KENYA ELECTRICITY TRANSMISSION COMPANY LIMITED MOMBASA NAIROBI 400KV & 220KV TRANSMISSION LINE PROJECT. Contract: Ketraco/1/6/09 QUARTERLY REPORT

Size: px
Start display at page:

Download "KENYA ELECTRICITY TRANSMISSION COMPANY LIMITED MOMBASA NAIROBI 400KV & 220KV TRANSMISSION LINE PROJECT. Contract: Ketraco/1/6/09 QUARTERLY REPORT"

Transcription

1 KENYA ELECTRICITY TRANSMISSION COMPANY LIMITED MOMBASA NAIROBI 400KV & 220KV TRANSMISSION LINE PROJECT Contract: Ketraco/1/6/09 QUARTERLY REPORT (OCTOBER-DECEMBER 2013) 1

2 1. INTRODUCTION 1.1. PROJECT OBJECTIVE Evacuation of power to Nairobi from the generation plants in Mombasa PROJECT SCOPE 1. Lot 1: Construction of 24km of 220kV overhead transmission line from Rabai Substation to future Mariakani Substation and about 167km of 400kV overhead transmission line from future Mariakani Substation to Tsavo River. 2. Lot 2: Construction of 12km of 220kV overhead transmission line from Embakasi Substation to future Athi-River Substation and about 279km of 400kV overhead transmission line from future Athi-River Substation to Tsavo River. 3. Lot 3: Extension and modification to the 220kV substations at Embakasi and Rabai to accommodate two new overhead transmission line circuits from Embakasi to Rabai, including 8km of 220kV cable from Embakasi Substation. 4. Consultant: Project Management and supervision work on sites for Lots 1, 2 and Total project funding: Euros 210 million as follows; Financier Euro(Millions) AfDB Group 58 AFD 60 EIB 60 GoK 32 Total 210 2

3 2. EXECUTIVE SUMMARY 2.1. Lot 1, Lot 2 and Lot 3 Overall project progress as at 31st December 2013 is 89.3% LOT 1 Overall contract progress is at 95.75%. By the end of this quarter, Lot 1 have completed all the foundations, i.e. 492 out of 492 foundations and 483 out of 492 towers have been erected. 120 km out of 190km of conductor stringing has been done. Most of the right of way issues have now been resolved. Negotiations for the remaining sections are being addressed with a view of clearing as soon as possible. The target is to complete this contract by end of March LOT 2 Overall contract progress is at 82.24% By the end of this quarter, 657 out of 750 foundations had been completed and 430 out of 750 towers erected. About 100km of this contract has no work going on as land owners have not given consent to proceed LOT 3 Overall, the Siemens contract is about 94.7% complete. The contract has been extended to 30th June 2014 owing to the works at Embakasi substation. This is due to the frequency of outages that can be given. All the equipments have been delivered. Rabai Substation At Rabai sub-station, all equipments have been installed, termination of protection, communication and control cables completed. Commissioning tests are ongoing and a shutdown schedule has been planned in February The substation shall be completed by mid-february

4 Embakasi Substation Embakasi sub-station construction progress is at 97% complete, 85% of 220kV equipment installation, 99% of civil works and 95% of gantries and steel structure installation is done. Termination of LV cables is on-going and the progress here is at 97.3%. Commissioning tests are ongoing as well. This substation is planned to be completed by the end of June

5 3. FINANCIAL REPORT PROJECT CONTRACT FI NO DOCUMENT PERIOD MOMBASA NAIROBI TRANSMISSION LINE /KE 2ND QUARTER REPORT 1 ST OCT- 31 ST DECEMBER 2013 Revenue Summary Financier Approved Funding Funding to date European Investment Bank 6,510,000,000 3,273,870, African Development Bank 6,293,000,000 3,064,339, AgencieFrancais de development 6,510,000,000 3,771,653, Government of Kenya 1,980,000,000 1,980,000, Total 21,293,000,000 12,089,863, Expenditure For the Period Powerline construction 216,517, Consultancy 31,967, Way leaves 133,824, Legal fees 7,838, Site travel 3,874, Other project costs 82,790, Total 476,813,

6 4. PROJECT PROGRESS 4.1. LOT 1 Lot 1 starts from Rabai substation to Tsavo River which has a total length of km. Construction progress on site is at 88.17% as summarized in the table below: NO. ITEM % WORK COMPLETED 220kV (24km) 400kV (166km) 1 Route Detailed Bush Clearing (Minimum 15m width) T.L Profile Approved Foundations Cast Towers erected Stringing Most of the Right of Way (ROW) issues in this Lot have been resolved. The pending ROW problems are being addressed on case by case basis. 6

7 400/220KV MOMBASA - NAIROBI TRANSMISSION LINE, KETRACO/1/6/09 LOT1LOT # 1, PROGRESS (SECTION WISE FOR 400KV) Section Section Length (KM) No. of towers Route (KM) Detail (KM) Check (KM) Excavation Concreting AP0-AP AP1-AP AP2-AP AP3-AP AP4-AP AP5-AP5a AP5a-AP AP6-AP AP7-AP AP8-AP8 A AP8A- AP AP9 - AP AP10-AP AP11-AP AP12-AP AP13-AP Tower Erection Conductor Stringing Final Sag(kms)

8 Section Section Length (KM) No. of towers Route (KM) Detail (KM) Check (KM) Excavation Concreting Tower Erection Conductor Stringing Final Sag(kms) AP14-AP AP15-AP15A AP15A-AP15B AP15B-AP15C- AP16A AP16A-AP AP16-AP AP17-TSAVO TSAVO 1- TSAVO TSAVO 2- TSAVO TSAVO 3- TSAVO TSAVO 4- TSAVO TSAVO 5- TSAVO RVIER Total LOT # 1 PROGRESS (SECTION WISE FOR 220KV) 8

9 Section Section Length (KM) No. of towers Route (KM) Detail (KM) Check (KM) Excavation Concreting Tower Erection Conductor Stringing Final Sag(kms) Section Section Length (KM) No. of towers Route (KM) Detail (KM) Check (KM) Excavation Chimney Tower Erection Conductor Stringing Final Sag(kms) AP1-AP AP2-AP AP3-AP AP4-AP AP5-AP AP6-APH Total Total for 400 & 220 KV

10 4.2. LOT 2 Lot 2 starts from Tsavo River to the 220kV 8 km cable at Embakasi. Total length of the line is 291km. Construction progress on site is at 59.46% as summarized in the table below: NO. ITEM CUMULATIVE % OF WORK COMPLETED 220kV (12km) 400kV (279km) 1 Route Detailed Bush Clearing (Minimum 15m width) T.L Profile Approved Foundations Cast Towers erected Stringing

11 400kV Isinya Tsavo Line Sl No Section KM No of Loc Route Detailed Check Excavation Pad Chimney Erection Stringing Remarks 1 Isniya S/S - AP Isiniya 2 AP AP AP AP AP AP AP AP AP9-9A AP9A AP AP AP AP AP14-Tsa Tsa15-AP12N Substation to AP8/10 is under wayleaves. 11

12 Sl No Section KM No of Loc Route Detailed Check Excavation Pad Chimney Erection Stringing Remarks 18 AP12N-AP11N AP11N - APT APT11-APT APT10-APT APT09-APT APT08-APT APT07-APT APT06-Tsa R.Jun A. Total Sl No Section KM No of Loc Route Detailed Check Excavation Pad Chimney Erection Stringing 400kV Isniya - Athi river line 26 TT3 -AP AP -1 -DESIRE DESIRE 1 -DESIRE

13 Sl No Section KM No of Loc Route Detailed Check Excavation Pad Chimney Erection Stringing Remarks 29 DESIRE 2 -AP AP -2 -AP AP 3 -AP AP 4 - AP5 B NEW B Total Sl No Section KM No of Loc Route Detailed Check Excavation Pad Chimney Erection Stringing 220kV Athi river - Embakasai line 1 AP -5B NEW -AP5B AP5B - AP6B AP6B - AP6B A AP6B A - TPB C Total Total Completion = A+B+C KM No of Loc Route Detailed Check Excavation Pad Chimney Erection Stringing

