ADMINISTRATIVE MANUAL FOR PROJECT IMPLEMENTATION

Size: px
Start display at page:

Download "ADMINISTRATIVE MANUAL FOR PROJECT IMPLEMENTATION"

Transcription

1 ADMINISTRATIVE MANUAL FOR PROJECT IMPLEMENTATION 1. Introduction The purpose of this manual is to give guidance and instructions to Project Developers (PD) on administration of the project implementation as well as on the reporting requirements in an EEP Mekong funded project. It is the PD s responsibility to make sure that enough information regarding the project implementation and financial performance has been included in the reports and that the reporting clearly states the situation of the project. It is recommended to always ask advice and guidance from the Regional Coordination Unit (RCU) (info@eepmekong.org) if there is any uncertainty whether the information provided by the PD is sufficient to approve their reporting. Please also note that the Administration Manual is updated and additional guidance added when considered necessary and therefore PDs need to make sure that they are always following the latest guidance/manual. The PD s will always be informed of the possible revisions of the manual through by the RCU. The latest version of the Manual will also be available at the EEP website ( This Manual is meant to be used aligned with the project contracts. If a part of this manual is in conflict with the contract, the contract shall be concerned as a priority. 2. Project Developer s responsibilities Every PD monitors their own project and is responsible for reporting the progress of the project as stated in the Reporting and Payment Schedule (RPS). PD is also responsible of implementing the project as agreed in the contract made with the Ministry for Foreign Affairs of Finland (Ministry). In more detail the PD s responsibilities of project administration and reporting towards the Programme are: a) The main contact person from the PD shall ensure that all relevant information is promptly provided to the RCU. Other project personnel are entitled to contact the RCU, but the PD is the main responsible party. Questions and reports should always be sent to info@eepmekong.org mailbox. The title of every shall start with the project code, as it makes it 1

2 easier for the RCU to follow-up on specific projects and thus enables a quicker answer to the PDs. PDs can also contact the RCU through the telephone number stated in the EEP Mekong website. The RCU is always the relevant party to address questions regarding the project and the whole programme. Therefore no project or programme related matter should be appointed to the donors or any other party involved in the Programme. b) Meeting the reporting requirements relating to the progress of the project and the financial reporting (please see chapter 3 for more details). PDs shall report the project progress to the RCU according to the reporting payment schedule (RPS) attached to the project contract, or to an addendum if the contract has been exceeded. Do notice that the reporting interval should not be longer than six month, please review chapter 3 for more detailed instruction regarding reporting.) PDs are responsible of sending an updated RPS to the RCU if there are changes in implementation that also affect the reporting. RPS should always be prepared considering the realistic timing when the milestones are met. PDs are responsible of requesting extension to the contract period if the original contract period is not long enough for implementing the project. It is important to realistically consider the time when the project is estimated to be finalized in order to avoid several extensions. 3. Preparing the reporting for the Project 3.1 Templates When reporting of the project progress, the EEP reporting templates shall be used. There is a template for narrative progress report and a template for financial report. There is also a separate template for the project completion report submitted after all the milestone reports and completion of the actual project. It should be noted that any parts of the templates should not be deleted or tailored but they should be completed in the given format. All the reporting shall also include the submission date. All templates can be found on the Programme website 2

3 3.2 Progress/milestone report Reporting should be results based and follow the guidelines set out in the specific reporting template, which complies with Annex III in the project contract. The progress reports should answer at least the following questions: a) Have the activities mentioned in the RPS been completed? Have the implemented activities contributed towards the planned results? If yes, the report should include information regarding the implementation of the activity. If no, there has to be a justification why the activities have not been completed and a clarification if they have been scheduled to be completed later during the project. b) In case of procurements, how the PD has ensured that procurement requirements have been met? The report has to clarify the procurement process and supporting documentation for the procurement shall be provided. Possible changes in the activities have to be justified, and how these changes are affecting the budget and the output results of the Project have to be clarified. If there are activities that have not been completed, the expenditures for the corresponding Milestone should be lower. If the Milestone activities include studies and/or evaluations that are stated as milestone deliverables, the reports of those studies and evaluation shall be attached to the report as annexes. If the PD wishes to make technical changes in the project plan, the report needs to clarify whether this has an effect on the output results of the projects. In general, if the outputs do not change, the technical changes can be approved. The PD should discuss any significant changes in the project with the RCU and these have to be approved by the RCU before the PD makes them. 3.3 Financial report Together with the payment request PDs are required to submit financial report showing funds received and costs covered by the grant during the reporting period. a) Reporting shall always be based on real expenditures and reported on correct budget lines. b) The financial reports shall consist of all expenditures related to the Project, regardless if the PD, third party or EEP funds them. c) All reported expenditure shall have proper supporting documentation and all 3

4 invoices paid with EEP funds shall be stamped with a Paid with funds of EEP Mekong stamp. d) For salaries paid by the PD, the payment shall be supported by an advice of receipt by the employee. If the salary is paid to the bank account of the employee, an extract from the PDs bank account clearly showing the amount and receiver is also acceptable. e) In case a service has been provided by a third party that verifiably cannot provide a receipt, the person will have to sign a receipt indicating the amount or estimated cost of the service and enclose a copy of her/his identity documentation/card. f) If an expense has been split between EEP Mekong and another donor, the voucher has to state the amount that has been requested from the EEP Mekong. g) If the reported expenditures have been covered by an advance payment, the PDs should use the exchange rate of the advance payment date when converting the expenses that are clearing the advance payment. For any other expenditure, the exchange rate to be used in conversion is the exchange rate on the reporting day. h) All expenditures relating to project shall be budgeted. Changes in budget shall be approved before the costs that are not in the last approved budget can be reclaimed. (Please see additional guidance below) i) The amount financed by EEP Mekong (euro) in the financial report shall equal to the amount in the disbursement request for the reporting period. j) Only eligible expenses can be reimbursed/funded by EEP Mekong. k) If there have been changes in activities, the finance report should indicate similar variation in expenditures. l) The total eligible expenses that can be reimbursed/funded by EEP Mekong cannot exceed the total amount stated in the contract. Thus, in practice, eligible expenses can only be reallocated between budget lines Guidelines for differences in budget line items Deviations of more than 10 percent or 1,000, whichever is less, from a budget line, shall be explained in the reporting. More specifically; a) It is acceptable that a budget line is exceeded with at most 10 percent or 3,000, whichever is less, without prior approval from the RCU. b) If a budget line is exceeded with more than 10 percent or 3,000, whichever is less, the additional expenses exceeding the budget line by 10 percent or 3,000, whichever is less, and prior approval to the change in budget has not 4

