1 USING THE NEW ENGLAND ELECTRIC SYSTEM LEAST COST PLANNING MODEL FOR PLANNING AND EVALUATING CONSERVATION AND LOAD MANAGEMENT PROGRAMS Elizabeth Hicks New England Power Service Company In 1985, the New England Electric System (NEES) developed a least cast planning model to support its balanced planning efforts. This PC based model is used by NEES to evaluate demand and supply options on an equal basis. The model is used to develop NEES's long range plan to meet its forecasted load growth. This paper will: 1) present an overview of NEES, ) briefly describe the NEES least cast planning model, ) describe the balanced process at NEES, 4) illustrate how the model is used in planning for new demand side programs, and 5) demonstrate how the model is used to evaluate existing demand side programs. OVERVIEW OF THE NEW ENGLAND ELECTRIC SYSTEM NEES has a holding company structure. It has retail companies serving about one-third of Massachusetts, almost three-quarters of Rhode Island, and a few towns in New Hampshire. The system has a peak demand of over 9 HW, 19 billion kwh in annual sales, and 1. million customers. The distribution of sales is: residential (8%), commercial (5%) and industrial (6%). Growth in sales has been over 5% on average for the past 4 years. OVERVIEW OF THE LEAST COST MODEL The NEES least cost model is easy to use and is us ed throughout the company. Major inputs to the model include economic assumptions, a long term forecast of energy and demand, marginal costs of energy and capacity, as weil as specific project information. The types of projects included in the model are conservation, load management, unit life extension, utility generation, and alternative energy contracts. Project specific information includes the costs in each year of the project, annual HW benefits of the project, escalators and other economic assumptions, and load duration curve impacts. The model computes the revenue requirements for each project on an annual and net present worth basis. The benefit of each project, whether supply or demand side, is computed identically --- a kwh is valued at the marginal energy cost and a kwat the value of deferring the construction of a gas turbine for one year. 8.97
2 The user can select the dispatch interval used in the model as weil as how to value the differences between summer and winter capacity. Af ter this is selected the model calculates the costs and benefits of each project. The user can rank the project uuder a number of different criteria including total cost/benefit, $/mw, mwhs, or a combination ranking. The users of the model use these rankings as weil as judgement and scenario analysis to develop a least cost plan. The model has major outputs: a production costing run, revenue requirements by project, and contribution by type of capacity to a given plan. BALANCED PLANNING AT NEES Balanced planning at NEES is an approach to evaluating the portfolio of options available to NEES to economically and reliably serve future customer requirements. Projects of all types including supply side options such as new generation and alternative energy are compared to demand side options on a consistent economic basis. This process has four phases. The first phase is the program analysis phase. In this phase an interdisciplinary group of personnel at NEES work together. The group includes representatives from demand planning, economic planning, power supply, engineering, and alternate energy. This group is responsible for developing the individual projects and developing an initial plan. This group uses the least cost model to screen individual and groups of projects. The next phase in the planning process is to use the initial least cost plan in a series of scenario analysis. This phase began by identifying the variables that influence planning at NEES. The variables identified included: load growth, fuel prices, regulatory conditions at a FERC level and at a state level, and local economic conditions. From this range of variables a number of plausible scenarios are developed. In NEES' most recent long range plan, 15 scenarios were developed in all. These scenarios were examined in detail and it was determined that several of the scenarios had similar outcomes. Thus the number of scenarios was narrowed to six. The scenarios for the most recent plan are: Base Case (.4 % annual growth before demand programs) High Growth (continued high economic growth in the region) Capacity Constraints/Slow Economy (the economy slows, some planned capacity is lost) C&LM takes off (accelerated demand-side activity) Oil interruption (high fuel prices leading to high electric prices) Industrial Bypass (deregulation of the electric utility industry) The range in load growth for these 6 scenarios is presented in Figure 1. The related capacity requirements range from 4 MW to 1 MW.
