Re: Rockland Electric Company, Docket No. EL18-111

Size: px
Start display at page:

Download "Re: Rockland Electric Company, Docket No. EL18-111"

Transcription

1 Margaret Comes Associate Counsel Rockland Electric Company 4 Irving Place, Room 1815-S, New York, NY Tel.: comesm@coned.com May 14, 2018 Hon. Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C Dear Ms. Bose: Re: Rockland Electric Company, Docket No. EL Pursuant to the Commission s Order to Show Cause ( OSC ) of March 15, 2018, 1 Rockland Electric Company ( RECO ) submits this proposed revision to its stated transmission rate and revenue requirement to reflect the recent change in the federal corporate income tax rate ( Filing ). 2 Included in this Filing are the following: this Cover Letter; Attachment A Marked Tariffs; Attachment B Clean Tariffs; and, Attachment C - Prepared Direct Accounting Panel Testimony with supporting exhibits RECO-1 and RECO-2. In support of this filing, RECO submits the testimony and associated exhibits of the accounting panel of John de la Bastide and Wenqi Wang, ( Accounting Panel ). 3 I. BACKGROUND A. Description of RECO and its Affiliates RECO is an electric-only utility that provides transmission, retail distribution, and provider of last resort service to approximately 73,000 customers in northern New Jersey. As a New Jersey utility, RECO is subject to the retail jurisdiction of the New Jersey Board of Public Utilities. RECO s service territory includes parts of three counties that border New York Bergen, Passaic, and Sussex but the majority of its customers (more than 59,000) reside in Bergen County. RECO classifies its Bergen County service territory as its Eastern Division, its Passaic County service territory as its Central FERC 61,224 (2018) ( OSC ). 2 Pursuant to Order 714, this Filing is being submitted by PJM Interconnection, LLC ( PJM ) on behalf of RECO as part of an XML filing package that conforms with the Commission s regulations. PJM has agreed to make all filings on behalf of PJM Transmission Owners in order to retain administrative control over the PJM Tariff. Thus, RECO has requested PJM submit these amendments to Attachment H-12 and Schedules 7 and 8 in the Etariff system as part of PJM s electronic Intra PJM Tariff. 3 See Attachment C.

2 Kimberly D. Bose May 14, 2018 Page 2 Division, and its Sussex County service territory as its Western Division. As discussed below, RECO is a PJM transmission owner because it has turned over operational control of its Eastern Division transmission assets to PJM. RECO s Central and Western Divisions, which are not geographically contiguous to its PJM service area, along with Orange and Rockland Utilities, Inc. ( O&R ), are members of the New York Independent System Operator, Inc. ( NYISO ). RECO is a wholly owned subsidiary of O&R, 4 which in turn is a wholly owned subsidiary of Consolidated Edison, Inc. ( CEI ), the parent company of Consolidated Edison Company of New York, Inc. ( Con Edison ). 5 O&R is an electric and gas utility and a transmission owner in the NYISO s control area. O&R serves more than 225,000 electric customers and more than 130,000 gas customers in three New York counties: Rockland, Orange, and Sullivan. Two of these counties, Rockland and Orange, border RECO s service territory. In 2015, O&R s peak load was 1009 MW. RECO has no operating employees; O&R provides all of RECO s administrative and operating services. Legal and other corporate services are provided to RECO by Con Edison. In addition, since the RECO and O&R transmission systems have historically been operated as a single system, O&R continues to design and operate them as a single integrated system ( Integrated Transmission System ) from its control center in Spring Valley, New York. In 2015, the peak load of the Integrated Transmission System was 1405 MW. B. RECO s 2017 Transmission Rate Filing On January 26, 2017, pursuant to section 205 of the Federal Power Act, RECO submitted tariff revisions ( 2017 Rate Filing ) proposing to update its stated annual transmission revenue requirement ( ATRR ) and transmission rates. The Staff of the New Jersey Board of Public Utilities ( NJBPU ) intervened and the New Jersey Division of Rate Counsel ( NJ Rate Counsel ) protested various aspects of RECO s Rate Filing. The Parties and Trial Staff were able to reach a negotiated resolution of the proceeding resulting in a black box Settlement Agreement. On September 6, 2017, RECO submitted an Offer of Settlement, which included the Settlement Agreement, and the Offer of Settlement was approved by the Commission on November 29, RECO s Compliance Filing with revised tariff sheets was accepted by the Commission on March 30, O&R also owned Pike County Light & Power Company, an electric and gas utility located in Pennsylvania until Con Edison is a regulated public utility that provides electric service in New York City and most of Westchester County, gas service in parts of New York City, and steam service within the borough of Manhattan. Con Edison serves approximately 3.3 million electric customers, 1.1 million gas customers, and 1,700 steam customers. Con Edison is a transmission owner in the NYISO s control area, a load serving entity, and a distribution provider in New York City and parts of Westchester County. 6 Letter Order, ER and -002 (November 29, 2017). 7 Letter Order, ER and -002 (March 30, 2018).

3 Kimberly D. Bose May 14, 2018 Page 3 As a result of the 2017 Rate Filing and Settlement Agreement, and as reflected in Attachment H-12 of the PJM Open-Access Transmission Tariff ("PJM OATT"), RECO s annual transmission revenue requirement ( TRR ) currently is $17,724,263 and its TRR rate currently is $ 44,799/MW per year. II. RECO S PROPOSED REDUCED TRANSMISSION REVENUE REQUIREMENT AND RATES To reflect the reduction in the federal corporate tax rate, the Company is proposing a decrease increase in: (a) the Attachment H-12 transmission revenue requirement ( TRR ) from $17,724,263 to $16,833,707 and (b) the Network Integration Transmission Service rate from $44,799 per megawatt per year to $42,458 per megawatt per year. As explained in more detail by the Accounting Panel, the Company is using the same methodology used in its 2017 Rate Filing. The Company started with the TRR of $19,661,232 that was proposed in its 2017 Rate Filing, which included $2,016,186 related to income taxes. The Company then adjusted the TRR for known and assumed components of the final black box settlement. The resulting change in revenue requirement requires a change in Schedules 7 and 8 of the PJM OATT, which are included in this filing. III. EFFECTIVE DATE RECO understands from its reading of the OSC that the Commission will set the effective date of the new transmission rates, and therefore, RECO has not included an effective date in the Filing. IV. SERVICE PJM has served a copy of this filing on all PJM Members and on all state utility regulatory commissions in the PJM Region by posting this filing electronically. In accordance with the Commission s regulations, 8 PJM will post a copy of this filing to the FERC filings section of its internet site, located at the following link: with a specific link to the newly-filed document, and will send an on the same date as this filing to all PJM Members and all state utility regulatory commissions in the PJM Region 9 alerting them that this filing has been made by PJM and is available by following such link. If the document is not immediately available by using the referenced link, the document will be available through the referenced link within 24 hours of the filing. Also, a copy of this filing will be available on the Commission s elibrary website located at the following 8 See 18 C.F.R 35.2(e) and (f)(3). 9 PJM already maintains, updates, and regularly uses lists for all PJM members and affected state commissions.

4 Kimberly D. Bose May 14, 2018 Page 4 link: in accordance with the Commission s regulations and Order No V. CORRESPONDENCE AND COMMUNICATIONS RECO requests that all correspondence and communications with respect to this filing be sent to, and the Secretary include on the official service list, the following persons: John de la Bastide Margaret Comes Director Financial Services Law Department Orange and Rockland Utilities, Inc. Consolidated Edison 1 Blue Hill Plaza Company of New York, Inc. Pearl River, NY Irving Place Room 1815-S (845) (212) delabastidej@oru.com comesm@coned.com VI. REQUEST FOR WAIVERS RECO requests that the Commission waive the requirements of 18 C.F.R to the extent necessary to accept this filing. Finally, RECO requests a waiver of any other Commission rule or regulation as may be necessary to permit the proposed Tariff revisions to be accepted by the Commission and made effective as requested. VII. CONCLUSION For the reasons discussed above and in the attached testimony, RECO respectfully requests that the Commission approve the following: RECO s proposed decrease in the Attachment H-12 transmission revenue requirement ( TRR ) from $17,724,263 to $16,833,707: the Network Integration Transmission Service rate from $44,799 per megawatt per year to $42,458 per megawatt per year; and, the Attachment H-12, Schedule 7, and Schedule 8 Tariff sheets included in this filing. Dated: May 14, 2018 New York, New York Respectfully submitted, ROCKLAND ELECTRIC COMPANY /s/ Margaret Comes Associate Counsel

5 CERTIFICATE OF SERVICE I hereby certify that I have this day served the foregoing document on the official service list compiled by the Secretary in this proceeding. Dated at New York, New York this 14th day of May, /s/ Margaret Comes

6 Attachment A Marked Tariffs

7 SCHEDULE 7 Long-Term Firm and Short-Term Firm Point-To-Point Transmission Service 1) The Transmission Customer shall pay each month for Reserved Capacity at the sum of the applicable charges set forth below for the Point of Delivery: Summary of Charges (in $/kw) Point of Delivery Yearly Charge Monthly Charge Weekly Charge Daily On-Peak 1 Charge Daily Off-Peak 2/ Charge Border of PJM AE Zone BG&E Zone Delmarva Zone JCPL Zone MetEd Zone Penelec Zone PECO Zone PPL Zone: Total charge is the sum of the components PPL: * AEC: UGI: * PPL: * AEC: UGI: * PPL: * AEC: UGI: * PPL: * AEC: UGI: * PPL: * AEC: UGI: * Pepco Zone PSE&G Zone AP Zone Rockland Zone / 4/ ComEd Zone * PPL Electric Utilities Corporation s and UGI Utilities respective component of the total charge is posted on the PJM Internet website. Page 1

