1 Risky Business Asset Management for Aging Hydro Plants Bonneville Power Administration Northwest Hydroelectric Association February 2016
2 The Federal Columbia River Power System 31 Powerplants (21 Corps, 10 Reclamation) 196 Generating Units 22,060 MW 60% of region s hydroelectric capacity 65 million+ MWh/year 2
3 Asset Age Over 30% of the assets in the FCRPS are at or exceeding their design life. Of those assets, over 60% are related to unit reliability and have direct impacts on generation. 3
4 Assessing Asset Condition The FCRPS uses the hydroamp Condition Assessment framework to assess the condition of over 5500 assets. The hydroamp guide contains specific instructions for the condition assessment of: Turbines Generators (Rotors and Stators) Excitation Systems Governors Transformers Circuit Breakers Surge Arrestors Cranes Batteries Compressed Air Systems Emergency Closure Gates and Valves Penstocks Additionally, a more generic Balance of Plant guide can be used to assess the condition of more than eighty additional components. 4
5 Projecting Condition Degradation The condition of each asset is projected over time using degradation curves derived from FCRPS and available industry data. In the chart above, the average equipment score of each plant for a given piece of equipment is plotted against the projected degradation rate. 5
6 Relating Condition to a Probability of Failure Using a combination of industry failure data as well as expert opinion elicitation, hydroamp condition is mapped to a probability of failure for each equipment type. 6
7 Calculating Risk With an understanding of condition, how it changes without intervention and how it relates to a probability of failure, risk can be forecast over time. Using Copperleaf s C55, the FCRPS forecasts the following risks and costs: Lost Generation Risk: Equipment failure may also result in longer outages and, thus, more lost generation than if replaced on a planned basis. This cost risk increases as equipment condition degrades over time. Direct Cost Risk: If equipment fails during the deferral period, intervention costs may be incrementally higher for collateral damage and planning, procurement, and scheduling inefficiencies (overtime, emergency hiring, contract premiums, etc.). This cost risk also increases as equipment condition degrades over time. Lost Efficiency Opportunity: Some equipment replacements (turbine runners, transformers and generator windings) reduce efficiency losses. Deferring replacement results in a lost opportunity to capture increased generation from higher efficiency equipment. Replacement Cost: Typically, the longer the replacement can be deferred, the lower the present value of its cost. 7
8 Optimizing Replacement Timing The Total Cost is the present value sum of replacement costs, risk costs and LEO. The cost minimum on this curve is the point at which financial risk is forecasted to begin growing faster than the benefit of investment deferral and represents the optimum time to forecast replacement to minimize lifecycle cost. 8
9 $000s Prioritizing Investment Capital Program Forecast For a given program level, the C55 Asset Analytics will fill in investment based on the cost minimization algorithm. Assets with lower deferral costs are deferred in favor of assets with higher deferral costs when a budget constraints are introduced. The chart above displays the results at a $300 million budget level from BPA s 2014 Capital Investment Review materials. 9
10 The Cost of Deferral High Deferral Cost Low Deferral Cost 10
11 Sensitivity Analysis Sensitivity analyses can help zero in on the optimal program level by analyzing both the qualitative and quantitative results. Running C55 Asset Analytics at different Capital Program levels can quickly show the impacts on the Condition, Age and Risk of assets over time. 11
12 Condition Forecast for a Given Capital Program 12
13 Condition Forecast for a Higher Capital Program 13
14 Lost Generation Risk Forecast 14
15 Non-Routine Expense Forecast 15
16 NPV of Different Capital Program Levels 16
17 Gordon Ashby
HydroAMP: Hydropower Asset Management
HydroAMP: Hydropower Asset Management Presented by Lori Rux,, Ph.D., P.E. Hydroelectric Design Center Tri-Service Infrastructure Systems Conference - August 2005 1 What is HydroAMP? Asset management tools
More informationAddressing the Tsunami of Aging Assets and Infrastructure
