Effective for SERC Region applicable Registered Entities on the first day of the first calendar quarter after approved by FERC.

Size: px
Start display at page:

Download "Effective for SERC Region applicable Registered Entities on the first day of the first calendar quarter after approved by FERC."

Transcription

1 Effective Date Effective for SERC Region applicable Registered Entities on the first day of the first calendar quarter after approved by FERC. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements 2. Number: PRC-006-SERC Purpose: To establish consistent and coordinated requirements for the design, implementation, and analysis of automatic underfrequency load shedding (UFLS) programs among all SERC applicable entities. 4. Applicability: 4.1 Coordinators 4.2 UFLS entities shall mean all entities that are responsible for the ownership, operation, or control of UFLS equipment as required by the UFLS program established by the Coordinators. Such entities may include one or more of the following: Transmission Owners Distribution Providers 4.3 Generator Owners 5. Background The SERC UFLS Standard: PRC-006-SERC-01 ( SERC UFLS Standard ) was developed to provide regional UFLS requirements to entities in SERC. UFLS requirements have been in place at a continent-wide level and within SERC for many years prior to implementation of federally mandated reliability compliance standards in When reliability standards were implemented in 2007, the Federal Energy Regulatory Commission ( FERC ), which is the government body with regulatory responsibility for electric reliability, issued FERC Order 693, recognizing 83 NERC Reliability Standards as enforceable by FERC and applicable to users, owners, and operators of the bulk power system (BPS). FERC did not approve the NERC UFLS standard, PRC in Order 693. FERC s reason for not approving PRC was that it recognized PRC as a fill-in the blank standard, and regional procedures associated with the standard were not submitted along with the standard. FERC s ruling in Order 693 required Regional Entities to provide the regional requirements necessary for completing the UFLS standard. In 2008, SERC commenced work on PRC-006-SERC-01. NERC also began work on revising PRC at a continent-wide level. The SERC standard has been developed to be consistent with the NERC UFLS standard. PRC-006-SERC-02 was developed per periodic review of the standard. PRC clearly defines the roles and responsibilities of parties to whom the standard applies. The standard identifies the Coordinator ( PC ) as the entity responsible for developing UFLS schemes within their PC area. The regional standard adds specificity not contained in the NERC standard for development and implementation of a UFLS scheme in the SERC Region that effectively mitigates the consequences of an underfrequency event. Page 1 of 13

2 Requirements and Measures R1. Each Coordinator shall include its SERC subregion as an identified island in the criteria (required by the NERC PRC standard on UFLS) for selecting portions of the BPS that may form islands. [Violation Risk Factor: Medium] [Time Horizon: Long-term ] 1.1 A Coordinator may adjust island boundaries to differ from subregional boundaries where necessary for the sole purpose of producing a contiguous subregional island more suitable for simulation. M1. Each Coordinator shall have evidence such as a methodology, procedure, report, or other documentation indicating that its criteria included selection of its SERC subregion(s) as an island per Requirement R1. R2. Each Coordinator shall select or develop an automatic UFLS scheme (percent of load to be shed, frequency set points, and time delays) for implementation by UFLS entities within its area that meets the following minimum requirements: [Violation Risk Factor: Medium] [Time Horizon: Long-term ] 2.1. Have the capability of shedding at least 30 percent of the Peak Demand (MW) served from the Coordinator s transmission system. The Peak Demand may be either summer or winter as determined by the Coordinator Shed load with a minimum of three frequency set points The highest frequency set point for relays used to arrest frequency decline shall be no lower than 59.3 Hz and not higher than 59.5 Hz This does not apply to UFLS relays with time delay of one second or longer and a higher frequency setpoint applied to prevent the frequency from stalling at less than 60 Hz when recovering from an underfrequency event The lowest frequency set point shall be no lower than 58.4 Hz The difference between frequency set points shall be at least 0.2 Hz but no greater than 0.5 Hz Time delay (from frequency reaching the set point to the trip signal) shall be at least six cycles. M2. Each Coordinator shall have evidence such as reports or other documentation that the UFLS scheme for its area meets the design requirements specified in Requirement R2. Page 2 of 13

3 R3. Each Coordinator, when performing design assessments specified in the NERC PRC standard on UFLS, shall conduct simulations of its UFLS scheme for an imbalance between load and generation of 13%, 22%, and 25% for all identified island(s) where such imbalance equals [(load minus actual generation output) / load]. [Violation Risk Factor: High] [Time Horizon: Long-term ] M3. Each Coordinator shall have evidence such as reports or other documentation that it performed the simulations of its UFLS scheme as required in Requirement R3. R4. Each UFLS entity that has a total load of 100 MW or greater in a Coordinator area in the SERC Region shall implement the UFLS scheme developed by their Coordinator. UFLS entities may implement the UFLS scheme developed by the Coordinator by coordinating with other UFLS entities. The UFLS scheme shall meet the following requirements on May 1 of each calendar year. [Violation Risk Factor: Medium] [Time Horizon: Operations ] 4.1. The percent of load shedding to be implemented shall be based on the actual or estimated substation or feeder demand (including losses) of the UFLS entities at the time coincident with the previous year s actual Peak Demand in the season specified by the Coordinator in R The amount of load in each load shedding step shall be within -1.0 and +3.0 of the percentage specified by the Coordinator (for example, if the specified percentage step load shed is 12%, the allowable range is 11 to 15%) The amount of total UFLS load of all steps combined shall be within -1.0 and +5.0 of the percentage specified by the Coordinator for the total UFLS load in the UFLS scheme. M4. Each UFLS entity that has a total load of 100 MW or greater in a Coordinator area in the SERC Region shall have evidence such as reports or other documentation demonstrating that its implementation of the UFLS scheme on May 1 of each calendar year meets the requirements of Requirement R4 (including all the data elements in Parts 4.1, 4.2, and 4.3) unless scheme changes per Requirement R6 are in process. R5. Each UFLS entity that has a total load less than 100 MW in a Coordinator area in the SERC Region shall implement the UFLS scheme developed by their Coordinator, but shall not be required to have more than one UFLS step. UFLS entities may implement the UFLS scheme developed by the Coordinator by coordinating with other UFLS entities. The UFLS scheme shall meet the following requirements on May 1 of each calendar year. [Violation Risk Factor: Medium] [Time Horizon: Operations ]. Page 3 of 13

