1 Northern Virginia District State of the District Helen L. Cuervo, P.E. District Engineer March 15, 2016

2 Northern Virginia District Construction Performance Bill Cuttler, P.E. District Construction Engineer March 15, 2016

3 3

4 Construction Delivery On-Time CONSTRUCTION FY 16 3/15/16 District 80% State 85% Target 77% # of Projects 20 MAINTENANCE District 73% State 85% Target 77% # of Projects 44 4

5 Construction Delivery On-Budget CONSTRUCTION FY16 3/15/16 District 85% State 91% Target 82% # of District Projects 20 MAINTENANCE District 91% State 96% Target 90% # of District Projects 44 5

6 Project Delivery: CQIP & Environmental Construction Quality Improvement Program FY16 3/15/16 District 96% State 95% Target 91% ENVIRONMENTAL COMPLIANCE District 98.9% State 98.8% Target 100% 6

7 Susan Shaw, P.E., Megaprojects Director 395 Express Lanes Northern Extension Project March 15, 2016

8 The Comprehensive Agreement executed in 2012 with 95 Express Lanes, LLC. (95 Express) for the 95 Express Lanes contemplated the potential future development of the Northern HOT Lanes along the I-395 corridor. 395 Express Lanes In November of 2015, VDOT and 95 Express signed a Development Framework Agreement (Agreement) outlining the Parties initial roles and responsibilities in developing this Project. 8

9 Regional Express Lanes Network 9

10 395 Express Lanes Project Scope Convert the two existing reversible High Occupancy Vehicle (HOV) lanes to High Occupancy Toll (HOT) lanes; construct an additional HOT lane (Total = 3 HOT Lanes) Install an Active Traffic Management System Install signage and toll systems Provide sound walls Provide improved connections between the proposed I-395 Express Lanes and Eads Street Conduct multimodal study 10

11 VDOT s Responsibilities Planning/Environmental Approvals Inclusion in MWCOG Transportation Planning Board s Constrained Long Range Plan (CLRP) Public Outreach Environmental Assessment and supporting technical studies Interchange Modification Report (IMR) Stormwater Management Approvals Preliminary Sound Wall Work Federal, State and Local Agency Coordination Multimodal Study (conducted by DRPT) 11

12 Responsibilities of 95 Express Preliminary Engineering and Design Cost Estimating Finance Plan Design-Build Procurement Hosting Industry Opportunity Session on March 23, 2016 at VDOT Northern Virginia Headquarters Office. For more information, visit Community Outreach for I-395 Express Lanes 12

13 Environmental Assessment VDOT initiating preparation of an Environmental Assessment (EA) for the I-395 Express Lanes Project Finalizing NEPA concurrence with FHWA Scoping sent January 2016 Technical studies to include: Traffic Analysis and Forecasting Air Analysis Noise Analysis Indirect and Cumulative Effects Public Information Meeting on April 11 and 13, 2016 Release of Draft EA anticipated later summer

14 Multimodal Study DRPT leading Transit/Transportation Demand Management (TDM) Study Scope is broader than project limits - will extend entire proposed I-395 and existing 95 Express Lanes corridor DRPT will solicit stakeholder input and finalize scope of study with goal of beginning study in March 2016 Study will identify transit services and TDM program enhancements that would increase mobility and benefit toll payers in the I-95/I-395 corridor A list of projects will be identified, prioritized for funding through this project 14

15 Key Project Milestones Key Milestones Begin Dates Public Outreach and Technical Coordination Ongoing Stakeholder Advisory Group Meeting #1 January 12, 2016 Begin NEPA Environmental Assessment January 2016 Stakeholder Advisory Group Meeting #2 March 2, 2016 Begin Multimodal Study March 2016 Public Information Meetings April 11 and 13, 2016 Adopted in Constrained Long Range Plan November 2016 Design Build Contract Award (95 Express) December 2016 Final NEPA Decision December 2016 Final Multimodal Study December 2016 Final Agreement January 2017 Begin Construction (95 Express) Spring 2017 Project Completion (95 Express) Summer

16 Susan Shaw, P.E., Megaprojects Director Transform 66: Outside the Beltway March 15,

17 I-66 Outside the Beltway Project Area Project Location Virginia 17

18 I-66 Outside the Beltway Preferred Alternative Elements Two Express Lanes (convert existing HOV lane & add one lane) HOV-3+ and buses travel free Non-HOV tolled Congestion-based tolls (similar to other Express Lanes in region) Converting HOV-2+ to HOV-3+ by 2020, consistent with the region s CLRP Three regular lanes Open to all traffic No tolls Ramp-to-ramp connections between interchanges (auxiliary lanes) Safety, interchange and operational improvements New transit service and other multimodal improvements High-frequency, fast and reliable bus service during extended peak periods Park-and-Ride facilities Transportation Demand Management (TDM) strategies Bicycle and pedestrian trail and improvements 18

19 Project Phasing Why Phase 1? Implementable by 2021 Invests wisely New construction accommodates future Metro extension Makes efficient use of existing infrastructure Elements of Phase 1 Provides 2 Express Lanes in each direction to Gainesville (University Boulevard) Provides new transit service and park-and-ride facilities Makes safety and operational improvements at key interchanges Future Phases Included in Preferred Alternative and environmental document Elements can be implemented to meet future demand as funding becomes available 19

20 New Transit Service Point-to-point commuter service between park-and-ride facilities and regional destinations Proposed new transit service includes: Preferred Alternative (By 2040) 20 Routes with up to 13,400 daily riders Phase 1 (By 2025) 13 routes with up to 10,000 daily riders Service assumed to be operated by Fairfax Connector and PRTC Some new transit service may be started during implementation of Transportation Management Plan (TMP) 20

21 Project Procurement All short-listed teams submitted their indicative financial proposals on December 1, The toll concession model (DBFOM) was selected as preferred delivery model and CTB and Transportation P3 Advisory Committee were briefed on the decision Draft Request for Proposals (RFP) has been posted on Project Website and includes: Volume I - Draft Instructions to Proposers ( ITP ) Volume II Draft Comprehensive Agreement ( CA ) Volume III Draft Technical Requirements ( TRs ) 21

22 Key Business Terms Concession Term: 50 years (4 years of construction and 46 years of operation) Financing Permits The Developer will finance the Project at its own cost and risk and non-recourse to VDOT. Up to $600 million public contribution VDOT will obtain required NEPA, CTB and FHWA approvals for Preferred Alternative Developer will be responsible for obtaining all other permits and government approvals, and will be responsible for obtaining any required reevaluation of the NEPA approvals as a result of Developer s ATCs. Design and Construction Fixed priced contract between the Developer and the Design-Build Contractor Intermediate Milestones Intermediate parking spaces: within 18 months of Construction NTP Remove traffic signals on Route 28: within 24 months of Construction NTP Operation and Maintenance (O&M) The Developer will be responsible for O&M of the Express Lanes, except for snow and ice removal 22

23 Other Major Features Funding for transit is a requirement in the financial plan Developer retains the risks for Higher than anticipated HOV use Extension of Metro after 10 years of operation Other corridor enhancements by Department (VDOT) with exception of constructing an additional General Purpose lane Alternative Technical Concepts (ATC) process Emphasis on innovation and increasing value Reduced scope or cheaper quality not acceptable Minimize negative impact of construction activities Expedited construction schedule with Liquidated Damages (LDs) for late Project Completion Liquidated damages for lane closures 23

