2005 Integrated Electricity Plan. Provincial IEP Committee Meeting #2 Economic Analysis February 22/23, 2005
|
|
- Julie Bennett
- 5 years ago
- Views:
Transcription
1 2005 Integrated Electricity Plan Provincial IEP Committee Meeting #2 Economic Analysis February 22/23, 2005
2 Presentation Overview Economic Analysis Economic vs Financial Analysis Unit Costs vs Portfolio Analysis Unit Costs Examples Portfolio Analysis Key questions in this section: Is the Committee sufficiently briefed on the financial analysis to be comfortable in reviewing the results? Does the Committee have the right data to make the trade-offs between portfolios? February 22/23, 2005 Page 2
3 Economic Analysis Objective to recommend a preferred portfolio Least cost with appropriate environmental and social consideration For each Portfolio: Determine costs and impacts of potential resource Based upon Supply / Demand balance, add sufficient resources Determine dispatch - which resources operate & how long? Determine total costs and impacts for portfolio Costs include Capital/ Fixed Operating/ Variable Operating/ Fuel/ Net Trade Revenue/ Transmission Impacts include GHG, air quality, land impact, water impacts Then compare Portfolios Including sensitivity analysis to assess uncertainties February 22/23, 2005 Page 3
4 Economic Analysis - High Level In least technical language: Determine types of resources available Including Demand Side Management Develop resource cost profile for each type Determine how big a basket of resources we need Fill basket with resources for each portfolio Determine total cost for each basket of resources Ultimately BC Hydro will run competitive acquisition processes in which various projects will be offered to BC Hydro based on proponents project/ structure/ financing. For the IEP, we need to understand the various resource costs and impacts to the extent required to structure obtain regulatory approval for resource calls. February 22/23, 2005 Page 4
5 Economic Analysis Objectives for 2005 IEP Ensure Consistent Representation of Projects IPP #1 vs IPP#2 IPP Technology #1 vs. IPP Technology #2 Ensure Level Playing Field: IPP Projects vs. BC Hydro Projects BCH projects include large hydro, resource smart, power smart Issues include discount rates, taxation, project life Compare resources based on their cost Consider merit of resources irrespective of who is assumed to develop them in the future Simplify the Economic Analysis From detailed corporate financial analysis to project comparison analysis February 22/23, 2005 Page 5
6 Simplification of Economic Analysis Within IEP Context - to determine the Net Present Value (NPV) costs of a portfolio and be able to compare portfolios Net Present Value - captures time value of money At the right level of detail to be able to understand impacts (not too detailed) but at a level that ensures we have done due diligence (i.e. enough detail to capture major impacts) What are the uncertainty bands around our data? Consider project pricing accuracy BCUC - planning estimates of +/- 35% Gas Price Forecast variability $US 3-5/MMBTU Electricity Price Forecast $US 30-52/ MWh February 22/23, 2005 Page 6
7 Typical Company/ IPP Cashflow Revenues Fixed costs Variable costs Taxes Capital expenditures Cost of Capital Changes in Working Capital Changes in Deferred Income Taxes February 22/23, 2005 Page 7
8 Different IPP Factors Capital structure Tax rate Tax shelter opportunities Risk factors Accuracy in estimates Credit worthiness In order to provide level playing field to all participants and to evaluate projects based on opportunity cost, not who develops them, all projects should be analyzed using the simplified method with consistent assumptions. February 22/23, 2005 Page 8
9 Economic Versus Financial IEP assesses resource preferences based on Economic Analysis of individual resource options and portfolios: Net Present Value Analysis (time value of money) Focuses on relative costs/benefits of alternative resource options/portfolios Can be done from BCH cost perspective (ratepayers) or from provincial perspective (i.e. shareholder s) Provincial cost perspective is net of provincial transfer payments Analysis done in real dollars (net of inflation) IEP assesses Rate Impact of portfolios using Financial Analysis: Estimates BC Hydro s year by year revenue requirements: what BC Hydro pays annually for IPP purchases and DSM reflects how BC Hydro recovers costs of BC Hydro/BCTC projects Preferably done in nominal dollars (with inflation included) February 22/23, 2005 Page 9
10 Economic Analysis Economic Cost Benefit: Assess Total Resource Cost which is the PV total costs vs PV benefits over economic life of project (with and without provincial transfers) Consistent assessment of BC Hydro/IPP/BCTC projects and DSM (includes customer costs) Ignores distribution of costs and benefits Intent: to select preferred portfolio irrespective of who develops the resources February 22/23, 2005 Page 10
11 Financial Analysis Rate Impact Analysis Determine BC Hydro s Annual Total Revenue Requirement Rate Surrogate: Annual Revenue Requirement Annual Energy Sales IPP Purchases: based on estimated purchase price (e.g. UEC based on contract life) BC Hydro Projects: annual financial cashflows as they would be recovered in revenue requirements Power Smart: Utility Cost only Intent: to reflect actual cost to acquire February 22/23, 2005 Page 11
12 Economic &Financial Analysis Direction to BC Hydro BC Hydro has been given direction at various points Most recently in the VIGP Decision and the 2004 RRA Decision the Commission directed BC Hydro to undertake both analyses Economic Analysis to decide amongst projects or portfolios Financial Analysis to assess rate impact of a selected project Consistent evaluation of BC Hydro and IPP projects (level playing field) In conclusion, the analysis for 2005 IEP is recommended to be: Economic Analysis to compare between Portfolios; Financial Analysis to undertake Rate Impact; Simplified Approach to analysis as being adequate within accuracy of the data. February 22/23, 2005 Page 12