3 The third phase of the NEES planning process is probability analysis. The purpose of this phase is to quantify uncertainties that affect plans and provides an estimate of how certain a given supply plan will actually meet future needs. In this phase, the most uncertain assumptions of possible supply plans are identified by the group working on probability analysis. The most uncertain assumptions are: load growth, alternative energy development, success of demand side programs, availability of purchased power and utility generation. Experienced NEES personnel assign probabilities to each of these variables. The resuit is a plan that meets the Company's capability responsibility over the next ten years. The final phase in the balanced planning process is to examine the financial impact of the plan. The cost impact on the customers as weil as the financial impact on the shareholders is examined. The results of all phases of the plan are then used by the planning team to create a final, balanced, least cost plan for NEES. The resultant plan contains a balanced mix of resources. This is presented graphically in Figure. The mix includes demand-side programs, alternate energy, purchased power, unit life extensions, and utility generation. Unit life extension if expected to contribute over 6 HW of needed capacity the year 7. Conservation and load management is expected to supply about 5 percent of incremental needs by 7. PLANNING NEW DEMAND-SIDE PROGRAMS Previous sections of this paper have briefly described the NEES least cost model and the balanced planning process at NEES. The remaining sections of this paper will describe in more detail the planning and evaluation of demand-side programs at NEES. Ideas for new demand-side programs at NEES come from a variety of sources. Results of pilot programs, research on new technologies, end use data, regulatory input, and results of programs at other utilities are used as inputs into this process. Teams of employees are formed from a number of organizational functions to develop ideas for new programs. The teams develop possible program designs and try to identify program barriers. Program concepts that look promising are developed further and are ultimately included in the balanced planning process. Before a demand-side program is included in the least cost model, a number of assumptions about the program must be developed. Information is required on the demand and energy impacts, expected market participation, life of the program impacts, and expected program costs. There are uncertainties associated with each of these assumptions, particularly expected market penetration. Some technologies, such as lighting replacement, have reasonably certain engineering savings associated with their implementation. For example, the associated savings of replacing a 4 watt fluorescent tube with a watt tube is a savings of 8 watt. In the case of a water heater wrap, where the 8.99.' '. "
4 usage depends on the number of people in the household, income and a whole host of socioeconomic variables as weil as the efficiency of the water heater, the estimate of savings is more difficult. Sensitivity analysis of each of the assumptions is done by the program planners. Usually assumptions are varied by 1-4 percent to evaluate how sensitive the cost effectiveness of the program is to the assumptions. A consensus on the assumptions is developed by the program planners. These consensus assumptions are then used in the program analysis phase where demand-side programs are compared to supply options. EVALUATING DEMAND-SIDE PROGRAMS There is a lot of uncertainty associated with demand-side programs. For this reason, demand-side programs are systematically evaluated at NEES. Not only are the energy and demand impacts quantified, but market penetration and customer acceptance are also assessed. Quite of ten, the results from the evaluation of a demnad-side program are significantly different that those us ed in the planning process. The results of the evaluation are then fedback into the next round of demand-side planning. Recent examples include a refrigerator rebate program (actual savings were 8 kwh/year, initial savings estimates were kwh) () and a lighting rebate (actual savings were 6% of total customer usage, initial savings estimates were 14 % of usage). Once actual costs and energy and peak savings are calculated, the same least cost model is used to to calculate a cost/benefit ratio. Actual program results are compared to each other and the other resource options. The long range plans are adjusted to these changes if necessary. CONCLUSIONS The NEES balanced planning process is one that compares supply and demand side options on a consistent basis to meet long term capacity needs. The process is one that considers a wide range of scenarios. The resuit is a long range capacity plan that is both flexible and meets NEES's capacity needs. A critical piece of this planning process is the design of new demand side programs. An in-house PC model is used to assist in the design of new demand side programs. This model is also used to evaluate demand side programs. REFERENCES (1) LowelI, J. and Others, Balanced Planning Guideline Report, New England Power Service Company, December, 1986 () New England Electric System, Evaluation Report on Massachusetts Electric Company's Enterprise Plan, Executive Summary, March,
5 FIGURE 1 Required Capacity 1 High Growth HICKS. 9 8 Base Case 7... Capacity Constraints! 6 Slow Economy " c ;s: ro C&LM Takes Off ~ 5 Oil Interruption.c I- 4 Industrial Bypass FIGURE Recommended Plan - Estimated Mix... " C ro ::J.c Contribution in 7 89 MW 1% 975 MW 4% 1 MW 5% 61 MW
For the Efficiency Maine Trust October 15, 2009 Eric Belliveau, Optimal Energy Inc.
DSM Economics For the Efficiency Maine Trust October 15, 2009 Eric Belliveau, Optimal Energy Inc. DSM Economics - Overview Why? Basics of Economics Benefits Costs Economic Test Overviews Economics of Sample
More informationMay 3, Dear Ms. Bordelon:
Entergy Services, Inc. 639 Loyola Avenue (70113) P.O. Box 61000 New Orleans, LA 70161-1000 Tel 504 576 4122 Fax 504 576 5579 Michael J. Plaisance Senior Counsel Legal Services - Regulatory May 3, 2018
More informationModeling and IRP Analysis of EE Resources in the Southwest
Modeling and IRP Analysis of EE Resources in the Southwest Jeff Schlegel, Ellen Zuckerman, & Adam Bickford Southwest Energy Efficiency Project (SWEEP) ACEEE EE as a Resource Conference -- October 31, 2017
More informationFinal Application for New License for Major Water Power Project Existing Dam
Final Application for New License for Major Water Power Project Existing Dam Northfield Mountain Pumped Storage Project (FERC Project Number 2485) Turners Falls Hydroelectric Project (FERC Project Number
More informationEnergy Efficiency Modeling Discussion. October 14th, 2016
Energy Efficiency Modeling Discussion October 14th, 2016 Major Energy Efficiency Modeling Assumptions 2 Vectren s IRP process will inform the level of Energy Efficiency (EE) to achieve in future program
More informationFIVE YEAR PLAN FOR ENERGY EFFICIENCY
FIVE YEAR PLAN FOR ENERGY EFFICIENCY Executive Summary Prepared for: Holy Cross Energy Navigant Consulting, Inc. 1375 Walnut Street Suite 200 Boulder, CO 80302 303.728.2500 www.navigant.com July 15, 2011
More informationAPPENDIX B: PORTFOLIO OPTIMIZATION MODEL
APPENDIX B: PORTFOLIO OPTIMIZATION MODEL PUBLIC UTILITY DISTRICT #1 OF SNOHOMISH COUNTY Prepared by Generation, Power, Rates, and Transmission Management Division Snohomish County PUD DRAFT 2017 Integrated
More informationGeneration Production Costs, Scheduling & Operating Rate
Disclaimer This training presentation is provided as a reference for preparing for the PJM Certification Exam. Note that the following information may not reflect current PJM rules and operating procedures.
