Updated Long Range Capital Outlay Operation/Maintenance Plan Report EXECUTIVE SUMMARY

Size: px
Start display at page:

Download "Updated Long Range Capital Outlay Operation/Maintenance Plan Report EXECUTIVE SUMMARY"

Transcription

1 Updated Long Range Capital Outlay Operation/Maintenance Plan Report EXECUTIVE SUMMARY Purpose of Report: To inform the School Board of the updated Long Range Capital Outlay Operation/Maintenance Plan based on life cycle costs for all District facilities. Building and maintaining schools and other required facilities in which students can achieve their highest potential is a constant process in our growing, changing city. The Sioux Falls School District maintains nearly 3,930,000 square feet of facilities at 39 locations ranging in age from less than one to 95 years old. Over the last 15 years, the District has significantly invested in keeping the conditions of the facilities excellent with three Capital Improvement Plans (CIP I, CIP II and CIP III). The District is now in the first year of a new seven year capital improvement plan which addresses growth, facility standards, security considerations and maintenance needs. The District will continue to evaluate equipment and facility needs while planning ahead for repairs, updates, and growth in population. The updated plan s base year projection cost incorporates two new facilities and is still approximately $400,000 below the initial 2007 plan. Administrative Recommendation to School Board: Acknowledge the updated Long Range Capital Outlay Operation/Maintenance Plan. Report Prepared by: Operational Services February 28, 2011

2 Updated Long Range Capital Outlay Operation/Maintenance Plan Report Purpose of Report: To inform the School Board of the updated Long Range Capital Outlay Operation/Maintenance Plan based on life cycle costs for all District facilities. District Priority Area: Facilities Goal/Strategy: F2.1 Update Long Range Capital Outlay Operation/Maintenance Plan to include new facilities. Explanation: The Sioux Falls School District operates and maintains facilities on 39 sites, consisting of acres of property and 3,927,186 square feet of floor space. The estimated replacement cost of existing District facilities would be in excess of $439,000,000, based on actual bids received on the RF Pettigrew Elementary and Career and Technical Education Academy projects. The District is committed to keeping its facilities in good condition. Over the past 15 years the District has significantly invested in this commitment with three Capital Improvement Plans (CIP I, CIP II and CIP III). The District is currently in its first year of a new seven (7) year capital improvement plan ( plan) that addresses growth, facility standards, security and maintenance needs. The following is a brief summary of each of the previous plans. CIP I planning began in 1995 with a committee consisting of over 40 community and school participants. The committee reviewed all facilities, established facility standards, and then applied the standards to all existing facilities. They looked at operational efficiencies and building consolidation options. The committee then developed an overall plan. A 30 million dollar bond issue was passed to partially fund the plan; capital outlay dollars were used to fund the remainder. Construction began in 1997 and was completed in CIP II planning began in 2001 as the CIP I program was ending. CIP II consisted of 3 parts: the Enrollment Growth Committee looked at the need and location of new construction to accommodate future enrollment growth; the Standards Review Committee reviewed and revised the District s facility standards to meet changing educational needs; and the Preventive Maintenance Committee reviewed and developed standards for facility components and equipment outlining life cycle information. The committees developed an overall plan addressing growth, standards and maintenance. The plan began in 2002 and was completed in Report Prepared by: Operational Services 1 February 28, 2011

3 CIP III planning began when increased growth concerns became apparent for the east and west sides of Sioux Falls. During the process, the School Board expressed concerns relating to elementary building size and additions in the CIP II plan. The final CIP III plan recommended two new elementary schools in lieu of several additions. The plan also addressed several standards and maintenance concerns at Lincoln High School and Howard Wood Field. The CIP II was then reviewed and modified to reduce the plan cost by approximately 5 million dollars. The two plans were scheduled and ran concurrently with completion in The current plan addresses future enrollment growth, facility standards, security related modifications, and also identifies major maintenance related projects throughout the District that will need to be funded in the Capital Outlay budget. The plan also includes the delayed Howard Wood Field grandstand and press box reconstruction project that was delayed in CIP III due to multiple Community Event Center studies. Building components installed during CIP I and II are aging and will increase the need for maintenance dollars in the future. Major buildings such as Roosevelt and Washington high schools while considered new during the CIP I planning are now 20 and 18 years old respectively. Similarly, Memorial and Anne Sullivan are now 15 years old. These buildings required very little maintenance expenditures during the CIP I implementation period. (See attached spreadsheet listing all District facilities showing initial construction date and dates of all related additions). The District is now updating the initial Long Range Capital Outlay Operation/ Maintenance Plan developed in 2007 to provide adequate funding for the operation/maintenance portion of the Capital Outlay budget. The following items were reviewed, compiled and incorporated into this updated Plan: Incorporate life cycle information standards for facility components and equipment developed and installed in CIP construction. Update building listing to include new and expanded facility, building/site components and equipment quantities with dates of installation. Evaluate condition of building/site components and equipment. Establish current repair and/or replacement estimates. Provide projected repair or replacement dates. Develop life cycle average yearly expenditures for the District based on life cycle information. Provide yearly installation matrix of major components. Develop a yearly life cycle average cost summary plan, projecting out 10 years with inflation, not taking into account CIP I, II and III improvements. Develop a yearly life cycle average cost summary plan, projecting out 10 years with inflation, integrating the improvements installed during CIP I, II and III. The plan would gradually increase the capital expenditures over the next 10 years, eventually catching up to the plan developed without CIP I, II and III in year 11. Report Prepared by: Operational Services 2 February 28, 2011

