Energy Resource Recovery Account (ERRA) 2018 Forecast of Operations Rebuttal Testimony Public Version

Size: px
Start display at page:

Download "Energy Resource Recovery Account (ERRA) 2018 Forecast of Operations Rebuttal Testimony Public Version"

Transcription

1 Application No.: Exhibit No.: Witnesses: A SCE-0 R. Sekhon D. Wong (U -E) Energy Resource Recovery Account (ERRA) 01 Forecast of Operations Rebuttal Testimony Public Version Before the Public Utilities Commission of the State of California Rosemead, California August 1, 01

2 I. INTRODUCTION (Wong) Southern California Edison Company (SCE) submits this Rebuttal Testimony in response to the August, 01, Testimony of the California Choice Energy Authority and Public Agency Coalition ( Joint Parties ) on its Application for Approval of its Forecast 01 ERRA Proceeding Revenue Requirement. 1

3 II. SCE S FORECAST OF TOTAL PORTFOLIO COSTS IS CONSISTENT WITH COMMISSION GUIDANCE (Wong) The Joint Parties inappropriately seek to change Commission policy and precedent in this SCEspecific ERRA proceeding. If the Joint Parties positions were accepted which they should not for all the reasons discussed below the departing load charge methodology for SCE s customers would be fundamentally different than for the other Investor-Owned Utilities ( IOUs ). The Joint Parties assert that the Commission has given relatively little guidance as to which IOU costs are to be included in the Total Portfolio Costs for calculating the Indifference Amount, 1 and use the lack of recent guidance on Total Portfolio Costs as an opportunity to introduce a new definition of what costs and resources should be included in departing load customers Cost Responsibility Surcharge ( CRS ). The Joint Parties create a new category of Avoidable Resources, which they define as conventional fossil-fueled Utility-Owned Generation ( UOG ) and Power Purchase Agreements ( PPAs ), propose that the fuel and variable costs associated with such Avoidable Resources be excluded from the Total Portfolio Costs used to calculate the Indifference Amount Charge (defined as the sum of the Competition Transition Charge ( CTC ) and Power Charge Indifference Adjustment ( PCIA )), and conclude that SCE s Total Portfolio Costs should be reduced by $1 million. The Commission should disregard the Joint Utilities testimony on the departing load charge methodology as outside of the scope of this SCEspecific proceeding. Moreover, as described in detail below, the Joint Parties calculations are incorrect, their proposal is wholly inconsistent with the Commission-adopted methodology for calculating the Indifference Charge, and their characterization of CAISO markets and dispatch practices is fundamentally flawed. 1 CCEA Testimony at p.. In many cases, parties refer to the full Indifference Charge simply as the PCIA.

4 A. SCE s CRS Calculation Already Excludes All Costs Associated with Cost Allocation Mechanism (CAM)-Eligible Resources and Gas Hedging Costs Pursuant to Decision ( D. ) 0-0-0, the net costs of any resources that are considered CAM-eligible are recovered from all customers through a separate non-bypassable charge known as the New System Generation Charge ( NSGC ). The Commission later clarified in D that the CRS and the [NSGC] should therefore be calculated and billed as separate items. In other words, the costs of any resources that are considered CAM-eligible, which are specified in Table VIII- of SCE s Opening Testimony, are considered ineligible for recovery through CRS and are already excluded from SCE s Indifference Calculation. As can be seen by comparing Table Joint Parties-1 with Table VIII- in Exhibit SCE-01, six of the eight resources identified by the Joint Parties as Avoidable Resources are already excluded from SCE s Indifference Calculation. As such, no adjustment associated with CAM-eligible Avoidable Resources is necessary. Additionally, SCE has also already excluded all gas hedging costs from the Total Portfolio Costs because these costs are discretionary. Correcting the Joint Parties obvious calculation errors results in the correction of the Joint Parties $1 million reduction in portfolio costs to approximately $ million, as shown in the table immediately below. However, SCE has correctly included the remaining $ million in resource costs shown in the Currently Included in CRS Indifference Calculation column in the Total Portfolio Costs. Removing them as the Joint Parties propose is inconsistent with the long-standing Commission-adopted methodology. As modified by D , D.-1-0 and D.-0-00, among others. D at p.. The six CAM-eligible resources specified in Table Joint Parties-1 are: Blythe Energy, CPV Sentinel, Walnut Creek Energy, Wellhead Power Delano, El Segundo, and SCE Peakers.

5 B. SCE s CRS Calculation is Consistent with the Commission-Adopted Methodology The Joint Parties proposal to exclude the fuel and variable costs ( marginal operating costs ) associated with operating SCE s CRS-eligible fossil-fueled resources is directly contrary to existing Commission direction and inconsistent with the Commission-adopted methodology for setting the Indifference Charge, and should be rejected. Joint Parties "To Be Excluded" The Indifference Charge is calculated based on the current above-market methodology established in D.0--0 ( Current Methodology ). The Current Methodology defines departing load customers cost responsibility ( Indifference Amount ) as the difference between the annual forecast cost of the generation portfolio procured by SCE ( Total Portfolio Costs ) and the annual forecast market value of that portfolio (defined as the forecast output of the resources in the generation portfolio multiplied by the Market Price Benchmark ( MPB )). Currently Included in CRS Indifference Calculation $000 UOG Fuel Costs not recovered in CAM PPA Fuel Costs not recovered in CAM Direct and Tolling Contract GHG Costs Gas Hedging Fuel Transportation (Carrying) Total $ 1,0 $, While the Joint Parties correctly note that the Commission has issued several decisions refining the MPB portion of the Current Methodology since it was first established, the Commission s lack of specific guidance on the specific buckets of particular costs that should be included in the Total Portfolio Costs should not be interpreted as ambiguity. D.0--0, D , D , and D all specify that the total costs of all CRS-eligible resources, with no arbitrary exclusions Subsequently modified by D , D , D , D.-1-01, and Resolution E-.

