Resettlement Plan Due Diligence Report

Size: px
Start display at page:

Download "Resettlement Plan Due Diligence Report"

Transcription

1 Resettlement Plan Due Diligence Report Document Stage: Updated Project Number: April 2014 NEP: Kathmandu Valley Water Supply Improvement Project Block Distribution System and Service Reservoir (Package I) Prepared by Project Implementation Directorate, Kathmandu Upatyaka Khanepani Limited (KUKL) for the Asian Development Bank.

2 Kathamandu Valley Water Supply Improvement Project (ADB Loan No NEP-SF) Due Diligence Report of Block Distribution System and Service Reservoir (BDS-SRT) Package (BDS 1) Project Implementation Directorate Kathmandu Upatyaka Khanepani Limited (KUKL) Anamnagar, Kathmandu April, 2014

3 Contents A BACKGROUND... 3 B PROJECT COMPONENTS... 3 II SCOPE OF LAND ACQUISITION AND RESETTLEMENT... 5 III SOCIOECONOMIC INFORMATION AND PROFILE... 8 A. SOCIOECONOMIC PROFILE... 8 B. GENDER CONSIDERATIONS... 9 IV Information disclosure, consultation, and participation A. PUBLIC CONSULTATION B. INFORMATION DISCLOSURE C. CONTINUED CONSULTATION AND PARTICIPATION V GRIEVANCE REDRESS MECHANISM VI. POLICY AND LEGAL FRAMEWORK A. ENTITLEMENTS ANNEX-I RESETTLEMENT CATAGORIZATION CHECKLIST ANNEX-II COMPENSATION PAYMENT STATUS ANNEX-III PHOTOGRAPHS ANNEX-IIV MAP OF RESERVOIR 2

4 I PROJECT DESCRIPTION A Background 1. The proposed Kathmandu Valley Water Supply Improvement Project 1 will support the ongoing efforts of the Government of Nepal towards improving the water supply services in Kathmandu Valley. The project will invest in bulk water transmission and distribution network improvement systems, and will complement the past and ongoing Asian Development Bank (ADB) projects. 2 The resultant synergy is expected to lead to increased efficiencies, greater improvement in service delivery, and higher impact on health outcomes and quality of life for inhabitants of Kathmandu Valley. 2. Kathmandu Valley is characterized by high urban population growth (estimated to be 6.6% per annum) and high population density (estimated to be more than 2,500 persons per km 2 ). 3 The total population of Kathmandu Valley is estimated to be 2.72 million in 2011, and is expected to hit 3.5 million in Rapid and largely unplanned urban growth, high population density, lack of sustainable water sources, and inadequate past investments in water supply infrastructure have resulted in abysmally poor availability and quality of drinking water. 4 Moreover, poor access to sanitation facilities, improper solid waste management systems, and groundwater and surface water pollution from untreated domestic sewage have caused increased disease incidence, health risks, and associated economic burdens disproportionately impacting the poor and vulnerable. 5 B Project Components Initially the BDS consisted into three packages. But, two more BDS packages has been in Bharkatpur and Kirtipur and still in design. And now the total numbers of BDS packages are five. The package I consisted construction of three reservoirs namely Arubari tank 8500 CU.M. Capacity, Mahankal Chaur -2 tank 8000 CU.M. Capacity and New Bansbari tank 9500 CU.M Capacity. In pipe lying for this package, the size of pipe varies from 400 mm to 1400 mm. The total length of pipe for this package is Km length. The package II consisted construction of two reservoirs namely New Panipokhari Tank 7500 CU.M. and Khumaltar 9500 CU.M capacity. In the pipe lying for this package, the size of pipe varies from 400 to 1100 mm. The total length of pipe for this package is Km length. The 1 The project was prepared through PPTA 4893-NEP: Preparing the Kathmandu Valley Water Distribution, Sewerage, and Urban Development Project, approved on 13 December Due to restructuring of ongoing loans, the work of PPTA started in 2009 and final report was submitted in May Loan 1820-NEP (SF): Melamchi Water Supply Project was approved on 21 December 2000 and became effective on 28 November Loans 2058/2059-NEP (SF): Kathmandu Valley Water Services Sector Development Program were approved on 18 December 2003 and became effective on 7 December Estimated projections by the Central Bureau of Statistics, Government of Nepal, A baseline survey done by CRISIL under PPTA 4893-NEP in September 2010 estimates water availability at 20 liters per capita per day (lpcd) and average duration of water supply at 0.4 hours per day. Kathmandu Upatyaka Khaneani Limited (KUKL), the operator, assesses the current availability as 45 lpcd. 5 Vulnerable groups include female-headed households and below poverty line households (the poverty line in current terms is NRs 12,457 per capita/year). The national average household size in Nepal is considered 5.27 (Poverty Trends in Nepal. National Planning Commission Secretariat, 2005). Therefore, it is assumed the poverty line is NRs 65,648 per household/year. 3

5 package III consisted construction of one water reservoir namely Balaju reservoir with 7000 CU.M. capacity. The length of pipe lying for this package is Km and the, size of pipe varies from 500 to 1000 mm. In totality BDS includes the installation of about 49 km of water mains ranging in diameter from 400 mm to 1,400 mm along the Kathmandu Ring Road (two lanes in each direction, with a 9 m carriageway) and along major city road corridors. These water mains will feed five existing service reservoirs and five new service reservoirs. The BDS will feed these new RVT at Arubari, Mahankal Chaur II, Bansbari, Balaju, and Khumaltar. The service reservoirs provide water to the distribution network. Most of these pipes will be within wider roads with heavy traffic. Traffic management planning and implementation will be critical to ensure continued public support and limited impacts to businesses. Temporary disturbance to businesses is anticipated for 3-5 days per m trench of the BDS component. Full road closure is not anticipated, as the Ring Road is a primary traffic artery within Kathmandu. Good construction practices and traffic management measures, including night works, will ensure continued access to businesses and limited disruption to business activity. In a few areas, vendors and hawkers will require temporary relocation, and will be provided assistance by the contractor in relocating and shifting. Location map of package I 4

6 II SCOPE OF LAND ACQUISITION AND RESETTLEMENT 3. There is no land acquisition under the proposed project. All land for service reservoirs were previously acquired under the ongoing ADB Loan (Ref. Annex II). The impacts resulted from land acquisition has already been addressed. The reservoir construction area is fenced with compound wall and blocked access of public. So, during the time of reservoir construction no impacts are anticipated in private land and business. The pipe line route for BDS package I follow more than 25 to 30 meter wide ring road and follows service track. The construction works within the right of way (RoW) for the Bulk Distribution System (BDS), 6 The temporary disruption for BDS approximately was estimated 3-5 days for BDS (from open trench to backfill). Trench sections for BDS will be Contractors are required to maintain access to shops to avoid and limit the disturbance to the extent possible, and mitigation measures are incorporated into their contracts and monitored by the construction supervision consultants. Temporary economic impacts to businesses along the BDS routes are expected to be short term, and avoided and/or mitigated through good traffic management planning and implementation, night works, and maintaining access to shops during the construction period, as outlined in the Environmental Management Plan (EMP). 7 Under the BDS, some mobile hawkers and vendors, including those with stalls and temporary structures, will be assisted by contractors in moving to alternative locations during the brief period of construction, and allowed to return once the area is declared complete of construction, usually within 5 days. In the event roads are fully closed, with access to shops disrupted, compensation for lost income will be made for the time of disruption. 8. The entitlement matrix has provisioned those businesses that experience full closures during the pipe lying period are entitled for compensation. Based on detail design of the pipe route alignment and reservoir construction area the disruption will be short and none of the business will experience full closure 4. The Ring Road, where the BDS will be laid, is a major transportation artery within Kathmandu with pockets of dense commercial activity. It consists of two lanes in each direction with a total of m carriageways on each side and a moveable barrier in some stretches. The total RoW of the Ring Road is approximately m wide. Closing the Ring Road during construction is not an option, as expressed by local authorities; therefore, good traffic management by the contractors in coordination with police, roads department, local VDCs, and communities is critical to ensure smooth flow of vehicles, safe passage of pedestrians, and limited business impacts. The construction method for BDS is open trenching with heavy excavation machinery. The contractors will be required to maintain access to shops during trenching (metal planks, spaces, etc), which is expected for 5-7 days for larger sized pipes (800-1,400 mm). Prior to construction, contractors and DSC, with the assistance of the community participation consultants, will be required to provide at least 1-2 weeks advance notice, along with an awareness campaign involving local area committees (Tole committees). Vendors: BDS works outside the carriageway will require temporary shifting of vendors. The areas of particular heavy vendor activity are in Narayangopal, Chabahil, and Bansbari area. 6 In some areas along the ring road, works are proposed outside the carriageway or shoulder, while still within the RoW. In these areas, no impacts are anticipated for vendors in these area. 7 To ensure disturbance is minimized to the extent possible, contractors will be required to expedite works in front of businesses, provide pedestrian planks across trenches, manage traffic flows, conduct works at night, etc. 8 The full closure of roads is expected to be minimal under the project, and based on discussions with contractors under the pilot DNI, is estimated to be around 20% of total roads in the planned DNI areas. Full closure is not expected in BDS areas, but more limited to DNI zones, where night works will also be considered to limit impacts. If closed, full closure is not expected to exceed 3-5 days. 5

