1 EIROPAS PARLAMENTS Budžeta kontroles komiteja DARBA DOKUMENTS par Eiropas Revīzijas palātas Īpašo ziņojumu Nr. 13/2013 (2013. gada budžeta izpildes apstiprināšana) "ES attīstības palīdzība Vidusāzijai" Budžeta kontroles komiteja Referents: Gilles Pargneaux DT\ doc PE v01-00 Vienoti daudzveidībā

2 Introduction This special report deals with the planning and management of European Union (EU) development assistance to the five Central Asian republics (Kazakhstan, Kyrgyzstan, Tajikistan, Turkmenistan and Uzbekistan) during the period The EU has been actively engaged with the countries of Central Asia since they became independent in The Commission s 2002 to 2006 Strategy Paper for Central Asia set out key objectives of the assistance strategy. These were to promote the stability and security in Central Asian countries and to assist in their pursuit of sustainable economic development and poverty reduction. For the period, the European Commission (EC) set out its plans for development assistance in a regional strategy paper it adopted in April The EU s policy towards Central Asia during the period to which the audit relates was agreed by the European Council in June 2007 and is set out in the Council document European Union and Central Asia: Strategy for a New Partnership which endorsed the Commission s approach. Through the Council s Strategy and the Commission s assistance programme, the EU defined the priorities for its cooperation with the region as a whole, highlighting security and stability as its main strategic interests. The strategy advocated active cooperation with the Central Asian states in order to promote peace, democracy and economic prosperity mainly through (i) the use of cooperation programmes and agreements along with political dialogue, (ii) the conciliation of bilateral approaches to tackle regional challenges, (iii) the identification of main policy areas and (iv) the increasing of the EU budget assistance for to around 750 million euro. From 1991 to 2013, more than 2,1 billion euro were allocated by the EU for development and humanitarian assistance to the five Central Asian republics. Until 2007, the assistance was delivered through the TACIS programme whose goals were to promote transition to the market economy and to reinforce democracy and the rule of law. In 2007, TACIS was replaced by the Development Cooperation Instrument (DCI) with other objectives assigned i.e. poverty reduction, sustainable economic and social development, and the integration of developing countries in the world economy. During the period, Kyrgyzstan and Tajikistan were the main beneficiaries of the development assistance with 435 million euro. It is also noteworthy that the EU development assistance to the region with 89 million USD for 2010 and 2011 remains below the contribution of other donors (175 million USD by the USA, 165 by Turkey, 124 by Japan and 109 million USD by Germany) and represents as well a little proportion of overall financial flows in terms of annual Foreign Direct Investment (less than 5% for Kazakhstan, Turkmenistan and Uzbekistan) and Gross Domestic Product (less than 0,2% annually). In 2011, the European Parliament concluded in its report 1 that EU funds were insufficient to allow the EU to have an impact in all of the Council s seven priority areas 2 and called on a better definition of the policy priorities and the compliance of these countries with international standards of democracy, governance, rule of law and human rights. The issue of 1 Text adopted, P7-TA (2011) 0588 on ''EU strategy for Central Asia". 2 The Council's priority axes are: (a) good governance, rule of law, human rights and democratisation, (b) education and training, (c) economic development, trade and investment, (d) transport and energy, (e) environmental sustainability and water management, (f) facing shared threats and challenges (g) intercultural dialogue. PE v /8 DT\ doc

3 corruption on the use of sector budget support in Kyrgyzstan and Tajikistan was also emphasized. Audit Scope and Objectives The audit assessed how the EEAS and the Commission planned and managed development assistance to Central Asia, in the period , in particular assistance paid under the Development Cooperation Instrument (DCI), which was the main financing instrument. The audit examined: whether, in allocating its budget, the Commission followed best practice and respected its declared priorities for development assistance in Central Asia; whether the Commission delivered development assistance in an appropriate way; whether the Commission successfully implemented its aid policy, developed it in the light of experience and reported appropriately. Other aspects of the EU strategy, such as policy dialogue, were not included in the scope of the audit. Audit work was carried out between June and November 2012 and was based on documentary review, interviews with visits made in October 2012 to Kyrgyzstan, Tajikistan and Uzbekistan, during which the auditors interviewed EU delegation staff, representatives of national authorities, Member States embassies, technical experts, civil society organisations, other donors and stakeholders. A total of 21 support programmes (19 country-specific and two regional programmes) were reviewed and the Court also carried out a survey on donor coordination and on other donors perceptions of the EU s work in the field for each of the five Central Asian republics. Court's Findings and Observations Allocation of the budget The Court first examined how the Commission allocated the EU budget and to what extent it followed best practices and followed its declared priorities for development assistance in Central Asia. The Court found that the Commission set three broad overall priorities for its spending within its regional strategy paper (RSP) namely fostering regional cooperation, reducing poverty and promoting democratisation and human rights. The RSP was then further clarified in an indicative programme with detailed plan for the allocation of aid and specific priorities. It also appeared from the audit that the Commission departed in certain respects from recognised best practices for the allocation of development aid as only limited justification was provided for justifying Commission's choice of spending priorities. However, in most cases, the Commission has shown continuity in the distribution of funds, ensured that EU spending was in line with those of other donors to avoid overlapping and has chosen good quality programmes. The Court acknowledged that the Commission had to face particular challenges in terms of coordination with partner countries in which for instance need assessments for development assistance were lacking, human rights and good governance DT\ doc 3/8 PE v01-00

4 were not the priority or national programmes were missing clear focus. Regardless those examples, the Court stated that the results of discussions between the Commission and recipient countries on aid priorities and on the alignment of the EU spending on national plans were reflected in the RSP and indicatives programmes and that the projects reviewed by the Court namely in Kyrgyzstan and Tajikistan were in line with the Commission strategy and with priorities of the partners. The Court observed that the Commission earmarked the highest levels of aid to the countries it perceived to be most in need and most willing and capable of best use of aid, namely Tajikistan and Kyrgyzstan. However, the audit revealed that the Commission s approach was less satisfactory in respect of the number of sectors to which it paid assistance according to the principle that EU donors should aim to focus their efforts on a maximum of three sectors in any partner country, so as to optimise results and reduce transaction costs. Notwithstanding the small size of its development assistance programme in Central Asia, the Commission did not apply this principle rigorously as four sectors for assistance were selected in Kyrgyzstan (governance, agriculture and rural development, education and social protection), five sectors in Tajikistan (governance, agriculture and rural development, social protection, private sector and health), and six in Uzbekistan (private sector, governance, health, agriculture and rural development, environment and energy and education). In addition, it was found that the Commission channelled EU development assistance money to various additional sectors through regional and thematic programmes. Despite an allocation of aid to too many areas, the Court identified no significant cases where aid was provided to a national programme which did not address one of the Commission's objectives of reducing poverty and improving governance. The amounts contracted by the end of 2012 respected the priorities of the RSP. Putting the policy into effect The second Court's audit objective was to evaluate the Commission' choice of delivery modes, the management of administrative costs, the monitoring tools and the design of the budget support. The Court identified several ways of delivering aid from 2007 to end 2012, namely through contribution agreements with international organisations (36% of the total value), budget support (28%), grants to NGOs (17%) and service and works contracts (19%). The Court further noted the large proportion by number of services and contracts (244 out of 435) but representing a small value which induces important administrative implications. In addition, the Commission used several financing instruments such as DCI, five thematic DCI instruments, five global instruments and the European Neighbourhood and Partnership Instrument (ENPI), the latter being operated in Union's Delegations or by Headquarters, thus adding further complexity to the overall management of the EU spending in Central Asia. The Court observed that a breakdown of the Union's spending by country and per sector was uneasy due to the weaknesses of the Common Relex Information system (CRIS). As regards administrative costs, the Court found that the Commission has not implemented a system for reporting on the overall administrative cost led by the delivering of its development assistance. The Court estimated for 2011 the level of administrative costs to 10.5 million euro (representing approximately 14,6% of the development spending for Central PE v /8 DT\ doc

