1 Follow up and reporting procedures Lead partners seminar 5th targeted call Lydwine Lafontaine
2 Table of contents Background information Subsidy contract Lead partner principles 1. Progress of the project: individual quality follow up a. Your aim b. The JTS aim c. How do we join our efforts? 2. Reporting procedures: programme rules a. Reporting frequency b. Content and quality of reporting c. Reporting trail d. IPA partners particularities
3 Table of contents 3. Financial issues FIRST LEVEL CONTROL (FLC) a. Definition of First Level Control b. Role and tasks of controller c. National control systems d. Complementary information ELIGIBILITY OF EXPENSES a. Reference documents (EU / MED / national rules) b. Principles c. Timeframe d. Budget lines e. Supporting documents f. Special attention DECOMMITMENT RULE AUDIT TRAIL
4 Background information Subsidy contract According to article 3 of the Subsidy Contract: A payment claim must be submitted to the JTS every 6 months Deadlines for submission must be respected (3 months) Payment claim includes: Progress report Certifications of expenditure Annexes: all material produced during the reporting period
5 Background information Subsidy contract According to articles 4 and 5 of the ERDF Subsidy Contract, the LP: signs the ERDF Subsidy Contract is responsible for the communication towards the program bodies is responsible for the communication within the partnership is responsible for the Progress Reports contents and ensure that all partners provide the necessary information regarding the drafting and eventual needed integrations to the reports receives the payment for all ERDF partners and has to redirect the partners share avoiding any delays (within 1 month). The monitoring role of the LP is essential
6 1. Progress of the project: individual quality follow up a. Your aim Make a change in the territories (visible, measurable) and make it last: Quality of production and outputs: produce something reliable, relevant, useful Generate outcomes and results: make target public know, have them use productions and outputs, make a difference in their lives Make it last: give a greater visibility, influence deeper, influence larger
7 1. Progress of the project: individual Support the Lead Partner and its partnership during the lifetime of the project To facilitate its implementation quality follow up b. The JTS aim To meet the objectives of the Project and the objectives of the Programme To ensure a high level of quality, with a result-oriented approach To maximise the impact on the target groups and the territories To ensure capitalisation and durability
8 1. Progress of the project: individual quality follow up c. How do we joint our efforts? JTS > project Attendance at and participation in project events Inform JTS (bilateral meetings if necessary) - plan ahead Proposals / orientations in the design of deliverables and the preparation of major events. For e.g. Kick off meeting coming soon (up to final conference) Project > JTS Attendance at programme events, contribute to programme network Participate in seminars, workshops (communication, capitalisation) Communicate dates to JTS for publication Use Programme tools for project dissemination and building community (website, social networks, library) Project > projects Capitalise and create synergies at any scale From former and on-going experience Create links with projects sharing a common approach (theme, aims, etc.) invite to events, work on common initiatives (newsletter for example, etc.) BREAK BARRIERS, AVOID ISOLATION AND CONFINEMENT
9 2. Reporting procedures: programme rules a. Reporting frequency Every 6 months a submission of: Progress report + annexes + list of deliverables (DBB) Payment claim + certifications of expenditure must be submitted to the JTS 5 th call projects Reporting period Starting date to 30 th June 1 st July to 31 st December Date of submission to the JTS 30 st September 31 st March Art: 3.3 of the Subsidy Contract.
10 2. Reporting procedures: programme rules b. Content and quality of reporting Progress report + annexes + list of deliverables (DBB) signed, comprehensive (+ part 4.1. publishable information) transparent, clear, honest supported with annexes: productions, list of signatures, pictures in case of events, agendas, list of participants, etc. in an organised way, easily identifiable (+ list of deliverables + publishable to be provided in.xls format) Payment claim + certifications of expenditure must be submitted to the JTS - signed, stamped, accurate, etc. - all related certificate, copies are sufficient Send full version in digital form and hard copies (provide DVD if necessary. In any case send DVD with all deliverables at the end of the project).
11 2. Reporting procedures: programme rules c. Reporting trail 1/ Each partner enters activities and expenditures on PRESAGE CTE Lead Partner validates the other partners expenses on PRESAGE CTE FLC of each partner (centralised or decentralised system) Validates the eligible expenditure Generates a First Level Control Certificate on PRESAGE CTE In Spain and Portugal: the FLC s certificate has to be validated by the responsible National Authority PP LP FLC/PP NA/FLC /PP 5 The Lead Partner gathers all the certificates and produce a payment claim + progress report on PRESAGE CTE LP 6 Submission to the JTS within the deadlines mentioned in the Subsidy Contract LP
12 2. Reporting procedures: programme rules c. Reporting trail 2/2 The JTS verifies the report: Conformity against application form 7 Conformity of validations by controllers against national systems Transfers to Managing Authority JTS/LP/ PP/FLC 8 9 The Managing Authority perform an additional control and ensures the precision of the payment claim, then communicates it to the Certifying Authority The Certifying Authority draws up payment order to the Lead partner MA/CA CA/LP 10 The Lead partner transfers funds to the ERDF partners LP
13 2. Reporting procedures: programme rules c. IPA particularities IPA partners will be able to make a request for advance payment, max 10% of allocated IPA budget Each IPA partner will sign a specific Subsidy Contract All their expenditures should be calculated in The Certifying Authority will draw up payment orders directly to the IPA partner concerned This system will be in place after the signature of the Financing Agreement between the competent Authorities of each IPA country in question, the European Commission, and the Managing Authority of the MED Programme.
