use on a Sustainable Project for the following PROJECT: (Name and location or address) THE OWNER: (Name, legal status

More information

SECTION SUPPLEMENTARY CONDITIONS A. APPLICATION

SECTION SUPPLEMENTARY CONDITIONS A. APPLICATION SECTION 00 73 13 SUPPLEMENTARY CONDITIONS A. APPLICATION 1. The Standard Form of Agreement of the American Institute of Architects, Document A101-2007, General Conditions of the Contract of the American

More information

Rail Owner Controlled Insurance Program Manual

Rail Owner Controlled Insurance Program Manual Rail Owner Controlled Insurance Program Manual Addendum No. 4 to June 2013 Edition (Updated 08-21-17) Update to Section 5 Enrolled and Excluded Contractor Required Coverage for Package P Contract Section

More information

3.1.2 The Contractor shall perform the Work in accordance with the Contract Documents.

3.1.2 The Contractor shall perform the Work in accordance with the Contract Documents. the portion of the Work affected by a material change. After the Owner furnishes the evidence, the Owner shall not materially vary such financial arrangements without prior notice to the Contractor. 2.2.2

More information

STANDARD FIXED PRICE AGREEMENT BETWEEN OWNER AND CONTRACTOR DRAFT

STANDARD FIXED PRICE AGREEMENT BETWEEN OWNER AND CONTRACTOR DRAFT STANDARD FIXED PRICE AGREEMENT BETWEEN OWNER AND CONTRACTOR This Agreement, made January 10, 2012 by and between Marion County, a political subdivision of the State of Florida, (hereinafter referred to

More information

APPENDIX B WASHINGTON SUBURBAN SANITARY COMMISSION PROCUREMENT OFFICE INSURANCE AND BONDING CONTRACT NO.

APPENDIX B WASHINGTON SUBURBAN SANITARY COMMISSION PROCUREMENT OFFICE INSURANCE AND BONDING CONTRACT NO. APPENDIX B WASHINGTON SUBURBAN SANITARY COMMISSION PROCUREMENT OFFICE INSURANCE AND BONDING CONTRACT NO. 1. INSURANCE REQUIREMENTS A. INSURANCE: The Contractor shall be required to maintain insurance for

More information

STANDARD SUBCONTRACT AGREEMENT FOR BUILDING CONSTRUCTION

STANDARD SUBCONTRACT AGREEMENT FOR BUILDING CONSTRUCTION STANDARD SUBCONTRACT AGREEMENT FOR BUILDING CONSTRUCTION THIS AGREEMENT made at Columbus, Ohio on by and between Lincoln Construction, Inc., hereinafter referred to as the Contractor, and, hereinafter

More information

2010 INSURANCE MANUAL

2010 INSURANCE MANUAL 2010 INSURANCE MANUAL All required insurance shall be in a form, amount, content and written by companies acceptable to the Georgia Department of Community Affairs (DCA). For identification purposes, all

More information

AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER PRE-CONSTRUCTION AND CONSTRUCTION SERVICES

AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER PRE-CONSTRUCTION AND CONSTRUCTION SERVICES AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER PRE-CONSTRUCTION AND CONSTRUCTION SERVICES AGREEMENT made by and between, hereinafter called the Owner, and SITESCOMMERCIAL, LLC 185 WIND CHIME COURT, SUITE

More information

ICSC CENTERBUILD CONFERENCE DECEMBER 2-5, 1998 ARIZONA BILTMORE PHOENIX, ARIZONA

ICSC CENTERBUILD CONFERENCE DECEMBER 2-5, 1998 ARIZONA BILTMORE PHOENIX, ARIZONA ICSC CENTERBUILD CONFERENCE DECEMBER 2-5, 1998 ARIZONA BILTMORE PHOENIX, ARIZONA A COMPARATIVE ANALYSIS OF THE 1997 CHANGES TO THE AIA GENERAL CONDITIONS TO THE CONTRACT FOR CONSTRUCTION (A201) STUART

