Cost of Service Study and Recommended Rate Design
|
|
- Candice Dalton
- 5 years ago
- Views:
Transcription
1 PEDERNALES ELECTRIC COOPERATIVE, INC. Cost of Service Study and Recommended Rate Design May 11, 2009 Presented by C. H. GUERNSEY & COMPANY Engineers Architects Consultants
2 Cost of Service and Rate Design Study Objectives: Ensure members are charged fair rates Ensure PEC reaches financial objectives Ensure non-discriminatory approach for all members Balance needs of PEC with impact on members Better align PEC with industry standards Encourage energy efficiency The ability to react to changes in power cost 2
3 Cost of Service and Rate Design Study Review: Use standard industry and regulatory practices Select a test year and make adjustments that are known, measurable and continuing in nature Prepare a financial forecast to determine the revenue requirement Develop a cost of service study, allocating the adjusted cooperative expenses to the rate classes as those expenses are incurred Design rates Develop a line extension policy based on allowable investment aligned with rate design 3
4 Cost of Service and Rate Design Study How costs are incurred: PEC builds facilities & provides service based on: Serving each meter no matter how small or how large Building facilities to serve the peak load PEC purchases power and passes through to members its power cost based on: The cost of power is determined by the wholesale supplier s rate 4
5 Cost of Service and Rate Design Study PEC specific considerations: Ability to grow equity, reflecting changes in the reporting of contributed capital Incorporation of forecast for low growth Ability to pay capital credits Establishment of new guidelines for proper implementation of power cost recovery Line extension policy review 5
6 Cost of Service and Rate Design Study Key Findings: Since last rate study, PEC expenses have increased significantly driven by area growth and inflation Current PEC establishment fee and line extension policies are not industry standard Current PEC service availability charge is significantly lower than needed to recover fixed costs The PCRF (power cost recovery factor) is not clearly or directly tied to power costs Service availability cost for Large Power members does not sufficiently consider load factor, efficiency and load size 6
7 Revenue Requirement Adjusted Test Year Proposed Rates Fixed 16% Margin 7% Non-Labor 8% Labor 10% Power Cost 59% Note: Percentages within cooperative electric industry norms 7
8 Billing Change Existing rates and Original Proposed rates Rates included both the PEC Delivery Charge and Power cost with four alternate rate designs First Revision Power cost and PEC Delivery Charges separated with two alternate rate designs Recommended PEC charges, base power cost and power cost adjustment separated into pieces to allow the member to clearly identify how much of the bill is: 1) Service Availability Charge 2) Distribution Energy Charge 3) Base Power Cost at the time rates were established and 4) Power Cost Adjustment (changes in power cost relative to base power cost) 8
9 9
10 How the Power Cost will work: Base power cost is $ per kwh for secondary customers this is fixed until the board authorizes the next general rate change Power Cost Adjustment: LCRA is lowering the wholesale rate which will be reflected on PEC s July 2009 LCRA Bill Base power cost will remain $ per kwh for secondary customers. The reduction in the wholesale rate will flow through to members directly through the Power Cost Adjustment 10
11 11
12 12
13 13
14 Every kwh the member conserves, lowers his or her bill by $ PEC gets a reduction of $ in reduced delivery revenue PEC s delivery costs do not go down Every kwh the member conserves, lowers PEC s margins by $
15 PURPA PURPA requires the cooperative to consider rate designs that encourage energy efficiency. It also requires the cooperative to consider that it remove the throughput incentive and other regulatory and management disincentives to energy efficiency. PEC is committed to promoting conservation and energy efficiency. Recovering distribution wires costs through energy charges is a disincentive to the cooperative to promote energy efficiency. 15
16 16
17 17
18 18
19 Note: Recommended billing includes Base Power Cost of $ per kwh. The Power Cost Adjustment factor will also be applicable to lighting 19
20 Line Extension Policy Proposed procedure Adjust Establishment Fee and add Line Extension policy providing for Contribution in Aid of Construction (CIAC) Proposed Accounting: CIAC reduces capital costs (depreciation and interest) which, over time, improves equity and lowers upward pressure on rates Cost of Service Study determines allowable investment PEC can make to serve each rate class Consistent with other Texas cooperatives 20
21 System Impact Fee / Contribution in Aid of Construction Member pays System Impact Fee of $200 PEC allows $2,000. For the typical residential customer this includes: 1 span of overhead single phase primary line The cost of a single phase transformer Service line from the transformer to the meter The meter Member pays full cost in excess of $2,000 21
22 FUTURE CONSIDERATIONS Time of Use (TOU) rates Wind / Renewable rates Distributed generation 22
Tariff and Business Rules. For Electric Service Provided by. Pedernales Electric Cooperative, Inc.
