Permitting, Procurement, Construction and Performance Risks

Size: px
Start display at page:

Download "Permitting, Procurement, Construction and Performance Risks"

Transcription

1 Permitting, Procurement, Construction and Performance Risks Daniel Bailey, Pierce Atwood LLP (moderator) Lynn Gresock, Tetra Tech John Zimmer, TRC Bill Allard, Burns & McDonnell Parker Hadlock, Cianbro Chris Whitney, Pierce Atwood LLP October 20, 2017 Boston, MA

2

3

4

5

6

7

8

9 Permitting Natural Gas Infrastructure in the Northeast Not for the Faint of Heart October 20, 2017

10 The Regulatory Climate has Changed Why has it become so difficult to permit new natural gas infrastructure? Regulatory requirements for projects have not changed significantly Public sentiment shift toward renewables Rise of social media o o o Gas Land Pipeline Safety NGOs / landowner coalitions Ease of Litigation / Permit Appeal o Direct impacts to project schedule and cost 10

11 Dealing with Regulatory Potholes At Federal, State and Local Levels Over-burdened, inexperienced staff Multiple permitting agencies with differing mandates and missions Political pressures o Article 97 in MA Sophisticated, well-funded NGOs Hundreds to thousands of stakeholder comments 11

12 What the Regulators Hear REGULATORS Project Sponsors & Customers We want: Regulatory certainty A level playing field Better federal/state coordination Recognition of the way projects develop Landowners & NGOs We want: More information More transparency Local control Regional planning A National/global energy strategy 12

13 401 Water Quality Certificate State administration of 401 WQC Especially critical in MA where it is tied directly to MEPA and local OOCs Why is it a critical path item on FERC regulated / NEPA projects? FERC will not issue NTP without all federal and federally-delegated approvals in-hand USACE cannot issue final NWP or IP without prior issuance of 401 How has it affected project design? Higher percentage of trenchless crossings to avoid jurisdictional resource impacts 13

14 Is There a Detour? Can problems be designed away? Can problems be legislated away? Can facts / common sense win the day? Can project supporters/advocates balance the negative voices? 14

15 Permitting Best Management Practices How can we increase our odds of acquiring required permits / approvals? Develop a reasonable project schedule Early agency / stakeholder outreach Educate the regulators Design to regulatory performance standards o Conduct the analyses Avoid, minimize, and mitigate impacts to environmental resources 15

16 John Zimmer Market Director Pipeline / LNG jzimmer@trcsolutions.com

17 MANAGING PROCUREMENT RISK William J Allard, PMP October 19, 2017

18 Risk Management Identification Project manager centric Acting in interest of stakeholders Achieving successful profitable project Response Five Step Risk Management Plan Analysis Project Risk Management Manage project contingency Develop consistent periodic review Evaluate uncertainties in Project (Project Risk) Opportunities Threats Mitigate the uncertainties to achieve favorable results for the project Input to the Estimating Process (Contingency) Evaluation Prioritization 18

19

20 Procurement Process Technical specification development RFP preparation Bid evaluation Contract negotiations Prepare and issue purchase orders Administer purchase orders and subcontracts Expediting Supplier surveillance and quality assurance Freight & logistics Import/Export compliance Contract administration and closeout On-site material management

21 Selecting the Contracting Strategy High Self-Perform Design Bid Build Owner s Capacity to Manage Project(s) EPC or Owner s Engineer Program/Project Management Low Medium Large Project Size Very Large

22 Pre-Qualify Contractors Pre-Qualify Contractors, Vendors & Suppliers Pre-qualification RFI process Pre-determined criteria to qualify Safety Financial Capacity Experience Skill sets Evaluate contractors/suppliers based on that criteria Score contractors/suppliers for use in bid evaluations 22

23 Contractor Sourcing & Prequalification Process Map Develop Potential bid lists Develop Prequalification package with questions to identify risks Packages proposed by Procurement Team Technical portions of RFPs developed with risks identified Commercial portions developed RFP packages issued RFP evaluation criteria developed with consideration of Risks Split evaluation between commercial and technical Page turn meetings to finalize evaluations Negotiations held with successful bidders

24 Contractors and Suppliers Each contractor or supplier comes with risks and opportunities Location of manpower Familiarity with work Familiarity with client s procedures and processes Past success/failures Assign a dollar value on those risks to complete evaluations Installed cost vs bid price Change is inevitable so quantify it in your risk matrix Collaborate to identify and minimize risk 24

25 Partnerships Utilize existing vendor relationships Contracts in place Standard Terms and Conditions Strong business relationships Known expectations Established Supplier Relationships to Build Business Partners Know processes and procedures

26 Construction Risk

27 Company Overview Parker Hadlock CIANBRO Founded In % Employee-Owned Top 100 U.S. Equipment Owner General Manager Wind Energy Services Mobile Workforce Region 1

28 Construction Risk Guiding Principles: Only take responsibility for things we can control or what we can actively manage and mitigate. Only assign risk to those most capable of managing it Project Delivery Model Types Schedule Labor Long Lead Procurement Specialty Equipment Subcontractor Relationships Location Liquidated Damages

29 Project Delivery Model Types Program Management Service for Fee Low Risk EPC Lump Sum At risk for Design & Construction No Risk for Performance Construct Only Lump sum At Risk for Construction only No Risk for Design or Performance

30 Schedule Reliance on others Duration Resources Mother Nature Is it Realistic

31 Labor Availability Skill Sets Cost

32 Long Lead Procurement Is Design Complete? (no changes) MFG &Transportation Risks (expediting ) Failures During Commissioning (Builders Risk must include soft cost coverage such as delay damages)

33 Specialty Equipment Equipment Availability Example: MLC 650 Capable of 130M hub height wind turbines

34 Subcontractors Relationships that transcend more than one project Trust Reliability Capability

35 Location If the unexpected occurs, can we recover with our own resources

36 Liquidated Damages Good: Separates the credible from the imposters Bad: Needs to be capped at some % of fee

37 Collaborate & Eliminate Risk (don t just shift it) Leverage each team members strengths to ensure risks are assigned to the team member most skilled at managing that risk. If you think you have spread risk onto a party that is ill equipped to manage it, you will likely get it back!!!