Addressing the Tsunami of Aging Assets and Infrastructure Asset Management WEI Operations Conference EXCHANGING EXPERTISE SINCE 1893 Addressing the Tsunami of Aging Assets and Infrastructure Federal Columbia
More informationCAPITAL BUDGET - REGULATED HYDROELECTRIC
Filed: 0-0- EB-0-000 Page of 0 0 CAPITAL BUDGET - REGULATED HYDROELECTRIC.0 PURPOSE This evidence provides an overview of the capital budget for OPG s regulated hydroelectric facilities for the historical
More informationCA-NLH-59 Depreciation Methodology and Asset Service Lives Page 1 of 3
CA-NLH-59 and Asset Service Lives Page 1 of 3 1 2 3 Q. Re: Calculation Procedure: Please state all reasons the Company did not propose a change to the Equal Life Group calculation procedure. To the extent
More informationCAPITAL EXPENDITURES - REGULATED HYDROELECTRIC
Filed: 0-0- EB-0-0 Exhibit D Tab Schedule Page of 0 0 0 CAPITAL EXPENDITURES - REGULATED HYDROELECTRIC.0 PURPOSE This evidence provides an overview of the capital expenditures for OPG s regulated hydroelectric
More informationISO Rules Part 500 Facilities Division 502 Technical Requirements Section Generating Unit Operating Requirements
Applicability 1 Section 502.6 applies to: (a) the operator of a generating unit that is: (i) synchronized to the interconnected electrical system; and (ii) directly connected to the transmission system
More informationRE: Initial Comments on the Integrated Program Review and Debt Service Options
July 6, 2010 Mr. Steve Wright Administrator Bonneville Power Administration 905 NE 11 th Street Portland, OR 97232 RE: Initial Comments on the Integrated Program Review and Debt Service Options Dear Mr.
More informationMarch 13, Elliot Mainzer Administrator Bonneville Power Administration 911 NE 11th Ave Portland, OR RE: Integrated Program Review - 2
March 13, 2017 Elliot Mainzer Administrator Bonneville Power Administration 911 NE 11th Ave Portland, OR 97232 RE: Integrated Program Review - 2 Dear Administrator Mainzer: Thank you for the opportunity
More informationFiscal Year 2013 Budget and Long Range Plan Columbia Generating Station. Brad Sawatzke VP, Nuclear Generation/CNO March 20, 2012
Fiscal Year 2013 Budget and Long Range Plan Columbia Generating Station Brad Sawatzke VP, Nuclear Generation/CNO March 20, 2012 Introduction Our goal is to provide safe, reliable, cost effective power
More informationAPPENDIX B: PORTFOLIO OPTIMIZATION MODEL
APPENDIX B: PORTFOLIO OPTIMIZATION MODEL PUBLIC UTILITY DISTRICT #1 OF SNOHOMISH COUNTY Prepared by Generation, Power, Rates, and Transmission Management Division Snohomish County PUD DRAFT 2017 Integrated
More informationASSESSMENT OF REGULATED ASSET DEPRECIATION RATES AND GENERATING STATION LIVES DECEMBER 2011
ONTARIO POWER GENERATION INC. TORONTO, ONTARIO ASSESSMENT OF REGULATED ASSET DEPRECIATION RATES AND GENERATING STATION LIVES DECEMBER 2011 Harrisburg, Pennsylvania Calgary, Alberta Valley Forge, Pennsylvania
More information2011 IRP Public Input Meeting. October 5, Pacific Power Rocky Mountain Power PacifiCorp Energy
2011 IRP Public Input Meeting October 5, 2010 Pacific Power Rocky Mountain Power PacifiCorp Energy Agenda Morning Session IRP Schedule Update Energy Gateway Transmission Construction Update and Evaluation
More informationWithin-Hour Capacity Markets in the Northwest. July 22, John Wellschlager Bonneville Power, Trading Floor Account Executive
Within-Hour Capacity Markets in the Northwest July 22, 2015 John Wellschlager Bonneville Power, Trading Floor Account Executive Slide 1 Why is BPA in the market for within-hour capacity? BPA s physical
More information10 Economic Uncertainty Analysis Probabilistic Analysis and Sensitivities Chapter Overview... 1
Table of Contents Economic Uncertainty Analysis....0 Chapter Overview.... Probabilistic Analysis with Scenarios..... Methodology...... Determination of Highest Impact Factors...... Combinations of Highest
More informationCOMPARISON OF NUCLEAR OUTAGE OM&A
Filed: 0-0- Page of 0 0 0 COMPARISON OF NUCLEAR OUTAGE OM&A.0 PURPOSE This evidence presents period-over-period comparisons of outage OM&A by station for 0-0 in support of the approval of OPG s forecast
More informationA New Resource Adequacy Standard for the Pacific Northwest. Background Paper
A New Resource Adequacy Standard for the Pacific Northwest Background Paper 12/6/2011 A New Resource Adequacy Standard for the Pacific Northwest Background Paper CONTENTS Abstract... 3 Summary... 3 Background...
