ATTACHMENT E BILLING PROCEDURES
|
|
- Emily Tyler
- 5 years ago
- Views:
Transcription
1 Job Name Job Location SWINERTON Job No. IF CHECKED, TEXTURA IS NOT USED ON THIS PROJECT A. Progress Payments ATTACHMENT E BILLING PROCEDURES All billings for work performed during the period of the 1st day of the month to the last day of the same month shall be made by the: 25 th of the current month (Textura is used on the Project). 20 th of the current month (Textura is NOT used on the Project). Unless otherwise directed or authorized, in writing by SWINERTON, all applications for payment and supporting documents, (including but not limited to lien releases, sworn statements, and the like) for Subcontractor, shall be in electronic format and shall be submitted to SWINERTON using the Textura payment management system prescribed by Contractor. Subcontractor shall be responsible for the fees and costs owed associated with Subcontractor s use of the Textura payment management system, and is responsible for confirming with Textura the costs that will be associated with billing for this Project. Textura can be reached at (866) or visit the website at If Textura is NOT used on the Project, all applications for payment and supporting documents for Subcontractor, shall be submitted electronically to NO OTHER FORM OF PAYMENT REQUEST WILL BE ACCEPTED. Payment requests received after the due date will be processed the following pay period. (See also Terms and Conditions Section 6(c). B. Lien Release The following lien releases will be required: a. Conditional Waiver and Release Upon Progress Payment form provided by Textura, or if Textura is not being used, in the format provided in Exhibit E-2, is to be submitted with each progress payment request except for the final request. b. Unconditional Waiver and Release Upon Progress Payment form provided by Textura, or if Textura is not being used, in the format provided in Exhibit E-3, is to be submitted after receipt of each progress payment except for the final payment. c. Conditional Waiver and Release Upon Final Payment form provided by Textura, or if Textura is not being used, in the format provided in Exhibit E-4, and Guarantee and Warranty form provided by Textura, or if Textura is not being, used in the format provided in Exhibit E-6, are to be submitted with the final payment request. d. Unconditional Waiver and Release Upon Final Payment form provided by Textura, or if Textura is not being used, in the format provided in Exhibit E-5, is to be submitted upon receipt of final payment. e. Sworn Statement of Subcontractor form provided by Textura, or if Textura is not being used, in the format provided in Exhibit E-1. Attachment E Billing Procedures Page 1 of 17 REV 01/12
2 Job Name Job Location SWINERTON Job No. NOTES: Textura currently requires that Unconditional Releases be provided PRIOR to release of payment to Subcontractor. IT IS UNDERSTOOD THAT A CONDITION PRECEDENT TO ANY UNCONDITIONAL WAIVER AND RELEASE ACTUALLY BECOMING EFFECTIVE IS THE ACTUAL PAYMENT OF THE FUNDS THAT ARE SUBJECT OF ANY SUCH UNCONDITIONAL WAIVER AND RELEASE TO SUBCONTRACTOR, AND THAT UNTIL THEN THE UNCONDITIONAL WAIVER AND RELEASE IS ESSENTIALLY BEING HELD IN TRUST BY TEXTURA. IF CONTRACTOR DOES NOT ACTUALLY MAKE THE SUBJECT PAYMENT TO SUBCONTRACTOR THEN THE UNCONDITIONAL WAIVER AND RELEASE SHALL BE INEFFECTIVE. C. Retention Prior to release of final payment to Subcontractor, Unconditional Waiver and Release Upon Final Payment lien release must be submitted for all sub-subcontractors and suppliers. An amount equivalent to ten percent (10%) of the amount shown to be due the Subcontractor on each estimate shall be withheld from the progress of the work. The Subcontractor s percent of retention will be reduced equivalent to any reduction received by the Contractor from the Owner. D. Contract Cost Breakdown 1. A Subcontract Schedule of Values, in a form directed by contractor, is to be completed electronically using the Textura payment management system proscribed by SWINERTON, or by hardcopy if Textura is not being used on the Project. 2. A Line Item titled Close-out is to be included and carry a value of 5% of the subcontract amount. A Line Item titled Record Document is to be included and carry a value of 5% of the subcontract amount. Subcontractor is to submit proposed format for Owner and SWINERTON acceptance no later than one month prior to first Progress Payment Request. Insurance and Bonds Payments cannot be made to Subcontractor unless properly executed Insurance Certificate, and Payment and Performance Bonds (if applicable) have been submitted on SWINERTON standard forms and have been kept current and in good standing. See Attachment A of the Subcontract Agreement, and also Terms and Conditions Sections 6, 8 and 9. E. Stored Materials Payment of stored materials will be considered on an individual basis and is subject to Owner s approval. Payment for materials not stored at the jobsite will be considered if request is accompanied by evidence of insurance and bonding. Furnish copies of shipping tags for stored materials as back up to the amount of your request. SWINERTON may choose to inspect the stored materials as a payment review step. The Subcontractor will be reimbursed for the value of the stored material only with no profit mark-up. The Owner is paying for an installed product and therefore will only recognize profit once the material is installed. See also Terms and Conditions Section 6(e). Attachment E Billing Procedures Page 2 of 17 REV 01/12
3 Job Name Job Location SWINERTON Job No. F. Affidavit of Subcontractor (included with this Attachment E) Each month an Affidavit of Subcontractor form must be filled out completely describing on whose behalf request for payment is being made. This form is to be filled out and signed with each Progress Payment. Attachment E Billing Procedures Page 3 of 17 REV 01/12
4 BLI# PROGRESS PAYMENT REQUEST To: SWINERTON Billing Date: Job Name: Location: Subcontract No.: From: Vendor No.: Subcontractor s Job No.: Subcontractor s App. No.: - # (Project Number Pay App #) CONTRACT INFORMATION Base Contract Amount: $ SWINERTON Issued Change Order(s) through No. : $ Total Contract to Date: $ BILLING INFORMATION This billing is for materials and/or work performed through:, 20. Base Contract: $ % cpt $ SWINERTON Change Order #1: $ % cpt $ SWINERTON Change Order #2: $ % cpt $ SWINERTON Change Order #3: $ % cpt $ SWINERTON Change Order #4: $ % cpt $ SWINERTON Change Order #5: $ % cpt $ SWINERTON Change Order #6: $ % cpt $ SWINERTON Change Order #7: $ % cpt $ SWINERTON Change Order #8: $ % cpt $ Continuation Sheet: $ % cpt $ TOTALS: Contract: $ % cpt Billing: $ These values must match SWINERTONUse Only: Approvals: Superintendent Project Manager Billing # Less: 10 % Retention Less: Prior Billings (NET): Total Due This Request: $ $ $ IMPORTANT: The Conditional Waiver & Release Upon Progress Payment must be signed and attached.