6 for marginal operating costs, are to be compared to the market value of the CRS-eligible resources to determine departing load customers cost responsibility. Indeed, D specifies the following: To derive the indifference amount, the market value of the IOU s supply portfolio is subtracted from the total portfolio cost The IOU total portfolio includes IOU-owned generation, purchased power, DWR contracts, fuel costs, and [non-load-based] California Independent System Operator (CAISO) costs. More recently, in its approval of the Joint IOU Protocol for determining the above-market costs of storage resources, the Commission confirmed that the marginal operating costs associated with operating a CRS-eligible storage resource and enabling its discharge of energy into the market should be included in the Indifference Amount. The Joint Parties assertion that their proposed exclusion of fuel and variable O&M costs is consistent with Commission precedent has no merit. In addition to being directly contrary to the Commission s direction in D to include fuel costs in the Total Portfolio Costs, the Joint Parties proposal is also nonsensical given the construct of the Current Methodology. As described above and in additional detail in Chapter IX of SCE s Opening Testimony, the Indifference Amount is defined as the difference between the forecast cost of the resources and the market value of the resources. The market value of each resource is determined by The Joint Parties cite the exclusion of forecasted load-related CAISO costs from the Total Portfolio Costs as evidence to support their proposal. However, the Commission made clear in D that only CAISO load-related costs, such as load-based congestion costs, should be excluded from the calculation. The corollary, of course, is that any CAISO supply-related costs should continue to be included in the Total Portfolio Costs because they are necessary for the operation of the CRS-eligible resources. See Exhibit A in the Testimony of the Joint Parties, served on January 1, 0 in R and adopted in D.-1-01, for the list of load-related CAISO charge codes to be excluded from the Total Portfolio Costs. Examples of supply-related CAISO costs that were not identified in Exhibit A and thus deemed by D to be CRS-eligible include: Forecasting Service Fees (ISO Charge Code 01) and No Pay Settlements (ISO Charge Codes 1,,, etc). However, please note that for purposes of administrative simplicity, SCE excludes all CAISO costs from the Total Portfolio Costs. See generally D.0--0 at p., D at p., D at p., D at p.. D at pp. - (emphasis added). D at pp. 1-.

7 multiplying its forecast energy output by the Energy MPB ( energy value ), its forecast RPS-eligible energy by the Renewable MPB, and its net qualifying capacity by the Capacity MPB. As such, the exclusion of the marginal operating costs necessary for the dispatch of fossil-fueled resources (i.e., fuel costs, GHG costs, or fuel transportation costs) from the Total Portfolio Costs, as the Joint Parties propose, would necessarily require a corresponding exclusion of the fossil-fueled resources energy value from the market value side of the equation failure to exclude the energy value while excluding the marginal operating costs is fundamentally asymmetrical. It simply does not make any sense to exclude the marginal operating costs of a fossil-fueled resource and still assume that it would generate energy to be sold in the market. SCE opposes the Joint Parties proposal even if it is modified to exclude both marginal operating costs as well as the market revenues because such a change would be inconsistent with the Current Methodology adopted by the Commission, and this is not the proceeding in which to determine changes to the Current Methodology. 1 C. The Joint Parties Incorrectly Characterize CAISO Market Operations (Sekhon) Notwithstanding the points articulated above, SCE notes that the Joint Parties have also fundamentally mischaracterized the basic structure of the CAISO market 1 and the procedures required by the Commission s Standard of Conduct (SOC ) for Least-Cost Dispatch ( LCD ). The Joint Parties state that SCE s Avoidable Resources are dispatched solely to meet the demands of bundled [service] customers. 1 That is simply wrong. As stated in Chapter IV of SCE s Opening Testimony, SCE forecasts the energy output of its generation portfolio based on a forecast of power, gas, and GHG prices, physical constraints of each generating unit, and contractual limitations. SCE s forecast methodology mirrors the CAISO day-ahead and real-time market operations by economically Based on the Joint Parties workpapers, a corresponding exclusion of the fossil-fueled energy-related market value is not a part of their proposal. 1 The Commission recently issued R (the PCIA OIR) to consider changes and reforms of the Current Methodology. 1 See Section. of the CAISO Business Practice Manual for Market Operations, available at 1 Joint Parties at p..

8 dispatching its resources in a least-cost manner, 1 rather than force-dispatching resources to meet SCE s forecast of its bundled service customers demand. Under both the SCE forecast model and CAISO operations, a generating resource or contract is selected to dispatch (on a market-wide basis) if its marginal operating cost is less than the market price of power in a given hour, while simultaneously observing all operating constraints. 1 Because dispatchable resources are only selected to dispatch when their marginal operating costs are less than the market price of power in that hour, by definition those resources only incur incremental marginal operating costs when they are in the money, regardless of the demands of bundled [service] customers in the period that the resources are dispatched. Put simply, fossil-fueled generators cannot generate energy without incurring marginal operating costs, and they would not generate energy unless they are able to recoup those costs. Accordingly, all of their avoidable costs -- as the Joint Parties define those -- are already avoided because the revenues, or energy value, received in the CAISO market for the generated energy exceed the marginal operating costs needed to generate that energy (i.e., revenues received in the CAISO market in that hour for the energy exceed the marginal operating costs needed to generate the energy). Pursuant to the Current Methodology used to determine departing load customers cost responsibility, the Indifference Calculation estimates the energy value of the resource using an administratively-set Energy MPB in lieu of using forecast CAISO revenues, which may vary by hour. As described in Chapter IX of SCE s Opening Testimony, this administratively-set Energy MPB uses load-weighted on- and off-peak energy price forecasts instead of hourly energy price forecasts an approach that the Commission deemed as a reasonable and transparent way to estimate the energy value of the generation portfolio. 1 As such, the estimated energy value using the Energy MPB may exceed, or be below, the forecast CAISO revenues. Moreover, the forecasts of marginal operating costs and 1 As directed by the Commission in its guidance on the Least Cost Dispatch (LCD) principle adopted in D Although SCE s testimony focuses on the CAISO energy market, the CAISO also operates an ancillary services market that also utilizes economic dispatch principles. 1 See generally D at pp. -.

9 energy value under the Current Methodology are not trued up for actual results. It is for these reasons that SCE is advocating, in the appropriate procedural forum and not in a utility-specific ERRA proceeding, that the Commission move away from all administratively-set MPBs. However, unless and until the Commission modifies the Current Methodology for all IOUs, or adopts an entirely new methodology for determining departing load customers cost responsibility for all IOUs, SCE s Indifference Charges must continue to be set using the methodology set forth in D

10 III. SCE S 01 RENEWABLE MPB SHOULD BE CALCULATED BASED ON THE METHODOLOGY ADOPTED IN D AND RESOLUTION E- (Wong) As described in SCE s Opening Testimony, pursuant to D and Resolution E-, the Renewable MPB is calculated by the Energy Division in October using the following data, which is submitted by each utility in an October 1 Tier 1 advice letter filing: 1. Most recent 1 months figures derived from the US Department of Energy survey of Western US renewable energy premiums compiled by the National Renewable Energy Laboratory (NREL), weighted at % (DOE Green Adder);. Average cost of the utilities newly-delivering (defined as projects starting deliveries in year n and n-1) RPS-compliant resources, weighted at % (IOU RPS Premium). 1 The Joint Parties recommend that the Commission abandon the weighted-average methodology (presumably just for SCE and not the other IOUs) outlined in Resolution E- by eliminating the use of the DOE Green Adder, and relying solely on the IOU RPS Premium to set the Renewable MPB. This proposal is procedurally improper and should be rejected, and the Commission should continue to rely on the methodology approved in D and Resolution E- to set the 01 CRS Indifference Charges. As noted in SCE s Opening Testimony, SCE used the 01 DOE Green Adder, which was reviewed and approved by the Energy Division, 1 as a proxy input pending the Energy Division s verification and finalization of the data submitted in the October 1, 01 Tier 1 advice letter filing. Pursuant to Resolution E-, the final Renewable MPB is calculated by the Energy Division using data included in the advice letters submitted by the three electric IOUs. As such, any factual dispute related to the validity of any individual Utility Green Pricing Programs used to calculate the 01 1 Resolution E- at p. and Exhibit A. 1 See Energy Division s November 1, 01 approval of SCE s Advice -E.

