4 Cost Estimation Assumptions

Size: px
Start display at page:

Download "4 Cost Estimation Assumptions"

Transcription

1 4 Cost Estimation Assumptions The Proposed Action would include the relocation of the existing commuter rail lines; construction of approximately four miles of new light rail track and systems; relocation of Lechmere Station; construction of six new stations, four new multi-span viaducts, and a storage and maintenance facility; installation of power, signals and communications systems; reconstruction of 11 brid ge structures; and acquisition of 24 new Green Line vehicles. Preliminary costs have been estimated for the major items based on the conceptual design completed to date. Minor items are accounted for in the contingency. Developing the preliminary cost estimates for the Green Line Extension project has been an iterative process. Prior to developing this New Starts Submittal package, preliminary cost estimates were submitted to the Federal Transit Administration (FTA)/ Project Management Oversight Consultant (PMOC) several times for review, while incorporating previously received comments. The materials provided in this submittal are the most up-to-date, and they address the FTA/ PMOC s latest comments received on August 1, 2011 in the draft results of the FTA/ PMOC Risk Assessment Workshop held in March Since September 2010, approximately $36 million in base costs were added in response to evolving project requirements and design development. Following the FTA/ PMOC s Risk Assessment Workshop held in March 2011 and project-level risk workshop in May 2011, the capital cost estimate increased further, adding an additional $72 million in costs not previously identified such as increasing the professional services allocation from 26% to 30%, extending the limits of the reconstruction of the Lechmere Viaduct to Land Boulevard, increasing the size of each of the stations and ad ding two buildings to the vehicle maintenance facility. These increases to the project base cost were, in part, offset by a 1% reduction in the overall project contingency and a reduction in the land acquisition costs. Also following these risk workshops, a new project schedule was established that provides a range of probable schedule outcomes (i.e. 10%, 50%, and 90% probability dates of not exceeding those dates). The capital cost estimate provided in this submittal uses the number identified as the 50 percent probability number in line with the 50 percent probability of not exceeding the revenue service start date of June Cost Estimation Assumptions /23/2011

2 2019. This is also consistent with the comments made in the PMOC s Risk Assessment report for the project. The upd ated capital cost estimate also utilizes the latest FTA s SCC Workbook obtained from the FTA s website in August It is anticipated that further refinements will continue to be made as the FTA/ PMOC coordination efforts continue throughout the New Starts application review process, and all upd ates will be documented accordingly. This chapter provides a summary of the general assumptions used to develop capital cost and operating and maintenance (O&M) cost estimates for the Proposed Action and, for comparison purposes, the Baseline Alternative. 4.1 Capital Cost The conceptual capital cost estimate includes all construction costs associated with the implementation of the project, including land acquisition and professional services. The professional services segment of the Green Line Extension project including elements such as project management, engineering, construction administration, insurance, inspections, fees/ permits, and start-up costs (covering project initiation work such as training, site access, and protection work performed by agency staff and outside contractors) are represented as a percentage of the construction cost. The cost estimate provided in this chapter was developed by calculating quantities for all proposed work and applying weighted average bid prices in 2010 published by MassDOT. The unit prices were refined based on estimates for other local transit projects in the Boston area, supplemental pricing research with the Massachusetts Bay Transportation Au thority (MBTA), coordination with contractors, and RS Means (an industry organization that publishes construction cost data). The 2010 base year costs for each line item were then escalated 3.5% to obtain 2011 base year dollars Contingency A 10 percent unallocated contingency was applied to the total base year dollars for Cost Categories to account for complexities in construction phasing for structures and off-site improvements that are not fully defined given the current level of design. The allocated contingency percentages were applied to each FTA cost category in accord ance with Table 4-1. Cost Estimation Assumptions /23/2011

3 Table 4-1 Capital Cost Contingency Percentage Allocation FTA Category No. Description 10 Guideway and Track Elements Allocated Contingency Percentage Guideway Elements At Grade or Above Grade Guideway Elements Aerial Structure 25 Track Elements 25 Stations, Stops, Terminals, Intermodal Lechmere Station 25 Other Stations Support Facilities: Yards, Shops, Admin Buildings Light Maintenance Facility 23 Yard and Yard Track Site Work & Special Conditions Demolition, Clearing, Earthwork 24 Haz. Materials, Cont. Soil Removal, Groundwater Treatments 24 Site Structures - Retaining Walls or Sound Walls 25 Pedestrian/ Bike Access 24 Temporary Facilities Systems Right-of-Way, Land, Existing Improvements Vehicles 5 The estimate includes a total contingency of $218.3 million, which is 29 percent (32 percent excluding vehicles) of the base year dollars for all categories (10-80) without contingency Professional Services The estimate for professional services was developed following standard MBTA practices and is consistent with recent MBTA submittals to FTA. The following percentages were applied to the total construction cost (base year d ollars and allocated contingency for Cost Categories 10-50) for each FTA professional service cost category in accord ance with Table 4-2. Cost Estimation Assumptions /23/2011