5 Asia) which can be divided as follows: 6.6 million euro (63%) dedicated to development cooperation work, 1.8 million euro for headquarters staff costs (17%) and 2.1 million euro (20%) including various support expenditure. Concerning the setting-up of SMART objectives and correlative indicators, a mixed picture was found during the Court's visits. In Tajikistan the technical assistance programme supporting the Ministry of Finance had vaguely formulated objectives, in Kyrgyzstan the food security information programme contained vague indicators and in Uzbekistan two out of the four programmes examined had no benchmarks and baselines defined to allow assessment of the added value of the programmes. For budget support (BS) activities in Tajikistan and Kyrgyzstan, the Court noted that Public Financial Management (PFM) programmes were present with disbursements conditional upon progress achieved towards PFM objectives. However, the Court estimated that in both countries, the Commission s enforcement of PFM conditions was insufficiently rigorous. In Kyrgyzstan even though progress had been slow, the Commission justified the disbursement of each of the three tranches mainly because it considered that the Kyrgyz government remained committed to further reforms. With regard to BS for social protection during the period in Tajikistan, the Commission had not defined strict deadlines by which the government had to comply with the conditions. Moreover, despite the serious problem of corruption in the republics of Central Asia, budget support programmes were not linked to specific anti-corruption measures. Implementing and reporting The Court finally analysed the way the Commission implemented and reported on its aid policy in Central Asia. The audit work identified cases with long delays in getting programmes under way due to heavy bureaucratic procedures in recipient administrations, difficulties in finding suitable fundable activities and complex Commission procedures delaying the strategy implementation. It was also observed that the speed of implementation varied significantly among partner countries: particular slow progress in Turkmenistan and Uzbekistan (reflecting the differences in priorities and approaches to development cooperation between the EU and these countries) and faster implementation in Kyrgyzstan and Tajikistan resulting from the improvement in development cooperation between the EU and these two countries. The Court found that the Commission committed about one third of the strategy budget to regional programmes to achieve leverage for its political efforts to promote regional cooperation. Although this was consistent with the EU strategy objectives, regional programmes have not achieved a genuine regional dimension neither in terms of joint implementation nor in terms of regional impact envisaged by its development strategy. A considerable share of the regional funds of the RSP have been committed to multi-country programmes (such as Erasmus and Tempus (36 %) and the Investment Facility for Central Asia programme (29 %)) mainly replicating similar activities in more than one beneficiary country rather than promoting cooperation between the Central Asian republics. The Border Management Programme for Central Asia (BOMCA) provides another example of varying participation among recipient countries with Uzbekistan and Turkmenistan participating DT\ doc 5/8 PE v01-00

6 selectively in the regional capacity-building activities and being unwilling to share their professional experience with the other countries. The Court noted that the Commission, following the 2010 mid-term review, has taken into account in the indicative programme, new developments in the partner countries such as the gradual development of civil society, the need for technical assistance programmes to be combined with budget support and institutional reform programmes. Some new types of programmes such as the investment facility programme were also integrated in the programming. Nevertheless, there was still room for improvement for the Court as the Commission did not take the opportunity to give higher priority to promoting twinning and secondment of staff between EU and Central Asian administrations albeit it was a priority identified in the Council s strategy for EU-Central Asian relations. In the field of budget support programmes in Kyrgyzstan and Tajikistan, useful recommendations were not taken on board. With regard to reporting activities, the Court found that the indicators were focused on activity rather than the intended results of the Council's new partnership strategy for Central Asia. Summary of the Commission and European External Action Service Replies The Commission and EEAS underlined the objective difficulties of Central Asian countries to advance with the reform agenda, their institutional and political framework being among the main limiting factors for the implementation of development cooperation. On budget allocation, the Commission recalled that the choices of interventions were in line with the relevant strategy papers and adequately justified and also agreed with the aid effectiveness principle of focusing aid on a maximum of three sectors with partner countries. The Commission and the EEAS undertook specific efforts, notably for , to concentrate the areas of intervention for bilateral assistance. The Commission and the EEAS reminded that the decision of the modality of implementation was the result of a specific analysis and integrated evaluation for each programme; including a consultation and quality scrutiny process and that the Commission was working to reduce the number of small-size projects. Furthermore, the Commission clarified that the reporting on the implementation necessarily involved different geographic and thematic services at headquarters while also both including the information on spending for different programmes and instruments and already different tools to evaluate the administrative costs involved with development cooperation. The Commission however considered the level of administrative costs calculated by the Court as overestimated. Regarding on-going budget support programmes, the Commission and the EEAS underlined that they were linked to specific corruption prevention measures. Eligibility criteria for budget support required a holistic approach based on credibility and positive implementation which are by nature general. Satisfactory progress should be based on a dynamic approach, looking at past and recent policy performance benchmarked against reform expectations, but allowing corrective measures and refining the objectives and targets if necessary. PE v /8 DT\ doc

7 The Commission and the EEAS recalled the peculiarity of Central Asia regional programmes, which provided opportunities for dialogue and promote good neighbourhood relations and regional cooperation. A genuine regional dimension was not always feasible in the given present Central Asia political conditions due notably to rivalries among countries. The Commission mentioned its efforts towards an increasing focus on results and, whenever relevant, has always taken on board the recommendations resulting from the implementation of the programmes. Ziņojuma sagatavotāja ieteikumi iespējamai iekļaušanai Komisijas ikgadējā ziņojumā par budžeta izpildi: [Eiropas Parlaments] 1. atzinīgi vērtē īpašo ziņojumu par ES attīstības palīdzību Vidusāzijai; pieņem zināšanai konstatējumus, secinājumus un ieteikumus un turpmāk tekstā izklāsta savas piezīmes un ieteikumus; Vispārīgas piezīmes 2. atzinīgi vērtē ziņojumā paustos apsvērumus, kas norāda uz Komisijas EĀDD nozīmīgajiem centieniem šajā sarežģītajā ģeogrāfiskajā un politiskajā kontekstā; 3. tomēr norāda, ka joprojām ir nepieciešami uzlabojumi, lai efektīvāk orientētu un izstrādātu ES attīstības stratēģijas, izmantojot atbilstīgus palīdzības veidus, tādējādi veicinot ES politisko mērķu atpazīstamību un ietekmi reģionālā līmenī; 4. uzsver, ka ES iesaistīšanās mērogam un raksturam ir jābūt dažādotam un atkarīgam no izmērāma progresa demokratizācijas, cilvēktiesību, labas pārvaldības, ilgtspējīgas sociālekonomiskās attīstības, tiesiskuma un korupcijas apkarošanas jomā, vajadzības gadījumā sniedzot palīdzību šā progresa veicināšanā saskaņā ar pamatnostādnēm, kas ir līdzīgas ES kaimiņattiecību politikas principiem. 5. uzskata, ka pastāvīgs ES atbalsts Vidusāzijas valstīm paredzētām programmām ir būtisks pārrobežu mehānisms reģiona valstu savstarpējās izpratnes un sadarbības veicināšanā; 6. atkārtoti pauž Eiropas Parlamenta gadā pieņemto nostāju, kurā secināts, ka ES finansējums ir nepietiekams, lai ES būtu ietekme visās septiņās prioritārajās jomās, ko noteikusi Padome, un kurā aicināts skaidrāk definēt politiskās prioritātes, kā arī to, kādā mērā šīs valstis nodrošina atbilstību demokrātijas, pārvaldes, tiesiskuma un cilvēktiesību starptautiskajiem standartiem; 7. norāda, ka attīstības sadarbība ar Vidusāzijas valstīm var sniegt rezultātus tikai tad, ja šīs valstis ievēro starptautiskos standartus attiecībā uz demokrātiju, pārvaldību, tiesiskumu un cilvēktiesībām; tāpat norāda, ka ES nedrīkst pakārtot attīstības sadarbību ekonomikas, enerģētikas vai drošības interesēm; Turpmākie apsvērumi saistībā ar attīstības palīdzības plānošanu un īstenošanu nākotnē DT\ doc 7/8 PE v01-00