4 This plan shows the District will save over $6,800,000 over the next 10 years as a result of CIP I, II and III improvements. The updated Plan s base year projection incorporates two new facilities and is still approximately $400,000 below the initial 2007 Plan. The reduction is due to the slow down in inflation over this three year period. Summary: As building/site components and equipment continue to age, the District must plan for the future maintenance of these facilities. With almost 3,563,000 square feet of facilities ranging in age from 1916 to 2010, the District will always have maintenance needs. By evaluating all major building components and projecting the life cycle needs of these components, the District is able to continually evaluate and plan for future maintenance needs. The District will always strive to provide facilities and an environment in which students can reach their highest level of achievement. Administrative Recommendation to School Board: Acknowledge the updated Long Range Capital Outlay Operation/Maintenance Plan. Report Prepared by: Operational Services 3 February 28, 2011

5 Updated Long Range Capital Outlay Operation/Maintenance Plan Report ATTACHMENT

Chamber of Commerce Issues Management Council July 12, A community discussion on increasing enrollment in the Sioux Falls School District

Chamber of Commerce Issues Management Council July 12, A community discussion on increasing enrollment in the Sioux Falls School District Chamber of Commerce Issues Management Council July 12, 2018 A community discussion on increasing enrollment in the Sioux Falls School District Current Reality: The Why Since 1990, District enrollment has

More information

Page Item 153 Overview 154 Revenues 156 Expenditures 157 Elementary School Allocation 158 Middle School Allocation 159 High School Allocation 160

Page Item 153 Overview 154 Revenues 156 Expenditures 157 Elementary School Allocation 158 Middle School Allocation 159 High School Allocation 160 - Page Item 153 Overview 154 Revenues 156 Expenditures 157 Elementary School Allocation 158 Middle School Allocation 159 High School Allocation 160 Special Education Allocation 161 Operational Services

More information

Page Item 174 Overview 175 Revenue 177 Expenditures 178 Elementary School Allocation 180 Middle School Allocation 181 High School Allocation 182

Page Item 174 Overview 175 Revenue 177 Expenditures 178 Elementary School Allocation 180 Middle School Allocation 181 High School Allocation 182 Page Item 174 Overview 175 Revenue 177 Expenditures 178 Elementary School Allocation 180 Middle School Allocation 181 High School Allocation 182 Operational Services/Central Services/Axtell Park School

More information

Page Item 172 Overview 173 Revenue 175 Expenditures 176 Elementary School Allocation 177 Middle School Allocation 178 High School Allocation 179

Page Item 172 Overview 173 Revenue 175 Expenditures 176 Elementary School Allocation 177 Middle School Allocation 178 High School Allocation 179 Page Item 172 Overview 173 Revenue 175 Expenditures 176 Elementary School Allocation 177 Middle School Allocation 178 High School Allocation 179 Special Education Allocation 180 Operational Services/Central

More information

Page Item 165 Overview 167 Revenue 168 Expenditures 169 Elementary School Allocation 171 Middle School Allocation 173 High School Allocation 175

Page Item 165 Overview 167 Revenue 168 Expenditures 169 Elementary School Allocation 171 Middle School Allocation 173 High School Allocation 175 Page Item 165 Overview 167 Revenue 168 Expenditures 169 Elementary School Allocation 171 Middle School Allocation 173 High School Allocation 175 Special Education Allocation 176 Operational Services Allocation

More information

ANNUAL REPORT OF DEVELOPER FEES

ANNUAL REPORT OF DEVELOPER FEES ANNUAL REPORT OF DEVELOPER FEES School District Name: Tulare Joint Union High School Reporting Period: July 1, 2015 through June 30, 2016 Date Report Made Available to the Public: November 10, 2016 Date

More information

Overview of Public Schools CIP

Overview of Public Schools CIP Overview of Public Schools CIP The Board of Education CIP includes public school construction, addition and modernization projects as well as other school related projects. The primary sources of funding

More information

PREPARING THE HOBBS FIRE DEPARTMENT FOR ENDING SOCIAL SECURITY PARTICIPATION

PREPARING THE HOBBS FIRE DEPARTMENT FOR ENDING SOCIAL SECURITY PARTICIPATION 1 PREPARING THE HOBBS FIRE DEPARTMENT FOR ENDING SOCIAL SECURITY PARTICIPATION STRATEGIC MANAGEMENT OF CHANGE BY: Steve Henry Hobbs, Fire Department Hobbs, New Mexico An applied research project submitted

More information

Follow this and additional works at: Part of the Business Commons

Follow this and additional works at:  Part of the Business Commons University of South Florida Scholar Commons College of Business Publications College of Business 1-1-2007 Sources of funding and categories of spending for the school district of Hillsborough County :

More information

Long Range Financial Plan

Long Range Financial Plan Long Range Financial Plan 2018 Table of Contents SUMMARY... 2 BUDGETING PHILOSOPHY AND CURRENT BUDGET... 3 FORECASTING ASSUMPTIONS... 4 HISTORICAL & PROJECTED DATA... 5 Revenues... 5 Local Revenue... 5

More information

Auxiliary Periodic Report Instructions

Auxiliary Periodic Report Instructions Auxiliary Periodic Report Instructions Overview Auxiliary Periodic Reports provide Periodic projections of revenues, expenses, transfers-in and transfers-out. After Auxiliary Periodic Reports are prepared,

More information

PORTA CUSD Bluejay Rd, Petersburg IL Tel Fax PORTA AT A GLANCE FY 2018

PORTA CUSD Bluejay Rd, Petersburg IL Tel Fax PORTA AT A GLANCE FY 2018 PORTA CUSD 202 17651 Bluejay Rd, Petersburg IL 62675 Tel 217-632-3803 Fax 217-632-3221 www.porta202.org PORTA AT A GLANCE FY 2018 Data within this document is a snapshot of the PORTA district s financial

More information

June 18, 2018 Lansing Community College Fiscal Year 2019 Proposed Budget Narrative. Introduction

June 18, 2018 Lansing Community College Fiscal Year 2019 Proposed Budget Narrative. Introduction June 18, 2018 Lansing Community College Fiscal Year 2019 Proposed Narrative Introduction The FY2019 process started in December 2017 when the Financial Services division invited all college employees to