7 The project construction activities don't disrupt vendors permanently. The vendors experience partial disturbance during the pipe lying period. The contractors are requested to work mainly night and less traffic time. Table 1: BDS Works and Potential Impacts Component Stretches Pipe Dia. (mm) Length (m) Estimated period of access disruption Estimated number of vendors to be temporarily Construction method (night/day) Ring Main Existing Mahankal Chaur Reservoir to Chabahil Chowk Rain Main Chabahil Chowk to Narayan Gopal Chowk days No vendors 4-5 days No vendors Night works Night and day works Feeder Main J2 (Near Arubari Tank) to Arubari Tank days No vendors Night works Feeder Main J4 (Near Mahankal Chair Tank) to Mahankal Chaur Tank days No vendors Night works Feeder Main Narayn Gopal Chowk to New Bansbari Tank days 10 vendors Night and day works Ring Main Chabahil Chowk to Gaushala Chowk Ring Main Khasi Bazar (Kalanki) to Sita Petrol Pump (Ch Km to Ch Km) days No vendors 5-7 days No vendors Night works Day (outside carriageway) Ring Main Sita Petrol Pump to Balkhu (Ch Km to Ch Km) days No vendors Day (outside carriageway) Ring Main Near Ekantakuna to Talchikhel Chowk (Ch Km. to Ch Km) days No vendors Table No 2 Construction of Service Reservoirs Reservoir Site Capacity (CU.M) Arubari Tank 8500 Mahankal Chaur New Bansbari Tank 9500 BDS = Bulk Distribution System, m = meter, mm = millimeter. 6

8 5. The following mitigation measures are proposed in the EMP to avoid and/or reduce the impacts to businesses during linear pipe works: (i) (ii) (iii) (iv) (v) (vi) (vii) Provide at least 1-2 weeks prior advance notice to the community along the stretch and conduct awareness campaigns in coordination with contractor, DSC, and community participation consultant. Distribute project information. Maintain access to avoid disturbance to residents and businesses by providing planks and leaving spaces for businesses and residents to maintain access. Manage traffic flows as per traffic management plan prepared by the contractor in coordination with local authorities and communities, and conduct works at night where possible. Limit amount of time when trenches are open, and complete works quickly where lots of businesses are located. Avoid full street closure to extent possible. Provide employment opportunity to the affected people. Place Implementation Directorate Kathmandu Upatyaka Khanepani Limited (PID KUKL) phone hotline in visible areas. Make community fully aware of grievance mechanism and provide contact information of Project Contractors will assist vendors and hawkers in shifting to alternative location. 7

9 A. Socioeconomic Profile III SOCIOECONOMIC INFORMATION AND PROFILE 6. Description of Package I Area. The package I service area is lies in Kathmandu Metropolitian City and Khadka Bhadrakali, and Jorpati VDC of Kathmandu district. The reservoir of Bansbari is located in Khadkabhadrakali VDC where the pipeline route passes through the Chhabahil, Sukedhara, Maharanjgung and Bansbari. The pipeline route is in ring road area. Demographic composition. There are 436,344 households in Kathmandu district where the population of male and female population are 913,001 and 831,239 and total population is 1,744,240 and average households' size 4.00 (census, 2011). The total population of service area is 1,003,285 in which male population is 533,127 and female population 470,158 and 354,764 households (census, 2011). 7. Social classification. The caste composition of project beneficiaries is heterogonous. Newar is the prominent inhabitants of Kathmandu valley. In terms of caste/ethnic composition of project beneficiaries' people 23.51% are Brahmin, 21.96% are Newar, 19.93% are Chhetri, 8.15% are Tamang and 4.01% are Magar. The percentage of Hindu followers is 91% and others are about 9%. In the Kathmandu Valley, Newar are considered an advanced indigenous people group. This group comprises about 41% of the valley population. 8. Age. The economically active age group between 15 and 59 years constitutes about 73.25% of the affected population. The other main age group 5 to 14 years is about 23% and 60 years over groups constitute about 4.75% of the affected population. There are no significant differences in the percentage of age distribution in package I area. 9. Health. The availability of health services in package I area is satisfactory. The government and private sector are operating health services in this service area. Altogether 4 government health centres, 11 private sector hospitals (214 beds) and 85 private clinics are operating in the area. In the service area 99% have toilet facility where as 1% have open defection practices. The gastric, asthma, fever and jaundice are common disease found among the affected people in service area. 10. Education. The Kathmandu Valley has long been considered the centre for higher education in Nepal. The literacy rate of Kathmandu district is 95.2%. The numbers of educational institutions in Kathmandu Valley are 826 school level and 186 college and university level education institutions where as in BDS package I service area 45 schools and 21 colleges are in operation. (District Profile, Kathmandu district, 2011). 11. Employment. The economy of the Kathmandu Valley is based on trade, commerce, and manufacturing industries like carpets and garments. Other economic sectors are agriculture, education, transport, hotels, and restaurants. Tourism is also a key component of the valley s economy. However, in the rural areas, the economy is still based on agriculture. 12. However, the National Living Standard Survey indicates that about 55.7% of the economically active population of 10 years of age and above in urban Kathmandu Valley is employed in the agriculture and non-agriculture sector, of which only 17% depends on farm activities. It means that about 83% of this group of population depends on non-farm activities such as manufacturing (24.0%), trade (42.6%), service sectors (28.6%), and other works (4.8%). 8

10 13. Economically active population. About 68.72`% of the total population in the valley aged 16 and above are economically active (Census 2011). Majority of the population of the Kathmandu Valley are engaged in agriculture and forestry (36%). The other major industries are manufacturing (17%), commerce (16%), construction (4%), and transportation/communication (3%). Among the affected population, at least one of their family members is engaged in service or any other income generating sources except business. 14. Poverty. The National Living Standard Survey 2010/11 indicates that about % of the population of Nepal lives below the poverty line. According to the NLSS Survey 2011, an individual is considered poor if his/her per capita total annual consumptions is below Rs. 19,261. It has also categorized the food items and non food items and the expenses required to be above the poverty line. Accordingly, the income required for providing adequate calories (2,220 kilocalorie) for an average Nepali to be active is Rs 11,929. For non-food items, for an average, the average income required is Rs. 7,332. Nepal Living Standard Survey conducted by CBS in 1995/96, 2003/04 and 2010/11 revealed that between the three surveys there had been substantial decrease in the poverty in Nepal. The survey shows that poverty had decreased faster in the urban areas from 1995/96 to 2003/04. However, the urban poverty has increased from 9.6 % to 15.5 % from 2003/04 to 2010/11, where as there was substantial decrease of poverty in rural areas Slums and squatter settlements. The rapid population growth has created a number of slums and squatter settlements in the Kathmandu Valley. But the numbers of slums and squatters are comparatively low in BDS package I service area. And based in detail design no slums, squatters and hawkers will be affected by the construction activity. B. Gender Considerations 16. The project will provide universal connections, including for poor and vulnerable households, including female-headed households. Employment will also be granted to females, with equal pay for men and women. In addition to the measures provided for addressing the gender concerns of the affected households, the resettlement plan will be implemented in consonance with the gender equity and social inclusion (GESI) plan for the project. 17. Women-headed households. According to the 2011 census, about 12% of households have been reported as female-headed in Kathmandu valley. Among the affected none of them were female headed households. 9 For the food item only, this has been calculated as NRs.11,929 per person per year (National Planning Commission of Nepal, Nepal Living Standard Survey 2010/2011). 10 Key reasons for the reduction in poverty include (a) the significant inflow of remittances, (b) decline in fertility rates, (c) increases in farm wages over the past decade and, importantly, (d) urbanization and the associated increase in high productivity economic activity compared with the lower productive activities of rural areas. 9

