1 Part I. Capital Programs Office Report: Capital Spending Update Part II. Transforming Capital Delivery September 12, 2016
2 Table of Contents 1) Capital Programs Office Report: Capital Spending Update 2) Transforming Capital Delivery 2
3 Overview Improving capital delivery is critical Capital delivery is vital to MBTA operations, service improvement and MBTA commitment to our customers FY 2017 FY 2021 CIP is different from previous CIPs o Improved focus and alignment on needs and priorities o Underdeveloped in terms of cashflows and deliverability Capital spending must more than double to achieve CIP spending levels o Actual spending FY 2012 FY 2016 was $3 billion o CIP programs $6.5 billion for FY STRATEGY PIPELINE $SPEND Priority Setting & Funding Availability (5-year CIP) Project Development (need, scope, budget and schedule) Delivery (design, plan of finance, procurement, construction/ manufacture) 3
4 Overview 1. Problems have been chronicled from Governor s Special Panel Assessment of MBTA April 2015 Unsustainable Operating Budget Lack of Accountability Chronic Capital Underinvestment Flawed Contracting Processes Bottlenecked Project Delivery Lack of Customer Focus Ineffective Workplace Practices Shortsighted Expansion Program Organizational Instability 4
5 Overview 2. Problems have been chronicled Ascent PGM Assessment Summer Capital delivery has historically not been a strategic imperative 2. Project development and budgeting processes inhibit effective program execution 3. Lack of data and a system of controls hinders effective decision-making 4. Cultural change is critical to the Capital Delivery transformation 5
6 Part I: Capital Spending Update 6
7 Capital Programs Report Delivering FY 17 CIP: Spending forecast of $850M-$950M Started with FY CIP priorities FY CIP projects an average annual spend of ~$1.3B Conducted a 30-day initial review of project spend plans based on input from each of the Authority s 32 Program Directors and 70 Project Managers and follow-up meetings with the Program Directors Developed a FY 2017 delivery and spend forecast of $850M - $950M, organized by programs and projects 7
8 Capital Programs Report FY 2017 projected spend is 21% increase over FY 2016 MBTA Capital Spending 8
9 Capital Programs Report FY 2017 forecasted spending on top CIP priorities reliability and modernization approximately 59% higher than prior year actual spending ~$850M-$950M 59% 9
10 Capital Programs Report FY 2017 YTD spending significantly lags both FY 2017 forecast and FY 2016 YTD (through August) Average Weekly Capital Spend (YTD Aug - 2 months) FY 2016 FY 2017 $16.9M $8.3M $135.2M YTD Aug 2015 (FY16-2 months) $66.6M YTD Aug 2016 (FY17-2 months) $22.5 M of spending variance due to lower spending on GLX 10
11 Capital Programs Report FY17 Projected vehicle department spend represents ~50% of overall projected spend and ramps up later in the year *Includes Revenue Vehicles program, R/O vehicles, and Green Line Type 9 vehicles. 11
12 FY 2017 CIP vs. FY 2017 Forecast Top 10 Programs represent 86% of FY 2017 forecast Top Projects (Program) FY 2016 Spending (ACTUAL) FY17 Forecast* (CURRENT) Accelerators R/O Line Infrastructure / Vehicles $46.0 $115.9 Positive Train Control** Functional Programs (SGR) Revenue Vehicles $121.9 $349.3 Bridge Winter Resiliency (Phase I & 2)*** Power Station Improvements Signals Expansion GLX $180.1 $80.3 Fitchburg Line Commuter Rail Top Programs Total $493.7 $770.4 Grand Total $743.0 $900.0 *Represents mid-point of range ($850M-$950M) **Payments only; does not include $58M of earned value ***Winter Resiliency does not include funding from operating budget. 12
13 Part 2: Transforming MBTA Capital Delivery 13
14 Transforming Capital Delivery Overview Objective: Transform capital delivery to achieve CIP (from $3B delivery in the last 5 years to $6.5B delivery in coming 5-years aligned with need and strategy) Recommendations: 1. Organization and capacity Develop organizational capability and structure to better integrate capital delivery and operations 2. Capital program management and controls Strengthen capital program management & controls 3. Streamline procurement and funding 4. Program acceleration Establish an integrated program focus on 2-3 transformation accelerator programs 14
15 Transforming Capital Delivery Short-term and Mid-term Initiatives Initiatives Short-term Mid-term Organization & Capacity Deliverable CIP/ Develop pipeline Create executive level Capital Program Office (complete) Establish a capital development coordination committee (underway) Recruit critical capital delivery leaders and staff (underway) FY 17 CIP Scrub (complete) Remove funding and financing bottlenecks (underway) Shorten procurement process (underway) Fund additional projects through pay go capital (underway) Develop a pipeline of future projects in line with CIP Bring all capital delivery together to align with maintenance and operations Strengthen development process for FY 18 CIP Explore alternative procurement methods Capital Program Management & Controls Track all projects through interim portfolio monthly reporting (underway) Convert tracking and reporting approach from funds-based to project-based (underway) Program Focus Accelerate transformation through focus on top programs (PTC, R/O line) (underway) Create cross-functional teams with culture of accountability (underway) Plan, budget and implement an integrated PMIS Develop portfolio wide controls team Set outcome-based goals and key performance indicators Roll out to other programs in portfolio 15