38

39 Thoughts on Contractual Approaches to Addressing and Mitigating Risk on Energy Infrastructure Projects Presented by Christopher C. Whitney, Esq., Pierce Atwood LLP

40 Overall, energy infrastructure project risks are managed through a combination of: 1. Operationally, through thoughtful business judgments about the many project risk factors identified by Parker Hadlock in his presentation; and 2. Legally, involving negotiating appropriate contract provisions (the subject of my presentation) 40

41 Contractual approaches to addressing and mitigating risk: 1. Start with the core principle offered by Mr. Hadlock of assigning risk to the party most capable of managing that risk; 2. Then choose appropriate project delivery approach a. EPC b. CMAR c. Design-Build d. IPD; 3. Then choose most appropriate form of contract 1. Manuscripted contract EPC 2. Industry form contract AIA, AGC, EJCDC; DBIA 41

42 Contractual approaches to addressing and mitigating risk (cont d): EPC contracts and performance guarantees - special considerations 42

43 Contractual approaches to addressing and mitigating risk (cont d): Addressing risk of delays or cost overruns due to Labor Issues: 1. Labor availability business judgment issue 2. Assigning responsibility for labor strife a. Labor harmony clause b. Force majeure clause c. Project labor Agreements 3. Prevailing wage issues 43

44 Contractual approaches to addressing and mitigating risk (cont d): Addressing insurance and indemnity issues: 1. Property insurance and waivers of subrogation 2. Payment and Performance bonds versus Subguard Insurance 3. Breadth of indemnity agreement 44

45 Contractual approaches to addressing and mitigating risk (cont d): Addressing payment issues: 1. Perfecting mechanics lien rights 2. Security for payments made for long lead items and offsite stored materials and equipment 3. Right to inspect work in progress off-site 4. Disputed change order payment provisions 45

46 Contractual approaches to addressing and mitigating risk (cont d): Addressing limitations of liability: 1. Mutual waiver of consequential damages 2. Limitation of Liability Clauses 3. Liquidated Damages 46

47 Contractual approaches to addressing and mitigating risk (cont d): Examples of violating core principle of assigning risk to the party most capable of managing that risk: 1. No damage for delay clause 2. Contractor responsible for unforeseen conditions clause 3. Overreaching indemnification clause 47

48 Christopher C. Whitney 72 Pine Street Providence, RI PH /

2013 Construction Series. Highlights

2013 Construction Series. Highlights 2013 Construction Series Highlights 2013 C-Series Highlights Revisions, enhancements, and coordination of all 20+ C- series documents Added three new documents: C-111, Advertisement for Bids C-451, Qualifications

More information

CONSTRUCTION NEGOTIATIONS

CONSTRUCTION NEGOTIATIONS CONSTRUCTION NEGOTIATIONS I. Contracts November 6, 2017 Presented by: Bryan Thomas Bradley Arant Boult Cummings LLP Attorney-Client Privilege. Agenda Construction Negotiations I. Contracts Know the Deal

More information

CONSTRUCTION LAW AND RISK MANAGEMENT

CONSTRUCTION LAW AND RISK MANAGEMENT Course Objective: CONSTRUCTION LAW AND RISK MANAGEMENT The objective of this course is to take an advanced look at the legal principles of construction law and how it applies to engineering and project

More information

2014 Aligned Risk Management Effective Strategies to Help Vendors Obtain Bonding and Insurance

2014 Aligned Risk Management Effective Strategies to Help Vendors Obtain Bonding and Insurance 2014 Aligned Risk Management Effective Strategies to Help Vendors Obtain Bonding and Insurance Presented By Ingrid Merriwether Merriwether & Williams Insurance Services Business Outreach Committee Meet

More information

Construction Risk in P3 Projects. Timothy J. Murphy Partner McMillan LLP

Construction Risk in P3 Projects. Timothy J. Murphy Partner McMillan LLP Construction Risk in P3 Projects Timothy J. Murphy Partner McMillan LLP Risk Transfer in a P3 Key aspects of a P3: Private sector financing Public sector clarity through output specifications Integrated

More information

Best Practices for Capital Projects. Agenda

Best Practices for Capital Projects. Agenda Best Practices for Capital Projects OR PRIMA Fall Conference Thursday, October 6, 2016 Agenda Introduction Project Risk Management Designing the Best Fit Insurance Program Risk Inventory and Assessment

More information

AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER PRE-CONSTRUCTION AND CONSTRUCTION SERVICES

AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER PRE-CONSTRUCTION AND CONSTRUCTION SERVICES AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER PRE-CONSTRUCTION AND CONSTRUCTION SERVICES AGREEMENT made by and between, hereinafter called the Owner, and SITESCOMMERCIAL, LLC 185 WIND CHIME COURT, SUITE

More information

REQUEST FOR QUALIFICATIONS/ PROPOSALS LEASE-LEASEBACK CONTRACTOR FOR

REQUEST FOR QUALIFICATIONS/ PROPOSALS LEASE-LEASEBACK CONTRACTOR FOR SANTA BARBARA UNIFIED SCHOOL DISTRICT REQUEST FOR QUALIFICATIONS/ PROPOSALS LEASE-LEASEBACK CONTRACTOR FOR Multi-Purpose Building Renovation Projects at Harding University Partnership School and Roosevelt

More information

MODULE 5 PROJECT RISK MANAGEMENT, PROCUREMENT AND CONTRACTS

MODULE 5 PROJECT RISK MANAGEMENT, PROCUREMENT AND CONTRACTS Advanced Project Management MODULE 5 PROJECT RISK MANAGEMENT, PROCUREMENT AND CONTRACTS 06 07 November 2018 Facilitator: Mr Mondli Mbambo Module Purpose Project Risk & Procurement Managment Knowledge Risk

More information

5/17/2013 BEST VALUE PROCUREMENT METHOD RFP PROCUREMENT METHOD EVALUATION CRITERIA FOR GOODS & SERVICES RFP FACTORS

5/17/2013 BEST VALUE PROCUREMENT METHOD RFP PROCUREMENT METHOD EVALUATION CRITERIA FOR GOODS & SERVICES RFP FACTORS SPECIAL GUEST SPEAKERS: Eduardo Belmarez Purchasing Agent City of Mission Lorena Garcia, CPPB Director of Purchasing M All ISD McAllen Maggie Rangel Assistant Director of Materials Management University