13 Economic vs Financial Project Life Factor Eg: Small hydro project Service life - 40 years Expected contract life - 20 years To calculate UEC/ UCC amortize capital cost Over 40 or 20 years? After 20 years - remaining value accrues to owner For economic analysis - use 40 years independent of developer For financial cost - 20 years Based on what the developer needs to obtain financing February 22/23, 2005 Page 13
14 Economic vs Financial WACC Weighted Average Cost of Capital Corporate Tax rate BC Hydro = 0.0% Inflation assumption = 2.0% BC Hydro Capital Structure Nominal Pre-tax cost Debt 80% 5.0% 4.0% Equity 20% 13.5% 2.7% Pre-tax WACC 6.7% BC Hydro Capital Structure Real Pre-tax cost Debt 80% 2.9% 2.3% Equity 20% 11.3% 2.3% Pre-tax WACC 4.6% February 22/23, 2005 Page 14
15 Economic vs Financial IPP WACC Corporate Tax rate IPP= 35.0% Inflation assumption = 2.0% IPP Capital Structure Real Pre-tax cost Debt 60% 4.9% 3.0% Equity 40% 11.3% 4.5% Pre-tax WACC 7.5% IPP Capital Structure Real Post-tax cost Debt 60% 3.2% 1.9% Equity 40% 7.3% 2.9% Pre-tax WACC 4.8% February 22/23, 2005 Page 15
16 Economic vs Financial Pre-tax WACC Analysis Puts all participants on level ground income taxes impacts on tax deductible expenses and net income before income taxes are eliminated Discounting pre-tax cash flow with pre-tax WACC will yield similar results as discounting post-tax cash flow with post-tax WACC The different tax shelter opportunities of different participants can be ignored because evaluation is based on the pre-tax basis Recommendation: Use pre-tax WACC for analysis purpose Have not settled on what rates to use February 22/23, 2005 Page 16
17 Economic vs Financial Discount Rates BC Hydro Discount Rate: pretax WACC 5-7% long term IPP Discount Rates: pretax WACC may be higher than BCH s but not a given (ultimately they ll bid their projects) Common Discount Rate: Social discount rate or opportunity cost of capital is appropriate for use in economic benefit-cost analysis Rate is still under debate For long life assets, portfolio results can be sensitive to choice of discount rates: Sensitivity analysis is recommended - 6%, 8%, 10% suggested some indication SDR should be lower Recommendation: For the economic analysis, utilize the Social Discount Rate; For the Financial Analysis, utilize a range of Discount Rates to test impacts of various corporations WACCs. February 22/23, 2005 Page 17
18 Economic vs Financial Subsidies There are various subsidies for renewable energy deployment initiatives These subsidies reduces the overall costs of the project developer However, these subsidies are also a societal cost since they are paid by the taxpayers Technologies that attract subsidies include: wind, fuel cell, photovoltaic, biomass and others Recommendation: Exclude subsidies in economic analysis Include subsidies in financial analysis February 22/23, 2005 Page 18
19 Economic vs Financial Factors Factor Economic Financial Discount rate Social Discount Weighted Average Rate Cost of Capital Project Life Economic Contract Taxes Excluded Included Subsidies Excluded Included * Corporate Overhead and sunk costs excluded from both analyses February 22/23, 2005 Page 19
20 Unit Costs vs Portfolio Costs Two basic ways in which to consider resource costs. Unit Cost Cost for each resource type per unit of output $/MWh - Unit Energy Cost [UEC] $/kw - Unit Capacity Costs [UCC] Resources produce both energy and capacity Typically, use UEC vs UCC if mostly energy project Portfolio Analysis Models the BC Hydro existing system Including existing IPP contracts Add resources to model how well customers needs are met Capacity and energy February 22/23, 2005 Page 20
21 Unit Costs vs Portfolio Costs Unit costs - useful summary metric for initial ranking/screening Applicable to: Supply and DSM resources / BC Hydro and IPP resources Determines costs for full output Portfolio Analysis provides more comprehensive assessment of resource options costs/benefits. Determines how resources expected to perform as part of basket For non-dispatchable resources (most renewables) $/MWh UEC costs monthly energy capability Calculate total annual cost For dispatchable resources (storage hydro, most thermals): fixed costs are input separately in $/year Variable costs are used in model s economic dispatch February 22/23, 2005 Page 21
22 Sample UEC Small Hydro Project Annual Energy Capability 90 GWh Installed Capacity 20 MW Dependable Capacity 5 MW Direct Capital Cost 40,000 $k Construction annual cashflow: Uniform over 3 years Fixed Annual Operating Cost: 2% of direct capital (800$k/yr) Fixed Annual Provincial taxes: 1.9% of direct capital(760$k/yr) Variable Operating Cost: $0/MWh Variable Provincial taxes: $1/MWh Fuel cost: N/A Fuel tax: N/A Project Life: 20 year contract February 22/23, 2005 Page 22
23 Sample UEC Small Hydro Project Investment Cost = Direct Capital + Interest During Construction amortized over contract life using pre-tax Weighted Average Cost of Capital as discount rate February 22/23, 2005 Page 23
24 Sample UCC Simple Cycle Gas Turbine Expected Annual Energy 65 GWh (in Heavy Load Hours) Installed Capacity 50 MW Dependable Capacity 50 MW Direct Capital Cost 40,000 $k Construction annual cashflow: Uniform over 2 years Project Life: 20 year contract Fixed Annual Operating Cost: 2% of direct capital (800$k/yr) Fixed Annual Provincial taxes: 1.9% of direct capital(760$k/yr) Variable Operating Cost: $4/MWh Variable Provincial taxes: $0/MWh Heat Rate 9000 GJ/GWh Fuel cost: $5/GJ ($45/MWh before tax) Fuel tax: 7% February 22/23, 2005 Page 24
25 Sample UCC Simple Cycle Gas Turbine February 22/23, 2005 Page 25
26 Possible Adjustments to Unit Costs Resource alternatives technical characteristics vary which affect their relative cost/value: Capacity value/ dependability for energy projects Energy value of capacity projects Location - affects transmission costs and losses Impact on system storage: Seasonal variation in energy delivery Daily/hourly variation in energy delivery Dispatchable? Can use be shifted to peak hours? Fuel Cost uncertainty February 22/23, 2005 Page 26