Tariff and Business Rules For Electric Service Provided by Pedernales Electric Cooperative, Inc. 201 South Avenue F P.O. Box 1 Johnson City, Texas 78636-0001 Adopted 6-15-09; Amended 8-16-10; 9-20-10;
More informationSystem Energy Losses
Power System Engineering, Inc. Evaluating Distribution System Losses Utilizing Data from Deployed AMI and GIS Systems IEEE Rural Electric Power Conference Jeff M. Triplett, P.E. triplettj@powersystem.org
More informationCOMMONWEALTH ELECTRIC COMPANY Cancels M.D.T.E. No. 300 Appendix B-1 Page 1 of 8 TERMS AND CONDITIONS - DISTRIBUTION SERVICE
Page 1 of 8 I. Applicability Appendix B - Line Extension Policy Individual Residential This Policy applies to single family residential Line Extensions. Upon Application for electric service under residential
More informationElectric Line Extension Policy
FOURTH REVISED SHEET NO. 5.1 CANCELLING THIRD REVISED SHEET NO. 5.1 Electric Line Extension Policy Residential and Non-Demand General Service A line extension, for purposes of this policy, shall include
More informationKind of Service: Electric Class of Service: As Applicable Docket No.: U Order No.: 19 Part IV. Rate Schedule No. 60 Effective: 3/31/16
4 th Revised Sheet No. 60.0.1 Schedule Sheet 1 of 14 Replacing: 3 rd Revised Sheet No. 60.0.1 60.0.0. EXTENSION OF FACILITIES 60.0.1. TABLE OF CONTENTS SECTION TITLE SCHEDULE SHEET 60.1. REGULATORY AUTHORITY
More informationSECTION I- UTILITY OPERATIONS
TABLE OF CONTENTS SECTION I- UTILITY OPERATIONS PAGE # 101 Description of Electric Utility Operations....8 101.1 Organization....8 101.2 Type of Service... 8 101.3 Service Area....8 102 Purpose and Scope
More informationEPCOR Energy Alberta Inc Default Supply Price Schedule Applicable to the City of Edmonton Service Territory
EPCOR Energy Alberta Inc. 2007 Default Supply Price Schedule Applicable to the City of Edmonton Service Territory EEAI Default Supply (Edmonton) Page 1 of 10 Default Supply - Price Schedule Non Time-of-Use
More informationRESIDENTIAL SERVICE CLASSIFICATION
Niagara-on-the-Lake Hydro Inc. Page 1 of 10 RESIDENTIAL SERVICE CLASSIFICATION This classification applies to an account taking electricity at 750 volts or less where the electricity is used exclusively
More informationEXECUTIVE SUMMARY OF APPLICATION
Updated: 0-0-0 EB-0-00 Page of EXECUTIVE SUMMARY OF APPLICATION. SCOPE OF APPLICATION Hydro One Networks Inc. ( Hydro One ) is applying for an Order approving the revenue requirement, cost allocation and
More informationBEFORE THE PENNSYLVANIA PUBLIC UTILITY COMMISSION. PENNSYLVANIA PUBLIC UTILITY COMMISSION v. PECO ENERGY COMPANY ELECTRIC DIVISION
PECO ENERGY COMPANY STATEMENT NO. BEFORE THE PENNSYLVANIA PUBLIC UTILITY COMMISSION PENNSYLVANIA PUBLIC UTILITY COMMISSION v. PECO ENERGY COMPANY ELECTRIC DIVISION DOCKET NO. R-01-0001 DIRECT TESTIMONY
More informationFINANCIAL and STATISTICAL REPORT for FEBRUARY 2013
FINANCIAL and STATISTICAL REPORT for FEBRUARY 2013 PUBLIC UTILITY DISTRICT NO. 1 OF OKANOGAN COUNTY TELEPHONE: (509)422-3310 POST OFFICE BOX 912 FAX: (509)422-4020 OKANOGAN, WASHINGTON 98840 COMPARATIVE
More informationMEDINA ELECTRIC COOPERATIVE, INC. RETAIL TARIFF
MEDINA ELECTRIC COOPERATIVE, INC. RETAIL TARIFF Board Approval January 12, 2006 Section 1 Statement of Operations PURPOSE. This tariff has been authorized by the Board of Directors of Medina Electric Cooperative,
More informationFINANCIAL and STATISTICAL REPORT for MARCH 2013
FINANCIAL and STATISTICAL REPORT for MARCH 213 PUBLIC UTILITY DISTRICT NO. 1 OF OKANOGAN COUNTY TELEPHONE: (59)422-331 POST OFFICE BOX 912 FAX: (59)422-42 OKANOGAN, WASHINGTON 9884 COMPARATIVE STATEMENT
More informationNovember 16, Ms. Donna Mitchell, CPA Controller/Treasurer City of Dover 5 East Reed Street Weyandt Hall, Suite 300 Dover, Delaware 19901
Ms. Donna Mitchell, CPA Controller/Treasurer 5 East Reed Street Weyandt Hall, Suite 300 Dover, Delaware 19901 Re: 2015 Electric Cost-of-Service and Rate Design Study Update Project Number 84122 Dear Ms.
