CUSC Modification Proposal Form CMP228
|
|
- Elinor Johnston
- 5 years ago
- Views:
Transcription
1 CUSC Modification Proposal Form CMP228 Connection and Use of System Code (CUSC) Title of the CUSC Modification Proposal Definition of Qualified Bank Submission Date 18 / 02 / 2014 Description of the Issue or Defect that the CUSC Modification Proposal seeks to address The CUSC currently requires Users to provide The Company with security in respect of the following categories: (i) Termination Amounts (CUSC Paragraph 2.19) (ii) Balancing Services Use of System Charges and Transmission Network Use of System Demand Charges (CUSC Paragraph 3.22) (iii) Cancellation Charge Secured Amounts (CUSC Paragraph 15 Part 3) For Users who do not meet the required The Company Credit Rating in the case of (i), who exceed their User s Allowed Credit in the case of (ii), or do not meet The Company Credit Rating in the case of (iii), a number of alternative forms of acceptable security are specified in the CUSC. Such alternative form of security may typically be in the form of a Letter of Credit or Performance Bond provided by a Qualified Bank. The CUSC definition of a Qualified Bank describes the entity as a bank, which might imply that the entity is expected to hold a UK banking licence to provide banking services, although this requirement is not specified in the definition. However, the reference to bank in the definition would appear to preclude other financial institutions, particularly trade credit insurance companies, which might otherwise meet the CUSC requirements relating to a Qualified Bank from providing security in the form of a Performance Bond or Letter of Credit. Description of the CUSC Modification Proposal Following the downgrading of several licensed banks by Moody s and Standard & Poor s during 2012 and 2013, the number of financial institutions with an adequate credit rating to provide security on behalf of Users under the CUSC has reduced. A smaller pool of prospective security providers and the potential for further downgradings is unlikely to incentivise Qualified Banks and similar entities to maintain or reduce their charge to Users for providing security
2 acceptable to The Company. The CUSC definition of Qualified Bank requires the entity providing a Performance Bond or Letter of Credit to meet the general description of being a bank. It is proposed that this general description be extended to include a company capable of providing trade related credit insurance, or trade credit insurance company, thereby increasing the number of prospective providers of security available to Users. Trade credit insurance companies would normally be members of the International Credit Insurance & Surety Association (ICISA) and capable of providing security of a similar level and form as that provided by a bank. Under this proposed change, the criteria which must be met by a trade credit insurance company to meet the definition of a Qualified Bank would be the same as the criteria to be met by bank, such that the level of security would be similar and neither The Company nor other Users would be disadvantaged by the choice of entity providing the security. Impact on the CUSC If this CUSC Modication Proposal is accepted, it is anticipated that the following change would need to be made to the CUSC: Amend the definition "Qualified Bank" or "Qualifying Bank". Do you believe the CUSC Modification Proposal will have a material impact on Greenhouse Gas Emissions? Yes / No No Impact on Core Industry Documentation. Please tick the relevant boxes and provide any supporting information None Urgency Recommended: Yes / No No Justification for Urgency Recommendation N/A Self-Governance Recommended: Yes / No Yes
3 Justification for Self-Governance Recommendation This CUSC Modification Proposal is intended to increase the range of providers capable of meeting the CUSC requirements relating to the provision of security and would not result in a reduction in the level of security currently provided by Users to The Company. Consequently, the User considers it unlikely to have a material effect on any of the above criteria. Should this CUSC Modification Proposal be considered exempt from any ongoing Significant Code Reviews? The Proposer is not aware of any ongoing Significant Code Review related to this Modification Proposal Impact on Computer Systems and Processes used by CUSC Parties: The Proposer does not anticipate that any Computer Systems or Computer Processes would be affected by this CUSC Modification Proposal. Details of any Related Modification to Other Industry Codes None. Justification for CUSC Modification Proposal with Reference to Applicable CUSC Objectives: Please tick the relevant boxes and provide justification: (a) the efficient discharge by The Company of the obligations imposed upon it by the Act and the Transmission Licence This CUSC Modification Proposal seeks to increase the range of providers capable of meeting the CUSC requirements relating to the provision of security available to Users, thereby reducing the effective preferential treatment of licensed banks above other financial institutions in the provision of security (Licence Condition 19E). (b) facilitating effective competition in the generation and supply of electricity, and (so far as consistent therewith) facilitating such competition in the sale, distribution and purchase of electricity. Increasing the number of potential providers of security is expected to reduce the cost to Users who are not Qualifying Companies, thereby facilitating effective competition in the generation and supply of electricity. (c) compliance with the Electricity Regulation and any relevant legally binding decision of the European Commission and/or the Agency.
