How to close the project

Size: px
Start display at page:

Download "How to close the project"

Transcription

1 Training on Project & Financial Management and Communication; Vienna, September 2013 How to close the project JTS CENTRAL EUROPE

2 Agenda of the workshop Time span from 10h30 13h00 Welcome Presentation of the final report template (1) Practical exercises on how to fill in the indicators Presentation of the final report template (2) Practical exercises on how to fill in the financial section and on costs Questions & Answers

3 Goals and expected results Goal of the presentation: To guide on how to prepare a comprehensive and accurate Final Report (FR) Expected result: The most important achievements of the project are made visible, making them suitable for further spreading and capitalisation To reduce the number of clarification rounds

4 Final Report vs. Progress Report Progress Report Focused on activities/deliverables/outputs/expenditure Final Report Focused on the major achievements of the project and potential impacts Highlighting the changes/improvements resulting from the project implementation Joint reflection with the partnership on project experience and achievements, and possible starting point for follow up actions

5 Final Report structure Section 0: Executive summary Section 1: Résumé of project objectives Section 2: Key achievements Project Outputs/Results Section 3: Project partnership Section 4: Sustainability and follow-up Section 5: Publicity, visibility and capitalisation potential Section 6: Finances Section 7: Programme Management Section 8: Annexes

6 Summary Section 0: Executive summary Abstract Catchy and understandable outline of project results (0,5 pages) Prepared or checked by COM Manager Text of project book can be used Summary Project results in broader perspective (1,5 pages) Main focus on objectives, key achievements (= outputs + results), transnational cooperation approach and sustainability

7 Résumé of project objectives Section 1: Résumé of project objectives Description of the project aims as in the Application Form Contribution to the CENTRAL EUROPE Programme goals Main obstacles and success factors experienced during project implementation

8 Key achievements outputs / results Section 2.1: Type/characteristics of achievements Presentation of qualitative aspects of project achievements and their contribution to set objectives Innovative aspects of project achievements Additional results eventually reached

9 Key achievements outputs / results Section 2.2: Target groups and territorial dimension of achievements Outline of main target groups that benefit from project outputs and results at partner level Territorial dimension of project achievements which territories are affected (geographic coverage)

10 Key achievements outputs / results Section 2.3: Output and results indicators Ensure consistency of output indicators (accumulated) with the last PR For result indicators ensure that figures reported do not include any double or multiple counting of the same achieved result (consistency with last PR not compulsory) Provide background information on all the reported figures (e.g. describing the related outputs, concerned institutions etc.)

11 Reminder on indicators Output Indicators: Types of Actions (A) The selected indicators need to Be clearly linked to finalised (Core) outputs Should not refer to standard outputs like e.g. project steering groups or project websites Include a detailed description in the respective textbox Be supported by adequate documents Be consistent with other sections of the FR and PR such as o o Volume of investment realised through Pilot Actions (reported for Type of Action Pilot action including investment ) should be consistent with the budget line investment in the Financial Report Volume of investment prepared and Volume of private/public funds leveraged (reported for Type of Action Investment preparation ) should be consistent with reported result indicator induced investment

12 Reminder on indicators Result indicators The selected indicators need to be Realistic and consistent Based on accomplished outputs/activities Focused on the own Area of Intervention (AoI) and on those AoIs with clear links to project aims as identified in the AF Ensure that no multiple counting occurs Ensure transparency of calculation and links to project activities

13 Project partnership Section 3.1: List of project partners Transferred automatically Section 3.2: Partnership map Drag and drop the stars referring to the latest set-up of the partnership Section 3.3: Added value of cooperation Description of contributions and involvement of the project partners Added value of transnational cooperation Contribution to cross-sector policy development and multilevel governance Synergies with other EU-funded projects/programmes

14 Sustainability and follow-up Section 4.1: Sustainability and mainstreaming of project results Financial, institutional, political sustainability in mid- and long-term perspective Success stories in mainstreaming of project results e.g. into different policy levels Future transfer of results beyond the partnership Inducement and preparation of investments (if applicable) Section 4.2: Durability of cooperation Future cooperation plans of the partnership and stakeholders

15 Sustainability and follow-up Section 4.3: Impacts Integration of project results into new/improved policies at regional, national, EU levels Leverage of future investments Contribution of the project to creation of new jobs Planned follow-up activities Ensure consistency with the information provided in the indicator section

16 Publicity, visibility and capitalisation potential Section 5.1: Communication and dissemination Major communication and dissemination measures Project results relevant for capitalisation Planned dissemination activities beyond the project lifetime Section 5.2: Outreach to target groups Describe the most relevant target group indicators Justify the achievements in terms of targets reached, exceeded or not reached at all Ensure that the figures reported do not include any double or multiple counting of the same target group (consistency with PR not compulsory)

17 Reminder on indicators Indicator: Outreach to selected target groups (B) The selected indicators need to Reflect only active involvement of target groups Consider only entities and not persons Ensure transparency of calculation and links to project activities Avoid multiple counting of the same entity in different periods

18 PRACTICAL EXERCISES

19 Closure costs All implementation related costs must be paid before the end date of the project (with the exception of Staff Costs and social charges) All costs related to the elaboration and submission of the last PR and Final Report are eligible until the submission date of the said reports set in the Subsidy Contract If the submission date is postponed by the MA/JTS then it is the submission date set by the MA/JTS that applies and costs are eligible until this date Costs related to the clarification rounds of the last PR and Final Report cannot be claimed.

20 Closure costs What does this mean? This means that if the submission date is set as 1 st February 2013: All costs related to the elaboration and submission of the last progress report and the final report, including where applicable audit costs, are eligible for funding if paid out before the due date of submission of the report set in the subsidy contract by the MA/JTS. The costs related to this can be validated by the FLC during the clarification rounds and the FLC documents would need to be revised.

