Reporting and First Level Control of Finance and Activities

Size: px
Start display at page:

Download "Reporting and First Level Control of Finance and Activities"

Transcription

1 Reporting and First Level Control of Finance and Activities First Level Control Seminar, 6/7 October 2010, Bergen Isabella Leong, Jesper Jönsson, Christian Zieske Joint Technical Secretariat Viborg

2 Rules of procedure Informal Feel free to Comment Ask questions...at any time...

3 Purpose of the 1st Level Control workshop Get the correct understanding of the reporting and first level control process Answer all your questions Set your mind for the interactive workshop How to convince the 1st level controller

4 Monitoring from Secretariat s perspective Project progress according to (your own) time plan Activity Finance Ensure that only approved activities are implemented (JTS has a limited mandate regarding deviations) Application Changes 1st level control

5 Secretariat jobs: Check compliance Operational Programme and Fact Sheets, national and EU regulations, report checks, ad-hoc advice monitor progress costed work plan : implementation and spending check and process within limited mandate to take decisions: we only administer the decision taken at Steering Committee

6 Lead Beneficiary Principle : (see OP and Fact Sheet # 5, please!) Continued responsibility for: Project implementation as promised in line with the approved application (and approved changes) and subsidy contract Eligibility of expenditure to trigger co-funding expenditure for approved activities only expenditure controlled by designated controllers controller s opinion is unqualified Transfer of ERDF / -equivalent to beneficiaries and report so, Lead First Level Controller to confirm Protecting the audit trail incl. secured documentation storage

7 Beneficiary Responsibility Beneficiary responsible for its incurred expenditure Beneficiary responsible for securing the audit trail Beneficiary responsible for delivery of the activities as agreed with the Lead Beneficiary and partnership

8 Standard reporting: 6 Steps Beneficiaries Sub-partners First Level Control (FLC) Paying Authority 4. Order to pay Bank(s) F S 3. Checked periodic report 5. Payment F B Secretariat 6. Payment Cover Letter (PCL) 1. Request to report 2. Periodic report Lead Beneficiary F S F B F B S S

9 5 payment 4 order to pay 3 checked periodic report Bank(s) Paying Authority 2 periodic report Secretariat Twice a year: 1 request to report per every 31 March and every 30 Sept. First Level Control Lead Beneficiary Sub-partners Beneficiaries Secretariat

10 5 payment 4 order to pay 3 checked periodic report Bank(s) Certifying Authority 2 periodic report Secretariat 1 request to report per every 31 March and every 30 Sept. 4 weeks at beneficiary level Which means: incl. FLC 2 weeks Lead beneficiary for consolidation incl. FLC First Level Control Lead Beneficiary Sub-partners Beneficiaries Secretariat

11 Reporting procedure I: Twice a year Reporting periods ending end of March & September Standard reporting forms The basic report forms Activity report is part of the financial claim The LB must approve the activity report for the beneficiary claim to be valid Only claims with no qualifications or clear quantifications can be included in the consolidated report by the Lead Beneficiary

12 Reporting procedure II: Deadlines for delivery of the full report 4 weeks for beneficiaries to deliver to LB + 2 weeks for the LB to deliver to JTS Plan well ahead Start before the end of the reporting period Have a well functioning system for daily management E.g. monthly reconciliations, one ring binder per claim updated on current basis Plan for clarifying issues with LB/project controller

13 Before you start thinking about reporting... Get a (good, competent and helpful) controller designated - who can carry out the job at a reasonable price level It is your responsibility to get one Do not be discouraged by the resistance of the system Whatever the excuse, you will not get the money until it is done

14 Before you start thinking about reporting...ii Get a partnership agreement in place signed by all! But do not let the formal processes overshadow the real thing...the project Adapt, run processes simultaneously... Insist on clear guidance from the Lead Beneficiary and the project controller on what is required for reporting... The Manual for First Level Control sets minimum requirements, LB can ask for more Let controllers meet/talk: It sometimes helps!

15 Frequent problems detected: Change the (sub-)project without approvals Forget to inform who is co-funding the project Award contracts without tender Possible but make sure you follow the rules Incur costs without registration in the accounting system Incur staff costs without timesheets Register time only once a month/6 months Leave timesheets without signatures

16 Not so SMART to... Start preparation just before the deadline Will you manage to clarify all issues? The Lead Beneficiary must respect the deadline or the whole project is kept hostage Why are there still open issues before reporting Not to talk to the controller before s/he comes to check you What should be ready, what format, what would help? Manage the process and do not let process manage you

17 Not so SMART to... Not to be consistent between the forms Not to answer all questions in the checklists Double check on controller It is their job - but your money Not to sign the forms You will get them back

18 Why are we so NOT SMART? System consistency You are part of a bigger picture... Have to follow our procedures Checklists can be unforgiving... Strong control focus on IVB Certifying Authority actually active...and strict NOT SMART does not mean unhelpful Let us know if you need help...

19 Important EU regulations: Norwegian beneficiaries of our programme are also subject to these rules! 1083 / 2006 General Provisions (Amendments have been made) 15(1) Additionality 55 Revenue generating projects 56 Eligibility of expenditure 57 Durabilty of operations 60 Functions: managing authority 66 Arrangements: monitoring 69 Information and publicity 72 Responsibilities of the Commission 80 Wholeness of payment to beneficiaries 81 Use of euro 90 Availability of documents 93 Automatic decommitment 102 Repayment 1080 / 2006 European Regional Development Fund 6(2) Territorial Cooperation 7(1) Eligibility of expenditure 13 Rules on eligibility of expenditure 15 Functions of managing authority 16 Control system 17 Financial management 20 Responsibilities of lead/beneficiaries 21 Conditions governing the location of operations 1828 / 2006 Rules for Implementation 8 Information and publicity measures for the public 9 Technical characteristics: information and publicity measures 13 Managing authority 14 Accounting records 15 Audit trail 16 Audit of operations & on the spot 19 Availability of documents 27 Definitions (Irregularities) 28 Initial reporting derogations 29 Urgent cases 30 Reporting of follow up Non-recovery 47ff Eligibility 51 In-kind 52 Overheads 53 Depreciation

20 Programme Rules:

21 Fact Sheets: I Financial Issues # 1 Exchange Rates # 2 Eligible Costs # 3 Auto Decommitment # 4 Public Tendering II Partnership # 5 Lead Beneficiary Principle # 6 Letters of Intent # 7 Public-Private Partnerships # 8 Sub-partners III Application & Approval # 9 Detailed Costed Workplan # 10 Technical Assessment Process IV Reporting # 11 Indicators # 12 Change of Budget # 13 Control and reporting # 14 Publicity Requirements # 15 Preparation Costs