14 3. Financial issues - FLC a. Definition of First Level Control Checks to be performed each time before submitting a payment claim in accordance with article 16 of Regulation 1080/2006 for ERDF partners & 108 of Regulation 718/2007 for IPA partners The reality of the declared expenditure The delivery of the products and services co-financed (as described in the approved Application Form) The soundness of the declared expenditure The compliance of such expenditure with Programme, EC and national rules Aims at checking the legality and the regularity of the expenditures declared by each partner Covers 100% of all declared expenses Administrative verifications; on-the-spot checks are recommended at least once during the project lifetime
15 3. Financial issues - FLC b. Role of tasks of the controller Shall ensure that activities and expenses are completed according to the national and Community eligibility regulations Shall check: All of the invoices, proofs of payment and any other justification document for declared expenditure The accounting precision of the declared expenses The mechanisms in place to avoid double funding Shall fill in and sign the First Level Control certificate trough PRESAGE CTE: First Level Controller Commitment Checklist Shall carry out checks within the deadlines set up in the Subsidy Contract Delays impede constant cash-flow and have a negative impact on financial performance of the projects and the programme
16 3. Financial issues - FLC c. National control systems 1/2 Each Member State (MS) / IPA Country: Has set up a First Level Control system Has determined the selection mode for controllers Each partner: must refer to the control system of the State where it is located must follow the information provided by the national bodies on the selection procedure
17 3. Financial issues - FLC c. National control systems 2/2 Centralized System ALBANIA* BOSNIA HERZEGOVINA* CROATIA* GREECE MALTA MONTENEGRO* SLOVENIA UK (Gibraltar) * This system will be in place after the signature of the Financing Agreement between the competent Authorities of each IPA country in question, the European Commission, and the Managing Authority. Decentralized System CYPRUS FRANCE ITALY SPAIN** Portugal** ** National validations must be obtained before submitting the payment claim. This must be taken into account in timetable for submitting claims.
18 3. Financial issues - FLC d. Complementary information 1/2 Donwload programme reference documents and guidance sorted by project phase
19 Example: Downloads in IMPLEMENTATION 3. Financial issues - FLC d. Complementary information 2/2
20 3. Financial issues - Eligibility of expenses a. Reference documents EU / MED / national rules 1/4 EU Regulations General Framework MED Programme Specific rules National rules
21 3. Financial issues - Eligibility of expenses a. Reference documents EU regulations 2/4 Council Regulation (EC) No 1083/2006 General Regulation + related amendments: (EC) No. 1341/ (EC) - No. 85/ (EC) No. 284/2009 Art. 56 Council Regulation (EC) No 1080/2006 ERDF Regulation + related amendment: (EC) No. 397/2009 Art. 7; Art. 13 Commission Regulation (EC) No 1828/2006 Implementing Regulation + related amendments (EC) No 846/2009 Art. 48 to Art. 53 Commission Regulation (EC) No 1085/2006 establishing an Instrument for Pre-Accession Assistance (IPA); Commission Regulation (EC) No 718/2007 Implementing Council Regulation + related amendments (EC) No 80/2010
22 3. Financial issues - Eligibility of expenses a. Reference documents EU regulations 3/4 Directive 2004/18/EC on Public works contracts, public supply contracts and public service contracts + amendments: Directive 2005/51/EC; Directive 2005/75/EC Commission Decision 2034 from 2007 defining Rules and procedures for service, supply and works contracts financed from the general budget of the European Communities for the purpose of cooperation with third countries Practical Guide to contract procedures for EC external actions (PRAG)
23 3. Financial issues - Eligibility of expenses a. Reference documents National rules 4/4 Each Member State defines specific rules on eligibility of expenditures - national manuals Project partners and first level controllers should always refer to relevant rules on eligibility defined at national level In case of doubt please contact NCP + JTS MED
24 3. Financial issues - Eligibility of expenses b. Principles Necessary to carry out project s activities/objectives Clearly related to activities foreseen in the approved AF Incurred during eligible periods (preparation-implementation-closure) Incurred within MED area. outside MED area but inside EU territory: duly justified and approved outside EU territory: approved case by case Real: actually borne directly by PPs and supported by accounting documents justifying incurred expenses/payments (invoices, pay rolls.) Supported by document attesting administrative procedures adopted (tenders, contract, ). Respect EU/Programme relevant rules Yes
25 3. Financial issues - Eligibility of expenses c. Timeframe Preparation costs 1/2 Engaged and invoiced between 1st January 2007 and date of submission of final AF Related payments within 1 month after the date of submission of final AF Link with preparation: direct and demonstrable Limit: Claimed: through 1 PR. Included in a specific certification of expenditure
26 3. Financial issues - Eligibility of expenses c. Timeframe Implementation/closure costs 2/2 Engaged, invoiced and paid out between: The day after the submission of complete AF Within date of project closure In case costs cannot be paid out within the date of project closure: paid out within two months after project closure Closure administrative expenditures (First Level Control and staff costs): may be engaged and paid out within two months after project closure EXCEPT for projects ending June 30 th 2015 Finalise documents to be submitted to FLC asap Do not wait the end of the reporting period
27 3. Financial issues - Eligibility of expenses d. Budget lines Staff Durable goods Consumable goods Travel and accommodation Services External expertise Promotion, information and publications Overheads Other First level control guidelines and fact sheets providing detailes information on: background information, guidance, supporting docs allocating costs on budget lines accounting
28 3. Financial issues - Eligibility of expenses e. Supporting documents 1/2 Staff List of personnel working on the project Employment/labour contracts or internal service orders Payslips Timesheets Evidence of the calculation method to calculate the hourly cost Proofs of payments of: salary, taxes, security schemes Durable/Consumable goods, services, external experts, promotion Evidence of compliance to public procurement rules at EU and national level: evidence of selection process Contracts Invoices Durable goods: evidence of the depreciation plan adopted for each element when depreciation applies Proofs of payment
29 3. Financial issues - Eligibility of expenses e. Supporting documents 2/2 Travel and accommodation List of personnel working on the project Agenda/programme of meeting/event Signed mission request/authorisation Travel invoices original tickets and all other original documentary evidence (i.e. boarding pass, invoices/other equivalent documents, in the case of e- tickets an with the booking number serves as a proof etc.) Proofs of payment Use of own car: reimbursement request through mileage sheet, according to national procedures and agreed values
30 3. Financial issues - Eligibility of expenses f. Special attention Public procurement VAT Depreciation Ineligible expenses (Representation expenditures, Interest on debt, Fines, Financial penalties, Expenditure on legal disputes, Exchange losses, Expenditures held outside the eligible period, Not supported by the relevant public procurement procedures, Lump sum, general estimations, unjustified calculations, VAT which is recoverable, Not justified by project s activities/objectives, Not supported by relevant documentation Revenues
31 3. Financial issues Decommitment rule 1/2 According to article 3.3 of the Subsidy Contract: «If the LP is claiming a payment for a six month period of which the amount of ERDF claimed is below the above foreseen amounts, there is no guarantee that the undeclared ERDF amount is available for the following periods, in regard to the art.93 of Regulation (EC) 1083/2006 (decommitment rule)» According to article 3.8 of the Subsidy Contract: «If the ERDF annuity of the MED Programme is decommitted by the Commission following the Regulation (EC)1083/2006, the authorities of the aforesaid programme reserve the option to cancel the ERDF subsidy related to expenses not incurred in due time.»