4 These are defined within the National Grid Electricity Transmission plc Licence under Standard Condition C10, paragraph 1. Objective (c) was added in November This refers specifically to European Regulation 2009/714/EC. Reference to the Agency is to the Agency for the Cooperation of Energy Regulators (ACER). This section is mandatory. You should detail why this Proposal better facilitates the Applicable CUSC Objectives compared to the current baseline. Please note that one or more Objective must be justified. Additional details Details of Proposer: (Organisation Name) Capacity in which the CUSC Modification Proposal is being proposed: (i.e. CUSC Party, BSC Party or National Consumer Council ) Details of Proposer s Representative: Name: Organisation: Telephone Number: Address: Details of Representative s Alternate: Name: Organisation: Telephone Number: Address: John Norbury (for the RWE Group of companies, including RWE Npower plc, RWE Npower Renewables Limited and RWE Supply & Trading GmbH) Network Connections Manager RWE Supply & Trading GmbH Windmill Hill Business Park Whitehill Way Swindon, Wiltshire SN5 6PB T +44 (0) M +44 (0) john.norbury@rwe.com CUSC Party As above David Munday UK Group Treasurer RWE Npower plc Windmill Hill Business Park Whitehill Way Swindon, Wiltshire SN5 6PB T +44 (0) M +44 (0) david.munday@rwenpower.com
5 Attachments (Yes/No): If Yes, Title and No. of pages of each Attachment: No.
6 Contact Us If you have any questions or need any advice on how to fill in this form please contact the Panel Secretary: Phone: For examples of recent CUSC Modifications Proposals that have been raised please visit the National Grid Website at rrentamendmentproposals/ Submitting the Proposal Once you have completed this form, please return to the Panel Secretary, either by to and copied to or by post to: Emma Clark CUSC Modifications Panel Secretary, TNS National Grid Electricity Transmission plc National Grid House Warwick Technology Park Gallows Hill Warwick CV34 6DA If no more information is required, we will contact you with a Modification Proposal number and the date the Proposal will be considered by the Panel. If, in the opinion of the Panel Secretary, the form fails to provide the information required in the CUSC, the Proposal can be rejected. You will be informed of the rejection and the Panel will discuss the issue at the next meeting. The Panel can reverse the Panel Secretary s decision and if this happens the Panel Secretary will inform you.
CUSC Modification Proposal Form CMP259
CUSC Modification Proposal Form CMP259 Connection and Use of System Code (CUSC) Title of the CUSC Modification Proposal Clarification of decrease in TEC as a Modification Submission Date 20 January 2016
More informationCUSC Modification Proposal Form CMP235
CUSC Modification Proposal Form CMP235 Connection and Use of System Code (CUSC) Title of the CUSC Modification Proposal Introduction of a new Relevant Interruption type when a User has had to Emergency
More informationCMP228 Definition of Qualified Bank
Stage 06: Final CUSC Modification Self- Governance Report Connection and Use of System Code CMP228 Definition of Qualified Bank 01 02 03 What stage is this document at? Initial Written Assessment Workgroup
More informationCMP288: Explicit charging arrangements for customer delays and backfeeds.