More information

CITY COUNCIL STUDY SESSION MEMORANDUM

CITY COUNCIL STUDY SESSION MEMORANDUM City and County of Broomfield, Colorado CITY COUNCIL STUDY SESSION MEMORANDUM To: From: Prepared by: Mayor and City Council Charles Ozaki, City and County Manager David Allen, Deputy Director of Public

More information

Loveland City Schools

Loveland City Schools Financial Report Five Year Forecast Update May, 2016 Public Finance Resources, 2015 1 Table of Contents Table of Contents 2 Executive Summary 3 PAGE # Revenue Overview 4 1.010 General Property Tax (Real

More information

Photos by Susie Fitzhugh. Levies 2019 Community Meetings April 2, 3, 23, 24 and 26, 2018

Photos by Susie Fitzhugh. Levies 2019 Community Meetings April 2, 3, 23, 24 and 26, 2018 Photos by Susie Fitzhugh Levies 2019 Community Meetings April 2, 3, 23, 24 and 26, 2018 Levies 2019 Community Meetings AGENDA Welcome/Introductions/Power Point presentation Operations Levy planning Building

More information

DOWNTOWN DORAL CHARTER ELEMENTARY SCHOOL, INC. FINANCIAL STATEMENTS WITH INDEPENDENT AUDITORS REPORTS THEREON JUNE 30, 2017

DOWNTOWN DORAL CHARTER ELEMENTARY SCHOOL, INC. FINANCIAL STATEMENTS WITH INDEPENDENT AUDITORS REPORTS THEREON JUNE 30, 2017 FINANCIAL STATEMENTS WITH INDEPENDENT AUDITORS REPORTS THEREON JUNE 30, 2017 TABLE OF CONTENTS Report of Independent Auditors on Basic Financial Statements and Supplementary Information 1-2 Management's

More information

HOSPITALITY HIGH SCHOOL OF WASHINGTON, DC, A PUBLIC CHARTER SCHOOL AUDITED FINANCIAL STATEMENTS AND SUPPLEMENTARY INFORMATION

HOSPITALITY HIGH SCHOOL OF WASHINGTON, DC, A PUBLIC CHARTER SCHOOL AUDITED FINANCIAL STATEMENTS AND SUPPLEMENTARY INFORMATION HOSPITALITY HIGH SCHOOL OF WASHINGTON, DC, A PUBLIC CHARTER SCHOOL AUDITED FINANCIAL STATEMENTS AND SUPPLEMENTARY INFORMATION YEARS ENDED JUNE 30, 2014 AND 2013 Table of Contents Page Independent Auditor

More information

Monthly School Board Standing Committee Meetings

Monthly School Board Standing Committee Meetings Monthly School Board Standing Committee Meetings October 10, 2017 5:30 P.M. Audit/Budget/Finance 5:40 P.M. Joint Audit/Budget/Finance & Personnel/Policy 5:55 P.M. Personnel/Policy Please Note: Committee

More information

Financial Section III

Financial Section III Financial Section III ANNUAL BUDGET SECTIONS EXECUTIVE SUMMARY ORGANIZATIONAL SECTION FINANCIAL SECTION INFORMATIONAL SECTION s are financial planning and decision-making documents. They contain information

More information

Los Angeles Unified School District Page 1 of 2

Los Angeles Unified School District Page 1 of 2 Los Angeles Unified School District 333 South Beaudry Ave, Los Angeles, CA 90017 File #: Rep-393-13/14, Version: 1 Amendment to the Facilities Services Division Strategic Execution Plan to Define and Approve

More information

General Fund Appropriation Resolution for Adoption By The Board of Education of White Pigeon Community Schools

General Fund Appropriation Resolution for Adoption By The Board of Education of White Pigeon Community Schools General Fund Appropriation Resolution for Adoption By The Resolved, that the General Fund Budget for White Pigeon Community Schools for the fiscal year 2016-2017 be adopted as follows. ACCOUNT 2014-2015

More information

of 5. Non-Instructional/Business Operations BUDGET PLANNING AND DEVELOPMENT

of 5. Non-Instructional/Business Operations BUDGET PLANNING AND DEVELOPMENT 1 of 5 BUDGET PLANNING AND DEVELOPMENT Budget planning and development for the District is an integral part of program planning so that the annual operating budget may effectively express and implement

More information

TABLE OF CONTENTS ACADEMIC AFFAIRS COMMITTEE Committee Chairman Krier. Following the Meeting of the Finance and Planning Committee

TABLE OF CONTENTS ACADEMIC AFFAIRS COMMITTEE Committee Chairman Krier. Following the Meeting of the Finance and Planning Committee TABLE OF CONTENTS ACADEMIC AFFAIRS COMMITTEE Committee Chairman Krier Date: May 8, 2003 Time: Place: Following the Meeting of the Finance and Planning Committee Board Meeting Room, Ninth Floor, Ashbel

More information

RETURN ON INVESTMENT ANALYSIS

RETURN ON INVESTMENT ANALYSIS PORT EVERGLADES 2014 MASTER/VISION PLAN APPENDIX J: ROI AND NPV CALCULATION TABLES PRESENTED BY RETURN ON INVESTMENT ANALYSIS The Port Everglades master planning and vision process utilized a project decision-matrix

More information

Hillsborough County Population and Employment Projections and Allocations DECEMBER 2017

Hillsborough County Population and Employment Projections and Allocations DECEMBER 2017 Hillsborough County Population and Employment Projections and Allocations DECEMBER 2017 Presentation Overview Overview of the Allocation Process Population and Employment Projections Trend Analysis 2045

More information

SPARTANBURG COUNTY SCHOOL DISTRICT FIVE DUNCAN, SOUTH CAROLINA FINANCIAL STATEMENTS AND SUPPLEMENTARY INFORMATION

SPARTANBURG COUNTY SCHOOL DISTRICT FIVE DUNCAN, SOUTH CAROLINA FINANCIAL STATEMENTS AND SUPPLEMENTARY INFORMATION DUNCAN, SOUTH CAROLINA FINANCIAL STATEMENTS AND SUPPLEMENTARY INFORMATION FOR THE FISCAL YEAR ENDED JUNE 30, 2014 FINANCIAL STATEMENTS AND SUPPLEMENTARY INFORMATION FOR THE FISCAL YEAR ENDED JUNE 30,