27 Dependable Capacity Adjustment: Sample UEC - Small Hydro Assume Value of Dependable Capacity = $50/kW-yr February 22/23, 2005 Page 27
28 Energy Value Adjustment : Sample UCC - Simple Cycle Gas Turbine Assume: Capacity Factor: 15% (65GWh/year during HLH) Variable OMA and Fuel: $4/MWh + $45/MWh +7% tax annual average HLH Market Value of energy: $55/MWh February 22/23, 2005 Page 28
29 Unit Cost Adjustments versus Portfolio Analysis TECHNICAL CHARACTERISTIC Capacity Dependable Energy Contribution of Capacity Resources Incremental Bulk Transmission System Costs Incremental Transmission Losses CAPTURE AS ADJUSTMENT TO UEC or UCC? include as cost adder with sensitivities credit energy value less variable production cost Depends on location and T assumptions Depends on location and T assumptions CAPTURED IN PORTFOLIO ANALYSIS? Yes, capacity scheduled based on dependability Yes, capacity resource energy reduces energy need Yes, major T projects are scheduled for projects and included in costs Limited to adder for large energy projects Impact on System Flexibility: Monthly energy delivery profile Daily/hourly energy delivery profile Dispatchable Complex adjustments Monthly energy delivery profile: YES Daily/hourly energy delivery profile: NO Dispatchable: PARTIAL Fuel Cost Uncertainty Sensitivity Analysis Economic dispatch and sensitivity analysis February 22/23, 2005 Page 29
30 UEC/ UCC & Portfolios Resource Options Database Resource Options Report IEP Portfolio Analysis Dispatchable Units Capital Cost Operating Cost Firm Energy Average Energy Dependable Capacity Dispatchable Units UEC $/MWh UCC $/kw-yr Dispatchable Units Capital Cost Operating Cost Calculate Dispatch Dependable Capacity Non-dispatchable units Capital Cost Operating Cost Monthly Energy Profile Firm Energy Average Energy Dependable Capacity Non-dispatchable Units UEC $/MWh UCC $/kw-yr Non-dispatchable Units UEC $/MWh Monthly Energy Profile Dependable Capacity February 22/23, 2005 Page 30
31 How UEC is used in Portfolios February 22/23, 2005 Page 31
32 Simple Portfolio Y (Resource D is Dispatchable) February 22/23, 2005 Page 32
33 Economic vs. Financial Analysis Economic Financial UEC/UCC X Portfolio X X * First portfolio analysis undertakes a least economic cost to acquire the resources. Then financial analysis determines the financial impact on rate payers (RIM). February 22/23, 2005 Page 33
34 Representation of Portfolio Costs At the last meeting - suggestion that portfolio costs should be shown as $/ MWh Large Net Present Value numbers were not meaningful Issues with isolating impacts and benefits of new resources New resources combined with existing resources for combined dispatch and variable/ fuel costs Benefits of all trade not be reflective of new resources Possible solution - select base portfolio to determine unit dispatch Incremental portfolios would be compared against base Costs become new resource capital, variable, fuel, and new trade revenue February 22/23, 2005 Page 34
35 Next Steps? Inclusion of potential future environmental liabilities in analysis Need for further briefing on economic and financial modeling? Do we have the right measures for the PIEPC to make trade-offs/ value portfolios? February 22/23, 2005 Page 35
36 Backup Slides February 22/23, 2005 Page 36
37 Calculation Examples FIGURE 1 EXAMPLE OF UNIT ENERGY COST CALCULATION Sample Energy Project In-service for 5 Years Starting in Year 4 dollars are 'real' which means net-of-inflation Assume discount rate is 6% (real) DISCOUNTED CASHFLOW CALCULATION OF UNIT COST: YEAR Capital Cost to Construct $225 $75 $75 $75 Annual Operating Cost $10 $10 $10 $10 $10 Total Cost $75 $75 $75 $10 $10 $10 $10 $10 Discount factor formula 1 1/(1.06) 1/(1.06)^2 1/(1.06)^3 1/(1.06)^4 1/(1.06)^5 1/(1.06)^6 1/(1.06)^7 Discounting factor Total Cost times discounting factor: $75 $70.8 $66.7 $8.4 $7.9 $7.5 $7.0 $6.7 Sum of Total discounted cost equals Present Value of total cost: $250 Annual Energy Benefit (Megawatt-hrs) Annual Energy times discount factor: Sum of discounted Annual Energy equals Present Value of Energy: 7.5 UNIT ENERGY COST = PV Total Cost/PV Energy Benefit= 33 $/MWh February 22/23, 2005 Page 37
38 Calculation Examples FIGURE 2 EXAMPLE OF UNIT ENERGY COST CALCULATION Sample Energy Project In-service for 5 Years Starting in Year 4 dollars are 'real' which means net-of-inflation Assume discount rate is 8% (real) DISCOUNTED CASHFLOW CALCULATION OF UNIT COST: YEAR Capital Cost to Construct $225 $75 $75 $75 Annual Operating Cost $10 $10 $10 $10 $10 Total Cost $75 $75 $75 $10 $10 $10 $10 $10 Discount factor formula 1 1/(1.08) 1/(1.08)^2 1/(1.08)^3 1/(1.08)^4 1/(1.08)^5 1/(1.08)^6 1/(1.08)^7 Discounting factor Total Cost times discounting factor: $75 $69.4 $64.3 $7.9 $7.4 $6.8 $6.3 $5.8 Sum of Total discounted cost equals Present Value of total cost: $243 Annual Energy Benefit (Megawatt-hrs) Annual Energy times discount factor: Sum of discounted Annual Energy equals Present Value of Energy: 6.8 UNIT ENERGY COST = PV Total Cost/PV Energy Benefit= 35 $/MWh February 22/23, 2005 Page 38
39 Calculation Examples Figure 4: Calculation of Levelized Cost Assume Discount rate = 6% year Example: Forecast Fuel Cost $/unit Levelizing is done over a specified period as per the following two examples: Present Fuel Cost levelized over years 1 to 8: year Forecast Fuel Cost $/unit (a) # of units of fuel (b) LEVELIZED FUEL COST Years 1-8 (a) divided by (b): 4.14 $/unit Fuel Cost levelized over years 4 to 8: year Forecast Fuel Cost $/unit (c) # of units of fuel (d) LEVELIZED FUEL COST Years 4-8 (c) divided by (d): 4.77 $/unit February 22/23, 2005 Page 39
40 Calculation Examples Figure 5: ANNUALIZED COST METHOD (applicable for projects that have same energy benefit every year) The Annualized Capital Cost is the Uniform Annual Payment over the project's 5 year life to repay the Capital Cost plus interest during construction based on 6 % YEARS to In-service: TOTAL: annual capital $75 $75 $75 0 $225 Interest during construction: (1.06)^2 (1.06)^1 1 Capital plus IDC $239 Total Capital + IDC 239 $ Annualized Capital Cost 57 $/year Annual Operating Cost 10 $/year Total Cost per year 67 Annual Energy 2 MWh Unit Energy Cost 33 $/MWh February 22/23, 2005 Page 40