22 Fact Sheet Examples: I Financial Issues, # 2 Eligible Costs Law EU regulations, National Rules (appendix 11 of the Manual) Real costs with supporting accounting evidence Time Submission of application project closure Derogation: Preparation costs Place Eligible area (NUTS 3-codes) 20% / 10% rules Operational Programme, Section Function Project application / approved changes Project relevant

23 Fact Sheet Examples: # 2 Eligible Costs - Staff costs must (excerpt): + Be certified...; + Be additional...; + Be based on documents...; + Be spent...; Unpaid voluntary work and other in-kind contributions are eligible provided that their value can be determined based on the amount of time spent and a standard rate for this time

24 Eligibility? Examples : Meetings in Amsterdam, Berlin, Brussels, London, Stockholm,...

25 Eligibility? Examples : Meetings in Amsterdam, Berlin, Brussels, London, Stockholm,...Outside NSR, but within BSR, NPP, NWE: max. 20% Outside that: max. 10%

26 Eligibility? Examples : Meetings in Amsterdam, Berlin, Brussels, London, Stockholm,...Outside NSR, but within BSR, NPP, NWE: max. 20%...project-relevant? Outside that: max. 10% Fact Sheet 2; Operational Programme section ; Article 56 of Commission Regulation 1083/2006; Articles 7 & 13 of Commission Regulation 1080/2006; Articles 47 ff of Commission Regulation 1828/2006 publicity with correct and complete logos, colours, size?

27 Eligibility? Examples : Meetings in Amsterdam, Berlin, Brussels, London, Stockholm,...Outside NSR, but within whichever is the lower BSR, NPP, NWE: max. 20%...project-relevant? Outside that: max. 10% Fact Sheet 2; Operational Programme section ; Article 56 of Commission Regulation 1083/2006; Articles 7 & 13 of Commission Regulation 1080/2006; Articles 47 ff of Commission Regulation 1828/2006 From the day of receipt of your application, but not without approval of the Steering Committee publicity with correct and complete logos, colours, size? Preparation costs Grant of up to or 2% of the total eligible budget, Only the latest approved contract!

28 Fact Sheet Examples: # 5 Lead Beneficiary Principle - responsibility for (excerpt): + Signing a partnership agreement with all the beneficiaries; + Appointment of a project controller; + Delivering project reports and documentation; + Delivering project outputs; + Production of documents required for control and payments; + Overall project management; + Compliance with public tendering procedures for the entire partnership.

29 Fact Sheet Examples: # 8 Sub-partners - Liabilities (excerpt): Sub-partners shall + Be attached to a full partner - The full partner they are attached to shall act as a first guarantor; + Either sign the joint partnership agreement or a contract with the full partner...; + be responsible and liable for their share; + keep a full audit trail of all invoices and expenses;

30 Fact Sheet Examples: # 8 Sub-partners - Sub-partners report audit: + The 1st level controller shall include on the spot checks at the subpartner s premises depending on his own assessment of the situation, the nature of activities performed by the sub-partner and in line with national rules for 1st level control. + The number of sub-partners shall be evaluated against the specific activities to be executed by the formal partner but should be a manageable number and, in principle, not exceed the number of full partners.

31 F(irst) L(evel) C(ontrol) :

32 Appendices, from First Level Control On Beneficiary Level On Project Level 5 The FLC Checklist 6 7 The Finance report 8 7a NEW: On-the-spot items 8a 10a The Activity report 10 The Mother of All Tables 9

33 Appendices 5 / 6, FLC Checklist Control question yes no n/a comments/ follow-up Does the compiled activity report reflect the individual activity reports sent in by beneficiaries? Have all the expenditure in this accumulated report been incurred for: - the purpose of implementing the operation in accordance with the descriptions provided in the original application or latest changes approved by the secretariat (including the annexes specifying the expenditure for budget lines 6, 8 and 10)? - If there were any deviations please describe them - Have the Lead Beneficiary prepared a change request to be sent with this report? - Does the expenditure incurred correspond to the activities agreed between beneficiary and the Lead Beneficiary? -If there were any deviations have they been clarified between beneficiaries and the Lead Beneficiary? - Does the expenditure reported reflect the implementation situation as described in the activity report, which forms part of this claim?

34 Appendices 5 / 6, FLC Checklist Control question yes no n/a comments/ follow-up Does the compiled activity report reflect the individual activity reports sent in by beneficiaries? Have all the expenditure in this accumulated report been incurred for: - the purpose of implementing the operation in accordance with the descriptions provided in the original application or latest changes approved by the secretariat (including the annexes specifying the expenditure for budget lines 6, 8 and 10)? - If there were any deviations please describe them - Have the Lead Beneficiary prepared a change request to be sent with this report? - Does the expenditure incurred correspond to the activities agreed between beneficiary and the Lead Beneficiary? -If there were any deviations have they been clarified between beneficiaries and the Lead Beneficiary? - Does the expenditure reported reflect the implementation situation as described in the activity report, which forms part of this claim? Please one tick per each question mark!

35 NEW: Appendices 7a & 8a Summary information about on-the-spot verifications Project: Beneficiary/ sub-partner Country 1st level controller details Amount of expenditure declared to the controller On-the-spot verifications of individual operations cf. Article 13.2b (1828/2006) No. Amount verified on-the-spot Date of on-the-spot verification... Date Date Signature by Lead/Beneficiary Signature by beneficiary/project controller Appendix 7a/8a

36 The Audit Trail: Every EURO of project expenditure is traceable: Legal basis: eligible, documented, project related costs Record: public procurement procedures respected Contracts: partnership agreements, order letters, invoices Delivery: proven as actually paid out, carried out, built, written Costs for which there is no project individual invoice: (e.g. overheads): use documents of equivalent probative value Confirm with all, especially smaller private partners: all documentation must be stored until 2023

37 1st level control checklist for accumulated expenditure on project level Does the compiled activity report reflect the individual activity reports sent in by beneficiaries? Have all the expenditure in this accumulated report been incurred for: - the purpose of implementing the operation in accordance with the descriptions provided in the original application or latest changes approved by the secretariat (including the annexes specifying the expenditure for budget lines 6, 8 and 10)? - if there were any deviations please describe them - Have the Lead Beneficiary prepared a change request to be sent with this report? - And corresponds to the activities agreed between beneficiary and the Lead Beneficiary? - If there were any deviations have they been clarified between beneficiaries and the Lead Beneficiary? - Does the expenditure reported reflect the implementation situation as described in the activity report, which forms part of this claim?