21 Closure costs Eligible PR & FR Submission 1.Feb. Not eligible time line Project End date Costs related to the clarification rounds of the last PR and Final Report cannot be claimed Implementation Related Costs have to be paid out/ transferred* Costs related to the elaboration and submission of the last progress report and the final report have to be paid out time line Can be validated by the FLC during the Clarifications *with the exception of Staff Costs and social charges

22 Section 6 - Finances Table 6.1 Financial summary Total Accumulated in Table 8.3 of Progress Report (except in case of irregularities during project implementation) Table 3 Project Funding of Application Form DOES NOT APPLY TO THE 1 st CALL! Accumulated ERDF in Table 8.3 of Progress Report: 1) Identify partner outside CE area; 2) Include the related amount in the present field Accumulated ERDF in Table 7.2 of Progress Report

23 Section 6 - Finances Table 6.1 Financial summary During project implementation few irregular amounts have been deducted with FCFs: - Total: 518,68 - ERDF: 389,01 - Public: 129,67 IMPORTANT: please ensure to reduce from ERDF, Public and/or Private Cofinancing the respective shares of irregular amounts

24 Section 6 - Finances Table Revenue after project closure Article 55 of Reg. (EC) 1083/2006 If you tick Yes, please fill in the following table: REMEMBER!!! In case of revenues NOT LISTED in the above table and generated BEFORE 31 MARCH 2017, the LP is to promptly inform the Managing Authority

25 Section 6 - Finances Table Control and audits If you tick Yes, please fill in the following table: PP no. Type of control (e.g. on-the-spot check, plausibility check) Institution that carried out control/audit Outcome of control/audit (summary of findings and/or recommendations) Follow-up actions undertaken Joint Technical Secretariat; Managing Authority; Certifying Authority; Audit Authority; Commission Services; National and EU controlling institutions; National responsible public authorities or authorized private control institutions (e.g., FLC co-ordinating body). DO NOT include controls done by your FLC!!!

26 Section 6 - Finances Table Irregularities If you tick Yes, please fill in the following table: PP no. Partner Institution Institution that detected the irregularity Reasons for Irregularity ERDF Ineligible Amount ( ) Follow-up actions undertaken Joint Technical Secretariat; Managing Authority; Certifying Authority; Audit Authority; Commission Services; National and EU controlling institutions; National responsible public authorities or authorized private control institutions (e.g. FLC). Ensure to include the ERDF share of the irregular amount Withdrawal of the irregularity by means of Financial Correction Form in the relevant PR

27 Section 6 - Finances Table Location of documents after closure REMEMBER!!! All supporting documents shall be stored in a safe and orderly manner for 3 years after the closure of the Programme, and in any case at least until 31 December 2022 If you tick Yes in case of any change concerning the place of storage documentation, please DO NOT forget to fill in the table In case of further changes in the location of the documents occurring before 31 December 2022, LP is to inform: The national body(-ies) responsible for First Level Control; The Programme Managing Authority.

28 Programme management Section 7: Programme management Constructive feedback on procedures, support from JTS/MA Suggestions on possible improvements in the current and future Programming periods Section 8: Annexes LP Final Report self-declaration (to be signed by the legal representative) being a confirmation of e.g. correctness of the information, validated expenditures, audit trail and revenues of the project to be delivered together with the final hardcopy version Other annexes considered relevant (avoid overlaps with the Progress Report)

29 PRACTICAL EXERCISES

30 QUESTIONS?

31 Contact CENTRAL EUROPE Programme Joint Technical Secretariat Kirchberggasse 33-35/11 A-1070 Vienna Tel: +43 (0) Fax: +43 (0) info@central2013.eu Web: FB:

Follow up and reporting procedures. Lead partners seminar 5th targeted call Lydwine Lafontaine

Follow up and reporting procedures. Lead partners seminar 5th targeted call Lydwine Lafontaine Follow up and reporting procedures Lead partners seminar 5th targeted call Lydwine Lafontaine Table of contents Background information Subsidy contract Lead partner principles 1. Progress of the project:

More information

Second Level Control: process and most common findings

Second Level Control: process and most common findings The CENTRAL EUROPE Programme Second Level Control: process and most common findings Training on Project, Finance Management and Communication Vienna - 11 September 2013 Content 1. Second Level Control

More information

FIRST LEVEL CONTROL: PRINCIPLES AND PRACTICE

FIRST LEVEL CONTROL: PRINCIPLES AND PRACTICE CENTRAL EUROPE PROGRAMME 2007-2013 Project financial management and controls Vienna, 7 th April 2011 FIRST LEVEL CONTROL: PRINCIPLES AND PRACTICE 1. Validation of expenditure: the FLC 2. General principles

More information

First call of Interreg CENTRAL EUROPE

First call of Interreg CENTRAL EUROPE Il Programma CENTRAL EUROPE 2020 Venice, 10 December 2014 First call of Luca Ferrarese - Joint Secretariat Key facts and figures of the first call for proposals o Open to all programme priorities and all

More information

Budget & Finances. Interreg Europe Secretariat. 23 March 2016 Lead applicant workshop. Sharing solutions for better regional policies

Budget & Finances. Interreg Europe Secretariat. 23 March 2016 Lead applicant workshop. Sharing solutions for better regional policies European Union European Regional Development Fund Sharing solutions for better regional policies Budget & Finances Interreg Europe Secretariat 23 March 2016 Lead applicant workshop Session content 1. Preliminary

More information

Factsheet N 6 Project implementation: delivering project outputs, achieving project objectives and bringing about the desired change

Factsheet N 6 Project implementation: delivering project outputs, achieving project objectives and bringing about the desired change Project implementation: delivering project outputs, achieving project objectives and bringing about the desired change Version No 13 of 23 November 2018 Table of contents I. GETTING STARTED: THE INITIATION

More information

PAC Guidelines for Project Progress Report

PAC Guidelines for Project Progress Report PAC Guidelines for Project Progress Report Version 1.0 September 2017 A stream of cooperation Programme co-funded by the European Union Content List of abbreviations... 5 Introduction... 6 PART I TECHNICAL

More information

Success factors for project development: focus on activities and partnership

Success factors for project development: focus on activities and partnership CENTRAL EUROPE PROGRAMME 2007-2013 Lead Applicant Briefing 4th Call for proposals Success factors for project development: focus on activities and partnership JTS CENTRAL EUROPE PROGRAMME OVERVIEW CONTENT

More information

How to plan your budget and project management?