More informationTARIFF FOR ELECTRIC SERVICE
TARIFF FOR ELECTRIC SERVICE, TARIFF FOR ELECTRIC SERVICE TABLE OF CONTENTS SECTION I. UTILITY OPERATIONS 101. Description of Electric Utility Operations 101.1 Organization 101.2 Type of Service 101.3 Service
More informationEast Central Energy. Rate schedule C&I. C&I Interruptible Service Effective: March 2018 revenue month Energy bills due in April
East Central Energy Rate schedule C&I C&I Interruptible Service Effective: March 2018 revenue month Energy bills due in April Availability This service is available to all non-residential members who agree
More informationHow Solar-Plus-Storage Can Re-Align Customer and Utility Values. Presented by Brock Mosovsky and Cory Welch
How Solar-Plus-Storage Can Re-Align Customer and Utility Values Presented by Brock Mosovsky and Cory Welch Customer Perspective Mid-day solar gen has significant value Image Source: https://www.caiso.com/documents/flexibleresourceshelprenewables_fastfacts.pdf
More informationElectric Rate Schedule GS-2 General Service - Demand
Page 1 of 5 Applicability This Schedule is applicable to general commercial customers having demands in excess of 20 kilowatts and less than 1,000 kilowatts, and public units for residential occupancy.
More informationDECATUR COUNTY RURAL ELECTRIC MEMBERSHIP CORPORATION GREENSBURG, INDIANA SCHEDULE IPS-I-3 INDUSTRIAL POWER SERVICE - INTERRUPTIBLE
Availability DECATUR COUNTY RURAL ELECTRIC MEMBERSHIP CORPORATION GREENSBURG, INDIANA SCHEDULE IPS-I-3 INDUSTRIAL POWER SERVICE - INTERRUPTIBLE Available in all of the territory served by the Corporation,
More informationONCOR ELECTRIC DELIVERY COMPANY LLC
Tariff for Transmission Service Oncor Electric Delivery Company LLC 1616 Woodall Rodgers Fwy Dallas, Texas 75202-1234 Contents Sheet 1 Revision: Nine Effective Date: November 27, 2017 Page 1 of 2 CONTENTS
More informationONCOR ELECTRIC DELIVERY COMPANY LLC
Tariff for Transmission Service Oncor Electric Delivery Company LLC 1616 Woodall Rodgers Fwy Dallas, Texas 75202-1234 Contents Sheet 1 Revision: Nine Effective Date: November 27, 2017 Page 1 of 2 CONTENTS
More informationPOLICY NO I. INTRODUCTION
POLICY NO. 300.11 SUBJECT: Distributed Generation Policy I. INTRODUCTION A. This policy shall apply to the interconnection and extended parallel operation of all qualifying distributed generation installations
More informationCommunity Solar Rate Rider: Schedule No February 13, 2018
Community Solar Rate Rider: Schedule No. 500 February 13, 2018 1 Community Solar Agenda Design Principles Program Highlights Pricing Methodology Example Customer Impact Conclusion Next Steps 2 Design Principles
More informationENMAX POWER CORPORATION Distribution AUC Rule 005: ANNUAL OPERATIONS FINANCIAL AND OPERATING REPORTING For the Year Ended December 31, 2017 $M
ENMAX POWER CORPORATION Distribution AUC Rule 005: ANNUAL OPERATIONS FINANCIAL AND OPERATING REPORTING For the Year Ended December 31, 2017 $M TABLE OF CONTENTS Schedule Schedule Name Page Sch 1 Summary
More informationCOST ALLOCATION. Cost Allocation Informational Filing Guidelines for Electricity Distributors dated November 15, 2006.
Filed: October 10, 2008 Schedule 1 Page 1 of 2 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 COST ALLOCATION PowerStream submitted a cost allocation informational filing with the Board
More informationINTERMOUNTAIN RURAL ELECTRIC ASSOCIATION RATES AND REGULATIONS
RATES AND REGULATIONS RATES AND REGULATIONS Table of Contents Part I: Part II: Part III: General Statement Definitions and Computation of Time Electric Rate Schedules Part IV: Electric Service Regulations
More informationM E M O R A N D U M. Issue
M E M O R A N D U M EUGENE WATER & ELECTRIC BOARD TO: Commissioners Mital, Simpson, Helgeson, Manning and Brown FROM: Cathy Bloom, Finance Manager; Sue Fahey, Fiscal Services Supervisor; Harvey Hall, Senior
More informationRATE SCHEDULES. Effective Date January 1, 2018
RATE SCHEDULES OF Effective Date January 1, 2018 SHALLOTTE, NORTH CAROLINA RATE SCHEDULES TABLE OF CONTENTS Schedule Name Schedule/Rider Page No. Residential Service R 1 Single-Phase General Service A
More informationSchedule 19 POWER PURCHASES FROM COGENERATION AND SMALL POWER PRODUCTION QUALIFYING FACILITIES
I. APPLICABILITY & AVAILABILITY This Schedule is applicable to any Cogenerator or Small Power Producer (Qualifying Facility), as defined in the Public Utility Regulatory Policies Act of 1978 (PURPA), which
More informationFINANCIAL and STATISTICAL REPORT for JUNE 2014
FINANCIAL and STATISTICAL REPORT for JUNE 214 PUBLIC UTILITY DISTRICT NO. 1 OF OKANOGAN COUNTY TELEPHONE: (59)422-331 POST OFFICE BOX 912 FAX: (59)422-42 OKANOGAN, WASHINGTON 9884 COMPARATIVE STATEMENT
More informationGARKANE ENERGY COOPERATIVE, INC. ELECTRIC SERVICE SCHEDULE SC STATE OF UTAH IMPACT FEES & SERVICE CHARGES
SCHEDULE SC IMPACT FEES & SERVICE CHARGES This schedule sets the amounts for impact fees, various services, and other miscellaneous charges authorized in the Rules and Regulations of either the Utah Public
More informationWashington Utilities and Transportation Commission
Mission Statement: The UTC protects consumers by ensuring that utility and transportation services are fairly priced, available, reliable, and safe. Washington Utilities and Transportation Commission Beginning
More informationSouthern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.