More information

Town of Barnstable Town Council

Town of Barnstable Town Council Town of Barnstable Town Council 367 Main Street, Village of Hyannis, MA 02601 508.862.4738 508.862.4770 E-mail: council@town.barnstable.ma.us www.town.barnstable.ma.us Councillors: Jessica Rapp Grassetti

More information

ROBIN KLENK, TREASURER

ROBIN KLENK, TREASURER BASIC FINANCIAL STATEMENTS FOR THE FISCAL YEAR ENDED JUNE 30, 2012 ROBIN KLENK, TREASURER BASIC FINANCIAL STATEMENTS TABLE OF CONTENTS Table of Contents... 1 Accountant s Compilation Report... 2 Management

More information

Welcome Colome Consolidated School Public Meeting. January 17, 2019 January 21, 2019

Welcome Colome Consolidated School Public Meeting. January 17, 2019 January 21, 2019 Welcome School Public Meeting January 17, 2019 January 21, 2019 How Did We Get Here? August 2017 started talking to Architects and Construction Managers We retained an architectural firm to design a Conceptual

More information

General Fund Appropriation Resolution for Adoption By The Board of Education of White Pigeon Community Schools

General Fund Appropriation Resolution for Adoption By The Board of Education of White Pigeon Community Schools General Fund Appropriation Resolution for Adoption By The Resolved, that the General Fund Budget for White Pigeon Community Schools for the fiscal year 2016-2017 be revised as follows. ACCOUNT 2015-2016

More information

RICHLAND-BEAN BLOSSOM COMMUNITY SCHOOL CORPORATION

RICHLAND-BEAN BLOSSOM COMMUNITY SCHOOL CORPORATION RICHLAND-BEAN BLOSSOM COMMUNITY SCHOOL CORPORATION CAPITAL PROJECTS FUND PLAN for the years 2017-2018-2019 September 19, 2016 Public Hearing CAPITAL PROJECTS PLAN (2017-2018-2019) September 19, 2016 RICHLAND-BEAN

More information

City of Falls Church

City of Falls Church 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 Meeting Date: 10-8-14 (Work Session) City of Falls Church Title: ORDINANCE TO AMEND ORDINANCE 1918 AND ORDINANCE 1919, REGARDING

More information

VASHON ISLAND SCHOOL DISTRICT No Fiscal Year-End Report & F

VASHON ISLAND SCHOOL DISTRICT No Fiscal Year-End Report & F VASHON ISLAND SCHOOL DISTRICT No. 402 Fiscal Year-End Report & F-196 2013-2014 To equip every student to engage, thrive, and contribute within an ever-changing world. Presented to the Vashon Island School

More information

PACKAGE PLAN JULY 5, 2017

PACKAGE PLAN JULY 5, 2017 General Conference of Seventh-Day Adventists West Central Africa Division WAD Business Professional Convention Afrikland Hotel Grand Bassam, Cote d Ivoire PACKAGE PLAN JULY 5, 2017 TOM EVANS CPA, NAD TREASURER/CFO

More information

University of Hawai i Operating Budget for Fiscal Year August 2, 2018 B&F Committee

University of Hawai i Operating Budget for Fiscal Year August 2, 2018 B&F Committee University of Hawai i Operating Budget for Fiscal Year 2018-19 August 2, 2018 B&F Committee Overview 1. Revenues are projected to increase by 1.9% compared to estimated FY18 actuals: General Fund increasing

More information

CAPE GEORGE COLONY CLUB MARINA RESERVES

CAPE GEORGE COLONY CLUB MARINA RESERVES CAPE GEORGE COLONY CLUB MARINA RESERVES Port Townsend, Washington STANDARD LEVEL 3 RESERVE STUDY UPDATE WITHOUT A SITE VISIT With funding recommendations for the 2019 fiscal year Issued October, 2018 Next

More information

LIST OF ABBREVIATIONS... i BRIEF INTRODUCTION TO CAGRD Enrollment and Activation... 5

LIST OF ABBREVIATIONS... i BRIEF INTRODUCTION TO CAGRD Enrollment and Activation... 5 TABLE OF CONTENTS LIST OF ABBREVIATIONS... i BRIEF INTRODUCTION TO CAGRD... 1 1. Enrollment and Activation... 5 2. Replenishment Obligation Incurred and Replenishment Obligation Completed... 7 3. Water

More information

Capital Fund Mechanisms and the Condition of Facilities in Rural and Small Schools

Capital Fund Mechanisms and the Condition of Facilities in Rural and Small Schools 79 Research in Rural Education, Volume 3, Number 2, 1985 Capital Fund Mechanisms and the Condition of Facilities in Rural and Small Schools DAVID S. HONEYMAN l AND G. KENT STEWART l Rural and small schools

More information

Transition Planning Case Study

Transition Planning Case Study Transition Planning Case Study This case study, set in the winter of 2012/2013, is based on an actual farming operation in Manitoba. To ensure the privacy of the owners operations, the names of the owners

More information

WEB APPENDIX 8A 7.1 ( 8.9)

WEB APPENDIX 8A 7.1 ( 8.9) WEB APPENDIX 8A CALCULATING BETA COEFFICIENTS The CAPM is an ex ante model, which means that all of the variables represent before-the-fact expected values. In particular, the beta coefficient used in

More information

PLEASANT GROVE, UTAH TRANSPORTATION IMPACT FEE FACILITIES PLAN AND ANALYSIS

PLEASANT GROVE, UTAH TRANSPORTATION IMPACT FEE FACILITIES PLAN AND ANALYSIS PLEASANT GROVE, UTAH TRANSPORTATION IMPACT FEE FACILITIES PLAN AND OCTOBER 2012 PREPARED BY: LEWIS YOUNG ROBERTSON & BURNINGHAM IMPACT FEE CERTIFICATION Impact Fee Facilities Plan (IFFP) Certification