11 DOE Green Adder calculation is premature and procedurally belongs as a protest to SCE s October 1, 01 Tier 1 advice letter filing. However, as a general matter, SCE agrees with the Joint Parties that the DOE Green Adder is not reflective of current market prices 0 and acknowledges that certain data that was on the National Renewable Energy Laboratory (NREL) website, which was maintained by NREL and simply accessed by SCE and the other IOUs annually for purposes of the October 1 Tier 1 advice letter filing, may be out of date. 1 Moreover, it appears as though the NREL website accessed by SCE on September 1, 01 for its October 1, 01 Tier 1 advice letter filing is no longer available. For these reasons, SCE does not disagree with the Joint Parties that the DOE Green Adder is fatally flawed. Indeed, as articulated in the Joint Utilities July 1, 01 Comments to Rulemaking (R.)1-0-0, it is SCE s position that the Commission wholly replace the Current Methodology and abandon the use of any administratively-set MPBs. However, the procedural venue to propose any changes to the Current Methodology, including any modifications to the MPBs, is R (i.e., the PCIA OIR), not an individual utility s ERRA Forecast proceeding. Until the Commission modifies the Current Methodology for all the IOUs in that Rulemaking, SCE s Renewable MPB must be calculated using the methodology outlined in D and Resolution E-. Specifically, pursuant to D.-1-01, the DOE Green Adder portion should be determined using the most recent 0 SCE noted its agreement with parties on this point at the December 1, 01 PCIA Working Group meeting. 1 Joint Parties Testimony at p.. SCE will access the NREL and DOE websites prior to its October 1, 01 Tier 1 advice letter filing to locate a list comparable to that filed and approved in SCE s Advice -E. If no comparable list is available, SCE will re-file the most recently reported list, which is that filed and approved in Advice -E. D at p. 1. See Comments of Pacific Gas and Electric, San Diego Gas and Electric, and Southern California Edison to R.1-0-0, filed July 1, 01, at pp. -. See R.1-0-0, the Order Instituting Rulemaking to Review, Revise, and Consider Alternatives to the Power Charge Indifference Adjustment. R identifies updates and alternative methods to the MPB as an issue to be considered in the proceeding. See R at p..

12 DOE [Green Adder] or figures of reported contract premiums for renewable energy in the Western U.S., which is the DOE Green Adder approved in 01, if no alternative data source is available. The Joint Parties proposal to replace the DOE Green Adder (currently effective value of $1./MWh) with the IOU RPS Premium (01 estimated value of $1./MWh) would eliminate the weighted average approach adopted by the Commission in D and Resolution E- and reduce the vintage Indifference Charges by %. 0 Such a modification is procedurally improper and ignores the direction provided by the Commission in D Specifically, in the discussion approving the weighted average approach, the Commission explained that setting the Renewable MPB equal to the IOU RPS Premium, as Direct Access parties had proposed in R.0-0-0, would be unacceptable because the IOU RPS Premium does not reflect all California-delivered RPSeligible wholesale supply and excludes RPS costs of [Energy Service Providers], [Community Choice Aggregators], [Community Aggregators], and publicly-owned utilities that make up more than % of California load. 1 The Commission concluded that, despite the questions and concerns that had been raised regarding the usefulness of the DOE data, some recognition of the DOE data sources [was warranted to offer] a broader measure of the California RPS market compared with exclusive reliance on IOU resource data. As such, pending Commission resolution of the necessary replacement of the Current Methodology in R.1-0-0, the only reasonable means to comply with the existing Commission direction and guidance on this matter is to use the 01 DOE Green Adder. D at p. (emphasis added). SCE notes that the DOE Green Adders effective in have ranged between $1./MWh and $1./MWh. See SCE Advice -E, 1-E, 0-E, and -E. SCE notes that despite proposing to eliminate the weighted average approach entirely and replacing it with the IOU RPS Premium, the Joint Parties continue to characterize the Renewable MPB as the Weighted Average Green Benchmark. 0 Estimates based on Joint Parties proposed Weighted Average Green Benchmark of $./MWh. 1 D at p. 1. D at p..

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Application Of Southern California Edison Company (U 338-E) For Approval Of Its Forecast 2017 ERRA Proceeding Revenue Requirement. A.16-05-001

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) )

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) ) BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Application of Southern California Edison Company (U 338-E For Applying the Market Index Formula And As-Available Capacity Prices Adopted

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION California Independent System Operator Corporation ) ) ) Docket No. ER13-872-000 MOTION TO INTERVENE AND COMMENTS OF SOUTHERN CALIFORNIA

More information

Schedule GTSR-CR Sheet 1 GREEN TARIFF SHARED RENEWABLES COMMUNITY RENEWABLES

Schedule GTSR-CR Sheet 1 GREEN TARIFF SHARED RENEWABLES COMMUNITY RENEWABLES Southern California Edison Revised Cal. PUC Sheet No. 59541-E Rosemead, California (U 338-E) Cancelling Original Cal. PUC Sheet No. 56740-E Schedule GTSR-CR Sheet 1 APPLICABILITY This Schedule is applicable

More information

Testimony of Stephen E. Pickett

Testimony of Stephen E. Pickett Application No.: Exhibit No.: Witness: SCE-1 S. Pickett (U -E) Testimony of Stephen E. Pickett Before the Public Utilities Commission of the State of California Rosemead, California August, 0 1 PREPARED

More information

PREPARED DIRECT TESTIMONY OF THE CALIFORNIA COMMUNITY CHOICE ASSOCIATION. VOLUME 2 Chapter 3 Public

PREPARED DIRECT TESTIMONY OF THE CALIFORNIA COMMUNITY CHOICE ASSOCIATION. VOLUME 2 Chapter 3 Public Rulemaking 1-0-0 Exhibit Date April, 0 Witnesses Various PREPARED DIRECT TESTIMONY OF THE CALIFORNIA COMMUNITY CHOICE ASSOCIATION VOLUME Chapter Public Going Forward Utility Portfolio Optimization (Common

