MONTE CARLO SIMULATION AND PARETO TECHNIQUES FOR CALCULATION OF MULTI- PROJECT OUTTURN-VARIANCE
|
|
- Pamela Lamb
- 6 years ago
- Views:
Transcription
1 MONTE CARLO SIMULATION AND PARETO TECHNIQUES FOR CALCULATION OF MULTI- PROJECT OUTTURN-VARIANCE Keith Futcher 1 and Anthony Thorpe 2 1 Colliers Jardine (Asia Pacific) Ltd., Hong Kong 2 Department of Civil and Building Engineering, Loughborough University, UK Cleland and King in 1986 described a scenario in which project data could also be used within a project management MIS for the purposes of portfolio management. Their approach assumed equal treatment in terms of data management. This research is a refinement of their model. A combination of Monte Carlo techniques and Pareto effects are used to simulate the probabalistic range of outturn performance for the portfolio in terms of expenditure if the high spend projects are managed to achieve the best ten percent of the range of performance achieved by the firm. The range of probable outturn variance between the planned and the actual expenditures of a portfolio of projects is calculated assuming that the probability distribution representing the best ten percent of the range of empirical performance achieved in reality is applied to increasing percents of high-spending projects in the portfolio. Keywords: Monte-Carlo simulation, multi-projects, Pareto technique, project management. INTRODUCTION The management of a portfolio of projects with the intention of achieving an optimum outcome is commonplace in construction management. Cleland and King published in 1983 a functional specification for a Project_Management_Information_System (PMIS) that also served as a tool for the management of a portfolio of projects. They did not define an optimum outcome for the portfolio instead they proposed that the project level data used to measure the performance of each project in a portfolio of projects could also be used to provide aggregated measures of performance for the entire portfolio. They saw this capability as a further benefit to be derived from the use of the information pipeline that could be created within computerized project management processes. On the basis of this, managing a portfolio of projects as a byproduct of project management appears to offer considerable added value to the use of a computerized PMIS. Advances in Information Technology (IT) since 1983 have increased the practicality of this proposition. However, there remain difficulties in this arrangement: especially the burden of data administration. According to the principles of Cleland and King, data must be collected at a uniform level of detail at frequent intervals, and then processed quickly to produce consistent snapshots of overall progress for use in a trend analysis. Such systems are intensive users of project level data that is costly to capture. They require the same range of detailed data, at the same frequency, from all the projects in the portfolio irrespective of their significance. 1 Keith_Futcher@cj-group.com 2 A.Thorpe@lboro.ac.uk Futcher, K and Thorpe, A (2001) Monte Carlo simulation and Pareto techniques for calculation of multi-project outturn-variance. In: Akintoye, A (Ed.), 17th Annual ARCOM Conference, 5-7 September 2001, University of Salford. Association of Researchers in Construction Management, Vol. 1,
2 Futcher and Thorpe The aggregation of this fine detailed data shows macro performance overall, but it does not easily operate in reverse to indicate at the higher end of the pipeline the micro problems existing within deviant projects. What is intriguing about Cleland and King s proposition is that twenty years on it is not apparently a commonplace approach adopted by the construction industry for the management of their portfolio of projects (Futcher and Rowlinson, 1998). AN ALTERNATIVE APPROACH An alternative to the Cleland and King proposition is to apply Pareto heuristics to focus attention on the lesser number of significant projects within the portfolio and to ensure that their performance is excellent because of their impact on the results for the portfolio overall. The methodology described in this paper is one element of a larger piece of research that sets out to prove that the satisfactory performance achieved by the lesser number of significant projects is a reasonable approximation of the outcome for the portfolio overall, other things being equal. Horner (1991, 1992) has taken a similar approach with construction estimating. He proposes using heuristics, based on the cost significance of items within the Bill of Quantities, that substantially reduce the overall estimating effort with only a minor loss of accuracy overall. In a similar manner, this research investigates the effectiveness of managing a portfolio of projects by basing success primarily on the outcome of the projects that have a high impact. It tests this proposition using empirical data. Empirical Data The empirical data is taken from the audited accounts of the Category A public works projects of the Public Works Programme (PWP) of the Hong Kong Government (HKG SAR) over the ten year period to Category A projects have a planned expenditure within the financial year. The data for each financial year is managed as a separate entity by the HKG SAR and used in that manner in this research i.e., as ten successive data sets of consistent heritage. This is a good source of data because it is a large portfolio that contains a diverse range of public works. Look to Table 1 for an indication of the range of this diversity. The attributes of the data within each data set are measured to indicate the representation and the consistency of the projects within the ten data sets. A good degree of representation exists within each portfolio of projects in terms of: Heads of Expenditure these are a sub-division of the PWP into broad groups of construction classification that correspond to the disciplines of each of the public works departments. Categories of work these are the type of architectural/engineering work according to a HKG SAR classification index of seventy eight types of public works. The diversity within each of the ten successive portfolios of projects is displayed in Table 2. The planned expenditure per annum changes as the project progresses, thus making the portfolios of projects more than ninety eight percent mutually exclusive, year on year. The expenditure of the funds budgeted per annum for each project is taken as a measure of satisfactory project achievement. The outcome performance for each project in these terms is the difference between the actual expenditure compared to the planned expenditure, i.e., it is an outturn variance that is expressed as a percent of the planned expenditure, or in differential Hong Kong Dollars. 826
3 Multi-project outturn-variance Table 1: General statistics of the annual portfolios within the period of this analysis Portfolio statistics in terms of project planned expenditure (HK$ 000s) Year Project Nos Low Value High Value Mode Value Mean Value Median Value , ,543 2, , ,035 2, , ,164 2, ,482, ,550 2, ,580, ,533 1, ,838, ,075 1, ,935, , ,777, ,012 1, , , , ,902 2,684 Table 2: Indicators of the diversity of projects within annual PWP portfolio of projects, Aspects of Diversity Financial Years beginning By Heads of Expenditure 702 Port and Airport Development % of planned exp Buildings % of planned exp Drainage % of planned exp Civil Engineering % of planned exp Highways % of planned exp New Towns % of planned exp Waterworks % of planned exp Housing < % of planned exp < By Categories of work Nos of types % (of 78 types)