14 4.3. LOT 3 Overall, this contract is about 94.7% complete. The progress of the main components of the contract is approximately as follows: Engineering: 97% complete Procurement: 100% complete Construction: 88% complete Pre-commissioning: 49% For Rabai sub-station, Pre-commissioning tests are complete; Commissioning functional tests are in progress. There are two commissioning shutdowns planned for Rabai substation in the month of February Rabai substation construction progress is at 99% complete. At Embakasi sub-station, Pre-commissioning tests are on-going. A total of six shutdowns have been scheduled for commissioning of Embakasi substation. Embakasi substation construction progress is at 97% complete. The 22O KV underground cable at Embakasi has been rerouted into the substation so as to be located away from the KPC fuel pipelines. The new route has been agreed in principle and confirmed to have no major hurdles that will hinder progress. This proposal has provided a solution for the completion of this activity. The High Voltage cable works are 82.4% complete. The components of the actual cable works is as follows. Activity Total Quantity Completed Balance % Completion Excavation 13.4km Cable Laying 54 Drums Backfilling 13.4km Concreting of Joint bay 16 Nos Joints 48 Nos

15 5. ACCESS, WAYLEAVES & COMPENSATION ACQUISITION OF WAYLEAVES. The table below shows a summary of payments made to identified structures, crops and land in Lot 1 and Lot 2 as at end of December 2013: S/no. CUMULATIVE AMOUNT PAID (KSHS) 1 Structures 29,179, Crops 1,624, Land 109,019, TOTAL 139,823,

16 Summary Report for MNTL Lot 1 Wayleave Status S/No LOCATION AREA PROBLEM DETAILS PROPOSED SOLUTION 01 AP 6/0 to AP 0/0 (220kV section) 02 AP 0/3,0/12 (400kv Section) Army barracks to Mariakani s/station Mwavumbo Group Ranch(Maji ya Chumvi) 03 AP10-AP11 Ndara Ranch/Sagalla Ranch Land offers given, but 2 PAPs have declined claiming compensation is too low. This affects stringing between AP6/0 to 6/8 (Terminal Tower) at the substation. Payment for PAPs within the Mariakani s/s is also pending (AP0/0). Compensation for land for a PAP in location 0/3.Cheque returned to rectify names but is yet to be released back to the PAP-Kamanza Beja Dele Two PAPS were claiming compensation for the same parcel of land in Mwavumbo Group Ranch. Dispute has now been resolved and payment is awaited Disputed compensation by Mr Mwamunga. Case is still in court. Stringing has been completed. 04 AP15/17 Muraru -Voi PAP (Mr Harold Mwangasu) has disputed the compensation and even returned cheque to Ketraco.He wants a re-valuation he has written to Ketraco that the tower has taken up the remaining parcel of land in such a way that he cannot perform any other economic activity on the affected part. 1. For AP 0/0,6/7,6/8--Pay compensation packages to PAPs living within the substation land and recover the amounts from monies set aside for the outright purchase of the substation. 2. For AP6/1-PAPs (Mupa Chigamba & Peter Chigulu Chigamba) KETRACO is engaging them to resolve the issue. 3. AP 6/3-Compensation for crops needs to be done all details are with KETRACO accounts section. 1. PAP to be paid immediately. 2. Pay PAPs as per the recommendations of the dispute resolution committee of the Ranch. Details of the same have been given to KETRACO s Finance Division. 1. KETRACO to send in a valuer as soon as possible to establish these details and advise before stringing starts in this section. 16

17 Summary Report for MNTL Lot 2 Wayleave Status S/No LOCATION AREA PROBLEM DETAILS PROPOSED SOLUTION 01 AP 1/19 Isinya -Athiriver Land Owner...Mr Parantai Wayleave status Not Clear was done on December 2013 and the owner wants payment before works resume. He remains adamant that the compensation must be negotiated with him. 02 Desire 1/3,1/4,1/5,1/6,- Maasai Rural Institute (Centre) Isinya-Athiriver There is dispute of ownership between - ACK Church & Locals(Two Parties) There are three blocks i.e Block 67, 9, 8. Owned as follows: i)block 67 Owned by Emboloi Group Ranch ii)block 9 by ACK iii)block 8 owned by locals Land is also said to be owned by olkejuado county council. The Governor is aware of the disputes and has written a letter adressing to Ketraco on the issue. Following prior meeting of the above interested parties in regard to the disputes, Money for the affected areas was deposited in a suspense account to await resolution of the dispute to enable Ketraco know who to compensate. KETRACO to pay Mr Parantai. 1. A meeting between Ketraco and the County commissioner, Governor, Chiefs and the management of ACK and representative of the locals has been proposed to chart the way forward as the locals have stopped worked claiming they have not been paid. 03 Desire 2/0 Isinya-Athiriver Section Land owner Mr Kepiro Tungas Compensation for Land has been paid. 4 towers have already been constructed in his land constructed and 1 is remaining ( T30) The line has been re-routed thus leaving out his structures which were previously 17 KETRACO plans to meet Mr Kepiro and the Local Adminstration and iron out the outstanding issues

18 S/No LOCATION AREA PROBLEM DETAILS PROPOSED SOLUTION 05 AP 2/11 Isinya-Athi river section 06 AP 2/0 Isinya Athi River Section 07 AP 2/12,13,14 Isinya Athiriver Section affected. He has received 70% of the affected structure though not in the Wayleave corridor now following the re-routing. He is demanding the remaining 30% although he has not demolished though he doesn t qualify to be paid. Land Owner. Mr Gachiko Disputed affected acreage Mr Gachiko has employed the services of a lawyer to follow up on the disputed acreage and compensation. The Offer letter for land Compensation was given out on 08/01/2014 to the lawyer Awaiting the lawyers response which is expected by 12 h January Land owners Erick & Mbugua. The said Parcel is owned by two brothers who have refused to meet Ketraco. They claim the compensation package offered by Ketraco is too low. One of the Brothers Mr Erick is willing to meet Ketraco and negotiate by next week. Land owner -Ukulima Sacco The land is owned by Afya Sacco and has been subdivided into plots. The plots are titled The PIT has already set the stage for negotiation with elected officials of the Sacco. Although the land is owned by Afya Sacco,some locals (Masais.are KETRACO or is following up on the issue. 1. KETRACO is engaging the land owners to resolve the issue. 2. The wayleave status is assumed to be clear as there has been no resistant here. 3. The Contractor has been asked to move in and start site works

19 S/No LOCATION AREA PROBLEM DETAILS PROPOSED SOLUTION claiming ownership) 08 AP2/4,5,6,7,8,9,10,11 Isinya Athiriver Section 09 AP 2/15 Isinya Athi River Section 10 AP 2/16 & 17 Isinya-Athi River Section Land Owner Alex Pushati He has already received his land compensation package. He claims he has not been paid his cow that fell into one of the foundation pits. He wants to be paid before any works start. He is also one of those pushing to be paid 85%. Land Owner-K-Ref Bank The land owners are not opposed to the line traversing their land They want to be involved in the process of determining the compensation package. The land has been subdivided into plots and beaconed. Land owner Winnie Njeri/Comp West Still waiting for land ownership documents for parcel claimed by Winnie Njeri. Ketraco or resurveyed the land parcels in Question as the acreage was disputed, Offer letter to be given upon submission of land ownership documents as promised by owners. Wayleave not clear. 1. The land owner has questioned the rational of compensating 30% of valued land. 1. Land owners questioning rationale of paying 30% of valued land. 1. Agree with owner to continue with site works as negotiations continue. 19