5 BLI# PROGRESS PAYMENT REQUEST CHANGE ORDER CONTINUATION SHEET To: SWINERTON Billing Date: Job Name: From: Billing Period.: (Subcontractor Name) TOTALS: Contract: $ % cpt Billing: $
6 CONTINUATION SHEET AIA DOUCMENT G703 PAGE OF PAGE AIA Document G702, APPLICATION AND CERTIFICATION FOR PAYMENT, containing APPLICATION NO: Contractor s signed certification is attached. APPLICATION DATE: In tabulations below, amounts are stated to the nearest dollar. PERIOD TO: Use Column I on Contracts where variable retainage for line items may apply. ARCHITECT S PROJECT NO: A B C D E F G H I ITEM NO. DESCRIPTION OF WORK SCHEDULED VALUE WORK COMPLETED FROM PREVIOUS APPLICATION (D + E) THIS PERIOD MATERIALS PRESENTLY STORED (NOT IN D OR E) TOTAL COMPLETED AND STORED TO DATE (D+E+F) % (G C) BALANCE TO (C G) RETAINAGE (IF VARIABLE RATE) GRAND TOTALS User may obtain validation of this document by requesting of the license a completed AIA Document D401 Certification of Document s Authenticity AIA DOCUMENT G703 CONTINUATION SHEET FOR G EDITION AIA 1992 G
7 SWORN STATEMENT FOR CONTRACTOR AND SUBCONTRACTOR STATE OF COUNTY OF The Affiant, (name) says they are, (Title) of (subcontractor), and has the authority to sign this document, and that Subcontractor has a contract with SWINERTON the general contractor on the following described premises in said County, to wit: (Full Address) That as an inducement to Contractor to advance monies to Subcontractor, and with the knowledge that Contractor will rely upon the representations made herein, the undersigned certifies that (a) except as specifically set forth on Subcontractor Payment application, this application makes claim for payment for all work performed on the Project during the period for which payment is sought, there is no claim which is being omitted and applicant waives any right to make any claim for any additional compensation relating to the period unless an exception is noted at this time, and (b) the following listed firms and individuals are the only parties from whom Subcontractor has purchased materials, rented equipment, or subcontracted portions of Subcontractor s work on said project (or has commitments or intends to purchase, rent or subcontract) from the commencement of said project to the date of project completion: Name What For Contract Price Retention Previous Payments This Payment Balance Due (inc. retention) TOTALS Amount of Original Contract Work Completed to Date Extras to Contract Less % Retention Total Contract and Extras Total after % Retention Credits to Contract Net Previously Paid Adjusted Total Contract Balance to Become Due Dated: COMPANY: ADDRESS: [NOTARY SIGNATURE REQUIRED]
8 Project Name: Project # Contract No.: Application No: To Company: Application Date: From Company: Period To: Name What For Contract Price Retention Previous Payments This Payment Balance Due (inc. retention) TOTALS Exhibit E-1
9 BLI# CONDITIONAL WAIVER AND RELEASE UPON PROGRESS PAYMENT Civil Code Section 3262(d)(1) USE THIS FORM THROUGH JUNE 30, 2012 Upon receipt by the undersigned of a check from SWINERTON in the sum of $ (Check Amount) payable to (Name of Payee), and when the check has been properly endorsed and has been paid by the bank upon which it is drawn, this document shall become effective to release any mechanic s lien, stop notice, or bond right the undersigned has on the (Name of Project) job for (Project Owner) located at (Address of Project) to the following extent. This release covers a progress payment for labor, services, equipment, or material furnished to SWINERTON through (Date) only and does not cover any retentions retained before or after the release date; extras furnished before the release date for which payment has not been received; extras or items furnished after the release date. Rights based upon work performed or items furnished under a written change order which has been fully executed by the parties prior to the release date are covered by this release unless specifically reserved by the claimant in this release. This release of any mechanic's lien, stop notice, or bond right shall not otherwise affect the contract rights, including rights between parties to the contract based upon a rescission, abandonment, or breach of the contract, or the right of the undersigned to recover compensation for furnished labor, services, equipment, or material covered by this release if that furnished labor, services, equipment, or material was not compensated by the progress payment. Before any recipient of this document relies on it, said party should verify evidence of payment to the undersigned. Dated: (Company Name) (Signature) (Name) (Title) Exhibit E-2
10 BLI# UNCONDITIONAL WAIVER AND RELEASE UPON PROGRESS PAYMENT Civil Code Section 3262(d)(4) USE THIS FORM THROUGH JUNE 30, 2012 The undersigned has been paid and has received a progress payment in the sum of $ (Amount of Check) for labor, services, equipment or material furnished to SWINERTON on the (Name of Project) job for (Project Owner) located at (Address of Project) and does hereby release any mechanic's lien, stop notice or bond right that the undersigned has on the above referenced job to the following extent. This release covers a progress payment for labor, services, equipment, or material furnished to SWINERTON through (Date) only and does not cover any retentions retained before or after the release date; extras furnished before the release date for which payment has not been received; extras or items furnished after the release date. Rights based upon work performed or items furnished under a written change order which has been fully executed by the parties prior to the release date are covered by this release unless specifically reserved by the claimant in this release. This release of any mechanic's lien, stop notice, or bond right shall not otherwise affect the contract rights, including rights between parties to the contract based upon a rescission, abandonment, or breach of the contract, or the right of the undersigned to recover compensation for furnished labor, services, equipment, or material covered by this release if that furnished labor, services, equipment, or material was not compensated by the progress payment. Dated: (Company Name) (Signature) (Name) (Title) NOTICE: THIS DOCUMENT WAIVES RIGHTS UNCONDITIONALLY AND STATES THAT YOU HAVE BEEN PAID FOR GIVING UP THOSE RIGHTS. THIS DOCUMENT IS ENFORCEABLE AGAINST YOU IF YOU SIGN IT, EVEN IF YOU HAVE NOT BEEN PAID. IF YOU HAVE NOT BEEN PAID, USE A CONDITIONAL RELEASE FORM. Exhibit E-3