CUSC Modification Proposal Form CMP288: Explicit charging arrangements for customer delays and backfeeds. At what stage is this document in the process? 01 02 Proposal Form Workgroup Consultation 03 Workgroup
More informationCUSC Amendment Proposal Form CAP: 161
CUSC Amendment Proposal Form CAP: 161 Title of Amendment Proposal: Transmission Access System Operator Release of Short-term Entry Rights Description of the Proposed Amendment (mandatory by proposer):
More informationCMP278. BSIS 2017 Housekeeping. CUSC Modification Proposal Form
CUSC Modification Proposal Form At what stage is this document in the process? CMP78 BSIS 07 Housekeeping 0 04 05 06 Initial Written Assessment Code Administrator Consultation Draft CUSC Modification Report
More informationNational Grid response to the open letter on BELLA participation in the Balancing Mechanism
National Grid House Warwick Technology Park Gallows Hill, Warwick CV34 6DA Electricity Industry Colleagues and Interested Parties Ian Pashley Electricity Codes Manager Transmission Ian.pashley@nationalgrid.com
More informationCMP282: The effect Negative Demand has on Zonal Locational Demand Tariffs. CUSC Modification Proposal Form
CUSC Modification Proposal Form CMP282: The effect Negative has on Zonal Locational Tariffs At what stage is this document in the process? 01 02 Proposal Form Workgroup Consultation 03 Workgroup Report
More informationFIRM FAST RESERVE EXPLANATION AND TENDER GUIDANCE DOCUMENT
FIRM FAST RESERVE EXPLANATION AND TENDER GUIDANCE DOCUMENT Issue #2 1 April 2013 National Grid Electricity Transmission plc National Grid House Warwick Technology Park Gallows Hill Warwick CV34 6DA Website:
More informationCAP189 Standard Gas Insulated Switchgear (GIS) Ownership Boundaries
Stage 03: Workgroup Report Connection and Use of System Code (CUSC) CAP189 Standard Gas Insulated Switchgear (GIS) Ownership Boundaries What stage is this document at? 01 02 03 04 05 Initial Written Assessment
More informationCMP239 Grandfathering Arrangements for the Small Generator Discount
CMP239 Grandfathering Arrangements for the Small Generator Discount Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size
More informationJoint Office of Gas Transporters 0321V: Code Governance Review: Approach to environmental assessments within the UNC
Modification Report Code Governance Review: Approach to environmental assessments within the UNC Modification Reference Number 0321V Version 2.0 This Modification Report is made pursuant to Rule 9.3.1
More informationCM063: Modify the definition of Force Majeure (Section J: Interpretation and Definitions)
STC Initial Modification Report CM063: Modify the definition of Force Majeure (Section J: Interpretation and Definitions) At what stage is this document in the process? 01 Initial Modification Report 02
More informationCA045 Arrangements for User Commitment
Stage 02: Proposed System Operator Transmission Owner Code (STC) CA045 Arrangements for User Commitment What stage is this document at? 01 02 03 Initial Proposed Amendment Report This proposal seeks to
More informationTENDER PACK 1 OPERATING MARGINS 2013 CAPACITY TENDER
TENDER PACK 1 OPERATING MARGINS 2013 CAPACITY TENDER This tender pack is designed for; Storage Facility Operators Primary Capacity holders at Storage Facilities Issued December 2012 Market Operation National
More informationCAP189 Standard Gas Insulated Switchgear (GIS) Ownership Boundaries
Stage 05: Draft CUSC Connection and Use of System Code (CUSC) CAP189 Standard Gas Insulated Switchgear (GIS) Ownership Boundaries This proposal seeks to modify the CUSC such that a User requesting a connection
More informationDemand assessment report for incremental capacity between Republic of Ireland [Gas Networks Ireland]
Demand assessment report for incremental capacity between Republic of Ireland [Gas Networks Ireland] and UK [National Grid] where no non-binding demand indications were received 2017-07-27 This report
More informationCMP291. Garth Graham for SSE Generation Ltd. CUSC Panel 23 rd February 2018
CMP291 The open, transparent, non discriminatory and timely publication the harmonised rules for grid connection (in accordance with the RfG, DCC and HVDC) and the harmonised rules on system operation
More informationApplicable Balancing Services Volume Data Methodology Statement
Applicable Balancing Services Volume Data Methodology Statement Effective Date: 01 April 2018 Version Number: 8.0 Published in accordance with Standard Condition C16 of National Grid Electricity Transmission
More informationGrid Code Issue Paper
For presentation at the April 2016 meeting of the Grid Code Development Forum Robert Selbie on behalf of National Grid Interconnector Physical Notification submissions following XBID (Cross Border Intra
More informationGeorge Moran, British Gas 28th August 2015
CMP 251: Removing the error margin in the cap on total TNUoS recovered by generation and introducing a new charging element to TNUoS to ensure compliance with European Commission Regulation 838/2010 George
More informationApplicable Balancing Services Volume Data Methodology Statement
Applicable Balancing Services Volume Data Methodology Statement Version Effective Date: 1 April 20131 Effective in respect of Settlement Days from : 01 April 2011 ABSVD Methodology Statement 1 Version
More informationCMP303 - Improving local circuit charge cost-reflectivity
CMP303 - Improving local circuit charge cost-reflectivity This modification seeks to make part of the TNUoS charge more cost-reflective through removal of additional costs from local circuit expansion
More informationSTCP19-5 Issue 002 Offshore Transmission System Compliance Process & Testing
STCP19-5 Issue 002 Offshore Transmission System Compliance Process & Testing STC Procedure Document Authorisation Company National Grid Electricity Transmission plc Name of Party Representative Signature
More informationBalancing Services Adjustment Data Methodology Statement
Balancing Services Adjustment Data Methodology Statement Effective Date: 01 April 2018 Version Number: 15.0 Published in accordance with Standard Condition C16 of National Grid Electricity Transmission
More information0364: An Appeals Process for Entry. Capacity Manifest Errors. Stage 02: Workgroup Report
Stage 02: What stage is this document in the process? : An Appeals Process for Entry u Capacity Manifest Errors This proposal would add an Appeal process to the Entry Capacity Manifest Error Process proposed
More informationExtension Of The Definition Of ECVAA Systems to include the centrally provided communications network.
