FINANCIAL MONITORING REPORTS FOR WORLD BANK-FINANCED PROJECTS: GUIDELINES FOR BORROWERS

Size: px
Start display at page:

Download "FINANCIAL MONITORING REPORTS FOR WORLD BANK-FINANCED PROJECTS: GUIDELINES FOR BORROWERS"

Transcription

1 FINANCIAL MONITORING REPORTS FOR WORLD BANK-FINANCED PROJECTS: GUIDELINES FOR BORROWERS OPERATIONS POLICY AND COUNTRY SERVICES NOVEMBER 30, 2001

2 ACRONYMS FMR FMS LACI M&E PAD PAS PIP PMR PS SA TL TT Financial Monitoring Report Financial Management Specialist Loan Administration Change Initiative Monitoring and Evaluation Project Appraisal Document Procurement Accredited Staff Project Implementation Plan Project Management Report Procurement Specialist Special Account Team Leader Task Team

3 FINANCIAL MONITORING REPORTS FOR WORLD BANK-FINANCED PROJECTS: GUIDELINES FOR BORROWERS CONTENTS Foreword...iv I. Introduction... 1 II. Financial Monitoring Reports... 2 A. Underlying Principles... 2 B. Contents of Financial Monitoring Reports... 3 C. Format of Financial Monitoring Reports... 9 D. Submission of Financial Monitoring Reports... 9 III. Disbursements IV. Transitional Arrangements V. Donor Coordination Annexes A. Sample Financial Monitoring Reports B. Disbursement Documentation for Investment Loans

4 FINANCIAL MONITORING REPORTS FOR WORLD BANK-FINANCED PROJECTS: GUIDELINES FOR BORROWERS FOREWORD 1. These guidelines have been prepared to assist the World Bank and its borrowers to reach agreement on the content, format, and timing of financial monitoring reports (FMRs) for Bank-financed projects. The guidelines apply to all investment loans and credits. 2. These guidelines replace previous guidance on PMRs contained in the Loan Administration Change Initiative Handbook and the Project Financial Management Manual Section I provides a brief background explanation of these changes. Section II provides detailed guidance on the development of FMRs, and discusses underlying principles; the basic content of FMRs (financial, physical progress, and procurement information); and FMR format, frequency, and submission. Section III discusses the disbursement implications of FMRs. Section IV discusses arrangements for transitioning to FMRs. Section V discusses coordination with other donors on FMR issues. There are also two annexes. Annex A provides illustrative examples of the possible format and content of FMRs, using five different types of projects. Annex B provides further information on the documentation required for disbursement for investment loans. 1 See the Loan Administration Change Initiative (LACI) Implementation Handbook, World Bank, Loan Department, September 1998; and Project Financial Management Manual, Exposure Draft, World Bank, Loan Department, February, iv

5 FINANCIAL MONITORING REPORTS FOR WORLD BANK-FINANCED PROJECTS: GUIDELINES FOR BORROWERS I. INTRODUCTION 1. Bank policy requires that projects be supervised to ensure that loan proceeds are used only for the purposes for which the loan was granted, with due regard to economy, efficiency, and the sustainable achievement of the project s development objectives. As an aspect of this supervision, the Bank requires borrowers to submit reports needed for effective project monitoring and evaluation. In July 1998, the Bank introduced a requirement for borrowers to prepare project management reports (PMRs) based on a standardized format, which included financial management, physical progress (outputs), and procurement reporting. Although the major objective of PMRs was to improve project financial management, the reports also provided a new basis for disbursements, described as PMR-based disbursements. 2. Change from PMR to FMR. The Bank has recently decided to simplify and customize reporting requirements, thus facilitating the generation of reports directly from the project management information systems rather than their having to be prepared separately. It has also been decided to rename PMRs as financial monitoring reports (FMRs) so as to clearly reflect their objective and to signal the changes from PMRs. While their objective is the same as the previous PMRs, the change in nomenclature reflects two key points that they focus on the financial aspects of projects and that their purpose is project monitoring, not management. The FMRs are not the same as the audited financial statements required annually for each project. However they may form the basis of these statements (see paragraph 10a). 3. Borrower and Bank Responsibilities. The borrower is responsible for putting in place and maintaining adequate financial management, procurement, and progress monitoring arrangements for the project as part of overall arrangements for project management. The Bank s role is to ensure that these arrangements are in place before project implementation begins, and that they remain in place throughout project execution. 4. Borrower Staff Responsibilities. The duties of project staff with respect to preparation of FMRs and other reports should be explained as part of the project s Operations Manual. The Project Manager/Coordinator is responsible for ensuring that a complete FMR is produced, and provided to all stakeholders in a timely manner. As manager of the project, he/she should also work with the appropriate government officials and project staff to provide narrative explanations of project progress and to take actions to address problems or take advantage of opportunities that may be presented in the FMR. Typically, the Project Accountant/Financial Manager is responsible for preparing the financial reports, while physical progress reports are produced by technical specialists and procurement reports by the project staff responsible for procurement. However, the exact responsibilities will vary depending on the nature of the project. 5. Bank Staff Responsibilities. Responsibility for project supervision by the Bank rests with the task team (TT) assigned to the project. As part of project preparation, the TT agrees on the arrangements for project supervision with borrower staff. These arrangements include the

6 2 format and content of reports to be provided by the borrower such as FMRs, annual financial statements and audit reports, and other reports required for effective project monitoring, evaluation, and disclosure. The team leader (TL) is the Bank s principal point of contact with the borrower. The TL is supported by financial management specialists (FMS), procurement specialists (PS) or procurement accredited staff (PAS), and other TT members. II. FINANCIAL MONITORING REPORTS 6. Although FMRs should be flexible and customized to each project or, where appropriate, to each country or sector, they must adhere to underlying principles, noted below. 1 Subsequent sections discuss the content, format, and frequency of FMRs. A. Underlying Principles 7. The principles that underpin FMRs are as follows: FMRs should provide information that is useful to the borrower while also providing the Bank with sufficient information to establish whether: funds disbursed to projects are being used for the purpose intended, project implementation is on track, and budgeted costs will not be exceeded. Financial information should be linked with information on physical progress and procurement, to give assurance that financial and physical progress are consistent. The monitoring of expenditures in relation to physical progress is a key aspect of ensuring that the project is under proper financial control, although in some projects it may be difficult to develop quantitative output indicators. Project monitoring by the Bank should be cost effective from the viewpoint of both the Bank and borrowers. This entails the following: 1 Financial monitoring reports provided to the Bank may be a sub-set or summary of the project s management reports, since for monitoring purposes the Bank does not need as detailed information as is contained in reports for project management. Such management reports should broadly follow the principles outlined in this section as regards: (a) flexibility of format and frequency; (b) report design predicated on the size, nature, and complexity of the project, and the systems, needs, and expertise of borrower staff; (c) the need to compare planned and actual expenditures in relation to physical progress and to analyze revealed variances; (d) the need to highlight issues requiring attention (including unexpected developments that may have a significant impact on the project s implementation or its procurement and financial management systems); and (e) the need to report project overall progress as agreed during project preparation. Bank staff may also provide assistance to the borrower on management reports to help determine the information required, the frequency of reporting, and how best to identify formats that can be produced from borrowers own systems and how to enhance those systems.

7 3 Reporting requirements that necessitate borrowers investing in or maintaining parallel or duplicate systems should be avoided, as far as possible (see paragraph 10a). While the FMR should allow the reader to compare information across the various reports, linkage of the information should be done through a consistent information structure and should not require new, complex, integrated information systems. The same structure of financial information should normally be used for project planning and costing, FMRs, the annual audited financial statements of the project, and implementation completion reports. The requirements for financial and procurement monitoring should, as far as possible, be aligned and integrated with other Bank requirements for project progress reporting and monitoring, including project outcome monitoring and reporting. For example, when semi-annual progress reporting is required, the FMR should be an integral part of these reports. As far as possible, borrowers are not required to provide the Bank with information already available to the Bank. An example is the procurement information on contracts above the prior-review threshold. Wherever possible, common reporting and monitoring arrangements should be agreed with other donors involved in the project (see paragraph 37). B. Contents of Financial Monitoring Reports 8. The format and content of FMRs should be determined as part of project appraisal (reflecting assessments of the financial management systems, procurement arrangements, and the overall review and assessments by the TL), and be agreed at negotiations. Other donors involved in the project should be invited to participate in the discussions (see paragraph 37). 9. Timing of Financial Management Arrangements. In all cases, adequate financial management arrangements, including the ability to produce a timely FMR, should be in place by loan effectiveness. 10. Required FMR Information. FMRs will include financial, physical progress, and procurement information. (Illustrative sample reports are shown in Annex A.) There should also be an introductory narrative discussion of project developments and progress during the period, to provide context to (or other explanations of) information reported in the financial, physical progress, and procurement sections. a. Financial Reports. At a minimum, financial reports must include a statement showing for the period and cumulatively (project life or year to date) cash receipts by sources and expenditures by main expenditure classifications; beginning and ending cash balances of the project; and supporting schedules comparing actual and planned expenditures.

