1 ATTACHMENT GG Network Upgrade Charge ATTACHMENTS ATTACHMENT GG NETWORK UPGRADE CHARGE 1. Network Upgrade Cost Allocation: This Attachment GG sets forth the method for calculating and collecting the charges associated with Network Upgrades and for distributing the revenues associated with such charges. This Attachment applies to those Network Upgrades that are determined under Attachment FF to be subject to this Attachment GG that are not subject to the cost recovery provisions of Attachment N. The charges under this Attachment GG shall be in addition to any charges under Schedules 7, 8, 9, 26-A and Determination of Network Upgrade Charge ( NUC ): (a) The Transmission Provider shall identify in this Attachment GG all Network Upgrades eligible under Attachment FF that form the basis of the NUC. Such designations shall be the same as those made for the relevant Network Upgrades in the MTEP. The NUC for each eligible project shall be its adjusted annual revenue requirement as computed in Section 3 below. In conjunction with providing its annual Attachment O, each Transmission Owner and/or ITC shall furnish to the Transmission Provider: (1) its NUC for each Network Upgrade subject to this Attachment GG as calculated below; and (2) its twelve (12) monthly transmission system peaks determined in accordance with Attachment O. Effective On: July 1, 2016

2 ATTACHMENT GG Network Upgrade Charge ATTACHMENTS (b) (c) The Transmission Provider shall apportion the NUC from (a) above in accordance with the applicable Attachment FF. For purposes of preparing Attachment GG, each Transmission Owner and/or ITC must utilize the same test period that is utilized in the preparation of its Attachment O. (d) Projects included in Attachment GG must be in-service prior to or during the test period indicated in (c) above. If the Transmission Owner and/or ITC receives FERC approval to include specific Network Upgrades that are recorded in construction work in progress (CWIP) but not yet in-service in the annual revenue requirement calculation, and the Transmission Provider includes such Network Upgrades on Appendix A of the MISO Transmission Expansion Plan, those projects may be included in Attachment GG provided the Transmission Owner and/or ITC supplies the Transmission Provider with evidence of FERC approval. (e) In order to prevent over recovery of Attachment O revenue, the revenue requirement calculated pursuant to Attachment GG (Attachment GG template, Page 2, Line 3, Column 10) will be subtracted by each Transmission Owner and ITC from their respective Attachment O revenue requirement. (f) The Network Upgrade annual revenue requirement apportioned to a pricing zone shall be the sum of all Transmission Owner and/or ITC s NUCs for the pricing zone including those NUCs allocated on a system-wide basis to all pricing zones as provided under Attachment FF, or to pricing zones in a specific Planning Area where a project terminates exclusively pursuant to Attachment FF-6. The Transmission Provider shall calculate rates to be collected pursuant to Schedule 26 for each pricing Effective On: July 1, 2016

3 ATTACHMENT GG Network Upgrade Charge ATTACHMENTS zone by taking the sum of the NUCs from the previous sentence and dividing by the current rate divisor 1 from Attachment O, Page 1, Line 15 in kw multiplied by 1000 to calculate an annual rate per MW. The per-unit rates will be calculated as: The monthly rate per MW will be the annual rate divided by 12 The weekly rate per MW will be the annual rate divided by 52 The On-Peak daily rate per MW will be the annual rate divided by 260 (capped at weekly rate) The On-Peak hourly rate per MW will be the annual Rate divided by 4160 (capped at weekly and daily rates) The Off-Peak daily rate per MW will be the annual rate divided by 365 The Off-Peak hourly per MW will be annual rate divided by 8760 (g) Drive-through and drive-out Transmission Service shall be charged a rate that is (1) the sum of all Transmission Owner and/or ITC NUCs apportioned to pricing zones divided by (2) the sum of the twelve (12) monthly transmission system peaks from Section 2(a)(2) above for all pricing zones. (h) American Transmission Systems, Incorporated (ATSI) has withdrawn from the Transmission Provider and integrated into PJM Interconnection, L.L.C. effective June 1, (1) Under Schedule 26, upon ATSI s integration into PJM Interconnection, L.L.C. effective June 1, 2011, Transmission Customers taking Transmission Service pay a portion of the revenue requirements of MTEP Effective On: July 1, 2016

4 ATTACHMENT GG Network Upgrade Charge ATTACHMENTS Projects (as defined in Schedule 37) approved by the Transmission Provider Board for construction by ATSI. Under Schedule 38, Duke Energy Ohio, Inc. (DEO) and Duke Energy Kentucky, Inc. (DEK) (or transmission customers in PJM's DEOK Zone as more fully described in Appendix 1 to Schedule 38) make comparable payments. As a result of ATSI s withdrawal from the Transmission Provider, effective June 1, 2011, this portion of the revenue requirements of MTEP Projects (as defined in Schedule 37) approved by the Transmission Provider Board for construction by ATSI, will no longer be calculated under this Attachment GG, and will be calculated under Schedule 37. This revenue requirement (as determined in Schedule 37, Section IV) will be included in the determination of the NUC under this Attachment GG for charges and revenue distributions under Schedules 26, 37 and 38. (2) Likewise, under Schedule 37, effective June 1, 2011, ATSI (as defined in Schedule 37) is responsible for paying a portion of the revenue requirements of MTEP Projects (as defined in Schedule 37) approved by the Transmission Provider Board for construction by MISO Transmission Owners (as defined in Schedule 37). As a result of ATSI s withdrawal from the Transmission Provider, effective June 1, 2011, rates for ATSI (as defined in Schedule 37) will no longer be calculated under this Attachment GG or Schedule 26. (3) The annual revenue requirement reflecting the ongoing financial obligation of ATSI (as defined in Schedule 37) payable to the MISO Transmission Owners (as defined in Schedule 37) will be calculated in accordance with Effective On: July 1, 2016

5 ATTACHMENT GG Network Upgrade Charge ATTACHMENTS this Attachment GG and Schedule 26 and included in the calculation of the Schedule 26 Drive-through and drive-out Transmission Service rates described in 2(g) above. (4) The revenue requirement reflecting the various MISO Zones' (as defined in Schedule 37) obligation to ATSI (as defined in Schedule 37), calculated pursuant to Schedule 37, will be included in the Schedule 26 zonal rate calculations but will be excluded from the Schedule 26 Drive-through and drive-out Transmission Service rates described in 2(g) above. (5) ATSI (as defined in Schedule 37) will no longer receive a pro rata share of the Schedule 26 revenues collected by the Transmission Provider related to Drive-through and drive-out Point-to-Point Transmission Service reservations. (i) DEO and DEK have withdrawn from the Transmission Provider and integrated into PJM Interconnection, L.L.C. effective January 1, (1) Under Schedule 26, upon DEO and DEK s (as defined in Schedule 38) integration into PJM Interconnection, L.L.C. effective January 1, 2012, Transmission Customers taking Transmission Service pay a portion of the revenue requirements of MTEP Projects (as defined in Schedule 38) approved by the Transmission Provider Board for construction by DEO and DEK. Under Schedule 37, upon DEO and DEK s integration into PJM Interconnection, L.L.C. effective January 1, 2012, ATSI makes a comparable payment. Effective January 1, Effective On: July 1, 2016

6 ATTACHMENT GG Network Upgrade Charge ATTACHMENTS , revenue requirements of MTEP Projects (as defined in Schedule 38) of DEO and DEK will no longer be calculated under this Attachment GG and will be calculated pursuant to Schedule 38. This revenue requirement (as determined in Schedule 38, Section IV) will be included in the determination of the NUC under this Attachment GG for charges and revenue distributions under Schedules 26, 37 and 38. (2) Likewise, under Schedule 38, effective January 1, 2012, DEO and DEK are responsible for paying a portion of the revenue requirements of MTEP Projects (as defined in Schedule 38) approved by the Transmission Provider Board for construction by MISO Transmission Owners and ATSI. (3) The annual revenue requirement reflecting the ongoing financial obligation of DEO and DEK payable to the MISO Transmission Owners and ATSI calculated in accordance with this Attachment GG and Schedules 37 and 38 will be included in the calculation of the Schedule 26 Drive-through and drive-out Transmission Service rates described in 2(g) above. (4) The revenue requirement reflecting the various Transmission Provider zones obligation and ATSI s obligation to DEO and DEK, calculated pursuant to Schedule 38, will be included in the Schedule 26 zonal rate calculations but will be excluded from the Schedule 26 Drive-through and drive-out Transmission Service rates described in 2(g) above. Effective On: July 1, 2016

7 ATTACHMENT GG Network Upgrade Charge ATTACHMENTS (5) DEO and DEK will no longer receive a pro rata share of the Schedule 26 revenues collected by the Transmission Provider related to Drive-through and drive-out Point-to-Point Transmission Service reservations. (j) Revenue requirements for non-transmission Owner or non-itc Selected Developer Competitive Transmission Facilities that are not MVPs for which the non-transmission Owner or non-itc Selected Developers or non-transmission Owner or non-itc Proposal Participants recover Competitive Transmission Facility revenue requirements in accordance with Schedule 48, as authorized by FERC, will be included in the determination of the NUC under this Attachment GG for charges and revenue distributions under Schedule 26. Updates to revenue requirements under Schedule 48 shall be submitted to the Transmission Provider in accordance with Schedule 48 or its designated formula rate protocols. 3. Calculation of the NUC: (a) The NUC shall be allocated as follows: (1) Annual Allocation Factors shall be calculated for the following five (5) cost of service elements, expressed as a percentage, using the formulae included in this Attachment GG which utilizes select entries from the currently effective Attachment O: a. Operation and Maintenance Expense b. General and Common Depreciation Expense c. Taxes Other Than Income Taxes Effective On: July 1, 2016

8 ATTACHMENT GG Network Upgrade Charge ATTACHMENTS d. Income Taxes e. Return (2) Subsections (3) through (9) describe the calculation of the Annual Allocation Factors using references to the Attachment O, FERC Form 1, formula rate. Table 1 provides the cross-references to RUS Form 12 and EIA Form 412 versions of Attachment O to calculate the Annual Allocation Factors for publicly-owned Transmission Owners. (3) The Operation and Maintenance Annual Allocation Factor shall be determined by dividing the amount included on Attachment O, Page 3, Line 8, Column 5 by the amount of Gross Transmission Plant In-Service included on Attachment O, Page 2, Line 2, Column 5. The Gross Transmission Plant In-Service shall include any CWIP including in Rate Base, if applicable. (4) The General and Common Depreciation Expense Annual Allocation Factor shall be determined by dividing the amount included on Attachment O, Page 3, Lines 10 & 11, Column 5 by the amount of Gross Transmission Plant In-Service included on Attachment O, Page 2, Line 2, Column 5. The Gross Transmission Plant In- Service shall include any CWIP included in Rate Base, if applicable. (5) The Taxes Other Than Income Taxes Annual Allocation Factor shall be determined by dividing the amount included on Attachment O, Page 3, Line 20, Column 5 by the amount of Gross Transmission Plant In-Service Effective On: July 1, 2016