P227 Initial Written Assessment Page 1 of 16 146/04 INITIAL WRITTEN ASSESSMENT for Modification Proposal P227 Extension Of The Definition Of ECVAA Systems to include the centrally provided communications
More informationDATED [ ] 200[ ] NATIONAL GRID ELECTRICITY TRANSMISSION PLC (1) and [ ] (2) FAST RESERVE FRAMEWORK AGREEMENT
DATED [ ] 200[ ] NATIONAL GRID ELECTRICITY TRANSMISSION PLC (1) and [ ] (2) FAST RESERVE FRAMEWORK AGREEMENT CONTRACT LOG NO: [NOTE Where Provider has an existing Fast Reserve clause in its CSA, Framework
More informationLoss of Transmission Access Compensation Guidance Note for Customers
Loss of Transmission Access Compensation Guidance Note for Customers This document has been produced to complement the Loss of Transmission Access Compensation Claim Form. Both the claim form and this
More informationThe Entry Capacity Substitution Methodology Statement
Issue 6.06.2 Revision ApprovedCons ultation Draft The Entry Substitution Methodology Statement Effective from 27 th February1 st November 2015 Page 1 of 32 The Entry Substitution Methodology Statement
More informationEntry Capacity Substitution Methodology Statement
Issue Revision 7.0 Approved Entry Substitution Methodology Statement Effective from 1 st November 2015 Page 1 of 30 ENTRY CAPACITY SUBSTITUTION METHODOLOGY STATEMENT Document Revision History Version/
More informationP236: Compensation Claims for MVRN Parties arising from an Outage
Stage 04: Draft Mod Report What stage is this document in the process? : Compensation Claims for MVRN Parties arising from an Outage Section Q8 of the BSC allows for a Party to claim compensation for losses
More informationThe Entry Capacity Substitution Methodology Statement
Issue 5.26.1 Revision Informal Consultation Draft The Entry Substitution Methodology Statement Effective from 2 nd February1 st September 2015 Page 1 of 31 ENTRY CAPACITY SUBSTITUTION METHODOLOGY STATEMENT
More informationShort Term Operating Reserve (STOR)
Short Term Operating Reserve (STOR) Tender Assessment Principles Version 4.0, December 2013 For Further Information please contact: Contracts & Settlements National Grid House, Warwick Technology Park
More informationBalancing Services Adjustment Data. Methodology Statement. Version Date: 1 April th November BSAD Methodology Statement 1
Balancing Services Adjustment Data Methodology Statement Balancing Services Adjustment Data Methodology Statement Version Date: 1 April 2007 05 th November 2009 BSAD Methodology Statement 1 Version Control
More informationOUR TERMS & CONDITIONS NPOWER SALE TERMS & CONDITIONS FOR STANDALONE NEST PRODUCTS
NPOWER SALE TERMS & CONDITIONS FOR STANDALONE NEST PRODUCTS These Terms & Conditions apply to the Contract between you and us. Please read them carefully. 1 DEFINITIONS Words which appear in bold type
More informationThe National Grid Company plc. Minutes of the Grid Code Review Panel National Grid House, Coventry 21 st February 2002
The National Grid Company plc Minutes of the Grid Code Review Panel National Grid House, Coventry 21 st February 2002 Members/Alternates Advisors/Observers Mike Metcalfe National Grid (Chair) Andy Balkwill,
More informationCMP223 Arrangements for Relevant Distributed Generators Under the Enduring Generation User Commitment
Stage 04: Code Administrator Consultation Connection and Use of System Code (CUSC) CMP223 Arrangements for Relevant Distributed Generators Under the Enduring Generation User Commitment 01 02 03 04 05 What