11 BLI# CONDITIONAL WAIVER AND RELEASE UPON FINAL PAYMENT Civil Code Section 3262(d)(3) USE THIS FORM THROUGH JUNE 30, 2012 Upon receipt by the undersigned of a check from SWINERTON in the sum of $ (Amount of Check) payable to (Name of Payee), and when the check has been properly endorsed and has been paid by the bank upon which it is drawn, this document shall become effective to release any mechanic s lien, stop notice, or bond right the undersigned has on the (Name of Project) job for (Project Owner) located at (Address of Project). This release covers the final payment to the undersigned for all labor, services, equipment, or material furnished on the job, except for disputed claims for additional work in the amount of $ (Amount of Outstanding Claim). Before any recipient of this document relies on it, the party should verify evidence of payment to the undersigned. Dated: (Company Name) (Signature) (Name) (Title) Exhibit E-4
12 BLI# UNCONDITIONAL WAIVER AND RELEASE UPON FINAL PAYMENT Civil Code Section 3262(d)(4) USE THIS FORM THROUGH JUNE 30, 2012 The undersigned has been paid in full for all labor, services, equipment or material furnished to SWINERTON on the (Name of Project) job for (Project Owner) located at (Address of Project), and does hereby waive and release any right to a mechanic s lien, stop notice, or any right against a labor and material bond on the job, except for disputed claims for extra work in the amount of $ (Amount of any outstanding Issues). Dated: (Company Name) (Signature) (Name) (Title) NOTICE: THIS DOCUMENT WAIVES RIGHTS UNCONDITIONALLY AND STATES THAT YOU HAVE BEEN PAID FOR GIVING UP THOSE RIGHTS. THIS DOCUMENT IS ENFORCEABLE AGAINST YOU IF YOU SIGN IT, EVEN IF YOU HAVE NOT BEEN PAID. IF YOU HAVE NOT BEEN PAID, USE A CONDITIONAL RELEASE FORM. Exhibit E-5
13 CONDITIONAL WAIVER AND RELEASE UPON PROGRESS PAYMENT [California Civil Code 8132] USE THIS FORM STARTING JULY 1, 2012 NOTICE: THIS DOCUMENT WAIVES THE CLAIMANT S LIEN, STOP PAYMENT NOTICE, AND PAYMENT BOND RIGHTS EFFECTIVE ON RECEIPT OF PAYMENT. A PERSON SHOULD NOT RELY ON THIS DOCUMENT UNLESS SATISFIED THAT THE CLAIMANT HAS RECEIVED PAYMENT. Identifying Information Name of Claimant: Name of Customer: Job Location: Owner: Through Date: Conditional Waiver and Release This document waives and releases lien, stop payment notice, and payment bond rights the claimant has for labor and service provided, and equipment and material delivered, to the customer on this job through the Through Date of this document. Rights based upon labor or service provided, or equipment or material delivered, pursuant to a written change order that has been fully executed by the parties prior to the date that this document is signed by the claimant are waived and released by this document, unless listed as an Exception below. This document is effective only on the claimant s receipt of payment from the financial institution on which the following check is drawn: Maker of Check: Amount of Check: $ Check Payable to: Exceptions This document does not affect any of the following: (1) Retentions. (2) Extras for which the claimant has not received payment. (3) The following progress payments for which the claimant has previously given a conditional waiver and release but has not received payment: Date(s) of waiver and release: Amount(s) of unpaid progress payment(s): $ (4) Contract rights, including (A) a right based on rescission, abandonment, or breach of contract, and (B) the right to recover compensation for work not compensated by the payment. Signature Claimant s Signature: Claimant s Title: Date of Signature: Exhibit E-2
14 UNCONDITIONAL WAIVER AND RELEASE UPON PROGRESS PAYMENT [California Civil Code 8134] USE THIS FORM STARTING JULY 1, 2012 NOTICE TO CLAIMANT: THIS DOCUMENT WAIVES AND RELEASES LIEN, STOP PAYMENT NOTICE, AND PAYMENT BOND RIGHTS UNCONDITIONALLY AND STATES THAT YOU HAVE BEEN PAID FOR GIVING UP THOSE RIGHTS. THIS DOCUMENT IS ENFORCEABLE AGAINST YOU IF YOU SIGN IT, EVEN IF YOU HAVE NOT BEEN PAID. IF YOU HAVE NOT BEEN PAID, USE A CONDITIONAL WAIVER AND RELEASE FORM. Identifying Information Name of Claimant: Name of Customer: Job Location: Owner: Through Date: Unconditional Waiver and Release This document waives and releases lien, stop payment notice, and payment bond rights the claimant has for labor and service provided, and equipment and material delivered, to the customer on this job through the Through Date of this document. Rights based upon labor or service provided, or equipment or material delivered, pursuant to a written change order that has been fully executed by the parties prior to the date that this document is signed by the claimant are waived and released by this document, unless listed as an Exception below. The claimant has received the following progress payment: $ Exceptions This document does not affect any of the following: (1) Retentions. (2) Extras for which the claimant has not received payment. (3) Contract rights, including (A) a right based on rescission, abandonment, or breach of contract, and (B) the right to recover compensation for work not compensated by the payment. Signature Claimant s Signature: Claimant s Title: Date of Signature: Exhibit E-3
15 CONDITIONAL WAIVER AND RELEASE ON FINAL PAYMENT [California Civil Code 8136] USE THIS FORM STARTING JULY 1, 2012 NOTICE: THIS DOCUMENT WAIVES THE CLAIMANT S LIEN, STOP PAYMENT NOTICE, AND PAYMENT BOND RIGHTS EFFECTIVE ON RECEIPT OF PAYMENT. A PERSON SHOULD NOT RELY ON THIS DOCUMENT UNLESS SATISFIED THAT THE CLAIMANT HAS RECEIVED PAYMENT. Identifying Information Name of Claimant: Name of Customer: Job Location: Owner: Conditional Waiver and Release This document waives and releases lien, stop payment notice, and payment bond rights the claimant has for labor and service provided, and equipment and material delivered, to the customer on this job. Rights based upon labor or service provided, or equipment or material delivered, pursuant to a written change order that has been fully executed by the parties prior to the date that this document is signed by the claimant are waived and released by this document, unless listed as an Exception below. This document is effective only on the claimant s receipt of payment from the financial institution on which the following check is drawn: Maker of Check: Amount of Check: $ Check Payable to: Exceptions This document does not affect any of the following: Disputed claims for extras in the amount of: $ Signature Claimant s Signature: Claimant s Title: Date of Signature: Exhibit E-4