20 S/No LOCATION AREA PROBLEM DETAILS PROPOSED SOLUTION 11 AP1/11,10,9 Isinya- Land Owner : Teresia Kosenger Tsavo/Isinya - Tower erection not done Athiriver There is dispute between the contractor and the land owner over fence destroyed during concreting and its yet to be fixed. 12 AP4/0- AP/10 Isinya -Tsavo Issues of 85 % Percentage compensation in this area is 30% while that of neighbouring Makueni is 80%-85% 13 AP6/1 Isinya -Tsavo Land Owner: Mr Kasaine ole Solitei Land Owner claims compensation package for land is too low. 14 AP11/0-AP12/0 Pending payments for Bush clearance.contractor has accepted to pay the outstanding bill. 1. Contractor to compensate for fence destroyed and costs as a result of such actions to be settled by him. 1. KETRACO to address the issue of 30% payment of valued land. 1. KETRACO to conclude. 1. Contractor to pay and move on site and commence any pending works. 20

21 FEES FOR PROFESSIONAL SERVICES MOMBASA-NAIROBI 400KV TRANSMISSION LINE Invoice No. Date Of Issue Description Labour Expenses Advance Payment Adjustment Total Invoice Value /05/09 Advance Payment 423, /11/09 Up to 31 Aug , , , , /03/10 Up to 29 Nov 09 Labour , /12/10 Up to 29 Nov 09 Expenses , /03/10 Credit Note for 3.5 Internal Airfares REF: invoice /06/10 Expenses Up to 28 Feb , , , /01/10 Labour Up to 28 Feb 10 58, , , /11/10 Labour Up to 28 May 10 31, , , /11/10 Expenses Up to 28 May 10 9, , , /11/10 Labour Up to 28 August 10 61, , , /11/10 Expenses Up to 28 August 10 17, , , /02/11 Labour Up To 03 December , , , /02/11 Expenses Up To 03 December , , , /05/11 Labour Up To 25 February , , , /08/11 Labour Up To 25 February CREDIT NOTE -110, , , /08/11 Labour Up To 25 February , , , /05/11 Expenses Up To 25 February , , , /08/11 Labour invoice up to 27 May , , , /08/11 Expenses Invoice up to 27 May , , , /12/11 Labour (Home Office) Invoice up to 02 December , , , /12/11 Labour (Site Visit) Invoice up to 02 December , , , Change in charge on due to change in CAD rate -3, , /12/11 Labour (Site) Invoice up to 02 December , , /05/12 Labour (Site) Invoice up to 02 March , , /05/12 Labour (Home office) Invoice up to 02 March , , TBC 01/11/12 Vehicle Purchase 33, , TBC 01/11/12 Expenses up to 01 June , , TBC 01/11/12 Labour (Site) Invoice up to 01 June , , TBC 01/11/12 Labour (Home Office) Invoice up to 01 June , , TBC 01/11/12 Labour (Home Office) up to 31 Aug 12 26, , TBC 01/11/12 Labour (Site) up to 31 Aug , , TBC 01/11/12 Expenses up to 31 Aug 12 38, , Total Paid 2,605,

22 Status of implementation of Environmental and Social Management Plan (ESMP): Quarterly report (January to March 2013) Possible Impact Mitigation measure Responsible person Loss of trees and crops due to clearance of wayleaves (Kenya Forest Service Kibwezi forest issue) Soil Erosion/Reduction in Soil Quality. Waste management 22 Status of implementation/corrective and preventive action Compensation Proponent The Kenya Forest Service has allowed KETRACO to construct the line along the boundary between Kibwezi Forest and Chyulu Hills National Park vide correspondence date June 5 th The agreed route has been subjected to an ESIA which has been approved by the financiers. The report has been submitted to NEMA for review and licencing.. Install erosion control Contractor No appreciable soil erosion has taken place in the measures quarter either due to dust storms or rain. Restoring the site to a condition that is visually acceptable to the community and reclaiming the areas impacted for future use (agricultural for example) Remove any contaminated soils Safe disposal procedures in accordance with NEMA waste management regulations, 2006 Natural drainage patterns are reinstated where they have been altered or impaired. Trenches/terraces (if any) are backfilled daily at close of day s work Top soil is always removed and retained for subsequent rehabilitation. Contractor The contractor has employed a safe waste management system in accordance to the waste management regulations of Waste from the sites including cement bags and food packaging is collected in the evenings to a central place. The municipal council of Voi and Makindu

23 Possible Impact Mitigation measure Responsible person Health, Sanitation and Hygiene. HIV/AIDS and other sexually transmitted diseases. Awareness campaign among Workers and local residents on health risks particularly of HIV/AIDS. Contractor to liaise with the Government and local NGO`s to provide both female and male condoms in appropriate designated places in the labour camp. Provision of first aid facilities at all sites where construction is being undertaken. Use of toilets /latrines in project. Status of implementation/corrective and preventive action collects and disposes the waste from the sites, camp and store. Contractor HIV/AIDS awareness together with other sexually transmitted diseases covered in the Tool Box Talk done daily before work commences. First aid facilities have been provided at appropriate places in the site and parties are encouraged to have clean, hygienic and sterilized first aid equipment. There are trained first aiders on site. Report by.. Date. Eng. Andolo Ambasi, Project Team Leader, Mombasa-Nairobi 400kV project 23

MOMBASA NAIROBI 400 KV TRANSMISSION LINE CONTRACT KETRACO/1/6/09 LOTS 1 and 2 MINUTES OF THE PRE BID MEETING

MOMBASA NAIROBI 400 KV TRANSMISSION LINE CONTRACT KETRACO/1/6/09 LOTS 1 and 2 MINUTES OF THE PRE BID MEETING 1 MOMBASA NAIROBI 400 KV TRANSMISSION LINE CONTRACT KETRACO/1/6/09 LOTS 1 and 2 MINUTES OF THE PRE BID MEETING DATE: 23 rd November, 2009 PRESENT: KPLC/ KETRACO/CONSULTANT TIME: 10.00Hrs VENUE: KETRACO

More information

TRANSMISSION CHARGING STATEMENT

TRANSMISSION CHARGING STATEMENT TRANSMISSION CHARGING STATEMENT 1 September 2016 1 September 2016 TABLE OF CONTENTS Page 1 Introduction... 1 2 General System Charges... 4 3 Site Specific Charges... 5 4 Connection Assets... 8 5 Least

More information

Portland General Electric Company P.U.C. Oregon No. E-18 Original Sheet No. I-1 RULE I LINE EXTENSIONS

Portland General Electric Company P.U.C. Oregon No. E-18 Original Sheet No. I-1 RULE I LINE EXTENSIONS P.U.C. Oregon No. E-18 Original Sheet No. I-1 RULE I LINE EXTENSIONS 1. Purpose This rule establishes procedures and defines respective cost responsibilities to provide a Line Extension to a builder, developer,

More information

EU-Kenya Cooperation in the Infrastructure sector - European Business Council 24 th April 2018

EU-Kenya Cooperation in the Infrastructure sector - European Business Council 24 th April 2018 EU-Kenya Cooperation in the Infrastructure sector - European Business Council 24 th April 2018 1 EU cooperation with Kenya The 11 th EDF National Indicative Programme (NIP) 2014-2020 in Kenya concentrates

More information

COMMONWEALTH ELECTRIC COMPANY Cancels M.D.T.E. No. 300 Appendix B-3 Page 1 of 9 TERMS AND CONDITIONS - DISTRIBUTION SERVICE

COMMONWEALTH ELECTRIC COMPANY Cancels M.D.T.E. No. 300 Appendix B-3 Page 1 of 9 TERMS AND CONDITIONS - DISTRIBUTION SERVICE Page 1 of 9 I. Applicability Appendix B - Line Extension Policy Commercial - Industrial This Policy applies to single-phase or three-phase Line Extensions necessary to serve all Commercial and Industrial

More information

Safeguards Monitoring Report

Safeguards Monitoring Report Safeguards Monitoring Report Semiannual Report Covering July-Dec 2016 period February 2017 (ESDIP) Tranche-2 Chimtala- Arghandi 220 kv DC Transmission Line Subproject (DABS - 006/ICB) Prepared by Da Afghanistan