More informationExhibit DAS-1. Tucson Electric Power Company Demand-Side Management Program Portfolio Plan
Exhibit DAS-1 Tucson Electric Power Company Demand-Side Management Program Portfolio Plan 2008-2012 TABLE OF CONTENTS 1. Introduction...3 2. DSM Portfolio Performance Costs, Savings and Net Benefits...3
More informationSUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS. ENERGY EFFICIENCY AND CUSTOMER-OWNED RESOURCES.
25.181. Energy Efficiency Goal. (a) (b) (c) Purpose. The purposes of this section are to ensure that: (1) electric utilities administer energy savings incentive programs in a market-neutral, nondiscriminatory
More informationPennsylvania s Energy Efficiency Uncapped
Pennsylvania s Energy Efficiency Uncapped Assessing the Potential Impact of Expanding the State s Energy Efficiency Program Beyond the Current Budget Cap Prepared for Keystone Energy Efficiency Alliance
More informationRevenue Requirement Application. 2004/05 and 2005/06. Volume 2. Appendix I. Power Smart 10-Year Plan
Revenue Requirement Application 2004/05 and 2005/06 Volume 2 Appendix I. Power Smart 10-Year Plan 10-Year Plan: 2002/03 through 2011/12 December 2, 2003 Table of Contents 1 PLAN SUMMARY...1 2 PLAN COST-EFFECTIVENESS
More informationEIPC Roll-Up Report & Scenarios
EIPC Roll-Up Report & Scenarios Zach Smith Director, Transmission Planning New York Independent System Operator IPTF/EGCWG/ESPWG Meeting January 6, 2014 2013 New York Independent System Operator, Inc.
More informationEnergy Conservation Resource Strategy
Energy Conservation Resource Strategy 2008-2012 April 15, 2008 In December 2004, EWEB adopted the most recent update to the Integrated Electric Resource Plan (IERP). Consistent with EWEB s three prior
More informationPublic Service Company of New Hampshire Comparison of Rates Effective July 1, 2014 and January 1, 2015
R Customer charge July 1, 2014 $ 12.39 $ 12.39 $ 12.39 All KWH $ 0.04042 $ 0.01786 $ (0.00225) $ 0.00330 $ 0.00055 $ 0.05988 $ 0.09870 $ 0.15858 R Customer charge January 1, 2015 $ 12.50 $ 12.50 $ 12.50
More informationMAR 2017 JAN 2017 DEC 2016 FEB 2017 HOEP*
Ontario Energy Report Q3 Electricity July September Electricity Prices Commodity Commodity cost comprises of two components, the wholesale price (the Hourly Ontario Energy Price) and the Global Adjustment.
More informationLong Run Marginal Cost (LRMC)
Long Run Marginal Cost (LRMC) Ryan Steele Power Supply Planning Specialist Agenda & Objectives Preliminary Discussion PART I Provide a historic overview of FBC s LRMC Highlights from BC Hydro s stated
More informationPublic Service Company of New Hampshire dba Eversource Energy Comparison of Rates Effective July 1, 2017 and January 1, 2018
R Customer charge July 1, 2017 $ 12.64 $ 12.64 $ 12.64 All KWH $ 0.04125 $ 0.02542 $ (0.00094) $ 0.00356 $ 0.00055 $ 0.06984 $ 0.11660 $ 0.18644 R Customer charge January 1, 2018 $ 12.69 $ 12.69 $ 12.69
More informationWashington Utilities and Transportation Commission
Mission Statement: The UTC protects consumers by ensuring that utility and transportation services are fairly priced, available, reliable, and safe. Washington Utilities and Transportation Commission Incorporation
More informationCITY OF HEALDSBURG RESOLUTION NO
CITY OF HEALDSBURG RESOLUTION NO. 91-2001 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF HEALDSBURG MODIFYING RESOLUTION 57-2001 BY ELIMINATING VARIOUS DISCOUNTS AND CREDITS AND ADDING A PUBLIC BENEFITS
More informationRaising Rivals Costs in Interconnected Wholesale Natural Gas and Electricity Markets
Raising Rivals Costs in Interconnected Wholesale Natural Gas and Electricity Markets Levi Marks University of California, Santa Barbara Kristina Mohlin Environmental Defense Fund Charles Mason University
More informationGEORGIA PUBLIC SERVICE COMMISSION
GEORGIA PUBLIC SERVICE COMMISSION Georgia Power Company s 01 Integrated Resource Plan and Application for Decertification of Plant Mitchell Units, A and B, Plant Kraft Unit 1 CT, and Intercession City
More informationTwelfth Revised Sheet No FLORIDA POWER & LIGHT COMPANY Cancels Eleventh Revised Sheet No INDEX OF CONTRACTS AND AGREEMENTS
Twelfth Revised Sheet No. 10.001 FLORIDA POWER & LIGHT COMPANY Cancels Eleventh Revised Sheet No. 10.001 INDEX OF CONTRACTS AND AGREEMENTS Sheet No. Contract Provisions - Various 10.010 Distribution Substation
More informationPrepared for the BC Sustainable Energy Association. Expanding Energy Efficiency for BC Hydro: Lessons from Industry Leaders.