16 UNCONDITIONAL WAIVER AND RELEASE ON FINAL PAYMENT [California Civil Code 8138] USE THIS FORM STARTING JULY 1, 2012 NOTICE TO CLAIMANT: THIS DOCUMENT WAIVES AND RELEASES LIEN, STOP PAYMENT NOTICE, AND PAYMENT BOND RIGHTS UNCONDITIONALLY AND STATES THAT YOU HAVE BEEN PAID FOR GIVING UP THOSE RIGHTS. THIS DOCUMENT IS ENFORCEABLE AGAINST YOU IF YOU SIGN IT, EVEN IF YOU HAVE NOT BEEN PAID. IF YOU HAVE NOT BEEN PAID, USE A CONDITIONAL WAIVER AND RELEASE FORM. Identifying Information Name of Claimant: Name of Customer: Job Location: Owner: Unconditional Waiver and Release This document waives and releases lien, stop payment notice, and payment bond rights the claimant has for labor and service provided, and equipment and material delivered, to the customer on this job. Rights based upon labor or service provided, or equipment or material delivered, pursuant to a written change order that has been fully executed by the parties prior to the date that this document is signed by the claimant are waived and released by this document, unless listed as an Exception below. The claimant has been paid in full. Exceptions This document does not affect any of the following: Disputed claims for extras in the amount of: $ Signature Claimant s Signature: Claimant s Title: Date of Signature: Exhibit E-5
17 GUARANTEE & WARRANTY The undersigned is a subcontractor, materialman and/or supplier on the project known as (Name of Project), located at (Address of Project) pursuant to Agreement with SWINERTON ( General Contractor ) dated, (date), Subcontract Agreement Number (Subcontract Number). The undersigned guarantees and warrants all materials and items furnished under this agreement to be in strict conformance with the Contract Documents and agrees to remove and replace any non-conforming items at his sole cost including, but not limited to, costs of correction, re-installation and repair of adjacent work effected by such corrective work. This Guarantee and Warranty is effective on the project s date of substantial completion, or such date as specified in the Contract Documents. This Guarantee and Warranty shall remain in effect for one year or longer as specified in the Contract Documents. The undersigned agrees to perform all guarantee/warranty work without any expenses whatever to the Owner or General Contractor, ordinary wear and tear, and unusual abuse and neglect excepted. In the event of failure to comply with the terms of this Guarantee and Warranty within ten (10) days after notified in writing by Owner or General contractor, the undersigned authorizes the Owner or General Contractor to proceed to have said non-conforming items repaired and made good at undersigned s expense. Undersigned will honor and pay costs and charges therefrom upon demand, including attorney s fees and costs of collection, if any. This Guaranty and Warranty shall be binding on the heirs, executors, successors and assigns of the undersigned. Start Date of Guarantee and Warranty: [ ] (Substantial Completion Date) Date: Company: Signed: Name: Title: Phone No.: License No.: Countersigned: Material Manufacturer Company: Signed: Name: Title: Phone No.: License No.: Exhibit E-6
State of: County of: Subscribed and sworn to before me this day of b. % of Stored Material $ 0.00
APPLICATION AND CERTIFICATION FOR PAYMENT 702 PAGE ONE OF PAGES TO OWNER: PROJECT: APPLICATION NO: 004(Retention) Distribution to: OWNER ARCHITECT PERIOD TO: 6/20/18 X CONTRACTOR FROM SUB-CONTRACTOR: VIA
More informationAC SUPPLY COMPANY, INC. TEXAS COMMERCIAL LIEN SEMINAR. Subcontractor and Sub-Subcontractor Forms. Private Commercial Construction Projects
AC SUPPLY COMPANY, INC. TEXAS COMMERCIAL LIEN SEMINAR Subcontractor and Sub-Subcontractor Forms Private Commercial Construction Projects Presented by: Bradley H. Rice DECKER, JONES P.C. 2000 Burnett Plaza
More informationSUBCONTRACTOR S APPLICATION FOR PAYMENT
SUBCONTRACTOR S APPLICATION FOR PAYMENT (Developed as a guide by The Associated General Contractors of America, The National Electrical Contractors Association, The Mechanical Contractors Association of
More informationSUBCONTRACTOR PAY APPLICATION REQUIREMENTS PLEASE PROVIDE A COPY OF THIS INFORMATION TO THE PERSON PREPARING YOUR INVOICES.
Exhibit A SUBCONTRACTOR PAY APPLICATION REQUIREMENTS PLEASE PROVIDE A COPY OF THIS INFORMATION TO THE PERSON PREPARING YOUR INVOICES. Subcontractor Pay Applications are typically to be prepared as of the
More informationCONSTRUCTION CONTRACT EXAMPLE
P a g e 1 CONSTRUCTION CONTRACT EXAMPLE THIS AGREEMENT, made and entered into this date, by and between, hereinafter called CONTRACTOR, and NPC QUALITY BURGER, INC., hereinafter called OWNER. IT IS HEREBY
More informationINTERIM WAIVER AND RELEASE UPON PAYMENT
EXHIBIT F STATE OF GEORGIA COUNTY OF INTERIM WAIVER AND RELEASE UPON PAYMENT THE UNDERSIGNED MECHANIC AND/OR MATERIALMAN, HAS BEEN EMPLOYED BY TO FURNISH FOR THE CONSTRUCTION OF IMPROVEMENTS KNOWN AS WHICH
More informationEXHIBIT P CONSULTANT S APPLICATION FOR PAYMENT *INSTRUCTION SHEET*
EXHIBIT P CONSULTANT S APPLICATION FOR PAYMENT *INSTRUCTION SHEET* **IMPORTANT** PLEASE REMOVE TOP PAGE BEFORE COMPLETING APPLICATION CONSULTANT NAME PROJECT NAME CONTRACT NUMBER As stated in the Agreement
More informationLIEN RELEASES. 2.5 A fill in the blanks fax is available at: F:\Design and Construction\Forms\Lien Fax for this purpose.
LIEN RELEASES 1.0 Philosophy 1.1 We need to protect RIT from contractor/supplier liens. 1.2 Articles 9.3.3 of the RIT General Conditions and Article 7.1.4 of the CM Agreement provide a method for this
More informationINTERIM WAIVER AND RELEASE UPON PAYMENT. The undersigned mechanic and/or materialman has been employed by Pattillo Construction
AL Form Subcontractor INTERIM WAIVER AND RELEASE UPON PAYMENT STATE OF ALABAMA COUNTY OF The undersigned mechanic and/or materialman has been employed by Pattillo Construction Corporation to furnish for
More informationREQUEST for CONTACT INFORMATION
REQUEST for CONTACT INFORMATION In an effort to insure appropriate communication, please fill out and return the following information to: ROBERT A. BOTHMAN, INC. Phone: (48) 279-2277 269 Scott Boulevard
More informationAIA Document G
1 AIA Document G702 1992 Application and Certificate for Payment TO OWNER: FROM CONTRACTOR: CONTRACTOR'S APPLICATION FOR PAYMENT Application is made for payment, as shown below, in connection with the
More informationStandard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project
Document A105 2007 Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project AGREEMENT made as of the in the year (In words, indicate day, month and year.) BETWEEN
More informationNEW AIR TRAFFIC CONTROL TOWER
DIVISION I NEW AIR TRAFFIC CONTROL TOWER CONSTRUCTION MANAGER AT RISK (CMAR) CONSTRUCTION SERVICES CONTRACT PROJECT NO. 927 TABLE OF CONTENTS ARTICLE PAGE ARTICLE 1 PARTICIPANTS AND PROJECT... 2 ARTICLE
More informationINSTRUCTIONS APPLICATION FOR PAYMENT
IMPORTANT: This form must be filled out in Microsoft Excel, printed, and then signed. Subcontractor must provide completed SubTier Releases (Interim or Final) WITH each monthly Application for Payment.