41 Calculation Egs. February 22/23, 2005 Page 41
42 Portfolio Modeling vs UEC Cost line items include: Capital cashflow and fixed annual costs for BCH/BCTC projects (e.g. REV5, transmission lines) UEC times annual GWh for non-dispatched new IPP resources Fixed annual costs including annualized capital cost are included for dispatchable resources System simulation model predicts expected variable operating costs for existing dispatchable resources (like Burrard), dispatchable new resource options (like a CCGT), expected economic spot market imports costs and exports revenues All these line items of annual cost (revenues) for study period, typically 20 years, are discounted at opportunity cost of capital Includes estimate of residual value for BCH/BCTC projects added in last year February 22/23, 2005 Page 42
BC Hydro Provincial Integrated Electricity Planning Committee Meeting 5 (July 12-14, 2005)
BC Hydro Provincial Integrated Electricity Planning Committee Meeting 5 (July 12-14, 2005) Information Sheet #12 Financial Impacts Background The financial objective for the IEP is to minimize cost. Most
More informationBC HYDRO S APPLICATION FOR 2004/05 AND 2005/06 REVENUE REQUIREMENTS BCOAPO et al. INFORMATION REQUESTS
BC HYDRO S APPLICATION FOR 2004/05 AND 2005/06 REVENUE REQUIREMENTS BCOAPO et al. INFORMATION REQUESTS QUESTION 1 Reference: Application, Volume 1, Chapter 1, page 1-7, Tables 1-1 and 1-2 a) Please clarify
More information2.0 Reference: Application, Volume I, Chapter 2, Consolidated Revenue Requirements and Financial Schedules
1 2.0 Reference: Application, Volume I, Chapter 2, Consolidated Revenue Requirements and Financial Schedules 2.2 2-3, Table 2-2: Please indicate for Columns C and D whether or not an average expected value
More informationClosing Comments. February 4, BY Site C Joint Review Panel Secretariat
PHILIP K. BARTON LAW CORPORATION STEVE DAVIS & ASSOCIATES CONSULTING LTD. February 4, 2014 BY E-MAIL (SiteCReview@ceaa-acee.gc.ca) Site C Joint Review Panel Secretariat Courtney Trevis, Panel Co-Manager
More informationFor the Efficiency Maine Trust October 15, 2009 Eric Belliveau, Optimal Energy Inc.
DSM Economics For the Efficiency Maine Trust October 15, 2009 Eric Belliveau, Optimal Energy Inc. DSM Economics - Overview Why? Basics of Economics Benefits Costs Economic Test Overviews Economics of Sample
More informationBC Hydro s Clean Power Call
BC Hydro s Clean Power Call November 27, 2007 Housekeeping Details Morning break at 9:45 for 15 minutes Lunch is at 12:30 for 30 minutes Break out groups at 1:30 for 1 hour Meeting ends at 4:00 Washrooms
More informationReference: Exhibit B-5-1, page 1-4, Section , Electricity Demand Growth
C18-2 REQUESTOR NAME: Independent Power Producers of B.C. INFORMATION REQUEST ROUND NO: 1 TO: BRITISH COLUMBIA HYDRO & POWER AUTHORITY DATE: July 5, 2006 PROJECT NO: 3698416 APPLICATION NAME: F2007/F2008
More informationFor further information, please contact Fred James at or by at
Tom A. Loski Chief Regulatory Officer Phone: 604-623-4046 Fax: 604-623-4407 bchydroregulatorygroup@bchydro.com July 21, 2016 Ms. Laurel Ross Acting Commission Secretary British Columbia Utilities Commission
More informationINFORMATION RELEASE BCUC Receives Comments from BC Hydro on Site C Inquiry Final Report November 24, 2017
Suite 410, 900 Howe Street Vancouver, BC Canada V6Z 2N3 bcuc.com P: 604.660.4700 TF: 1.800.663.1385 F: 604.660.1102 INFORMATION RELEASE BCUC Receives Comments from BC Hydro on Site C Inquiry Final Report
More informationRe: FortisBC Inc. Application for Approval of Demand Side Management Expenditures for the Period of 2015 and 2016
ERICA HAMILTON COMMISSION SECRETARY Commission.Secretary@bcuc.com web site: http://www.bcuc.com VIA EMAIL August 22, 2014 SIXTH FLOOR, 900 HOWE STREET, BOX 250 VANCOUVER, BC CANADA V6Z 2N3 TELEPHONE: (604)
More informationINFORMATION RELEASE BCUC responds to BC Hydro s comments on the Site C Inquiry Final Report November 28, 2017
INFORMATION RELEASE BCUC responds to BC Hydro s comments on the Site C Inquiry Final Report November 28, 2017 Vancouver The British Columbia Utilities Commission (BCUC) has responded to the letter from
More informationAPPENDIX B: PORTFOLIO OPTIMIZATION MODEL
APPENDIX B: PORTFOLIO OPTIMIZATION MODEL PUBLIC UTILITY DISTRICT #1 OF SNOHOMISH COUNTY Prepared by Generation, Power, Rates, and Transmission Management Division Snohomish County PUD DRAFT 2017 Integrated
More informationThe Economics and Financing of Distributed Generation Investment. Budapest, Hungary November 17, 2016
The Economics and Financing of Distributed Generation Investment Budapest, Hungary November 17, 2016 Topics to Cover How to Finance Distributed Generation Investments 1 Importance of financial aspects
More informationRevenue Requirement Application 2004/05 and 2005/06. Volume 1. Chapter 2. Consolidated Revenue Requirements and Financial Schedules
Revenue Requirement Application 00/0 and 00/0 Volume 1 Chapter. Consolidated Revenue Requirements and Financial Schedules Table of Contents LIST OF FIGURES... -IV LIST OF TABLES... -IV LIST OF SCHEDULES...-V
More information1: Levelized Cost of Energy. Calculation. Methodology and Sensitivity
1: Levelized Cost of Energy Calculation Methodology and Sensitivity What is LCOE? Levelized Cost of Energy (LCOE) is the constant unit cost (per kwh or MWh) of a payment stream that has the same present
More informationRevenue Requirement Application. 2004/05 and 2005/06. Volume 2. Appendix I. Power Smart 10-Year Plan
Revenue Requirement Application 2004/05 and 2005/06 Volume 2 Appendix I. Power Smart 10-Year Plan 10-Year Plan: 2002/03 through 2011/12 December 2, 2003 Table of Contents 1 PLAN SUMMARY...1 2 PLAN COST-EFFECTIVENESS
More informationEskom 2018/19 Revenue Application