8 Point of Delivery Yearly Charge Monthly Charge AEP East Zone 5/ Monthly Charge X 12 Attachment H-14 Weekly Charge Daily On- Peak 1 Charge Daily Off- Peak 2/ Charge Yearly Charge / 52 Weekly Charge / 5 Weekly Charge / 7 Dayton Zone Duquesne Zone Dominion Zone 6/ ATSI Zone DEOK Zone EKPC Zone Attachment H-21 Attachment H-22 Attachment H-24 Attachment H-21 Attachment H-22 Attachment H-24 Attachment H-21 Attachment H-22 Attachment H-24 Attachment H-21 Attachment H-22 Attachment H-24 Attachment H-21 Attachment H-22 Attachment H-24 Effective December 1, 2004, the charge for Points of Delivery at the Border of PJM and the Transitional Revenue Neutrality Charge under this Schedule 7 shall not apply to any Reserved Capacity with a Point of Delivery of the Midwest Independent Transmission System Operator, Inc. obtained pursuant to requests submitted on or after November 17, 2003, for service commencing on or after April 1, Effective April 1, 2006, the charge for Points of Delivery at the Border of PJM and the Transitional Revenue Neutrality Charge under this Schedule 7 shall not apply to any Reserved Capacity with a Point of Delivery of the Midwest Independent Transmission System Operator, Inc. 1/ Monday Friday except the following holidays: New Years Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, and Christmas Day. 2/ Saturday and Sunday and the following holidays: New Years Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, and Christmas Day. 3/ Each month, revenue credits will be applied to the gross charge in accordance with section 8 below to determine the actual charge to the Transmission Customer. 4/ The charges for the ComEd zone are posted on PJM s website. In addition to other rates set forth in this schedule, customers within the ComEd zone shall be charged for recovery of RTO start-up costs at the following rates, each computed to four decimal places: Annual Rate - $/kw/year = $1,523,039, divided by the 1 CP demand for the ComEd zone for the prior calendar year; Monthly Rate - $/kw/month. = Annual Rate divided by 12; Weekly Rate - $/kw/week = Annual Rate divided by 52; Daily Rate - $/kw/day = Weekly Rate divided by 5. Page 2

9 In order to ensure that the charge does not result in either an over-recovery or under-recovery of ComEd s start-up costs, PJM will institute an annual true-up mechanism in the month of May of each of the years In May of each of those years, PJM will compare the amount collected under this charge for the previous 12 months with the target annual amount of $1,523,039 and calculate any credits or surcharges that would be needed to ensure that $1,523,039 is collected for each year. Any credit or surcharge will be assessed in the June bills for years , consistent with the above methodology. 5/ The rates for firm point-to-point transmission service in the AEP Zone will be charged at the yearly, monthly, weekly or daily rate equivalent to the rate effective in such period under Attachment H-14. In addition to other rates set forth in this schedule, customers within the AEP East Zone shall be charged for recovery of RTO start-up costs at the following rates, each computed to four decimal places: Annual Rate - $/kw/year = $2,362,185, plus any applicable true-up adjustment, divided by the 1 CP demand for the AEP East Zone for the prior calendar year; Monthly Rate - $/kw/month. = Annual Rate divided by 12; Weekly Rate - $/kw/week = Annual Rate divided by 52; Daily Rate - $/kw/day = Weekly Rate divided by 5. For the period November 1, 2005 through March 31, 2006, the rate shall be $8.94/MW-month; for the period April 1 through December 31, 2006, the rate shall be $8.60/MW-month, thereafter, the rate will be subject to the following true-up: In order to ensure that the charge does not result in either over-recovery or underrecovery of AEP s start-up costs, PJM will institute an annual true-up mechanism and implement revised charges as of January 1st of each of the years In January of each of those years, PJM will compare the amount collected under this charge for the previous year or part thereof with the target annual amount of $2,362,185 and calculate the rates that would be needed, given the expected billing demands, to collect $2,362,185, adjusted for any prior year over-collection or under-collection. In the final year that the rate is collected, PJM will calculate the rate to collect five-twelfths of the annual amount ($984,244), plus or minus any prior year true up amount, by May 31 of that year, and shall charge such rate until that amount is collected, whether that date be before or after May 31, / The service period charges rounded to four decimal places for the Dominion Zone are as follows: Page 3

10 Yearly Charge - $/kw/year = the formula rate for Network Integration Transmission Service as described in Attachment H-16 and Attachment H- 16A divided by 1000 kw/mw Monthly Charge - $/kw/month. = Yearly Charge divided by 12; Weekly Charge - $/kw/week = Yearly Charge divided by 52; Daily On-Peak Charge - $/kw/day = Weekly Charge divided by 5; Daily Off-Peak Charge - $/kw/day = Weekly Charge divided by 7. On a monthly basis, revenue credits shall be calculated based on the sum of VEPCO s share of revenues collected during the month from Schedule 7 and Network Integration Transmission Service to Non-Zone Network Load under Attachment H-A. The sum of these revenue credits will appear as an adjustment to the to the gross monthly service period charges produced by the above formula. 2) The total demand charge in any week, pursuant to a reservation for Daily On-Peak Delivery, or Daily Off-Peak Delivery shall not exceed the Weekly Delivery rate specified in section (1) above for weekly service times the highest amount in kilowatts of Reserved Capacity and any additional transmission service, if any, in any day during such week. 3) Discounts: Three principal requirements apply to discounts for transmission service as follows: (1) any offer of a discount made by the Transmission Provider must be announced to all Eligible Customers solely by posting on the OASIS, (2) any customer-initiated requests for discounts (including requests for use by one s wholesale merchant or an Affiliate s use) must occur solely by posting on the OASIS, and (3) once a discount is negotiated, details must be immediately posted on the OASIS. For any discount agreed upon for service on a path, from point(s) of receipt to point(s) of delivery, the Transmission Provider must offer the same discounted transmission service rate for the same time period to all Eligible Customers on all unconstrained transmission paths that go to the same point(s) of delivery on the Transmission System. 4) Congestion, Losses and Capacity Export: In addition to any payment under this Schedule, the Transmission Customer shall pay Redispatch Costs as specified in Section 27 of the Tariff. The Transmission Customer shall be responsible for losses as specified in the Tariff. Any Transmission Customer that is a Capacity Export Transmission Customer, shall pay any applicable charges, and receive any applicable credits, for such a customer pursuant to Attachment DD. 5) Other Supporting Facilities and Taxes: In addition to the rates set forth in section (1) of this schedule, the Transmission Customer shall pay charges determined on a case-by-case basis for facilities necessary to provide Transmission Service at voltages lower than those shown in Attachment H for the applicable Zone(s) and any amounts necessary to reimburse PJMSettlement for any amounts payable as sales, excise, Btu, carbon, value-added or similar Page 4

11 taxes (other than taxes based upon or measured by net income) with respect to the amounts payable pursuant to the Tariff. 6) Transitional Revenue Neutrality Charge: In addition to the rates set forth in section (1) of this schedule and any other applicable charges, the Transmission Customer shall also pay for Reserved Capacity for delivery at the border of the PJM Region a non-discountable charge of $3.60/kw/year, $0.30/kw/mo., $0.0692/kw/week, $0.0099/kw/day-off-peak, or $0.0138/kw/dayon-peak. PJM shall distribute all revenues from the Transitional Revenue Neutrality Charge to Allegheny Power. The charge provided for under this section (6) shall terminate effective as of the day on which the sum total of the revenues collected by this charge, the Transitional Revenue Neutrality Charge under Schedule 8, and the Transitional Market Expansion Charge under Schedule 11 equal $84,993,360. 7) Transmission Enhancement Charges. In addition to the rates set forth in Section (1) of this Schedule and any other applicable charges, the Transmission Customer shall also pay any Transmission Enhancement Charges for which it is designated as a Responsible Customer under Schedule 12 appended to the Tariff. 8) Determination of monthly charges for ComEd Zone: On a monthly basis, revenue credits shall be calculated based on the sum of ComEd s share of revenues collected during the month from: (i) the PJM Border Rate under Schedule 7; (ii) Network Integration Transmission Service to Non-Zone Network Load under Attachment H-A; (iii) Seams Elimination Charge/Cost Adjustment/Assignment ( SECA ) revenues allocable to ComEd under the Tariff; and (iv) any Point-To-Point Transmission Service where the Point of Receipt and the Point of Delivery are both internal to the ComEd Zone. On this basis, the sum of these revenues will appear as a reduction to the gross monthly rate stated above on a Transmission Customer s bill in that month for service under this schedule. 9) Determination of monthly charges for AEP Zone: On a monthly basis, revenue credits shall be calculated based on the sum of AEP s share of revenues collected during the month from: (i) the PJM Border Rate under Schedule 7; (ii) Network Integration Transmission Service to Non-Zone Network Load under Attachment H-A; and (iii) Firm Point-To-Point Transmission Service where the Point of Delivery is internal to the AEP Zone. The sum of these revenue credits will appear as an adjustment (reduction) to the gross monthly rate stated above on a Transmission Customer s bill in that month for service under this schedule. 10) Resales: The rates and rules governing charges and discounts stated above shall not apply to resales of transmission service, compensation for which shall be governed by section 23.1 of the Tariff. Page 5

12 SCHEDULE 8 Non-Firm Point-To-Point Transmission Service 1) The Transmission Customer shall pay for Non-Firm Point-To-Point Transmission Service up to the sum of the applicable charges set forth below for the Point of Delivery: Summary of Charges Point of Delivery Monthly Charge ($/kw) Weekly Charge ($/kw) Daily On- Peak 1/ Charge ($/kw) Daily Off- Peak 2/ Charge ($/kw) Hourly On-Peak 3/ Charge ($/MWh) Hourly Off- Peak 4/ Charge ($/MWh) Border of PJM AE Zone BG&E Zone Delmarva Zone JCPL Zone MetEd Zone Penelec Zone PECO Zone PPL Zone: Total charge is the sum of the components PPL: * AEC: UGI: * PPL: * AEC: UGI: * PPL: * AEC: UGI: * PPL: * AEC: UGI: * PPL: * AEC: 0.11 UGI: * PPL: * AEC: 0.05 UGI: * Pepco Zone PSE&G Zone AP Zone Rockland Zone / 6/ ComEd Zone * PPL Electric Utilities Corporation s and UGI Utilities respective component of the total charge is posted on the PJM Internet website. Page 6