4 Futcher and Thorpe Table 3 shows the Spearman s Rank Correlation between the dollar value of the planned expenditure compared to the dollar value of outturn variance of the projects and also the percent outturn variance of the projects. These indicate that empirical outcome achieved by the portfolios overall was not sensitive to the performance achieved by the significant projects. Table 3: Correlation Coefficients between values of Amended Estimate and Outturn variance Year Correlation coefficients of Planned Exp Vs Outturn variance $ Vs Outturn variance $ Vs % Outturn variance TESTING A SIGNIFICANCE APPROACH TO THE MANAGEMENT OF A PORTFOLIO OF PROJECTS The portfolio management approach used by the Government of Hong Kong is to individually manage all of the projects so that each one achieves a close match with its spending target. If this is successful, the total spending target for all the projects becomes a close match with the overall budgeted expenditure. The research proposes a more selective approach whereby the management effort given to each project is varied to ensure a high degree of success for the high impact projects and a routine outcome for the less significant remainder of the projects. In case of the HKG SAR the projects of greatest planned expenditure are deemed as being the more significant. Mathematical validation of a significance approach The mathematical validation assumes that the significant projects within the portfolio perfectly achieve their planned expenditure, i.e., zero outturn variance. The mathematical calculation is carried out for increasing numbers of significant projects in terms of percent of the portfolio. The constituent projects in the portfolio of projects are ordered in descending value of planned expenditure. The effect is calculated of an increasing percent of the highest value projects achieving a zero value outturn variance, whilst the outturn variance for the remainder of the projects is unchanged. The relationship between the percent of significant projects that achieves a perfect outcome, and the overall success achieved by the portfolio overall, is then considered. The methodology is shown in Figure 1. Stochastic validation of a significance approach The mathematical validation is an idealistic approach as it is improbable that the highest value (high impact) projects will all achieve a perfect outturn of nil variance. The stochastic validation assumes that if the significant projects in the portfolio are given sufficient management attention they can achieve the premier performance exhibited within the portfolio. Using Monte Carlo methods the stochastic outcome of each significant project can be derived from a probability curve that represents the better project performance found within the portfolios of projects. This curve is derived from the frequency distribution of project outturn variance i.e., for all the 828
5 Multi-project outturn-variance projects in the portfolio by a best fitting to the ten continuous probability distributions listed in Table 4. Data Set = 1989/90 Calc 'Original Outturn' for whole population Place projects in descending order of planned expenditure For projects n = 0 to n = p where p =population of dataset Let n = n + 1 n > p Yes Next data set till = 1999/2000 then END for project n, let 'actual exp' = 'planned exp' Calc revised Outturn for whole population Calc percent = 'High Impact' projects by value, (Sum 'Planned Exp' for n = 1 to n = n divided by Sum 'Planned Exp' for n =1 to n = p) Print percent 'High Impact' projects by No and by Value Print Percent improvement to Outturn Next n Figure 1: Flow chart of mathematical method for evaluating the impact of project significance on portfolio outturn This method of curve fitting chooses values for the parameters of the probability distributions to better fit to the data set. The results of the distribution fitting to each of the ten standard, continuous distributions are tested using the standard goodness of fit methods shown in Table
6 Futcher and Thorpe Table 4: Continuous Probability Distributions used for best fit comparison with the empirical frequency data. Continuous Probability Typical application Curve Triangular Simplistic: used if minimum, maximum and most likely values are known, assumed intermediary linear variation Weibull Complex: used to represent physical effects Normal Used to describe natural phenomena or uncertain variables Beta Used to represent variability over a fixed range Logistic Used to represent growth Extreme Value Used to describe the largest value of a response over a period of time i.e., flood flows. Exponential Used to describe events recurring at random in time Gamma Used to describe a wide range of physical quantities i.e., pollutant quantities Lognormal Used where values are positively skewed Uniform Simplistic: all values between the minimum and the maximum occur with equal likelihood. Table 5: Tests for degree of fit of empirical data to probability distributions Goodness of fit test Typical application (ref Sargent and Wainwright, 1998) Chi square Gauges the general accuracy of the fit. Generally, a value greater than 0.5 indicates a close fit Kolmogorov Smirnov Is essentially the largest vertical distance between the two cumulative distributions. Generally, a value less than 0.03 indicates a close fit Anderson Darling Resembles Kolmogrov Smirnov except that it weights the differences between the two distributions at their tails greater than at their mid ranges. This method is used when a better fit is needed at the extreme tails of the distribution. Generally, a value less than 1.5 indicates a close fit If, the curve fitting of the empirical values of outturn variance from each of the ten data sets is a close fit to one of the continuous probability distributions, particularly within the range of zero to twenty percent outturn variance, then this part of the probability distribution is used in the Monte Carlo analyses. If not, the curve fitting exercise is repeated for the empirical values of outturn variance within the zero to twenty percent outturn variance range of higher performance. The best fit probability distribution derived from this calculation is used in the Monte Carlo analysis to assign a stochastic value of high performance outturn variance in the case of the significant projects in the portfolio. The curve fitting and the Monte Carlo analysis is performed by using Crystal Ball Version 4.0 software by Decisioneering ( com). Figure 2 shows some of the probability distributions available within the software for curve fitting. Figure 3 is an example of a probability distribution derived from curve fitting for the empirical dataset and used in the Monte Carlo analysis in this research. 830