9 ATTACHMENT GG Network Upgrade Charge ATTACHMENTS included on Attachment O, Page 2, Line 2, Column 5. The Gross Transmission Plant In-Service shall include any CWIP included in Rate Base, if applicable. (6) The Annual Allocation Factor for Expense shall be the sum of (3), (4) and (5) above. (7) The Income Tax Annual Allocation Factor shall be determined by dividing the amount included on Attachments O, Page 3, Line 27, Column 5 by the amount included for the Net Transmission Plant In-Service Attachment O, Page 2, Line 14, Column 5. The Net Transmission Plant In-Service shall include any CWIP included in Rate Base if applicable. This component shall be zero for publicly-owned Transmission Owners. (8) The Return Annual Allocation Factor shall be determined by dividing the amount included on Attachment O, Page 3, Line 28, Column 5 by the amount of Net Transmission Plant In-Service included on Attachment O, Page 2, Line 14, Column 5. The Net Transmission Plant In-Service shall include any CWIP included in Rate Base, if applicable. (9) The Annual Allocation Factor for Return shall be the sum of (7) and (8) above. (10) The NUC to be used in Schedule 26 for each individual project subject to this Attachment GG shall be the sum of the project s Annual Expense Charge plus the project s Annual Return Charge plus the Project s Depreciation Expense plus any applicable True-Up Adjustment, where: Effective On: July 1, 2016

10 ATTACHMENT GG Network Upgrade Charge ATTACHMENTS a. Annual Expense Charge equals the project s Gross Plant multiplied by the Annual Allocation Factor for Expense calculated in (6) above; b. Annual Return Charge equals the project s Net Plant multiplied by the Annual Allocation Factor for Return calculated in (9) above; c. Depreciation Expense equals the actual value booked, or projected to be booked for forward-looking rate periods, for the project and included in Attachment O, Page 3, Line 12, column 5. Only Transmission Owners and/or ITCs that have received Commission approval to use a forward-looking test period to determine Attachment O rates may use projected values; d. True-Up Adjustment equals any applicable Attachment GG true-up amount calculated under a FERCaccepted mechanism for a particular Transmission Owner; and e. The project s Gross Plant and Net Plant values shall be the respective balances for the facilities comprising the project as incorporated in the Gross Plant values from Attachment O as identified in (3), (4) and (5) above and Net Plant values from Attachment O as identified in (7) and (8) above. These balances shall reflect any retirements or subsequent like kind replacements associated with the ongoing maintenance of the facilities identified in the project. (11) Each individual project shall be identified separately as a sub-row of line 1 on page 2 of the Attachment GG Effective On: July 1, 2016

11 ATTACHMENT GG Network Upgrade Charge ATTACHMENTS template attached, to be identified as line 1a, 1b, etc. The Transmission Owner shall add additional sub-rows to line 1 as needed to accommodate additional projects. (Note: An example of the operation of this NUC mechanism is appended to this Attachment GG after the Attachment GG Rate Formula Template) (b) Nothing contained in this Attachment GG shall limit the right of an ITC and/or Transmission Owner under Section 205 of the Federal Power Act and consistent with the ISO Agreement to file with the Commission individually and unilaterally to recover the cost of a Network Upgrade in a manner other than that specified in this Attachment GG, including, but not limited to recover rate incentives not specified herein and to recover the cost of Network Upgrades through its pricing zone rates under Schedules 7, 8, and 9 as calculated pursuant to Attachment O. 4. Network Upgrades Recovered under Attachment O Subject to agreement between or among the Transmission Owner and/or ITCs constructing, owning or financing the Network Upgrade within the affected pricing zone(s), to the extent that one Transmission Owner and/or ITC completes a Network Upgrade that benefits Transmission Customers in one or more additional pricing zones separate from those upgrades accruing benefits only to the individual Transmission Owner and/or ITC pricing zone and in the event the Network Upgrade is not recorded on the books of the Transmission Owner and/or ITC as transmission plant subject to recovery in state and federal rates, a regulatory asset will be set up on the accounting systems for each affected Transmission Owner and/or ITC equivalent Effective On: July 1, 2016

12 ATTACHMENT GG Network Upgrade Charge ATTACHMENTS to its share of the Network Upgrade costs. The regulatory asset will be recognized as a new Line 29a on Page 2 of Attachment O subject to regulatory approval revising Attachment O as such. Such regulatory asset will be subject to the average depreciation rate of the pricing zone s other transmission plant. To the extent that adjacent Transmission Owner and/or ITCs construct and own portions of a Network Upgrade, the regulatory asset methodology described herein shall be used to allocate these costs to match the benefits accruing to those Transmission Customers to the greatest extent practicable. Attachment GG - Generic Formula Rate calculation Rate Formula Template For the 12 months ended 12/31/ Utilizing Attachment O Data MISO Generic Company Page 1 of 2 To be completed in conjunction with Attachment O. (1) (2) (3) (4) Attachment O Line Page, Line, Col. Transmission Allocator No. 1 Gross Transmission Plant Total Attach O, Page 2, Line 2, Col. 5 (Note A) 0 Effective On: July 1, 2016

13 ATTACHMENT GG Network Upgrade Charge ATTACHMENTS Net Transmission Plant Total Attach O, Page 2, Lines 14 and 23b, Col. 5 (Note B) 0 O&M EXPENSE 3 Total O&M Allocated to Transmission Attach O, Page 3, Line 8, Col Annual Allocation Factor for O&M (Line 3 divided by Line 1, Col. 3) 0.00% 0.00% GENERAL AND COMMON (G&C) DEPRECIATION EXPENSE 5 Total G&C Depreciation Expense Attach O, Page 3, Lines 10 & 11, Col. 5 (Note H) 0 6 Annual Allocation Factor for G&C Depreciation Expense (Line 5 divided by Line 1, Col. 3) 0.00% 0.00% TAXES OTHER THAN INCOME TAXES 7 Total Other Taxes Attach O, Page 3, Line 20, Col Annual Allocation Factor for Other Taxes (Line 7 divided by Line 1, Col. 3) 0.00% 0.00% 9 Annual Allocation Factor for Expense Sum of lines 4, 6 & % INCOME TAXES 10 Total Income Taxes Attach O, Page 3, Line 27, Col Annual Allocation Factor for Income Taxes (Line 10 divided by Line 2, Col. 3) 0.00% 0.00% RETURN 12 Return on Rate Base Attach O, Page 3, Line 28, Col Annual Allocation Factor for Return on Rate Base (Line 12 divided by Line 2, Col. 3) 0.00% 0.00% 14 Annual Allocation Factor for Return Sum of lines 11 & % Effective On: July 1, 2016

14 ATTACHMENT GG Network Upgrade Charge ATTACHMENTS Attachment GG - Generic Formula Rate calculation Rate Formula Template For the 12 months ended 12/31/ Utilizing Attachment O Data MISO Generic Company Page 2 of 2 Network Upgrade Charge Calculation by Project (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) Annual Annual MTEP Allocation Annual Allocation Annual Project Network Line Project Project Gross Factor for Expense Project Net Factor for Return Depreciation Annual Revenue True-Up Upgrade No. Project Name Number Plant Expense Charge Plant Return Charge Expense Requirement Adjustment Charge Sum Col. 10 & 11 (Note C) (Page 1, Line 9) (Col. 3 * Col. 4) (Note D) (Page 1, Line 14) (Col. 6 * Col. 7) (Note E) (Sum Col. 5, 8 & 9) (Note F) (Note G) 1a Project 1 P1 $0 0.00% $0 $0 0.00% $0 $0 $0 $0 $0 1b Project 2 P2 $0 0.00% $0 $0 0.00% $0 $0 $0 $0 $0 1c Project 3 P3 $0 0.00% $0 $0 0.00% $0 $0 $0 $0 $0 2 Annual Totals $0 $0 $0 3 Rev. Req. Adj for Attachment O $0 Effective On: July 1, 2016

15 ATTACHMENT GG Network Upgrade Charge ATTACHMENTS Note Letter A Gross Transmission Plant is that identified on Page 2, Line 2 of Attachment O and includes any sub lines 2a or 2b etc. and is inclusive of any CWIP included in rate base when authorized by FERC order less any prefunded AFUDC, if applicable. B Net Transmission Plant is that identified on Page 2, Line 14 of Attachment O and includes any sub lines 14a or 14b etc. and is inclusive of any CWIP included in rate base when authorized by FERC order less any prefunded AFUDC, if applicable. C Project Gross Plant is the total capital investment for the project calculated in the same method as the gross plant value in Line 1 and includes CWIP in rate base less any prefunded AFUDC, if applicable. This value includes subsequent capital investments required to maintain the facilities to their original capabilities. D Project Net Plant is the Project Gross Plant Identified in Column 3 less the associated Accumulated Depreciation. E Project Depreciation Expense is the actual value booked for the project and included in the Depreciation Expense in Attachment O, Page 3, Line 12. F True-Up Adjustment is included pursuant to a FERC approved methodology, if applicable. G The Network Upgrade Charge is the value to be used in Schedules 26, 37 and 38. H The Total General and Common Depreciation Expense excludes any depreciation expense directly associated with a project and thereby included in Page 2, Column 9. Effective On: July 1, 2016

16 ATTACHMENT GG Network Upgrade Charge ATTACHMENTS Table 1 Cross Reference to Attachment O for Completion of Attachment GG Attachment GG FERC Form 1 EIA Form 412 Non-Levelized EIA Form 412 Cash Flow RUS Form 12 Non-Levelized RUS Form 12 Cash Flow Gross Transmission Plant Page 1, Line 1, Col. 3 Page 2, Line 2, Col. 5 Page 2, Line 2, Col. 5 Page 3, Line 2, Col. 5 Page 2, Line 2, Col. 5 Page 3, Line 2, Col. 5 Net Transmission Plant* Page 1, Line 2, Col. 3 Page 2, Line 14, Col. 5 Page 2, Line 14, Col. 5 Page 3, Line 2, Col. 5 Page 2, Line 14, Col. 5 Page 3, Line 2, Col. 5 O&M Expense Page 1, Line 3, Col. 3 Page 3, Line 8, Col. 5 Page 3, Line 8, Col. 5 Page 2, Line 8, Col. 5 Page 3, Line 8, Col. 5 Page 2, Line 8, Col. 5 General and Common Depreciation Expense Page 1, Line 5, Col. 3 P. 3, Lines 10&11, Col. 5 P. 3, Lines 10&11, Col. 5 N/A Page 3, Lines 10 & 11, Col. 5 N/A Taxes Other Than Income Taxes Page 1, Line 7, Col. 3 Page 3, Line 20, Col. 5 Page 3, Line 20, Col. 5 Page 2, Line 19, Col. 5** Page 3, Line 20, Col. 5 Page 2, Line 19, Col. 5 Total Income Taxes Page 1, Line 10, Col. 3 Page 3, Line 27, Col. 5 Page 3, Line 27, Col. 5 N/A Page 3, Line 27, Col. 5 N/A Return on Rate Base Page 1, Line 12, Col. 3 Page 3, Line 28, Col. 5 Page 3, Line 28, Col. 5 Page 2, Line 11, Col. 5 & Page 3, Line 28, Col. 5 Page 2, Line 11, Col. 5 & Page 2, Line 21, Col. 5*** Page 2, Line 21, Col. 5 Notes: * The Net Transmission Plant for Transmission Owners using an Attachment O based on either EIA Form 412 Cash Flow or RUS Form 12 Cash Flow shall use their Gross Transmission Plant from Page 2, Line 2, Column 5 for a Net Transmission Plant value. These two Attachment Os do not allow for the recovery of depreciation expense nor do they decrement rate base for accumulated depreciation, therefore to maintain a consistent methodology between Attachment O and Attachment GG no depreciation expense would be recovered under Attachment GG nor would any accumulated depreciation be included in the calculation of the Net Transmission Plant balances. ** The Taxes Other Than Income Taxes for SMMPA s EIA Form 412 Cash Flow Attachment O shall use Page 2, Line 20, Col. 5. *** The Return on Rate Base for SMMPA s EIA Form 412 Cash Flow Attachment O shall use Page 2, Line 12, Col. 5 and Page 2, Line 22, Col. 5. Effective On: July 1, 2016