More information

SUBCONTRACT (SHORT FORM)

SUBCONTRACT (SHORT FORM) SUBCONTRACTOR: PHONE SUBCONTRACT (SHORT FORM) PROJECT: LOCATION: This agreement is made and effective, by and between SUN CONSTRUCTION & FACILITY SERVICES, INC. (Contractor) and (Subcontractor) which are

More information

AIA Document A201 TM 2007

AIA Document A201 TM 2007 AIA Document A201 TM 2007 General Conditions of the Contract for Construction for the following PROJECT: (Name and location or address) THE OWNER: (Name and address) THE ARCHITECT: (Name and address) TABLE

More information

SUBCONTRACT CONSTRUCTION AGREEMENT

SUBCONTRACT CONSTRUCTION AGREEMENT SUBCONTRACT CONSTRUCTION AGREEMENT THIS SUBCONTRACT CONSTRUCTION AGREEMENT, made and executed this day of, 20, by and between SHERWOOD CONSTRUCTION, INC (hereinafter referred to as "Contractor"), and (hereinafter

More information

GENERAL CONDITIONS of the CONTRACT FOR CONSTRUCTION for the ARCHDIOCESE OF CHICAGO (2004 Archdiocese Edition)

GENERAL CONDITIONS of the CONTRACT FOR CONSTRUCTION for the ARCHDIOCESE OF CHICAGO (2004 Archdiocese Edition) GENERAL CONDITIONS of the CONTRACT FOR CONSTRUCTION for the ARCHDIOCESE OF CHICAGO (2004 Archdiocese Edition) TABLE OF CONTENTS ARTICLE 1...1 General Provision...1 1.1 Definitions...1 1.2 Execution, Correlation

More information

Document A Standard Form of Agreement Between Contractor and Subcontractor

Document A Standard Form of Agreement Between Contractor and Subcontractor Document A401 2017 Standard Form of Agreement Between Contractor and Subcontractor AGREEMENT made as of the day of in the year (In words, indicate day, month and year.) BETWEEN the Contractor: (Name, legal

More information

MASTER SUBCONTRACT AGREEMENT

MASTER SUBCONTRACT AGREEMENT Back s Construction, Inc. 1602 Front Street, Suite 100 San Diego, CA 92101 Phone: 619-713-2566 Fax: 619-713-0992 MASTER SUBCONTRACT AGREEMENT This subcontract made and entered into this Monday, January

More information

Document A SP General Conditions of the Contract for Construction, for use on a Sustainable Project, Construction Manager as Adviser Edition

Document A SP General Conditions of the Contract for Construction, for use on a Sustainable Project, Construction Manager as Adviser Edition Document A232 2009 SP General Conditions of the Contract for Construction, for use on a Sustainable Project, Construction Manager as Adviser Edition for the following PROJECT: (Name, and location or address)

More information

GENERAL CONDITIONS. of the CONTRACT FOR CONSTRUCTION. for the ARCHDIOCESE OF CHICAGO. for SOLE SOURCE CONTRACTS. (2004 Archdiocese Edition)

GENERAL CONDITIONS. of the CONTRACT FOR CONSTRUCTION. for the ARCHDIOCESE OF CHICAGO. for SOLE SOURCE CONTRACTS. (2004 Archdiocese Edition) Document #: 861154 GENERAL CONDITIONS of the CONTRACT FOR CONSTRUCTION for the ARCHDIOCESE OF CHICAGO for SOLE SOURCE CONTRACTS (2004 Archdiocese Edition) 86 Document #: 861161 TABLE OF CONTENTS ARTICLE

More information

Document A General Conditions of the Contract for Construction, Construction Manager as Adviser Edition

Document A General Conditions of the Contract for Construction, Construction Manager as Adviser Edition Document A232 2009 General Conditions of the Contract for Construction, Construction Manager as Adviser Edition for the following PROJECT: (Name, and location or address) THE CONSTRUCTION MANAGER: (Name,