32 3. Financial issues Decommitment rule 2/2 If the Programme is not able to report the target of the relevant year, it will lose the ERDF not reported. This reduction will impact on the projects. Projects not respecting their contractual commitments could see their ERDF budget reduced. Selection Committee will decide the method of application of the decommitment rule.
33 3. Financial issues Audit trail 1/2 Partners must ensure that all accounting documents linked to the project are available and filed separately Original copies of documents to be kept by each partner Until December 31 st 2021 Later if requested at national level The Lead partner is responsible for the implementation of suitable audit trail overview Copies of documents to be sent to Lead partner (e-version) recommendation
34 3. Financial issues Audit trail 2/2 Partner must have a mechanism in place to avoid double funding (= same expenditure reimbursed by different sources of funding) In order to ensure a clear identification of the expenditures: Opening of a specific bank account for the project payments (or a separate project code); Recording of the costs in expenditure lists by budget line, component and reporting period; Noting the allocation (project title and project number) directly on the invoices/equivalent documents
35 Thank you for your attention Joint Technical Secretariat MED PROGRAMME
IPA partners seminar. Eligibility of expenditure and specificities of the public procurement. Dubrovnik, 5 th February 2013
IPA partners seminar Eligibility of expenditure and specificities of the public procurement Dubrovnik, 5 th February 2013 Index Reference documents Eligibility: General rules Timeframe Budget lines Supporting
More informationKnowledge and Innovation Consultants. Financial Management and Reporting Greek Magistral Lesson Izmir, 28/06/2011
Knowledge and Innovation Consultants Financial Management and Reporting Greek Magistral Lesson Izmir, 28/06/2011 Financial Management and Reporting 1 The financial management of a project requires the
More informationSouth East Europe (SEE) SEE Control Guidelines
South East Europe (SEE) SEE Control Guidelines Version 1.4. Final version approved by the MC 10 th June 2009 1 st amendment to be approved by MC (2.0) 1 CONTENTS 1 Purpose and content of the SEE Control
More informationMED PROGRAMME. First Level Control in practice. Most common mistakes - Follow-up measures
MED PROGRAMME First Level Control in practice Most common mistakes - Follow-up measures Torino 11 April 2011 BACKGROUND Major common mistakes detected during JTS check 1 st and 2 nd PR Delays in finalization
More informationFIRST LEVEL CONTROL: PRINCIPLES AND PRACTICE
CENTRAL EUROPE PROGRAMME 2007-2013 Project financial management and controls Vienna, 7 th April 2011 FIRST LEVEL CONTROL: PRINCIPLES AND PRACTICE 1. Validation of expenditure: the FLC 2. General principles
More informationELIGIBILITY OF EXPENSES: APPLICABLE RULES
INFO DAY ON PROJECT IMPLEMENTATION 1 ST CALL FOR PROJECT PROPOSALS ELIGIBILITY OF EXPENSES: APPLICABLE RULES Hierarchy of rules on eligibility of expenditure Rules defined in EU legal framework ERDF Programme
More informationFactsheet N 6 Project implementation: delivering project outputs, achieving project objectives and bringing about the desired change
Project implementation: delivering project outputs, achieving project objectives and bringing about the desired change Version No 13 of 23 November 2018 Table of contents I. GETTING STARTED: THE INITIATION
More informationFirst level control report including checklist
First level control report including checklist Project title Project acronym Project number Report Number 1. Project and progress report Name 2. Project Partner Name Organisation Job title Division/Unit/Department
More informationLead Partner Seminar. JS/MA Riga
Lead Partner Seminar JS/MA 9.12.2015 Riga Welcome to the Lead Partner Seminar Objective of the day: Give the Lead Partner the needed tools to best implement the project To know where to come with questions
More informationGuidance on management verifications Cooperation Programme Interreg V-A Greece - Italy
Guidance on management verifications Cooperation Programme Interreg V-A Greece - Italy 2014-2020 Greece-Italy v.10 1 Table of contents Introduction 1. General 1.1 Regulatory requirements 1.2 General principles
More informationTerms of Reference for the Fund Operator The EEA and Norway Grants Global Fund for Regional Cooperation EEA and Norwegian Financial Mechanisms
Terms of Reference for the Fund Operator The EEA and Norway Grants Global Fund for Regional Cooperation EEA and Norwegian Financial Mechanisms 2014-2021 Table of Contents 1. Introduction... 3 1.1 Objectives
More informationCENTRAL EUROPE Control and Audit Guidelines TABLE OF CONTENTS
TABLE OF CONTENTS 1. INTRODUCTION... 3 1.1. TERMINOLOGY... 4 1.2. REGULATORY FRAMEWORK... 5 1.3. THE DIFFERENT CONTROL LEVELS... 6 2. FIRST LEVEL CONTROL SET UP... 8 2.1. CONTROL SYSTEMS IN PLACE IN CENTRAL
More informationPROGRAMME RULES ON ELIGIBILITY OF EXPENDITURES
PROGRAMME RULES ON ELIGIBILITY OF EXPENDITURES Final version adopted by the JMC on 24 February 2016 Table of contents INTRODUCTION... - 4-1. LIST OF DEFINITIONS... - 4-2. LIST OF ABBREVIATIONS... - 5-3.