4 Table 4-2 Professional Service Percentage Allocation FTA Category No and Description Engineering Project Management Construction Administration Professional Liability Insurance Legal/Permits Surveys, Testing, Inspection Start-Up 0.2 Allocated Percentage In addition, an allocated contingency of 10 percent was added to each item in the professional service category. The result is a professional service estimate that is 30 percent of the construction estimate Baseline Cost The costs for the Baseline Alternative have been estimated using similar assumptions and contingencies as those for the capital cost estimate. The Baseline Alternative includes all measures required to expand bus service to cover the service area of the Proposed Action, including a new bus maintenance facility, 19 new buses, eight new Green Line vehicles, and expansion of the existing Lechmere Bus Terminal, including land acquisition Summary Capital costs for the Proposed Action and the Baseline Alternative are itemized in the New Starts Workbook Standardized Cost Categories (SCC) for Capital Projects 1 and are included in Attachment 4A. The standard inflation rate of 3.5 percent was provided in the latest FTA SCC sheet inflation worksheet on the FTA website (2011). The capital cost estimate for the Build Alternative is $1.2 billion in 2011 dollars, which results in an annualized cost of $72.0 million and a year of expend iture total cost of $1.3 billion. The capital cost estimate for the Build Alternative also includes finance charges totaling $ million in YOE dollars. The capital cost estimate for the Baseline Alternative is $168.2 million, which results in an annualized cost of $13.3 million. 1 Federal Transit Administration Standardized Cost Categories for Capital Projects Revision 14. August 5, Cost Estimation Assumptions /23/2011

5 4.2 Operating and Maintenance Cost The O&M costs for the Green Line Extension project are based on the fully allocated O&M cost model developed specifically for the Green Line Extension and are part of this submittal. The O&M cost model methodology and results as of 2011 can be found in the MBTA Operation and Maintenance Cost Mod el Method ology and Results Report, dated December 13, 2011 (Attachment 4B). This O&M cost model was developed consistent with FTA s draft guid ance for the estimation of operating and maintenance costs that is part of FTA s Procedures and Technical Methods for Transit Project Planning. As such, the cost model is based on a resource build -up approach that fully allocates each unit cost factor to a supply (Level of Service) variable for all MBTA mod es. Unit costs are further broken d own by object class (wages, salaries, healthcare, unleaded / diesel, CNG, propulsion utilities, other utilities, and other) so as to provide the flexibility to inflate each object class at a different escalation rate if needed. Each unit cost factor is multiplied by the appropriate Level of Service (LOS) variable and the financial model. The O&M cost model is based on the most recent available expense date from the MBTA s general ledger and the most recent actual level of service. As discussed in Chapter 3, the Central Transportation Planning Staff (CTPS) developed an annualization factor of 293 based on MBTA s recent operating statistics, such as service schedules for weekdays, weekends, and holid ays within a year. For both the Proposed Action and the Baseline Alternative, the annualization factor allowed various daily operating statistics (ridership, revenue vehicle hours, and revenue vehicle miles) to be converted to their respective annual values. The O&M costs were calculated using the fully allocated cost model. MassDOT believes that the model is a conservative approach for this project since it is an extension of an existing MBTA mature system. The annual O&M cost estimates are $24.8 million for the Proposed Action and $14.7 million for the Baseline Alternative in 2011 dollars. The detailed breakdown of the cost estimates are in Attachment 4C. Cost Estimation Assumptions /23/2011

6 This Page Intentionally Left Blank Cost Estimation Assumptions /23/2011

CHAPTER 6: COST ESTIMATES

CHAPTER 6: COST ESTIMATES CHAPTER 6: COST ESTIMATES 115 116 UNION STATION GEORGETOWN: ALTERNATIVES ANALYSIS for PREMIUM TRANSIT SERVICE The Recommended Alternative could be designed and constructed under a number of financing options.

More information

10 Financial Analysis

10 Financial Analysis 10 Financial Analysis This chapter summarizes the financial analysis for the No-Build Alternative and the proposed METRO Blue Line Light Rail Transit (BLRT) Extension project. This chapter also describes

More information

8. FINANCIAL ANALYSIS

8. FINANCIAL ANALYSIS 8. FINANCIAL ANALYSIS This chapter presents the financial analysis conducted for the Locally Preferred Alternative (LPA) selected by the Metropolitan Transit Authority of Harris County (METRO) for the.

More information

Honolulu High-Capacity Transit Corridor Project Alternatives Analysis

Honolulu High-Capacity Transit Corridor Project Alternatives Analysis Alternatives Analysis Financial Feasibility Report November 30, 2006 Prepared for: City and County of Honolulu Prepared by: PB Consult Inc. Under Subcontract to: Parsons Brinckerhoff Quade & Douglas, Inc.

More information

CHAPTER 9 FINANCIAL CONSIDERATIONS

CHAPTER 9 FINANCIAL CONSIDERATIONS CHAPTER 9 FINANCIAL CONSIDERATIONS 9.1 INTRODUCTION This chapter presents anticipated costs, revenues, and funding for the Berryessa Extension Project (BEP) Alternative and the Silicon Valley Rapid Transit

More information

Capital Cost Estimation Methodology

Capital Cost Estimation Methodology West Broadway Transit Study Capital Cost Estimation Methodology 7/6/2015 Prepared by the SRF Consulting Group Team for Capital Cost Estimation Methodology Page i Introduction... 1 1. Capital Costs... 1

More information

Executive Change Control Board. January 15, 2016

Executive Change Control Board. January 15, 2016 Executive Change Control Board January 15, 2016 1 Today s Topics Review In Kind Land Transfer (Action) Review Project Schedule Review Project Cost Estimate at 60% Design Review Project Scope (Action) Next

More information

Executive Change Control Board. March 30, 2016

Executive Change Control Board. March 30, 2016 Executive Change Control Board March 30, 2016 1 Today s Topics Review Civil Cost Estimate at 90% Next Steps 2 Review Civil Cost Estimate at 90% 3 Requested City/County Scope Elements Adjusted 60% cost

More information

WESTSIDE SUBWAY EXTENSION

WESTSIDE SUBWAY EXTENSION Table of Contents Table of Contents 1.0 INTRODUCTION... 1-1 2.0 COST ESTIMATE METHODOLOGY... 2-1 2.1 Capital Cost Methodology... 2-1 2.2 Capital Cost Categories... 2-1 2.2.1 SCC 10 Guideway and Track Elements...