More informationUtah Preconstruction and Construction Lien Law
Utah Preconstruction and Construction Lien Law Chapter Survey What is a Lien? Who is Entitled to a Lien? State Construction Registry Program Notice of Retention Notice of Commencement Preliminary Notice
More informationCONSTRUCTION CONTRACT RIDER
CONSTRUCTION CONTRACT RIDER In connection with the work at, Massachusetts (the Development ) to be performed by (the Contractor ) pursuant to the Construction Contract dated, 20 between the Contractor
More informationRICE UNIVERSITY SHORT FORM CONTRACT
RICE UNIVERSITY SHORT FORM CONTRACT This Rice University Short Form Contract (this Contract ) is entered into by and between WILLIAM MARSH RICE UNIVERSITY, a Texas non-profit corporation (the University
More informationIMPERIAL CONSTRUCTION, INC. 400 Interstate 20 West, Suite 200 Weatherford, Texas Telephone: (817) Facsimile: (817)
IMPERIAL CONSTRUCTION, INC. 400 Interstate 20 West, Suite 200 Weatherford, Texas 76086 Telephone: (817) 341-8886 Facsimile: (817) 341-0191 WORK ORDER TO TEXAS SPECIFIC BLANKET AGREEMENT BETWEEN CONTRACTOR
More informationG E O R G I A P O R T S A U T H O R I T Y I N S U R A N C E R E Q U I R E M E N T S
Page 11 of 17 G E O R G I A P O R T S A U T H O R I T Y I N S U R A N C E R E Q U I R E M E N T S The contractor shall provide certificates of insurance in a form acceptable to the Georgia Ports Authority
More informationSUBCONTRACT AGREEMENT GENERAL TERMS AND CONDITIONS
Subcontract No: Date: SUBCONTRACT AGREEMENT Genoa Construction Services, Inc., a Georgia corporation ("Contractor"), hereby enters into this Subcontract Agreement ( Subcontract ) with NAME OF SUBCONTRACTOR,
More informationWelcome to the Model Residential Owner/Design Consultant Professional Service Agreement
Welcome to the Model Residential Owner/Design Consultant Professional Service Agreement The Council for the Construction Law Section of the Washington State Bar Association prepared this Model Residential
More informationCONTRACT. Owner and Contractor agree as follows: 1. Scope of Work.
CONTRACT This agreement (the "Contract") is made this day of, by and between (the "Contractor") and (name of parish corporation, ABN or high school corporation) (the "Owner"), for the purpose of stating
More informationSAFETY FIRST GRANT CONTRACT
SAFETY FIRST GRANT CONTRACT This agreement (the Contract ) is made this day of, by and between (the Contractor ) and (the Owner ), for the (Name of Parish Corporation, ABN or high school corporation) purpose
More informationWaiver & Releases for Subcontractors / Second Tier Subcontractors & Suppliers
THE ALBERT M. HIGLEY CO. 2926 CHESTER AVENUE CLEVELAND, OHIO 44114-4414 OFFICE: 216.861.2050 WWW.AMHIGLEY.COM Waiver & Releases for Subcontractors / Second Tier Subcontractors & Suppliers All subcontractor
More informationAGC TEXT COPY THE ASSOCIATED GENERAL CONTRACTORS OF AMERICA AGC DOCUMENT NO. 603 STANDARD SHORT FORM AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR
THE ASSOCIATED GENERAL CONTRACTORS OF AMERICA AGC DOCUMENT NO. 603 STANDARD SHORT FORM AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR (Where Contractor Assumes Risk of Owner Payment) The original text
More informationAIA Document A101 TM 2007
AIA Document A101 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum AGREEMENT made as of the day of in the year (In words, indicate day, month
More informationAIA Document A101 TM 2007
AIA Document A101 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum AS MODIFIED BY OWNER AGREEMENT made as of the day of in the year (In words,
More informationSECTION 8 - MEASUREMENT AND PAYMENT TABLE OF CONTENTS
SECTION 8 - MEASUREMENT AND PAYMENT TABLE OF CONTENTS Section Page 8-1 BASIS AND MEASUREMENT OF PAYMENT QUANTITIES... 8.1 8-1.01 Unit Price Contracts... 8.1 8-1.02 Lump Sum or Job Contracts... 8.1 8-1.03
More informationHOUSING CONSTRUCTION CONTRACT (Projects up to $10,000)
HOUSING CONSTRUCTION CONTRACT (Projects up to $10,000) THIS CONTRACT is by and between the Stockbridge-Munsee Community ( TRIBE ), for its Division of Community Housing, whose address is N8618 Oak St.,
More informationRECENT DEVELOPMENTS IN IDAHO S MECHANIC LIEN LAWS
RECENT DEVELOPMENTS IN IDAHO S MECHANIC LIEN LAWS C. Clayton Gill March 3, 2011 Idaho Land Title Association Education Seminar Moffatt Thomas OVERVIEW 1. Protecting Deeds of Trusts and Mortgages from Priority
More informationDEVELOPER EXTENSION AGREEMENT
DEVELOPER EXTENSION AGREEMENT SILVER LAKE WATER DISTRICT APPLICATION AND AGREEMENT TO CONSTRUCT EXTENSION TO DISTRICT SYSTEM Project: Developer: The undersigned, Developer (also referred to as Owner )
More informationMASTER SUBCONTRACTOR AGREEMENT
The Builders Association of Minnesota, its local associations, and Fredrikson & Byron, P.A. disclaim any liability resulting from the use of these sample forms, and remind you that no single form is appropriate
More informationStandard Form of Agreement Between Design-Builder and Contractor. The Design-Builder has entered into a Design-Build Contract with the Owner dated:
Document A142 2014 Standard Form of Agreement Between Design-Builder and Contractor AGREEMENT made as of the day of in the year (In words, indicate day, month and year.) BETWEEN the Design-Builder: (Name,
More informationWESTERN RIVERSIDE COUNCIL OF GOVERNMENTS EQUIPMENT PURCHASE AGREEMENT
WESTERN RIVERSIDE COUNCIL OF GOVERNMENTS EQUIPMENT PURCHASE AGREEMENT This Equipment Purchase Agreement ( Agreement ) is entered into this day of, 20, by and between the Western Riverside Council of Governments,
More informationSECTION 8 - MEASUREMENT AND PAYMENT TABLE OF CONTENTS
SECTION 8 - MEASUREMENT AND PAYMENT TABLE OF CONTENTS Section Page 8-1 BASIS AND MEASUREMENT OF PAYMENT QUANTITIES... 8-1 8-1.01 Unit Price Contracts... 8-1 8-1.02 Lump Sum or Job Contracts... 8-1 8-1.03
More information«f80» «f81» «f82», «f83» LENDER SERVICING AGREEMENT
.. The fields in this document are filled in by Mortgage+Care Loan Origination Software. Please contact us at (800)481-2708 or www.mortcare.com for a list of mergeable documents. «f80» «f81» «f82», «f83»
More informationWashington University in St. Louis
Washington University in St. Louis Construction Terms and Conditions A. AGREEMENT. The Purchase Order, these Terms and Conditions, any special conditions, Owner s Policies, Design Standards and Insurance
More informationConstruction Law: Greensboro Builders Association Remodelers Counsel
Construction Law: Greensboro Builders Association Remodelers Counsel February 25, 2010 J. Patrick Haywood Carruthers & Roth, P.A. 235 N. Edgeworth Street Greensboro, NC 27401 Direct Line: (336) 478-1177
More informationTennessee Housing Development Agency 404 James Robertson Parkway, Suite 1200 Nashville, Tennessee / Ted R.