More informationFLC Guidance. Page 1. Version. September *Disclaimer: This is a living document and further content will be developed at a later stage.
FLC Guidance Version September 2017 *Disclaimer: This is a living document and further content will be developed at a later stage. Page 1 Table of Contents... 1 CHAPTER 1 General principles... 3 1.1 Introduction...
More informationPART 7: OVERVIEW ON PROJECT IMPLEMENTATION PRINCIPLES
Applicants Manual for the period 2014-2020 Version 1.1 PART 7: OVERVIEW ON PROJECT IMPLEMENTATION PRINCIPLES edited by the Managing Authority/Joint Secretariat Budapest, Hungary, 2015 Applicants Manual
More informationBudget & Finances. Interreg Europe Secretariat. 23 March 2016 Lead applicant workshop. Sharing solutions for better regional policies
European Union European Regional Development Fund Sharing solutions for better regional policies Budget & Finances Interreg Europe Secretariat 23 March 2016 Lead applicant workshop Session content 1. Preliminary
More informationControl Guidelines for INTERREG IPA CBC Programmes
Control Guidelines for INTERREG IPA CBC Programmes Version 3.0 June 2018-1 - Contents ABBREVIATIONS 4 1. EXECUTIVE SUMMARY 5 2. LEGISLATIVE AND INSTITUTIONAL FRAMEWORK 5 2.1. European legislative framework
More informationHow to plan your budget and project management?
European Union European Regional Development Fund Sharing solutions for better regional policies How to plan your budget and project management? Ilaria Piazza Interreg Europe Secretariat i.piazza@interregeurope.eu
More informationEligibility Rules of Expenditures
Eligibility Rules of Expenditures 1 The content of chapter 4.4, 4.5 and 4.6 may be subject of modification during the application phase. CONTENT 1. GENERAL PRINCIPLES AND REGULATORY FRAMEWORK... 2 1.1.
More informationAnnex 3 First level control report including checklist
European Union European Regional Development Fund Sharing solutions for better regional policies Anne 3 First level control report including checklist The first level control report and checklist constitute
More informationSMALL PROJECT CONSOLIDATED PROGRESS REPORT FORM including guidelines
SMALL PROJECT CONSOLIDATED PROGRESS REPORT FORM including guidelines GET ACQUAINTED WITH PROGRAMME MANUAL AND APPROPRIATE NATIONAL GUIDELINES BEFORE FILLING IN SMALL PROJECT PROGRESS / CONSOLIDATED PROGRESS
More informationFinancial rules and procedures
European Union European Regional Development Fund Sharing solutions for better regional policies Financial rules and procedures Ilaria Piazza Finance Officer Interreg Europe Content 1. Eligibility of expenditure
More informationHow to close the project
Training on Project & Financial Management and Communication; Vienna, 11-12 September 2013 How to close the project JTS CENTRAL EUROPE Agenda of the workshop Time span from 10h30 13h00 Welcome Presentation
More informationGUIDE FOR THE REIMBURSEMENT OF TRAVEL AND ACCOMMODATION EXPENSES AND PAYMENT OF SUBSISTENCE ALLOWANCES
Helsinki, 29 September 2009 Doc: MB/59/2009 final GUIDE FOR THE REIMBURSEMENT OF TRAVEL AND ACCOMMODATION EXPENSES AND PAYMENT OF SUBSISTENCE ALLOWANCES to Management Board members, Committee and Forum
More informationGUIDE FOR PROJECT IMPLEMENTATION
GUIDE FOR PROJECT IMPLEMENTATION PRACTICAL GUIDANCE FOR PROJECT PARTNERS Version 5.0 (15.1.2019) Contents 1. Introduction... 3 2. Starting up the project... 4 2.1. Fulfilling conditions... 5 2.2. Hand
More informationADRION 2 call for proposals Priority Axis 2 Financial aspects. Tirana, 11 April 2018
ADRION 2 call for proposals Priority Axis 2 Financial aspects Tirana, 11 April 2018 Overall budget and project budget Available programme budget: ERDF IPA Total EU contribution Priority Axis 2 29.197.521,05
More informationGUIDE FOR THE REIMBURSEMENT OF TRAVEL AND ACCOMMODATION EXPENSES AND PAYMENT OF SUBSISTENCE ALLOWANCES
GUIDE FOR THE REIMBURSEMENT OF TRAVEL AND ACCOMMODATION EXPENSES AND PAYMENT OF SUBSISTENCE ALLOWANCES to Management Board members, Committee and Forum members and other participants invited to attend
More informationINTERREG III B CADSES. Payment Claim Manual
INTERREG III B CADSES Payment Claim Manual 1) Background / Description of involved actors The following chapters give a short overview about the actors involved in the PIC Interreg III B Cadses, their
More informationFinancial Control. Thi s p r og r am m e is co- f i nanced by t he E ur op ean R eg i onal D ev el op m ent F und.