Southern California Edison Revised Cal. PUC Sheet No. 62547-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 57088-E APPLICABILITY Schedule CCA-INFO Sheet 1 Applicable to Community
More informationOntario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB KENORA HYDRO ELECTRIC CORPORATION LTD.
Commission de l énergie de l Ontario DECISION AND RATE ORDER KENORA HYDRO ELECTRIC CORPORATION LTD. Application for an order approving just and reasonable rates and other charges for electricity distribution
More informationTHE NARRAGANSETT ELECTRIC COMPANY POLICY 3 LINE EXTENSION AND CONSTRUCTION ADVANCE POLICY
THE NARRAGANSETT ELECTRIC COMPANY POLICY 3 LINE EXTENSION AND CONSTRUCTION ADVANCE POLICY FOR COMMERCIAL, INDUSTRIAL AND EXISTING RESIDENTIAL CUSTOMERS The terms of this policy shall apply when a commercial,
More informationOntario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB ALGOMA POWER INC.
Commission de l énergie de l Ontario DECISION AND RATE ORDER ALGOMA POWER INC. Application for rates and other charges to be effective January 1, 2019 By Delegation, Before: Jane Scott 1 INTRODUCTION AND
More informationIssues Paper on Proposed Revisions to the Western Power Network Access Arrangement (2017/18 to 2021/22 - AA4)
Issues Paper on Proposed Revisions to the Western Power Network Access Arrangement (2017/18 to 2021/22 - AA4) 31 October 2017 (amended 14 November 2017) (2017/18 to 2021/22 AA4) Economic Regulation Authority
More informationOntario Energy Board RP Board Proposal Regulated Price Plan for Electricity Consumers. Submission of Aegent Energy Advisors Inc.
Ontario Energy Board RP-2004-0205 Board Proposal Regulated Price Plan for Electricity Consumers Submission of Aegent Energy Advisors Inc. December 21, 2004 INTRODUCTION Aegent Energy Advisors Inc. (Aegent)
More informationARKANSAS PUBLIC SERVICE COMMISSION
2 nd Revised Sheet No. 61.0.1 Schedule Sheet 1 of 18 Replacing: 1 st Revised Sheet No. 61.0.1 61.0. TARIFF GOVERNING THE INSTALLATION OF ELECTRIC UNDERGROUND RESIDENTIAL DISTRIBUTION SYSTEMS AND UNDERGROUND
More informationCOST ALLOCATION. Filed: EB Exhibit G1 Tab 3 Schedule 1 Page 1 of INTRODUCTION
Filed: 0-- EB-0-0 Exhibit G Tab Schedule Page of COST ALLOCATION.0 INTRODUCTION 0 Hydro One Networks Inc s total revenue requirement for each of the five years of the Custom Cost of Service (COS) period,
More informationBoard of Directors PO Box 1 Johnson City, TX Regular Meeting
Board of Directors PO Box 1 Johnson City, TX 78636 Regular Meeting www.pec.coop ~ Agenda ~ Call PEC Toll Free 1-888- 554-4732 Monday, April 21, 2014 10:00 AM PEC Headquarters Auditorium 1. Call to Order
More informationThe Cleveland Electric Illuminating Company Cleveland, Ohio P.U.C.O. No. 13 Page 1 of 1. P.U.C.O. No. 13 SCHEDULE OF RATES FOR ELECTRIC SERVICE
The Cleveland Electric Illuminating Company Cleveland, Ohio P.U.C.O. No. 13 Page 1 of 1 P.U.C.O. No. 13 SCHEDULE OF RATES FOR ELECTRIC SERVICE Filed pursuant to Order dated May 27, 2009, in Case No. 08-935-EL-SSO
More informationFINANCIAL and STATISTICAL REPORT for MARCH 2014
FINANCIAL and STATISTICAL REPORT for MARCH 2014 PUBLIC UTILITY DISTRICT NO. 1 OF OKANOGAN COUNTY TELEPHONE: (509)422-3310 POST OFFICE BOX 912 FAX: (509)422-4020 OKANOGAN, WASHINGTON 98840 OPERATING REVENUE
More information20 ANNU 17 AL REPORT
2017 ANNUAL REPORT 2017 Year-End Review Letter To Our Members Being a member-owned electric cooperative, we strive for noticeably superior member services. This is not only one of our strategic goals,
More informationName: City: State: Zip Code: Is the applicant the property owner at the system address? Yes No. City: State: Zip Code: City: State: Zip Code:
Maryland Level 1 Interconnection Request Application Form and Conditional Agreement to Interconnect (Lab Certified Inverter-based Small Generator Facilities Less than 10 kw) Interconnection Applicant Contact
More informationAustin Energy Load Cooperative Program Enrollment Form
Austin Energy Load Cooperative Program Enrollment Form Complete and sign the following enrollment form to participate in the Austin Energy Load Cooperative Program. Please refer to attached Austin Energy
More informationOntario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB NIAGARA PENINSULA ENERGY INC.