How to plan your budget and project management? European Union European Regional Development Fund Sharing solutions for better regional policies How to plan your budget and project management? Ilaria Piazza Interreg Europe Secretariat i.piazza@interregeurope.eu

More information

Lead Partner Seminar. JS/MA Riga

Lead Partner Seminar. JS/MA Riga Lead Partner Seminar JS/MA 9.12.2015 Riga Welcome to the Lead Partner Seminar Objective of the day: Give the Lead Partner the needed tools to best implement the project To know where to come with questions

More information

MED PROGRAMME. First Level Control in practice. Most common mistakes - Follow-up measures

MED PROGRAMME. First Level Control in practice. Most common mistakes - Follow-up measures MED PROGRAMME First Level Control in practice Most common mistakes - Follow-up measures Torino 11 April 2011 BACKGROUND Major common mistakes detected during JTS check 1 st and 2 nd PR Delays in finalization

More information

FLC Guidance. Page 1. Version. September *Disclaimer: This is a living document and further content will be developed at a later stage.

FLC Guidance. Page 1. Version. September *Disclaimer: This is a living document and further content will be developed at a later stage. FLC Guidance Version September 2017 *Disclaimer: This is a living document and further content will be developed at a later stage. Page 1 Table of Contents... 1 CHAPTER 1 General principles... 3 1.1 Introduction...

More information

Programme Manual

Programme Manual 1.1.1. 25 October 2010 Table of contents 0. Introduction... 1 1. General programme information... 2 1.1. Main objectives of the programme...2 1.2. Programme area...2 1.3. Programme funding...2 1.4. Programme

More information

South East Europe (SEE) SEE Control Guidelines

South East Europe (SEE) SEE Control Guidelines South East Europe (SEE) SEE Control Guidelines Version 1.4. Final version approved by the MC 10 th June 2009 1 st amendment to be approved by MC (2.0) 1 CONTENTS 1 Purpose and content of the SEE Control

More information

Project Changes. Lead Partner Seminar 4th Call for Proposal Budapest 10th December 2012

Project Changes. Lead Partner Seminar 4th Call for Proposal Budapest 10th December 2012 Project Changes Lead Partner Seminar 4th Call for Proposal Budapest 10th December 2012 Content 1. 2. 3. Fundamental principles Main categories of project change Single types of project change Fundamental

More information

CENTRAL EUROPE PROGRAMME

CENTRAL EUROPE PROGRAMME CENTRAL EUROPE PROGRAMME 2007-20132013 CENTRAL EUROPE INFODAY Venice, 4 March 2008 Barbara Di Piazza JTS CENTRAL EUROPE PROGRAMME PROGRAMME AREA FINANCIAL ALLOCATION ERDF budget National contribution Total

More information

Knowledge and Innovation Consultants. Financial Management and Reporting Greek Magistral Lesson Izmir, 28/06/2011

Knowledge and Innovation Consultants. Financial Management and Reporting Greek Magistral Lesson Izmir, 28/06/2011 Knowledge and Innovation Consultants Financial Management and Reporting Greek Magistral Lesson Izmir, 28/06/2011 Financial Management and Reporting 1 The financial management of a project requires the

More information

Guidelines for the AF DSP call for proposals

Guidelines for the AF DSP call for proposals Guidelines for the AF DSP call for proposals A stream of cooperation edited by the Managing Authority/Joint Secretariat Budapest, Hungary, 2018 Programme co-funded by the European Union Table of content

More information

Cohesion Policy Territorial Co-operation

Cohesion Policy Territorial Co-operation Cohesion Policy 2007-2013 2013 Objective European Territorial Co-operation operation FORALPS Conference Trento, 7 March 2008 Nicoletta Gardini European Commission DG Regional Policy Unit Italy & Malta

More information

Seed Money Facility. Lead Applicants seminar Budapest, 11 April 2016

Seed Money Facility. Lead Applicants seminar Budapest, 11 April 2016 Seed Money Facility Lead Applicants seminar Budapest, 11 April 2016 Seed Money Facility (SMF) Call main elements Content: Aim and format of the SMF call Governance Project structure Partnership and partners

More information

First level control report including checklist

First level control report including checklist First level control report including checklist Project title Project acronym Project number Report Number 1. Project and progress report Name 2. Project Partner Name Organisation Job title Division/Unit/Department

More information

Fact Sheet 14 - Partnership Agreement

Fact Sheet 14 - Partnership Agreement - Partnership Agreement Valid from Valid to Main changes Version 2 27.04.15 A previous version was available on the programme website but all projects must use this version. Core message: It is a regulatory

More information

GUIDE FOR PROJECT IMPLEMENTATION

GUIDE FOR PROJECT IMPLEMENTATION GUIDE FOR PROJECT IMPLEMENTATION PRACTICAL GUIDANCE FOR PROJECT PARTNERS Version 5.0 (15.1.2019) Contents 1. Introduction... 3 2. Starting up the project... 4 2.1. Fulfilling conditions... 5 2.2. Hand

More information

Partnership Agreement between the Lead Partner and the other project partners

Partnership Agreement between the Lead Partner and the other project partners Partnership Agreement between the Lead Partner and the other project partners Foreword This Partnership Agreement is signed on the basis of the following documents that form the legal framework applicable

More information

Reporting and First Level Control of Finance and Activities

Reporting and First Level Control of Finance and Activities Reporting and First Level Control of Finance and Activities First Level Control Seminar, 6/7 October 2010, Bergen Isabella Leong, Jesper Jönsson, Christian Zieske Joint Technical Secretariat Viborg Rules

More information

URBACT II PROGRAMME MANUAL

URBACT II PROGRAMME MANUAL European Regional Development Fund 2007-2013 Objective 3: European Territorial Cooperation URBACT II PROGRAMME MANUAL (Technical Working Document) Approved by the Monitoring Committee on 21/11/2007 Modified

More information

ERDF SUBSIDY CONTRACT NO...