Financial Control Thi s p r og r am m e is co- f i nanced by t he E ur op ean R eg i onal D ev el op m ent F und. Financial flows and reporting European Commission Managing Authority/Certifying Authority
More information1st Level Control in the North Sea Region Programme
1st Level Control in the North Sea Region Programme First Level Control Seminar, 6/7 October 2010, Bergen Tomasz Petrykowski Joint Technical Secretariat Viborg Relevant bodies of the programme Organisations
More informationProject Implementation Seminar
Project Implementation Seminar Financial Flows George Papapostolou Financial Officer JS Financial Flows Project implementation lifecycle Cash Flow Pre-Financing Amortization Cash Flow Pre-Financing Estimations
More informationINTERREG 2 Seas Mers Zeeën First Level Control Manual
INTERREG 2 Seas Mers Zeeën 2014-2020 First Level Control Manual Version of 29/11/2018 Table of Content 1. INTRODUCTION... 5 1.1. PURPOSE AND OBJECTIVE OF THIS MANUAL... 5 1.2. TERMINOLOGY... 5 2. LEGAL
More informationPROCUREMENT OF SERVICES OPEN CALL FOR TENDERS (Article 29 decree No of 30/12/2005) FRAMEWORK CONTRACT
PROCUREMENT OF SERVICES OPEN CALL FOR TENDERS (Article 29 decree No. 2005-1742 of 30/12/2005) FRAMEWORK CONTRACT Object: The externalisation of First Level Control activities within the framework of the
More informationPartnership Agreement between the Lead Partner and the other project partners
Partnership Agreement between the Lead Partner and the other project partners Foreword This Partnership Agreement is signed on the basis of the following documents that form the legal framework applicable
More informationProject Changes. Lead Partner Seminar 4th Call for Proposal Budapest 10th December 2012
Project Changes Lead Partner Seminar 4th Call for Proposal Budapest 10th December 2012 Content 1. 2. 3. Fundamental principles Main categories of project change Single types of project change Fundamental
More informationCONSOLIDATED PROGRESS REPORT FORM including guidelines
CONSOLIDATED PROGRESS REPORT FORM including guidelines GET ACQUAINTED WITH PROGRAMME MANUAL AND APPROPRIATE NATIONAL GUIDELINES BEFORE FILLING IN PROGRESS / CONSOLIDATED PROGRESS REPORT PLEASE NOTE THAT
More informationERDF SUBSIDY CONTRACT NO...
The Government Office for Development and European Cohesion Policy, Kotnikova 5, SI 1000 Ljubljana, Slovenia, acting as the Managing Authority of the Cooperation Programme Interreg V-A Slovenia-Hungary
More informationFinancial rules and procedures in Interreg Europe - second call projects
European Union European Regional Development Fund Sharing solutions for better regional policies Financial rules and procedures in Interreg Europe - second call projects Aleksandra Niechajowicz Finance
More informationCHECK-LIST FOR CONTROLLERS/AUDITORS
Managing Authority Ministry of Finance of the Republic of Estonia Estonia Russia Cross Border Cooperation Programme 2014 2020 CHECK-LIST FOR CONTROLLERS/AUDITORS Template of control check-list Audit firm/public
More information8 th Financial Managers Seminar
2002-2012 A Decade of Territorial Evidence 8 th Financial Managers Seminar Athens, 7 March 2013 Reporting expenditure, eligibility, audit trail Reporting documents Activity Report (individual partner Activity
More informationProject Monitoring and Reporting Workshop for Interreg programmes
Project Monitoring and Reporting Workshop for Interreg programmes Who, why, how? 21-22 April 2016 Sofia, Bulgaria Interact is co-financed by the European Regional Development Fund (ERDF) Responsibilities
More informationGuidance document on. management verifications to be carried out by Member States on operations co-financed by
Final version of 05/06/2008 COCOF 08/0020/04-EN Guidance document on management verifications to be carried out by Member States on operations co-financed by the Structural Funds and the Cohesion Fund
More informationTable of contents. Introduction Regulatory requirements... 3
COCOF 08/0020/02-EN DRAFT Guidance document on management verifications to be carried out by Member States on projects co-financed by the Structural Funds and the Cohesion Fund for the 2007 2013 programming
More informationGUIDELINES FOR FIRST LEVEL CONTROL on CBC Programmes, co-financed by IPA BULGARIA - SERBIA BULGARIA - MACEDONIA BULGARIA - TURKEY
GUIDELINES FOR FIRST LEVEL CONTROL on CBC Programmes, co-financed by IPA BULGARIA - SERBIA BULGARIA - MACEDONIA BULGARIA - TURKEY Version* Date: Notes 1.1. May, 2011 Final approved version, valid for BG
More informationInterreg V-A Latvia Lithuania Programme
Interreg V-A Latvia Lithuania Programme 2014 2020 FINANCIAL CONTROL MANUAL Approved by the Head of the Managing Authority Sandis Cakuls on 02.11.2017 Version 2 TABLE OF CONTENTS 1. Introduction 4 2. General
More informationSIU Management and Monitoring System PROGRESS REPORT USER MANUAL PART 2
SIU Management and Monitoring System PROGRESS REPORT USER MANUAL PART 2 Version 1.0 of 14 August 2018 European Regional Development Fund www.italy-croatia.eu TABLE OF CONTENTS INTRODUCTION... 2 4.4.2 SECTION
More informationProject Selection Criteria Transnational Cooperation Programme Interreg Balkan Mediterranean