7 Multi-project outturn-variance Figure 2: Example the range of standard probability distributions within Crystal Ball software Figure 3: Probability distribution of the best 20% performance achieved in the empirical data from the HKG SAR. Crystal Ball allows selected variables in an Excel spreadsheet to be assigned a stochastic value according to a user selected probability distribution. In this case, the values of the outturn variance for each of the significant projects are randomly assigned a stochastic value from within the Beta distribution to represent the achievable range of higher performance found within the portfolio: other projects are unchanged. This random selection occurs for each significant project and for each trial carried out by the software, in this case one thousand trials. A frequency distribution of portfolio outturn is derived from these trials. Figure shows an example of the output from this research. 831
8 Futcher and Thorpe The methodology for a stochastic validation of the significance approach is shown in Figure 5. For the purposes of this research it is assumed that the significant projects can achieve the best ten percent of the two-hundred percent range of outturn variance found within the empirical data. The effect is calculated, of an increasing percentage of the highest value projects achieving an actual expenditure that represents this better performance whilst the outturn variance for the remainder of the projects is unchanged. The relationship between greater success for high impact projects compared to the achievement for the portfolio as a whole is then considered. Figure 4: Monte Carlo generated output of the outturn variance of expenditure for the HKG SAR PWP empirical data for 1% of significant projects. Table 6 is an example of the results derived by this method of analysis for the PWP portfolio of projects of the HKG SAR. It contains the actual results achieved by the empirical data, compared to the mathematical modelled results, and compared to the 95%, 90%, 75% and 50% percentile outcome derived from the Monte Carlo analyses. The Ave mean is the average of the mean values derived from each of the one thousand Monte Carlo trials for each significant project in the analysis. In this case, the Ave-mean outturn variance in the significant projects is 8.93% compared the 0.0% assumed for the mathematical modelling. CONCLUSIONS The management approach of the HKG SAR is to achieve a perfect outcome for all the projects in the PWP. The empirical data from the HKG SAR showed that in they achieved an under spend of twenty five percent of budgeted expenditure. Theoretically this outturn variance could have been reduced by 10%, 12%, or 21% percent, if it were possible for correspondingly 5%, 10%, or 20% of the high spend projects to achieve a perfect outcome. However, it is unrealistic to expect an ideal outcome to be achieved by a large number of high spend projects. 832
9 Multi-project outturn-variance Data Set = 1989/90 START Calc 'Original Outturn' for whole population Next Data Set Place projects in descending order of planned expenditure Calculate the Frequency Distribution of Percent Outturn Variance For projects n = 0 to n = p Let p = Integer(Population/100) Let r = r + 1, where r = 1 to 20 % Select probability distribution that is best-fit to the 0% to 20% range Percent Outturn Variance Let n = n + 1 Use Monte Carlo analysis to set Percent Outturn Variance for project no. = n Data set = 1998/1999? No n > p END Run Monte Carlo to calculate revised Outturn for whole population Calculate percent = 'High Impact' projects by value, (Sum 'Planned Exp' for n = 1 to n = n divided by Sum 'Planned Exp' for n =1 to p) Print 'Percent High Impact' projects by $Value and No.projects Print Percent Outturn Variance Yes Let r = r + 1, Let p = p*r r > 20? Figure 5: Flow chart of stochastic method for evaluating the impact of project significance on portfolio outturn The combination of Pareto and Monte Carlo methodology described here sets more realistic aspirations for the same portfolio of projects. Using this approach, there is an evens probability that the outturn variance of the portfolio will be improved by 5%, 6%, or 10%. If, the corresponding 5%, 10%, or 20% of the high spend projects achieve an outcome that falls within the best 10% of the range of empirical performance achieved by the projects within the portfolio. On the basis of results of using this methodology over ten sets of empirical data, heuristics are proposed for the application of this significant project approach to the management of portfolios of projects in the manner of Cleland and King. No 833
10 Futcher and Thorpe Table 6: Comparison of the improved outtrun for the portfolio due to the impact of the outturn variance for 1% to 20% significant projects according to 'actual', 'ideal' and 'stochastic' scenarios % No % Value Outturn percent of target expenditure achieved projects Actual Ideal Monte Carlo Percentiles modified % % Ave-Mean 95% 90% 75% 50% outturn variance per project 1% 25% % 38% % 45% % 51% % 55% % 59% % 62% % 65% % 67% % 69% % 71% % 72% % 74% % 76% % 77% % 78% % 79% % 81% % 82% % 83% REFERENCES Cleland, D. and King, W. (1983) Systems Analysis and Project Management. Singapore: McGraw-Hill International Futcher, K.G. and Rowlinson, S. (1998) Information technology used by Hong Kong contractors. The life-cycle of construction IT innovations ~ Technology transfer from research to practice, CIB proceedings CIB/W (ed. Bork, B and Jagbeck, C). Sweden: Royal Institute of Technology Futcher, K.G. and Rowlinson, S. (1999) Strategic use of IT by the Contractors and Consultants in the Hong Kong construction industry. Proceedings CIB/W78 (June, 1999). Vancouver. Hong Kong Government (1990) Annual Report of the Director of Accounting Services and the Accounts of Hong Kong for the year ended 31 March Hong Kong: Government Printer. Horner, R.M.W. (1991) Iterative estimating can double Estimator's output. Construction Management Research Unit, University of Dundee. Horner, R.M.W. (1992) Measurement, valuation and control, of civil engineering works SERC Research Grant No GR/F/ Sargent, R., and Wainwright, E. (1998) Crystal Ball Version 4.0 User Manual. Denver: Decisioneering 834
Appendix A. Selecting and Using Probability Distributions. In this appendix
Appendix A Selecting and Using Probability Distributions In this appendix Understanding probability distributions Selecting a probability distribution Using basic distributions Using continuous distributions
More informationHow to Consider Risk Demystifying Monte Carlo Risk Analysis
How to Consider Risk Demystifying Monte Carlo Risk Analysis James W. Richardson Regents Professor Senior Faculty Fellow Co-Director, Agricultural and Food Policy Center Department of Agricultural Economics
More informationSENSITIVITY ANALYSIS IN CAPITAL BUDGETING USING CRYSTAL BALL. Petter Gokstad 1
SENSITIVITY ANALYSIS IN CAPITAL BUDGETING USING CRYSTAL BALL Petter Gokstad 1 Graduate Assistant, Department of Finance, University of North Dakota Box 7096 Grand Forks, ND 58202-7096, USA Nancy Beneda
More informationContents. An Overview of Statistical Applications CHAPTER 1. Contents (ix) Preface... (vii)
Contents (ix) Contents Preface... (vii) CHAPTER 1 An Overview of Statistical Applications 1.1 Introduction... 1 1. Probability Functions and Statistics... 1..1 Discrete versus Continuous Functions... 1..