17 ATTACHMENT GG Network Upgrade Charge ATTACHMENTS Table 2 Transmission Expansion Projects Authorized for Network Upgrade Charge (reserved ) 1 Loads that are included in the Attachment O rate divisor for the NSP Companies pricing zone (zone 16), but are located in the OTP load balancing area and are charged the applicable OTP pricing zone (zone 18) Schedule 26 rate, shall be excluded from the zone 16 Schedule 26 rate divisor and included in the zone 18 Schedule 26 rate divisor for purposes of calculating the Schedule 26 rates in zones 16 and 18. Effective On: July 1, 2016

18 ATTACHMENT GG GRE Network Upgrade Charge ATTACHMENT GG GRE NETWORK UPGRADE CHARGE 1. Network Upgrade Cost Allocation: This Attachment GG - GRE sets forth the method for calculating and collecting the charges associated with Network Upgrades and for distributing the revenues associated with such charges. This Attachment applies to those Network Upgrades that are determined under Attachment FF to be subject to this Attachment GG - GRE that are not subject to the cost recovery provisions of Attachment N. The charges under this Attachment GG - GRE shall be in addition to any charges under Schedules 7, 8, 9, 26-A and Determination of Network Upgrade Charge ( NUC ): (a) The Transmission Provider shall identify in this Attachment GG - GRE all Network Upgrades eligible under Attachment FF that form the basis of the NUC. Such designations shall be the same as those made for the relevant Network Upgrades in the MTEP. The NUC for each eligible project shall be its adjusted annual revenue requirement as computed in Section 3 below. In conjunction with providing its annual Attachment O - GRE, Great River Energy shall furnish to the Transmission Provider: (1) its NUC for each Network Upgrade subject to this Attachment GG - GRE as calculated below; and (2) its twelve (12) monthly transmission system peaks determined in accordance with Attachment O - GRE. (b) The Transmission Provider shall apportion the NUC from (a) above in accordance with the applicable Attachment FF.

19 ATTACHMENT GG GRE Network Upgrade Charge (c) For purposes of preparing Attachment GG - GRE, Great River Energy must utilize the same test period that is utilized in the preparation of its Attachment O - GRE. (d) Projects included in Attachment GG - GRE must be in-service prior to or during the test period indicated in (c) above. If the Great River Energy receives FERC approval to include specific Network Upgrades that are recorded in construction work in progress (CWIP) but not yet in-service in the annual revenue requirement calculation, and the Transmission Provider includes such Network Upgrades on Appendix A of the MISO Transmission Expansion Plan, those projects may be included in Attachment GG - GRE provided that Great River Energy supplies the Transmission Provider with evidence of FERC approval. (e) In order to prevent over recovery of Attachment O - GRE revenue, the revenue requirement calculated pursuant to Attachment GG - GRE (Attachment GG - GRE template, Page 2, Line 3, Column 10a) will be subtracted from Great River Energy s Attachment O - GRE revenue requirement. (f) The NUC is a zonal rate charged via Schedule 26. The Network Upgrade annual revenue requirement apportioned to a pricing zone shall be the sum of all Transmission Owner and/or ITC s NUCs for the pricing zone including those NUCs allocated on a system-wide basis to all pricing zones as provided under Attachment FF. Section 2 of the Transmission Provider s pro forma Attachment GG provides a complete description of the development and application of the NUC. 3. Calculation of the NUC: (a) The NUC shall be allocated as follows:

20 ATTACHMENT GG GRE Network Upgrade Charge i. Annual Allocation Factors shall be calculated for the following six (6) cost of service elements, expressed as a percentage, using the formulae included in this Attachment GG - GRE which utilizes select entries from the currently effective Attachment O GRE: a. Operation and Maintenance Expense b. General and Common Depreciation Expense c. Taxes Other Than Income Taxes d. Income Taxes e. Return f. Incentive Return ii. Subsections (iii) through (x) describe the calculation of the Annual Allocation Factors using references to the Attachment O GRE. iii. The Operation and Maintenance Annual Allocation Factor shall be determined by dividing the amount included on Attachment O - GRE, Page 3, Line 8, Column 5 by the amount of Gross Transmission Plant In-Service included on Attachment O - GRE, Page 2, Line 2, Column 5. The Gross Transmission Plant In-Service shall include any CWIP included in Rate Base (Attachment O-GRE, Page 2, Line 18a, Column 5) and Prefunded AFUDC on CWIP in Rate Base (Attachment O-GRE, Page 2, Line 23a, Column 5), if applicable. iv. The General and Common Depreciation Expense Annual Allocation Factor shall be determined by dividing the amount included on Attachment O - GRE, Page 3, Lines 10 & 11, Column 5 by the amount of Gross Transmission Plant

21 ATTACHMENT GG GRE Network Upgrade Charge In-Service included on Attachment O - GRE, Page 2, Line 2, Column 5. The Gross Transmission Plant In-Service shall include any CWIP included in Rate Base, if applicable. v. The Taxes Other Than Income Taxes Annual Allocation Factor shall be determined by dividing the amount included on Attachment O - GRE, Page 3, Line 20, Column 5 by the amount of Gross Transmission Plant In-Service included on Attachment O - GRE, Page 2, Line 2, Column 5. The Gross Transmission Plant In-Service shall include any CWIP included in Rate Base (Attachment O - GRE, Page 2, Line 18a, Column 5) and Prefunded AFUDC on CWIP in Rate Base (Attachment O - GRE, Page 2, Line 23a, Column 5), if applicable. vi. The Annual Allocation Factor for Expense shall be the sum of (iii), (iv), and (v) above. vii. The Income Tax Annual Allocation Factor shall be determined by dividing the amount included on Attachments O - GRE, Page 3, Line 27, Column 5 by the amount included for the Net Transmission Plant In-Service Attachment O - GRE, Page 2, Line 14, Column 5. The Net Transmission Plant In-Service shall include any CWIP included in Rate Base (Attachment O - GRE, Page 2, Line 18a, Column 5), Prefunded AFUDC on CWIP in Rate Base (Attachment O - GRE, Page 2, Line 23a, Column 5), and the Unamortized Balance of Abandoned Plant (Attachment O - GRE, Page 2, Line 23b, Column 5), if applicable.

22 ATTACHMENT GG GRE Network Upgrade Charge This component shall be zero for publicly-owned Transmission Owners. viii. The Return Annual Allocation Factor shall be determined by dividing the amount included on Attachment O - GRE, Page 3, Line 28, Column 5 by the amount of Net Transmission Plant In-Service included on Attachment O - GRE, Page 2, Line 14, Column 5. The Net Transmission Plant In-Service shall include any CWIP included in Rate Base (Attachment O - GRE, Page 2, Line 18a, Column 5), Prefunded AFUDC on CWIP in Rate Base (Attachment O - GRE, Page 2, Line 23a, Column 5), and the Unamortized Balance of Abandoned Plant (Attachment O - GRE, Page 2, Line 23b, Column 5), if applicable. ix. The Annual Allocation Factor for Return shall be the sum of (vii) and (viii) above. x. The Annual Allocation Factor for Incentive Return shall be determined by subtracting the value in Attachment O - GRE, Page 4, Line 24 from the value in Attachment O - GRE, Page 4, Line 29. xi. The NUC to be used in Schedule 26 for each individual project subject to this Attachment GG - GRE shall be the sum of the project s Annual Expense Charge plus the project s Annual Return Charge plus the project s Annual Incentive Return Charge plus the project s Depreciation Expense plus any applicable True-Up Adjustment, where: 1. Annual Expense Charge equals the project s Gross Plant multiplied by the Annual Allocation Factor for Expense

23 ATTACHMENT GG GRE Network Upgrade Charge calculated in (vi) above; 2. Annual Return Charge equals the project s Net Plant multiplied by the Annual Allocation Factor for Return calculated in (ix) above; 3. Annual Incentive Return Charge equals the project s Net Plant multiplied by the Annual Allocation Factor for Incentive Return calculated in (x) above; 4. Depreciation Expense equals the actual value booked for the project and included in Attachment O, Page 3, Line 12, column 5; 5. True-Up Adjustment equals any applicable Attachment GG - GRE true-up amount calculated under the FERC-accepted mechanism for Great River Energy; and 6. The project s Gross Plant and Net Plant values shall be the respective balances for the facilities comprising the project as incorporated in the Gross Plant values from Attachment O - GRE as identified in (iii) and (iv) above and Net Plant values from Attachment O - GRE as identified in (vi) and (vii) above. These balances shall reflect any retirements or subsequent like kind replacements associated with the ongoing maintenance of the facilities identified in the project. xii. Each individual project shall be identified separately as a sub-row of line

24 ATTACHMENT GG GRE Network Upgrade Charge 1on page 2 of the Attachment GG - GRE template attached, to be identified as line 1a, 1b, etc. Great River Energy shall add additional sub-rows to line 1 as needed to accommodate additional projects. (b) Nothing contained in this Attachment GG - GRE shall limit the right of Great River Energy under Section 205 of the Federal Power Act and consistent with the ISO Agreement to file with the Commission individually and unilaterally to recover the cost of a Network Upgrade in a manner other than that specified in this Attachment GG - GRE, including, but not limited to recover rate incentives not specified herein and to recover the cost of Network Upgrades through its pricing zone rates under Schedules 7, 8, and 9 as calculated pursuant to Attachment O - GRE. 4. Network Upgrades Recovered under Attachment O Subject to agreement between or among the Transmission Owner and/or ITCs constructing, owning or financing the Network Upgrade within the affected pricing zone(s), to the extent that one Transmission Owner and/or ITC completes a Network Upgrade that benefits Transmission Customers in one or more additional pricing zones separate from those upgrades accruing benefits only to the individual Transmission Owner and/or ITC pricing zone and in the event the Network Upgrade is not recorded on the books of the Transmission Owner and/or ITC as transmission plant subject to recovery in state and federal rates, a regulatory asset will be set up on the accounting systems for each affected Transmission Owner and/or ITC equivalent to its share of the Network Upgrade costs. The regulatory asset will be recognized as a new Line 29a on Page 2 of Attachment O - GRE subject to regulatory approval revising Attachment O as

25 ATTACHMENT GG GRE Network Upgrade Charge such. Such regulatory asset will be subject to the average depreciation rate of the pricing zone s other transmission plant. To the extent that adjacent Transmission Owner and/or ITCs construct and own portions of a Network Upgrade, the regulatory asset methodology described herein shall be used to allocate these costs to match the benefits accruing to those Transmission Customers to the greatest extent practicable.