More informationUNC 0680: UNC Changes as a Consequence of no deal United Kingdom Exit from the European Union. UNC Modification
UNC Modification At what stage is this document in the process? UNC 0680: UNC Changes as a Consequence of no deal United Kingdom Exit from the European Union Purpose of Modification: A number of minor
More informationModification Report Re-assessment of User Unsecured Credit Limits Modification Reference Number 0041 Version 2.0
Modification Report Re-assessment of User Unsecured Credit Limits Modification Reference Number 0041 Version 2.0 This Modification Report is made pursuant to Rule 7.3 of the Modification Rules and follows
More informationCMP223 Arrangements for
Stage 02: 03: Workgroup Consultation Report Connection and and Use Use of of System Code (CUSC) CMP223 Arrangements for Relevant Distributed Generators Under the Enduring Generation User Commitment What
More informationNotice of Indicative Gas Transmission Transportation Charges effective from 1 April November 2018
Notice of Indicative Gas Transmission Transportation Charges effective from 1 April 2019 2 November 2018 National Grid Notice of Indicative NTS Charges 1 April 2019 0 Contents 1. Introduction 2 Basis of
More informationAnnual Compliance Report. National Grid Electricity Transmission plc
Annual Compliance Report National Grid Electricity Transmission plc Prepared pursuant to paragraphs 27 and 28 of Special Condition 2O (Business separation requirements and compliance obligations, and conduct
More informationAncillary & Other Services Volume Methodology Statement
Ancillary & Other Services Volume Methodology Statement Version: 05 October 2001 Example (for the purposes of BSC P34 Modification Proposal working Group) of 1 October 2001 Ancillary and Other Services
More informationUNC 0686 (Urgent): Removal of the NTS Optional Commodity Rate with adequate notice. UNC Modification
UNC Modification At what stage is this document in the process? UNC 0686 (Urgent): Removal of the NTS Optional Commodity Rate with adequate notice Purpose of Modification: Removal of the NTS Optional Commodity
More informationNew Participation Category to the BSC Clearing House
69/012 INITIAL WRITTEN ASSESSMENT for Modification Proposal P146 New Participation Category to the BSC Clearing House Prepared by: ELEXON 1 Limited Date of issue: 7 November 2003 Document reference: P146IR
More informationCUSC - SECTION 3 USE OF SYSTEM CONTENTS
CUSC - SECTION 3 USE OF SYSTEM CONTENTS 3.1 Introduction PART IA - GENERAL - GENERATION 3.2 Rights to Use the National Electricity Transmission System 3.3 Other Site Specific Technical Conditions for Embedded
More informationTerms and Conditions related to Balancing
Natasha Z Smith Head of Wholesale Markets Electricity Ofgem 10 South Colonnade Canary Wharf London E14 4PU Kyla Berry Markets & Balancing Development Manager Kyla.Berry@nationalgrid.com Direct tel. +44
More informationScottishPower Energy Management Limited 27 May CUSC Modification Proposal CMP264 Embedded Generation Triad Avoidance Standstill (EGTAS)
ScottishPower Energy Management Limited 27 May 2015 CUSC Modification Proposal CMP264 Embedded Generation Triad Avoidance Standstill (EGTAS) 1 Embedded Generation Triad Avoidance Standstill (EGTAS) Proposal
More informationPurpose of Modification: The Modification proposes to amend BSC Section K to allow ELEXON to carry over BSC Seasonal GC/DC.