8 8. uzskata, ka turpmākās reģionālās programmas Komisijai jāizstrādā tā, lai tās nodrošinātu patiesu reģionālo dimensiju; 9. prasa, lai Komisija koncentrēti novirzītu visu sniegto palīdzību nelielam jomu skaitam; 10. norāda, ka turpmākā attīstības palīdzība ir jāpilnveido gan pastiprinot koordināciju ES iekšienē, gan aktīvāk sadarbojoties ar citiem starptautiskajiem līdzekļu devējiem un reģionālajiem dalībniekiem; 11. visnotaļ atbalsta to, lai visās Vidusāzijas valstīs tiktu atvērtas pilnībā funkcionējošas ES delegācijas, tādējādi nostiprinot ES klātbūtni un atpazīstamību reģionā un ilgtermiņa sadarbību un sasaisti ar visiem sabiedrības sektoriem, kā arī veicinot virzību uz dziļāku izpratni par tiesiskumu un cilvēktiesībām un to nostiprināšanu; delegāciju klātbūtne būtiski atbalstīs attīstības palīdzības mērķu sasniegšanu; 12. aicina Komisiju izveidot aprēķināšanas un ziņošanas sistēmu attiecībā uz kopējām administratīvām izmaksām saistībā ar attīstības palīdzības sniegšanu; 13. prasa, lai Komisija noteiktu un piemērotu stingrus un objektīvi pārbaudāmus nosacījumus attiecībā uz ikvienu spēkā esošu budžeta atbalsta programmu, jo īpaši pienācīgu uzmanību veltot atbalstam, kas paredzēts korupcijas apkarošanas mehānismiem; 14. atgādina, ka korupcija Vidusāzijas valstīs ir smaga problēma; Transparency International korupcijas uztveres indeksā gadā tām tika piešķirts rādītājs mazāks nekā 28 no 100, un Kirgizstāna, Turkmenistāna, kā arī Uzbekistāna tika ierindotas starp pēdējiem 10 % no 182 apsekotajām valstīm; 15. uzskata, ka šāda plaši izplatīta korupcija var negatīvi ietekmēt Komisijas reputāciju un samazināt atbalsta programmu efektivitāti; 16. lēmumi par piešķiršanu jāpieņem, pamatojoties uz partnervalstu panākto progresu nevis uz deklarēto apņemšanos īstenot reformas, uzsver, cik svarīgi ir nodrošināt pienācīgu politisko dialogu, kura pamatā būtu stimulējoša pieeja un pastāvīga nozares reformu un programmu uzraudzība, novērtējot darbību un rezultātu ilgtspējību; 17. prasa nodrošināt lielāku pārredzamību attiecībā uz ES un dalībvalstu vēstniecību piešķīrumiem, lai atbalstītu patiesi neatkarīgus nevalstiskos partnerus, tādējādi palīdzot tiem būt ietekmīgiem konsolidētas pilsoniskās sabiedrības veidošanā; 18. prasa, lai Komisija uzlabotu programmu izstrādi un īstenošanu, ņemot vērā gūtās mācības un mainīgos apstākļus; 19. prasa Komisijai ziņot par rezultātiem un ietekmi tā, lai būtu iespējams salīdzināt plānoto un sasniegto. PE v /8 DT\ doc

DARBA DOKUMENTS. LV Vienoti daudzveidībā LV

DARBA DOKUMENTS. LV Vienoti daudzveidībā LV EIROPAS PARLAMENTS 2014-2019 Budžeta kontroles komiteja 8.9.2014 DARBA DOKUMENTS par Eiropas Revīzijas palātas Īpašo ziņojumu Nr. 18/2013 (2013. gada budžeta izpildes apstiprināšana). Dalībvalstu lauksaimniecības

More information

EIROPAS PARLAMENTS Budžeta kontroles komiteja DARBA DOKUMENTS

EIROPAS PARLAMENTS Budžeta kontroles komiteja DARBA DOKUMENTS EIROPAS PARLAMENTS 2014-2019 Budžeta kontroles komiteja 26.3.2015 DARBA DOKUMENTS par Eiropas Revīzijas palātas Īpašo ziņojumu Nr. 3/2015 (2014. finanšu gada budžeta izpildes apstiprināšana) ES garantija

More information

COMMUNICATION FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT, THE COUNCIL, THE EUROPEAN ECONOMIC AND SOCIAL COMMITTEE AND THE COMMITTEE OF THE REGIONS

COMMUNICATION FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT, THE COUNCIL, THE EUROPEAN ECONOMIC AND SOCIAL COMMITTEE AND THE COMMITTEE OF THE REGIONS EUROPEAN COMMISSION Brussels, 13.10.2011 COM(2011) 638 final COMMUNICATION FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT, THE COUNCIL, THE EUROPEAN ECONOMIC AND SOCIAL COMMITTEE AND THE COMMITTEE OF THE

More information

DARBA DOKUMENTS. LV Vienoti daudzveidībā LV

DARBA DOKUMENTS. LV Vienoti daudzveidībā LV EIROPAS PARLAMENTS 2014-2019 Budžeta kontroles komiteja 10.9.2014 DARBA DOKUMENTS par Eiropas Revīzijas palātas Īpašo ziņojumu Nr. 2/2014 (2013. finanšu gada budžeta izpildes apstiprināšana) Vai preferenciālie

More information

VADEMECUM ON FINANCING IN THE FRAME OF THE EASTERN PARTNERSHIP

VADEMECUM ON FINANCING IN THE FRAME OF THE EASTERN PARTNERSHIP EUROPEAN COMMISSION EUROPEAN EXTERNAL ACTION SERVICE VADEMECUM ON FINANCING IN THE FRAME OF THE EASTERN PARTNERSHIP ***LAST UPDATE 24 SEPTEMBER 2010*** Table of Contents PART I An Overview of the Eastern

More information

EXTERNAL ASSISTANCE PROGRAMMES. An Introduction

EXTERNAL ASSISTANCE PROGRAMMES. An Introduction EXTERNAL ASSISTANCE PROGRAMMES An Introduction 1 Overview What are the main programmes? What do they fund? How is the money allocated and managed? How is it tendered? How can you participate? What appeal?