5 been approved in advance by the RCU, the expenses might not be considered as eligible expenses even if they otherwise could be eligible expenses. c) If prior approval cannot be reasonable obtained, the change shall be communicated to the RCU as soon as possible. This means mostly a separate communication to RCU from the normal progress reporting. 3.4 Project Completion Report For a completed project, the Company must send the RCU a project completion report including photos for possible publication on the Programme website and in related publications. Please note that the final payment will be paid against approved Project Completion Report. The project completion report shall include a profound analysis of changes in the project context and of the target group and the beneficiaries. In addition, the report shall contain a detailed assessment of the project progress and results based on comparing the intervention logic and plans with actual achievements, stating deviations, comments and observations made, as well as providing a description of the monitoring and management measures implemented. Based on this assessment, the report shall bring out conclusions with regard to future perspectives of the Project sustainability. The project completion report shall also include the Auditor s report. A brief leaflet covering the main outputs shall be completed by the end of the project by the project developer to attract further financiers (related applicable costs are to be included in the project budget) and contribute tangible and succinct information necessary for potential EEP Mekong replication, scale-up and knowledge sharing purposes 4. Disbursement of Grants Grants are disbursed to projects after required reports and disbursement requests have been verified. Disbursements are paid only against written payment requests to the RCU in the form and content as shown in Annex II of the Project Contract. The template for the letter can be found from the EEP Mekong website. The payment request shall be prepared by the PD, signed by the authorized person and sent to the RCU address info@eepmekong.org. When sending the reports it is important to ensure that all the required documentation is submitted. The PDs should ensure that the report is as clear as possible and that a third person can understand the calculations and reconcile the numbers in the report with the related vouchers without any difficulties. If the RCU has to request missing documentation or clarification on the reporting, 5

6 this will slow down the disbursement process. If all the documentation is in place, the disbursements should be made within 30 days of receiving the disbursement request. The final payment to the PD is subject to approval of the Project Completion Report and that the RCU has received an audit report regarding the project in the format described in section 4. As the requested funds have been received, the PD shall confirm the received amount to the RCU by sending a bank statement via Procurement PDs are required to make all procurement in accordance with the contents of the Finnish legislation on public procurement (see Act on Public Contracts, available at generally accepted principles and good procurement practices. As a general rule, the lowest price forms the selection criterion in competitive tendering. A favorable price in terms of overall economy can also be applied. Dividing contracts into parts in order to keep the contract value below any threshold mentioned below is strictly forbidden. The following procurement guidelines shall be followed: a) Costs below 100: procedure to be decided upon by the company; b) Costs between 100 to 3 999: comparison of at least three quotes/offers obtained directly from suppliers, The quotes and justifications for selection shall be annexed to a progress report. Offers shall be obtained from at least 3 different suppliers whenever possible. The basis for the selection shall be documented and included in the disbursement request. c) Costs between to : competitive tendering with invitations to tender sent directly to potential suppliers; The quotes and reasons for selection shall be annexed to a progress report. Principles of equal and non-discriminatory treatment of tenderers shall be complied with. Selection of the provider shall be made in the first place on the basis of competitive tendering. When using competitive tendering, the Company shall draw up an invitation to tender and ask for tenders by , fax and/or letter. The invitation to tender can be delivered directly to selected potential tenderers (at least three whenever possible). All significant information concerning the purchase and the contract shall be presented in the written invitation to tender. 6

7 The time limit for submitting written tenders must be reasonable. Direct awarding shall only be used to the extent: the costs of competitive tendering exceed the benefits obtained from competitive tendering; the contract is urgent for reasons independent of the Company; a corresponding product has been procured in the recent past and the price level is known; and/or no other potential suppliers have been identified. If direct awarding has been applied, this has to be agreed upon with the ECO in advance. d) Costs above : competitive open tendering with invitations to tender announced publicly. The procurement procedure shall be beforehand separately agreed upon with the RCU. For Finnish Companies, procurements shall be made taking into account the Finnish act on public contracts (348/2007) and the Finnish Government decree on public contracts (614/2007) as they read when the procurement process is commenced by the Company In cases where Finnish procurement legislation is not applicable, the Company (Finnish or other) shall procure the goods or services in accordance with what is stated above as regards purchases of Euros. When a procurement with a total value of more than is done, the specific selection criteria has to be communicated to the RCU before the procurement process, in order to remove doubts that specific selection criteria have been chosen to enable the selection of a pre- determined supplier. It is important to ensure that the procurement guidelines have been followed specifically and documented sufficiently. Procurement documents shall be attached to the report. The sufficient documentation regarding procurements includes: a) Invitation and advertisement of a tender relevant to size of the tender b) Evaluation of the proposals, where all received proposals are ranked based on the criteria mentioned in the original tender. c) Further clarification why a specific tender was approved before others. The documentation does not need to be extensive, but it has to make it clear how the Public Procurement Act was followed in the process. 7

8 6. Project Audit report The Project Developer Company shall appoint the auditors of the project. The project audits have to be performed by a legally authorized and certified audit firm and will have to present the firm s findings, risks and recommendations on the following aspects: Financial statements and documents verifications, to insure that: a) there is an acceptable endorsement document for each expense; b) all expenses have been made according to the project budget; c) budgetary deviations and reallocations are in line with these current guidelines and other instructions given by the MFA, furthermore clearly indicated and justified; d) all expenses are supported by appropriate original receipts and invoices as proofs of payment; e) expenses reimbursed by or charged to EEP do not include VAT that the PD can, or reasonable could, reclaim; f) all the original invoices, receipts or any other voucher issued to the Company s name are stamped with the statement Paid with funds of EEP Mekong ; and g) expenditure is within reasonable range of costs benchmarked against rates specified in the project document, market prices and/or other acceptable industry or Government rates for professional fees, mileage compensation and daily subsistence allowances. Performance assessment, to insure that: a) the analysis of quantifiable project outputs is based on indicators specified in the full project proposal document; b) the quality of workmanship and adherence to installation and safety standards follow acceptable best practices in the country or the region of implementation as defined in the full project proposal document; c) the performance of technologies installed reaches the level(s) defined in the project document; and d) the final project beneficiaries are reasonably satisfied with the use of the equipment installed or services delivered from the project. 8

9 Sustainability assessment, to insure that: a) project activities can continue beyond EEP funding as envisioned per the full project proposal; and b) there are adequate maintenance arrangements in place for long term operations of installed systems. An audit report shall be issued showing explicit approval the handling of Grant funds for the execution of the Project. The report will have to be sealed and signed by the auditor including his/her name with certification number and submitted to the RCU. If the audit is perform by an audit firm that is not internationally well known, the documents proofing the authorization and certification of the audit firm have to be sent to the RCU with the audit report. The Project Developer Company must ensure that the cost for the audit is included in the approved project budget and in the settlement for the last disbursement. 7. Eligible expenses All expenditure must be necessary for the project and reasonable. All reimbursed costs are subject to discretion and their eligibility evaluated in relation to the project plan and project decision. Costs are only considered eligible, if proper procurement procedures have been followed, when products or services are sources from another party. 7.1 Eligible expenses a) products and services purchased from external service providers; b) costs related to the evaluation of project effectiveness and monitoring; c) only reasonable project personnel travel and accommodation expenses and daily allowances in accordance with travelling regulations of the Government of Finland. The updated regulation is available on the EEP website d) acquisition costs of fixed assets necessary for project implementation (machinery, equipment, etc.), to the extent verified that no public assistance has been granted for their acquisition during the five previous years; e) rental or leasing costs of premises, machinery and equipment necessary for project implementation (including motor vehicles) if they result solely from the Project; f) general costs (indirect costs), e.g. costs resulting from the use of telephone calls, electricity or water, as well as accounting costs, rental and cleaning costs, office costs, when these can be shown to have occurred solely from the project (the allocation of indirect costs must be clearly demonstrated); and g) audit costs. 9