More informationRisk Management Plan for the <Project Name> Prepared by: Title: Address: Phone: Last revised:
for the Prepared by: Title: Address: Phone: E-mail: Last revised: Document Information Project Name: Prepared By: Title: Reviewed By: Document Version No: Document Version Date: Review Date:
More informationEnergy Conservation Resource Strategy
Energy Conservation Resource Strategy 2008-2012 April 15, 2008 In December 2004, EWEB adopted the most recent update to the Integrated Electric Resource Plan (IERP). Consistent with EWEB s three prior
More information2017/ /20 SERVICE PLAN
SERVICE PLAN September 2017 For more information on Columbia Basin Trust contact: 300 445 13 Avenue Castlegar, B.C. V1N 1G1 1.800.505.8998 info@cbt.org Or visit our website at ourtrust.org. Board Chair
More informationUK Power Networks. Overall Cost Benefit Analysis
UK Power Networks Overall Cost Benefit Analysis Contents 1 Executive Summary 3 1.1 Analysis Conclusions 3 1.2 Summary Table 4 2 Introduction 5 2.1 Scope 5 2.2 Input Parameters 6 2.3 Asset Replacement/Refurbishment
More informationMODULE 5 PROJECT RISK MANAGEMENT, PROCUREMENT AND CONTRACTS
Advanced Project Management MODULE 5 PROJECT RISK MANAGEMENT, PROCUREMENT AND CONTRACTS 06 07 November 2018 Facilitator: Mr Mondli Mbambo Module Purpose Project Risk & Procurement Managment Knowledge Risk
More informationBC HYDRO S ANNUAL REPORT 2007 REPORTING ON OUR TRIPLE BOTTOM LINE PERFORMANCE MAKE A DIFFERENCE
BC HYDRO S ANNUAL REPORT 2007 REPORTING ON OUR TRIPLE BOTTOM LINE PERFORMANCE MAKE A DIFFERENCE c o n t e n t s About BC Hydro and this Report... 4 Message from the Chair and President and CEO... 5 Business
More informationESG. Climate Special Issue: Sink or Swim. matters FEATURES:
ESG matters Environmental, Social and Governance thought piece Issue Climate Special Issue: Sink or Swim FEATURES: 08 Guest article by Christiana Figueres, Executive Secretary of the UN Framework Convention
More informationProject Selection Risk
Project Selection Risk As explained above, the types of risk addressed by project planning and project execution are primarily cost risks, schedule risks, and risks related to achieving the deliverables
More informationFiscal Year 2016 Columbia Generating Station Annual Operating Budget
Fiscal Year 2016 Columbia Generating Station Annual Operating Budget Table of Contents Table Page Summary 3 Key Assumptions/Qualifications 4 Memorandum of Agreement (MOA) Table 1 5 Columbia Station Costs
More informationFiscal Year 2010 Columbia Generating Station Annual Operating Budget
Fiscal Year 2010 Columbia Generating Station Annual Operating Budget Table of Contents Table Page Summary 3 Key Assumptions/Qualifications 4 Memorandum of Agreement (MOA) Table 1 5 Columbia Station Costs
More informationPrototype Wind PPA Term Sheet
Prototype Wind PPA Term Sheet Background: This Prototype Wind PPA Term Sheet ( Term Sheet ) sets forth the current requirements that PSE wants the Respondent to address or incorporate into any proposal
More informationUncertainty, Risk and Electricity Sector Planning
Uncertainty, Risk and Electricity Sector Planning NATIONAL CONFERENCE OF STATE LEGISLATURES NATIONAL ASSOCIATION REGULATORY UTILITY COMMISSIONERS Transmission and Energy Portfolio Planning Workshop May
More informationFiscal Year 2013 Columbia Generating Station Annual Operating Budget
Fiscal Year 2013 Columbia Generating Station Annual Operating Budget Prepared 3/20/12 Table of Contents Table Page Summary 3 Key Assumptions/Qualifications 4 Memorandum of Agreement (MOA) Table 1 5 Columbia
More informationLong-Term Rate Forecast
Long-Term Rate Forecast OVERVIEW This brief provides background information on the Long-Term Rate Forecast (LTRF) used in the 2011 Integrated Resource Plan (IRP). It is similar to the report filed as Attachment
