RESTRUCTURING PAPER ON A. PROPOSED PROJECT RESTRUCTURING OF EMERGENCY POWER REHABILITATION PROJECT (CR 3933 & TF 54718) (June 22, 2004)

Similar documents
Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (TF-52541) ON A GRANT. IN THE AMOUNT OF US$ 7.

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA MULT-54718) ON A CREDIT AND A GRANT

IMPLEMENTATION COMPLETION AND RESULTS REPORT (TF-91120) ON A GRANT IN THE AMOUNT OF US$57 MILLION) TO THE ISLAMIC REPUBLIC OF AFGHANISTAN FOR A

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING CENTRAL ASIA SOUTH ASIA ELECTRICITY TRANSMISSION AND TRADE PROJECT (CASA-1000)

FOR OFFICIAL USE ONLY

Regional Power Transmission Interconnection Project (Afghanistan and Tajikistan)

Central Asia South Asia Electricity Transmission and Trade Project


FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF TRANSMISSION GRID STRENGTHENING PROJECT LOAN

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING

Realizing a Central Asia-South Asia Regional Electricity Market: CASA-1000

CASA-1000 Project List of FAQs

Afghanistan: Energy Supply Improvement Investment Program (Tranche 2)

ARTF Administrator s Report on Financial Status as of January 19, 2009 (end of Jadi 10 th month of SY1387)

INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE

Periodic Financing Request Report. Afghanistan: Energy Supply Improvement Investment Program (Tranche 3)

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE SECOND ADDITIONAL FINANCING (CREDIT 4987-CM) BOARD APPROVAL DATE: JUNE 23, 2011

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF INFRASTRUCTURE TRANSPORT INVESTMENT PROJECT LOAN (ADDITIONAL FINANCING)

REPORT OF THE AUDITOR GENERAL ON THE FINANCIAL STATEMENTS OF THE UGANDA ELECTRICITY TRANSMISSION COMPANY LIMITED

Afghanistan: Multitranche Financing Facility for Energy Sector Development Investment Program

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING ELECTRICITY SECTOR EFFICIENCY ENHANCEMENT PROJECT CR SE. April 25, 2005 TO THE

AFGHANISTAN COUNTRY BRIEF

The World Bank Kabul Urban Transport Efficiency Improvement Project (P131864)

Financing Agreement CONFORMED COPY GRANT NUMBER H732 -AF. (Financial Sector Rapid Response Project) between ISLAMIC REPUBLIC OF AFGHANISTAN.

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF GEOTHERMAL POWER GENERATION DEVELOPMENT PROJECT GEF TF IND APPROVED ON MAY 29, 2008

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IDA Mar ,450,000.00

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING STRENGTHENING TAX SYSTEMS AND BUILDING TAX POLICY ANALYSIS CAPACITY APPROVED ON APRIL 28, 2017

SOUTH-WEST ROADS: WESTERN EUROPE-WESTERN CHINA INTERNATIONAL TRANSIT CORRIDOR (CAREC 1B & 6B) (P099270)

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE ENERGY SECTOR STRENGTHENING PROJECT LOAN OCTOBER 25, 2010 TO THE

Implementation Status & Results Afghanistan Technical Assistance for Water-sector Capacity Building (P112097)

IDA CR. NO.4554-UG AND GEF TRUST FUND GRANT AGREEMENT NO. TF:

Implementation Status & Results Lebanon LB-EMERGENCY POWER SECTOR REFORM CAPACITY REINFORCEMENT (P104774)

Afghanistan Reconstruction Trust Fund. Quarterly Report to ARTF Donors. September 23, 2009 to December 21, Prepared by the ARTF Administrator

Safeguards Monitoring Report

Document of The World Bank FOR OFFICIAL USE ONLY SUPPLEMENTAL CREDIT DOCUMENT INTERNATIONAL DEVELOPMENT ASSOCIATION

The World Bank Land Husbandry, Water Harvesting and Hillside Irrigation (P114931)