26 ATTACHMENT GG GRE Rate Formula Template Attachment GG GRE Formula Rate calculation Rate Formula Template Utilizing Attachment O - GRE Data For the 12 months ended 12/31/ Great River Energy Page 1 of 2 To be completed in conjunction with Attachment O-GRE. (1) (2) (3) (4) Attachment O-GRE Line Page, Line, Col. Transmission Allocator No. 1 Gross Transmission Plant Total Attach O, Page 2, Line 2, Col. 5 (Note A) 0 2 Net Transmission Plant Total Attach O, Page 2, Line 14, Col. 5 (Note B) 0 O&M EXPENSE 3 Total O&M Allocated to Transmission Attach O, Page 3, Line 8, Col Annual Allocation Factor for O&M (Line 3 divided by Line 1, Col. 3) 0.00% 0.00% GENERAL AND COMMON (G&C) DEPRECIATION EXPENSE 5 Total G&C Depreciation Expense Attach O, Page 3, Lines 10 & 11, Col. 5 (Note I) 0 6 Annual Allocation Factor for G&C Depreciation Expense (Line 5 divided by Line 1, Col. 3) 0.00% 0.00% TAXES OTHER THAN INCOME TAXES 7 Total Other Taxes Attach O, Page 3, Line 20, Col Annual Allocation Factor for Other Taxes (Line 7 divided by Line 1, Col. 3) 0.00% 0.00% 9 Annual Allocation Factor for Expense Sum of Lines 4, 6 and %

27 ATTACHMENT GG GRE Rate Formula Template INCOME TAXES 10 Total Income Taxes Attach O, Page 3, Line 27, Col Annual Allocation Factor for Income Taxes (Line 10 divided by Line 2, Col. 3) 0.00% 0.00% RETURN 12 Return on Rate Base Attach O, Page 3, Line 28, Col Annual Allocation Factor for Return on Rate Base (Line 12 divided by Line 2, Col. 3) 0.00% 0.00% 14 Annual Allocation Factor for Return Sum of Lines 11 and % 14a Annual Allocation Factor for Incentive Return Attach O, Page 4, Line % 0.00%

28 ATTACHMENT GG GRE Rate Formula Template Attachment GG GRE Formula Rate calculation Rate Formula Template Utilizing Attachment O - GRE Data For the 12 months ended 12/31/ Great River Energy Page 2 of 2 Network Upgrade Charge Calculation by Project (1) (2) (3) (4) (5) (6) (7) (8) (8a) (8b) (9) (10) (10a) (11) (12) Lin e No. Project Name MTEP Project Numbe r Project Gross Plant Annua l Alloca tion Factor for Expen se Annual Expense Charge Project Net Plant Annual Allocatio n Factor for Return Annual Return Charge Annual Allocati on Factor for Incentiv e Return Annual Incenti ve Return Charge Project Depreciati on Expense Annual Revenue Requireme nt Annual Revenue Requireme nt Excluding Annual Incentive Return Charge True-Up Adjustm ent Network Upgrade Charge (Note C) (Page 1 line 9) (Col. 3 * Col. 4) (Note D) (Page 1 line 14) (Col. 6 * Col. 7) (Page 1, line 14a, Col. 4) (Col. 6 * Col. 8a) (Note E) (Sum Col. 5, 8, 8b & 9) Col. 10 less Col. 8b (Note H) (Note F) Sum Col. 10 & 11 (Note G) 1a Project 1 P1 1b Project 2 P2 1c Project 3 P3 $ % $0.00 $ % $0.00 $ % $0.00 $ - #DIV/0! $ - #DIV/0! $ - #DIV/0! #DIV/0! 0.00% $0 $0 #DIV/0! #DIV/0! $0 #DIV/0! #DIV/0! 0.00% $0 $0 #DIV/0! #DIV/0! $0 #DIV/0! #DIV/0! 0.00% $0 $0 #DIV/0! #DIV/0! $0 #DIV/0! 2 Annual Totals $0 #DIV/0! #DIV/0! $0 #DIV/0! 3 Rev. Req. Adj For Attachment O- GRE #DIV/0!

29 ATTACHMENT GG GRE Rate Formula Template Note Letter A Gross Transmission Plant is that identified on Page 2, Line 2 of Attachment O - GRE and includes any sub lines 2a or 2b etc. and is inclusive of any CWIP and Prefunded AFUDC on CWIP in rate base when authorized by FERC order. The Prefunded AFUDC amount is a reduction to rate base. B Net Transmission Plant is that identified on Page 2, Line 14 of Attachment O - GRE and includes any sub lines 14a or 14b etc. and is inclusive of any CWIP, Prefunded AFUDC on CWIP, and Unamortized Balance of Abandoned Plant included in rate base when authorized by FERC order. Prefunded AFUDC amount is a reduction to rate base. C Project Gross Plant is the total capital investment for the project calculated in the same method as the gross plant value in Line 1 and is inclusive of any CWIP and Prefunded AFUDC on CWIP when authorized by FERC order. The Prefunded AFUDC amount is a reduction to rate base. This value includes subsequent capital investments required to maintain the facilities to their original capabilities. D Project Net Plant is the Project Gross Plant Identified in Column 3 less the associated Accumulated Depreciation and is inclusive of any CWIP, Prefunded AFUDC on CWIP, and Unamortized Balance of Abandoned Plant in rate base when authorized by FERC order. The Prefunded AFUDC amount is a reduction to rate base. E Project Depreciation Expense is the actual value booked for the project and included in the Depreciation Expense in Attachment O - GRE, Page 3, Line 12. F True-Up Adjustment is included pursuant to a FERC approved methodology, if applicable. G The Network Upgrade Charge is the value to be used in Schedules 26, 37 and 38. H Annual Incentive Return Charge revenues for FERC-accepted projects utilizing a hypothetical capital structure are not included in Attachment O - GRE, Page 3, Line 30, Column 5 and Page 4, Lines 35 & 36a. I The Total General and Common Depreciation Expense excludes any depreciation expense directly associated with a project and thereby included in Page 2, Column 9.

30 ATTACHMENT GG GRE Annual True-Up Procedure ATTACHMENT GG - GRE ANNUAL TRUE-UP PROCEDURE FOR GREAT RIVER ENERGY 1. Applicability This Attachment GG GRE Annual True-Up Procedure shall apply to all projects of Great River Energy ( GRE ) where the individual project annual revenue requirement, or Network Upgrade Charge ( NUC ) in Attachment GG - GRE, or Construction Work in Progress ( CWIP ) is calculated pursuant to Attachment GG - GRE for cost recovery under various Schedules under this tariff, including but not limited to Schedules 26, 37 and 38. For purposes of the Attachment GG GRE Annual True-Up Procedure, when reference is made to Schedule 26 hereinafter, that reference includes all rate schedules that recover the revenue requirements of Attachment GG. The Schedules included on page 4, line 36a of Attachment O GRE shall conform to the various Schedules identified in the Attachment GG GRE Annual True-Up Procedure. 2. True-Up Procedure This procedure will true-up GRE cost recovery for projects whose costs are recovered under Schedule 26 for each calendar year beginning in 2009 by calculating a Zonal True-Up Adjustment for each such GRE project in each MISO pricing zone, which will be applied to the project revenue requirement allocated to each pricing zone two years later. Each year at the time of its Annual Updates under Attachment O - GRE, GRE shall use Attachment GG - GRE to determine the annual revenue requirement for all projects that are

31 ATTACHMENT GG GRE Annual True-Up Procedure eligible for regional cost recovery under Schedule 26, consistent with the projected information that is used to calculate its Attachment O - GRE revenue requirement and zonal rate for this same year. This True-Up Procedure describes how GRE will calculate true-up adjustments for each such project in order to (1) true-up the projected revenue requirements to the actual revenue requirements and (2) true-up revenue collections each year, by pricing zone, to ensure that customers in each zone ultimately pay the share of the actual revenue requirement ( Actual Revenue Requirement ) allocated to that zone by MISO pursuant to the applicable cost allocation provisions in Attachment FF. True-Up of Projected Revenue Requirements to Actual Revenue Requirements For each year ( True-Up Year ) an Attachment GG project revenue requirement using projected data ( Projected Revenue Requirement ) will be calculated for use in Schedule 26. The Actual Revenue Requirement for the project during the True-Up Year will be calculated during the following year pursuant to Attachment GG - GRE using actual data from GRE s Attachment O - GRE and Annual Operating Report for the True-Up Year. The Attachment GG - GRE Cost True-Up Adjustment shall equal the difference between the Projected Revenue Requirement and the Actual Revenue Requirement for the True-Up Year. The Cost True-Up Adjustment shall be allocated among pricing zones in the same manner as the Projected Revenue Requirement is allocated among pricing zones. True-Up of Annual Revenues Collected to Annual Revenue Requirement, by Zone For each True-Up Year the Schedule 26 revenues for each GRE project collected by MISO in each pricing zone shall be compared to the portion of GRE s Attachment GG - GRE

32 ATTACHMENT GG GRE Annual True-Up Procedure revenue requirement for that project allocated to that pricing zone for Schedule 26 rate calculation purposes during the True-Up Year. The Schedule 26 revenues for the True-Up Year collected in each pricing zone for each project shall be calculated by allocating total GRE Schedule 26 Revenue for the True-Up Year among projects and pricing zones. The allocation of total GRE Schedule 26 Revenue for the True-Up Year by project, by pricing zone shall be equal to: A times B, divided by C, where: A is the total GRE Schedule 26 Revenue for the True-Up Year; B is the project Attachment GG - GRE Revenue Requirement allocated to the pricing zone during the True-Up Year, times the actual average 12 Coincident Peak ( CP ) zonal load for the pricing zone during the True-Up Year (page 1, line 15 of Attachment O) 1, divided by the average 12 CP zonal load (page 1, line 15 of Attachment O) 2 that was used to calculate the Schedule 26 rate for the pricing zone during the True-Up Year; and C is the sum of all B, across all projects and pricing zones. Any excess or shortfall in actual revenue, compared to projected revenue requirement is each project s Revenue True-Up Adjustment for each pricing zone. True-Up of CWIP Projects Under Attachment GG The True-Up Procedure will also be used to calculate the True-Up Adjustments for projects recovering CWIP under Attachment GG - GRE. The Cost True-Up Adjustment for CWIP projects will be calculated for each year of CWIP recovery by taking the difference between the projected CWIP and the actual CWIP in the same year. Similarly, the Revenue True-Up Adjustment for CWIP projects will be the net excess or shortfall of Schedule 26 CWIP

33 ATTACHMENT GG GRE Annual True-Up Procedure revenue collected compared to the projected CWIP in the same year. The Schedule 26 CWIP revenue will be calculated in the same manner as Schedule 26 revenues calculated for other projects under Attachment GG - GRE. The Cost True-Up Adjustment and Revenue True-Up Adjustment will be calculated for each year where CWIP is recovered until the project is placed in service. Attachment GG - GRE Zonal True-Up Adjustment The sum of each project s Cost True-Up Adjustment and the Revenue True-Up Adjustment for each pricing zone shall constitute the Attachment GG - GRE Zonal True-Up Adjustment for that pricing zone for the True-Up Year. The Attachment GG - GRE Zonal True-Up Adjustment for each project and related calculations shall be posted to the GRE page of the Transmission Provider s OASIS no later than August 1 of the calendar year following the True-Up Year. Interest on any over recovery of the zonal Attachment GG - GRE Revenue Requirement shall be determined based on the Commission s regulations at 18 C.F.R 35.19a. Interest on any under recovery of the revenue requirement shall be determined using the interest rate equal to GRE s actual short-term debt costs capped at the applicable FERC refund interest rate. In either case, the interest payable shall be calculated using an average interest rate for the twentyfour (24) months during which the over or under recovery in the revenue requirement exists. The interest rate to be applied to the over or under recovery in the revenue requirement will be determined using the average rate for the nineteen (19) months preceding August of the current year.