10 7.2 Ineligible expenses Expenditure that is not based on the approved project plan or on financing decisions issued for the project or which has not been agreed on authoritatively with the Programme in project negotiations: a) merit pay, bonuses, fringe benefits and similar supplements to wages that are paid in addition to regular wage; b) general staff training; c) fines, penalty fees and legal expenses, except legal expenses that are related to the project and that has been approved in the budget; d) financing expenses: interest on loans, fees related to financing transactions, currency exchange fees and exchange rate losses; e) fees resulting from opening or managing an account, if providing the Grant does not specifically require this; f) value-added tax (VAT) that may be deducted or refunded, or compensated for in another way; g) fees related to customs clearance; h) expenditure without original receipts stamped Paid with funds of EEP Mekong ; i) expenditure with professional fees, mileage rates, rental rates, etc which have not been agreed authoritatively and in advance with the Programme; and j) expenditure for equipment, installations and maintenance which do not comply with professionally acceptable standards in the country of implementation or with those presented in the project document. 8. Other implementation related rules 8.1 Repayment of unused funds Any amount, including interest, which has already been disbursed but has not been fully used by the end of the project, shall be paid back in the full amount as applicable. 8.2 Billboard on project sites Project sites will have to feature an installed metal billboard sign to identify the project as one financed by the Donors through the Programme. The design of the sign must be coordinated with the RCU. The project proponent shall ensure that the sign cost is included in the approved project budget. 8.3 Use of the EEP Mekong logo in project related material produced by the PD 10

11 All printed or electronic documents related to the project prepared by the PD, either for promotional, information or other purposes, including project related information on the PD s website, will have to include the legend Project financed by the Ministry for Foreign Affairs of Finland, and the logo of EEP Mekong, which will be provided by the RCU. Additionally, the document layout and illustrations shall be sent to the RCU for approval prior to printing and publication. In case the project is co-funded by other donors, the legend can be expanded to reflect such co-funding as appropriate. 8.4 Guidance and regulation from the Ministry or the RCU The Ministry or the RCU as its representative has the right to provide additional information or guidance to the Project Developer Company regarding the execution and financial management of the project as well as to issue further audit and audit report related specifications. The Project Developer Company must comply with such further guidance and specifications. 8.5 Project related VAT The Programme is not able to deduct or get the VAT paid refunded. The grant disbursed to the PDs from the Programme is, from the Ministry s behalf, considered to be a grant, not a payment for services provided by PDs for the Programme. The PDs are responsible for following the applicable VAT regulation in the country or countries where the project or the PD is located and choose to deduct or apply for refunding of VAT for Project related expenses, if this is possible. The PDs can only get funding from the Programme for VAT expenses, if the PD cannot choose to deduct or apply for refunding of the VAT for Project related expenses. 11

Contents. Ulkoministeriö Utrikesministeriet Ministry for Foreign Affairs of Finland

Contents. Ulkoministeriö Utrikesministeriet Ministry for Foreign Affairs of Finland 1 Contents 1. Introduction 2. Project Developer Responsibilities 3. Milestone Reporting 4. Monitoring and Site Visits 5. Disbursement of Funds 6. Repayable Grant 7. Procurement 8. Project Audit Report

More information

GUIDELINES. for EEP MEKONG PROJECTS IMPLEMENTATION. August 2016 ENERGY AND ENEVIRONMENT PARTNERSHIP PROGRAMME WITH THE MEKONG REGION (EEP MEKONG)

GUIDELINES. for EEP MEKONG PROJECTS IMPLEMENTATION. August 2016 ENERGY AND ENEVIRONMENT PARTNERSHIP PROGRAMME WITH THE MEKONG REGION (EEP MEKONG) GUIDELINES for EEP MEKONG PROJECTS IMPLEMENTATION August 2016 ENERGY AND ENEVIRONMENT PARTNERSHIP PROGRAMME WITH THE MEKONG REGION (EEP MEKONG) GUIDELINES for EEP MEKONG PROJECTS IMPLEMENTATION August

More information

NCF 7 Project Implementation Manual

NCF 7 Project Implementation Manual NCF 7 Project Implementation Manual November 2017 Table of Contents 1 INTRODUCTION... 4 2 GRANTEES RESPONSIBILITIES... 4 3 PROGRESS REPORTING... 4 3.1 Progress report... 4 3.2 Project completion report...

More information

Annex 2: Project Financial Reporting & Monitoring Guidelines and Procurement Framework

Annex 2: Project Financial Reporting & Monitoring Guidelines and Procurement Framework Annex 2: Project Financial Reporting & Monitoring Guidelines and Procurement Framework (Sourced from Section 5 & 6 of the SANBio/BioFISA II Project Implementation Guidelines) 1. Costs supported by the

More information

TERMS OF REFERENCE FOR AN EXPENDITURE VERIFICATION OF A GRANT CONTRACT - EXTERNAL ACTION OF THE EUROPEAN UNION -

TERMS OF REFERENCE FOR AN EXPENDITURE VERIFICATION OF A GRANT CONTRACT - EXTERNAL ACTION OF THE EUROPEAN UNION - TERMS OF REFERENCE FOR AN EXPENDITURE VERIFICATION OF A GRANT CONTRACT - EXTERNAL ACTION OF THE EUROPEAN UNION - HOW TO USE THIS TERMS OF REFERENCE MODEL? All text highlighted in yellow in this ToR model

More information

South East Europe (SEE) SEE Control Guidelines

South East Europe (SEE) SEE Control Guidelines South East Europe (SEE) SEE Control Guidelines Version 1.4. Final version approved by the MC 10 th June 2009 1 st amendment to be approved by MC (2.0) 1 CONTENTS 1 Purpose and content of the SEE Control

More information

FAQ. Questions and answers relating to the 2014 call for proposals for NGO operating grants for funding in 2015 (Latest update September 2014)

FAQ. Questions and answers relating to the 2014 call for proposals for NGO operating grants for funding in 2015 (Latest update September 2014) FAQ Questions and answers relating to the 2014 call for proposals for NGO operating grants for funding in 2015 (Latest update September 2014) CORRIGENDUM: In the first version of the Application Guide,

More information

ALLEGATO A ANNEX VII Special Conditions Grant Contract Expenditure Verification

ALLEGATO A ANNEX VII Special Conditions Grant Contract Expenditure Verification ALLEGATO A ANNEX VII Special Conditions Grant Contract Expenditure Verification TERMS OF REFERENCE FOR AN EXPENDITURE VERIFICATION OF A GRANT CONTRACT - EXTERNAL ACTIONS OF THE EUROPEAN COMMUNITY - ANNEX