More informationExcelSim 2003 Documentation
ExcelSim 2003 Documentation Note: The ExcelSim 2003 add-in program is copyright 2001-2003 by Timothy R. Mayes, Ph.D. It is free to use, but it is meant for educational use only. If you wish to perform
More informationPresented at the 2012 SCEA/ISPA Joint Annual Conference and Training Workshop -
Applying the Pareto Principle to Distribution Assignment in Cost Risk and Uncertainty Analysis James Glenn, Computer Sciences Corporation Christian Smart, Missile Defense Agency Hetal Patel, Missile Defense
More information**BEGINNING OF EXAMINATION** A random sample of five observations from a population is:
**BEGINNING OF EXAMINATION** 1. You are given: (i) A random sample of five observations from a population is: 0.2 0.7 0.9 1.1 1.3 (ii) You use the Kolmogorov-Smirnov test for testing the null hypothesis,
More informationELEMENTS OF MONTE CARLO SIMULATION
APPENDIX B ELEMENTS OF MONTE CARLO SIMULATION B. GENERAL CONCEPT The basic idea of Monte Carlo simulation is to create a series of experimental samples using a random number sequence. According to the
More informationSubject CS1 Actuarial Statistics 1 Core Principles. Syllabus. for the 2019 exams. 1 June 2018
` Subject CS1 Actuarial Statistics 1 Core Principles Syllabus for the 2019 exams 1 June 2018 Copyright in this Core Reading is the property of the Institute and Faculty of Actuaries who are the sole distributors.
More informationCalifornia Department of Transportation(Caltrans)
California Department of Transportation(Caltrans) Probabilistic Cost Estimating using Crystal Ball Software "You cannot exactly predict an uncertain future" Presented By: Jack Young California Department
More informationUsing Monte Carlo Analysis in Ecological Risk Assessments
10/27/00 Page 1 of 15 Using Monte Carlo Analysis in Ecological Risk Assessments Argonne National Laboratory Abstract Monte Carlo analysis is a statistical technique for risk assessors to evaluate the uncertainty
More informationSTOCHASTIC COST ESTIMATION AND RISK ANALYSIS IN MANAGING SOFTWARE PROJECTS
Full citation: Connor, A.M., & MacDonell, S.G. (25) Stochastic cost estimation and risk analysis in managing software projects, in Proceedings of the ISCA 14th International Conference on Intelligent and
More informationLONG INTERNATIONAL. Rod C. Carter, CCP, PSP and Richard J. Long, P.E.
Rod C. Carter, CCP, PSP and Richard J. Long, P.E. LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com
More informationUPDATED IAA EDUCATION SYLLABUS
II. UPDATED IAA EDUCATION SYLLABUS A. Supporting Learning Areas 1. STATISTICS Aim: To enable students to apply core statistical techniques to actuarial applications in insurance, pensions and emerging
More informationFebruary 2010 Office of the Deputy Assistant Secretary of the Army for Cost & Economics (ODASA-CE)
U.S. ARMY COST ANALYSIS HANDBOOK SECTION 12 COST RISK AND UNCERTAINTY ANALYSIS February 2010 Office of the Deputy Assistant Secretary of the Army for Cost & Economics (ODASA-CE) TABLE OF CONTENTS 12.1
More informationSTOCHASTIC COST ESTIMATION AND RISK ANALYSIS IN MANAGING SOFTWARE PROJECTS
STOCHASTIC COST ESTIMATION AND RISK ANALYSIS IN MANAGING SOFTWARE PROJECTS Dr A.M. Connor Software Engineering Research Lab Auckland University of Technology Auckland, New Zealand andrew.connor@aut.ac.nz
More informationFrequency Distribution Models 1- Probability Density Function (PDF)
Models 1- Probability Density Function (PDF) What is a PDF model? A mathematical equation that describes the frequency curve or probability distribution of a data set. Why modeling? It represents and summarizes
More informationGUIDANCE ON APPLYING THE MONTE CARLO APPROACH TO UNCERTAINTY ANALYSES IN FORESTRY AND GREENHOUSE GAS ACCOUNTING
GUIDANCE ON APPLYING THE MONTE CARLO APPROACH TO UNCERTAINTY ANALYSES IN FORESTRY AND GREENHOUSE GAS ACCOUNTING Anna McMurray, Timothy Pearson and Felipe Casarim 2017 Contents 1. Introduction... 4 2. Monte
More informationก ก ก ก ก ก ก. ก (Food Safety Risk Assessment Workshop) 1 : Fundamental ( ก ( NAC 2010)) 2 3 : Excel and Statistics Simulation Software\
ก ก ก ก (Food Safety Risk Assessment Workshop) ก ก ก ก ก ก ก ก 5 1 : Fundamental ( ก 29-30.. 53 ( NAC 2010)) 2 3 : Excel and Statistics Simulation Software\ 1 4 2553 4 5 : Quantitative Risk Modeling Microbial
More informationGN47: Stochastic Modelling of Economic Risks in Life Insurance
GN47: Stochastic Modelling of Economic Risks in Life Insurance Classification Recommended Practice MEMBERS ARE REMINDED THAT THEY MUST ALWAYS COMPLY WITH THE PROFESSIONAL CONDUCT STANDARDS (PCS) AND THAT
More informationDo Not Sum Earned-Value-Based WBS-Element Estimates-at-Completion
Do Not Sum Earned-Value-Based WBS-Element Estimates-at-Completion Stephen A. Book The Aerospace Corporation P.O. Box 92957 Los Angeles, CA 90009-2957 (310) 336-8655 stephen.a.book@aero.org Society of Cost
More informationFitting parametric distributions using R: the fitdistrplus package