Eskom 2018/19 Revenue Application Nersa Public Hearings Klerksdorp 13 November 2017 Where we are coming from This revenue application is being made for the year 2018/19, after the Energy Regulator maintained
More informationDecember 9, City of Farmington Integrated Resource Planning (IRP)
December 9, 2016 City of Farmington Integrated Resource Planning (IRP) Restricted Siemens AG 2013 All rights reserved. Answers for infrastructure and cities. Pace Global Disclaimer This Report was produced
More informationLong Run Marginal Cost (LRMC)
Long Run Marginal Cost (LRMC) Ryan Steele Power Supply Planning Specialist Agenda & Objectives Preliminary Discussion PART I Provide a historic overview of FBC s LRMC Highlights from BC Hydro s stated
More informationBC Hydro Revenue Requirements 2004/ /06. Financial Overview. Dana Hardy BC Hydro Controller
Financial Overview Dana Hardy BC Hydro Controller Objectives To review the calculation of BC Hydro s revenue requirement To illustrate the impact of key cost drivers on BC Hydro s Revenue Requirement To
More informationWithin-Hour Capacity Markets in the Northwest. July 22, John Wellschlager Bonneville Power, Trading Floor Account Executive
Within-Hour Capacity Markets in the Northwest July 22, 2015 John Wellschlager Bonneville Power, Trading Floor Account Executive Slide 1 Why is BPA in the market for within-hour capacity? BPA s physical
More informationFinancial Analysis and Cash Flow
Financial Analysis and Cash Flow Version 2.0 Integrated Financial Analysis SOAPP CT.25 uses the capital cost and operating cost estimates to develop a Capital Outlay Schedule and a Pro Forma Income and
More informationEconomic Impacts of New Jersey s Proposed Renewable Portfolio Standard Report Schedules
Economic Impacts of New Jersey s Proposed Renewable Portfolio Standard Report Schedules David E. Dismukes, Ph.D. Acadian Consulting Group 6455 Overton Street Baton Rouge, Louisiana 70808 December 16, 2005
More informationPrepared for the BC Sustainable Energy Association. Expanding Energy Efficiency for BC Hydro: Lessons from Industry Leaders.
Prepared for the BC Sustainable Energy Association Expanding Energy Efficiency for BC Hydro: Lessons from Industry Leaders June 19, 2012 Overview 1. Key Terms and Concepts 2. BC Hydro s IRP 3. US Data
More informationLecture in Energy Economics: Life Cycle Cost Analysis for Bankable Projects in Sustainable Energy
Lecture in Energy Economics: Life Cycle Cost Analysis for Bankable Projects in Sustainable Energy INOGATE Programme New ITS Project, Ad Hoc Expert Facility (AHEF) Task AM-54-55-56 Slides prepared by: Ali
More informationGeorgia Power Company s Qualifying Facilities (QF) Fundamentals
Georgia Power Company s Qualifying Facilities (QF) Fundamentals Public Utilities Regulatory Policies Act ( PURPA ) Legislative Purpose: To combat the energy crisis of the 1970s To promote energy conservation
More informationIPP Investment Market Framework and Technical Assistance Phase II
Consultants for Resources Evaluation Donald I. Hertzmark Team Leader September 4, 2008 Mr. Siseho Simasiku Chief Executive Officer Electricity Control Board of Namibia 8 Bismarck Street P.O. Box 2923 Windhoek,
More informationCase-study location: Battaglia Terme\Galzignano Terme
Economic modelling of low-temperature geothermal energy Case-study location: Battaglia Terme\Galzignano Terme Activity 4.3 in WP 4 Partner: PADUA Coordinated by: UM Index 1. INTRODUCTION... 3 2. ASSESSMENT
More informationFinancial Incentives for Deploying Carbon Capture and Storage: Tom Wilson Sr. Program Manager CSLF Financing Roundtable 2010 April 6, 2010
Financial Incentives for Deploying Carbon Capture and Storage: How Much are they Worth? Tom Wilson Sr. Program Manager CSLF Financing Roundtable 2010 April 6, 2010 Background Carbon capture and storage
More informationGREEK RENEWABLES SUPPORT SCHEME PROPOSALS
BRIEFING GREEK RENEWABLES SUPPORT SCHEME PROPOSALS MARCH 2016 BRIEF OUTLINE OF THE SCHEME PHOTOVOLTAIC PROJECTS TRANSITIONAL PROVISIONS NON-INTERCONNECTED ISLANDS COMPETITIVE BIDDING PROCESS FROM 2017
More informationAlberta Coalition Presentation. BCUC Workshop - August 23, BCTC Network Economy and Open Access Transmission Tariff
C8-7 Alberta Coalition Presentation BCUC Workshop - August 23, 2006 BCTC Network Economy and Open Access Transmission Tariff August 23, 2006 Alberta Coalition 1 Overview of AC Evidence August 23, 2006
More informationLong-Term Rate Forecast
Long-Term Rate Forecast OVERVIEW This brief provides background information on the Long-Term Rate Forecast (LTRF) used in the 2011 Integrated Resource Plan (IRP). It is similar to the report filed as Attachment
More informationManitoba Hydro 2015 General Rate Application
Manitoba Hydro 2015 General Rate Application OVERVIEW & REASONS FOR THE APPLICATION Darren Rainkie Vice-President, Finance & Regulatory Manitoba Hydro Why Rate Increases are Needed 2 Manitoba Hydro is
More informationAPPENDIX B: WHOLESALE AND RETAIL PRICE FORECAST
Seventh Northwest Conservation and Electric Power Plan APPENDIX B: WHOLESALE AND RETAIL PRICE FORECAST Contents Introduction... 3 Key Findings... 3 Background... 5 Methodology... 7 Inputs and Assumptions...
More informationBC Hydro FIrST QUArTEr report FISCAL 2015
BC Hydro FIRST QUARTER REPORT FISCAL 2015 BC Hydro & Power Authority Management S Discussion and Analysis This Management s Discussion and Analysis (MD&A) reports on British Columbia Hydro and Power Authority
More informationBChgdro. lor\js. FOR GEt\JE B-1. September 30,2009
BChgdro FOR GEt\JE lor\js B-1 Joanna Sofield Chief Regulatory Officer Phone: (0) -0 Fax: (0) -0 bchydroregulatorygroup@bchydro.com September 0,009 Ms. Erica M. Hamilton Commission Secretary British Columbia
More informationManagement recommends the following enhancements to these modifications to the provisions for commitment costs:
California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: May 9, 2012 Re: Decision on Commitment
More informationAttached is BC Hydro s annual filing of the Report on Demand-Side Management Activities for the 12 months ending March 31, 2012.
