1 Short Term Operating Reserve (STOR) Tender Assessment Principles Version 4.0, December 2013 For Further Information please contact: Contracts & Settlements National Grid House, Warwick Technology Park Gallows Hill Warwick CV34 6DA T: E: W: +44 (0) About this Document This document sets out the principles that National Grid considers in assessing tenders for Short Term Operating Reserve (STOR) and constitutes the tender assessment principles published by National Grid for the purposes of the STOR tender rules and Standard Contract Terms (SCTs).

2 CONTENTS BACKGROUND 1 Reserve Requirement MAIN ASSESSMENT 3 Main Economic Assessment STOR Tender Costs Costs of Alternative Reserve Sources Diagrammatical Summary of STOR Assessment ADDITIONAL ASSESSMENT CONSIDERATIONS 5 Additional Assessment Considerations Historic Reliability Geographical Location of STOR Unit or Site Flexible Providers Premium Flexible Providers Further Assessment Principles

3 BACKGROUND Reserve Requirement National Grid Electricity Transmission plc (National Grid), procures its reserve requirement through a number of balancing services to enable it to manage the security and quality of supply. The requirement comprises a number of different elements which cater for different events or circumstances that occur on the system that require the delivery of additional power (MW) in short timescales. Typically, an incident will occur that will see a mismatch in the balance between supply and demand, which in turn sees the frequency drop when supply is insufficient to meet the required level of demand. To meet this mismatch, additional power needs to be made available either in the form of additional generation or demand reduction. Most commonly, this is provided initially at least, by a service known as Frequency Response. Frequency Response initiates automatically, however it is only sustainable for 30 minutes at most, meaning that replacement power in the form of Reserve is brought onto the system in timescales of 2-30 minutes in order to replace it. This is shown diagrammatically below: As noted above, Frequency Response has a maximum sustainability of approximately 30 minutes. In practice however, National Grid will seek to replace it as soon as possible, such that it can be reused in the event of any further system events. This places a practical requirement for the delivery of reserve energy in timescales of 20 minutes or less. The STOR service permits providers that are able to deliver energy within 240 minutes to tender for the provision of STOR. In practice, this means that tenders are valued differently, depending on whether they meet the less than or equal to 20 minute response threshold or not. All STOR units can still be used for reserve purposes, but depending on which side of the 20 minute response time threshold they lie, they have different utilisation characteristics hence have to be considered separately for operational purposes. Operationally, those units with a longer notice period (greater than 20min) cannot simply be utilised in response to an incident, as it is unlikely that they would be in place in time to allow them to take over from the automatic Frequency Response service. To manage this operationally, National Grid can synchronise longer notice STOR units, when they are more economic than alternative options (e.g. generation in the Balancing Mechanism), such that they are 1 1

4 generating throughout a period where National Grid anticipates that it may need to utilise reserve services. Then, as these units are generating surplus energy, the overall system surplus can be resolved by reducing output on other units. This effectively creates reserve energy on these other units, which can then be utilised within 20 minutes should an event occur. Counter to this, units that are able to respond in less than or equal to 20 mins can simply be held in readiness for a system event and then utilised only when such an event occurs. As a result of the above, the payment profile for units that can or cannot respond within 20 minutes is clearly different. The greater than 20 min notice units effectively have an implicit positioning fee that occurs as National Grid has to run the unit in anticipation of, and not solely in reaction to, a system issue. The net result of this is that the utilisation fee of longer notice units becomes crucial. 2 2

5 MAIN ASSESSMENT Main Economic Assessment National Grid will look to secure a proportion of its reserve requirement via STOR tenders, in an economic and efficient manner. The accepted tenders will be selected such that the total costs of securing the Reserve and operating the system are lower than without the selection of those tenders. STOR Tender Costs The costs of the STOR Tender include: Expected availability fees = tendered availability price * tendered MW * expected hours of availability Availability price as per tendered, expected hours available as forecast by National Grid and influenced by historic performance of provider. Utilisation payments of STOR = tendered utilisation price * forecast MWh of utilisation A greater Minimum Non Zero Time (MNZT) / minimum utilisation period will increase the forecast MWh of utilisation, and hence may make the tender less attractive. As noted above, should a service have a much longer notice period, National Grid will also have to consider how many occasions on which it will need to run the unit in anticipation of system issues, not merely the number of times it will need to run the unit in reaction to system issues. Costs of Alternative Reserve Sources The costs of the Alternative sources of Reserve may include: Cost of securing Reserve through: Offers within the Balancing Mechanism (BM) on unsynchronised generation BM Start-Up services Pre Gate closure Balancing Transactions (PGBTs) Forward Trading Market length (zero cost) Market provided headroom (zero cost) Costs associated with energy balancing. Without a STOR provider for instance, an offer is accepted elsewhere at greater cost with a similar response time. As part of the assessment, National Grid will assess the varying requirements to create reserve across each STOR season and window and also account for the varying level of utilisation of this Reserve within the same timeframes. 3 3