8 4 Line Item Reporting. The line item reporting in the FMR should follow the borrower s chart of accounts as far as possible, provided that it separately records all significant discrete activities, as determined during the financial management assessment and agreed at negotiation. Where the borrower s chart of accounts does not provide the level of reporting detail needed for project monitoring, either it should be amended or the FMR should be prepared separately from the borrower s project management system. This chart of accounts will normally reflect expenditure items which differ from disbursement categories. 2 Relationship Between FMRs and Annual Financial Statements. In drawing from the project management system, the cumulative FMRs over the project year will in many cases be able to be used as the project s annual financial statements. This will result in more cost-effective reporting. It may also result in more costeffective and timely auditing of the project annual financial statements, to the extent that FMRs may be reviewed as part of the auditor s interim work on the annual financial statements. 3 Avoiding Parallel or Duplicative Systems. Two aspects are relevant to reducing the number of unnecessary reporting systems: To the extent possible, borrower financial management systems should be used for project management reporting. At project appraisal, therefore, the borrower and the Bank should evaluate and discuss the capacity of the borrower s systems and the possibility of improvements that would enable the borrower to produce the FMR from the project management system. For example, the use of the borrower s chart of accounts for the financial reports should be considered. If borrower financial management systems cannot be used, any separate or ring fenced accounting system developed for project management should also be capable of producing FMRs, rather than having them produced from a system that is separate from project management. Monitoring reports should normally draw on the more detailed information used by the implementing agency for project management. b. Physical Progress Reports. Physical progress reports include narrative information and output indicators (agreed during project preparation) linking financial information with physical progress, and highlight issues that require attention. (See paragraphs 21 through 26 for guidance on monitoring physical progress.) 2 3 The borrower provides information by disbursement category to the Loan Department through withdrawal applications. The FMRs are unaudited reports, but may prove useful to auditors as they carry out their interim work. When used for disbursements, the auditors must provide an opinion in the annual financial statements as to the eligibility of the expenditures financed by the Bank and the existence of adequate support documentation in the project entity s files.

9 5 c. Procurement Reports. Procurement reports provide information on the procurement of goods, work, and related services, and the selection of consultants, and on compliance with agreed procurement methods. The reports compare procurement performance against the plan agreed at negotiations or subsequently updated, and highlight key procurement issues such as staffing and building borrower capacity. In addition to procurement progress, the reports include information on all authorized contract variations. Information on complaints by bidders, unsatisfactory performance by contractors, and any major contractual disputes may also be included. 11. FMRs for Small Operations. Where the value of the loan, credit, or grant does not exceed US$5 million, such as for learning and innovation loans (LILs), the relatively small amount of funds involved and the likely less complex nature of the project will normally enable more simplified forms of reporting to be adopted. Although reporting is still necessary on financial, physical progress, and procurement aspects, there will normally be fewer individual components and output indicators, resulting in simpler, less detailed reporting. Less frequent reporting may also be appropriate. 12. Scope of the FMR. The FMR encompasses the total project as described in the PAD, and not only the use of Bank funds. The FMR thus reflects all project activities, financing, and expenditures, including funds from other donors and contributions in kind such as labor and accommodation, irrespective of whether the project implementing agency controls the funds for a particular aspect of the project. If a borrower or a co-financier provides goods and services that it finances directly or to which contributions in kind are made, appropriate valuations should be undertaken to determine the amounts to be recorded in the accounts. If this information is not readily available, the FMR should not be delayed. Instead, a note to this effect should be included in the FMR, and the necessary information attached to a subsequent FMR, once available Multiple Implementing Agencies. The reporting arrangements for a project with multiple implementing entities should be determined no later than appraisal, and agreed and documented at negotiations, along with the format and frequency of the FMRs. Ideally, a single FMR should be submitted for a project for each reporting period. For example, where two or more implementing entities each have responsibility for different components of a project and there is a central (coordinating) project unit and one special account (SA), the central project unit should prepare a consolidated FMR, covering the various implementing entities. However, there are situations where this may not be possible. For example, a project may have multiple implementing agencies, each with an SA and responsible for implementing the project in a separate zone, state, or province, and there may be no central project unit. Where this makes the preparation of a consolidated FMR infeasible, each implementing entity should prepare a separate FMR. 14. Currency of the FMR. The currency in which the reports will be prepared should be agreed at negotiations. FMRs should be prepared in the currency in which borrowers normally 4 FMRs are not required to provide procurement information on activities financed by other donors, although the discussion of project progress should mention the status of these contracts and their impact on overall project progress.

10 6 keep their books of account. Where the accounts are maintained in a currency other than the currency of the SA, the issue of currency translation will arise. As a general rule, the opening and closing balances of the SA (and of any other bank accounts relating to the project that are held in a currency different from the books of account) should be translated at the rate ruling on the opening and closing dates, respectively. Expenditures made out of the SA (and other bank accounts as mentioned above) should be stated at the rate ruling on the transaction dates. The actual exchange rates used should be disclosed in a note to the FMR. 15. Accounting Policies. There are two generally recognized accounting bases used by governments cash and accrual accounting. 5 These accounting bases determine whether, how, and when to record or recognize transactions/events. The cash basis of accounting is normally acceptable for projects implemented by non-revenue-earning entities. The accrual basis is necessary where the management of liabilities requires specific attention, and where full-cost information (as opposed to cash payments) is needed. The full accrual basis is therefore required of all commercial/revenue-earning entities in receipt of Bank funds. In practice, different levels of government in the same country may use different bases of accounting, or modified versions thereof. However, only one basis of accounting should be applied to a project. Project accounting policies should be agreed at negotiations and also disclosed in a note to the FMR. 16. Project Planning. Effective project monitoring requires adequate project planning, including a financial plan. Without such plans there is no base against which to compare actual results. The planning process should start early during project preparation. As the project is developed, the plan becomes more specific and is expressed in the form of a guiding project implementation plan (PIP), which provides a basis for monitoring the project and identifying areas that require corrective action. The information in the initial PIP should include cost tables, physical output measures, and cost information. The PIP should be updated when significant changes to underlying assumptions or to project implementation occur, to ensure that it remains realistic. 17. Sound Project Implementation Plans. A good project implementation plan should include the following information: Financial projections or forecasts for the life of the project broken down by appropriate period, from which the annual budgets for the project should be developed; A procurement plan, including the activities and processes associated with the project (for instance, arrangements and process to secure the services of contractors); The format and content of, and the auditing arrangements for, project financial reports; Measures of physical progress and other monitorable indicators that can be validly related to costs; and 5 In addition to these accounting bases, governments also use commitment accounting. This basis, which is used mainly for budgetary control, recognizes transactions when they are committed, for example, when an order is placed. This is not an acceptable basis for the preparation of FMRs.

11 7 The criteria for following up variances between planned and actual costs and physical progress. 18. Financial Planning: First Steps. Financial planning starts with the cost information generated either by COSTAB software (used by the Bank for the preparation of project cost tables) or by other means, such as a spreadsheet. The Bank s task team and borrower staff have joint responsibility for ensuring that this information is properly prepared. The cost tables should, where possible, be based on the borrower s chart of accounts to ensure that project financial reports can also be prepared on this basis. 6 Before project implementation, borrowers, with support as needed from Bank staff, should refine the cost information into detailed specifications for project activities, detailed schedules (including procurement plan), and expenditure budgets broken down by time periods, as appropriate. The budgeted expenditure for each quarter (or any other appropriate period) should reflect the project activities scheduled for the quarter (or period). 19. Revising Project Budgets. Planning figures need to remain realistic if reported variances are to be meaningful. Therefore, before the beginning of each fiscal year of the project, borrower staff should review, and revise as necessary, the project budget for the coming year, reflecting any updating of the PIP. This will avoid reporting variances that arise solely from project delays that have not been reflected in an updated PIP or budget. The revised budget should normally be sent to the TL at least two months before the beginning of the project fiscal year. 20. Variance Analysis. Financial reports depict variances between planned and actual costs. Similarly, physical progress monitoring reports and procurement reports show variances between planned and actual outputs and contracting, respectively. Significant variances should be analyzed, and explanations, together with the remedial actions to be taken, should be given in the reports. The level at which a variance is significant and requires further investigation or remedial action should be agreed during project preparation, either by setting a percentage level of variance or agreeing on those activities to be addressed. The cost of a small activity may vary by a large percentage, but its impact on the project as a whole may be relatively insignificant. Therefore, the level of variance that needs to be addressed could differ from one activity to another within the project, as well as between projects. 21. Monitoring Physical Progress. As noted in paragraph 7, monitoring expenditures in relation to physical progress is a key aspect of ensuring that project costs are under control. Physical progress monitoring requires data on project outputs that reflect the cost drivers of the project components. Some borrowers do not systematically collect such output data, and others need to strengthen their current systems for doing so. For this reason, identifying relevant outputs requires close attention during project preparation. This requires all of the following: A project design that identifies the project components and the set of activities to which outputs relate 7 ; 6 7 The borrower s chart of accounts may be the central government s accounting system, or the chart of accounts of the entity or agency that is responsible for project implementation. An example is the Bank s logical framework for overall project design and development which can be found in the Bank s Project Appraisal Document.

12 8 An understanding of the link between outputs and costs; and A reliable means of recording and reporting outputs. 22. Designing Output Indicators. Although the nature of the project determines how physical progress will be monitored, output indicators should generally be designed to relate output to cost, as identifiable outputs of each project component (or activity) are usually directly linked to or drive costs. In some cases, monitoring indicators may be in the form of contract status information. 23. Monitoring Methodology. The method of relating outputs to cost is suitable where there is a readily measurable flow of reasonably homogeneous outputs that can be determined as the main cost drivers (for example, people trained, items supplied, cases assessed, treatments carried out, permits issued). However, where construction is a major component of the project, there may be no flow of outputs until the construction activities are completed. In this case, the use of contract information may be the appropriate basis for monitoring project progress. For some projects both methods may be used for example, an education project may have a component for training teachers (units of output method) and another component for building a university (contract management method). Sometimes neither of these methods will be feasible, and a different approach, such as narrative information, may be appropriate. 24. Scope of Output Monitoring. Output monitoring needs to be approached realistically. It is not necessary for output measures to be developed for all project components and activities. Rather, attention might focus on measuring the outputs of key activities and on developing output information systems that can be expanded in coverage over time. 25. Project Outcome Measures. Project outcome measures, which indicate the project s success in achieving development objectives such as improving learning outcomes, changing target group practices or behaviors, or increasing agricultural production are not normally an appropriate basis for relating to costs in FMRs. They are required for a different purpose, that of monitoring and evaluating project effectiveness and progress toward project development objectives. However, both output and outcome measures are part of the Bank s logical framework for overall project design and management. These project development objective and outcome measures should also form part of the required monitoring and evaluation (M&E) plan for the project. 26. Timing of Indicator Determination. The development of output indicators for physical progress monitoring should be undertaken in conjunction with the development of output and outcome indicators for the M&E plan. This will avoid duplication as in some cases the same output indicators may be relevant for physical progress monitoring and M&E. 8 8 Further guidance on output and outcome measures is contained in the Bank s Performance Monitoring Indicators Handbook (1996).