ERDF SUBSIDY CONTRACT NO... The Government Office for Development and European Cohesion Policy, Kotnikova 5, SI 1000 Ljubljana, Slovenia, acting as the Managing Authority of the Cooperation Programme Interreg V-A Slovenia-Hungary

More information

INTERACT III Draft Cooperation Programme

INTERACT III Draft Cooperation Programme INTERACT III 2014-2020 Draft Cooperation Programme version 2.5.1, 18 July 2014 Contents 1. Strategy for the cooperation programme s contribution to the Union strategy for smart, sustainable and inclusive

More information

3 rd Call for Project Proposals

3 rd Call for Project Proposals IPA CROSS-BORDER PROGRAMME "GREECE THE FORMER YUGOSLAV REPUBLIC OF MACEDONIA 2007-2013" 3 rd Call for Project Proposals Project Selection Criteria CCI: 2007 CB 16 I PO 009 The following Project Selection

More information

Project Progress Report User Guide

Project Progress Report User Guide Project Progress Report User Guide Transnational Cooperation Programme Interreg Balkan-Mediterranean 2014-2020 CCI 2014TC16M4TN003 Balkan-Mediterranean is co-financed by European Union and National Funds

More information

Il programma Central Europe: stato dell arte e prospettive per il futuro

Il programma Central Europe: stato dell arte e prospettive per il futuro Programma CENTRAL EUROPE 2007-2013 - evento tematico nazionale Montecchio Maggiore (VI), 5 Dicembre 2012 Il programma Central Europe: stato dell arte e prospettive per il futuro Luca Ferrarese Joint Technical

More information

Guidance for reporting

Guidance for reporting Guidance for reporting This document guides lead partners (LP) through the reporting carried out on the ems as foreseen in the subsidy contract and described in the factsheet 4.7 Project reporting. Please

More information

Final Project Report Manual

Final Project Report Manual A guideline for Lead Partners Version 1.0 (23 January 2006) INTERREG III B CADSES NP Joint Technical Secretariat An der Kreuzkirche 6 01067 Dresden, Germany Tel: +49 351 488 1021 Fax: +49 351 488 1025

More information

INTERREG V-B ADRIATIC IONIAN PROGRAMME ADRION. Guidelines for the submission of the Project Progress Report via ems

INTERREG V-B ADRIATIC IONIAN PROGRAMME ADRION. Guidelines for the submission of the Project Progress Report via ems INTERREG V-B ADRIATIC IONIAN PROGRAMME ADRION Guidelines for the submission of the Project Progress Report via ems Table of contents 1. General information... 3 2. Generation of project progress report...

More information

INTERREG 2 Seas Mers Zeeën First Level Control Manual

INTERREG 2 Seas Mers Zeeën First Level Control Manual INTERREG 2 Seas Mers Zeeën 2014-2020 First Level Control Manual Version of 29/11/2018 Table of Content 1. INTRODUCTION... 5 1.1. PURPOSE AND OBJECTIVE OF THIS MANUAL... 5 1.2. TERMINOLOGY... 5 2. LEGAL

More information

SIU Management and Monitoring System PROGRESS REPORT USER MANUAL PART 2

SIU Management and Monitoring System PROGRESS REPORT USER MANUAL PART 2 SIU Management and Monitoring System PROGRESS REPORT USER MANUAL PART 2 Version 1.0 of 14 August 2018 European Regional Development Fund www.italy-croatia.eu TABLE OF CONTENTS INTRODUCTION... 2 4.4.2 SECTION

More information

An overview of the eligibility rules in the programming period

An overview of the eligibility rules in the programming period Rules and conditions applicable to actions co-financed from Structural Funds and Cohesion Fund An overview of the eligibility rules in the programming period 2007-2013 FEBRUARY 2009 1 Table of contents

More information

Financial rules and procedures in Interreg Europe - second call projects

Financial rules and procedures in Interreg Europe - second call projects European Union European Regional Development Fund Sharing solutions for better regional policies Financial rules and procedures in Interreg Europe - second call projects Aleksandra Niechajowicz Finance

More information

Project Monitoring and Reporting Workshop for Interreg programmes

Project Monitoring and Reporting Workshop for Interreg programmes Project Monitoring and Reporting Workshop for Interreg programmes Who, why, how? 21-22 April 2016 Sofia, Bulgaria Interact is co-financed by the European Regional Development Fund (ERDF) Responsibilities

More information

PART 7: OVERVIEW ON PROJECT IMPLEMENTATION PRINCIPLES

PART 7: OVERVIEW ON PROJECT IMPLEMENTATION PRINCIPLES Applicants Manual for the period 2014-2020 Version 1.1 PART 7: OVERVIEW ON PROJECT IMPLEMENTATION PRINCIPLES edited by the Managing Authority/Joint Secretariat Budapest, Hungary, 2015 Applicants Manual

More information

Implementation Manual. Version 2.1 December 2016

Implementation Manual. Version 2.1 December 2016 Implementation Manual Version 2.1 December 2016 Content INTRODUCTION... 6 A. HOW TO GET STARTED WITH THE PROJECT... 9 A.1. General requirements... 9 A.1.1. Signing the subsidy contract... 9 A.1.2. Setting