6 Diagrammatical Summary of STOR Assessment 4 4

7 ADDITIONAL ASSESSMENT CONSIDERATIONS Additional Assessment Considerations Historically, the greatest weighting in the assessment of STOR contracts has sat with the appraisal of its economic value against the alternative sources of Reserve. However, other factors are increasingly starting to play a more important role in the assessment process. Economic factors still make up the significant majority of the assessment decision, however where the economic decision is marginal, other factors can be given more weight. These include the following: Historic Reliability Additional costs are associated with provider unreliability. Non-delivery of providers will result in actions taken on services with quicker response times and potentially higher prices. National Grid has devised a reliability measure, which is made up on two elements based on a rolling 12-month utilisation history: (1) Delivered MWs against contracted MW expectation (2) Delivery of MWs within contracted response times Geographical Location of the STOR Unit or Site As a greater volume of generation connects to the GB transmission system in advance of the necessary transmission reinforcement works, the network becomes ever more constrained. In practical terms, this means that should additional reserve be required to meet a shortfall in one area of the country, there may not be sufficient capacity in the transmission lines between a STOR provider and that area of the country to allow that unit to be utilised. This can also be the case where restrictions on a local distribution system restrict the ability of National Grid to use a STOR unit to respond to certain system issues. Flexible Providers Under STOR, flexible providers will submit indicative availability for each window and season when tendering. These availabilities will be used to determine which tenders are economic to accept, given the underlying volatility that is expected in the alternative cost of actions. The flexibility of providers results in week-ahead availability being submitted to National Grid and using these submitted availabilities, National Grid will assess whether to accept or reject availability at the week-ahead stage. To confirm, this assessment is subject to all the other assessment principles described in this document. As stated above, all flexible tenders are subject to an economic assessment and the total volume accepted, per tender round, is capped accordingly. During such flexible tender assessment consideration is also given to the minimum committed STOR requirement - proportional to the expected largest loss in generation on the transmission system at any one time and calculated on a per STOR season basis - which consequently directly influences the accepted flexible volumes. 5 5

8 Premium Flexible Providers Service availability and consequential delivery is paramount to National Grid and the introduction of the premium flexible service highlights our need to mitigate against the risk of accepting flexible tenders (which might deliver limited benefit over the contract term) by incentivising availability, during periods of most value to us i.e. the premium windows. This option, does however result in National Grid being exposed to greater risk particularly with regard to over/under procurement and availability turnout and therefore necessitates a devaluation which will be applied to each tender opting for the premium flexible product at the assessment stage. The method for such devaluation will be based on assumptions associated with historic flexible and committed availability profiles whilst taking into account potential alternative actions including both BM alternative actions and other alternative contracting options. To confirm, this assessment is subject to all the other assessment principles described in this document. Further Assessment Principles In addition, National Grid will take into account other factors in the appraisal of compliant tenders. The order in which these factors are listed is not an indication of the relative importance of each to the others: Any health or safety issues relevant to tendered units or sites The interaction of any other balancing service provided by the tenderer to National Grid from the unit or site in question The speed, flexibility and reliability of interface arrangements between National Grid and the provider The financial position of the tenderer and its holding company (if any) The impact of agreed special conditions by the tenderer and National Grid Any other factors that, in National Grid s reasonable opinion, are relevant in appraising the viability of any STOR tender submitted. 6 6

Balancing Services Adjustment Data Methodology Statement

Balancing Services Adjustment Data Methodology Statement Balancing Services Adjustment Data Methodology Statement Effective Date: 01 April 2018 Version Number: 15.0 Published in accordance with Standard Condition C16 of National Grid Electricity Transmission

More information

SHORT TERM OPERATING RESERVE. General Description of the Service. 14 th April 2017

SHORT TERM OPERATING RESERVE. General Description of the Service. 14 th April 2017 SHORT TERM OPERATING RESERVE General Description of the Service 14 th April 2017 1. Introduction This document provides a summary of the service of Short Term Operating Reserve (STOR) as set out in detail

More information

Balancing Services Adjustment Data. Methodology Statement. Version Date: 1 April th November BSAD Methodology Statement 1

Balancing Services Adjustment Data. Methodology Statement. Version Date: 1 April th November BSAD Methodology Statement 1 Balancing Services Adjustment Data Methodology Statement Balancing Services Adjustment Data Methodology Statement Version Date: 1 April 2007 05 th November 2009 BSAD Methodology Statement 1 Version Control

More information

Applicable Balancing Services Volume Data Methodology Statement

Applicable Balancing Services Volume Data Methodology Statement Applicable Balancing Services Volume Data Methodology Statement Version Effective Date: 1 April 20131 Effective in respect of Settlement Days from : 01 April 2011 ABSVD Methodology Statement 1 Version

More information

Applicable Balancing Services Volume Data Methodology Statement

Applicable Balancing Services Volume Data Methodology Statement Applicable Balancing Services Volume Data Methodology Statement Effective Date: 01 April 2018 Version Number: 8.0 Published in accordance with Standard Condition C16 of National Grid Electricity Transmission

More information

FIRM FAST RESERVE EXPLANATION AND TENDER GUIDANCE DOCUMENT

FIRM FAST RESERVE EXPLANATION AND TENDER GUIDANCE DOCUMENT FIRM FAST RESERVE EXPLANATION AND TENDER GUIDANCE DOCUMENT Issue #2 1 April 2013 National Grid Electricity Transmission plc National Grid House Warwick Technology Park Gallows Hill Warwick CV34 6DA Website:

More information

DATED [ ] 200[ ] NATIONAL GRID ELECTRICITY TRANSMISSION PLC (1) and [ ] (2) FAST RESERVE FRAMEWORK AGREEMENT

DATED [ ] 200[ ] NATIONAL GRID ELECTRICITY TRANSMISSION PLC (1) and [ ] (2) FAST RESERVE FRAMEWORK AGREEMENT DATED [ ] 200[ ] NATIONAL GRID ELECTRICITY TRANSMISSION PLC (1) and [ ] (2) FAST RESERVE FRAMEWORK AGREEMENT CONTRACT LOG NO: [NOTE Where Provider has an existing Fast Reserve clause in its CSA, Framework