24 Procurement Next Steps Ongoing One-on-One meetings with Proposers/ATC process May 2016 Public hearing on final draft RFP May 2016 Complete FHWA review and approval of final draft RFP May 2016 CTB Briefing on changes to the draft RFP as a result of public hearings and one-on-one meetings June 2016 Issue final RFP July 2016 receive Technical Proposals August 2016 receive Financial Proposals September 2016 PPTA Audit / final FOPI; select Preferred Proposer October 2016 CTB briefing / Commercial Close April 2017 Financial Close 24

25 Key Milestones Revised EA 15-Day Public Review & Comment Period January/February 2016 Final Environmental Document March/April 2016 Consideration of ATCs March/April 2016 Public Hearing on Final Draft RFP & HOV-2 to HOV-3 Conversion May 2016 Final RFP May 2016 Selection of Developer September 2016 Design Public Hearing Early 2017 Construction Start 2017 Open to Traffic

26 Megaprojects Support Megaprojects Support 66 Outside the Beltway 66 Inside the Beltway 395 Express Lanes Northern Extension Other Projects Dulles Rail Traffic Management Program (TMP) GEC 1 GEC 2 TBD TBD 26

27 Amanda Baxter, Special Projects Manager Transform 66 Inside the Beltway March 15,

28 Project Map 28 28

29 Project Benefits Move more people up to 40,000 per day by 2040 and enhance connectivity for the I-66 Corridor Provide more travel choices for singleoccupancy vehicles (SOV) Enhance transit service Create opportunities for improved level of service of parallel routes Provide seamless connectivity to the region s 40+ miles of express lanes Provide revenue stream support to multimodal components on I-66 and complementary corridors adjacent to I-66 29

30 How the Tolling Works Hours of Operations: Eastbound: 5:30 AM 9:30 AM Westbound: 3:00 PM 7:00 PM All other times there is not an HOV or Toll restriction HOV 2+ toll free in 2017, HOV 3+ toll free in 2020 All vehicles using the lanes during tolling periods must have an E-ZPass or E-ZPass Flex, if they are HOV, mounted in vehicle. 30

31 Toll Gantry Locations 31

32 Toll Gantry Example 32

33 HOV Enforcement 33

34 Typical Pricing Sign Layout Toll Price Signs Toll prices will be displayed on electronic pricing signs Drivers will see two pricing signs before each entry point Signs will show the total price for up to three destinations. Drivers will lock in their toll price for their destination at the first pricing sign Toll prices may be adjusted as often as every five minutes based on real-time traffic conditions Signs may display pricing information prior to tolling period 34

35 Example Trip 35

36 Key Milestones Key Milestones Dates Public Outreach Working Group/Stakeholder Technical Advisory Group Meetings Ongoing Ongoing Group 1 Multimodal Component Selection/Implementation Spring 2016 Tolling Construction Start Summer 2016 Toll Begins Summer

37 How Toll Revenue Will Be Used Toll revenue can only be used for components selected by the Northern Virginia Transportation Commission that will: Benefit toll paying users of I-66 inside the Beltway Move more people through the corridor Submitted by a jurisdiction in Planning District 8 Implemented within 5 years Eligible components include: Enhanced bus service Vanpool and carpool improvements Metrorail improvements Roadway improvements on parallel routes Park and ride lots Roadway operational improvements Transportation systems management 37

38 Initial Multimodal Program Milestones Key Milestones Dates Develop prioritization criteria and Call for Components application materials Ongoing Brief all eligible applicants February 2016 Approve prioritization criteria, Call for Components, and notice of Public Hearing Approve draft list of projects, hold public hearing, approve final list March 2016 April to June 2016 Submit initial multimodal program for CTB approval June 2016 Execute standard project agreements July 2016 Target for implementation Summer

39 Eastbound Widening Project Widening of I-66 eastbound from two to three lanes between the Dulles Connector Road to Fairfax Drive-Exit 71 (approximately 4 miles) Requires preparation of an Environmental Assessment pursuant to NEPA Will require analysis for Sound Walls Tolling will continue through construction Constructed expected to begin Early 2018 New lane expected to open early

40 I-66 Inside the Beltway Project Procurement Civil Infrastructure Award June 2016 Tolling Integration Award May 2016 Widening Design-Build Request for Proposals - June 2017 Award Dec Open to Traffic - Late 2019/early

41 I-66 Inside the Beltway Amanda Baxter Special Projects Development Manager March 15, 2016

42 HOUSE BILL 2 Assessment of Initial Draft Scenario Nicholas J. Roper, P.E. District Project Development Engineer nicholas.roper@vdot.virginia.gov Phone: (703) March 15, 2016

43 Project Cost Delivery Design Adm By Principal Improvement Type HB2 Initial Draft Scenario District NOVA Bristol Culpeper Fredericksburg Hampton Rds Lynchburg Richmond Salem Staunton No. of Projects No. of New Projects Highway Bike/Pedestrian Rail Transit Bus Transit TDM VDOT Locality VDOT Consultant TBD or Other DBB DB TBD or Other Total $2,514M $91M $113M $279M $1,090M $96M $220M $164M $146M x $1M $1M < x $10M $10M < x $50M $50M < x $100M $100M < x $200M x > $200M of 256 projects appear to be new -- 37%

44 PRINCIPAL IMPROVEMENT TYPE Statewide <1% 4% 4% 20% 72% District Highway Bike/Pedestrian Rail Transit TDM Bus Transit Highway Rail Transit Bike/Pedestrian Bus Transit More than 25% of projects are bike/ped or transit Bike/ped projects are a significant proportion of projects in almost every District Multimodal is in 44

45 PROJECT ADMINISTRATION Statewide 40 District 35 29% % VDOT Admn By VDOT Majority of projects will be administered by VDOT, but... Admn By Locality Locality administered projects continue to comprise a significant proportion of the transportation program Localities plan to administer almost 90% of NOVA projects

46 Statewide DESIGN District 76 VDOT Consultant 10 5 TBD or Other 0 VDOT Consultant TBD or Other At least 30% of projects will be designed by VDOT staff Design resources for majority of projects has not yet been determined

47 DELIVERY Statewide District DBB % 53% DB TBD or Other 5 0 1% DBB DB TBD or Other Design-Bid-Build is the method of delivery for >50% of projects Very small percentage of projects have been selected for Design-Build Delivery of almost 50% of projects has not yet been determined

48 PROJECT COST Statewide District x $1M $1M < x $10M $10M < x $50M $50M < x $100M $100M < x $200M x $200M x $1M $1M < x $10M $10M < x $50M $50M < x $100M $100M < x $200M x $200M More than 75% of projects are under $10M 95% of projects are under $50M 5% of projects are greater than $50M