More information

Version 4: 29 th June 2017

Version 4: 29 th June 2017 PROGRAMME RULES INTERREG VA CROSS-BORDER PROGRAMME FOR TERRITORIAL CO-OPERATION 2014-2020 NORTHERN IRELAND, BORDER REGION OF IRELAND AND WESTERN SCOTLAND & PEACE IV EU PROGRAMME FOR PEACE AND RECONCILIATION

More information

Regulation on the implementation of the European Economic Area (EEA) Financial Mechanism

Regulation on the implementation of the European Economic Area (EEA) Financial Mechanism the European Economic Area (EEA) Financial Mechanism 2014-2021 Adopted by the EEA Financial Mechanism Committee pursuant to Article 10.5 of Protocol 38c to the EEA Agreement on 8 September 2016 and confirmed

More information

SMALL PROJECT CONSOLIDATED PROGRESS REPORT FORM including guidelines

SMALL PROJECT CONSOLIDATED PROGRESS REPORT FORM including guidelines SMALL PROJECT CONSOLIDATED PROGRESS REPORT FORM including guidelines GET ACQUAINTED WITH PROGRAMME MANUAL AND APPROPRIATE NATIONAL GUIDELINES BEFORE FILLING IN SMALL PROJECT PROGRESS / CONSOLIDATED PROGRESS

More information

INTERREG IVA Programme. Guidance Note on Information and Publicity G5/IIVA

INTERREG IVA Programme. Guidance Note on Information and Publicity G5/IIVA INTERREG IVA Programme Guidance Note on Information and Publicity G5/IIVA 1. General 1.1 Section 1, Information and Communication, of European Commission Regulation (EC) No 1828/2006 requires the Special

More information

ANNEX. to the Comission Decision. amending Decision C(2013) 1573

ANNEX. to the Comission Decision. amending Decision C(2013) 1573 EUROPEAN COMMISSION Brussels, 30.4.2015 C(2015) 2771 final ANNEX 1 ANNEX to the Comission Decision amending Decision C(2013) 1573 on the approval of the guidelines on the closure of operational programmes

More information

Project Implementation. Project Implementation Seminar Monika Balode, Project Coordinator September 2018 Tallinn & Stockholm

Project Implementation. Project Implementation Seminar Monika Balode, Project Coordinator September 2018 Tallinn & Stockholm Project Implementation Project Implementation Seminar Monika Balode, Project Coordinator September 2018 Tallinn & Stockholm Contents Result orientation Cooperation Lead partner principle Guidance documents

More information

Full Application Form

Full Application Form Full Application Form PART A Project summary A.1 Project identification Programme priority Specific objective Project acronym Project title Project number Name of the Lead Applicant organization in English

More information

Guidance for Member States on the Drawing of Management Declaration and Annual Summary

Guidance for Member States on the Drawing of Management Declaration and Annual Summary EGESIF_15-0008-02 19/08/2015 EUROPEAN COMMISSION European Structural and Investment Funds Guidance for Member States on the Drawing of Management Declaration and Annual Summary Programming period 2014-2020

More information

F A C T S H E E T PROGRAMME MANUAL. Interreg IPA CBC Italy Albania Montenegro Programme. 4.7 Project changes and ems procedures

F A C T S H E E T PROGRAMME MANUAL. Interreg IPA CBC Italy Albania Montenegro Programme. 4.7 Project changes and ems procedures F A C T S H E E T Interreg IPA CBC Italy Albania Montenegro Programme PROGRAMME MANUAL 4.7 Project changes and ems procedures Current version 01 Updated 1 October 2018 Contacts js@italy-albania-montenegro.eu

More information

Guidance on management verifications Cooperation Programme Interreg V-A Greece - Italy

Guidance on management verifications Cooperation Programme Interreg V-A Greece - Italy Guidance on management verifications Cooperation Programme Interreg V-A Greece - Italy 2014-2020 Greece-Italy v.10 1 Table of contents Introduction 1. General 1.1 Regulatory requirements 1.2 General principles

More information

ADRION 2nd Call for Proposals - Priority Axis 2 Technical guidance on how to submit a project proposal using the on-line application system ems

ADRION 2nd Call for Proposals - Priority Axis 2 Technical guidance on how to submit a project proposal using the on-line application system ems ADRION 2nd Call for Proposals - Priority Axis 2 Technical guidance on how to submit a project proposal using the on-line application system ems Version 1-26 March 2018 1 Table of Content 1. Purpose...

More information

European networks, experience and recommendations helping cities and citizens to become Energy Efficient

European networks, experience and recommendations helping cities and citizens to become Energy Efficient INTERREG IVC European networks, experience and recommendations helping cities and citizens to become Energy Efficient Mini-Programme Manual Updated version 22 February 2011 Mini-Programme Manual EnercitEE

More information

CONSOLIDATED PROGRESS REPORT FORM including guidelines

CONSOLIDATED PROGRESS REPORT FORM including guidelines CONSOLIDATED PROGRESS REPORT FORM including guidelines GET ACQUAINTED WITH PROGRAMME MANUAL AND APPROPRIATE NATIONAL GUIDELINES BEFORE FILLING IN PROGRESS / CONSOLIDATED PROGRESS REPORT PLEASE NOTE THAT

More information

GUIDE FOR FILLING IN THE APPLICATION FORM 4TH CALL. Central Baltic Programme Version 4.0 ( )

GUIDE FOR FILLING IN THE APPLICATION FORM 4TH CALL. Central Baltic Programme Version 4.0 ( ) GUIDE FOR FILLING IN THE APPLICATION FORM 4TH CALL Central Baltic Programme 2014-2020 Version 4.0 (4.7.2018) Contents Introduction... 2 Small and regular projects... 2 The emonitoring System... 2 Important

More information

ECOLOGICAL CORRIDORS WORKSHOP-CONNECTGREEN 22 APRIL 2016 PRŮHONICE, CZECH REPUBLIC. Part-financed by the Europen Union