More information

Twinning and Technical assistance Facility in support to the EU- Armenia ENP AP implementation CRIS n ENPI/2008/

Twinning and Technical assistance Facility in support to the EU- Armenia ENP AP implementation CRIS n ENPI/2008/ EN 1 EN ACTION FICHE FOR ARMENIA - ENPI AAP 2008 1. IDENTIFICATION Title Total cost Aid method / Management mode Twinning and Technical assistance Facility in support to the EU- Armenia ENP AP implementation

More information

Official Journal of the European Union

Official Journal of the European Union L 210/82 31.7.2006 COUNCIL REGULATION (EC) No 1085/2006 of 17 July 2006 establishing an Instrument for Pre-Accession Assistance (IPA) THE COUNCIL OF THE EUROPEAN UNION, Having regard to the Treaty establishing

More information

What funding for EU external action after 2013?

What funding for EU external action after 2013? What funding for EU external action after 2013? Meta Informations Creation date 12-01-2011 Last update date User name null Case Number 023301706302201211 Invitation Ref. Status N Are you replying...? Identification

More information

The DAC s main findings and recommendations. Extract from: OECD Development Co-operation Peer Reviews

The DAC s main findings and recommendations. Extract from: OECD Development Co-operation Peer Reviews The DAC s main findings and recommendations Extract from: OECD Development Co-operation Peer Reviews Luxembourg 2017 Luxembourg has strengthened its development co-operation programme The committee concluded

More information

REGULATION (EU) No 232/2014 OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL of 11 March 2014 establishing a European Neighbourhood Instrument

REGULATION (EU) No 232/2014 OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL of 11 March 2014 establishing a European Neighbourhood Instrument 15.3.2014 EN Official Journal of the European Union L 77/27 REGULATION (EU) No 232/2014 OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL of 11 March 2014 establishing a European Neighbourhood Instrument THE

More information

Private Sector and development: a global responsibility?

Private Sector and development: a global responsibility? Private Sector and development: a global responsibility? - the EU Communication on the role of Private sector and Development - The conclusions of the Foreign Affairs Council - Points of Departure of Concord

More information

Operational Criteria for the submission of proposals to the EU Trust Fund for Colombia

Operational Criteria for the submission of proposals to the EU Trust Fund for Colombia Operational Criteria for the submission of proposals to the EU Trust Fund for Colombia Potential EU Trust Fund partners shall submit proposals (concept notes and action documents) directly to the following

More information

Guidelines on participation in EU External Aid Programmes

Guidelines on participation in EU External Aid Programmes Guidelines on participation in EU External Aid Programmes Welcomeurope AGRICULTURE, RURAL DEVELOPMENT & FOOD SECURITY IN THE EU EXTERNAL AID INSTRUMENTS Brussels, 13 June 2012 PROGRAMME 1- The EU External

More information

Official Journal of the European Union DECISIONS

Official Journal of the European Union DECISIONS L 17/40 23.1.2018 DECISIONS COUNCIL DECISION (CFSP) 2018/101 of 22 January 2018 on the promotion of effective arms export controls THE COUNCIL OF THE EUROPEAN UNION, Having regard to the Treaty on European

More information

Challenges Of The Indirect Management Of Eu Funds In Albania

Challenges Of The Indirect Management Of Eu Funds In Albania Challenges Of The Indirect Management Of Eu Funds In Albania Neritan Totozani, Msc Central Financing & Contracting Unit, Ministry of Finance, Albania doi: 10.19044/esj.2016.v12n7p170 URL:http://dx.doi.org/10.19044/esj.2016.v12n7p170

More information

DAC-code Sector Public Sector Policy and Administrative Management

DAC-code Sector Public Sector Policy and Administrative Management ANNEX 1 ANNUAL ACTION PROGRAMME 2012 FOR UKRAINE PART 1 1. IDENTIFICATION Title/Number Total cost Aid method / Method of implementatio n Framework Programme in support of EU-Ukraine Agreements CRIS: ENPI/2012/23714

More information

EN Official Journal of the European Union L 77/95

EN Official Journal of the European Union L 77/95 15.3.2014 EN Official Journal of the European Union L 77/95 REGULATION (EU) No 236/2014 OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL of 11 March 2014 laying down common rules and procedures for the implementation

More information

ANNEX. 1. IDENTIFICATION Beneficiary CRIS/ABAC Commitment references Total cost EU Contribution Budget line. Turkey IPA/2017/40201

ANNEX. 1. IDENTIFICATION Beneficiary CRIS/ABAC Commitment references Total cost EU Contribution Budget line. Turkey IPA/2017/40201 ANNEX to Commission Implementing Decision adopting an Annual Action Programme for Turkey under the Instrument for Pre-accession Assistance (IPA II) for the year 2017 1. IDENTIFICATION Beneficiary CRIS/ABAC

More information

Action Fiche for Armenia Sector Multi Sector

Action Fiche for Armenia Sector Multi Sector Action Fiche for Armenia 1. IDENTIFICATION Title Total cost Aid method / Management mode DAC-code Twinning Projects between 3 or 4 Armenian administrations and their equivalent in EU Member States to foster

More information

COUNCIL OF THE EUROPEAN UNION. Brussels, 15 May /07 DEVGEN 89 ACP 94 RELEX 347

COUNCIL OF THE EUROPEAN UNION. Brussels, 15 May /07 DEVGEN 89 ACP 94 RELEX 347 COUNCIL OF THE EUROPEAN UNION Brussels, 15 May 2007 9558/07 DEVGEN 89 ACP 94 RELEX 347 NOTE from : General Secretariat on : 15 May 2007 No. prev. doc. : 9090/07 Subject : EU Code of Conduct on Complementarity

More information

The European Neighbourhood and Partnership Instrument. DG RELEX UNIT ER-D-1 European Neighbourhood Policy Coordination General Coordination

The European Neighbourhood and Partnership Instrument. DG RELEX UNIT ER-D-1 European Neighbourhood Policy Coordination General Coordination The European Neighbourhood and Partnership Instrument DG RELEX UNIT ER-D-1 European Neighbourhood Policy Coordination General Coordination Objectives of the presentation The EU s political geography Development

More information

EVALUATION WORK PROGRAMME FOR STRATEGIC EVALUATIONS

EVALUATION WORK PROGRAMME FOR STRATEGIC EVALUATIONS EUROPEAN COMMISSION Directorate-General for International Cooperation and Development Evaluation EVALUATION WORK PROGRAMME 2017-2021 FOR STRATEGIC EVALUATIONS I Introduction I.1 Principles and framework

More information

Zambia s poverty-reduction strategy paper (PRSP) has been generally accepted

Zambia s poverty-reduction strategy paper (PRSP) has been generally accepted 15 ZAMBIA The survey sought to measure objective evidence of progress against 13 key indicators on harmonisation and alignment (see Foreword). A four-point scaling system was used for all of the Yes/No

More information

«FICHE CONTRADICTOIRE»

«FICHE CONTRADICTOIRE» «FICHE CONTRADICTOIRE» Evaluation of the Commission s External Cooperation with Angola (Country level evaluation) (*For details on the recommendations please refer to the main report) Recommendations STRATEGIC

More information

ANNEX. DAC code Sector Economic and Development Planning

ANNEX. DAC code Sector Economic and Development Planning ANNEX 1. IDTIFICATION Title Total cost Aid method management mode Technical Cooperation Facility 1.5M (2.4% of NIP) Project approach partially decentralised management DAC code 15010 Sector Economic and