49 IIM-IID-3.0 Funding Requirements for Construction Program Projects - Principles Projects in the SYIP: Have an established budget and schedule and they are to be delivered on-time and within budget Data must be accurate and reliable in appropriate systems of record Are safety, operational, reconstruction and capital projects that are fully funded through completion. State and federally funded projects must be fully funded. Projects of statewide significance requiring large studies, such as NEPA, IMRs, IJRs, etc. that have been identified by the CTB, Secretary of Transportation, or Commissioner will be funded through an appropriate source Consistent with Code of Virginia (E) VDOT and locality administered projects that do not advance or that are cancelled may require payback of expended state and federal funds VDOT will maintain flexibility in working with local governments and regional planning bodes so that projects using local or regional funds (i.e., NVTA, HRTAC, local project contributions) can be funded by phase with identified funding from other sources 49

50 The Virginia Department of Transportation (VDOT) is pleased to announce its selection as the Featured Agency for the 2016 International Bridge Conference VDOT will provide a Keynote Speaker for the Opening Session, a Chairperson, technical presentations and exhibits for the Featured Agency Booth To help VDOT maintain a prominent role for Virginia and its bridge community throughout the Conference, Consultants and Contractors are encouraged to: Submit projects to the IBC Executive Committee for presentation. The 2016 IBC has issued its Call for Papers at Establish exhibitor booths and sponsor activities at the 2016 IBC Provide assistance (TBD) to VDOT for the Featured Agency Session with exhibits for the Featured Agency Booth For coordination and questions, contact your local VDOT District Bridge Engineer or: Kendal R. Walus, P.E. State Structure & Bridge Engineer Phone: (804) kendal.walus@vdot.virginia.gov Nicholas J. Roper, P.E. NOVA District Project Development Engineer Phone: (703) nicholas.roper@vdot.virginia.gov

51 Nicholas J. Roper, P.E. Office: (703) Cell: (703)

MAJOR BUSINESS TERMS FOR THE TRANSFORM 66 P3 PROJECT IN THE COMMONWEALTH OF VIRGINIA DBFOM DELIVERY METHOD

MAJOR BUSINESS TERMS FOR THE TRANSFORM 66 P3 PROJECT IN THE COMMONWEALTH OF VIRGINIA DBFOM DELIVERY METHOD October 1, 2015 MAJOR BUSINESS TERMS FOR THE TRANSFORM 66 P3 PROJECT IN THE COMMONWEALTH OF VIRGINIA DBFOM DELIVERY METHOD This Term Sheet ( Term Sheet ) provides a summary of major business terms to be

More information

F = MA : CSG SLC WEBINAR DECEMBER 16, J. Douglas Koelemay, Director

F = MA : CSG SLC WEBINAR DECEMBER 16, J. Douglas Koelemay, Director F = MA : CSG SLC WEBINAR DECEMBER 16, 2014 J. Douglas Koelemay, Director VIRGINIA LEADERSHIP IN PUBLIC-PRIVATE PARTNERSHIPS PPTA enabling legislation adopted 1995; PPEA followed PPTA implementation guidelines

More information

HB2 and HB1887 Update

HB2 and HB1887 Update HB2 and HB1887 Update Nick Donohue Deputy Secretary of Transportation April 20, 2015 HB2 Legislation Requires Commonwealth Transportation Board to adopt statewide prioritization process to evaluate projects

More information

I-81 Corridor Improvement Plan. October 2018 Public Meetings

I-81 Corridor Improvement Plan. October 2018 Public Meetings I-81 Corridor Improvement Plan October 2018 Public Meetings I-81 Corridor Improvement Plan Overview of I-81 Corridor Improvement Plan purpose Summary of public feedback Prioritization of potential improvements

More information

REQUEST FOR INFORMATION

REQUEST FOR INFORMATION REQUEST FOR INFORMATION Regarding the Interstate 66 Corridor Improvements (From US Route 15 in Prince William County To Interstate 495 in Fairfax County RFI Issuance Date: June 27, 2013 RFI Closing Date:

More information

DRAFT REQUEST FOR QUALIFICATIONS RELATING TO THE TRANSFORM 66 P3 PROJECT UNDER THE VIRGINIA PUBLIC-PRIVATE TRANSPORTATION ACT OF 1995 (AS AMENDED)

DRAFT REQUEST FOR QUALIFICATIONS RELATING TO THE TRANSFORM 66 P3 PROJECT UNDER THE VIRGINIA PUBLIC-PRIVATE TRANSPORTATION ACT OF 1995 (AS AMENDED) DRAFT REQUEST FOR QUALIFICATIONS RELATING TO THE TRANSFORM 66 P3 PROJECT UNDER THE VIRGINIA PUBLIC-PRIVATE TRANSPORTATION ACT OF 1995 (AS AMENDED) VIRGINIA DEPARTMENT OF TRANSPORTATION POSTED AUGUST 31,

More information

DRAFT REQUEST FOR PROPOSALS TO DEVELOP, DESIGN, CONSTRUCT, FINANCE, OPERATE AND MAINTAIN THE TRANSFORM 66 P3 PROJECT

DRAFT REQUEST FOR PROPOSALS TO DEVELOP, DESIGN, CONSTRUCT, FINANCE, OPERATE AND MAINTAIN THE TRANSFORM 66 P3 PROJECT DRAFT REQUEST FOR PROPOSALS TO DEVELOP, DESIGN, CONSTRUCT, FINANCE, OPERATE AND MAINTAIN THE TRANSFORM 66 P3 PROJECT UNDER THE VIRGINIA PUBLIC-PRIVATE TRANSPORTATION ACT OF 1995 (AS AMENDED) VOLUME I INSTRUCTIONS

More information

I-64 Capacity Improvements Segment III Initial Financial Plan

I-64 Capacity Improvements Segment III Initial Financial Plan I-64 Capacity Improvements Segment III Initial Financial Plan State Project # 0064-965-229/0064-099-229 P101, R201, C501, B638, B639, B640, B641, B642, B643, D609, D610, D611 Federal # NHPP-064-3(498)/

More information

Draft TransAction Plan: Overview and Findings. Martin E. Nohe, Chairman July 13, 2017

Draft TransAction Plan: Overview and Findings. Martin E. Nohe, Chairman July 13, 2017 Draft TransAction Plan: Overview and Findings Martin E. Nohe, Chairman July 13, 2017 1 NVTA s Long Range Transportation Planning Responsibility NVTA is legislatively required to prepare a long range regional

More information

MEMORANDUM OF AGREEMENT TRANSFORM66: INSIDE THE BELTWAY PROJECT. This Memorandum of Agreement ( MOA ) is entered into on, 2015, between

MEMORANDUM OF AGREEMENT TRANSFORM66: INSIDE THE BELTWAY PROJECT. This Memorandum of Agreement ( MOA ) is entered into on, 2015, between REDLINED - NOTES CHANGES FROM 11/23/15 VERSION MEMORANDUM OF AGREEMENT TRANSFORM66: INSIDE THE BELTWAY PROJECT This Memorandum of Agreement ( MOA ) is entered into on, 2015, between the Commonwealth Transportation

More information

SEPTEMBER 2018 DULLES CORRIDOR ENTERPRISE REPORT OF THE FINANCIAL ADVISORS

SEPTEMBER 2018 DULLES CORRIDOR ENTERPRISE REPORT OF THE FINANCIAL ADVISORS SEPTEMBER 2018 DULLES CORRIDOR ENTERPRISE REPORT OF THE FINANCIAL ADVISORS The Airports Authority established the Dulles Corridor Enterprise (DCE) Fund to segregate the financial activity associated with