11 IV Information disclosure, consultation, and participation A. Public Consultation 18. While preparing this Due Diligence Report (DDR) an extensive consultation program with project affected households and stakeholders were carried out, in line with the requirements pertaining to environment and social considerations of ADB. The public, business owners, affected people and shopkeepers were informed about the possibility of disruption to the business. The tools used for consultations were stakeholder workshops and meetings, and focus group discussions (FGD). These consultations provided inputs for identification of the felt needs of the communities, and the relevant stakeholders. In BDS package I route alignment and vendors, business owner were informed about the possibility of disruption to the business. During the visits, the AP's were asked the status of compensation payment status and potential temporarily impacted areas that could experience partial disruption of roads/galli. In the pipe line route and reservoir construction area extensive consultations were carried out and informed the project activities and possible short disturbance during construction work. The table below no 3 shows the date, location, issues raised by the local people and detail issues raised during the public consultations. Table no.3 Public Consultation Matrix Date 12 March March 2014 No. of Participants Male:7 Female:8 Male:6 Female:3 Location Participants attended Mahankal Local vendors, local people, project benefices Khadkra Bhadraka li Vendors and project benefices Topic/issues discussed Traffic diversion, business disruption, quality of works and, employment Wage discrimination, Compensation package, construction time Information disseminated Appropriate alternative route traffic management will be carried out, priority to local people in job, compensation will be provided for full time disruption No discrimination in wage rate, construction time will be in less traffic period and complete rehabilitation work immediately B. Information Disclosure 19. To provide for more transparency in planning and for further active involvement of beneficiary people and other stakeholders, project information was disseminated through disclosure of the translated versions of the DDR. The information will be made available at public places, including the offices of PID, KUKL main office and branch offices, contractor site office and Ward Office of Kathmandu Metropolitian city. A copy of the DDR will be disclosed on the ADB and project related websites, and is also available from PID upon request. 10

12 C. Continued Consultation and Participation 20. The PID has extended and expanded the consultation and disclosure process during the detailed design stage and will be continued during construction period of the project. CAPC has been recruited to ensure ongoing consultations and public awareness during project implementation. This has been coordinate with the PID, design and supervision consultant (DSC), and contractors to ensure that communities are made fully aware of project activities in all stages of construction. A community awareness and participation plan was also prepared for the project and implementing by CAPC in coordination with the PID and DSC safeguards expert. Community groups such as TLO and vendor associations have been consulting and made aware of the civil works and project activities prior to construction. 11

13 V GRIEVANCE REDRESS MECHANISM 21. A grievance redress mechanism (GRM) has been established (safeguard officer from PID, safeguard expert from DSC, CAPC, contractor and TLO member) in PID to receive, evaluate, and facilitate the resolution of affected people s concerns, complaints, and grievances about the social and environmental performance at the level of the project. A Community Issue Resolution Team (CIRT) is also established to address the grievances immediately in the field level. The Safeguard officer from PID has been assigned as coordinator for grievance handling. The name and contact number for GRM team has been mentioned in brochure and leaflets. The GRM aims to provide a trusted way to voice and resolve concerns linked to the project, and to be an effective way to address affected people s concerns. The GRM for the project is outlined below, and consists of three levels with time-bound schedules and specific persons to address grievances. 22. First level of GRM. The first level and most accessible and immediate contact for the fastest resolution of grievances by CIRT (contractors, CAPC, TLO member and DSC supervisor) on site. Prior to construction of any works, CAPC, DSC, and contractors are to hold local community meetings to notify the local residents and businesses of the temporary disturbance, and to inform them of the project. If a local area committee (tole committee) exists in the area, they should also be informed and made aware of the project. If any complaints arise, the contractors, DSC, and PID can immediately resolve the complaint on site, and if necessary, with the assistance of the local tole committee. The PID office can also be involved in grievance redress at this stage. The Contractor and CAPC office phone number will be posted in public areas within the project area and construction sites. Any person with a grievance related to the project works can contact the project to file a complaint. The CAPC consultants will document the complaint, and immediately address and resolve the issue with the contractor within 1-2 days, if the complaint remains unresolved at the field level. The assistance of the DSC safeguards specialists (the environmental specialist or social safeguards specialist) to help resolve the issue. The CAPC consultants will notify the PID safeguards unit that a complaint was received, and whether it was resolved. The CAPC will fully document the following information: (i) name of the person, (ii) date complaint was received, (iii) nature of complaint, (iv) location, and (v) how the complaint was resolved. 23. Second level of GRM. Should the grievance remain unresolved; the CAPC consultants will forward the complaint to the PID safeguards unit. The person filing the grievance will be notified by the CAPC consultants that the grievance was forwarded to the PID safeguards unit. The PID safeguard unit Chief will address the grievance. Grievances will be resolved through continuous interactions with affected persons, and the PID will answer queries and resolve grievances regarding various issues, including environmental, social, or livelihood impacts. Corrective measures will be undertaken at the field level by the PID safeguards staff within 7 days. The relevant safeguards unit staff will fully document the following information: (i) name of the person, (ii) date complaint was received, (iii) nature of complaint, (iv) location, and (v) how the complaint was resolved. 24. Third level of GRM. Should the grievance remain unresolved, the PID project director will activate the third level of the GRM by referring the issue (with written documentation) to the local Grievance Redress Committee (GRC) of the KUKL, who will, based on review of the grievances, address them in consultation with the PID safeguards unit, project director, and affected persons. The local GRC will consist of members of the PID, affected persons, and local area committee, among others determined to provide impartial, balanced views on any issues. The GRC should consist of around five persons. A hearing will be called with the GRC, if necessary, where the affected person can present his or her concerns/issues. The process will promote conflict resolution through mediation. The 12

14 local GRC will meet as necessary when there are grievances to be addressed. The local GRC will suggest corrective measures at the field level and assign clear responsibilities for implementing its decision within 15 days. The functions of the local GRC are as follows: (i) to provide support to affected persons on problems arising from environmental or social disruption, asset acquisition (if necessary), and eligibility for entitlements, compensation and assistance; (ii) to record grievances of affected persons, categorize and prioritize them, and provide solutions within 15 days; and (iii) to report to the aggrieved parties developments regarding their grievances and decisions of the GRC. The PID safeguards officers will be responsible for processing and placing all papers before the GRC, recording decisions, issuing minutes of the meetings, and taking follow-up action to see that formal orders are issued and the decisions carried out. 25. Fourth level of GRM. In the event that a grievance is not addressed by the contractor, DSC, branch office, PID, or GRC, the affected person can seek legal redress of the grievance in the appropriate courts, the fourth level of the GRM, which is the formal legal court system. The grievance redress mechanism and procedure is depicted in Figure 1. 13

15 Figure 1: Grievance Redress Mechanism (GRM) Affected Person 1st Level Grievances Field Level: Contractor, DSC,CAPC 1-2 Days Grievance Redressed Not Redressed 2nd Level Grievances Not Redressed PID Safeguards Unit 7 Days Grievance Redressed 3rd Level Grievances Not Redressed Grievance Redress Committee 15 Days Grievance Redressed 4th Level Grievances Higher Authority/ Court of Law DSC= design and supervision consultant, GRM= grievance redress mechanism, PID= project implementation directorate. 14

16 VI. POLICY AND LEGAL FRAMEWORK 26. ADB Safeguards Policy Statement (2009). The three important elements of the ADB s Safeguards Policy Statement (SPS) are (i) compensation to replace lost assets, livelihood, and income; (ii) assistance for relocation, including provision of relocation sites with appropriate facilities and services; and (iii) assistance for rehabilitation to achieve at least the same level of well-being with the project as without it. In addition, the absence of legal title to land should not be a bar to compensation. ADB SPS requires compensation prior to actual income loss. In cases where the contractors know which streets will be closed and for how long, compensation can be paid out to the businesses prior to construction. 27. Government of Nepal Laws. As there is no land acquisition, the government s policies, e.g. The Land Acquisition Act, 2034 (1977) are not relevant for this project. The Government of Nepal has no policy to compensate for temporary impacts during construction. A. Entitlements 28. The entitlement matrix (Table 4) summarizes the main types of losses and the corresponding entitlements in accordance with the ADB policies. In addition to temporary impacts, the entitlement matrix also covers damages to structures during construction. 15

17 Table 4: Entitlement Matrix Type of Loss Entitlement Unit Description of Entitlement and Implementation Procedures 1.Damages caused during construction Remarks Responsibility 1.1 Government and private structures Titleholder Tenant Informal settlers on government land Where damages occur to private, community, or government property as a result of construction works, the cost of restoring these to at least their original condition will be the responsibility of the contractor as part of their contract. Extreme care should be taken by the contractors to avoid damaging any properties during construction. Compensation for the losses will be borne by the contractor. Contractor/PID/DSC/CAPC 2. Community facilities and resources 2.1 Loss of community structures Local community Restoration of affected community buildings and structures to at least previous condition, or replacement in areas identified in consultation with affected communities and relevant authorities will be carried out. Extreme care should be taken by the contractors to avoid damaging any properties during construction. Compensation for the losses will be borne by the contractor. Contractor/PID/ CAPC Community structures include service roads, inner roads, temples, footpaths/trails, culverts, and water points. 2.2 Loss of drinking water and sanitation Residents and businesses There will be immediate replacement and restoration of the water points. The time gap between the construction of new system and transfer from the old system should be minimized. Alternative sources of water should be made available during the construction period. Contractor/PID/DSC/ CAPC 16