13 AEP East Zone 7/ Nov. 1, 2005 AEP East Zone 7/ Attachment H-14 Monthly Charge X 12 / 52 Weekly Charge / 5 Weekly Charge / 7 Daily On- Peak Charge / 16 SECA Ended W-JF Line In Dayton Zone Dayton Zone Duquesne Zone Duquesne Zone Dominion Zone 8/ Dominion Zone 8/ ATSI Zone ATSI Zone Attachment H-21 Rate Pursuant to Attachment H-21 Attachment H-21 Rate Pursuant to Attachment H-21 Rate Pursuant to Attachment H-21 DEOK Zone DEOK Zone Attachment H-22 Attachment H-22 Attachment H-22 Rate Pursuant to Attachment H-22 Rate Pursuant to Attachment H-22 EKPC Zone EKPC Zone Attachment H-24 Attachment H-24 Attachment H-24 Rate Pursuant to Attachment H-24 Rate Pursuant to Attachment H-24 1/ Monday - Friday except the following holidays: New Years Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, and Christmas Day. 2/ Saturday and Sunday and the following holidays: New Years Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, and Christmas Day. 3/ 7:00 a.m. up to the hour ending 11:00 p.m. 4/ 11:00 p.m. up to the hour ending 7:00 a.m. 5/ Each month, revenue credits will be applied to the gross charge in accordance with Paragraph 9 below to determine the actual charge to the Transmission Customer. 6/ The charges for the ComEd zone are posted on PJM s website. In addition to the other rates set forth in this schedule, customers within the ComEd zone shall be charged for recovery of RTO start-up costs at the following rates, each computed to four decimal places: Annual Rate - $/kw/year = $1,523,039, divided by the 1 CP demand for the ComEd zone for the prior calendar year; Monthly Rate - $/kw/month. = Annual Rate divided by 12; Weekly Rate - $/kw/week = Annual Rate divided by 52; Daily rate - $/kw/day = Weekly Rate divided by 5. In order to ensure that the charge does not result in either an over-recovery or underrecovery of ComEd s start-up costs, PJM will institute an annual true-up mechanism in the month of May of each of the years In May of each of those years, PJM will compare the amount collected under this charge for the previous 12 months with the target annual amount of $1,523,039 and calculate any credits or surcharges that would be Page 7

14 needed to ensure that $1,523,039 is collected for each year. Any credit or surcharge will be assessed in the June bills for years , consistent with the above methodology. 7/ The rates for non-firm point-to-point transmission service in the AEP Zone will be charged at the monthly, weekly, daily or hourly rate equivalent to the rate effective in such period under Attachment H-14. In addition to other rates set forth in this schedule, customers within the AEP East Zone shall be charged for recovery of RTO start-up costs at the following rates, each computed to four decimal places: Annual Rate - $/kw/year = $2,362,185, plus any applicable true-up adjustment, divided by the 1 CP demand for the AEP East Zone for the prior calendar year; Monthly Rate - $/kw/month. = Annual Rate divided by 12; Weekly Rate - $/kw/week = Annual Rate divided by 52; Daily Rate - $/kw/day = Weekly Rate divided by 5. For the period November 1, 2005 through March 31, 2006, the rate shall be $8.94/MWmonth; for the period April 1 through December 31, 2006, the rate shall be $8.60/MWmonth, thereafter, the rate will be subject to the following true-up: In order to ensure that the charge does not result in either over-recovery or underrecovery of AEP s start-up costs, PJM will institute an annual true-up mechanism and implement revised charges as of January 1st of each of the years In January of each of those years, PJM will compare the amount collected under this charge for the previous year or part thereof with the target annual amount of $2,362,185 and calculate the rates that would be needed, given the expected billing demands, to collect $2,362,185, adjusted for any prior year over-collection or under-collection. In the final year that the rate is collected, PJM will calculate the rate to collect five-twelfths of the annual amount, ($984,244), plus or minus any prior year true up amount, by May 31 of that year, and shall charge such rate until that amount is collected, whether that date be before or after May 31, Effective December 1, 2004, the charge for Points of Delivery at the Border of PJM and the Transitional Revenue Neutrality Charge under this Schedule 8 shall not apply to any Reserved Capacity with a Point of Delivery of the Midwest Independent Transmission System Operator, Inc. obtained pursuant to requests submitted on or after November 17, 2003, for service commencing on or after April 1, Effective April 1, 2006, the charge for Points of Delivery at the Border of PJM and the Transitional Revenue Neutrality Charge under this Schedule 7 shall not apply to any Reserved Capacity with a Point of Delivery of the Midwest Independent Transmission System Operator, Inc. 8/ The service period charges rounded to four decimal places for the Dominion Zone are as follows: Page 8

15 Monthly Charge - $/kw/month = the formula rate for Network Integration Transmission Service as described in Attachment H-16 and Attachment H-16A divided by 12 divided by 1000 kw/mw; Weekly Charge - $/kw/week = 12 times Monthly Charge divided by 52; Daily On-Peak Charge - $/kw/day = Weekly Charge divided by 5; Daily Off-Peak Charge - $/kw/day = Weekly Charge divided by 7; Hourly On-Peak Charge - $/MWh = Daily On-Peak Charge / 16 hours *1000 kw/ MW; Hourly Off-Peak Charge - $/ MWh = Daily Off-Peak Charge / 24 hours *1000 kw/ MW. 2) The total demand charge in any week, pursuant to a reservation for Daily On-Peak Delivery or Daily Off-Peak Delivery, shall not exceed the Weekly Delivery rate specified in section (1) above for weekly service times the highest amount in kilowatts of Reserved Capacity and any additional transmission service, if any, in any day during such week. 3) Hourly delivery: The basic charge shall be that agreed upon by the Parties at the time this service is reserved and in no event shall exceed the amounts set forth above for a Point of Delivery. The total demand charge in any day, pursuant to a reservation for Hourly delivery, shall not exceed the rate specified in section (1) above for daily service times the highest amount in kilowatts of Reserved Capacity in any hour during such day. In addition, the total demand charge in any week, pursuant to a reservation for Hourly or Daily delivery, shall not exceed the rate specified in section (1) above for weekly service times the highest amount in kilowatts of Reserved Capacity in any hour during such week. 4) Discounts: Three principal requirements apply to discounts for transmission service as follows: (1) any offer of a discount made by the Transmission Provider must be announced to all Eligible Customers solely by posting on the OASIS, (2) any customer-initiated requests for discounts (including requests for use by one s wholesale merchant or an Affiliate s use) must occur solely by posting on OASIS, and (3) once a discount is negotiated, details must be immediately posted on the OASIS. For any discount agreed upon for service on a path, from point(s) of receipt to point(s) of delivery, the Transmission Provider must offer the same discounted transmission service rate for the same time period to all Eligible Customers on all unconstrained transmission paths that go to the same point(s) of delivery on the Transmission System. 5) Congestion, Losses and Capacity Export: A Transmission Customer desiring Non- Firm Point-to-Point Transmission Service may elect to pay transmission congestion charges. If the Transmission Customer so elects, it shall either (a) if the applicable Transmission Congestion Charge as calculated pursuant to Attachment K is positive, pay the higher of the applicable Transmission Congestion Charge or the applicable rate under section (1) above, or (b) if the Page 9

16 applicable Transmission Congestion Charge as calculated pursuant to Attachment K is negative, pay or be credited the sum of the applicable Transmission Congestion Charge and the rate under section (1) above. The Transmission Customer shall be responsible for losses as specified in the Tariff. Any Transmission Customer that is a Capacity Export Transmission Customer, shall pay for any applicable charges, and receive any applicable credits, for such a customer pursuant to Attachment DD. 6) Other Supporting Facilities and Taxes: In addition to the charges set forth in section (1) of this schedule, the Transmission Customer shall pay charges determined on a case-by-case basis for facilities necessary to provide Transmission Service at voltages lower than those shown in Attachment H for the applicable Zone(s) and any amounts necessary to reimburse the Transmission Provider for any amounts payable as sales, excise, Btu, carbon, value-added or similar taxes (other than taxes based upon or measured by net income) with respect to the amounts payable pursuant to the Tariff. 7) Transmission Enhancement Charges: In addition to the rates set forth in Section (1) of this Schedule and any other applicable charges, the Transmission Customer shall also pay any Transmission Enhancement Charges for which it is designated as a Responsible Customer under Schedule 12 appended to the Tariff. 8) Determination of monthly charges for ComEd Zone: On a monthly basis, revenue credits shall be calculated based on the sum of ComEd s share of revenues collected during the month from: (i) the PJM Border Rate under Schedule 7; (ii) Network Integration Transmission Service to Non-Zone Network Load under Attachment H-A; (iii) Seams Elimination Charge/Cost Adjustment/Assignment ( SECA ) revenues allocable to ComEd under the Tariff; and (iv) any Point-To-Point Transmission Service where the Point of Receipt and the Point of Delivery are both internal to the ComEd Zone. On this basis, the sum of these revenues will appear as a reduction to the gross monthly rate stated above on a Transmission Customer s bill in that month for service under this schedule. 9) Resales: The rates and rules governing charges and discounts stated above shall not apply to resales of transmission service, compensation for which shall be governed by section 23.1 of the Tariff. Page 10

17 ATTACHMENT H-12 Annual Transmission Rates -- Rockland Electric Company for Network Integration Transmission Service 1. The annual transmission revenue requirement is $17,724,26316,833,707 and the rate for Network Integration Transmission Service is $44,79942,548 per megawatt per year. 2. The rate stated in section 1 above shall be effective until amended by the Regional Transmission Owner(s) within the Zone or modified by the Commission. 3. In addition to the rate set forth in section 1 above, the Network Customer purchasing Network Integration Transmission Service shall pay for transmission congestion charges, in accordance with the provisions of the Tariff, and any amounts necessary to reimburse the Regional Transmission Owners for any amounts payable by them as sales, excise, Btu, carbon, value-added or similar taxes (other than taxes based upon or measured by net income) with respect to the amounts payable pursuant to the Tariff. Page 11

18 Attachment B Clean Tariff Records

19 SCHEDULE 7 Long-Term Firm and Short-Term Firm Point-To-Point Transmission Service 1) The Transmission Customer shall pay each month for Reserved Capacity at the sum of the applicable charges set forth below for the Point of Delivery: Summary of Charges (in $/kw) Point of Delivery Yearly Charge Monthly Charge Weekly Charge Daily On-Peak 1 Charge Daily Off-Peak 2/ Charge Border of PJM AE Zone BG&E Zone Delmarva Zone JCPL Zone MetEd Zone Penelec Zone PECO Zone PPL Zone: Total charge is the sum of the components PPL: * AEC: UGI: * PPL: * AEC: UGI: * PPL: * AEC: UGI: * PPL: * AEC: UGI: * PPL: * AEC: UGI: * Pepco Zone PSE&G Zone AP Zone Rockland Zone / 4/ ComEd Zone * PPL Electric Utilities Corporation s and UGI Utilities respective component of the total charge is posted on the PJM Internet website. Page 1