ECOLOGICAL CORRIDORS WORKSHOP-CONNECTGREEN 22 APRIL 2016 PRŮHONICE, CZECH REPUBLIC. Part-financed by the Europen Union ECOLOGICAL CORRIDORS WORKSHOP-CONNECTGREEN 22 APRIL 2016 PRŮHONICE, CZECH REPUBLIC Part-financed by the Europen Union 22nd of April (Friday) 9:00 11:00 Opening of the Meeting - welcome and opening remarks

More information

La partecipazione dei territori ai programmi CTE: il caso CENTRAL EUROPE e prospettive per il

La partecipazione dei territori ai programmi CTE: il caso CENTRAL EUROPE e prospettive per il European Cooperation Day Venice, 23 September 2013 La partecipazione dei territori ai programmi CTE: il caso CENTRAL EUROPE e prospettive per il 2014-2020 Luca Ferrarese Joint Technical Secretariat 1.

More information

ELIGIBILITY OF EXPENSES: APPLICABLE RULES

ELIGIBILITY OF EXPENSES: APPLICABLE RULES INFO DAY ON PROJECT IMPLEMENTATION 1 ST CALL FOR PROJECT PROPOSALS ELIGIBILITY OF EXPENSES: APPLICABLE RULES Hierarchy of rules on eligibility of expenditure Rules defined in EU legal framework ERDF Programme

More information

DRAFT TEMPLATE AND GUIDELINES FOR THE CONTENT

DRAFT TEMPLATE AND GUIDELINES FOR THE CONTENT DRAFT 21.05.2013 DRAFT TEMPLATE AND GUIDELINES FOR THE CONTENT OF THE OPERATIONAL PROGRAMME Version 3 21.05.2013 This document is based on the Presidency compromise text (from 19 December 2012), which

More information

IMPLEMENTATION MANUAL. Version 3.1 July 2018

IMPLEMENTATION MANUAL. Version 3.1 July 2018 IMPLEMENTATION MANUAL Version 3.1 July 2018 Content INTRODUCTION... 6 A. HOW TO GET STARTED WITH THE PROJECT... 9 A.1. General requirements... 9 A.1.1. Signing the subsidy contract... 9 A.1.2. Setting

More information

Interreg V-A Latvia Lithuania Programme

Interreg V-A Latvia Lithuania Programme Interreg V-A Latvia Lithuania Programme 2014 2020 FINANCIAL CONTROL MANUAL Approved by the Head of the Managing Authority Sandis Cakuls on 02.11.2017 Version 2 TABLE OF CONTENTS 1. Introduction 4 2. General

More information

PROCUREMENT OF SERVICES OPEN CALL FOR TENDERS (Article 29 decree No of 30/12/2005) FRAMEWORK CONTRACT

PROCUREMENT OF SERVICES OPEN CALL FOR TENDERS (Article 29 decree No of 30/12/2005) FRAMEWORK CONTRACT PROCUREMENT OF SERVICES OPEN CALL FOR TENDERS (Article 29 decree No. 2005-1742 of 30/12/2005) FRAMEWORK CONTRACT Object: The externalisation of First Level Control activities within the framework of the

More information

CENTRAL EUROPE Control and Audit Guidelines TABLE OF CONTENTS

CENTRAL EUROPE Control and Audit Guidelines TABLE OF CONTENTS TABLE OF CONTENTS 1. INTRODUCTION... 3 1.1. TERMINOLOGY... 4 1.2. REGULATORY FRAMEWORK... 5 1.3. THE DIFFERENT CONTROL LEVELS... 6 2. FIRST LEVEL CONTROL SET UP... 8 2.1. CONTROL SYSTEMS IN PLACE IN CENTRAL

More information

First Level Controller MANUAL

First Level Controller MANUAL First Level Controller MANUAL P r o g r a m m e co- f i n a n c e d b y E R D F P a g e 1 72 Version 2 (08/03/2018) P r o g r a m m e co- f i n a n c e d b y E R D F P a g e 2 72 This document will be

More information

Having regard to the Treaty on the Functioning of the European Union, and in particular Article 291 thereof,

Having regard to the Treaty on the Functioning of the European Union, and in particular Article 291 thereof, L 244/12 COMMISSION IMPLEMTING REGULATION (EU) No 897/2014 of 18 August 2014 laying down specific provisions for the implementation of cross-border cooperation programmes financed under Regulation (EU)

More information

Alpine Space programme. Project implementation handbook

Alpine Space programme. Project implementation handbook Alpine Space programme Project implementation handbook Version 05 as of 12.01.2017 Introduction Dear reader, This "Project implementation handbook has been made to provide the (potential) project participants

More information

ems Technical Guidance

ems Technical Guidance ems Technical Guidance Version 4.9 13/02/18 Page 1 of 55 Contents 1. Introduction... 4 1.1 Regular and Micro-Projects... 4 1.2 About ems... 4 1.3 Support when filling in the application... 4 1.4 Submitting

More information

SELECTION CRITERIA. for applications submitted to the INTERREG V-A Austria-Hungary Programme

SELECTION CRITERIA. for applications submitted to the INTERREG V-A Austria-Hungary Programme SELECTION CRITERIA for applications submitted to the INTERREG V-A Austria-Hungary Programme Version 2.0 19.04.2017 Project selection in the programme INTERREG V-A Austria-Hungary Project selection is based

More information

III. modus operandi of Tier 2

III. modus operandi of Tier 2 III. modus operandi of Tier 2 Objective, country and project eligibility 70 Budget and timing 71 Project preparation: formulation of proposals 71 Project appraisal 72 Project approval 73 Agreements and

More information

Lead Applicant Seminar Cambridge, 6 November 2009

Lead Applicant Seminar Cambridge, 6 November 2009 INTERREG IVA 2 Mers Seas Zeeën Cross-border Cooperation Programme 2007-2013 Lead Applicant Seminar Cambridge, 6 November 2009 Joint Technical Secretariat INTERREG IV A 2 Seas Programme Table of contents