More information

Measure K Bond Program Update. August 18, 2009 Board of Education Workshop

Measure K Bond Program Update. August 18, 2009 Board of Education Workshop Measure K Bond Program Update August 18, 2009 Board of Education Workshop Presentation Summary I. Implementation Update II. Current Project Updates III. Project Prioritization IV. Master Program Budget

More information

COMMUNITY INVESTMENT PLAN FOR FISCAL YEARS 2016 TO 2021

COMMUNITY INVESTMENT PLAN FOR FISCAL YEARS 2016 TO 2021 COMMUNITY INVESTMENT PLAN FOR FISCAL YEARS 2016 TO 2021 PUBLIC SCHOOLS: New Construction, Additions, Modernizations Fiscal Year 2016 2017 2018 2019 2020 2021 Allocation Complete Project Cost Career and

More information

CHAPTER 4: FIVE-YEAR CONSTRUCTION PLAN

CHAPTER 4: FIVE-YEAR CONSTRUCTION PLAN CHAPTER 4: FIVE-YEAR CONSTRUCTION PLAN 4.1 Overview 4.2 Master Plan Summary 4.3 List of Projects in Order of Priority 4.4 Cumulative Capacities and Loads for each Space Type 4.5 The Capacity of Existing

More information

Summary of Significant Forecast Assumptions and Accounting Policies For the Fiscal Years Ending June 30, 2018 through 2022

Summary of Significant Forecast Assumptions and Accounting Policies For the Fiscal Years Ending June 30, 2018 through 2022 ONTARIO LOCAL SCHOOL DISTRICT RICHLAND COUNTY 1 Summary of Significant Forecast Assumptions and Accounting Policies For the Fiscal Years Ending June 30, 2018 through 2022 Note 1 - Nature and Limitations

More information

5120 West Goldleaf Circle, Suite 400 Los Angeles, CA (877)

5120 West Goldleaf Circle, Suite 400 Los Angeles, CA (877) 512 West Goldleaf Circle, Suite 4 Los Angeles, CA 956 (877) 531-6284 www.mathnasium.com Franchised Units: 786 In Business Since: 22 Royalty: 1% Company-Owned Units: 11 Average Franchise Fee: $49K IFA Member:

More information

STATE OF KANSAS AID TO SCHOOL DISTRICTS

STATE OF KANSAS AID TO SCHOOL DISTRICTS kslegres@klrd.ks.gov 68-West Statehouse, 300 SW 10th Ave. Topeka, Kansas 66612-1504 (785) 296-3181 FAX (785) 296-3824 http://www.kslegislature.org/klrd STATE OF KANSAS AID TO SCHOOL DISTRICTS This memorandum

More information

School Finance Basics and District Support Operations. Budgeting. When Do You Begin?

School Finance Basics and District Support Operations. Budgeting. When Do You Begin? School Finance Basics and District Support Operations The Legislature implemented the school funding formula that exists in Arizona today starting in the 1980-1981 school year. The formula was developed

More information

Eric Hawkes, Director, University Recreation, North Carolina State University

Eric Hawkes, Director, University Recreation, North Carolina State University To: Cc: Eric Hawkes, Director, University Recreation, North Carolina State University Dr. Lisa Zapata, Vice Provost, Student Development, Health and Wellness, North Carolina State University Lisa Johnson,

More information

Mr. Rick Wood, Director of Business Operations

Mr. Rick Wood, Director of Business Operations October 12, 2011 TO: FROM: RE: Administrative Council Mr. Rick Wood, Director of Business Operations Budget Guidelines for the 2012-2013 Budget At the October 11, 2011 meeting, the Board of Education approved

More information

Overview of Public Schools CIP

Overview of Public Schools CIP Overview of Public Schools CIP The Public Schools Community Investment Plan (CIP) includes school construction, additions and modernizations, as well as other school related projects. For more than a decade

More information

THE NOYCE FOUNDATION (A California Nonprofit Private Foundation) *** FINANCIAL STATEMENTS. Years Ended December 31, 2006 and 2005

THE NOYCE FOUNDATION (A California Nonprofit Private Foundation) *** FINANCIAL STATEMENTS. Years Ended December 31, 2006 and 2005 *** FINANCIAL STATEMENTS Years Ended December 31, 2006 and 2005 TABLE OF CONTENTS Pages INDEPENDENT AUDITOR'S REPORT 1 FINANCIAL STATEMENTS: Statements of Financial Position 2 Statements of Activities

More information

There hasn t been a bond referendum in our district since building the original facility in 1977.

There hasn t been a bond referendum in our district since building the original facility in 1977. The architect concept in this document was drawn by Howard & Helmer Architects (H&H) after several community, staff and board meetings over the last year. This concept plan was chosen after reviewing 5

More information

12/01/2010 Page 1 of 8

12/01/2010 Page 1 of 8 12/01/2010 Page 1 of 8 MOWING TRIMMING OF HIGHWAY RIGHT-OF-WAY DESCRIPTION: This work shall consist of removal and disposal of litter and the mowing and trimming of the highway rights of way for vegetation

More information

Multi-Year Financial Analysis FY2015 FY2019. November 2013

Multi-Year Financial Analysis FY2015 FY2019. November 2013 Multi-Year Financial Analysis FY2015 FY2019 November 2013 University of Maine System Multi Year Financial Analysis Fiscal Years 2015 to 2019 Table of Contents I. Introduction... 2 II. Developing the Multi