13 9 C. Format of Financial Monitoring Reports 27. The FMR comprises a financial report, a physical progress report, and a procurement report. Although the FMR format is specific to each project, it is desirable to avoid an unnecessary number of differing formats. Borrowers may therefore wish to reach agreement with the Bank on a more standardized format that can be used across projects in the country, and especially for all projects within a particular sector. The format of the FMR should take account of the nature, size, and complexity of each project, while also ensuring that the Bank receives the information it requires for project monitoring. The format should be determined during project preparation, and be agreed at negotiations. For illustrative purposes, a number of sample FMRs are shown in Annex A. 28. Financial Reports. As far as possible, financial reports should be in a format that the borrower s systems can produce, and this format must be acceptable to the Bank. Bank staff work with clients to identify such formats and in order to assist, where necessary, in developing arrangements to produce such reports. 29. Physical Progress Reports. These will vary in format, based on the nature of the project. 30. Procurement Reports. The main purpose of procurement reports is to facilitate project monitoring, including ex-post reviews of procurement. Procurement reports should be designed in a way that enables project implementation staff to improve the quality and reliability of procurement administration, taking into account the particular circumstances of each project and loan type. For example, for LILs or community-driven development projects, procurement reports may be less detailed than normally required. For some projects, a TL may wish to monitor every contract below the prior review threshold, 9 while for others (for example, community-based operations), it may be preferable to set a minimum threshold for reporting to the Bank so as to avoid an excessively long report. D. Submission of Financial Monitoring Reports 31. The frequency of preparation of FMRs and their submission to the Bank should be determined at the project appraisal stage and agreed at negotiations, and should coincide, as far as possible, with the submission of similar reports to the Bank. The minimum frequency of reporting should be every six months, but most projects would be expected to report quarterly. 10 Complex, high-risk projects may require FMRs on a more frequent basis. The first FMR will 9 10 The Bank obtains information on contracts above the prior review threshold, and maintains this information in its internal systems. However, in some cases it may be preferred by the borrower and the Bank to also include these contracts in the FMR, in order to provide a comprehensive view of all Bank-financed procurement in one report. Such a comprehensive report on procurement may not be required in every FMR, but it may be prove useful at certain key junctures, such as for the midterm review. Many projects are required to submit semi-annual progress reports. When this is the case, every-other quarterly FMR could be integrated into the semi-annual report.

14 10 normally cover the period from the date of effectiveness to the end of the first full quarter after effectiveness Timing of FMR Submission. The FMR should normally be submitted to the TL within 45 days of the end of the reporting period. If the FMR is not provided on a timely basis, the TL will follow this up with the borrower to determine the reason for the delay and the planned date of report submission. Late submission of FMRs to the Bank will normally lead to more intensive supervision by the Bank task team and may result in the application of legal remedies for noncompliance. Additionally, disbursements to the project will be delayed if the project is using report-based disbursements. III. DISBURSEMENTS 33. Borrowers continue to have a choice between transaction-based and (streamlined) reportbased disbursements. However, to be eligible for report-based disbursements borrowers must meet certain requirements. These requirements and other issues related to disbursement documentation are set out in Annex B. IV. TRANSITIONAL ARRANGEMENTS 34. The requirement to provide the Bank with FMRs applies to all projects appraised from January 1, However, borrowers may also continue to use the standardized PMR format. 35. Projects Appraised Between July 1, 1998 and December 31, For projects appraised between July 1, 1998 and December 31, 2001, borrowers that have previously committed to preparing PMRs may request the Bank to agree to a process for converting to FMRs. Bank staff will work with borrower staff to determine and agree upon appropriate reporting arrangements. 36. Projects Currently Utilizing PMR-Based Disbursements. Borrowers disbursing on the basis of the standardized PMRs before January 1, 2002, may continue to do so. In this case, the requirements and procedures outlined in the relevant Disbursement Letter will continue to apply. Alternatively, borrowers may switch to the new FMRs comprising the basic reporting requirements described in these guidelines plus the additional reporting requirements for reportbased disbursements, referred to in Annex B For projects with significant expenditures prior to loan/credit effectiveness, it may be preferable to have the first FMR produced and submitted to the Bank prior to the first full quarter after effectiveness. Borrowers may also wish to submit FMRs prior to the first full quarter for other reasons, e.g. to get feedback from the Bank and other stakeholders regarding how the report can be improved, or to demonstrate the entity s readiness for reportbased disbursements. These guidelines are not applicable to projects that were appraised prior to July 1, 1998, as these projects were not required to produce PMRs.

15 11 V. DONOR COORDINATION 37. Where a project is funded jointly by the Bank and other donors, and there is alignment of project preparation schedules, Bank staff will work with the other donors to coordinate the various capacity assessments, in order to streamline this process. Where appropriate, Bank and borrower staff should work to agree, to the extent practicable, on common format, content, and frequency of progress reports to be submitted to donors. By reducing multiple reporting, harmonization may reduce both borrower and donor costs.

16 ANNEX A SAMPLE FINANCIAL MONITORING REPORTS 1. This annex provides five illustrative examples of Financial Monitoring Reports (FMRs), as follows: Government of Atlantis Education Project Appletonia Urban Highway Project Pacifica Social Safety Net Project Plutonia Tax Administration Project Hibernia Education LIL (example of a small operation) 2. While adaptations to these formats may be agreed between the Bank and borrowers, these adaptations should not reduce the core content of the reports to a level below the minimum necessary for project monitoring by the Bank. It is also expected that many borrowers will wish to have consistent reporting formats within their country, or in certain sectors, and this aim will be supported by the Bank. 3. Table 3 in Annex B lists the additional information needed to support report-based disbursements. 4. The Bank and borrowers may agree that additional information should be added to these formats. Examples of such additional information include updated forecasts of expenditure, schedules of assets (or asset categories) financed by the Bank, an analysis of Bank financing by loan disbursement category, year-to-date financial results, supporting schedules or notes that provide a more detailed analysis of key activity areas or one or more line items in the expenditure reports, and fuller narrative explanations of performance and actions to be taken to address identified problem areas. Some of the sample reports provided here suggest ways of integrating this type of additional information with the core reports. 5. Borrowers that provide the information set out in the PMRs introduced in 1998, fully satisfy the requirements of FMRs.

17 FINANCIAL MONITORING REPORTS - SAMPLE 1 ANNEX A Sample I Page 1 of 8 GOVERNMENT OF ATLANTIS EDUCATION SECTOR IMPROVEMENT PROJECT Contents 1. Discussion of Project Progress 2. Sources and Uses of Funds Statement 3. Uses of Funds by Project Activities (supports the Sources/Uses of Funds) 4. Physical Progress Report - physical outputs 5. Physical Progress Report - status of large works and services 6. Procurement Monitoring Report - narrative and tables [This provides an example of an education project that includes significant construction activities, equipment purchases, and training. The Sources and Uses of Funds Statement includes a cash forecast for the next six months, to facilitate project planning and monitoring. Physical progress is monitored by units of output, where practical, and by contract/work progress for construction activities.]

18 DISCUSSION OF PROJECT PROGRESS ANNEX A Sample I Page 2 of 8 GOVERNMENT OF ATLANTIS EDUCATION SECTOR IMPROVEMENT PROJECT FMR as part of progress reporting 1. The attached reports provide information on the progress of the project in terms of financial activity, key output measures, and procurement for the January-March quarter. The FMRs for the periods ending in June and December are incorporated into the larger semi-annual progress report. A comprehensive report of project progress will be prepared in preparation for the midterm review of the project. Comments on the FMR (including explanation of significant variances) 2. All project components are at least partially completed. The attached Physical Progress Reports show progress in terms of output, for some activities, and work progress for others. As agreed during project appraisal, only the key project activities, and/or those that lend themselves to such reporting, are included in the physical progress reports. Below is a discussion of progress on major project activities. 3. Activity 1a: New Decentralized MIS - The costs in the financial reports reflect the purchase of servers for the Ministry of Education, the purchase and installation of 50 computers in district offices and some software purchase and installation. Before any district office can be fully linked, some additional programming is required at the central level, software must be fully installed at the district offices, and all IT staff must be trained (6 of 30 staff have been trained to date). It is still planned for the system to "go live" in March 2002, although in the district of Heravora, the unstable political situation may delay implementation. 4. Activity 1b: Construction of New District Offices - Construction of buildings 1-5 is expected to be on schedule and within cost estimates. Building 6 will be completed early, but will be above cost estimates due to heavy rains at the project site in November The contract for buildings 7-10 was signed March 28, Component 2: Increasing Access - Rehabilitation of secondary schools is proceeding as planned. Construction of 50 community-managed primary schools is ahead of schedule, as the general contractor's modular design has resulted in efficiencies and economies of scale. Forty schools are complete and 24 of these are already being used. 6. Component 3: Teacher and Principal Development - Courses are proceeding as planned, with the main variance being in the cost of the management training for principals, the price for which was about 10% higher than planned. The training services were procured in accordance with World Bank procedures, with the No Objection received from the Bank Task Team Leader on October 5, Component 4: Project Management - Costs of project management significantly exceeded the plan during the quarter due to the payment of back-pay to 3 employees whose salary could not be paid in previous months due to contractual delays. Cumulative costs in this component are in line with the plan and the PAD amounts.