More information

I N V I T A T I O N T O B I D B I D # DOOR AND WINDOW REPLACEMENT AT SOUTH PORTLAND SCHOOLS

I N V I T A T I O N T O B I D B I D # DOOR AND WINDOW REPLACEMENT AT SOUTH PORTLAND SCHOOLS I N V I T A T I O N T O B I D B I D # 1 0-17 FINANCE DEPARTMENT GREGORY N. L HEUREUX Finance Director KRISTIE BRADBURY Deputy Finance Director COLLEEN C. SELBERG Purchasing Agent DOOR AND WINDOW REPLACEMENT

More information

CITY AND COUNTY OF SAN FRANCISCO Port of San Francisco. Contract No Pier 23 Roof Repair. ADDENDUM No. 1 Issued: December 16, 2016

CITY AND COUNTY OF SAN FRANCISCO Port of San Francisco. Contract No Pier 23 Roof Repair. ADDENDUM No. 1 Issued: December 16, 2016 CITY AND COUNTY OF SAN FRANCISCO Port of San Francisco Contract No. 2784 Pier 23 Roof Repair ADDENDUM No. 1 Issued: December 16, 2016 The following clarifications, changes, additions or deletions are incorporated

More information

OGC-S Owner-Contractor Construction Agreement

OGC-S Owner-Contractor Construction Agreement Owner-Contractor Construction Agreement This agreement is entered into as of ( Effective Date ) between Lone Star College (the "College"), a public junior college pursuant to Section 130.004 of the Texas

More information

STANDARD FIXED PRICE AGREEMENT BETWEEN OWNER AND CONTRACTOR

STANDARD FIXED PRICE AGREEMENT BETWEEN OWNER AND CONTRACTOR STANDARD FIXED PRICE AGREEMENT BETWEEN OWNER AND CONTRACTOR This Agreement, made May 6, 2014 by and between Marion County, a political subdivision of the State of Florida, (hereinafter referred to as the

More information

ADVERTISEMENT FOR BIDS GRATIOT COMMUNITY AIRPORT MOWING SERVICES BID B. Mowing services for the Gratiot Community Airport

ADVERTISEMENT FOR BIDS GRATIOT COMMUNITY AIRPORT MOWING SERVICES BID B. Mowing services for the Gratiot Community Airport ADVERTISEMENT FOR BIDS GRATIOT COMMUNITY AIRPORT MOWING SERVICES BID B Sealed bids will be received by the Gratiot Community Airport at the City of Alma municipal office at 525 East Superior Street, P.O.

More information

MANITOBA HOUSING SUPPLEMENTAL CONDITIONS CONTRACT #: XXXX GENERAL

MANITOBA HOUSING SUPPLEMENTAL CONDITIONS CONTRACT #: XXXX GENERAL GENERAL 1. Stipulated Price Contract CCDC2-2008 2. CCDC2-2008 Supplemental Conditions The Construction Contract for this project is the standard Construction Document- CCDC2 2008, Stipulated Price Contract.

More information

AIA Document A105 TM 2017

AIA Document A105 TM 2017 AIA Document A105 TM 2017 Standard Short Form of Agreement Between Owner and Contractor AGREEMENT made as of the» day of in the year 2018» (In words, indicate day, month and year.) BETWEEN the Owner: (Name,

More information

Document A401 TM. Standard Form of Agreement Between Contractor and Subcontractor

Document A401 TM. Standard Form of Agreement Between Contractor and Subcontractor Document A401 TM 2007 Standard Form of Agreement Between Contractor and Subcontractor AGREEMENT made as of the day of in the year (In words, indicate day, month and year.) BETWEEN the Contractor: (Name,

More information

ROCHESTER SCHOOLS MODERNIZATION PROJECT PHASE 2b School Without Walls Commencement Academy INSURANCE REQUIREMENTS