BSC Modification Proposal Form P358 At what stage is this document in the process? 01 Modification 02 Workgroup Report Roll over of BSC Seasonal GC/DC 03 04 Draft Modification Report Final Modification
More informationApologies Name Initials Position Robert Longden RL Alternate Users Panel Member Adam Lattimore AL ELEXON
Minutes Meeting name Meeting number 141 CUSC Modifications Panel Date of meeting 26 October 2012 Location National Grid House, Warwick Attendees Name Initials Position Mike Toms MT Panel Chair Emma Clark
More informationP294 Addition of Offshore Transmission System and OTSUA to the definition of the Total System
Stage 03: Assessment Report What stage is this document in the process? Addition of Offshore Transmission System and OTSUA to the definition of the Total System Amend the BSC definition of Total System
More informationTransmission Charging Methodologies Forum
Transmission Charging Methodologies Forum Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. 11
More information1.0 Introduction and Status Review 1.1. Approval of minutes (06 December 2018)
UNC Workgroup 0667 Minutes Inclusion and Amendment of Entry Incremental Capacity Release NPV test in UNC Tuesday 08 January 2019 at Radcliffe House, Blenheim Court, Warwick Road, Solihull B91 2AA Attendees
More informationOfgem s conclusions on best practice guidelines for Network Operator credit cover - brief background and initial thoughts
Ofgem s conclusions on best practice guidelines for Network Operator credit cover - brief background and initial thoughts Paul Murphy Commercial, Charging and Revenue UK Transmission Brief History March
More informationTransmission Charging Methodologies Forum. National Grid House, Warwick
Meeting report Meeting name Date of meeting 9 th September 2015 Time 11:00 14:00 Location Transmission Charging Methodologies Forum National Grid House, Warwick Attendees Name Initials Company Paul Wakeley
More informationCODE MODIFICATION PROPOSAL No 0230 Amendment to the QSEC and AMSEC Auction Timetables Version 2.0 Date: 15/10/2008. Non Urgent
CODE MODIFICATION PROPOSAL No 0230 Amendment to the QSEC and AMSEC Auction Timetables Version 2.0 Date: 15/10/2008 Proposed Implementation Date: 01/04/2009 Urgency: Non Urgent 1 The Modification Proposal
More informationAddressing under-allocation of flows from BBL arising from misalignment of reference conditions
Stage 01: Modification 0560 Urgent: Addressing under-allocation of flows from BBL arising from misalignment of reference conditions At what stage is this document in the process? 01 Modification 02 03
More informationP344 Project TERRE implementation into GB market arrangements
Project TERRE implementation into GB market arrangements This Modification seeks to align the Balancing and Settlement Code (BSC) with the European Balancing Project TERRE (Trans European Replacement Reserves
More informationUNC 0623: Governance Arrangements for Alternatives to Self-Governance Modification Proposals. UNC Workgroup Report
UNC Workgroup Report At what stage is this document in the process? UNC 0623: Governance Arrangements for Alternatives to Self-Governance Modification Proposals Purpose of Modification: This is a Governance
More informationBP Supercharge Application Form
BP Supercharge Application Form BP Supercharge Application Form In order for Allstar to complete your application and issue you with your BP Supercharge cards, we will need the information indicated on
More informationConsultation on Capacity Methodology Statements. Conclusions Report
Consultation on Capacity Methodology Statements Conclusions Report 30 th May 2017 National Grid Gas Transmission Page 1 30 th May 2017 Executive Summary Introduction National Grid Gas plc s ( National
More information3 OUR INSTALLERS 4 OUR RESPONSIBILITY
NPOWER SALE TERMS & CONDITIONS FOR NEST THERMOSTAT 1 OUR CONTRACT These Terms & Conditions apply to the Contract between you and us. Please read them carefully. Words which appear in bold type throughout
More informationAssessment Procedure Consultation Responses. P318 Change of Party ID/Company Number Through Enabling Assignment
Assessment Procedure Consultation Change of Party ID/Company Number Through Enabling Assignment Phase Initial Written Assessment This Assessment Procedure Consultation was issued on 9 July 2015, with responses
More informationChanges to the Stages of Emergency Resulting from Changes Introduced by Exit Reform v0.1. Draft Legal Text
TPD Section Q 1.1 1.2 1.3 Emergency Procedures Draft Legal Text 1.3.1 "Emergency Procedures" means in relation to a Network Gas Supply Emergency, the document issued by National Grid NTS entitled 'Network
More informationJoint Office of Gas Transporters 0231V: Changes to the Reasonable Endeavours Scheme to better incentivise the detection of theft
CODE MODIFICATION PROPOSAL No 0231V Changes to the Reasonable Endeavours Scheme to better incentivise the detection of Theft Version 1.0 Date: 20/11/2009 Proposed Implementation Date: Urgency: TBC Non
More informationFollowing Industry Consultation
Report to Authority Proposed Revisions to the Balancing Principles Statement, Balancing Services Adjustment Data Methodology Statement, Procurement Guidelines, System Management Action Flagging Methodology
More informationSTCP 16-1 Issue 005 Investment Planning
STCP 16-1 Issue 005 Investment Planning STC Procedure Document Authorisation Company Name of Party Representative Signature Date National Grid Electricity Transmission plc SP Transmission plc Scottish
More informationCMP222 User Commitment for Non- Generation Users Volume 1
Stage 06: Final CUSC Modification Report Connection and Use of System Code (CUSC) CMP222 User Commitment for Non- Generation Users Volume 1 This proposal seeks to introduce enduring User Commitment arrangements
More informationCUSC Amendments Panel
Present: Minutes and Actions Arising from Meeting No.96 Held on 03 April 2009 Mark Ripley MR Panel Chair David Smith DS Secretary Hedd Roberts HR Panel Member (National Grid) Paul Jones PJ Panel Member
More informationThank you for providing SSE, with the opportunity to comment on the above Modification Proposal.
