1 International Science Programme (ISP) Uppsala University Revised Jan 2019 Annex 1. ISP Guidelines for financial administration Reporting, audit, procurement, revised budget and requests Contents Requests of funds... 2 Release of new allocation... 2 Revised budget... 2 Local funds... 3 Financial reporting, local funds... 4 Audit... 5 Procurement... 6 Visits and travels... 6 Templates and documents... 6 Dates and Deadlines... 7

2 Requests of funds The project/network leader manages the ISP allocation of the project/network. A deputy project leader could also manage the funds if agreed with ISP. 1. Any costs charged to the project shall be approved by the responsible project or network leader. The project leader must therefore approve/sanction the expenditure by sending a request of funds by to the Program Director at ISP. 2. The request shall clearly specify the purpose of the payment and contain the necessary bank details. IBAN, SWIFT, bank, payee = account holder. The project is responsible for supplying correct information and any problem that would arise from sending inaccurate payment details to ISP. 3. Usage of private accounts and funds must be avoided. Local funds at the university account should be used for these costs or alternatively, ISP can make direct payments against a pro forma invoice or an invoice. If reimbursement is necessary it should be done from the local university s ISP account. Release of new allocation 1. New requests of transfer for local use will only be considered when at least 70% of the transferred funds have been used. (Exceptions may be granted in well-justified cases). 2. Before approval of the Statement of Accounts of the previous year and the Revised Budget for the present year by ISP, requests for transfer for local use of any previously approved amount carried forward from the last previous year at the ISP account + up to 20% of the present year s allocation. 3. All requests should agree with the Revised Budget. If they do not, new approval by ISP must be sought and granted before requested funds are transferred. 4. Any errors and deviation in the Statement of Accounts and the Revised Budget must be investigated and clarified before ISP executes transfer of funds in the present fiscal year. Revised budget The research group/network submits a budget for the project in connection with the grant application that is evaluated by the reference group. If ISP funding is approved, a new revised budget must be prepared annually and submitted to ISP 28 February as latest. 1. The balance carried forward from the previous year on the local account shall be inserted in the proper place in the Revised Budget for the present fiscal year, expressed in SEK at an exchange rate given at at the day of budget revision. A pdf-printout of the webpage must verify the currency conversion figure, and be appended to the Revised Budget. 2. Any funds held at the account at ISP approved to be carried forward to the present year, as given by the yearly summary of funding and expenditure provided by ISP, must also be inserted in the Revised Budget form. 3. Finally, the allocation for the present year, according to agreement (and also given by the 2

3 yearly summary of funding and expenditure provided by ISP), must be inserted in the proper place in the Revised Budget form. 4. The total budget for the present year amounts to [any carry over at the local account from the previous year + [any carry over at the account held at ISP from the previous fiscal year] + [the present year s allocation]. 5. The total budget is the basis for the revised budget. The budget lines must be revised, to add to the figure obtained in The Revised Budget is allowed to contain new budget lines in relation to the original budget. However, all budget lines should be clearly justified in an appended document. 7. In case of a new period of funding or newly started activities, the budget revision must consider and take into account all recommendations communicated from the application assessment by the Scientific Reference Group in the previous year. ISP should be informed in writing how the recommendations are addressed. Local funds If funds are transferred to the local organization of the supported activity and managed by the research group/network, they are considered as local funds and are accounted for separately by the project. Direct payments made by ISP to pay invoices etc. are accounted for by ISP and are subject to an annual external audit. The University/institution creates a specific account at the institution to account for the ISP funds and expenditures separately from other sources of income and costs from other projects. Exclusively the project leader manages the account. Eligible costs Eligible costs are incurred during the implementation of the project; they are identifiable, verifiable and determined according to the applicable accounting standards and according to the partner s standard accounting practices. Any payment/reimbursement is for the actual cost that is verified by supporting documentation such as an invoice or receipt. An approved budget is not a verification of an actual cost. The expenditure items shall follow the approved revised budget under planned activities or the specification made in the request of funds made by the project leader. For transferred funds to the local account, the aggregated specification of costs in the request will serve as budget in the statement of account for local funds. Budget modifications are allowed only if approved by ISP. Expenditures incurred and not aligned with the approved budget is considered as ineligible. Any remuneration costs must be approved by ISP and verified by supporting documentation. The costs must be justified, reasonable and comply with sound financial management. Items financed by another organization, travel costs in business or first class, extra allowances such as sitting allowances, are not considered eligible costs. Indirect costs are eligible if they are in accordance with a general and documented decision by the authority and approved by ISP. 3

4 Financial reporting, local funds The Statement of Accounts of local funds for the year, added with any audit or other report or specification, should be submitted to ISP before the given deadline the present year, and is to be reviewed by an assigned ISP financial administrator and approved by the responsible program director before transfer of funds following a new request can be executed, subject to exceptions and conditions under section C. New Requests. Date of submission The report should be submitted to ISP 31 of March Period The accounting period for the annual report is from the 1 January to 31 December. Identification of Statement of Account The name given by ISP to the project shall be stated as for example IPICS LAO 01, IPMS EAUMP TAN etc. Balance brought forward The balance brought forward from the previous year, as given in the corresponding Statement of Accounts pertaining to that year. Funds, income All transfers received from ISP during the year, as separate lines. If applicable, with the actual exchange rates stated. Expenditure categories for compilation of the statement of accounts for local ISP funds. Only expenditure incurred during the year, aggregated to categories as separate lines. The expenditures should be traceable by verifications (kept locally). Equipment Specify the purchased equipment. Documented by invoices and purchase detail. Chemicals Documented by invoice, receipt. Travel Travel costs for conferences etc., includes such daily allowance, airfare, accommodation. Specify the purpose of the travel Number of days abroad The subsistence allowance Documented by activity report and receipt. PhD student Allowances Specify the name of student and amount received. Documented by receipt. Master Student allowances Specify the name of student and amount received. Documented by receipt Local meeting/workshops All costs for organizing meetings/workshops. Documented by attendance list, invoice, receipts 4