16 Transforming Capital Delivery 1. Organization and Capacity Objective: Capable organization with capacity to deliver capital and improve integration with operations. Steps: 1. Create an executive level Capital Programs Office with oversight of capital delivery as a whole (underway) 2. Create a Capital Development Coordination Committee to support the CIP, capital pipeline development and prioritizing capital delivery (underway) 3. Create an Infrastructure Group responsible for all capital delivery (currently in three separate areas D&C, E&M and Railroad Ops) (underway) 4. Expand project controls to cover the full capital program (currently only covers D&C with separate Vehicle Engineering controls) 5. Recruit leadership to each area (underway) 6. Staff up according to capital delivery demand (being planned) 16
17 Transforming Capital Delivery 2. Shorten construction procurement process Project Procurement Process Concept Planning (Variable Timeframe) Design Procurement (11-12 Month Process) Design (Variable Timeframe) Construction Procurement (7-9 Month Process) Construction (Variable Timeframe) 17
18 Transforming Capital Delivery 2. Shorten construction procurement process to no more than 3 months GOAL: Reduce Advertisement to Contractor NTP (Notice to Proceed) to no more than 3 months Current Issues: Duplicative processes, Extensions to Bid Period, Excessive time required to complete routine tasks Approach: - Eliminate duplicative processes - Hold to Stated Bid Periods - Reduce time for routine tasks - Review Bid Timelines with Construction Industry groups - Engage Capital Programs Office - Validate approach 18
19 Transforming Capital Delivery 2. Shorten construction procurement: winterization shows success is possible Construction Procurement Process SUCCESS STORY Winter Resiliency FY 2016 Actual Spending: $45.4M Winter Resiliency FY 2017 Spending Forecast: $41.4M Winter Resiliency II 6/10/16 Advertising Date 7/6/16 Bid Opening 7/25/16 FMCB Approval 7/26/16 Notice of Award 8/15/16 Contract Executed and NTP Issued 66 Days from Project Advertisement to Contractor NTP First Weekend Work on Schedule for the Weekend of 9/10 We should achieve these results on all jobs 19
20 Transforming Capital Delivery 2. Shorten construction procurement process Total of all Projects to be advertised between now and 2016 YE = $194,800,000 Test Projects Projects to be advertised between now and 2016 YE Project Name On-Call Contracting Services - Trackwork Wellington Track Expansion Tracks Rockport Commuter Rail Layover Facility Mansfield Commuter Rail Accessibility Improvements IT Data Center, 45 High Street Central Square & Harvard Station Elevators Wollaston Station Improvements Fairmount Line Blue Hill Ave. Commuter Rail Station Engineer s Estimate $15.0M $20.0M $4.2M $9.0M $3.0M $8.0M $37.0M $18.2M 20
21 Transforming Capital Delivery 2. Shorten construction procurement process Test Projects (Confirmed) Projects to be advertised between now and 2016 YE Project Name On-Call Power Replacement Elevators, Alewife Shawsheen River Bridge, Wilmington, MA Orange Line Test Track at Wellington Yard Gloucester Drawbridge Engineer s Estimate $15.0M $5.4M $2.0M $10.0M $48.0M 21
22 Transforming Capital Delivery 3. Track all projects through interim portfolio monthly reporting Expand monthly reporting to include other key project /program delivery metrics: o o o FY17 quarterly forecast spending Estimate at completion Major schedule milestones Finalize the conversion of tracking and reporting approach from fundsbased to project-based Plan, budget and implement an integrated Project Management Information System (PMIS) 22
23 Transforming Capital Delivery 4. Transformation Accelerator Programs In advance of organizational change, focus on top 2-3 programs now Programs will: o o o o o Be outcomes-based Led by cross functional teams Set a baseline scope, budget, schedule, and cashflow Provide regular reports to allow timely decision making Develop and maintain risk management programs Transformational Accelerator Programs: o o o Red / Orange Line Infrastructure and Vehicles (representing 13% of Five Year CIP) Positive Train Control (representing 7% of Five Year CIP) Third program to be selected 23
24 Transforming Capital Delivery PTC: Example Transformation Accelerator Program Integrated Leadership and Structure Steering Committee MassDOT, MBTA, Keolis & Jacobs General Manager Brian Shortsleeve Program Manager Brad Kesler Deputy Program Manager Brent Lesjak (Jacobs) Other Resources Funding / Finance Mike Abramo, Paul Brandley Legal Support Sue Cobb, Marie Breen Procurement Jerry Polcari, Beth Tetreault Government Relations Scott Bosworth Media Relations Joe Pesaturo Environmental Services Andrew Brennan Operations Interface Ryan Coholan Delphine Picard (Keolis) Public Outreach Rose Yates Joe Nolan (CPP) Project Management & Controls Maribel Kelly Mike Hurley (Jacobs) Design Oversight & Approvals Dave Diaz (LTK) John Mitchell (Keolis) System Integration John Mitchell (Keolis) Dan Shay (Jacobs) 24