More information

Risk Allocation in Underground Construction and the Benefits of the ECI/Portland Model Approach

Risk Allocation in Underground Construction and the Benefits of the ECI/Portland Model Approach Risk Allocation in Underground Construction and the Benefits of the ECI/Portland Model Approach Matt Swinton David A. Hecker Kiewit Infrastructure Group David A. Hecker Kiewit Corporation Group General

More information

Innovative Ways to Insure Project Risks

Innovative Ways to Insure Project Risks Innovative Ways to Insure Project Risks Construction Project Risks Construction project participants owners, financiers, architects, engineers, contractors, construction managers, suppliers, etc. - all

More information

Intro Public-Private Partnership (P3) Finance Course

Intro Public-Private Partnership (P3) Finance Course Intro Public-Private Partnership (P3) Finance Course Identifying P3 Projects and Knowing the Atmosphere Kylee Anastasi Director, Capital Projects and Infrastructure Advisory PricewaterhouseCoopers LLP

More information

Better Contracts, Better Projects: The ConsensusDocs Solution

Better Contracts, Better Projects: The ConsensusDocs Solution Better Contracts, Better Projects: The ConsensusDocs Solution Better Contracts, Better Projects: The ConsensusDocs Solution Richard H. Lowe Duane Morris LLP This session is eligible for 1 Contact Hour.

More information

The City of Tarpon Springs

The City of Tarpon Springs Prepared By: Carr, Riggs & Ingram August 29, 2018 The City of Tarpon Springs Contract Compliance Assessment of The Reverse Osmosis Water Treatment Facility Table of Contents Transmittal Letter... 1 Executive

More information

Construction Contracting 101 & Public Bidding Requirements

Construction Contracting 101 & Public Bidding Requirements Construction Contracting 101 & Public Bidding Requirements WASDA 50 th Annual Educational Conference May 16, 2017 Andrew T. Phillips Steven L. Nelson Milwaukee Madison 411 East Wisconsin Avenue Suite 1000

More information

VALUE FOR MONEY ASSESSMENT HIGHWAY 407 EAST PHASE 1 PROJECT

VALUE FOR MONEY ASSESSMENT HIGHWAY 407 EAST PHASE 1 PROJECT VALUE FOR MONEY ASSESSMENT HIGHWAY 407 EAST PHASE 1 PROJECT 1 2 3 4 Highway 407 East Phase 1 Project Artist s rendering Highlights of Highway 407 East Phase 1 Highway 407 East will help to relieve congestion

More information

Preventing and Managing the Risk of a Subcontractor Default A Best Practices Checklist

Preventing and Managing the Risk of a Subcontractor Default A Best Practices Checklist Tough times have depleted balance sheets and left working capital levels dangerously low for many subcontractors. Defaults are on the rise and expected to increase; a trend that has somewhat been masked

More information

Construction Project Management from the Owner s Perspective

Construction Project Management from the Owner s Perspective Construction Project Management from the Owner s Perspective Presented at: IMUA 2013 Annual Meeting May 21, 2013 Page 1 Agenda Introduction to Risk Management Risk through the Project Life Cycle Project

More information

Construction Management Contract This agreement is made by (Contractor) and (Owner) on the date written beside our signatures.

Construction Management Contract This agreement is made by (Contractor) and (Owner) on the date written beside our signatures. Construction Management Contract This agreement is made by (Contractor) and (Owner) on the date written beside our signatures. Contractor Address Address City, Zip Work Phone Number: Cell Phone Number:

More information

CONSTRUCTION CONTRACT ANALYSIS. Robert Zellmer, CCA Manager Baker Tilly

CONSTRUCTION CONTRACT ANALYSIS. Robert Zellmer, CCA Manager Baker Tilly CONSTRUCTION CONTRACT ANALYSIS Robert Zellmer, CCA Manager Baker Tilly OVERVIEW Today s topics: Contract Key Terms Documentation Requirements Red Flags LEARNING OBJECTIVE Deepen management s understanding

More information

Introduction by Philip Croessmann, V.P., Director of Risk Management Sources of Construction Claims Common Types of Construction Claims Risk

Introduction by Philip Croessmann, V.P., Director of Risk Management Sources of Construction Claims Common Types of Construction Claims Risk Introduction by Philip Croessmann, V.P., Director of Risk Management Sources of Construction Claims Common Types of Construction Claims Risk Management Preconstruction & Construction Managing Construction

More information

DB and P3 Subsurface Projects - Contractual Risk Allocation Principles: New Terrain, Old Ground, or Both

DB and P3 Subsurface Projects - Contractual Risk Allocation Principles: New Terrain, Old Ground, or Both DB and P3 Subsurface Projects - Contractual Risk Allocation Principles: New Terrain, Old Ground, or Both Risk Management for Underground Construction Seminar November 29, 2017 David J. Hatem, PC Donovan

More information

IDAHO STATE UNIVERSITY POLICIES AND PROCEDURES (ISUPP) Purchasing Policy ISUPP 2560

IDAHO STATE UNIVERSITY POLICIES AND PROCEDURES (ISUPP) Purchasing Policy ISUPP 2560 IDAHO STATE UNIVERSITY POLICIES AND PROCEDURES (ISUPP) Purchasing Policy ISUPP 2560 POLICY INFORMATION Policy Section: Finance Policy Title: Purchasing Policy Responsible Executive (RE): Chief Financial

More information

Risk Identification & Contract Risk Management

Risk Identification & Contract Risk Management Risk Identification & Contract Risk Management In the world of geospatial Presenters Bob Hanson Senior Vice President, Michael Baker International Geospatial Practice Leader 717 221-2005 rhanson@mbakerintl.com

More information

ILLINOIS COMMUNITY COLLEGE CFO SPRING 2010 CONFERENCE DANCING WITH CONSTRUCTION FIRMS WHAT ARE YOUR OPTIONS? CONSTRUCTION MANAGER VS GENERAL