More information

P3 CONTRACTS. Morteza Farajian, Ph.D. November 2016

P3 CONTRACTS. Morteza Farajian, Ph.D. November 2016 P3 CONTRACTS Morteza Farajian, Ph.D. November 2016 What is a Public-Private Partnership (P3)? Overview of P3s Definition P3 Defined A P3 involves a partnership between the public and private sector to

More information

Fiscal Year VDOT Annual Budget June 2017

Fiscal Year VDOT Annual Budget June 2017 Fiscal Year 2018 VDOT Annual Budget June 2017 This Page Intentionally Left Blank Annual Budget FY 2018 2 Virginia Department of Transportation Table of Contents Overview.. 5 Revenues.. 7 Highway Maintenance

More information

Performance-Based Operating Assistance Allocation Methodology

Performance-Based Operating Assistance Allocation Methodology Performance-Based Operating Assistance Allocation Methodology Amy Inman Acting Planning &Mobility Programs Administrator Department of Rail and Public Transportation SB1140 Public Meeting October 2, 2013

More information

Fiscal Year VDOT Annual Budget June 2018

Fiscal Year VDOT Annual Budget June 2018 Fiscal Year 2019 VDOT Annual Budget June 2018 This Page Intentionally Left Blank Annual Budget FY 2019 2 Virginia Department of Transportation Table of Contents Overview. 5 Revenues. 7 Highway Maintenance

More information

OCTOBER 2017 DULLES CORRIDOR ENTERPRISE REPORT OF THE FINANCIAL ADVISORS

OCTOBER 2017 DULLES CORRIDOR ENTERPRISE REPORT OF THE FINANCIAL ADVISORS OCTOBER 2017 DULLES CORRIDOR ENTERPRISE REPORT OF THE FINANCIAL ADVISORS The Airports Authority established the Dulles Corridor Enterprise (DCE) Fund to segregate the financial activity associated with

More information

Military Highway Continuous Flow Intersection (CFI) Initial Financial Plan

Military Highway Continuous Flow Intersection (CFI) Initial Financial Plan Military Highway Continuous Flow Intersection (CFI) Initial Financial Plan State Project Number(s): 0013-122-V03, 0165-122-V04, 0165-122-181 UPC(s): 9783, 1765, 84243 1 Table of Contents 1. Project Description...

More information

Countywide Dialogue on Transportation

Countywide Dialogue on Transportation Countywide Dialogue on Transportation Fairfax Federation November 15, 2012 Fairfax County Background Fairfax County s economic health depends on an efficient transportation system. The County strives to

More information

I-66 RFI Response Vinci Concessions USA 25 November 2013

I-66 RFI Response Vinci Concessions USA 25 November 2013 General: 1. Please describe your firm, its experience in relation to public-private partnership projects, and its potential interest in relation to the Project (e.g., design/engineering firm, construction

More information

Northern Virginia Transportation Commission: 2018 Legislative and Policy Agenda

Northern Virginia Transportation Commission: 2018 Legislative and Policy Agenda Northern Virginia Transportation Commission: 2018 Legislative and Policy Agenda Northern Virginia s economic growth and global competitiveness are directly tied to the region s transit network. Transit

More information

Transit Subsidy. Mission Statement. Mandates

Transit Subsidy. Mission Statement. Mandates Mission Statement The Potomac and Rappahannock Transportation Commission (PRTC) is a multi-jurisdictional agency representing Prince William, Stafford, and Spotsylvania Counties and the Cities of Manassas,

More information

Review and Update of Year 2035 Regional Transportation Plan

Review and Update of Year 2035 Regional Transportation Plan Review and Update of Year 2035 Regional Transportation Plan #217752 1 Background Every four years, the Year 2035 Plan is reviewed Elements of review Validity of Plan Year 2035 forecasts Transportation

More information

Draft TransAction Plan: Overview and Findings. Keith Jasper, NVTA July 10, 2017

Draft TransAction Plan: Overview and Findings. Keith Jasper, NVTA July 10, 2017 Draft TransAction Plan: Overview and Findings Keith Jasper, NVTA July 10, 2017 1 Long Range Transportation Planning Responsibility NVTA is legislatively required to prepare a long range regional transportation

More information

Introduction Project Overview How Express Lanes Work 101 Managed Lane Financial Forecast Performance Comparison Ownership Considerations Transit

Introduction Project Overview How Express Lanes Work 101 Managed Lane Financial Forecast Performance Comparison Ownership Considerations Transit Joint Board Ownership Workshop November 16, 2018 1 Introduction Project Overview How Express Lanes Work 101 Managed Lane Financial Forecast Performance Comparison Ownership Considerations Transit Equity

More information

VIRGINIA S STATE OF THE STATE ADDRESS

VIRGINIA S STATE OF THE STATE ADDRESS VIRGINIA S STATE OF THE STATE ADDRESS TRB ADC40 Summer Session July 27, 2009 Paul M. Kohler Noise Abatement Program Manager AGENDA 1. Economic Status of Virginia 2. Reorganization of VDOT 3. Projects of

More information

Chairman Smedberg and the VRE Operations Board

Chairman Smedberg and the VRE Operations Board Agenda Item 9-A Action Item To: From: Chairman Smedberg and the VRE Operations Board Doug Allen Date: March 17, 2017 Re: Approval of Gainesville-Haymarket Extension Study Alternative for Preliminary Engineering

More information

RECOMMENDATION TO THE DULLES CORRIDOR AND FINANCE COMMITTEES

RECOMMENDATION TO THE DULLES CORRIDOR AND FINANCE COMMITTEES Dulles Toll Road RECOMMENDATION TO THE DULLES CORRIDOR AND FINANCE COMMITTEES PROPOSED AMENDMENT TO REGULATION THAT ESTABLISHES TOLL RATES FOR THE USE OF THE DULLES TOLL ROAD ACTION REQUESTED JUNE 2018

More information

Fiscal Year Commonwealth Transportation Fund Budget June 2018

Fiscal Year Commonwealth Transportation Fund Budget June 2018 Fiscal Year 2019 Commonwealth Transportation Fund Budget June 2018 This Page Intentionally Left Blank 2 Virginia Department of Transportation Financial Planning Division 1221 E. Broad Street, 4th Floor

More information

6d.) HB2 District Grant Program Allocation Formula

6d.) HB2 District Grant Program Allocation Formula 6d.) HB2 District Grant Program Allocation Formula Presentation to the FAMPO Policy Committee December 14, 2015 HB 2 District Grant Program Background Allocates 50% of funding available from HB2 Prioritization

More information

Sec Transportation management special use permits Purpose and intent.