34 ATTACHMENT GG GRE Annual True-Up Procedure The Attachment GG - GRE Revenue Requirement for a project allocated to each pricing zone during the year following this calculation (True-Up Year plus 2) shall be the sum of the Projected Revenue Requirement for True-Up Year plus 2 allocated to the pricing zone, plus or minus the Attachment GG - GRE Zonal True-Up Adjustment for that zone from the previous year s calculation, if any, including interest, as explained above. 1 For pricing zones utilizing a projected test year, this will be the actual load used for the Attachment O calculation of actual net revenue requirement for the True-Up Year, performed in the following year. For pricing zones utilizing a historic test year, this will be the divisor load used for the Attachment O calculation based on True-Up year data, used to calculate rates effective June 1 of the year following the True-Up Year. 2 For pricing zones using a projected test year, this will be the projected zonal load for the True-Up Year used for the Attachment O calculation that is the basis for rates charged during the True-Up Year. For pricing zones using historical test years, this shall be the weighted average of the average 12 CP load based on data from True Up Year 2 (which is the basis for Schedule 26 rate calculations for the first five months of the True-Up Year) and the average 12 CP load based on data from True-Up Year -1 (which is the basis for the Schedule 26 rate calculation for the last seven months of the True-Up Year).

35 ATTACHMENT GG ITCM Annual True-Up Procedure ATTACHMENT GG MIDWEST ANNUAL TRUE-UP PROCEDURE FOR ITC MIDWEST LLC 1. Applicability This Attachment GG Midwest Annual True-Up Procedure shall apply to all projects of ITC Midwest where the individual project annual revenue requirement, or Network Upgrade Charge ( NUC ) in Attachment GG, is calculated pursuant to Attachment GG for cost recovery under various Schedules under this tariff, including but not limited to Schedules 26, 37, and 38. For purposes of the Attachment GG Midwest Annual True-Up Procedure, when reference is made to Schedule 26 hereinafter, that reference includes all rate schedules that recover the revenue requirements of Attachment GG. The schedules included on page 4, Line 36a of Attachment O Midwest shall conform to the various Schedules identified in this Attachment GG Midwest Annual True-Up Procedure. 2. True-Up Procedure This procedure will true-up ITC Midwest cost recovery for those projects whose costs are recovered under Schedule 26 for each calendar year beginning in 2009 by calculating a Zonal True-Up Adjustment for each such ITC Midwest Project in each MISO pricing zone, which will be applied to the project revenue requirement allocated to each pricing zone two years later. Each year at the time of its Annual Updates under Attachment O - Midwest, ITC Midwest shall use Attachment GG to determine the annual revenue requirement for all projects that are eligible for regional cost recovery under Schedule 26, consistent with the projected

36 ATTACHMENT GG ITCM Annual True-Up Procedure information that is used to calculate its Attachment O - Midwest revenue requirement and zonal rate for this same year. This True-Up Procedure describes how ITC Midwest will calculate true-up adjustments for each such project in order to (1) true-up the projected revenue requirements to the actual revenue requirements, and (2) true-up revenue collections each year, by pricing zone, to ensure that customers in each zone ultimately pay the share of the actual revenue requirement ( Actual Revenue Requirement ) allocated to that zone by MISO pursuant to the applicable cost allocation provisions in Attachment FF. True-Up of Projected Revenue Requirements to Actual Revenue Requirements For each year ( True-Up Year ) an Attachment GG project revenue requirement using projected data ( Projected Revenue Requirement ) will be calculated for use in Schedule 26. The Actual Revenue Requirement for the project during the True-Up Year will be calculated during the following year pursuant to Attachment GG using actual data from Attachment O - Midwest and FERC Form 1 for the True-Up Year. The Attachment GG Cost True-Up Adjustment shall equal the difference between the Projected Revenue Requirement and the Actual Revenue Requirement for the True-Up Year. The Cost True-Up Adjustment shall be allocated among pricing zones in the same manner as the Projected Revenue Requirement is allocated among pricing zones. True-Up of Annual Revenues Collected to Annual Revenue Requirement, by Zone For each True-Up Year the Schedule 26 revenues for each ITC Midwest project collected by MISO in each pricing zone shall be compared to the portion of ITC Midwest s Attachment GG revenue requirement for that project allocated to that pricing zone for Schedule 26 rate

May 15, Duke Energy Ohio, Inc., and Duke Energy Kentucky, Inc. Formula Rate Annual Update Docket No. ER

May 15, Duke Energy Ohio, Inc., and Duke Energy Kentucky, Inc. Formula Rate Annual Update Docket No. ER Gary A. Morgans 202 429 6234 gmorgans@steptoe.com 1330 Connecticut Avenue, NW Washington, DC 20036-1795 202 429 3000 main www.steptoe.com The Hon. Kimberly D. Bose Secretary Federal Energy Regulatory Commission

More information

NORTHERN INDIANA PUBLIC SERVICE COMPANY Attachment GG True-Up Adjustment For the Year Ended December 31, 2014

NORTHERN INDIANA PUBLIC SERVICE COMPANY Attachment GG True-Up Adjustment For the Year Ended December 31, 2014 NORTHERN INDIANA PUBLIC SERVICE COMPANY Attachment GG True-Up Adjustment For the Year Ended December 31, 2014 Attachment GG Projected Proportion Actual True Up Revenue of Revenues Revenue Interest allocated

More information

June 20, Ms. Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C

June 20, Ms. Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C McGuireWoods LLP 2001 K Street N.W. Suite 400 Washington, DC 20006-1040 Phone: 202.857.1700 Fax: 202.857.1737 www.mcguirewoods.com Julia Dryden English Direct: 202.857.1706 jenglish@mcguirewoods.com Fax:

More information

MISO SCHEDULE 38 SCHEDULES SCHEDULE 38. MTEP Project Cost Recovery for DEO and DEK

MISO SCHEDULE 38 SCHEDULES SCHEDULE 38. MTEP Project Cost Recovery for DEO and DEK SCHEDULE 38 I. Definitions Any capitalized terms not defined in this Schedule 38 shall have the meaning as defined in Module A of the Tariff. Definitions for this Schedule 38 are as follows: A. ATSI American

More information

ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC

ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC 20004-1404

More information

Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/2019 Utilizing FERC Form 1 Data

Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/2019 Utilizing FERC Form 1 Data Attachment O Page 1 of 5 Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/2019 Utilizing FERC Form 1 Data Northern Indiana Public Service Company LLC Line Allocated No.

More information

Midwest Independent Transmission System Operator, Inc. Duke Energy Ohio, Inc. and Duke Energy Kentucky, Inc. Docket No. ER

Midwest Independent Transmission System Operator, Inc. Duke Energy Ohio, Inc. and Duke Energy Kentucky, Inc. Docket No. ER Lori A. Spence Deputy General Counsel Direct Dial: 317-249-5442 E-mail: lspence@misoenergy.org November 2, 2011 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street,

More information

System Load * Days in Month Weighted Load In Month Effective by Month January 2, ,727 February 2, ,665 March 2, ,515

System Load * Days in Month Weighted Load In Month Effective by Month January 2, ,727 February 2, ,665 March 2, ,515 NIPSCO Aggregate 206 True-up Calculations Instructions: Inputs are indicated by light yellow highlighted cells with blue bold font. For "Company Name" be sure to use our standard abbreviations or check

More information

Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/15 Utilizing FERC Form 1 Data

Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/15 Utilizing FERC Form 1 Data Attachment O Page 1 of 5 Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/15 Utilizing FERC Form 1 Data Northern Indiana Public Service Company Line Allocated No. Amount

More information

Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/17 Utilizing FERC Form 1 Data

Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/17 Utilizing FERC Form 1 Data Attachment O Page 1 of 5 Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/17 Utilizing FERC Form 1 Data Northern Indiana Public Service Company Line Allocated No. Amount

More information

1 GROSS REVENUE REQUIREMENT (page 3, line 31, column 5) $ 121,165,696

1 GROSS REVENUE REQUIREMENT (page 3, line 31, column 5) $ 121,165,696 Attachment O Page 1 of 5 Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/14 Utilizing FERC Form 1 Data Line Allocated No. Amount 1 GROSS REVENUE REQUIREMENT (page 3, line

More information

Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/2016 Utilizing FERC Form 1 Data

Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/2016 Utilizing FERC Form 1 Data Attachment O Page 1 of 5 Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/2016 Utilizing FERC Form 1 Data Northern Indiana Public Service Company Line Allocated No. Amount

More information

First Revised Sheet No. 2758L. Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/10 Utilizing FERC Form 1 Data VECTREN

First Revised Sheet No. 2758L. Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/10 Utilizing FERC Form 1 Data VECTREN Midwest ISO FERC Electric Tariff, Fourth Revised Volume No. 1 First Revised Sheet No. 2758L Superseding Original Sheet No. 2758L Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended

More information

ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC

ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC 20004-1404

More information

Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/2018 Utilizing FERC Form 1 Data

Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/2018 Utilizing FERC Form 1 Data page 1 of 5 Thirteen Monthly Balances Composite Depreciation Rates Line Allocated No. Amount 1 GROSS REVENUE REQUIREMENT (page 3, line 31) $ 601,791,927 REVENUE CREDITS (Note T) Total Allocator 2 Account

More information

Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/2015 Utilizing FERC Form 1 Data

Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/2015 Utilizing FERC Form 1 Data page 1 of 5 Thirteen Monthly Balances Composite Depreciation Rates Line Allocated No. Amount 1 GROSS REVENUE REQUIREMENT (page 3, line 31) $ 565,724,391 REVENUE CREDITS (Note T) Total Allocator 2 Account

More information

In addition to this transmittal letter and associated records for the etariff database, this filing includes:

In addition to this transmittal letter and associated records for the etariff database, this filing includes: 1050 Thomas Jefferson Street, NW Seventh Floor Washington, DC 20007 (202) 298-1800 Phone (202) 338-2416 Fax SUBMITTED VIA E-TARIFF FILING January 4, 2017 Kimberly D. Bose Secretary Federal Energy Regulatory

More information

Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/2019 Utilizing FERC Form 1 Data

Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/2019 Utilizing FERC Form 1 Data page 1 of 5 Thirteen Monthly Balances Composite Depreciation Rates Line Allocated No. Amount 1 GROSS REVENUE REQUIREMENT (page 3, line 31) $ 575,738,213 REVENUE CREDITS (Note T) Total Allocator 2 Account