More information

READINESS REVIEW ENTRY INTO PROJECT DEVELOPMENT. Columbia Pike Streetcar Arlington County, Virginia FTA Region 3

READINESS REVIEW ENTRY INTO PROJECT DEVELOPMENT. Columbia Pike Streetcar Arlington County, Virginia FTA Region 3 READINESS REVIEW ENTRY INTO PROJECT DEVELOPMENT Columbia Pike Streetcar Arlington County, Virginia FTA Region 3 December 19, 2012 Final PMOC Contract Number: DTFT60-09-00016 Task Order Number: 007, Work

More information

Executive Change Control Board. August 3, 2016

Executive Change Control Board. August 3, 2016 Executive Change Control Board August 3, 2016 1 Today s Topics Approval of Meeting Minutes 90% Cost Estimate Project Schedule Project Scope and Budget Action Next Steps 2 90% Cost Estimate 3 Project Cost

More information

MEMORANDUM. Santa Clara Valley Transportation Authority Board of Directors. Michael T. Burns General Manager. DATE: August 4, 2008

MEMORANDUM. Santa Clara Valley Transportation Authority Board of Directors. Michael T. Burns General Manager. DATE: August 4, 2008 MEMORANDUM TO: FROM: Santa Clara Valley Transportation Authority Board of Directors Michael T. Burns General Manager DATE: August 4, 2008 SUBJECT: BART Operating Subsidy This memorandum summarizes and

More information

DURHAM-ORANGE LIGHT RAIL TRANSIT PROJECT FINANCIAL RISKS AND MITIGATION STRATEGIES APRIL 2017

DURHAM-ORANGE LIGHT RAIL TRANSIT PROJECT FINANCIAL RISKS AND MITIGATION STRATEGIES APRIL 2017 DURHAM-ORANGE LIGHT RAIL TRANSIT PROJECT FINANCIAL RISKS AND MITIGATION STRATEGIES APRIL 2017 There are several financial risks to the 2017 County Transit Plans (Plans) that could arise at different times

More information

Quarterly Status Report

Quarterly Status Report Capital Projects Quarterly Status Report 3rd Quarter FY2017: January 1 March 31, 2017 Prepared for the June 7, 2017 SamTrans Board Meeting San Mateo County Transit District San Mateo County Transit District

More information

This chapter describes the initial financial analysis and planning for the construction and operations of the Locally Preferred Alternative (LPA).

This chapter describes the initial financial analysis and planning for the construction and operations of the Locally Preferred Alternative (LPA). 8 FINANCIAL ANALYSIS This chapter describes the initial financial analysis and planning for the construction and operations of the Locally Preferred Alternative (LPA). The alternative formerly known as

More information

University Link LRT Extension

University Link LRT Extension (November 2007) The Central Puget Sound Regional Transit Authority, commonly known as Sound Transit, is proposing to implement an extension of the Central Link light rail transit (LRT) Initial Segment

More information

Contents. Appendix. Cost Model Structure. Tables

Contents. Appendix. Cost Model Structure. Tables Alternatives Analysis Alt ti A l i Technical Methodology Report: Operating and Cost Estimating and Results Prepared for: Washington County Regional Railroad Authority on behalf of the Gateway Corridor

More information

Tech Memo #4: Capital Costs

Tech Memo #4: Capital Costs MILWAUKEE COUNTY EAST-WEST BUS RAPID TRANSIT Tech Memo #4: Capital Costs REVISION #1 DATE June 28, 2016 Prepared for: Milwaukee County 10320 W. Watertown Plank Rd. Wauwatosa, WI 53226 Prepared by: AECOM

More information

RESOLUTION NO. R Tacoma Link Expansion Baseline Budget, Schedule, Phase Gate 5, and Project Naming

RESOLUTION NO. R Tacoma Link Expansion Baseline Budget, Schedule, Phase Gate 5, and Project Naming RESOLUTION NO. R2017-31 Tacoma Link Expansion Baseline Budget, Schedule, Phase Gate 5, and Project Naming MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Capital Committee Board PROPOSED ACTION 09/14/2017

More information

Chapter 6: Financial Resources

Chapter 6: Financial Resources Chapter 6: Financial Resources Introduction This chapter presents the project cost estimates, revenue assumptions and projected revenues for the Lake~Sumter MPO. The analysis reflects a multi-modal transportation

More information

PURPLE LINE FINANCIAL PLAN June 20, 2011 WORKING DRAFT Note: Contains preliminary information subject to future revision Version 1: June 20, 2011 Maryland Transit Administration Purple Line Financial Plan

More information

Chapter 9 Financial Considerations. 9.1 Introduction

Chapter 9 Financial Considerations. 9.1 Introduction 9.1 Introduction Chapter 9 This chapter presents anticipated costs, revenues, and funding for the NEPA BART Extension Alternative. A summary of VTA s financial plan for the BART Extension Alternative is

More information

CHAPTER 9 FINANCIAL CONSIDERATIONS

CHAPTER 9 FINANCIAL CONSIDERATIONS CHAPTER 9 FINANCIAL CONSIDERATIONS 9.1 INTRODUCTION This chapter presents anticipated costs, revenues, and funding for the BEP and the SVRTP. A summary evaluation of VTA s financial plan for the proposed

More information

Regional Connector Transit Corridor Draft Environmental Impact Statement/ Draft Environmental Impact Report APPENDIX HH FINANCIAL ANALYSIS REPORT