18 Type of Loss Entitlement Unit Description of Entitlement and Implementation Procedures 3. Temporary loss of income Remarks Responsibility 3.1 Temporary loss of business Titleholder Licensed and nonlicensed vendors, and titled and non-titled households/tenants Businesses are entitled to compensation for each day of disturbance on fully closed roads. An income survey will serve as the cut-off date. All businesses identified in the project-impacted areas (sections ready for construction) on the cut-off date will be entitled to compensation for their lost income based on the tax record or, in its absence, comparable rates from registered businesses of the same type with tax records. For shops not qualifying under these categories (hawkers, vendors, etc.), there is the option of using the actual income based on survey followed by a verification of the income data based on comparable incomes in the project area. An income survey prior to construction will serve as the cut-off date. DSC/PID/ CAPC Mobile hawkers and vendors will be assisted by contractors in moving to alternative locations during the period of construction. 3.2 Vulnerable persons Female-headed, and below poverty line households, the annual poverty line data is NRs. 19,261 per capita/year or NRs 93,994 per household/year: NLSS Survey, 2011 Vulnerable persons will be entitled to preferential employment (unskilled labor) under the project. Vulnerable persons will be identified during income survey, with the list given to PID and contractor. DSC/PID/ CAPC /contractor 4. Structures 4.1 Temporary loss of structures in right of way Temporary or semipermanent structures or stalls that belong to licensed and non-licensed vendors, and titled and non-titled households Affected persons will: (i) receive advanced notice of at least 2 weeks; (ii) have rights to salvage materials from structure; (iii)receive assistance in shifting to nearby location; and (iv) be allowed to return to original site after completion of construction works. DSC = Design and Supervision Consultants, PID = Project Implementation Directorate. There will be temporary shifting for 5-7 days during period of construction. DSC CAPC and contractor will identify alternative site and help in shifting. Contractor/ DSC/PID/CIRT 17

19 A. Project Data Sub'project Title: BDS Package I ANNEX I Kathmandu Upatkaya Khanepani Limited RESETTLEMENT CATEGORIZATION B. Screening Questions for Resettlement Categorization Probable social impacts Yes No Remarks Will the project include any physical construction work? Does the project include upgrading /rehabilitation nor new construction? Construction of new reservoir tank and pipe lying works Are any project effect likely leads to loss of housing, other assets, resource use or incomes/livelihoods? Does land required for the project? Does the land compensation need to pay for land or any loss? Is the ownership status and current usage of the land known? NA Will there be loss of housing? The compensation is paid under loan 1820, minute is attached Will there be loss of agricultural plots? No agricultural land will disrupted Will there be losses of crops, trees, and fixed assets? No crops & trees will be disrupted. Will there be loss of businesses or enterprises? Will there be loss of incomes? Will the vendors experience full closure? Partial disruption is expected Will people lose access to facilities, services, or natural resources? Will any social or economic activities be affected by land use.related changes? Water scarcity will met C. Information on Affected Persons: Any estimate of the likely number of households that will be affected by the sub.project? [ ] No [ ] Yes If yes, approximately how many? Are any of them tenants, bonded labor or vulnerable to poverty risks? [ ] No [ ] Yes If yes, please briefly describe their situation. After reviewing the answer above, it is determined that the sub.project is A [ ] Categorized as A project, a full Resettlement Plan is required [ ] Categorized as B project, a short Resettlement Plan is required [ ] Categorized as C project, no Resettlement Plan is required 18

20 ANNEX-II Compensation Payment and Land Acquisition Status of Reservoir S.N. Ward No. Old Plot Total Area Affected Area Area Owner's Name Rate per Ropani R A P D R A P D (Ropani) Sq meter Amount Rs. Date Remarks 1 8 Ka Lina Tuladhar 2,080, ,000 27/8/ Ka Nain Kumari Khatri 2,080,000 3,250,000 27/8/ Ka Satrughan P. Upadhya 2,080,000 5,265,104 28/8/ Ka Ang Phulhan Sherpra 2,080,000 3,217,552 28/8/ Ka Rama KC 1,300,000 1,625,000 29/10/ Ka Narahari, Mitharam 2,080, ,000 22/11/2002 Khatri Total ,747,656 19

21 Annex III Photographs Consultation meeting with community people Information dissemination and consultation 20

22 MAP OF RESERVOIR 21

Resettlement Plan. Nepal: Kathmandu Valley Water Supply Improvement Project

Resettlement Plan. Nepal: Kathmandu Valley Water Supply Improvement Project Resettlement Plan Document Stage: Updated Project Number: 34304 January 2014 Nepal: Kathmandu Valley Water Supply Improvement Project Prepared by CDM Smith Inc. for the Project Implementation Directorate,

More information

Prepared by: GHD Pty Ltd., Australia in assn with Integrated Consultants Nepal (ICON) Pvt. Lt. Nepal

Prepared by: GHD Pty Ltd., Australia in assn with Integrated Consultants Nepal (ICON) Pvt. Lt. Nepal Technical Assistance Consultant s Report Project Number: 34304 December 2006 NEPAL: Kathmandu Valley Water Distribution, Sewerage, and Urban Development Project (Financed by: Technical Assistance Special

More information

Nepal: Decentralized Rural Infrastructure and Livelihood Project- Additional Financing

Nepal: Decentralized Rural Infrastructure and Livelihood Project- Additional Financing Resettlement Planning Document Due Diligence Report Loan Number: 2796 and Grant Number: 0267 NEP June 2012 Nepal: Decentralized Rural Infrastructure and Livelihood Project- Additional Financing Ghupa-Sanghu

More information

FINANCIAL ANALYSIS. A. Kathmandu Upatyaka Khanepani Limited

FINANCIAL ANALYSIS. A. Kathmandu Upatyaka Khanepani Limited Kathmandu Valley Wastewater Management Project (RRP NEP 43524) FINANCIAL ANALYSIS A. Kathmandu Upatyaka Khanepani Limited 1. Kathmandu Upatyaka Khanepani Limited (KUKL) is a public company registered under

More information

Semi-Annual Social Safeguards Monitoring Report. SRI: Greater Colombo Wastewater Management Project

Semi-Annual Social Safeguards Monitoring Report. SRI: Greater Colombo Wastewater Management Project Semi-Annual Social Safeguards Monitoring Report Project No. 36173-013 Period Covering July to December 2013 April 2014 SRI: Greater Colombo Wastewater Management Project Prepared by the Ministry of Local

More information

GOVERNMENT OF KARNATAKA

GOVERNMENT OF KARNATAKA Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized GOVERNMENT OF KARNATAKA Karnataka Urban Water Supply Modernization Project (KUWSMP) RESETTLEMENT

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE Appendix 3 13 A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The project preparatory technical assistance (PPTA) is required to help the government of Mongolia design the Regional Road Development

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE Appendix 4 11 A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The government has identified the priority areas to be covered under the ensuing loan project and prepared outline technical studies

More information

Environmental Assessment and Review Framework. Mongolia: Western Regional Road Corridor Investment Program

Environmental Assessment and Review Framework. Mongolia: Western Regional Road Corridor Investment Program Western Regional Road Corridor Investment Program (RRP MON 41193) Environmental Assessment and Review Framework September 2011 Mongolia: Western Regional Road Corridor Investment Program Prepared by the

More information

ASIAN DEVELOPMENT BANK RESETTLEMENT PLAN. Subproject: SH-70 (Gaya to Rajauli)

ASIAN DEVELOPMENT BANK RESETTLEMENT PLAN. Subproject: SH-70 (Gaya to Rajauli) ASIAN DEVELOPMENT BANK RESETTLEMENT PLAN Subproject: SH-70 (Gaya to Rajauli) BIHAR STATE HIGHWAYS PROJECT ROAD CONSTRUCTION DEPARTMENT (RCD) GOVERNMENT OF BIHAR FEBRUARY 2008 TABLE OF CONTENTS ITEM Page

More information

MFF - Bihar Urban Development Investment Program (Facility Concept)

MFF - Bihar Urban Development Investment Program (Facility Concept) India: MFF - Bihar Urban Development Investment Program (Facility Concept) Project Name Project Number 41603-013 Country Project Status Project Type / Modality of Assistance Source of Funding / Amount

More information

Resettlement Planning Document. IND: Bihar State Highways Project Subproject: SH-74 (Hajipur Areraj)

Resettlement Planning Document. IND: Bihar State Highways Project Subproject: SH-74 (Hajipur Areraj) Resettlement Planning Document Resettlement Plan Document Stage: Updated Project Number: 41127 August 2008 IND: Bihar State Highways Project Subproject: SH-74 (Hajipur Areraj) Prepared by Road Construction

More information

SECTOR ASSESSMENT (SUMMARY): TRANSPORT 1

SECTOR ASSESSMENT (SUMMARY): TRANSPORT 1 Country Partnership Strategy: Viet Nam, 2012 2015 SECTOR ASSESSMENT (SUMMARY): TRANSPORT 1 Sector Road Map 1. Sector Performance, Problems, and Opportunities 1. Investment in the transport sector in Viet

More information

LOAN AGREEMENT (Special Operations) LOAN AGREEMENT dated 17 January 2013 between KINGDOM OF CAMBODIA ( Borrower ) and ASIAN DEVELOPMENT BANK ( ADB ).