20 Point of Delivery Yearly Charge Monthly Charge AEP East Zone 5/ Monthly Charge X 12 Attachment H-14 Weekly Charge Daily On- Peak 1 Charge Daily Off- Peak 2/ Charge Yearly Charge / 52 Weekly Charge / 5 Weekly Charge / 7 Dayton Zone Duquesne Zone Dominion Zone 6/ ATSI Zone DEOK Zone EKPC Zone Attachment H-21 Attachment H-22 Attachment H-24 Attachment H-21 Attachment H-22 Attachment H-24 Attachment H-21 Attachment H-22 Attachment H-24 Attachment H-21 Attachment H-22 Attachment H-24 Attachment H-21 Attachment H-22 Attachment H-24 Effective December 1, 2004, the charge for Points of Delivery at the Border of PJM and the Transitional Revenue Neutrality Charge under this Schedule 7 shall not apply to any Reserved Capacity with a Point of Delivery of the Midwest Independent Transmission System Operator, Inc. obtained pursuant to requests submitted on or after November 17, 2003, for service commencing on or after April 1, Effective April 1, 2006, the charge for Points of Delivery at the Border of PJM and the Transitional Revenue Neutrality Charge under this Schedule 7 shall not apply to any Reserved Capacity with a Point of Delivery of the Midwest Independent Transmission System Operator, Inc. 1/ Monday Friday except the following holidays: New Years Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, and Christmas Day. 2/ Saturday and Sunday and the following holidays: New Years Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, and Christmas Day. 3/ Each month, revenue credits will be applied to the gross charge in accordance with section 8 below to determine the actual charge to the Transmission Customer. 4/ The charges for the ComEd zone are posted on PJM s website. In addition to other rates set forth in this schedule, customers within the ComEd zone shall be charged for recovery of RTO start-up costs at the following rates, each computed to four decimal places: Annual Rate - $/kw/year = $1,523,039, divided by the 1 CP demand for the ComEd zone for the prior calendar year; Monthly Rate - $/kw/month. = Annual Rate divided by 12; Weekly Rate - $/kw/week = Annual Rate divided by 52; Daily Rate - $/kw/day = Weekly Rate divided by 5. In order to ensure that the charge does not result in either an over-recovery or under-recovery of ComEd s start-up costs, PJM will institute an annual true-up Page 2

21 mechanism in the month of May of each of the years In May of each of those years, PJM will compare the amount collected under this charge for the previous 12 months with the target annual amount of $1,523,039 and calculate any credits or surcharges that would be needed to ensure that $1,523,039 is collected for each year. Any credit or surcharge will be assessed in the June bills for years , consistent with the above methodology. 5/ The rates for firm point-to-point transmission service in the AEP Zone will be charged at the yearly, monthly, weekly or daily rate equivalent to the rate effective in such period under Attachment H-14. In addition to other rates set forth in this schedule, customers within the AEP East Zone shall be charged for recovery of RTO start-up costs at the following rates, each computed to four decimal places: Annual Rate - $/kw/year = $2,362,185, plus any applicable true-up adjustment, divided by the 1 CP demand for the AEP East Zone for the prior calendar year; Monthly Rate - $/kw/month. = Annual Rate divided by 12; Weekly Rate - $/kw/week = Annual Rate divided by 52; Daily Rate - $/kw/day = Weekly Rate divided by 5. For the period November 1, 2005 through March 31, 2006, the rate shall be $8.94/MW-month; for the period April 1 through December 31, 2006, the rate shall be $8.60/MW-month, thereafter, the rate will be subject to the following true-up: In order to ensure that the charge does not result in either over-recovery or underrecovery of AEP s start-up costs, PJM will institute an annual true-up mechanism and implement revised charges as of January 1st of each of the years In January of each of those years, PJM will compare the amount collected under this charge for the previous year or part thereof with the target annual amount of $2,362,185 and calculate the rates that would be needed, given the expected billing demands, to collect $2,362,185, adjusted for any prior year over-collection or under-collection. In the final year that the rate is collected, PJM will calculate the rate to collect five-twelfths of the annual amount ($984,244), plus or minus any prior year true up amount, by May 31 of that year, and shall charge such rate until that amount is collected, whether that date be before or after May 31, / The service period charges rounded to four decimal places for the Dominion Zone are as follows: Yearly Charge - $/kw/year = the formula rate for Network Integration Transmission Service as described in Attachment H-16 and Attachment H- 16A divided by 1000 kw/mw Page 3

22 Monthly Charge - $/kw/month. = Yearly Charge divided by 12; Weekly Charge - $/kw/week = Yearly Charge divided by 52; Daily On-Peak Charge - $/kw/day = Weekly Charge divided by 5; Daily Off-Peak Charge - $/kw/day = Weekly Charge divided by 7. On a monthly basis, revenue credits shall be calculated based on the sum of VEPCO s share of revenues collected during the month from Schedule 7 and Network Integration Transmission Service to Non-Zone Network Load under Attachment H-A. The sum of these revenue credits will appear as an adjustment to the to the gross monthly service period charges produced by the above formula. 2) The total demand charge in any week, pursuant to a reservation for Daily On-Peak Delivery, or Daily Off-Peak Delivery shall not exceed the Weekly Delivery rate specified in section (1) above for weekly service times the highest amount in kilowatts of Reserved Capacity and any additional transmission service, if any, in any day during such week. 3) Discounts: Three principal requirements apply to discounts for transmission service as follows: (1) any offer of a discount made by the Transmission Provider must be announced to all Eligible Customers solely by posting on the OASIS, (2) any customer-initiated requests for discounts (including requests for use by one s wholesale merchant or an Affiliate s use) must occur solely by posting on the OASIS, and (3) once a discount is negotiated, details must be immediately posted on the OASIS. For any discount agreed upon for service on a path, from point(s) of receipt to point(s) of delivery, the Transmission Provider must offer the same discounted transmission service rate for the same time period to all Eligible Customers on all unconstrained transmission paths that go to the same point(s) of delivery on the Transmission System. 4) Congestion, Losses and Capacity Export: In addition to any payment under this Schedule, the Transmission Customer shall pay Redispatch Costs as specified in Section 27 of the Tariff. The Transmission Customer shall be responsible for losses as specified in the Tariff. Any Transmission Customer that is a Capacity Export Transmission Customer, shall pay any applicable charges, and receive any applicable credits, for such a customer pursuant to Attachment DD. 5) Other Supporting Facilities and Taxes: In addition to the rates set forth in section (1) of this schedule, the Transmission Customer shall pay charges determined on a case-by-case basis for facilities necessary to provide Transmission Service at voltages lower than those shown in Attachment H for the applicable Zone(s) and any amounts necessary to reimburse PJMSettlement for any amounts payable as sales, excise, Btu, carbon, value-added or similar taxes (other than taxes based upon or measured by net income) with respect to the amounts payable pursuant to the Tariff. Page 4

23 6) Transitional Revenue Neutrality Charge: In addition to the rates set forth in section (1) of this schedule and any other applicable charges, the Transmission Customer shall also pay for Reserved Capacity for delivery at the border of the PJM Region a non-discountable charge of $3.60/kw/year, $0.30/kw/mo., $0.0692/kw/week, $0.0099/kw/day-off-peak, or $0.0138/kw/dayon-peak. PJM shall distribute all revenues from the Transitional Revenue Neutrality Charge to Allegheny Power. The charge provided for under this section (6) shall terminate effective as of the day on which the sum total of the revenues collected by this charge, the Transitional Revenue Neutrality Charge under Schedule 8, and the Transitional Market Expansion Charge under Schedule 11 equal $84,993,360. 7) Transmission Enhancement Charges. In addition to the rates set forth in Section (1) of this Schedule and any other applicable charges, the Transmission Customer shall also pay any Transmission Enhancement Charges for which it is designated as a Responsible Customer under Schedule 12 appended to the Tariff. 8) Determination of monthly charges for ComEd Zone: On a monthly basis, revenue credits shall be calculated based on the sum of ComEd s share of revenues collected during the month from: (i) the PJM Border Rate under Schedule 7; (ii) Network Integration Transmission Service to Non-Zone Network Load under Attachment H-A; (iii) Seams Elimination Charge/Cost Adjustment/Assignment ( SECA ) revenues allocable to ComEd under the Tariff; and (iv) any Point-To-Point Transmission Service where the Point of Receipt and the Point of Delivery are both internal to the ComEd Zone. On this basis, the sum of these revenues will appear as a reduction to the gross monthly rate stated above on a Transmission Customer s bill in that month for service under this schedule. 9) Determination of monthly charges for AEP Zone: On a monthly basis, revenue credits shall be calculated based on the sum of AEP s share of revenues collected during the month from: (i) the PJM Border Rate under Schedule 7; (ii) Network Integration Transmission Service to Non-Zone Network Load under Attachment H-A; and (iii) Firm Point-To-Point Transmission Service where the Point of Delivery is internal to the AEP Zone. The sum of these revenue credits will appear as an adjustment (reduction) to the gross monthly rate stated above on a Transmission Customer s bill in that month for service under this schedule. 10) Resales: The rates and rules governing charges and discounts stated above shall not apply to resales of transmission service, compensation for which shall be governed by section 23.1 of the Tariff. Page 5

24 SCHEDULE 8 Non-Firm Point-To-Point Transmission Service 1) The Transmission Customer shall pay for Non-Firm Point-To-Point Transmission Service up to the sum of the applicable charges set forth below for the Point of Delivery: Summary of Charges Point of Delivery Monthly Charge ($/kw) Weekly Charge ($/kw) Daily On- Peak 1/ Charge ($/kw) Daily Off- Peak 2/ Charge ($/kw) Hourly On-Peak 3/ Charge ($/MWh) Hourly Off- Peak 4/ Charge ($/MWh) Border of PJM AE Zone BG&E Zone Delmarva Zone JCPL Zone MetEd Zone Penelec Zone PECO Zone PPL Zone: Total charge is the sum of the components PPL: * AEC: UGI: * PPL: * AEC: UGI: * PPL: * AEC: UGI: * PPL: * AEC: UGI: * PPL: * AEC: 0.11 UGI: * PPL: * AEC: 0.05 UGI: * Pepco Zone PSE&G Zone AP Zone Rockland Zone / 6/ ComEd Zone * PPL Electric Utilities Corporation s and UGI Utilities respective component of the total charge is posted on the PJM Internet website. Page 6