19 ANNEX A Sample I Page 3 of 8 Cash Receipts Forecast: Next 6 months Government Funds 24, ,000 75,000 IBRD Funds 129, , ,000 Total Financing 153, , ,000 Less: Expenditures by Component Government of Atlantis: Education Sector Improvement Project Sources and Uses of Funds World Bank (IBRD) Loan No ATL for the Quarter ended March 31, 2001 in Atlantic Pesos (APs) 000's Quarter Cumulative Institutional Strengthening 94, , ,000 Increasing Access 60, ,000 24,251 Teacher and Principal Development 2,500 17,450 5,500 Project Management 1,600 6,500 2,952 Other (including Loan Fee) - 12,250 12,000 Total Expenditures 158, , ,703 Receipts Less Expenditures (5,000) 58,000 20,297 Add: Foreign Exchange Difference (1,000) (14,000) 0 Net change in Cash (6,000) 44,000 20,297 Opening Cash Balances Project Bank Account 2, ,000 IBRD/IDA Special Account 48, ,000 Total Opening Cash 50, ,000 Add: Net change in cash (6,000) 44,000 20,297 Net Cash Available 44,000 44,000 64,297 Closing Cash Balances Project Bank Account 4,000 4,000 14,297 IBRD/IDA Special Account 40,000 40,000 50,000 Total Closing Cash Balances 44,000 44,000 64,297 Notes: /i. The following rates were used for conversion: - Opening balance of SA in Quarter: 1 US$= 14.7 APS; - IBRD funds received and any foreign currency expenditures made, are converted at the rate of exchange on the date of the transaction. The weighted average of these rates since project inception is approximately Closing balance of SA: 1 US$= 14.9 APS;

20 ANNEX A Sample I Page 4 of 8 (in Atlantic Pesos (APs) 000's) /i Quarter Cumulative PAD: Life of Revised Project Component/Activity /ii Planned Actual Variance Planned Actual Variance Project PAD /iv 1. Institutional Strengthening a. New Decentralized MIS 10,000 5,000 5,000 18,300 12,250 6,050 15,300 18,300 b. Construction of District Offices 42,500 54,000-11, , , , , ,000 c. Technical Assistance 40,000 34,500 5, , ,000 6, , ,050 d. Professional Training , ,355 1,650 1,650 e. Overseas Fellowships 4,000 1,100 2,900 19,000 17,500 1,500 51,000 51,000 Sub-total 96,600 94,695 1, , ,045-90,095 1,050,000 1,050, Increasing Access a. Secondary Schools Rehabilitation 27,250 25,000 2, ,000 95, , , ,000 b. New Community-Managed Prim. Schools 20,450 35,000-14, , ,000-25, , ,000 Sub-total 47,700 60,000-12, , ,000 80, , , Teacher and Principal Development a. Teacher Training 1,000 2,500-1,500 9,200 9, ,500 13,500 b. Management Training for Principals 1, ,500 6,800 7,950-1,150 15,000 15,000 Sub-total 2,500 2, ,000 17,450-1,450 38,500 28, Project Management a. Staff Costs ,400 4, ,000 10,000 b. Other /iii ,800 2, ,000 5,000 Sub-total 700 1, ,200 6, ,000 15, Other (including Loan Fee) ,000 12, ,000 12,000 Total Project Expenditure 147, ,795-11, , ,245-12,095 1,555,500 1,555,500 Note: /i Government of Atlantis: Education Sector Improvement Project World Bank (IBRD) Loan No ATL Uses of Funds by Project Activity--For the Quarter ended March 31, 2001 The exchange rates applicable to planned expenditures is 15 Aps/1US$. For actual expenditures, foreign currency payments are translated to Aps at the rate in effect on the date of the transaction. See Also the notes to the Sources and Uses of Funds Statement. /ii The items under "Project Activities" are those agreed with the World Bank at the time of appraisal, and as stated in the PAD. /iii Includes office rent, utility bills, office supplies, and other small expenditures /iv This reflects the revisions agreed to during the midterm review of December, 2000.

21 ANNEX A Sample I Page 5 of 8 Government of Atlantis: Education Sector Improvement Project Physical Progress Report World Bank (IBRD) Loan No ATL For the Quarter ending March 31, 2001 Par 1: Units of Output / i Total for Project Life Cumulative to Date Actual as a % Component/ Units of Total Costs (Actual) Units of Costs of total planned Activity No. Project Component/Activity /Output Output APS '000 Output /ii APS '000 for project life Comments 1 Institutional Strengthening Output Cost 1d Professional Training Technical courses 20 1, % 13% Workshops % 12% 1e Overseas Fellowships Masters Degree Program 10 6, ,800 40% 47% Doctorate Degree Program 25 45, ,000 20% 22% 3 Teacher and Principal Development 3a Teacher Training Refresher courses 15 4, ,500 67% 56% Workshops 30 9, ,000 73% 78% 3b Management Training for Principals Notes: School Management Courses 20 15, ,950 40% 53% See discussion / i This schedule includes certain non-construction activities that can be measured by units of output. Construction activities and major research projects are included in Part 2 of these Physical Progress Reports. /ii Includes only completed workshops, courses, fellowships, etc. Therefore costs reported here will in some cases appear to be high relative to outputs, since the costs include partially completed items.

22 Government of Atlantis: Education Sector Improvement Project Physical Progress Report World Bank (IBRD) Loan Number 1234-ATL For the Quarter ending March 31, 2001 ANNEX A Sample I Page 6 of 8 PART 2: CONTRACT/ WORK PROGRESS Component/ Activity No. Notes: Project Component/Activity /Output Cost (APS '000) Completion Date Cost (APS '000) Output /2 Cost to date as a % of Planned Total Cost /1 1 Institutional Strengthening 1b New District Education Offices Districts 1-2: Buildings A&B 140,000 10/31/ ,000 80% completed 86% Districst 3-5: Buildings C, D & E 250,000 6/30/ ,000 45% completed 40% District 6: Building F 100,000 12/31/ ,000 90% completed 105% Comments expected completion June '01 Districts 7-10: Building G, H, I & J 240,000 1/31/ Contract Signed 0% contract signed 3/28/01 1c Technical Assistance Physical Facilities Planning 150,000 10/13/ , % Completed 107% Design & Dev. of Academic Program for: - Agricultural Studies 30,050 6/30/ ,000 40% Completed 47% - Conflict Resolution 69,000 6/30/ ,000 80% Completed 87% 2 Education Quality 2a Sec. Schools Rehabilitation (20 schools) Original Plan to Completion Progress to date 300,000 6/30/ ,000 5 completed 27% completion date now 9/30/03 25, in progress average 22% complete Community-managed Primary 2b 150,000 6/30/ , completed 83% ahead of schedule Schools (50 one and two-room schools) 4,750 2 in progress /1 Costs to date represent the cash payments made to contractors. Since mobilization advances typically are for 20% of the contract amount, costs are generally overstated for projects in the early stages of completion. Since 10% of contracts are maintained as retention amounts, costs of contracts that are near 100% completion may be slightly understated. /2 Based on a combination of certification from contractors and inspection of works, goods, or services by project management. Where multiple units are involved, the Output figure is a weighted average. This calculation was discussed and agreed with the World Bank during project appraisal.

23 ANNEX A Sample I Page 7 of 8 PROCUREMENT REPORTS Government of Atlantis Atlantis Education Sector Improvement Project World Bank Loan No: 1234-ATL Procurement Status as of March 31, 2001 Part I, A Descriptive Summary: The procurement function has improved in the last six months, but there have been some particular implementation problems, as explained below. 1. Procurement staffing: An additional person with works experience has been hired by the PIU, and thus the project is fully staffed in the procurement function, with two professional staff and one assistant. The new staff member will attend the Bank-sponsored Procurement of Works training in October. He will be responsible for all refurbishing contracts of the IT centers. 2. Complaints by bidders, consultants, and end users: Complaints were received from two bidders for the refurbishing of the Main IT center. Both bidders complained that the financial working capital requirement stated in the bid document was too high, and even though they are fully capable of performing the contract and have done so in the past, they will not be able to participate in the competition as they do not meet the criteria. We have asked the Bank to reconsider this requirement. 3. Contract amendments, variations orders: In buildings B and C, due to the requirements of the District Fire Marshal, a sprinkler system has to be installed and some design changes are being made to increase the number of the Fire exit doors. This will be covered by an amendment to the contract. 4. Unsatisfactory performance by contractors/suppliers/consultants: The installation of the Education Information System is behind schedule. This will affect the overall implementation of the project. The supplier is blaming the consultant for system design, and the client for long delays in decision making. This is a major concern and will be discussed during the upcoming visit of the Bank s Procurement Specialist. 5. Disputes which may lead to contractual claims, cancellation of contracts, arbitration or legal remedies: The issue stated in 4 above is a potential contractual problem and may lead to claims by the contractor. Part II, Tables (format as agreed during project preparation): Table 1. Table 2. Table 3. Procurement of Goods Procurement of Works Selection of Consultants