Commission de l énergie de l Ontario DECISION AND RATE ORDER NIAGARA PENINSULA ENERGY INC. Application for an order approving just and reasonable rates and other charges for electricity distribution to
More informationOntario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB ORANGEVILLE HYDRO LIMITED
Commission de l énergie de l Ontario DECISION AND RATE ORDER ORANGEVILLE HYDRO LIMITED Application for an order approving just and reasonable rates and other charges for electricity distribution to be
More informationPublic Service Company of New Hampshire Comparison of Rates Effective July 1, 2014 and January 1, 2015
R Customer charge July 1, 2014 $ 12.39 $ 12.39 $ 12.39 All KWH $ 0.04042 $ 0.01786 $ (0.00225) $ 0.00330 $ 0.00055 $ 0.05988 $ 0.09870 $ 0.15858 R Customer charge January 1, 2015 $ 12.50 $ 12.50 $ 12.50
More informationDECISION AND RATE ORDER
DECISION AND RATE ORDER WELLINGTON NORTH POWER INC. Application for rates and other charges to be effective May 1, 2019 By Delegation, Before: Pascale Duguay March 28, 2019 Ontario Energy Board 1 INTRODUCTION
More informationUnited Electric Cooperative Services, Inc.
United Electric Cooperative Services, Inc. s: 1: Utility Operations 2: Rates and Charges 3: Service Rules and Regulations TABLE OF CONTENTS SECTION I UTILITY OPERATIONS 101 Description of Electric Utility
More informationCOMMONWEALTH ELECTRIC COMPANY Cancels M.D.T.E. No. 300 Appendix B-3 Page 1 of 9 TERMS AND CONDITIONS - DISTRIBUTION SERVICE
Page 1 of 9 I. Applicability Appendix B - Line Extension Policy Commercial - Industrial This Policy applies to single-phase or three-phase Line Extensions necessary to serve all Commercial and Industrial
More informationNSTAR ELECTRIC COMPANY d/b/a EVERSOURCE ENERGY SUMMARY OF ELECTRIC SERVICE DELIVERY RATES. M.D.P.U. No C Page 1 of 9
Page 1 of 9 R-1 7 A1/A5 ALL Customer $7.00 $7.00 $7.00 Residential 01/48 Energy (kwh) $0.04563 $0.01833 $0.06396 ($0.00057) $0.00088 ($0.00052) $0.02585 $0.00250 $0.01475 $0.01725 $0.00050 $0.10735 32/66/68
More informationCooperative Electric Rates 2013 Power System Engineering, Inc.
Cooperative Electric Rates Ideas for Responding to Current Challenges Facing Electric Cooperatives Jeff Laslie Senior Financial Analyst Power System Engineering Phone: 317.322.5906 Email: lasliej@powersystem.org
More informationNSTAR ELECTRIC COMPANY d/b/a EVERSOURCE ENERGY SUMMARY OF ELECTRIC SERVICE DELIVERY RATES. M.D.P.U. No E Page 1 of 10
Page 1 of 10 No. Code Area Component Distribution Rate Adjust (1) Distribution Decoupling Transition Transmission (2) System Benefits Recon. Total EEC Energy Delivery R-1 7 A1/A5 ALL Customer $7.00 $7.00
More informationTHE NARRAGANSETT ELECTRIC COMPANY POLICY 1 LINE EXTENSION POLICY FOR INDIVIDUAL RESIDENTIAL CUSTOMERS
THE NARRAGANSETT ELECTRIC COMPANY POLICY 1 LINE EXTENSION POLICY FOR INDIVIDUAL RESIDENTIAL CUSTOMERS When an individual residential customer ( Customer ) requests that a distribution line be extended
More informationTARIFF CHANGES. Effective with meter readings on and after June 1, 2014 the Power Cost Adjustment is $ per kwh for all rates.