25 AEP East Zone 7/ Nov. 1, 2005 AEP East Zone 7/ Attachment H-14 Monthly Charge X 12 / 52 Weekly Charge / 5 Weekly Charge / 7 Daily On- Peak Charge / 16 SECA Ended W-JF Line In Dayton Zone Dayton Zone Duquesne Zone Duquesne Zone Dominion Zone 8/ Dominion Zone 8/ ATSI Zone ATSI Zone Attachment H-21 Rate Pursuant to Attachment H-21 Attachment H-21 Rate Pursuant to Attachment H-21 Rate Pursuant to Attachment H-21 DEOK Zone DEOK Zone Attachment H-22 Attachment H-22 Attachment H-22 Rate Pursuant to Attachment H-22 Rate Pursuant to Attachment H-22 EKPC Zone EKPC Zone Attachment H-24 Attachment H-24 Attachment H-24 Rate Pursuant to Attachment H-24 Rate Pursuant to Attachment H-24 1/ Monday - Friday except the following holidays: New Years Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, and Christmas Day. 2/ Saturday and Sunday and the following holidays: New Years Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, and Christmas Day. 3/ 7:00 a.m. up to the hour ending 11:00 p.m. 4/ 11:00 p.m. up to the hour ending 7:00 a.m. 5/ Each month, revenue credits will be applied to the gross charge in accordance with Paragraph 9 below to determine the actual charge to the Transmission Customer. 6/ The charges for the ComEd zone are posted on PJM s website. In addition to the other rates set forth in this schedule, customers within the ComEd zone shall be charged for recovery of RTO start-up costs at the following rates, each computed to four decimal places: Annual Rate - $/kw/year = $1,523,039, divided by the 1 CP demand for the ComEd zone for the prior calendar year; Monthly Rate - $/kw/month. = Annual Rate divided by 12; Weekly Rate - $/kw/week = Annual Rate divided by 52; Daily rate - $/kw/day = Weekly Rate divided by 5. In order to ensure that the charge does not result in either an over-recovery or underrecovery of ComEd s start-up costs, PJM will institute an annual true-up mechanism in the month of May of each of the years In May of each of those years, PJM will compare the amount collected under this charge for the previous 12 months with the target annual amount of $1,523,039 and calculate any credits or surcharges that would be Page 7

26 needed to ensure that $1,523,039 is collected for each year. Any credit or surcharge will be assessed in the June bills for years , consistent with the above methodology. 7/ The rates for non-firm point-to-point transmission service in the AEP Zone will be charged at the monthly, weekly, daily or hourly rate equivalent to the rate effective in such period under Attachment H-14. In addition to other rates set forth in this schedule, customers within the AEP East Zone shall be charged for recovery of RTO start-up costs at the following rates, each computed to four decimal places: Annual Rate - $/kw/year = $2,362,185, plus any applicable true-up adjustment, divided by the 1 CP demand for the AEP East Zone for the prior calendar year; Monthly Rate - $/kw/month. = Annual Rate divided by 12; Weekly Rate - $/kw/week = Annual Rate divided by 52; Daily Rate - $/kw/day = Weekly Rate divided by 5. For the period November 1, 2005 through March 31, 2006, the rate shall be $8.94/MWmonth; for the period April 1 through December 31, 2006, the rate shall be $8.60/MWmonth, thereafter, the rate will be subject to the following true-up: In order to ensure that the charge does not result in either over-recovery or underrecovery of AEP s start-up costs, PJM will institute an annual true-up mechanism and implement revised charges as of January 1st of each of the years In January of each of those years, PJM will compare the amount collected under this charge for the previous year or part thereof with the target annual amount of $2,362,185 and calculate the rates that would be needed, given the expected billing demands, to collect $2,362,185, adjusted for any prior year over-collection or under-collection. In the final year that the rate is collected, PJM will calculate the rate to collect five-twelfths of the annual amount, ($984,244), plus or minus any prior year true up amount, by May 31 of that year, and shall charge such rate until that amount is collected, whether that date be before or after May 31, Effective December 1, 2004, the charge for Points of Delivery at the Border of PJM and the Transitional Revenue Neutrality Charge under this Schedule 8 shall not apply to any Reserved Capacity with a Point of Delivery of the Midwest Independent Transmission System Operator, Inc. obtained pursuant to requests submitted on or after November 17, 2003, for service commencing on or after April 1, Effective April 1, 2006, the charge for Points of Delivery at the Border of PJM and the Transitional Revenue Neutrality Charge under this Schedule 7 shall not apply to any Reserved Capacity with a Point of Delivery of the Midwest Independent Transmission System Operator, Inc. 8/ The service period charges rounded to four decimal places for the Dominion Zone are as follows: Page 8

May 8, Response to Show Cause Order, Filing of Revised Tariff Sheet And Request for Any Necessary Waivers. The Dayton Power and Light Company

May 8, Response to Show Cause Order, Filing of Revised Tariff Sheet And Request for Any Necessary Waivers. The Dayton Power and Light Company The Dayton Power and Light Company 1065 Woodman Drive, Dayton Ohio 45458 May 8, 2018 Via etariff Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington,

More information

2016/2017 RPM Capacity Performance Transition Incremental Auction Results

2016/2017 RPM Capacity Performance Transition Incremental Auction Results Introduction The 2016/2017 Capacity Performance Transition Incremental Auction ( CP Transition Auction ) opened on August 27, 2015, and the auction results were posted on August 31, 2015. This document

More information

December 23, By etariff Filing Hon. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426

December 23, By etariff Filing Hon. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 December 23, 2014 By etariff Filing Hon. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 Re: Nevada Power Company and Sierra Pacific Power Company,

More information

ATLANTIC CITY ELECTRIC COMPANY BPU NJ

ATLANTIC CITY ELECTRIC COMPANY BPU NJ Attachment 1 Attachment 1 Page 1 of 3 ATLANTIC CITY ELECTRIC COMPANY BPU NJ No. 11 Electric Service - Section IV Revised Sheet Replaces Revised Sheet No. 60 RIDER (BGS) Basic Generation Service (BGS) Basic

More information

July 15, 2015 VIA ELECTRONIC FILING

July 15, 2015 VIA ELECTRONIC FILING July 15, 2015 VIA ELECTRONIC FILING The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20246 Re: Southwest Power Pool, Inc., Docket No.

More information

SKADDEN, ARPS, SLATE, MEAGHER & FLOM LLP 1440 NEW YORK AVENUE, N.W. WASHINGTON, D.C

SKADDEN, ARPS, SLATE, MEAGHER & FLOM LLP 1440 NEW YORK AVENUE, N.W. WASHINGTON, D.C DIRECT DIAL (202) 371-7070 DIRECT FAX (202) 661-8229 EMAIL ADDRESS MIKE.NAEVE@SKADDEN.COM SKADDEN, ARPS, SLATE, MEAGHER & FLOM LLP 1440 NEW YORK AVENUE, N.W. WASHINGTON, D.C. 20005-2111 TEL: (202) 371-7000

More information

June 20, Ms. Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C

June 20, Ms. Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C McGuireWoods LLP 2001 K Street N.W. Suite 400 Washington, DC 20006-1040 Phone: 202.857.1700 Fax: 202.857.1737 www.mcguirewoods.com Julia Dryden English Direct: 202.857.1706 jenglish@mcguirewoods.com Fax:

More information

20% RATE DISCOUNT FOR YOUR FIRST 2 MONTHS! CL&P United Illuminating Locally Produced

20% RATE DISCOUNT FOR YOUR FIRST 2 MONTHS! CL&P United Illuminating Locally Produced CONNECTICUT CONNECTICUT MARKET HISTORY * ED 13% 52,268,772 lbs 3,103,458 57,495,649 CL&P 9.48 8.4 12.00 United Illuminating 10.62 9.2 13.00 20% RATE DISCOUNT FOR YOUR FIRST 2 MONTHS! 1,670 POUNDS BY 19

More information

January 25, By Electronic Filing

January 25, By Electronic Filing Gary J. Newell P 202.370.0137 F 202.370.0143 gnewell@jsslaw.com Jennings, Strouss & Salmon, P.L.C. 1350 I Street, NW Suite 810 Washington, D.C. 200053305 jsslaw.com January 25, 2019 By Electronic Filing

More information

ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC

ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC 20004-1404

More information

March 7, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426

March 7, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 March 7, 2012 Re: California Independent

More information

JOSEPH A. HOLTMAN - ELECTRIC. 1 Q. Please state your name, title, employer and business. 4 Electricity Supply for Consolidated Edison Company of

JOSEPH A. HOLTMAN - ELECTRIC. 1 Q. Please state your name, title, employer and business. 4 Electricity Supply for Consolidated Edison Company of 1 Q. Please state your name, title, employer and business 2 address. 3 A. My name is Joseph A. Holtman. I am Director - 4 Electricity Supply for Consolidated Edison Company of 5 New York, Inc. ("Con Edison"

More information

ROCKLAND ELECTRIC COMPANY PROPOSAL FOR BASIC GENERATION SERVICE REQUIREMENTS TO BE PROCURED EFFECTIVE JUNE 1, 2016

ROCKLAND ELECTRIC COMPANY PROPOSAL FOR BASIC GENERATION SERVICE REQUIREMENTS TO BE PROCURED EFFECTIVE JUNE 1, 2016 STATE OF NEW JERSEY BOARD OF PUBLIC UTILITIES IN THE MATTER OF THE PROVISION OF BASIC GENERATION SERVICE FOR THE PERIOD BEGINNING JUNE 1, 2016 Docket No. ER15040482 ROCKLAND ELECTRIC COMPANY PROPOSAL FOR

More information

ROCKLAND ELECTRIC COMPANY PROPOSAL FOR BASIC GENERATION SERVICE REQUIREMENTS TO BE PROCURED EFFECTIVE JUNE 1, 2018

ROCKLAND ELECTRIC COMPANY PROPOSAL FOR BASIC GENERATION SERVICE REQUIREMENTS TO BE PROCURED EFFECTIVE JUNE 1, 2018 STATE OF NEW JERSEY BOARD OF PUBLIC UTILITIES IN THE MATTER OF THE PROVISION OF BASIC GENERATION SERVICE FOR THE PERIOD BEGINNING JUNE 1, 2018 Docket No. ER17040335 ROCKLAND ELECTRIC COMPANY PROPOSAL FOR

More information

DEFAULT SERVICE IN PENNSYLVANIA. David B. MacGregor, Esquire Anthony D. Kanagy, Esquire Post & Schell, P.C.