4 5.1. The percent of load shedding to be implemented shall be based on the actual or estimated substation or feeder demand (including losses) of the UFLS entities at the time coincident with the previous year actual Peak Demand in the season specified by the Coordinator in R The amount of total UFLS load shall be within ± 5.0 of the percentage specified by the Coordinator for the total UFLS load in the UFLS scheme. M5. Each UFLS entity that has a total load less than 100 MW in a Coordinator area in the SERC Region shall have evidence such as reports or other documentation demonstrating that its implementation of the UFLS scheme on May 1 of each calendar year meets the requirements of Requirement R5 (including all the data elements in Parts 5.1and 5.2) unless scheme changes per Requirement R6 are in process. R6. Each UFLS entity shall implement changes to the UFLS scheme which involve frequency settings, relay time delays, changes to the percentage of load in the scheme, or changes to the peak season selected in R2.1 within 18 months of notification by the Coordinator. [Violation Risk Factor: High] [Time Horizon: Long-term ] M6. Each UFLS entity shall have evidence such as reports or other documentation demonstrating that it has made the appropriate scheme changes within 18 months per Requirement R6. Such evidence is only required if the Coordinator makes changes to the UFLS scheme as specified in Requirement R6. R7. Each Coordinator shall provide the following information to SERC according to the schedule specified by SERC. [Violation Risk Factor: Lower] [Time Horizon: Longterm ] 7.1. Underfrequency trip set points (Hz) 7.2. Total clearing time associated with each set point (sec). This includes the time from when frequency reaches the set point and ends when the breaker opens Amount of previous year actual or estimated load associated with each set point, both in percent and in MW. The percentage and the Load demand (MW) shall be based on the time coincident with the previous year actual Peak Demand. M7. Each Coordinator shall have evidence such as reports or other documentation that data specified in Requirement R7 was provided to SERC in accordance with the schedule. Page 4 of 13

5 R8. Each Generator Owner shall provide the following information within 30 days of a request by SERC to facilitate post-event analysis of frequency disturbances. [Violation Risk Factor: Lower] [Time Horizon: Long-term ] 8.1. Generator protection automatic underfrequency and overfrequency trip set points (Hz) Total clearing time associated with each set point (sec). This is defined as the time that begins when frequency reaches the set point and ends when the breaker opens. If inverse time underfrequency relays are used, provide the total clearing time at 59.0, 58.5, 58.0, and 57.0 Hz Maximum generator net MW that could be tripped automatically due to an underfrequency or overfrequency condition. M8. Each Generator Owner shall have evidence such as reports or other documentation that data specified in Requirement R8 was provided to SERC as requested. Page 5 of 13

6 Compliance Compliance enforcement authority SERC Reliability Corporation Compliance monitoring and assessment process Compliance Audit Self-Certification Spot Checking Compliance Violation Investigation Self-Reporting Complaint Evidence retention Each Coordinator, UFLS Entity and Generator Owner shall keep data or evidence to show compliance as identified below unless directed by SERC to retain specific evidence for a longer period of time as part of an investigation. Each Coordinator, UFLS Entity and Generator Owner shall retain the current evidence of each Requirement and Measure as well as any evidence necessary to show compliance since the last compliance audit. If a Coordinator, UFLS Entity or Generator Owner is found noncompliant, it shall keep information related to the non-compliance until found compliant or for the retention period specified above, whichever is longer. The compliance enforcement authority shall keep the last audit records and all requested and submitted subsequent audit records. Page 6 of 13

7 Time Horizons, Violation Risk Factors, and Violation Severity Levels Table 1 R# Time Horizon VRF Violation Severity Level Lower Moderate High Severe R1 Long-term Medium N/A N/A N/A Coordinator did not have evidence that its criteria included selection of its SERC subregion(s) as an island, with or without adjusted boundaries. R2 Long-term Medium Coordinator's scheme did not meet one of the UFLS system design requirements identified in 2.2 through 2.6 Coordinator's scheme did not meet two of the UFLS system design requirements identified in 2.2 through 2.6. Coordinator's scheme did not meet three of the UFLS system design requirements identified in 2.2 through 2.6. Coordinator's scheme did not meet 2.1 Four or more of the UFLS system design requirements identified in 2.2 through 2.6. R3 Long-term High N/A Coordinator failed to conduct one of the required simulations of its UFLS scheme. N/A Coordinator failed to conduct two of the required simulations of its UFLS scheme. R4 Operations Medium The UFLS entity s implemented UFLS scheme had one load shedding step outside the range specified in 4. The UFLS entity s implemented UFLS scheme had two load shedding steps outside the range specified in 4. The UFLS entity s implemented UFLS scheme had three or more load shedding steps outside the range The UFLS entity s implemented UFLS scheme had three or more load shedding steps outside the range Page 7 of 13

8 Table 1 R# Time Horizon VRF Violation Severity Level Lower Moderate High Severe specified in 4.2. specified in 4.2. AND The UFLS entity's The UFLS entity's implemented UFLS implemented UFLS scheme had a total load scheme had a total load outside the range outside the range specified in 4.3. specified in 4.3. R5 Operations Medium N/A N/A N/A The UFLS entity's implemented UFLS scheme had a total load outside the range specified in 5.2. R6 Long-term High The UFLS entity implemented required scheme changes but made them 1 to 30 days after the scheduled The UFLS entity implemented required scheme changes but made them 31 to 40 days after the scheduled The UFLS entity implemented required scheme changes but made them 41 to 50 days after the scheduled The UFLS entity implemented required scheme changes but made them more than 50 days after the scheduled date The UFLS entity failed to implement the required scheme changes. R7 Long-term Lower Coordinator provided the data required in R7 to SERC 1 to 10 days Coordinator provided the data required in R7 to SERC 11 to 20 days Coordinator provided the data required in R7 to SERC 21 to 30 days Coordinator provided the data required in R7 to SERC more than 30 Page 8 of 13

9 Table 1 R# Time Horizon VRF Violation Severity Level Lower Moderate High Severe after the scheduled submittal after the scheduled submittal after the scheduled submittal days after the scheduled submittal R8 Long-term Lower provided the data required in R8 to SERC 1 to 10 days after the requested submittal Coordinator did not provide to SERC one piece of information listed in R7. provided the data required in R8 to SERC 11 to 20 days after the requested submittal Coordinator did not provide to SERC two pieces of information listed in R7. provided the data required in R8 to SERC 21 to 30 days after the requested submittal Coordinator did not provide to SERC any of the information listed in R7. provided the data required in R8 to SERC more than 30 days after the requested submittal did not provide to SERC one piece of information listed in R8. did not provide to SERC two pieces of information listed in R8. did not provide to SERC any of the information listed in R8. Page 9 of 13