More informationCity of Glendale, Arizona Pavement Management Program
City of Glendale, Arizona Pavement Management Program Current Year Plan (FY 2014) and Five-Year Plan (FY 2015-2019) EXECUTIVE SUMMARY REPORT December 2013 TABLE OF CONTENTS TABLE OF CONTENTS I BACKGROUND
More informationElectricity Power System Planning
Chapter 3 Section 3.02 Ministry of Energy Electricity Power System Planning Standing Committee on Public Accounts Follow-Up on Section 3.05, 2015 Annual Report The Committee held a public hearing in November
More informationA Priority System for Allocating an O&M Budget
A Priority System for Allocating an O&M Budget Elsie Myers Martin Lee Merkhofer Lee Merkhofer Consulting This paper describes a priority system developed for Northern States Power to allocate its annual
More informationCAISO 15-Min Liquidity
CAISO 15-Min Liquidity CAISO Stakeholder Meeting October 6, 2015 Alex Spain Trading Floor Manager Power Services BPA Dave Dernovsek Day Ahead Trader Power Services BPA Presentation Objectives Federal Columbia
More informationAPPENDIX B: WHOLESALE AND RETAIL PRICE FORECAST
Seventh Northwest Conservation and Electric Power Plan APPENDIX B: WHOLESALE AND RETAIL PRICE FORECAST Contents Introduction... 3 Key Findings... 3 Background... 5 Methodology... 7 Inputs and Assumptions...
More informationRisk Management FUN! Humor Me
Risk Management FUN! Humor Me Leveraging Project Risk Management to Solidify Your RIM Business Continuity P R E S E N T E D B Y : M A R Y L. C L I N T O N, M B A, P M P W E D N E S D A Y, J U N E 2 1,
More informationMeeting the challenges of the changing actuarial role. Actuarial Transformation in property-casualty insurers
Meeting the challenges of the changing actuarial role Actuarial Transformation in property-casualty insurers 1 As companies seek to drive profitable growth, both short term and long term, increasing the
More informationQuantitative Cost-Benefit Analysis
SERIES 3: Building Resilience Quantitative Cost-Benefit Analysis Guide 3.10.0 Contents 3.10.0: Guide 3.10.1: Activity This training set is designed for teams that need to implement a quantitative cost-benefit
More informationChapter 19: Worksheet mark scheme (21 marks, HL )
Chapter 19: Worksheet mark scheme (21 marks, HL 21 + 12) 1 Machine A costs $700,000 and has forecast net cash flows of: $50,000 in year 1 $100,000 in year 2 $350,000 in year 3 $500,000 in year 4 The machine
More informationAries Project Prefeasibility Study Optimization Report
Aries Project Prefeasibility Study Optimization Report Submitted to: RAM River Coal Corporation Project Number: 624-12 Date: August 8, 2017 Norwest Corporation Suite 1830, 1066 W. Hastings Street Vancouver,
More information- Definition - Qualitative and Quantitative IP Valuation
Basics on Intellectual Property Valuation - Definition - Qualitative and Quantitative IP Valuation Tehran December 11, 2017 Christopher M. Kalanje Counsellor, SMEs and Entrepreneurship Support Division,
More informationQUALITY CONTROL Prepared: D. Vree Reviewed: M. Müller Approved: F. Wester BACKGROUND MATERIAL...
POSITION PAPER STAKE HOLDER CONSULTATION PROCESS OFFSHORE GRID NL Type: Position paper Work stream Technical Topic: T.6 Protection Filename ONL 15-080-T6_Protection_PP_v1 Version 1 - release for Expert
More information15. BONNEVILLE POWER ADMINISTRATION (BPA) PROGRAMS
15. BONNEVILLE POWER ADMINISTRATION (BPA) PROGRAMS Program Names: A. Conservation and Renewables Discount (C&RD) B. Conservation Augmentation (Con/Aug) Mechanism: A. 0.5mill/kWh discount on wholesale price
More informationReview of Production Theory: Chapter 2 1
Review of Production Theory: Chapter 2 1 Why? Trade is a residual (EX x = Q x -C x; IM y= C y- Q y) Understand the determinants of what goods and services a country produces efficiently and which inefficiently.