DEFAULT SERVICE IN PENNSYLVANIA. David B. MacGregor, Esquire Anthony D. Kanagy, Esquire Post & Schell, P.C. DEFAULT SERVICE IN PENNSYLVANIA David B. MacGregor, Esquire Anthony D. Kanagy, Esquire Post & Schell, P.C. Synopsis: This presentation provides an overview of default electric service in Pennsylvania beginning

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION New York Independent System Operator, Inc. ) PJM Interconnection, L.L.C. ) Docket Nos. ER17-905-002 ) MOTION FOR LEAVE TO ANSWER

More information

In addition to this transmittal letter and associated records for the etariff database, this filing includes:

In addition to this transmittal letter and associated records for the etariff database, this filing includes: 1050 Thomas Jefferson Street, NW Seventh Floor Washington, DC 20007 (202) 298-1800 Phone (202) 338-2416 Fax SUBMITTED VIA E-TARIFF FILING January 4, 2017 Kimberly D. Bose Secretary Federal Energy Regulatory

More information

RATES FOR EXPORT TRANSMISSION SERVICE

RATES FOR EXPORT TRANSMISSION SERVICE Page of RATES FOR EXPORT TRANSMISSION.0 INTRODUCTION The OEB has directed Hydro One Transmission to monitor and report to the Board, at the next rate case, on the functioning of the Export Transmission

More information

November 29, RE: Southern California Edison Company s Formula Transmission Rate Annual Update Filing in Docket No. ER (TO2019)

November 29, RE: Southern California Edison Company s Formula Transmission Rate Annual Update Filing in Docket No. ER (TO2019) Jeffrey L. Nelson Director FERC Rates & Market Integration Ms. Kimberly D. Bose, Secretary 888 First Street, N.E. Washington, DC 20426 RE: Southern California Edison Company s Formula Transmission Rate

More information

June 5, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426

June 5, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Texas Eastern Transmission, LP Mailing Address: 5400 Westheimer Court P.O. Box 1642 Houston, Texas 77056 Houston, TX 77251-1642 713.627.5400 main June 5, 2017 Ms. Kimberly D. Bose, Secretary Federal Energy

More information

PJM Interconnection, L.L.C. ( PJM ), under Section 205 of the Federal Power Act

PJM Interconnection, L.L.C. ( PJM ), under Section 205 of the Federal Power Act PJM Interconnection, L.L.C. 2750 Monroe Boulevard Audubon, PA 19403 March 30, 2018 Elizabeth P. Trinkle Counsel T: (610) 666-4707 F: (610) 666-8211 Elizabeth.Trinkle@pjm.com The Honorable Kimberly D. Bose

More information

N. Am. Elec. Reliability Corp., 119 FERC 61,060, order on reh g, 120 FERC 61,260 (2007).

N. Am. Elec. Reliability Corp., 119 FERC 61,060, order on reh g, 120 FERC 61,260 (2007). The Honorable Kimberly D. Bose Secretary November 7, 2008 Page 2 Arkansas. SPP currently has 50 Members, serving more than 4 million customers in a 255,000 square-mile area covering all or part of eight

More information

Second Revision of Sheet No P.S.C.U. No. 50 Canceling First Revision of Sheet No ROCKY MOUNTAIN POWER ELECTRIC SERVICE SCHEDULE NO.

Second Revision of Sheet No P.S.C.U. No. 50 Canceling First Revision of Sheet No ROCKY MOUNTAIN POWER ELECTRIC SERVICE SCHEDULE NO. Second Revision of Sheet No. 31.1 P.S.C.U. No. 50 Canceling First Revision of Sheet No. 31.1 ROCKY MOUNTAIN POWER ELECTRIC SERVICE SCHEDULE NO. 31 STATE OF UTAH Partial Requirements Service Large General

More information

7.3 Auction Procedures Role of the Office of the Interconnection.

7.3 Auction Procedures Role of the Office of the Interconnection. 7.3 Auction Procedures. 7.3.1 Role of the Office of the Interconnection. Financial Transmission Rights auctions shall be conducted by the Office of the Interconnection in accordance with standards and

More information

March 28, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C

March 28, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C March 28, 2018 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 700 Louisiana Street, Suite 700 Houston, Texas 77002-2700 John A. Roscher

More information

D. RSCP SUPPLIER PAYMENTS AND CUSTOMER RATES

D. RSCP SUPPLIER PAYMENTS AND CUSTOMER RATES 32 RSCP SUPPLIER PAYMENTS AND CUSTOMER RATES D. RSCP SUPPLIER PAYMENTS AND CUSTOMER RATES This summary is provided for bidder convenience only. Any statements herein describing BGS- RSCP rates or supplier

More information

Non-Conforming Negotiated Rate Agreement Update; El Paso Natural Gas Company, L.L.C.; Docket No. RP19-

Non-Conforming Negotiated Rate Agreement Update; El Paso Natural Gas Company, L.L.C.; Docket No. RP19- February 28, 2019 Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Attention: Ms. Kimberly D. Bose, Secretary Re: Non-Conforming Negotiated Rate Agreement Update; El Paso

More information

American Electric Power Service Corporation Docket No. ER10- -

American Electric Power Service Corporation Docket No. ER10- - American Electric Power 801 Pennsylvania Avenue N.W. Suite 320 Washington, DC 20004 AEP.com May 3, 2010 Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E.

More information

PJM Reliability Pricing Model

PJM Reliability Pricing Model Note: Presentation by B. Hobbs et al. on the dynamic analysis of the RPM is attached PJM Reliability Pricing Model Murty P. Bhavaraju PJM Interconnection IEEE/PES General Meeting Tampa, FL June 27, 2007

More information

January 22, Compliance Filing of Virginia Electric and Power Company Docket No. EL

January 22, Compliance Filing of Virginia Electric and Power Company Docket No. EL Troutman Sanders LLP 401 9th Street, N. W., Suite 1000 Washington, D.C. 200042134 troutman.com Anne K. Dailey anne.dailey@troutman.com January 22, 2019 The Honorable Kimberly D. Bose, Secretary Federal

More information

Financial Transmission and Auction Revenue Rights

Financial Transmission and Auction Revenue Rights Section 13 FTRs and ARRs Financial Transmission and Auction Revenue Rights In an LMP market, the lowest cost generation is dispatched to meet the load, subject to the ability of the transmission system

More information

January 3, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.

January 3, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. January 3, 2018 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Columbia Gas Transmission, LLC 700 Louisiana Street, Suite 700 Houston,

More information

Non-Conforming, Negotiated Rate Transportation Service Agreement Filing; El Paso Natural Gas Company, L.L.C.; Docket No. RP17-

Non-Conforming, Negotiated Rate Transportation Service Agreement Filing; El Paso Natural Gas Company, L.L.C.; Docket No. RP17- September 21, 2017 Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Attention: Ms. Kimberly D. Bose, Secretary Re: Non-Conforming, Negotiated Rate Transportation Service

More information

Entergy Services, Inc., Docket No. ER Informational Filing of Annual Transmission Formula Rate Update

Entergy Services, Inc., Docket No. ER Informational Filing of Annual Transmission Formula Rate Update Entergy Services, Inc. 101 Constitution Ave., N.W. Suite 200 East Washington, DC 20001 Tel: 202 530 7323 Fax: 202 530 7350 E-mail: mgriffe@entergy.com Michael C. Griffen Assistant General Counsel Federal

More information

Financial Transmission and Auction Revenue Rights

Financial Transmission and Auction Revenue Rights Section 13 FTRs and ARRs Financial Transmission and Auction Revenue Rights In an LMP market, the lowest cost generation is dispatched to meet the load, subject to the ability of the transmission system

More information

August 16, Attachment 1 to the Formula Rate is the Formula Protocols, and Attachment 2 is the Formula Spreadsheet. 2

August 16, Attachment 1 to the Formula Rate is the Formula Protocols, and Attachment 2 is the Formula Spreadsheet. 2 Karen Koyano Principle Manager FERC Rates and Compliance Ms. Kimberly D. Bose, Secretary 888 First Street, N.E. Washington, DC 20426 Dear Ms. Bose: Pursuant to Section 205 of the Federal Power Act and

More information

May 15, Duke Energy Ohio, Inc., and Duke Energy Kentucky, Inc. Formula Rate Annual Update Docket No. ER

May 15, Duke Energy Ohio, Inc., and Duke Energy Kentucky, Inc. Formula Rate Annual Update Docket No. ER Gary A. Morgans 202 429 6234 gmorgans@steptoe.com 1330 Connecticut Avenue, NW Washington, DC 20036-1795 202 429 3000 main www.steptoe.com The Hon. Kimberly D. Bose Secretary Federal Energy Regulatory Commission

More information

December 29, American Electric Power Service Corporation Docket No. ER

December 29, American Electric Power Service Corporation Docket No. ER American Electric Power 1 Riverside Plaza Columbus, OH 43215 AEP.com Honorable Kimberly D Bose Secretary Federal Energy Regulatory Commission 888 First St., N.E. Washington D.C. 20426 December 29, 2015

More information

Twelfth Revised Sheet No FLORIDA POWER & LIGHT COMPANY Cancels Eleventh Revised Sheet No INDEX OF CONTRACTS AND AGREEMENTS

Twelfth Revised Sheet No FLORIDA POWER & LIGHT COMPANY Cancels Eleventh Revised Sheet No INDEX OF CONTRACTS AND AGREEMENTS Twelfth Revised Sheet No. 10.001 FLORIDA POWER & LIGHT COMPANY Cancels Eleventh Revised Sheet No. 10.001 INDEX OF CONTRACTS AND AGREEMENTS Sheet No. Contract Provisions - Various 10.010 Distribution Substation

More information

ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC

ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC 20004-1404 202-756-3300 Fax: 202-756-3333 March 2, 2011 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission

More information

Market Seller Offer Cap Balancing Ratio Issue

Market Seller Offer Cap Balancing Ratio Issue Market Seller Offer Cap Balancing Ratio Issue Patrick Bruno Capacity Market Operations Market Implementation Committee February 7, 2018 www.pjm.com Overview of the Issue The current rules set the default

More information

July 21, Southwest Power Pool, Inc., Docket No. ER Submission of Response to Request for Additional Information

July 21, Southwest Power Pool, Inc., Docket No. ER Submission of Response to Request for Additional Information July 21, 2016 VIA ELECTRONIC FILING Penny Murrell Director, Division of Electric Power Regulation-Central Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: Southwest

More information

August 1, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C

August 1, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C August 1, 2018 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 700 Louisiana Street, Suite 700 Houston, Texas 77002-2700 John A. Roscher

More information

SIDLEY AUSTIN LLP 701 FIFTH AVENUE, SUITE 4200 SEATTLE, WA AMERICA ASIA PACIFIC EUROPE

SIDLEY AUSTIN LLP 701 FIFTH AVENUE, SUITE 4200 SEATTLE, WA AMERICA ASIA PACIFIC EUROPE SIDLEY AUSTIN LLP 701 FIFTH AVENUE, SUITE 4200 SEATTLE, WA 98104 AMERICA ASIA PACIFIC EUROPE SBERMAN@SIDLEY.COM +1 206 262 7681 October 1, 2018 Via etariff Filing Kimberly D. Bose Secretary Federal Energy

More information

August 1, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426

August 1, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Texas Eastern Transmission, LP Mailing Address: 5400 Westheimer Court P.O. Box 1642 Houston, Texas 77056 Houston, TX 77251-1642 713.627.5400 main August 1, 2017 Ms. Kimberly D. Bose, Secretary Federal

More information

Terms of Service 1. Basic Service Prices. Your rate plan will be as specified in your Welcome Letter or Electric Service Agreement.