Project Selection Criteria Transnational Cooperation Programme Interreg Balkan Mediterranean 2014 2020 CCI 2014TC16M4TN003 22/06/2015 Version 1.0 Balkan-Mediterranean is co-financed by European Union and
More informationEuropean networks, experience and recommendations helping cities and citizens to become Energy Efficient
INTERREG IVC European networks, experience and recommendations helping cities and citizens to become Energy Efficient Mini-Programme Manual Updated version 22 February 2011 Mini-Programme Manual EnercitEE
More informationHaving regard to the Treaty on the Functioning of the European Union, and in particular Article 291 thereof,
L 244/12 COMMISSION IMPLEMTING REGULATION (EU) No 897/2014 of 18 August 2014 laying down specific provisions for the implementation of cross-border cooperation programmes financed under Regulation (EU)
More informationExpenditure reporting procedure in PRESAGE-CTE
Seminar for First Level Controllers MED Programme Expenditure reporting procedure in PRESAGE-CTE Thessaloniki, 24 th September 2010 Table of contents 1. To login to PRESAGE CTE 2. To enter expenditure
More informationSTART Danube Region Project Fund Workshop for Lead- and Project Partners. May, 6 th 2015 Vienna
START Danube Region Project Fund Workshop for Lead- and Project Partners May, 6 th 2015 Vienna PAC 10 & EuroVienna (Implementing Body) EUSDR Priority Area Coordinator 10 / (City of Vienna, Austria): Dr.
More informationABBREVIATIONS AND GLOSSARY
Applicants Manual for the period 2014-2020 Version 1.1 edited by the Managing Authority/Joint Secretariat Budapest, Hungary, 2016 Applicants Manual Abbreviations and Glossary 1 ABBREVIATIONS AA AF AfR
More informationEligibility rules, Financial control, Procurement
Eligibility rules, Financial control, Procurement Get started! seminar Munich Germany 2 February 2016 Christina Bauer Magdalena Friedwagner-Maislinger Wolfgang Schrattenecker Managing authority Thi s p
More informationProject Development - Rules on eligibility of expenditure
Project Development - Rules on eligibility of expenditure Interreg finance management camp 20 23 March 2018 I Sofia, Bulgaria Iuliia Kauk, Interact Programme Hierarchy of rules Rules on eligibility of
More informationAssignment Name: Workshop on EU Budget Support for civil servants of Macedonia Section 1. Introductory Information
P R O C U R E M E N T N O T I C E Assignment Name: Workshop on EU Budget Support for civil servants of Macedonia Section 1. Introductory Information 1.1 Background information on the Regional School of
More informationGuidelines for the AF DSP call for proposals
Guidelines for the AF DSP call for proposals A stream of cooperation edited by the Managing Authority/Joint Secretariat Budapest, Hungary, 2018 Programme co-funded by the European Union Table of content
More informationCoordinators' day on ICT PSP project management Financial Issues, Reporting, payments, cost claims and Certification Modalities
Coordinators' day on ICT PSP project management Financial Issues, Reporting, payments, cost claims and Certification Modalities Ann Van Menxel DG CNECT H6 Brussels, 17 December 2013 Legal references Reimbursement
More informationProject Implementation. Project Implementation Seminar Monika Balode, Project Coordinator September 2018 Tallinn & Stockholm
Project Implementation Project Implementation Seminar Monika Balode, Project Coordinator September 2018 Tallinn & Stockholm Contents Result orientation Cooperation Lead partner principle Guidance documents
More informationFirst Level Controller MANUAL
First Level Controller MANUAL P r o g r a m m e co- f i n a n c e d b y E R D F P a g e 1 72 Version 2 (08/03/2018) P r o g r a m m e co- f i n a n c e d b y E R D F P a g e 2 72 This document will be
More informationInterreg IPA Cross-border Cooperation Programme Greece-Albania
Interreg IPA Cross-border Cooperation Programme Greece-Albania 2014-2020 SUBSIDY CONTRACT No. In Thessaloniki, today, the , at the premises of the Managing Authority located at 65, Leoforos
More informationFirst Level Control of finance and activities: The Programme rules
First Level Control of finance and activities: The Programme rules First Level Control seminar Germany Hamburg, 6 September 2016 Carsten Westerholt and Christian Byrith Agenda a lot of information presented
More informationReporting and First Level Control of Finance and Activities
Reporting and First Level Control of Finance and Activities First Level Control Seminar, 6/7 October 2010, Bergen Isabella Leong, Jesper Jönsson, Christian Zieske Joint Technical Secretariat Viborg Rules
More informationTABLE OF CONTENTS PREFACE 0 GENERAL PROVISIONS 1 STAFF COSTS 2 OFFICE AND ADMINISTRATIVE EXPENDITURE 3 TRAVEL AND ACCOMMODATION COSTS
CATALOGUE OF ELIGIBLE COSTS Interreg V-A Euregio Meuse-Rhine Version 3 - December 2018 TABLE OF CONTENTS PREFACE 0 GENERAL PROVISIONS 0.1 LEGAL BASIS 0.2 ELIGIBLE COSTS 0.2.1 INTERNAL INVOICING 0.2.2 CASH
More informationINTERNATIONAL ORGANISATIONS QUESTIONS
INTERNATIONAL ORGANISATIONS QUESTIONS A. General 1. What is an International Organisation? An international Organisation can only be considered as such under the Financial Regulation if the following criteria