ROCHESTER SCHOOLS MODERNIZATION PROJECT PHASE 2b School Without Walls Commencement Academy INSURANCE REQUIREMENTS INSURANCE REQUIREMENTS 00 73 16-1 SECTION 00 73 16 - INSURANCE REQUIREMENTS Contractor shall obtain at its own cost and expense all the insurance described below (the Required Insurance ) that will protect

More information

CCIP ADDENDUM. Blasting or any blasting operations;

CCIP ADDENDUM. Blasting or any blasting operations; CCIP ADDENDUM 1. Overview. The Contractor has arranged with Aon Risk Services South, Inc., (the CCIP Administrator ) to be insured under its Contractor Controlled Insurance Program ( CCIP ). The CCIP is

More information

General Conditions for Construction GCC201. Contract Type: Document No. for the following PROJECT: (Name and location or address) EXAMPLE

General Conditions for Construction GCC201. Contract Type: Document No. for the following PROJECT: (Name and location or address) EXAMPLE Page 1 of 37 for the following PROJECT: (Name and location or address) EXAMPLE THE OWNER: (Name and address) Example, THE ARCHITECT: (Name and address) TABLE OF ARTICLES 1 GENERAL PROVISIONS 2 OWNER 3

More information

W.E. O Neil Construction Co. of Arizona c/o (Project Coordinator) 4511 E. Kerby Avenue Phoenix, AZ Fax (480)

W.E. O Neil Construction Co. of Arizona c/o (Project Coordinator) 4511 E. Kerby Avenue Phoenix, AZ Fax (480) W.E. O NEIL CONSTRUCTION CO. OF ARIZONA INSURANCE REQUIREMENTS Project Name Project Address City, State Zip Subcontractor SHALL NOT COMMENCE WORK at the site until it has obtained and provided all insurance

More information

C R D A Capital Region Development Authority

C R D A Capital Region Development Authority C R D A Capital Region Development Authority 100 Columbus Boulevard Suite 500 Hartford, CT 06103-2819 Tel (860) 527-0100 Fax (860) 527-0133 www.crdact.net September 26, 2018 Addendum #3 Regional Market

More information

Bernards (Project Name) CCIP Insurance Manual

Bernards (Project Name) CCIP Insurance Manual Bernards (Project Name) CCIP Insurance Manual Policy Year: xxxx-xxxx Alliant Version 01 1 Table of Contents 1.1 INTRODUCTION... 3 1.2 Overview... 3 1.3 About this Manual... 4 2.0 PROJECT DIRECTORY... 5

More information

AIA Document A201 TM 2007

AIA Document A201 TM 2007 AIA Document A201 TM 2007 General Conditions of the Contract for Construction for the following PROJECT: (Name and location or address) Pre-Construction and Construction Management at Risk Services Lafayette

More information

AIA Document C196 TM 2008

AIA Document C196 TM 2008 AIA Document C196 TM 2008 Standard Form of Agreement Between Single Purpose Entity and Owner for Integrated Project Delivery AGREEMENT made as of the day of in the year (In words, indicate day, month and

More information

INSURANCE REQUIREMENTS FOR CONSTRUCTION PROJECTS Effective Date: April 23, 2018

INSURANCE REQUIREMENTS FOR CONSTRUCTION PROJECTS Effective Date: April 23, 2018 INSURANCE REQUIREMENTS FOR CONSTRUCTION PROJECTS Effective Date: April 23, 2018 The contract documents for each construction project will identify the standard specifications to be used for that specific

More information

EXHIBIT G. Insurance Requirements. [with CCIP]

EXHIBIT G. Insurance Requirements. [with CCIP] SECTION 1 GENERAL INSURANCE REQUIREMENTS EXHIBIT G Insurance Requirements [with CCIP] A. CCIP. Contractor has implemented a Contractor Controlled Insurance Program ( CCIP ) to furnish certain insurance

More information

Document A Standard Abbreviated Form of Agreement Between Owner and Contractor

Document A Standard Abbreviated Form of Agreement Between Owner and Contractor Document A104 2017 Standard Abbreviated Form of Agreement Between Owner and Contractor AGREEMENT made as of the day of in the year (In words, indicate day, month and year.) BETWEEN the Owner: (Name, legal