Offshore Grid Development in Germany

LOAN AGREEMENT. (Zhejiang Power Development Project) between PEOPLE S REPUBLIC OF CHINA. and INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING RWANDA ELECTRICITY ACCESS SCALE-UP AND SECTOR WIDE APPROACH (SWAP) DEVELOPMENT PROJECT

Kyrgyz Republic 2007 JOINT COUNTRY PORTFOLIO REVIEW. IDB Portfolio. Background Paper

Report and Recommendation of the President to the Board of Directors. Proposed Grant Republic of Tajikistan: Regional Power Transmission Project

MUHAMMAD DAUD Ex GM Planning/Consultant Planning NTDC/ Member Pakistan Working Group for CASA For SAARC Workshop Lahore, 30th, September, 2015

India: Enhancing Capacity of State Utilities in Preparing Energy Sector Projects

FINANCIAL ANALYSIS: PROJECT 1

Electricity Power System Planning

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF GOVERNMENT S CENTRAL PUBLIC ADMINISTRATION REFORM (CPAR) PROJECT

Japanese ODA Loan. Ex-ante Evaluation

AFRICAN DEVELOPMENT BANK GROUP

ASIAN DEVELOPMENT BANK

IMPLEMENTATION COMPLETION AND RESULTS REPORT ON A GRANT (TF-93632) IN THE AMOUNT OF US$18 MILLION TO THE ISLAMIC REPUBLIC OF AFGHANISTAN FOR A

Financing Agreement. (Energy Community of South East Europe APL 3 Montenegro Project) between THE REPUBLIC OF MONTENEGRO. and

Document of The World Bank FOR OFFICIAL USE ONLY PROJECT COMPLETION NOTE (SCL-4198; WBTF28362) LOAN/GEF GRANT

TRANSMISSION CHARGING STATEMENT

FOR OFFICIAL USE ONLY

Muskrat Falls Project

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-80090) ON A LOAN IN THE AMOUNT OF US$110 MILLION TO THE REPUBLIC OF UZBEKISTAN FOR THE

Afghanistan Reconstruction Trust Fund Report to Donors. First Quarter of the Afghan Fiscal Year 1386 March 21, 2007 to June 21, 2007

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-3967/ ARTF / ARTF ) IN THE AMOUNT OF SDR 17 MILLION US$25 MILLION EQUIVALENT

The World Bank Indonesia Power Transmission Development Project (P117323)

Afghanistan Reconstruction Trust Fund Report to Donors

Supreme Audit Office 0 Government of Islamic Republic of Afghanistan

Energy Community of South East Europe Program- FYR Macedonia Component-AD MEPSO Project (Loan No MK) Amendment of the Loan Agreement

ELECTRICITY ACT, 2005

Afghanistan Reconstruction Trust Fund Report to Donors. Second Quarter of the Afghan Fiscal Year 1386 June 22, 2007 to September 22, 2007

How Infrastructure Investments Support the U.S. Economy: Employment, Productivity and Growth

Law No. (13) Of 2012 Renewable Energy & Energy Efficiency Law

The World Bank LK GPOBA - Access to Sanitation Project (P111161)

BEFORE THE MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS 600 North Robert Street St. Paul, MN 55101

AGREEMENT Between The Northwest Seaport Alliance and Seattle City Light For Terminal 5 Modernization. Recitals

BEFORE THE MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS 600 North Robert Street St. Paul, MN 55101

Project Agreement. (Private Sector Development Support Project) between INTERNATIONAL DEVELOPMENT ASSOCIATION. and

Muskrat Falls Project Oversight Committee. Committee Report March 2015

Georgian National Electricity Regulatory Commission

Zambia Kafue Town - Muzuma - Victoria Falls Regional Transmission Line Reinforcement Project

March 31, Mr. Roy Plucknett Grant Officer USAID/Afghanistan U.S. Embassy Great Massoud Circle Kabul, Afghanistan