More informationF A C T S H E E T PROGRAMME MANUAL. Interreg IPA CBC Italy Albania Montenegro Programme. 4.7 Project changes and ems procedures
F A C T S H E E T Interreg IPA CBC Italy Albania Montenegro Programme PROGRAMME MANUAL 4.7 Project changes and ems procedures Current version 01 Updated 1 October 2018 Contacts js@italy-albania-montenegro.eu
More informationINTERREG V-A GREECE-ITALY PROGRAMME PATRA 24/04/2018 PREVEZA 26/04/2018
INTERREG V-A GREECE-ITALY PROGRAMME 2014-2020 PATRA 24/04/2018 PREVEZA 26/04/2018 1 FIRST LEVEL CONTROL GUIDELINES & PROCEDURES 2 General Guidelines (1/8) Regulation (EU) 1303/2013, Article 125 Functions
More informationFact Sheet 13 Roles and responsibilities in project partnerships
Roles and responsibilities in project partnerships Valid from Valid to Main changes Version 3 03.05.17 -Minor wording change recommending the use of the same FLC for local partnerships. -Clarified the
More informationFinancial Webinar. IMI 2 projects :00 CET
Financial Webinar IMI 2 projects 12.05.2017 10:00 CET Agenda How to use GoToWebinar o Gaëlle Lanckmans, IMI Finance Cost Eligibility o Gaëlle Lanckmans, IMI Finance Reporting requirements and Migration
More informationImportant Messages - Grants
GRANT IMPORTANT MESSAGES Important Messages - Grants SCOPE Important messages contain: 1) procedural rules ( procedure ) e.g. interpretation of the PRAG or internal procedures etc. 2) recommendations e.g.
More informationProject Administration
Co-funded by the European Union Project Administration Maria Grazia Bonanomi, UCSC Diverse Kick-off meeting - Milan, 22-24 January 2014 Outline: - Context - Key features - Final Reporting Package - Eligible
More information1 st call for proposals, 2 nd call for proposals, Priority 3 Better network of harbours version
1 st call for proposals, 2 nd call for proposals, Priority 3 Better network of harbours version 14.09.16 Annex 2 Revenue Guidelines Table of contents Table of contents 1 1. Abbreviations and definitions
More informationFact Sheet; Errors, financial corrections, irregularities, recoveries and withdrawals
The 2014 2020 Interreg Programme Management Handbook is composed of fact sheets. Each theme is covered by one fact sheet so that the reader can easily and quickly choose the relevant fact sheet. Fact Sheet;
More informationGREECE-THE FORMER YUGOSLAV REPUBLIC OF MACEDONIA I.P.A. CROSS BORDER PROGRAMME
Greece - The former Yugoslav Republic of Macedonia 2007-2013 IPA Cross-Border Programme GREECE-THE FORMER YUGOSLAV REPUBLIC OF MACEDONIA I.P.A. CROSS BORDER PROGRAMME 2007-2013 PROGRESS REPORT no. co-financed
More informationLIFE Grant Agreement Financial Aspects Highlights
LIFE Grant Agreement Financial Aspects Highlights Kick-off Meetings Call 2016 Action Grants Strand buddies (EASME) Congratulations for obtaining the Grant! And Welcome to the Finance presentation SUMMARY
More informationANNEX. to the Comission Decision. amending Decision C(2013) 1573
EUROPEAN COMMISSION Brussels, 30.4.2015 C(2015) 2771 final ANNEX 1 ANNEX to the Comission Decision amending Decision C(2013) 1573 on the approval of the guidelines on the closure of operational programmes
More informationGUIDANCE DOCUMENT ON THE FUNCTIONS OF THE CERTIFYING AUTHORITY. for the programming period
Final version of 25/07/2008 COCOF 08/0014/02-EN GUIDANCE DOCUMENT ON THE FUNCTIONS OF THE CERTIFYING AUTHORITY for the 2007 2013 programming period Table of contents 1. Introduction... 3 2. Main functions
More informationGreece The former Yugoslav Republic of Macedonia IPA Cross-Border Programme SUBSIDY CONTRACT A
Greece The former Yugoslav Republic of Macedonia IPA Cross-Border Programme 2007-2013 SUBSIDY CONTRACT A No. : < > SUBSIDY CONTRACT No. In Athens, today, the , at the Ministry of Development,
More informationRULES ON ELIGIBILITY OF COSTS
Annex 1 of the Call for proposals RULES ON ELIGIBILITY OF COSTS These rules present various possible categories of eligible costs. The call for proposal may then stipulate that only some of the below categories
More informationTERMS OF REFERENCE FOR AN EXPENDITURE VERIFICATION OF A GRANT CONTRACT - EXTERNAL ACTION OF THE EUROPEAN UNION -
TERMS OF REFERENCE FOR AN EXPENDITURE VERIFICATION OF A GRANT CONTRACT - EXTERNAL ACTION OF THE EUROPEAN UNION - HOW TO USE THIS TERMS OF REFERENCE MODEL? All text highlighted in yellow in this ToR model
More informationFact Sheet 14 - Partnership Agreement
- Partnership Agreement Valid from Valid to Main changes Version 2 27.04.15 A previous version was available on the programme website but all projects must use this version. Core message: It is a regulatory
More informationSeed Money Facility. Lead Applicants seminar Budapest, 11 April 2016
Seed Money Facility Lead Applicants seminar Budapest, 11 April 2016 Seed Money Facility (SMF) Call main elements Content: Aim and format of the SMF call Governance Project structure Partnership and partners
More informationInterreg Nord
Interreg Nord 2014-2020 Programme area Nord and Sápmi First level control in Nord programme Sweden centralized system for FLC Two FLC at County Administrative Board of Norrbotten, placed in Luleå Finland