More information

BASIC FINANCIAL STATEMENTS CITY SCHOOL DISTRICT OF SYRACUSE, NEW YORK JUNE 30, 2013

BASIC FINANCIAL STATEMENTS CITY SCHOOL DISTRICT OF SYRACUSE, NEW YORK JUNE 30, 2013 BASIC FINANCIAL STATEMENTS CITY SCHOOL DISTRICT OF SYRACUSE, NEW YORK (A COMPONENT UNIT OF THE CITY OF SYRACUSE, NEW YORK) TABLE OF CONTENTS INDEPENDENT AUDITOR S REPORT 1-3 MANAGEMENT S DISCUSSION AND

More information

FIR RIDGE II CONDOMINIUM

FIR RIDGE II CONDOMINIUM FIR RIDGE II CONDOMINIUM BELLINGHAM, WASHINGTON UPDATE WITHOUT SITE VISIT FEBRUARY 2014 FOR USE WITH THE FEBRUARY 2012 RESERVE STUDY PREPARED BY: DENISE DANA, RESERVE SPECIALIST M. ARCH, REGISTERED ARCHITECT

More information

Levies February 2010 Supporting Seattle s Children. Seattle School Board Work Session September 2, 2009

Levies February 2010 Supporting Seattle s Children. Seattle School Board Work Session September 2, 2009 Levies February 2010 Supporting Seattle s Children Seattle School Board Work Session September 2, 2009 Agenda Introduction and Overview Operations Levy BMAR BTA III Board Guidelines BTA III Project / BTA

More information

Long Range Financial Forecast

Long Range Financial Forecast Long Range Financial Rebecca Underhill Assistant City Manager/ Director of Finance 300 W Walker League City, TX 77573 Main: 281.554.1000 Direct: 281.554.1368 April 17, 2017 www.leaguecity.com City Manager,

More information

Request for Proposal

Request for Proposal Merced Fire Department Standards of Cover Request for Proposal Michael R. Wilkinson, Fire Chief Merced Fire Department 99 E. 16 th Street Merced, CA 95340 SECTION 1 INTRODUCTION The Merced Fire Department

More information

Missouri Western State University A Component Unit of the State of Missouri

Missouri Western State University A Component Unit of the State of Missouri Accountants Report and Financial Statements (Including Reports Required Under OMB-133) June 30, 2005 and 2004 June 30, 2005 and 2004 Contents Management s Introduction... 1 Independent Accountants Report

More information

TAUSSIG DEVELOPMENT IMPACT FEE JUSTIFICATION STUDY CITY OF ESCALON. Public Finance Public Private Partnerships Urban Economics Clean Energy Bonds

TAUSSIG DEVELOPMENT IMPACT FEE JUSTIFICATION STUDY CITY OF ESCALON. Public Finance Public Private Partnerships Urban Economics Clean Energy Bonds DAVID TAUSSIG & ASSOCIATES, INC. DEVELOPMENT IMPACT FEE JUSTIFICATION STUDY CITY OF ESCALON B. C. SEPTEMBER 12, 2016 Public Finance Public Private Partnerships Urban Economics Clean Energy Bonds Prepared

More information

School Advocacy Committee - Finance

School Advocacy Committee - Finance School Advocacy Committee - Finance February 24, 2013 6:00 p.m. Tonight s Agenda Welcome and Introductions Tour of the Northern Middle Facility Finance Presentation Human Resources Presentation Small Group

More information

DIOCESE OF FORT WAYNE - SOUTH BEND RETIREMENT PLAN FOR LAY TEACHERS AND LAY EMPLOYEES SUMMARY PLAN DESCRIPTION

DIOCESE OF FORT WAYNE - SOUTH BEND RETIREMENT PLAN FOR LAY TEACHERS AND LAY EMPLOYEES SUMMARY PLAN DESCRIPTION DIOCESE OF FORT WAYNE - SOUTH BEND RETIREMENT PLAN FOR LAY TEACHERS AND LAY EMPLOYEES SUMMARY PLAN DESCRIPTION DECEMBER, 2000 INTRODUCTION Retirement may seem far off--or it may be just around the corner.

More information

Pamwin Component Accounting User Manual December 2009

Pamwin Component Accounting User Manual December 2009 Pamwin Component Accounting User Manual December 2009 For support phone 020 8254 5581 email Pamwin@m3h.co.uk 5 Commonside East Mitcham Surrey CR4 2QA Pamwin Component Accounting User Manual 1 of 17 Contents

More information

Historical Perspective:

Historical Perspective: Historical Perspective: 16.55 square miles 17 miles north of center city Philadelphia in Bucks County Enrollment peaked at over 17,000 students in the 1970s (5,700 today) Birthplace of the American Space

More information

Bid No /7 Release Date: January 25, 2019

Bid No /7 Release Date: January 25, 2019 Houston County School District Rehobeth elementary Lunchroom Kitchen a/c Replacement Request for Proposal (RFP) Bid Opening Date & Time: Friday February 15, 2019 9:00am (Central Time) I. MISCELLANEOUS

More information

Summary of Significant Forecast Assumptions and Accounting Policies For the Fiscal Years Ending June 30, 2013 through 2017

Summary of Significant Forecast Assumptions and Accounting Policies For the Fiscal Years Ending June 30, 2013 through 2017 ONTARIO LOCAL SCHOOL DISTRICT RICHLAND COUNTY 1 Summary of Significant Forecast Assumptions and Accounting Policies For the Fiscal Years Ending June 30, 2013 through 2017 Note 1 - Nature and Limitations

More information

Based on most current budget data and actual expenditures through October 31, 2017

Based on most current budget data and actual expenditures through October 31, 2017 Based on most current budget data and actual expenditures through October 31, 2017 Financial Reporting Periods Enrollment Average Daily Attendance LCFF Expenditures Multi-Year Projections Minimum Wage

More information

August 2000 Report No Purpose. Background

August 2000 Report No Purpose. Background The Florida Legislature Special Report August 2000 Report No. 00-02 Lake County School District Needs Better Planning and Communication to Address Budget Problems at a glance The Lake County School District

More information

Fast Tools & Resources. Machinery Financing

Fast Tools & Resources. Machinery Financing Machinery Financing With this program, the user can evaluate the financial implications of four types of financing alternatives. A net present value and cash-flow schedule are generated for a: Purchase