10 Regional Variances None Interpretations None Guideline and Technical Basis 1. Existing UFLS schemes Each Coordinator should consider the existing UFLS programs which are in place and should consider input from the UFLS entities in developing the UFLS scheme. 2. Basis for SERC standard requirements SERC Standard PRC-006-SERC-02 is not a stand-alone standard, but was written to be followed in conjunction with NERC Standard PRC The primary focus of SERC Standard PRC-006-SERC-02 was to provide region-specific requirements for the implementation of the higher tier NERC standard requirements with the goals of a) adding clarity and b) providing for consistency and a coordinated UFLS scheme for the SERC Region as a whole. Generally speaking, requirements already in the NERC standard were not repeated in the SERC standard. Therefore, both the NERC and SERC standards must be followed to ensure full compliance. 3. Basis for applying a percentage load shedding value to Forecast Load versus Actual Load Coordinator will develop a UFLS scheme to meet the performance requirements of NERC Standard PRC Requirement R3 and SERC Standard PRC-006- SERC-02 Requirement R2. This development will result in certain percentages of load for each UFLS entity in the Coordinator s area for which automatic under frequency load shedding must be implemented. Coordinator develops these percentages based on forecast peak load demand. However, the UFLS entity implements these percentages based on the previous year s actual peak demand. Applying the same percentage to these different base values was intentional to ensure that both the Coordinator and UFLS entities had a clear, measurable value to use in performing their respective roles in meeting the standard. Coordinators typically use forecast demands in their work. Whereas the previous year s actual (or estimated) demand is typically more available to UFLS entities. Additionally, the use of percentages based on these different base values tends to minimize the error due to the time lag between design and actual field implementation. Since a percentage is provided by the Coordinator to the UFLS entities, any differences between the design values (i.e., forecast load) and the implemented values (i.e., previous year s actual) would naturally tend to match up reasonably well. For example, if the total planning area load in MW for which UFLS was installed during the time of implementation was slightly higher or lower than the MW value used in the design by the Coordinator, multiplying by the specified percentage would result in an implemented load shedding scheme that also had a reasonably similar higher or lower MW value. Page 10 of 13

11 4. Basis for May 1 and 18 month time frames Each UFLS entity must annually review that the amount of UFLS load shedding implemented is within a certain tolerance as specified by SERC Standard PRC-006-SERC-02 Requirement R4 or Requirement R5 by May 1 of the current year. May 1 was chosen to allow sufficient time after the previous year s peak occurred to make adjustments in the field to the implementation if necessary to meet the tolerances specified in Requirement R4 or Requirement R5. Therefore, the May 1 date applies only to implementation of the existing percentages of load shedding specified by the Coordinator. On the other hand, the 18-month time frame specified in PRC-006-SERC-02 Requirement R6 is intended to allow sufficient budgeting, procurement, and installation time for additional equipment, or for significant setting changes to existing equipment necessary to meet a revised load shedding scheme design that has been specified by the Coordinator. During this 18-month transition period, the May 1 measurement of R4 or Requirement R5 would not apply. 5. Basis for smaller entity threshold of 100 MW Most distribution substations have transformers rated in the range of 10 to 40 MVA. Usually most transformers would serve 1 to 4 feeders and each feeder will normally carry between 8 and 10 MVA. In general, assuming that each feeder would carry 10 MW, an entity with a load slightly greater than 100 MW would have at least 10 feeders available. For a program with three 10 % steps, only 3 feeders would be required to have under frequency load shed capabilities. The 100 MW threshold seems to provide adequate flexibility for implementing load shedding in three steps for entities slightly greater than 100 MW. Rationale: During development of this standard, text boxes were embedded within the standard to explain the rationale for various parts of the standard. Upon BOT approval, the text from each of the rationale text boxes was moved to this section. Rationale for R1: Studying the Region as an island is required by the NERC standard. Most regions have only one or a few different UFLS schemes. Where there is more than one scheme, studying this island demonstrates that the schemes are coordinated and performing adequately. Because there are so many different UFLS schemes in SERC (18 different schemes were represented in the 2007 SERC UFLS study), the SDT believes that applying the schemes to each subregion as an island is a necessary additional test of the coordination of the various UFLS schemes. Without this additional test, a poorly performing scheme may be masked by the large number of good performing schemes in the Region. A subregion island study, which would have a smaller number of schemes, would be more likely to uncover the poorly performing scheme and therefore get it fixed. This approach will result in a much better overall performance of the UFLS programs in SERC. The SDT recognized that there may be simulation problems due to opening the ties to utilities outside the subregion. Therefore, the subregion island boundaries are allowed to be adjusted to produce an island more suitable for simulation. Page 11 of 13

12 (Note: The SERC Subregions are identified in paragraph 4.2 of the SERC Reliability Corporation Bylaws: The Region is currently geographically divided into five subregions that are identified as Southeastern, Central, VACAR, Delta, and Gateway. ) Rationale for R2: These requirements for the UFLS schemes in SERC have been in place for many years (except 2.6). The SDT believes that these requirements are still needed to ensure consistency for the various schemes which are used in SERC. Part 2.6 is designed to prevent spurious operations due to transient frequency swings. Rationale for R3: R4 of the NERC standard PRC requires the PC to conduct assessments of UFLS schemes through dynamic simulations to verify that they meet performance requirements for generation/load imbalances of up to 25%. This requirement defines specific imbalances that are to be studied within SERC. The 13% and 22% levels were determined from simulations of the worst case frequency overshoot for the UFLS schemes in SERC. Rationale for R4: The SDT believes it is necessary to put a requirement on how well the UFLS scheme is implemented. This requirement specifies how close the actual load shedding amounts must be to the percentage of load called for in the scheme. A 4 percentage point range is allowed for each individual step, but the allowed range for all steps combined is 6 percentage points. Rationale for R5: The SDT believes it is necessary to put a requirement on how well the UFLS scheme is implemented. This requirement specifies how close the actual load shedding amounts must be to the percentage of load called for in the scheme. The SDT recognizes that UFLS entities with a load of less than 100 MW may have difficulty in implementing more than one UFLS step and in meeting a tight tolerance. The basis of the 100 MW comes from typical feeder load dropped by UFLS relays, and the use of a 100 MW threshold in other regional UFLS standards. Rationale for R6: The SDT believes it is necessary to put a requirement on how quickly changes to the scheme should be implemented. This requirement specifies that changes must be implemented within 18 months of notification by the PC. The 18 month interval was chosen to give a reasonable amount of time for making changes in the field. All of the SERC Region has existing UFLS schemes which, based on periodic simulations, have provided reliable protection for years. Events which result in islanding and an activation of the UFLS schemes are extremely rare in SERC. Therefore, the SDT does not believe that changes to an existing UFLS scheme will be needed in less than 18 months. However, if a PC determines there is a need for changing the UFLS scheme faster than 18 months, then the PC may require the implementation to be done sooner as allowed by NERC Reliability Standard PRC Page 12 of 13

13 Rationale for R7: The NERC standard requires that a UFLS database be maintained by the Coordinator. This requirement specifies what data must be reported to SERC. A SERC UFLS database is needed to facilitate data sharing across the SERC Region, with other regions, and with NERC. Rationale for R8: The SDT believes that generator over and under frequency tripping data is needed to supplement the UFLS data provided by the Coordinator for post-event analysis of frequency disturbances. This requirement states what data must be reported to SERC by the Generator Owners. Since the inverse time curve cannot easily be placed into the SERC database, four clearing times based on data from the curve are requested. These clearing times are intended to cover a range of frequencies needed for event replication as well as provide information about generators that trip at a higher frequency than is allowed by the NERC standard. Version History Version Date Action Change Tracking 1 September 19, 2011 SERC Board Approved 1 November 3, 2011 Adopted by NERC Board of Trustees 1 December 20, 2012 FERC Order issued approving PRC-006-SERC 01 1 March 11, 2013 Modified the Rationale and changed the VRF for Requirement R6 from Medium to High per a compliance filing (Filed on 3/11/13) 2 June 28, 2017 SERC Board Approved 2 August 10, 2017 Adopted by NERC Board of Trustees 2 October 16, 2017 FERC Order issued approving PRC-006-SERC-02 Page 13 of 13

Newfoundland. Brunswick R1 NA NA NA NA NA NA NA NA NA

Newfoundland. Brunswick R1 NA NA NA NA NA NA NA NA NA Effective Dates Requirement Jurisdiction Alberta British Columbia Manitoba New Brunswick Newfoundland Nova Scotia Ontario Quebec Saskatchewan USA R1 NA NA NA NA NA NA NA NA NA 4/1/14 R2 NA NA NA NA NA

More information

FAC Facility Interconnection Studies

FAC Facility Interconnection Studies A. Introduction 1. Title: Facility Interconnection Studies 2. Number: FAC-002-2 3. Purpose: To study the impact of interconnecting new or materially modified Facilities on the Bulk Electric System. 4.