Janet Fraser Chief Regulatory Officer Phone: 60-6-06 Fax: 60-6-07 bchydroregulatorygroup@bchydro.com July 0, 01 Ms. Erica Hamilton Commission Secretary British Columbia Utilities Commission Sixth Floor
More informationSPO PLANNING ANALYSIS 2015 ENO IRP. Updates for the Final IRP SEPTEMBER 18, 2015
SPO PLANNING ANALYSIS 2015 ENO IRP Updates for the Final IRP SEPTEMBER 18, 2015 INTRODUCTION OBJECTIVES The following topics will be discussed: Effects of Union Reallocation on ENO Supply Plan Supply Role
More informationKEY FINDINGS AND RESOURCE STRATEGY
KEY FINDINGS AND RESOURCE STRATEGY The Council s Power Plan Goal - Ensure an adequate, efficient and affordable regional power system Major Components Forecast of regional electricity demand over the next
More informationPPAs and Tariff Design
RENEWABLE ENERGY TRAINING PROGRAM FINANCING RENEWABLE ENRGY PROJECTS PPAs and Tariff Design Bassem Abou Nehme Energy Finance Consultant TWI - Financial Solutions 1 Outline What is a PPA? Structure of PPA
More informationhydro /Yl- Fax: (604) Y,-- ww.bchydro. com Yours sinc
-".... /Yl- -.-'- BC hydro Tony Morris Acting Chief Regulatory Offcer Phone: (604) 623-4046 Fax: (604) 623-4407 June 27, 2005 Mr. Robert J. Pellatt Commission Secretary British Columbia Utilities Commission
More informationBEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION
BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION IN THE MATTER OF SOUTHWESTERN PUBLIC SERVICE COMPANY S APPLICATION REQUESTING: ( ACKNOWLEDGEMENT OF ITS FILING OF THE 0 ANNUAL RENEWABLE ENERGY PORTFOLIO
More informationPerformance-Based Ratemaking
Performance-Based Ratemaking Rhode Island Utility Business Models Discussion April 24, 2017 Tim Woolf Consultant for the Division of Public Utilities and Carriers Outline Financial incentives under traditional
More information9. Integrated Resource Plan and Risk Analysis
9. Integrated Resource Plan and Risk Analysis Ameren Missouri 9. Integrated Resource Plan and Risk Analysis Highlights Ameren Missouri has developed a robust range of alternative resource plans that reflect
More informationSCHEDULE 85 COGENERATION AND SMALL POWER PRODUCTION STANDARD CONTRACT RATES
IDAHO POWER COMPANY FOURTH REVISED SHEET NO. 85-1 THIRD REVISED SHEET NO. 85-1 AVAILABILITY Service under this schedule is available for power delivered to the Company's control area within the State of
More informationQ4/17 Analyst Conference Call
Q4/17 Analyst Conference Call Brian Vaasjo, President & CEO Bryan DeNeve, SVP Finance & CFO February 16, 2018 capitalpower.com Forward-looking information Cautionary statement Certain information in this
More informationNova Scotia Utility and Review Board. Section 2
Nova Scotia Utility and Review Board IN THE MATTER OF The Public Utilities Act, R.S.N.S. 1989, c.380, as amended - and - IN THE MATTER OF an Application by Nova Scotia Power Incorporated for Approval of
More informationBritish Columbia Hydro and Power Authority
2016/17 SECOND QUARTER REPORT MANAGEMENT S DISCUSSION AND ANALYSIS This Management s Discussion and Analysis (MD&A) reports on British Columbia Hydro and Power Authority s (BC Hydro or the Company) consolidated
More informationBEFORE THE PUBLIC UTILITY COMMISSION OF OREGON UM (RVOS), the Commission adopt Staff s proposed methodology for determining RVOS and
1 1 In the Matter of : PUBLIC UTILITY COMMISSION OF OREGON, Investigation to Determine the Resource Value of Solar. I. Introduction. BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON UM STAFF OPENING BRIEF
More informationaccumulated in cost of energy accounts throughout the year.
23. Reference: Application, Volume 1, Chapter 2, page 2-, lines 8-23. 0(b) Please provide illustrative examples based on the F2006 forecast of how the actual Heritage Energy will be established in cases
More informationPROJECT FINANCE GLOSSARY
API Gravity Availability Barrel Barrel of oil equivalent Barter Base load plant Berne Union Bid Bond BOT BPCD BTU Bullion Buyer Credit Capacity charge A measure of density of Crude Oil or other liquid
More informationQ Earnings Presentation March 4, 2015
Q4 2014 Earnings Presentation March 4, 2015 1 Safe Harbor Statement Certain statements in the Business Update and Order Backlog sections contain forward-looking statements within the meaning of the safe
More informationPage 1 of 15
0 MIPUG/MPA -00 page "In some model runs across resource plans, rates would be required to rise by anywhere from % to 0% or more for a sustained period in order to maintain Manitoba Hydro's financial probity
More informationThe cost allocation principles and methodologies in this Attachment Y cover only
31.5 Cost Allocation and Cost Recovery 31.5.1 The Scope of Attachment Y Cost Allocation 31.5.1.1 Regulated Responses The cost allocation principles and methodologies in this Attachment Y cover only regulated
More informationSCHEDULE C ELECTRICITY PURCHASE AGREEMENT TERM SHEET TRANSMISSION AND LARGE DISTRIBUTION CONNECTED PROJECTS
SCHEDULE C ELECTRICITY PURCHASE AGREEMENT TERM SHEET TRANSMISSION AND LARGE DISTRIBUTION CONNECTED PROJECTS The following is a summary of the key terms and conditions of the proposed standard form electricity
More informationTRANSALTA CORPORATION
Management's Discussion and Analysis TRANSALTA CORPORATION Second Quarter Report for 2018 This Management s Discussion and Analysis ( MD&A ) contains forward-looking statements. These statements are based
More informationValue of DER. Con Edison and Orange & Rockland. Developer Workshop
Value of DER Con Edison and Orange & Rockland Developer Workshop July 24, 2017 1 Housekeeping In case of emergency Dial 911 or alert the Security Desk Con Edison s TLC Address: 43-82 Vernon Blvd, LIC,
More information2015 RATE DESIGN APPLICATION (RDA) TRANSMISSION SERVICE RATE (TSR) STRUCTURES WORKSHOP #1
2015 RATE DESIGN APPLICATION (RDA) TRANSMISSION SERVICE RATE (TSR) STRUCTURES WORKSHOP #1 22 October, 2014 INTRODUCTION AGENDA Approximate Time Item Presenter(s) 9 :00 9:10 Welcome Anne Wilson Background
More informationGeneration investment in a liberalised electricity market. 28 March 2008
Generation investment in a liberalised electricity market 28 March 2008 Darryl Biggar Australian Competition and Consumer Commission Australian Energy Regulator Investment in electricity markets Demand
More informationRichmond Building Energy Challenge
Richmond Building Energy Challenge Robert Greenwald, P.Eng., MBA, President (Principal) Robert Greenwald has 25 years of energy management experience including developing energy plans, determining opportunities,
More informationQ I N T E R I M R E P O R T. Brookfield Renewable Partners L.P.