More information

ISG202-SPAR REPORTING ON JANUARY 2018 SYSTEM PRICE ANALYSIS REPORT 1 SYSTEM PRICES AND LENGTH

ISG202-SPAR REPORTING ON JANUARY 2018 SYSTEM PRICE ANALYSIS REPORT 1 SYSTEM PRICES AND LENGTH Count of Settlement Periods -8 - -7-7 - -6-6 - -5-5 - -4-4 - -3-3 - -2-2 - -1-1 - - 1 1-2 2-3 3-4 4-5 5-6 6-7 7-8 8-9 9-1 1 + PUBLIC ISG22-SPAR REPORTING ON JANUARY 218 ISSUE 27 PUBLISHED 2 FEBRUARY 218

More information

CUSC Modification Proposal Form CMP259

CUSC Modification Proposal Form CMP259 CUSC Modification Proposal Form CMP259 Connection and Use of System Code (CUSC) Title of the CUSC Modification Proposal Clarification of decrease in TEC as a Modification Submission Date 20 January 2016

More information

ISG206-SPAR REPORTING ON MAY 2018 SYSTEM PRICE ANALYSIS REPORT 1 SYSTEM PRICES AND LENGTH

ISG206-SPAR REPORTING ON MAY 2018 SYSTEM PRICE ANALYSIS REPORT 1 SYSTEM PRICES AND LENGTH Count of Settlement Periods -1+ -1 - -9-9 - -8-8 - -7-7 - -6-6 - -5-5 - -4-4 - -3-3 - -2-2 - -1-1 - - 1 1-2 2-3 3-4 4-5 5-6 6-7 7-8 8-9 9-1 1 + PUBLIC ISG26-SPAR REPORTING ON MAY 218 ISSUE 31 PUBLISHED

More information

CUSC Amendment Proposal Form CAP: 161

CUSC Amendment Proposal Form CAP: 161 CUSC Amendment Proposal Form CAP: 161 Title of Amendment Proposal: Transmission Access System Operator Release of Short-term Entry Rights Description of the Proposed Amendment (mandatory by proposer):

More information

CUSC Modification Proposal Form CMP235

CUSC Modification Proposal Form CMP235 CUSC Modification Proposal Form CMP235 Connection and Use of System Code (CUSC) Title of the CUSC Modification Proposal Introduction of a new Relevant Interruption type when a User has had to Emergency

More information

Firm Frequency Response (FFR) Market Information Report for Mar-18

Firm Frequency Response (FFR) Market Information Report for Mar-18 Firm Frequency Response (FFR) Market Information Report for Mar-18 Published Jan-18 Key Points This Market Information Report is relevant for tenders submitted in Feb- 18 for delivery in Mar-18. Tenders

More information

TENDER PACK 1 OPERATING MARGINS 2013 CAPACITY TENDER

TENDER PACK 1 OPERATING MARGINS 2013 CAPACITY TENDER TENDER PACK 1 OPERATING MARGINS 2013 CAPACITY TENDER This tender pack is designed for; Storage Facility Operators Primary Capacity holders at Storage Facilities Issued December 2012 Market Operation National

More information

Section T: Settlement and Trading Charges. how Trading Charges for each Trading Party and National Grid are determined;

Section T: Settlement and Trading Charges. how Trading Charges for each Trading Party and National Grid are determined; BSC Simple Guide Section T: Settlement and Trading Charges Section T sets out: (a) (b) (c) how Trading Charges for each Trading Party and National Grid are determined; the data required in order to calculate

More information

SHORT-TERM OPERATING RESERVE DESPATCH PROCEDURE STOR DESPATCH PROCEDURE. for Non-Balancing Mechanism Participants

SHORT-TERM OPERATING RESERVE DESPATCH PROCEDURE STOR DESPATCH PROCEDURE. for Non-Balancing Mechanism Participants SHORT-TERM OPERATING RESERVE DESPATCH PROCEDURE STOR DESPATCH PROCEDURE for Non-Balancing Mechanism Participants Version 1.3 reviewed December 2008 ASP1 CONTENTS PART 1 - STOR DESPATCH INTRODUCTION...1

More information

Firm Frequency Response (FFR) Market Information Report

Firm Frequency Response (FFR) Market Information Report Firm Frequency Response (FFR) Market Information Report December 217 Key Points This Market Information Report is relevant for tenders submitted in Jan- 18 for delivery between February 218 and July 22.

More information

Firm Frequency Response Market Information for Dec-17

Firm Frequency Response Market Information for Dec-17 Firm Frequency Response Market Information for Dec-17 FFR Market Information Monthly Report Published Oct-17 Please note that we are constantly making changes to this report and as a result the content

More information

STCP19-5 Issue 002 Offshore Transmission System Compliance Process & Testing

STCP19-5 Issue 002 Offshore Transmission System Compliance Process & Testing STCP19-5 Issue 002 Offshore Transmission System Compliance Process & Testing STC Procedure Document Authorisation Company National Grid Electricity Transmission plc Name of Party Representative Signature

More information

CMP223 Arrangements for Relevant Distributed Generators Under the Enduring Generation User Commitment

CMP223 Arrangements for Relevant Distributed Generators Under the Enduring Generation User Commitment Stage 04: Code Administrator Consultation Connection and Use of System Code (CUSC) CMP223 Arrangements for Relevant Distributed Generators Under the Enduring Generation User Commitment 01 02 03 04 05 What

More information

CREDIT LIMITS METHODOLOGY

CREDIT LIMITS METHODOLOGY CREDIT LIMITS METHODOLOGY PREPARED BY: Electricity Metering & Settlements DOCUMENT NO: N/A VERSION NO: 10 PREPARED FOR: National Electricity Market FINAL Disclaimer (a) Purpose This document has been prepared

More information

The Renewable Heat Incentive. A reformed and refocussed scheme SVT Response

The Renewable Heat Incentive. A reformed and refocussed scheme SVT Response The Renewable Heat Incentive A reformed and refocussed scheme SVT Response Neil Liddell-Young 27 th April 2016 No. Question Response 1 Do you agree with the proposed policy approach for degression and