More information

Fiscal Year (FY13) Operating Budget and Capital Budget Overview

Fiscal Year (FY13) Operating Budget and Capital Budget Overview Approved by President Rush Fiscal Year 2012-2013 (FY13) Operating Budget and Capital Budget Overview Background A university budget represents the complex interchange between revenue streams that support

More information

Kansas 2017 Legislative Changes

Kansas 2017 Legislative Changes (Rev. 12-8-17) Kansas 2017 Legislative Changes INCOME TAX RATES SB 30 NOTICE 17-02 EFFECTIVE TAX YEAR 2017 TY 2017 Income Tax Rates Married Filing Joint $0 - $30,000 (2016 2.7%) 2.90% $30,001 - $60,000

More information

BEST FINANCIAL MANAGEMENT PRACTICES SELF-ASSESSMENT INSTRUMENT FOR FLORIDA SCHOOL DISTRICTS

BEST FINANCIAL MANAGEMENT PRACTICES SELF-ASSESSMENT INSTRUMENT FOR FLORIDA SCHOOL DISTRICTS REPORT NO. 97-34 BEST FINANCIAL MANAGEMENT PRACTICES SELF-ASSESSMENT INSTRUMENT FOR FLORIDA SCHOOL DISTRICTS January 1998 Florida Legislature Office of Program Policy Analysis and Government Accountability

More information

USD 483 Kismet-Plains

USD 483 Kismet-Plains USD 483 Kismet-Plains Budget General Information (characteristics of district) Supplemental Information for Tables in Summary of Expenditures KSDE Website Information Available Summary of Expenditures

More information

Cumberland Comprehensive Plan - Demographics Element Town Council adopted August 2003, State adopted June 2004 II. DEMOGRAPHIC ANALYSIS

Cumberland Comprehensive Plan - Demographics Element Town Council adopted August 2003, State adopted June 2004 II. DEMOGRAPHIC ANALYSIS II. DEMOGRAPHIC ANALYSIS A. INTRODUCTION This demographic analysis establishes past trends and projects future population characteristics for the Town of Cumberland. It then explores the relationship of

More information

DAT MEETING NOTES # 1

DAT MEETING NOTES # 1 DAT MEETING NOTES # 1 MOA ARCHITECTURE Design Advisory Team 821 17 th Street, Suite 400 Denver, Colorado 80202 303.308.1190 Phone 303.308.1197 Fax Project: Superior Elementary School Date: 11 November

More information

Capital Projects Fund

Capital Projects Fund The capital projects fund is used to account for the resources used for the acquisition, construction, or improvement of major capital facilities, including those of the enterprise fund. The capital projects

More information

( Mai/lie EXETER TOWNSHIP SCHOOL DISTRICT ANNUAL FINANCIAL REPORT. Year Ended June 30, Certified Public Accountants and Business Consultants

( Mai/lie EXETER TOWNSHIP SCHOOL DISTRICT ANNUAL FINANCIAL REPORT. Year Ended June 30, Certified Public Accountants and Business Consultants ANNUAL FINANCIAL REPORT Year Ended June 30, 2014 ( Mai/lie Expulls~ B~yond Th~ Numb~rs Certified Public Accountants and Business Consultants INTRODUCTORY SECTION TABLE OF CONTENTS YEAR ENDED JUNE 30, 2014

More information

FINANCIAL STATEMENTS WITH INDEPENDENT AUDITOR'S REPORTS THEREON JUNE 30, 201Q

FINANCIAL STATEMENTS WITH INDEPENDENT AUDITOR'S REPORTS THEREON JUNE 30, 201Q A CHARTER SCHOOL AND COMPONENT UNIT OF THE DISTRICT SCHOOL BOARD OF VOLUSIA COUNTY, FLORIDA FINANCIAL STATEMENTS WITH INDEPENDENT AUDITOR'S REPORTS THEREON JUNE 30, 201Q CONTENTS Page Management's Discussion

More information

CHAPTER 3: PROJECT PRIORITIES AND SELECTION

CHAPTER 3: PROJECT PRIORITIES AND SELECTION CHAPTER 3: PROJECT PRIORITIES AND SELECTION 3.1 Overview 3.2 Steps in the Capital Outlay Process 3.3 State Funding Configurations 3.4 Priority Criteria for Capital Outlay 3.5 Types of Projects 3.6 Community

More information

Executive Summary December 31, 2016 City of Fargo, North Dakota

Executive Summary December 31, 2016 City of Fargo, North Dakota Executive Summary December 31, 2016 www.eidebailly.com Executive Summary Year Ended December 31, 2016 Purpose of the Executive Summary The City receives audited financial statements each year, however

More information

PUBLIC NOTICE OF TAX EQUITY AND FISCAL RESPONSIBILITY ACT HEARING

PUBLIC NOTICE OF TAX EQUITY AND FISCAL RESPONSIBILITY ACT HEARING Tuesday, April 4, 2017 PUBLIC NOTICE OF TAX EQUITY AND FISCAL RESPONSIBILITY ACT HEARING The Illinois Finance Authority (the IFA ) will hold a public hearing as required by Section 147(f) of the Internal

More information

SPARTANBURG COUNTY SCHOOL DISTRICT FIVE DUNCAN, SOUTH CAROLINA FINANCIAL STATEMENTS AND SUPPLEMENTARY INFORMATION

SPARTANBURG COUNTY SCHOOL DISTRICT FIVE DUNCAN, SOUTH CAROLINA FINANCIAL STATEMENTS AND SUPPLEMENTARY INFORMATION DUNCAN, SOUTH CAROLINA FINANCIAL STATEMENTS AND SUPPLEMENTARY INFORMATION FOR THE FISCAL YEAR ENDED JUNE 30, 2012 FINANCIAL STATEMENTS AND SUPPLEMENTARY INFORMATION FOR THE FISCAL YEAR ENDED JUNE 30,