Sec Transportation management special use permits Purpose and intent. Sec. 11-700 Transportation management special use permits. 11-701 Purpose and intent. There are certain uses of land which, by their location, nature, size and/or density, or by the accessory uses permitted

More information

Bond Counsel Services

Bond Counsel Services HAMPTON ROADS TRANSPORTATION ACCOUNTABILITY COMMISSION REQUEST FOR PROPOSALS FOR PROFESSIONAL SERVICES* Bond Counsel Services ISSUED: September 4, 2015 Proposal Number: FY16-001 *The contract that will

More information

AMENDED AND RESTATED COMPREHENSIVE AGREEMENT RELATING TO THE ROUTE 495 HOT LANES IN VIRGINIA PROJECT DATED AS OF DECEMBER 19, 2007 BY AND AMONG

AMENDED AND RESTATED COMPREHENSIVE AGREEMENT RELATING TO THE ROUTE 495 HOT LANES IN VIRGINIA PROJECT DATED AS OF DECEMBER 19, 2007 BY AND AMONG EXECUTION COPY AMENDED AND RESTATED COMPREHENSIVE AGREEMENT RELATING TO THE ROUTE 495 HOT LANES IN VIRGINIA PROJECT DATED AS OF DECEMBER 19, 2007 BY AND AMONG VIRGINIA DEPARTMENT OF TRANSPORTATION, an

More information

Public Hearing Tarrant County. April 14, 2009

Public Hearing Tarrant County. April 14, 2009 Public Hearing Tarrant County April 14, 2009 Public Hearing Agenda Welcome and Project Overview Ms. Maribel P. Chavez, P.E. District Engineer Texas Department of Transportation Fort Worth District 2 Public

More information

Governor Harry W. Nice Memorial Bridge Improvement Project. Charles County Commissioners Presentation September 1, 2009

Governor Harry W. Nice Memorial Bridge Improvement Project. Charles County Commissioners Presentation September 1, 2009 Governor Harry W. Nice Memorial Bridge Improvement Project Charles County Commissioners Presentation September 1, 2009 Purpose of Presentation Provide a project update since the last Charles County Commissioners

More information

Transit Subsidy. Mission Statement. Mandates

Transit Subsidy. Mission Statement. Mandates Mission Statement The Potomac and Rappahannock Transportation Commission (PRTC) is a multi-jurisdictional agency representing Prince William, Stafford, and Spotsylvania Counties and the Cities of Manassas,

More information

COMPREHENSIVE AGREEMENT RELATING TO THE TRANSFORM 66 P3 PROJECT DATED AS OF DECEMBER 8, 2016, BY AND BETWEEN

COMPREHENSIVE AGREEMENT RELATING TO THE TRANSFORM 66 P3 PROJECT DATED AS OF DECEMBER 8, 2016, BY AND BETWEEN EXECUTION VERSION COMPREHENSIVE AGREEMENT RELATING TO THE TRANSFORM 66 P3 PROJECT DATED AS OF DECEMBER 8, 2016, BY AND BETWEEN VIRGINIA DEPARTMENT OF TRANSPORTATION, an Agency of the Commonwealth of Virginia

More information

Arlington Transportation Demand Managment Strategic Plan FY FY2040

Arlington Transportation Demand Managment Strategic Plan FY FY2040 Arlington Transportation Demand Managment Strategic Plan Arlington County Transportation Demand Management Strategic Plan, FY2013 - FY2040 FY2013 - FY2040 Arlington Transportation Partners The Commuter

More information

FY 2017 Rural Transportation Planning Work Program SCOPE OF WORK

FY 2017 Rural Transportation Planning Work Program SCOPE OF WORK FY 2017 Rural Transportation Planning Work Program SCOPE OF WORK for the Roanoke Valley-Alleghany Regional Commission (July 1, 2016 June 30, 2017) P.O. Box 2569, Roanoke, VA 24010 Ph: 540.343.4417 rvarc@rvarc.org

More information

FINANCIAL REPORT JUNE 30, 2017

FINANCIAL REPORT JUNE 30, 2017 FINANCIAL REPORT JUNE 30, 2017 This Page Intentionally Left Blank FINANCIAL REPORT JUNE 30, 2017 Terry McAuliffe Governor Aubrey L. Layne, Jr. Secretary of Transportation Charles A. Kilpatrick, P.E. Commissioner

More information

10-Year Capital Highway Investment Plan DRAFT

10-Year Capital Highway Investment Plan DRAFT 10-Year Capital Highway Investment Plan DRAFT 2018-2027 DRAFT AUGUST 2017 1 Table of Contents PURPOSE OF 10-YEAR CAPITAL HIGHWAY INVESTMENT PLAN... 1 This page intentionally left blank. SUMMARY OF INVESTMENT

More information

HRTPO TTAC RECOMMENDATIONS ON THE HB2 PRIORITIZATION PROCESS

HRTPO TTAC RECOMMENDATIONS ON THE HB2 PRIORITIZATION PROCESS HRTPO TTAC RECOMMENDATIONS ON THE HB2 PRIORITIZATION PROCESS February 4, 2015 BACKGROUND The Office of the Secretary of Transportation is coordinating stakeholder input during the development of the House

More information

FINANCIAL REPORT JUNE 30, 2015

FINANCIAL REPORT JUNE 30, 2015 FINANCIAL REPORT JUNE 30, 2015 This Page Intentionally Left Blank FINANCIAL REPORT JUNE 30, 2015 Terry McAuliffe Governor Aubrey L. Layne, Jr. Secretary of Transportation Charles A. Kilpatrick, P.E. Commissioner

More information

JANUARY 2018 DULLES CORRIDOR ENTERPRISE REPORT OF THE FINANCIAL ADVISORS

JANUARY 2018 DULLES CORRIDOR ENTERPRISE REPORT OF THE FINANCIAL ADVISORS JANUARY 2018 DULLES CORRIDOR ENTERPRISE REPORT OF THE FINANCIAL ADVISORS The Airports Authority established the Dulles Corridor Enterprise (DCE) Fund to segregate the financial activity associated with

More information

Fiscal Year VDOT Annual Budget June 2011

Fiscal Year VDOT Annual Budget June 2011 Fiscal Year 2011-2012 VDOT Annual Budget June 2011 For Further Information Contact: Virginia Department of Transportation Financial Planning Division 1221 E. Broad Street, 4th Floor Richmond, VA 23219

More information

10-Year Capital Highway Investment Plan DRAFT

10-Year Capital Highway Investment Plan DRAFT This document is made available electronically by the Minnesota Legislative Reference Library as part of an ongoing digital archiving project. http://www.leg.state.mn.us/lrl/lrl.asp 10-Year Capital Highway

More information

Managing Change, Challenges & Other Things Malcolm T. Kerley, P.E. Chief Engineer, Virginia Department of Transportation Chair, AASHTO Subcommittee

Managing Change, Challenges & Other Things Malcolm T. Kerley, P.E. Chief Engineer, Virginia Department of Transportation Chair, AASHTO Subcommittee Managing Change, Challenges & Other Things Malcolm T. Kerley, P.E. Chief Engineer, Virginia Department of Transportation Chair, AASHTO Subcommittee on Bridges & Structures April 19, 2010 1 Topics VDOT

More information

Transportation Investment Corporation Service Plan 2012/ /15

Transportation Investment Corporation Service Plan 2012/ /15 Service Plan 2012/13 2014/15 TABLE OF CONTENTS MESSAGE FROM THE CHAIR... 3 ORGANIZATIONAL OVERVIEW... 5 Mandate and Enabling Legislation... 5 Our Vision... 5 Our Values... 5 TI CORP LOCATIONS... 7 CORPORATE

More information

Chapter 6: Financial Resources

Chapter 6: Financial Resources Chapter 6: Financial Resources Introduction This chapter presents the project cost estimates, revenue assumptions and projected revenues for the Lake~Sumter MPO. The analysis reflects a multi-modal transportation