More informationJune 3, 2005
ROBERT J. PELLATT COMMISSION SECRETARY Commission.Secretary@bcuc.com web site: http://www.bcuc.com SIXTH FLOOR, 900 HOWE STREET, BOX 250 VANCOUVER, B.C. CANADA V6Z 2N3 TELEPHONE: (604) 660-4700 BC TOLL
More information83C Questions and Answers
83C Questions and Answers (1) Section 1.10 Could the Evaluation Team elaborate on what types of changes constitute a new project, including listing additional examples? For example, we have assumed that
More informationAmerican Municipal Power, Inc.; Ohio Municipal Electric Generation Agency Joint Ventures: 1, 2, 4, 5, and 6; Municipal Energy Services Agency
American Municipal Power, Inc.; Ohio Municipal Electric Generation Agency Joint Ventures: 1, 2, 4, 5, and 6; Municipal Energy Services Agency Combined Financial Statements and Supplemental Information
More informationMaintenance: definition
Maintenance: definition Group of technical, administrative and managerial actions during one component s life cycle, intended to keep or re-establish it into a state which allows it to carry out the required
More informationQUANTITATIVE COST-BENEFIT ANALYSIS
3.7.0 SERIES 3 Building Resilience QUANTITATIVE COST-BENEFIT ANALYSIS Contents of Set 3.7.0: Guide 3.7.1: Activity This training set is designed for teams that need to implement a quantitative cost-benefit
More informationStochastic Loss of Load Study for the 2011 Integrated Resource Plan
November 18, 2010 Stochastic Loss of Load Study for the 2011 Integrated Resource Plan INTRODUCTION PacifiCorp evaluates the desired level of capacity planning reserves for each integrated resource plan.
More informationSENSITIVITY ANALYSIS IN CAPITAL BUDGETING USING CRYSTAL BALL. Petter Gokstad 1
SENSITIVITY ANALYSIS IN CAPITAL BUDGETING USING CRYSTAL BALL Petter Gokstad 1 Graduate Assistant, Department of Finance, University of North Dakota Box 7096 Grand Forks, ND 58202-7096, USA Nancy Beneda
More informationRISK IDENTIFICATION ON CONSTRUCTION PLAN FOR HTGR-10 IN INDONESIA
RISK IDENTIFICATION ON CONSTRUCTION PLAN FOR HTGR-10 IN INDONESIA Sri Sudadiyo IAEA Technical Meeting on Risk Management in Nuclear Power Plant Construction 6 8 September 2016, Vienna Center for Nuclear
More informationAnnex G Guidance on Demonstration of Additionality
Annex G Guidance on Demonstration of Additionality 1 In this Annex several examples are given for the demonstration of additionality. It follows the steps of the Combined tool to identify the baseline
More informationNews from the Oklahoma Corporation Commission Matt Skinner, Public Information Phone: (405) , FAX: (405)
News from the Oklahoma Corporation Commission Matt Skinner, Public Information Phone: (405) 521-4180, FAX: (405) 521-6945 m.skinner@occemail.com April 28, 2006 KEEPING THE LIGHTS ON New Commission reliability
More informationCAPITAL BUDGET NUCLEAR
Updated: 00-0- EB-00-00 Tab Page of 0 0 CAPITAL BUDGET NUCLEAR.0 PURPOSE The purpose of this evidence is to present an overview description of the nuclear capital project budget for the historical year,
More informationManagement Services Reviewer by Ma. Elenita Balatbat-Cabrera
Course Name: Course Title: Instructors: Required Text: Course Description: XMASREV Management Services Review David, Dimalanta and Morales Management Services Reviewer by Ma. Elenita Balatbat-Cabrera This
More informationGlobal Credit Research New Issue 15 MAY New Issue: Chelan County Public Util. Dist 1, WA
Global Credit Research New Issue 15 MAY 2009 New Issue: Chelan County Public Util. Dist 1, WA MOODY'S ASSIGNS TO CHELAN COUNTY PUBLIC UTILITY DISTRICT'S DEBT ISSUANCES; OUTLOOK HAS BEEN CHANGED TO NEGATIVE
More informationINFORMATION RELEASE BCUC responds to BC Hydro s comments on the Site C Inquiry Final Report November 28, 2017