More information

Initial Environmental Examination

Initial Environmental Examination Initial Environmental Examination June 2017 IND: Green Energy Corridor and Grid Strengthening Project (320 kv VSC-HVDC power transmission lines between Pugalur, Tamil Nadu and North Trichur, Kerala) Annexures

More information

PUBLIC WORKS DEPARTMENT

PUBLIC WORKS DEPARTMENT Departmental Summary FUND/ACTIVITY ACTUAL ADOPTED AMENDED RECOMM. General Fund: Revenue Administration 494,646 501,667 501,035 508,551 Municipal Trash Collection 101,185 60,358 60,358 60,962 Total Revenues

More information

PIDA. Work Based Project Focus for IS4D-- Per Learning Agreement. Agency. WBP Milestone or Output Progress June Corridor

PIDA. Work Based Project Focus for IS4D-- Per Learning Agreement. Agency. WBP Milestone or Output Progress June Corridor Beira-Nacala Rail Corridor PIDA Corridor Agency Work Based Project Focus for IS4D-- Per Learning Agreement WBP Milestone or Output Progress June 2015 Feasibility studies for Malawi Railway Rehab & Reconstruction

More information

PUBLIC WORKS DEPARTMENT Departmental Summary FUND/ACTIVITY ACTUAL ADOPTED AMENDED ADOPTED General Fund: Revenue Administration

PUBLIC WORKS DEPARTMENT Departmental Summary FUND/ACTIVITY ACTUAL ADOPTED AMENDED ADOPTED General Fund: Revenue Administration Departmental Summary FUND/ACTIVITY ACTUAL ADOPTED AMENDED ADOPTED General Fund: Revenue Administration 494,751 453,181 494,253 501,667 Municipal Trash Collection 59,158 59,760 59,760 60,358 Total Revenues

More information

ARRANGEMENT OF REGULATIONS

ARRANGEMENT OF REGULATIONS L.I.1935 ELECTRICITY SUPPLY AND DISTRIBUTION (STANDARDS OF PERFORMANCE) REGULATIONS, 2008 Regulation 1. Purpose 2. Application ARRANGEMENT OF REGULATIONS Purpose and Application Application for new service

More information

KAKAMEGA SOCIAL SECTOR BUDGET BRIEF

KAKAMEGA SOCIAL SECTOR BUDGET BRIEF KAKAMEGA SOCIAL SECTOR BUDGET BRIEF (2013-14 to 2015-16) Highlights In 2015-2016, county spent Ksh 9.9 billion, out of which 36 per cent was spent on social sector. Between 2013-2014 and 2015-2016, along

More information

ELECTRICITY ACT, 2005

ELECTRICITY ACT, 2005 ELECTRICITY ACT, 2005 ARRANGEMENTOF SECTIONS Section PART 1 PRELIMINARY 1. Short title 2. Interpretation 3. Objectives PART II FUNCTIONS OF THE DEPARTMENT OF STATE 4. Functions of the Department of State

More information

PREAMBLE The Kenya Anti- Corruption Commission is required under section 36 of the Anti-Corruption and Economic Crimes Act to prepare quarterly

PREAMBLE The Kenya Anti- Corruption Commission is required under section 36 of the Anti-Corruption and Economic Crimes Act to prepare quarterly PREAMBLE The Kenya Anti- Corruption Commission is required under section 36 of the Anti-Corruption and Economic Crimes Act to prepare quarterly reports. Section 35 provides that: (1) Following an investigation

More information

METRO VANCOUVER REGIONAL DISTRICT FILMING REGULATIONS

METRO VANCOUVER REGIONAL DISTRICT FILMING REGULATIONS METRO VANCOUVER REGIONAL DISTRICT FILMING REGULATIONS FILMING REGULATIONS An ordinance to regulate the conditions under which filming may occur on MVRD premises, under the authority of The Local Government

More information

TRANSMISSION LICENCE NO. 2 OF 2009 LICENCE FOR TRANSMISSION OF ELECTRICITY IN THE STATE OF MAHARASHTRA

TRANSMISSION LICENCE NO. 2 OF 2009 LICENCE FOR TRANSMISSION OF ELECTRICITY IN THE STATE OF MAHARASHTRA MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai - 400 005 Tel. No. 022 22163964/65/69 Fax 022 22163976 E-mail mercindia@mercindia.org.in

More information

WELLINGTON CITY COUNCIL POLICY ON UNDERGROUNDING OF OVERHEAD CABLES

WELLINGTON CITY COUNCIL POLICY ON UNDERGROUNDING OF OVERHEAD CABLES WELLINGTON CITY COUNCIL POLICY ON UNDERGROUNDING OF OVERHEAD CABLES CONTENTS Foreword 3 Summary of Council Policy 3 Introduction 5 Definitions 5 Policy Objectives 5 Undergrounding Principles 5 Cost and

More information

GLNG PROJECT - ENVIRONMENTAL IMPACT STATEMENT

GLNG PROJECT - ENVIRONMENTAL IMPACT STATEMENT 7 Values and Management of Impacts J:\Jobs\42626220\07 Deliverables\EIS\FINAL for Public Release\7. Values and Management of Impacts\7-12 Visual Amenity\07 12 Visual Amenity (Section 7.12) FINAL PUBLIC.doc

More information

Applying for a Kinder Morgan Canada. Proximity Permit. Design and Construction Guidelines CANADA

Applying for a Kinder Morgan Canada. Proximity Permit. Design and Construction Guidelines CANADA Applying for a Kinder Morgan Canada Proximity Permit Design and Construction Guidelines CANADA A Guide to Applying for a Kinder Morgan Canada Proximity Permit Kinder Morgan Canada operates the Trans Mountain

More information

LIBERTY UTILITIES (CALPECO ELECTRIC) LLC SOUTH LAKE TAHOE, CALIFORNIA 2nd Revised CPUC Sheet No. 224 Canceling 1 st Revised CPUC Sheet No.

LIBERTY UTILITIES (CALPECO ELECTRIC) LLC SOUTH LAKE TAHOE, CALIFORNIA 2nd Revised CPUC Sheet No. 224 Canceling 1 st Revised CPUC Sheet No. SOUTH LAKE TAHOE, CALIFORNIA 2nd Revised CPUC Sheet No. 224 Canceling 1 st Revised CPUC Sheet No. 224 A. Applicability Under the provisions of this rule Utility shall make extensions and alterations of

More information

Portland General Electric Company P.U.C. Oregon No. E-18 Original Sheet No. C-1 RULE C CONDITIONS GOVERNING CUSTOMER ATTACHMENT TO FACILITIES

Portland General Electric Company P.U.C. Oregon No. E-18 Original Sheet No. C-1 RULE C CONDITIONS GOVERNING CUSTOMER ATTACHMENT TO FACILITIES P.U.C. Oregon No. E-18 Original Sheet No. C-1 RULE C CONDITIONS GOVERNING CUSTOMER ATTACHMENT TO FACILITIES 1. Acceptance of Electricity Service By establishing or requesting a POD or by continuing an

More information

Public Works Department

Public Works Department Departmental Summary FUND/ACTIVITY ACTUAL ADOPTED AMENDED ADOPTED General Fund: Revenue Administration 246,334 316,548 245,742 245,742 Municipal Trash Collection 57,049 57,000 58,169 58,169 Total Revenues

More information

The World Bank Kabul Urban Transport Efficiency Improvement Project (P131864)

The World Bank Kabul Urban Transport Efficiency Improvement Project (P131864) Public Disclosure Authorized SOUTH ASIA Afghanistan Transport & Digital Development Global Practice Recipient Executed Activities Investment Project Financing FY 2014 Seq No: 8 ARCHIVED on 09-Feb-2018

More information

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING THE INFORMAL SETTLEMENTS IMPROVEMENT PROJECT CREDIT 4873-KE

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING THE INFORMAL SETTLEMENTS IMPROVEMENT PROJECT CREDIT 4873-KE Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY Report No: 104604 Public Disclosure Authorized Public Disclosure Authorized RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING

More information

Directlink Joint Venture. Transmission Network Service Provider Annual Performance Report

Directlink Joint Venture. Transmission Network Service Provider Annual Performance Report Directlink Joint Venture Transmission Network Service Provider August 2017 TABLE OF CONTENTS 1. ANNUAL COMPLIANCE REPORTING... 3 1.1 NETWORK SAFETY AND RELIABILITY 3 1.1.1 Improvement Programs and Activites

More information

DECISION AND ORDER ON PHASE 1

DECISION AND ORDER ON PHASE 1 Commission de l énergie de l Ontario DECISION AND ORDER ON PHASE 1 HYDRO ONE NETWORKS INC. Leave to construct a new transmission line and facilities in the Windsor-Essex Region, Ontario. Before: Ken Quesnelle

More information

VIE: Power Transmission Investment Program, Tranche 2 500kV Pleiku-My Phuoc-Cau Bong Transmission Line (Binh Duong Province)

VIE: Power Transmission Investment Program, Tranche 2 500kV Pleiku-My Phuoc-Cau Bong Transmission Line (Binh Duong Province) Social Monitoring Report July 2014 VIE: Power Transmission Investment Program, Tranche 2 500kV Pleiku-My Phuoc-Cau Bong Transmission Line (Binh Duong Province) Prepared by Central Vietnam Power Projects

More information

Proposed Changes to the National Energy Board Electricity Regulations 1

Proposed Changes to the National Energy Board Electricity Regulations 1 Proposed Changes to the National Energy Board Electricity Regulations 1 SHORT TITLE 1. These Regulations may be cited as the National Energy Board Electricity Regulations. INTERPRETATION 2. In these Regulations,

More information

Power Workers' Union (PWU) INTERROGATORY #1. Ref (a): Participant Information Package: Exhibit C1-2-1, Page 5 of 6, Table 2 (OM&A Expenditures)

Power Workers' Union (PWU) INTERROGATORY #1. Ref (a): Participant Information Package: Exhibit C1-2-1, Page 5 of 6, Table 2 (OM&A Expenditures) Filed: 0-0- 0-0 Tx Rates Schedule Page of Power Workers' Union (PWU) INTERROGATORY # Ref (a): Participant Information Package: Exhibit C--, Page of, Table (OM&A Expenditures) Table : 0 Board Approved versus

More information

Western Power Distribution (East Midlands) plc Registered in England and Wales No

Western Power Distribution (East Midlands) plc Registered in England and Wales No CONNECTION AGREEMENT THIS AGREEMENT is made the day of 2014 Between Western Power Distribution (East Midlands) plc Registered in England and Wales No. 2366923 Whose REGISTERED OFFICE is at And Avonbank

More information

Between the Western Sydney Parklands Trust (the Trust) (LAND OWNER) and

Between the Western Sydney Parklands Trust (the Trust) (LAND OWNER) and PERMIT TO ENTER Between the Western Sydney Parklands Trust (the Trust) (LAND OWNER) and (ENTRANT) DEED made the day of, over land at / known as: Address Western Sydney Parklands Certificate of Title LAND

More information

Between the Parramatta Park Trust (the Trust) (LAND OWNER) and

Between the Parramatta Park Trust (the Trust) (LAND OWNER) and PERMIT TO ENTER Between the Parramatta Park Trust (the Trust) (LAND OWNER) and (ENTRANT) DEED made the day of, over land at / known as: Address Parramatta Park Certificate of Title LAND OWNER Parramatta

More information

Pollution Incident Response Management Plan

Pollution Incident Response Management Plan Pollution Incident Response Management Plan 24-28 Childs Road Chipping Norton NSW 2170 Version 1 Initial Release Date: 2 nd February 2015 PIRMP Barca Metals 24-28 Childs Road, Chipping Norton NSW 2170

More information

Connection and Use of System Charge Methodology Statement ("Condition 25 Statement")

Connection and Use of System Charge Methodology Statement (Condition 25 Statement) Connection and Use of System Charge Methodology Statement ("Condition 25 Statement") Revised Effective Date: 1 st January 2016 Approved by the Authority for Electricity Regulation, Oman Connection and

More information

The World Bank Northern Corridor Transport Improvement Project (P082615)

The World Bank Northern Corridor Transport Improvement Project (P082615) Public Disclosure Authorized AFRICA Kenya Transport & ICT Global Practice IBRD/IDA Specific Investment Loan FY 2004 Seq No: 23 ARCHIVED on 19-Nov-2015 ISR20887 Implementing Agencies: Kenya Civil Aviation

More information

ANNEXURE-A INVITATION FOR BID (IFB) (LOCAL COMPETETIVE BIDDING) Name of Line

ANNEXURE-A INVITATION FOR BID (IFB) (LOCAL COMPETETIVE BIDDING) Name of Line ANNEXURE-A INVITATION FOR BID (IFB) (LOCAL COMPETETIVE BIDDING) SRM E-Tender No. T-1879/MSETCL/CO/C&M/Pretender/TKC-Lines/GEC RFx No.6000000656 1.0 The Maharashtra State Electricity Transmission Company

More information

Water Supply Customer Contract Terms & Conditions. Table of Contents

Water Supply Customer Contract Terms & Conditions. Table of Contents Water Supply Customer Contract Terms & Conditions Table of Contents 1. What is a customer contract and who is covered by it? 1.1 What is a customer contract? 1.2 Customer categories covered by the contract?

More information

AGREEMENT Between The Northwest Seaport Alliance and Seattle City Light For Terminal 5 Modernization. Recitals

AGREEMENT Between The Northwest Seaport Alliance and Seattle City Light For Terminal 5 Modernization. Recitals AGREEMENT Between The Northwest Seaport Alliance and Seattle City Light For Terminal 5 Modernization This Agreement is made and entered into this day of, 2016, by and between the City of Seattle, a municipal

More information

Los Angeles County Public Works. Right-of-Entry Permit for Residential Debris Removal on Private Property Checklist for Property Owners

Los Angeles County Public Works. Right-of-Entry Permit for Residential Debris Removal on Private Property Checklist for Property Owners Right-of-Entry Permit for Residential Debris Removal on Private Property Checklist for Property Owners The County of Los Angeles is working with the California Governor s Office of Emergency Services (CalOES)

More information

GENERAL PROVISIONS I. WORK REQUIREMENTS

GENERAL PROVISIONS I. WORK REQUIREMENTS GENERAL PROVISIONS I. WORK REQUIREMENTS 1. Inspection The Permittee shall request initial inspection from the County at 408-573-2429 a minimum of twenty-four (24) hours prior to any work being performed.

More information

Muskrat Falls Project Oversight Committee. Committee Report March 2015

Muskrat Falls Project Oversight Committee. Committee Report March 2015 Muskrat Falls Project Oversight Committee Committee Report March 2015 Table of Contents Introduction...2 Project Performance...4 Long-term Cost and Schedule...5 Current Cost and Schedule to March 2015...11

More information

Mr Leboo Ole Morintat AG, County Secretary Nairobi City County P.O Box Nairobi. 30 th November 2017, Dear Mr.

Mr Leboo Ole Morintat AG, County Secretary Nairobi City County P.O Box Nairobi. 30 th November 2017, Dear Mr. Mr Leboo Ole Morintat AG, County Secretary Nairobi City County P.O Box 30075-00100 Nairobi 30 th November 2017, Dear Mr. Morintat, RE: MEMORANDUM ON THE DRAFT COUNTY INTEGRATED DEVELOPMENT PLAN 2018-2022

More information

CONDITIONS OF SERVICE Algoma Power Inc. Conditions of Service Proposed Effective February 15, /9/2019

CONDITIONS OF SERVICE Algoma Power Inc. Conditions of Service Proposed Effective February 15, /9/2019 CONDITIONS OF SERVICE 2019 1/9/2019 Algoma Power Inc Conditions of Service Proposed Effective February 15, 2019 PREFACE The Distribution System Code (DSC) requires that each distributor produce a Conditions

More information

On behalf of the Board of Directors, it is my pleasure and privilege to extend a very warm welcome to all of you to this 26th Annual General Meeting.