More information

Creative Europe Sub-programme Culture Financial management

Creative Europe Sub-programme Culture Financial management Creative Europe Sub-programme Culture Financial management 10 November 2014 Sandra Delespesse & Maria-Paz Benito 1 Content Financial tasks Eligibility of costs Important documents Checks, audit and evaluation

More information

Financial Guidelines for Beneficiaries EDCTP Association October 2016

Financial Guidelines for Beneficiaries EDCTP Association October 2016 Financial Guidelines for Beneficiaries EDCTP Association October 2016 This document is prepared as a supplement to the Grant Agreement (GA), where majority of the information is extracted from. In the

More information

Important Messages - Grants

Important Messages - Grants GRANT IMPORTANT MESSAGES Important Messages - Grants SCOPE Important messages contain: 1) procedural rules ( procedure ) e.g. interpretation of the PRAG or internal procedures etc. 2) recommendations e.g.

More information

or institution which in turn is a member of the International Federation of Accountants (IFAC).

or institution which in turn is a member of the International Federation of Accountants (IFAC). Terms of Reference for an Expenditure Verification of a Grant Contract for Estonia - Latvia- Russia Cross Border Cooperation Programme within the European Neighbourhood and Partnership Instrument 2007-2013

More information

1.12 Date of budget revision submission: Enter the month and year the budget revision was submitted for approval Prepared by: Enter the name of

1.12 Date of budget revision submission: Enter the month and year the budget revision was submitted for approval Prepared by: Enter the name of Instructions for completion of budget template A guide and toolkit on project budgeting and cost allocation This guide contains a budget template to help organisations calculate the full cost of a particular

More information

Yellow cells denote information required to be entered. Grey cells denote no information should be entered.

Yellow cells denote information required to be entered. Grey cells denote no information should be entered. A guide and toolkit on project budgeting and cost allocation This guide contains a budget template to help organisations calculate the full cost of a particular project or service, including an appropriate

More information

SMALL PROJECT CONSOLIDATED PROGRESS REPORT FORM including guidelines

SMALL PROJECT CONSOLIDATED PROGRESS REPORT FORM including guidelines SMALL PROJECT CONSOLIDATED PROGRESS REPORT FORM including guidelines GET ACQUAINTED WITH PROGRAMME MANUAL AND APPROPRIATE NATIONAL GUIDELINES BEFORE FILLING IN SMALL PROJECT PROGRESS / CONSOLIDATED PROGRESS

More information

Funding for companies research and development operations Eligible costs and project monitoring

Funding for companies research and development operations Eligible costs and project monitoring Funding for companies research and development operations Eligible costs and project monitoring Funding terms and conditions: Funding for companies R&D activities 23 November 2017 Copyright Tekes Accountable

More information

FINANCIAL GUIDELINES AND STANDARDS FOR EVENT MANAGEMENT

FINANCIAL GUIDELINES AND STANDARDS FOR EVENT MANAGEMENT ANNEX 2 FINANCIAL GUIDELINES AND STANDARDS FOR EVENT MANAGEMENT (to be fine-tuned upon contract signature) 2 INDEX Page 1. FOREWORDS. 5 2. GENERAL PRINCIPLES.. 5 3. BUDGET MANAGEMENT WORKFLOW 5 3.1 PRE-EVENT

More information

Terms of Reference for the Fund Operator The EEA and Norway Grants Global Fund for Regional Cooperation EEA and Norwegian Financial Mechanisms

Terms of Reference for the Fund Operator The EEA and Norway Grants Global Fund for Regional Cooperation EEA and Norwegian Financial Mechanisms Terms of Reference for the Fund Operator The EEA and Norway Grants Global Fund for Regional Cooperation EEA and Norwegian Financial Mechanisms 2014-2021 Table of Contents 1. Introduction... 3 1.1 Objectives

More information

Lead Partner Seminar. JS/MA Riga

Lead Partner Seminar. JS/MA Riga Lead Partner Seminar JS/MA 9.12.2015 Riga Welcome to the Lead Partner Seminar Objective of the day: Give the Lead Partner the needed tools to best implement the project To know where to come with questions

More information

GUIDE FOR PROJECT IMPLEMENTATION

GUIDE FOR PROJECT IMPLEMENTATION GUIDE FOR PROJECT IMPLEMENTATION PRACTICAL GUIDANCE FOR PROJECT PARTNERS Version 5.0 (15.1.2019) Contents 1. Introduction... 3 2. Starting up the project... 4 2.1. Fulfilling conditions... 5 2.2. Hand

More information

Fact Sheet 14 - Partnership Agreement

Fact Sheet 14 - Partnership Agreement - Partnership Agreement Valid from Valid to Main changes Version 2 27.04.15 A previous version was available on the programme website but all projects must use this version. Core message: It is a regulatory

More information

Annex 3 First level control report including checklist

Annex 3 First level control report including checklist European Union European Regional Development Fund Sharing solutions for better regional policies Anne 3 First level control report including checklist The first level control report and checklist constitute

More information

UKF Project Monitoring Guidelines Version 4

UKF Project Monitoring Guidelines Version 4 REPUBLIC OF CROATIA MINISTRY OF SCIENCE, EDUCATION AND SPORTS UKF Project Monitoring Guidelines Version 4 UNITY THROUGH KNOWLEDGE FUND office@ukf.hr, www.ukf.hr, +385 1 2352 685 Planinska 1, HR-10000 Zagreb,

More information

UN-Habitat Policy For Implementing Partners. UN-Habitat. Policy For. Partners

UN-Habitat Policy For Implementing Partners. UN-Habitat. Policy For. Partners UN-Habitat Policy For Implementing Partners 01 Version Date Author/Reviewer Status V1 06.12.2016 Mohamed Robleh Circulated for SMB comments V2 27.01.2017 Andrew Cox Approved For further information, please

More information

CONSOLIDATED PROGRESS REPORT FORM including guidelines

CONSOLIDATED PROGRESS REPORT FORM including guidelines CONSOLIDATED PROGRESS REPORT FORM including guidelines GET ACQUAINTED WITH PROGRAMME MANUAL AND APPROPRIATE NATIONAL GUIDELINES BEFORE FILLING IN PROGRESS / CONSOLIDATED PROGRESS REPORT PLEASE NOTE THAT

More information

Checklist for Assessing Action Budget and Simplified Cost Options for Grant Contracts

Checklist for Assessing Action Budget and Simplified Cost Options for Grant Contracts Checklist for Assessing Action Budget and Simplified Cost Options for Grant Contracts The checklist is composed of procedures and checks that apply to - each cost category / subcategory - specific cost

More information

First Level Control of finance and activities: The Programme rules

First Level Control of finance and activities: The Programme rules First Level Control of finance and activities: The Programme rules First Level Control seminar Germany Hamburg, 6 September 2016 Carsten Westerholt and Christian Byrith Agenda a lot of information presented