More information

Standard Development Timeline

Standard Development Timeline PRC 012 2 Remedial Action Schemes Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft

More information

BAL-002-2(i) Disturbance Control Standard Contingency Reserve for Recovery from a Balancing Contingency Event

BAL-002-2(i) Disturbance Control Standard Contingency Reserve for Recovery from a Balancing Contingency Event Balancing A. Introduction 1. Title: Disturbance Control Standard Contingency Reserve for Recovery from a Balancing 2. Number: BAL-002-2(i) 3. Purpose: To ensure the Balancing Authority or Reserve Sharing

More information

PRC Remedial Action Schemes

PRC Remedial Action Schemes PRC-012-2 Remedial Action Schemes A. Introduction 1. Title: Remedial Action Schemes 2. Number: PRC-012-2 3. Purpose: To ensure that Remedial Action Schemes (RAS) do not introduce unintentional or unacceptable

More information

10-day Formal Comment Period with a 5-day Additional Ballot (if necessary), pursuant to a Standards Committee authorized waiver.

10-day Formal Comment Period with a 5-day Additional Ballot (if necessary), pursuant to a Standards Committee authorized waiver. Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

1. Title: Qualified Transfer Path Unscheduled Flow (USF) Relief

1. Title: Qualified Transfer Path Unscheduled Flow (USF) Relief A. Introduction 1. Title: Qualified Transfer Path Unscheduled Flow (USF) Relief 2. Number: IRO-006-WECC-2 3. Purpose: Mitigation of transmission overloads due to unscheduled flow on Qualified Transfer

More information

Standard PRC-004-3(x) Protection System Misoperation Identification and Correction

Standard PRC-004-3(x) Protection System Misoperation Identification and Correction Standard PRC-004-3(x) Protection System Misoperation Identification and Correction Standard Development Timeline This section is maintained by the drafting team during the development of the standard and

More information

September 30th, 2013 Dave and TFSS, Please find attached final responses to the clarification requests on the NPCC Regional Standard for Automatic UFLS PRC -006-NPCC-1 as reviewed and approved during the

More information

Standard INT Interchange Initiation and Modification for Reliability

Standard INT Interchange Initiation and Modification for Reliability A. Introduction 1. Title: Interchange Initiation and Modification for Reliability 2. Number: INT-010-2 3. Purpose: To provide guidance for required actions on Confirmed Interchange or Implemented Interchange

More information

Standard FAC Facility Ratings. A. Introduction

Standard FAC Facility Ratings. A. Introduction A. Introduction 1. Title: Facility Ratings 2. Number: FAC-008-3 3. Purpose: To ensure that Facility Ratings used in the reliable planning and operation of the Bulk Electric System (BES) are determined

More information

45-day Comment and Initial Ballot day Final Ballot. April, BOT Adoption. May, 2015

45-day Comment and Initial Ballot day Final Ballot. April, BOT Adoption. May, 2015 Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

Future Development Plan:

Future Development Plan: Standard BAL-007-1 Balance of Resources and Demand Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will be removed when the standard

More information

BAL Disturbance Control Standard Contingency Reserve for Recovery from a Balancing Contingency Event

BAL Disturbance Control Standard Contingency Reserve for Recovery from a Balancing Contingency Event A. Introduction 1. Title: Disturbance Control Standard Contingency Reserve for Recovery from a 2. Number: BAL-002-3 3. Purpose: To ensure the Balancing Authority or Reserve Sharing Group balances resources

More information

BAL Frequency Response & Frequency Bias Setting Standard

BAL Frequency Response & Frequency Bias Setting Standard Attachment A BAL 003 1 Frequency Response & Frequency Bias Setting Standard Background This document outlines the ERO process for supporting the Frequency Response Standard (FRS). Event Selection Criteria

More information

3. Purpose: To specify the quantity and types of Contingency Reserve required to ensure reliability under normal and abnormal conditions.

3. Purpose: To specify the quantity and types of Contingency Reserve required to ensure reliability under normal and abnormal conditions. WECC Standard BAL-002-WECC-2 A. Introduction 1. Title: 2. Number: BAL-002-WECC-2 3. Purpose: To specify the quantity and types of required to ensure reliability under normal and abnormal conditions. 4.

More information

August 17, 2017 VIA ELECTRONIC FILING. Veronique Dubois Régie de l'énergie Tour de la Bourse 800, Place Victoria Bureau 255 Montréal, Québec H4Z 1A2

August 17, 2017 VIA ELECTRONIC FILING. Veronique Dubois Régie de l'énergie Tour de la Bourse 800, Place Victoria Bureau 255 Montréal, Québec H4Z 1A2 !! August 17, 2017 VIA ELECTRONIC FILING Veronique Dubois Régie de l'énergie Tour de la Bourse 800, Place Victoria Bureau 255 Montréal, Québec H4Z 1A2 Re: Revisions to the Violation Risk Factors for Reliability

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft

More information

Violation Risk Factor and Violation Severity Level Justifications Project Modifications to BAL

Violation Risk Factor and Violation Severity Level Justifications Project Modifications to BAL Violation Risk Factor and Violation Severity Level Justifications Project 2017-01 Modifications to BAL-003-1.1 This document provides the standard drafting team s (SDT s) justification for assignment of

More information

3. Purpose: To specify the quantity and types of Contingency Reserve required to ensure reliability under normal and abnormal conditions.

3. Purpose: To specify the quantity and types of Contingency Reserve required to ensure reliability under normal and abnormal conditions. WECC Standard BAL-002-WECC-2a A. Introduction 1. Title: 2. Number: BAL-002-WECC-2a 3. Purpose: To specify the quantity and types of required to ensure reliability under normal and abnormal conditions.