Terms of Service 1. Basic Service Prices. Your rate plan will be as specified in your Welcome Letter or Electric Service Agreement. Nittany Energy, LLC Pennsylvania Residential and Small Business Electric Generation Service West Penn Power Online Enrollment Disclosure Statement and Terms of Service This is an agreement for electric

More information

BY ELECTRONIC FILING Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.

BY ELECTRONIC FILING Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. ANDREW W. TUNNELL t: (205) 226-3439 f: (205) 488-5858 e: atunnell@balch.com BY ELECTRONIC FILING Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington,

More information

June 13, Informational Filing Public Service Electric and Gas Company, Annual True-Up Adjustment Docket No. ER

June 13, Informational Filing Public Service Electric and Gas Company, Annual True-Up Adjustment Docket No. ER Hesser G. McBride, Jr. Associate General Regulatory Counsel Law Department 80 Park Plaza, T5G, Newark, NJ 07102-4194 tel: 973.430.5333 fax: 973.430.5983 email: Hesser.McBride@pseg.com June 13, 2016 VIA

More information

Calculate Net Annual Transmission Revenue Requirements (ATRR) and Rates for SPP Tariff. Total Transmission A. Zonal Net ATRR 1 Gross ATRR $60,516,589

Calculate Net Annual Transmission Revenue Requirements (ATRR) and Rates for SPP Tariff. Total Transmission A. Zonal Net ATRR 1 Gross ATRR $60,516,589 Page 1 Formula-based Rate Template Calculate Net Annual Transmission Revenue Requirements (ATRR) and Rates for SPP Tariff Line No. Acct Description Notes Total Transmission A. Zonal Net ATRR 1 Gross ATRR

More information

Calculate Net Annual Transmission Revenue Requirements (ATRR) and Rates for SPP Tariff. Total Transmission A. Zonal Net ATRR 1 Gross ATRR $48,861,618

Calculate Net Annual Transmission Revenue Requirements (ATRR) and Rates for SPP Tariff. Total Transmission A. Zonal Net ATRR 1 Gross ATRR $48,861,618 Page 1 Formula-based Rate Template Calculate Net Annual Transmission Revenue Requirements (ATRR) and Rates for SPP Tariff Line Acct Description Notes Total Transmission A. Zonal Net ATRR 1 Gross ATRR $48,861,618

More information

Operating Agreement Redlines

Operating Agreement Redlines Option J1 Proposed OA and OATT Revisions for FTR Defaults Operating Agreement Redlines OPERATING AGREEMENT, SCHEDULE 1 PJM INTERCHANGE ENERGY MARKET 7.3 Auction Procedures. 7.3.1 Role of the Office of

More information

Mailing Address: P.O. Box 1642 Houston, Texas September 1, 2011

Mailing Address: P.O. Box 1642 Houston, Texas September 1, 2011 Big Sandy Pipeline, LLC 5400 Westheimer Court Houston, TX 77056-5310 Mailing Address: P.O. Box 1642 Houston, Texas 77251-1642 713.627.5400 main September 1, 2011 Ms. Kimberly D. Bose, Secretary Federal

More information

Rocky Mountain Power Exhibit RMP (JRS-1S) Docket No ER-15 Witness: Joelle R. Steward BEFORE THE WYOMING PUBLIC SERVICE COMMISSION

Rocky Mountain Power Exhibit RMP (JRS-1S) Docket No ER-15 Witness: Joelle R. Steward BEFORE THE WYOMING PUBLIC SERVICE COMMISSION Exhibit RMP (JRS-1S) BEFORE THE WYOMING PUBLIC SERVICE COMMISSION ROCKY MOUNTAIN POWER Exhibit Accompanying Supplemental Direct Testimony of Joelle R. Steward June 2015 Exhibit RMP (JRS-1S) Page 1 of 34

More information

Balancing Ratio Determination

Balancing Ratio Determination Balancing Ratio Determination Patrick Bruno Sr. Engineer, Capacity Market Operations Markets Implementation Committee March 7, 2018 www.pjm.com Issue Recap The current rules set the default Market Seller

More information

RE: Southern California Edison Company s Formula Transmission Rate Annual Update Filing in Docket No. ER (TO11)

RE: Southern California Edison Company s Formula Transmission Rate Annual Update Filing in Docket No. ER (TO11) Jeffrey L. Nelson Director FERC Rates & Market Integration Ms. Kimberly D. Bose, Secretary 888 First Street, N.E. Washington, DC 20426 RE: Southern California Edison Company s Formula Transmission Rate

More information

October 5, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426

October 5, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 5400 Westheimer Court Houston, TX 77056-5310 Mailing Address: P.O. Box 1642 Houston, TX 77251-1642 713.627.5400 main October 5, 2015 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission

More information

Sierrita is hereby submitting its responses to the April 3, 2018 OEMR Data Request questions.

Sierrita is hereby submitting its responses to the April 3, 2018 OEMR Data Request questions. April 10, 2018 Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 Attention: Re: Ms. Kimberly D. Bose, Secretary Office of Energy Market Regulation Letter Order Pursuant to

More information

STATEMENT OF NATURE, REASONS AND BASIS

STATEMENT OF NATURE, REASONS AND BASIS October 1, 2012 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: Texas Eastern Transmission, LP, Docket No. RP13- -000 Dear Ms. Bose: Pursuant

More information

Consolidated Edison, Inc. 6-Year Financials and Operating Statistics

Consolidated Edison, Inc. 6-Year Financials and Operating Statistics Consolidated Edison, Inc. 6-Year Financials and Operating Statistics 2001-2006 Consolidated Edison, Inc. Annual Dividend Growth Dividends Per Share ($)* 2.12 2.14 2.18 2.20 2.22 2.24 2.26 2.28 2.30 2.32

More information

October 4, 2013 VIA ELECTRONIC FILING

October 4, 2013 VIA ELECTRONIC FILING VIA ELECTRONIC FILING The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: New York Independent System Operator, Inc. s, Report

More information

ATTACHMENTS ATTACHMENT GG NETWORK UPGRADE CHARGE

ATTACHMENTS ATTACHMENT GG NETWORK UPGRADE CHARGE ATTACHMENT GG Network Upgrade Charge ATTACHMENTS 32.0.0 ATTACHMENT GG NETWORK UPGRADE CHARGE 1. Network Upgrade Cost Allocation: This Attachment GG sets forth the method for calculating and collecting

More information

Mailing Address: P.O. Box 1642 Houston, TX

Mailing Address: P.O. Box 1642 Houston, TX 5400 Westheimer Court Houston, TX 77056-5310 713.627.5400 main Mailing Address: P.O. Box 1642 Houston, TX 77251-1642 August 20, 2013 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission

More information

June 5, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426

June 5, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 June 5, 2015 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Tuscarora Gas Transmission Company 700 Louisiana Street, Suite 700 Houston, TX

More information

September 2, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426

September 2, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 California Independent System Operator Corporation September 2, 2014 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California

More information

SOUTHERN CALIFORNIA EDISON COMPANY

SOUTHERN CALIFORNIA EDISON COMPANY UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Southern California Edison Company ) Docket No. ER17- -000 SOUTHERN CALIFORNIA EDISON COMPANY ANNUAL UPDATE FILING OF THE TRANSMISSION

More information

5.2 Transmission Congestion Credit Calculation Eligibility.

5.2 Transmission Congestion Credit Calculation Eligibility. 5.2 Transmission Congestion culation. 5.2.1 Eligibility. (a) Except as provided in Section 5.2.1(b), each FTR Holder shall receive as a Transmission Congestion Credit a proportional share of the total

More information

Pennsylvania Residential and Small Commercial Contract Summary and Terms of Service CONTRACT SUMMARY

Pennsylvania Residential and Small Commercial Contract Summary and Terms of Service CONTRACT SUMMARY Pennsylvania Residential and Small Commercial Contract Summary and Terms of Service CONTRACT SUMMARY Our Contact Information Price Structure Generation/Supply Price Term of Agreement Deposit Spark Energy,

More information

SOUTHERN CALIFORNIA EDISON COMPANY

SOUTHERN CALIFORNIA EDISON COMPANY UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Southern California Edison Company ) Docket No. ER18- -000 SOUTHERN CALIFORNIA EDISON COMPANY ANNUAL UPDATE FILING OF THE TRANSMISSION

More information

Transmission Access Charge Informational Filing

Transmission Access Charge Informational Filing California Independent System Operator September 27, 213 The Honorable Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 2426 Re: California Independent

More information

Medium General Service Time-of-Use Transition

Medium General Service Time-of-Use Transition Original Sheet No.: 213 Medium General Service Time-of-Use Transition AVAILABILITY Available throughout the Company s entire electric service area where the facilities of the Company are of adequate capacity

More information

RE: Southern California Edison Company s Formula Transmission Rate Annual Update Filing in Docket No. ER (TO11)

RE: Southern California Edison Company s Formula Transmission Rate Annual Update Filing in Docket No. ER (TO11) James A. Cuillier Director FERC Rates & Regulation Ms. Kimberly D. Bose, Secretary 888 First Street, N.E. Washington, DC 20426 RE: Southern California Edison Company s Formula Transmission Rate Annual