More information

CMP223 Arrangements for

CMP223 Arrangements for Stage 02: 03: Workgroup Consultation Report Connection and and Use Use of of System Code (CUSC) CMP223 Arrangements for Relevant Distributed Generators Under the Enduring Generation User Commitment What

More information

Loss of Transmission Access Compensation Guidance Note for Customers

Loss of Transmission Access Compensation Guidance Note for Customers Loss of Transmission Access Compensation Guidance Note for Customers This document has been produced to complement the Loss of Transmission Access Compensation Claim Form. Both the claim form and this

More information

CUSC Modification Proposal Form CMP228

CUSC Modification Proposal Form CMP228 CUSC Modification Proposal Form CMP228 Connection and Use of System Code (CUSC) Title of the CUSC Modification Proposal Definition of Qualified Bank Submission Date 18 / 02 / 2014 Description of the Issue

More information

National Grid Electricity Transmission plc Balancing Mechanism Review

National Grid Electricity Transmission plc Balancing Mechanism Review www.pwc.co.uk 17 March 2015 National Grid Electricity Transmission plc Balancing Mechanism Review Approach Document for year ending 31 March 2015 Contents I Introduction 4 Basis for review 4 II Scope

More information

Direct Dial: May Your Ref: Our Ref : MP No: P12

Direct Dial: May Your Ref: Our Ref : MP No: P12 Direct Dial: 020-7901 7412 2 May 2002 The National Grid Company, BSC Signatories and Other Interested Parties Your Ref: Our Ref : MP No: P12 Dear Colleague, Modification to the Balancing and Settlement

More information

The Entry Capacity Substitution Methodology Statement

The Entry Capacity Substitution Methodology Statement Issue 6.06.2 Revision ApprovedCons ultation Draft The Entry Substitution Methodology Statement Effective from 27 th February1 st November 2015 Page 1 of 32 The Entry Substitution Methodology Statement

More information

CHARGING METHODOLOGY STATEMENT FOR THE ELECLINK INTERCONNECTOR

CHARGING METHODOLOGY STATEMENT FOR THE ELECLINK INTERCONNECTOR CHARGING METHODOLOGY STATEMENT FOR THE ELECLINK INTERCONNECTOR ISSUE 1.0 1 Contents 1. Introduction... 3 2. Interconnector charging methodology... 3 2.1 Introduction... 3 2.2 Objectives of the Charging

More information

P344 Project TERRE implementation into GB market arrangements

P344 Project TERRE implementation into GB market arrangements Project TERRE implementation into GB market arrangements This Modification seeks to align the Balancing and Settlement Code (BSC) with the European Balancing Project TERRE (Trans European Replacement Reserves

More information

The Entry Capacity Substitution Methodology Statement

The Entry Capacity Substitution Methodology Statement Issue 5.26.1 Revision Informal Consultation Draft The Entry Substitution Methodology Statement Effective from 2 nd February1 st September 2015 Page 1 of 31 ENTRY CAPACITY SUBSTITUTION METHODOLOGY STATEMENT

More information

All CE TSOs proposal for additional properties of FCR in accordance with Article 154(2) of the Commission Regulation (EU) 2017/1485 of 2

All CE TSOs proposal for additional properties of FCR in accordance with Article 154(2) of the Commission Regulation (EU) 2017/1485 of 2 All CE TSOs proposal for additional properties of FCR in accordance with Article 154(2) of the Commission Regulation (EU) 2017/1485 of 2 August 2017 establishing a guideline on electricity transmission

More information

Comverge Qualifications

Comverge Qualifications Comverge Commercial Group National Demand Response Presentation Comverge Qualifications Public Company listed on the NASDAQ (Ticker: COMV) Largest Demand Response Provider 6.1 GW enabled through 5 million

More information

CHAPTER 1. General Provisions

CHAPTER 1. General Provisions IFA Interconnector s Border Specific Annex to the Harmonised Allocation Rules for long-term transmission rights in accordance with Article 52 of Commission Regulation (EU) 2016/1719 of 26 September 2016

More information

Entry Capacity Substitution Methodology Statement

Entry Capacity Substitution Methodology Statement Issue Revision 7.0 Approved Entry Substitution Methodology Statement Effective from 1 st November 2015 Page 1 of 30 ENTRY CAPACITY SUBSTITUTION METHODOLOGY STATEMENT Document Revision History Version/

More information

Electricity Balancing Significant Code Review

Electricity Balancing Significant Code Review Electricity Balancing Significant Code Review Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line.

More information

National Grid response to the open letter on BELLA participation in the Balancing Mechanism

National Grid response to the open letter on BELLA participation in the Balancing Mechanism National Grid House Warwick Technology Park Gallows Hill, Warwick CV34 6DA Electricity Industry Colleagues and Interested Parties Ian Pashley Electricity Codes Manager Transmission Ian.pashley@nationalgrid.com

More information

UNIVERSITY OF CAMBRIDGE INFORMATION SERVICES COMMITTEE PROJECT AND PROGRAMME GOVERNANCE: DECISION MAKING PROCESS

UNIVERSITY OF CAMBRIDGE INFORMATION SERVICES COMMITTEE PROJECT AND PROGRAMME GOVERNANCE: DECISION MAKING PROCESS UNIVERSITY OF CAMBRIDGE INFORMATION SERVICES COMMITTEE PROJECT AND PROGRAMME GOVERNANCE: DECISION MAKING PROCESS Document Status: Approving Body: Last Update: Author: Approved Information Services Committee

More information

Tax Strategy. March 2018

Tax Strategy. March 2018 Tax Strategy March 2018 Contents 03 Introduction 04 Our approach to tax Do the right thing Total tax contribution 05 Governance and management of tax risk Roles and responsibilities Tax risks 06 Internal

More information

California ISO October 1, 2002 Market Design Elements

California ISO October 1, 2002 Market Design Elements California October 1, 2002 Market Design Elements California Board of Governors Meeting April 25, 2002 Presented by Keith Casey Manager of Market Analysis and Mitigation Department of Market Analysis 1

More information

Contents Introduction Chapter 1 - Security Policy... 6

Contents Introduction Chapter 1 - Security Policy... 6 Policy statement Contents Introduction... 5 PURPOSE... 5 SYSTEM OPERATOR POLICIES TO ACHIEVE THE PPOS and dispatch objective... 5 Avoid Cascade Failure... 5 Frequency... 6 Other Standards... 6 Restoration...