More information

Fiscal Year VDOT Annual Budget June 2017

Fiscal Year VDOT Annual Budget June 2017 Fiscal Year 2018 VDOT Annual Budget June 2017, January 2018 Overview The Fiscal Year 2018 () budget for the (VDOT) identifies the estimated revenues and the distribution of the revenues to the related

More information

Preliminary Findings and Recommendations

Preliminary Findings and Recommendations Review of the Comprehensive Agreement between the North Carolina Department of Transportation and I-77 Mobility Partners LLC Preliminary Findings and Recommendations July 2017 Overview NCDOT has initiated

More information

ITEM #17: HAMPTON ROADS REGIONAL CONNECTORS STUDY: Camelia Ravanbakht, HRTPO

ITEM #17: HAMPTON ROADS REGIONAL CONNECTORS STUDY: Camelia Ravanbakht, HRTPO ITEM #17: HAMPTON ROADS REGIONAL CONNECTORS STUDY: Camelia Ravanbakht, HRTPO SUMMARY: An update on the Hampton Roads Regional Connectors Study (formerly titled the Study of the Remaining Components of

More information

INVESTING STRATEGICALLY

INVESTING STRATEGICALLY 11 INVESTING STRATEGICALLY Federal transportation legislation (Fixing America s Surface Transportation Act FAST Act) requires that the 2040 RTP be based on a financial plan that demonstrates how the program

More information

Fiscal Year Commonwealth Transportation Fund Budget June 2014

Fiscal Year Commonwealth Transportation Fund Budget June 2014 Fiscal Year 2015 Commonwealth Transportation Fund Budget June 2014 2 For Further Information Contact: Virginia Department of Transportation Financial Planning Division 1221 E. Broad Street, 4th Floor Richmond,

More information

Arlington County, Virginia

Arlington County, Virginia Arlington County, Virginia METRO METRO 2015 2024 CIP Metro Funding Project Description The Washington Metropolitan Area Transit Authority (WMATA/Metro) is a unique federal-state-local partnership formed

More information

Transit Subsidy. Mission Statement. Mandates

Transit Subsidy. Mission Statement. Mandates Mission Statement The Potomac and Rappahannock Transportation Commission (PRTC) is a multi-jurisdictional agency representing Prince William, Stafford, and Spotsylvania Counties and the Cities of Manassas,

More information

Key Missing Transportation Links and Virginia s Transportation Funding Crisis. NAIOP Northern Virginia Commercial Real Estate Development Association

Key Missing Transportation Links and Virginia s Transportation Funding Crisis. NAIOP Northern Virginia Commercial Real Estate Development Association Key Missing Transportation Links and Virginia s Transportation Funding Crisis NAIOP Northern Virginia Commercial Real Estate Development Association January 15, 2013 Northern Virginia Transportation Alliance

More information

Performance After Funding Breakout Session #4. Thursday, September 20, 2018 Michaela McCain Moderator Outreach Manager Local Assistance Division

Performance After Funding Breakout Session #4. Thursday, September 20, 2018 Michaela McCain Moderator Outreach Manager Local Assistance Division Performance After Funding Breakout Session #4 Thursday, September 20, 2018 Michaela McCain Moderator Outreach Manager Local Assistance Division Federal Funds Management Wendy E. Thomas Director of Federal

More information

VDOT s Pavement Management Program Virginia Asphalt Association Annual Meeting, 2013

VDOT s Pavement Management Program Virginia Asphalt Association Annual Meeting, 2013 VDOT s Pavement Management Program Virginia Asphalt Association Annual Meeting, 2013 Commissioner Gregory Whirley Virginia Department of Transportation Outline of the Presentation Where we are now current

More information

THE OFFICE OF TRANSPORTATION PUBLIC PRIVATE PARTNERSHIPS ( OTP3 )

THE OFFICE OF TRANSPORTATION PUBLIC PRIVATE PARTNERSHIPS ( OTP3 ) THE OFFICE OF TRANSPORTATION PUBLIC PRIVATE PARTNERSHIPS ( OTP3 ) VIRGINIA DEPARTMENT OF TRANSPORTATION ( VDOT ) VIRGINIA DEPARTMENT OF RAIL AND PUBLIC TRANSPORTATION ( DRPT ) RESPONSE TO REQUEST FOR INFORMATION

More information

Planning Board Worksession No.6: Transportation and Staging

Planning Board Worksession No.6: Transportation and Staging Planning Board Worksession No.6: Transportation and Staging Prior Worksessions January 27: Focused on transportation analysis and staging recommendations in the Draft Plan. February 9: Reviewed the Executive

More information

UCI Legislative Update. May 26, 2016 Julie Brown Local Assistance Division

UCI Legislative Update. May 26, 2016 Julie Brown Local Assistance Division UCI Legislative Update May 26, 2016 Julie Brown Local Assistance Division Legislative Updates HB 1402 (2015) Payments to City of Richmond for movinglanes converted to bicycle lanes; also required study.

More information

Planning Board Worksession No.1-Transportation and Staging

Planning Board Worksession No.1-Transportation and Staging Planning Board Worksession No.1-Transportation and Staging Planning Board Worksession No.1: Transportation and Staging Public Hearing: January 12, 2017 Public Record Closes: January 26, 2017 Sector Plan

More information

Corridors of Commerce DRAFT Scoring and Prioritization Process. Patrick Weidemann Director of Capital Planning and Programming November 1, 2017

Corridors of Commerce DRAFT Scoring and Prioritization Process. Patrick Weidemann Director of Capital Planning and Programming November 1, 2017 Corridors of Commerce DRAFT Scoring and Prioritization Process Patrick Weidemann Director of Capital Planning and Programming November 1, 2017 Project Purpose To develop and implement a scoring and project

More information

Transit Subsidy. Projected FY17 Transit Subsidy

Transit Subsidy. Projected FY17 Transit Subsidy Mission Statement Transit Subsidy The Potomac and Rappahannock Transportation Commission (PRTC) is a multi-jurisdictional agency representing Prince William, Stafford, and Spotsylvania Counties and the

More information

BOARD OF SUPERVISORS TRANSPORTATION/LAND USE COMMITTEE INFORMATION ITEM. Dulles Corridor Metrorail Phase 2 Update

BOARD OF SUPERVISORS TRANSPORTATION/LAND USE COMMITTEE INFORMATION ITEM. Dulles Corridor Metrorail Phase 2 Update BOARD OF SUPERVISORS TRANSPORTATION/LAND USE COMMITTEE INFORMATION ITEM Date of Meeting: March 11, 2016 # 4 SUBJECT: Dulles Corridor Metrorail Phase 2 Update ELECTION DISTRICT: Countywide STAFF CONTACTS:

More information

SR 520 BRIDGE. Investment Grade Traffic and Revenue Study Update. SR 520 Bridge and the Eastside plus West Approach Bridge Project

SR 520 BRIDGE. Investment Grade Traffic and Revenue Study Update. SR 520 Bridge and the Eastside plus West Approach Bridge Project SR 520 BRIDGE Investment Grade Traffic and Revenue Study Update SR 520 Bridge and the Eastside plus West Approach Bridge Project February 16, 2017 Photographs Courtesy of WSDOT Table of Contents Executive

More information

The Federal Perspective: Project Finance, TIFIA and Public Private Partnerships

The Federal Perspective: Project Finance, TIFIA and Public Private Partnerships The Federal Perspective: Project Finance, TIFIA and Public Private Partnerships Mark Sullivan, Federal Highway Administration Innovative Transportation Finance Workshop Shoreview, Minnesota October 20,

More information

This chapter describes the initial financial analysis and planning for the construction and operations of the Locally Preferred Alternative (LPA).