Prepared for the BC Sustainable Energy Association Expanding Energy Efficiency for BC Hydro: Lessons from Industry Leaders June 19, 2012 Overview 1. Key Terms and Concepts 2. BC Hydro s IRP 3. US Data
More informationExplanatory note data publication Front Report
Explanatory note data publication Front Report At the end of each business day, ICE Endex establishes settlement prices for all the markets it operates. The Front Report as published in the ICE Report
More informationARTICLE 24. SECTION 1. Sections and of the General Laws in Chapter 24-18
======= art.0/1 ======= 1 ARTICLE 1 1 1 0 1 0 SECTION 1. Sections -1- and -1- of the General Laws in Chapter -1 entitled Municipal Road and Bridge Revolving Fund are hereby amended to read as follows:
More informationDated: October 24, 2016 BEFORE THE STATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION
C, 1T BEFORE THE STATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION J, -,. In the matter of: ) Electric Distribution Utilities ) Docket No. DE 1- ) Development of New Alternative Net Metering Tariffs )
More informationThe Company's resource management effort is a continuous process. used by the Company to manage its portfolio in order to: (i) maximize the use of
V. MANAGEMENT OF THE RESOURCE PORTFOLIO A. Introduction The Company's resource management effort is a continuous process used by the Company to manage its portfolio in order to: (i) maximize the use of
More informationBC Hydro Revenue Requirements Application Evidence #1
BC Hydro Revenue Requirements Application Evidence #1 BCUC Project No.: 3698430 By: Ludo Bertsch, Horizon Technologies Inc. For: ESVI Energy Solutions for Vancouver Island Society Date: Oct 6, 2006 Background
More informationComverge Qualifications
Comverge Commercial Group National Demand Response Presentation Comverge Qualifications Public Company listed on the NASDAQ (Ticker: COMV) Largest Demand Response Provider 6.1 GW enabled through 5 million
More informationAugust EEAC Small Business Offerings & Services. August 16, 2017
August EEAC Small Business Offerings & Services August 16, 2017 Topics 1. Small Businesses in Massachusetts 2. Dive into Turnkey Small Business Services 3. Small Business Case Study 2 Stage Setting: Small
More informationCalifornia Independent System Operator Corporation Fifth Replacement Electronic Tariff
Table of Contents 39. Market Power Mitigation Procedures... 2 39.1 Intent Of CAISO Mitigation Measures; Additional FERC Filings... 2 39.2 Conditions For The Imposition Of Mitigation Measures... 2 39.2.1
More information16 th Revision of Sheet No. 83 Canceling 15 th Revision of Sheet No. 83, 7 th Revision WN U-60 of Sheet No. 255 and 2 nd Revision of Sheet No.
16 th Revision of Sheet No. 83 Canceling 15 th Revision of Sheet No. 83, 7 th Revision WN U-60 of Sheet No. 255 and 2 nd Revision of Sheet No. 255-a, INC. ELECTRICITY CONSERVATION SERVICE 1. PURPOSE: To
More information4.1 Daily & Hourly Bid Components
4.1 Daily & Hourly Bid Components This section is based on CAISO Tariff Section 30.4 Election for Start-Up and Minimum Load Costs and Section 39.6.1.6. (Start-Up and Minimum Load Costs are not applicable
More informationManual 05. NYISO Day-Ahead Demand Response Program Manual
Manual 05 NYISO Day-Ahead Demand Response Program Manual Issued: December, 2018 Version: 4.0 Effective Date: 12/03/2018 Committee Acceptance: 11/14/2018 BIC Prepared by: NYISO Distributed Resources Operations
More informationREPORT TO THE PUBLIC UTILITIES BOARD
REPORT TO THE PUBLIC UTILITIES BOARD CURTAILABLE RATE PROGRAM APRIL 1, 2011 MARCH 31, 2012 JULY 2012 TABLE OF CONTENTS Page No. SUMMARY... 1 BACKGROUND... 1 PERFORMANCE FOR 2011/12... 3 Curtailment Options...3
More informationFinancial Implications of using Energy Efficiency to contribute towards meeting a Federal RES: Case Study of Kansas
Financial Implications of using Energy Efficiency to contribute towards meeting a Federal RES: Case Study of Kansas Peter Cappers Charles Goldman Lawrence Berkeley National Laboratory ACE 5 th National
More informationFebruary 20, National Grid Renewable Energy Standard Procurement Plan Docket No. 3765
February 20, 2007 Luly Massaro Clerk Public Utilities Commission 89 Jefferson Boulevard Warwick, Rhode Island 02888 Re: National Grid Renewable Energy Standard Procurement Plan Docket No. 3765 Dear Luly:
More informationGT Pricing in RTD. Presented by Andrew P. Hartshorn Principal, LECG. Market Structures Working Group. DRAFT: For Discussion Purposes Only
GT Pricing in RTD Presented by Andrew P. Hartshorn Principal, LECG Market Structures Working Group Albany, NY May 17 th, 2005 AGENDA Today s presentation will illustrate the revised approach for the scheduling
More informationMASSACHUSETTS CROSS-CUTTING BEHAVIORAL PROGRAM EVALUATION INTEGRATED REPORT JUNE 2013