LOAN AGREEMENT (Special Operations) LOAN AGREEMENT dated 17 January 2013 between KINGDOM OF CAMBODIA ( Borrower ) and ASIAN DEVELOPMENT BANK ( ADB ). LOAN AGREEMENT (Special Operations) LOAN AGREEMENT dated 17 January 2013 between KINGDOM OF CAMBODIA ( Borrower ) and ASIAN DEVELOPMENT BANK ( ADB ). WHEREAS (A) by a loan agreement of even date herewith

More information

PROJECT PREPARATION TECHNICAL ASSISTANCE

PROJECT PREPARATION TECHNICAL ASSISTANCE 12 Appendix 4 A. Justification PROJECT PREPARATION TECHNICAL ASSISTANCE 1. A regional project preparatory technical assistance (R-PPTA) is required to prepare the Pacific Renewable Energy Investment Facility

More information

Detailed Project Report. Devitar-Phulasi-Pokhari Road Subproject Ramechhap

Detailed Project Report. Devitar-Phulasi-Pokhari Road Subproject Ramechhap Government of Nepal Ministry of Federal Affairs and Local Development Central Level Project Implementation Unit Earthquake Emergency Assistance Project Lalitpur, Nepal Earthquake Emergency Assistance Project

More information

COMPENSATION, ASSISTANCE AND RESETTLEMENT POLICY PROPOSED FOR

COMPENSATION, ASSISTANCE AND RESETTLEMENT POLICY PROPOSED FOR Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized DIRECTORATE FOR ROADS OF VIETNAM PROJECT MANAGEMENT UNIT 3 ================= COMPENSATION,

More information

Karnataka Integrated Urban Water Management Investment Program (RRP IND 43253) ECONOMIC ANALYSIS

Karnataka Integrated Urban Water Management Investment Program (RRP IND 43253) ECONOMIC ANALYSIS Karnataka Integrated Urban Water Management Investment Program (RRP IND 43253) A. Introduction ECONOMIC ANALYSIS 1. Karnataka. Karnataka is one of the top ten states in India by gross domestic product

More information

Kyrgyz Republic: Emergency Assistance for Recovery and Reconstruction

Kyrgyz Republic: Emergency Assistance for Recovery and Reconstruction Completion Report Project Number: 44236-013 Loan Number: 2668 Grant Number: 0217 July 2017 Kyrgyz Republic: Emergency Assistance for Recovery and Reconstruction This document is being disclosed to the

More information

Environmental Safeguard Monitoring Report. FIJ: Transport Infrastructure Investment Sector Project

Environmental Safeguard Monitoring Report. FIJ: Transport Infrastructure Investment Sector Project Environmental Safeguard Monitoring Report Semi Annual Report July 2016 ADB Project Number: 48141-001 ADB Loan Number: 3210 FIJ: Transport Infrastructure Investment Sector Project Prepared by Fiji Roads

More information

Setting Standards for Sustainable Development Update and Review of the World Bank s Safeguard Policies Case Studies in Indonesia

Setting Standards for Sustainable Development Update and Review of the World Bank s Safeguard Policies Case Studies in Indonesia Setting Standards for Sustainable Development Update and Review of the World Bank s Safeguard Policies Case Studies in Indonesia Phase 3 Consultation in Indonesia January 26-28, 2016 Objective Illustrate

More information

ASIAN DEVELOPMENT BANK RESETTLEMENT PLAN. Subproject: SH-69 (Dumaria - Ranitalab)

ASIAN DEVELOPMENT BANK RESETTLEMENT PLAN. Subproject: SH-69 (Dumaria - Ranitalab) ASIAN DEVELOPMENT BANK RESETTLEMENT PLAN Subproject: SH-69 (Dumaria - Ranitalab) BIHAR STATE HIGHWAYS PROJECT ROAD CONSTRUCTION DEPARTMENT (RCD) GOVERNMENT OF BIHAR FEBRUARY 2008 TABLE OF CONTENTS ITEM

More information

Combined Resettlement and Indigenous Peoples Plan

Combined Resettlement and Indigenous Peoples Plan Regional Urban Development Project (RRP NEP 47252) Combined Resettlement and Indigenous Peoples Plan August 2017 NEPAL: Regional Urban Development Project Construction of Integrated Waste Processing Sites

More information

INTEGRATED SAFEGUARDS DATA SHEET RESTRUCTURING STAGE Note: This ISDS will be considered effective only upon approval of the project restructuring

INTEGRATED SAFEGUARDS DATA SHEET RESTRUCTURING STAGE Note: This ISDS will be considered effective only upon approval of the project restructuring Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized o INTEGRATED SAFEGUARDS DATA SHEET RESTRUCTURING STAGE te: This ISDS will be considered

More information

OFFICIAL -1 L(-L DOCUMENTS. Between. and

OFFICIAL -1 L(-L DOCUMENTS. Between. and Public Disclosure Authorized OFFICIAL -1 L(-L DOCUMENTS ADDENDUM No 2 TO ADMINISTRATION AGREEMENT Between Public Disclosure Authorized Public Disclosure Authorized the EUROPEAN UNION (represented by the

More information

Safeguards Monitoring Report

Safeguards Monitoring Report Safeguards Monitoring Report Semiannual Report Covering July-Dec 2016 period February 2017 (ESDIP) Tranche-2 Chimtala- Arghandi 220 kv DC Transmission Line Subproject (DABS - 006/ICB) Prepared by Da Afghanistan

More information

VIE: Renewable Energy Development and Network Expansion and Rehabilitation for Remote Communes Sector Project. Sub-project: So Vin Hydropower Project

VIE: Renewable Energy Development and Network Expansion and Rehabilitation for Remote Communes Sector Project. Sub-project: So Vin Hydropower Project Final Resettlement Monitoring Report Document stage: Final Project number: Loan 2517 May, 2017 VIE: Renewable Energy Development and Network Expansion and Rehabilitation for Remote s Sector Project Sub-project:

More information

FINAL EVALUATION VIE/033. Climate Adapted Local Development and Innovation Project

FINAL EVALUATION VIE/033. Climate Adapted Local Development and Innovation Project FINAL EVALUATION VIE/033 Climate Adapted Local Development and Innovation Project PROJECT SUMMARY DATA Country Long project title Short project title LuxDev Code Vietnam Climate Adapted Local Development

More information

Periodic Financing Request Report. India: Karnataka Integrated Urban Water Management Investment Program (Tranche 2)

Periodic Financing Request Report. India: Karnataka Integrated Urban Water Management Investment Program (Tranche 2) Periodic Financing Request Report Project Number: 43253-027 MFF Number: 0080-IND October 2018 India: Karnataka Integrated Urban Water Management Investment Program (Tranche 2) Distribution of this document

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK . ASIAN DEVELOPMENT BANK TAR: BAN 35242 TECHNICAL ASSISTANCE TO THE PEOPLE S REPUBLIC OF BANGLADESH FOR PREPARING THE GAS SECTOR DEVELOPMENT PROJECT April 2004 CURRENCY EQUIVALENTS (as of 21 April 2004)

More information

OPERATIONS MANUAL BANK POLICIES (BP)

OPERATIONS MANUAL BANK POLICIES (BP) BANK POLICIES (BP) OM Section F1/BP Page 1 of 2 These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject. SAFEGUARD POLICY STATEMENT 1. The Asian Development

More information

Republic of Azerbaijan: Water Supply and Sanitation Investment Program Tranche 4

Republic of Azerbaijan: Water Supply and Sanitation Investment Program Tranche 4 Periodic Financing Request Report Project Number: 42408-044 MFF Number: 0032 July 2016 Republic of Azerbaijan: Water Supply and Sanitation Investment Program Tranche 4 Distribution of this document is

More information

Timor-Leste: Baucau to Viqueque Highway Project

Timor-Leste: Baucau to Viqueque Highway Project Resettlement Plan Project Number: 51115 June 2017 Timor-Leste: Baucau to Viqueque Highway Project Prepared by the Government of Timor-Leste for the Asian Development Bank. Table of Contents EXECUTIVE

More information

Resettlement Plan. India: National Capital Region Urban Infrastructure Financing Facility Project 1 - Bahadurgarh-Badli Road

Resettlement Plan. India: National Capital Region Urban Infrastructure Financing Facility Project 1 - Bahadurgarh-Badli Road Resettlement Plan Document Stage: Draft Project Number: 41598 September 2013 India: National Capital Region Urban Infrastructure Financing Facility Project 1 - Bahadurgarh-Badli Road Prepared by the Haryana

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE 8 Appendix 3 A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The Government of the Republic of the Union of Myanmar has requested the Asian Development Bank (ADB) to provide a project preparatory

More information

SECTOR ASSESSMENT (SUMMARY): ROAD TRANSPORT (NON-URBAN)

SECTOR ASSESSMENT (SUMMARY): ROAD TRANSPORT (NON-URBAN) Second Jharkhand State Road Project (RRP IND 49125) SECTOR ASSESSMENT (SUMMARY): ROAD TRANSPORT (NON-URBAN) A. Sector Performance, Problems, and Opportunities 1. State context. The state of Jharkhand was

More information

48081 v1. India: Andhra Pradesh Road Sector Project. Environmental and. Social Management Framework. For. Maintenance Road. (approx.