SIGAR. USAID s Installation of Turbine Generator Unit 2 at Kajaki Dam Hydropower Plant: Audit of Costs Incurred by Da Afghanistan Breshna Sherkat

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE

FRAMEWORK FINANCING AGREEMENT

Technical Assistance Report

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-48680) ON A LOAN IN THE AMOUNT OF US$200 MILLION UKRAINE FOR THE POWER TRANSMISSION PROJECT

US$M): Sector Board : FPD Cofinancing (US$M US$M): (US$M US$M):

ALSTOM T&D India Quarter ended September 2012 Results. 15 th November, 2012

ASIAN DEVELOPMENT BANK

Applications for Participating Transmission Owner Status Attachment C - Transmission Revenue Requirement

The offices responsible for coordination of all matters related to the implementation of this arrangement are:

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE

Bhutan: Sustainable Rural Electrification Project

Update on the Roadmap for Nigerian Power Sector Reform

Tanahu Hydropower Project (RRP NEP 43281) FINANCIAL ANALYSIS. A. Introduction

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT ON A. CREDIT AND SUPPLEMENTAL GRANT (IDA-3735-AF and IDA-H1630)

Eugene Water & Electric Board Adopted Budget. December 5, 2017

2018 ERO Enterprise Metrics

US$M): Sector Board : Energy and Mining Cofinancing (US$M (US$M US$M): US$M): Closing Date : 12/31/ /31/2010.

Notice of Entering into a Compact with the Federal Democratic Republic of Nepal

2017 Metrics with Historical Data

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE THIRD HIGHWAY PROJECT. IBRD 7889-AZ (May25, 2010) AND IDA 4723-AZ (May 25, 2010) TO THE

Georgian State Electrosystem JSC. Special Purpose Project Financial Statements for the year ended 31 December 2016

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING PROJECT TO IMPROVE EDUCATION QUALITY IN MALAWI PROJECT LOAN TO THE REPUBLIC OF MALAWI

Transcription:

Document of The World Bank Report No: RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF EMERGENCY POWER REHABILITATION PROJECT (CR 3933 & TF 54718) (June 22, 2004) TO THE ISLAMIC REPUBLIC OF AFGHANISTAN June 18, 2010

Regional Vice President: Country Director: Sector Manager / Director: Task Team Leader: Isabel M. Guerrero Nicholas J. Krafft Salman Zaheer/ John Stein Mesfin Wodajo Jijo 2

AFGHANISTAN: EMERGENCY POWER REHABILITATION PROJECT (P083908) (Cr.3933 & TF54718) Restructuring Paper 1. The proposed project restructuring involves a second extension of the closing date of (a) Cr 3933 from September 30, 2010 to September 30, 2012 and (b) the Afghanistan Reconstruction Trust Fund Grant TF54718 from June 30, 2010 to September 30, 2012, to enable completion of ongoing contracts for project works. The project background, implementation status and the team s recommendation for the proposed extension are given in the sections below. 2. Background: The World Bank approved on June 22, 2004, a credit of SDR 72.4 million (US$105 million) to fund the Afghanistan Emergency Power Rehabilitation Project (EPRP); the credit 3933 became effective on July 27, 2004. The project's development objective is to provide improved and reliable power supply to the people in Kabul. The original project consisted of 6 components: Part A: Rehabilitation and expansion of distribution networks in Kabul. Part B: Rehabilitation of Naghlu hydropower station. Part C: Rehabilitation of the 110 kv transmission line from Naghlu to the Kabul East substation and Kabul North substation. Part D: Technical assistance for project implementation support. Part E: Commercialization of the power utility, DABM. Part F: Technical assistance for Ministry of Energy and Water (MEW) and DABM (the electricity supply department). 3. The project is co-financed by an ARTF grant TF 54718 ( US$ 20 million ) for Part B of the project. 4. Initially, project implementation had been very slow. In December 2006, the project was restructured to (i) reduce the scope of Part A of the project to rehabilitate and expand the core medium voltage network in Kabul and reallocate credit proceeds to finance critical parts of the northern transmission system to allow the import of lower cost power from neighboring countries to supply Kabul ( an added Part G of the project); (ii) outsource project management to a consulting firm to mitigate project implementation delays; (iii) revise the project's outcome indicator to increased grid supplied power consumption by customers in Kabul by 70% at the end of the project; and (iv) extend the credit closing date by 20 months from January 31, 2009 to September 30, 2010. The closing date of TF 54718 was also extended from January 31, 2009 to June 30, 2010. 5. Project performance: Following project restructuring and the outsourcing of project management, the project's performance started to turn around. The Project's DO rating is Satisfactory. With the exception of Part B, all project works are substantially completed and project components ratings are Satisfactory or Moderately Satisfactory. 3