More information

Overview of Dormant Accounts Fund (DAF) Support Event Financial Guidance Capital Projects July 2017

Overview of Dormant Accounts Fund (DAF) Support Event Financial Guidance Capital Projects July 2017 Overview of Dormant Accounts Fund (DAF) Support Event Financial Guidance Capital Projects July 2017 OVERVIEW Payment and Return Cycle summary Payment of Grant Aid Financial Reporting - Eligibility of Expenditure

More information

ASEAN-ROK Cooperation Fund (AKCF) Manual

ASEAN-ROK Cooperation Fund (AKCF) Manual ASEAN-ROK Cooperation Fund (AKCF) Manual Working Draft Prepared by ASEAN-ROK Programme Management Team (AKPMT) 1 P a g e Table of Contents 1. Introduction: How to use this Manual 1.1 Objective 1.2 Target

More information

INTERNATIONAL ORGANISATIONS QUESTIONS

INTERNATIONAL ORGANISATIONS QUESTIONS INTERNATIONAL ORGANISATIONS QUESTIONS A. General 1. What is an International Organisation? An international Organisation can only be considered as such under the Financial Regulation if the following criteria

More information

A CEPR / DFID Research Initiative MAJOR RESEARCH GRANT BUDGET GUIDELINES

A CEPR / DFID Research Initiative MAJOR RESEARCH GRANT BUDGET GUIDELINES Coordinated by: In partnership with: A CEPR / DFID Research Initiative MAJOR RESEARCH GRANT BUDGET GUIDELINES 2017-2020 Contents 1 Introduction... 2 2 General rules... 2 3 Definition of Costs... 2 3.1

More information

RECOMMENDATIONS FOR PROJECT

RECOMMENDATIONS FOR PROJECT Memo RECOMMENDATIONS FOR PROJECT 0 IMPLEMENTATION ACCORDING TO DEVELOPMENT COOPERATION AND DEMOCRACY PROMOTION PROGRAM BY THE MINISTRY OF FOREIGN AFFAIRS Requirements Mistakes Tips TABLE OF CONTENTS INTRODUCTION...1

More information

FinancialGuidelines forunitaidgrantees

FinancialGuidelines forunitaidgrantees FinancialGuidelines forunitaidgrantees 6April2018 Table of Contents Purpose and Scope... 4 General Funding Principles... 5 Budgeting... 8 Budget Management... 10 Disbursements... 12 Financial Reporting...

More information

Version: 14 June, IKI Guidelines for international applicants

Version: 14 June, IKI Guidelines for international applicants Version: 14 June, 2017 IKI Guidelines for international applicants Table of Contents A. General Information about the International Climate Initiative... 4 B. Project Outline... 4 B.1 Applicants... 4 B.2

More information

CHECK-LIST FOR CONTROLLERS/AUDITORS

CHECK-LIST FOR CONTROLLERS/AUDITORS Managing Authority Ministry of Finance of the Republic of Estonia Estonia Russia Cross Border Cooperation Programme 2014 2020 CHECK-LIST FOR CONTROLLERS/AUDITORS Template of control check-list Audit firm/public

More information

Annex VI. Model terms of reference for the Certificate on the Financial Statements

Annex VI. Model terms of reference for the Certificate on the Financial Statements Annex VI Pielikums Nr.2 Model terms of reference for the Certificate on the Financial Statements 1. Audit objectives The certificate on the financial statements and underlying accounts, produced by an

More information

TERMS OF REFERENCE FOR PROJECT ANNUAL EXTERNAL AUDIT

TERMS OF REFERENCE FOR PROJECT ANNUAL EXTERNAL AUDIT TERMS OF REFERENCE FOR PROJECT ANNUAL EXTERNAL AUDIT I. INTRODUCTION Marie Stopes International Afghanistan, MSIA, wishes to engage the services of an audit firm, the Auditor, for the purpose of auditing

More information

Project Administration

Project Administration Co-funded by the European Union Project Administration Maria Grazia Bonanomi, UCSC Diverse Kick-off meeting - Milan, 22-24 January 2014 Outline: - Context - Key features - Final Reporting Package - Eligible

More information

CDKN Expenses Policy

CDKN Expenses Policy CDKN Expenses Policy Principal guidelines for suppliers August 2015 Climate & Development Knowledge Network CDKN Expenses Policy August 2015 Page 1 of 13 Contents 1. Introduction 3 2. Expenses Policy 4

More information

First Level Control of finance and activities: The Programme rules

First Level Control of finance and activities: The Programme rules First Level Control of finance and activities: The Programme rules First Level Control seminar Norway Oslo, 23 January 2017 Carsten Westerholt and Christian Byrith Agenda a lot of information presented

More information

Guide for Applicants

Guide for Applicants The Romanian-EEA Research Programme 2012-2017 RO14 - Programme Area: Research within priority Sectors Monica Cruceru Program Coordinator UEFISCDI I. Definitions II. Eligibility of applicants and project

More information

Annex 1. ISP Guidelines for financial administration Reporting, audit, procurement, revised budget and requests

Annex 1. ISP Guidelines for financial administration Reporting, audit, procurement, revised budget and requests International Science Programme (ISP) Uppsala University Revised Jan 2019 Annex 1. ISP Guidelines for financial administration Reporting, audit, procurement, revised budget and requests Contents Requests

More information

III. modus operandi of Tier 2

III. modus operandi of Tier 2 III. modus operandi of Tier 2 Objective, country and project eligibility 70 Budget and timing 71 Project preparation: formulation of proposals 71 Project appraisal 72 Project approval 73 Agreements and

More information

LIFE Grant Agreement Financial Aspects Highlights

LIFE Grant Agreement Financial Aspects Highlights LIFE Grant Agreement Financial Aspects Highlights Kick-off Meetings Call 2016 Action Grants Strand buddies (EASME) Congratulations for obtaining the Grant! And Welcome to the Finance presentation SUMMARY

More information

Financial Instructions No 1 of 2017 Examination of Payment Vouchers Prior to Disbursement

Financial Instructions No 1 of 2017 Examination of Payment Vouchers Prior to Disbursement Financial Instructions Examination of Payment Vouchers Prior to Disbursement Financial Instructions No 1 of 2017 Examination of Payment Vouchers Prior to Disbursement 1. The following financial instructions

More information

Guidelines for financial reporting of projects funded by Otto per Mille of the Waldensian Church of Italy (Union of Methodist and Waldensian Churches)

Guidelines for financial reporting of projects funded by Otto per Mille of the Waldensian Church of Italy (Union of Methodist and Waldensian Churches) Guidelines for financial reporting of projects funded by Otto per Mille of the Waldensian Church of Italy (Union of Methodist and Waldensian Churches) Projects approved in 2017 1. Grant Disbursement procedure