More information

Schedule GTSR-GR Sheet 1 GREEN TARIFF SHARED RENEWABLES GREEN RATE

Schedule GTSR-GR Sheet 1 GREEN TARIFF SHARED RENEWABLES GREEN RATE Southern California Edison Revised Cal. PUC Sheet No. 59547-E Rosemead, California (U 338-E) Cancelling Original Cal. PUC Sheet No. 56750-E Schedule GTSR-GR Sheet 1 APPLICABILITY This Schedule is applicable

More information

December 11, 2003 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION

December 11, 2003 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION Akbar Jazayeri Director of Revenue and Tariffs December 11, 2003 ADVICE 1717-E-A (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Tariff Modifications Associated

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Application of Pacific Gas and Electric Company (U 39-E) for Approval of Demand Response Programs, Pilots and Budgets for Program Years

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA. And Related Matters. Application Application

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA. And Related Matters. Application Application BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Application of San Diego Gas & Electric Company (U902E) for Authority to Implement Optional Pilot Program to Increase Customer Access to

More information

Russell G. Worden Director, Regulatory Operations Southern California Edison Company 8631 Rush Street Rosemead, CA 91770

Russell G. Worden Director, Regulatory Operations Southern California Edison Company 8631 Rush Street Rosemead, CA 91770 ;STATE OF CALIFORNIA PUBLIC UTILITIES COMMISSION SAN FRANCISCO, CA 94102-3298 Edmund G. Brown Jr., Governor November 13, 2015 Advice Letter 3219-E and 3219-E-A Russell G. Worden Director, Regulatory Operations

More information

107 FERC 61, 042 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

107 FERC 61, 042 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 107 FERC 61, 042 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Pat Wood, III, Chairman; Nora Mead Brownell, and Joseph T. Kelliher. California Independent System Operator

More information

Procurement and Risk Management Update. Presented to RCEA Board of Directors October 16, 2017

Procurement and Risk Management Update. Presented to RCEA Board of Directors October 16, 2017 Procurement and Risk Management Update Presented to RCEA Board of Directors October 16, 2017 Update on 2017 Discussion Topics Current headroom outlook Review procurement activities Update on 2018 Preliminary

More information

Residential Line and Service Extension Allowance Testimony. Application No.: Witnesses: C. Silsbee S. Reed J. Schichtl L. Vellanoweth (U 338-E)

Residential Line and Service Extension Allowance Testimony. Application No.: Witnesses: C. Silsbee S. Reed J. Schichtl L. Vellanoweth (U 338-E) Application No.: Exhibit No.: Witnesses: SCE-1 C. Silsbee S. Reed J. Schichtl L. Vellanoweth (U -E) Residential Line and Service Extension Allowance Testimony Before the Public Utilities Commission of

More information

PREPARED DIRECT TESTIMONY OF THE CALIFORNIA COMMUNITY CHOICE ASSOCIATION. VOLUME 1 Chapters 1, 2A and 2B

PREPARED DIRECT TESTIMONY OF THE CALIFORNIA COMMUNITY CHOICE ASSOCIATION. VOLUME 1 Chapters 1, 2A and 2B Rulemaking 1-0-0 Exhibit Date April, 01 Witnesses Various PREPARED DIRECT TESTIMONY OF THE CALIFORNIA COMMUNITY CHOICE ASSOCIATION VOLUME 1 Chapters 1, A and B Introduction PCIA Effectiveness in Avoiding

More information

Annual Electric True-Up Submittal Change to PG&E's Electric Rates on January 1, 2019

Annual Electric True-Up Submittal Change to PG&E's Electric Rates on January 1, 2019 Erik Jacobson Director Regulatory Relations Pacific Gas and Electric Company 77 Beale St., Mail Code B13U P.O. Box 770000 San Francisco, CA 94177 Facsimile: (415) 973-3582 September 4, 2018 Advice 5376-E

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. ) Southern California Edison ) Docket No. ER Company )

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. ) Southern California Edison ) Docket No. ER Company ) UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) Southern California Edison ) Docket No. ER12-239-000 Company ) SOUTHERN CALIFORNIA EDISON COMPANY S REQUEST FOR LEAVE AND RESPONSE

More information

ADVICE LETTER (AL) SUSPENSION NOTICE ENERGY DIVISION

ADVICE LETTER (AL) SUSPENSION NOTICE ENERGY DIVISION ADVICE LETTER (AL) SUSPENSION NOTICE ENERGY DIVISION Utility Name: SCE Utility Number/Type: U338-E Advice Letter Number(s) 3214-E Date AL(s) Filed) 5/1/15 Utility Contact Person: Darrah Morgan Utility

More information

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California Cancelling Revised Cal. PUC Sheet No E*

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California Cancelling Revised Cal. PUC Sheet No E* Southern California Edison Revised Cal. PUC Sheet No. 28371-E Rosemead, California Cancelling Revised Cal. PUC Sheet No. 26736-E* Schedule PE Sheet 1 APPLICABILITY Applicable to all SCE Bundled Service

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA COMMENTS OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA COMMENTS OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking to Develop an Electricity Integrated Resource Planning Framework and to Coordinate and Refine Long-Term Procurement

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. San Diego Gas & Electric Company ) Docket No.

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. San Diego Gas & Electric Company ) Docket No. UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION San Diego Gas & Electric Company ) Docket No. EL15-103-000 REQUEST FOR REHEARING OF PACIFIC GAS AND ELECTRIC COMPANY AND SOUTHERN

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) ) ) ) ) ) ) ) )

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) ) ) ) ) ) ) ) ) BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking Regarding Policies, Procedures and Rules for Development of Distribution Resources Plans Pursuant to Public

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA OPENING BRIEF OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E)

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA OPENING BRIEF OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Expedited Application Of Southern California Edison Company (U 338-E) Regarding Energy Resource Recovery Account Trigger Mechanism. Application

More information

OPINION APPROVING A RATE DESIGN SETTLEMENT LOWERING PACIFIC GAS AND ELECTRIC COMPANY S RATES BY $799 MILLION

OPINION APPROVING A RATE DESIGN SETTLEMENT LOWERING PACIFIC GAS AND ELECTRIC COMPANY S RATES BY $799 MILLION ALJ/JJJ/hl2 Mailed 2/27/2004 Decision 04-02-062 February 26, 2004 BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Investigation into the ratemaking implications for

More information

4.1 Daily & Hourly Bid Components

4.1 Daily & Hourly Bid Components 4.1 Daily & Hourly Bid Components This section is based on CAISO Tariff Section 30.4 Election for Start-Up and Minimum Load Costs and Section 39.6.1.6. (Start-Up and Minimum Load Costs are not applicable

More information

2018 General Rate Case

2018 General Rate Case Application No.: Exhibit No.: Witnesses: A.1-0-001 SCE-TURN-01 S. Menon (SCE) W. Marcus (TURN) (U -E) 01 General Rate Case SCE-TURN Joint Supplemental Testimony Regarding SPIDA Software Disallowance Scenarios