More information

Guidance for Member States on Performance framework, review and reserve

Guidance for Member States on Performance framework, review and reserve EGESIF_18-0021-01 19/06/2018 Version 2.0 EUROPEAN COMMISSION European Structural and Investment Funds Guidance for Member States on Performance framework, review and reserve This version was updated further

More information

EN 1 EN. Annex. Sector Policy Support Programme: Sector budget support (centralised management) DAC-code Sector Trade related adjustments

EN 1 EN. Annex. Sector Policy Support Programme: Sector budget support (centralised management) DAC-code Sector Trade related adjustments Annex 1. Identification Title/Number Trinidad and Tobago Annual Action Programme 2010 on Accompanying Measures on Sugar; CRIS reference: DCI- SUCRE/2009/21900 Total cost EU contribution : EUR 16 551 000

More information

Evaluation of the European Union s Co-operation with Kenya Country level evaluation

Evaluation of the European Union s Co-operation with Kenya Country level evaluation "FICHE CONTRADICTOIRE" Evaluation of the European Union s Co-operation with Kenya Country level evaluation Recommendations Responses of Services: Follow-up (one year later) GENERAL RECOMMENDATIONS 1 Give

More information

Follow-up by the European Commission to the EU-ACP JPA on the resolution on private sector development strategy, including innovation, for sustainable

Follow-up by the European Commission to the EU-ACP JPA on the resolution on private sector development strategy, including innovation, for sustainable Follow-up by the European Commission to the EU-ACP JPA on the resolution on private sector development strategy, including innovation, for sustainable Development. The European External Action Service

More information

Evaluation of the European Neighbourhood Instrument Draft Report Executive summary January 2017

Evaluation of the European Neighbourhood Instrument Draft Report Executive summary January 2017 Evaluation of the European Neighbourhood Instrument Draft Report Executive summary January 2017 Development and Cooperation EuropeAid This report has been prepared by Lead company Consortium composed by

More information

Evaluation of Budget Support Operations in Morocco. Summary. July Development and Cooperation EuropeAid

Evaluation of Budget Support Operations in Morocco. Summary. July Development and Cooperation EuropeAid Evaluation of Budget Support Operations in Morocco Summary July 2014 Development and Cooperation EuropeAid A Consortium of ADE and COWI Lead Company: ADE s.a. Contact Person: Edwin Clerckx Edwin.Clerck@ade.eu

More information

Multi-country European Integration Facility

Multi-country European Integration Facility 1 INSTRUMENT FOR PRE-ACCESSION ASSISTANCE (IPA II) 2014-2020 Multi-country European Integration Facility Action Summary The objective of the EU Integration Facility is to assist the IPA II beneficiaries

More information

Mutual Accountability: The Key Driver for Better Results

Mutual Accountability: The Key Driver for Better Results Third International Roundtable Managing for Development Results Hanoi, Vietnam February 5-8, 2007 Mutual Accountability: The Key Driver for Better Results A Background Paper Third International Roundtable

More information

IMPLEMENTING THE PARIS DECLARATION AT THE COUNTRY LEVEL

IMPLEMENTING THE PARIS DECLARATION AT THE COUNTRY LEVEL CHAPTER 6 IMPLEMENTING THE PARIS DECLARATION AT THE COUNTRY LEVEL 6.1 INTRODUCTION The six countries that the evaluation team visited vary significantly. Table 1 captures the most important indicators

More information

Ex-post Evaluation of ENPI CBC Programmes

Ex-post Evaluation of ENPI CBC Programmes Ex-post Evaluation of 2007-2013 ENPI CBC Programmes Executive summary January 2018 Evaluation carried out on behalf of the European Commission Desk Report Volume 2 April 2017 Particip GmbH and AETS Volume

More information

CE TEXTE N'EST DISPONIBLE QU'EN VERSION ANGLAISE

CE TEXTE N'EST DISPONIBLE QU'EN VERSION ANGLAISE CE TEXTE N'EST DISPONIBLE QU' VERSION ANGLAISE ANNEX 1 1. IDTIFICATION Title/Number Support Services to the National Authorising Officer CRIS NO: FED/2009/021-496 Total cost Total: 315,800 (EC Contribution:

More information

FINANCING THE EU NEIGHBOURHOOD KEY FACTS AND FIGURES FOR THE EASTERN PARTNERSHIP

FINANCING THE EU NEIGHBOURHOOD KEY FACTS AND FIGURES FOR THE EASTERN PARTNERSHIP CES Working Papers Volume VIII, Issue 3 FINANCING THE EU NEIGHBOURHOOD KEY FACTS AND FIGURES FOR THE EASTERN PARTNERSHIP Ioana SANDU * Gabriela DRAGAN ** Abstract: The EU is permanently trying to secure

More information

Having regard to the Treaty on the Functioning of the European Union, and in particular Article 291 thereof,

Having regard to the Treaty on the Functioning of the European Union, and in particular Article 291 thereof, L 244/12 COMMISSION IMPLEMTING REGULATION (EU) No 897/2014 of 18 August 2014 laying down specific provisions for the implementation of cross-border cooperation programmes financed under Regulation (EU)

More information

EN Official Journal of the European Union L 77/77

EN Official Journal of the European Union L 77/77 15.3.2014 EN Official Journal of the European Union L 77/77 REGULATION (EU) No 234/2014 OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL of 11 March 2014 establishing a Partnership Instrument for cooperation

More information

STRATEGIC PROJECT SUPPORT TO EU ASSISTANCE IN THE CONTEXT OF EU EXTERNAL POLICIES

STRATEGIC PROJECT SUPPORT TO EU ASSISTANCE IN THE CONTEXT OF EU EXTERNAL POLICIES STRATEGIC PROJECT SUPPORT TO EU ASSISTANCE IN THE CONTEXT OF EU EXTERNAL POLICIES IMPLEMENTATION PLAN - WP2018 1. Summary The ETF provides support to the EC services and the EU Delegations (EUD) in its

More information

Annex I Action Fiche for West Bank and Gaza Strip/ ENPI

Annex I Action Fiche for West Bank and Gaza Strip/ ENPI Annex I Action Fiche for West Bank and Gaza Strip/ ENPI 1. IDENTIFICATION Title/Number Total cost Aid method / Method of implementation PEGASE: Support to Recurrent Expenditures of the PA EUR 158,500,000

More information

Poverty Profile Executive Summary. Azerbaijan Republic

Poverty Profile Executive Summary. Azerbaijan Republic Poverty Profile Executive Summary Azerbaijan Republic December 2001 Japan Bank for International Cooperation 1. POVERTY AND INEQUALITY IN AZERBAIJAN 1.1. Poverty and Inequality Measurement Poverty Line

More information

Sudan. Sudan is a lower-middle income country with a gross national income (GNI) of USD 1 220

Sudan. Sudan is a lower-middle income country with a gross national income (GNI) of USD 1 220 00 Sudan INTRODUCTION Sudan is a lower-middle income country with a gross national income (GNI) of USD 1 220 per capita (2009) which has grown at an average rate of 7% per annum since 2005 (WDI, 2011).