More information

Southwestern Public Service Company. Transmission. Formula Rate Template. and Supporting Worksheets. Schedule 1 Annual Revenue Requirement

Southwestern Public Service Company. Transmission. Formula Rate Template. and Supporting Worksheets. Schedule 1 Annual Revenue Requirement Transmission Formula Rate Template and Supporting Worksheets Schedule 1 Annual Revenue Requirement For the 2014 TrueUp For the Period January 1, 2014 through December 31, 2014 Rate Formula Template Table

More information

(1) (2) (3) (4) (5) 1 GROSS REVENUE REQUIREMENT (page 3, line 47) $

(1) (2) (3) (4) (5) 1 GROSS REVENUE REQUIREMENT (page 3, line 47) $ page 1 of 5 Attachment H Formula Rate NonLevelized Rate Formula Template For the 12 months ended 12/31/2018 Utilizing FERC Form 1 Data (1) (2) (3) (4) (5) Line Allocated No. Amount 1 GROSS REVENUE REQUIREMENT

More information

January 25, By Electronic Filing

January 25, By Electronic Filing Gary J. Newell P 202.370.0137 F 202.370.0143 gnewell@jsslaw.com Jennings, Strouss & Salmon, P.L.C. 1350 I Street, NW Suite 810 Washington, D.C. 200053305 jsslaw.com January 25, 2019 By Electronic Filing

More information

July 15, 2015 VIA ELECTRONIC FILING

July 15, 2015 VIA ELECTRONIC FILING July 15, 2015 VIA ELECTRONIC FILING The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20246 Re: Southwest Power Pool, Inc., Docket No.

More information

Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/10 Utilizing FERC Form 1 Data

Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/10 Utilizing FERC Form 1 Data Midwest ISO First Revised Sheet No. 2647 FERC Electric Tariff, Fourth Revised Volume No. 1 Superseding Original Sheet No. 2647 page 1 of 5 Thirteen Monthly Balances Composite Depreciation Rates Line Allocated

More information

Total Network Revenue Requirement per Attachment O $ 463,230,109. Network Billings $ (462,862,216) True-up to be collected in 2011 $ 367,893

Total Network Revenue Requirement per Attachment O $ 463,230,109. Network Billings $ (462,862,216) True-up to be collected in 2011 $ 367,893 Estimated Network Revenue Requirement True-up For the Year Ended December 31, 2009 Total Network Revenue Requirement per $ 463,230,109 Network Billings $ (462,862,216) True-up to be collected in 2011 $

More information

Formula Rate - Non-Levelized For the 12 months ended 12/31/2015 Rate Formula Template Utilizing EKPC 2015 Form FF1 Data (ver.

Formula Rate - Non-Levelized For the 12 months ended 12/31/2015 Rate Formula Template Utilizing EKPC 2015 Form FF1 Data (ver. page 1 of 5 Line Allocated No. Amount 1 GROSS REVENUE REQUIREMENT (page 3, line 29) 72,070,265 REVENUE CREDITS Note A Total Allocator 2 Account No. 454 (page 4, line 34) 152,462 TP 1.00000 152,462 3 Account

More information

July 21, Southwest Power Pool, Inc., Docket No. ER Submission of Response to Request for Additional Information

July 21, Southwest Power Pool, Inc., Docket No. ER Submission of Response to Request for Additional Information July 21, 2016 VIA ELECTRONIC FILING Penny Murrell Director, Division of Electric Power Regulation-Central Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: Southwest

More information

5.2 Transmission Congestion Credit Calculation Eligibility.

5.2 Transmission Congestion Credit Calculation Eligibility. 5.2 Transmission Congestion culation. 5.2.1 Eligibility. (a) Except as provided in Section 5.2.1(b), each FTR Holder shall receive as a Transmission Congestion Credit a proportional share of the total

More information

5.2 Transmission Congestion Credit Calculation Eligibility.

5.2 Transmission Congestion Credit Calculation Eligibility. 5.2 Transmission Congestion Credit Calculation. 5.2.1 Eligibility. (a) Except as provided in Section 5.2.1(b), each FTR Holder shall receive as a Transmission Congestion Credit a proportional share of

More information

Calculate Net Annual Transmission Revenue Requirements (ATRR) and Rates for SPP Tariff. Total Transmission A. Zonal Net ATRR 1 Gross ATRR $60,516,589

Calculate Net Annual Transmission Revenue Requirements (ATRR) and Rates for SPP Tariff. Total Transmission A. Zonal Net ATRR 1 Gross ATRR $60,516,589 Page 1 Formula-based Rate Template Calculate Net Annual Transmission Revenue Requirements (ATRR) and Rates for SPP Tariff Line No. Acct Description Notes Total Transmission A. Zonal Net ATRR 1 Gross ATRR

More information

Calculate Net Annual Transmission Revenue Requirements (ATRR) and Rates for SPP Tariff. Total Transmission A. Zonal Net ATRR 1 Gross ATRR $48,861,618

Calculate Net Annual Transmission Revenue Requirements (ATRR) and Rates for SPP Tariff. Total Transmission A. Zonal Net ATRR 1 Gross ATRR $48,861,618 Page 1 Formula-based Rate Template Calculate Net Annual Transmission Revenue Requirements (ATRR) and Rates for SPP Tariff Line Acct Description Notes Total Transmission A. Zonal Net ATRR 1 Gross ATRR $48,861,618

More information

Entergy Services, Inc., Docket No. ER Informational Filing of Annual Transmission Formula Rate Update

Entergy Services, Inc., Docket No. ER Informational Filing of Annual Transmission Formula Rate Update Entergy Services, Inc. 101 Constitution Ave., N.W. Suite 200 East Washington, DC 20001 Tel: 202 530 7323 Fax: 202 530 7350 E-mail: mgriffe@entergy.com Michael C. Griffen Assistant General Counsel Federal

More information

ITC Midwest 2014 Attachment O True-Up Presentation. Presenter: David Grover Manager, Transmission Pricing July 8, 2015

ITC Midwest 2014 Attachment O True-Up Presentation. Presenter: David Grover Manager, Transmission Pricing July 8, 2015 2014 Attachment O True-Up Presentation Presenter: David Grover Manager, Transmission Pricing July 8, 2015 Presentation Purpose Discuss the 2014 Annual True-Up posting Walk through the timeline and mechanics

More information

ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC

ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC 20004-1404 202-239-3300 Fax: 202-239-3333 www.alston.com September 1, 2016 To: Re: Parties to FERC Docket No. ER08-386-000 Potomac-Appalachian

More information

SCHEDULE FORMULA RATE FOR DETERMINATION OF ANNUAL TRANSMISSION REVENUE REQUIREMENT AND SCHEDULE 1 ANNUAL REVENUE REQUIREMENT

SCHEDULE FORMULA RATE FOR DETERMINATION OF ANNUAL TRANSMISSION REVENUE REQUIREMENT AND SCHEDULE 1 ANNUAL REVENUE REQUIREMENT SCHEDULE 10 FORMULA RATE FOR DETERMINATION OF ANNUAL TRANSMISSION REVENUE REQUIREMENT AND SCHEDULE 1 ANNUAL REVENUE REQUIREMENT This Schedule contains the Formula Rate that the Transmission Provider will

More information

2017 Actual Cost Attachment O, GG and MM Rate Template Presentation

2017 Actual Cost Attachment O, GG and MM Rate Template Presentation 2017 Actual Cost Attachment O, GG and MM Rate Template Presentation Dehn Stevens General Manager Transmission July 19, 2018 Meeting Purpose The purpose of today s meeting is to review the 2017 Attachments

More information

5.14 Installed Capacity Spot Market Auction and Installed Capacity Supplier Deficiencies LSE Participation in the ICAP Spot Market Auction

5.14 Installed Capacity Spot Market Auction and Installed Capacity Supplier Deficiencies LSE Participation in the ICAP Spot Market Auction 5.14 Installed Capacity Spot Market Auction and Installed Capacity Supplier Deficiencies 5.14.1 LSE Participation in the ICAP Spot Market Auction 5.14.1.1 ICAP Spot Market Auction When the ISO conducts

More information

ITC Holdings Corp. Fourth Quarter & Year End 2013 Investor Call February 27, 2014

ITC Holdings Corp. Fourth Quarter & Year End 2013 Investor Call February 27, 2014 ITC Holdings Corp. Fourth Quarter & Year End 2013 Investor Call February 27, 2014 Safe Harbor Language & Legal Disclosure This presentation contains certain statements that describe our management s beliefs

More information

RE: Notice of 2015 Annual Formula Rate Update Posting and Customer Meeting

RE: Notice of 2015 Annual Formula Rate Update Posting and Customer Meeting September 2, 2014 TO: All Interested Parties RE: Notice of 2015 Annual Formula Rate Update Posting and Customer Meeting In accordance with Section 1.3(a) of the Oklahoma Gas and Electric Company ( OG&E

More information

Cost Allocation Reform Update

Cost Allocation Reform Update Cost Allocation Reform Update Regional Expansion Criteria and Benefits Working Group May 18, 2017 Conditions Precedent for Regional Transmission Investment 1. Increased consensus regarding the issue(s)

More information

June 13, Informational Filing Public Service Electric and Gas Company, Annual True-Up Adjustment Docket No. ER

June 13, Informational Filing Public Service Electric and Gas Company, Annual True-Up Adjustment Docket No. ER Hesser G. McBride, Jr. Associate General Regulatory Counsel Law Department 80 Park Plaza, T5G, Newark, NJ 07102-4194 tel: 973.430.5333 fax: 973.430.5983 email: Hesser.McBride@pseg.com June 13, 2016 VIA

More information

Attachment 2 to Appendix IX Formula Rate Spreadsheet

Attachment 2 to Appendix IX Formula Rate Spreadsheet Attachment 2 to Appendix IX Formula Rate Spreadsheet Table of Contents Worksheet Name Schedule Purpose Overview Base TRR Components. BaseTRR 1 Full Development of Retail and Wholesale Base TRRs IFPTRR

More information

Attachment 2 to Appendix IX Formula Rate Spreadsheet

Attachment 2 to Appendix IX Formula Rate Spreadsheet Attachment 2 to Appendix IX Formula Rate Spreadsheet Table of Contents Worksheet Name Schedule Purpose Overview Base TRR Components. BaseTRR 1 Full Development of Retail and Wholesale Base TRRs IFPTRR

More information

Attachment 2 to Appendix IX Formula Rate Spreadsheet

Attachment 2 to Appendix IX Formula Rate Spreadsheet Attachment 2 to Appendix IX Formula Rate Spreadsheet Table of Contents Worksheet Name Schedule Purpose Overview Base TRR Components. BaseTRR 1 Full Development of Retail and Wholesale Base TRRs IFPTRR

More information

N. Am. Elec. Reliability Corp., 119 FERC 61,060, order on reh g, 120 FERC 61,260 (2007).

N. Am. Elec. Reliability Corp., 119 FERC 61,060, order on reh g, 120 FERC 61,260 (2007). The Honorable Kimberly D. Bose Secretary November 7, 2008 Page 2 Arkansas. SPP currently has 50 Members, serving more than 4 million customers in a 255,000 square-mile area covering all or part of eight