Regional Connector Transit Corridor Draft Environmental Impact Statement/ Draft Environmental Impact Report APPENDIX HH FINANCIAL ANALYSIS REPORT Draft Environmental Impact Statement/ Draft Environmental Impact Report APPENDIX HH FINANCIAL ANALYSIS REPORT State Clearinghouse Number: 2009031043 April 2010 Prepared for Los Angeles County Metropolitan

More information

Engineering & Project Management Division

Engineering & Project Management Division Division Summary Michael Schipper, Deputy General Manager The Engineering and Project Management Division is responsible for RTA s planning, real estate, and capital project design and construction administrative

More information

The DRAFT Bus and Rail Investment Plan in Orange County

The DRAFT Bus and Rail Investment Plan in Orange County The DRAFT Bus and Rail Investment Plan in Orange County 5/31/2012 The Bus and Rail Investment Plan in Orange County I. INTRODUCTION 3 II. TRANSIT STEPS LEADING UP TO THIS PLAN 4 III. PLAN ELEMENTS 5 A.

More information

Honolulu High-Capacity Transit Corridor Project

Honolulu High-Capacity Transit Corridor Project Draft Financial Plan August 12, 2008 Prepared for: City and County of Honolulu Prepared by: PB Consult Inc. Under Subcontract to: PB Americas, Inc. TABLE OF CONTENTS 1 CHAPTER 1 INTRODUCTION...1-1 Description

More information

Quarterly Status Report

Quarterly Status Report Capital Projects Quarterly Status Report 2nd Quarter FY2018: October 01 December 31, 2017 Prepared for the March 07, 2018 SamTrans Board Meeting San Mateo County Transit District San Mateo County Transit

More information

Quarterly Status Report

Quarterly Status Report Capital Projects Quarterly Status Report 2nd Quarter FY2017: October 1 December 31, 2016 Prepared for the March 1, 2017 SamTrans Board Meeting San Mateo County Transit District San Mateo County Transit

More information

8.0 FINANCIAL ANALYSIS

8.0 FINANCIAL ANALYSIS Chapter 8 Financial Analysis 8.0 FINANCIAL ANALYSIS This chapter presents a summary of the financial analysis for the Central Corridor Light Rail Transit (LRT) Project, a description of the Project Sponsor

More information

Corridor Management Committee. May 6, 2015

Corridor Management Committee. May 6, 2015 Corridor Management Committee May 6, 2015 1 Today s Topics Project Budget and Schedule Update Project Options Work Plan Upcoming Meeting Schedule 2 Project Budget and Schedule Update 3 Project Updates:

More information

Cases on Revenue Generated by Transit Agencies

Cases on Revenue Generated by Transit Agencies Cases on Revenue Generated by Transit Agencies This page left intentionally blank. Turnkey Procurement Community Transit Snohomish County, Washington This page left intentionally blank. Turnkey Procurement

More information

Financial Plan. Section 8 STATUS QUO PLAN STATUS QUO PLAN ASSUMPTIONS STATUS QUO PLAN BUDGET ITEMS

Financial Plan. Section 8 STATUS QUO PLAN STATUS QUO PLAN ASSUMPTIONS STATUS QUO PLAN BUDGET ITEMS Section 8 Financial Plan This final section of the TDP contains the financial information with regard to the improvements described in Section 7, Alternatives. The financial information is divided into

More information

Washington Metropolitan Area Transit Authority Board Action/Information Summary

Washington Metropolitan Area Transit Authority Board Action/Information Summary Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD Number: 201958 Resolution: Yes No TITLE: Second Quarter Capital Program Update PRESENTATION SUMMARY:

More information

BOSTON REGION METROPOLITAN PLANNING ORGANIZATION

BOSTON REGION METROPOLITAN PLANNING ORGANIZATION NMETROPOLITAN PLANNING ORGANIZATIO BOSTON REGION MPO BOSTON REGION METROPOLITAN PLANNING ORGANIZATION Stephanie Pollack, MassDOT Secretary and CEO and MPO Chair Karl H. Quackenbush, Executive Director,

More information

TEX Rail Fort Worth, Texas Project Development (Rating Assigned November 2012)

TEX Rail Fort Worth, Texas Project Development (Rating Assigned November 2012) TEX Rail Fort Worth, Texas Project Development (Rating Assigned November 2012) Summary Description Proposed Project: Commuter Rail 37.6 Miles, 14 Stations (12 new, two existing) Total Capital Cost ($YOE):

More information

Budget Discussion. July 2009 Citizens Advisory Committee

Budget Discussion. July 2009 Citizens Advisory Committee Budget Discussion July 2009 Citizens Advisory Committee Budget presentation How did TriMet arrive at the LPA budget How are estimates developed How are we tracking changes How are we doing with the budget

More information

Section I Year-to-date revenues collected and projected revenues and expenditures for the current fiscal year

Section I Year-to-date revenues collected and projected revenues and expenditures for the current fiscal year Report to Secretary of Administration and Finance and House and Senate Committees on Ways and Means regarding Revenue Projections and Changes to Fare and Fee Structure of the Massachusetts Bay Transportation

More information

BOSTON REGION METROPOLITAN PLANNING ORGANIZATION

BOSTON REGION METROPOLITAN PLANNING ORGANIZATION PLANNING ORGANIZATIO BOSTON REGION MPO NMETROPOLITAN BOSTON REGION METROPOLITAN PLANNING ORGANIZATION Stephanie Pollack, MassDOT Secretary and CEO and MPO Chair Karl H. Quackenbush, Executive Director,

More information

Rail Modernization Study REPORT TO CONGRESS. April Prepared by: Federal Transit Administration