MASSACHUSETTS CROSS-CUTTING BEHAVIORAL PROGRAM EVALUATION INTEGRATED REPORT JUNE 2013 Prepared for: MASSACHUSETTS ENERGY EFFICIENCY ADVISORY COUNCIL & BEHAVIORAL RESEARCH TEAM Prepared by: OPINION DYNAMICS
More informationLong Island Power Authority Approved 2002 Operating Budget Approved 2002 and 2003 Capital Budgets
Approved 2002 Operating Budget Approved 2002 and 2003 Capital Budgets George E. Pataki Governor Richard M. Kessel Chairman LONG ISLAND POWER AUTHORITY APPROVED 2002 OPERATING BUDGET APPROVED 2002 AND 2003
More informationKEY FINDINGS AND RESOURCE STRATEGY
KEY FINDINGS AND RESOURCE STRATEGY The Council s Power Plan Goal - Ensure an adequate, efficient and affordable regional power system Major Components Forecast of regional electricity demand over the next
More informationBEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION
BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION IN THE MATTER OF SOUTHWESTERN PUBLIC SERVICE COMPANY S APPLICATION REQUESTING: ( ACKNOWLEDGEMENT OF ITS FILING OF THE 0 ANNUAL RENEWABLE ENERGY PORTFOLIO
More informationAPPENDIX B: WHOLESALE AND RETAIL PRICE FORECAST
Seventh Northwest Conservation and Electric Power Plan APPENDIX B: WHOLESALE AND RETAIL PRICE FORECAST Contents Introduction... 3 Key Findings... 3 Background... 5 Methodology... 7 Inputs and Assumptions...
More informationTHE NARRAGANSETT ELECTRIC COMPANY RENEWABLE ENERGY GROWTH PROGRAM FOR NON-RESIDENTIAL CUSTOMERS
Sheet 1 1. Introduction This tariff ( Tariff ) describes the terms and conditions under which an Applicant for an eligible distributed generation project ( DG Project ) will receive funding pursuant to
More informationNiagara Mohawk Power Corporation d/b/a National Grid Residential Building Practices and Demonstration Program: Impact Evaluation Summary
Niagara Mohawk Power Corporation d/b/a National Grid Residential Building Practices and Demonstration Program: Impact Evaluation Summary PROGRAM SUMMARY Prepared by: DNV KEMA, January 15, 2014 The OPower-administered
More informationEnergy Efficiency Resource Ramping Assumptions
Energy Efficiency Resource Ramping Assumptions Class 2 DSM Resource Ramping This document presents the methods used by The Cadmus Group, Inc. (Cadmus) and the Energy Trust of Oregon (Energy Trust) to develop
More informationDraft Small Customer Aggregation Program Rules
Draft Small Customer Aggregation Program Rules 1. Aggregations must be at least 2.0 MW for DADRP, 1.0 MW for RTDRP, 100 kw for SCR and 100 kw for EDRP. In each case the requirement is zone-specific. The
More informationIMPACT AND PROCESS EVALUATION OF AMEREN ILLINOIS COMPANY BEHAVIORAL MODIFICATION PROGRAM (PY5) FINAL OPINION DYNAMICS. Prepared for: Prepared by:
IMPACT AND PROCESS EVALUATION OF AMEREN ILLINOIS COMPANY S BEHAVIORAL MODIFICATION PROGRAM (PY5) FINAL Prepared for: AMEREN ILLINOIS COMPANY Prepared by: OPINION DYNAMICS 1999 Harrison Street Suite 1420
More informationPAUL CHERNICK ELLEN HAWES
STATE OF NEW HAMPSHIRE BEFORE THE PUBLIC UTILITIES COMMISSION Development of New Alternative Net Metering ) Tariffs and/or Other Regulatory Mechanisms ) Docket No. DE 1- and Tariffs for Customer-Generators
More informationRIPUC No Sheet 1 THE NARRAGANSETT ELECTRIC COMPANY RENEWABLE ENERGY GROWTH PROGRAM COST RECOVERY PROVISION
Sheet 1 1. INTRODUCTION The Company s rates for Retail Delivery Service are subject to adjustment to reflect the recovery of costs incurred in accordance with the provisions of Rhode Island General Laws
More informationFinal Version October 19, ENERGY EFFICIENCY PLAN TERM SHEET
CORE PRINCIPLES ENERGY EFFICIENCY PLAN TERM SHEET Energy efficiency is a cornerstone of the Commonwealth s long term energy policy. The Plan ( Plan ) reflects this key role and builds upon the high level
More informationDerivative market design & performance. Masterclass for the Restructured Electricity Industry August 2005 CEEM, 2005
Derivative market design & performance Masterclass for the Restructured Electricity Industry 24-26 August 2005 CEEM, 2005 Participant motivation for trading electricity derivatives: price-risk management
More informationFiled with the Iowa Utilities Board on September 22, 2016, TF STATE OF IOWA DEPARTMENT OF COMMERCE BEFORE THE IOWA UTILITIES BOARD
STATE OF IOWA DEPARTMENT OF COMMERCE BEFORE THE IOWA UTILITIES BOARD IN RE: ) DOCKET NO. TF-2016-0290 ) INTERSTATE POWER AND ) RESPONSE LIGHT COMPANY ) ) The Environmental Law & Policy Center and the Iowa
More informationRESPONSES TO INTERROGATORIES OF LOW-INCOME ENERGY NETWORK INTERROGATORIES
EB-0-00 Schedule Filed: 0 Apr Page of INTERROGATORY A-: Reference(s): Community Outreach and Education Initiative THESL CDM Application: Community Outreach & Education at Page describes Priority Neighbourhoods
More informationSTATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION DOCKET NO. DE PUBLIC SERVICE COMPANY OF NEW HAMPSHIRE
Attachment EHC-R-1 Page 1 of 2 STATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION DOCKET NO. DE 14-238 PUBLIC SERVICE COMPANY OF NEW HAMPSHIRE Date Request Received: 10/2/15 Date of Response: 10/16/15