5 Other Costs For costs that cannot be classified in any of the categories above. To be specified if more than 500 USD. Documented by inovoice or receipt. Administration of Project Network leader remuneration etc. Includes all travel costs in association with project administration, such as daily allowance, airfare, hotel etc., for example when attending reference group meeting. Documented by invoices, receipts. Indirect costs Research groups may budget department/faculty overhead costs on ISP funds requested for local use given: - that the overhead has been previously decided and documented by the appropriate institutional body (department/faculty board, or at higher university governing level), and is applied equally to all grants received. (The percentage should be indicated and which kinds of costs are covered, as well as information about at which administrative level the percentage has been decided.) - that the first request to ISP each budget year for transfer of funds for local use should be appended with a copy of this decision. Per diems, daily allowance. Participants in ISP activities are entitled to a daily allowance when they travel abroad. The allowance is USD 50 per day excluding hotel. 10 USD per day if accommodation and meals are pre-paid or covered by ISP. Documented by receipt. Interest Any incurred interest to the project shall be verified by supporting documentation and the interest rate indicated. Budget A column for the budgeted costs is inserted next to the expenditure column. If the whole allocation is transferred to the local account, the revised budget for the year will serve as the budget. If the allocation is in part transferred to the local account, the specification(s) of costs in the request(s) is/are used as the approved budget. If the expenditures deviate from budget >25% it should be addressed in the comments section. Signatures The Statement of Accounts must be signed by the accountable leader/coordinator of the activity and the financially accountable institutional officer at the appropriate administrative level in the leader s/coordinator s organization. Audit Activities receiving transfers from ISP for local use exceeding 284,000 SEK in a year or accumulated during the agreement period shall be subject to external audit with respect to this/those years. However, ISP also has the right to request that an audit of a supported partner is performed even in 5

6 cases where this limit is not reached. The auditor shall be external, perform and report the audit according to the Terms of Reference for audit that ISP makes available. The project leader must respond to any findings reported by the auditor in a Management Response that is submitted to the programme director together with the audit report, no later than 31 March each year. For the terms of reference for audit of local costs, see the document Annex 2, Procurement When purchasing equipment, Sida procurement guidelines must be followed (available on request). In brief: -Purchases worth 300,000 and above must be accomplished by means of an international open tender procedure following publication of a procurement notice. -Purchases worth 100, ,000 are accomplished by means of an open tender procedure published locally. -Purchases worth 60, ,000 must be accomplished by means of a competitive negotiated procedure without publication, in which at least three suppliers are consulted and the terms of the contract is negotiated with one or more of them. -Purchases worth 60,000 or less should follow local regulations, or Uppsala university rules should apply, implying that the selection of supplier should be documented for purchases worth 10,000 60,000. Visits and travels Before a sandwich study period is commenced, the project leader must send a request to ISP to administer the stay with the project s allocation. The sandwich student fills the fellowship form and send it as a pdf to the program director and the administrator of the program. ISP will provide the visitors in Sweden with insurance, accommodation and a monthly allowance of SEK ( SEK for post doc). ISP can also arrange for the travel. Templates and documents The templates and documents for ISP direct support program are available at 6

7 Dates and Deadlines The latest dates to submit report and requests to ISP are as follows: Yearly revised budget Activity report Statements of Accounts (if audit is not required) Audit report and management response Request to carry over funds to the next fiscal year Request for payments and transfer of funds YY0228 YY0228 YY0228 YY0331 YY1120 YY1210 7

UKF Project Monitoring Guidelines Version 4

UKF Project Monitoring Guidelines Version 4 REPUBLIC OF CROATIA MINISTRY OF SCIENCE, EDUCATION AND SPORTS UKF Project Monitoring Guidelines Version 4 UNITY THROUGH KNOWLEDGE FUND office@ukf.hr, www.ukf.hr, +385 1 2352 685 Planinska 1, HR-10000 Zagreb,

More information

GUIDING PRINCIPLES FOR BUDGET MAKING IN PHASE 2 WINDOW 1

GUIDING PRINCIPLES FOR BUDGET MAKING IN PHASE 2 WINDOW 1 GUIDING PRINCIPLES FOR BUDGET MAKING IN PHASE 2 WINDOW 1 Phase 1 For the purposes of a Phase 1 application, an estimate of the grant applied for is expected for an amount not exceeding 12 million DKK for

More information

FINANCIAL GUIDELINES AND STANDARDS FOR EVENT MANAGEMENT

FINANCIAL GUIDELINES AND STANDARDS FOR EVENT MANAGEMENT ANNEX 2 FINANCIAL GUIDELINES AND STANDARDS FOR EVENT MANAGEMENT (to be fine-tuned upon contract signature) 2 INDEX Page 1. FOREWORDS. 5 2. GENERAL PRINCIPLES.. 5 3. BUDGET MANAGEMENT WORKFLOW 5 3.1 PRE-EVENT

More information

FAQ. Questions and answers relating to the 2014 call for proposals for NGO operating grants for funding in 2015 (Latest update September 2014)

FAQ. Questions and answers relating to the 2014 call for proposals for NGO operating grants for funding in 2015 (Latest update September 2014) FAQ Questions and answers relating to the 2014 call for proposals for NGO operating grants for funding in 2015 (Latest update September 2014) CORRIGENDUM: In the first version of the Application Guide,

More information

ADMINISTRATIVE MANUAL FOR PROJECT IMPLEMENTATION

ADMINISTRATIVE MANUAL FOR PROJECT IMPLEMENTATION ADMINISTRATIVE MANUAL FOR PROJECT IMPLEMENTATION 1. Introduction The purpose of this manual is to give guidance and instructions to Project Developers (PD) on administration of the project implementation

More information

GUIDELINES FOR CCM FUNDING

GUIDELINES FOR CCM FUNDING GUIDELINES FOR CCM FUNDING Overview 1. In recognition of the important role of Country Coordinating Mechanisms 1 ( CCMs ) in the Global Fund architecture (including their central role in proposal development,

More information

Important Messages - Grants

Important Messages - Grants GRANT IMPORTANT MESSAGES Important Messages - Grants SCOPE Important messages contain: 1) procedural rules ( procedure ) e.g. interpretation of the PRAG or internal procedures etc. 2) recommendations e.g.