More information

Section IV - General Conditions

Section IV - General Conditions TABLE OF CONTENTS Article Number Title Page 0 Index to General Conditions 2 1 Definitions 6 2 Preliminary Matters 9 3 Contract Documents: Intent, Amending and Reuse 11 4 Availability of Lands: Physical

More information

Insurance Requirements for Contractors

Insurance Requirements for Contractors Insurance Requirements for Contractors I. CONTRACTOR S LIABILITY AND WORKERS COMPENSATION INSURANCE Contractor shall procure and maintain for the duration of the contract insurance against claims for injuries

More information

THE CONSTRUCTION MANAGEMENT ASSOCIATION OF AMERICA, INC. CMAA Document CMAR-2 (2013 Edition)

THE CONSTRUCTION MANAGEMENT ASSOCIATION OF AMERICA, INC. CMAA Document CMAR-2 (2013 Edition) THE CONSTRUCTION MANAGEMENT ASSOCIATION OF AMERICA, INC. CMAA Document CMAR-2 (2013 Edition) Standard Form of Contract Between Construction Manager and Contractor (Construction Manager At-Risk) This document

More information

AIA Document A201 TM 2007

AIA Document A201 TM 2007 AIA Document A201 TM 2007 General Conditions of the Contract for Construction for the following PROJECT: (Name and location or address) THE OWNER: (Name and address) THE ARCHITECT: (Name and address) TABLE

More information

Construction of the Leased Premises

Construction of the Leased Premises Construction of the Leased Premises Pre-Construction Requirements Construction Start The Tenant is required to commence construction no later than fourteen days after receipt by the Tenant of approved

More information

Document A401 TM. Standard Form of Agreement Between Contractor and Subcontractor

Document A401 TM. Standard Form of Agreement Between Contractor and Subcontractor Document A401 TM 2017 Standard Form of Agreement Between Contractor and Subcontractor AGREEMENT made as of the day of in the year (In words, indicate day, month and year.) BETWEEN the Contractor: (Name,

More information

CONTRACT AND GENERAL CONDITIONS BETWEEN OWNER AND CONTRACTOR (GUARANTEED MAXIMUM PRICE)

CONTRACT AND GENERAL CONDITIONS BETWEEN OWNER AND CONTRACTOR (GUARANTEED MAXIMUM PRICE) CONTRACT AND GENERAL CONDITIONS BETWEEN OWNER AND CONTRACTOR (GUARANTEED MAXIMUM PRICE) THIS AGREEMENT, effective this day of, 201, by and between hereinafter called the "Contractor, and, Vail Unified

More information

SAMPLE DOCUMENT SUBCONTRACT AGREEMENT

SAMPLE DOCUMENT SUBCONTRACT AGREEMENT SUBCONTRACT AGREEMENT THIS SUBCONTRACT, made this day of by and between (hereinafter "Contractor"), with an office and principal place of business at and (hereinafter "Subcontractor") with an office and

More information

Contractor for any and all liability, costs, expenses, fines, penalties, and attorney s fees resulting from its failure to perform such duties.

Contractor for any and all liability, costs, expenses, fines, penalties, and attorney s fees resulting from its failure to perform such duties. SUBCONTRACT AGREEMENT THIS SUBCONTRACT, made this day of, 20 by and between (hereinafter "Contractor"), with an office and principal place of business at and (hereinafter "Subcontractor") with an office

More information

EXHIBIT C CONSULTANT INSURANCE REQUIREMENTS SACRAMENTO AREA FLOOD CONTROL AGENCY

EXHIBIT C CONSULTANT INSURANCE REQUIREMENTS SACRAMENTO AREA FLOOD CONTROL AGENCY EXHIBIT C CONSULTANT INSURANCE REQUIREMENTS SACRAMENTO AREA FLOOD CONTROL AGENCY Revised: March 2016 INSURANCE REQUIREMENTS Without limiting Consultant s indemnification, Consultant shall procure and maintain