More information

Dkt. No. ER Draft Informational Filing. Table of Contents

Dkt. No. ER Draft Informational Filing. Table of Contents Table of Contents Worksheet Name Schedule Purpose Overview Base TRR Components. BaseTRR 1 Full Development of Retail and Wholesale Base TRRs. IFPTRR 2 Calculation of the Incremental Forecast Period TRR

More information

Dkt. No. ER Draft Informational Filing. Table of Contents

Dkt. No. ER Draft Informational Filing. Table of Contents Table of Contents Worksheet Name Schedule Purpose Overview Base TRR Components. BaseTRR 1 Full Development of Retail and Wholesale Base TRRs. IFPTRR 2 Calculation of the Incremental Forecast Period TRR

More information

GridLiance West Transco LLC (GWT) Formula Rate Index

GridLiance West Transco LLC (GWT) Formula Rate Index (GWT) Formula Rate Index Appendix III Main Body of the Formula Attachment 1 Revenue Credit Worksheet Attachment 2 Cost Support Attachment 2a Cost Support Attachment 2b Cost Support Attachment 3 Incentives

More information

Attachment 2 to Appendix IX Formula Rate Spreadsheet

Attachment 2 to Appendix IX Formula Rate Spreadsheet Attachment 2 to Appendix IX Formula Rate Spreadsheet Table of Contents Worksheet Name Schedule Purpose Overview Base TRR Components. BaseTRR 1 Full Development of Retail and Wholesale Base TRRs IFPTRR

More information

Attachment 2 to Appendix IX Formula Rate Spreadsheet

Attachment 2 to Appendix IX Formula Rate Spreadsheet Attachment 2 to Appendix IX Formula Rate Spreadsheet Table of Contents Worksheet Name Schedule Purpose Overview Base TRR Components. BaseTRR 1 Full Development of Retail and Wholesale Base TRRs IFPTRR

More information

TRANSMISSION OWNER ZONAL PLACEMENT PROCESS

TRANSMISSION OWNER ZONAL PLACEMENT PROCESS TRANSMISSION OWNER ZONAL PLACEMENT PROCESS Published July 2017 CONTENTS Section 1: Introduction, Scope & Steps... 1 Subsection A: Introduction To Zonal Placement... 1 Subsection B: Scope... 1 Subsection

More information

Formula Rate - Appendix A Estimate Notes FERC Form 1 Page # or Instruction 2015 Shaded cells are input cells Allocators

Formula Rate - Appendix A Estimate Notes FERC Form 1 Page # or Instruction 2015 Shaded cells are input cells Allocators Page 1 of 25 Formula Rate - Appendix A Estimate Notes FERC Form 1 Page # or Instruction 2015 Shaded cells are input cells Allocators 1 Transmission Wages Expense p354.21.b 5,926,573 2 Total Wages Expense

More information

Attachment 2 to Appendix IX Formula Rate Spreadsheet

Attachment 2 to Appendix IX Formula Rate Spreadsheet Attachment 2 to Appendix IX Formula Rate Spreadsheet Table of Contents Worksheet Name Schedule Purpose Overview Base TRR Components. BaseTRR 1 Full Development of Retail and Wholesale Base TRRs IFPTRR

More information

Re: Rockland Electric Company, Docket No. EL18-111

Re: Rockland Electric Company, Docket No. EL18-111 Margaret Comes Associate Counsel Rockland Electric Company 4 Irving Place, Room 1815-S, New York, NY 10003 Tel.: 212-460-3013 Email: comesm@coned.com May 14, 2018 Hon. Kimberly D. Bose Secretary Federal

More information

December 29, American Electric Power Service Corporation Docket No. ER

December 29, American Electric Power Service Corporation Docket No. ER American Electric Power 1 Riverside Plaza Columbus, OH 43215 AEP.com Honorable Kimberly D Bose Secretary Federal Energy Regulatory Commission 888 First St., N.E. Washington D.C. 20426 December 29, 2015

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION EXHIBIT SCE-4 EXHIBIT TO THE TESTIMONY OF MR. BERTON J.

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION EXHIBIT SCE-4 EXHIBIT TO THE TESTIMONY OF MR. BERTON J. UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) Southern California Edison Company ) ) Dkt. No. ER18- -000 EXHIBIT SCE-4 EXHIBIT TO THE TESTIMONY OF MR. BERTON J. HANSEN ON BEHALF

More information

PROTOCOLS AS INCORPORATED INTO WESTAR S OATT

PROTOCOLS AS INCORPORATED INTO WESTAR S OATT PROTOCOLS AS INCORPORATED INTO WESTAR S OATT FERC Electric Tariff ORIGINAL Sheet No. 228 ATTACHMENT H-2 Formula Rate Implementation Protocols I. Annual Update 1. The rate formula template in Attachment

More information

RATES FOR EXPORT TRANSMISSION SERVICE

RATES FOR EXPORT TRANSMISSION SERVICE Page of RATES FOR EXPORT TRANSMISSION.0 INTRODUCTION The OEB has directed Hydro One Transmission to monitor and report to the Board, at the next rate case, on the functioning of the Export Transmission

More information

Appendix 1 Duquesne Light Company Attachment H -17A Page 1 of 25 Formula Rate - Appendix A True-Up Notes FERC Form 1 Page # or Instruction 2017 Shaded cells are input cells Allocators 1 Transmission Wages

More information

History of Cost Allocation within MISO RECB TF. January 29, 2015

History of Cost Allocation within MISO RECB TF. January 29, 2015 History of Cost Allocation within MISO RECB TF January 29, 2015 Cost Allocation FERC Orders, Filings, and Rulings Cost allocation for MISO began with Order 2003 which instituted a pro forma Generator Interconnection

More information

GridLiance West Transco LLC (GWT) Formula Rate Index

GridLiance West Transco LLC (GWT) Formula Rate Index (GWT) Formula Rate Index Appendix III Main Body of the Formula Attachment 1 Revenue Credit Worksheet Attachment 2 Cost Support Attachment 2a Cost Support Attachment 2b Cost Support Attachment 3 Incentives

More information

ATTACHMENT A clean copy of the revised tariff sheets (Exhibit No. AEP102A) Exhibit No. AEP 102A Page 1 of 44 Southwest Power Pool pro forma Third Revised Sheet No. 94 FERC Electric Tariff Superseding Second

More information

May 8, Response to Show Cause Order, Filing of Revised Tariff Sheet And Request for Any Necessary Waivers. The Dayton Power and Light Company

May 8, Response to Show Cause Order, Filing of Revised Tariff Sheet And Request for Any Necessary Waivers. The Dayton Power and Light Company The Dayton Power and Light Company 1065 Woodman Drive, Dayton Ohio 45458 May 8, 2018 Via etariff Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington,

More information

Overview. Overview of SCE Retail Base TRR. SCE's retail Base Transmission Revenue Requirement is the sum of the following components:

Overview. Overview of SCE Retail Base TRR. SCE's retail Base Transmission Revenue Requirement is the sum of the following components: Table of Contents Worksheet Name Overview BaseTRR IFPTRR TrueUpAdjust TUTRR ROR PlantInService PlantStudy AccDep ADIT CWIP PHFU AbandonedPlant WorkCap IncentivePlant IncentiveAdder PlantAdditions Depreciation

More information

September 1, Southern California Edison Company/ Docket No. ER

September 1, Southern California Edison Company/ Docket No. ER Anna J. Valdberg Senior Attorney anna.valdberg@sce.com September 1, 2011 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 Re: Southern California

More information

ARKANSAS PUBLIC SERVICE COMMISSION

ARKANSAS PUBLIC SERVICE COMMISSION ARKANSAS PUBLIC SERVICE COMMISSION First Revised Sheet No. 4-9.1/34 Replacing: Original Sheet No. CenterPoint Energy Resources Corp. d/b/a CenterPoint Energy Arkansas Gas (Name of Company) Kind of Service:

More information

The following words and terms shall have the following meanings when used in this Tariff:

The following words and terms shall have the following meanings when used in this Tariff: Sheet 1 1. Introduction This tariff ( Tariff ) describes the terms and conditions under which an Applicant for an eligible distributed generation project ( DG Project ) will receive funding pursuant to

More information

PPL Electric Utilities Corporation

PPL Electric Utilities Corporation Page 1 of 22 ATTACHMENT H8G PPL Electric Utilities Corporation Formula Rate Appendix A Notes FERC Form 1 Page # or Instruction 2014 Data Shaded cells are input cells Allocators Wages & Salary Allocation

More information

October 8, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.

October 8, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. October 8, 2012 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: Duke Energy Carolinas, LLC; Carolina Power & Light Company;

More information

AEPTCo subsidiaries in PJM Transmission Cost of Service Formula Rate Utilizing Historic Cost Data for 2013 and Projected Net Plant at Year-End 2014

AEPTCo subsidiaries in PJM Transmission Cost of Service Formula Rate Utilizing Historic Cost Data for 2013 and Projected Net Plant at Year-End 2014 Transmission Cost of Service Utilizing Historic Cost Data for 2013 and Projected Net Plant at YearEnd 2014 Projected TCOS Page 1 of 37 Line Transmission No. Amount 1 REVENUE REQUIREMENT (w/o incentives)

More information

MVP Postage Stamp Cost Allocation and Portfolio Requirement Regional Expansion Criteria and Benefits Working Group. September 28, 2017

MVP Postage Stamp Cost Allocation and Portfolio Requirement Regional Expansion Criteria and Benefits Working Group. September 28, 2017 MVP Postage Stamp Cost Allocation and Portfolio Requirement Regional Expansion Criteria and Benefits Working Group September 28, 2017 What is a Multi Value Project? A Multi Value Project is one or more

More information

AEPTCo subsidiaries in PJM Transmission Cost of Service Formula Rate Utilizing Historic Cost Data for 2014 and Projected Net Plant at Year-End 2015

AEPTCo subsidiaries in PJM Transmission Cost of Service Formula Rate Utilizing Historic Cost Data for 2014 and Projected Net Plant at Year-End 2015 AEPTCo subsidiaries in PJM Transmission Cost of Service Utilizing Historic Cost Data for 2014 and Projected Net Plant at YearEnd 2015 Projected TCOS Page 1 of 75 AEP OHIO TRANSMISSION COMPANY Line Transmission

More information

ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC

ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC 20004-1404

More information

R E S O L U T I O N. Passed by the Public Utility Board of the City of Rochester, Minnesota, this. President. Secretary

R E S O L U T I O N. Passed by the Public Utility Board of the City of Rochester, Minnesota, this. President. Secretary R E S O L U T I O N BE IT RESOLVED by the Public Utility Board of the City of Rochester, Minnesota, that the said Board in accordance with provisions of Minnesota Statutes Section 216B.164, Subdivision

More information

UNS Electric, Inc. Rates for Transmission Service For June 1, 2016 Through May 31, 2017 Data For Period Ending December 31, 2015

UNS Electric, Inc. Rates for Transmission Service For June 1, 2016 Through May 31, 2017 Data For Period Ending December 31, 2015 UNS Electric, Inc. Rates for Transmission Service For June 1, 2016 Through May 31, 2017 Data For Period Ending December 31, 2015 Mohave Total Line Division Division Company 1 2016 Revenue Requirements