25 Questions Questions? 25
26 BACK UP 26
27 FY 2017 Target Spend vs. FY 2017 Actual Spend Pay Go Capital FY 2017 Actual Spending also reflects need to accelerate PROJECTS/PROGRAMS FY17 Target FY17 Spending SUBWAY/ BUS 1. Beacon Junction (Green Line): Replace signal cables, flood mitigation, improved track function 2. Red, Orange, Green Line Signals System Design: Prepare signals for delivery of new vehicles 3. Bus scheduling improvement: Software that dynamic route and operator scheduling, enabling more flexible service planning effort 4. AFC 2.0 Design and consumer website: System design and performance specifications for next generation AFC; mobile platform 5. Short Term Power Investments: Sub-station replacements; 3 rd rail power supply, tunnel lighting, and emergency electrical duct bank 6. Station improvements: Leveraging schedule shut-downs to make critical station improvements 7. Unimog: Replace existing Unimog vehicle (purchased 1987) used for work on road and right of way; lower maintenance costs $2.2M $10.0M $4.7M $8.2M $10.0M $0.1M $1.2M $0.4M $0.0M $0.1M $0.3M $0.0M $0.0M $0.0M 8. Asset Management Systems $0.5M $0.0M 9. Green Line Rail Grinding $4.5M $0.0M 10. TransitMaster Server Upgrade $0.5M $0.0M COMMUTER RAIL 11. Worcester Line De-stressing: Improve existing track conditions and significantly reduce heat-related speed restrictions $3.2M $1.8M 12. Locos restoration to increase fleet size: Initial rebuild of 5 locos $3.6M $0.0M 13. Lynn Garage: Repairs to garage leased space to local community college for improved safety and state of good repair needs $6.1M $0.0M Total Budgeted Pay-Go Projects (1-13) $54.8M $2.5M 27
FMCB overview Work plan. Draft for Discussion & Policy Purposes Only 1
FMCB overview Work plan 1 FMCB deliverables The legislation creating the FMCB lays out 13 distinct areas on which the FMCB is to report on monthly and annually: 1. capital planning 2. separation of capital
More informationGM Remarks FMCB. February 13, Draft for Discussion & Policy Purposes Only
GM Remarks FMCB February 13, 2017 Overview Hingham Ferry Terminal Opening Patriots Parade Winter Storm Preparation and Execution Capital Spending Trend January Update FY18 Budget: Flexible Contracting
More informationFY2020 Budget Outlook
Finance and Capital Committee Information Item IV-A October 11, 2018 FY2020 Budget Outlook 35 of 60 Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD
More informationKeeping Metro Safe, Reliable and Affordable
Finance Committee Information Item III-B September 14, 2017 Keeping Metro Safe, Reliable and Affordable Washington Metropolitan Area Transit Authority Keeping Metro Safe, Reliable and Affordable 1 Purpose
More informationFY18 Budget Presentation
FY18 Budget Presentation Fiscal and Management Control Board April 13, 2017 Overview 1. FMCB and MBTA management continues to work diligently to close the operating budget deficit 2. Every operating dollar
More informationOperating Budget Stability Q1 FY17 Financial Update
Operating Budget Stability Q1 FY17 Financial Update Report to Fiscal and Management Control Board Without action, operating deficit was on track to reach $427M by FY20 STATUS QUO FY17 PRO FORMA 8.1.2015
More informationGeneral Manager Remarks FMCB 10/6/2016
General Manager Remarks FMCB 10/6/2016 Christopher T. Flynn 2 Education and performance awards MBA from the University of Massachusetts Bachelors of Arts in Economics from Merrimack College ACEC QBS AWARD
More informationCaltrain Rail Operations, Maintenance and Support Services Procurement Process. Current agreement expired June 30, 2011
Caltrain Rail Operations, Maintenance and Support Services Procurement Process Board of Directors September 1, 2011 Background Current agreement expired June 30, 2011 Service provided for 10 years under
More informationCapital & Strategic Planning Committee. Item III - A. January 25, FY2019 Capital Budget Work Session
Capital & Strategic Planning Committee Item III - A January 25, 2018 FY2019 Capital Budget Work Session Page 4 of 29 Washington Metropolitan Area Transit Authority Board Action/Information Summary Action
More informationPerformance Management Accountability Meeting Data as of October, 2012
Performance Management Accountability Meeting Data as of October, 2012 Richard A. Davey, Secretary & CEO Office of Performance Management and Innovation Celia J. Blue, Assistant Secretary November 27,
More informationFY18 Budget Update and Options Recap
FY18 Budget Update and Options Recap Fiscal and Management Control Board April 10, 2017 Overview 1. FMCB and MBTA management continues to work diligently to close the operating budget deficit 2. Every
More informationWashington Metropolitan Area Transit Authority Board Action/Information Summary
Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD Number: 201958 Resolution: Yes No TITLE: Second Quarter Capital Program Update PRESENTATION SUMMARY:
More informationTRACKER. Mid-Year Update Fiscal Year 2017
TRACKER Mid-Year Update Fiscal Year 2017 Stephanie Pollack Secretary and CEO Prepared by the Office of Performance Management and Innovation February 2017 MassDOT FY17 Tracker: Mid-Year Update 2 Mid-Year
More informationWASHINGTON METROPOLITAN AREA TRANSIT AUTHORITY TRANSPORTATION IMPROVEMENT PROGRAM CAPITAL COSTS (in $1,000)
TIP ID: 5853 Agency ID: Title: Rail Cars - Replacement, Rehabilitation, Expansion, & Enhancements Local 0/0/100 11,629 e 5,380 e 5,600 e 10,980 PRIIA 50/0/50 265,887 e 154,860 e 246,189 e 158,438 e 141,875
More informationFY2014 Capital and Operating Budget Discussion
Finance & Administration Committee Information Item III-B December 6, 2012 FY2014 Capital and Operating Budget Discussion Page 18 of 44 Washington Metropolitan Area Transit Authority Board Action/Information
More informationFor Action. TTC 15-Year Capital Investment Plan & Capital Budget & Plan. Summary
For Action TTC 15-Year Capital Investment Plan & 2019 2028 Capital Budget & Plan Date: January 24, 2019 To: TTC Board From: Chief Financial Officer Summary The purpose of this report is to 1. Submit for
More informationOperating Budget Report
Operating Budget Report MTD Operating Budget ($ in Millions) Oct-FY2012 Oct-FY2013 Variance FY13 Actual Actual Budget $ Percent $140M Operating Expenditures ($ in Millions) Revenue $ 67 $ 70 $ 79 $ (8)
More informationAnalysis of Transit 20 Year Capital Forecasts: FTA TERM Model vs. Transit Estimates
Analysis of Transit 20 Year Capital Forecasts: FTA TERM Model vs. Transit Estimates Dr. Allan M. Zarembski PE, FASME, Hon. Mbr. AREMA Research Professor and Director of the Railroad Engineering and Safety
More informationFY2018 Third Quarter Financial Update
Finance and Committee Information Item IV-A May 10, 2018 Third Quarter Financial Update Page 30 of 53 Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information
More informationGM/CEO s Proposed FY2020 Budget
Finance and Capital Committee Information Item IV-A November 1, 2018 GM/CEO s Proposed FY2020 Budget Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD
More informationOperating Budget Report
Operating Budget Report MTD Operating Budget ($ in Millions) Sept-FY2012 Sept-FY2013 Variance FY13 Actual Actual Budget $ Percent $140M Operating Expenditures ($ in Millions) Revenue $ 67 $ 68 $ 71 $ (3)
More informationMetro Orange Line Extension
Metro Orange Line Extension quarterly project status report 10-1265cmc 2010 lacmta Santa Susana Wash STRATHERN SATICOY SHERMAN VANOWEN ERWIN TOPANGA CYN BL TOPANGA CYN BL 27 ROSCOE BL Roscoe ROSCOE BL
More informationProject Connect. August 10, 2011
Project Connect August 10, 2011 Introduction Meeting Minutes Approval Project Status Report IV&V Update By Ernst & Young Other Business Public Comments Review of Actions from Meeting Schedule Next Meeting
More informationAudit of the Accelerated Infrastructure Program 2 Governance Phase 1 and 2
Final Report Audit of the Accelerated Infrastructure Program 2 Governance Phase 1 and 2 October 11, 2016 Office of Audit and Evaluation Table of contents Executive summary... i Introduction... 1 Focus
More informationMetro s Path Forward. A comprehensive approach toward reform. July 26, 2017
Metro s Path Forward A comprehensive approach toward reform July 26, 2017 Metro Reform: Executive Summary Metro is not living up to the promise of public transit: to be a safe, affordable and reliable
More informationMassDOT Highway ACEC State Markets Conference April 5, Jonathan Gulliver, Highway Administrator John J. Bechard, P.E., Deputy Chief Engineer
MassDOT Highway ACEC State Markets Conference April 5, 2018 Jonathan Gulliver, Highway Administrator John J. Bechard, P.E., Deputy Chief Engineer About MassDOT Highway 9,561 Lane Miles of Interstate, Numbered
More informationFFY Transportation Improvement Program (TIP) Transit Project List (FFY2017)
The file you have accessed is entitled FFY 2017-2021 Transportation Improvement Program (TIP) Transit Project List. Contained in the file are the Federal Transit Administration program number, Massachusetts
More informationAnnual Performance Report Proposal MassDOT SFY Prepared by OPM&I November, 2015
Annual Performance Report Proposal MassDOT SF 2015 Prepared by OPM&I ovember, 2015 Legislative Mandate Acts of 2009 Established the Office of Performance Management & Innovation Charged with working with
More informationCITY OF LIVINGSTON ORGANIZATIONAL STRATEGIC PLAN MARCH 2019
CITY OF LIVINGSTON ORGANIZATIONAL STRATEGIC PLAN 2019-05 MARCH 2019 What is an Organizational Strategic Plan? Strategic planning is an organizational management activity that is used to set priorities,
More informationMBTA Advisory Board FY19 Massachusetts Bay Transportation Authority Operating Budget Oversight Report
MBTA Advisory Board FY19 Massachusetts Bay Transportation Authority Operating Budget Oversight Report REPORT Offered by the Finance Committee March 29, 2018 FINANCE COMMITTEE MEMBERS John Buckley, Sr.