38 1st level control checklist for benficiary expenditure

39 Periodical Report on Activities - Content Project summary List of beneficiaries, including sub-partners Changes section Work Package description and activities, results and impacts Transnational partnership Transnational approach Innovation Publicity and communications Project and environmental indicators Enclosures

40 Frequent problems detected: Sign the Activity Report Inactive beneficiaries specify delay in activities Consolidating of beneficiary information Style of reporting Follow-up requests in Concluding Letter (included in the request to September 2010) Indicators Enclosure(s)

41 Is expenditure project-relevant? Project Application Beneficiaries Subbeneficiaries Activities m.investments Results Communication Indicators Activity Report Direct interrelation Beneficiary-level reports

42 Work Package 3 - Deliverables Knowledge transfer, innovation, test bed, demonstration and certification for Ballast Water Treatment Systems (BMTS): Report to assess certification procedures: BWMS Workshop for dissemination of study results and discuss design Report on results of experimental study to improve and expand certification procedures Implementation of procedure and evaluation of BWP: Dissemination workshops, seminars and visits Evaluation of BWP: On-site (harbour) Demonstration centre and workshops on site Wageningen IMARES: Report status mesocom studies and opportunities Experimental studies and redesign

43 Application Activity 1 Budget 100 Payment approved Finance Report Contract Partner Reports Activity: 1.1 Finance: 20 Activity: 1.2 Project Level: Activity Report 100 for Activity 1 occured Finance: 50 Activity: 1.3 Finance: 30 Activity 1 carried out

44 Example: Material Investments E.g.: Education Centre Check application form Correct partner? Corresponds with description? Correct timing? Corresponds with indicative budget? On the spot check, pictures, evidence?

45 It s not always us: Delays please prepare per & Incorrect please follow latest guidance Incomplete please check completeness Incomprehensible please clarify logically NO qualification or CLEAR quantification or DEDUCT until clarification

46 QUESTIONS, QUESTIONS, QUESTIONS...

47 THANK YOU PLEASE USE FOR FUTURE CONTACT

Practical Reporting Do s and Dont s

Practical Reporting Do s and Dont s Practical Reporting Do s and Dont s First Level Control Seminar March 2011 Isabella Leong Joint Technical Secretariat Viborg Rules of procedure Informal Feel free to Comment Ask questions...at any time...

More information

1st Level Control in the North Sea Region Programme

1st Level Control in the North Sea Region Programme 1st Level Control in the North Sea Region Programme First Level Control Seminar, 6/7 October 2010, Bergen Tomasz Petrykowski Joint Technical Secretariat Viborg Relevant bodies of the programme Organisations

More information

FLC Guidance. Page 1. Version. September *Disclaimer: This is a living document and further content will be developed at a later stage.

FLC Guidance. Page 1. Version. September *Disclaimer: This is a living document and further content will be developed at a later stage. FLC Guidance Version September 2017 *Disclaimer: This is a living document and further content will be developed at a later stage. Page 1 Table of Contents... 1 CHAPTER 1 General principles... 3 1.1 Introduction...

More information

Fact Sheet 13 Roles and responsibilities in project partnerships

Fact Sheet 13 Roles and responsibilities in project partnerships Roles and responsibilities in project partnerships Valid from Valid to Main changes Version 3 03.05.17 -Minor wording change recommending the use of the same FLC for local partnerships. -Clarified the

More information

South East Europe (SEE) SEE Control Guidelines

South East Europe (SEE) SEE Control Guidelines South East Europe (SEE) SEE Control Guidelines Version 1.4. Final version approved by the MC 10 th June 2009 1 st amendment to be approved by MC (2.0) 1 CONTENTS 1 Purpose and content of the SEE Control

More information

Factsheet N 6 Project implementation: delivering project outputs, achieving project objectives and bringing about the desired change

Factsheet N 6 Project implementation: delivering project outputs, achieving project objectives and bringing about the desired change Project implementation: delivering project outputs, achieving project objectives and bringing about the desired change Version No 13 of 23 November 2018 Table of contents I. GETTING STARTED: THE INITIATION

More information

Project Implementation Seminar

Project Implementation Seminar Project Implementation Seminar Financial Flows George Papapostolou Financial Officer JS Financial Flows Project implementation lifecycle Cash Flow Pre-Financing Amortization Cash Flow Pre-Financing Estimations

More information

First level control report including checklist

First level control report including checklist First level control report including checklist Project title Project acronym Project number Report Number 1. Project and progress report Name 2. Project Partner Name Organisation Job title Division/Unit/Department

More information

Lead Partner Seminar. JS/MA Riga

Lead Partner Seminar. JS/MA Riga Lead Partner Seminar JS/MA 9.12.2015 Riga Welcome to the Lead Partner Seminar Objective of the day: Give the Lead Partner the needed tools to best implement the project To know where to come with questions

More information

Follow up and reporting procedures. Lead partners seminar 5th targeted call Lydwine Lafontaine

Follow up and reporting procedures. Lead partners seminar 5th targeted call Lydwine Lafontaine Follow up and reporting procedures Lead partners seminar 5th targeted call Lydwine Lafontaine Table of contents Background information Subsidy contract Lead partner principles 1. Progress of the project:

More information

Guidance for reporting

Guidance for reporting Guidance for reporting This document guides lead partners (LP) through the reporting carried out on the ems as foreseen in the subsidy contract and described in the factsheet 4.7 Project reporting. Please

More information

ERDF SUBSIDY CONTRACT NO...