INFORMATION RELEASE BCUC responds to BC Hydro s comments on the Site C Inquiry Final Report November 28, 2017 Vancouver The British Columbia Utilities Commission (BCUC) has responded to the letter from
More informationOPG REPORTS 2017 THIRD QUARTER FINANCIAL RESULTS. Darlington Refurbishment Project Remains on Time and on Budget at One-Year Mark
OPG REPORTS 2017 THIRD QUARTER FINANCIAL RESULTS Nov. 9, 2017 Darlington Refurbishment Project Remains on Time and on Budget at One-Year Mark Toronto: Ontario Power Generation Inc. (OPG or Company) today
More informationSouth East Local Enterprise Partnership Business Case Review Pro-Forma: Strategic Case
INDEPENDENT TECHNICAL EVALUATION (GATE 1 & 2) Scheme Name: Date Completed: Completed By: South East Local Enterprise Partnership Business Case Review Pro-Forma: Strategic Case Question Value / Source R/A/G
More informationSuperseding REVISED Sheet No. 38 REVISED SHEET NO. 38 Effective March 20, 2008 Effective February 6, 2014 RULE NO. 18. Net Energy Metering
Superseding REVISED Sheet No. 38 REVISED SHEET NO. 38 Effective March 20, 2008 Effective February 6, 2014 A. ELIGIBLE CUSTOMER-GENERATOR RULE NO. 18 Net Energy Metering Net energy metering is available
More informationCopyright 2009 Pearson Education Canada
Operating Cash Flows: Sales $682,500 $771,750 $868,219 $972,405 $957,211 less expenses $477,750 $540,225 $607,753 $680,684 $670,048 Difference $204,750 $231,525 $260,466 $291,722 $287,163 After-tax (1
More informationAnalytic measures of credit capacity can help bankcard lenders build strategies that go beyond compliance to deliver business advantage
How Much Credit Is Too Much? Analytic measures of credit capacity can help bankcard lenders build strategies that go beyond compliance to deliver business advantage Number 35 April 2010 On a portfolio
More informationSALT RIVER PROJECT SMALL GENERATOR INTERCONNECTION PROCEDURES (SGIP) (For Generating Facilities No Larger Than 20 MW)
Improvement and Power District Original Sheet No. P-1 SALT RIVER PROJECT SMALL GENERATOR INTERCONNECTION PROCEDURES (SGIP) (For Generating Facilities No Larger Than 20 MW) Approved by SRP Board of Directors:
More informationFiscal Year 2012 Columbia Generating Station Annual Operating Budget
Fiscal Year 2012 Columbia Generating Station Annual Operating Budget Table of Contents Table Page Summary 3 Key Assumptions/Qualifications 4 Memorandum of Agreement (MOA) Table 1 5 Columbia Station Costs
More informationDeveloping Optimized Maintenance Work Programs for an Urban Roadway Network using Pavement Management System
Developing Optimized Maintenance Work Programs for an Urban Roadway Network using Pavement Management System M. Arif Beg, PhD Principal Consultant, AgileAssets Inc. Ambarish Banerjee, PhD Consultant, AgileAssets
More informationQuantitative Cost-Benefit Analysis
SERIES 3: Building Resilience Quantitative Cost-Benefit Analysis Guide 3.10.0 Contents 3.10.0: Guide 3.10.1: Activity This training set is designed for teams that need to implement a quantitative cost-benefit
More informationMontecristo Hydroelectric Project
Montecristo Hydroelectric Project Answers to Clarifications Required Reference No. UNFCCC 1077 Date: August 22, 2007 2 Montecristo Hydroelectric Project Answers to Clarifications Required Reference No.
More informationTHE NEED TO CONVERT MAINTENANCE AND ENGINEERING TO A FINANCIAL BASIS
Using Financial/Decision Analysis Risk Optimization to Prioritize Maintenance Expenditures, Justify Maintenance Spending and Maximise the NPV Savings of The Maintenance Function David A. Mauney Structural
More informationBest Practices in Project Risk Management. Presented by: Jeff Miller, PMP - Director of Project Management Interstates Control Systems, Inc.