On behalf of the Board of Directors, it is my pleasure and privilege to extend a very warm welcome to all of you to this 26th Annual General Meeting. Chairman's Speech for the 26 th Annual General Meeting of Kirloskar Ferrous Industries Limited on 3 rd August, 2017. Welcome Good morning Ladies and Gentlemen On behalf of the Board of Directors, it is

More information

RE: PROPOSED MANAWATU DISTRICT PLAN CHANGE 55 HEARINGS

RE: PROPOSED MANAWATU DISTRICT PLAN CHANGE 55 HEARINGS 30 November 2016 File: 13/134 DDI: 09 917 4305 Email: kblair@burtonconsultants.co.nz Manawatu District Council Private Bag 10 001 FEILDING 4743 Attention: Hearing Committee: Plan Change 55 By email only:

More information

MEMBERS PRESENT: M. Aubrey D. Pritchard S. Bonnett T. Mitchell R. Govenlock D. Keylor

MEMBERS PRESENT: M. Aubrey D. Pritchard S. Bonnett T. Mitchell R. Govenlock D. Keylor MINUTES MUNICIPAL PLANNING COMMISSION WOODLANDS COUNTY June 17, 2015 A meeting of the Woodlands County Municipal Planning Commission was held Wednesday, June 17, 2015 at the Woodlands County Regional Municipal

More information

DISCUSSION PAPER DECISION-MAKING ROLES ON PROJECTS

DISCUSSION PAPER DECISION-MAKING ROLES ON PROJECTS DISCUSSION PAPER DECISION-MAKING ROLES ON PROJECTS TOPIC: Roles and responsibilities for making decisions under the National Energy Board Act (NEB Act). CONTEXT: In 2012, there were legislative amendments

More information

MAIN CIVIL WORKS CONTRACT SCHEDULE 12 CHANGES TABLE OF CONTENTS

MAIN CIVIL WORKS CONTRACT SCHEDULE 12 CHANGES TABLE OF CONTENTS MAIN CIVIL WORKS CONTRACT SCHEDULE 12 CHANGES TABLE OF CONTENTS 1 INTERPRETATION... 1 1.1 Definitions... 1 2 CHANGES... 1 2.1 BC Hydro s Right to Require Changes... 1 2.2 Restrictions on Changes... 1 2.3

More information

REQUEST FOR QUOTATION (RFQ) Sidewalk Trip Hazard Remediation Concrete Sidewalk Shaving

REQUEST FOR QUOTATION (RFQ) Sidewalk Trip Hazard Remediation Concrete Sidewalk Shaving REQUEST FOR QUOTATION (RFQ) Sidewalk Trip Hazard Remediation Concrete Sidewalk Shaving A. INTRODUCTION The is accepting quotations for the remediation of concrete sidewalks in Kindersley, Saskatchewan.

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Date ISDS Prepared/Updated: 29-Jan-2013

More information

Section III Evaluation and Qualification Criteria (Revision 1)

Section III Evaluation and Qualification Criteria (Revision 1) Section III Evaluation and Qualification (Revision 1) Section III. Evaluation and Qualification This Section contains all the criteria that the Employer shall use to evaluate bids and qualify Bidders.

More information

LICENCE AGREEMENT. For a Holiday Home at. Old Park Wood

LICENCE AGREEMENT. For a Holiday Home at. Old Park Wood LICENCE AGREEMENT For a Holiday Home at Old Park Wood LICENCE AGREEMENT OF A HOLIDAY HOME PITCH AND CARAVAN/LODGE AT OLD PARK WOOD Part I - Particulars PARK OWNER (referred to as we/us/our throughout this

More information

INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE . Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Date ISDSPrepared/Updated: Date ISDS Approved/Disclosed I. BASIC INFORMATION 1. Basic

More information

REQUEST FOR PROPOSALS FOR BID TOWN OF MIDDLESEX, VERMONT TROPICAL STROM IRENE FEDERAL BUYOUT DEMOLITIONS

REQUEST FOR PROPOSALS FOR BID TOWN OF MIDDLESEX, VERMONT TROPICAL STROM IRENE FEDERAL BUYOUT DEMOLITIONS REQUEST FOR PROPOSALS FOR BID TOWN OF MIDDLESEX, VERMONT TROPICAL STROM IRENE FEDERAL BUYOUT DEMOLITIONS Contact: Sarah Merriman Town Clerk/Select Board Assistant Town of Middlesex 5 Church Street Middlesex,

More information

ARKANSAS PUBLIC SERVICE COMMISSION

ARKANSAS PUBLIC SERVICE COMMISSION 2 nd Revised Sheet No. 61.0.1 Schedule Sheet 1 of 18 Replacing: 1 st Revised Sheet No. 61.0.1 61.0. TARIFF GOVERNING THE INSTALLATION OF ELECTRIC UNDERGROUND RESIDENTIAL DISTRIBUTION SYSTEMS AND UNDERGROUND

More information

Dispute Resolution in Construction Projects in Gaza Strip: Practical Case Studies

Dispute Resolution in Construction Projects in Gaza Strip: Practical Case Studies Dispute Resolution in Construction Projects in Gaza Strip: Practical Case Studies A. Enshassi 1 and B. Thabet 2 1 School of Civil Engineering, IUG, Palestine. enshassi@mail.iugaza.edu 2 Palestine Industrial

More information

DESIGN BUILD PARKING LOT AND MODULAR FACILITY FOR LYNX PARATRANSIT OPERATIONS (LOC EXPANSION) RFP 18-R01 ADDENDUM NUMBER ONE (1) August 3, 2018

DESIGN BUILD PARKING LOT AND MODULAR FACILITY FOR LYNX PARATRANSIT OPERATIONS (LOC EXPANSION) RFP 18-R01 ADDENDUM NUMBER ONE (1) August 3, 2018 Clarification: DESIGN BUILD PARKING LOT AND MODULAR FACILITY FOR LYNX PARATRANSIT OPERATIONS (LOC EXPANSION) RFP 18-R01 ADDENDUM NUMBER ONE (1) August 3, 2018 Proposers may submit clarifying questions

More information

REPUBLIC OF KENYA IN THE NATIONAL ENVIRONMENT TRIBUNAL AT NAIROBI TRIBUNAL APPEAL NO. NET/05/2005 OF A.T. KAMINCHIA..APPELLANT VERSUS RULING

REPUBLIC OF KENYA IN THE NATIONAL ENVIRONMENT TRIBUNAL AT NAIROBI TRIBUNAL APPEAL NO. NET/05/2005 OF A.T. KAMINCHIA..APPELLANT VERSUS RULING REPUBLIC OF KENYA IN THE NATIONAL ENVIRONMENT TRIBUNAL AT NAIROBI TRIBUNAL APPEAL NO. NET/05/2005 OF 2005 1. A.T. KAMINCHIA..APPELLANT VERSUS 1. NATIONA ENVIRONMENT MANAGEMENT AUTHORITY.1 ST RESPONDENT

More information

6.0 MONITORING AND CONTINGENCY PLANS

6.0 MONITORING AND CONTINGENCY PLANS 6.0 MONITORING AND CONTINGENCY PLANS 6.1 MONITORING The primary objective of compliance and effects monitoring is to confirm whether mitigation and protective measures are effectively implemented and to

More information

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF TRANSMISSION GRID STRENGTHENING PROJECT LOAN

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF TRANSMISSION GRID STRENGTHENING PROJECT LOAN Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY Report No: RES22644 Public Disclosure Authorized Public Disclosure Authorized RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING

More information

Transmission Cost Allocation Methodology and Distribution Cost Allocation Method. As approved by AER

Transmission Cost Allocation Methodology and Distribution Cost Allocation Method. As approved by AER Transmission Cost Allocation Methodology and Distribution Cost Allocation Method As approved by AER June 2015 Tasmanian Networks Pty Ltd ABN 24 167 357 299 PO Box 606 Moonah TAS 7009 Enquiries regarding

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Date ISDS Prepared/Updated: 21-Aug-2013

More information

Area : sq. mtrs. (Tentative) C Rate : Rs. 1650/- per sq.mt. D. Allotment Price : Rs. /- F. Total : (D + E) : Rs. /-

Area : sq. mtrs. (Tentative) C Rate : Rs. 1650/- per sq.mt. D. Allotment Price : Rs. /- F. Total : (D + E) : Rs. /- Date : No. Sub: Offer-cum-Allotment letter for plot of land in Dahej SEZ Ref: 1. Your application dated 2. DSL s Provisional Offer letter dated 3. LoA issued by DC vide No. dated Dear Sir, With reference

More information

School Lettings Policy

School Lettings Policy School Lettings Policy Responsibility: Finance, Premises and Health & Safety Sub-Committee of the Board of Governors Approval Date: December 2015 Review Date: July 2017 Status: Live Table of Contents Rationale...