More information

A. Introduction. C. Measures. Standard CIP-001-2a Sabotage Reporting

A. Introduction. C. Measures. Standard CIP-001-2a Sabotage Reporting A. Introduction 1. Title: Sabotage Reporting 2. Number: CIP-001-2a 3. Purpose: Disturbances or unusual occurrences, suspected or determined to be caused by sabotage, shall be reported to the appropriate

More information

NERC TPL Standard Overview

NERC TPL Standard Overview NERC TPL-001-4 Standard Overview Attachment K Quarter 3 Stakeholder s Meeting September 29, 2016 1 Background New NERC TPL Standard 2016 TPL Plan and Status Update 2015 Planning Assessment Results Compliance

More information

A. Introduction. 1. Title: Event Reporting. 2. Number: EOP-004-3

A. Introduction. 1. Title: Event Reporting. 2. Number: EOP-004-3 A. Introduction 1. Title: Event Reporting 2. Number: EOP-004-3 3. Purpose: To improve the reliability of the Bulk Electric System by requiring the reporting of events by Responsible Entities. 4. Applicability:

More information

2017 Metrics with Historical Data

2017 Metrics with Historical Data 2017 Metrics with Historical Data Metrics In support of the ERO Enterprise s goals, there are six reliability metrics to measure progress on reliability improvement. There is also one metric to measure

More information

Implementation Plan Project PRC-005 FERC Order No. 803 Directive PRC-005-6

Implementation Plan Project PRC-005 FERC Order No. 803 Directive PRC-005-6 Project 2007-17.4 PRC-005 FERC Order No. 803 Directive PRC-005-6 Standards Involved Approval: PRC 005 6 Protection System, Automatic Reclosing, and Sudden Pressure Relaying Maintenance Retirement: PRC

More information

Drafting team considers comments, makes conforming changes on fourth posting

Drafting team considers comments, makes conforming changes on fourth posting Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft

More information

Procedure for ERO Support of Frequency Response and Frequency Bias Setting Standard

Procedure for ERO Support of Frequency Response and Frequency Bias Setting Standard Procedure for ERO Support of Frequency Response and Frequency Bias Setting Standard I Table of Contents Preface... iii Introduction...iiv Chapter 1: Event Selection Process... 1 Event Selection Objectives...

More information

April 6, 2018 VIA OVERNIGHT MAIL. Sheri Young, Secretary of the Board National Energy Board th Avenue SW Calgary, Alberta T2R 0A8

April 6, 2018 VIA OVERNIGHT MAIL. Sheri Young, Secretary of the Board National Energy Board th Avenue SW Calgary, Alberta T2R 0A8 !! April 6, 2018 VIA OVERNIGHT MAIL Sheri Young, Secretary of the Board National Energy Board 517 10 th Avenue SW Calgary, Alberta T2R 0A8 Re: North American Electric Reliability Corporation Dear Ms. Young:

More information

A. Introduction. B. Requirements and Measures

A. Introduction. B. Requirements and Measures A. Introduction 1. Title: Event Reporting 2. Number: EOP-004-4 3. Purpose: To improve the reliability of the Bulk Electric System by requiring the reporting of events by Responsible Entities. 4. Applicability:

More information

Project PRC Protection System Maintenance

Project PRC Protection System Maintenance Project 2007-17 PRC-005-2 Protection System Maintenance This document provides the drafting team s justification for assignment of violation risk factors (VRFs) and violation severity levels (VSLs) for

More information

EXCERPTS from the SAMS-SPCS SPS Technical Reference

EXCERPTS from the SAMS-SPCS SPS Technical Reference Problem Statement The existing NERC Glossary of Terms definition for a Special Protection System (SPS or, as used in the Western Interconnection, a Remedial Action Scheme or RAS) lacks clarity and specificity

More information

Procedure for ERO Support of Frequency Response and Frequency Bias Setting Standard

Procedure for ERO Support of Frequency Response and Frequency Bias Setting Standard Procedure for ERO Support of Frequency Response and Frequency Bias Setting Standard NERC Report Title Report Date I Table of Contents Preface... iii Introduction...iiv Chapter 1: Event Selection Process...

More information

May 13, 2009 See Implementation Plan for BAL-005-1

May 13, 2009 See Implementation Plan for BAL-005-1 BL-005-1 Balancing uthority Control. Introduction 1. Title: utomatic Generation Balancing uthority Control 2. Number: BL-005-0.2b1 3. Purpose: This standard establishes requirements for Balancing uthority

More information

AUFLS information paper

AUFLS information paper AUFLS information paper Contents 1 Introduction... 1 2 The under-frequency management challenge... 1 3 Overview of current arrangements... 3 3.1 The current AUFLS exemptions... 4 4 Initiatives to address

More information

NERC Reliability Standards Project Updates (August 23, Updated)

NERC Reliability Standards Project Updates (August 23, Updated) NERC Reliability Standards Project Updates (August 23, 2012 - Updated) Concurrent Postings Project 2007-17 - Protection System Maintenance and Testing The proposed PRC-005-2 Protection System Maintenance

More information

Standard BAL Real Power Balancing Control Performance

Standard BAL Real Power Balancing Control Performance A. Introduction 1. Title: Real Power Balancing Control Performance 2. Number: BAL 001 2 3. Purpose: To control Interconnection frequency within defined limits. 4. Applicability: 4.1. Balancing Authority

More information

Attachment A. BAL Frequency Response & Frequency Bias Setting Standard. Supporting Document

Attachment A. BAL Frequency Response & Frequency Bias Setting Standard. Supporting Document Attachment A BAL-003-1 Frequency Response & Frequency Bias Setting Standard Frequency Response Obligation (FRO) for the Interconnection The ERO, in consultation with regional representatives, has established

More information

Reliability Guideline: Operating Reserve Management

Reliability Guideline: Operating Reserve Management Reliability Guideline: Operating Reserve Management Preamble: It is in the public interest for NERC to develop guidelines that are useful for maintaining or enhancing the reliability of the Bulk Electric

More information

BES Definition Implementation Guidance

BES Definition Implementation Guidance BES Definition Implementation Guidance August 25, 2014 3353 Peachtree Road NE Suite 600, North Tower Atlanta, GA 30326 NERC BES Definition Implementation Guidance June 23, 2014 404-446-2560 www.nerc.com

More information

Background Information:

Background Information: Project 2010-14.1 Balancing Authority Reliability-based Control BAL-002-2 Disturbance Control Performance - Contingency Reserve for Recovery from a Balancing Contingency Event Please do not use this form

More information

2018 ERO Enterprise Metrics

2018 ERO Enterprise Metrics 2018 ERO Enterprise Metrics Metrics In support of the ERO Enterprise s goals, there are six reliability metrics to measure achievement of a highly reliable and secure bulk power system (BPS). There is

More information

NORMES DE FIABILITÉ DE LA NERC - BAL (VERSION ANGLAISE)

NORMES DE FIABILITÉ DE LA NERC - BAL (VERSION ANGLAISE) COORDONNATEUR DE LA FIABILITÉ Direction Contrôle des mouvements d énergie Demande R-3699-2009 NORMES DE FIABILITÉ DE LA NERC - BAL (VERSION ANGLAISE) Original : 2013-03-27 HQCMÉ-8, Document 2.4 Révisé

More information

Re: Analysis of NERC Standard Process Results, Fourth Quarter 2013 Docket Nos. RR , RR