Rail Modernization Study REPORT TO CONGRESS. April Prepared by: Federal Transit Administration REPORT TO CONGRESS April 2009 Prepared by: Federal Transit Administration U.S. Department of Transportation Federal Transit Administration 1201 New Jersey Avenue S.E. Washington DC 20590 The Honorable

More information

Instruction Manual. For the. National Park Service. Alternative Transportation Systems. Financial Proforma

Instruction Manual. For the. National Park Service. Alternative Transportation Systems. Financial Proforma Instruction Manual For the National Park Service Alternative Transportation Systems Financial Proforma 2007 This Instruction Manual provides step-by-step guidance on completing the National Park Service

More information

Forecasting Asset Conditions with Decay Curves April 16, 2012 Keith Gates, PE Senior Analyst, Strategic Planning & Analysis

Forecasting Asset Conditions with Decay Curves April 16, 2012 Keith Gates, PE Senior Analyst, Strategic Planning & Analysis Forecasting Asset Conditions with Decay Curves April 16, 2012 Keith Gates, PE Senior Analyst, Strategic Planning & Analysis 9 th National Conference on Transportation Asset Management San Diego, California

More information

APPROVE INCREASE TO L1FE-OF-PROJECT BUDGET

APPROVE INCREASE TO L1FE-OF-PROJECT BUDGET 44 One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2000 Tel metro.net CONSTRUCTION COMMITTEE JANUARY 16, 2014 PROJECT: ACTION: PATSAOURAS PLAZA BUSWAY STATION (PPBS) APPROVE INCREASE TO L1FE-OF-PROJECT

More information

Analysis of Transit 20 Year Capital Forecasts: FTA TERM Model vs. Transit Estimates

Analysis of Transit 20 Year Capital Forecasts: FTA TERM Model vs. Transit Estimates Analysis of Transit 20 Year Capital Forecasts: FTA TERM Model vs. Transit Estimates Dr. Allan M. Zarembski PE, FASME, Hon. Mbr. AREMA Research Professor and Director of the Railroad Engineering and Safety

More information

RTD Board Briefing. Eagle P3 Project Draft RFP. January 6, 2009

RTD Board Briefing. Eagle P3 Project Draft RFP. January 6, 2009 RTD Board Briefing Eagle P3 Project Draft RFP January 6, 2009 Eagle P3 Draft RFP Background Outline of Draft RFP Major Deal Points Payment Structure Page 2 Page 3 Background Eagle P3 Project Eagle P3 Project

More information

Cancelled. Final Action

Cancelled. Final Action RESOLUTION NO. R2018-16 Baseline Budget and Schedule for the Lynnwood Link Extension MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Capital Committee Board PROPOSED ACTION 05/10/2018 05/24/2018 Cancelled

More information

Board of Directors Meeting Monday March 26, :30 p.m.

Board of Directors Meeting Monday March 26, :30 p.m. Board of Directors Meeting Monday March 26, 2018 3:30 p.m. Intermodal Transportation Center (ITC) 1001 Jones Street, 2nd Floor Community Room Fort Worth, TX 76102 BOARD OF DIRECTORS MEETING AGENDA 3:30

More information

Appendix E: Revenues and Cost Estimates

Appendix E: Revenues and Cost Estimates Appendix E: Revenues and Cost Estimates Photo Source: Mission Media Regional Financial Plan 2020-2040 Each metropolitan transportation plan must include a financial plan. In this financial plan, the region

More information

FY2018 Third Quarter Financial Update

FY2018 Third Quarter Financial Update Finance and Committee Information Item IV-A May 10, 2018 Third Quarter Financial Update Page 30 of 53 Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information

More information

TRACKER. Mid-Year Update Fiscal Year 2017

TRACKER. Mid-Year Update Fiscal Year 2017 TRACKER Mid-Year Update Fiscal Year 2017 Stephanie Pollack Secretary and CEO Prepared by the Office of Performance Management and Innovation February 2017 MassDOT FY17 Tracker: Mid-Year Update 2 Mid-Year

More information

CHAPTER 7: Financial Plan

CHAPTER 7: Financial Plan CHAPTER 7: Financial Plan Report Prepared by: Contents 7 FINANCIAL PLAN... 7-1 7.1 Introduction... 7-1 7.2 Assumptions... 7-1 7.2.1 Operating Revenue Assumptions... 7-2 7.2.2 Operating Cost Assumptions...

More information

Quarterly Status Report

Quarterly Status Report Capital s Quarterly Status Report d Quarter FY2016: 1 31, 201 Prepared for the, 2016 SamTrans Board Meeting San Mateo County Transit District San Mateo County Transit District QUARTERLY CAPITAL PROGRAM

More information

Final Interim Policy Guidance Federal Transit Administration Capital Investment Grant Program

Final Interim Policy Guidance Federal Transit Administration Capital Investment Grant Program U.S. DEPARTMENT OF TRANSPORTATION FEDERAL TRANSIT ADMINISTRATION Final Interim Policy Guidance Federal Transit Administration Capital Investment Grant Program August 2015 TABLE OF CONTENTS Introduction...