More information

ROCKLAND ELECTRIC COMPANY B.P.U. NO. 3 - ELECTRICITY. 1st Revised Leaf No. 18 Superseding Original Leaf No. 18 GENERAL INFORMATION

ROCKLAND ELECTRIC COMPANY B.P.U. NO. 3 - ELECTRICITY. 1st Revised Leaf No. 18 Superseding Original Leaf No. 18 GENERAL INFORMATION 1st Revised Leaf No. 18 Superseding Original Leaf No. 18 No. 15 IDENTIFICATION OF EMPLOYEES Company employees or agents authorized to enter upon its customers premises are provided with photo identification

More information

Service Schedule ADSL & FTTC December 2016

Service Schedule ADSL & FTTC December 2016 Service Schedule ADSL & FTTC December 2016 1 DEFINITIONS AND INTERPRETATIONS 1.1 Words or phrases used with capital letters in this Service Schedule shall have the same meanings given in the Master Services

More information

Guideline Scope of Services and Tariff of Fees for Persons Registered in terms of the Engineering Profession Act, 2000, (Act No.

Guideline Scope of Services and Tariff of Fees for Persons Registered in terms of the Engineering Profession Act, 2000, (Act No. Page 1 BOARD NOTICE 30 OF 2007 Engineering Council of South Africa Guideline Scope of Services and Tariff of Fees for Persons Registered in terms of the Engineering Profession Act, 2000, (Act No.46 of

More information

Electric Price Outlook for Indiana Low Load Factor (LLF) customers December 2016

Electric Price Outlook for Indiana Low Load Factor (LLF) customers December 2016 Electric Price Outlook for Indiana Low Load Factor (LLF) customers December 2016 Price projection We project our prices for Low Load Factor customers to increase 4 to 6 percent in 2017 compared to 2016.

More information

VIE: Power Transmission Investment Program, Tranche 1 220kV Phu My Industrial Zone Substation and 220kV Song May-Uyen Hung Transmission Line

VIE: Power Transmission Investment Program, Tranche 1 220kV Phu My Industrial Zone Substation and 220kV Song May-Uyen Hung Transmission Line Social Monitoring Report Semestral Report July to December 2014 VIE: Power Transmission Investment Program, Tranche 1 220kV Phu My Industrial Zone Substation and 220kV Song May-Uyen Hung Transmission Line

More information

OHIO DEPARTMENT OF TRANSPORTATION OFFICE OF REAL ESTATE

OHIO DEPARTMENT OF TRANSPORTATION OFFICE OF REAL ESTATE DATE: July 1, 2015 OHIO DEPARTMENT OF TRANSPORTATION OFFICE OF REAL ESTATE TO: FROM: Users of the Real Estate Manual (Permits) Wendi Snyder, Utility & Railroad Program Manager RE: Changes and Updates to

More information

Electric Price Outlook for Indiana High Load Factor (HLF) customers December 2016

Electric Price Outlook for Indiana High Load Factor (HLF) customers December 2016 Electric Price Outlook for Indiana High Load Factor (HLF) customers December 2016 Price projection We project our prices for High Load Factor customers to increase 4 to 6 percent in 2017 compared to 2016.

More information

TERMS OF REFERENCE TULINDE TUSOME PROJECT IN KILIFI AND KWALE, KENYA ENVIRONMENTAL IMPACT ASSESSMENT. Programme department, Plan International Kenya

TERMS OF REFERENCE TULINDE TUSOME PROJECT IN KILIFI AND KWALE, KENYA ENVIRONMENTAL IMPACT ASSESSMENT. Programme department, Plan International Kenya TERMS OF REFERENCE TULINDE TUSOME PROJECT IN KILIFI AND KWALE, KENYA ENVIRONMENTAL IMPACT ASSESSMENT Project Name Tulinde Tusome Start date of the Action 08/02/2016 End date of the Action 11/03/2016 Contracting

More information

Muskrat Falls Project Oversight Committee

Muskrat Falls Project Oversight Committee Muskrat Falls Project Oversight Committee Quarterly Project Update Period Ending December 31, 2017 February 12, 2018 Table of Contents 1. Total Project Summary as of December 31, 2017 2. 2017 Performance

More information

Cost Estimation for Regional Transmission Overlay Study (RTOS)

Cost Estimation for Regional Transmission Overlay Study (RTOS) Cost Estimation for Regional Transmission Overlay Study (RTOS) Purpose & Key Takeaways Purpose: To provide detail for MISO s cost estimation approach Key Takeaways: Planning-Level and Scoping-Level MISO

More information

RULE H NEW SERVICE ATTACHMENTS AND DISTRIBUTION LINE INSTALLATIONS OR ALTERATIONS

RULE H NEW SERVICE ATTACHMENTS AND DISTRIBUTION LINE INSTALLATIONS OR ALTERATIONS Idaho Power Company First Revised Sheet No. H-1 I.P.U.C. No. 29, Tariff No. 101 Original Sheet No. H-1 This rule applies to requests for electric service under Schedules 1, 3, 4, 5, 7, 9, 19, 24, 45, and

More information

REGIONAL EVALUATION FRAMEWORK 1.0 INTRODUCTION 2.0 PURPOSE 3.0 DEFINITIONS. Edmonton Metropolitan Region Planning Toolkit

REGIONAL EVALUATION FRAMEWORK 1.0 INTRODUCTION 2.0 PURPOSE 3.0 DEFINITIONS. Edmonton Metropolitan Region Planning Toolkit Edmonton Metropolitan Region Planning Toolkit Re-imagine. Plan. Build. Edmonton Metropolitan Region Growth Plan 1.0 INTRODUCTION On October 26, 2017, the Government of Alberta approved the Edmonton Metropolitan

More information

Vidarbha Industries Power Limited - Transmission

Vidarbha Industries Power Limited - Transmission Vidarbha Industries Power Limited - Transmission Revised Petition towards: Approval of Capital Cost and Determination of Aggregate Revenue Requirement ( ARR ) for the period FY 14-15 to FY 15-16 Filed

More information

ROCKY MOUNTAIN POWER First Revision of Sheet No. R12-1 Canceling Original Sheet No. R12-1

ROCKY MOUNTAIN POWER First Revision of Sheet No. R12-1 Canceling Original Sheet No. R12-1 First Revision of Sheet No. R12-1 Canceling Original Sheet No. R12-1 I. - Conditions and Definitions A. Contracts Before building an Extension, the Company may require the Applicant to sign a contract.

