IMPORTANT FACTS ABOUT PUBLIC PROJECTS UNDER IOWA LAW

Size: px
Start display at page:

Download "IMPORTANT FACTS ABOUT PUBLIC PROJECTS UNDER IOWA LAW"

Transcription

1 IMPORTANT FACTS ABOUT PUBLIC PROJECTS UNDER IOWA LAW Can payments be withheld for warranty items? Industry professionals need to help owners understand the difference between warranty items and punch list items; money cannot be retained for warranty items. Punch list items are those items that have yet to be completed, need touch-up, or did not comply with the contract documents when originally done. Warranty items, on the other hand, are those items that have developed problems after being installed. As for punch list items, only a reasonable amount can be retained, not the entire outstanding balance. What is the maximum allowable retainage on public projects? This issue of retainage on public projects is governed by the provisions of Iowa Code Chapter 573 (except for the Board of Regents, which is governed by Chapter 262). A public owner shall hold up to five percent of each progress payment until 30 days after completion and final acceptance. Normally, completion and final acceptance is acknowledged in a resolution passed at a public meeting of the public entity, such as a school board or city council. The reason they have to wait 30 days is because this is the cutoff time for claims to be filed by subcontractors and suppliers. At the end of 30 days, the public owner holds twice the amount of any claims which have been filed with it and releases the balance, if any, to the general contractor. The general contractor may bond off the claims separately from the bond provided at the beginning of the project, which would then allow the public owner to release any retainage held pursuant to the statutory requirement for claims. As for projects let by the Board of Regents, they can, if they choose, pay the entire amount of each progress payment until 95% completion, then hold the remaining 5% as above. It should be noted that the retainage requirement is at the discretion of the public owner. It is up to five percent, so they could choose not to hold retainage if they so desired, or an amount less than five percent, but once they choose to hold retainage, they are obligated not to release it until 30 days after completion and final acceptance. The other point is they cannot hold more than five percent, even if there are more claims than retainage. A general contractor cannot hold more than five percent against a subcontractor or supplier. Are lien wavers required on public projects? On public projects, lien waivers are not required, and just to add to the paper work everyone has to attend to. A mechanic s lien cannot be filed against a public project. If a claim is filed under Iowa Code Chapter 573, the owner is projected by the retainage (up to 5% of the contract amount) and the payment bond that is mandatory on public projects over $25,000. Can a public entity reserve the right not to award to the lowest responsible bidder? A public entity must award a contract for construction of a public improvement to the responsible bidder with the lowest responsive bid. This cannot be changed by adding language in the information to bidders which attempts to reserve the right to award a contract in the best interest of the public entity.

2 Can a construction manager be retained without the need for public bidding? Yes, as a professional service provider a CM can be retained without the necessity competitive bid. However, this does not change the requirement that all contracts for construction in excess of $25,000 are subject to Iowa s competitive bidding laws. Are LOL clauses for contractors prudent? Owners and design professionals should not attempt to limit design liability as to the general contractor through the use of limited liability clauses (LOL) or similar devices. This issue should be between the owner and design professional only. Is the design-build method of construction legal under Iowa law? No, under current Iowa law requiring public projects to be competitively bid, public entities are prohibited from utilizing the design-build project delivery system.

3 The following are commonly asked questions regarding public bidding in Iowa. This information is designed to serve as a guide to contractors, public officials and letting authorities. Q. What bid must a public authority accept? A. Public improvements, other than highways, must be let to the lowest responsible bidder. Highway letting authorities may take into account the price of the bid, financial ability, experience and equipment. Q. What does lowest responsible bidder mean? A. It does not mean the lowest dollar figure. The amount of the bid is only one factor in determining the winning bid. A public authority has wide discretion in determining who is a responsible bidder, but it must have a valid reason for determining whether a bidder is responsible or not responsible. Q. When is the determination made that a bidder is responsible? A. Generally, that decision is made after the bid opening, but before the contract is awarded by the public authority. There is no state law requiring that this determination be made before bids are solicited or opened by the public authority. Thus, just because a potential bidder is sent a bid proposal by a public authority, does not mean the public authority has made a determination that potential bidder is qualified to bid or is a responsible bidder. However, bid proposals may contain requirements, such as net worth or bonding capacity, which are such that a potential bidder is precluded from submitting a bid because of its inability to satisfy those requirements. Q. Under what circumstances may a public authority reject bids? A. Generally, a public authority may reject all bids for any reason, including the fact the bids were all above its estimate of the cost of the project. It may reject any bid not conforming to the request for bids. Q. If a public authority rejects all bids, must it relet the bids? A. Highway letting authorities (state or county) may reject all bids and let the award to a private contractor or construct the project itself using day labor, but the cost of the project may not exceed the lowest bid received. It need not relet the bid. Other public authorities may reject all bids, but must relet the project. It may not reject all bids and negotiate a price with a private contractor. Q. Can a public authority give a preference to local contractors? A. A public authority (state or local) must give a preference to an in-state contractor equal to any preference give by the state in which the out-of-state contractor comes from.