TARIFF CHANGES Date: May 21, 2014 Effective Date: June 1, 2014 Changes: Explanation: Power Cost Adjustment Increase Effective with meter readings on and after June 1, 2014 the Power Cost Adjustment is
More informationLong Island Power Authority Fifth Revised Leaf No. 280 PSEG LONG ISLAND LONG ISLAND CHOICE PROGRAM TARIFF LEAVES
Long Island Power Authority Fifth Revised Leaf No. 280 PSEG LONG ISLAND LONG ISLAND CHOICE PROGRAM TARIFF LEAVES Long Island Power Authority Fifth Revised Leaf No. 280 IX. LONG ISLAND CHOICE PROGRAM TABLE
More informationIN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B);
Ontario Energy Board Commission de l énergie de l Ontario IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B); AND IN THE MATTER OF an application by Horizon Utilities Corporation
More informationTraditional Economic Regulation of Electric Utilities
DECEMBER 17, 2018 Traditional Economic Regulation of Electric Utilities U.S. EPA Jessica Shipley Associate jshipley@raponline.org Introductions The Regulatory Assistance Project (RAP) is a global NGO providing
More informationNSTAR ELECTRIC COMPANY d/b/a EVERSOURCE ENERGY SUMMARY OF ELECTRIC SERVICE DELIVERY RATES. M.D.P.U. No C Page 1 of 10
Page 1 of 10 No. Code Area Component Distribution Rate Adjust (1) Distribution Decoupling Transition Transmission (2) System Benefits Recon. Total EEC Energy Delivery R-1 7 A1/A5 ALL Customer $7.00 $7.00
More informationOPTIONAL LARGE GENERAL SERVICE - HIGH OFF-PEAK USE
6100 Neil Road, Reno, Nevada 68th Revised PUCN Sheet No. 79 Tariff No. Electric No. 1 Cancelling 67th Revised PUCN Sheet No. 79 APPLICABLE This schedule is available as an option to Schedule No. GS-3 for
More informationWhy Consumer Advocates Should Support Decoupling
Why Consumer Advocates Should Support Decoupling 2011 ACEEE National Conference on Energy Efficiency as a Resource Tim Woolf September 27, 2011 www.synapse-energy.com 2011 Synapse Energy Economics Inc.
More informationWake Electric Membership Corporation. Wake Forest, North Carolina RATE SCHEDULES
Wake Electric Membership Corporation Wake Forest, North Carolina RATE SCHEDULES Docket EC 47, Sub 43 Effective Date: February 1, 2018 Supersedes: EMC Rates January 1, 2017 TABLE OF CONTENTS RESIDENTIAL
More informationBC HYDRO S RATE DESIGN APPLICATION FARM AND IRRIGATION CUSTOMER ISSUES. Presentation to the BC Cranberry Marketing Commission (BCCMC) June 15, 2015
BC HYDRO S RATE DESIGN APPLICATION FARM AND IRRIGATION CUSTOMER ISSUES Presentation to the BC Cranberry Marketing Commission (BCCMC) June 15, 2015 AGENDA Background on BC Hydro s 2015 Rate Design Application
More informationIN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B);
Ontario Energy Board Commission de l énergie de l Ontario IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B); AND IN THE MATTER OF an application by Hydro Ottawa Limited
More informationGlobal Adjustment. Overview. Christine Woon, P. Eng. Key Account Specialist Customer Care
Global Adjustment Overview Christine Woon, P. Eng. Key Account Specialist Customer Care Understanding Global Adjustment (GA) The GA was established by the Provincial Government in 2005 to cover the cost
More informationPlease direct any inquiries regarding this matter to the undersigned.