More information

Financial Instruments supported by the European Structural and Investment (ESI) Funds in

Financial Instruments supported by the European Structural and Investment (ESI) Funds in Regional Financial Instruments supported by the European Structural and Investment (ESI) Funds in 2014-2020 REGIO B3, DG Regional and Urban European Commission Regional 2 ERDF support through financial

More information

ESPON 2020 Cooperation Programme Operation Specification Final

ESPON 2020 Cooperation Programme Operation Specification Final Version 25 June 2015 ESPON 2020 Cooperation Programme Operation Specification Final 1 Table of Content Part I Context and Scope of the Operation Proposal 1.1 Context of the ESPON 2020 Cooperation Programme

More information

PART 1: DANUBE TRANSNATIONAL PROGRAMME

PART 1: DANUBE TRANSNATIONAL PROGRAMME Applicants Manual for the period 2014-2020 Version 1 PART 1: DANUBE TRANSNATIONAL PROGRAMME edited by the Managing Authority/Joint Secretariat Budapest, Hungary, 2015 Applicants Manual Part 1 1 PART 1:

More information

CLOSURE GUIDELINES SEMINAR. Section 4 Submission of closure documents

CLOSURE GUIDELINES SEMINAR. Section 4 Submission of closure documents CLOSURE GUIDELINES SEMINAR Section 4 Submission of closure documents 4.1.2 CLOSURE DOCUMENTS for IPA CBC 1. Final statement of expenditure (as integral part of the final payment application) issued by

More information

ABBREVIATIONS AND GLOSSARY

ABBREVIATIONS AND GLOSSARY Applicants Manual for the period 2014-2020 Version 1.1 edited by the Managing Authority/Joint Secretariat Budapest, Hungary, 2016 Applicants Manual Abbreviations and Glossary 1 ABBREVIATIONS AA AF AfR

More information

Financial instruments in ESIF programmes

Financial instruments in ESIF programmes EUROPEAN COMMISSION Financial instruments in ESIF programmes 2014 2020 A short reference guide for Managing Authorities This short reference guide is designed to provide an overview of the main elements

More information

Interreg CENTRAL EUROPE Programme Implementation Manual. Version 1 ( )

Interreg CENTRAL EUROPE Programme Implementation Manual. Version 1 ( ) Interreg CENTRAL EUROPE Programme Implementation Manual Version 1 (08.07.2015) TABLE OF CONTENTS INTRODUCTION... 1 A. HOW TO GET STARTED WITH THE PROJECT... 3 A.1. General requirements... 3 A.1.1. Signing

More information

Guidance for Member States on Preparation, Examination and Acceptance of Accounts

Guidance for Member States on Preparation, Examination and Acceptance of Accounts EGESIF_15_0018-02 final 09/02/2016 EUROPEAN COMMISSION European Structural and Investment Funds Guidance for Member States on Preparation, Examination and Acceptance of Accounts DISCLAIMER: This is a document

More information

ANNUAL IMPLEMENTATION REPORT. The URBACT II Programme YEAR Objective concerned: Objective 3: European Territorial Cooperation

ANNUAL IMPLEMENTATION REPORT. The URBACT II Programme YEAR Objective concerned: Objective 3: European Territorial Cooperation The URBACT II Programme 2007-2013 ANNUAL IMPLEMENTATION REPORT YEAR 2007 OPERATIONNAL PROGRAMME: Objective concerned: Objective 3: European Territorial Cooperation Eligible area concerned: UE Member States

More information

ANNUAL DEVELOPMENT ACCOUNT PROGRESS REPORT

ANNUAL DEVELOPMENT ACCOUNT PROGRESS REPORT ANNUAL DEVELOPMENT ACCOUNT PROGRESS REPORT Note: The progress reports are part of the monitoring of the projects and will be used by the Programme Manager in the reporting to the General Assembly. The

More information

Factsheet n. 1 Introduction and Background

Factsheet n. 1 Introduction and Background INTERREG V A Italy Croatia CBC Programme Factsheet n. 1 Introduction and Background Version N 1 of 20 th February 2017 Programme co-financed by the European Regional Development Fund (ERDF) TABLE OF CONTENTS

More information

URBACT IMPLEMENTATION NETWORKS

URBACT IMPLEMENTATION NETWORKS URBACT IMPLEMENTATION NETWORKS URBACT in a nutshell European Territorial Cooperation programme (ETC) cofinanced by ERDF All 28 Member States as well as 2 Partner States (Switzerland and Norway) are eligible

More information

ERAC 1202/17 MI/evt 1 DG G 3 C

ERAC 1202/17 MI/evt 1 DG G 3 C EUROPEAN UNION EUROPEAN RESEARCH AREA AND INNOVATION COMMITTEE ERAC Secretariat Brussels, 2 March 2017 (OR. en) ERAC 1202/17 NOTE From: To: Subject: ERAC Secretariat Delegations ERAC Opinion on Streamlining

More information

Annex 3 First level control report including checklist

Annex 3 First level control report including checklist European Union European Regional Development Fund Sharing solutions for better regional policies Anne 3 First level control report including checklist The first level control report and checklist constitute

More information

DANUBE DANUBE Transnational Programme and CENTRAL EUROPE 2020 Richárd GÖNCZI National Contact Point, Hungary Széchenyi Programme Office

DANUBE DANUBE Transnational Programme and CENTRAL EUROPE 2020 Richárd GÖNCZI National Contact Point, Hungary Széchenyi Programme Office preparation of a transnational cooperation programme 2014- Transnational Programme and CENTRAL EUROPE Richárd GÖNCZI National Contact Point, Hungary Széchenyi Programme Office 22. April 2015 Content (0)