4 A local public authority (city, county, school district) may not give a preference to a local contractor over another in-state contractor. Q. If I make a mistake in my bid, can I withdraw it? A. A bidder has an absolute right to withdraw a bid for any reason prior to the bid opening. After the bid opening, there may be a penalty, often in the amount of the bid bond. Whether the public authority allows a bidder to withdraw a bid after opening without penalty depends on whether the mistake was merely a clerical mistake (i.e. someone miscalculated or left out a critical component) which is obvious on the face of the bid and whether the public authority has changed its position because of the bid. Generally the earlier the attempted withdrawal, the more likely the chances it can be done without penalty. Q. What types of construction services don t need to be bid? A. Generally, professional services such as architects, engineers and construction managers on a project need not be bid. Q. May a public authority award a project to a bid which does not conform to the request for bids? A. No. The public authority may not award a project to a bidder whose bid does not conform to the request for bids, not may it negotiate with that bidder to change its bid to be in conformance with the request. Q. What are my options if I am the low bidder but I am not awarded the bid or I am the second low bidder, but I don t think the low bidder is qualified or made a bid in conformance with the request for bids? A. Like withdrawing a bid, the quicker a protest is made to the public authority about its award of the bid, the greater the chances are of successfully convincing it to set aside the bid, if your reason is valid. If the public authority has made a mistake in awarding the bid, it may reject all bids and relet the project or award the bid to the lowest responsible bidder who has submitted a valid bid. Q. What are my options if the public authority denies my protest and awards the bid to another? A. You may sue in district court (or if a state agency is involved, through the state s administrative appeals process), but your damages are generally limited to the cost of preparing your bid. You may also sue to enjoin the award of the bid, but you must act extremely quickly in this case, before the project is started. Furthermore, generally only a taxpayer of the public entity awarding the bid has the right to sue to enjoin the letting of the bid. Being the losing bidder does not give a contractor standing to

5 bring such an action, unless the contractor is a taxpaying entity of that public authority. CAVEAT: These questions and answers are designed to give the contractor a thumbnail sketch of common issues arising regarding state and local bidding laws. They do not address federal procurement requirements for federal projects because of the complexity of those rules and regulations. Also the exact answer to any legal question will always depend on the specific facts.

11/12/2015. School Construction A Refresher PUBLIC CONSTRUCTION ISSUES INTRODUCTIONS TODAY S PRESENTERS. November 12, 2015

11/12/2015. School Construction A Refresher PUBLIC CONSTRUCTION ISSUES INTRODUCTIONS TODAY S PRESENTERS. November 12, 2015 School Construction A Refresher November 12, 2015 2015 MASBO Fall Conference DoubleTree Park Place Minneapolis Minnesota Mark Azman Shamus O Meara O Meara, Leer, Wagner & Kohl, P.A. O Meara, Leer, Wagner

More information

Chapter 3.24 PURCHASING PROCEDURES

Chapter 3.24 PURCHASING PROCEDURES Page 1/8 Chapter 3.24 PURCHASING PROCEDURES Sections: 3.24.003 Definitions. 3.24.005 Types of contracts. 3.24.010 Service contracts. 3.24.020 Guidelines for service contracts. 3.24.030 Repealed. 3.24.040

More information

GENERAL CONDITIONS AND INSTRUCTIONS TO BIDDERS FOR STATEWIDE CONTRACTS FOR SERVICES

GENERAL CONDITIONS AND INSTRUCTIONS TO BIDDERS FOR STATEWIDE CONTRACTS FOR SERVICES Department of General Services GSPUR-11D Rev. 1/17/03 GENERAL CONDITIONS AND INSTRUCTIONS TO BIDDERS FOR STATEWIDE CONTRACTS FOR SERVICES 1. SUBMISSIONS OF BIDS: a. Bids are requested for the item(s) described