24 ATLANTIS EDUCATION SECTOR IMPROVEMENT PROJECT: PROCUREMENT MONITORING TABLES TABLE 1: Procurement of Goods (contracts not subject to prior review but above US$ 25,000) TIME SCHEDULE (Dates) Start Doc REF# Description Estimate (US$) Procm't Prep. Advertise Bid Invitation Bid Opening Evaluation Contract Final Contract Amt Supplier Method Complete Signed delivery US$ Name ANNEX A Sample I Page 8 of Software & install 60,000 NCB Plan 6/2/2000 6/20/2000 7/5/2000 9/10/ /5/ /30/ /30/2000 Actual 6/15/2000 6/30/2000 7/20/2000 9/20/ /15/ /5/ /30/2000 Sell Computer 52,000 Inc Servers & install 249,000 NCB Plan 7/3/2000 8/5/2000 9/10/ /15/ /5/ /30/2000 1/10/2001 Actual 6/25/2000 7/30/2000 9/15/ /25/ /20/ /14/2000 1/30/ , computers & install 220,000 NCB Plan 8/5/2000 9/10/ /15/ /30/ /25/2000 1/20/2001 3/5/2001 DVW Traders Ltd. Actual 8/5/2000 9/15/ /20/ /5/ /30/2000 1/20/2001 3/10/ ,000 MW Computers servers & install 150,000 IS Plan 5/3/2001 6/15/2001 6/30/2001 7/25/2001 TABLE 2: Procurement of Works (not subject to prior review but above US$ 100,000) TIME SCHEDULE (Dates) REF# Description Estimate (US$) Procm't Start Doc Advertise Bid Invitation Bid Evaluation Contract Complete Contract Amt Contractor Method Preparation Opening Complete Signed Construction US$ Name District7-10, Bldg I 1,250,000 NCB Plan 7/5/2000 8/10/2000 9/20/ /30/2000 1/25/2001 3/28/2001 1/3/2004 Actual 8/15/2000 9/30/ /15/ /30/2000 2/15/2001 3/28/2001 CCC 1,350,000 Construction Sec. Schools Rehab 760,000 NCB Plan 6/10/2002 7/25/2002 9/15/ /25/ /30/2002 1/15/2003 6/30/2003 Actual District3-5, Bldg E 1,350,000 NCB Plan 6/10/2002 7/25/2002 9/15/ /25/ /30/2002 1/15/2003 6/30/2003 Actual Primary Schools 1,250,000 NCB Plan 6/10/2002 7/25/2002 9/15/ /25/ /30/2002 1/15/2003 6/30/2003 Actual TABLE 3: Selection of Consultants (not subject to prior review but above US$25,000) /I TIME SCHEDULE (Dates) REF# Description Estimate (US$) Selection Advertise Start RFP Doc Send out Tech Prop T Evaluation Final Eval Contract Complete Contract Amt Cons/Firm Method Preparation RFP Opening Complete Complete Signed Assignment US$ Name IT Staff trained 50,000 QBS Plan 8/5/2000 7/30/2000 9/5/ /15/ /20/ /15/ /25/2000 1/30/2001 Actual 8/5/2000 7/30/2000 9/5/ /15/ /20/ /15/ /25/2000 1/30/ ,000 GBM Professional Trng 51,000 QBS Plan 9/10/2000 8/15/ /15/ /25/ /20/2000 1/18/2001 2/5/2001 4/30/2001 Actual 10/10/2000 9/12/ /17/ /29/ /30/2000 1/25/2001 2/15/ ,000 B. Andersen O/seas Fellowship 45,000 IndividualPlan 9/20/ /25/ /30/ /10/ /30/2001 Actual 9/15/ /30/ /30/ /14/ ,000 Mr. Xxxx Teacher Training 180,000 QCBS Plan 10/15/2000 9/25/ /25/2000 1/10/2001 1/30/2001 2/20/2001 2/28/2001 4/30/2001 Actual 10/15/2000 9/30/ /30/2000 1/15/2001 2/15/2001 2/28/2001 3/5/ ,000 Trainers Inc. Notes: 1. Prior review thresholds: Goods US$250,000, Works US$1.5 million, Consultants $200,000 for firms and $50,000 for individuals. 2. Exchange rate used for contract expected to be in local currency: US$1 = 14.5 Aps.

FIDUCIARY ARRANGEMENTS FOR SECTORWIDE APPROACHES (SWAPS)

FIDUCIARY ARRANGEMENTS FOR SECTORWIDE APPROACHES (SWAPS) FIDUCIARY ARRANGEMENTS FOR SECTORWIDE APPROACHES (SWAPS) OPERATIONS POLICY AND COUNTRY SERVICES APRIL 2, 2002 FIDUCIARY ARRANGEMENTS FOR SECTORWIDE APPROACHES (SWAPS) CONTENTS Page I. Introduction..1 II.

More information

Outreach Seminar: Business Opportunities in World Bank-Funded Projects FY 2014

Outreach Seminar: Business Opportunities in World Bank-Funded Projects FY 2014 Outreach Seminar: Business Opportunities in World Bank-Funded Projects FY 2014 Lending, Trends, and Project Development Cycle Data as of Oct 2014 Fiscal Year 2014 = July 1, 2013 to June 30, 2014 339 Operations

More information

Development Credit Agreement

Development Credit Agreement Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized CONFORMED COPY CREDIT NUMBER 3993 STP Development Credit Agreement (Governance Capacity Building Technical Assistance

More information

Sustainable Island Resource Framework Fund OAS / Department of Environment Antigua and Barbuda

Sustainable Island Resource Framework Fund OAS / Department of Environment Antigua and Barbuda Sustainable Island Resource Framework Fund OAS / Department of Environment Antigua and Barbuda Marko Markov, St. John`s, 23 February 2016 1 WHAT IS SIRFF Special Fund established under the EPMA Independent

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE Appendix 3 9 A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The PPTA will review and assess the performance of the secondary education subsector in Viet Nam and identify the challenges, which

More information

VOLTA RIVER AUTHORITY

VOLTA RIVER AUTHORITY VOLTA RIVER AUTHORITY Capital Expenditure Guidelines November 2012 TABLE OF CONTENTS PAGE 1.0 Purpose and Scope of Guidelines...3 2.0 Projects Guidelines Apply To....4 3.0 Exemptions from Guidelines...4

More information

FM Harmonization Frequently Asked Questions August 2013

FM Harmonization Frequently Asked Questions August 2013 FM Harmonization Frequently Asked Questions August 2013 The harmonization of Financial Management (FM) arrangements by Development Partners (DPs) can assist in reducing the burden of multiple FM systems

More information

Business Transformation Project/Common Purpose 3.01 Procurement

Business Transformation Project/Common Purpose 3.01 Procurement MINISTRY OF COMMUNITY AND SOCIAL SERVICES Business Transformation Project/Common Purpose 3.01 Procurement Historically, the Ministry of Community and Social Services has provided social assistance to needy

More information

POLICY TITLE: Purchasing District Purchasing POLICY NO: 850 PAGE 1 of 11 PURCHASING POLICY 1 - DISTRICT PURCHASING

POLICY TITLE: Purchasing District Purchasing POLICY NO: 850 PAGE 1 of 11 PURCHASING POLICY 1 - DISTRICT PURCHASING POLICY TITLE: Purchasing District Purchasing POLICY NO: 850 PAGE 1 of 11 PURCHASING POLICY 1 - DISTRICT PURCHASING It is the policy of the Mountain Home School District to make purchases of goods, services,

More information

PROGRAM-FOR-RESULTS FINANCING INTERIM GUIDANCE NOTE TO STAFF: FIDUCIARY SYSTEMS ASSESSMENT. Operations Policy and Country Services

PROGRAM-FOR-RESULTS FINANCING INTERIM GUIDANCE NOTE TO STAFF: FIDUCIARY SYSTEMS ASSESSMENT. Operations Policy and Country Services PROGRAM-FOR-RESULTS FINANCING INTERIM GUIDANCE NOTE TO STAFF: FIDUCIARY SYSTEMS ASSESSMENT These interim guidance notes are intended for internal use by Bank staff to provide a framework to conduct assessments

More information

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF GEOTHERMAL POWER GENERATION DEVELOPMENT PROJECT GEF TF IND APPROVED ON MAY 29, 2008

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF GEOTHERMAL POWER GENERATION DEVELOPMENT PROJECT GEF TF IND APPROVED ON MAY 29, 2008 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF

More information

Loan Administration Change Initiative (LACI) Implementation Handbook

Loan Administration Change Initiative (LACI) Implementation Handbook Loan Administration Change Initiative (LACI) Implementation Handbook Preface This Handbook sets forth the main concepts of the Loan Administration Change Initiative (LACI) and provides guidance to Bank

More information

Mongolia: Development of State Audit Capacity

Mongolia: Development of State Audit Capacity Technical Assistance Report Project Number: 47198-001 Capacity Development Technical Assistance (CDTA) November 2013 Mongolia: Development of State Audit Capacity The views expressed herein are those of

More information

GUIDELINES: ANNUAL FINANCIAL REPORTING AND AUDITING FOR WORLD BANK-FINANCED ACTIVITIES

GUIDELINES: ANNUAL FINANCIAL REPORTING AND AUDITING FOR WORLD BANK-FINANCED ACTIVITIES GUIDELINES: ANNUAL FINANCIAL REPORTING AND AUDITING FOR WORLD BANK-FINANCED ACTIVITIES FINANCIAL MANAGEMENT SECTOR BOARD JUNE 30, 2003 ACRONYMS FMR IAS IASB IFAC-PSC IFRS INTOSAI IPSAS ISA MDB OECD-DAC

More information

Loan Agreement. (Real Property Registration and Cadastre Project) between REPUBLIC OF CROATIA. and

Loan Agreement. (Real Property Registration and Cadastre Project) between REPUBLIC OF CROATIA. and CONFORMED COPY LOAN NUMBER 4674 HR Loan Agreement (Real Property Registration and Cadastre Project) between REPUBLIC OF CROATIA and INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT Dated September

More information

III. modus operandi of Tier 2

III. modus operandi of Tier 2 III. modus operandi of Tier 2 Objective, country and project eligibility 70 Budget and timing 71 Project preparation: formulation of proposals 71 Project appraisal 72 Project approval 73 Agreements and

More information

World Bank HIV/AIDS Program

World Bank HIV/AIDS Program blic Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized World Bank HIV/AIDS Program A Guidance Note on Disbursement Procedures This document was

More information

Annex C. Sample ToR for Independent Procurement Review

Annex C. Sample ToR for Independent Procurement Review 1. Introduction Annex C. Sample ToR for Independent Procurement Review TERMS OF REFERENCE INDEPENDENT PROCUREMENT REVIEW (IPR) 1.1. The procurement team of the World Bank requires an independent review

More information

New Development Bank Procurement Policy

New Development Bank Procurement Policy New Development Bank Procurement Policy Owner: Operations Division Version: 2015 V4 Revision Date: [10] March 2016 Procurement Policy All rights reserved. Any unauthorized use, duplication or disclosure

More information

Procurement. OP January 2011 Page 1 of 10. Revised July 1, 2014

Procurement. OP January 2011 Page 1 of 10. Revised July 1, 2014 Page 1 of 10 "OP/BP11:00 "Procurement, were revised on July 2014 to take into account the recommendations in " World Bank Group A New Approach to Country Engagement" (R2014-0089), which were approved by

More information

Technical Cooperation: Guidelines for Clients Managing Donor Funded Consultancy Assignments. October 2014

Technical Cooperation: Guidelines for Clients Managing Donor Funded Consultancy Assignments. October 2014 Technical Cooperation: Guidelines for Clients Managing Donor Funded Consultancy Assignments October 2014 Definitions and Abbreviations Affiliate: AICU: Assignment: Consultant(s): Commitment Number: CRF:

More information

PEFA Handbook. Volume I: The PEFA Assessment Process Planning, Managing and Using PEFA

PEFA Handbook. Volume I: The PEFA Assessment Process Planning, Managing and Using PEFA PEFA Handbook Volume I: The PEFA Assessment Process Planning, Managing and Using PEFA October 18, 2016 PEFA Secretariat Washington DC USA 1 Table of Contents PEFA ASSESSMENT HANDBOOK... 5 Preface... 5

More information

PEFA Handbook. Volume I: The PEFA Assessment Process Planning, Managing and Using PEFA

PEFA Handbook. Volume I: The PEFA Assessment Process Planning, Managing and Using PEFA PEFA Handbook Volume I: The PEFA Assessment Process Planning, Managing and Using PEFA Second edition November 20, 2018 PEFA Secretariat Washington DC, USA Table of Contents PEFA ASSESSMENT HANDBOOK...