Fitting parametric distributions using R: the fitdistrplus package M. L. Delignette-Muller - CNRS UMR 5558 R. Pouillot J.-B. Denis - INRA MIAJ user! 2009,10/07/2009 Background Specifying the probability
More informationBetter decision making under uncertain conditions using Monte Carlo Simulation
IBM Software Business Analytics IBM SPSS Statistics Better decision making under uncertain conditions using Monte Carlo Simulation Monte Carlo simulation and risk analysis techniques in IBM SPSS Statistics
More informationHomework Problems Stat 479
Chapter 10 91. * A random sample, X1, X2,, Xn, is drawn from a distribution with a mean of 2/3 and a variance of 1/18. ˆ = (X1 + X2 + + Xn)/(n-1) is the estimator of the distribution mean θ. Find MSE(
More informationProbabilistic Benefit Cost Ratio A Case Study
Australasian Transport Research Forum 2015 Proceedings 30 September - 2 October 2015, Sydney, Australia Publication website: http://www.atrf.info/papers/index.aspx Probabilistic Benefit Cost Ratio A Case
More informationA Probabilistic Approach to Determining the Number of Widgets to Build in a Yield-Constrained Process
A Probabilistic Approach to Determining the Number of Widgets to Build in a Yield-Constrained Process Introduction Timothy P. Anderson The Aerospace Corporation Many cost estimating problems involve determining
More informationMonte Carlo Simulation (General Simulation Models)
Monte Carlo Simulation (General Simulation Models) Revised: 10/11/2017 Summary... 1 Example #1... 1 Example #2... 10 Summary Monte Carlo simulation is used to estimate the distribution of variables when
More informationWC-5 Just How Credible Is That Employer? Exploring GLMs and Multilevel Modeling for NCCI s Excess Loss Factor Methodology
Antitrust Notice The Casualty Actuarial Society is committed to adhering strictly to the letter and spirit of the antitrust laws. Seminars conducted under the auspices of the CAS are designed solely to
More informationRisk vs. Uncertainty: What s the difference?
Risk vs. Uncertainty: What s the difference? 2016 ICEAA Professional Development and Training Workshop Mel Etheridge, CCEA 2013 MCR, LLC Distribution prohibited without express written consent of MCR,
More informationGamma Distribution Fitting
Chapter 552 Gamma Distribution Fitting Introduction This module fits the gamma probability distributions to a complete or censored set of individual or grouped data values. It outputs various statistics
More informationStochastic Analysis Of Long Term Multiple-Decrement Contracts
Stochastic Analysis Of Long Term Multiple-Decrement Contracts Matthew Clark, FSA, MAAA and Chad Runchey, FSA, MAAA Ernst & Young LLP January 2008 Table of Contents Executive Summary...3 Introduction...6
More informationMarket Risk: FROM VALUE AT RISK TO STRESS TESTING. Agenda. Agenda (Cont.) Traditional Measures of Market Risk
Market Risk: FROM VALUE AT RISK TO STRESS TESTING Agenda The Notional Amount Approach Price Sensitivity Measure for Derivatives Weakness of the Greek Measure Define Value at Risk 1 Day to VaR to 10 Day
More informationChapter 3 Descriptive Statistics: Numerical Measures Part A
Slides Prepared by JOHN S. LOUCKS St. Edward s University Slide 1 Chapter 3 Descriptive Statistics: Numerical Measures Part A Measures of Location Measures of Variability Slide Measures of Location Mean
More informationRISK MITIGATION IN FAST TRACKING PROJECTS
Voorbeeld paper CCE certificering RISK MITIGATION IN FAST TRACKING PROJECTS Author ID # 4396 June 2002 G:\DACE\certificering\AACEI\presentation 2003 page 1 of 17 Table of Contents Abstract...3 Introduction...4
More informationIntroduction to Algorithmic Trading Strategies Lecture 8
Introduction to Algorithmic Trading Strategies Lecture 8 Risk Management Haksun Li haksun.li@numericalmethod.com www.numericalmethod.com Outline Value at Risk (VaR) Extreme Value Theory (EVT) References
More informationChapter 2 Uncertainty Analysis and Sampling Techniques
Chapter 2 Uncertainty Analysis and Sampling Techniques The probabilistic or stochastic modeling (Fig. 2.) iterative loop in the stochastic optimization procedure (Fig..4 in Chap. ) involves:. Specifying
More informationRisk Video #1. Video 1 Recap
Risk Video #1 Video 1 Recap 1 Risk Video #2 Video 2 Recap 2 Risk Video #3 Risk Risk Management Process Uncertain or chance events that planning can not overcome or control. Risk Management A proactive
More informationSimulating the Need of Working Capital for Decision Making in Investments
INT J COMPUT COMMUN, ISSN 1841-9836 8(1):87-96, February, 2013. Simulating the Need of Working Capital for Decision Making in Investments M. Nagy, V. Burca, C. Butaci, G. Bologa Mariana Nagy Aurel Vlaicu
More informationAIRCURRENTS: PORTFOLIO OPTIMIZATION FOR REINSURERS
MARCH 12 AIRCURRENTS: PORTFOLIO OPTIMIZATION FOR REINSURERS EDITOR S NOTE: A previous AIRCurrent explored portfolio optimization techniques for primary insurance companies. In this article, Dr. SiewMun