More information

TEXAS MECHANIC S LIEN LAW

TEXAS MECHANIC S LIEN LAW TEXAS MECHANIC S LIEN LAW 2018-2019 Go to: Texas Mechanics Lien Forms More Info: www.nationallienlaw.com Section Contents Pre-lien Notice(s) Name of Notice Who Must Use This Notice When How to Serve Verified

More information

COUNSEL S CORNER. Iowa Code Chapter 26 Iowa Construction Bidding Procedures Act. By Danielle Jess Haindfield Ahlers & Cooney, P.C.

COUNSEL S CORNER. Iowa Code Chapter 26 Iowa Construction Bidding Procedures Act. By Danielle Jess Haindfield Ahlers & Cooney, P.C. COUNSEL S CORNER Iowa Code Chapter 26 Iowa Construction Bidding Procedures Act By Danielle Jess Haindfield Ahlers & Cooney, P.C. New Competitive Bidding Law passed by the Iowa legislature in 2006. Law

More information

PROCUREMENT PROCEDURES

PROCUREMENT PROCEDURES PROCUREMENT PROCEDURES BIDS Board 5-27-08 BP 3311 The District shall purchase equipment, supplies and services using competitive bidding when required by law and in accordance with statutory requirements

More information

Webinar: Making the Right Choices in Government Contracting Part 3

Webinar: Making the Right Choices in Government Contracting Part 3 Public Contracting Institute LLC Webinar: Making the Right Choices in Government Contracting Part 3 Presented by Richard D. Lieberman, FAR Consultant, Website: www.richarddlieberman.com. Email rliebermanconsultant@gmail.com.

More information

DOING BUSINESS WITH MUSKEGON COUNTY

DOING BUSINESS WITH MUSKEGON COUNTY DOING BUSINESS WITH MUSKEGON COUNTY Purchasing is a division of the Finance and Management Services Department. Its responsibilities include purchasing the necessary supplies, services, and equipment at

More information

OKEECHOBEE COUNTY PROCUREMENT POLICY

OKEECHOBEE COUNTY PROCUREMENT POLICY OKEECHOBEE COUNTY PROCUREMENT POLICY I. SCOPE Purchasing authority is vested in the Office of the County Administrator, subject to limitations prescribed herein. This policy applies to expenditure(s) of

More information

SUMMARY OF MECHANICS LIEN LAW FOR TEXAS. With Changes for 2012

SUMMARY OF MECHANICS LIEN LAW FOR TEXAS. With Changes for 2012 SUMMARY OF MECHANICS LIEN LAW FOR TEXAS With Changes for 2012 Section Contents Pre-lien Notice(s) Name of Notice Who Must Use This Notice When How to Serve Verified or notarized? Section Contents Mechanic

More information

ARLINGTON COUNTY PURCHASING RESOLUTION

ARLINGTON COUNTY PURCHASING RESOLUTION ARLINGTON COUNTY PURCHASING RESOLUTION ADOPTED: DECEMBER 1982 AMENDED: JUNE 1983 AMENDED: OCTOBER 1984 AMENDED: JUNE 1985 AMENDED: JULY 1986 AMENDED: JUNE 1987 AMENDED: JANUARY 1990 AMENDED: JULY 1991

More information

BID FORM FOR WEST GEAUGA LOCAL SCHOOLS DISTRICT MIDDLE SCHOOL SECURITY ENTRANCE 8611 CEDAR ROAD CHESTERLAND, OHIO FOR

BID FORM FOR WEST GEAUGA LOCAL SCHOOLS DISTRICT MIDDLE SCHOOL SECURITY ENTRANCE 8611 CEDAR ROAD CHESTERLAND, OHIO FOR BID FORM FOR WEST GEAUGA LOCAL SCHOOLS DISTRICT MIDDLE SCHOOL SECURITY ENTRANCE 8611 CEDAR ROAD CHESTERLAND, OHIO 44026 FOR THE WEST GEAUGA LOCAL SCHOOLS DISTRICT BOARD OF EDUCATION BIDS DUE AT 12:00 P.M.