More information

RERT: RELIABILITY AND EMERGENCY RESERVE TRADER

RERT: RELIABILITY AND EMERGENCY RESERVE TRADER RERT: RELIABILITY AND EMERGENCY RESERVE TRADER June 2017 SLIDE 1 OVERVIEW Summer 2017/18 What RERT is How RERT works How to be involved in RERT SLIDE 2 SUMMER 2017-18 For up to date reserve forecasts for

More information

Following Industry Consultation

Following Industry Consultation Report to Authority Proposed Revisions to the Balancing Principles Statement, Balancing Services Adjustment Data Methodology Statement, Procurement Guidelines, System Management Action Flagging Methodology

More information

DIRECT CLIENT DISCLOSURE DOCUMENT 1. Indirect Clearing Goldman Sachs International

DIRECT CLIENT DISCLOSURE DOCUMENT 1. Indirect Clearing Goldman Sachs International DIRECT CLIENT DISCLOSURE DOCUMENT 1 Indirect Clearing Goldman Sachs International Introduction 2 Throughout this document references to "we", "our" and "us" are references to the clearing broker's client

More information

8 th March Energy Security Board c/- COAG Energy Council Secretariat Department of the Environment and Energy GPO Box 787 CANBERRA ACT 2601

8 th March Energy Security Board c/- COAG Energy Council Secretariat Department of the Environment and Energy GPO Box 787 CANBERRA ACT 2601 8 th March 2018 Energy Security Board c/- COAG Energy Council Secretariat Department of the Environment and Energy GPO Box 787 CANBERRA ACT 2601 PO Box 63, Dickson ACT 2602 Ph: 6267 1800 info@aluminium.org.au

More information

CONSTRAINT RELAXATION PROCEDURE

CONSTRAINT RELAXATION PROCEDURE CONSTRAINT RELAXATION PROCEDURE PREPARED BY: AEMO Markets Electricity Market Monitoring DOCUMENT REF: ME_PD_03 VERSION: 3 EFFECTIVE DATE: 17 November 2017 STATUS: FINAL Approved for distribution and use

More information

CROSS BORDER CAPACITY ALLOCATION FOR THE EXCHANGE OF ANCILLARY SERVICES

CROSS BORDER CAPACITY ALLOCATION FOR THE EXCHANGE OF ANCILLARY SERVICES CROSS BORDER CAPACITY ALLOCATION FOR THE EXCHANGE OF ANCILLARY SERVICES A POSITION PAPER BY THE ENTSO-E ANCILLARY SERVICES WORKING GROUP JANUARY 2012 Purpose & objectives of the paper This paper further

More information

Fast Reserve Post Assessment WebEx July-18

Fast Reserve Post Assessment WebEx July-18 Fast Reserve Post Assessment WebEx July-18 21 June 2018 Introduction This WebEx: Relates to the results of the July-18 Fast Reserve tender round that were published on the website on the 19 th July 2018.

More information

Tempus state aid judgment. Advice for capacity agreement holders and capacity market applicants 15 November 2018

Tempus state aid judgment. Advice for capacity agreement holders and capacity market applicants 15 November 2018 Tempus state aid judgment Advice for capacity agreement holders and capacity market applicants 15 November 2018 The following message is being sent to all capacity agreement holders and capacity market

More information

Tax Strategy. March 2019.

Tax Strategy. March 2019. . March 2019. National Grid March 2019 The 2016 Finance Act introduced a requirement for large businesses to publish their tax strategy. National Grid made our first publication in March 2018 in accordance

More information

CABINET GROUNDS MAINTENANCE CONTRACT

CABINET GROUNDS MAINTENANCE CONTRACT Report No: 9/2017 PUBLIC REPORT CABINET 17 January 2017 GROUNDS MAINTENANCE CONTRACT Report of the Director for Places (Environment, Planning & Transport) Strategic Aim: Sustainable Growth Key Decision:

More information

CUSC - SECTION 14 CHARGING METHODOLOGIES CONTENTS

CUSC - SECTION 14 CHARGING METHODOLOGIES CONTENTS CUSC - SECTION 14 CHARGING METHODOLOGIES CONTENTS 14.1 Introduction Part I -The Statement of the Connection Charging Methodology 14.2 Principles 14.3 The Calculation of the Basic Annual Connection Charge

More information

REA response to Consultation on Minima and Maxima in the CfD Allocation Process

REA response to Consultation on Minima and Maxima in the CfD Allocation Process REA response to Consultation on Minima and Maxima in the CfD Allocation Process The Renewable Energy Association (REA) is pleased to submit this response to the above consultation. The REA represents a

More information

Chapter 5: Trading. Industry Guide to the I-SEM

Chapter 5: Trading. Industry Guide to the I-SEM Chapter 5: Trading Industry Guide to the I-SEM 1 5.1 Submission timelines Each market operates over different timelines, as described in Chapter 4. By way of an example, the combined submission timelines