More information

Corridor Management Committee. May 6, 2015

Corridor Management Committee. May 6, 2015 Corridor Management Committee May 6, 2015 1 Today s Topics Project Budget and Schedule Update Project Options Work Plan Upcoming Meeting Schedule 2 Project Budget and Schedule Update 3 Project Updates:

More information

6 Report No.: JSDSC1361 1

6 Report No.: JSDSC1361 1 Public Disclosure Authorized INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE 6 Report No.: JSDSC1361 1,2 Date ISDS Prepared/Updated: 05-Nov-2015 Date ISDS Approved/Disclosed: 06-Nov-2015 Public Disclosure

More information

KANSAS CITY POWER & LIGHT COMPANY P.S.C. MO. No. 2 Fourth Revised Sheet No Canceling P.S.C. MO. No. 2 Third Revised Sheet No. 1.

KANSAS CITY POWER & LIGHT COMPANY P.S.C. MO. No. 2 Fourth Revised Sheet No Canceling P.S.C. MO. No. 2 Third Revised Sheet No. 1. P.S.C. MO. No. 2 Fourth Revised 1.30 2 Third Revised 1.30 9. EXTENSION OF FACILITIES SECTIONS 9.01 THROUGH 9.11 SHALL BE APPLICABLE TO FACILITY EXTENSION AGREEMENTS EXECUTED ON AND AFTER JANUARY 1, 2018.

More information

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB3202 Project Name. Kenya Nairobi Urban Toll Road PRG Region

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB3202 Project Name. Kenya Nairobi Urban Toll Road PRG Region Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB3202 Project Name Kenya

More information

Fiscal Year Budget

Fiscal Year Budget Fiscal Year 2019 Budget Fiscal Year 2019 Project 3 Annual Budget Project 3 Fiscal Year 2019 Table of Contents Table Page Summary 3 Summary of Costs Table 1 4 Summary of Full Time Equivalent Table 2 5 Positions

More information

DEPARTMENT OF ENVIRONMENTAL PROTECTION Policy Office

DEPARTMENT OF ENVIRONMENTAL PROTECTION Policy Office DEPARTMENT OF ENVIRONMENTAL PROTECTION Policy Office DOCUMENT NUMBER: 012-4180-001 TITLE: Policy for the Consideration of Community Environmental Projects in Conjunction with Assessment of Civil Penalty

More information

COUNTY GOVERNMENT OF KIAMBU

COUNTY GOVERNMENT OF KIAMBU COUNTY GOVERNMENT OF KIAMBU TENDER NAME: CONSTRUCTION AND REHABILITATION OF KIMENDE GITITHIA ROAD ( 2 KM)-KIJABE WARD, LARI SUB COUNTY. TENDER NO : CGK/RTPW&U/RMLF/003/2016-2017 NAME OF BIDDER: DATE :

More information

TERMS AND CONDITIONS OF SALE ACN: ABN:

TERMS AND CONDITIONS OF SALE ACN: ABN: TERMS AND CONDITIONS OF SALE ACN: 169 441 383 ABN: 28 169 441 383 OFFER TO SUPPLY / QUOTATION VALIDITY Our offer is valid for a period of 30 days from the date of quotation. Notwithstanding; the details

More information

VIE: Power Transmission Investment Program, Tranche 2 220kV Cau Bong-Hoc Mon-Binh Tan Transmission Line

VIE: Power Transmission Investment Program, Tranche 2 220kV Cau Bong-Hoc Mon-Binh Tan Transmission Line Social Monitoring Report Semi Annual Report January June 2016 VIE: Power Transmission Investment Program, Tranche 2 220kV Cau Bong-Hoc Mon-Binh Tan Transmission Line Prepared by the Southern Vietnam Power

More information

2018 BUDGET AND FINANCIAL PLAN

2018 BUDGET AND FINANCIAL PLAN Questionnaire 2018 BUDGET AND FINANCIAL PLAN January 1, 2018 - January 23, 2018 The Township of Langley is reviewing the Draft 2018 2022 Five-Year Financial Plan with emphasis on the 2018 Budget. Your

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Public Disclosure Authorized INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Date ISDS Prepared/Updated: 22-Apr-2015 Report No.: ISDSC8904 Date ISDS Approved/Disclosed: 27-Apr-2015 Public Disclosure Authorized

More information

PREQUALIFICATION QUESTIONNAIRE

PREQUALIFICATION QUESTIONNAIRE PREUALIFICATION UESTIONNAIRE 1.0 COMPANY DETAILS 1.1 Please complete the company details below: Company: Post Code: Tel: E-mail Contact: Title: CRN: Fax: Website: 1.2 Does this Company have a Parent Company

More information

Content Copy Of Original

Content Copy Of Original Content Copy Of Original Ministry of the Environment and Climate Change Ministère de l Environnement et de l Action en matière de changement climatique Halton Crushed Stone Limited 85 Passmore Avenue P.O.

More information

Muskrat Falls Project Oversight Committee

Muskrat Falls Project Oversight Committee Muskrat Falls Project Oversight Committee Quarterly Department Report Name Period Ending September 30, 2017 November 3, 2017 Table of Contents 1. September Project Summary 2. Oversight Committee Reporting

More information

Wanganui - Stratford Investment Proposal. Attachment B Costing report

Wanganui - Stratford Investment Proposal. Attachment B Costing report Wanganui - Stratford Investment Proposal Attachment B Costing report September 2009 Document Revision Control Document Number/Version Description Date 001/ A Wanganui-Stratford Investment Proposal Attachment

More information

Osprey House, Tuesday 30 September 2014

Osprey House, Tuesday 30 September 2014 Osprey House, Tuesday 30 September 2014 Cautionary statement This presentation contains certain statements that are neither reported financial results nor other historical information. These statements

More information

Main Laws and Regulations for Foreign Investment in China Foreign investments in China are subject to a series of laws and regulations.

Main Laws and Regulations for Foreign Investment in China Foreign investments in China are subject to a series of laws and regulations. Setting up Business Easier Than It Looks Foreign investors can now determine an organizational structure according to the operations of their enterprises at their own discretion. Foreigners intending to

More information

Assessing and Dealing with Environmental Liabilities of Local Governments. LGANT 2014 Dennis Kefalas, P. Eng. SAO City of Yellowknife

Assessing and Dealing with Environmental Liabilities of Local Governments. LGANT 2014 Dennis Kefalas, P. Eng. SAO City of Yellowknife Assessing and Dealing with Environmental Liabilities of Local Governments LGANT 2014 Dennis Kefalas, P. Eng. SAO City of Yellowknife Overview Obligations Environmental Liabilities Landfill Closure and

More information

Attachment C New York State Energy Research and Development Authority ( NYSERDA ) AGREEMENT

Attachment C New York State Energy Research and Development Authority ( NYSERDA ) AGREEMENT Attachment C New York State Energy Research and Development Authority ( NYSERDA ) 1. Agreement Number: 2. Subgrantee: 3. Project Contact: 4. Effective Date: _/ /2016 5. Total Amount of Award: $ 6. Project

More information

GENERAL CONDITIONS FOR THE SUPPLY OF WORKS

GENERAL CONDITIONS FOR THE SUPPLY OF WORKS VDP_ZoD/2014 GENERAL CONDITIONS FOR THE SUPPLY OF WORKS PREAMBLE 1. These General Conditions (hereinafter referred to as VDP_ZoD ) regulate the conditions in performing a Works between the company ABB,

More information

Peter Farrer welcomed everyone to the meeting and introduced key SW representatives.

Peter Farrer welcomed everyone to the meeting and introduced key SW representatives. Note of Bathgate Public Meeting 6.3.16 Peter Farrer welcomed everyone to the meeting and introduced key SW representatives. Mark McEwen ran through the actions arising from the previous meeting. It was

More information

CONNECTION OF OFFSHORE WIND ONSHORE -- Some Food for Thought to Aid the Discussion at the Post-Conference Workshop

CONNECTION OF OFFSHORE WIND ONSHORE -- Some Food for Thought to Aid the Discussion at the Post-Conference Workshop Deeper Water Offshore Wind Conference by GIC CONNECTION OF OFFSHORE WIND ONSHORE -- Some Food for Thought to Aid the Discussion at the Post-Conference Workshop Dr Chuan Zhang The Crown Estate, UK London,

More information