More information

DISADVANTAGED BUSINESS ENTERPRISE (DBE) SUPPLEMENTAL SPECIFICATION INSTRUCTIONS TO BIDDERS PRE- AWARD REQUIREMENTS

DISADVANTAGED BUSINESS ENTERPRISE (DBE) SUPPLEMENTAL SPECIFICATION INSTRUCTIONS TO BIDDERS PRE- AWARD REQUIREMENTS May 2, 2014 DISADVANTAGED BUSINESS ENTERPRISE (DBE) SUPPLEMENTAL SPECIFICATION It is the policy of the South Carolina Department of Transportation (SCDOT) to ensure nondiscrimination in the award and administration

More information

CITY OF TACOMA SMALL WORKS ROSTER PROGRAM FOR PUBLIC WORKS AND IMPROVEMENTS CONTRACTS

CITY OF TACOMA SMALL WORKS ROSTER PROGRAM FOR PUBLIC WORKS AND IMPROVEMENTS CONTRACTS CITY OF TACOMA SMALL WORKS ROSTER PROGRAM FOR PUBLIC WORKS AND IMPROVEMENTS CONTRACTS Table of Contents Page(s) I. GENERAL...2 A. Objective...2 B. Authority...2 C. Definitions...2 & 3 II. SCOPE OF PROGRAM...3

More information

Avoiding Common Payment Pitfalls for Subcontractors: A Primer on Federal Contracting Payment Remedies

Avoiding Common Payment Pitfalls for Subcontractors: A Primer on Federal Contracting Payment Remedies Avoiding Common Payment Pitfalls for Subcontractors: A Primer on Federal Contracting Payment Remedies Shoshana E. Rothman BrigliaMcLaughlin, PLLC April 2017 Seminar Goals: 1. Understand key contract clauses

More information

Public Works Contracts in Missouri Presented March 8, 2011 by Joe Lauber Missouri City Clerks and Finance Officers Association 2011 Spring Institute

Public Works Contracts in Missouri Presented March 8, 2011 by Joe Lauber Missouri City Clerks and Finance Officers Association 2011 Spring Institute Public Works Contracts in Missouri Presented March 8, 2011 by Joe Lauber Missouri City Clerks and Finance Officers Association 2011 Spring Institute Serving those who serve the public Introduction/Background

More information

MANUAL OF PROCEDURE. Small Local Business Enterprises Initiative Incentives

MANUAL OF PROCEDURE. Small Local Business Enterprises Initiative Incentives MANUAL OF PROCEDURE PROCEDURE NUMBER: 6550 PAGE 1 of 5 PROCEDURE TITLE: Small Local Business Enterprises Initiative Incentives STATUTORY REFERENCE: FLORIDA STATUTES 1001.64, 287.055, 287.057, 288.703 (1)

More information

In accordance with 61 O.S. 108 and 115, a sworn statement shall accompany any competitive bid submitted for a public construction contract.

In accordance with 61 O.S. 108 and 115, a sworn statement shall accompany any competitive bid submitted for a public construction contract. State of Oklahoma Capital Assets Management Construction and Properties Bid Affidavits In accordance with 61 O.S. 108 and 115, a sworn statement shall accompany any competitive bid submitted for a public

More information

Public Owners Guide to Legal Issues on the Bidding and Award of Construction Contracts in Iowa

Public Owners Guide to Legal Issues on the Bidding and Award of Construction Contracts in Iowa Public Owners Guide to Legal Issues on the Bidding and Award of Construction Contracts in Iowa Volume I, Edition II Published April 2006 Updated January 2009 Public Owners Guide to Legal Issues on the

More information

REQUEST FOR BIDS MINOR REPAIRS

REQUEST FOR BIDS MINOR REPAIRS REQUEST FOR BIDS MINOR REPAIRS SOLICITATION #A10-01-17-3415 SEQUOYAH COUNTY Bids Due: February 16, 2017 @ 5:00 P.M. Housing Authority of the Cherokee Nation P.O. Box 1007 Tahlequah, OK 74465 (918) 456-5482

More information

Discover How Thousands Have Taken Control Of Their Future Through Private Lending!