More information

or institution which in turn is a member of the International Federation of Accountants (IFAC).

or institution which in turn is a member of the International Federation of Accountants (IFAC). Terms of Reference for an Expenditure Verification of a Grant Contract for Estonia - Latvia- Russia Cross Border Cooperation Programme within the European Neighbourhood and Partnership Instrument 2007-2013

More information

The Marie Curie Actions FP7 Financial Guidelines

The Marie Curie Actions FP7 Financial Guidelines The Marie Curie Actions FP7 Financial Guidelines SPECIFIC PROVISIONS RELATED TO MARIE CURIE ACTIONS FINANCED UNDER THE FP7 "PEOPLE" PROGRAMME Part 3: Projects funded in the PEOPLE Work Programmes calls

More information

TERMS OF REFERENCE FOR AN EXPENDITURE VERIFICATION OF A GRANT CONTRACT - EXTERNAL ACTION OF THE EUROPEAN UNION -

TERMS OF REFERENCE FOR AN EXPENDITURE VERIFICATION OF A GRANT CONTRACT - EXTERNAL ACTION OF THE EUROPEAN UNION - TERMS OF REFERENCE FOR AN EXPENDITURE VERIFICATION OF A GRANT CONTRACT - EXTERNAL ACTION OF THE EUROPEAN UNION - HOW TO USE THIS TERMS OF REFERENCE MODEL? All text highlighted in yellow in this ToR model

More information

Danida Fellowship Centre January 2016

Danida Fellowship Centre January 2016 Danida Fellowship Centre January 2016 General Conditions for Grants to Development Research Supported through Denmark s International Development Cooperation Contents: Introduction... 4 1. Ethical and

More information

JITS funding guide. JITS Network Secretariat. 08 January Version 3

JITS funding guide. JITS Network Secretariat. 08 January Version 3 JITS funding guide JITS Network Secretariat 08 January 2018 Version 3 Table of Contents I. Background... 2 II. Scope and conditions... 2 II.1. Travel and accommodation... 4 II.2. Interpretation and translation...

More information

Creative Europe Sub-programme Culture Financial management

Creative Europe Sub-programme Culture Financial management Creative Europe Sub-programme Culture Financial management 10 November 2014 Sandra Delespesse & Maria-Paz Benito 1 Content Financial tasks Eligibility of costs Important documents Checks, audit and evaluation

More information

GUIDE FOR THE REIMBURSEMENT OF TRAVEL AND ACCOMMODATION EXPENSES AND PAYMENT OF SUBSISTENCE ALLOWANCES

GUIDE FOR THE REIMBURSEMENT OF TRAVEL AND ACCOMMODATION EXPENSES AND PAYMENT OF SUBSISTENCE ALLOWANCES Helsinki, 29 September 2009 Doc: MB/59/2009 final GUIDE FOR THE REIMBURSEMENT OF TRAVEL AND ACCOMMODATION EXPENSES AND PAYMENT OF SUBSISTENCE ALLOWANCES to Management Board members, Committee and Forum

More information

Preparing your CanExport claim. The Canadian Trade Commissioner Service Le Service des délégués commerciaux du Canada

Preparing your CanExport claim. The Canadian Trade Commissioner Service Le Service des délégués commerciaux du Canada Preparing your CanExport claim The Canadian Trade Commissioner Service Le Service des délégués commerciaux du Canada Before You Begin Refer to the Applicant Guide for information on eligible and ineligible

More information

Danida Fellowship Centre February

Danida Fellowship Centre February Danida Fellowship Centre February 2017-1 General Conditions for Grants to Development Research Supported through Denmark s International Development Cooperation Content: Introduction... 4 1. Ethical and

More information

ALLEGATO A ANNEX VII Special Conditions Grant Contract Expenditure Verification

ALLEGATO A ANNEX VII Special Conditions Grant Contract Expenditure Verification ALLEGATO A ANNEX VII Special Conditions Grant Contract Expenditure Verification TERMS OF REFERENCE FOR AN EXPENDITURE VERIFICATION OF A GRANT CONTRACT - EXTERNAL ACTIONS OF THE EUROPEAN COMMUNITY - ANNEX

More information

EA-1/20 S1 A-AB: 2016

EA-1/20 S1 A-AB: 2016 Publication Reference EA-1/20 S1 A-AB: 2016 Supplement 1 to EA-1/20 A Procedure for Control of Expenditures and Preparation of Budgets Terms and Conditions for Financial Compensation from the Operating

More information

Model terms of reference for the certificate on the financial statements

Model terms of reference for the certificate on the financial statements Model terms of reference for the certificate on the financial statements Terms of erence for an Independent Report of Factual Findings on costs declared under a Grant Agreement financed under the Call

More information

TERMS OF REFERENCE FOR PROJECT ANNUAL EXTERNAL AUDIT

TERMS OF REFERENCE FOR PROJECT ANNUAL EXTERNAL AUDIT TERMS OF REFERENCE FOR PROJECT ANNUAL EXTERNAL AUDIT I. INTRODUCTION Marie Stopes International Afghanistan, MSIA, wishes to engage the services of an audit firm, the Auditor, for the purpose of auditing

More information

GUIDE FOR PROJECT IMPLEMENTATION

GUIDE FOR PROJECT IMPLEMENTATION GUIDE FOR PROJECT IMPLEMENTATION PRACTICAL GUIDANCE FOR PROJECT PARTNERS Version 5.0 (15.1.2019) Contents 1. Introduction... 3 2. Starting up the project... 4 2.1. Fulfilling conditions... 5 2.2. Hand

More information

Annex VI. Model terms of reference for the Certificate on the Financial Statements

Annex VI. Model terms of reference for the Certificate on the Financial Statements Annex VI Pielikums Nr.2 Model terms of reference for the Certificate on the Financial Statements 1. Audit objectives The certificate on the financial statements and underlying accounts, produced by an

More information

Amendment Request Form National Authorities for Apprenticeships

Amendment Request Form National Authorities for Apprenticeships Executive Agency, Education Audiovisual and Culture ERASMUS + PROGRAMME Amendment Request Form National Authorities for Apprenticeships Agreement number: Proposal number: Title: Coordinator: DECLARATION

More information

PROJECT IMPLEMENTATION DOCUMENT NO.2 REPORTING TEMPLATES & E-TOOL

PROJECT IMPLEMENTATION DOCUMENT NO.2 REPORTING TEMPLATES & E-TOOL Establishing the European Geological Surveys Research Area to deliver a Geological Service for Europe PROJECT IMPLEMENTATION DOCUMENT NO.2 REPORTING TEMPLATES & E-TOOL Joint Call on applied geoscience

More information

Financial workshop. Creative Europe - Culture 10 October 2018

Financial workshop. Creative Europe - Culture 10 October 2018 Financial workshop Creative Europe - Culture 10 October 2018 OBJECTIVES of workshop Awareness and clarification about key financial issues Recommendations on the financial management Preparation of the