ILLINOIS COMMUNITY COLLEGE CFO SPRING 2010 CONFERENCE DANCING WITH CONSTRUCTION FIRMS WHAT ARE YOUR OPTIONS? CONSTRUCTION MANAGER VS GENERAL ILLINOIS COMMUNITY COLLEGE CFO SPRING 2010 CONFERENCE DANCING WITH CONSTRUCTION FIRMS WHAT ARE YOUR OPTIONS? CONSTRUCTION MANAGER VS GENERAL CONTRACTOR APRIL 30, 2010 1 Agenda The Players A Major Decision

More information

Design-Build Risk and Insurance Table of Contents

Design-Build Risk and Insurance Table of Contents Design-Build Risk and Insurance Table of Contents Design-Build Risk and Insurance (3rd ed.) Preface About the Editor About the Authors Topical Index Chapter 1: Design-Build Construction o The Design-Build

More information

Standard Form of Agreement Between OWNER AND CONSTRUCTION MANAGER Construction Manager At-Risk

Standard Form of Agreement Between OWNER AND CONSTRUCTION MANAGER Construction Manager At-Risk CMAA Document CMAR-1 Standard Form of Agreement Between OWNER AND CONSTRUCTION MANAGER Construction Manager At-Risk 2004 EDITION This document is to be used in connection with CMAA Standard Form of Contract

More information

SUBCONTRACTOR EXPECTATIONS IN FEDERAL CONTRACTING

SUBCONTRACTOR EXPECTATIONS IN FEDERAL CONTRACTING SUBCONTRACTOR EXPECTATIONS IN FEDERAL CONTRACTING Reducing Risk & Meeting Requirements as Government Subcontractor AGENDA ointroduction othe Process oproposal Phase onegotiations ocompliance and Accountability

More information

AIA CONTRACT DOCUMENTS

AIA CONTRACT DOCUMENTS AIA CONTRACT DOCUMENTS A101, A102 and A201 Sanjay Kurian Becker & Poliakoff, P.A. Forms of Documents AIA A101-2007 (Lump sum) AIA A102-2007 (Guaranteed Maximum Price) AIA A201-2007 (General Conditions)

More information

4/15/2014. The Changing Landscape of Construction Projects traditional contracting collaborative approaches

4/15/2014. The Changing Landscape of Construction Projects traditional contracting collaborative approaches Hall & Company is a Registered Provider with the American Institute of Architects Continuing Education Systems. Credit earned based on the completion of this program will be reported to AIA/CES for AIA

More information

Introduction and Overview

Introduction and Overview Introduction to Public Contracting Procurement and Public Works Presented by Barbara R. Gadbois, Esq. and Theodore L. Senet, Esq. County Counsels Association of California March 17, 2016 2016 Gibbs Giden

More information

Request for Qualifications for Owner s Program Management Services For Wilton Police Headquarters Renovation and Expansion

Request for Qualifications for Owner s Program Management Services For Wilton Police Headquarters Renovation and Expansion Page 1 of 11 Request for Qualifications for Owner s Program Management Services For Wilton Police Headquarters Renovation and Expansion The Town of Wilton (the Town) will receive sealed qualifications

More information

SUBCONTRACTOR PREQUALIFICATION APPLICATION GENERAL INFORMATION

SUBCONTRACTOR PREQUALIFICATION APPLICATION GENERAL INFORMATION Date of Response: Company name: SUBCONTRACTOR PREQUALIFICATION APPLICATION GENERAL INFORMATION DBA: Phone: E-mail: Main Office Address: State: ZIP Code: Website: Sole Proprietorship: Partnership: Corporation:

More information

Raising Equity for large biomass to power projects

Raising Equity for large biomass to power projects Specialist investment. 16/09/2016 Raising Equity for large biomass to power projects Presentation to IrBEA 'Financing Bioenergy Projects' Workshop Dublin 14 th September 2016 Dedicated Renewable Focused

More information

EXHIBIT "A" RESPONSIBILITIES AND SERVICES OF PROGRAM MANAGER 1. BASIC SERVICES A-1 2. GENERAL PROGRAM SERVICES A-6

EXHIBIT A RESPONSIBILITIES AND SERVICES OF PROGRAM MANAGER 1. BASIC SERVICES A-1 2. GENERAL PROGRAM SERVICES A-6 EXHIBIT "A" RESPONSIBILITIES AND SERVICES OF PROGRAM MANAGER 1. BASIC SERVICES A-1 2. GENERAL PROGRAM SERVICES A-6 3. PLANNING AND ADMINISTRATION A-6 OF THE PROJECT 4. PRECONSTRUCTION PHASE A-7 5. PRE-BIDDING

More information

Document A133 TM. AGREEMENT made as of the day of in the year 20 (In words, indicate day, month and year.)

Document A133 TM. AGREEMENT made as of the day of in the year 20 (In words, indicate day, month and year.) Document A133 TM 2009 Standard Form of Agreement Between Owner and Construction Manager as Constructor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price AGREEMENT

More information

20% of the Fee and 80% of the Liability: Navigating the Minefield of Construction Contract Administration

20% of the Fee and 80% of the Liability: Navigating the Minefield of Construction Contract Administration 20% of the Fee and 80% of the Liability: Navigating the Minefield of Construction Contract Administration RLI Design Professionals Design Professionals Learning Event DPLE 272 August 5, 2015 RLI Design

More information

IMPORTANCE OF DUE DILIGENCE AND FINANCIAL DUE DILIGENCE. 12 th Nov CA. SUJAL SHAH

IMPORTANCE OF DUE DILIGENCE AND FINANCIAL DUE DILIGENCE. 12 th Nov CA. SUJAL SHAH IMPORTANCE OF DUE DILIGENCE AND FINANCIAL DUE DILIGENCE 12 th Nov 2011 - CA. SUJAL SHAH Contents Meaning of Due Diligence Review (DDR) Scope of DDR Situations calling for DDR Types of DDR Financial DDR

More information

AGREEMENT BETWEEN THE BOARD OF REGENTS OF THE TEXAS A&M UNIVERSITY SYSTEM AND SPAWGLASS CONSTRUCTION CORP., CONSTRUCTION MANAGER-AT-RISK