More information

GUIDELINES AND TERMS OF REFERENCE FOR AUDITS OF PROJECTS WITH FINANCING BY THE WORLD BANK IN THE LATIN AMERICA AND CARIBBEAN REGION

GUIDELINES AND TERMS OF REFERENCE FOR AUDITS OF PROJECTS WITH FINANCING BY THE WORLD BANK IN THE LATIN AMERICA AND CARIBBEAN REGION Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized GUIDELINES AND TERMS OF REFERENCE FOR AUDITS OF PROJECTS WITH FINANCING BY THE WORLD

More information

Lloyd s Underwriting Management Standards: Pre-Bind Quality Assurance (PBQA)

Lloyd s Underwriting Management Standards: Pre-Bind Quality Assurance (PBQA) market bulletin Ref: Y4015 Title Purpose Type From Lloyd s Underwriting Management Standards: Pre-Bind Quality Assurance (PBQA) To confirm expectations regarding Managing Agents procedures for Pre- Bind

More information

UNCONTROLLED WHEN PRINTED

UNCONTROLLED WHEN PRINTED 1. SUMMARY Process Definition: Finance and Contracting 1.1. This document defines the processes provided by the (F&S, or the Division) Finance and Contracting team in detail. 1.2. The relationship between

More information

SCOTTISH FUNDING COUNCIL CAPITAL PROJECTS DECISION POINT PROCESS

SCOTTISH FUNDING COUNCIL CAPITAL PROJECTS DECISION POINT PROCESS SCOTTISH FUNDING COUNCIL CAPITAL PROJECTS DECISION POINT PROCESS Incorporating amendments by Scottish Futures Trust (Proposals for Decision Points 2 5 Only) Executive summary... 1 Section 1: Introduction

More information

Fund for Gender Equality Monitoring and Evaluation Framework Executive Summary

Fund for Gender Equality Monitoring and Evaluation Framework Executive Summary Fund for Gender Equality Monitoring and Framework Executive Summary Primary Goal of the Monitoring and Framework The overall aim of this Monitoring and (M&E) Framework is to ensure that the Fund for Gender

More information

Country Practice Area(Lead) Additional Financing Social, Urban, Rural and Resilience P Indonesia Global Practice

Country Practice Area(Lead) Additional Financing Social, Urban, Rural and Resilience P Indonesia Global Practice Public Disclosure Authorized 1. Project Data Report Number : ICRR0021284 Public Disclosure Authorized Public Disclosure Authorized Project ID P111577 Project Name ID-Local Government and Decentralization

More information

Consolidated Procurement Plan

Consolidated Procurement Plan Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized I. General Consolidated Procurement Plan 2. Project information: ZIMBABWE The Zimbabwe PFM Enhancement Project responds

More information

Joint Partnership Arrangement

Joint Partnership Arrangement Joint Partnership Arrangement Concerning Common Arrangements for Joint Support to the Health Strategic Plan 2008-2015 between the Royal Government of Cambodia and the 2nd Health Sector Support Program

More information

Multi-Donor Trust Fund for the Malawi Public Finance and Economic Management Reform Program Grant Agreement

Multi-Donor Trust Fund for the Malawi Public Finance and Economic Management Reform Program Grant Agreement Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized MDTF GRANT NUMBER TF013825 Multi-Donor Trust Fund for the Malawi Public Finance and Economic Management Reform Program

More information

SAMPLE REQUEST FOR PROPOSALS UNDER JAPANESE ODA LOANS

SAMPLE REQUEST FOR PROPOSALS UNDER JAPANESE ODA LOANS CONSULTANTS SAMPLE REQUEST FOR PROPOSALS UNDER JAPANESE ODA LOANS SELECTION OF CONSULTANTS Japan International Cooperation Agency (JICA) September 2009 version 1.0 CONTENTS Preface... i Section 1. Letter

More information

Science and Information Resources Division

Science and Information Resources Division MINISTRY OF NATURAL RESOURCES Science and Information Resources Division The mandate of the Ministry of Natural Resources is to achieve the sustainable development of the province s natural resources,

More information

Standard Form of Agreement Between OWNER AND CONSTRUCTION MANAGER Construction Manager as Owner s Agent

Standard Form of Agreement Between OWNER AND CONSTRUCTION MANAGER Construction Manager as Owner s Agent CMAA Document A-1 Standard Form of Agreement Between OWNER AND CONSTRUCTION MANAGER Construction Manager as Owner s Agent 2013 EDITION This document is to be used in connection with the Standard Form of

More information

2 nd INDEPENDENT EXTERNAL EVALUATION of the EUROPEAN UNION AGENCY FOR FUNDAMENTAL RIGHTS (FRA)

2 nd INDEPENDENT EXTERNAL EVALUATION of the EUROPEAN UNION AGENCY FOR FUNDAMENTAL RIGHTS (FRA) 2 nd INDEPENDENT EXTERNAL EVALUATION of the EUROPEAN UNION AGENCY FOR FUNDAMENTAL RIGHTS (FRA) TECHNICAL SPECIFICATIONS 15 July 2016 1 1) Title of the contract The title of the contract is 2nd External

More information

OPERATIONS MANUAL BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject.

OPERATIONS MANUAL BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject. OM Section H5/BP Page 1 of 4 BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject. A. Introduction ADDITIONAL FINANCING 1. The

More information

Chapter 33 Coordinating the Use of Lean Across Ministries and Certain Other Agencies

Chapter 33 Coordinating the Use of Lean Across Ministries and Certain Other Agencies Chapter 33 Coordinating the Use of Lean Across Ministries and Certain Other Agencies 1.0 MAIN POINTS The Government is seeking to use Lean as a systematic way to improve service delivery and create a culture

More information

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Report No.

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Report No. Project Name Region Sector Project ID Borrower(s) Report No. PID5794 Lebanon-Municipal Infrastructure Project (@+) Middle East and North Africa Region Other Urban Development LBPE50544 Lebanese Republic

More information

BENCHMARKING PPP PROCUREMENT 2017 IN MAURITIUS

BENCHMARKING PPP PROCUREMENT 2017 IN MAURITIUS BENCHMARKING PPP PROCUREMENT 2017 IN MAURITIUS Regulatory and Institutional Framework for PPPs Does the regulatory framework in your country allow procuring PPPs?. If yes, please specify the relevant regulatory

More information

IPP TRANSACTION ADVISOR TERMS OF REFERENCE

IPP TRANSACTION ADVISOR TERMS OF REFERENCE IPP TRANSACTION ADVISOR TERMS OF REFERENCE Terms of reference for transaction advisor services to the Government of [ ] for the [insert description of the project] (the Project ). Contents 1. Introduction

More information

INTERNATIONAL ASSOCIATION OF INSURANCE SUPERVISORS

INTERNATIONAL ASSOCIATION OF INSURANCE SUPERVISORS Guidance Paper No. 2.2.x INTERNATIONAL ASSOCIATION OF INSURANCE SUPERVISORS GUIDANCE PAPER ON ENTERPRISE RISK MANAGEMENT FOR CAPITAL ADEQUACY AND SOLVENCY PURPOSES DRAFT, MARCH 2008 This document was prepared

More information

HLCM Procurement Network Procurement Process and Practice Harmonization in Support of Field Operations, Phase II

HLCM Procurement Network Procurement Process and Practice Harmonization in Support of Field Operations, Phase II HLCM Procurement Network Procurement Process and Practice Harmonization in Support of Field Operations, Phase II Introduction This Project proposal has been prepared by the HLCM Procurement Network (PN)

More information

UNICEF Moldova. Terms of Reference

UNICEF Moldova. Terms of Reference UNICEF Moldova Terms of Reference Individual Consultancy on Public Finance for Development of the National Action Plan for Gradual Implementation of the Sanitary and Hygiene Norms for Preschools Duration

More information

Capital Improvement Projects

Capital Improvement Projects REPORT # 2011-12 AUDIT Of the Richmond City Department of Parks, Recreation and Community Facilities Capital Improvement Projects TABLE OF CONTENTS Executive Summary..... i Comprehensive List of Recommendations

More information

Facilities Planning (Revised 2016)

Facilities Planning (Revised 2016) Facilities Planning (Revised 2016) Chapter 7830 Draft Revision November 2016 Table of Contents.010 Campus Planning & Project Management.020 Definitions.030 Small/Medium Projects Project Decision Process

More information

Development Credit Agreement. (Provincial Health Project) between REPUBLIC OF INDONESIA. and INTERNATIONAL DEVELOPMENT ASSOCIATION

Development Credit Agreement. (Provincial Health Project) between REPUBLIC OF INDONESIA. and INTERNATIONAL DEVELOPMENT ASSOCIATION Public Disclosure Authorized CONFORMED COPY CREDIT NUMBER 3381 IND Public Disclosure Authorized Development Credit Agreement (Provincial Health Project) between REPUBLIC OF INDONESIA and Public Disclosure

More information

- and - - and - KPMG INC.