More information

Producer Organisation Scheme

Producer Organisation Scheme EMFF Operational Programme 2014-2020 Producer Organisation Scheme 2014-15 EUROPEAN UNION This measure is part-financed by the European Maritime and Fisheries Fund Ireland s EU Structural and Investment

More information

A guide of financial procedures for DPES researchers, staff and students

A guide of financial procedures for DPES researchers, staff and students A guide of financial procedures for DPES researchers, staff and students The following document is a summary of selected financial policies and procedures of the University of Toronto and will be updated

More information

Funding for companies research and development operations Eligible costs and project monitoring

Funding for companies research and development operations Eligible costs and project monitoring Funding for companies research and development operations Eligible costs and project monitoring Funding terms and conditions: Funding for companies R&D activities 23 November 2017 Copyright Tekes Accountable

More information

Version: 14 June, IKI Guidelines for international applicants

Version: 14 June, IKI Guidelines for international applicants Version: 14 June, 2017 IKI Guidelines for international applicants Table of Contents A. General Information about the International Climate Initiative... 4 B. Project Outline... 4 B.1 Applicants... 4 B.2

More information

ANNEX III FINANCIAL AND CONTRACTUAL RULES I. RULES APPLICABLE TO BUDGET CATEGORIES BASED ON UNIT CONTRIBUTIONS

ANNEX III FINANCIAL AND CONTRACTUAL RULES I. RULES APPLICABLE TO BUDGET CATEGORIES BASED ON UNIT CONTRIBUTIONS ANNEX III FINANCIAL AND CONTRACTUAL RULES KEY ACTION 2 SCHOOL EXCHANGE PARTNERSHIPS [KA229] I. RULES APPLICABLE TO BUDGET CATEGORIES BASED ON UNIT CONTRIBUTIONS I.1 Conditions for eligibility of unit contributions

More information

Eligibility of costs in the Horizon 2020 funded EUROfusion project

Eligibility of costs in the Horizon 2020 funded EUROfusion project Eligibility of costs in the Horizon 2020 funded EUROfusion project Garching, 3 December 2015 Other Direct Costs: Travel,, Other Goods & Services Presented by: Melanie John, EUROfusion Coordinator Unit,

More information

FINANCIAL GUIDELINES. TEAM-SI-JOINT Call Brussels, 19 March 2018

FINANCIAL GUIDELINES. TEAM-SI-JOINT Call Brussels, 19 March 2018 FINANCIAL GUIDELINES TEAM-SI-JOINT Call 2019 Brussels, 19 March 2018 Budget lines A. Investment costs B. Operational costs C. Personnel costs D. Scholarship costs E. Coordination costs See Annex 3 budget

More information

Specific Agreement on Research Collaboration between Sweden and Makerere University during the period 3 November June 2020

Specific Agreement on Research Collaboration between Sweden and Makerere University during the period 3 November June 2020 Specific Agreement on Research Collaboration between Sweden and Makerere University during the period 3 November 2015 30 June 2020 between The Uganda state owned Makerere University ( Mak ) and The Swedish

More information

Guide for Applicants

Guide for Applicants EUROPEAN COMMISSION EUROSTAT Guide for Applicants Eurostat Grants Version 4.0 11 January 2018 1/55 IMPORTANT NOTICE The Guide for Applicants is a user guide that aims to explain to applicants and beneficiaries

More information

Community Partnerships Program Eligible Costing Rules and Financial Management Guidelines

Community Partnerships Program Eligible Costing Rules and Financial Management Guidelines Community Partnerships Program Eligible Costing Rules and Financial Management Guidelines Top tips when preparing your budget... 2 What are eligible costs?... 3 I. Personnel, Payroll and other Compensation...

More information

GUIDE FOR THE REIMBURSEMENT OF TRAVEL AND ACCOMMODATION EXPENSES AND PAYMENT OF SUBSISTENCE ALLOWANCES

GUIDE FOR THE REIMBURSEMENT OF TRAVEL AND ACCOMMODATION EXPENSES AND PAYMENT OF SUBSISTENCE ALLOWANCES GUIDE FOR THE REIMBURSEMENT OF TRAVEL AND ACCOMMODATION EXPENSES AND PAYMENT OF SUBSISTENCE ALLOWANCES to Management Board members, Committee and Forum members and other participants invited to attend

More information

LIFE Grant Agreement Financial Aspects Highlights

LIFE Grant Agreement Financial Aspects Highlights LIFE Grant Agreement Financial Aspects Highlights Kick-off Meetings Call 2016 Action Grants Strand buddies (EASME) Congratulations for obtaining the Grant! And Welcome to the Finance presentation SUMMARY

More information

B. NON-ELIGIBLE COSTS If the implementation of the action includeds non-eligible costs, please detail them here.

B. NON-ELIGIBLE COSTS If the implementation of the action includeds non-eligible costs, please detail them here. INSTRUCTIONS: The framework partnership agreement and the grant agreement constitute the legal basis for the grant, please read them carefully. For costs not incurred in euros, the monthly exchange rate

More information

PROJECT IMPLEMENTATION DOCUMENT NO.1 REPORTING PROCEDURES AND MONITORING INDICATORS

PROJECT IMPLEMENTATION DOCUMENT NO.1 REPORTING PROCEDURES AND MONITORING INDICATORS Establishing the European Geological Surveys Research Area to deliver a Geological Service for Europe PROJECT IMPLEMENTATION DOCUMENT NO.1 REPORTING PROCEDURES AND MONITORING INDICATORS Joint Call on applied

More information

1.12 Date of budget revision submission: Enter the month and year the budget revision was submitted for approval Prepared by: Enter the name of

1.12 Date of budget revision submission: Enter the month and year the budget revision was submitted for approval Prepared by: Enter the name of Instructions for completion of budget template A guide and toolkit on project budgeting and cost allocation This guide contains a budget template to help organisations calculate the full cost of a particular

More information

Eligible Costing Rules and Financial Management Guidelines

Eligible Costing Rules and Financial Management Guidelines TOP TIPS Alberta Wildfires 2016: Community Organization Partnerships Program Eligible Costing Rules and Financial Management Guidelines WHEN PREPARING YOUR BUDGET For each Budget Category a non-exhaustive

More information

Revised 1 Guidance Note on Financial Engineering Instruments under Article 44 of Council Regulation (EC) No 1083/2006

Revised 1 Guidance Note on Financial Engineering Instruments under Article 44 of Council Regulation (EC) No 1083/2006 REVISED VERSION 08/02/2012 COCOF_10-0014-05-EN EUROPEAN COMMISSION DIRECTORATE-GENERAL REGIONAL POLICY Revised 1 Guidance Note on Financial Engineering Instruments under Article 44 of Council Regulation

More information

GUIDELINES FOR FINANCIAL REPORTING

GUIDELINES FOR FINANCIAL REPORTING GUIDELINES FOR FINANCIAL REPORTING FOR PROJECTS FUNDED BY THE OLOF PALME INTERNATIONAL CENTER Revised 2017-11-07 1. FORMS AND TEMPLATES FOR THE REPORTING... 3 2. DEPOSITING OF FUNDS... 4 3. INTEREST...