More informationResidential Rate OIR Rate Design and Bill Impact Analysis Model
Residential Rate OIR Rate Design and Bill Impact Analysis Model Table of Contents Table of Contents... 1 Overview... 3 Embedded Help Function... 3 Using the Model... 4 Description of Inputs and Running
More informationActual neighborhood of Sunrun customer homes
This presentation contains forward-looking statements within the meaning of Section 27A of the Securities Act of 1933 and Section 21E of the Securities Exchange Act of 1934. Forward-looking statements
More informationAll text in Red Italics is sample verbiage or instructions and may to be removed from the final document.
ESA / IGA Schedules Project Documents include the following Schedules which are incorporated herein and made a part of the IGA and ESA when approved by the ISSUER and ESCO: Schedule A Schedule B Schedule
More informationCITY OF BURLINGTON, VERMONT ELECTRIC DEPARTMENT. Financial Statements and Required Supplementary Information. June 30, 2017 and 2016
Financial Statements and Required Supplementary Information (With Independent Auditors Report Thereon) Table of Contents Page(s) Independent Auditors Report 1 2 Management s Discussion and Analysis Required
More informationElectric Rate Schedule GS-2 General Service - Demand
Page 1 of 5 Applicability This Schedule is applicable to general commercial customers having demands in excess of 20 kilowatts and less than 1,000 kilowatts, and public units for residential occupancy.
More informationOPTIONAL LARGE GENERAL SERVICE - HIGH OFF-PEAK USE
6100 Neil Road, Reno, Nevada 68th Revised PUCN Sheet No. 79 Tariff No. Electric No. 1 Cancelling 67th Revised PUCN Sheet No. 79 APPLICABLE This schedule is available as an option to Schedule No. GS-3 for
More informationWinter Reliability Assessment En Banc Hearing Docket No. M
225 North Shore Drive Pittsburgh, PA 15212-5861 www.eqt.com TEL 412.395.3205 FAX 412.395.3155 November 4, 2005 James J. McNulty Secretary Pennsylvania Public Utility Commission Commonwealth Keystone Building
More informationComparison of Performance-Based Capacity Models in ISO-NE and PJM June 2, 2016
Comparison of Performance-Based Capacity Models in ISO-NE and PJM June 2, 2016 Michael Borgatti, Director, RTO Services Gabel Associates, Inc. Michael.Borgatti@gabelassociates.com 732.296.0770 1 Goals
More informationReal Time Scheduling. Reserve Settlements
Real Time Scheduling Reserve Settlements General Settlement Rules There will be a full two settlement. Reserve services will be scheduled and settled nominally on a 5-min. basis. Units are not required
More informationEstimating Capacity Benefits of the AC Transmission Public Policy Projects
Memorandum TO: NYISO Board of Directors FROM: David B. Patton and Pallas LeeVanSchaick DATE: RE: Estimating Capacity Benefits of the AC Transmission Public Policy Projects A. Introduction In the second
More informationQuarterly Report to the Pennsylvania Public Utility Commission
Quarterly Report to the Pennsylvania Public Utility Commission For the Period September 1, 2015 through November 30, 2015 Program Year 7, Quarter 2 For Pennsylvania Act 129 of 2008 Energy Efficiency and
More informationCalifornia Independent System Operator Corporation Fifth Replacement Electronic Tariff
Table of Contents 39. Market Power Mitigation Procedures... 2 39.1 Intent Of CAISO Mitigation Measures; Additional FERC Filings... 2 39.2 Conditions For The Imposition Of Mitigation Measures... 2 39.2.1
More informationCalifornia ISO October 1, 2002 Market Design Elements
California October 1, 2002 Market Design Elements California Board of Governors Meeting April 25, 2002 Presented by Keith Casey Manager of Market Analysis and Mitigation Department of Market Analysis 1
More informationChapter 7 DESIGN FLAWS AND A WORSENING CRISIS. Sequential Markets and Strategic Bidding
Chapter 7 DESIGN FLAWS AND A WORSENING CRISIS During the first two successful years of restructuring in California, prices declined. This initial success meant that the restructured market s design flaws
More informationPSEG ANNOUNCES 2017 THIRD QUARTER RESULTS. Net Income of $0.78 Per Share. Non-GAAP Operating Earnings of $0.82 Per Share
For further information, contact: Investor News NYSE: PEG Kathleen A. Lally, Vice President Investor Relations Phone: 973-430-6565 Carlotta Chan, Manager - Investor Relations Phone: 973-430-6596 PSEG ANNOUNCES
More informationQuarterly Report to the Pennsylvania Public Utility Commission
Quarterly Report to the Pennsylvania Public Utility Commission For the Period September 1, 2015 through November 30, 2015 Program Year 7, Quarter 2 For Pennsylvania Act 129 of 2008 Energy Efficiency and
More informationWASTE HEAT TO POWER. DOE; Pacific CHP; Northwest CHP; California Stationary Fuel Cell Collaborative. Project Financing Considerations.