More information

CUSC Section 15 (CMP192) User Commitment Methodology

CUSC Section 15 (CMP192) User Commitment Methodology CUSC Section 15 (CMP192) User Commitment Methodology Guidance and Implementation Document 1 May 2012 Version 1 1 1. Summary... 3 2. Purpose of the document...3 3. Background... 4 4. Attributable and Wider

More information

ENHANCED FREQUENCY RESPONSE. Invitation to tender for pre-qualified parties. 8th July 2016 v2.2

ENHANCED FREQUENCY RESPONSE. Invitation to tender for pre-qualified parties. 8th July 2016 v2.2 ENHANCED FREQUENCY RESPONSE Invitation to tender for pre-qualified parties 8th July 2016 v2.2 2 Contents 1 Eligibility... 3 2 Introduction... 3 3 Contractual Requirements... 4 4 Timescales... 6 5 Tender

More information

cc. Robert O Rourke Jo Aston Paul Bell Denis Kelly Robbie Ahern Michael Beggs Tony Hearne 1st April 2015 Dear Sir and Madam,

cc. Robert O Rourke Jo Aston Paul Bell Denis Kelly Robbie Ahern Michael Beggs Tony Hearne 1st April 2015 Dear Sir and Madam, Jenny Pyper Utility Regulator Queens House 14 Queen Street Belfast BT1 6ED Gareth Blaney Commission for Energy Regulation The Exchange Belgard Square North Tallaght Dublin 24 cc. Robert O Rourke Jo Aston

More information

Extended Reserve Selection Methodology

Extended Reserve Selection Methodology Extended Reserve Selection Methodology Extended Reserve Manager Version 1.3.3 20 February 2017 Revision history Version Date Description Author 1.0 31 August 2016 Draft presented to the Authority and System

More information

ISO Rules Part 300 System Reliability and Operations Division 306 Outages and Disturbances Section Generation Outage Reporting and Coordination

ISO Rules Part 300 System Reliability and Operations Division 306 Outages and Disturbances Section Generation Outage Reporting and Coordination Applicability 1 Section 306.5 applies to: (a) a pool participant with a generating source asset with a maximum capability of five (5) MW or higher; (b) a legal owner of a source asset described in subsection

More information

Supplemental Balancing Reserve

Supplemental Balancing Reserve Supplemental Balancing Reserve From Forecasting to Despatch Pete Chandler Control Implementation Manager SBR Units Contracted Long notice start up required Eggborough 52 Hours Fiddlers Ferry 26 Hours South

More information

OPERATING MARGINS GAS DELIVERY AGREEMENT LNG STORAGE BETWEEN NATIONAL GRID GAS PLC AND SERVICE PROVIDER

OPERATING MARGINS GAS DELIVERY AGREEMENT LNG STORAGE BETWEEN NATIONAL GRID GAS PLC AND SERVICE PROVIDER OPERATING MARGINS GAS DELIVERY AGREEMENT LNG STORAGE BETWEEN NATIONAL GRID GAS PLC AND SERVICE PROVIDER National Grid Legal National Grid House Warwick Technology Park Gallows Hill Warwick CV34 6DA T:

More information

executive summary ExEcuTivE SuMMAry

executive summary ExEcuTivE SuMMAry executive summary 1 British Energy was privatised in 1996. In 2002, the price of electricity fell and on 5 September 2002, the Company applied to the Department of Trade and Industry (the Department) for

More information

COMMISSION REGULATION (EU) NO. 543/2013. Article 17.1.a: Rules on Balancing

COMMISSION REGULATION (EU) NO. 543/2013. Article 17.1.a: Rules on Balancing COMMISSION REGULATION (EU) NO. 543/2013 Article 17.1.a: Rules on Balancing Tender Rules Frequency Containment Reserves Required Amount ±64 MW (2018) FCR Austria Tenders Tendering Period Weekly (Friday

More information

Response to ENTSOE public consultation. Network Code on Capacity Allocation and Congestion Management for. Electricity

Response to ENTSOE public consultation. Network Code on Capacity Allocation and Congestion Management for. Electricity Response to ENTSOE public consultation On Network Code on Capacity Allocation and Congestion Management for Electricity 23 May 2012 EUROPEX Rue Montoyer 31 Bte 9 BE-1000 Brussels T. : +32 2 512 34 10 E.:

More information

ATTACHMENT Q PJM CREDIT POLICY

ATTACHMENT Q PJM CREDIT POLICY ATTACHMENT Q PJM CREDIT POLICY C. Financial Transmission Right Auctions Credit requirements described herein for FTR activity are applied separately for each customer account of a Market Participant. FTR

More information

TABLE OF CONTENTS... 2

TABLE OF CONTENTS... 2 Information Paper on Modifications to the EirGrid Market Operator and EirGrid Transmission System Operator, necessitated to implement the Integrated Single Electricity Market (I-SEM) Reference: CER/16/368

More information

XBID Information Package Published February 2018 Updated December 2018

XBID Information Package Published February 2018 Updated December 2018 XBID Information Package Published February 2018 Updated December 2018 1. Purpose of this document This document centralises, consolidates and comprehensively describes the necessary information which

More information

EAI Response to ACER Consultation on Forward Risk-Hedging Products and Harmonisation of Long-Term Capacity Allocation Rules

EAI Response to ACER Consultation on Forward Risk-Hedging Products and Harmonisation of Long-Term Capacity Allocation Rules Version 1.0 ACER Consultation on Forward Risk-Hedging Products and Harmonisation of Long-Term Capacity Allocation Rules EAI Response to ACER Consultation on Forward Risk-Hedging Products and Harmonisation

More information

Review of the Frequency Operating Standard Issues Paper REL0065

Review of the Frequency Operating Standard Issues Paper REL0065 01 August 2017 Mr. Neville Henderson Chairman Australian Energy Market Commission Reliability Panel PO Box A2449 Sydney South NSW 1235 Review of the Frequency Operating Standard Issues Paper REL0065 Energy

More information

Rules for Standard Offer Service Auction

Rules for Standard Offer Service Auction Charles River Associates and Market Design Inc August 11, 1997 Rules for Standard Offer Service Auction This document presents the rules for Eastern Utilities Associates auction for standard offer service.