More information

Certification of Financial Statements for ICT PSP projects

Certification of Financial Statements for ICT PSP projects DG INFORMATION SOCIETY AND MEDIA ICT Policy Support Programme Competitiveness and Innovation Framework Programme Certification of Financial Statements for ICT PSP projects Version 1.0 (03-03-2008) Certification

More information

South East Europe (SEE) SEE Control Guidelines

South East Europe (SEE) SEE Control Guidelines South East Europe (SEE) SEE Control Guidelines Version 1.4. Final version approved by the MC 10 th June 2009 1 st amendment to be approved by MC (2.0) 1 CONTENTS 1 Purpose and content of the SEE Control

More information

Coordinators' day on ICT PSP project management Financial Issues, Reporting, payments, cost claims and Certification Modalities

Coordinators' day on ICT PSP project management Financial Issues, Reporting, payments, cost claims and Certification Modalities Coordinators' day on ICT PSP project management Financial Issues, Reporting, payments, cost claims and Certification Modalities Ann Van Menxel DG CNECT H6 Brussels, 17 December 2013 Legal references Reimbursement

More information

Financial Reporting. Tempus IV. Kyiv-Mohyla Academy Kiev 16 November Ana Ramon de la Cruz and Giulia Moro

Financial Reporting. Tempus IV. Kyiv-Mohyla Academy Kiev 16 November Ana Ramon de la Cruz and Giulia Moro Financial Reporting Tempus IV Kyiv-Mohyla Academy Kiev 16 November 2016 Ana Ramon de la Cruz and Giulia Moro 1 1. General principles Exchange rate Co-financing Transfer of money 2. Budget headings (purpose,

More information

Multi-Beneficiary Model Grant Agreement

Multi-Beneficiary Model Grant Agreement H2020 Programme Multi-Beneficiary Model Grant Agreement Pre-Commercial Procurement (PCP) and Procurement of Innovative Solutions (PPI) (H2020 MGA PCP/PPI Multi) Version 5.0 18 October 2017 Disclaimer This

More information

Yellow cells denote information required to be entered. Grey cells denote no information should be entered.

Yellow cells denote information required to be entered. Grey cells denote no information should be entered. A guide and toolkit on project budgeting and cost allocation This guide contains a budget template to help organisations calculate the full cost of a particular project or service, including an appropriate

More information

Project Administration

Project Administration Co-funded by the European Union Project Administration Maria Grazia Bonanomi, UCSC Diverse Kick-off meeting - Milan, 22-24 January 2014 Outline: - Context - Key features - Final Reporting Package - Eligible

More information

PROJECT IMPLEMENTATION DOCUMENT NO.1 REPORTING PROCEDURES AND MONITORING INDICATORS

PROJECT IMPLEMENTATION DOCUMENT NO.1 REPORTING PROCEDURES AND MONITORING INDICATORS Establishing the European Geological Surveys Research Area to deliver a Geological Service for Europe PROJECT IMPLEMENTATION DOCUMENT NO.1 REPORTING PROCEDURES AND MONITORING INDICATORS Joint Call on applied

More information

GUIDELINES FOR APPLICANTS FOR EU FUNDING OF PLANT HEALTH EMERGENCY MEASURES

GUIDELINES FOR APPLICANTS FOR EU FUNDING OF PLANT HEALTH EMERGENCY MEASURES EUROPEAN COMMISSION DIRECTORATE-GENERAL FOR HEALTH AND FOOD SAFETY Food chain: Stakeholders and International Relations Food Safety Programmes, Emergency Funding SANTE/10527/2016/Rev 2, GUIDELINES FOR

More information

Rules concerning gifts and hospitality at Stockholm University

Rules concerning gifts and hospitality at Stockholm University 1 (6) DECISION 2017-11-09 Dnr SU FV 1.1.6-0419-16 Helena Linnell Ulf Nyman Strategic Planning and Vice-Chancellor s Office Rules concerning gifts and hospitality at Stockholm University 1. Initial starting

More information

B. NON-ELIGIBLE COSTS If the implementation of the action includeds non-eligible costs, please detail them here.

B. NON-ELIGIBLE COSTS If the implementation of the action includeds non-eligible costs, please detail them here. INSTRUCTIONS: Please read carefully the call document and the model agreements - in case of selection, the framework partnership agreement and the grant agreement will constitute the legal basis for the

More information

FINANCIAL AND REPORTING ISSUES AND AUDITS IN RESEARCH PROJECTS IN THE CZECH-NORWEGIAN RESEARCH PROGRAMME CZ09

FINANCIAL AND REPORTING ISSUES AND AUDITS IN RESEARCH PROJECTS IN THE CZECH-NORWEGIAN RESEARCH PROGRAMME CZ09 1 FINANCIAL AND REPORTING ISSUES AND AUDITS IN RESEARCH PROJECTS IN THE CZECH-NORWEGIAN RESEARCH PROGRAMME CZ09 Date: 23 September 2016 Introduction: Some of the Norwegian project partners have experienced

More information

THE REGIONAL MUNICIPALITY OF PEEL COUNCIL EXPENSE POLICY REVIEW COMMITTEE

THE REGIONAL MUNICIPALITY OF PEEL COUNCIL EXPENSE POLICY REVIEW COMMITTEE THE REGIONAL MUNICIPALITY OF PEEL COUNCIL EXPENSE POLICY REVIEW COMMITTEE AGENDA CEPRC - 3/2017 DATE: Thursday, December 7, 2017 TIME: LOCATION: 11:00 AM 12:30 PM 5th Floor Boardroom Regional Administrative