ERDF SUBSIDY CONTRACT NO... The Government Office for Development and European Cohesion Policy, Kotnikova 5, SI 1000 Ljubljana, Slovenia, acting as the Managing Authority of the Cooperation Programme Interreg V-A Slovenia-Hungary

More information

FIRST LEVEL CONTROL: PRINCIPLES AND PRACTICE

FIRST LEVEL CONTROL: PRINCIPLES AND PRACTICE CENTRAL EUROPE PROGRAMME 2007-2013 Project financial management and controls Vienna, 7 th April 2011 FIRST LEVEL CONTROL: PRINCIPLES AND PRACTICE 1. Validation of expenditure: the FLC 2. General principles

More information

Project Monitoring and Reporting Workshop for Interreg programmes

Project Monitoring and Reporting Workshop for Interreg programmes Project Monitoring and Reporting Workshop for Interreg programmes Who, why, how? 21-22 April 2016 Sofia, Bulgaria Interact is co-financed by the European Regional Development Fund (ERDF) Responsibilities

More information

Partnership Agreement between the Lead Partner and the other project partners

Partnership Agreement between the Lead Partner and the other project partners Partnership Agreement between the Lead Partner and the other project partners Foreword This Partnership Agreement is signed on the basis of the following documents that form the legal framework applicable

More information

First Level Control of finance and activities: The Programme rules

First Level Control of finance and activities: The Programme rules First Level Control of finance and activities: The Programme rules First Level Control seminar Germany Hamburg, 6 September 2016 Carsten Westerholt and Christian Byrith Agenda a lot of information presented

More information

How to close the project

How to close the project Training on Project & Financial Management and Communication; Vienna, 11-12 September 2013 How to close the project JTS CENTRAL EUROPE Agenda of the workshop Time span from 10h30 13h00 Welcome Presentation

More information

Project Progress Report User Guide

Project Progress Report User Guide Project Progress Report User Guide Transnational Cooperation Programme Interreg Balkan-Mediterranean 2014-2020 CCI 2014TC16M4TN003 Balkan-Mediterranean is co-financed by European Union and National Funds

More information

Control Guidelines for INTERREG IPA CBC Programmes

Control Guidelines for INTERREG IPA CBC Programmes Control Guidelines for INTERREG IPA CBC Programmes Version 3.0 June 2018-1 - Contents ABBREVIATIONS 4 1. EXECUTIVE SUMMARY 5 2. LEGISLATIVE AND INSTITUTIONAL FRAMEWORK 5 2.1. European legislative framework

More information

First Level Control of finance and activities: The Programme rules

First Level Control of finance and activities: The Programme rules First Level Control of finance and activities: The Programme rules First Level Control seminar Norway Oslo, 23 January 2017 Carsten Westerholt and Christian Byrith Agenda a lot of information presented

More information

PART 7: OVERVIEW ON PROJECT IMPLEMENTATION PRINCIPLES

PART 7: OVERVIEW ON PROJECT IMPLEMENTATION PRINCIPLES Applicants Manual for the period 2014-2020 Version 1.1 PART 7: OVERVIEW ON PROJECT IMPLEMENTATION PRINCIPLES edited by the Managing Authority/Joint Secretariat Budapest, Hungary, 2015 Applicants Manual

More information

Knowledge and Innovation Consultants. Financial Management and Reporting Greek Magistral Lesson Izmir, 28/06/2011

Knowledge and Innovation Consultants. Financial Management and Reporting Greek Magistral Lesson Izmir, 28/06/2011 Knowledge and Innovation Consultants Financial Management and Reporting Greek Magistral Lesson Izmir, 28/06/2011 Financial Management and Reporting 1 The financial management of a project requires the

More information

Guidance on management verifications Cooperation Programme Interreg V-A Greece - Italy

Guidance on management verifications Cooperation Programme Interreg V-A Greece - Italy Guidance on management verifications Cooperation Programme Interreg V-A Greece - Italy 2014-2020 Greece-Italy v.10 1 Table of contents Introduction 1. General 1.1 Regulatory requirements 1.2 General principles

More information

Guidance for Member States on Preparation, Examination and Acceptance of Accounts

Guidance for Member States on Preparation, Examination and Acceptance of Accounts EGESIF_15_0018-02 final 09/02/2016 EUROPEAN COMMISSION European Structural and Investment Funds Guidance for Member States on Preparation, Examination and Acceptance of Accounts DISCLAIMER: This is a document

More information

Terms of Reference for the Fund Operator The EEA and Norway Grants Global Fund for Regional Cooperation EEA and Norwegian Financial Mechanisms

Terms of Reference for the Fund Operator The EEA and Norway Grants Global Fund for Regional Cooperation EEA and Norwegian Financial Mechanisms Terms of Reference for the Fund Operator The EEA and Norway Grants Global Fund for Regional Cooperation EEA and Norwegian Financial Mechanisms 2014-2021 Table of Contents 1. Introduction... 3 1.1 Objectives

More information

Investing in your future

Investing in your future Investing in your future ESF Certifying Authority, Department of Education and Skills Circular 1/2012 (Replacing ESF Certifying Authority, Department of Enterprise Trade and Employment Circular 1/2008)

More information

INTERREG 2 Seas Mers Zeeën First Level Control Manual

INTERREG 2 Seas Mers Zeeën First Level Control Manual INTERREG 2 Seas Mers Zeeën 2014-2020 First Level Control Manual Version of 29/11/2018 Table of Content 1. INTRODUCTION... 5 1.1. PURPOSE AND OBJECTIVE OF THIS MANUAL... 5 1.2. TERMINOLOGY... 5 2. LEGAL

More information

GUIDE FOR PROJECT IMPLEMENTATION

GUIDE FOR PROJECT IMPLEMENTATION GUIDE FOR PROJECT IMPLEMENTATION PRACTICAL GUIDANCE FOR PROJECT PARTNERS Version 5.0 (15.1.2019) Contents 1. Introduction... 3 2. Starting up the project... 4 2.1. Fulfilling conditions... 5 2.2. Hand

More information

Fact Sheet 14 - Partnership Agreement

Fact Sheet 14 - Partnership Agreement - Partnership Agreement Valid from Valid to Main changes Version 2 27.04.15 A previous version was available on the programme website but all projects must use this version. Core message: It is a regulatory

More information

BALANCE. Reporting, auditing and payment. Kick-off meeting, Copenhagen, Denmark. Jesper H. Andersen 31 August + 1 September 2005

BALANCE. Reporting, auditing and payment. Kick-off meeting, Copenhagen, Denmark. Jesper H. Andersen 31 August + 1 September 2005 BALANCE Reporting, auditing and payment Kick-off meeting, Copenhagen, Denmark 31 August + 1 September 2005 Jesper H. Andersen (jha@dhi.dk) Reporting is based on the project description in the approved

More information

Annex 3 First level control report including checklist

Annex 3 First level control report including checklist European Union European Regional Development Fund Sharing solutions for better regional policies Anne 3 First level control report including checklist The first level control report and checklist constitute

More information

MED PROGRAMME. First Level Control in practice. Most common mistakes - Follow-up measures

MED PROGRAMME. First Level Control in practice. Most common mistakes - Follow-up measures MED PROGRAMME First Level Control in practice Most common mistakes - Follow-up measures Torino 11 April 2011 BACKGROUND Major common mistakes detected during JTS check 1 st and 2 nd PR Delays in finalization