More information

MTA Long Island Rail Road

MTA Long Island Rail Road MTA Long Island Rail Road Budget July Financial Plan -2008 MISSION STATEMENT The mission of the MTA Long Island Rail Road is to provide a safe, accessible, clean, cost-effective, customer-focused rail

More information

Arlington County, Virginia

Arlington County, Virginia Arlington County, Virginia METRO METRO 2015 2024 CIP Metro Funding Project Description The Washington Metropolitan Area Transit Authority (WMATA/Metro) is a unique federal-state-local partnership formed

More information

FY18 Budget Update and Options Recap

FY18 Budget Update and Options Recap FY18 Budget Update and Options Recap Fiscal and Management Control Board April 10, 2017 Overview 1. FMCB and MBTA management continues to work diligently to close the operating budget deficit 2. Every

More information

2.0 PROJECT FINANCIAL PLAN...

2.0 PROJECT FINANCIAL PLAN... Table of Contents Table of Contents 1.0 INTRODUCTION... 1-1 1.1 Purpose of Financial Plan... 1-1 1.2 Key Changes Since 2010 Financial Plan... 1-2 1.3 Project Description... 1-4 1.4 Project Sponsor: Los

More information

Operating Budget Stability Q1 FY17 Financial Update

Operating Budget Stability Q1 FY17 Financial Update Operating Budget Stability Q1 FY17 Financial Update Report to Fiscal and Management Control Board Without action, operating deficit was on track to reach $427M by FY20 STATUS QUO FY17 PRO FORMA 8.1.2015

More information

Traffic Impact Analysis Guidelines Methodology

Traffic Impact Analysis Guidelines Methodology York County Government Traffic Impact Analysis Guidelines Methodology Implementation Guide for Section 154.037 Traffic Impact Analysis of the York County Code of Ordinances 11/1/2017 TABLE OF CONTENTS

More information

Implementation Project Development and Review 255

Implementation Project Development and Review 255 Introduction 248 Implementation Principles 249 Public Agency Fiduciary Responsibilities 250 Project Development and Review Process 252 Project Development and Review 255 Maintenance 23 Implementation Implementation

More information

Dulles Corridor Metrorail Project

Dulles Corridor Metrorail Project Dulles Corridor Metrorail Project MONTHLY COST AND SCHEDULE UPDATE FOR PHASES 1 AND 2 AS OF NOVEMBER 30, 2014 JANUARY 2015 0 Phase 1 Cost Summary November Expenditures $ 1.6 Million Total Expenditures

More information

SR 520 BRIDGE. Investment Grade Traffic and Revenue Study Update. SR 520 Bridge and the Eastside plus West Approach Bridge Project

SR 520 BRIDGE. Investment Grade Traffic and Revenue Study Update. SR 520 Bridge and the Eastside plus West Approach Bridge Project SR 520 BRIDGE Investment Grade Traffic and Revenue Study Update SR 520 Bridge and the Eastside plus West Approach Bridge Project February 16, 2017 Photographs Courtesy of WSDOT Table of Contents Executive

More information

FY2017 Budget Discussion

FY2017 Budget Discussion Finance & Administration Committee Information Item IV-B November 5, 2015 FY2017 Budget Discussion Page 70 of 116 Washington Metropolitan Area Transit Authority Board Action/Information Summary Action

More information

VALLEY METRO RAIL FY18 Budget EXECUTIVE SUMMARY

VALLEY METRO RAIL FY18 Budget EXECUTIVE SUMMARY VALLEY METRO RAIL FY18 Budget EXECUTIVE SUMMARY FY18 ADOPTED ANNUAL OPERATING AND CAPITAL BUDGET Valley Metro Rail, Inc. (VMR) is a public non-profit corporation whose members are the cities of Chandler,

More information

General Manager Remarks FMCB 10/6/2016

General Manager Remarks FMCB 10/6/2016 General Manager Remarks FMCB 10/6/2016 Christopher T. Flynn 2 Education and performance awards MBA from the University of Massachusetts Bachelors of Arts in Economics from Merrimack College ACEC QBS AWARD

More information

Financial Report - FY 2017 Year to Date May 31, 2017

Financial Report - FY 2017 Year to Date May 31, 2017 Financial Report - FY 2017 Year to Date July 19, 2017 1 Major Highlights Revenue Sales tax remittances received through YTD April 2017 are 4.2% higher than YTD April 2016 Plaza Saltillo lease income budgeted

More information

Audit of the Honolulu Authority Fo~ Rapid Transportation (HART)

Audit of the Honolulu Authority Fo~ Rapid Transportation (HART) OFFICE OF THE CITY AUDITOR City. and County of Honolulu / State of Hawai i Audit of the Honolulu Authority Fo~ Rapid Transportation (HART) COUNCIL COM. 10 Report No. 16-03/April 2016 Audit of the Honolulu

More information

Available online at ScienceDirect. Procedia Engineering 123 (2015 ) Creative Construction Conference 2015 (CCC2015)

Available online at  ScienceDirect. Procedia Engineering 123 (2015 ) Creative Construction Conference 2015 (CCC2015) Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 123 (2015 ) 574 580 Creative Construction Conference 2015 (CCC2015) A method for estimating contingency based on project complexity

More information

Terre View Research Facility Relocation Washington State University Pullman, WA Project Manual

Terre View Research Facility Relocation Washington State University Pullman, WA Project Manual Terre View Research Facility Relocation Washington State University Pullman, WA Project Manual Project No. 9574-2018 Issued 7/19/2017 Washington State University Facility Services, Capital Terre View Research

More information

Cost Risk Assessments Planning for Project or Program Uncertainty with Confidence Brian Bombardier, PE

Cost Risk Assessments Planning for Project or Program Uncertainty with Confidence Brian Bombardier, PE Cost Risk Assessments Planning for Project or Program Uncertainty with Confidence Brian Bombardier, PE 602-778-7324 brian.bombardier@hdrinc.com 2015 HDR, Inc., all rights reserved. Addressing Cost and

More information

Metro. Board Report. Fare revenue projections, based on preliminary assumptions for ridership

Metro. Board Report. Fare revenue projections, based on preliminary assumptions for ridership Metro Board Report Los Angeles County Metropolitan Transportation Authority One Gateway Plaza 3rd Floor Board Room Los Angeles, CA SUBJECT: FY18 BUDGET DEVELOPMENT UPDATE ACTION: RECEIVE AND FILE RECOMMENDATION