More information

EU Funding opportunities for CSOs

EU Funding opportunities for CSOs EU Funding opportunities for CSOs Funding for Development and Relief (FDR) working group Croatian Study Visit Lonne Poissonnier, CONCORD 23 September 2013 1 CONCORD s work on EU funding for CSOs Objectives:

More information

The DAC s main findings and recommendations. Extract from: OECD Development Co-operation Peer Reviews

The DAC s main findings and recommendations. Extract from: OECD Development Co-operation Peer Reviews The DAC s main findings and recommendations Extract from: OECD Development Co-operation Peer Reviews Poland 2017 1 Towards a comprehensive Polish development effort Indicator: The member has a broad, strategic

More information

EU budget For 500 million Europeans For growth and employment. Citizenship, freedom, security and justice. The EU as a global player

EU budget For 500 million Europeans For growth and employment. Citizenship, freedom, security and justice. The EU as a global player EU budget 2012 For 500 million Europeans For growth and employment 1.4 % Citizenship, freedom, security and justice Natural resources: rural development, environment and fisheries 10.9 % 40.8 % 6.4 % The

More information

COHESION POLICY

COHESION POLICY INTEGRATED SUSTAINABLE URBAN DEVELOPMENT COHESION POLICY 2014-2020 The European Commission adopted legislative proposals for cohesion policy for 2014-2020 in October 2011 This factsheet is one in a series

More information

Job Description and Requirements Programme Manager State-building and Governance Job no in the EU Delegation to the Republic of Yemen

Job Description and Requirements Programme Manager State-building and Governance Job no in the EU Delegation to the Republic of Yemen JOB PROFILE 17/08/2013 Job Description and Requirements Programme Manager State-building and Governance Job no. 127004 in the EU Delegation to the Republic of Yemen Job Type: Contract Agent Function Group

More information

Proposal for a REGULATION OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL. establishing a financing instrument for development cooperation

Proposal for a REGULATION OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL. establishing a financing instrument for development cooperation EUROPEAN COMMISSION Brussels, 7.12.2011 COM(2011) 840 final 2011/0406 (COD) Proposal for a REGULATION OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL establishing a financing instrument for development cooperation

More information

Implementation of Sustainable Development Goals in the European Union. Focus on development cooperation. Carlos BERROZPE GARCÍA

Implementation of Sustainable Development Goals in the European Union. Focus on development cooperation. Carlos BERROZPE GARCÍA Implementation of Sustainable Development Goals in the European Union Focus on development cooperation Carlos BERROZPE GARCÍA Head of Sector SDGs DG International Cooperation and Development European Commission

More information

COMMUNICATION FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT, THE COUNCIL, THE EUROPEAN ECONOMIC AND SOCIAL COMMITTEE AND THE COMMITTEE OF THE REGIONS

COMMUNICATION FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT, THE COUNCIL, THE EUROPEAN ECONOMIC AND SOCIAL COMMITTEE AND THE COMMITTEE OF THE REGIONS EUROPEAN COMMISSION Brussels, 13.10.2011 COM(2011) 637 final COMMUNICATION FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT, THE COUNCIL, THE EUROPEAN ECONOMIC AND SOCIAL COMMITTEE AND THE COMMITTEE OF THE

More information

Guideline for strengthened bilateral relations. EEA and Norway Grants

Guideline for strengthened bilateral relations. EEA and Norway Grants Guideline for strengthened bilateral relations EEA and Norway Grants 2009 2014 Adopted by the Financial Mechanism Committee 29.03.2012, amended on 28 January 2016 Contents 1 Purpose of the guideline...

More information

Vanuatu. Vanuatu is a lower-middle-income country with a gross national income (GNI) of

Vanuatu. Vanuatu is a lower-middle-income country with a gross national income (GNI) of 00 Vanuatu INTRODUCTION Vanuatu is a lower-middle-income country with a gross national income (GNI) of USD 2 620 per capita (2009) and a population of 240 000 (WDI, 2011). Net official development assistance

More information

DRAFT REPORT. EN United in diversity EN. European Parliament 2016/2304(INI)

DRAFT REPORT. EN United in diversity EN. European Parliament 2016/2304(INI) European Parliament 2014-2019 Committee on Regional Development 2016/2304(INI) 2.3.2017 DRAFT REPORT on increasing engagement of partners and visibility in the performance of European Structural and Investment

More information

The EU Youth Strategy beyond 2018: a focused strategy with a coordinated management

The EU Youth Strategy beyond 2018: a focused strategy with a coordinated management Proposal for the governance of the EU Youth Strategy The EU Youth Strategy beyond 2018: a focused strategy with a coordinated management This paper aims at exploring how Member States and relevant stakeholders

More information

Official web site of the Ministry:

Official web site of the Ministry: HUNGARY POLICY FRAMEWORK The Ministry of Foreign Affairs of the Republic of Hungary is responsible for planning and coordinating the Hungarian international development cooperation and humanitarian aid

More information

Multi-country European Integration Facility

Multi-country European Integration Facility 1 INSTRUMENT FOR PRE-ACCESSION ASSISTANCE (IPA II) 2014-2020 Multi-country European Integration Facility Action Summary The objective of the EU Integration Facility is to assist the IPA II beneficiaries

More information

Official Journal of the European Union DECISIONS

Official Journal of the European Union DECISIONS 6.7.2018 L 171/11 DECISIONS DECISION (EU) 2018/947 OF THE EUROPEAN PARLIAMT AND OF THE COUNCIL of 4 July 2018 providing further macro-financial assistance to Ukraine THE EUROPEAN PARLIAMT AND THE COUNCIL

More information

Structure of EU institutions and Europe Aid proposal: An introduction

Structure of EU institutions and Europe Aid proposal: An introduction Multilateral Advocacy for Development of Co-operatives in ASEAN Mr. Santosh Kumar Program Manager Mr. Mohit Dave Research Officer International Co-operative Alliance Asia and Pacific 25-July 2018 Structure

More information

Low proportion of donor missions are co-ordinated. Improve national information systems and plans. Low quality of poverty-related data

Low proportion of donor missions are co-ordinated. Improve national information systems and plans. Low quality of poverty-related data 16 EGYPT INTRODUCTION WITH A POPULATION OF 75 MILLION, Egypt has a gross national income (GNI) of USD 1 350 per person. According to the latest consensus, conducted in 2000, 3% of the population lived

More information

9228/18 SBC/sr 1 DGG 1A

9228/18 SBC/sr 1 DGG 1A Council of the European Union Brussels, 24 May 2018 (OR. en) Interinstitutional File: 2018/0058 (COD) 9228/18 'I' ITEM NOTE From: General Secretariat of the Council ECOFIN 477 CODEC 826 RELEX 443 COEST

More information

EU Code of Conduct on Complementarity and Division of Labour in Development Policy 1

EU Code of Conduct on Complementarity and Division of Labour in Development Policy 1 EU Code of Conduct on Complementarity and Division of Labour in Development Policy 1 This Code of Conduct presents operational principles for EU donors regarding complementarity in development cooperation.