More informationBOSTON REGION METROPOLITAN PLANNING ORGANIZATION
NMETROPOLITAN PLANNING ORGANIZATIO BOSTON REGION MPO BOSTON REGION METROPOLITAN PLANNING ORGANIZATION Stephanie Pollack, MassDOT Secretary and CEO and MPO Chair Karl H. Quackenbush, Executive Director,
More informationBOSTON REGION METROPOLITAN PLANNING ORGANIZATION
PLANNING ORGANIZATIO BOSTON REGION MPO NMETROPOLITAN BOSTON REGION METROPOLITAN PLANNING ORGANIZATION Stephanie Pollack, MassDOT Secretary and CEO and MPO Chair Karl H. Quackenbush, Executive Director,
More informationFinancial Report Fiscal Year 2018
Financial Report Fiscal Year 2018 Year to Date September 30, 2018 1 Major Highlights Revenue Sales tax remittances received in FY2018 are 6.5% higher than FY2017 Additional $20 million in operating grants
More informationOperating Budget Stability
Operating Budget Stability March Financial Update Report to Agenda Executive Summary March Performance Against FY16 Budget March Performance Against Same Period Last Year Appendix Financial Detail: March
More information5307 RTD Cape Ann Transportation Authority 117A00 PREVENTIVE MAINTENANCE $350,000 $0 $0 $87,500 $437,500
Transit Project List (FY2017) 5310 RTD0004368 Cape Ann Transportation Authority 117A00 PREVENTIVE MAINTENANCE $350,000 $0 $0 $87,500 $437,500 RTD0004875 MetroWest Regional Transit Authority 117C00 NON
More informationFY2017 Year-End Financial Update
Finance Committee Information Item III-A September 14, 2017 FY2017 Year-End Financial Update Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD Number:
More informationProposed Capital Plan Amendment. July 2013 MTA Board Briefing
Proposed 2010-2014 Capital Plan Amendment July 2013 MTA Board Briefing Briefing Agenda Purpose of 2010-2014 Capital Plan Amendment Amendment overview Amendment highlights Efficiency initiatives Mitigation
More informationReview of FasTracks Status and Future Strategic Direction
Review of FasTracks Status and Future Strategic Direction Regional Transportation District August 21, 2008 1 Overview RTD has experienced a dramatic increase in ridership over the past year, showing that
More informationMTACC CPOC ESA Overview and Budget/Schedule Risk Assessment
MTACC CPOC ESA Overview and Budget/Schedule Risk Assessment May 21, 2012 MTA Capital Construction 0 ESA - Budget & Schedule Ranges $Billions 9 8 7 6 7.22 MTA 2009 FTA MTA - 2012 2009 7.32 8.01 7.86 7.81
More informationMetropolitan Transportation Authority Proposed Capital Program
Metropolitan Transportation Authority Proposed 2008-2013 Capital Program Thomas P. DiNapoli New York State Comptroller Kenneth B. Bleiwas Deputy Comptroller Report 11-2008 March 2008 The proposed capital
More informationProject Connect Connect January 11, 2012
Project Connect January 11, 2012 Introduction Meeting Minutes Approval Project Status Report IV&V Update By Ernst & Young Other Business Public Comments Review of Actions from Meeting Scheduling of Next
More informationUniversity Link LRT Extension
(November 2007) The Central Puget Sound Regional Transit Authority, commonly known as Sound Transit, is proposing to implement an extension of the Central Link light rail transit (LRT) Initial Segment
More informationApproval of Proposed FY 2019 Annual Budget and 20-Year Financial Plan
Approval of Proposed FY 2019 Annual Budget and 20-Year Financial Plan Committee of the Whole September 18, 2018 Joseph G. Costello Senior Vice President, Finance 0 Board Calendar Date Subject July 10 Draft
More informationFlexible Contracting and Productivity Improvements: 10 Year Projected Savings. February 2017
Flexible Contracting and Productivity Improvements: 10 Year Projected Savings February 2017 Savings Due to Pacheco Waiver and Negotiated Productivity Gains Projected to Save MBTA $400 Million Over 10 Years
More informationQuarterly Capital Progress Update
Finance & Administration Committee Information Item IV-A September 13, 2012 Quarterly Capital Progress Update Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information
More informationMunicipal Transportation Agency FY Capital Improvement Program Balboa Park. Balboa Park Citizen s Advisory Committee April 22, 2014
Municipal Transportation Agency FY 2015 2019 Capital Improvement Program Balboa Park Balboa Park Citizen s Advisory Committee April 22, 2014 Presentation Outline Overview of the MTA s 5-Year CIP Proposal
More informationToronto Transit Commission
OPERATING PROGRAM SUMMARY Contents Overview I: 2015 2017 Service Overview and Plan 7 II: 2015 Budget by Service 12 III: Issues for Discussion 36 Toronto Transit Commission 2015 OPERATING BUDGET OVERVIEW
More informationTHE CORPORATION OF THE CITY OF WINDSOR POLICY
THE CORPORATION OF THE CITY OF WINDSOR POLICY Service Area: Office of the Chief Administrative Officer Policy No.: CR252/2014 Department: Approval Date: October 6, 2014 Division: Corporate Initiatives
More informationCapital Improvement Program Update
Finance & Administration Committee Information Item III-A May 12, 2011 Capital Improvement Program Update Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information
More informationSEPTA s State of Good Repair Funding Crisis
SEPTA s State of Good Repair Funding Crisis Jeffrey D. Knueppel, PE Deputy General Manager Laura J. Zale Senior Asset Management Analyst State of Good Repair Summit. March 27, 2013 The Southeastern Pennsylvania