Tennessee Housing Development Agency 404 James Robertson Parkway, Suite 1200 Nashville, Tennessee 37243-0900 615/815-2200 Ted R. Fellman Writer s Phone Number: Executive Director 615-815-2200 Writer s
More informationW I T N E S S E T H:
GENERAL CONTRACTORS SUBCONTRACT AGREEMENT THIS CONTRACT, made and entered into the day of, 20, by and between, a Tennessee, having its principal place of business at, hereinafter referred to as "Contractor"
More informationARTICLE 1 ARTICLE 3 CONTRACTOR THE SUBCONTRACT DOCUMENTS ARTICLE 2 MUTUAL RIGHTS AND RESPONSIBILITIES
ARTICLE 1 THE SUBCONTRACT DOCUMENTS 1.1 The Subcontract Documents consist of (1) this Agreement; (2) the prime Contract, consisting of the Agreement between the Owner and Contractor and the other Contract
More informationEXHIBIT M PUBLIC FUNDS AMOUNT PAYMENT TERMS
EXHIBIT M PUBLIC FUNDS AMOUNT PAYMENT TERMS Section 1 Department Payments and Adjustments (a) Starting on the Financial Close Date, the Department will make Public Funds Amount payments in accordance with
More informationOwner-Contractor Construction Agreement For Owner Controlled Insurance Program
Owner-Contractor Construction Agreement For Owner Controlled Insurance Program This agreement is entered into as of ( Effective Date ) between Lone Star College (the "College"), a public junior college
More informationDocument Checklist for 203k Loans
Document Checklist for 203k Loans HUD-92700: 203(k) and Streamlined (k) Maximum Mortgage Worksheet HUD-92700a: 203(k) Borrower's Acknowledgment Appraisal with all improvements listed on Repairs & Updates
More informationAPPLICATION FOR PAYMENT PROCEDURE SUBCONTRACT EXHIBIT F
Subcontract No.: Enter Number Cost Code: Enter Code TOCCI BUILDING CORPORATION Vendor No.: Enter Number APPLICATION FOR PAYMENT PROCEDURE SUBCONTRACT EXHIBIT F To standardize the Application for Payment
More informationProvide all materials to complete the {Contracts.Description} Scope of Work in strict accordance with this purchase order.
All invoices for goods and/or work covered by this Purchase Order shall be sent to ap@cmbteam.com, unless otherwise stated. PURCHASE ORDER NO.:{Contracts.ContractNum PROJECT NO.: {Projects.Number} CSI
More informationCONSTRUCTION MANAGER AT RISK (CMAR) CONSTRUCTION SERVICES CONTRACT
Terminal Concessions Remodel CONSTRUCTION MANAGER AT RISK (CMAR) CONSTRUCTION SERVICES CONTRACT PROJECT NO. 1086 TABLE OF CONTENTS ARTICLE PAGE ARTICLE 1 PARTICIPANTS AND PROJECT... 3 ARTICLE 2 CONTRACT
More informationAIA Document A101 TM 2007
AIA Document A101 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum AGREEMENT made as of the day of in the year (In words, indicate day, month
More informationDocument A101 TM. Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum
Document A101 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum AGREEMENT made as of the day of in the year (In words, indicate day, month and
More information! " # $ " % made as of the 24 day of May in the year 2006 (In words, indicate day, month and year) the Owner: (Name, address and other information)
! " # $ " % made as of the 24 day of May in the year 2006 (In words, indicate day, month and year) the Owner: (Name, address and other information) Wynne Public Schools P.O. Box 69 Wynne, AR 72396 Telephone
More informationAIA Document A201 TM 1997
AIA Document A201 TM 1997 General Conditions of the Contract for Construction for the following PROJECT: (Name and location or address): Project University of Maine at Farmington THE OWNER: (Name and address):
More informationRENOVATION CONTRACT. Borrower Name(s): Phone #: Phone #:
RENOVATION CONTRACT Case Number: Date: Borrower Name(s): Phone #: Phone #: THIS RENOVATION CONTRACT ( Contract ) dated as of, by and between ( Owner ) and ( Contractor ). Owner and Contractor, in consideration
More informationDocument A General Conditions of the Contract for Construction, Construction Manager as Adviser Edition
Document A232 2009 General Conditions of the Contract for Construction, Construction Manager as Adviser Edition for the following PROJECT: (Name, and location or address) THE CONSTRUCTION MANAGER: (Name,
More informationSMALL SERVICE, REHABILITATION, OR CONSTRUCTION AGREEMENT
SMALL SERVICE, REHABILITATION, OR CONSTRUCTION AGREEMENT (This Agreement shall be utilized for any service, rehabilitation, or construction project when funding sources contain no additional restrictions
More informationSTG Indemnity Agreement
STG Indemnity Agreement INDEMNITY AGREEMENT 1 This indemnification is made and given by: referred to herein as "Indemnitor" (whether one or more) for the benefit of Stewart Title Guaranty Company and (individually
More informationSUPPLIER - TERMS AND CONDITIONS Materials and Goods
SUPPLIER - TERMS AND CONDITIONS Materials and Goods 1. BINDING EFFECT; ACCEPTANCE. This purchase order and all subsequent purchase orders delivered by Buyer to Seller (each, an "order"), shall be governed
More informationPO Box 2279 Concord, NH
PO Box 2279 Concord, NH 03302-2279 Each month, we require our subcontractors to submit a lien waiver before payment is released, in accordance with our subcontractor contract terms, which can be found
More informationSUBCONTRACT. by and between. to perform the Work identified in Article 2 in accordance with the Projects Contract documents.