More information

9. RELATIONSHIP BETWEEN ISO AND PARTICIPATING TOs. Each Participating TO shall enter into a Transmission Control Agreement with the

9. RELATIONSHIP BETWEEN ISO AND PARTICIPATING TOs. Each Participating TO shall enter into a Transmission Control Agreement with the First Revised Sheet No. 121 ORIGINAL VOLUME NO. I Replacing Original Sheet No. 121 9. RELATIONSHIP BETWEEN ISO AND PARTICIPATING TOs. 9.1 Nature of Relationship. Each Participating TO shall enter into

More information

MISO SCHEDULE 39 Multi-Value Project Financial Obligations and Cost Recovery SCHEDULES SCHEDULE 39

MISO SCHEDULE 39 Multi-Value Project Financial Obligations and Cost Recovery SCHEDULES SCHEDULE 39 SCHEDULE 39 MULTI-VALUE PROJECT FINANCIAL OBLIGATIONS AND COST RECOVERY FOR WITHDRAWING TRANSMISSION OWNERS I. Definitions Any capitalized terms not defined in this Schedule 39 shall have the meaning as

More information

Office Fax pepco.com

Office Fax pepco.com Amy L. Blauman Assistant General Counsel EP1132 701 Ninth Street NW Washington, DC 20068-0001 Office 202.872.2122 Fax 202.331.6767 pepco.com alblauman@pepcoholdings.com May 16, 2016 Ms. Kimberly D. Bose

More information

Office Fax delmarva.com

Office Fax delmarva.com Amy L. Blauman Assistant General Counsel EP1132 701 Ninth Street NW Washington, DC 20068-0001 Office 202.872.2122 Fax 202.331.6767 delmarva.com alblauman@pepcoholdings.com May 16, 2016 Ms. Kimberly D.

More information

Potomac Electric Power Company ( Pepco ), Docket No. ER Informational Filing of 2017 Formula Rate Annual Update; Notice of Annual Meeting

Potomac Electric Power Company ( Pepco ), Docket No. ER Informational Filing of 2017 Formula Rate Annual Update; Notice of Annual Meeting Amy L. Blauman Assistant General Counsel Edison Place 701 Ninth Street NW Washington, DC 20068-0001 Office 202.872.2122 Fax 202.331.6767 pepco.com alblauman@pepcoholdings.com May 12, 2017 Ms. Kimberly

More information

Natural Gas Pipeline Company of America LLC Part 6. Eighth Revised Volume No. 1 Version GENERAL TERMS AND CONDITIONS

Natural Gas Pipeline Company of America LLC Part 6. Eighth Revised Volume No. 1 Version GENERAL TERMS AND CONDITIONS Natural Gas Pipeline Company of America LLC Part 6 FERC Gas Tariff General Terms and Conditions Eighth Revised Volume No. 1 Version 0.0.0 GENERAL TERMS AND CONDITIONS Issued On: September 30, 2010 Effective

More information

APPENDIX IX ATTACHMENT 1 FORMULA RATE PROTOCOLS

APPENDIX IX ATTACHMENT 1 FORMULA RATE PROTOCOLS APPENDIX IX ATTACHMENT 1 FORMULA RATE PROTOCOLS 1. INTRODUCTION SCE shall calculate its Base Transmission Revenue Requirement ( Base TRR ), as defined in Section 3.6 of the main definitions section of

More information

Injection / Withdrawal CARP

Injection / Withdrawal CARP Injection / Withdrawal CARP Decisions Note: To inform the RECB Stakeholders at their upcoming September 30 th meeting, this version of the Decision Tree contains the decisions made by CARP (in bold/italics)

More information

FRR Alternative. Jeff Bastian Manager, Capacity Market Operations Market Implementation Committee April 10, 2019 PJM

FRR Alternative. Jeff Bastian Manager, Capacity Market Operations Market Implementation Committee April 10, 2019 PJM FRR Alternative Jeff Bastian Manager, Capacity Market Operations Market Implementation Committee April 10, 2019 FRR Alternative The Fixed Resource Requirement ( FRR ) Alternative provides an alternative

More information

Guide to Customer Contributions and FortisAlberta Investment

Guide to Customer Contributions and FortisAlberta Investment Guide to Customer Contributions and FortisAlberta Investment April 1, 2018 TABLE OF CONTENTS Introduction... 3 1. Customer contributions... 4 1.1. Customer Contributions... 4 1.2. Optional Supply Facilities...

More information

Montana-Dakota Utilities Co. A Division of MDU Resources Group, Inc. 400 N 4 th Street Bismarck, ND 58501

Montana-Dakota Utilities Co. A Division of MDU Resources Group, Inc. 400 N 4 th Street Bismarck, ND 58501 4 th Revised Sheet No. 30 Canceling 3 rd Revised Sheet No. 30 Page 1 of 6 1. Applicability: This rate schedule constitutes a cost of gas (COG) provision and specifies the procedure to be utilized to adjust

More information

Index. Rate Formula Template. For the 12 months ended 12/31/ New York Transco LLC

Index. Rate Formula Template. For the 12 months ended 12/31/ New York Transco LLC Index Rate Formula Template Utilizing FERC Form 1 Data New York Transco LLC Projected Annual Transmission Revenue Requirement For the 12 months ended 12/31/ Appendix A Main body of the Formula Rate Attachment

More information

MISO Cost Allocation Response. RECBWG February 15, 2018

MISO Cost Allocation Response. RECBWG February 15, 2018 MISO Cost Allocation Response RECBWG February 15, 2018 MISO Cost Allocation Response: February 2018 Context The overall objective of the MISO transmission cost allocation methodology is to align who pays

More information

Rate Formula Template (A) (B) (C) (D) (E) (F)

Rate Formula Template (A) (B) (C) (D) (E) (F) Page 1 of 4 Rate Formula Template (A) (B) (C) (D) (E) (F) Line Allocated No. Reference Worksheet/Note Amount A. NETWORK SERVICE 1 GROSS REVENUE REQUIREMENT Page 2, line 26, col. (F) $ 116,851,990 REVENUE

More information

ARKANSAS PUBLIC SERVICE COMMISSION

ARKANSAS PUBLIC SERVICE COMMISSION ARKANSAS PUBLIC SERVICE COMMISSION Original Sheet No. 44.1 Schedule Sheet 1 of 33 Including Attachments Entergy Arkansas, Inc. Name of Company Kind of Service: Electric Part III. Title: Formula Rate Plan

More information

Station Power Standby Service Schedule Designation R3 Standard Contract Rider No. 3

Station Power Standby Service Schedule Designation R3 Standard Contract Rider No. 3 Station Power Standby Service Schedule Designation R3 Standard Contract Rider No. 3 DE 963-1826 2/17 THIS RIDER, dated 20, is attached to and becomes a part of an electric service agreement dated 20, between,

More information

ENTERGY LOUISIANA, LLC

ENTERGY LOUISIANA, LLC Page 32.1 ENTERGY LOUISIANA, LLC ELECTRIC SERVICE Effective Date: October 1, 2015 Filed Date: August 31, 2015 Supersedes: IS Revision 3 effective 6/1/14 Revision 0 Schedule Consists of: Five Pages EXPERIMENTAL

More information

Rate Formula Template Utilizing FERC Form 1 for the 12 months ended 12/31/2011. Oklahoma Gas and Electric Company. Index of Worksheets

Rate Formula Template Utilizing FERC Form 1 for the 12 months ended 12/31/2011. Oklahoma Gas and Electric Company. Index of Worksheets Rate Formula Template Utilizing FERC Form 1 for the 12 months ended 12/31/2011 (Enter whether "Projected Data" or "Actual Data") Projected Data Attachment H Addendum 2A Oklahoma Gas and Electric Company

More information

Transmission Formula Rate 2017 Annual Update. June 23, 2017

Transmission Formula Rate 2017 Annual Update. June 23, 2017 Transmission Formula Rate 2017 Annual Update June 23, 2017 1 Topics Introductions Annual Update Overview 2017 Projection and 2016 True-Up Schedule 1 Additional Information Questions and Discussion 2 OASIS

More information

ATTACHMENT NO POPULATED FORMULA RATE

ATTACHMENT NO POPULATED FORMULA RATE ATTACHMENT NO. 1 2008 POPULATED FORMULA RATE Attachment No. 1 Page 1 of 27 ATTACHMENT H13A Commonwealth Edison Company Formula Rate Appendix A Notes FERC Form 1 Page # or Instruction Shaded cells are input

More information

The Low Voltage Access Charge shall be determined in accordance with the ISO Tariff.

The Low Voltage Access Charge shall be determined in accordance with the ISO Tariff. 5. Access Charges and Transmission Rates. 5.1 Low Voltage Access Charge. The Low Voltage Access Charge shall be determined in accordance with the ISO Tariff. The Low Voltage Access Charge customer shall

More information

January 22, Compliance Filing of Virginia Electric and Power Company Docket No. EL

January 22, Compliance Filing of Virginia Electric and Power Company Docket No. EL Troutman Sanders LLP 401 9th Street, N. W., Suite 1000 Washington, D.C. 200042134 troutman.com Anne K. Dailey anne.dailey@troutman.com January 22, 2019 The Honorable Kimberly D. Bose, Secretary Federal

More information

DUKE ENERGY OHIO REQUEST FOR PROPOSALS FOR PEAKING/INTERMEDIATE POWER SUPPLY IN RESPONSE TO OHIO SENATE BILL 221

DUKE ENERGY OHIO REQUEST FOR PROPOSALS FOR PEAKING/INTERMEDIATE POWER SUPPLY IN RESPONSE TO OHIO SENATE BILL 221 DUKE ENERGY OHIO REQUEST FOR PROPOSALS FOR PEAKING/INTERMEDIATE POWER SUPPLY IN RESPONSE TO OHIO SENATE BILL 221 DUKE ENERGY OHIO Table of Contents Section Description Page 1.0 Purpose of Request for Proposals

More information

CAISO. Settlements & Billing. CRR Hourly Settlement CC 6700

CAISO. Settlements & Billing. CRR Hourly Settlement CC 6700 CAISO Settlements & Billing CRR Hourly Settlement CC 6700 Table of Contents 1. Purpose of Document 3 2. Introduction 3 2.1 Background 3 2.2 Description 4 3. Charge Code Requirements 4 3.1 Business Rules

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 26. Transmission Rates and Charges... 2 26.1 Access Charge... 2 26.1.1 Publicly Owned Electric Utilities Access Charge... 5 26.1.2 Regional Access Charge Settlement... 6 26.1.3 Distribution

More information

Schedule 19 POWER PURCHASES FROM COGENERATION AND SMALL POWER PRODUCTION QUALIFYING FACILITIES

Schedule 19 POWER PURCHASES FROM COGENERATION AND SMALL POWER PRODUCTION QUALIFYING FACILITIES I. APPLICABILITY & AVAILABILITY This Schedule is applicable to any Cogenerator or Small Power Producer (Qualifying Facility), as defined in the Public Utility Regulatory Policies Act of 1978 (PURPA), which

More information