More information

CDKN Expenses Policy

CDKN Expenses Policy CDKN Expenses Policy Principal guidelines for suppliers August 2015 Climate & Development Knowledge Network CDKN Expenses Policy August 2015 Page 1 of 13 Contents 1. Introduction 3 2. Expenses Policy 4

More information

MARIE CURIE INTRA-EUROPEAN FELLOWSHIP FOR CAREER DEVELOPMENT

MARIE CURIE INTRA-EUROPEAN FELLOWSHIP FOR CAREER DEVELOPMENT ANNEX III SPECIFIC PROVISIONS MARIE CURIE INTRA-EUROPEAN FELLOWSHIP FOR CAREER DEVELOPMENT III. 1 Definitions In addition to the definitions in Article II.1, the following definitions apply to this grant

More information

A CEPR / DFID Research Initiative MAJOR RESEARCH GRANT BUDGET GUIDELINES

A CEPR / DFID Research Initiative MAJOR RESEARCH GRANT BUDGET GUIDELINES Coordinated by: In partnership with: A CEPR / DFID Research Initiative MAJOR RESEARCH GRANT BUDGET GUIDELINES 2017-2020 Contents 1 Introduction... 2 2 General rules... 2 3 Definition of Costs... 2 3.1

More information

MODEL FOR THE CERTIFICATE ON THE FINANCIAL STATEMENTS

MODEL FOR THE CERTIFICATE ON THE FINANCIAL STATEMENTS Grant Agreement number: [insert number] [insert acronym] [insert call identifier of the master call] H2020 Model Grant Agreement: Multi-beneficiary General MGA: December 2013 ANNEX 5 MODEL FOR THE CERTIFICATE

More information

Audit certificate template for Horizon2020 projects funded by SERI

Audit certificate template for Horizon2020 projects funded by SERI Audit certificate template for Horizon2020 projects funded by SERI Under Article 4.1 of the subsidy agreement concluded between SERI and the Swiss research institution (hereinafter referred to as beneficiary),

More information

IPA partners seminar. Eligibility of expenditure and specificities of the public procurement. Dubrovnik, 5 th February 2013

IPA partners seminar. Eligibility of expenditure and specificities of the public procurement. Dubrovnik, 5 th February 2013 IPA partners seminar Eligibility of expenditure and specificities of the public procurement Dubrovnik, 5 th February 2013 Index Reference documents Eligibility: General rules Timeframe Budget lines Supporting

More information

ANNEX III FINANCIAL and CONTRACTUAL RULES I. RULES APPLICABLE TO BUDGET CATEGORIES BASED ON UNIT CONTRIBUTIONS

ANNEX III FINANCIAL and CONTRACTUAL RULES I. RULES APPLICABLE TO BUDGET CATEGORIES BASED ON UNIT CONTRIBUTIONS ANNEX III FINANCIAL and CONTRACTUAL RULES I. RULES APPLICABLE TO BUDGET CATEGORIES BASED ON UNIT CONTRIBUTIONS I.1 Conditions for eligibility of unit contributions Where the grant takes the form of a unit

More information

Request for Proposals. For. Financial Aid Services. Issued by: Pennsylvania State System of Higher Education Office of the Chancellor

Request for Proposals. For. Financial Aid Services. Issued by: Pennsylvania State System of Higher Education Office of the Chancellor Request for Proposals For Issued by: Pennsylvania State System of Higher Education RFP # 2010-QCC-RLG-04 Issue Date: January 22, 2010 Response Date: February 12, 2010 Table of Contents Page Part I General

More information

AUDIT CERTIFICATE GUIDANCE NOTES 6 TH FRAMEWORK PROGRAMME

AUDIT CERTIFICATE GUIDANCE NOTES 6 TH FRAMEWORK PROGRAMME AUDIT CERTIFICATE GUIDANCE NOTES 6 TH FRAMEWORK PROGRAMME WORKING NOTES FOR CONTRACTORS AND CERTIFYING ENTITIES MATERIALS PREPARED BY INTERDEPARTMENTAL AUDIT CERTIFICATE WORKING GROUP/ COORDINATION GROUP

More information

The UN Trust Fund to End Violence against Women Annex 3: Budget Guidelines

The UN Trust Fund to End Violence against Women Annex 3: Budget Guidelines Contents The UN Trust Fund to End Violence against Women Annex 3: Budget Guidelines 1. General Guidelines & Requirements... 1 2. Budget for Project Activities... 2 3. Budget for M&E/Audit/Management Costs...

More information

Annex 2: Project Financial Reporting & Monitoring Guidelines and Procurement Framework

Annex 2: Project Financial Reporting & Monitoring Guidelines and Procurement Framework Annex 2: Project Financial Reporting & Monitoring Guidelines and Procurement Framework (Sourced from Section 5 & 6 of the SANBio/BioFISA II Project Implementation Guidelines) 1. Costs supported by the

More information

Policy Number: FAST-BUFA 201 Policy Approved: April 2011

Policy Number: FAST-BUFA 201 Policy Approved: April 2011 + Policy Title: Travel- Authorizations and Reimbursement Policy Number: FAST-BUFA 201 Policy Approved: April 2011 Policies Superseded: 603, FINA-103 Review/revision(s): August 2013, August 2014, December

More information

Guideline Feasibility Study Guideline

Guideline Feasibility Study Guideline A10 revised August 23, 2018 Guideline Feasibility Study Guideline Fredskorpset/FK Norway PO Box 8055 Dep 0031 Oslo, Norway Organisational ID: NO 981965132 Contents 1. The feasibility study application...