WASTE HEAT TO POWER DOE; Pacific CHP; Northwest CHP; California Stationary Fuel Cell Collaborative Project Financing Considerations Wally McOuat HMH Energy Resources, Inc. 100 Larkspur Landing Circle,
More informationnew. york. independent. system. operator
new. york. independent. system. operator nyiso Day-Ahead Demand Response Program Manual revised: 05. 1821. 2001 1 nyiso Day-Ahead Demand Reduction Program Manual (Rev. 5/1821/2001) 1.0 Definitions and
More informationPortland General Electric Reports 2017 Financial Results and Initiates 2018 Earnings Guidance
February 16, 2018 Portland General Electric Reports 2017 Financial Results and Initiates 2018 Earnings Guidance Full-year 2017 financial results on target excluding the effects of the Tax Cuts and Jobs
More informationHydro-Québec Requête R DOMINION BOND RATING SERVICE LIMITED AOÛT Original : HQT-8, Document 3.
A Requête R-3401-98 DOMINION BOND RATING SERVICE LIMITED AOÛT 2000 Original : 2000-08-15 HQT-8, Document 3.2 (En liasse) Bond, Long Term Debt and Preferred Share Ratings (The rating is based on the Provincial
More informationXcel Energy Minnesota 2012 Rate Case Overview (Docket No:12-961) November 15, 2012
Xcel Energy Minnesota 2012 Rate Case Overview (Docket No:12-961) November 15, 2012 *All data is from: U.S. Department of Energy Energy Information Administration Minnesota Chamber of Commerce We represent
More informationAnnual Report to the Pennsylvania Public Utility Commission For the period December 2009 to May 2010 Program Year 2009
Annual Report to the Pennsylvania Public Utility Commission For the period December 2009 to May 2010 Program Year 2009 For Act 129 of 2008 Energy Efficiency and Conservation Program Prepared by Duquesne
More informationEffective for SERC Region applicable Registered Entities on the first day of the first calendar quarter after approved by FERC.
Effective Date Effective for SERC Region applicable Registered Entities on the first day of the first calendar quarter after approved by FERC. Introduction 1. Title: Automatic Underfrequency Load Shedding
More informationSolar is a Bright Investment
Solar is a Bright Investment Investing in a solar system seems like a great idea, but what are the financial implications? How much will it cost and what is the payback? These are common questions that
More informationThe following words and terms shall have the following meanings when used in this Tariff:
Sheet 1 1. Introduction This tariff ( Tariff ) describes the terms and conditions under which an Applicant for an eligible distributed generation project ( DG Project ) will receive funding pursuant to
More informationBOARD OF PUBLIC UTILITIES KANSAS CITY, KANSAS
BOARD OF PUBLIC UTILITIES KANSAS CITY, KANSAS Electric Utility Revenues, Revenue Requirements, Cost of Service, And Rates Draft Final Report (As Updated) February 2010 February 1, 2010 Kansas City Board
More informationAdvice 4991-E-C Issued by Date Filed July 23, 2018 Decision Robert S. Kenney Effective July 23, 2018 Vice President, Regulatory Affairs Resolution
Revised Cal. P.U.C. Sheet No. 42644-E Cancelling Revised Cal. P.U.C. Sheet No. 40233-E ELECTRC SCHEDULE E-BP Sheet 1 BASE NTERRUPTBLE PROGRAM APPLCABLTY: This rate schedule is available until modified
More informationRegulatory and Tax Treatment of Electric Resources
Regulatory and Tax Treatment of Electric Resources Stan Hadley and Eric Hirst, Oak Ridge National Laboratory Integrated resource planning (IRP) focuses on providing customer energy-service needs at the
More informationSolar PV where the sun doesn t shine: Estimating the economic impacts of support schemes for residential PV with detailed net demand profiling
Sources: www.engineersjournal.ie; www.investopedia.com; www.theguardian.com Solar PV where the sun doesn t shine: Estimating the economic impacts of support schemes for residential PV with detailed net
More informationPower 2022 Tariff Evaluation Methodology. 19 July 2018
Power 2022 Tariff Evaluation Methodology 19 July 2018 Contents Part 1 Tariff Evaluation Methodology Structure and Calculation Part 2 Bidder Inputs to the TEM Part 3 TEM Outputs Refer for more detail to
More informationMICHIGAN PUBLIC SERVICE COMMISSION Case No.: U-18411
Exhibit No.: A-1 (JRC-1) Calculation of Base GCR Ceiling Factor Page: 1 of 1 Twelve-Month Period Ending March 31, 2019 Witness: JRCoker Based on the December 2017 COG Forecast and the November 2017 Sales
More informationVillage of Lyndonville Electric Department (A Component Unit of the Village of Lyndonville, Vermont) FINANCIAL STATEMENTS.