More information

IN2IT FINANCIAL WORKSHOP

IN2IT FINANCIAL WORKSHOP IN2IT FINANCIAL WORKSHOP DR. VERED HOLZMANN IN2IT PROJECT MANAGER MTA, 13 MARCH 2016 Agenda Part A: Erasmus+ Office: Rationale of the Erasmus+ budget management Unit costs vs. Actual costs Control unit

More information

Control activities that are part of the process are detailed in the riskcontrol

Control activities that are part of the process are detailed in the riskcontrol Policy Title Previous title (if any) Cash Transfers to Implementing Partners N/A Policy objective Target audience Risk control matrix Checklist The policy and procedures outline the process for management

More information

Bilateral Guideline. EEA and Norwegian Financial Mechanisms

Bilateral Guideline. EEA and Norwegian Financial Mechanisms Bilateral Guideline EEA and Norwegian Financial Mechanisms 2014 2021 Adopted by the Financial Mechanism Committee on 9 February 2017 09 February 2017 Contents 1 Introduction... 4 1.1 Definition of strengthened

More information

IKI Guidelines for international applicants - IKI Selection Procedure 2018

IKI Guidelines for international applicants - IKI Selection Procedure 2018 IKI Guidelines for international applicants - IKI Selection Procedure 2018 Effective until replaced Note: Modifications because of the new IKI Funding Information for the IKI selection procedure 2018 are

More information

Market Replication: Eco-Innovation F I N A N C I A L G U I D E L I N E S for co-ordinators and co-beneficiaries

Market Replication: Eco-Innovation F I N A N C I A L G U I D E L I N E S for co-ordinators and co-beneficiaries Market Replication: Eco-Innovation 2008-2013 F I N A N C I A L G U I D E L I N E S for co-ordinators and co-beneficiaries I ACCOUNTING DOCUMENTS 2 II COST REIMBURSEMENT 3 III WHAT ARE ELIGIBLE COSTS? 4

More information

First level control report including checklist

First level control report including checklist First level control report including checklist Project title Project acronym Project number Report Number 1. Project and progress report Name 2. Project Partner Name Organisation Job title Division/Unit/Department

More information

KA2 Strategic Partnerships Financial Management. 21st September

KA2 Strategic Partnerships Financial Management. 21st September KA2 Strategic Partnerships Financial Management 21st September 2017 Leargas.Ireland @Leargas www.leargas.ie 1 Overview General Principles of Financial Management Eligibility of Expenses (eligible and ineligible

More information

HEQCO REQUEST FOR PROPOSAL (RFP) INSTRUCTIONS PROPOSAL SUBMISSION INSTRUCTIONS

HEQCO REQUEST FOR PROPOSAL (RFP) INSTRUCTIONS PROPOSAL SUBMISSION INSTRUCTIONS HEQCO REQUEST FOR PROPOSAL (RFP) INSTRUCTIONS PROPOSAL SUBMISSION INSTRUCTIONS Proposals are to be submitted according to the following method: 1. Proposal submission must contain one (1) electronic copy

More information

WHITFIELD COUNTY, GEORGIA PURCHASING POLICY AND MANUAL January 14, 2014

WHITFIELD COUNTY, GEORGIA PURCHASING POLICY AND MANUAL January 14, 2014 1 WHITFIELD COUNTY, GEORGIA PURCHASING POLICY AND MANUAL January 14, 2014 WHITFIELD COUNTY, GEORGIA PURCHASING POLICY AND MANUAL TABLE OF CONTENTS Purchasing Policy Introduction... 3 Policy Specifics...

More information

Guideline for strengthened bilateral relations. EEA and Norway Grants

Guideline for strengthened bilateral relations. EEA and Norway Grants Guideline for strengthened bilateral relations EEA and Norway Grants 2009 2014 Adopted by the Financial Mechanism Committee 29.03.2012, amended on 28 January 2016 Contents 1 Purpose of the guideline...

More information

Factsheet N 6 Project implementation: delivering project outputs, achieving project objectives and bringing about the desired change

Factsheet N 6 Project implementation: delivering project outputs, achieving project objectives and bringing about the desired change Project implementation: delivering project outputs, achieving project objectives and bringing about the desired change Version No 13 of 23 November 2018 Table of contents I. GETTING STARTED: THE INITIATION

More information

BID FOR HIRING OF AGENCY FOR PRINTING JOBS IN CONSULTANCY DEVELOPMENT CENTRE (CDC) CONSULTANCY DEVELOPMENT CENTRE

BID FOR HIRING OF AGENCY FOR PRINTING JOBS IN CONSULTANCY DEVELOPMENT CENTRE (CDC) CONSULTANCY DEVELOPMENT CENTRE BID FOR HIRING OF AGENCY FOR PRINTING JOBS IN CONSULTANCY DEVELOPMENT CENTRE (CDC) CONSULTANCY DEVELOPMENT CENTRE (Autonomous Institution of DSIR, Ministry of Science & Technology) 2 nd Floor, Core IV-B,

More information

Audit certificate template for Horizon2020 projects funded by SERI

Audit certificate template for Horizon2020 projects funded by SERI Audit certificate template for Horizon2020 projects funded by SERI Under Article 4.1 of the subsidy agreement concluded between SERI and the Swiss research institution (hereinafter referred to as beneficiary),

More information

Financial Reporting. Tempus IV. Kyiv-Mohyla Academy Kiev 16 November Ana Ramon de la Cruz and Giulia Moro

Financial Reporting. Tempus IV. Kyiv-Mohyla Academy Kiev 16 November Ana Ramon de la Cruz and Giulia Moro Financial Reporting Tempus IV Kyiv-Mohyla Academy Kiev 16 November 2016 Ana Ramon de la Cruz and Giulia Moro 1 1. General principles Exchange rate Co-financing Transfer of money 2. Budget headings (purpose,

More information

Accounting Qualification. Indirect Tax (Level 3) Reference material

Accounting Qualification. Indirect Tax (Level 3) Reference material Accounting Qualification Indirect Tax (Level 3) Reference material The Association of Accounting Technicians December 2010 Reference material for AAT assessment of Indirect Tax Introduction This document

More information

Guide to Financial Issues relating to ICT PSP Grant Agreements

Guide to Financial Issues relating to ICT PSP Grant Agreements DG COMMUNICATIONS NETWORKS, CONTENT AND TECHNOLOGY ICT Policy Support Programme Competitiveness and Innovation Framework Programme Guide to Financial Issues relating to ICT PSP Grant Agreements Version

More information

Mono-Beneficiary Model Grant Agreement

Mono-Beneficiary Model Grant Agreement Justice Programme & Rights, Equality and Citizenship Programme Mono-Beneficiary Model Grant Agreement (JUST/REC MGA Mono) Version 2.0 10 January 2017 Disclaimer This document is aimed at assisting applicants

More information

Education, Audiovisual and Culture Executive Agency GRANT AGREEMENT FOR AN ACTION WITH MULTIPLE BENEFICIARIES