More informationFirst Level Control of finance and activities: The Programme rules
First Level Control of finance and activities: The Programme rules First Level Control seminar Norway Oslo, 23 January 2017 Carsten Westerholt and Christian Byrith Agenda a lot of information presented
More informationFinancial Guidelines for Beneficiaries EDCTP Association October 2016
Financial Guidelines for Beneficiaries EDCTP Association October 2016 This document is prepared as a supplement to the Grant Agreement (GA), where majority of the information is extracted from. In the
More informationVersion 4: 29 th June 2017
PROGRAMME RULES INTERREG VA CROSS-BORDER PROGRAMME FOR TERRITORIAL CO-OPERATION 2014-2020 NORTHERN IRELAND, BORDER REGION OF IRELAND AND WESTERN SCOTLAND & PEACE IV EU PROGRAMME FOR PEACE AND RECONCILIATION
More informationInvesting in your future
Investing in your future ESF Certifying Authority, Department of Education and Skills Circular 1/2012 (Replacing ESF Certifying Authority, Department of Enterprise Trade and Employment Circular 1/2008)
More information3 rd Call for Project Proposals
IPA CROSS-BORDER PROGRAMME "GREECE THE FORMER YUGOSLAV REPUBLIC OF MACEDONIA 2007-2013" 3 rd Call for Project Proposals Project Selection Criteria CCI: 2007 CB 16 I PO 009 The following Project Selection
More informationPAC Guidelines for Project Progress Report
PAC Guidelines for Project Progress Report Version 1.0 September 2017 A stream of cooperation Programme co-funded by the European Union Content List of abbreviations... 5 Introduction... 6 PART I TECHNICAL
More informationIMPLEMENTATION GUIDE
European Territorial Cooperation Programme Med 2007-2013 (CCI 2007 CB 163 PO 045) European regional development fund IMPLEMENTATION GUIDE Version May 2012 SUMMARY Introduction... 4 1. Main characteristics
More informationFINANCIAL GUIDELINES AND STANDARDS FOR EVENT MANAGEMENT
ANNEX 2 FINANCIAL GUIDELINES AND STANDARDS FOR EVENT MANAGEMENT (to be fine-tuned upon contract signature) 2 INDEX Page 1. FOREWORDS. 5 2. GENERAL PRINCIPLES.. 5 3. BUDGET MANAGEMENT WORKFLOW 5 3.1 PRE-EVENT
More informationWaterways Forward. Project management issues. 3rd PWG meeting 8 September 2010, Milan
Waterways Forward Project management issues 3rd PWG meeting 8 September 2010, Milan Contents Presentation of project status process and administrative issues; 1st 8 months of implementation compared to
More informationEuropean Commission Directorate General for Development and Cooperation - EuropeAid
European Commission Directorate General for Development and Cooperation - EuropeAid Practical guide to procedures for programme estimates (project approach) Version 4.0 December 2012 CONTENTS 1. INTRODUCTION...
More informationWelcome and Introduction
Welcome and Introduction Halfway through the programming 2014-2020 halfway through the programme spending? 22 February 2018 I Nice, France Iuliia Kauk, Interact Objectives Get an update on the state of
More informationCOMMISSION DECISION. of on technical provisions necessary for the operation of the transition facility in the Republic of Croatia
EUROPEAN COMMISSION Brussels, 13.6.2013 C(2013) 3463 final COMMISSION DECISION of 13.6.2013 on technical provisions necessary for the operation of the transition facility in the Republic of Croatia EN
More informationGUIDELINES FOR FIRST LEVEL CONTROL ON INTERREG-IPA BULGARIA SERBIA, BULGARIA TURKEY AND BULGARIA FORMER YUGOSLAV REPUBLIC OF MACEDONIA CBC PROGRAMMES
GUIDELINES FOR FIRST LEVEL CONTROL ON INTERREG-IPA BULGARIA SERBIA, BULGARIA TURKEY AND BULGARIA FORMER YUGOSLAV REPUBLIC OF MACEDONIA CBC PROGRAMMES Version* Date: Notes 1.2. June 2017 Final approved
More informationUser s guide for filling in the Execution Report
User s guide for filling in the Execution Report Investing in our commun future JTS Final-Version January 2011 1 JTS Final-Version January 2011 2 Table of Contents A - The implementation report form: general
More informationFinancial Reporting First Level Control
Financial Reporting First Level Control Xander Storms Frank Everaarts It s not that hard! Report twice a year about content, progress and costs The Lead Beneficiary collects and integrates the data Those
More informationImplementation Manual. Version 2.1 December 2016
Implementation Manual Version 2.1 December 2016 Content INTRODUCTION... 6 A. HOW TO GET STARTED WITH THE PROJECT... 9 A.1. General requirements... 9 A.1.1. Signing the subsidy contract... 9 A.1.2. Setting
More informationURBACT III Programme Manual
URBACT III Programme Manual Fact Sheet 4B National URBACT Points Section 1. National URBACT Points in the URBACT III Operational programme: context and objective Section 2. Role of National URBACT Points
More informationProject Implementation Manual Transnational Cooperation Programme Interreg Balkan-Mediterranean
Project Implementation Manual Transnational Cooperation Programme Interreg Balkan-Mediterranean 2014-2020 CCI 2014TC16M4TN003 Adopted by the Monitoring Committee, on 05/05/2017 Balkan-Mediterranean is
More information