Re: Analysis of NERC Standard Process Results, Fourth Quarter 2013 Docket Nos. RR , RR VIA ELECTRONIC FILING January 29, 2014 Ms. Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, D.C. 20426 Dear Ms. Bose: Re: Analysis of NERC Standard Process

More information

Implementation Plan Project PRC-005 FERC Order No. 803 Directive PRC-005-6

Implementation Plan Project PRC-005 FERC Order No. 803 Directive PRC-005-6 PRC-005-6 Standards Involved Approval: PRC-005-6 Protection System, Automatic Reclosing, and Sudden Pressure Relaying Maintenance Retirement: PRC-005-5 Protection System, Automatic Reclosing, and Sudden

More information

ERO Enterprise CMEP Practice Guide: Phased Implementation Plans with Completion Percentages March 24, 2017

ERO Enterprise CMEP Practice Guide: Phased Implementation Plans with Completion Percentages March 24, 2017 ERO Enterprise CMEP Practice Guide: Phased Implementation Plans with Completion Percentages March 24, 2017 Background In support of successful implementation of and compliance with the North American Electric

More information

Violation Risk Factor and Violation Severity Level Justifications Project Modifications to CIP Standards

Violation Risk Factor and Violation Severity Level Justifications Project Modifications to CIP Standards Violation Risk Factor and Justifications Project 2016-02 Modifications to CIP Standards This document provides the standard drafting team s (SDT s) justification for assignment of violation risk factors

More information

Standard INT Interchange Transaction Implementation

Standard INT Interchange Transaction Implementation A. Introduction 1. Title: Interchange Transaction Implementation 2. Number: INT-003-3 3. Purpose: To ensure Balancing Authorities confirm Interchange Schedules with Adjacent Balancing Authorities prior

More information

NPCC Regional Reliability Reference Directory # 5 Reserve

NPCC Regional Reliability Reference Directory # 5 Reserve NPCC Regional Reliability Reference Directory # 5 Task Force on Coordination of Operations Revision Review Record: December 2 nd, 2010 October 11 th, 2012 Adopted by the Members of the Northeast Power

More information

Standard BAL Real Power Balancing Control Performance

Standard BAL Real Power Balancing Control Performance A. Introduction 1. Title: Real Power Balancing Control Performance 2. Number: BAL-001-2 3. Purpose: To control Interconnection frequency within defined limits. 4. Applicability: 4.1. Balancing Authority

More information

5.14 Installed Capacity Spot Market Auction and Installed Capacity Supplier Deficiencies LSE Participation in the ICAP Spot Market Auction

5.14 Installed Capacity Spot Market Auction and Installed Capacity Supplier Deficiencies LSE Participation in the ICAP Spot Market Auction 5.14 Installed Capacity Spot Market Auction and Installed Capacity Supplier Deficiencies 5.14.1 LSE Participation in the ICAP Spot Market Auction 5.14.1.1 ICAP Spot Market Auction When the ISO conducts

More information

Group Arizona Public Service Company Janet Smith, Regulatory Affairs Supervisor Yes. Yes. Group Salt River Project Chris Chavez for Mike Gentry Yes

Group Arizona Public Service Company Janet Smith, Regulatory Affairs Supervisor Yes. Yes. Group Salt River Project Chris Chavez for Mike Gentry Yes Name (1 Responses) Organization (1 Responses) Name (5 Responses) Lead Contact (5 Responses) Question 1 (6 Responses) Question 1 Comments (6 Responses) Question 2 (6 Responses) Question 2 Comments (6 Responses)

More information

ATTACHMENT E. Page 1 of 8 REAL POWER BALANCING CONTROL PERFORMANCE

ATTACHMENT E. Page 1 of 8 REAL POWER BALANCING CONTROL PERFORMANCE Page 1 of 8 REAL POWER BALANCING CONTROL PERFORMANCE A. INTRODUCTION 1. Title: Real Power Balancing Control Performance 2. Number: BAL-001-2 3. Purpose: To control Interconnection frequency within defined

More information

BAL Background Document. August 2014

BAL Background Document. August 2014 BAL-002-2 Background Document August 2014 1 Table of Contents Introduction... 3 Rationale by Requirement... 78 Requirement 1... 78 Requirement 2... 1112 2 Introduction The revision to NERC Policy Standards

More information

Paragraph 81 Project Technical White Paper

Paragraph 81 Project Technical White Paper Paragraph 81 Project Technical White Paper December 20, 2012 Table of Contents I. Introduction...4 A. Consensus Process...4 B. Standards Committee...5 II. Executive Summary...6 III. Criteria...7 Criterion

More information

SERC Reliability Corporation Business Plan and Budget

SERC Reliability Corporation Business Plan and Budget SERC Reliability Corporation 3701 Arco Corporate Drive, Suite 300 Charlotte, NC 28273 704.357.7372 Fax 704.357.7914 www.serc1.org SERC Reliability Corporation 2018 Business Plan and Budget DRAFT April

More information

WECC S ta n d a rd P RC WECC-1 P ro te c tio n S ys tem an d R e m ed ia l Actio n S ch e m e Mis o p eratio n

WECC S ta n d a rd P RC WECC-1 P ro te c tio n S ys tem an d R e m ed ia l Actio n S ch e m e Mis o p eratio n WECC S ta n d a rd P RC-00 4 -WECC-1 P ro te c tio n S ys tem an d R e m ed ia l Actio n S ch e m e Mis o p eratio n A. Introduction 1. Title: Protection System and Remedial Action Scheme Misoperation

More information

2017 Business Plan and Budget. Texas Reliability Entity, Inc. Approved by Texas RE Board of Directors. Date:, 2016

2017 Business Plan and Budget. Texas Reliability Entity, Inc. Approved by Texas RE Board of Directors. Date:, 2016 2017 Business Plan and Texas Reliability Entity, Inc. Approved by Texas RE Board of Directors Date:, 2016 Approved by the Texas RE Board of Directors, 2016 1 Table of Contents Table of Contents... 2 Introduction...

More information

Violation Risk Factor and Violation Severity Level Justifications Project Modifications to CIP Standards

Violation Risk Factor and Violation Severity Level Justifications Project Modifications to CIP Standards Violation Risk Factor and Violation Severity Level Justifications Project 2016-02 Modifications to CIP Standards This document provides the standard drafting team s (SDT s) justification for assignment

More information

SERC Reliability Corporation Business Plan and Budget

SERC Reliability Corporation Business Plan and Budget SERC Reliability Corporation 3701 Arco Corporate Drive, Suite 300 Charlotte, NC 28273 704.357.7372 Fax 704.357.7914 www.serc1.org SERC Reliability Corporation 2018 Business Plan and Budget FINAL June 28,

More information

January 31, Ms. Kimberly Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426

January 31, Ms. Kimberly Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 January 31, 2011 Ms. Kimberly Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 Re: NERC Abbreviated Notice of Penalty regarding Sharyland Utilities, LP, as

More information

PJM & MISO Assumptions and Criteria for Testing of New Resources

PJM & MISO Assumptions and Criteria for Testing of New Resources & Assumptions and Criteria for Testing of New Resources 1 Introduction These slides provide a description and comparison of the assumptions and criteria used by and during the study of customer proposed