More information

ELECTRIC SCHEDULE E-SDL Sheet 1 SPLIT-WHEELING DEPARTING LOAD

ELECTRIC SCHEDULE E-SDL Sheet 1 SPLIT-WHEELING DEPARTING LOAD Revised Cal. P.U.C. Sheet No. 28588-E Cancelling Revised Cal. P.U.C. Sheet No. 27455-E ELECTRIC SCHEDULE E-SDL Sheet 1 APPLICABILITY: TERRITORY: RATES: This schedule is applicable to customers that have

More information

CCA 101: Policy and Governance Dawn Weisz, MCE Chief Executive Officer

CCA 101: Policy and Governance Dawn Weisz, MCE Chief Executive Officer CCA 101: Policy and Governance Dawn Weisz, MCE Chief Executive Officer Presentation Overview Growth of CCA Core Policy Issues Exit Fees and Non-Bypassable Charges Future of California s Energy Policies

More information

REBUTTAL TESTIMONY OF NEIL MILLAR ON BEHALF OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION

REBUTTAL TESTIMONY OF NEIL MILLAR ON BEHALF OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION Application No.: --00 Exhibit No.: Witness: Neil Millar In the Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (UE) for a Certificate of Public Convenience and Necessity for the West of

More information

Summary of Prior CAISO Filings and Commission Orders Concerning CAISO Market Redesign Efforts

Summary of Prior CAISO Filings and Commission Orders Concerning CAISO Market Redesign Efforts Summary of Prior CAISO Filings and Commission Orders Concerning CAISO Market Redesign Efforts 1. Commission Directives to Submit a Market Redesign Plan The direct origin of the requirement that the CAISO

More information

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. Southern California Edison Revised Cal. PUC Sheet No. 28658-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 27754-E INCREMENTAL SALES RATE AGREEMENT (To be inserted by utility) Issued

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA REPLY BRIEF OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E)

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA REPLY BRIEF OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Expedited Application of Southern California Edison Company (U338E) Regarding Energy Resource Recovery Account Trigger Mechanism. Application

More information

December 10, Advice 5440-E (Pacific Gas and Electric Company ID U 39 E) Public Utilities Commission of the State of California

December 10, Advice 5440-E (Pacific Gas and Electric Company ID U 39 E) Public Utilities Commission of the State of California Erik Jacobson Director Regulatory Relations Pacific Gas and Electric Company 77 Beale St., Mail Code B13U P.O. Box 770000 San Francisco, CA 94177 December 10, 2018 Fax: 415-973-3582 Advice 5440-E (Pacific

More information

April 6, Your courtesy in this matter is appreciated. Very truly yours, James M. Lehrer

April 6, Your courtesy in this matter is appreciated. Very truly yours, James M. Lehrer James M. Lehrer Senior Attorney James.Lehrer@sce.com April 6, 2005 Docket Clerk California Public Utilities Commission 505 Van Ness Avenue San Francisco, California 94102 RE: APPLICATION NO. 04-12-014

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 39. Market Power Mitigation Procedures... 2 39.1 Intent Of CAISO Mitigation Measures; Additional FERC Filings... 2 39.2 Conditions For The Imposition Of Mitigation Measures... 2 39.2.1

More information

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. Southern California Edison Revised Cal. PUC Sheet No. 64409-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 58722-E Schedule NEM Sheet 1 APPLICABILITY Applicable to Eligible Customer-Generators

More information

Schedule NEM-V-ST Sheet 1 VIRTUAL NET METERING FOR MULTI-TENANT AND MULTI-METER PROPERTIES SUCCESSOR TARIFF

Schedule NEM-V-ST Sheet 1 VIRTUAL NET METERING FOR MULTI-TENANT AND MULTI-METER PROPERTIES SUCCESSOR TARIFF Southern California Edison Revised Cal. PUC Sheet No. 60503-E Rosemead, California (U 338-E) Cancelling Original Cal. PUC Sheet No. 58758-E Schedule NEM-V-ST Sheet 1 APPLICABILITY This Schedule is applicable

More information

Southern California Edison Company (U 338-E) Smart Meter Opt-Out Phase 2 Rebuttal Testimony

Southern California Edison Company (U 338-E) Smart Meter Opt-Out Phase 2 Rebuttal Testimony Application No.: Exhibit No.: Witnesses: A.-0-00 K. Ellison G. Huckaby L. Letizia J. Lim L. Miller L. Oliva (U -E) Southern California Edison Company (U -E) Smart Meter Opt-Out Phase Rebuttal Testimony

More information

BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON UM 1953 I. INTRODUCTION

BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON UM 1953 I. INTRODUCTION BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON UM 1953 In the Matter of PORTLAND GENERAL ELECTRIC COMPANY, STAFF'S OPENING BRIEF Investigation into Proposed Green Tariff. I. INTRODUCTION Pursuant to Administrative

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking to Review, Revise, and Consider Alternatives to the Power Charge Indifference Adjustment. Rulemaking 17-06-026

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 39. Market Power Mitigation Procedures... 2 39.1 Intent of CAISO Mitigation Measures; Additional FERC Filings... 2 39.2 Conditions for the Imposition of Mitigation Measures... 2 39.2.1

More information

SDG&E REBUTTAL TESTIMONY OF CYNTHIA S. FANG (ELECTRIC RATES AND BILL COMPARISON) JUNE 18, 2018

SDG&E REBUTTAL TESTIMONY OF CYNTHIA S. FANG (ELECTRIC RATES AND BILL COMPARISON) JUNE 18, 2018 Company: San Diego Gas & Electric Company (U902M) Proceeding: 2019 General Rate Case Application: A.17-10-007/-008 (cons.) Exhibit: SDG&E-246 SDG&E REBUTTAL TESTIMONY OF CYNTHIA S. FANG (ELECTRIC RATES

More information

January 22, Establishment of Smart Energy Program and Modification of Summer Discount Plan in Compliance with Decision

January 22, Establishment of Smart Energy Program and Modification of Summer Discount Plan in Compliance with Decision Russell G. Worden Managing Director, State Regulatory Operations January 22, 2018 ADVICE 3731-E (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Establishment of

More information

2018 General Rate Case Rebuttal Testimony

2018 General Rate Case Rebuttal Testimony Application No.: A.1-0-001 Exhibit No.: SCE-, Vol. 0 Witnesses: R. Ramos J. Smolk R. Swartz D. Tessler S. Tran (U -E) 01 General Rate Case Rebuttal Testimony Administrative & General (A&G) Volume 0 Legal

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION California Independent System ) Docket No. ER18-1169-000 Operator Corporation ) MOTION TO INTERVENE AND PROTEST OF THE DEPARTMENT

More information

Ellen Wolfe Resero Consulting for WPTF. February 28, 2018

Ellen Wolfe Resero Consulting for WPTF. February 28, 2018 Western Power Trading Forum Comments on CAISO CRR Auction Efficiency Workshop and Stakeholder Process Ellen Wolfe Resero Consulting for WPTF February 28, 2018 WPTF appreciates the ability to submit these

More information

BEFORE THE PENNSYLVANIA PUBLIC UTILITY COMMISSION : : : : : REPLY OF PECO ENERGY COMPANY TO EXCEPTIONS

BEFORE THE PENNSYLVANIA PUBLIC UTILITY COMMISSION : : : : : REPLY OF PECO ENERGY COMPANY TO EXCEPTIONS BEFORE THE PENNSYLVANIA PUBLIC UTILITY COMMISSION PETITION OF PECO ENERGY COMPANY FOR APPROVAL OF ITS DEFAULT SERVICE PROGRAM FOR THE PERIOD FROM JUNE 1, 2015 THROUGH MAY 31, 2017 : : : : : DOCKET NO.