More information

User Travel Regulations

User Travel Regulations XFEL.EU UN-2017-001.0 USER NOTE User Travel Regulations H. Shie, T. Larsson, and S. Bertini for the User Office at European XFEL European X-Ray Free-Electron Laser Facility GmbH Holzkoppel 4 22869 Schenefeld

More information

Terms of Reference for the Fund Operator The EEA and Norway Grants Global Fund for Regional Cooperation EEA and Norwegian Financial Mechanisms

Terms of Reference for the Fund Operator The EEA and Norway Grants Global Fund for Regional Cooperation EEA and Norwegian Financial Mechanisms Terms of Reference for the Fund Operator The EEA and Norway Grants Global Fund for Regional Cooperation EEA and Norwegian Financial Mechanisms 2014-2021 Table of Contents 1. Introduction... 3 1.1 Objectives

More information

Travel and Reimbursement Policy EPF Meetings / Events

Travel and Reimbursement Policy EPF Meetings / Events Travel and Reimbursement Policy EPF Meetings / Events All representatives of patient organisations who have been invited and whose registration has been confirmed for an EPF event will be reimbursed for

More information

CERTIFICATES ISSUED BY EXTERNAL AUDITORS GUIDANCE NOTES FOR BENEFICIARIES AND AUDITORS

CERTIFICATES ISSUED BY EXTERNAL AUDITORS GUIDANCE NOTES FOR BENEFICIARIES AND AUDITORS CERTIFICATES ISSUED BY EXTERNAL AUDITORS GUIDANCE NOTES FOR BENEFICIARIES AND AUDITORS MATERIALS PREPARED BY THE WORKING GROUP ON CERTIFICATE ON THE METHODOLOGY UNDER FP7: DG RESEARCH AND INNOVATION DG

More information

INTERNATIONAL ORGANISATIONS QUESTIONS

INTERNATIONAL ORGANISATIONS QUESTIONS INTERNATIONAL ORGANISATIONS QUESTIONS A. General 1. What is an International Organisation? An international Organisation can only be considered as such under the Financial Regulation if the following criteria

More information

Travel Forms Effective November 1, 2018 Presented by Miranda Salvatore Accounts Payable

Travel Forms Effective November 1, 2018 Presented by Miranda Salvatore Accounts Payable Travel Forms Effective November 1, 2018 Presented by Miranda Salvatore Accounts Payable Discussion Highlights New Forms Updated Forms Details of each form Day Travel Expense Form International Travel Request

More information

Cost Guidelines. Version 1.4. V1.4_valid as of 1/4/2014 Page 1

Cost Guidelines. Version 1.4. V1.4_valid as of 1/4/2014 Page 1 Cost Guidelines for the accounting of project costs in funding applications and reports for projects based on funding agreements according to the FTE-Richtlinien and FFG-Richtlinien Version 1.4 V1.4_valid

More information

RULES FOR THE REIMBURSEMENT OF TRAVEL AND SUBSISTENCE EXPENSES FOR EXCHANGE OF OFFICIALS

RULES FOR THE REIMBURSEMENT OF TRAVEL AND SUBSISTENCE EXPENSES FOR EXCHANGE OF OFFICIALS EUROPEAN COMMISSION CONSUMERS, HEALTH, AGRICULTURE AND FOOD EXECUTIVE AGENCY Consumers and Food Safety Unit RULES FOR THE REIMBURSEMENT OF TRAVEL AND SUBSISTENCE EXPENSES FOR EXCHANGE OF OFFICIALS CONSUMER

More information

TEMPUS Reformation of the Curricula on Built Environment in the Eastern Neighbouring Area

TEMPUS Reformation of the Curricula on Built Environment in the Eastern Neighbouring Area TEMPUS Reformation of the Curricula on Built Environment in the Eastern Neighbouring Area Lina Zemeckyte lina.zemeckyte@vgtu.lt Hierarchy of TEMPUS documentation CALL FOR PROPOSALS Grant Agreement: SPECIAL

More information

PROGRAMME RULES ON ELIGIBILITY OF EXPENDITURES

PROGRAMME RULES ON ELIGIBILITY OF EXPENDITURES PROGRAMME RULES ON ELIGIBILITY OF EXPENDITURES Final version adopted by the JMC on 24 February 2016 Table of contents INTRODUCTION... - 4-1. LIST OF DEFINITIONS... - 4-2. LIST OF ABBREVIATIONS... - 5-3.

More information

AUDIT CERTIFICATE WORKING NOTES 6 TH FRAMEWORK PROGRAMME

AUDIT CERTIFICATE WORKING NOTES 6 TH FRAMEWORK PROGRAMME AUDIT CERTIFICATE WORKING NOTES 6 TH FRAMEWORK PROGRAMME WORKING NOTES FOR CONTRACTORS AND CERTIFYING ENTITIES MATERIALS PREPARED BY INTERDEPARTMENTAL AUDIT CERTIFICATE WORKING GROUP VERSION 1 APPROVED

More information

Rules. Unofficial translation. - for aid from the EUDP to projects within research, development and demonstration.

Rules. Unofficial translation. - for aid from the EUDP to projects within research, development and demonstration. Energy Technology Development and Demonstration Programme Rules - for aid from the EUDP to projects within research, development and demonstration. Table of contents 1 INTRODUCTION... 5 2 BENEFICIARIES

More information

FELLOWSHIP AGREEMENT

FELLOWSHIP AGREEMENT Annex B: FELLOWSHIP AGREEMENT Eastern Partnership Civil Society Facility GDSI Limited within the EU-funded project the Eastern Partnership Civil Society Facility

More information

The Swedish International Development Cooperation Agency, Sida,

The Swedish International Development Cooperation Agency, Sida, Page 1 of 10 Grant agreement (The "Agreement") The Swedish International Development Cooperation Agency, Sida, Organisation number: 202100-4789 Sida 105 25 Stockholm Sweden, ("Sida") of the one part, and

More information

Set of rules for AAU credit cards with corporate liability - staff

Set of rules for AAU credit cards with corporate liability - staff Aalborg University Set of rules for AAU credit cards with corporate liability - staff Disclaimer This set of rules for AAU credit cards with corporate liability has been translated into English from the

More information

Eligibility of costs in the Horizon 2020 funded EUROfusion project

Eligibility of costs in the Horizon 2020 funded EUROfusion project Eligibility of costs in the Horizon 2020 funded EUROfusion project Garching, 3 December 2015 Subcontractors and other third party support Presented by: Michael Erdmann, EUROfusion Coordinator Unit, Max-Planck-Institute

More information

SAS (the payer) has the responsibility to comply with the withholding tax provisions and not the non-resident recipient.