More informationSome Characteristics of Data
Some Characteristics of Data Not all data is the same, and depending on some characteristics of a particular dataset, there are some limitations as to what can and cannot be done with that data. Some key
More informationMaking sense of Schedule Risk Analysis
Making sense of Schedule Risk Analysis John Owen Barbecana Inc. Version 2 December 19, 2014 John Owen - jowen@barbecana.com 2 5 Years managing project controls software in the Oil and Gas industry 28 years
More information[D7] PROBABILITY DISTRIBUTION OF OUTSTANDING LIABILITY FROM INDIVIDUAL PAYMENTS DATA Contributed by T S Wright
Faculty and Institute of Actuaries Claims Reserving Manual v.2 (09/1997) Section D7 [D7] PROBABILITY DISTRIBUTION OF OUTSTANDING LIABILITY FROM INDIVIDUAL PAYMENTS DATA Contributed by T S Wright 1. Introduction
More informationAs we saw in Chapter 12, one of the many uses of Monte Carlo simulation by
Financial Modeling with Crystal Ball and Excel, Second Edition By John Charnes Copyright 2012 by John Charnes APPENDIX C Variance Reduction Techniques As we saw in Chapter 12, one of the many uses of Monte
More informationPARAMETRIC AND NON-PARAMETRIC BOOTSTRAP: A SIMULATION STUDY FOR A LINEAR REGRESSION WITH RESIDUALS FROM A MIXTURE OF LAPLACE DISTRIBUTIONS
PARAMETRIC AND NON-PARAMETRIC BOOTSTRAP: A SIMULATION STUDY FOR A LINEAR REGRESSION WITH RESIDUALS FROM A MIXTURE OF LAPLACE DISTRIBUTIONS Melfi Alrasheedi School of Business, King Faisal University, Saudi
More informationSTATISTICAL DISTRIBUTIONS AND THE CALCULATOR
STATISTICAL DISTRIBUTIONS AND THE CALCULATOR 1. Basic data sets a. Measures of Center - Mean ( ): average of all values. Characteristic: non-resistant is affected by skew and outliers. - Median: Either
More informationSimulation Lecture Notes and the Gentle Lentil Case
Simulation Lecture Notes and the Gentle Lentil Case General Overview of the Case What is the decision problem presented in the case? What are the issues Sanjay must consider in deciding among the alternative
More informationINDIAN INSTITUTE OF SCIENCE STOCHASTIC HYDROLOGY. Lecture -26 Course Instructor : Prof. P. P. MUJUMDAR Department of Civil Engg., IISc.
INDIAN INSTITUTE OF SCIENCE STOCHASTIC HYDROLOGY Lecture -26 Course Instructor : Prof. P. P. MUJUMDAR Department of Civil Engg., IISc. Summary of the previous lecture Hydrologic data series for frequency
More informationStochastic model of flow duration curves for selected rivers in Bangladesh
Climate Variability and Change Hydrological Impacts (Proceedings of the Fifth FRIEND World Conference held at Havana, Cuba, November 2006), IAHS Publ. 308, 2006. 99 Stochastic model of flow duration curves
More informationMeasuring and managing market risk June 2003
Page 1 of 8 Measuring and managing market risk June 2003 Investment management is largely concerned with risk management. In the management of the Petroleum Fund, considerable emphasis is therefore placed
More informationProbability and Statistics
Kristel Van Steen, PhD 2 Montefiore Institute - Systems and Modeling GIGA - Bioinformatics ULg kristel.vansteen@ulg.ac.be CHAPTER 3: PARAMETRIC FAMILIES OF UNIVARIATE DISTRIBUTIONS 1 Why do we need distributions?
More informationWeb Extension: Continuous Distributions and Estimating Beta with a Calculator
19878_02W_p001-008.qxd 3/10/06 9:51 AM Page 1 C H A P T E R 2 Web Extension: Continuous Distributions and Estimating Beta with a Calculator This extension explains continuous probability distributions
More informationKARACHI UNIVERSITY BUSINESS SCHOOL UNIVERSITY OF KARACHI BS (BBA) VI
88 P a g e B S ( B B A ) S y l l a b u s KARACHI UNIVERSITY BUSINESS SCHOOL UNIVERSITY OF KARACHI BS (BBA) VI Course Title : STATISTICS Course Number : BA(BS) 532 Credit Hours : 03 Course 1. Statistical
More informationHow To: Perform a Process Capability Analysis Using STATGRAPHICS Centurion
How To: Perform a Process Capability Analysis Using STATGRAPHICS Centurion by Dr. Neil W. Polhemus July 17, 2005 Introduction For individuals concerned with the quality of the goods and services that they
More informationImproving Returns-Based Style Analysis
Improving Returns-Based Style Analysis Autumn, 2007 Daniel Mostovoy Northfield Information Services Daniel@northinfo.com Main Points For Today Over the past 15 years, Returns-Based Style Analysis become
More informationLoss Simulation Model Testing and Enhancement
Loss Simulation Model Testing and Enhancement Casualty Loss Reserve Seminar By Kailan Shang Sept. 2011 Agenda Research Overview Model Testing Real Data Model Enhancement Further Development Enterprise
More informationSYLLABUS OF BASIC EDUCATION SPRING 2018 Construction and Evaluation of Actuarial Models Exam 4
The syllabus for this exam is defined in the form of learning objectives that set forth, usually in broad terms, what the candidate should be able to do in actual practice. Please check the Syllabus Updates