FINANCIAL STATEMENTS TABLE OF CONTENTS Page INDEPENDENT AUDITOR S REPORT MANAGEMENT S DISCUSSION AND ANALYSIS FINANCIAL STATEMENTS Statements of Net Position 1 Statements of Revenues, Expenses and Changes
More informationMerrill Lynch Sues Reliant Over Termination of Working Capital Facility
December 30, 2008 Merrill Lynch Sues Reliant Over Termination of Working Capital Facility Merrill Lynch & Co. filed a suit against Reliant Energy in the Supreme Court of the State of New York, alleging
More informationNPCC 2017 MARITIMES AREA INTERIM REVIEW OF RESOURCE ADEQUACY
NPCC 2017 MARITIMES AREA INTERIM REVIEW OF RESOURCE ADEQUACY NEW BRUNSWICK POWER CORP. NOVA SCOTIA POWER INC. MARITIME ELECTRIC COMPANY, LIMITED NORTHERN MAINE ISA, INC. Approved by RCC December 5, 2017
More informationSTATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS PUBLIC UTILITIES COMMISSION
STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS PUBLIC UTILITIES COMMISSION IN RE: THE NARRAGANSETT : ELECTRIC COMPANY : d/b/a NATIONAL GRID : GAS COST RECOVERY CHARGE : DOCKET NO. 4520 REPORT AND ORDER
More informationUnderstanding Variable Consideration. May 22, 2018 MEMBER OF ALLINIAL GLOBAL, AN ASSOCIATION OF LEGALLY INDEPENDENT FIRMS
Understanding Variable Consideration May 22, 2018 MEMBER OF ALLINIAL GLOBAL, AN ASSOCIATION OF LEGALLY INDEPENDENT FIRMS 2018 Wolf & Company, P.C. Before we get started Today s presentation slides can
More informationDemand-Side Management Annual Status Report Electric and Natural Gas Public Service Company of Colorado
Demand-Side Management Annual Status Report Electric and Natural Gas Public Service Company of Colorado March 31, 2018 / Proceeding No. 16A-0512EG 2017 xcelenergy.com 2018 Xcel Energy Inc. Xcel Energy
More informationUnitil Corporation Earnings Conference Call. First Quarter 2018
Unitil Corporation Earnings Conference Call First Quarter 2018 Financial and Other Information April 26, 2018 Safe Harbor Provision This presentation contains forward-looking statements made pursuant to
More informationEEAC EM&V Briefing. Ralph Prahl EEAC Consultant EM&V Team Leader July 9th, 2013
EEAC EM&V Briefing Ralph Prahl EEAC Consultant EM&V Team Leader July 9th, 2013 Organization of Presentation EM&V in Massachusetts: Past, Present and Future Past Background Review of MA EM&V Framework Current
More informationA New Resource Adequacy Standard for the Pacific Northwest. Background Paper
A New Resource Adequacy Standard for the Pacific Northwest Background Paper 12/6/2011 A New Resource Adequacy Standard for the Pacific Northwest Background Paper CONTENTS Abstract... 3 Summary... 3 Background...
More informationTHE NARRAGANSETT ELECTRIC COMPANY RENEWABLE ENERGY GROWTH PROGRAM COST RECOVERY PROVISION
Sheet 1 of 6 1. INTRODUCTION The Company s rates for Retail Delivery Service are subject to adjustment to reflect the recovery of costs incurred in accordance with the provisions of Rhode Island General
More informationEast Central Energy. Rate schedule C&I. C&I Interruptible Service Effective: March 2018 revenue month Energy bills due in April
East Central Energy Rate schedule C&I C&I Interruptible Service Effective: March 2018 revenue month Energy bills due in April Availability This service is available to all non-residential members who agree
More informationCross-border exchange and sharing of generation reserve capacity
Cross-border exchange and sharing of generation reserve capacity Fridrik Mar Baldursson, Reykjavik University Ewa Lazarczyk, Reykjavik University Marten Ovaere, KU Leuven Stef Proost, KU Leuven ference,
More informationAcceptance Criteria: What Accuracy Will We Require for M&V2.0 Results, and How Will We Prove It?
Acceptance Criteria: What Accuracy Will We Require for M&V2.0 Results, and How Will We Prove It? 1 Quality, accurate results Tool testing can tell us that 2.0 technologies are reliable can model, predict
More information