More information

Q&A on simplified cost options in programmes. March 2018 Application, control and audit: use of simplified cost options for staff costs

Q&A on simplified cost options in programmes. March 2018 Application, control and audit: use of simplified cost options for staff costs Q&A on simplified cost options in programmes Application, control and audit: use of simplified cost options for staff costs Disclaimer: Answers to questions presented in this Q&A document have been drafted

More information

Department of Enterprise, Trade & Employment

Department of Enterprise, Trade & Employment Department of Enterprise, Trade & Employment Circular No. ESF/PA/1-2001 31 July 2001 FINANCIAL MANAGEMENT AND CONTROL PROCEDURES FOR THE EUROPEAN SOCIAL FUND (ESF) 2000-2006 1. Background The purpose of

More information

Greece The former Yugoslav Republic of Macedonia IPA Cross-Border Programme SUBSIDY CONTRACT A

Greece The former Yugoslav Republic of Macedonia IPA Cross-Border Programme SUBSIDY CONTRACT A Greece The former Yugoslav Republic of Macedonia IPA Cross-Border Programme 2007-2013 SUBSIDY CONTRACT A No. : < > SUBSIDY CONTRACT No. In Athens, today, the , at the Ministry of Development,

More information

Budget & Finances. Interreg Europe Secretariat. 23 March 2016 Lead applicant workshop. Sharing solutions for better regional policies

Budget & Finances. Interreg Europe Secretariat. 23 March 2016 Lead applicant workshop. Sharing solutions for better regional policies European Union European Regional Development Fund Sharing solutions for better regional policies Budget & Finances Interreg Europe Secretariat 23 March 2016 Lead applicant workshop Session content 1. Preliminary

More information

SMALL PROJECT CONSOLIDATED PROGRESS REPORT FORM including guidelines

SMALL PROJECT CONSOLIDATED PROGRESS REPORT FORM including guidelines SMALL PROJECT CONSOLIDATED PROGRESS REPORT FORM including guidelines GET ACQUAINTED WITH PROGRAMME MANUAL AND APPROPRIATE NATIONAL GUIDELINES BEFORE FILLING IN SMALL PROJECT PROGRESS / CONSOLIDATED PROGRESS

More information

Appointment of a First Level Controller - Statement of Requirements (SOR)

Appointment of a First Level Controller - Statement of Requirements (SOR) Territorial Co-operation Programmes 2014-2020 Appointment of a First Level Controller - Statement of Requirements (SOR) Introduction Beneficiaries participating in Territorial Co-operation Programmes are

More information

Project Selection Criteria Transnational Cooperation Programme Interreg Balkan Mediterranean

Project Selection Criteria Transnational Cooperation Programme Interreg Balkan Mediterranean Project Selection Criteria Transnational Cooperation Programme Interreg Balkan Mediterranean 2014 2020 CCI 2014TC16M4TN003 22/06/2015 Version 1.0 Balkan-Mediterranean is co-financed by European Union and

More information

INTERREG III B CADSES. Payment Claim Manual

INTERREG III B CADSES. Payment Claim Manual INTERREG III B CADSES Payment Claim Manual 1) Background / Description of involved actors The following chapters give a short overview about the actors involved in the PIC Interreg III B Cadses, their

More information

Financial Reporting First Level Control

Financial Reporting First Level Control Financial Reporting First Level Control Xander Storms Frank Everaarts It s not that hard! Report twice a year about content, progress and costs The Lead Beneficiary collects and integrates the data Those

More information

Control and audit. One of the main concerns of the EU COMM. Single audit system recommended by European Court of Auditors:

Control and audit. One of the main concerns of the EU COMM. Single audit system recommended by European Court of Auditors: Control and audit One of the main concerns of the EU COMM. Single audit system recommended by European Court of Auditors: Integrated audit approach whereby the work of auditors at one level may be used

More information

Guidelines for the AF DSP call for proposals

Guidelines for the AF DSP call for proposals Guidelines for the AF DSP call for proposals A stream of cooperation edited by the Managing Authority/Joint Secretariat Budapest, Hungary, 2018 Programme co-funded by the European Union Table of content

More information

Project Implementation. Project Implementation Seminar Monika Balode, Project Coordinator September 2018 Tallinn & Stockholm

Project Implementation. Project Implementation Seminar Monika Balode, Project Coordinator September 2018 Tallinn & Stockholm Project Implementation Project Implementation Seminar Monika Balode, Project Coordinator September 2018 Tallinn & Stockholm Contents Result orientation Cooperation Lead partner principle Guidance documents

More information

Official Journal of the European Union

Official Journal of the European Union 13.5.2014 L 138/5 COMMISSION DELEGATED REGULATION (EU) No 480/2014 of 3 March 2014 supplementing Regulation (EU) No 1303/2013 of the European Parliament and of the Council laying down common provisions

More information

Report on the annual accounts of the European Schools for the financial year together with the Schools replies

Report on the annual accounts of the European Schools for the financial year together with the Schools replies Report on the annual accounts of the European Schools for the financial year 2016 together with the Schools replies 12, rue Alcide De Gasperi - L - 1615 Luxembourg T (+352) 4398 1 E eca-info@eca.europa.eu

More information

CONSOLIDATED PROGRESS REPORT FORM including guidelines

CONSOLIDATED PROGRESS REPORT FORM including guidelines CONSOLIDATED PROGRESS REPORT FORM including guidelines GET ACQUAINTED WITH PROGRAMME MANUAL AND APPROPRIATE NATIONAL GUIDELINES BEFORE FILLING IN PROGRESS / CONSOLIDATED PROGRESS REPORT PLEASE NOTE THAT

More information

Interreg IPA Cross-border Cooperation Programme Greece-Albania

Interreg IPA Cross-border Cooperation Programme Greece-Albania Interreg IPA Cross-border Cooperation Programme Greece-Albania 2014-2020 SUBSIDY CONTRACT No. In Thessaloniki, today, the , at the premises of the Managing Authority located at 65, Leoforos

More information

ANNEX. to the Comission Decision. amending Decision C(2013) 1573

ANNEX. to the Comission Decision. amending Decision C(2013) 1573 EUROPEAN COMMISSION Brussels, 30.4.2015 C(2015) 2771 final ANNEX 1 ANNEX to the Comission Decision amending Decision C(2013) 1573 on the approval of the guidelines on the closure of operational programmes