Tim Dear Tim, Modification Proposal 0298 WWU proposes to: Resolve a number of anomalies in UNC TPD section V which do not clearly provide the required credit position for Users or Transporters. SSE agree
More informationSuspending the Implementation of the Zonal Allocation of Transmission Losses
Draft MODIFICATION REPORT for Modification Proposal P156 Suspending the Implementation of the Zonal Allocation of Transmission Losses Prepared by: Modification Group Date of issue: 22.01.04 Document reference:
More informationName Initials Position
Minutes Meeting name CUSC Modifications Panel Meeting number 209 Date of meeting 30 June 2017 Location National Grid House, Warwick Attendees Name Initials Position Mike Toms MT Panel Chair Caroline Wright
More informationRAILTRACK THE RAILWAY GROUP STANDARDS CODE
RAILTRACK THE RAILWAY GROUP STANDARDS CODE June 1998 Explanatory Introduction Railtrack, by virtue of the 1993 Railways Act, its control of the network and the law relating to health and safety, has a
More informationInclusion and Amendment of Entry Incremental Capacity Release NPV test in UNC
UNC Modification At what stage is this document in the process? UNC 0667 (Urgent): Inclusion and Amendment of Entry Incremental Capacity Release NPV test in UNC Purpose of Modification: This Modification
More informationTax Strategy. March 2018
Tax Strategy March 2018 Contents 03 Introduction 04 Our approach to tax Do the right thing Total tax contribution 05 Governance and management of tax risk Roles and responsibilities Tax risks 06 Internal
More informationCYPRUS ENERGY REGULATORY AUTHORITY
CYPRUS ENERGY REGULATORY AUTHORITY METHODOLOGY AND CRITERIA FOR THE EVALUATION OF INVESTMENTS IN ELECTRICITY AND GAS INFRASTRUCTURE PROJECTS (ARTICLE 13(6) OF REGULATION (EU) No. 347/2013) 2015 WWW. C
More informationUNC 0636B: Updating the parameters for the NTS Optional Commodity Charge. UNC Modification
UNC Modification UNC 0636B: Updating the parameters for the NTS Optional Commodity Charge At what stage is this document in the process? Purpose of Modification: To update the parameters used in the derivation
More information01 Letter of introduction from Sir John Parker and Steve Holliday National Grid plc
2009/10 Performance Summary Shaping the future Welcome from Sir John Parker and Steve Holliday How we performed Our business Shaping the future Shareholder information 01 Letter of introduction from Sir
More informationTransmission Charging Methodologies Forum. 11:00am 3:00pm National Grid House, Warwick
Meeting report Meeting name Date of meeting 14 th January 2015 Time Location Transmission Charging Methodologies Forum 11:00am 3:00pm National Grid House, Warwick Attendees Name Initials Company Patrick
More informationAgents provide services on our behalf. Service providers provide services to us.