SAS (the payer) has the responsibility to comply with the withholding tax provisions and not the non-resident recipient. The Singapore Actuarial Society (SAS) Process for Payments to Non-Singapore Tax Resident Entities (Corporates or Individuals) Date: 21 June 2018 Tax information below is of a general nature and may not

More information

Tips on Administrative issues and Financial Reporting KOM ANYWHERE Soraya Hidalgo European Projects Office - UPC

Tips on Administrative issues and Financial Reporting KOM ANYWHERE Soraya Hidalgo European Projects Office - UPC Tips on Administrative issues and Financial Reporting Soraya Hidalgo European Projects Office - UPC Outline H2020 Main changes Grant Agreement Structure Financial reporting Elegibility criteriai Do s and

More information

Multi-Beneficiary Model Grant Agreement

Multi-Beneficiary Model Grant Agreement European Research Council (ERC) Multi-Beneficiary Model Grant Agreement ERC Starting Grants, Consolidator Grants and Advanced Grants (H2020 ERC MGA Multi) Version 5.0 18 October 2017 Disclaimer This document

More information

KA2 Strategic Partnerships Financial Management. 21st September

KA2 Strategic Partnerships Financial Management. 21st September KA2 Strategic Partnerships Financial Management 21st September 2017 Leargas.Ireland @Leargas www.leargas.ie 1 Overview General Principles of Financial Management Eligibility of Expenses (eligible and ineligible

More information

ANNEX III FINANCIAL AND CONTRACTUAL RULES I. RULES APPLICABLE TO BUDGET CATEGORIES BASED ON UNIT CONTRIBUTIONS

ANNEX III FINANCIAL AND CONTRACTUAL RULES I. RULES APPLICABLE TO BUDGET CATEGORIES BASED ON UNIT CONTRIBUTIONS ANNEX III FINANCIAL AND CONTRACTUAL RULES I. RULES APPLICABLE TO BUDGET CATEGORIES BASED ON UNIT CONTRIBUTIONS I.1 Conditions for eligibility of unit contributions Where the grant takes the form of a unit

More information

Audit certificates. Training Seminar Brussels 28 November 2006

Audit certificates. Training Seminar Brussels 28 November 2006 Audit certificates Training Seminar Brussels 28 November 2006 Overview Introduction Audit certificate requirements What When By whom Audit certificate template Audit certificate guidance notes for contractors

More information

ANNEX III FINANCIAL AND CONTRACTUAL RULES I. RULES APPLICABLE TO BUDGET CATEGORIES BASED ON UNIT CONTRIBUTIONS

ANNEX III FINANCIAL AND CONTRACTUAL RULES I. RULES APPLICABLE TO BUDGET CATEGORIES BASED ON UNIT CONTRIBUTIONS ANNEX III FINANCIAL AND CONTRACTUAL RULES I. RULES APPLICABLE TO BUDGET CATEGORIES BASED ON UNIT CONTRIBUTIONS I.1 Conditions for eligibility of unit contributions Where the grant takes the form of a unit

More information

H2020 Annotated Model Grant Agreement (AGA) v 5.0 ( ) track changes

H2020 Annotated Model Grant Agreement (AGA) v 5.0 ( ) track changes H2020 GENERAL MGA 17 third parties Participants roles should correspond to their real contribution to the project. Main actors should be the beneficiaries and third parties should perform secondary tasks.

More information

This is the flowchart for stating/reporting the budget starting from the proposal phase tup till diurng control by an auditor. The key message is

This is the flowchart for stating/reporting the budget starting from the proposal phase tup till diurng control by an auditor. The key message is 1 2 3 This is the flowchart for stating/reporting the budget starting from the proposal phase tup till diurng control by an auditor. The key message is that funding is not based on the estimated budget,

More information

ANNEX III FINANCIAL and CONTRACTUAL RULES I. RULES APPLICABLE TO BUDGET CATEGORIES BASED ON UNIT CONTRIBUTIONS

ANNEX III FINANCIAL and CONTRACTUAL RULES I. RULES APPLICABLE TO BUDGET CATEGORIES BASED ON UNIT CONTRIBUTIONS ANNEX III FINANCIAL and CONTRACTUAL RULES I. RULES APPLICABLE TO BUDGET CATEGORIES BASED ON UNIT CONTRIBUTIONS I.1 Conditions for eligibility of unit contributions Where the grant takes the form of a unit

More information

] DISBURSEMENT PROCEDURES

] DISBURSEMENT PROCEDURES ] DISBURSEMENT PROCEDURES 1.1 General: The purpose of guidelines contained herein is to lay down the Disbursement Procedures for the projects funded by the SAARC DEVELOPMENT FUND (SDF). It intends to provide

More information

HEQCO REQUEST FOR PROPOSAL (RFP) INSTRUCTIONS PROPOSAL SUBMISSION INSTRUCTIONS

HEQCO REQUEST FOR PROPOSAL (RFP) INSTRUCTIONS PROPOSAL SUBMISSION INSTRUCTIONS HEQCO REQUEST FOR PROPOSAL (RFP) INSTRUCTIONS PROPOSAL SUBMISSION INSTRUCTIONS Proposals are to be submitted according to the following method: 1. Proposal submission must contain one (1) electronic copy

More information

SMALL PROJECT CONSOLIDATED PROGRESS REPORT FORM including guidelines

SMALL PROJECT CONSOLIDATED PROGRESS REPORT FORM including guidelines SMALL PROJECT CONSOLIDATED PROGRESS REPORT FORM including guidelines GET ACQUAINTED WITH PROGRAMME MANUAL AND APPROPRIATE NATIONAL GUIDELINES BEFORE FILLING IN SMALL PROJECT PROGRESS / CONSOLIDATED PROGRESS

More information

DECISION 08/2013/GB OF THE GOVERNING BOARD OF THE EUROPEAN POLICE COLLEGE AMENDING DECISION 30/2006/GB OF THE GOVERNING BOARD

DECISION 08/2013/GB OF THE GOVERNING BOARD OF THE EUROPEAN POLICE COLLEGE AMENDING DECISION 30/2006/GB OF THE GOVERNING BOARD DECISION 08/2013/GB OF THE GOVERNING BOARD OF THE EUROPEAN POLICE COLLEGE AMENDING DECISION 30/2006/GB OF THE GOVERNING BOARD OF THE EUROPEAN POLICE COLLEGE LAYING DOWN ADMINISTRATIVE RULES, COMMITMENTS

More information

BILATERAL FUND GUIDELINES

BILATERAL FUND GUIDELINES BILATERAL FUND GUIDELINES Athens July 2014 Table of Contents About the NGO Programme: We are all Citizens... 4 Bilateral Fund... 7 Open calls... 9 Measure (a) seed money... 10 1. Eligible applicants...

More information