Q2 2017 I N T E R I M R E P O R T Brookfield Renewable Partners L.P. OUR OPERATIONS We manage our facilities through operating platforms in North America, Colombia, Brazil, and Europe which are designed
More informationRETAIL ACCESS PROGRAM AUGUST 25, 2011 PRESENTERS: David Keir, Transmission Rates Manager, (david.keir@bchydro.com) Fred James, Rates and Tariff Manager, (fred.james@bchydro.com) Justin Miedema, Regulatory
More informationSession 1.2 Discounting and Project Alternatives. Introductory Course on Economic Analysis of Investment Projects
Session 1.2 Discounting and Project Alternatives Introductory Course on Economic Analysis of Investment Projects Project statements Comparison of benefits and costs Typically investment costs (equipment,
More informationTHE ELECTRIC HONEYPOT: THE PROFITABILITY OF DEREGULATED ELECTRIC GENERATION COMPANIES By Edward Bodmer
THE ELECTRIC HONEYPOT: THE PROFITABILITY OF DEREGULATED ELECTRIC GENERATION COMPANIES By Edward Bodmer EXECUTIVE SUMMARY Purpose and Conclusions of the Study This report presents the results of an investigative
More informationISO Transmission Planning Process. Supplemental Sensitivity Analysis: Risks of early economic retirement of gas fleet
ISO 2016-2017 Transmission Planning Process Supplemental Sensitivity Analysis: Risks of early economic retirement of gas fleet January 4, 2018 Contents 1. Introduction... 1 2. Background... 1 3. Objectives
More informationBMO 2015 Fixed Income Conference. Todd Stack VP & Treasurer
BMO 2015 Fixed Income Conference Todd Stack VP & Treasurer 1 Forward Looking Statements This presentation may contain forward looking statements, including statements regarding the business and anticipated
More informationTransAlta Corporation. Investor Presentation April 2017
TransAlta Corporation Investor Presentation April 2017 1 Forward Looking Statements This presentation may include forward-looking statements or information (collectively referred to herein as forward-looking
More informationMTEP16 Futures Development Workshop 1/15/15
MTEP16 Futures Development Workshop 1/15/15 Overview Objectives MTEP16 proposed futures Uncertainty variables definitions Next steps 2 Objective Ensure MTEP16 Futures are effective and are developed in
More informationPortland General Electric Company Sheet No SCHEDULE 201 QUALIFYING FACILITY 10 MW or LESS AVOIDED COST POWER PURCHASE INFORMATION
Portland General Electric Company Sheet No. 201-1 PURPOSE SCHEDULE 201 QUALIFYING FACILITY 10 MW or LESS AVOIDED COST POWER PURCHASE INFORMATION To provide information about Standard Avoided Costs and
More informationSustainable Energy Handbook
Sustainable Energy Handbook Module 6.1 Simplified Financial Models Published in February 2016 1 Introduction to simplified financial models The simplified financial model is a tool that enables to understand
More informationBritish Columbia Hydro and Power Authority
2017/18 THIRD QUARTER REPORT MANAGEMENT S DISCUSSION AND ANALYSIS This Management s Discussion and Analysis (MD&A) reports on British Columbia Hydro and Power Authority s (BC Hydro or the Company) consolidated
More informationBrookfield Renewable Energy Partners L.P. Q INTERIM REPORT
Brookfield Renewable Energy Partners L.P. Q3 2015 INTERIM REPORT TABLE OF CONTENTS Letter to Shareholders 1 Generation and Financial Review for the Three Months Ended September 30, 2015 10 Generation and
More informationBRITISH COLUMBIA UTILITIES COMMISSION
C8-24 BRITISH COLUMBIA UTILITIES COMMISSION Project No.3698719, FortisBC Inc. (FBC), Application for Approval of a Multi-Year Performance Based Ratemaking Plan for 2014 2018, and FBC Application for Acceptance
More informationVolatility, risk, and risk-premium in German and Continental power markets
Volatility, risk, and risk-premium in German and Continental power markets Stefan Judisch Supply & Trading GmbH RWE Supply & Trading PAGE 0 Agenda 1. What are the market fundamentals telling us? 2. What
More informationBC Hydro takes this opportunity to raise the following two matters.
Tom A. Loski Chief Regulatory Officer Phone: 0--0 Fax: 0--0 bchydroregulatorygroup@bchydro.com September, 0 Ms. Erica Hamilton Commission Secretary British Columbia Utilities Commission Sixth Floor 00
More informationSCHEDULE C ELECTRICITY PURCHASE AGREEMENT - TERM SHEET SMALL PROJECTS
SCHEDULE C ELECTRICITY PURCHASE AGREEMENT - TERM SHEET SMALL PROJECTS The following is a summary of the key terms and conditions of the proposed standard form electricity purchase agreement ( EPA ) for
More informationHorizon Holdings Inc.
Horizon Holdings Inc. Management s Discussion and Analysis For the year ended December 31, 2011 and Auditors Report to the Shareholders and Consolidated Financial Statements Year ended December 31, 2011
More informationFor further information please contact Fred James at
BChydro Joanna Sofield Chief Regulatory Officer Phone: (604) 6-4046 Fax: (604) 6-4407 regulatory. group@bchydro.com July,008 Ms. Erica M. Hamilton Commission Secretary British Columbia Utilities Commission
More informationBuilding on strengths
Building on strengths CIBC World Markets 10 th Annual Whistler Institutional Investor Conference Steve Snyder, President & CEO February 23, 2007 Forward looking statements This presentation may contain
More informationTHIRD QUARTER REPORT FOR 2007
TRANSALTA CORPORATION THIRD QUARTER REPORT FOR 2007 MANAGEMENT S DISCUSSION AND ANALYSIS This management s discussion and analysis ( MD&A ) contains forward-looking statements. These statements are based
More information2. The Start-Up Cost Curve - this is calculated using the following information:
8.2.1.3 SIBR Generated Bid (Physical Bids only) In the event that SIBR must generate a Bid or Bid component to comply with Tariff requirements, SIBR will generate a Bid or Bid component for the resource.