More information

Financial rules and procedures in Interreg Europe - second call projects

Financial rules and procedures in Interreg Europe - second call projects European Union European Regional Development Fund Sharing solutions for better regional policies Financial rules and procedures in Interreg Europe - second call projects Aleksandra Niechajowicz Finance

More information

How to Prepare the Winding-Up Declaration

How to Prepare the Winding-Up Declaration How to Prepare the Winding-Up Declaration This presentation is a summarisation of a presentation prepared by Marianna Miklós- Molnár, Director of Strategy and Methodology, Directorate General for Audit

More information

INTERREG V-A GREECE-ITALY PROGRAMME PATRA 24/04/2018 PREVEZA 26/04/2018

INTERREG V-A GREECE-ITALY PROGRAMME PATRA 24/04/2018 PREVEZA 26/04/2018 INTERREG V-A GREECE-ITALY PROGRAMME 2014-2020 PATRA 24/04/2018 PREVEZA 26/04/2018 1 FIRST LEVEL CONTROL GUIDELINES & PROCEDURES 2 General Guidelines (1/8) Regulation (EU) 1303/2013, Article 125 Functions

More information

KA2 Strategic Partnerships Financial Management. 21st September

KA2 Strategic Partnerships Financial Management. 21st September KA2 Strategic Partnerships Financial Management 21st September 2017 Leargas.Ireland @Leargas www.leargas.ie 1 Overview General Principles of Financial Management Eligibility of Expenses (eligible and ineligible

More information

Guidance document on. management verifications to be carried out by Member States on operations co-financed by

Guidance document on. management verifications to be carried out by Member States on operations co-financed by Final version of 05/06/2008 COCOF 08/0020/04-EN Guidance document on management verifications to be carried out by Member States on operations co-financed by the Structural Funds and the Cohesion Fund

More information

Table of contents. Introduction Regulatory requirements... 3

Table of contents. Introduction Regulatory requirements... 3 COCOF 08/0020/02-EN DRAFT Guidance document on management verifications to be carried out by Member States on projects co-financed by the Structural Funds and the Cohesion Fund for the 2007 2013 programming

More information

European networks, experience and recommendations helping cities and citizens to become Energy Efficient

European networks, experience and recommendations helping cities and citizens to become Energy Efficient INTERREG IVC European networks, experience and recommendations helping cities and citizens to become Energy Efficient Mini-Programme Manual Updated version 22 February 2011 Mini-Programme Manual EnercitEE

More information

Version 4: 29 th June 2017

Version 4: 29 th June 2017 PROGRAMME RULES INTERREG VA CROSS-BORDER PROGRAMME FOR TERRITORIAL CO-OPERATION 2014-2020 NORTHERN IRELAND, BORDER REGION OF IRELAND AND WESTERN SCOTLAND & PEACE IV EU PROGRAMME FOR PEACE AND RECONCILIATION

More information

ADMINISTRATIVE MANUAL FOR PROJECT IMPLEMENTATION

ADMINISTRATIVE MANUAL FOR PROJECT IMPLEMENTATION ADMINISTRATIVE MANUAL FOR PROJECT IMPLEMENTATION 1. Introduction The purpose of this manual is to give guidance and instructions to Project Developers (PD) on administration of the project implementation

More information

Guidance for Member States on Audit of Accounts

Guidance for Member States on Audit of Accounts EGESIF_15_0016-02 final 29/01/2015 EUROPEAN COMMISSION European Structural and Investment Funds Guidance for Member States on Audit of Accounts DISCLAIMER: This is a document prepared by the Commission

More information

LEADER ICT System User Guide Project Claim

LEADER ICT System User Guide Project Claim LEADER ICT System Guide Project Claim Glossary Abbreviation CRM CRO DRCD EFT EOI LCDC LDC LDS LFP Promoter RDP TCAN TRN Definition Customer Relationship Management Companies Registration Office Department

More information

This document is meant purely as a documentation tool and the institutions do not assume any liability for its contents

This document is meant purely as a documentation tool and the institutions do not assume any liability for its contents 2006R1828 EN 01.12.2011 003.001 1 This document is meant purely as a documentation tool and the institutions do not assume any liability for its contents B C1 COMMISSION REGULATION (EC) No 1828/2006 of

More information

CENTRAL EUROPE Implementation Manual IMPLEMENTATION MANUAL

CENTRAL EUROPE Implementation Manual IMPLEMENTATION MANUAL IMPLEMENTATION MANUAL 1 TABLE OF CONTENTS 0. INTRODUCTION NOTE... 3 1. START-UP PHASE... 4 1.1 Subsidy Contract... 5 1.2 Partnership Agreement... 6 1.3 Setting-up project structures... 7 1.4 Start-up report...

More information

Greece The former Yugoslav Republic of Macedonia IPA Cross-Border Programme OVERALL CONTRACT. Document No. 12.1: OVERALL MA CONTRACT

Greece The former Yugoslav Republic of Macedonia IPA Cross-Border Programme OVERALL CONTRACT. Document No. 12.1: OVERALL MA CONTRACT Greece The former Yugoslav Republic of Macedonia IPA Cross-Border Programme 2007-2013 OVERALL CONTRACT No. : < > Document No. 12.1: OVERALL MA CONTRACT OVERALL CONTRACT No. In Athens, today, the

More information

F A C T S H E E T PROGRAMME MANUAL. Interreg IPA CBC Italy Albania Montenegro Programme. 4.7 Project changes and ems procedures

F A C T S H E E T PROGRAMME MANUAL. Interreg IPA CBC Italy Albania Montenegro Programme. 4.7 Project changes and ems procedures F A C T S H E E T Interreg IPA CBC Italy Albania Montenegro Programme PROGRAMME MANUAL 4.7 Project changes and ems procedures Current version 01 Updated 1 October 2018 Contacts js@italy-albania-montenegro.eu

More information

Guidance for Member States on Article 41 CPR - Requests for payment

Guidance for Member States on Article 41 CPR - Requests for payment EGESIF_15-0006-01 08/06/2015 EUROPEAN COMMISSION European Structural and Investment Funds Guidance for Member States on Article 41 CPR - Requests for payment DISCLAIMER This is a working document prepared

More information

Fact Sheet; Errors, financial corrections, irregularities, recoveries and withdrawals

Fact Sheet; Errors, financial corrections, irregularities, recoveries and withdrawals The 2014 2020 Interreg Programme Management Handbook is composed of fact sheets. Each theme is covered by one fact sheet so that the reader can easily and quickly choose the relevant fact sheet. Fact Sheet;