- and - - and - KPMG INC. CANADA PROVINCE OF QUEBEC DISTRICT OF QUEBEC DIVISION: 01-MONTREAL S.C.: 500-11-051625-164 500-11-051624-167 IN THE MATTERS OF THE NOTICES OF INTENTION AND OF THE INTERIM RECEIVERSHIP OF: S U P E R I O

More information

Charter School Financial Performance Framework and Guidance

Charter School Financial Performance Framework and Guidance DPI Charter School Financial Performance Framework Guide Charter School Financial Performance Framework and Guidance North Carolina Department of Public Instruction Division of School Business Revised

More information

Development Credit Agreement

Development Credit Agreement Public Disclosure Authorized CONFORMED COPY CREDIT NUMBER 3909 YF Public Disclosure Authorized Development Credit Agreement (Transport Rehabilitation Project) Public Disclosure Authorized between SERBIA

More information

IFAD Handbook for Financial Reporting and Auditing of IFAD- Financed Projects

IFAD Handbook for Financial Reporting and Auditing of IFAD- Financed Projects - 2018 IFAD Handbook for Financial Reporting and Auditing of IFAD- Financed Projects 1 The IFAD Handbook for Financial Reporting and Auditing for IFAD-Financed Projects is available online for public use

More information

(Taunsa Barrage Emergency Rehabilitation and Modernization Project) between INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT.

(Taunsa Barrage Emergency Rehabilitation and Modernization Project) between INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT. Public Disclosure Authorized CONFORMED COPY LOAN NUMBER 7277-PAK Public Disclosure Authorized Project Agreement (Taunsa Barrage Emergency Rehabilitation and Modernization Project) Public Disclosure Authorized

More information

Proposal to adopt International Public Sector Accounting Standards (IPSAS) by the Agency

Proposal to adopt International Public Sector Accounting Standards (IPSAS) by the Agency Board of Governors GOV/2007/10 Date: 13 February 2007 Restricted Distribution Original: English For official use only Programme and Budget Committee Proposal to adopt International Public Sector Accounting

More information

THE GLOBAL FUND to Fight AIDS, Tuberculosis and Malaria

THE GLOBAL FUND to Fight AIDS, Tuberculosis and Malaria THE GLOBAL FUND to Fight AIDS, Tuberculosis and Malaria Guidelines for Annual Audits of Program Financial Statements Table of Contents 1. Introduction 2. Operational Policies and Practices 3. Follow-up

More information

AFRICAN DEVELOPMENT BANK GROUP

AFRICAN DEVELOPMENT BANK GROUP AFRICAN DEVELOPMENT BANK GROUP Rules and Procedures for the Use of Consultants Procurement and Fiduciary Services Department (ORPF) May 2008 Edition TABLE OF CONTENTS I. INTRODUCTION --------------------------------------------------------------------------------

More information

Guidelines for Financial Assurance Planning

Guidelines for Financial Assurance Planning For Global Fund Grants Guidelines for Financial Assurance Planning June 2016 Geneva, Switzerland The financial assurance plan provides improvements to the way the Global Fund obtains financial assurance

More information

Minneapolis Public Schools Special District No. 1. Reports on Government Auditing Standards, Uniform Guidance and Legal Compliance.

Minneapolis Public Schools Special District No. 1. Reports on Government Auditing Standards, Uniform Guidance and Legal Compliance. Reports on Government Auditing Standards, Uniform Guidance and Legal Compliance June 30, 2016 Table of Contents Schedule of Expenditures of Federal Awards 1 Notes to the Schedule of Expenditures of Federal

More information

(Second Education Project) between. and

(Second Education Project) between. and Public Disclosure Authorized CREDIT NUMBER CONFORMED COPY 663 MAG Public Disclosure Authorized DEVELOPMENT CREDIT AGREEMENT Public Disclosure Authorized (Second Education Project) between DEMOCRATIC REPUBLIC

More information

Global Environment Facility Grant Agreement

Global Environment Facility Grant Agreement Public Disclosure Authorized CONFORMED COPY GEF GRANT NUMBER TF092100 Public Disclosure Authorized Global Environment Facility Grant Agreement (Agricultural Development Program Support Project) Public

More information

October Hundred and Fortieth Session. Rome, October Measures to improve Implementation of the Organization's Support Cost Policy

October Hundred and Fortieth Session. Rome, October Measures to improve Implementation of the Organization's Support Cost Policy October 2011 FC 140/8 E FINANCE COMMITTEE Hundred and Fortieth Session Rome, 10-14 October 2011 Measures to improve Implementation of the Organization's Support Cost Policy Queries on the substantive content

More information

Social Protection Discussion Paper Series

Social Protection Discussion Paper Series No. 0106 Social Protection Discussion Paper Series Guide for Task Teams on Procurement Procedures Used in Social Funds Jorge A. Cavero Uriona February 2001 Social Protection Unit Human Development Network

More information

Chapter 8 Special Categories of Contracts

Chapter 8 Special Categories of Contracts Sam Chapter 8 Special Categories of Contracts Section 1 Supplemental Policy and Procedure................................. 207 8.1.1 General......................................................... 207

More information

Financing Agreement CONFORMED COPY GRANT NUMBER H732 -AF. (Financial Sector Rapid Response Project) between ISLAMIC REPUBLIC OF AFGHANISTAN.

Financing Agreement CONFORMED COPY GRANT NUMBER H732 -AF. (Financial Sector Rapid Response Project) between ISLAMIC REPUBLIC OF AFGHANISTAN. Public Disclosure Authorized CONFORMED COPY GRANT NUMBER H732 -AF Public Disclosure Authorized Financing Agreement Public Disclosure Authorized (Financial Sector Rapid Response Project) between ISLAMIC

More information

FOR OFFICIAL USE ONLY

FOR OFFICIAL USE ONLY Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY PROJECT PAPER ON A PROPOSED ADDITIONAL

More information

People s Republic of China: Study on Natural Resource Asset Appraisal and Management System for the National Key Ecological Function Zones

People s Republic of China: Study on Natural Resource Asset Appraisal and Management System for the National Key Ecological Function Zones Technical Assistance Report Project Number: 50004-001 Policy and Advisory Technical Assistance (PATA) October 2016 People s Republic of China: Study on Natural Resource Asset Appraisal and Management System

More information

INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT

INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT CONFORMED COPY LOAN NUMBER 7971-BY Loan Agreement (Road Upgrading and Modernization Project) between REPUBLIC OF BELARUS and INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT Dated November 19, 2010

More information

Internal Audit of the Republic of Albania Country Office January Office of Internal Audit and Investigations (OIAI) Report 2017/24

Internal Audit of the Republic of Albania Country Office January Office of Internal Audit and Investigations (OIAI) Report 2017/24 Internal Audit of the Republic of Albania Country Office January 2018 Office of Internal Audit and Investigations (OIAI) Report 2017/24 Internal Audit of the Albania Country Office (2017/24) 2 Summary

More information

UNIVERSAL SERVICE AND ACCESS FINAL REPORT

UNIVERSAL SERVICE AND ACCESS FINAL REPORT UNIVERSAL SERVICE AND ACCESS FINAL REPORT 0 1 Contents INTRODUCTION... 2 Updates... 4 Electronic Communications Bill... 4 Electronic Communications (Universal Service and Access Fund) Regulations... 12

More information

Socialist Republic of Vietnam. Reporting Period: From 08/20/2017 to 04/03/2018 Report Date: 04/03/2018 Ministry of Natural Resources and Environment

Socialist Republic of Vietnam. Reporting Period: From 08/20/2017 to 04/03/2018 Report Date: 04/03/2018 Ministry of Natural Resources and Environment PMR Project Implementation Status Report (ISR) 1. SUMMARY INFORMATION Implementing Country/Technical Partner: Socialist Republic of Vietnam Reporting Period: From 08/20/2017 to 04/03/2018 Report Date:

More information

QUESTIONNAIRE ON FISCAL INSTITUTIONS [COUNTRY]

QUESTIONNAIRE ON FISCAL INSTITUTIONS [COUNTRY] QUESTIONNAIRE ON FISCAL INSTITUTIONS [COUNTRY] This questionnaire is designed to gather basic information on fiscal institutions and practices as a basis for review of a country's fiscal management system

More information

Liberia Reconstruction Trust Fund Implementation Manual

Liberia Reconstruction Trust Fund Implementation Manual Liberia Reconstruction Trust Fund Implementation Manual Updated November 2009 2011-02-28 LRTF Implementation Manual 1 I. Background... 3 II. Coverage... 3 III. General Principles... 4 IV. Project Development

More information

Affordable Housing Program 2018 Implementation Plan

Affordable Housing Program 2018 Implementation Plan Affordable Housing Program 2018 Implementation Plan I) Overview of the Affordable Housing Program A) Introduction Affordable Housing Program 2018 Implementation Plan The Affordable Housing Program ( AHP

More information

VANUATU NATIONAL INFRASTRUCTURE MASTERPLAN. Terms of Reference for Consultants

VANUATU NATIONAL INFRASTRUCTURE MASTERPLAN. Terms of Reference for Consultants VANUATU NATIONAL INFRASTRUCTURE MASTERPLAN Terms of Reference for Consultants 1. BACKGROUND INFORMATION Government of Vanuatu has requested TA support in the formulation and preparation of a national infrastructure

More information

Republic of Indonesia: Aligning Asian Development Bank and Country Systems for Improved Project Performance

Republic of Indonesia: Aligning Asian Development Bank and Country Systems for Improved Project Performance Technical Assistance Report Project Number: 47287-001 Capacity Development Technical Assistance (CDTA) December 2013 Republic of Indonesia: Aligning Asian Development Bank and Country Systems for Improved

More information

ST/SGB/2018/3 1 June United Nations

ST/SGB/2018/3 1 June United Nations 1 June 2018 United Nations Regulations and Rules Governing Programme Planning, the Programme Aspects of the Budget, the Monitoring of Implementation and the Methods of Evaluation Secretary-General s bulletin

More information

South Sudan Common Humanitarian Fund (South Sudan CHF) Terms of Reference (TOR)