48081 v1. India: Andhra Pradesh Road Sector Project. Environmental and. Social Management Framework. For. Maintenance Road. (approx. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized 48081 v1 India: Andhra Pradesh Road Sector Project Environmental and Social Management

More information

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized I. Basic Information Date prepared/updated: 04/15/2010 1. Basic Project Data Original

More information

INITIAL POVERTY AND SOCIAL ANALYSIS. Country: India Project Title: Loan to PNB Housing Finance Limited. FI Department/Division: PSOD/PSFI

INITIAL POVERTY AND SOCIAL ANALYSIS. Country: India Project Title: Loan to PNB Housing Finance Limited. FI Department/Division: PSOD/PSFI INITIAL POVERTY AND SOCIAL ANALYSIS Country: India Project Title: Loan to PNB Housing Finance Limited Lending/ Financing Modality: FI Department/Division: PSOD/PSFI I. POVERTY IMPACT AND SOCIAL DIMENSIONS

More information

GEO: Sustainable Urban Transport Investment Program, Tranche 2 Tbilisi-Rustavi Urban Road Link (Section-1: km 0 to 4 Tbilisi Phonichala) (Addendum)

GEO: Sustainable Urban Transport Investment Program, Tranche 2 Tbilisi-Rustavi Urban Road Link (Section-1: km 0 to 4 Tbilisi Phonichala) (Addendum) Resettlement Plan December 2014 GEO: Sustainable Urban Transport Investment Program, Tranche 2 Tbilisi-Rustavi Urban Road Link (Section-1: km 0 to 4 Tbilisi Phonichala) (Addendum) Prepared by the Municipal

More information

OFFICIAL DOCUMENTS. The World Bank. Public Disclosure Authorized. Public Disclosure Authorized

OFFICIAL DOCUMENTS. The World Bank. Public Disclosure Authorized. Public Disclosure Authorized Public Disclosure Authorized OFFICIAL DOCUMENTS The World Bank 1818 H Street N.W. (202) 473-1000 INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT Washington, D.C. 20433 Cable Address: INTBAFRAD INTERNATIONAL

More information

(i) Loan Disbursement Handbook means ADB s Loan Disbursement Handbook (2012, as amended from time to time);

(i) Loan Disbursement Handbook means ADB s Loan Disbursement Handbook (2012, as amended from time to time); 2 (f) Goods means equipment and materials to be financed out of the proceeds of the Loan, including related services such as transportation, insurance, installation, commissioning, training, and initial

More information

The Melamchi Water Supply Project

The Melamchi Water Supply Project The Melamchi Water Supply Project An effort to quench the ever growing thirst of the Kathmandu Valley Finance 663 International Finance, Spring 1 2014 Team Pancha: Chris Freeman, Nabin Khanal, Waqas Satti,

More information

SOUTH ASIA REGIONAL PUBLIC PROCUREMENT CONFERENCE Dhaka, Bangladesh (November 1-3, 2015)

SOUTH ASIA REGIONAL PUBLIC PROCUREMENT CONFERENCE Dhaka, Bangladesh (November 1-3, 2015) 3RD SOUTH ASIA REGIONAL PUBLIC PROCUREMENT CONFERENCE Dhaka, Bangladesh (November 1-3, 2015) COUNTRY PRESENTATION - NEPAL Sunil Kumar Karn, Joint Secretary Public Procurement Monitoring Office (PPMO) Kathmandu,

More information

Will the integration of negative externalities into project design be included in the redrafted ESF? How does the Bank ensure that project

Will the integration of negative externalities into project design be included in the redrafted ESF? How does the Bank ensure that project Review and Update of the World Bank s Environmental and Social Safeguard Policies Phase 2 Feedback Summary Date: February 26, 2015 Location: Nairobi, Kenya Audience: NGOs and CSOs Overview and Key Issues

More information

ANNEX ICELAND NATIONAL PROGRAMME IDENTIFICATION. Iceland CRIS decision number 2012/ Year 2012 EU contribution.

ANNEX ICELAND NATIONAL PROGRAMME IDENTIFICATION. Iceland CRIS decision number 2012/ Year 2012 EU contribution. ANNEX ICELAND NATIONAL PROGRAMME 2012 1 IDENTIFICATION Beneficiary Iceland CRIS decision number 2012/023-648 Year 2012 EU contribution 11,997,400 EUR Implementing Authority European Commission Final date

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE (Preparing the Gujarat Solar and Smart Grid Development Investment Program)

PROJECT PREPARATORY TECHNICAL ASSISTANCE (Preparing the Gujarat Solar and Smart Grid Development Investment Program) PROJECT PREPARATORY TECHNICAL ASSISTANCE (Preparing the Gujarat Solar and Smart Grid Development Investment Program) 1. A project preparatory technical assistance (PPTA) for $700,000 in grant funds is

More information

Earthquake 2005 Recovery and Reconstruction

Earthquake 2005 Recovery and Reconstruction Earthquake 2005 Recovery and Reconstruction 2 Earthquake 8 Oct 2005 Nine Districts 1. MANSHERA 2. BATAGRAM 3. SHANGLA 4. ABBOTTABAD 5. KOHISTAN Epicentre 6. MUZAFFARABAD 7. NELUM 8. BAGH 9. RAWALAKOT Depth:

More information

RESTRUCTURING PAPER ON A

RESTRUCTURING PAPER ON A Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank RESTRUCTURING PAPER ON A Report No: 63424-AR PROPOSED PROJECT

More information

XII. CGIF Environmental and Social Safeguards Policy and Framework 1

XII. CGIF Environmental and Social Safeguards Policy and Framework 1 A. Policy XII. CGIF Environmental and Social Safeguards Policy and Framework 1 1. Credit Guarantee and Investment Facility (CGIF), a trust fund of the Asian Development Bank (ADB) was established to promote

More information

Responding to the Earthquake in Nepal. Avani Dixit, Disaster Risk Management Specialist Jyoti Pandey, Social Protection Analyst

Responding to the Earthquake in Nepal. Avani Dixit, Disaster Risk Management Specialist Jyoti Pandey, Social Protection Analyst Responding to the Earthquake in Nepal Avani Dixit, Disaster Risk Management Specialist Jyoti Pandey, Social Protection Analyst Earthquake and the response needs Housing reconstruction project: Grant &

More information

Periodic Financing Request Report. India: Kolkata Environmental Improvement Investment Program (Tranche 2)

Periodic Financing Request Report. India: Kolkata Environmental Improvement Investment Program (Tranche 2) Periodic Financing Request Report Project Number: 42266-025 MFF Number: 0075 August 2016 India: Kolkata Environmental Improvement Investment Program (Tranche 2) Distribution of this document is restricted

More information

Initial Environmental Examination

Initial Environmental Examination Initial Environmental Examination June 2017 IND: Green Energy Corridor and Grid Strengthening Project (320 kv VSC-HVDC power transmission lines between Pugalur, Tamil Nadu and North Trichur, Kerala) Annexures

More information

TURKEY ISTANBUL MUNICIPAL INFRASTRUCTURE PROJECT (RESTRUCTURING) PROJECT PAPER

TURKEY ISTANBUL MUNICIPAL INFRASTRUCTURE PROJECT (RESTRUCTURING) PROJECT PAPER Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized TURKEY ISTANBUL MUNICIPAL INFRASTRUCTURE PROJECT (RESTRUCTURING) PROJECT PAPER Responsible

More information

NORTH EASTERN REGION CAPITAL CITIES DEVELOPMENT INVESTMENT PROGRAMME (LOAN NO 2528-IND & 2834-IND)

NORTH EASTERN REGION CAPITAL CITIES DEVELOPMENT INVESTMENT PROGRAMME (LOAN NO 2528-IND & 2834-IND) NORTH EASTERN REGION CAPITAL CITIES DEVELOPMENT INVESTMENT PROGRAMME (LOAN NO 2528-IND & 2834-IND) PROJECT IMPLEMENTATION STATUS FOR SHILLONG-MEGHALAYA (7 th May 2012) TRANCHE I STATUS A. CONSTRUCTING