More information

FEDERAL TRANSIT ADMINISTRATION PROJECT MANAGEMENT OVERSIGHT PROGRAM

FEDERAL TRANSIT ADMINISTRATION PROJECT MANAGEMENT OVERSIGHT PROGRAM FEDERAL TRANSIT ADMINISTRATION PROJECT MANAGEMENT OVERSIGHT PROGRAM Contract No. DTFT60-04-D-00015 Project No. DC-27-5044 FTA Task Order 12 Programmatic Services Work Order 5G CLIN 0005: Subtask 32A: Project

More information

Recommend to Board. Final Action

Recommend to Board. Final Action RESOLUTION NO. R2016-20 Rebaseline the Tacoma Trestle Track & Signal Project MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Capital Committee Board PROPOSED ACTION 07/14/2016 07/28/2016 Recommend to Board

More information

CRENSHAW/LAX TRANSIT CORRIDOR PROJECT - PRELIMINARY ENGINEERING OPTION II

CRENSHAW/LAX TRANSIT CORRIDOR PROJECT - PRELIMINARY ENGINEERING OPTION II One Gateway Plaza Los Angeles. CA 90012-295; 16 MEASURE R PROJECT DELIVERY COMMITTEE SEPTEMBER 16, 2010 SUBJECT: ACTION: CRENSHAW/LAX TRANSIT CORRIDOR PROJECT - PRELIMINARY ENGINEERING OPTION II APPROVE

More information

Amend FY 2006 Infrastructure Renewal Program

Amend FY 2006 Infrastructure Renewal Program Washington Metropolitan Area Transit Authority Amend FY 2006 Infrastructure Renewal Program Budget Committee December 8, 2005 Purpose That the Budget Committee approve and forward to the Board for approval

More information

METRO. Metro Funding. Associated Master Plan: Comprehensive Master Transportation Plan (MTP) for Arlington. Neighborhood(s):

METRO. Metro Funding. Associated Master Plan: Comprehensive Master Transportation Plan (MTP) for Arlington. Neighborhood(s): METRO METRO METRO 2017 2026 CIP Metro Funding Project Description The Washington Metropolitan Area Transit Authority (WMATA/Metro) is a unique federal-state-local partnership formed to provide mass transit

More information

TRANSBAY JOINT POWERS AUTHORITY

TRANSBAY JOINT POWERS AUTHORITY STAFF REPORT FOR CALENDAR ITEM NO.: 10 FOR THE MEETING OF: June 9, 2016 BRIEF DESCRIPTION: TRANSBAY JOINT POWERS AUTHORITY Adoption of a Final Revised Baseline for Phase 1 of the Transbay Transit Center

More information

Financial Report Fiscal Year 2018

Financial Report Fiscal Year 2018 Financial Report Fiscal Year 2018 Year to Date March 31, 2018 Presented on May 21, 2018 1 Major Highlights Revenue FY2018 sales tax revenue budgeted at 2.5% growth over FY2017 Sales tax remittances received

More information

2040 Long Range Transportation Plan. Financial Summary

2040 Long Range Transportation Plan. Financial Summary 2040 Long Range Transportation Plan Financial Summary FINANCIAL OUTLOOK Establishing MPO Transportation Plan fiscal forecasts for a twenty year planning horizon in today s transportation environment is

More information

JP Morgan Public Finance Transportation Utility Conference

JP Morgan Public Finance Transportation Utility Conference JP Morgan Public Finance Transportation Utility Conference April 18-19, 2018 Presented by: Brenden Morgan Sr. Manager of Debt & Investments Table of Contents I. Overview of the Region and RTD II. Updates

More information

FFY Transportation Improvement Program (TIP) Transit Project List (FFY2017)

FFY Transportation Improvement Program (TIP) Transit Project List (FFY2017) The file you have accessed is entitled FFY 2017-2021 Transportation Improvement Program (TIP) Transit Project List. Contained in the file are the Federal Transit Administration program number, Massachusetts

More information

CITY OF LOS ANGELES INTER-DEPARTMENTAL CORRESPONDENCE

CITY OF LOS ANGELES INTER-DEPARTMENTAL CORRESPONDENCE CITY OF LOS ANGELES INTER-DEPARTMENTAL CORRESPONDENCE DATE: TO: Honorable City Council c/o City Clerk, Room 395, City Hall Attention: Honorable Nury Martinez, Chair, Energy and the Environment Committee

More information

Washington Metropolitan Area Transit Authority Metro Budget Overview

Washington Metropolitan Area Transit Authority Metro Budget Overview Washington Metropolitan Area Transit Authority Metro Budget Overview February 2011 Metro 10,877 Employees (10,974 budgeted) 1,491 Buses 588 Escalators and 237 Elevators 106 Miles of Track 92 Traction Power

More information

Chapter 5: Cost and Revenues Assumptions

Chapter 5: Cost and Revenues Assumptions Chapter 5: Cost and Revenues Assumptions Chapter 5: Cost and Revenues Assumptions INTRODUCTION This chapter documents the assumptions that were used to develop unit costs and revenue estimates for the

More information

Washington Metropolitan Area Transit Authority

Washington Metropolitan Area Transit Authority Washington Metropolitan Area Transit Authority Financial Report issued in Accordance with Government Auditing Standards For the Years Ended June 30, 2016 and 2015 Single Audit Reports issued in Accordance

More information

MOTION NO. M Tacoma Link Expansion CMC Phase 1 Preconstruction Services PROPOSED ACTION