6. From January 21, 2009, 40 MW of imported power began to flow to Kabul from Uzbekistan via the northern transmission system, bringing great relief to the people of Kabul. By early 2010, imports from Uzbekistan increased to about 100 MW, extending hours of power supply to 14-24 hours daily, compared to the situation of 3-4 hours on alternate days before April 2009. On a rolling year basis, grid-supplied power consumption by customers in Kabul for the last complete rolling year ending November 2009 reached 571,800 MWh, which is 100 % increase above the baseline level of 284,000 MWh, Corporatization of DABM was approved by the cabinet on March 17, 2008 ; the Corporate DABS launched its formal operation in September 2009; billing and collections has significantly improved; the first customer services and call center in Kabul was inaugurated on February 22, 2010 and, DABS plans to establish more centers in Kabul and in the regions. 7. Rehabilitation of Naghlu hydropower station: The above project results notwithstanding, rehabilitation of the Naghlu hydropower station is seriously behind schedule. The original four units of 25 MW each at the Naghlu hydropower station were supplied from Russia. A contract for their rehabilitation was finally awarded to Technopromexport of Russia (TPE) on August 30, 2006. Assessment of extent of rehabilitation requirement, manufacture of replacement parts, delays on the part of DABS to shut down and hand over the units to TPE, deteriorating security situation in the surrounding area of the site, the absence of supervisory consultant (Fitchner of Germany terminated their contract with MEW on account of staff safety concerns and demobilized in July 2008), and outstanding claims from the contractor resulting from change orders for works and security related expenses, all contributed to the implementation slippages. To date, TPE has substantially completed the rehabilitation of only one unit 8. Actions taken by MEW/DABS: In March 2009, MEW contracted SMEC International Ltd (SMEC for management services for the Naghlu hydropower station rehabilitation. MEW and TPE have agreed on the following actions: (a) MEW/DABS to hand over the second unit to TPE by June 30, 2010, and decommission and hand over the other two units in good time; (b) TPE to complete the rehabilitation of the three turbine units within 24 months from June 2010; (c) MEW to consider legitimate claims by TPE associated with (i) additional costs for enhanced measures to address the worsening security situation in the project area, (ii) additional costs necessitated to carry out Change of Orders issued by the Employer, (iii) appropriate amendment to the letter of Credit (LC) of the contract to suitably include the above additional costs including provision for price adjustment. (d) TPE will: (i) strictly adhere to the revised milestones for the rehabilitation of the units, (ii) review its security arrangements on a continuous basis and take appropriate measures as needed, 4

(e) MEW/SMEC will closely follow up on contract progress and resolve contractual issues promptly. 9. Recommendation. Considering that (a) some of the factors causing implementation slippage of Part B of the project are outside the control of the MEW/DABS; (b) the rehabilitation of the remaining three units is economically and environmentally justified; (c) MEW has an action plan in place to complete the project by the revised closing date; and (d) the supervisory consultant is now in place and is actively managing the component, we would recommend that you approve the proposed extension of Cr 3933 and TF 54718 to September 30, 2012, to enable completion of the Naghlu hydropower station rehabilitation works, thereby ensuring the project outcomes. 5