More information

Geographic & Thematic Programming of EU aid

Geographic & Thematic Programming of EU aid Geographic & Thematic Programming of EU aid EU Budget 2014-2020 CONCORD presentation at Policy Forum for Development 18th June 2013 Alexandra Makaroff Chair of the Funding for Development & Relief (FDR)

More information

Guidance for Member States on Performance framework, review and reserve

Guidance for Member States on Performance framework, review and reserve EGESIF_18-0021-01 19/06/2018 Version 12.0 07/01/2015 EUROPEAN COMMISSION European Structural and Investment Funds Guidance for Member States on Performance framework, review and reserve This version was

More information

Introduction

Introduction 2009-06-29 Utrikesdepartementet Action Plan on Aid Effectiveness 2009-2011 Introduction The Paris Declaration on Aid Effectiveness (2005) and the Accra Agenda for Action (AAA, 2008) are in the process

More information

COMMISSION OF THE EUROPEAN COMMUNITIES

COMMISSION OF THE EUROPEAN COMMUNITIES COMMISSION OF THE EUROPEAN COMMUNITIES Brussels, 1.8.2005 COM(2005)354 final COMMUNICATION FROM THE COMMISSION TO THE COUNCIL, THE EUROPEAN PARLIAMENT, THE EUROPEAN ECONOMIC AND SOCIAL COMMITTEE AND THE

More information

ACTION FICHE N 1 FOR THE KYRGYZ REPUBLIC. Total cost: EUR. DAC-code Sector SociaVWelfare Service

ACTION FICHE N 1 FOR THE KYRGYZ REPUBLIC. Total cost: EUR. DAC-code Sector SociaVWelfare Service ACTION FICHE N 1 FOR THE KYRGYZ REPUBLIC 1. IDENTIFICATION Title/Number Total cost Sector Policy Support Programme, Social Protection and PFM - Kyrgyzstan 2007-2009 - Third allocation DCI-ASIE/2009/021-363

More information

The EU's External Investment Plan The new generation instrument for sustainable development

The EU's External Investment Plan The new generation instrument for sustainable development The EU's External Investment Plan The new generation instrument for sustainable development Brussels, 19 January 2018 Filiberto Ceriani Sebregondi, Head of Division, European External Action Service Francesca

More information

CAMBODIA. Cambodia is a low-income country with a gross national income (GNI) of USD 610 per

CAMBODIA. Cambodia is a low-income country with a gross national income (GNI) of USD 610 per 00 CAMBODIA INTRODUCTION Cambodia is a low-income country with a gross national income (GNI) of USD 610 per capita in 2009 (WDI, 2011). It has a population of approximately 15 million and more than a quarter

More information

SERBIA. Support to participation in EU Programmes. Action Summary INSTRUMENT FOR PRE-ACCESSION ASSISTANCE (IPA II)

SERBIA. Support to participation in EU Programmes. Action Summary INSTRUMENT FOR PRE-ACCESSION ASSISTANCE (IPA II) INSTRUMENT FOR PRE-ACCESSION ASSISTANCE (IPA II) 2014-2020 SERBIA Support to participation in EU Programmes Action Summary This Action represents continuation of Serbian participation in EU programmes

More information

Proposal for a COUNCIL REGULATION. establishing an Instrument for Nuclear Safety Cooperation. {SEC(2011) 1472 final} {SEC(2011) 1473 final}

Proposal for a COUNCIL REGULATION. establishing an Instrument for Nuclear Safety Cooperation. {SEC(2011) 1472 final} {SEC(2011) 1473 final} EUROPEAN COMMISSION Brussels, 7.12.2011 COM(2011) 841 final 2011/0414 (NLE) Proposal for a COUNCIL REGULATION establishing an Instrument for Nuclear Safety Cooperation {SEC(2011) 1472 final} {SEC(2011)

More information

1. Preamble. 2. Principles and objectives

1. Preamble. 2. Principles and objectives 1. Preamble 1.1. This Framework Memorandum (FM) contains the understandings of the Government of Ghana (GoG) and the Development Partners which have signed this FM (hereafter called the signatory DPs),

More information

Synthesis of key recommendations and decisions 8 March 2018

Synthesis of key recommendations and decisions 8 March 2018 SDG-Education 2030 Steering Committee Paris, 28 February-2 March 2018 Synthesis of key recommendations and decisions 8 March 2018 This synthesis summarizes the main recommendations and decisions made at

More information

REPORT FROM THE COMMISSION TO THE COUNCIL AND THE EUROPEAN PARLIAMENT

REPORT FROM THE COMMISSION TO THE COUNCIL AND THE EUROPEAN PARLIAMENT EUROPEAN COMMISSION Brussels, 19.9.2016 COM(2016) 600 final REPORT FROM THE COMMISSION TO THE COUNCIL AND THE EUROPEAN PARLIAMENT on the activities of the EU Platform for Blending in External Cooperation

More information

Regulation on the implementation of the European Economic Area (EEA) Financial Mechanism

Regulation on the implementation of the European Economic Area (EEA) Financial Mechanism the European Economic Area (EEA) Financial Mechanism 2014-2021 Adopted by the EEA Financial Mechanism Committee pursuant to Article 10.5 of Protocol 38c to the EEA Agreement on 8 September 2016 and confirmed

More information

SERBIA. Support to participation in Union Programmes INSTRUMENT FOR PRE-ACCESSION ASSISTANCE (IPA II) Action summary

SERBIA. Support to participation in Union Programmes INSTRUMENT FOR PRE-ACCESSION ASSISTANCE (IPA II) Action summary INSTRUMENT FOR PRE-ACCESSION ASSISTANCE (IPA II) 2014-2020 SERBIA Support to participation in Union Programmes Action summary This Action will facilitate Serbian participation in EU programmes by cofinancing

More information

POLAND. AT A GLANCE: Gross bilateral ODA (unless otherwise shown)

POLAND. AT A GLANCE: Gross bilateral ODA (unless otherwise shown) POLAND AT A GLANCE: Gross bilateral ODA 2013 2014 (unless otherwise shown) 1 POLICY FRAMEWORK Poland s development cooperation is guided by the Act on Development Co-operation, approved in September 2011

More information

6315/18 ML/ab 1 DG G 2A

6315/18 ML/ab 1 DG G 2A Council of the European Union Brussels, 20 February 2018 (OR. en) 6315/18 FIN 139 INST 65 OUTCOME OF PROCEEDINGS From: General Secretariat of the Council To: Delegations No. prev. doc.: 5939/18 FIN 90

More information

Action Fiche for Libya

Action Fiche for Libya Action Fiche for Libya 1. IDENTIFICATION Title/Number Total cost Aid method / Method of implementation Public administration capacity-building facility (ENPI/2011/276-708) EU contribution: EUR 4.5 million

More information

72 ND REGULAR MEETING OF THE COMMITTEE OF PERMANENT REPRESENTATIVES TO UNITED NATIONS HUMAN SETTLEMENTS PROGRAMME 10 APRIL 2019

72 ND REGULAR MEETING OF THE COMMITTEE OF PERMANENT REPRESENTATIVES TO UNITED NATIONS HUMAN SETTLEMENTS PROGRAMME 10 APRIL 2019 72 ND REGULAR MEETING OF THE COMMITTEE OF PERMANENT REPRESENTATIVES TO UNITED NATIONS HUMAN SETTLEMENTS PROGRAMME 10 APRIL 2019 Agenda Item 8 Thematic / Country Presentation Working with the European Union

More information

Programming Aid Instruments

Programming Aid Instruments Programming Aid Instruments 2014-2020 Techni Policy Forum for Development 18 June 2013 Introduction Outline of presentation Policy Initiatives Implementing the principles of Agenda for Change Programming

More information

TOSSD AND TYPES OF AID INVOLVING NO CROSS-BORDER RESOURCE FLOWS

TOSSD AND TYPES OF AID INVOLVING NO CROSS-BORDER RESOURCE FLOWS Organisation for Economic Co-operation and Development Development Co-operation Directorate Development Assistance Committee DCD/DAC/STAT(2018)20 English text only 26 March 2018 DAC Working Party on Development