More information

WECC Process for Risk-Based Compliance Oversight Inherent Risk Assessment and Compliance Oversight Plan

WECC Process for Risk-Based Compliance Oversight Inherent Risk Assessment and Compliance Oversight Plan WECC Process for Risk-Based Compliance Oversight Inherent Risk Assessment and Compliance Oversight Plan WECC Entity Oversight Effective Date: April 1, 2017 155 North 400 West, Suite 200 Salt Lake City,

More information

2019 Business Plan and Budget. Texas Reliability Entity, Inc. Approved by Texas RE Board of Directors

2019 Business Plan and Budget. Texas Reliability Entity, Inc. Approved by Texas RE Board of Directors 2019 Business Plan and Budget Texas Reliability Entity, Inc. Approved by Texas RE Board of Directors Date: May 23, 2018 1 Table of Contents Table of Contents... 2 Introduction... 3 Section A Statutory

More information

Approved Business Plan and Budget. Florida Reliability Coordinating Council, Inc.

Approved Business Plan and Budget. Florida Reliability Coordinating Council, Inc. Approved 2016 Business Plan and Budget Florida Reliability Coordinating Council, Inc. Approved: 6/25/2015 Table of Contents Introduction... 3 Organizational Overview... 3 Membership and Governance... 4

More information

Project : 02: TPL-001 Assess Transmission Future Needs. John Odom Drafting Team Chair June 30, 2009

Project : 02: TPL-001 Assess Transmission Future Needs. John Odom Drafting Team Chair June 30, 2009 Project 2006-02: 02: TPL-001 001-1 Assess Transmission Future Needs John Odom Drafting Team Chair June 30, 2009 Agenda 1. NERC Antitrust Compliance Guidelines 2. Opening Remarks and Introductions 3. Webinar

More information

Approved Business Plan and Budget. Florida Reliability Coordinating Council, Inc.

Approved Business Plan and Budget. Florida Reliability Coordinating Council, Inc. Approved 2015 Business Plan and Budget Florida Reliability Coordinating Council, Inc. Approved: 6/25/2014 Table of Contents Introduction... 3 Organizational Overview... 3 Membership and Governance... 4

More information

A. Introduction. Standard MOD Flowgate Methodology

A. Introduction. Standard MOD Flowgate Methodology A. Introduction 1. Title: Flowgate Methodology 2. Number: MOD-030-3 3. Purpose: To increase consistency and reliability in the development and documentation of transfer capability calculations for short-term

More information

DS3 System Services Protocol Interim Arrangements

DS3 System Services Protocol Interim Arrangements DS3 System Services Protocol Interim Arrangements DS3 System Services Implementation Project August 2017 Version 2.1 Contents 1 Introduction... 3 2 Governance... 5 3 Compliance Requirements... 6 4 Performance

More information

Information Document Available Transfer Capability and Transfer Path Management ID # R

Information Document Available Transfer Capability and Transfer Path Management ID # R Information Documents are not authoritative. Information Documents are for information purposes only and are intended to provide guidance. In the event of any discrepancy between an Information Document

More information

Transmission Connection Procedures EB

Transmission Connection Procedures EB Transmission Connection Procedures Transmission Connection Procedures Table of Contents 1.0 INTRODUCTION...1 2.0 HYDRO ONE CONNECTION PROCEDURES...4 2.1 TOTAL NORMAL SUPPLY CAPACITY PROCEDURE...5 2.2 AVAILABLE

More information

Standard MOD Flowgate Methodology

Standard MOD Flowgate Methodology A. Introduction 1. Title: Flowgate Methodology 2. Number: MOD-030-1 3. Purpose: To increase consistency and reliability in the development and documentation of transfer capability calculations for short-term

More information

SPP Reserve Sharing Group Operating Process

SPP Reserve Sharing Group Operating Process SPP Reserve Sharing Group Operating Process Effective: 1/1/2018 1.1 Reserve Sharing Group Purpose In the continuous operation of the electric power network, Operating Capacity is required to meet forecasted

More information

Contents Introduction Chapter 1 - Security Policy... 6

Contents Introduction Chapter 1 - Security Policy... 6 Policy statement Contents Introduction... 5 PURPOSE... 5 SYSTEM OPERATOR POLICIES TO ACHIEVE THE PPOS and dispatch objective... 5 Avoid Cascade Failure... 5 Frequency... 6 Other Standards... 6 Restoration...

More information

Transmission Planning Standards Industry Webinar: Footnote b. January 8, 2012 John Odom, FRCC, Standard Drafting Team Chair

Transmission Planning Standards Industry Webinar: Footnote b. January 8, 2012 John Odom, FRCC, Standard Drafting Team Chair Transmission Planning Standards Industry Webinar: Footnote b January 8, 2012 John Odom, FRCC, Standard Drafting Team Chair Topics Brief history Overview of as posted draft standard Changes since last posting

More information

COLUMBIAGRID GEOMAGNETIC DISTURBANCE DRAFT STUDY REPORT

COLUMBIAGRID GEOMAGNETIC DISTURBANCE DRAFT STUDY REPORT COLUMBIAGRID GEOMAGNETIC DISTURBANCE DRAFT STUDY REPORT (NERC Standard TPL-007-1) Revision 1 February 1, 2018 ColumbiaGrid 8338 NE Alderwood Road, Suite 140 Portland, OR 97220 www.columbiagrid.org (503)

More information

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION ) ) ) ) ) ) ) ) ) ) ) DIRECT TESTIMONY RUTH M. SAKYA. on behalf of.

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION ) ) ) ) ) ) ) ) ) ) ) DIRECT TESTIMONY RUTH M. SAKYA. on behalf of. BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION IN THE MATTER OF SOUTHWESTERN PUBLIC SERVICE COMPANY S INTERIM REPORT ON ITS PARTICIPATION IN THE SOUTHWEST POWER POOL REGIONAL TRANSMISSION ORGANIZATION,

More information

ReliabilityFirst Regional Criteria 1. Operating Reserves

ReliabilityFirst Regional Criteria 1. Operating Reserves ReliabilityFirst Regional Criteria 1 Operating Reserves 1 A ReliabilityFirst Board of Directors approved good utility practice document which are not reliability standards. ReliabilityFirst Regional Criteria

More information

Compliance Monitoring and Enforcement Program Quarterly Report

Compliance Monitoring and Enforcement Program Quarterly Report Compliance Monitoring and Enforcement Program Quarterly Report Q2 2018 August 15, 2018 NERC Report Title Report Date I Table of Contents Preface... iii Executive Summary... iv Chapter 1 : CMEP Activities...