More information

INTERREG IIIC West Zone. Programme Complement

INTERREG IIIC West Zone. Programme Complement INTERREG IIIC West Zone Table of Content 1. Description of Measures... 1 1.1 Operation Type (a) Regional Framework Operations (RFO)... 2 1.2 Operation Type (b) Individual Co-operation Project:... 3 1.3

More information

Official Journal of the European Union

Official Journal of the European Union 13.5.2014 L 138/5 COMMISSION DELEGATED REGULATION (EU) No 480/2014 of 3 March 2014 supplementing Regulation (EU) No 1303/2013 of the European Parliament and of the Council laying down common provisions

More information

EUROPEAN COMMISSION. EGESIF_ final 22/02/2016

EUROPEAN COMMISSION. EGESIF_ final 22/02/2016 EGESIF_14-0015-02 final 22/02/2016 EUROPEAN COMMISSION GUIDELINES FOR DETERMINING FINANCIAL CORRECTIONS TO BE MADE TO EXPENDITURE CO-FINANCED BY THE EU UNDER THE STRUCTURAL FUNDS AND THE EUROPEAN FISHERIES

More information

Project Implementation Seminar

Project Implementation Seminar Project Implementation Seminar Financial Flows George Papapostolou Financial Officer JS Financial Flows Project implementation lifecycle Cash Flow Pre-Financing Amortization Cash Flow Pre-Financing Estimations

More information

1. Delegations will find in the Annex the fifth revision of the above-mentioned proposal.

1. Delegations will find in the Annex the fifth revision of the above-mentioned proposal. Council of the European Union Brussels, 18 December 2018 (OR. en) Interinstitutional File: 2018/0252(NLE) 11126/5/18 REV 5 ATO 51 CADREFIN 159 NOTE From: To: General Secretariat of the Council Delegations

More information

INTERACT III Communication Strategy

INTERACT III Communication Strategy INTERACT III 2014-2020 Communication Strategy INTERACT is co-financed by the European Regional Development Fund (ERDF) Contents Contents... 1 1 Introduction... 2 2 Analysis of the current situation...

More information

BALANCE. Reporting, auditing and payment. Kick-off meeting, Copenhagen, Denmark. Jesper H. Andersen 31 August + 1 September 2005

BALANCE. Reporting, auditing and payment. Kick-off meeting, Copenhagen, Denmark. Jesper H. Andersen 31 August + 1 September 2005 BALANCE Reporting, auditing and payment Kick-off meeting, Copenhagen, Denmark 31 August + 1 September 2005 Jesper H. Andersen (jha@dhi.dk) Reporting is based on the project description in the approved

More information

CENTRAL EUROPE Implementation Manual IMPLEMENTATION MANUAL

CENTRAL EUROPE Implementation Manual IMPLEMENTATION MANUAL IMPLEMENTATION MANUAL 1 TABLE OF CONTENTS 0. INTRODUCTION NOTE... 3 1. START-UP PHASE... 4 1.1 Subsidy Contract... 5 1.2 Partnership Agreement... 6 1.3 Setting-up project structures... 7 1.4 Start-up report...

More information

Generating successful projects, developing and managing the project pipeline Trainer: Robin Smail Independent Consultant & Visiting Expert EIPA

Generating successful projects, developing and managing the project pipeline Trainer: Robin Smail Independent Consultant & Visiting Expert EIPA Generating successful projects, developing and managing the project pipeline Trainer: Robin Smail Independent Consultant & Visiting Expert EIPA Successful projects: Operations that contribute to specific

More information

GUIDANCE HOW TO APPLY VIA THE ELECTRONIC MONITORING SYSTEM INTERREG V A LATVIA LITHUANIA PROGRAMME

GUIDANCE HOW TO APPLY VIA THE ELECTRONIC MONITORING SYSTEM INTERREG V A LATVIA LITHUANIA PROGRAMME Approved by the Head of the Managing Authority on 29 April 2016 Sandis Cakuls GUIDANCE HOW TO APPLY VIA THE ELECTRONIC MONITORING SYSTEM INTERREG V A LATVIA LITHUANIA PROGRAMME 2014 2020 Version 1.0 1

More information

Greece The former Yugoslav Republic of Macedonia IPA Cross-Border Programme SUBSIDY CONTRACT A

Greece The former Yugoslav Republic of Macedonia IPA Cross-Border Programme SUBSIDY CONTRACT A Greece The former Yugoslav Republic of Macedonia IPA Cross-Border Programme 2007-2013 SUBSIDY CONTRACT A No. : < > SUBSIDY CONTRACT No. In Athens, today, the , at the Ministry of Development,

More information

Revised 1 Guidance Note on Financial Engineering Instruments under Article 44 of Council Regulation (EC) No 1083/2006

Revised 1 Guidance Note on Financial Engineering Instruments under Article 44 of Council Regulation (EC) No 1083/2006 REVISED VERSION 08/02/2012 COCOF_10-0014-05-EN EUROPEAN COMMISSION DIRECTORATE-GENERAL REGIONAL POLICY Revised 1 Guidance Note on Financial Engineering Instruments under Article 44 of Council Regulation

More information

Council conclusions on the review of the European Union Strategy for the Baltic Sea Region

Council conclusions on the review of the European Union Strategy for the Baltic Sea Region COUNCIL OF THE EUROPEAN UNION Council conclusions on the review of the European Union Strategy for the Baltic Sea Region 325th GERAL AFFAIRS Council meeting Brussels, 5 November 20 The Council adopted

More information

Guidance for EoI and AF

Guidance for EoI and AF Guidance for EoI and AF Two-step call for proposals This guidance provides support to applicants in the development of their application documents in the ems (e-monitoring system). It refers to two-step

More information

User s guide for filling in the Execution Report

User s guide for filling in the Execution Report User s guide for filling in the Execution Report Investing in our commun future JTS Final-Version January 2011 1 JTS Final-Version January 2011 2 Table of Contents A - The implementation report form: general

More information