More information

SYRACUSE UNIVERSITY Contractor Insurance Requirements The Contractor shall provide, maintain and deliver during the term of this Agreement the following insurance with at least the minimum coverages and

More information

TOWN OF BURLINGTON PURCHASING DEPARTMENT New Four Stage Breathing Air Compressor Contract #17S

TOWN OF BURLINGTON PURCHASING DEPARTMENT New Four Stage Breathing Air Compressor Contract #17S TOWN OF BURLINGTON PURCHASING DEPARTMENT New Four Stage Breathing Air Compressor Contract #17S-220-0006 If this document is used to submit a bid then you must submit your contact information to Kate Moskos

More information

Document A201/CMa. General Conditions of the Contract for Construction where the Construction Manager is NOT a Constructor

Document A201/CMa. General Conditions of the Contract for Construction where the Construction Manager is NOT a Constructor TM Document A201CMa General Conditions of the Contract for Construction where the Construction Manager is NOT a Constructor 1992 for the following PROJECT: (Name and location or address): Interior Finish

More information

AIA Document A101 TM 2007

AIA Document A101 TM 2007 AIA Document A101 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum AGREEMENT made as of the day of in the year (In words, indicate day, month

More information

ConsensusDocs 751 STANDARD SHORT FORM AGREEMENT BETWEEN CONSTRUCTOR AND SUBCONTRACTOR

ConsensusDocs 751 STANDARD SHORT FORM AGREEMENT BETWEEN CONSTRUCTOR AND SUBCONTRACTOR ConsensusDocs 751 STANDARD SHORT FORM AGREEMENT BETWEEN CONSTRUCTOR AND SUBCONTRACTOR Job No. [ ] Subcontract No. [ ] This Agreement is made this [ ] day of [ ], [ ], by and between CONSTRUCTOR, L&L Builders

More information

AIA Document A107 TM 1997

AIA Document A107 TM 1997 AIA Document A107 TM 1997 Abbreviated Standard Form of Agreement Between Owner and Contractor for Construction Projects of Limited Scope where the basis of payment is a STIPULATED SUM AGREEMENT made as

More information

Document A201 TM. General Conditions of the Contract for Construction

Document A201 TM. General Conditions of the Contract for Construction Document A201 TM 2007 General Conditions of the Contract for Construction for the following PROJECT: (Name and location or address) THE OWNER: (Name, legal status and address) THE ARCHITECT: (Name, legal

More information

INDOOR BLEACHER SAFETY RAILS MANDATORY WALK-THRU ON MONDAY, MAY 16, 2016 AT 10:00 A.M. AT CENTRAL OFFICE ANNEX, 24 SCHOOL RD.

INDOOR BLEACHER SAFETY RAILS MANDATORY WALK-THRU ON MONDAY, MAY 16, 2016 AT 10:00 A.M. AT CENTRAL OFFICE ANNEX, 24 SCHOOL RD. SPECIFICATIONS AND BID FORMS FOR INDOOR BLEACHER SAFETY RAILS MANDATORY WALK-THRU ON MONDAY, MAY 16, 2016 AT 10:00 A.M. AT CENTRAL OFFICE ANNEX, 24 SCHOOL RD., WESTON, CT 06883 BID: #16-007- BOE Due on

More information

responsibility of Tenant and/or Construction Contractors or Construction Subcontractors to pay.

responsibility of Tenant and/or Construction Contractors or Construction Subcontractors to pay. responsibility of Tenant and/or Construction Contractors or Construction Subcontractors to pay. (h) Primary Coverage. For claims arising out of or relating to work on the Specific Project, Tenant s insurance

More information

OREGON STATE UNIVERSITY

OREGON STATE UNIVERSITY OREGON STATE UNIVERSITY SUPPLEMENTAL GENERAL CONDITIONS To The PUBLIC IMPROVEMENT GENERAL CONDITIONS Project Name: Magruder Hall Hospital Expansion & Renovation The following modify the November 1, 2016