MOTION NO. M Tacoma Link Expansion CMC Phase 1 Preconstruction Services PROPOSED ACTION MOTION NO. M2017-45 Tacoma Link Expansion CMC Phase 1 Preconstruction Services MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Capital Committee 04/13/2017 Final Action Ahmad Fazel, DECM Executive Director

More information

FY18 Budget Presentation

FY18 Budget Presentation FY18 Budget Presentation Fiscal and Management Control Board April 13, 2017 Overview 1. FMCB and MBTA management continues to work diligently to close the operating budget deficit 2. Every operating dollar

More information

MassDOT Highway ACEC State Markets Conference April 5, Jonathan Gulliver, Highway Administrator John J. Bechard, P.E., Deputy Chief Engineer

MassDOT Highway ACEC State Markets Conference April 5, Jonathan Gulliver, Highway Administrator John J. Bechard, P.E., Deputy Chief Engineer MassDOT Highway ACEC State Markets Conference April 5, 2018 Jonathan Gulliver, Highway Administrator John J. Bechard, P.E., Deputy Chief Engineer About MassDOT Highway 9,561 Lane Miles of Interstate, Numbered

More information

FY2020 Budget Outlook

FY2020 Budget Outlook Finance and Capital Committee Information Item IV-A October 11, 2018 FY2020 Budget Outlook 35 of 60 Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD

More information

CENTRAL CITY LINE PROJECT UPDATE AND SMALL STARTS EVALUATION & RATINGS APPLICATION UPDATED & REVISED 4/20/17

CENTRAL CITY LINE PROJECT UPDATE AND SMALL STARTS EVALUATION & RATINGS APPLICATION UPDATED & REVISED 4/20/17 CENTRAL CITY LINE PROJECT UPDATE AND SMALL STARTS EVALUATION & RATINGS APPLICATION UPDATED & REVISED 4/20/17 EXECUTIVE SUMMARY The Central City Line (CCL) is a proposed 6-mile long high performance Bus

More information

Washington Metropolitan Area Transit Authority

Washington Metropolitan Area Transit Authority Washington Metropolitan Area Transit Authority Financial Report For the Fiscal Years Ended June 30, 2017 and 2016 Table of Contents Washington Metropolitan Area Transit Authority Financial Report For the

More information

The Bus and Rail Investment Plan in Orange County

The Bus and Rail Investment Plan in Orange County The Bus and Rail Investment Plan in Orange County Revised: 9/27/2012 Adopted: 10/2/2012 The Bus and Rail Investment Plan in Orange County I. INTRODUCTION 3 II. TRANSIT STEPS LEADING UP TO THIS PLAN 4 III.

More information

INVESTING STRATEGICALLY

INVESTING STRATEGICALLY 11 INVESTING STRATEGICALLY Federal transportation legislation (Fixing America s Surface Transportation Act FAST Act) requires that the 2040 RTP be based on a financial plan that demonstrates how the program

More information

Revised Phase 1 Budget Recommendation Transbay CAC July 9, 2013

Revised Phase 1 Budget Recommendation Transbay CAC July 9, 2013 Revised Phase 1 Budget Recommendation Transbay CAC July 9, 2013 Agenda Review of February/March Budget Discussions Risk & Vulnerability Assessment Structural Steel Bid Results Budget Risk Assessment Contingencies

More information

Date of Meeting: November 7, 2017 Item No.: 4D_Supp PROJECT AUTHORIZATION FOR PARCEL 77 AUTO TERMINAL DEVELOPMENT

Date of Meeting: November 7, 2017 Item No.: 4D_Supp PROJECT AUTHORIZATION FOR PARCEL 77 AUTO TERMINAL DEVELOPMENT Date of Meeting: November 7, 2017 Item No.: 4D_Supp PROJECT AUTHORIZATION FOR PARCEL 77 AUTO TERMINAL DEVELOPMENT Project Authorization As referenced in NWSA Resolution No. 2016-04, Exhibit A, Delegation

More information

Page 1 form HUD (4/2008)

Page 1 form HUD (4/2008) Capital Fund Financing Program OMB No. 2577-0226 Part I: Summary PHA Name: Housing Authority of the City of Shreveport of CFFP: FFY of Grant: 2009 FFY of Grant Approval: Type of Grant Original Annual Statement

More information

Total Operating Activities for FY17 are $56.9 million, an increase of $5.1M or 9.8% from FY16.

Total Operating Activities for FY17 are $56.9 million, an increase of $5.1M or 9.8% from FY16. FY17 ADOPTED ANNUAL OPERATING AND CAPITAL BUDGET Valley Metro Rail, Inc. (VMR) is a public non-profit corporation whose members are the cities of Chandler, Glendale, Mesa, Phoenix, and Tempe. VMR plans,

More information

Memphis Urban Area- Metropolitan Planning Organization Transportation Policy Board Meeting. August 23, 2018

Memphis Urban Area- Metropolitan Planning Organization Transportation Policy Board Meeting. August 23, 2018 Memphis Urban Area- Metropolitan Planning Organization Transportation Policy Board Meeting August 23, 2018. 1 Transit Asset Management (TAM) is a business model that prioritizes funding based on the condition

More information

FY2017 Year-End Financial Update

FY2017 Year-End Financial Update Finance Committee Information Item III-A September 14, 2017 FY2017 Year-End Financial Update Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD Number:

More information

Contracts Administration Management Action Plan Status June 20, 2013

Contracts Administration Management Action Plan Status June 20, 2013 Related to Agenda Item W1 Contracts Administration Management Action Plan Status June 20, 2013 Background In January 2012, the Board authorized an on-call management and consulting services contract with

More information