South Sudan Common Humanitarian Fund (South Sudan CHF) Terms of Reference (TOR) South Sudan Common Humanitarian Fund (South Sudan CHF) Terms of Reference (TOR) 14 February 2012 List of Acronyms AA Administrative Agent AB Advisory Board CAP Consolidated Appeal Process CHF Common Humanitarian

More information

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING THE EMERGENCY SCHOOL CONSTRUCTION AND REHABILITATION PROJECT (ESCRP TF GRANT )

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING THE EMERGENCY SCHOOL CONSTRUCTION AND REHABILITATION PROJECT (ESCRP TF GRANT ) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF

More information

ENERGY SAVINGS PERFORMANCE CONTRACT. between THE CITY [\] / MUNICIPALITY [\] and [ESCO COMPANY]

ENERGY SAVINGS PERFORMANCE CONTRACT. between THE CITY [\] / MUNICIPALITY [\] and [ESCO COMPANY] ENERGY SAVINGS PERFORMANCE CONTRACT between THE CITY [\] / MUNICIPALITY [\] and [ESCO COMPANY] At [place], [day] [month] 2014 1 Pursuant to (i) Article 26 in relation to Article 27 of the Energy Efficiency

More information

Comfort Letters and Due Diligence Meetings

Comfort Letters and Due Diligence Meetings HKSIR 400 Issued October 2005 Revised October 2011, December 2012 Effective for engagements where the investment circular is dated on or after 1 January 2006 Hong Kong Standard on Investment Circular Reporting

More information

Greater Bristol Bus Network Major Scheme Business Case. Chapter 1. Developing the Full Approval Major Scheme Business Case

Greater Bristol Bus Network Major Scheme Business Case. Chapter 1. Developing the Full Approval Major Scheme Business Case Greater Bristol Bus Network Major Scheme Business Case Chapter 1 Developing the Full Approval Major Scheme Business Case i ii 1. The Case for Full Approval INTRODUCTION 1.1.1 Bath and North East Somerset,

More information

UPDATE. Financial Intermediary Lending and Environmental Assessment. Environmental Assessment

UPDATE. Financial Intermediary Lending and Environmental Assessment. Environmental Assessment Environmental Assessment S o u r c e b o o k UPDATE Environment Department June 2002 The World Bank Number 27 Financial Intermediary Lending and Environmental Assessment The World Bank supports economic

More information

MINNEAPOLIS PUBLIC SCHOOLS SPECIAL DISTRICT NO. 1 REPORTS ON GOVERNMENT AUDITING STANDARDS, OMB CIRCULAR A-133 SINGLE AUDIT AND LEGAL COMPLIANCE

MINNEAPOLIS PUBLIC SCHOOLS SPECIAL DISTRICT NO. 1 REPORTS ON GOVERNMENT AUDITING STANDARDS, OMB CIRCULAR A-133 SINGLE AUDIT AND LEGAL COMPLIANCE REPORTS ON GOVERNMENT AUDITING STANDARDS, OMB CIRCULAR A-133 SINGLE AUDIT AND LEGAL COMPLIANCE For the Year Ended TABLE OF CONTENTS SCHEDULE OF EXPENDITURES OF FEDERAL AWARDS... 1 NOTES TO THE SCHEDULE

More information

IFAD Handbook for Financial Reporting and Auditing of IFAD-financed Projects

IFAD Handbook for Financial Reporting and Auditing of IFAD-financed Projects IFAD Handbook for Financial Reporting and Auditing of IFAD-financed Projects The IFAD Handbook for Financial Reporting and Auditing of is available online for public use and dissemination. It is primarily

More information

AFGHANISTAN ALLOCATION GUIDELINES 22 JANUARY 2014

AFGHANISTAN ALLOCATION GUIDELINES 22 JANUARY 2014 AFGHANISTAN ALLOCATION GUIDELINES 22 JANUARY 2014 I. Contents Introduction... 2 Purpose... 2 Scope... 2 Rationale... 2 Acronyms... 2 I. Funding Mechanisms... 3 A. Eligibility... 3 B. Standard Allocation...

More information

C.A.O. BRIEFING NOTE FAIRNESS AND EQUITY

C.A.O. BRIEFING NOTE FAIRNESS AND EQUITY C.A.O. BRIEFING NOTE FAIRNESS AND EQUITY Measurable Standards and Criteria for Consultants - Commissioners have taken the necessary steps to ensure that measurable standards and acceptance criteria are

More information

Project Administration Instructions

Project Administration Instructions Project Administration Instructions PAI 6.02 Page 1 of 2 PROJECT ADMINISTRATION MISSIONS A. Introduction 1. ADB missions dispatched for loan and technical assistance (TA) project administration are classified

More information

Productive Partnerships In Agriculture (PPAP) PROJECT IMPLEMENTATION MANUAL

Productive Partnerships In Agriculture (PPAP) PROJECT IMPLEMENTATION MANUAL Productive Partnerships In Agriculture (PPAP) PROJECT IMPLEMENTATION MANUAL Section 4 Financial Management Manual MARCH 15, 2010 PNG Department of Agriculture and Livestock PO Box 2033 Port Moresby NCD

More information

INCLUSIVE HOUSING FINANCE PROGRAM

INCLUSIVE HOUSING FINANCE PROGRAM Public Disclosure Authorized INCLUSIVE HOUSING FINANCE PROGRAM Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized 1. The assessment 1 indicates that the fiduciary systems

More information

GGGI Project Cycle Management Manual

GGGI Project Cycle Management Manual GGGI Project Cycle Management Manual VERSION 1.0 1 VERSION CONTROL Current version: Version 1.0 Authorized by: Date: 27 January 2017 Frank Rijsberman, Director General, GGGI 2 Contents Acronyms...4 1.

More information

CLIENT INFORMATION HANDBOOK & TERMS & CONDITIONS

CLIENT INFORMATION HANDBOOK & TERMS & CONDITIONS Updated: - March 2015 FEE REFERENCE: - SFA/19.05.2015 MGL- ARCHITECTS. CLIENT INFORMATION HANDBOOK & TERMS & CONDITIONS Contents: - 1) Services - Scope of Work 2) Fees - Cost of Work 3) MGL - Terms & Conditions

More information

Document of The World Bank

Document of The World Bank Document of The World Bank PROJECT COMPLETION NOTE OF A LEARNING AND INNOVATION LOAN IN THE AMOUNT OF SDR 2.7 MILLION (US$4 MILLION EQUIVALENT) TO THE REPUBLIC OF MALAWI FOR A DEVELOPMENT LEARNING CENTER

More information

AUDIT UNDP AFGHANISTAN. Local Governance Project (Project No ) Report No Issue Date: 23 December 2016

AUDIT UNDP AFGHANISTAN. Local Governance Project (Project No ) Report No Issue Date: 23 December 2016 UNITED NATIONS DEVELOPMENT PROGRAMME AUDIT OF UNDP AFGHANISTAN Local Governance Project (Project No. 90448) Report No. 1745 Issue Date: 23 December 2016 Table of Contents Executive Summary i I. About the

More information

Memo No. Issue Summary No. 1, Supplement No. 2. Issue Date October 29, Meeting Date(s) EITF November 12, 2015

Memo No. Issue Summary No. 1, Supplement No. 2. Issue Date October 29, Meeting Date(s) EITF November 12, 2015 Memo No. Issue Summary No. 1, Supplement No. 2 Memo Issue Date October 29, 2015 Meeting Date(s) EITF November 12, 2015 Contact(s) Jenifer Wyss Lead Author, Project Lead (203) 956-3479 Jane Rizzuto Co-Author

More information

Program-for-Results Financing 1

Program-for-Results Financing 1 Operational Manual BP 9.00 - Program-for-Results Financing These procedures were prepared for use by World Bank staff and are not necessarily a complete treatment of the subject. BP 9.00 February, 2012

More information

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Jun ,670,000.00

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Jun ,670,000.00 Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0020366 Public Disclosure Authorized Public Disclosure Authorized Project ID P107666 Country Peru Project

More information

Guidance document on. management verifications to be carried out by Member States on operations co-financed by

Guidance document on. management verifications to be carried out by Member States on operations co-financed by Final version of 05/06/2008 COCOF 08/0020/04-EN Guidance document on management verifications to be carried out by Member States on operations co-financed by the Structural Funds and the Cohesion Fund

More information

DOCU MENTS FOFFRCIAL71?

DOCU MENTS FOFFRCIAL71? Public Disclosure Authorized FOFFRCIAL71? DOCU MENTS The.World Bank 1818 H Street N.W. (202) 473-1000 INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT Washington, D.C. 20433 Cable Address: INTBAFRAD

More information

Federal Republic of Somalia Ministry of Post and Telecommunications REQUEST FOR EXPRESSIONS OF INTEREST/APPLICATIONS

Federal Republic of Somalia Ministry of Post and Telecommunications REQUEST FOR EXPRESSIONS OF INTEREST/APPLICATIONS JAMHUURIYADDA FEDRAALKA SOOMAALIYA Wasaaradda raz Boostada & Isgaarsiinta Mashruuca Taakulaynta Isgaarsiinta (P148588) Federal Republic of Somalia Ministry of Post and Telecommunications جمهورية الصومال

More information

INDIA LOW INCOME HOUSING FINANCE PROJECT. Request for Expressions of Interest

INDIA LOW INCOME HOUSING FINANCE PROJECT. Request for Expressions of Interest INDIA LOW INCOME HOUSING FINANCE PROJECT Request for Expressions of Interest Capacity building for housing finance lending to informal borrowers and making use of informal property as loan collateral Loan

More information

Obtaining Quality Employee Benefit Plan Audit Services: The Request for Proposal and Auditor Evaluation Process

Obtaining Quality Employee Benefit Plan Audit Services: The Request for Proposal and Auditor Evaluation Process Obtaining Quality Employee Benefit Plan Audit Services: The Request for Proposal and Auditor Evaluation Process The AICPA Employee Benefit Plan Audit Quality Center has prepared this document to assist

More information