Phone 800 555-5555 Fax 999 555-5551 TO: 4320 Eucalyptus Way Santa Rosa CA 95401 SUBCONTRACT PROJECT: 186 Williams Post Office 19420 Williams Rd. Monte Rio CA 95462 This agreement entered into this day
More informationAPPLICATION FOR BUSINESS CREDIT
_. Return Completed Application to: Pike Industries, Inc. 3 Eastgate Park Road Belmont, NH 03220 Phone: 603.527.5100 Fax: 603.527.5101 Email: r1arremit@pikeindustries.com APPLICATION FOR BUSINESS CREDIT
More informationEQUIPMENT LENDING AGREEMENT
EQUIPMENT LENDING AGREEMENT The person signing this agreement and the organization on whose behalf the equipment lending is being made (collectively the Borrower ) are responsible for compliance with this
More informationCDBG/HOME CONTRACT DOCUMENTS NEW HOUSING CONSTRUCTION
CDBG/HOME CONTRACT DOCUMENTS NEW HOUSING CONSTRUCTION 2013 CDBG/HOME HOUSING NEW CONSTRUCTION CONTRACT THIS CONSTRUCTION CONTRACT is made and entered into this day of 2013, by and between, (marital status),
More informationDocument A101 TM. Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum
Document A101 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum AGREEMENT made as of. (Date of issuance of Owner s Purchase Order) BETWEEN the
More informationAIA Document A201 TM 2007
AIA Document A201 TM 2007 General Conditions of the Contract for Construction for the following PROJECT: (Name and location or address) THE OWNER: (Name and address) THE ARCHITECT: (Name and address) TABLE
More informationSHORT FORM STANDARD SUBCONTRACT. This Agreement is made this day of, 20, between
SHORT FORM STANDARD SUBCONTRACT This Agreement is made this day of, 20, between (Contractor) and (Subcontractor). The work described in Section I below shall be performed in accordance with the prime contract
More informationDocument A401. Standard Form of Agreement Between Contractor and Subcontractor
TM Document A401 1997 Standard Form of Agreement Between Contractor and Subcontractor AGREEMENT made as of the day of in the year (In words, indicate day, month and year) BETWEEN the Contractor: (Name,
More informationSTANDARD SUBCONTRACT AGREEMENT FOR BUILDING CONSTRUCTION
STANDARD SUBCONTRACT AGREEMENT FOR BUILDING CONSTRUCTION THIS AGREEMENT made at Columbus, Ohio on by and between Lincoln Construction, Inc., hereinafter referred to as the Contractor, and, hereinafter
More informationFIXTURE TERMS & CONDITIONS Materials & Goods
FIXTURE TERMS & CONDITIONS Materials & Goods 1. BINDING EFFECT; ACCEPTANCE. This purchase order and all subsequent purchase orders delivered by Supplier to The Pep Boys Manny, Moe & Jack, and its affiliates,
More informationDocument A201 TM 2007 SP
AIA Document A201 TM 2007 SP General Conditions of the Contract for Construction, for use on a Sustainable Project for the following PROJECT: (Name and location or address) THE OWNER: (Name, legal status
More informationConsensusDocs 751 STANDARD SHORT FORM AGREEMENT BETWEEN CONSTRUCTOR AND SUBCONTRACTOR
ConsensusDocs 751 STANDARD SHORT FORM AGREEMENT BETWEEN CONSTRUCTOR AND SUBCONTRACTOR Job No. [ ] Subcontract No. [ ] This Agreement is made this [ ] day of [ ], [ ], by and between CONSTRUCTOR, L&L Builders
More informationADDENDUM TO INVITATION FOR BIDS Fortuna Union High School District Proposition 39 LED Lighting Retrofit Bid No Addendum #2 February 23, 2017
ADDENDUM TO INVITATION FOR BIDS Fortuna Union High School District Proposition 39 LED Lighting Retrofit Bid No. 17-001 Addendum #2 February 23, 2017 To All Prospective Bidders: The Fortuna Union High School
More informationCOLGATE RENTALS CORP BRUCKNER BOULEVARD, BRONX, NY * TEL (718) * FAX (718) Credit Application
Company Information COLGATE RENTALS CORP. Credit Application Full Legal Name of Company: Date: Contact: Title: Cell: E-mail: Website: Rent or Own: Rigger s License No: Insurance Co for GL: Tax ID: NYC
More informationDocument A Standard Form of Agreement Between Contractor and Subcontractor
Document A401 2017 Standard Form of Agreement Between Contractor and Subcontractor AGREEMENT made as of the day of in the year (In words, indicate day, month and year.) BETWEEN the Contractor: (Name, legal
More informationSAMPLE SPECIFICATION SECTION SALES AND USE TAX SAVINGS
SAMPLE SPECIFICATION SECTION SALES AND USE TAX SAVINGS GENERAL DESCRIPTION A. PURPOSE: The Owner,, is a Tax Exempt Instrumentality of the State of Alabama. As such, it is authorized to and desires to enter
More informationContractor for any and all liability, costs, expenses, fines, penalties, and attorney s fees resulting from its failure to perform such duties.