More informationFY2018 Second Quarter Financial Update
Finance and Committee Information Item III-A February 8, 2018 Second Quarter Financial Update 4 of 52 Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information
More informationFinancial Management Report... 3
November 13, 2013 Table of Contents Financial Management Report... 3 OPERATING FUNDS STATEMENT OF REVENUES & EXPENSES... 3 METROPOLITAN COUNCIL INVESTMENT PERFORMANCE SHORT-TERM PORTFOLIO... 4 METROPOLITAN
More informationF = MA : CSG SLC WEBINAR DECEMBER 16, J. Douglas Koelemay, Director
F = MA : CSG SLC WEBINAR DECEMBER 16, 2014 J. Douglas Koelemay, Director VIRGINIA LEADERSHIP IN PUBLIC-PRIVATE PARTNERSHIPS PPTA enabling legislation adopted 1995; PPEA followed PPTA implementation guidelines
More informationBoard Chair Ron Daily and Members Omnitrans Board of Directors FISCAL YEAR ANNUAL BUDGET EXECUTIVE SUMMARY
DATE: May 2, 2018 ITEM # F4 TO: Board Chair Ron Daily and Members Omnitrans Board of Directors THROUGH: P. Scott Graham, CEO/General Manager FROM: SUBJECT: Maurice Mansion, Treasury Manager FISCAL YEAR
More informationFY17 Budget Discussion
FY17 Budget Discussion Metro is Everywhere Metro is a lot more than buses and trains. Anyone who has boarded a bus or a train, driven on the freeway, used the toll roads, stopped at a traffic signal, or
More informationCapital Program Committee Personnel Cost Discussion April 4, 2017
Capital Program Committee Personnel Cost Discussion April 4, 2017 Personnel Cost Allocation Current DOT Legislative Requirements Required transfer of salaries from capital back to operating budget M.G.L.
More informationOperating Budget Overview 2019
OPERATING BUDGET Operating Overview 2019 Introduction In planning for a vibrant, healthy and sustainable community, the Town of Halton Hills is committed to providing community leadership on issues of
More informationQuarterly Financial Performance Report Q2 2017
Quarterly Financial Performance Report Q2 2017 Connecting Communities / Ride the Wave T (206) 398-5000 TTY Relay 711 401 S Jackson Street Seattle, WA 98104 soundtransit.org main@soundtransit.org Page 1
More informationFinancial Report Fiscal Year 2018
Financial Report Fiscal Year 2018 Year to Date July 31, 2018 Presented on September 17, 2018 1 Major Highlights Revenue FY2018 sales tax revenue budgeted at 2.5% growth over FY2017 Sales tax remittances
More informationJul Aug Sept Oct Nov Dec Jan Feb Mar Apr May Jun
REVENUE AND RIDERSHIP 4th Quarter FY2014 REVENUE (in Millions) $90M $85M $80M $75M $70M $65M $60M $55M $50M 79 77 74 74 72 70 FY2013 Actual FY2014 Budget FY2014 Actual 79 85 78 78 77 67 66 70 59 67 65
More informationChairman Skinner and the VRE Operations Board. Authorization to Issue a Request for Proposals for Federal Legislative Services
Agenda Item 8-A Consent Item To: From: Chairman Skinner and the VRE Operations Board Doug Allen Date: February 19, 2016 Re: Authorization to Issue a Request for Proposals for Federal Legislative Services
More informationMETRO. Fiscal Year Monthly Performance Report. Revenue Expense Ridership Performance. November 2018 (Third Quarter Fiscal Year-to Date)
METRO Fiscal Year 2019 Monthly Performance Report Revenue Expense Ridership Performance (Third Quarter Fiscal Year-to Date) 12/12/2018 Table of Contents Section A Section B Section C Section D Section
More informationState of Good Repair Review
Finance & Administration Committee Action Item IV-D October 9, 2014 State of Good Repair Review Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD Number:
More informationRAC Capital Presentatition May 5, 2010
RAC Capital Presentation ti May 5, 2010 Flexible Six-Year Agreement Flexible Six-Year Agreement minimum funding commitment to match Federal funds, and to annually assess availability of additional funds
More informationEngineering & Project Management Division
Division Summary Michael Schipper, Deputy General Manager The Engineering and Project Management Division is responsible for RTA s planning, real estate, and capital project design and construction administrative
More informationCalACT Expo Transit Asset Management (TAM) Plan Workshop 49 CFR 625 April 24, 2017
CalACT Expo Transit Asset Management (TAM) Plan Workshop 49 CFR 625 April 24, 2017 Poll Question 2 Today s Presentation Transit Asset Management Context and Background Final Rule Provisions Reduced burden
More informationImplementation Project Development and Review 255
Introduction 248 Implementation Principles 249 Public Agency Fiduciary Responsibilities 250 Project Development and Review Process 252 Project Development and Review 255 Maintenance 23 Implementation Implementation
More informationMay 31, 2016 Financial Report
2016 May 31, 2016 Financial Report Capital Metropolitan Transportation Authority 7/13/2016 Table of Contents SUMMARY REPORTS Budgetary Performance - Revenue 2 - Sales Tax Revenue 6 - Operating Expenses
More informationLetter of Direction Interim Report
2016-17 Letter of Direction Interim Report June 30, 2016 Table of Contents 1 Introduction... 3 1.1 Letter of Direction (LOD)... 3 1.2 Letter of Direction (LOD) Report Back... 4 2 Communications Protocols...