More information

HVAC REPACEMENT. Construction Documents. Quitman County Schools Quitman County, Mississippi. Project Manual For. Project No

HVAC REPACEMENT. Construction Documents. Quitman County Schools Quitman County, Mississippi. Project Manual For. Project No Project Manual For HVAC REPACEMENT Quitman County Schools Project No. 16030 Construction Documents 28 April 2016 One Jackson Place, Suite 250 188 East Capitol Street Jackson, Mississippi 39201 D B PN

More information

AGC TEXT COPY THE ASSOCIATED GENERAL CONTRACTORS OF AMERICA AGC DOCUMENT NO. 603 STANDARD SHORT FORM AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR

AGC TEXT COPY THE ASSOCIATED GENERAL CONTRACTORS OF AMERICA AGC DOCUMENT NO. 603 STANDARD SHORT FORM AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR THE ASSOCIATED GENERAL CONTRACTORS OF AMERICA AGC DOCUMENT NO. 603 STANDARD SHORT FORM AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR (Where Contractor Assumes Risk of Owner Payment) The original text

More information

Document A141 TM Exhibit B. Insurance and Bonds. for the following PROJECT: (Name and location or address)

Document A141 TM Exhibit B. Insurance and Bonds. for the following PROJECT: (Name and location or address) Insurance and Bonds Document A141 TM 2014 Exhibit B for the following PROJECT: (Name and location or address) Native Village of Eyak Community Health Center Repair Project P.O. Box 1388 Cordova, AK 99574

More information

Mailing address: P.O. Box, 9422, South Portland, ME Telephone (207) Fax (207)

Mailing address: P.O. Box, 9422, South Portland, ME Telephone (207) Fax (207) Page 1 of 9 Bid #10-18 Sealed bids for purchase of a replacement Sound System for the South Portland High School Auditorium, for the City of South Portland, Maine, as specified below, in the Specifications

More information

REQUEST FOR PROPOSALS (RFP) No. LHFC_RT2017_0818_3 BUILDING DEMOLITION SERVICES REQUEST FOR PROPOSALS FOR DEMOLITION SERVICES

REQUEST FOR PROPOSALS (RFP) No. LHFC_RT2017_0818_3 BUILDING DEMOLITION SERVICES REQUEST FOR PROPOSALS FOR DEMOLITION SERVICES REQUEST FOR PROPOSALS FOR DEMOLITION SERVICES Introduction and Preface The Laredo Housing Facilities Corporation (LHFC), a subsidiary of the Laredo Housing Authority (LHA), will receive sealed proposals

More information

MUSCOGEE (CREEK) NATION CHURCH & CEREMONIAL GROUND CAMP, CAMP HOUSE & FELLOWSHIP HALL GRANT PROGRAM APPLICATION CHECKLIST

MUSCOGEE (CREEK) NATION CHURCH & CEREMONIAL GROUND CAMP, CAMP HOUSE & FELLOWSHIP HALL GRANT PROGRAM APPLICATION CHECKLIST MUSCOGEE (CREEK) NATION CHURCH & CEREMONIAL GROUND CAMP, CAMP HOUSE & FELLOWSHIP HALL GRANT PROGRAM APPLICATION CHECKLIST D A letter from the Ceremonial Ground Mekko or Pastor stating the need for the

More information

AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER. Pre-Construction and Construction Phase Services

AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER. Pre-Construction and Construction Phase Services AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER Pre-Construction and Construction Phase Services FP&M Project No, CP00Error! Bookmark not defined. AGREEMENT made by and between the Board of Regents, State

More information

AIA Document A101 TM 2007

AIA Document A101 TM 2007 AIA Document A101 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum AGREEMENT made as of the day of in the year (In words, indicate day, month

More information

Insurance Requirements. The Bidder shall be required to procure, at its sole cost and expense, all insurance required by this Attachment.