AGREEMENT BETWEEN THE BOARD OF REGENTS OF THE TEXAS A&M UNIVERSITY SYSTEM AND SPAWGLASS CONSTRUCTION CORP., CONSTRUCTION MANAGER-AT-RISK AGREEMENT BETWEEN THE BOARD OF REGENTS OF THE TEXAS A&M UNIVERSITY SYSTEM AND SPAWGLASS CONSTRUCTION CORP., CONSTRUCTION MANAGER-AT-RISK 1 ARTICLE 1 SCOPE OF WORK 2 DEFINITIONS TABLE OF CONTENTS 3 CONTRACTOR

More information

Slide 1. Slide 2. Slide 3 LEARNING OBJECTIVES WHAT S THE DIFFERENCE? PERSONAL AND PROFESSIONAL EXCELLENCE

Slide 1. Slide 2. Slide 3 LEARNING OBJECTIVES WHAT S THE DIFFERENCE? PERSONAL AND PROFESSIONAL EXCELLENCE Slide 1 PERSONAL AND PROFESSIONAL EXCELLENCE Contract Administration Beginning With the End in Mind David E. Nash, CPPO, CPPB 50 TH ANNUAL CONFERENCE MAY 24-27, 2017 ORLANDO, FLORIDA Slide 2 LEARNING OBJECTIVES

More information

Standard Form of Agreement Between Design-Builder and Contractor. The Design-Builder has entered into a Design-Build Contract with the Owner dated:

Standard Form of Agreement Between Design-Builder and Contractor. The Design-Builder has entered into a Design-Build Contract with the Owner dated: Document A142 2014 Standard Form of Agreement Between Design-Builder and Contractor AGREEMENT made as of the day of in the year (In words, indicate day, month and year.) BETWEEN the Design-Builder: (Name,

More information

To Joint Venture or Not to Joint Venture Keys to a Successful Joint Venture Project

To Joint Venture or Not to Joint Venture Keys to a Successful Joint Venture Project To Joint Venture or Not to Joint Venture Keys to a Successful Joint Venture Project Kimberly Ramundo, Partner Erin Luke, Senior Associate Agenda/Objectives Joint Venture Overview Reasons for Using a Joint

More information

VALUE FOR MONEY ASSESSMENT TRILLIUM HEALTH PARTNERS CREDIT VALLEY HOSPITAL SITE PRIORITY AREAS REDEVELOPMENT PROJECT

VALUE FOR MONEY ASSESSMENT TRILLIUM HEALTH PARTNERS CREDIT VALLEY HOSPITAL SITE PRIORITY AREAS REDEVELOPMENT PROJECT VALUE FOR MONEY ASSESSMENT TRILLIUM HEALTH PARTNERS CREDIT VALLEY HOSPITAL SITE PRIORITY AREAS REDEVELOPMENT PROJECT - PAGE 1 - - PAGE 2 - - PAGE 3 - - PAGE 4 - - PAGE 5 - Credit Valley Hospital Priority

More information

83C Questions and Answers

83C Questions and Answers 83C Questions and Answers (2) Section 1.7.4.1 Can the Evaluation Team provide guidance on the scope and amount of information that could be requested from ISO-NE, and the expected magnitude of any associated

More information

Comparing the Standard Form Design-Build Agreements: AIA, ConsensusDocs & DBIA Agreement Forms. Alison Ashford Patrick J. O Connor, Jr.

Comparing the Standard Form Design-Build Agreements: AIA, ConsensusDocs & DBIA Agreement Forms. Alison Ashford Patrick J. O Connor, Jr. Comparing the Standard Form Design-Build Agreements: AIA, ConsensusDocs & DBIA Agreement Forms Practising Law Institute June 25, 2014 New York, New York Alison Ashford Patrick J. O Connor, Jr. Brian Perlberg

More information

Transactional Insurance: Winning Deals and Eliminating Liabilities

Transactional Insurance: Winning Deals and Eliminating Liabilities Mergers & Acquisitions Transactional Insurance: Winning Deals and Eliminating Liabilities Jay Rittberg Americas Head of M&A Insurance, AIG, New York American International Group, Inc. All Rights Reserved.

More information

Table of Contents. The Builders Risk Book

Table of Contents. The Builders Risk Book The Builders Risk Book Table of Contents The Builders Risk Book Preface About the Authors Topical Index Chap. 1--Introduction to Builders Risk Insurance o Knowledge of Construction Industry and Contracts

More information

AUDITING CONSTRUCTION CAPITAL PROJECTS 101

AUDITING CONSTRUCTION CAPITAL PROJECTS 101 AUDITING CONSTRUCTION CAPITAL PROJECTS 101 January 9, 2018 Adam Rouse Managing Consultant acrouse@bkd.com 1 TO RECEIVE CPE CREDIT Participate in entire webinar Answer polls when they are provided If you

More information

OREGON STATE UNIVERSITY CM/GC CONTRACT. (Construction Manager/General Contractor)

OREGON STATE UNIVERSITY CM/GC CONTRACT. (Construction Manager/General Contractor) OREGON STATE UNIVERSITY CM/GC CONTRACT (Construction Manager/General Contractor) THE CONTRACT IS BETWEEN: OWNER: Oregon State University And CONSTRUCTION MANAGER/ GENERAL CONTRACTOR (referred to as Contractor

More information

REQUEST FOR PROPOSAL Project with Construction Manager Services At Risk with Guaranteed Maximum Price

REQUEST FOR PROPOSAL Project with Construction Manager Services At Risk with Guaranteed Maximum Price REQUEST FOR PROPOSAL Project with Construction Manager Services At Risk with Guaranteed Maximum Price Dining Center Replacement Building Project MA-1014 Revised October, 2010 REQUEST FOR PROPOSALS FOR

More information

Document A SP General Conditions of the Contract for Construction, for use on a Sustainable Project, Construction Manager as Adviser Edition

Document A SP General Conditions of the Contract for Construction, for use on a Sustainable Project, Construction Manager as Adviser Edition Document A232 2009 SP General Conditions of the Contract for Construction, for use on a Sustainable Project, Construction Manager as Adviser Edition for the following PROJECT: (Name, and location or address)

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS REQUEST FOR PROPOSALS Covington Point Lift Station Improvements CCE PROJECT NO. 812-100(C) February 21, 2013 PREPARED BY: CITY OF COVINGTON 317 NORTH JEFFERSON AVENUE COVINGTON, LOUISIANA 70433 I. REQUEST