Best Practices in Project Risk Management Presented by: Jeff Miller, PMP - Director of Project Management Interstates Control Systems, Inc. What is Project Risk Management? PMBOK Definition of Project
More informationReview of the Federal Transit Administration s Transit Economic Requirements Model. Contents
Review of the Federal Transit Administration s Transit Economic Requirements Model Contents Summary Introduction 1 TERM History: Legislative Requirement; Conditions and Performance Reports Committee Activities
More informationProject Management Professional (PMP) Exam Prep Course 06 - Project Time Management
Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management Slide 1 Looking Glass Development, LLC (303) 663-5402 / (888) 338-7447 4610 S. Ulster St. #150 Denver, CO 80237 information@lookingglassdev.com
More informationRISK MANAGEMENT. Budgeting, d) Timing, e) Risk Categories,(RBS) f) 4. EEF. Definitions of risk probability and impact, g) 5. OPA
RISK MANAGEMENT 11.1 Plan Risk Management: The process of DEFINING HOW to conduct risk management activities for a project. In Plan Risk Management, the remaining FIVE risk management processes are PLANNED
More informationContinuing Education Course #287 Engineering Methods in Microsoft Excel Part 2: Applied Optimization
1 of 6 Continuing Education Course #287 Engineering Methods in Microsoft Excel Part 2: Applied Optimization 1. Which of the following is NOT an element of an optimization formulation? a. Objective function
More informationMETHODOLOGY For Risk Assessment and Management of PPP Projects
METHODOLOGY For Risk Assessment and Management of PPP Projects December 26, 2013 The publication was produced for review by the United States Agency for International Development. It was prepared by Environmental
More informationXXXXX. Skookum Creek Power Project. Interconnection Facilities Study and Project Plan
XXXXX Skookum Creek Power Project Interconnection Facilities Study and Project Plan June 29, 2011 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2011. All rights
More informationTHESL S REGULATORY REGIMS
THESL S REGULATORY REGIMS PRESENTED BY: ARTHUR BERDICHEVSKY P.ENG., MBA TORONTO HYDRO December 4, 2012 CORPORATE STRUCTURE Shareholder Direction Regulated by Ontario Securities Commission Governance Financing
More informationUnofficial Comment Form Emergency Operations EOP-004-4
2015-08 Emergency Operations EOP-004-4 Do not use this form for submitting comments. Use the electronic form to submit comments on Project 2015-08 Emergency Operations; EOP-004-4 Event Reporting. The electronic
More informationFiscal Year Budget
Fiscal Year 2019 Budget Fiscal Year 2019 Project 3 Annual Budget Project 3 Fiscal Year 2019 Table of Contents Table Page Summary 3 Summary of Costs Table 1 4 Summary of Full Time Equivalent Table 2 5 Positions
More informationFiscal Year 2015 Columbia Generating Station Annual Operating Budget
Fiscal Year 2015 Columbia Generating Station Annual Operating Budget Table of Contents Table Page Summary 3 Key Assumptions/Qualifications 4 Memorandum of Agreement (MOA) Table 1 5 Columbia Station Costs
More informationEmerald People's Utility District Power Risk Management Procedures Guide
Emerald People's Utility District Power Risk Management Procedures Guide Proposed by the Financial Risk Management Team (FRMT) Updated March 13, 2013 1 Financial Risk Management and Trading Guidelines
More informationNATIONWIDE ASSET ALLOCATION INVESTMENT PROCESS
Nationwide Funds A Nationwide White Paper NATIONWIDE ASSET ALLOCATION INVESTMENT PROCESS May 2017 INTRODUCTION In the market decline of 2008, the S&P 500 Index lost more than 37%, numerous equity strategies
More information9. Integrated Resource Plan and Risk Analysis
9. Integrated Resource Plan and Risk Analysis Ameren Missouri 9. Integrated Resource Plan and Risk Analysis Highlights Ameren Missouri has developed a robust range of alternative resource plans that reflect
More informationThe role of an actuary in a Policy Administration System implementation
The role of an actuary in a Policy Administration System implementation Abstract Benefits of a New Policy Administration System (PAS) Insurance is a service and knowledgebased business, which means that
More informationPortland General Electric
Exhibit 99.2 Portland General Electric Earnings Conference Call Third Quarter 2018 Cautionary Statement Information Current as of October 26, 2018 Except as expressly noted, the information in this presentation
More informationANNEX to the Commission Decision C(2018)1514 of