Education, Audiovisual and Culture Executive Agency GRANT AGREEMENT FOR AN ACTION WITH MULTIPLE BENEFICIARIES Education, Audiovisual and Culture Executive Agency «DEFU_UNOP» GRANT AGREEMENT FOR AN ACTION WITH MULTIPLE BENEFICIARIES Mixed financing (reimbursement based on percentage of eligible costs and lump sum(s)

More information

IPA partners seminar. Eligibility of expenditure and specificities of the public procurement. Dubrovnik, 5 th February 2013

IPA partners seminar. Eligibility of expenditure and specificities of the public procurement. Dubrovnik, 5 th February 2013 IPA partners seminar Eligibility of expenditure and specificities of the public procurement Dubrovnik, 5 th February 2013 Index Reference documents Eligibility: General rules Timeframe Budget lines Supporting

More information

GUIDELINES FOR CCM FUNDING

GUIDELINES FOR CCM FUNDING GUIDELINES FOR CCM FUNDING Overview 1. In recognition of the important role of Country Coordinating Mechanisms 1 ( CCMs ) in the Global Fund architecture (including their central role in proposal development,

More information

Tender Specifications attached to the Invitation to tender

Tender Specifications attached to the Invitation to tender Ref. Ares(2015)3457155-20/08/2015 Tender Specifications attached to the Invitation to tender Brussels, 20/08/2015 Invitation to tender N SRB/NEG/1/2015 for the provision of legal advice for bridge financing

More information

World Bank HIV/AIDS Program

World Bank HIV/AIDS Program blic Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized World Bank HIV/AIDS Program A Guidance Note on Disbursement Procedures This document was

More information

GRANT AGREEMENT / DONATION CONTRACT NO... Article 1. General Provisions

GRANT AGREEMENT / DONATION CONTRACT NO... Article 1. General Provisions Project Rural and Regional Development Support to the Republic of Serbia is financed by the Swiss Agency for Development and Cooperation (hereinafter referred to as: Donor ) and implemented by a NIRAS

More information

GUIDELINES FOR APPLICANTS FOR EU FUNDING OF PLANT HEALTH EMERGENCY MEASURES

GUIDELINES FOR APPLICANTS FOR EU FUNDING OF PLANT HEALTH EMERGENCY MEASURES EUROPEAN COMMISSION DIRECTORATE-GENERAL FOR HEALTH AND FOOD SAFETY Food chain: Stakeholders and International Relations Food Safety Programmes, Emergency Funding SANTE/10527/2016/Rev 2, GUIDELINES FOR

More information

] DISBURSEMENT PROCEDURES

] DISBURSEMENT PROCEDURES ] DISBURSEMENT PROCEDURES 1.1 General: The purpose of guidelines contained herein is to lay down the Disbursement Procedures for the projects funded by the SAARC DEVELOPMENT FUND (SDF). It intends to provide

More information

Interreg Nord

Interreg Nord Interreg Nord 2014-2020 Programme area Nord and Sápmi First level control in Nord programme Sweden centralized system for FLC Two FLC at County Administrative Board of Norrbotten, placed in Luleå Finland

More information

Council, 4 December 2014 Proposed changes to Financial Regulations and Scheme of Delegation

Council, 4 December 2014 Proposed changes to Financial Regulations and Scheme of Delegation Council, 4 December 2014 Proposed changes to Financial Regulations and Scheme of Delegation Executive summary and recommendations Introduction The finance systems upgrade project together with forthcoming

More information

Regulation on the implementation of the European Economic Area (EEA) Financial Mechanism

Regulation on the implementation of the European Economic Area (EEA) Financial Mechanism the European Economic Area (EEA) Financial Mechanism 2014-2021 Adopted by the EEA Financial Mechanism Committee pursuant to Article 10.5 of Protocol 38c to the EEA Agreement on 8 September 2016 and confirmed

More information

TERMS OF REFERENCE (TOR) FOR AUDITS OF UN-WOMEN NGO, GOV T, IGO AND GRANT PROJECTS

TERMS OF REFERENCE (TOR) FOR AUDITS OF UN-WOMEN NGO, GOV T, IGO AND GRANT PROJECTS TERMS OF REFERENCE (TOR) FOR AUDITS OF UN-WOMEN NGO, GOV T, IGO AND GRANT PROJECTS TABLE OF CONTENTS Introduction... 3 A. Background... 7 B. Project Management... 7 C. Consultations with concerned parties...

More information

1 st call for proposals, 2 nd call for proposals, Priority 3 Better network of harbours version

1 st call for proposals, 2 nd call for proposals, Priority 3 Better network of harbours version 1 st call for proposals, 2 nd call for proposals, Priority 3 Better network of harbours version 14.09.16 Annex 2 Revenue Guidelines Table of contents Table of contents 1 1. Abbreviations and definitions

More information

Producer Organisation Scheme

Producer Organisation Scheme EMFF Operational Programme 2014-2020 Producer Organisation Scheme 2014-15 EUROPEAN UNION This measure is part-financed by the European Maritime and Fisheries Fund Ireland s EU Structural and Investment

More information

PROCEDURE FOR THE USE OF CORPORATE CREDIT CARD FOR THE BENEFIT OF INSTITUTIONAL RESEARCH DEVELOPMENT

PROCEDURE FOR THE USE OF CORPORATE CREDIT CARD FOR THE BENEFIT OF INSTITUTIONAL RESEARCH DEVELOPMENT CERTIFIED TRANSLATION Central Administration of the University of Puerto Rico Finance Circular 15-25 RECTORS, DEANS OF ACADEMIC AFFAIRS, DEAN OF ADMINISTRATION, DIRECTORS OF FINANCE AND DIRECTORS OF ACCOUNTING

More information

b) Annex II: Proposal Submission Form, to be completed and returned with your proposal; and

b) Annex II: Proposal Submission Form, to be completed and returned with your proposal; and Dear Sir/Madam, Subject: Request for Proposals for [Provision of Cash Delivery Services] Project no. Multiple 1. The United Nations Office for Project Services (UNOPS) is seeking qualified offers for the

More information

European Commission Directorate General for Development and Cooperation - EuropeAid

European Commission Directorate General for Development and Cooperation - EuropeAid European Commission Directorate General for Development and Cooperation - EuropeAid Practical guide to procedures for programme estimates (project approach) Version 4.0 December 2012 CONTENTS 1. INTRODUCTION...