More information

Criteria for rating wind power projects

Criteria for rating wind power projects Criteria for rating wind power projects Executive Summary CRISIL has outstanding ratings on 21 wind power project companies as on June 30, 2015. Wind power projects depend primarily on wind speeds for

More information

CMP228 Definition of Qualified Bank

CMP228 Definition of Qualified Bank Stage 06: Final CUSC Modification Self- Governance Report Connection and Use of System Code CMP228 Definition of Qualified Bank 01 02 03 What stage is this document at? Initial Written Assessment Workgroup

More information

0506A: Gas Performance Assurance Framework and Governance Arrangements. 01 Modi(ication. Stage 01: Modification

0506A: Gas Performance Assurance Framework and Governance Arrangements. 01 Modi(ication. Stage 01: Modification Stage 01: : Gas Performance Assurance Framework and Governance Arrangements u At what stage is this document in the process? 01 Modi(ication 02 03 04 Workgroup Report Draft Modi(ication Report Final Modi(ication

More information

Intraday Offers Update & Manual 11 Revisions Review

Intraday Offers Update & Manual 11 Revisions Review Intraday Offers Update & Manual 11 Revisions Review Lisa Morelli Manager, Real-time Market Operations Market Implementation Committee June 7, 2017 Intraday Offers (Hourly Offers) Filing History FERC initiates

More information

Cross-Border Intraday: Questions & Answers

Cross-Border Intraday: Questions & Answers Last update: 04/12/2018 Cross-Border Intraday: Questions & Answers 1. What is the Cross-Border Intraday initiative? The Cross-Border Intraday initiative (XBID Project) started as a joint initiative by

More information

DE MINIMIS ACCEPTANCE THRESHOLD (DMAT) AND CONTINUOUS ACCEPTANCE DURATION LIMIT (CADL) REVIEW 2018

DE MINIMIS ACCEPTANCE THRESHOLD (DMAT) AND CONTINUOUS ACCEPTANCE DURATION LIMIT (CADL) REVIEW 2018 PAPER NAME De Minimis acceptance Threshold (DMAT) and Continuous Acceptance Duration Limit (CADL) Review Target Audience Purpose of paper Deadline for responses Contact name and details BSC Parties For

More information

Notice of Indicative Gas Transmission Transportation Charges effective from 1 April November 2018

Notice of Indicative Gas Transmission Transportation Charges effective from 1 April November 2018 Notice of Indicative Gas Transmission Transportation Charges effective from 1 April 2019 2 November 2018 National Grid Notice of Indicative NTS Charges 1 April 2019 0 Contents 1. Introduction 2 Basis of

More information

18 April 2016 Draft for consultation

18 April 2016 Draft for consultation All TSOs proposal for intraday cross-zonal gate opening and gate closure times in accordance with Article 59 of Commission Regulation (EU) 2015/1222 of 24 July 2015 establishing a guideline on capacity

More information

WP1 - Overview of EMR Settlement

WP1 - Overview of EMR Settlement WP1 - Overview of EMR Settlement EMRS Working Practice Public Version: 5.0 Date: 01 March 2018 Table of Contents Change Amendment Record 3 1. Introduction 4 1.1 Scope and Purpose of the Working Practice

More information

July MODIFICATION REPORT MODIFICATION PROPOSAL P78 Revised Definition of System Buy Price and System Sell Price

July MODIFICATION REPORT MODIFICATION PROPOSAL P78 Revised Definition of System Buy Price and System Sell Price July 2002 MODIFICATION REPORT MODIFICATION PROPOSAL P78 Revised Definition of System Buy Price and System Sell Price Prepared by ELEXON on behalf of the Balancing and Settlement Code Panel Document Reference

More information

Object: Technical and market design improvements urgently required for XBID go-live

Object: Technical and market design improvements urgently required for XBID go-live To: Klaus-Dieter Borchardt Director for the Internal Energy Market, European Commission, DG Energy Cc: Alberto Pototschnig Director, ACER Cosimo Campidoglio Director for Market Monitoring, Analysis and

More information

Tier 1 Compensation Education

Tier 1 Compensation Education Tier 1 Compensation Education January 5, 2015 Problem Statement Tier 1 synch reserves are credited at the synch reserve market clearing price when the non-synch reserve market clearing price is above $0.

More information

SEMO PX MARKET DESIGN

SEMO PX MARKET DESIGN SEMO PX MARKET DESIGN November 2017 EirGrid 2017. Commercial In Confidence. Table of Contents 1. Background... 4 2. High Level Processes for Ex-Ante Markets... 6 2.1 Day-ahead MRC and Intraday Coupled

More information

COMPARISION OF OFFSHORE REQUIREMENTS

COMPARISION OF OFFSHORE REQUIREMENTS Key to Table COMPARISION OF OFFSHORE REQUIREMENTS (Comparison based on GB Grid Code Issue 4 Revision 13 only and ENSTO - E RFG Internal Version dated 26 June 2012) (Note Does not include other Industry

More information

Demand assessment report for incremental capacity between Republic of Ireland [Gas Networks Ireland]

Demand assessment report for incremental capacity between Republic of Ireland [Gas Networks Ireland] Demand assessment report for incremental capacity between Republic of Ireland [Gas Networks Ireland] and UK [National Grid] where no non-binding demand indications were received 2017-07-27 This report

More information

The market setup in the Baltics explanation with examples

The market setup in the Baltics explanation with examples The market setup in the Baltics explanation with examples Table of Contents The market setup in the Nordic-... 3 Baltic exchange area... 3 Daily routines at Nord Pool... 4 Price calculation principles...