More informationReport by Finance and Administration Committee (B) Washington Metropolitan Area Transit Authority Board Action/Information Summary
Report by Finance and Administration Committee (B) 01-28-2016 Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD Number: 201701 Resolution: Yes No TITLE:
More informationFinance & Administration Committee Information Item IV-A October 9, 2014 Momentum Update
Finance & Administration Committee Information Item IV-A October 9, 2014 Momentum Update Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD Number:
More informationContracts Administration Management Action Plan Status June 20, 2013
Related to Agenda Item W1 Contracts Administration Management Action Plan Status June 20, 2013 Background In January 2012, the Board authorized an on-call management and consulting services contract with
More informationTESTIMONY OF RICHARD SARLES
TESTIMONY OF RICHARD SARLES Before the Council of the District of Columbia Committee on Economic Development on WMATA s FY2015 Budget Wednesday, April 30, 2014 Good Morning, Chairperson Bowser and other
More informationCITY OF LIVINGSTON ORGANIZATIONAL STRATEGIC PLAN APPROVED 05 MARCH 2019
CITY OF LIVINGSTON ORGANIZATIONAL STRATEGIC PLAN 2019- APPROVED 05 MARCH 2019 What is an Organizational Strategic Plan? Strategic planning is an organizational management activity that is used to set priorities,
More informationTSCC Budget Review TriMet
TSCC Budget Review 2017-18 TriMet 1. Introduction to the District: The Tri-County Metropolitan Transportation District (TriMet) boundary covers about 575 square miles of the urban portions of Multnomah,
More informationAMTRAK PURSUING PRIVATE INVESTMENT TO SUPPORT NORTHEAST CORRIDOR HIGH-SPEED RAIL PLANS
FOR IMMEDIATE RELEASE May 19, 2011 ATK-11-076a Contact: Media Relations 202 906.3860 AMTRAK PURSUING PRIVATE INVESTMENT TO SUPPORT NORTHEAST CORRIDOR HIGH-SPEED RAIL PLANS WASHINGTON Amtrak is developing
More informationProposed Capital Improvement Plan (CIP)
2017-2021 Proposed Capital Improvement Plan (CIP) Office of Management & Budget and Engineering & Project Management August 2, 2016 2017-2021 CIP Calendar o CIP Development Kickoff o CPWG Prioritized Requests
More informationQuarterly Financial Performance Report Q1 2017
Quarterly Financial Performance Report Q1 2017 Connecting Communities / Ride the Wave T (206) 398-5000 TTY Relay 711 401 S Jackson Street Seattle, WA 98104 soundtransit.org main@soundtransit.org Page 1
More informationManagement Committee Meeting date: March 8, 2017 For the Metropolitan Council meeting of March 22, 2017
Business Item No. 2017-42 JT Management Committee Meeting date: March 8, 2017 For the Metropolitan Council meeting of March 22, 2017 Subject: 2017 Unified Budget Amendment Carryforward Amendment District(s),
More informationGovernor s FY 2019 Revised, FY 2020 and Capital Budget Recommendations House Finance Committee April 9, 2019
Governor s FY 2019 Revised, FY 2020 and Capital Budget Recommendations House Finance Committee April 9, 2019 Quasi-public agency Established in 1964 Responsible: Fixed route bus service and Americans with
More informationCRISIS MANAGEMENT AND RECOVERY SOLUTIONS. Delivering results, implementing change.