This chapter describes the initial financial analysis and planning for the construction and operations of the Locally Preferred Alternative (LPA). 8 FINANCIAL ANALYSIS This chapter describes the initial financial analysis and planning for the construction and operations of the Locally Preferred Alternative (LPA). The alternative formerly known as

More information

A. HAMPTON ROADS TRANSPORTATION FUND: MONTHLY FINANCIAL REPORT

A. HAMPTON ROADS TRANSPORTATION FUND: MONTHLY FINANCIAL REPORT ITEM #25: FOR YOUR INFORMATION A. HAMPTON ROADS TRANSPORTATION FUND: MONTHLY FINANCIAL REPORT The Virginia Department of Transportation (VDOT) provides the HRTPO with monthly financial reports relating

More information

Technical Memorandum #1: Baseline Conditions. This section provides an overview of the main services operated and assets maintained by PRTC.

Technical Memorandum #1: Baseline Conditions. This section provides an overview of the main services operated and assets maintained by PRTC. Technical Memorandum #1: Baseline Conditions INTRODUCTION This Baseline Conditions Technical Memorandum provides a summary of the key services provided by the Potomac and Rappahannock Transportation Commission

More information

Transportation Funding and Improving Roadway Services Delivery

Transportation Funding and Improving Roadway Services Delivery Transportation Funding and Improving Roadway Services Delivery Transportation Advisory Commission October 5, 2010 1 STUDY PROGRESS Finalize project scope, perform initial data collection, and gather input

More information

Prioritization and Programming Process. NCDOT Division of Planning and Programming November 16, 2016

Prioritization and Programming Process. NCDOT Division of Planning and Programming November 16, 2016 Prioritization and Programming Process NCDOT Division of Planning and Programming November 16, 2016 Today s Roadmap 1. Planning and Programming Division Overview 2. Strategic Investments (STI) Law 3. Prioritization

More information

REQUEST FOR PROPOSAL TRANSPORTATION & MOBILITY PLANNING DIVISION. I-66 Multimodal Study REFERENCE NO: TMPD GENERAL. 11JAN06-IPD-RFP Page 1

REQUEST FOR PROPOSAL TRANSPORTATION & MOBILITY PLANNING DIVISION. I-66 Multimodal Study REFERENCE NO: TMPD GENERAL. 11JAN06-IPD-RFP Page 1 REQUEST FOR PROPOSAL TRANSPORTATION & MOBILITY PLANNING DIVISION I-66 Multimodal Study REFERENCE NO: TMPD 10-03 GENERAL Page 1 The Transportation and Mobility Planning Division (TMPD) of the Virginia Department

More information

Fiscal Year Revised VDOT Annual Budget November 2014

Fiscal Year Revised VDOT Annual Budget November 2014 Fiscal Year 2015 Revised VDOT Annual Budget November 2014 Revised Annual Budget 2 Virginia Department of Transportation Table of Contents Overview.. 5 Revenues.. 7 Highway Maintenance and Operating Fund

More information

LOCATION AND DESIGN DIVISION

LOCATION AND DESIGN DIVISION VIRGINIA DEPARTMENT OF TRANSPORTATION LOCATION AND DESIGN DIVISION INSTRUCTIONAL AND INFORMATIONAL MEMORANDUM GENERAL SUBJECT: Practical Design Flexibility in the Project Development Process SPECIFIC SUBJECT:

More information

Appendix E: Revenues and Cost Estimates

Appendix E: Revenues and Cost Estimates Appendix E: Revenues and Cost Estimates Photo Source: Mission Media Regional Financial Plan 2020-2040 Each metropolitan transportation plan must include a financial plan. In this financial plan, the region

More information

The Outlook and Options for Infrastructure Financing in Virginia

The Outlook and Options for Infrastructure Financing in Virginia The Outlook and Options for Infrastructure Financing in Virginia Coalition of High Growth Localities Fiscal Analytics, Ltd. November, 2012 1989 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001

More information

Transit Funding and Reform Update

Transit Funding and Reform Update Transit Funding and Reform Update Jennifer Mitchell Agency Director House Appropriations Transportation Subcommittee January 21, 2019 1 Statewide Operating Assistance MERIT (HB 1539-2018) Statewide Transit

More information

COMPREHENSIVE AGREEMENT RELATING TO THE TRANSFORM 66 P3 PROJECT DATED AS OF [ ] BY AND BETWEEN

COMPREHENSIVE AGREEMENT RELATING TO THE TRANSFORM 66 P3 PROJECT DATED AS OF [ ] BY AND BETWEEN COMPREHENSIVE AGREEMENT RELATING TO THE TRANSFORM 66 P3 PROJECT DATED AS OF [ ] BY AND BETWEEN VIRGINIA DEPARTMENT OF TRANSPORTATION, an Agency of the Commonwealth of Virginia AND [ ], a [ ] **THE VIRGINIA

More information

University Link LRT Extension

University Link LRT Extension (November 2007) The Central Puget Sound Regional Transit Authority, commonly known as Sound Transit, is proposing to implement an extension of the Central Link light rail transit (LRT) Initial Segment

More information

Fiscal Year 2018 Annual Report to the Joint Commission on Transportation Accountability Relating to the Hampton Roads Transportation Fund

Fiscal Year 2018 Annual Report to the Joint Commission on Transportation Accountability Relating to the Hampton Roads Transportation Fund Joint Commission on Transportation Accountability Relating to the Hampton Roads Transportation Fund Hampton Roads Transportation Accountability Commission 723 Woodlake Drive Chesapeake, Virginia 23320

More information

MINUTES OF SEPTEMBER 5, 2017

MINUTES OF SEPTEMBER 5, 2017 CITIZENS ADVISORY COMMITTEE (CAC) SAN MATEO COUNTY TRANSPORTATION AUTHORITY (TA) 1250 San Carlos Avenue, San Carlos CA 94070 Bacciocco Auditorium, 2 nd Floor MINUTES OF SEPTEMBER 5, 2017 MEMBERS PRESENT:

More information

May 31, 2016 Financial Report

May 31, 2016 Financial Report 2016 May 31, 2016 Financial Report Capital Metropolitan Transportation Authority 7/13/2016 Table of Contents SUMMARY REPORTS Budgetary Performance - Revenue 2 - Sales Tax Revenue 6 - Operating Expenses

More information

Virginia Department of Transportation

Virginia Department of Transportation Virginia Department of Transportation BLUEPRINT UPDATE JOINT COMMISSION ON TRANSPORTATION ACCOUNTABILITY David S. Ekern, Commissioner August 18, 2009 1 2008 Highlights and Accomplishments VDOT achieved