More information

C 051 Engr s Letter to Owner Concerning Bonds and Insurance. Provisions added for the use of a Warranty Bond

C 051 Engr s Letter to Owner Concerning Bonds and Insurance. Provisions added for the use of a Warranty Bond The Engineers Joint Cintract Documents Committee (EJCDC ) has updated the EJCDC Construction Series Documents for 2018. Below is a summary of the revisions that were made to the 2018 edition of the EJCDC

More information

VIRGINIA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR SECTION 109 MEASUREMENT AND PAYMENT

VIRGINIA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR SECTION 109 MEASUREMENT AND PAYMENT SECTION 102.01 PREQUALIFICATION OF BIDDERS of the Specifications is amended as follows: The eighth paragraph is replaced by the following: When the Contractor's actual progress is more than 10 percent

More information

Shutting Down the Construction Project

Shutting Down the Construction Project White Paper Real Estate August 2012 Shutting Down the Construction Project by Robert A. James, Amy L. Pierce and Noa L. Clark Article originally appeared in Perspectives on Real Estate, Spring 2010 edition.

More information

The Battle Royal: AGC Consensus Contracts vs. AIA Documents

The Battle Royal: AGC Consensus Contracts vs. AIA Documents The Battle Royal: AGC Consensus Contracts vs. AIA Documents David A. Ericksen, Esq. Severson & Werson, A Professional Corporation One Embarcadero Center, 26th Floor, San Francisco, CA 94111 Direct Line:

More information

Administrative Policy for Procurement, Bidding, Bid Specifications, Consulting, Request For Qualifications (RFQ), and Evaluation Criteria

Administrative Policy for Procurement, Bidding, Bid Specifications, Consulting, Request For Qualifications (RFQ), and Evaluation Criteria CITY OF LARAMIE Policy Title: Administrative Policy for Procurement, Bidding, Bid Specifications, Consulting, Request For Qualifications (RFQ), and Evaluation Criteria Policy Number: 2014-01 Page 1 of

More information

The Toler Firm LLC A Construction Law Firm Timothy N. Toler September 23, 2015

The Toler Firm LLC A Construction Law Firm Timothy N. Toler September 23, 2015 The Toler Firm LLC A Construction Law Firm Timothy N. Toler September 23, 2015 Negotiating 8 Key Contract Clauses from the Contractor s Perspective (Part 1 of 2) 1 This is the first of a two-part overview

More information

These regulations are issued pursuant to the following Sections of the Municipal Code of Chicago:

These regulations are issued pursuant to the following Sections of the Municipal Code of Chicago: 1. GENERAL PROVISIONS 1.1. Statement of Authority These regulations are issued pursuant to the following Sections of the Municipal Code of Chicago: Section 2-92-410 of the Municipal Code of Chicago establishes

More information

ARTICLE 8: BASIC SERVICES

ARTICLE 8: BASIC SERVICES THE SCOPE OF SERVICES ADDED BY THIS AMENDMENT IS FOR A CM AT RISK PROJECT ONLY. THE SCOPE OF SERVICES SPECIFIED BELOW INCLUDES ARTICLES 8.1, 8.3, 8.4, 8.5, 8.6, 8.7 AND 8.8. THE SERVICES SPECIFIED IN ARTICLE

More information

MINDA INDUSTRIES LIMITED RISK MANAGEMENT POLICY

MINDA INDUSTRIES LIMITED RISK MANAGEMENT POLICY ` MINDA INDUSTRIES LIMITED RISK MANAGEMENT POLICY MINDA INDUSTRIES LIMITED RISK MANAGEMENT POLICY 1. Vision To develop organizational wide capabilities in Risk Management so as to ensure a consistent,

More information

Minding the Gap. Strategic Best Practices for Negotiating Your LTSA with Your TPA by: Richard E. Thompson II, Esq.

Minding the Gap. Strategic Best Practices for Negotiating Your LTSA with Your TPA by: Richard E. Thompson II, Esq. Minding the Gap Strategic Best Practices for Negotiating Your LTSA with Your TPA by: Richard E. Thompson II, Esq. Mercer Thompson LLC 191 Peachtree Street NE Suite 4410 Atlanta, GA. 30303-1756 Ph: 404-577-4200

More information

City Policy & Procedure

City Policy & Procedure City Policy & Procedure Subject: PUBLIC-PRIVATE PARTNERSHIP (P3) POLICY Policy Number: #1011 Effective: September 3rd, 2014 Purpose: The City of Brandon Public-Private Partnership (P3) Policy intends to

More information

I SIGNED THAT? SCARY STORIES & SOLUTIONS

I SIGNED THAT? SCARY STORIES & SOLUTIONS I SIGNED THAT? SCARY STORIES & SOLUTIONS Contract Clauses and Practices That Impact Your Insurance Costs and Bottom Line Geoffrey S. Gavett Gavett, Datt & Barish, P.C. Presented by Chesapeake Region Safety

More information

Primer for Managing Airport Construction Risk

Primer for Managing Airport Construction Risk Primer for Managing Airport Construction Risk ACI Conference Nashville January 15, 2016 Agenda Contract Issues Project Insurance Considerations Controlled Insurance Programs (CIPs) Project Specific GL/Excess

More information

The Transportation Partnership Opportunity Fund

The Transportation Partnership Opportunity Fund The Commonwealth of Virginia The Transportation Partnership Opportunity Fund Assistance Application September 2005 THE COMMONWEALTH OF VIRGINIA All applicants must complete Sections 1 and 2. Private entities

More information

Introduction to Risk for Project Controls

Introduction to Risk for Project Controls Introduction to Risk for Project Controls By Eukeni Urrechaga, PE Quick view at Project Controls Project Controls, like project management, is much an art as it is a science. The secret of good project

More information

CONTRACT GUIDANCE FOR TROUT UNLIMITED CHAPTERS AND COUNCILS.