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) )

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION North American Electric Reliability Corporation ) ) Docket No. PETITION OF THE NORTH AMERICAN ELECTRIC RELIABILITY CORPORATION FOR

More information

New Mexico Public Regulation Commission P. O. Box Paseo de Peralta Santa Fe, New Mexico 87504

New Mexico Public Regulation Commission P. O. Box Paseo de Peralta Santa Fe, New Mexico 87504 THE NEW MEXICO INTERCONNECTION MANUAL (To be Used in Conjunction with New Mexico Public Regulation Commission Rule 17.9.568 NMAC, Interconnection of Generating Facilities with a Rated Capacity Up to and

More information

Final Business Plan and Budget. Florida Reliability Coordinating Council, Inc. Approved:

Final Business Plan and Budget. Florida Reliability Coordinating Council, Inc. Approved: Final 2018 Business Plan and Budget Florida Reliability Coordinating Council, Inc. Approved: 062917 Table of Contents Introduction... 3 Organizational Overview... 3 Membership and Governance... 4 Statutory

More information

Unofficial Comment Form Emergency Operations EOP-004-4

Unofficial Comment Form Emergency Operations EOP-004-4 2015-08 Emergency Operations EOP-004-4 Do not use this form for submitting comments. Use the electronic form to submit comments on Project 2015-08 Emergency Operations; EOP-004-4 Event Reporting. The electronic

More information

The second effective date allows entities time to comply with Requirements R1, R2, R4, R5, R6, and R7.

The second effective date allows entities time to comply with Requirements R1, R2, R4, R5, R6, and R7. Effective Dates Generator Owners There are two effective dates associated with this standard. The first effective date allows Generator Owners time to develop documented maintenance strategies or procedures

More information

INVESTMENT GUIDE. Your fund. Your wealth. Your future. This document forms part of the Product Disclosure Statement dated 24 September 2018

INVESTMENT GUIDE. Your fund. Your wealth. Your future. This document forms part of the Product Disclosure Statement dated 24 September 2018 Your fund. Your wealth. Your future. This document forms part of the Product Disclosure Statement dated 24 September 2018 INVESTMENT GUIDE 24 SEPTEMBER 2018 We offer you flexibility and choice when it

More information

145 FERC 61,141 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. 18 CFR Part 40. [Docket No. RM ; Order No.

145 FERC 61,141 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. 18 CFR Part 40. [Docket No. RM ; Order No. 145 FERC 61,141 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 18 CFR Part 40 [Docket No. RM13-13-000; Order No. 789] Regional Reliability Standard BAL-002-WECC-2 Contingency Reserve (Issued

More information

Application instruction for the maintenance of frequency controlled reserves

Application instruction for the maintenance of frequency controlled reserves Appendix 2 to the Yearly Agreement and Hourly Market Agreement for Frequency Controlled Normal Operation Reserve and Frequency Controlled Disturbance Reserve Valid as of 1 January 2017 Unofficial translation

More information

Project Disturbance and Sabotage Reporting

Project Disturbance and Sabotage Reporting Project 2009-01 Disturbance and Sabotage Reporting Consideration of Issues and Directives Issue or Directive Source Consideration of Issue or Directive CIP 001 1 NERC Audit Observation Team "What is meant

More information

WECC Criterion TPL-001-WECC-CRT-3.1

WECC Criterion TPL-001-WECC-CRT-3.1 WECC Criterion TPL-001-WECC-CRT-3.1 A. Introduction 1. Title: Transmission System Planning Performance 2. Number: TPL-001-WECC-CRT-3.1 3. Purpose: To facilitate coordinated near-term and long-term transmission

More information

Violation Risk Factor and Violation Severity Level Justifications Project Emergency Operations

Violation Risk Factor and Violation Severity Level Justifications Project Emergency Operations Violation Risk Factor and Justifications Project 2015-08 Emergency Operations This document provides the drafting team s justification for assignment of violation risk factors (VRFs) and violation severity

More information

WECC Standard BAL-STD Operating Reserves

WECC Standard BAL-STD Operating Reserves A. Introduction 1. Title: Operating Reserves 2. Number: BAL-STD-002-0 3. Purpose: Regional Reliability Standard to address the Operating Reserve requirements of the Western Interconnection. 4. Applicability

More information

The Narragansett Electric Company Standards for Connecting Distributed Generation. R.I.P.U.C. No Canceling R.I.P.U.C. No.

The Narragansett Electric Company Standards for Connecting Distributed Generation. R.I.P.U.C. No Canceling R.I.P.U.C. No. Effective R.I.P.U.C. No. 2163 : S:\RADATA1\RATE ADMINISTRATION\Tariffs_Current\Narragansett Sheet 1 TABLE OF CONTENTS 1.0 Introduction...3 1.1 Applicability...3 1.2 Definitions...3 1.3 Forms and Agreements...8

More information

TRANSMISSION OWNER ZONAL PLACEMENT PROCESS

TRANSMISSION OWNER ZONAL PLACEMENT PROCESS TRANSMISSION OWNER ZONAL PLACEMENT PROCESS Published July 2017 CONTENTS Section 1: Introduction, Scope & Steps... 1 Subsection A: Introduction To Zonal Placement... 1 Subsection B: Scope... 1 Subsection

More information

REPORT TO THE PUBLIC UTILITIES BOARD

REPORT TO THE PUBLIC UTILITIES BOARD REPORT TO THE PUBLIC UTILITIES BOARD CURTAILABLE RATE PROGRAM APRIL 1, 2011 MARCH 31, 2012 JULY 2012 TABLE OF CONTENTS Page No. SUMMARY... 1 BACKGROUND... 1 PERFORMANCE FOR 2011/12... 3 Curtailment Options...3

More information

WECC Criterion PRC-012-WECC-1

WECC Criterion PRC-012-WECC-1 A. Introduction 1. Title: Remedial Action Schemes 2. Number: PRC-012-WECC-CRT-1 3. Purpose: To establish a documented Remedial Action Scheme (RAS) review procedure 4. Applicability: The Applicable Entity

More information

WECC Criterion PRC-003-WECC-CRT-1.3

WECC Criterion PRC-003-WECC-CRT-1.3 WECC Criterion PRC-003-WECC-CRT-1.3 A. Introduction 1. Title: Analysis, Reporting, and Mitigation of Transmission and Generation Protection System and Remedial Action Scheme Misoperations Procedure 1 2.

More information

Please contact the undersigned if you have any questions concerning this filing.

Please contact the undersigned if you have any questions concerning this filing. !! November 17, 2016 VIA ELECTRONIC FILING Ms. Katie Mitchell Chief Clerk New Brunswick Energy and Utilities Board P.O. Box 5001 15 Market Square, Suite 1400 Saint John, NB E2L 4Y9 Re: North American Electric

More information

1 Overview of the Alberta Capacity Market

1 Overview of the Alberta Capacity Market 1 Overview of the Alberta Capacity Market Rationale 1. Alberta Capacity Market Framework To supplement the Comprehensive Market Design proposal (CMD 2), the associated rationale documents outline the rationale

More information

T-D Interconnections: Best Value Planning White Paper January 2016

T-D Interconnections: Best Value Planning White Paper January 2016 T-D Interconnections: Best Value Planning White Paper Updated January 2016 1. Purpose This paper defines the process and criteria that together constitute joint best value planning (BVP) between ATC and

More information