Insurance Requirements. The Bidder shall be required to procure, at its sole cost and expense, all insurance required by this Attachment. GROUP 31503 BITUMINOUS CONCRETE HOT MIX ASPHALT VPP PAGE 1 of 7 Insurance Requirements The Bidder shall be required to procure, at its sole cost and expense, all insurance required by this Attachment.

More information

GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION

GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION Table of Contents Page Article 1. Definitions... 3 Article 2. Correlation, Interpretation and Intent of Contract Documents... 7 Article 3. Familiarity with Work, Conditions and Laws... 8 Article 4. Bonds...

More information

In September 2018, NCARB updated the ARE 5.0 Handbook to include 2017 AIA Contract Documents updates for the following documents:

In September 2018, NCARB updated the ARE 5.0 Handbook to include 2017 AIA Contract Documents updates for the following documents: In September 2018, NCARB updated the ARE 5.0 Handbook to include 2017 AIA Contract Documents updates for the following documents: A101-2017: Standard Form of Agreement Between Owner and Contractor where

More information

LEGAL ADVERTISEMENT CITY OF WINTER GARDEN REQUEST FOR QUALIFICATIONS (RFQ) RFQ #EN DESIGN CRITERIA PROFESSIONAL SERVICES

LEGAL ADVERTISEMENT CITY OF WINTER GARDEN REQUEST FOR QUALIFICATIONS (RFQ) RFQ #EN DESIGN CRITERIA PROFESSIONAL SERVICES LEGAL ADVERTISEMENT CITY OF WINTER GARDEN REQUEST FOR QUALIFICATIONS (RFQ) RFQ #EN13-004 DESIGN CRITERIA PROFESSIONAL SERVICES REQUEST FOR QUALIFICATIONS (RFQ) NO. EN13-004 FOR A DESIGN CRITERIA PROFESSIONAL

More information

Attachment I GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION

Attachment I GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION GENERAL CONDITIONS Attachment I GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION These General Conditions, the Supplementary Conditions and Special or other Conditions made part of this specifications

More information

General Contract Comments The contract s Insurance Requirements should include the following terms or similar wording: It is understood and agreed tha

General Contract Comments The contract s Insurance Requirements should include the following terms or similar wording: It is understood and agreed tha Contractual Risk Transfer/Hold Harmless/Indemnification Best Practices to Consider Many contractors require other contractors and subcontractors with whom they work to sign written job contracts. However,

More information

University of Maine System Supplementary Conditions to AIA A General Conditions of the Contract for Construction

University of Maine System Supplementary Conditions to AIA A General Conditions of the Contract for Construction University of Maine System Supplementary Conditions to AIA A201 2007 General Conditions of the Contract for Construction 1.1.8 Add the following: The Architect is the Initial Decision Maker for this Agreement.

More information

SMALL ORDERS TERMS AND CONDITIONS - BLANKET

SMALL ORDERS TERMS AND CONDITIONS - BLANKET 1. COMPLIANCE WITH LAWS Contractor must observe and comply with all applicable federal, state, county and municipal laws, statutes, regulations, codes, ordinances and executive orders, in effect now or

More information

WESTERN RIVERSIDE COUNCIL OF GOVERNMENTS EQUIPMENT PURCHASE AGREEMENT

WESTERN RIVERSIDE COUNCIL OF GOVERNMENTS EQUIPMENT PURCHASE AGREEMENT WESTERN RIVERSIDE COUNCIL OF GOVERNMENTS EQUIPMENT PURCHASE AGREEMENT This Equipment Purchase Agreement ( Agreement ) is entered into this day of, 20, by and between the Western Riverside Council of Governments,

More information

GENERAL CONDITIONS OF THE CONTRACT FOR NON-CONSTRUCTION

GENERAL CONDITIONS OF THE CONTRACT FOR NON-CONSTRUCTION GENERAL CONDITIONS OF THE CONTRACT FOR NON-CONSTRUCTION ---------------------------ARTICLE 1 --------------------------- GENERAL PROVISIONS 1.1 Governing Law: The Contract shall be governed by the law

More information