More information

Westwood Country Club Redevelopment

Westwood Country Club Redevelopment Westwood Country Club Redevelopment Economic and Fiscal Impact March, 2014 Prepared for: Mensch Capital Partners Prepared By: Kent Gardner, Ph.D. Project Director 1 South Washington Street Suite 400 Rochester,

More information

ACTUARIAL REPORT CANADA STUDENT LOANS PROGRAM ON THE AS AT 31 J ULY Published in. qwewrt. of the Superintendent of Financial Institutions Canada

ACTUARIAL REPORT CANADA STUDENT LOANS PROGRAM ON THE AS AT 31 J ULY Published in. qwewrt. of the Superintendent of Financial Institutions Canada Published in 2005 ACTUARIAL REPORT ON THE CANADA STUDENT LOANS PROGRAM AS AT 31 J ULY 2004 u Office of the Superintendent of Financial Institutions Canada Bureau du surintendant des institutions financières

More information

Level 3 Reserve Study without a Site a Site Visit Visit

Level 3 Reserve Study without a Site a Site Visit Visit Level 3 Reserve Study without a Site a Site Visit Visit We offer two types of reports for a Level 3 Reserve Study with a Site Visit, RS-3 - Standard Reserve Study without a site visit SMRS-3 - Statutory

More information

Hillsborough County Population and Employment Projections and Allocations DECEMBER 2017

Hillsborough County Population and Employment Projections and Allocations DECEMBER 2017 Hillsborough County Population and Employment Projections and Allocations DECEMBER 2017 Presentation Overview Overview of the Allocation Process Population and Employment Projections Trend Analysis 2045

More information

Lincoln Educational Services Corporation Reports Second Quarter 2007 Results

Lincoln Educational Services Corporation Reports Second Quarter 2007 Results Lincoln Educational Services Corporation Reports Second Quarter 2007 Results West Orange, New Jersey, August 7, 2007 Lincoln Educational Services Corporation (Nasdaq: LINC) ( Lincoln ) today reported second

More information

SCHOOL BUDGET NEWS. Elmira City School District. May School District Annual Budget Vote and School Board Election May 17, 2016

SCHOOL BUDGET NEWS. Elmira City School District. May School District Annual Budget Vote and School Board Election May 17, 2016 SCHOOL BUDGET NEWS Elmira City School District May 2016 School District Annual Budget Vote and School Board Election May 17, 2016 VOTING INFO: WHEN: May 17 Dear Community Members, On behalf of the Board

More information

BERKELEY UNIFIED SCHOOL DISTRICT Measure I Construction Oversight Committee

BERKELEY UNIFIED SCHOOL DISTRICT Measure I Construction Oversight Committee BERKELEY UNIFIED SCHOOL DISTRICT Measure I Construction Oversight Committee AGENDA November 17, 2011 6:00 7:30 PM 1720 Oregon Street Berkeley, CA 94703 (510) 644-6066 1. Call to Order 2. Approval of Meeting

More information

CONTE SCHOOL RENOVATION

CONTE SCHOOL RENOVATION North Adams Public Presentation April 2013 CONTE SCHOOL RENOVATION OUTLINE Introduction Massachusetts School Building Authority & Process Schematic Design: Site Plan School Images Floor Plans Cost Estimate

More information

School District No. 45 (West Vancouver)

School District No. 45 (West Vancouver) Annual Budget School District No. 45 (West Vancouver) June 30, 2016 June 30, 2016 Table of Contents Bylaw... 1 Annual Budget - Revenue and Expense - Statement 2... 2 Annual Budget - Changes in Net Financial

More information

Overview of Public Schools CIP

Overview of Public Schools CIP Overview of Public Schools CIP The Public Schools Community Investment Plan (CIP) includes school construction, such as additions and modernizations, as well as other school-related projects. School construction

More information

South Tech Preparatory Academy, Inc. Basic Financial Statements and Additional Information For the Year Ended June 30, 2015

South Tech Preparatory Academy, Inc. Basic Financial Statements and Additional Information For the Year Ended June 30, 2015 South Tech Preparatory Academy, Inc. Basic Financial Statements and Additional Information For the Year Ended June 30, 2015 Table of Contents Independent Auditor s Report 1 2 Management's Discussion and

More information

Fiscal Impact Analysis

Fiscal Impact Analysis Fiscal Impact Analysis Waterfront West Newburyport, MA March 22, 2017 Prepared By Fougere Planning & Development, Inc. Prepared For Newburyport Manager, LLC FOUGERE PLANNING & DEVELOPMENT, Inc. Mark J.

More information

Approval of FY18 Capital Budget and FY19-FY23 Capital Improvement Program Request

Approval of FY18 Capital Budget and FY19-FY23 Capital Improvement Program Request Agenda Item Number ITEM TYPE: Action BOARD AGENDA ITEM TITLE: Approval of FY18 Capital Budget and FY19-FY23 Capital Improvement Program Request DATE: October 19, 216 OVERVIEW: The attached FY18 Capital

More information

CAPITAL BUDGET FY 2020 & CAPITAL IMPROVEMENT PROGRAM FY REQUEST

CAPITAL BUDGET FY 2020 & CAPITAL IMPROVEMENT PROGRAM FY REQUEST CAPITAL BUDGET FY 22 & CAPITAL IMPROVEMENT PROGRAM FY 221-225 REQUEST Board of Education 1/1/218 BOARD OF EDUCATION Bob E. Lord, President Donna M. Sivigny, Vice-President Virginia R. Harrison, Member

More information

The Cost of Ownership of New Mexico s Public School Facilities

The Cost of Ownership of New Mexico s Public School Facilities The Cost of Ownership of New Mexico s Public School Facilities Robert A. Gorrell Director Public School Facilities Authority 1312 Basehart SE, Suite 200 Albuquerque, NM 87106 505.843.6272 rgorrell@nmpsfa.org

More information