More informationTHE USE OF THE LOGNORMAL DISTRIBUTION IN ANALYZING INCOMES
International Days of tatistics and Economics Prague eptember -3 011 THE UE OF THE LOGNORMAL DITRIBUTION IN ANALYZING INCOME Jakub Nedvěd Abstract Object of this paper is to examine the possibility of
More informationMarket Risk Analysis Volume I
Market Risk Analysis Volume I Quantitative Methods in Finance Carol Alexander John Wiley & Sons, Ltd List of Figures List of Tables List of Examples Foreword Preface to Volume I xiii xvi xvii xix xxiii
More informationMonte Carlo Introduction
Monte Carlo Introduction Probability Based Modeling Concepts moneytree.com Toll free 1.877.421.9815 1 What is Monte Carlo? Monte Carlo Simulation is the currently accepted term for a technique used by
More informationBrooks, Introductory Econometrics for Finance, 3rd Edition
P1.T2. Quantitative Analysis Brooks, Introductory Econometrics for Finance, 3rd Edition Bionic Turtle FRM Study Notes Sample By David Harper, CFA FRM CIPM and Deepa Raju www.bionicturtle.com Chris Brooks,
More informationCHAPTER 11. Topics. Cash Flow Estimation and Risk Analysis. Estimating cash flows: Relevant cash flows Working capital treatment
CHAPTER 11 Cash Flow Estimation and Risk Analysis 1 Topics Estimating cash flows: Relevant cash flows Working capital treatment Risk analysis: Sensitivity analysis Scenario analysis Simulation analysis
More informationValue of Information in Spreadsheet Monte Carlo Simulation Models
Value of Information in Spreadsheet Monte Carlo Simulation Models INFORMS 010 Austin Michael R. Middleton, Ph.D. Decision Toolworks Mike@DecisionToolworks.com 15.10.7190 Background Spreadsheet models are
More informationStatistical Modeling Techniques for Reserve Ranges: A Simulation Approach
Statistical Modeling Techniques for Reserve Ranges: A Simulation Approach by Chandu C. Patel, FCAS, MAAA KPMG Peat Marwick LLP Alfred Raws III, ACAS, FSA, MAAA KPMG Peat Marwick LLP STATISTICAL MODELING
More informationSTATISTICAL FLOOD STANDARDS
STATISTICAL FLOOD STANDARDS SF-1 Flood Modeled Results and Goodness-of-Fit A. The use of historical data in developing the flood model shall be supported by rigorous methods published in currently accepted
More informationDistribution analysis of the losses due to credit risk
Distribution analysis of the losses due to credit risk Kamil Łyko 1 Abstract The main purpose of this article is credit risk analysis by analyzing the distribution of losses on retail loans portfolio.
More informationQQ PLOT Yunsi Wang, Tyler Steele, Eva Zhang Spring 2016
QQ PLOT INTERPRETATION: Quantiles: QQ PLOT Yunsi Wang, Tyler Steele, Eva Zhang Spring 2016 The quantiles are values dividing a probability distribution into equal intervals, with every interval having
More informationLearning Le cy Document
PROGRAMME CONTROL Quantitative Risk Assessment Procedure Document Number: CR-XRL-Z9-GPD-CR001-50004 Document History: Revision Prepared Date: Author: Reviewed by: Approved by: Reason for Issue 1.0 15-06-2015
More informationInstitute of Actuaries of India Subject CT6 Statistical Methods
Institute of Actuaries of India Subject CT6 Statistical Methods For 2014 Examinations Aim The aim of the Statistical Methods subject is to provide a further grounding in mathematical and statistical techniques
More informationEffect of Data Collection Period Length on Marginal Cost Models for Heavy Equipment
Effect of Data Collection Period Length on Marginal Cost Models for Heavy Equipment Blake T. Dulin, MSCFM and John C. Hildreth, Ph.D. University of North Carolina at Charlotte Charlotte, NC Equipment managers
More informationHomework Problems Stat 479
Chapter 2 1. Model 1 is a uniform distribution from 0 to 100. Determine the table entries for a generalized uniform distribution covering the range from a to b where a < b. 2. Let X be a discrete random
More informationParameter Sensitivities for Radionuclide Concentration Prediction in PRAME
Environment Report RL 07/05 Parameter Sensitivities for Radionuclide Concentration Prediction in PRAME The Centre for Environment, Fisheries and Aquaculture Science Lowestoft Laboratory Pakefield Road
More informationAnalysis of truncated data with application to the operational risk estimation
Analysis of truncated data with application to the operational risk estimation Petr Volf 1 Abstract. Researchers interested in the estimation of operational risk often face problems arising from the structure
More informationDECISION SUPPORT Risk handout. Simulating Spreadsheet models
DECISION SUPPORT MODELS @ Risk handout Simulating Spreadsheet models using @RISK 1. Step 1 1.1. Open Excel and @RISK enabling any macros if prompted 1.2. There are four on-line help options available.
More informationClark. Outside of a few technical sections, this is a very process-oriented paper. Practice problems are key!