More information

Nepal: Road Connectivity Sector I Project

Nepal: Road Connectivity Sector I Project Validation Report October 2017 Nepal: Road Connectivity Sector I Project Reference Number: PVR-523 Project Number: 37266-032 Grant Number: 0051 ABBREVIATIONS ADB Asian Development Bank DOR Department of

More information

Section 3.06 is deleted and the following is substituted therefor:

Section 3.06 is deleted and the following is substituted therefor: 2 (c) Section 3.03 is deleted and the following is substituted therefor: Commitment Charge; Credit; Maturity Premium. (a) The Borrower shall pay a commitment charge on the unwithdrawn amount of the Loan

More information

Community Managed Revolving Fund (Sustainable mechanism of microfinance practices to disadvantaged community)

Community Managed Revolving Fund (Sustainable mechanism of microfinance practices to disadvantaged community) Community Managed Revolving Fund (Sustainable mechanism of microfinance practices to disadvantaged community) A paper presented in Micro Finance Summit 2008 New departure in expanding the outreach of Micro-finance

More information

UNITED NATIONS ASSISTANCE MISSION IN SOMALIA UNSOM

UNITED NATIONS ASSISTANCE MISSION IN SOMALIA UNSOM CALL FOR PROPOSALS Reinsertion Projects for Disengaged Al Shabab combatants in dedicated transition facilities in Mogadishu, Beletweyne, Baidoa, Kismayo SOMALIA Introduction In 2012 the Federal Government

More information

Multitranche Financing Facility India: Rural Road Sector II Investment Program (Project 1)

Multitranche Financing Facility India: Rural Road Sector II Investment Program (Project 1) Validation Report Reference Number: PVR-326 Project Number: 37066 Loan Number: 2248 October 2014 Multitranche Financing Facility India: Rural Road Sector II Investment Program (Project 1) Independent Evaluation

More information

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: AB4291 Project Name. Wenchuan Earthquake Recovery Project Region

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: AB4291 Project Name. Wenchuan Earthquake Recovery Project Region Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: AB4291 Project Name Wenchuan

More information

PROJECT AGREEMENT. (Hebei Energy Efficiency Improvement and Emission Reduction Project) between ASIAN DEVELOPMENT BANK. and

PROJECT AGREEMENT. (Hebei Energy Efficiency Improvement and Emission Reduction Project) between ASIAN DEVELOPMENT BANK. and LOAN NUMBER 2835-PRC PROJECT AGREEMENT (Hebei Energy Efficiency Improvement and Emission Reduction Project) between ASIAN DEVELOPMENT BANK and HEBEI PROVINCIAL GOVERNMENT DATED 6 MARCH 2012 PRC 44012 PROJECT

More information

Metrolinx-City of Toronto-Toronto Transit Commission Master Agreement for Light Rail Transit Projects

Metrolinx-City of Toronto-Toronto Transit Commission Master Agreement for Light Rail Transit Projects STAFF REPORT ACTION REQUIRED Metrolinx-City of Toronto-Toronto Transit Commission Master Agreement for Light Rail Transit Projects Date: October 23, 2012 To: From: Wards: City Council City Manager All

More information

LOAN AGREEMENT (Special Operations) LOAN AGREEMENT dated 17 January 2013 between KINGDOM OF CAMBODIA ( Borrower ) and ASIAN DEVELOPMENT BANK ( ADB ).

LOAN AGREEMENT (Special Operations) LOAN AGREEMENT dated 17 January 2013 between KINGDOM OF CAMBODIA ( Borrower ) and ASIAN DEVELOPMENT BANK ( ADB ). LOAN AGREEMENT (Special Operations) LOAN AGREEMENT dated 17 January 2013 between KINGDOM OF CAMBODIA ( Borrower ) and ASIAN DEVELOPMENT BANK ( ADB ). WHEREAS (A) the Borrower has applied to ADB for a loan

More information

AFG: Transport Network Development Investment Program, Tranche 1 (Bagramy Sapary Road Project)

AFG: Transport Network Development Investment Program, Tranche 1 (Bagramy Sapary Road Project) Transport Network Development Investment Program Resettlement Planning Document Land Acquisition & Resettlement Plan Document Status: Final December 2014 AFG: Transport Network Development Investment Program,

More information

REPUBLIC OF TURKEY FOURTH EXPORT FINANCE INTERMEDIARY LOAN (EFIL IV) (LOAN NUMBER )

REPUBLIC OF TURKEY FOURTH EXPORT FINANCE INTERMEDIARY LOAN (EFIL IV) (LOAN NUMBER ) REPUBLIC OF TURKEY FOURTH EXPORT FINANCE INTERMEDIARY LOAN (EFIL IV) (LOAN NUMBER ) ENVIRONMENTAL FRAMEWORK FOR PARTICIPATING FINANCIAL INSTITUTIONS JANUARY, 2011 III. ENVIRONMENTAL REVIEW PROCEDURES Background

More information

Demand for Environmental Quality in Kathmandu, Nepal: Evidence from Knowledge, Attitude, Behavior and Choice Experiment Survey

Demand for Environmental Quality in Kathmandu, Nepal: Evidence from Knowledge, Attitude, Behavior and Choice Experiment Survey Demand for Environmental Quality in Kathmandu, Nepal: Evidence from Knowledge, Attitude, Behavior and Choice Experiment Survey Hari Katuwal University of New Mexico June 12, 2012 Aesthetic, Cultural, Religious

More information

LAND ACQUISITION AND RESETTLEMENT COMPENSATION POLICY FRAMEWORK AND IMPLEMENTING GUIDELINES

LAND ACQUISITION AND RESETTLEMENT COMPENSATION POLICY FRAMEWORK AND IMPLEMENTING GUIDELINES LAND ACQUISITION AND RESETTLEMENT COMPENSATION POLICY FRAMEWORK AND IMPLEMENTING GUIDELINES Supplementary Appendix to the Report Recommendation of the President to the Board of Directors on the HEALTH

More information

People s Republic of China: Emergency Assistance for Wenchuan Earthquake Reconstruction Project

People s Republic of China: Emergency Assistance for Wenchuan Earthquake Reconstruction Project Validation Report Reference Number: PVR-462 Project Number: 42496-013 Loan Number: 2508 December 2016 People s Republic of China: Emergency Assistance for Wenchuan Earthquake Reconstruction Project Independent

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Date ISDS Prepared/Updated: 14-Jul-2014

More information

ECONOMIC ANALYSIS. A. Introduction and Macroeconomic Context

ECONOMIC ANALYSIS. A. Introduction and Macroeconomic Context Dhaka Water Supply Network Improvement Project (RRP BAN 47254-003) ECONOMIC ANALYSIS A. Introduction and Macroeconomic Context 1. Economic growth in Bangladesh averaged an very healthy 6.1% during FY2006

More information

Agenda item 12: Consideration of accreditation proposals

Agenda item 12: Consideration of accreditation proposals Page 5 (h) (j) (k) (l) (m) (n) Also requests the Appointment Committee to provide additional recommendations on the salary levels for consideration by the Board at its eleventh meeting; Decides that the

More information

Strategy beyond Twelfth Five Year Plan - Achievement of Sustainable Development Goals

Strategy beyond Twelfth Five Year Plan - Achievement of Sustainable Development Goals Strategy beyond Twelfth Five Year Plan - Achievement of Sustainable Development Goals Demographic Indicators Indicator Himachal Pradesh (Census 2011) All India Population (million) 6.8 1210 Decennial Growth

More information

Final Evaluation & Outcome Assessment of Promotion of Sustainable Agriculture for Nutrition and Food Security (POSAN FS) Project

Final Evaluation & Outcome Assessment of Promotion of Sustainable Agriculture for Nutrition and Food Security (POSAN FS) Project Terms of Reference (TOR) For Final Evaluation & Outcome Assessment of Promotion of Sustainable Agriculture for Nutrition and Food Security (POSAN FS) Project Re-circulation date: 11/01/ Closing date: 18/01/

More information

Charges schemes. New connections and developer services charges scheme 2019/2020 Page 1 of 64

Charges schemes. New connections and developer services charges scheme 2019/2020 Page 1 of 64 s schemes Page 1 of 64 United Utilities Water Limited has published four charges schemes for 2019/2020 charging year. They include the charges to be paid for services provided by us in the course of carrying

More information

Integrated Safeguards Data Sheet Identification / Concept Stage (ISDS)

Integrated Safeguards Data Sheet Identification / Concept Stage (ISDS) Public Disclosure Authorized The World Bank Public Disclosure Authorized Public Disclosure Authorized Integrated Safeguards Data Sheet Identification / Concept Stage (ISDS) Concept Stage Date ISDS Prepared/Updated:

More information

AC workshop on the M&E of adaptation Nadi, Fiji, 9-11 September 2013

AC workshop on the M&E of adaptation Nadi, Fiji, 9-11 September 2013 AC workshop on the M&E of adaptation Nadi, Fiji, 9-11 September 2013 Input by Chakra Pani Sharma, Under Secretary, Environment Management Section, Ministry of Federal Affair and Local Development, Nepal

More information

PAK: National Motorway M-4 Gojra Shorkot Khanewal Section Project

PAK: National Motorway M-4 Gojra Shorkot Khanewal Section Project Internal Monitoring Report September 2016 PAK: National Motorway M-4 Gojra Shorkot Khanewal Section Project Prepared by National Highway Authority of Ministry of Communications for the Islamic Republic

More information

(c) Section 3.07 is deleted and the following is substituted therefor:

(c) Section 3.07 is deleted and the following is substituted therefor: 2 outstanding Loan on which a higher Fixed Spread is applicable. The amount of the Rebate shall be determined by multiplying (i) the difference between the Fixed Spread applicable to the outstanding Loan

More information

HPEC (Ahluwalia) Report 2011

HPEC (Ahluwalia) Report 2011 HPEC (Ahluwalia) Report 2011 Highlights and Recommendations October 11, 2012 Goa First Regional Knowledge Dissemination Workshop Bhopal, Madhya Pradesh Urban Share of Total Population in 2011 (per cent)

More information

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project Name PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Bhutan Second Rural Access

More information

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Dec ,000, Original Commitment 400,000,

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Dec ,000, Original Commitment 400,000, Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0020001 Public Disclosure Authorized Project ID P100580 Country Ukraine Project Name ROADS & SAFETY IMPROVEMENT

More information

Republic of the Maldives: Preparing Business Strategy for Port Development

Republic of the Maldives: Preparing Business Strategy for Port Development Technical Assistance Report Project Number: 47283 Capacity Development Technical Assistance (CDTA) November 2013 Republic of the Maldives: Preparing Business Strategy for Port Development The views expressed

More information

Planning, Budgeting and Financing

Planning, Budgeting and Financing English Version Planning, Budgeting and Financing Post-Disaster Recovery and Reconstruction Activities in Khammouane Province, Lao PDR Developed under the Khammouane Development Project (KDP), Implemented

More information

Prepared by the Department of Roads for the Ministry of Finance and the Asian Development Bank.

Prepared by the Department of Roads for the Ministry of Finance and the Asian Development Bank. Social Monitoring Report Semiannual Report December 2016 NEP: SASEC Road Connectivity Prepared by the Department of Roads for the Ministry of Finance and the Asian Development Bank. This social monitoring

More information

OFFICIAL DOCUMENTS. Loan Agreement

OFFICIAL DOCUMENTS. Loan Agreement Public Disclosure Authorized OFFICIAL DOCUMENTS LOAN NUMBER 8796-IQ Public Disclosure Authorized Loan Agreement (Baghdad Water Supply and Sewerage Improvement Project) between REPUBLIC OF IRAQ Public Disclosure

More information

MITIGATING THE IMPACT OF THE FINANCIAL CRISIS ON THE URBAN POOR USING RESULTS-BASED FINANCING SUCH AS OUTPUT-BASED AID FOR SLUM UPGRADING

MITIGATING THE IMPACT OF THE FINANCIAL CRISIS ON THE URBAN POOR USING RESULTS-BASED FINANCING SUCH AS OUTPUT-BASED AID FOR SLUM UPGRADING INFRA GUIDANCE NOTES THE WORLD BANK, WASHINGTON, DC May 2009 IN-1 MITIGATING THE IMPACT OF THE FINANCIAL CRISIS ON THE URBAN POOR USING RESULTS-BASED FINANCING SUCH AS OUTPUT-BASED AID FOR SLUM UPGRADING

More information

MAIN FINDINGS OF THE DECENT WORK COUNTRY PROFILE ZAMBIA. 31 January 2013 Launch of the Decent Work Country Profile

MAIN FINDINGS OF THE DECENT WORK COUNTRY PROFILE ZAMBIA. 31 January 2013 Launch of the Decent Work Country Profile MAIN FINDINGS OF THE DECENT WORK COUNTRY PROFILE ZAMBIA Griffin Nyirongo Griffin Nyirongo 31 January 2013 Launch of the Decent Work Country Profile OUTLINE 1. Introduction What is decent work and DW Profile

More information

The Performance of Palestinian Local Governments

The Performance of Palestinian Local Governments The Performance of Palestinian Local Governments An Assessment of Service Delivery Outcomes and Performance Drivers in the West Bank and Gaza Main findings and Policy Recommendations National Dissemination

More information

Report and Recommendation of the President to the Board of Directors. Proposed Loan and Grant Nepal: Subregional Transport Enhancement Project

Report and Recommendation of the President to the Board of Directors. Proposed Loan and Grant Nepal: Subregional Transport Enhancement Project Report and Recommendation of the President to the Board of Directors Project Number: 44143 October 2010 Proposed Loan and Grant Nepal: Subregional Transport Enhancement Project CURRENCY EQUIVALENTS (as

More information

ACHIEVEMENT OF TECHNICAL ASSISTANCE OUTCOMES

ACHIEVEMENT OF TECHNICAL ASSISTANCE OUTCOMES Timor-Leste: CPS 2011 2015 Final Review Validation, Linked Document 7 ACHIEVEMENT OF TECHNICAL ASSISTANCE OUTCOMES Road Transport TA 7698 - Supporting Road Network Development Outcome: The Ministry of

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK TAR:NEP 37266 TECHNICAL ASSISTANCE (Financed by the Japan Special Fund) TO THE KINGDOM OF NEPAL FOR PREPARING THE TRANSPORT CONNECTIVITY SECTOR PROJECT June 2004 CURRENCY EQUIVALENTS

More information

Welcome to Presentation of Twelfth Five Year Plan and Annual Plan Proposal Madhya Pradesh. May 11, 2012

Welcome to Presentation of Twelfth Five Year Plan and Annual Plan Proposal Madhya Pradesh. May 11, 2012 Welcome to Presentation of Twelfth Five Year Plan and Annual Plan Proposal Madhya Pradesh May 11, 2012 1 ACHIEVEMENTS OF ELEVENTH PLAN (ECONOMY) Targets and Achievement Sector Target for Growth Expected

More information

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE. I. Basic Information Date prepared/updated: 12/13/2006

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE. I. Basic Information Date prepared/updated: 12/13/2006 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized I. Basic Information Date prepared/updated: 12/13/2006 INTEGRATED SAFEGUARDS DATASHEET

More information

Islamic Republic of Pakistan: Karachi Bus Rapid Transit Project

Islamic Republic of Pakistan: Karachi Bus Rapid Transit Project Project Design Advance Project Number: 47279-003 September 2016 Islamic Republic of Pakistan: Karachi Bus Rapid Transit Project This document is being disclosed to the public in accordance with ADB's Public

More information

AZERBAIJAN MOTORWAY IMPROVEMENT AND DEVELOPMENT Baku Shamakhi Road Widening

AZERBAIJAN MOTORWAY IMPROVEMENT AND DEVELOPMENT Baku Shamakhi Road Widening SFG1532 Public Disclosure Authorized AZERBAIJAN REPUBLIC Public Disclosure Authorized Public Disclosure Authorized MINISTRY OF TRANSPORT AZERROADSERVICE OPEN JOINT STOCK COMPANY AZERBAIJAN MOTORWAY IMPROVEMENT

More information

Republic of Indonesia: Aligning Asian Development Bank and Country Systems for Improved Project Performance

Republic of Indonesia: Aligning Asian Development Bank and Country Systems for Improved Project Performance Technical Assistance Report Project Number: 47287-001 Capacity Development Technical Assistance (CDTA) December 2013 Republic of Indonesia: Aligning Asian Development Bank and Country Systems for Improved

More information

Implementation of the SDGs in Nepal: Status and Challenges

Implementation of the SDGs in Nepal: Status and Challenges Implementation of the SDGs in Nepal: Status and Challenges South Asia Forum on the Sustainable Development Goals, 4-5 October 2018, India Habitat Centre, New Delhi Khomraj Koirala Joint Secretary National

More information

Report and Recommendation of the President to the Board of Directors. Proposed Loan Nepal: Urban Water Supply and Sanitation (Sector) Project

Report and Recommendation of the President to the Board of Directors. Proposed Loan Nepal: Urban Water Supply and Sanitation (Sector) Project Report and Recommendation of the President to the Board of Directors Project Number: 35173-015 September 2018 Proposed Loan Nepal: Urban Water Supply and Sanitation (Sector) Project Distribution of this

More information