Discover How Thousands Have Taken Control Of Their Future Through Private Lending! Investments Secured by Real Estate! Discover How Thousands Have Taken Control Of Their Future Through Private Lending! Here s What We Do: We are a multi-service Company who buys, renovates, sells, and

More information

Construction Contracting. Agents and Vendors. Contractual Relationships. Agents and Vendors. Agents and Vendors. Outline

Construction Contracting. Agents and Vendors. Contractual Relationships. Agents and Vendors. Agents and Vendors. Outline Construction Contracting Institute for Facilities Management Outline 1. Contractual Relationships 2. Delivery Approaches 3. Bidding & Award Don Guckert The University of Iowa Agents and Vendors Contractual

More information

Alameda County Transportation Commission SAMPLE PROGRAM COMPLIANCE LANGUAGE: CONSTRUCTION

Alameda County Transportation Commission SAMPLE PROGRAM COMPLIANCE LANGUAGE: CONSTRUCTION SAMPLE PROGRAM COMPLIANCE LANGUAGE: CONSTRUCTION For Alameda CTC-funded projects subject to the Local Business Contract Equity (LBCE) Program Note to Project Sponsor: Be sure that your legal staff reviews

More information

CHARLOTTE PUBLIC SCHOOLS CONSTRUCTION MANAGEMENT SERVICES REQUEST FOR PROPOSALS ("RFP")

CHARLOTTE PUBLIC SCHOOLS CONSTRUCTION MANAGEMENT SERVICES REQUEST FOR PROPOSALS (RFP) CHARLOTTE PUBLIC SCHOOLS CONSTRUCTION MANAGEMENT SERVICES REQUEST FOR PROPOSALS ("RFP") May 12, 2017 CHARLOTTE PUBLIC SCHOOLS A. Instructions REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES PART

More information

PROCUREMENT POLICY SAN MATEO COUNTY TRANSIT DISTRICT

PROCUREMENT POLICY SAN MATEO COUNTY TRANSIT DISTRICT ATTACHMENT A PROCUREMENT POLICY SAN MATEO COUNTY TRANSIT DISTRICT The San Mateo County Transit District ( District ) is organized and established pursuant to the San Mateo County Transit District Act,

More information

In accordance with 61 O.S. 108 and 115, a sworn statement shall accompany any competitive bid submitted for a public construction contract.

In accordance with 61 O.S. 108 and 115, a sworn statement shall accompany any competitive bid submitted for a public construction contract. State of Oklahoma Capital Assets Management Construction and Properties Bid Affidavits In accordance with 61 O.S. 108 and 115, a sworn statement shall accompany any competitive bid submitted for a public

More information

FEDERAL GRANT ADMINISTRATION PROCUREMENT PROCEDURES Regulation Code: 8305

FEDERAL GRANT ADMINISTRATION PROCUREMENT PROCEDURES Regulation Code: 8305 Submitted to the Board for Information June 7, 2018 FEDERAL GRANT ADMINISTRATION PROCUREMENT PROCEDURES Regulation Code: 8305 This regulation applies to contracts for purchases of goods (apparatus, supplies,

More information

Managing Construction Risks

Managing Construction Risks Managing Construction Risks RISK #1 The project s budget is understated, and money runs out before the project is completed. (1) Develop a detailed budget with a contingency. The contingency for new construction

More information

APPLICATION FOR PRE-QUALIFICATION OF GENERAL CONTRACTORS FOR NORTH ORANGE COUNTY COMMUNITY COLLEGE DISTRICT

APPLICATION FOR PRE-QUALIFICATION OF GENERAL CONTRACTORS FOR NORTH ORANGE COUNTY COMMUNITY COLLEGE DISTRICT APPLICATION FOR PRE-QUALIFICATION OF GENERAL CONTRACTORS FOR NORTH ORANGE COUNTY COMMUNITY COLLEGE DISTRICT NORTH ORANGE COUNTY COMMUNICTION COLLEGE DISTRICT PURCHASING DEPARTMENT 1830 WEST ROMNEYA DR.