EN ANNEX to the Commission Decision C(2018)1514 of 16.3.2018 The annual work programme for the implementation of the pilot projects "EU butterfly monitoring and indicators", "Using satellite images to
More information1997 PACIFIC NORTHWEST COORDINATION AGREEMENT
1997 PACIFIC NORTHWEST COORDINATION AGREEMENT Agreement for Coordination of Operations among Power Systems of the Pacific Northwest June 18, 1997 Conformed Copy i Table of Contents Table of Contents i
More informationNorthern Wasco County People s Utility District. Report of Independent Auditors and Financial Statements with Supplementary Information for
Report of Independent Auditors and Financial Statements with Supplementary Information for Northern Wasco County People s Utility District December 31, 2016 and 2015 (Restated) CONTENTS BOARD OF DIRECTORS,
More informationMemorandum. This memorandum does not require Board action. EXECUTIVE SUMMARY
California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Eric Hildebrandt, Executive Director, Market Monitoring Date: November 7, 2018 Re: Department of Market Monitoring
More information2005 Integrated Electricity Plan. Provincial IEP Committee Meeting #2 Economic Analysis February 22/23, 2005
2005 Integrated Electricity Plan Provincial IEP Committee Meeting #2 Economic Analysis February 22/23, 2005 Presentation Overview Economic Analysis Economic vs Financial Analysis Unit Costs vs Portfolio
More informationWe Provide the Insights. You Invest in the Right Opportunities. Solutions for Private Equity
We Provide the Insights. You Invest in the Right Opportunities. Solutions for Private Equity S&P Global Market Intelligence offers private equity practitioners access to essential information about companies,
More informationColonial Gas Company d/b/a National Grid Financial Statements For the years ended March 31, 2013 and March 31, 2012
Colonial Gas Company d/b/a National Grid Financial Statements For the years ended March 31, 2013 and March 31, 2012 COLONIAL GAS COMPANY TABLE OF CONTENTS Page No. Independent Auditor's Report 2 Balance
More informationModel Maestro. Scorto TM. Specialized Tools for Credit Scoring Models Development. Credit Portfolio Analysis. Scoring Models Development
Credit Portfolio Analysis Scoring Models Development Scorto TM Models Analysis and Maintenance Model Maestro Specialized Tools for Credit Scoring Models Development 2 Purpose and Tasks to Be Solved Scorto
More informationMANAGING THE RISKS ON TRANSFORMER ASSETS
MANAGING THE RISKS ON TRANSFORMER ASSETS by ARUN D YARGOLE & TONY McGRAIL DOBLE ENGINEERING COMPANY ayargole@doble.com What is an Asset? In commercial terms- It is an Entity that gives the owner the revenue
More informationEnergy Northwest, WA
CREDIT OPINION Energy Northwest, WA New Issue-Moody s assigns Aa1 to Energy Northwest s (WA) CGS, Proj. 1 and Proj. 3 rev. bnds. Rating outlooks are stable. New Issue Summary Rating Rationale Contacts
More informationAnalysis of Market and Non-Market Principles of Access for Wind Generation connection to Active Network Management Schemes
Analysis of Market and Non-Market Principles of Access for Wind Generation connection to Active Network Management Schemes Laura KANE Graham AULT Laura HANNANT University of Strathclyde UK Smarter Grid
More information16 th Revision of Sheet No. 83 Canceling 15 th Revision of Sheet No. 83, 7 th Revision WN U-60 of Sheet No. 255 and 2 nd Revision of Sheet No.
16 th Revision of Sheet No. 83 Canceling 15 th Revision of Sheet No. 83, 7 th Revision WN U-60 of Sheet No. 255 and 2 nd Revision of Sheet No. 255-a, INC. ELECTRICITY CONSERVATION SERVICE 1. PURPOSE: To
More informationBC Hydro Provincial Integrated Electricity Planning Committee Meeting 5 (July 12-14, 2005)
BC Hydro Provincial Integrated Electricity Planning Committee Meeting 5 (July 12-14, 2005) Information Sheet #12 Financial Impacts Background The financial objective for the IEP is to minimize cost. Most
More informationFresno, California FINANCIAL STATEMENTS. For the Year Ended June 30, 2017
FINANCIAL STATEMENTS For the Year Ended TABLE OF CONTENTS Page Independent Auditor s Report... 1 Management s Discussion and Analysis... 3 Basic Financial Statements: Government-Wide Financial Statements:
More informationRisk Based Inspection A Key Component to Generating Value from a Mechanical Integrity Program API Singapore 2012
the global leader in asset performance management solutions Risk Based Inspection A Key Component to Generating Value from a Mechanical Integrity Program API Singapore 2012 Agenda Introduction Achieving
More information