CONTRACT GUIDANCE FOR TROUT UNLIMITED CHAPTERS AND COUNCILS. CONTRACT GUIDANCE FOR TROUT UNLIMITED CHAPTERS AND COUNCILS. Table of Contents. Table of Contents. 1 I. Introduction. 2 II. Required Reviews and Getting Help. 2 III. Existing TU Policies. 3 IV. TU's Liability

More information

Ahsan Jamal. Case Study IDENTIFYING AND MANAGING KEY RISKS IN CONSTRUCTION PROJECTS

Ahsan Jamal. Case Study IDENTIFYING AND MANAGING KEY RISKS IN CONSTRUCTION PROJECTS Ahsan Jamal Case Study IDENTIFYING AND MANAGING KEY RISKS IN CONSTRUCTION PROJECTS Introduction For the last couple of years, we have seen enormous growth in the construction industry of Pakistan due to

More information

Contract Management in Offshore & Marine, EPCIC and Shipyard

Contract Management in Offshore & Marine, EPCIC and Shipyard An Intensive 5 Day Training Course Contract Management in Offshore & Marine, EPCIC and Shipyard 18-22 Nov 2018, Dubai 28 Apr - 02 May 2019, Dubai 17-21 Nov 2019, Dubai 18-JUL-18 This course is Designed,

More information

Major Projects Advisory Project Leadership Series

Major Projects Advisory Project Leadership Series KPMG GLOBAL ENERGY INSTITUTE Major Projects Advisory Project Leadership Series February 7, 2013 Disclaimer The information contained herein is of a general nature and is not intended to address the circumstances

More information

Change Orders and Consensus Contracts

Change Orders and Consensus Contracts Change Orders and Consensus Contracts Change Orders and Consensus Contracts Greg Long Allen Estes Long Electric Company Gordon & Rees This session is eligible for 2 Continuing Education Hours. For these

More information

Construction Contracting. Agents and Vendors. Contractual Relationships. Agents and Vendors. Agents and Vendors. Outline

Construction Contracting. Agents and Vendors. Contractual Relationships. Agents and Vendors. Agents and Vendors. Outline Construction Contracting Institute for Facilities Management Outline 1. Contractual Relationships 2. Delivery Approaches 3. Bidding & Award Don Guckert The University of Iowa Agents and Vendors Contractual

More information

City of Charlotte Uniform Guidance Procurement Policy

City of Charlotte Uniform Guidance Procurement Policy City of Charlotte Uniform Guidance Procurement Policy I. Objective The objective of this Policy is to establish guidelines that meet or exceed the procurement requirements for purchases of goods (apparatus,

More information

Responsibility Determination for General Contractors Who May Desire to Submit Bid Proposals for the Construction of [PROJECT TITLE]

Responsibility Determination for General Contractors Who May Desire to Submit Bid Proposals for the Construction of [PROJECT TITLE] Responsibility Statement and Questionnaire CITY OF NAPA PUBLIC WORKS DEPARTMENT NAPA, CALIFORNIA [DATE] Responsibility Determination for General Contractors Who May Desire to Submit Bid Proposals for the

More information

Proposed Change to Unsecured Credit Scoring Model

Proposed Change to Unsecured Credit Scoring Model Proposed Change to Unsecured Credit Scoring Model John Jucha Senior Credit Analyst, Corporate Credit Business Issues Committee September 12, 2018, KCC COPYRIGHT NYISO 2018. ALL RIGHTS RESERVED Agenda Background

More information

Project Risk Management Remove, Mitigate, Manage

Project Risk Management Remove, Mitigate, Manage Project Risk Management Remove, Mitigate, Manage Jeri Krug Torsak Project Controls Manager Regional Transportation District Jeri.Torsak@rtd-Denver.com Overall Comments Hire the best and the brightest,

More information

DOMINION BUILDERS, LLC requires that allsubcontractors interested in working with us, complete this pre-qualification form.

DOMINION BUILDERS, LLC requires that allsubcontractors interested in working with us, complete this pre-qualification form. DOMINION BUILDERS, LLC requires that allsubcontractors interested in working with us, complete this pre-qualification form. Complete the form below and email or fax (both the form and all attachments)

More information

Boise State University BSU Policy #6130 Effective Date: March 1998 Revised: July 1, 2010 PURCHASING

Boise State University BSU Policy #6130 Effective Date: March 1998 Revised: July 1, 2010 PURCHASING Boise State University BSU Policy #6130 Effective Date: March 1998 Revised: July 1, 2010 PURCHASING Purpose: To establish policies and procedures governing purchases made with University funds. Additional

More information

GOVERNMENT GO AL A VERNMENT CCOUNTING AL A Monterey County

GOVERNMENT GO AL A VERNMENT CCOUNTING AL A Monterey County GOVERNMENTAL ACCOUNTING Monterey County CONTRACTS/PURCHASING STAFF Mike Derr Debra Bayard DeAundra Lewelling Gina Encallado Tom Skinner Robert Durham Contracts/Purchasing Officer Management Analyst III

More information

Construction Management at Risk. Cheryl Olson, CPPO, C.P.M., FCCN Kristine Rumping, CPPB, FCCM

Construction Management at Risk. Cheryl Olson, CPPO, C.P.M., FCCN Kristine Rumping, CPPB, FCCM Construction Management at Risk Cheryl Olson, CPPO, C.P.M., FCCN Kristine Rumping, CPPB, FCCM 1 Welcome and Introductions Construction Management at Risk Defined Benefits Statutory Guidelines Solicitation

More information

GREENVILLE UTILITIES COMMISSION Greenville, North Carolina REQUEST FOR QUALIFICATIONS. Construction Manager at Risk (CMR) Services

GREENVILLE UTILITIES COMMISSION Greenville, North Carolina REQUEST FOR QUALIFICATIONS. Construction Manager at Risk (CMR) Services GREENVILLE UTILITIES COMMISSION Greenville, North Carolina REQUEST FOR QUALIFICATIONS Construction Manager at Risk (CMR) Services NEW OPERATIONS CENTER A. SCOPE OF SOLICITATION AND TECHNICAL INFORMATION

More information

Lifecycle. https://www.occ.gov/news-issuances/bulletins/2013/bulletin html

Lifecycle. https://www.occ.gov/news-issuances/bulletins/2013/bulletin html Vendor Management Vendor Matchmaking 1. Determining the banks needs and wants. 2. Searching for a vendor to fill that need or want. 3. Request for Proposals 4. Selecting Vendor 5. Contract Negotiations