More information

REQUEST FOR VERIFICATION

REQUEST FOR VERIFICATION Copy No: 01 Page 1 of 12 REQUEST FOR VERIFICATION I, (state full names of Applicant) duly authorized representative of (hereinafter referred to as the Measured Entity ), hereby request 1 NET BEE EMPOWERED

More information

صندوق تطوير وا قراض البلديات Muncipal Development & Lending Fund MDLF CAPACITY BUILDING

صندوق تطوير وا قراض البلديات Muncipal Development & Lending Fund MDLF CAPACITY BUILDING صندوق تطوير وا قراض البلديات Muncipal Development & Lending Fund MDLF CAPACITY BUILDING A practical training manual March, 2010 Preface The Municipal Development and Lending Fund (MDLF) is a sustainable

More information

NEPAD/Spanish Fund for African Women s empowerment

NEPAD/Spanish Fund for African Women s empowerment NEPAD/Spanish Fund for African Women s empowerment Project Proposal Format Annex 0 1 P age Proposal Format Proposal Cover Page: PROPOSAL TO THE NEPAD- SPANISH FUND FOR AFRICAN WOMEN s EMPOWERMENT Organization

More information

DESK REVIEW UNDP AFGHANISTAN OVERSIGHT OF THE MONITORING AGENT OF THE LAW AND ORDER TRUST FUND FOR AFGHANISTAN

DESK REVIEW UNDP AFGHANISTAN OVERSIGHT OF THE MONITORING AGENT OF THE LAW AND ORDER TRUST FUND FOR AFGHANISTAN UNITED NATIONS DEVELOPMENT PROGRAMME DESK REVIEW OF UNDP AFGHANISTAN OVERSIGHT OF THE MONITORING AGENT OF THE LAW AND ORDER TRUST FUND FOR AFGHANISTAN Report No. 1310 Issue Date: 9 October 2014 Table of

More information

Certification of Financial Statements for ICT PSP projects

Certification of Financial Statements for ICT PSP projects DG INFORMATION SOCIETY AND MEDIA ICT Policy Support Programme Competitiveness and Innovation Framework Programme Certification of Financial Statements for ICT PSP projects Version 1.0 (03-03-2008) Certification

More information

MODEL FOR THE CERTIFICATE ON THE FINANCIAL STATEMENTS

MODEL FOR THE CERTIFICATE ON THE FINANCIAL STATEMENTS Grant Agreement number: [insert number] [insert acronym] [insert call identifier of the master call] H2020 Model Grant Agreement: Multi-beneficiary General MGA: December 2013 ANNEX 5 MODEL FOR THE CERTIFICATE

More information

Office of the Auditor General of Norway. Handbook for the Office of the Auditor General s Development Cooperation

Office of the Auditor General of Norway. Handbook for the Office of the Auditor General s Development Cooperation Office of the Auditor General of Norway Handbook for the Office of the Auditor General s Development Cooperation i Photo: The Office of the Auditor General of Norway Illustration: Lobo Media AS March 2009

More information

e.com-cert Ltd. General business conditions and certification rules

e.com-cert Ltd. General business conditions and certification rules Area of validity Current regulation details the general business and certification conditions of e.com-cert Ltd. which is deemed obligatory to itself, and handled as contractual agreement towards its partners.

More information

INSTRUCTIONS TO BIDDERS

INSTRUCTIONS TO BIDDERS INSTRUCTIONS TO BIDDERS All University of Alabama Solicitations are made upon and subject to the following conditions, if applicable, unless otherwise noted in the Solicitation: 1.0 Definitions 1.1 The

More information

The UN Trust Fund to End Violence against Women Annex 3: Budget Guidelines

The UN Trust Fund to End Violence against Women Annex 3: Budget Guidelines Contents The UN Trust Fund to End Violence against Women Annex 3: Budget Guidelines 1. General Guidelines & Requirements... 1 2. Budget for Project Activities... 2 3. Budget for M&E/Audit/Management Costs...

More information

Investing in your future

Investing in your future Investing in your future ESF Certifying Authority, Department of Education and Skills Circular 1/2012 (Replacing ESF Certifying Authority, Department of Enterprise Trade and Employment Circular 1/2008)

More information

Page 1 of 22 Catholic Charities Spokane Policy & Procedures Financial Management (FIN) APPROVED BY EXECUTIVE DIRECTOR APPROVED BY BOARD OF DIRECTORS

Page 1 of 22 Catholic Charities Spokane Policy & Procedures Financial Management (FIN) APPROVED BY EXECUTIVE DIRECTOR APPROVED BY BOARD OF DIRECTORS Page 1 of 22 APPROVED BY EXECUTIVE DIRECTOR SIGNATURE DATE APPROVED BY BOARD OF DIRECTORS SIGNATURE (Chief Representative) DATE TITLE: Financial Management POLICY: s financial accountability and viability

More information

Audit certificates. Training Seminar Brussels 28 November 2006

Audit certificates. Training Seminar Brussels 28 November 2006 Audit certificates Training Seminar Brussels 28 November 2006 Overview Introduction Audit certificate requirements What When By whom Audit certificate template Audit certificate guidance notes for contractors

More information

Guide to delivering European funding

Guide to delivering European funding Guide to delivering European funding Section eight: Costs and expenditure 1 Section eight: Costs and expenditure (v8.0 23 May 2017) About this guide This is just one section in a series of fifteen guidance

More information

ANNEX K GUIDELINES and CHECKLIST for assessing ACTION BUDGETs and SIMPLIFIED COST OPTIONS for Union financed GRANT CONTRACTS

ANNEX K GUIDELINES and CHECKLIST for assessing ACTION BUDGETs and SIMPLIFIED COST OPTIONS for Union financed GRANT CONTRACTS ANNEX K GUIDELINES and CHECKLIST for assessing ACTION BUDGETs and SIMPLIFIED COST OPTIONS for Union financed GRANT CONTRACTS Introduction This document includes guidance and a checklist for the Contracting

More information

EUROPEAN COMMISSION DIRECTORATE-GENERAL FOR HUMANITARIAN AID AND CIVIL PROTECTION - ECHO

EUROPEAN COMMISSION DIRECTORATE-GENERAL FOR HUMANITARIAN AID AND CIVIL PROTECTION - ECHO EUROPEAN COMMISSION DIRECTORATE-GENERAL FOR HUMANITARIAN AID AND CIVIL PROTECTION - ECHO FRAMEWORK PARTNERSHIP AGREEMENT WITH INTERNATIONAL ORGANISATIONS PREAMBLE 1 The European Union's humanitarian action

More information

8 th Financial Managers Seminar

8 th Financial Managers Seminar 2002-2012 A Decade of Territorial Evidence 8 th Financial Managers Seminar Athens, 7 March 2013 Reporting expenditure, eligibility, audit trail Reporting documents Activity Report (individual partner Activity

More information

Guidance: Transition between Allocation Utilization Periods

Guidance: Transition between Allocation Utilization Periods Guidance: Transition between Allocation Utilization Periods Version 2 July 2017 In 2014, the Global Fund moved from a Rounds-based funding model to an allocation-based funding model. Whereas the first

More information

FISCAL CONTROLS. Purpose. Policy. Procedure. Date of Approval: August 18, 2013

FISCAL CONTROLS. Purpose. Policy. Procedure. Date of Approval: August 18, 2013 FISCAL CONTROLS Date of Approval: August 18, 2013 Purpose The Board believes in implementing and following fiscal management practices to ensure that the School s funds are appropriately managed in order

More information

External Consultants & General Contractors Contracts

External Consultants & General Contractors Contracts The University of British Columbia Land and Building Services Prepared by: Frank Geyer Work Procedure Approved by: David Barnes External Consultants & General Contractors Contracts Issue Date: 21 November

More information