More information

GUIDELINES FOR FIRST LEVEL CONTROL on CBC Programmes, co-financed by IPA BULGARIA - SERBIA BULGARIA - MACEDONIA BULGARIA - TURKEY

GUIDELINES FOR FIRST LEVEL CONTROL on CBC Programmes, co-financed by IPA BULGARIA - SERBIA BULGARIA - MACEDONIA BULGARIA - TURKEY GUIDELINES FOR FIRST LEVEL CONTROL on CBC Programmes, co-financed by IPA BULGARIA - SERBIA BULGARIA - MACEDONIA BULGARIA - TURKEY Version* Date: Notes 1.1. May, 2011 Final approved version, valid for BG

More information

ELIGIBILITY OF EXPENSES: APPLICABLE RULES

ELIGIBILITY OF EXPENSES: APPLICABLE RULES INFO DAY ON PROJECT IMPLEMENTATION 1 ST CALL FOR PROJECT PROPOSALS ELIGIBILITY OF EXPENSES: APPLICABLE RULES Hierarchy of rules on eligibility of expenditure Rules defined in EU legal framework ERDF Programme

More information

on the Parallel Audit on by the Working Group on Structural Funds

on the Parallel Audit on by the Working Group on Structural Funds Report to the of the heads of the Supreme Audit Institutions of the Member States of the European Union and the European Court of Auditors on the Parallel Audit on by the Working Group on Structural Funds

More information

CENTRAL EUROPE Control and Audit Guidelines TABLE OF CONTENTS

CENTRAL EUROPE Control and Audit Guidelines TABLE OF CONTENTS TABLE OF CONTENTS 1. INTRODUCTION... 3 1.1. TERMINOLOGY... 4 1.2. REGULATORY FRAMEWORK... 5 1.3. THE DIFFERENT CONTROL LEVELS... 6 2. FIRST LEVEL CONTROL SET UP... 8 2.1. CONTROL SYSTEMS IN PLACE IN CENTRAL

More information

This report was commissioned by the Interreg IVB North Sea Region Programme as part of its on-going evaluation process.

This report was commissioned by the Interreg IVB North Sea Region Programme as part of its on-going evaluation process. Ongoing Evaluation of the INTERREG IVB North Sea Region Programme 2007 2013 North Sea Region Programme Papers No. 13 Institutional Capacity and Performance (1) Sub-theme: Financial management and control

More information

SIU Management and Monitoring System PROGRESS REPORT USER MANUAL PART 2

SIU Management and Monitoring System PROGRESS REPORT USER MANUAL PART 2 SIU Management and Monitoring System PROGRESS REPORT USER MANUAL PART 2 Version 1.0 of 14 August 2018 European Regional Development Fund www.italy-croatia.eu TABLE OF CONTENTS INTRODUCTION... 2 4.4.2 SECTION

More information

Guidance on a common methodology for the assessment of management and control systems in the Member States ( programming period)

Guidance on a common methodology for the assessment of management and control systems in the Member States ( programming period) Final version of 12/09/2008 EUROPEAN COMMISSION DIRECTORATE-GENERAL MARITIME AFFAIRS AND FISHERIES EFFC/27/2008 Guidance on a common methodology for the assessment of management and control systems in

More information

FICHE 21 MODEL OF DELEGATED ACTS SETTING OUT STANDARD SCALES OF UNIT COSTS VERSION 2-21 OCTOBER Version

FICHE 21 MODEL OF DELEGATED ACTS SETTING OUT STANDARD SCALES OF UNIT COSTS VERSION 2-21 OCTOBER Version Version 2-21.10.2013 FICHE 21 MODEL OF DELEGATED ACTS SETTING OUT STANDARD SCALES OF UNIT COSTS AND LUMP SUMS DEFINED BY THE COMMISSION VERSION 2-21 OCTOBER 2013 Regulation Article European Social Fund

More information

PROCUREMENT OF SERVICES OPEN CALL FOR TENDERS (Article 29 decree No of 30/12/2005) FRAMEWORK CONTRACT

PROCUREMENT OF SERVICES OPEN CALL FOR TENDERS (Article 29 decree No of 30/12/2005) FRAMEWORK CONTRACT PROCUREMENT OF SERVICES OPEN CALL FOR TENDERS (Article 29 decree No. 2005-1742 of 30/12/2005) FRAMEWORK CONTRACT Object: The externalisation of First Level Control activities within the framework of the

More information

PROGRAMME RULES ON ELIGIBILITY OF EXPENDITURES

PROGRAMME RULES ON ELIGIBILITY OF EXPENDITURES PROGRAMME RULES ON ELIGIBILITY OF EXPENDITURES Final version adopted by the JMC on 24 February 2016 Table of contents INTRODUCTION... - 4-1. LIST OF DEFINITIONS... - 4-2. LIST OF ABBREVIATIONS... - 5-3.

More information

GUIDANCE DOCUMENT ON THE FUNCTIONS OF THE CERTIFYING AUTHORITY. for the programming period

GUIDANCE DOCUMENT ON THE FUNCTIONS OF THE CERTIFYING AUTHORITY. for the programming period Final version of 25/07/2008 COCOF 08/0014/02-EN GUIDANCE DOCUMENT ON THE FUNCTIONS OF THE CERTIFYING AUTHORITY for the 2007 2013 programming period Table of contents 1. Introduction... 3 2. Main functions

More information

Simplified Cost Options:

Simplified Cost Options: Simplified Cost Options: DG EMPL audit approach Jeroen Jutte Head of Unit Relations with Control Authorities, Legal Procedures, Audit Direct Management and EGF Audit implications Need to consider audit

More information

Quick appraisal of major project. Guidance application: for Member States on Article 41 CPR. Requests for payment

Quick appraisal of major project. Guidance application: for Member States on Article 41 CPR. Requests for payment Quick appraisal of major project Guidance application: for Member States on Article 41 CPR Requests for payment Europe Direct is a service to help you find answers to your questions about the European

More information

COMMISSION DECISION. of on technical provisions necessary for the operation of the transition facility in the Republic of Croatia

COMMISSION DECISION. of on technical provisions necessary for the operation of the transition facility in the Republic of Croatia EUROPEAN COMMISSION Brussels, 13.6.2013 C(2013) 3463 final COMMISSION DECISION of 13.6.2013 on technical provisions necessary for the operation of the transition facility in the Republic of Croatia EN

More information

COMMISSION DELEGATED REGULATION (EU)