Standard terms for supplying electricity and gas to domestic customers Glossary agents and service providers Agents provide services on our behalf. Service providers provide services to us. central charge
More informationOptional De-registration by Insolvent Party
67/008 ASSESSMENT REPORT for Modification Proposal P127 Optional De-registration by Insolvent Party Prepared by: Governance Standing Modification Group (GSMG) Date of issue: 5 September 2003 Document reference:
More informationCONTRACT RULES: ELECTRICITY CONTRACTS
CONTRACT RULES: ELECTRICITY CONTRACTS W SECTION W - CONTRACT RULES 1 - ICE FUTURES UK EFA CALENDAR BASE ELECTRICITY FUTURES CONTRACT (EFA) ICE FUTURES UK EFA CALENDAR PEAK ELECTRICITY FUTURES CONTRACT
More informationGrid Code Workgroup Consultation Response Proforma
Grid Code Workgroup Consultation Response Proforma GC0101 EU Connection Codes GB Implementation Mod 2 Industry parties are invited to respond to this consultation expressing their views and supplying the
More information2. User Pays a) Classification of the Proposal as User Pays or not and justification for classification
Tim Davies Joint Office By email to enquiries@gasgovernance.co.uk 9 th February 2011 Dear Tim SUBJECT: Total Gas & Power Ltd (TGP) consultation response to Modifications 0339, 0339A & 0340. Total Gas &
More informationCODE MODIFICATION PROPOSAL No 0262 Treatment of Capacity affected by Force Majeure Version 4.0 Date: 18/08/2009. Non Urgent
CODE MODIFICATION PROPOSAL No 0262 Treatment of Capacity affected by Force Majeure Version 4.0 Date: 18/08/2009 Proposed Implementation Date: 01/10/09 Urgency: Non Urgent 1 The Modification Proposal a)
More informationAnnual EMR Compliance Report. National Grid Electricity Transmission plc
Annual EMR Compliance Report National Grid Electricity Transmission plc Prepared pursuant to paragraphs 2N.25 and 2N.26 of Special Condition 2N of the Electricity Transmission Licence granted to National
More informationPeterborough City Council Application for a premises licence under the Gambling Act 2005 (vessel) PLEASE READ THE FOLLOWING INSTRUCTIONS FIRST
Peterborough City Council Application for a premises licence under the Gambling Act 2005 (vessel) PLEASE READ THE FOLLOWING INSTRUCTIONS FIRST If you are completing this form by hand, please write legibly
More informationEmissions Trading Schemes
Meeting: Meeting Location: International Public Sector Accounting Standards Board Ottawa, Canada Meeting Date: December 2-5, 2013 Agenda Item 3 For: Approval Discussion Information Objective(s) of Agenda
More informationRisk Navigator. User guide - Prospect
Risk Navigator User guide - Prospect Risk Navigator is npower s web-based based platform giving customers secure and easy access to market news as it breaks, allowing them to monitor wholesale price movement
More informationTax Strategy. March 2019.
. March 2019. National Grid March 2019 The 2016 Finance Act introduced a requirement for large businesses to publish their tax strategy. National Grid made our first publication in March 2018 in accordance
More informationUNC Text Allocation Register
UNC Allocation Register This register identifies the text provider, in column G, for each modification. Column F '' shows who is next using the numerical order in the Transporter list at the top of this
More informationPREQUALIFICATION PACKAGE FOR
PREQUALIFICATION PACKAGE FOR THERMAL ENERGY STORAGE TANK REHABILITATION (REVISED) PROJECT 17-59 Due Date and Location for Submittal: 2:00 pm on Monday, December 18, 2017 City Clerk City of Beverly Hills
More informationTransmission Charging Methodologies Forum
Transmission Charging Methodologies Forum Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. Tuesday
More informationPROPOSER'S QUALIFICATIONS STATEMENT
PROPOSER'S QUALIFICATIONS STATEMENT PROJECT TITLE: High Pressure Loop Transmission Line Phase 1 PROPOSAL SUBMITTED BY: (Print or Type Name of Bidder) The undersigned certifies the truth and correctness
More informationStatement of amounts credited to investor education and protection fund (See rule 3)
Statement of amounts credited to investor education and protection fund (See rule 3) FORM NO. 1 Registration No. Authorised Capital : Rs. (To be submitted by the Company to the concerned Registrar of Companies
More informationTempus state aid judgment. Advice for capacity agreement holders and capacity market applicants 15 November 2018
Tempus state aid judgment Advice for capacity agreement holders and capacity market applicants 15 November 2018 The following message is being sent to all capacity agreement holders and capacity market
More informationSTCP 19-2 Issue 005 Construction Process & Scheme Closure
STCP 19-2 Issue 005 Construction Process & Scheme Closure STC Procedure Document Authorisation Party National Grid Electricity Transmission plc SP Transmission Ltd Scottish Hydro-Electric Transmission
More informationCUSC - SECTION 14 CHARGING METHODOLOGIES CONTENTS
CUSC - SECTION 14 CHARGING METHODOLOGIES CONTENTS 14.1 Introduction Part I -The Statement of the Connection Charging Methodology 14.2 Principles 14.3 The Calculation of the Basic Annual Connection Charge
More informationDirect Dial: August Our Ref: MP No P125
Direct Dial: 020 7901 7412 The National Grid Company, BSC Signatories and Other Interested Parties 08 August 2003 Our Ref: MP No P125 Dear Colleague Modification to the Balancing and Settlement Code (
More information