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking to Continue Implementation and Administration, and Consider Further Development, of California Renewables

More information

PREPARED REBUTTAL TESTIMONY OF HECTOR A. MADARIAGA ON BEHALF OF SOUTHERN CALIFORNIA GAS COMPANY

PREPARED REBUTTAL TESTIMONY OF HECTOR A. MADARIAGA ON BEHALF OF SOUTHERN CALIFORNIA GAS COMPANY Application of San Diego Gas & Electric Company (U0M) for Authority, Among Other Things, to Increase Rates and Charges for Electric and Gas Service Effective on January 1, 01. A.-1-00 (Filed December 1,

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA APPLICATION OF PACIFIC GAS AND ELECTRIC COMPANY ANN H. KIM GAIL L.

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA APPLICATION OF PACIFIC GAS AND ELECTRIC COMPANY ANN H. KIM GAIL L. BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Application of Pacific Gas and Electric Company for Approval of Economic Development Rate for 2013-2017 (U 39 E) Application No. 12-03-

More information

October 24, 2000 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION

October 24, 2000 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION Donald A. Fellows, Jr. Manager of Revenue and Tariffs October 24, 2000 ADVICE 1493-E (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Revision to SCE s Interruptible

More information

Amendment to extend exceptional dispatch mitigated energy settlement rules and modify residual imbalance energy settlement rules

Amendment to extend exceptional dispatch mitigated energy settlement rules and modify residual imbalance energy settlement rules California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Nancy Saracino, Vice President, General Counsel & Chief Administrative Officer Date: September 7, 2012 Re:

More information

Ensuring Resource Adequacy in California: An Alternative to Centralized Capacity Markets

Ensuring Resource Adequacy in California: An Alternative to Centralized Capacity Markets Ensuring Resource Adequacy in California: An Alternative to Centralized Capacity Markets Presentation to the CAISO Independent Market Surveillance Committee by the Bilateral Trading Group August 8, 2006

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION California Independent System ) Docket No. ER18-641-000 Operator Corporation ) MOTION TO INTERVENE AND PROTEST OF THE DEPARTMENT

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking to Continue Implementation and Administration, and Consider Further Development of, California Renewables

More information

SOUTHERN CALIFORNIA GAS COMPANY ADVANCED METERING INFRASTRUCTURE AMENDED REBUTTAL TESTIMONY CHAPTER 3 SOCALGAS AMI DEPLOYMENT PLAN, COSTS,

SOUTHERN CALIFORNIA GAS COMPANY ADVANCED METERING INFRASTRUCTURE AMENDED REBUTTAL TESTIMONY CHAPTER 3 SOCALGAS AMI DEPLOYMENT PLAN, COSTS, Application No.: A.0-0-0 Exhibit No.: SCG 1 Date: June 1, 00 Witness: Mark L. Serrano SOUTHERN CALIFORNIA GAS COMPANY ADVANCED METERING INFRASTRUCTURE AMENDED REBUTTAL TESTIMONY CHAPTER SOCALGAS AMI DEPLOYMENT

More information

SUBJECT: SCEs 2014 Assembly Bill 57 Bundled Procurement Plan Compliance Filing

SUBJECT: SCEs 2014 Assembly Bill 57 Bundled Procurement Plan Compliance Filing STATE OF CALIFORNIA Edmund G. Brown Jr., Governor PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 February 16, 2016 Advice Letter: 3349-E Russell G. Worden Managing Director,

More information

BEFORE THE PENNSYLVANIA PUBLIC UTILITY COMMISSION. PENNSYLVANIA PUBLIC UTILITY COMMISSION v. PECO ENERGY COMPANY DOCKET NO.

BEFORE THE PENNSYLVANIA PUBLIC UTILITY COMMISSION. PENNSYLVANIA PUBLIC UTILITY COMMISSION v. PECO ENERGY COMPANY DOCKET NO. PECO ENERGY COMPANY STATEMENT NO. -R BEFORE THE PENNSYLVANIA PUBLIC UTILITY COMMISSION PENNSYLVANIA PUBLIC UTILITY COMMISSION v. PECO ENERGY COMPANY DOCKET NO. R-01-0001 REBUTTAL TESTIMONY WITNESS: ALAN

More information

SDG&E Applies to Default Small Non-Residential Customers to Critical Peak Pricing in 2013

SDG&E Applies to Default Small Non-Residential Customers to Critical Peak Pricing in 2013 UGI Utilities - Gas Division Files Unopposed POR Settlement UGI Utilities, Inc. - Gas Division has filed an unopposed settlement that would institute a Purchase of Receivables program for customers served

More information

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. Southern California Edison Revised Cal. PUC Sheet No. 58755-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 55676-E APPLICABILITY Schedule NEM-V Sheet 1 Applicable to Qualified Customers

More information

2015 General Rate Case Rebuttal Testimony

2015 General Rate Case Rebuttal Testimony Application No.: Exhibit No.: Witnesses: A.1--00 SCE- M. Bennett G. Henry S. Lu P. Miller J. Trapp R. Worden (U -E) 01 General Rate Case Rebuttal Testimony Human Resources (HR) Department, Benefits And

More information

CHAPTER II NEW CURTAILMENT ORDER PREPARED DIRECT TESTIMONY OF STEVE WATSON BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

CHAPTER II NEW CURTAILMENT ORDER PREPARED DIRECT TESTIMONY OF STEVE WATSON BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Application No: Exhibit No.: Witness: A.1-0- Steve Watson Application of Southern California Gas Company (U 0 G) and San Diego Gas & Electric Company (U 0 G) for Authority to Revise their Curtailment Procedures

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking to Continue Implementation and Administration, and Consider Further Development, of California Renewables

More information

Southern California Edison s Renewable Auction Mechanism (RAM) Program. June 6, 2014 EPRG Workshop on Distributed Generation and Smart Connections