More information

Development of the Cost Feasible Plan

Development of the Cost Feasible Plan March 15, 2012 TPO Board and Advisory Committee Meetings Development of the Cost Feasible Plan Transportation Outlook 2035 LRTP Update Atkins Development of the Cost Feasible Plan P a g e 1 Development

More information

SOUTHERN BELTWAY US-22 TO I-79 PROJECT 2013 FINANCIAL PLAN. Pennsylvania Turnpike Commission Allegheny and Washington Counties, Pennsylvania

SOUTHERN BELTWAY US-22 TO I-79 PROJECT 2013 FINANCIAL PLAN. Pennsylvania Turnpike Commission Allegheny and Washington Counties, Pennsylvania SOUTHERN BELTWAY US-22 TO I-79 PROJECT 2013 FINANCIAL PLAN Pennsylvania Turnpike Commission Allegheny and Washington Counties, Pennsylvania January 2013 Table of Contents... 1 Introduction... 2 Project

More information

Dominion Boulevard Improvements with Toll System VDOT Initial Financial Plan February 1, 2012

Dominion Boulevard Improvements with Toll System VDOT Initial Financial Plan February 1, 2012 VDOT February 1, 2012 Table of Contents Section 1 Summary.2 Project Description. 2 Project Background 2 Current Activities.3 Project Schedule.4 Section 2 Project Cost Estimate..4 Section 3 Project Financing..5

More information

Solutions: Accelerating Infrastructure Projects Goldman, Sachs & Co. April 22, 2008

Solutions: Accelerating Infrastructure Projects Goldman, Sachs & Co. April 22, 2008 MUNIROOT\V_NY\MuniVol0\Shared\Zach\PPP\Greg Carey's Speech for Texas Transportation Forum v4.10.08.doc effroz 11 Apr 2008 16:46 1/13 Solutions: Accelerating Infrastructure Projects Goldman, Sachs & Co.

More information

MAJOR BUSINESS TERMS I-64 HAMPTON ROADS BRIDGE-TUNNEL EXPANSION PROJECT IN THE COMMONWEALTH OF VIRGINIA. March 14, 2019

MAJOR BUSINESS TERMS I-64 HAMPTON ROADS BRIDGE-TUNNEL EXPANSION PROJECT IN THE COMMONWEALTH OF VIRGINIA. March 14, 2019 MAJOR BUSINESS TERMS I-64 HAMPTON ROADS BRIDGE-TUNNEL EXPANSION PROJECT IN THE COMMONWEALTH OF VIRGINIA This Term Sheet ( Term Sheet ) sets out a summary of major business terms for the I-64 Hampton Roads

More information

Addressing Virginia s Transportation Needs: A 3-Step Process. Delegate S. Chris Jones Southern Legislative Conference July 19, 2015

Addressing Virginia s Transportation Needs: A 3-Step Process. Delegate S. Chris Jones Southern Legislative Conference July 19, 2015 Addressing Virginia s Transportation Needs: A 3-Step Process Delegate S. Chris Jones Southern Legislative Conference July 19, 2015 1 2013: Virginia Adopts Enhanced Revenue Stream for Transportation After

More information

JANUARY 2017 DULLES CORRIDOR ENTERPRISE REPORT OF THE FINANCIAL ADVISORS

JANUARY 2017 DULLES CORRIDOR ENTERPRISE REPORT OF THE FINANCIAL ADVISORS JANUARY 2017 DULLES CORRIDOR ENTERPRISE REPORT OF THE FINANCIAL ADVISORS The Airports Authority established the Dulles Corridor Enterprise (DCE) Fund to segregate the financial activity associated with

More information

3. Performance targets for asset condition and system performance (Attached) John Madera, NSVRC

3. Performance targets for asset condition and system performance (Attached) John Madera, NSVRC Winchester-Frederick County MPO Policy Board Meeting Agenda Frederick County Administrative Offices - First Floor Conference Room 107 N. Kent Street, Winchester, VA October 17, 2018-10:00 a.m. 1. ADMINISTRATIVE

More information

Fiscal Year Commonwealth Transportation Fund Budget June 2015

Fiscal Year Commonwealth Transportation Fund Budget June 2015 Fiscal Year 2016 Commonwealth Transportation Fund Budget June 2015 2 For Further Information Contact: Virginia Department of Transportation Financial Planning Division 1221 E. Broad Street, 4th Floor Richmond,

More information

Description of the Submission / Conditions Precedent

Description of the Submission / Conditions Precedent Submittal Relating to the Development of the TxDOT North Tarrant Express Project, Segments 3A and 3B through a Facility Implementation Plan and Facility Agreement Description of the Submission / Conditions

More information

Managed Lanes: Transaction Strategies from the PPP Forefront

Managed Lanes: Transaction Strategies from the PPP Forefront Managed Lanes: Transaction Strategies from the PPP Forefront December 2015 kpmg.com Managed Lanes: Transaction Strategies from the PPP Forefront 1 Introduction Managed lane projects have become an important

More information

I-80 Corridor Unsolicited Proposal Transportation Board Meeting December 3, 2018

I-80 Corridor Unsolicited Proposal Transportation Board Meeting December 3, 2018 I-80 Corridor Unsolicited Proposal Transportation Board Meeting December 3, 2018 UNSOLICITED PROPOSAL NDOT is actively addressing issues on I-80 Reno-Sparks Traffic Study (Completed Spring 2018) o Identified

More information

CMAQ marks decreased by a total of approximately $30.4 million RSTP marks decreased by a total of approximately $36.7 million

CMAQ marks decreased by a total of approximately $30.4 million RSTP marks decreased by a total of approximately $36.7 million HRTPO Board Meeting April 18, 2013 Agenda ITEM #17: FOR YOUR INFORMATION 17A. UPDATED CMAQ AND RSTP MARKS FOR FY 2014-2019 The HRTPO staff received updated preliminary estimates (marks) for the Congestion

More information

1 EXECUTIVE SUMMARY. Figure 1-1: SR 156 Study Area & Monterey Expressway Alignment

1 EXECUTIVE SUMMARY. Figure 1-1: SR 156 Study Area & Monterey Expressway Alignment 1 EXECUTIVE SUMMARY The Transportation Agency for Monterey County (TAMC) Board commissioned a Level 2 Traffic and Revenue study on the feasibility of collecting tolls to fund the proposed new SR156 connector

More information

METRO. Metro Funding. Associated Master Plan: Comprehensive Master Transportation Plan (MTP) for Arlington. Neighborhood(s):

METRO. Metro Funding. Associated Master Plan: Comprehensive Master Transportation Plan (MTP) for Arlington. Neighborhood(s): METRO METRO METRO 2017 2026 CIP Metro Funding Project Description The Washington Metropolitan Area Transit Authority (WMATA/Metro) is a unique federal-state-local partnership formed to provide mass transit

More information

FEBRUARY 2015 DULLES CORRIDOR ENTERPRISE REPORT OF THE FINANCIAL ADVISORS

FEBRUARY 2015 DULLES CORRIDOR ENTERPRISE REPORT OF THE FINANCIAL ADVISORS FEBRUARY 2015 DULLES CORRIDOR ENTERPRISE REPORT OF THE FINANCIAL ADVISORS The Airports Authority established the Dulles Corridor Enterprise (DCE) Fund to segregate the financial activity associated with

More information