More information

GUIDELINES FOR STRATEGIES IN SWEDISH DEVELOPMENT COOPERATION AND HUMANITARIAN ASSISTANCE

GUIDELINES FOR STRATEGIES IN SWEDISH DEVELOPMENT COOPERATION AND HUMANITARIAN ASSISTANCE GUIDELINES FOR STRATEGIES IN SWEDISH DEVELOPMENT COOPERATION AND HUMANITARIAN ASSISTANCE Annex to Government Decision 21 December 2017 (UD2017/21053/IU) Guidelines for strategies in Swedish development

More information

Coherence Report Insights from the External Evaluation of the External Financing Instruments Final Report - Annexes July 2017

Coherence Report Insights from the External Evaluation of the External Financing Instruments Final Report - Annexes July 2017 Coherence Report Insights from the External Evaluation of the External Financing Instruments Final Report - Annexes July 2017 International Co-operation and Development Lead company Consortium composed

More information

«FICHE CONTRADICTOIRE» Joint Country Level Evaluation of Bangladesh. (*For details on the recommendations please refer to the main report)

«FICHE CONTRADICTOIRE» Joint Country Level Evaluation of Bangladesh. (*For details on the recommendations please refer to the main report) Ref. Ares(2016)5406779-16/09/2016 «FICHE CONTRADICTOIRE» Joint Country Level Evaluation of Bangladesh (*For details on the recommendations please refer to the main report) Recommendations Response of Commission

More information

SURVEY GUIDANCE CONTENTS Survey on Monitoring the Paris Declaration Fourth High Level Forum on Aid Effectiveness

SURVEY GUIDANCE CONTENTS Survey on Monitoring the Paris Declaration Fourth High Level Forum on Aid Effectiveness SURVEY GUIDANCE 2011 Survey on Monitoring the Paris Declaration Fourth High Level Forum on Aid Effectiveness This document explains the objectives, process and methodology agreed for the 2011 Survey on

More information

Summary of Findings, Recommendations and Lessons Learnt. 1st Meeting of the Programme Steering Committee. Chisinau, Moldova September 28 29, 2012

Summary of Findings, Recommendations and Lessons Learnt. 1st Meeting of the Programme Steering Committee. Chisinau, Moldova September 28 29, 2012 Improving capacities to eliminate and prevent recurrence of obsolete pesticides as a model for tackling unused hazardous chemicals in the former Soviet Union Summary of Findings, Recommendations and Lessons

More information

OPINION. EN United in diversity EN 2014/0121(COD) of the Committee on Economic and Monetary Affairs. for the Committee on Legal Affairs

OPINION. EN United in diversity EN 2014/0121(COD) of the Committee on Economic and Monetary Affairs. for the Committee on Legal Affairs EUROPEAN PARLIAMT 2014-2019 Committee on Economic and Monetary Affairs 2014/0121(COD) 2.3.2015 OPINION of the Committee on Economic and Monetary Affairs for the Committee on Legal Affairs on the proposal

More information

The 2030 Agenda for Sustainable Development and the new European Consensus on Development

The 2030 Agenda for Sustainable Development and the new European Consensus on Development The 2030 Agenda for Sustainable Development and the new European Consensus on Development Martin HEATHER Policy Officer, European Commission s Directorate-General for International Cooperation and Development

More information

EU Development Cooperation and its. Funding programmes

EU Development Cooperation and its. Funding programmes EU Development Cooperation and its Funding programmes 2014-2020 1 1.1. EU Committments for Dev Co 2.2. International framework 3.3. Funding programmes 4.4. Procedures 2 1. 1. Lisbon Treaty Art 21 External

More information

EU FUNDING PROGRAMMES IN THE FIELD OF DEVELOPMENT AID

EU FUNDING PROGRAMMES IN THE FIELD OF DEVELOPMENT AID EU FUNDING PROGRAMMES IN THE FIELD OF DEVELOPMENT AID EU FORDERUNG FUR MIGRANTEN ORGANISATIONEN UND TRAGER DER PARTICIPATIONS UND INTEGRATIONS ARBEIT IN BERLIN MOVE GLOBAL 25 October 2014, Berlin About

More information

CONCORD, the European NGO Confederation for Relief and Development, is seeking a:

CONCORD, the European NGO Confederation for Relief and Development, is seeking a: CONCORD, the European NGO Confederation for Relief and Development, is seeking a: CONSULTANT TO PRODUCE A PUBLICATION ON THE ENGAGEMENT OF EU DELEGATIONS WITH CSOs CONCORD is the European Confederation

More information

WORKING DOCUMENT. EN United in diversity EN on the review of the European Neighbourhood policy. Committee on Foreign Affairs

WORKING DOCUMENT. EN United in diversity EN on the review of the European Neighbourhood policy. Committee on Foreign Affairs EUROPEAN PARLIAMT 2014-2019 Committee on Foreign Affairs 31.3.2015 WORKING DOCUMT on the review of the European Neighbourhood policy Committee on Foreign Affairs Rapporteur: Eduard Kukan DT\1055258.doc

More information

Marche Region. Ex Ante Evaluation report. Executive summary. Roma, June 2015

Marche Region. Ex Ante Evaluation report. Executive summary. Roma, June 2015 Marche Region 2014-2020 COMMITTENTE RDP for Marche Ex Ante Evaluation report Roma, June 2015 Executive summary EXECUTIVE SUMMARY Introduction The Ex Ante Evaluation (EAE) of the Rural Development Programme

More information

Office of the Auditor General of Norway. Handbook for the Office of the Auditor General s Development Cooperation

Office of the Auditor General of Norway. Handbook for the Office of the Auditor General s Development Cooperation Office of the Auditor General of Norway Handbook for the Office of the Auditor General s Development Cooperation i Photo: The Office of the Auditor General of Norway Illustration: Lobo Media AS March 2009

More information

Moldova. Moldova is a lower-middle income country with a GNI of USD per capita (2009)

Moldova. Moldova is a lower-middle income country with a GNI of USD per capita (2009) 00 INTRODUCTION is a lower-middle income country with a GNI of USD 1 560 per capita (2009) which has grown at an average rate of 5.2% per annum since 2005 (WDI, 2011). It has a population of 3.6 million

More information

2 nd INDEPENDENT EXTERNAL EVALUATION of the EUROPEAN UNION AGENCY FOR FUNDAMENTAL RIGHTS (FRA)

2 nd INDEPENDENT EXTERNAL EVALUATION of the EUROPEAN UNION AGENCY FOR FUNDAMENTAL RIGHTS (FRA) 2 nd INDEPENDENT EXTERNAL EVALUATION of the EUROPEAN UNION AGENCY FOR FUNDAMENTAL RIGHTS (FRA) TECHNICAL SPECIFICATIONS 15 July 2016 1 1) Title of the contract The title of the contract is 2nd External

More information

WORKING DOCUMENT. EN United in diversity EN. European Parliament

WORKING DOCUMENT. EN United in diversity EN. European Parliament European Parliament 2014-2019 Committee on Budgetary Control 24.4.2017 WORKING DOCUMT on ECA Special Report 5/2017 (2016 Discharge): Youth unemployment - have EU policies made a difference? An assessment

More information

Donors engagement: Supporting education in fragile and conflictaffected

Donors engagement: Supporting education in fragile and conflictaffected 2009 Donors engagement: Supporting education in fragile and conflictaffected states Overview to encourage greater engagement in education in fragile and conflictaffected states. This policy brief puts

More information