Southern California Edison s Renewable Auction Mechanism (RAM) Program. June 6, 2014 EPRG Workshop on Distributed Generation and Smart Connections Southern California Edison s Renewable Auction Mechanism (RAM) Program June 6, 2014 EPRG Workshop on Distributed Generation and Smart Connections The RAM Contracting Tool In D.10-12-048 ( the RAM Decision

More information

STATE OF IOWA BEFORE THE IOWA UTILITIES BOARD : : : : : : : : : : : : MIDAMERICAN ENERGY COMPANY S INITIAL BRIEF

STATE OF IOWA BEFORE THE IOWA UTILITIES BOARD : : : : : : : : : : : : MIDAMERICAN ENERGY COMPANY S INITIAL BRIEF STATE OF IOWA BEFORE THE IOWA UTILITIES BOARD IN RE MIDAMERICAN ENERGY COMPANY Docket No. EAC-2016-0006 Docket No. EAC-2017-0006 MIDAMERICAN ENERGY COMPANY S INITIAL BRIEF Table of Contents I. PROCEDURAL

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA. And Related Matter. Rulemaking

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA. And Related Matter. Rulemaking BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Application of SAN DIEGO GAS & ELECTRIC COMPANY (U902E) for Approval of its Electric Vehicle-Grid Integration Pilot Program. Application

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Credit and Capital Issues Affecting the ) Docket No. AD09-2-000 Electric Power Industry ) COMMENTS OF SOUTHERN CALIFORNIA EDISON

More information

2015 General Rate Case

2015 General Rate Case Application No.: Exhibit No.: SCE-, Vol. 0, Revision 1 Witnesses: J. Carrillo M. Childs P. Wong R. Fisher P. Hunt D. Lee K. Shimmel R. Worden (U -E) 01 General Rate Case Public Version ERRATA Results of

More information

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) DIRECT TESTIMONY RUTH M. SAKYA.

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) DIRECT TESTIMONY RUTH M. SAKYA. BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION IN THE MATTER OF SOUTHWESTERN PUBLIC SERVICE COMPANY S APPLICATION REQUESTING: (1) ACKNOWLEDGEMENT OF ITS FILING OF THE 2016 ANNUAL RENEWABLE ENERGY PORTFOLIO

More information

February 14, RE: Southern California Edison 2006 General Rate Case, A , et al.

February 14, RE: Southern California Edison 2006 General Rate Case, A , et al. Frank A. McNulty Senior Attorney mcnultfa@sce.com February 14, 2005 Docket Clerk California Public Utilities Commission 505 Van Ness Avenue San Francisco, California 94102 RE: Southern California Edison

More information

Dynamic Pricing Proposals of Southern California Edison Company in Compliance with D

Dynamic Pricing Proposals of Southern California Edison Company in Compliance with D Application No.: Exhibit No.: Witnesses: A.-0- SCE-01 Russ Garwacki Robert Thomas Lisa Vellanoweth (U -E) Dynamic Pricing Proposals of Southern California Edison Company in Compliance with D.0-0-0 Before

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Application of Southern California Edison Company (U 338-E) to Establish Marginal Costs, Allocate Revenues, and Design Rates. A.17-06-030

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 39. Market Power Mitigation Procedures... 2 39.1 Intent Of CAISO Mitigation Measures; Additional FERC Filings... 2 39.2 Conditions For The Imposition Of Mitigation Measures... 2 39.2.1

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) MOTION TO INTERVENE AND COMMENTS OF SOUTHERN CALIFORNIA EDISON COMPANY

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) MOTION TO INTERVENE AND COMMENTS OF SOUTHERN CALIFORNIA EDISON COMPANY UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION California Independent System Operator Corp., Docket No. ER15-1229-000 MOTION TO INTERVENE AND COMMENTS OF Pursuant to Rules 211

More information

Schedule NEM-V Sheet 1 VIRTUAL NET ENERGY METERING FOR MULTI-TENANT AND MULTI-METER PROPERTIES

Schedule NEM-V Sheet 1 VIRTUAL NET ENERGY METERING FOR MULTI-TENANT AND MULTI-METER PROPERTIES Southern California Edison Revised Cal. PUC Sheet No. 55676-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 54511-E* APPLICABILITY Schedule NEM-V Sheet 1 Applicable to Qualified

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA. And Related Matters. Application Application

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA. And Related Matters. Application Application BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Application of Pacific Gas and Electric Company (U39E) for Approval of Demand Response Programs, Pilots and Budgets for Program Years 2018-2022.

More information

ALJ/AES/lil Date of Issuance 12/21/2011 DECISION IMPLEMENTING PORTFOLIO CONTENT CATEGORIES FOR THE RENEWABLES PORTFOLIO STANDARD PROGRAM

ALJ/AES/lil Date of Issuance 12/21/2011 DECISION IMPLEMENTING PORTFOLIO CONTENT CATEGORIES FOR THE RENEWABLES PORTFOLIO STANDARD PROGRAM ALJ/AES/lil Date of Issuance 12/21/2011 Decision 11-12-052 December 15, 2011 BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking to Continue Implementation and

More information

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. Southern California Edison Revised Cal. PUC Sheet No. 59895-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 57290-E GENERATING FACILITY INTERCONNECTION AGREEMENT (Non-Exporting)

More information

SDG&E REBUTTAL TESTIMONY OF NORMA G. JASSO (REGULATORY ACCOUNTS) June 2015

SDG&E REBUTTAL TESTIMONY OF NORMA G. JASSO (REGULATORY ACCOUNTS) June 2015 Company: San Diego Gas & Electric Company (U0M) Proceeding: 01 General Rate Case Application: A.1--00 Exhibit: SDG&E- SDG&E REBUTTAL TESTIMONY OF NORMA G. JASSO (REGULATORY ACCOUNTS) June 01 BEFORE THE

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA FILED 12/01/17 04:59 PM Order Instituting Rulemaking to Continue Implementation and Administration, and Consider Further Development of,

More information

Schedule NEM-ST Sheet 1 NET ENERGY METERING SUCCESSOR TARIFF

Schedule NEM-ST Sheet 1 NET ENERGY METERING SUCCESSOR TARIFF Southern California Edison Revised Cal. PUC Sheet No. 60463-E Rosemead, California (U 338-E) Cancelling Original Cal. PUC Sheet No. 58728-E Schedule NEM-ST Sheet 1 APPLICABILITY This Schedule is applicable

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION AES Huntington Beach, LLC ) Docket No. ER13-351-000 ANSWER OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION TO MOTION TO