B- David Bennett General Counsel and Corporate Secretary Regulatory Department FortisBC Inc. 90 Esplanade Box 0 Trail BC VR L Ph: (0) 77 08 Fax: 866 60 9 David.Bennett@fortisbc.com www.fortisbc.com September
More informationPOLICY NUMBER: 409 EFFECTIVE DATE: 5/26/2015
POLICY NUMBER: 409 EFFECTIVE DATE: 5/26/2015 SUBJECT: OBJECTIVE: POLICY: DEFINITIONS: Distributed Generation/Net-Metering To establish the application procedure and qualification criteria for all customers
More informationPublic Service Company of New Hampshire dba Eversource Energy Comparison of Rates Effective July 1, 2017 and January 1, 2018
R Customer charge July 1, 2017 $ 12.64 $ 12.64 $ 12.64 All KWH $ 0.04125 $ 0.02542 $ (0.00094) $ 0.00356 $ 0.00055 $ 0.06984 $ 0.11660 $ 0.18644 R Customer charge January 1, 2018 $ 12.69 $ 12.69 $ 12.69
More informationEUGENE WATER & ELECTRIC BOARD INDEPENDENT AUDITOR S REPORTS AND FINANCIAL STATEMENTS DECEMBER 31, 2006 AND 2005
INDEPENDENT AUDITOR S REPORTS AND FINANCIAL STATEMENTS DECEMBER 31, 2006 AND 2005 CONTENTS BOARD OF COMMISSIONERS AND OFFICERS 1 PAGE INDEPENDENT AUDITOR S REPORT 2 MANAGEMENT S DISCUSSION AND ANALYSIS
More informationOhio Edison Company Akron, Ohio P.U.C.O. No. 11 Page 1 of 1. P.U.C.O. No. 11 SCHEDULE OF RATES FOR ELECTRIC SERVICE
Ohio Edison Company Akron, Ohio P.U.C.O. No. 11 Page 1 of 1 P.U.C.O. No. 11 SCHEDULE OF RATES FOR ELECTRIC SERVICE Filed pursuant to Order dated May 27, 2009, in Case No. 08-935-EL-SSO et al., before Issued
More informationWESTERN MASSACHUSETTS
Page 1 of 5 PART A - TOTAL DELIVERY RATES (1) Reconciling Rates = Sum of Part B Rates MDPU Service Rate Base Reconciling Total Revenue Energy Efficiency Charge (EEC) Renewable Total Schedule No. Area Component
More informationNAVARRO COUNTY ELECTRIC COOPERATIVE, INC. Distributed Generation Short Form Contract & DG Rider
NAVARRO COUNTY ELECTRIC COOPERATIVE, INC. Distributed Generation Short Form Contract & DG Rider November 1, 2015 Page 1 COOPERATIVE AGREEMENT FOR INTERCONNECTION OF DISTRIBUTED GENERATION SHORT FORM CONTRACT
More informationEPCOR Energy Alberta Inc. ( EEAI ) Price Schedule Applicable to Default Supply Customers within the City of Edmonton
EPCOR Energy Alberta Inc. ( EEAI ) Price Schedule Applicable to Default Supply Customers within the City of Edmonton (EPCOR Distribution and Transmission Inc.) Page 1 of 6 Non Time-of-Use Metered Service
More informationManitoba Hydro 2015 General Rate Application
Manitoba Hydro 2015 General Rate Application OVERVIEW & REASONS FOR THE APPLICATION Darren Rainkie Vice-President, Finance & Regulatory Manitoba Hydro Why Rate Increases are Needed 2 Manitoba Hydro is
More informationRATE RTPD REAL TIME PRICING - DAY AHEAD (RESTRICTED)
1 of 5 AVAILABILITY Available in all areas served from the interconnected system of the Company. APPLICABILITY Applicable to industrial power service when the Consumer s entire electrical requirements
More informationMAR 2017 JAN 2017 DEC 2016 FEB 2017 HOEP*
Ontario Energy Report Q3 Electricity July September Electricity Prices Commodity Commodity cost comprises of two components, the wholesale price (the Hourly Ontario Energy Price) and the Global Adjustment.
More informationELECTRIC RATE SCHEDULE NO. 3-CP-C LARGE GENERAL SERVICE-CP-C
GREENVILLE UTILITIES COMMISSION I. AVAILABILITY ELECTRIC RATE SCHEDULE NO. 3-CP-C LARGE GENERAL SERVICE-CP-C This schedule is available for electric service used by a nonresidential customer where the
More informationATTACHMENT 8 SUMMARY OF FIXED/VARIABLE SPLITS HORIZON UTILITIES RZ
EB-2017-0024 Alectra Utilities Corporation 2018 EDR Application Exhibit 3 Tab 1 Schedule 1 Filed: July 7, 2017 ATTACHMENT 8 SUMMARY OF FIXED/VARIABLE SPLITS HORIZON UTILITIES RZ Summary of Fixed Variable
More informationRatemaking and Financial Incentives to Facilitate Energy Efficiency and Conservation
Ratemaking and Financial Incentives to Facilitate Energy Efficiency and Conservation The Institute for Regulatory Policy Studies Illinois State University Springfield, Illinois Russell A. Feingold Vice
More informationSuperseding Revised Sheet No. 65 REVISED SHEET NO. 65 Effective June 20, 2008 Effective March 1, 2011 RIDER M. Off-Peak and Curtailable Service
Superseding Revised Sheet No. 65 REVISED SHEET NO. 65 RIDER M Off-Peak and Curtailable Service AVAILABILITY: This Rider is available to customers served under rate Schedule J, DS, P, whose maximum measured
More informationNEWMARKET - TAY POWER DISTRIBUTION LTD.