COMMISSION DELEGATED REGULATION (EU) L 148/54 20.5.2014 COMMISSION DELEGATED REGULATION (EU) No 532/2014 of 13 March 2014 supplementing Regulation (EU) No 223/2014 of the European Parliament and of the Council on the Fund for European Aid

More information

Guidance for Member States on the Drawing of Management Declaration and Annual Summary

Guidance for Member States on the Drawing of Management Declaration and Annual Summary EGESIF_15-0008-02 19/08/2015 EUROPEAN COMMISSION European Structural and Investment Funds Guidance for Member States on the Drawing of Management Declaration and Annual Summary Programming period 2014-2020

More information

Creative Europe Sub-programme Culture Financial management

Creative Europe Sub-programme Culture Financial management Creative Europe Sub-programme Culture Financial management 10 November 2014 Sandra Delespesse & Maria-Paz Benito 1 Content Financial tasks Eligibility of costs Important documents Checks, audit and evaluation

More information

Project Implementation. Project Implementation Seminar Monika Balode, Project Coordinator September 2018 Tallinn & Stockholm

Project Implementation. Project Implementation Seminar Monika Balode, Project Coordinator September 2018 Tallinn & Stockholm Project Implementation Project Implementation Seminar Monika Balode, Project Coordinator September 2018 Tallinn & Stockholm Contents Result orientation Guidance documents Lead partner principle Cooperation

More information

3 rd Call for Project Proposals

3 rd Call for Project Proposals IPA CROSS-BORDER PROGRAMME "GREECE THE FORMER YUGOSLAV REPUBLIC OF MACEDONIA 2007-2013" 3 rd Call for Project Proposals Project Selection Criteria CCI: 2007 CB 16 I PO 009 The following Project Selection

More information

General Terms and Conditions for Grand Solutions Contents

General Terms and Conditions for Grand Solutions Contents Valid from January 15, 2018 General Terms and Conditions for Grand Solutions Contents 1. Introduction... 2 1.1 Area of Applicability... 2 1.2 Danish version... 2 1.3 Amendments to the General Terms and

More information

PAC Guidelines for Project Progress Report

PAC Guidelines for Project Progress Report PAC Guidelines for Project Progress Report Version 1.0 September 2017 A stream of cooperation Programme co-funded by the European Union Content List of abbreviations... 5 Introduction... 6 PART I TECHNICAL

More information

An overview of the eligibility rules in the programming period

An overview of the eligibility rules in the programming period Rules and conditions applicable to actions co-financed from Structural Funds and Cohesion Fund An overview of the eligibility rules in the programming period 2007-2013 FEBRUARY 2009 1 Table of contents

More information

Guidance Note 14 Micro Project scheme

Guidance Note 14 Micro Project scheme Guidance Note 14 Micro Project scheme Please be aware that the Programme has a zero-tolerance approach to Fraud of any form. The Programme will always seek to recover any payments found to be a result

More information

First Level Control and Verifications of ESI Funds

First Level Control and Verifications of ESI Funds First Level Control and Verifications of ESI Funds 2014 2020 l Interactive Workshop 15 16 November 2018 Nice, France EXPERTS This two day intensive workshop focuses on: Maeve Hamilton Head of EU Managing

More information

Regulation on the implementation of the European Economic Area (EEA) Financial Mechanism

Regulation on the implementation of the European Economic Area (EEA) Financial Mechanism the European Economic Area (EEA) Financial Mechanism 2014-2021 Adopted by the EEA Financial Mechanism Committee pursuant to Article 10.5 of Protocol 38c to the EEA Agreement on 8 September 2016 and confirmed

More information

First Level Controller MANUAL

First Level Controller MANUAL First Level Controller MANUAL P r o g r a m m e co- f i n a n c e d b y E R D F P a g e 1 72 Version 2 (08/03/2018) P r o g r a m m e co- f i n a n c e d b y E R D F P a g e 2 72 This document will be

More information

MAIN LESSONS LEARNED

MAIN LESSONS LEARNED MAIN LESSONS LEARNED from the first reporting round with two pilot projects To ensure your online reporting for the North Sea Region Programme is efficient, please read this short document addressing key

More information

Project Changes. Lead Partner Seminar 4th Call for Proposal Budapest 10th December 2012

Project Changes. Lead Partner Seminar 4th Call for Proposal Budapest 10th December 2012 Project Changes Lead Partner Seminar 4th Call for Proposal Budapest 10th December 2012 Content 1. 2. 3. Fundamental principles Main categories of project change Single types of project change Fundamental

More information

Communication Strategy

Communication Strategy Communication Strategy 2014-2020 Joining efforts to lead the way to stronger, more sustainable economies and societies. www.northsearegion.eu Table of contents 1 I About this document... 3 2 I Background...

More information

1 st call for proposals, 2 nd call for proposals, Priority 3 Better network of harbours version

1 st call for proposals, 2 nd call for proposals, Priority 3 Better network of harbours version 1 st call for proposals, 2 nd call for proposals, Priority 3 Better network of harbours version 14.09.16 Annex 2 Revenue Guidelines Table of contents Table of contents 1 1. Abbreviations and definitions

More information

Social Market Economy in Member States I : ESF. ESF Legislation and Policy, Financial Engineering

Social Market Economy in Member States I : ESF. ESF Legislation and Policy, Financial Engineering EUROPEAN COMMISSION Employment, Social Affairs and Inclusion Social Market Economy in Member States I : ESF ESF Legislation and Policy, Financial Engineering Brussels, 27 September 2011 EMPL/E/1 D (2011)

More information

UKF Project Monitoring Guidelines Version 4

UKF Project Monitoring Guidelines Version 4 REPUBLIC OF CROATIA MINISTRY OF SCIENCE, EDUCATION AND SPORTS UKF Project Monitoring Guidelines Version 4 UNITY THROUGH KNOWLEDGE FUND office@ukf.hr, www.ukf.hr, +385 1 2352 685 Planinska 1, HR-10000 Zagreb,

More information

CLOSURE GUIDELINES SEMINAR. Section 4 Submission of closure documents

CLOSURE GUIDELINES SEMINAR. Section 4 Submission of closure documents CLOSURE GUIDELINES SEMINAR Section 4 Submission of closure documents 4.1.2 CLOSURE DOCUMENTS for IPA CBC 1. Final statement of expenditure (as integral part of the final payment application) issued by

More information

Financial rules and procedures

Financial rules and procedures European Union European Regional Development Fund Sharing solutions for better regional policies Financial rules and procedures Ilaria Piazza Finance Officer Interreg Europe Content 1. Eligibility of expenditure

More information