More information

SECOND REVISED SDG&E DIRECT TESTIMONY OF KENNETH J. DEREMER (POST-TEST YEAR RATEMAKING) April 6, 2018

SECOND REVISED SDG&E DIRECT TESTIMONY OF KENNETH J. DEREMER (POST-TEST YEAR RATEMAKING) April 6, 2018 Company: San Diego Gas & Electric Company (U 0 M) Proceeding: 01 General Rate Case Application: A.1--00 Exhibit: SDG&E--R SECOND REVISED SDG&E DIRECT TESTIMONY OF KENNETH J. DEREMER (POST-TEST YEAR RATEMAKING)

More information

Exhibit A Affidavit of Alan Varvis

Exhibit A Affidavit of Alan Varvis Affidavit of Alan Varvis Page 1 of 9 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Southern California Edison Company ) Docket No. ER16- -000 AFFIDAVIT OF ALAN VARVIS FOR SOUTHERN

More information

APPENDIX IX ATTACHMENT 1 FORMULA RATE PROTOCOLS

APPENDIX IX ATTACHMENT 1 FORMULA RATE PROTOCOLS APPENDIX IX ATTACHMENT 1 FORMULA RATE PROTOCOLS 1. INTRODUCTION SCE shall calculate its Base Transmission Revenue Requirement ( Base TRR ), as defined in Section 3.6 of the main definitions section of

More information

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. Southern California Edison Revised Cal. PUC Sheet No. 57517-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 55662-E Schedule NEM Sheet 1 APPLICABILITY Applicable to Eligible Customer-Generators

More information

Storage as a Transmission Asset Stakeholder Comment Template

Storage as a Transmission Asset Stakeholder Comment Template Storage as a Transmission Asset Stakeholder Comment Template Submitted by Company Date Submitted David Kates The Nevada Hydro Company, Inc. (707) 570-1866 david@leapshydro.com The Nevada Hydro Company,

More information

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. Southern California Edison Revised Cal. PUC Sheet No. 65881-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 64401-E Schedule CPP Sheet 1 APPLICABILITY This Schedule is optional for

More information

Management recommends the following enhancements to these modifications to the provisions for commitment costs:

Management recommends the following enhancements to these modifications to the provisions for commitment costs: California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: May 9, 2012 Re: Decision on Commitment

More information

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. Southern California Edison Revised Cal. PUC Sheet No. 59107-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 57595-E Schedule TOU-GS-3 Sheet 1 APPLICABILITY Applicable to single-

More information

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. Southern California Edison Revised Cal. PUC Sheet No. 62766-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 53907-E Sheet 1 DIRECT ACCESS CUSTOMER RELOCATION DECLARATION (To be inserted

More information

Southern California Edison Company s Supplemental Exhibit in Response to Administrative Law Judge s May 6, Ruling

Southern California Edison Company s Supplemental Exhibit in Response to Administrative Law Judge s May 6, Ruling Application No.: Exhibit No.: Witnesses: A.1-11-00 SCE- Douglas Snow Melvin Stark (U -E) Southern California Edison Company s Supplemental Exhibit in Response to Administrative Law Judge s May, 01 Email

More information

SOUTHERN CALIFORNIA EDISON COMPANY S (U 338-E) 2011 RENEWABLES PORTFOLIO STANDARD PROCUREMENT PLAN VOLUME 1

SOUTHERN CALIFORNIA EDISON COMPANY S (U 338-E) 2011 RENEWABLES PORTFOLIO STANDARD PROCUREMENT PLAN VOLUME 1 BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking to Continue Implementation and Administration of California Renewables Portfolio Standard Program. ) ) ) )

More information

PHASE I.A. DIRECT TESTIMONY OF DR. KARL MEEUSEN ON BEHALF OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION

PHASE I.A. DIRECT TESTIMONY OF DR. KARL MEEUSEN ON BEHALF OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION Rulemaking No.: --00 Exhibit No.: Witness: Dr. Karl Meeusen Order Instituting Rulemaking to Integrate and Refine Procurement Policies and Consider Long-Term Procurement Plans. Rulemaking --00 PHASE I.A.

More information

Rebuttal Testimony of Southern California Edison for Phase 1 of the 2015 Nuclear Decommissioning Costs Triennial Proceeding PUBLIC VERSION

Rebuttal Testimony of Southern California Edison for Phase 1 of the 2015 Nuclear Decommissioning Costs Triennial Proceeding PUBLIC VERSION Application No.: Exhibit No.: Witnesses: A.1-0-00 SCE- R. Bledsoe S. Lelewer R. Worden (U -E) Rebuttal Testimony of Southern California Edison for Phase 1 of the 01 Nuclear Decommissioning Costs Triennial

More information

Application No.: A Exhibit No.: SCE-1, Vol. 3. S. DiBernardo S. Samiullah D. Hopper G. Golden (U 338-E) Before the

Application No.: A Exhibit No.: SCE-1, Vol. 3. S. DiBernardo S. Samiullah D. Hopper G. Golden (U 338-E) Before the Application No.: A.1-01- Exhibit No.: SCE-1, Vol. Witnesses: R. Thomas S. DiBernardo S. Samiullah D. Hopper G. Golden (U -E) SOUTHERN CALIFORNIA EDISON COMPANY S (U - E) TESTIMONY IN SUPPORT OF ITS APPLICATION

More information

BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON UM 1182 PRELIMINARY DETERMINATIONS MADE; ABBREVIATED SCHEDULE SET TO CONCLUDE DOCKET I.

BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON UM 1182 PRELIMINARY DETERMINATIONS MADE; ABBREVIATED SCHEDULE SET TO CONCLUDE DOCKET I. In the Matter of ORDERNO: 13 ENTERED JUN 1 0 2013 BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON UM 1182 PUBLIC UTILITY COMMISSION OF OREGON, ORDER Investigation Regarding Competitive Bidding DISPOSITION:

More information

2018 General Rate Case

2018 General Rate Case Application No.: Exhibit No.: Witnesses: A.16-09-001 SCE-59 B. Anderson D. Bernaudo T. Cameron M. Childs D. Gunn T. Guntrip G. Henry C. Jacobs D. Kempf S. Menon D. Tessler (U 338-E) 2018 General Rate Case

More information

RE: Southern California Edison Company s Formula Transmission Rate Annual Update Filing in Docket No. ER (TO11)

RE: Southern California Edison Company s Formula Transmission Rate Annual Update Filing in Docket No. ER (TO11) James A. Cuillier Director FERC Rates & Regulation Ms. Kimberly D. Bose, Secretary 888 First Street, N.E. Washington, DC 20426 RE: Southern California Edison Company s Formula Transmission Rate Annual

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA CLEAN COALITION COMMENTS ON THIRD REVISED POWER PURCHASE AGREEMENT

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA CLEAN COALITION COMMENTS ON THIRD REVISED POWER PURCHASE AGREEMENT BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking to Continue Implementation and Administration of California Renewables Portfolio Standard Program. Rulemaking

More information