More information

Ms. Laurel Ross, Acting Commission Secretary and Director

Ms. Laurel Ross, Acting Commission Secretary and Director Diane Roy Vice President, Regulatory Affairs Gas Regulatory Affairs Correspondence Email: gas.regulatory.affairs@fortisbc.com Electric Regulatory Affairs Correspondence Email: electricity.regulatory.affairs@fortisbc.com

More information

The Commonwealth of Massachusetts

The Commonwealth of Massachusetts The Commonwealth of Massachusetts DEPARTMENT OF PUBLIC UTILITIES D.P.U. 13-57 March 29, 2013 Joint Petition of Fitchburg Gas and Electric Light Company d/b/a Unitil, Massachusetts Electric Company and

More information

SUBCONTRACTOR PREQUALIFICATION

SUBCONTRACTOR PREQUALIFICATION Copyright 2012 by the Construction Financial Management Association. All rights reserved. This article first appeared in CFMA Building Profits. Reprinted with permission. BY JAMES L. BLY & J. ANDREW BRACH

More information

Construction Law Update Comparing Contracts-A Review Of The AIA 201 and ConsensusDocs

Construction Law Update Comparing Contracts-A Review Of The AIA 201 and ConsensusDocs Construction Law Update Comparing Contracts-A Review Of The 201 and ConsensusDocs Michael P. Sams, Esq. Kenney & Sams, P.C. Old City Hall 45 School Street Boston, MA 02108 (617)-722-6045 mpsams@kandslegal.com

More information

!!" #$!%&#!" ' (& ')*+!"

!! #$!%&#! ' (& ')*+! !!" #$!%&#!" ' (& ')*+!" '&$,$- 1 OVERVIEW Documents organized in accordance with Construction Specification Institute Table of Contents Relationship between Division 0 and Division 1 ODOT and City Supplement

More information

COPYRIGHTED MATERIAL INDEX

COPYRIGHTED MATERIAL INDEX INDEX Abandonment, cost and damage proof, contractors, 401 Acceleration: constructive, 202-205, 248 elements of, 203, 249-250 delay causes, compensable delays, 241-245 delay causes, excusable delays, 240-241

More information

STANDARD FORM OF CONTRACT FOR CONSTRUCTION MANAGEMENT SERVICES INCLUDING CONSTRUCTION FOR A GUARANTEED MAXIMUM PRICE BETWEEN

STANDARD FORM OF CONTRACT FOR CONSTRUCTION MANAGEMENT SERVICES INCLUDING CONSTRUCTION FOR A GUARANTEED MAXIMUM PRICE BETWEEN STANDARD FORM OF CONTRACT FOR CONSTRUCTION MANAGEMENT SERVICES INCLUDING CONSTRUCTION FOR A GUARANTEED MAXIMUM PRICE BETWEEN THE DEKALB COUNTY BOARD OF EDUCATION AND THE CONSTRUCTION MANAGER Construction

More information

ConsensusDocs Guidebook

ConsensusDocs Guidebook ConsensusDocs Guidebook ConsensusDocs 410 Agreement and General Conditions Between Owner and Design-Builder (Cost of the Work Plus Fee with GMP) August 2013 Edition Page 1 of 10 Copyright 2013 by ConsensusDocs

More information

Understanding Key Construction Contract Provisions ATTORNEYS AND COUNSELORS AT LAW 1

Understanding Key Construction Contract Provisions ATTORNEYS AND COUNSELORS AT LAW 1 Understanding Key Construction Contract Provisions THOMAS O. WILLIAMS, Esquire March 16, 2012 ATTORNEYS AND COUNSELORS AT LAW 1 COPYRIGHT MATERIALS This educational activity is protected by U.S. and Internationalcopyright

More information

Administrative Policies And Procedures

Administrative Policies And Procedures Administrative Policies And Procedures Adm. Policy No: 1.08 Effective Date: April 2000 SUBJECT: SPONSOR: Purchasing of Goods and Services (Over $10,000) Corporate Contracting POLICY: PURPOSE: SCOPE: It

More information

In accordance with 61 O.S. 108 and 115, a sworn statement shall accompany any competitive bid submitted for a public construction contract.

In accordance with 61 O.S. 108 and 115, a sworn statement shall accompany any competitive bid submitted for a public construction contract. State of Oklahoma Capital Assets Management Construction and Properties Bid Affidavits In accordance with 61 O.S. 108 and 115, a sworn statement shall accompany any competitive bid submitted for a public

More information

Project Organization Part 2 & 3 Payment & Award Method

Project Organization Part 2 & 3 Payment & Award Method 1.040/1.401 Project Management Spring 2007 Project Organization Part 2 & 3 Payment & Award Method Dr. SangHyun Lee Department of Civil and Environmental Engineering Massachusetts Institute of Technology

More information

Construction Fundamentals: Avoiding Common Pitfalls

Construction Fundamentals: Avoiding Common Pitfalls Construction Fundamentals: Avoiding Common Pitfalls Matthew M. Hoffman, Esquire Tucker Arensberg, P.C. June 21, 2017 Copyright 2016 Tucker Arensberg, P.C. All Rights Reserved. Program Standardized Contracts

More information

REQUEST FOR PROPOSALS Accounting and Business Advisory Services for Borrowers of the PIDC Contract Line-Of-Credit

REQUEST FOR PROPOSALS Accounting and Business Advisory Services for Borrowers of the PIDC Contract Line-Of-Credit REQUEST FOR PROPOSALS Accounting and Business Advisory Services for Borrowers of the PIDC Contract Line-Of-Credit Issue Date: March 20, 2018 Due Date: April 20, 2018-12:00 Noon This RFP is also available

More information

Manual for the IPP Checklist

Manual for the IPP Checklist Manual for the IPP Checklist Introduction This manual is intended both for the ATI underwriters, for IPPs and sponsors who consider applying for political risk and liquidity risk cover, and for government

More information

REQUEST FOR PROPOSALS PROFESSIONAL CONSULTING SERVICES RFP

REQUEST FOR PROPOSALS PROFESSIONAL CONSULTING SERVICES RFP REQUEST FOR PROPOSALS FOR PROFESSIONAL CONSULTING SERVICES RFP 252018 Town of Scarborough P.O. Box 360 259 U.S. Route One Scarborough, Maine 04070-0360 Released on April 12, 2018 Proposals Due on May 7,

More information