More information

Pursuant to section 205 of the Federal Power Act ( FPA ), 1 and part 35 of the regulations

Pursuant to section 205 of the Federal Power Act ( FPA ), 1 and part 35 of the regulations PJM Interconnection, L.L.C. 2750 Monroe Blvd Audubon, PA 19403-2497 Jeanine S. Watson Senior Counsel T: (610) 666-4438 ǀ F: (610) 666-8211 jeanine.watson@pjm.com February 7, 2017 The Honorable Kimberly

More information

Small General Service Demand Time-of-Use

Small General Service Demand Time-of-Use First Revised Sheet No.: 204 Superseding Original Sheet No.: 204 Small General Service Demand Time-of-Use AVAILABILITY Available throughout the Company s entire electric service area where the facilities

More information

SIDLEY AUSTIN LLP 701 FIFTH AVENUE, SUITE 4200 SEATTLE, WA AMERICA ASIA PACIFIC EUROPE

SIDLEY AUSTIN LLP 701 FIFTH AVENUE, SUITE 4200 SEATTLE, WA AMERICA ASIA PACIFIC EUROPE SIDLEY AUSTIN LLP 701 FIFTH AVENUE, SUITE 4200 SEATTLE, WA 98104 AMERICA ASIA PACIFIC EUROPE SBERMAN@SIDLEY.COM +1 206 262 7681 October 1, 2018 Via etariff Filing Kimberly D. Bose Secretary Federal Energy

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C ) Docket Nos. ER17-211-000 Mid-Atlantic Interstate Transmission, LLC ) ER17-214-000 and ) ER17-216-000

More information

April 28, Southwest Power Pool, Inc., Docket No. ER11- Submission of Formula Rate Template

April 28, Southwest Power Pool, Inc., Docket No. ER11- Submission of Formula Rate Template Secretary Federal Energy Regulatory Commission 888 First Street NE Washington, DC 20426 Re: Southwest Power Pool, Inc., Docket No. ER11- Submission of Formula Rate Template Honorable Secretary Bose: Pursuant

More information

SIDLEY AUSTIN LLP 701 FIFTH AVENUE, SUITE 4200 SEATTLE, WA AMERICA ASIA PACIFIC EUROPE

SIDLEY AUSTIN LLP 701 FIFTH AVENUE, SUITE 4200 SEATTLE, WA AMERICA ASIA PACIFIC EUROPE SIDLEY AUSTIN LLP 701 FIFTH AVENUE, SUITE 4200 SEATTLE, WA 98104 AMERICA ASIA PACIFIC EUROPE SBERMAN@SIDLEY.COM +1 206 262 7681 October 1, 2018 Via etariff Filing Kimberly D. Bose Secretary Federal Energy

More information

March 25, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C

March 25, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C March 25, 2010 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Gas Transmission Northwest Corporation 717 Texas Street, Suite 2400 Houston,

More information

December 19, Cal. Indep. Sys. Operator Corp., 165 FERC 61,140 (2018) (November 19 Order).

December 19, Cal. Indep. Sys. Operator Corp., 165 FERC 61,140 (2018) (November 19 Order). California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, D.C. 20426 December 19, 2018 Re: California

More information

ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC

ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC 20004-1404

More information

150 FERC 61,116 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

150 FERC 61,116 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 150 FERC 61,116 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Cheryl A. LaFleur, Chairman; Philip D. Moeller, Tony Clark, Norman C. Bay, and Colette D. Honorable.

More information

BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION DOCKET NO. ER DIRECT TESTIMONY AND EXHIBIT ALAN C. HEINTZ ON BEHALF OF TAMPA ELECTRIC COMPANY

BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION DOCKET NO. ER DIRECT TESTIMONY AND EXHIBIT ALAN C. HEINTZ ON BEHALF OF TAMPA ELECTRIC COMPANY BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION DOCKET NO. ER10- -000 DIRECT TESTIMONY AND EXHIBIT OF ALAN C. HEINTZ ON BEHALF OF TAMPA ELECTRIC COMPANY 1 2 ALAN C. HEINTZ DIRECT TESTIMONY AND EXHIBIT

More information

Rover Pipeline LLC Docket No. RP Compliance with Order on Compliance Filing

Rover Pipeline LLC Docket No. RP Compliance with Order on Compliance Filing December 8, 2017 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: Rover Pipeline LLC Docket No. RP17-772- Compliance with Order on

More information

American Electric Power Service Corporation ER Etariff Compliance Filing

American Electric Power Service Corporation ER Etariff Compliance Filing American Electric Power 801 Pennsylvania Avenue N.W. Suite 320 Washington, DC 20004 AEP.com March 9, 2011 Monique Rowtham- Kennedy Senior Counsel Regulatory Services (202) 383-3436 (202) 383-3459 (F) Honorable

More information

If there are any questions concerning this filing, please contact the undersigned.

If there are any questions concerning this filing, please contact the undersigned. California Independent System Operator Corporation June 13, 2008 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: One Hundred

More information

BEIJING BOSTON BRUSSELS CENTURY CITY CHICAGO DALLAS GENEVA. FOUNDED February 23, 2018

BEIJING BOSTON BRUSSELS CENTURY CITY CHICAGO DALLAS GENEVA. FOUNDED February 23, 2018 SIDLEY AUSTIN LLP 701 FIFTH AVENUE, SUITE 4200 SEATTLE, WA 98104 BEIJING BOSTON BRUSSELS CENTURY CITY CHICAGO DALLAS GENEVA HONG KONG HOUSTON LONDON LOS ANGELES MUNICH NEW YORK PALO ALTO SAN FRANCISCO

More information

BEIJING BOSTON BRUSSELS CENTURY CITY CHICAGO DALLAS GENEVA. FOUNDED February 23, 2018

BEIJING BOSTON BRUSSELS CENTURY CITY CHICAGO DALLAS GENEVA. FOUNDED February 23, 2018 SIDLEY AUSTIN LLP 701 FIFTH AVENUE, SUITE 4200 SEATTLE, WA 98104 BEIJING BOSTON BRUSSELS CENTURY CITY CHICAGO DALLAS GENEVA HONG KONG HOUSTON LONDON LOS ANGELES MUNICH NEW YORK PALO ALTO SAN FRANCISCO

More information

PROTOCOLS AS INCORPORATED INTO WESTAR S OATT

PROTOCOLS AS INCORPORATED INTO WESTAR S OATT PROTOCOLS AS INCORPORATED INTO WESTAR S OATT FERC Electric Tariff ORIGINAL Sheet No. 228 ATTACHMENT H-2 Formula Rate Implementation Protocols I. Annual Update 1. The rate formula template in Attachment

More information

Any questions regarding this filing should be directed to the undersigned at (402)

Any questions regarding this filing should be directed to the undersigned at (402) Northern Natural Gas Company P.O. Box 3330 Omaha, NE 68103-0330 402 398-7200 November 13, 2018 Via efiling Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington,

More information

August 24, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.

August 24, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. California Independent System Operator Corporation August 24, 2007 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: One Hundred

More information

January 17, via etariff

January 17, via etariff CLIFFORD S. SIKORA 202.274.2950 telephone Clifford.Sikora@troutmansanders.com TROUTMAN SANDERS LLP Attorneys at Law 401 9th Street, N. W., Suite 1000 Washington, D.C. 20004-2134 202.274.2950 telephone

More information

Informational Filing of Midwest Independent Transmission System Operator, Inc. s Independent Market Monitor

Informational Filing of Midwest Independent Transmission System Operator, Inc. s Independent Market Monitor Potomac Economics, Ltd. 9990 Fairfax Boulevard, Suite 560 Telephone: 703-383-0720 Fairfax, Virginia 22030 Facsimile: 703-383-0796 Honorable Kimberly D. Bose, Secretary Federal Energy Regulatory Commission

More information

January 25, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.

January 25, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. California Independent System Operator Corporation January 25, 2008 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: One Hundred

More information

GridLiance West Transco LLC Docket No. ES Amendment to Application Under Section 204 of the Federal Power Act

GridLiance West Transco LLC Docket No. ES Amendment to Application Under Section 204 of the Federal Power Act January 12, 2017 VIA ELECTRONIC FILING Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: GridLiance West Transco LLC Docket No. ES17-9-000 Amendment

More information

May 18, Black Hills Power, Inc. Docket Nos. ER and EL Compliance Filing Revising Attachment H Formula Rate Protocols

May 18, Black Hills Power, Inc. Docket Nos. ER and EL Compliance Filing Revising Attachment H Formula Rate Protocols Texas New York Washington, DC Connecticut Seattle Dubai London Blake R. Urban Attorney 202.828.5868 Office 800.404.3970 Fax Blake.Urban@bgllp.com Bracewell & Giuliani LLP 2000 K Street NW Suite 500 Washington,

More information

STATEMENT OF NATURE, REASONS AND BASIS

STATEMENT OF NATURE, REASONS AND BASIS Texas Eastern Transmission, LP Mailing Address: 5400 Westheimer Court P.O. Box 1642 Houston, Texas 77056 Houston, TX 77251-1642 713.627.5400 main March 29, 2018 Ms. Kimberly D. Bose, Secretary Federal

More information

FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, DC 20426

FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, DC 20426 FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, DC 20426 OFFICE OF ENERGY MARKET REGULATION Sidley Austin LLP 701 Fifth Avenue, Suite 4200 Seattle, WA 98104 Baltimore Gas and Electric Company Suite 1301,

More information

SERVICE CLASSIFICATION NO. 14-RA STANDBY SERVICE

SERVICE CLASSIFICATION NO. 14-RA STANDBY SERVICE Fourth Revised Leaf No. 135 Consolidated Edison Company Superseding Second Revised Leaf No. 135 (Third Revised Leaf No. 135 Canceled) Applicable to Use of Service for SERVICE CLASSIFICATION NO. 14-RA The

More information

Orange and Rockland Utilities, Inc Annual Financial Statements and Notes

Orange and Rockland Utilities, Inc Annual Financial Statements and Notes Orange and Rockland Utilities, Inc. 2007 Annual Financial Statements and Notes Financial Statements Report of Independent Registered Public Accounting Firm Consolidated Balance Sheet Consolidated Income

More information

December 7, Compliance with Order No. 844 Response to Deficiency Letter

December 7, Compliance with Order No. 844 Response to Deficiency Letter California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California Independent System

More information