More informationBROOKFIELD RENEWABLE PARTNERS L.P. Q Supplemental Information
BROOKFIELD RENEWABLE PARTNERS L.P. Q2 2018 Supplemental Information Three and Six Months Ended June 30, 2018 CAUTIONARY STATEMENT REGARDING FORWARD-LOOKING STATEMENTS This Supplemental Information contains
More information2 CA/KPL-Nalcor-157 Consumer Question: NALCOR has offered that although there has been
Reference from the Lieutenant-governor in Council On the Muskrat Falls Project (the "Muskrat Falls Review") REQUESTS FOR INFORMATION 1 2 CA/KPL-Nalcor-157 Consumer Question: NALCOR has offered that although
More informationNo-Load Definition: Educational Document
No-Load: Past and Present PJM began as a power pool where generating companies agreed to centralized dispatch of their generation. PJM originally dispatched the pool using incremental cost curves developed
More informationEconomic Benefit Analysis of the Navajo Generating Station to the Central Arizona Water Conservation District and Its Customers
ENERGY VENTURES ANALYSIS JANUARY 2018 Economic Benefit Analysis of the Navajo Generating Station to the Central Arizona Water Conservation District and Its Customers January 2018 Prepared by: ENERGY VENTURES
More informationDear Shareholder: H. Stanley Marshall President and Chief Executive Officer Fortis Inc.
Dear Shareholder: Fortis achieved another significant milestone in the second quarter with the acquisition of two regulated electric utilities in western Canada. Since the acquisition closed on May 31st,
More informationPlatte River Power Authority
Independent Auditor s Report and Financial Statements Financial Statements Years Ended Contents Independent Auditor s Report...1 Management s Discussion and Analysis (Unaudited)...3 Financial Statements
More informationTRANSALTA CORPORATION
Management's Discussion and Analysis TRANSALTA CORPORATION First Quarter Report for 2018 This Management s Discussion and Analysis ( MD&A ) contains forward-looking statements. These statements are based
More informationReview of LADWP Feed-In-Tariff Proposal for City Council
Review of LADWP Feed-In-Tariff Proposal for City Council Frederick H. Pickel, Ph.D Office of Public Accountability / Ratepayer Advocate, City of Los Angeles opa@lacity.org tel. 213-482-6814 Jan 22, 2013
More informationWhat is the range of costs?
Oliver Froend Costs and Revenues are considered separately for the implementation phase and for the operation phase Implementation Costs Direct Costs Indirect Costs Possible Revenues: Subsidies & grants(mostly
More informationAvailable To owners of Qualifying Facilities ( QF ) making sales of electricity to the Company in the State of Oregon.
FACILITIES OF GREATER THAN 10,000 KW Page 1 Available To owners of Qualifying Facilities ( QF ) making sales of electricity to the Company in the State of Oregon. Applicable For power purchased from Qualifying
More informationCommercial Operations. Steve Muscato Chief Commercial Officer
Commercial Operations Steve Muscato Chief Commercial Officer PORTFOLIO OPTIMIZATION ERCOT MARKET KEY TAKEAWAYS POWER PORTFOLIO AS A SERIES OF OPTIONS Vistra converts unit parameters and fuel logistics
More informationFINANCIAL ANALYSIS: PROJECT 1
Green Power Development and Energy Efficiency Improvement Investment Program (RRP SRI 47037) A. Background and Rationale FINANCIAL ANALYSIS: PROJECT 1 1. Project 1 of the Green Power Development and Energy
More informationNYISO s Compliance Filing to Order 745: Demand Response. Wholesale Energy Markets
NYISO s Compliance Filing to Order 745: Demand Response Compensation in Organized Wholesale Energy Markets (Docket RM10-17-000) Donna Pratt NYISO Manager, Demand Response Products Market Issues Working
More informationINVESTMENT OPPORTUNITIES AND TECHNOLOGY SELECTION: IPP VALUE PROPOSITION FOR ERCOT A WHITE PAPER BY WÄRTSILÄ
INVESTMENT OPPORTUNITIES AND TECHNOLOGY SELECTION: IPP VALUE PROPOSITION FOR ERCOT A WHITE PAPER BY WÄRTSILÄ INVESTMENT OPPORTUNITIES AND TECHNOLOGY SELECTION: IPP VALUE PROPOSITION FOR ERCOT INDEX Executive
More informationWASTE HEAT TO POWER. DOE; Pacific CHP; Northwest CHP; California Stationary Fuel Cell Collaborative. Project Financing Considerations.
WASTE HEAT TO POWER DOE; Pacific CHP; Northwest CHP; California Stationary Fuel Cell Collaborative Project Financing Considerations Wally McOuat HMH Energy Resources, Inc. 100 Larkspur Landing Circle,
More informationREPORT TO THE PUBLIC UTILITIES BOARD
REPORT TO THE PUBLIC UTILITIES BOARD CURTAILABLE RATE PROGRAM APRIL 1, 2011 MARCH 31, 2012 JULY 2012 TABLE OF CONTENTS Page No. SUMMARY... 1 BACKGROUND... 1 PERFORMANCE FOR 2011/12... 3 Curtailment Options...3
More informationMay 3, Dear Ms. Bordelon:
Entergy Services, Inc. 639 Loyola Avenue (70113) P.O. Box 61000 New Orleans, LA 70161-1000 Tel 504 576 4122 Fax 504 576 5579 Michael J. Plaisance Senior Counsel Legal Services - Regulatory May 3, 2018
More informationCEO Presentation. Curt Morgan Chief Executive Officer
CEO Presentation Curt Morgan Chief Executive Officer Vistra Energy: Changing the Power Landscape EVOLUTION OF SECTOR & INVESTOR SENTIMENT LATE 2016 / EARLY 2017 TODAY Overall Sector Sentiment Poor Retail
More information