CRISIS MANAGEMENT AND RECOVERY SOLUTIONS Delivering results, implementing change. CRISIS MANAGEMENT AND RECOVERY SOLUTIONS The threats of natural disasters and other extreme events are significant and
More informationBenefits of Long-Range Capital Planning
Benefits of Long-Range Capital Planning Presentation at the Transportation Research Board 9 th National Conference on Transportation Asset Management Stephen A. Berrang Director, Capital Program Management
More informationAugust 31, 2016 Financial Report
August 31, 2016 Financial Report Capital Metropolitan Transportation Authority 10/14/2016 Table of Contents SUMMARY REPORTS Budgetary Performance - Revenue 2 - Sales Tax Revenue 6 - Operating Expenses
More informationSFMTA 2013 Revenue Bond Board of Directors
SFMTA Municipal Transportation Agency Image: Market and Geary Streets, circa 1920s, Muni Centennial logo SFMTA 2013 Revenue Bond Board of Directors 09 03 2013 SAN FRANCISCO, CALIFORNIA Background In 2007,
More informationFinancial Update for the Period Ended April 7, 2018
For Information Financial Update for the Period Ended April 7, 2018 Date: June 12, 2018 To: TTC Board From: Chief Financial Officer Summary The purpose of this report is to provide the Board with the operating
More informationSAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY
THIS PRINT COVERS CALENDAR ITEM NO. : 12 SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY DIVISION: Finance and Information Technology BRIEF DESCRIPTION: Adopting the SFMTA s Fiscal Year (FY) 2019 2023 Capital
More informationPolicy, Planning, Finance & Administration
OPERATING BUDGET NOTES CONTENTS Overview 1. 2018-2020 Service Overview and Plan 5 2. 2018 Preliminary Operating Budget by Service 12 3. Issues for Discussion N/A Appendices 1. 2017 Service Performance
More informationFY19 Budget - Discussion. April 2018
FY19 Budget - Discussion April 2018 FY19 Proposed Budget: $6.6 Billion General Planning & Programs 3% Identify regional mobility needs and solutions Debt Service 6% Obligations from current and past projects
More informationProp K Grouped Allocation Requests November 2018 Board Action. Table of Contents
Item 7 Enclosure Citizens Advisory Committee October 24, 2018 Prop K Grouped Allocation Requests November 2018 Board Action Table of Contents No. Fund Source Project Sponsor 1 1 Prop K PCJPB Expenditure
More informationMETRO. Fiscal Year Monthly Performance Report. Revenue Expense Ridership Performance. February 2018 (First Quarter Fiscal Year-to Date)
METRO Fiscal Year 2018 Monthly Performance Report Revenue Expense Ridership Performance (First Quarter Fiscal Year-to Date) 3/12/2018 Table of Contents Section A Section B Section C Section D Section E
More informationMemorandum. Date: RE: Citizens Advisory Committee
Memorandum Date: 03.04.2010 RE: Citizens Advisory Committee March 10, 2010 To: From: Subject: Summary Citizens Advisory Committee Maria Lombardo Chief Deputy Director for Policy and Programming Lee Saage
More informationExecutive Change Control Board. January 15, 2016
Executive Change Control Board January 15, 2016 1 Today s Topics Review In Kind Land Transfer (Action) Review Project Schedule Review Project Cost Estimate at 60% Design Review Project Scope (Action) Next
More informationToronto Transit Commission
OPERATING ANALYST NOTES Contents Overview & Recommendations I: 2015 2017 Service Overview and Plan 6 II: 2015 Recommended Budget by Service 11 III: Issues for Discussion 35 Toronto Transit Commission 2015
More informationSection I Year-to-date revenues collected and projected revenues and expenditures for the current fiscal year
Report to Secretary of Administration and Finance and House and Senate Committees on Ways and Means regarding Revenue Projections and Changes to Fare and Fee Structure of the Massachusetts Bay Transportation
More informationMetropolitan Council. Big Picture 2016 Unified Budget
Metropolitan Council Big Picture 2016 Unified Budget Council Meeting June 24, 2014 Timeline for Budget Development Jun 24 Jul-Aug Aug 12 Aug 12 Aug 26 Oct Dec 9 Council - Big-Picture Operating & Capital
More informationMetrolinx-City of Toronto-Toronto Transit Commission Master Agreement for Light Rail Transit Projects
STAFF REPORT ACTION REQUIRED Metrolinx-City of Toronto-Toronto Transit Commission Master Agreement for Light Rail Transit Projects Date: October 23, 2012 To: From: Wards: City Council City Manager All
More informationPreliminary Fiscal Year 2016 Budget Update. Standing Committee on Finance & Audit
Preliminary Fiscal Year 2016 Update Standing Committee on Finance & Audit February 5, 2015 Leading the Nation in Transportation Excellence Massachusetts Bay Transportation Authority Ten Park Plaza, Suite
More informationM E M O R A N D U M EUGENE WATER & ELECTRIC BOARD
M E M O R A N D U M EUGENE WATER & ELECTRIC BOARD TO: Commissioners Helgeson, Brown, Mital, Simpson and Carlson FROM: Frank Lawson, General Manager DATE: October 27, 2017 SUBJECT:, 2017 Operating Dashboard
More informationSummary of Committee Discussion/Questions Pat Jones, Tom McGannon and Mark Leemon presented and responded to questions.
Committee Report Business Item No. 2017-46 Transportation Committee For the Metropolitan Council meeting of February 22, 2017 Subject: Railworks Track Systems, Inc. Construction Contract 16P310 Proposed
More informationMetropolitan Transportation Authority: East Side Access Cost Overruns
Metropolitan Transportation Authority: East Side Access Cost Overruns Thomas P. DiNapoli New York State Comptroller Kenneth B. Bleiwas Deputy Comptroller Report 12-2013 March 2013 Highlights East Side
More information