More information

TRANSMISSION CONSTRAINT MANAGEMENT REQUIREMENT NOTICE - [TCMRN/05/15]

TRANSMISSION CONSTRAINT MANAGEMENT REQUIREMENT NOTICE - [TCMRN/05/15] Transmission Constraint Management Requirement Notice: Invitation to Tender Pack, Letter 2 To All Service Providers 31 July 2015 Issue 1 Steve Lam Account Manager steven.lam@nationalgrid.com Direct tel:

More information

Chief Executives Group North Yorkshire and York 8 September 2016 LEP update

Chief Executives Group North Yorkshire and York 8 September 2016 LEP update Agenda item 2 Chief Executives Group North Yorkshire and York 8 September 2016 LEP update 1 Purpose of the report 1.1 The purpose of the report is to update the Chief Executives Group on; Post Brexit EU

More information

I-SEM Technical Specification (ITS)

I-SEM Technical Specification (ITS) I-SEM Technical Specification (ITS) VOLUME C: BALANCING MARKET V2.0 COPYRIGHT NOTICE All rights reserved. This entire publication is subject to the laws of copyright. This publication may not be reproduced

More information

Terms and Conditions related to Balancing

Terms and Conditions related to Balancing Natasha Z Smith Head of Wholesale Markets Electricity Ofgem 10 South Colonnade Canary Wharf London E14 4PU Kyla Berry Markets & Balancing Development Manager Kyla.Berry@nationalgrid.com Direct tel. +44

More information

DS3 System Services Protocol Regulated Arrangements

DS3 System Services Protocol Regulated Arrangements DS3 System Services Protocol Regulated Arrangements DS3 System Services Implementation Project 12 December 2017 Version 1.0 Contents 1 Introduction... 4 1.1 Service Provider Intermediary for a Providing

More information

All NEMOs proposal for the price coupling algorithm and for the continuous trading matching algorithm, also incorporating TSO and NEMO proposals for

All NEMOs proposal for the price coupling algorithm and for the continuous trading matching algorithm, also incorporating TSO and NEMO proposals for All NEMOs proposal for the price coupling algorithm and for the continuous trading matching algorithm, also incorporating TSO and NEMO proposals for a common set of requirements, in accordance with Article

More information

ADAPTING THE TARGET MODEL TO VALUE FLEXIBILITY

ADAPTING THE TARGET MODEL TO VALUE FLEXIBILITY ADAPTING THE TARGET MODEL TO VALUE FLEXIBILITY Stephen Woodhouse 3 November 2015 AGENDA ADAPTING THE TARGET MODEL TO VALUE FLEXIBILITY To be covered in this session: What is flexibility? Reality and misconceptions

More information

FERC Order Minute Settlements Manual Revisions

FERC Order Minute Settlements Manual Revisions FERC Order 825 5 Minute Settlements Manual Revisions Ray Fernandez Manager, Market Settlements Development Market Settlements Subcommittee October 30, 2017 Impacted Settlement Manuals M-27 Open Access

More information

RECOMMENDATIONS: NGET SYSTEM OPERATOR INCENTIVE INCOME ADJUSTING EVENTS A report to Ofgem. August 2013 INCOME ADJUSTING EVENTS

RECOMMENDATIONS: NGET SYSTEM OPERATOR INCENTIVE INCOME ADJUSTING EVENTS A report to Ofgem. August 2013 INCOME ADJUSTING EVENTS \ RECOMMENDATIONS: NGET 2011-13 SYSTEM OPERATOR INCENTIVE INCOME ADJUSTING EVENTS A report to Ofgem RECOMMENDATIONS: NGET 2011-13 SYSTEM OPERATOR INCENTIVE INCOME ADJUSTING EVENTS Contact details Name

More information

ELECTRICITY BALANCING IN EUROPE

ELECTRICITY BALANCING IN EUROPE EUROPEAN ELECTRICITY BALANCING GUIDELINE NOVEMBER 2018 AN OVERVIEW OF THE EUROPEAN BALANCING MARKET AND ELECTRICITY BALANCING GUIDELINE European Network of Transmission System Operators for Electricity

More information

Grid Code Issue Paper

Grid Code Issue Paper For presentation at the April 2016 meeting of the Grid Code Development Forum Robert Selbie on behalf of National Grid Interconnector Physical Notification submissions following XBID (Cross Border Intra

More information

Official. NHS standard sub-contract for the provision of clinical services 2017/18 and 2018/19 (full length and shorterform.

Official. NHS standard sub-contract for the provision of clinical services 2017/18 and 2018/19 (full length and shorterform. NHS standard sub-contract for the provision of clinical services 2017/18 and 2018/19 (full length and shorterform versions) Guidance NHS standard sub-contract for the provision of clinical services 2017/18

More information

Change of Ownership for Feed in Tariffs (FIT) Form Change of Responsibility Form First Utility accepts no liability for the accuracy for this form.

Change of Ownership for Feed in Tariffs (FIT) Form Change of Responsibility Form First Utility accepts no liability for the accuracy for this form. This form should be used to notify First Utility of transfer of responsibility from the FIT Generator to another party. Examples might be where a FIT Generator no longer resides at the installation address

More information

Review of the GB Regulatory and Legal Framework. John Hayling, UK Power Networks

Review of the GB Regulatory and Legal Framework. John Hayling, UK Power Networks Review of the GB Regulatory and Legal Framework John Hayling, UK Power Networks UK Power Networks An Introduction End Customers Millions Service Area km² Underground Network km Overhead Network km Energy

More information