Commission de l énergie de l Ontario DECISION AND RATE ORDER NEWMARKET - TAY POWER DISTRIBUTION LTD. Application for an order approving just and reasonable rates and other charges for electricity distribution
More information2017 COST OF SERVICE, RATE TRAJECTORIES AND BILLING DETERMINANTS. March 6, 2017
2017 COST OF SERVICE, RATE TRAJECTORIES AND BILLING DETERMINANTS March 6, 2017 AGENDA Cost of Service (COS), Trajectories, and Billing Determinants Overview Rate Trajectories & Cost of Service (COS) Results
More informationTITLE 165. CORPORATION COMMISSION CHAPTER 40. STANDARD TERMS OF PURCHASES FROM PURCHASERS OF 100 KW OR LESS PERMANENT RULES
TITLE 165. CHAPTER 40. STANDARD TERMS OF PURCHASES FROM PURCHASERS OF 100 KW OR LESS PERMANENT RULES UPDATED, EFFECTIVE 9-12-2014 Last Amended The Oklahoma Register Volume 31, Number 24 September 2, 2014
More informationResidential General Service Less Than 50 kw General Service - 50 to 999,000 kw 1,000 to 4,999 kw Large Use Standby - General Service kw
Page 1 of 65 Residential This classification refers to an account where the electricity is used exclusively in a separately metered living accommodation. Customers shall be residing in singledwelling units
More informationCOMPANY OVERVIEW ABOUT PEC METERING. Background
COMPANY OVERVIEW ABOUT PEC METERING Background PEC Metering (Pty) Ltd is a private professional company established in 1994, specialising in utility management services and energy management with operations
More informationIN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B);
Ontario Energy Board Commission de l énergie de l Ontario IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B); AND IN THE MATTER OF an application by Hydro One Inc. for
More informationPWC SCHEDULE OF DEPOSITS, FEES AND CHARGES. Table of Contents
PWC SCHEDULE OF DEPOSITS, FEES AND CHARGES Table of Contents I. DEFINITIONS... 2 II. DEPOSITS... 3 A. Establishment of Credit... 3 B. Deposit Refunds... 4 III. CUSTOMER SERVICE FEES AND CHARGES... 4 A.
More informationSCHEDULE 19 LARGE POWER SERVICE
Idaho Power Company First Revised Sheet No. 19-1 I.P.U.C. No. 29, Tariff No. 101 Original Sheet No. 19-1 PUBLIC UTILITIES COMMISSION Jan. 19, 2011 Jan. 1, 2011 Per O.N. 32132 AVAILABILITY Service under
More informationIN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B) (the Act );
Ontario Energy Board Commission de l énergie de l Ontario EB-2013-0196 EB-2013-0187 EB-2013-0198 IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B) (the Act ); AND IN THE
More informationDATE: November 18, 2015 SUBJECT: 2016 Proposed Budgets, Revenue Requirements, and Prices OBJECTIVE: Approval of 2016 Budget and Price Proposals
M E M O R A N D U M EUGENE WATER & ELECTRIC BOARD TO: FROM: Commissioners Mital, Simpson, Helgeson, Manning and Brown Sue Fahey, Finance Manager; Harvey Hall, Deborah Hart and Edward Yan, Senior Financial
More informationIN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B);
Ontario Energy Board Commission de l énergie de l Ontario IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B); AND IN THE MATTER OF an application by Erie Thames Powerlines
More informationOntario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB VERIDIAN CONNECTIONS INC.
Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER VERIDIAN CONNECTIONS INC. Application for rates and other charges to be effective May 1, 2018 By Delegation, Before: Jane
More informationChapter 22. Electric Power Service
Chapter 22 Electric Power Service Part 1 Electric Power Service 22-101. Application 22-102. Deposits 22-103. Payments 22-104. Inspection 22-105. Service Connections 22-106. Relocation of Utility s Facilities
More informationIN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B);
Ontario Energy Board Commission de l énergie de l Ontario IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B); AND IN THE MATTER OF an application by Hydro One Inc. for
More informationNATIONAL ENERGY REGULATOR OF SOUTH AFRICA
In the matter regarding NATIONAL ENERGY REGULATOR OF SOUTH AFRICA DETERMINATION OF THE MUNICIPAL TARIFF GUIDELINE FOR THE FINANCIAL YEAR 2013/14 AND THE REVISION OF MUNICIPAL TARIFF BENCHMARKS DECISION
More informationWake Electric Membership Corporation. Wake Forest, North Carolina RATE SCHEDULES
Wake Electric Membership Corporation Wake Forest, North Carolina RATE SCHEDULES Docket EC 47, Sub 38 Effective Date: July 1, 2014 Supersedes: EMC Rates January 1, 2014 TABLE OF CONTENTS RESIDENTIAL SERVICE...
More informationHalifax Electric Membership Corporation
Rev. 1/1/18 Halifax Electric Membership Corporation Electric Rate Schedules NORTH CAROLINA 33, MARTIN ENFIELD, NORTH CAROLINA Electric Rate Schedules Table of Contents Schedule Description Page Effective
More informationELECTRIC UTILITY RATES
ELECTRIC UTILITY RATES Schedule 7 Schedule 20 Schedule 23 Schedule 24 Schedule 25 Schedule 36 Schedule 37 Schedule 38 Schedule 50 Schedule 80 Schedule 81 Schedule 82 Schedule 90 Schedule 200 Schedule 210
More information