Opening Thoughts Outside of a few technical sections, this is a very process-oriented paper. Practice problems are key! Outline I. Introduction Objectives in creating a formal model of loss reserving:
More informationStatistics & Flood Frequency Chapter 3. Dr. Philip B. Bedient
Statistics & Flood Frequency Chapter 3 Dr. Philip B. Bedient Predicting FLOODS Flood Frequency Analysis n Statistical Methods to evaluate probability exceeding a particular outcome - P (X >20,000 cfs)
More informationOperational Risk Modeling
Operational Risk Modeling RMA Training (part 2) March 213 Presented by Nikolay Hovhannisyan Nikolay_hovhannisyan@mckinsey.com OH - 1 About the Speaker Senior Expert McKinsey & Co Implemented Operational
More informationQuantitative Risk Analysis with Microsoft Project
Copyright Notice: Materials published by ProjectDecisions.org may not be published elsewhere without prior written consent of ProjectDecisions.org. Requests for permission to reproduce published materials
More informationAnalysis of the Oil Spills from Tanker Ships. Ringo Ching and T. L. Yip
Analysis of the Oil Spills from Tanker Ships Ringo Ching and T. L. Yip The Data Included accidents in which International Oil Pollution Compensation (IOPC) Funds were involved, up to October 2009 In this
More informationTABLE OF CONTENTS - VOLUME 2
TABLE OF CONTENTS - VOLUME 2 CREDIBILITY SECTION 1 - LIMITED FLUCTUATION CREDIBILITY PROBLEM SET 1 SECTION 2 - BAYESIAN ESTIMATION, DISCRETE PRIOR PROBLEM SET 2 SECTION 3 - BAYESIAN CREDIBILITY, DISCRETE
More informationHomeowners Ratemaking Revisited
Why Modeling? For lines of business with catastrophe potential, we don t know how much past insurance experience is needed to represent possible future outcomes and how much weight should be assigned to
More informationCost Risk and Uncertainty Analysis
MORS Special Meeting 19-22 September 2011 Sheraton Premiere at Tysons Corner, Vienna, VA Mort Anvari Mort.Anvari@us.army.mil 1 The Need For: Without risk analysis, a cost estimate will usually be a point
More informationXSG. Economic Scenario Generator. Risk-neutral and real-world Monte Carlo modelling solutions for insurers
XSG Economic Scenario Generator Risk-neutral and real-world Monte Carlo modelling solutions for insurers 2 Introduction to XSG What is XSG? XSG is Deloitte s economic scenario generation software solution,
More informationUncertainty Analysis with UNICORN
Uncertainty Analysis with UNICORN D.A.Ababei D.Kurowicka R.M.Cooke D.A.Ababei@ewi.tudelft.nl D.Kurowicka@ewi.tudelft.nl R.M.Cooke@ewi.tudelft.nl Delft Institute for Applied Mathematics Delft University
More informationInternational Cost Estimating and Analysis Association Testable Topics List CCEA
International Cost Estimating and Association Testable Topics List CCEA Testable Topics List The Testable Topics List Cost Estimating Basics COST ESTIMATING BASICS Budgeting, Investment, and Planning of
More informationINSTITUTE AND FACULTY OF ACTUARIES SUMMARY
INSTITUTE AND FACULTY OF ACTUARIES SUMMARY Specimen 2019 CP2: Actuarial Modelling Paper 2 Institute and Faculty of Actuaries TQIC Reinsurance Renewal Objective The objective of this project is to use random
More informationA Study on the Risk Regulation of Financial Investment Market Based on Quantitative
80 Journal of Advanced Statistics, Vol. 3, No. 4, December 2018 https://dx.doi.org/10.22606/jas.2018.34004 A Study on the Risk Regulation of Financial Investment Market Based on Quantitative Xinfeng Li
More informationCommonly Used Distributions
Chapter 4: Commonly Used Distributions 1 Introduction Statistical inference involves drawing a sample from a population and analyzing the sample data to learn about the population. We often have some knowledge
More informationSTARRY GOLD ACADEMY , , Page 1
ICAN KNOWLEDGE LEVEL QUANTITATIVE TECHNIQUE IN BUSINESS MOCK EXAMINATION QUESTIONS FOR NOVEMBER 2016 DIET. INSTRUCTION: ATTEMPT ALL QUESTIONS IN THIS SECTION OBJECTIVE QUESTIONS Given the following sample
More informationThis item is the archived peer-reviewed author-version of:
This item is the archived peer-reviewed author-version of: Impact of probability distributions on real options valuation Reference: Peters Linda.- Impact of probability distributions on real options valuation
More informationQuantitative Trading System For The E-mini S&P
AURORA PRO Aurora Pro Automated Trading System Aurora Pro v1.11 For TradeStation 9.1 August 2015 Quantitative Trading System For The E-mini S&P By Capital Evolution LLC Aurora Pro is a quantitative trading
More informationCost Containment through Offsets in the Cap-and-Trade Program under California s Global Warming Solutions Act 1 July 2011
Cost Containment through Offsets in the Cap-and-Trade Program under California s Global Warming Solutions Act 1 July 2011 This document outlines the results of the economic modeling performed by the Environmental
More information,,, be any other strategy for selling items. It yields no more revenue than, based on the
ONLINE SUPPLEMENT Appendix 1: Proofs for all Propositions and Corollaries Proof of Proposition 1 Proposition 1: For all 1,2,,, if, is a non-increasing function with respect to (henceforth referred to as
More informationDescribing Uncertain Variables
Describing Uncertain Variables L7 Uncertainty in Variables Uncertainty in concepts and models Uncertainty in variables Lack of precision Lack of knowledge Variability in space/time Describing Uncertainty
More informationConfidence Intervals for the Median and Other Percentiles
Confidence Intervals for the Median and Other Percentiles Authored by: Sarah Burke, Ph.D. 12 December 2016 Revised 22 October 2018 The goal of the STAT COE is to assist in developing rigorous, defensible
More informationQuantitative Methods
THE ASSOCIATION OF BUSINESS EXECUTIVES DIPLOMA PART 2 QM Quantitative Methods afternoon 27 November 2002 1 Time allowed: 3 hours. 2 Answer any FOUR questions. 3 All questions carry 25 marks. Marks for
More informationModeling Medical Professional Liability Damage Caps An Illinois Case Study
Modeling Medical Professional Liability Damage Caps An Illinois Case Study Prepared for: Casualty Actuarial Society Ratemaking and Product Management Seminar Chicago, IL Prepared by: Susan J. Forray, FCAS,
More informationStochastic Modelling: The power behind effective financial planning. Better Outcomes For All. Good for the consumer. Good for the Industry.
Stochastic Modelling: The power behind effective financial planning Better Outcomes For All Good for the consumer. Good for the Industry. Introduction This document aims to explain what stochastic modelling
More informationBasic Procedure for Histograms
Basic Procedure for Histograms 1. Compute the range of observations (min. & max. value) 2. Choose an initial # of classes (most likely based on the range of values, try and find a number of classes that
More informationSimulation. LEARNING OBJECTIVES : After studying this chapter, you should be able to :
16 Simulation LEARNING OBJECTIVES : After studying this chapter, you should be able to : l explain the term simulation and reasons for using simulation; l identify the steps in the simulation process;
More informationSection 3 describes the data for portfolio construction and alternative PD and correlation inputs.
Evaluating economic capital models for credit risk is important for both financial institutions and regulators. However, a major impediment to model validation remains limited data in the time series due
More information