SUBCONTRACT AGREEMENT THIS SUBCONTRACT, made this day of, 20 by and between (hereinafter "Contractor"), with an office and principal place of business at and (hereinafter "Subcontractor") with an office
More informationSAMPLE DOCUMENT SUBCONTRACT AGREEMENT
SUBCONTRACT AGREEMENT THIS SUBCONTRACT, made this day of by and between (hereinafter "Contractor"), with an office and principal place of business at and (hereinafter "Subcontractor") with an office and
More informationSUBCONTRACT AGREEMENT
Phone: 806-763-5263 SUBCONTRACT AGREEMENT PO Box 2791 Lubbock, TX 79408 Fax: 806-763-5843 This Subcontract Agreement (herein called "Agreement") is made and entered into as of this 17th day of October,
More informationENERGY EFFICIENCY CONTRACTOR AGREEMENT
ENERGY EFFICIENCY CONTRACTOR AGREEMENT 2208 Rev. 2/1/13 THIS IS AN AGREEMENT by and between PUBLIC UTILITY DISTRICT NO. 1 OF SNOHOMISH COUNTY (the District ) and a contractor registered with the State
More informationEXHIBIT E SUBCONTRACT TERMS ARTICLE I THE CONTRACT DOCUMENTS
EXHIBIT E SUBCONTRACT TERMS ARTICLE I THE CONTRACT DOCUMENTS 1.1 The Contract Documents which shall govern this Subcontract and the Subcontract Work (referred to herein as the "Work") consist of this Subcontract
More informationAIA Document A201 TM 1997
AIA Document A201 TM 1997 General Conditions of the Contract for Construction for the following PROJECT: (Name and location or address): A201 conversion Michigan State University East Lansing, MI THE OWNER:
More informationSTANDARD AGREEMENT BETWEEN OWNER AND CONTRACTOR for The University of Texas Health Science Center at Tyler Construction Projects
STANDARD AGREEMENT BETWEEN OWNER AND CONTRACTOR for The University of Texas Health Science Center at Tyler Construction Projects This Agreement is made as of, 2016 (the Effective Date ), by and between
More informationASHI DIAMONDS, LLC. 18 EAST 48TH STREET, 14TH FLOOR NEW YORK, N.Y ((212) ~ FAX (212) ~ ((800) 622-ASHI
ASHI DIAMONDS, LLC. 18 EAST 48TH STREET, 14TH FLOOR NEW YORK, N.Y. 10017 ((212) 319-8291 ~ FAX (212) 319-4341 ~ ((800) 622-ASHI S E C U R I T Y A G R E E M E N T This Purchase Money Security Interest Agreement
More informationSUBCONTRACT AGREEMENT
Job No.: Subcontract No.: Cost Code: Vendor No.: number number number number SUBCONTRACT AGREEMENT AGREEMENT made this date day of month, year (hereinafter Agreement or Subcontract ) between and Swinerton
More informationSubcontract Agreement
S THIS AGREEMENT made as of the day of, 2012 BETWEEN the Contractor: TCL Partners 5212 123 rd Place SE Everett, WA 98208 and the For the Following Project: The Architect for the Project: The Contractor
More informationGeneral Conditions for Construction GCC201. Contract Type: Document No. for the following PROJECT: (Name and location or address) EXAMPLE
Page 1 of 37 for the following PROJECT: (Name and location or address) EXAMPLE THE OWNER: (Name and address) Example, THE ARCHITECT: (Name and address) TABLE OF ARTICLES 1 GENERAL PROVISIONS 2 OWNER 3
More information3.1.2 The Contractor shall perform the Work in accordance with the Contract Documents.
the portion of the Work affected by a material change. After the Owner furnishes the evidence, the Owner shall not materially vary such financial arrangements without prior notice to the Contractor. 2.2.2
More informationTexas Lien & Bond Law Booklet
Texas Lien & Bond Law Booklet Presented by: Jason C. Spencer Telephone: (512) 900-3032 Facsimile: (512) 900-3082 jspencer@andrewsmyers.com www.andrewsmyers.com AUTHOR BIO Jason C. Spencer is a shareholder
More informationSUBCONTRACT FOR BUILDING CONSTRUCTION
SUBCONTRACT FOR BUILDING CONSTRUCTION TABLE OF ARTICLES 1. AGREEMENT 2. SCOPE OF WORK 3. SCHEDULE OF WORK 4. CONTRACT PRICE 5. PAYMENT 6. CHANGES, CLAIMS AND DELAYS 7. CONTRACTOR'S OBLIGATIONS 8. SUBCONTRACTOR'S
More informationTHIS CONSTRUCTION CONTRACT ( Contract ) dated as of ( Owner ) and ( Contractor ) having a principal place of business at.
Homeowner Contractor HomeStyle Renovation Contract Loan Number: Date: Borrower Name(s): Phone #: Phone #: THIS CONSTRUCTION CONTRACT ( Contract ) dated as of by and between ( Owner ) and ( Contractor )
More informationProject Name, Improvement District No. Improvement District Number
CONTRACT THIS AGREEMENT, made and entered into this day of, 20, between the City of Fargo (a Municipal Corporation, under the laws of North Dakota) by the City Commission, hereinafter called the City,
More informationDocument A401 TM. Standard Form of Agreement Between Contractor and Subcontractor
Document A401 TM 2017 Standard Form of Agreement Between Contractor and Subcontractor AGREEMENT made as of the day of in the year (In words, indicate day, month and year.) BETWEEN the Contractor: (Name,
More informationAvoiding Common Payment Pitfalls for Subcontractors: A Primer on Federal Contracting Payment Remedies
Avoiding Common Payment Pitfalls for Subcontractors: A Primer on Federal Contracting Payment Remedies Shoshana E. Rothman BrigliaMcLaughlin, PLLC April 2017 Seminar Goals: 1. Understand key contract clauses
More informationDOCUMENT AA REQUEST FOR COMPETITIVE SEALED PROPOSALS
District Wide Security Vestibules Bryan Independent School District CSP #16-3741 DOCUMENT AA REQUEST FOR COMPETITIVE SEALED PROPOSALS Competitive Sealed Proposals for the work identified below in accordance
More informationcommercial credit application
commercial credit application IRBY ELECTRICAL DISTRIBUTOR Please complete the following application in its entirety to ensure prompt processing of the account setup. You are welcome to email the final
More informationStandard Form of Agreement Between Contractor and Subcontractor
Document A401 2007 Standard Form of Agreement Between Contractor and Subcontractor AGREEMENT made as of the in the year (In words, indicate day, month and year.) day of BETWEEN the Contractor: (Name, legal
More informationHomeStyle Renovation Submission Checklist
HomeStyle Renovation Submission Checklist Borrower Name: Loan #: Homestyle Calculation Worksheet (LoanBuilder) * HomeStyle Renovation Consumer Tips (Form 1204) signed by borrower Appraisal with all improvements
More informationAIA CONTRACT DOCUMENTS
AIA CONTRACT DOCUMENTS A101, A102 and A201 Sanjay Kurian Becker & Poliakoff, P.A. Forms of Documents AIA A101-2007 (Lump sum) AIA A102-2007 (Guaranteed Maximum Price) AIA A201-2007 (General Conditions)
More informationOGC-S Owner-Contractor Construction Agreement
Owner-Contractor Construction Agreement This agreement is entered into as of ( Effective Date ) between Lone Star College (the "College"), a public junior college pursuant to Section 130.004 of the Texas
More informationSUBCONTRACTOR AGREEMENT
SUBCONTRACTOR AGREEMENT This Subcontractor Agreement (herein referred to as "Agreement"), made this day of _, 20 between Bianchi Construction LLC, ("Contractor"), and ("Subcontractor"). Terms: The basic
More informationSUBCONTRACT (Short Form)
DISTRIBUTION: SUB / CGS / FIELD / FILE SUBCONTRACT (Short Form) 11777 West Lake Park Drive Milwaukee, WI 53224 (414) 577-1177 Fax: (414) 577-1155 www.cgschmidt.com Date: Project: Project Owner: Project
More informationSTANDARD AGREEMENT BETWEEN OWNER AND CONTRACTOR For Construction Services for The University of Texas MD Anderson Cancer Center
STANDARD AGREEMENT BETWEEN OWNER AND CONTRACTOR For Construction Services for The University of Texas MD Anderson Cancer Center This Agreement is made as of, 20 (the Effective Date ), by and between The
More information