More information

Mini-bid Guidelines For Certain Service & Technology Contracts Established by the State of New York Office of General Services

Mini-bid Guidelines For Certain Service & Technology Contracts Established by the State of New York Office of General Services Mini-bid Guidelines For Certain Service & Technology Contracts Established by the State of New York Office of General Services Issued: May 2001 Updated: August 2009 Purpose: This document provides general

More information

1997 Part 2. Document B141. Standard Form of Architect's Services: Design and Contract Administration TABLE OF ARTICLES

1997 Part 2. Document B141. Standard Form of Architect's Services: Design and Contract Administration TABLE OF ARTICLES TM Document B141 Standard Form of Architect's Services: Design and Contract Administration 1997 Part 2 TABLE OF ARTICLES 2.1 PROJECT ADMINISTRATION SERVICES 2.2 SUPPORTING SERVICES 2.3 EVALUATION AND PLANNING

More information

CONTRACTOR QUALIFICATION QUESTIONNAIRE. May 23, 2010

CONTRACTOR QUALIFICATION QUESTIONNAIRE. May 23, 2010 CONTRACTOR QUALIFICATION QUESTIONNAIRE May 23, 2010 1 CONTRACTOR QUALIFICATION QUESTIONNAIRE Public Improvement Contracts Federal Requirements funding & laws State Requirements funding & laws Local o Chapter

More information

INVITATION FOR BIDS (IFB) NO KMHS/BHA Cottages at Forest Park for the Housing Authority of the City of Bremerton (BHA)

INVITATION FOR BIDS (IFB) NO KMHS/BHA Cottages at Forest Park for the Housing Authority of the City of Bremerton (BHA) TABLE OF CONTENTS INVITATION FOR BIDS Section Description Page 1.0 IFB Information At-A-Glance 2 2.0 Introduction and BHA Background 2 3.0 Project Background 3 4.0 Scope of Work / Technical Specifications

More information

In accordance with 61 O.S. 108 and 115, a sworn statement shall accompany any competitive bid submitted for a public construction contract.

In accordance with 61 O.S. 108 and 115, a sworn statement shall accompany any competitive bid submitted for a public construction contract. State of Oklahoma Capital Assets Management Construction and Properties Bid Affidavits In accordance with 61 O.S. 108 and 115, a sworn statement shall accompany any competitive bid submitted for a public

More information

Title 28 (Authorize ADOT to procure multiple Job Order Contracting contracts in a single procurement)

Title 28 (Authorize ADOT to procure multiple Job Order Contracting contracts in a single procurement) Changes to Existing Law 2010 Proposal (SB 1406 and Proposed Committee Amendment) -- Alternative Project Delivery Methods (APDM) Legislation February 17, 2010 Title 15 (Repeal requirement for schools to

More information

Miller Act. Nabil dmaidi 1

Miller Act. Nabil dmaidi 1 Miller Act Enacted in 1935 Federal Contracts over $25,000 Contractor shall provide Bonds Performance Bonds in the amount to protect the U.S. List of Surety Companies acceptable in Federal Register Bid

More information

Current Legal and Financial Trends in Government Contracting

Current Legal and Financial Trends in Government Contracting Current Legal and Financial Trends in Government Contracting 2013 National Defense Authorization Act ( NDAA ): Introduced significant changes to limitations on subcontracting ( LOS ) and mentor-protégé

More information

Section 7000 Procurement

Section 7000 Procurement Section 7000 Procurement Table of Contents 7100 Conflicts of Interest 7110 Conduct of Employees 7200 Procurement Methods 7210 Small Purchase 7220 Competitive Sealed Bids 7230 Competitive Negotiation 7240

More information

Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH John R. Kasich, Governor Jerry Wray, Director

Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH John R. Kasich, Governor Jerry Wray, Director Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH 43223 John R. Kasich, Governor Jerry Wray, Director 5/16/2013 Project 130251 Addendum No. 5 PID No. 80695 LUC IR 475

More information

REQUEST FOR BID PROPOSALS

REQUEST FOR BID PROPOSALS REQUEST FOR BID PROPOSALS FOR EASTERN OREGON TRADE AND EVENT CENTER PROJECT BID ISSUANCE #8 LANDSCAPING AND IRRIGATION Hermiston, Oregon February 12, 2016 Eastern Oregon Trade and Event Center BID ISSUANCE

More information

DIOCESE OF DALLAS POLICIES AND PROCEDURES FOR CONSTRUCTION, RENOVATIONS AND MAJOR REPAIRS

DIOCESE OF DALLAS POLICIES AND PROCEDURES FOR CONSTRUCTION, RENOVATIONS AND MAJOR REPAIRS DIOCESE OF DALLAS POLICIES AND PROCEDURES FOR CONSTRUCTION, RENOVATIONS AND MAJOR REPAIRS Policies and Procedures for Construction, Renovations and Major Repairs (2-10-11) Page 1 of 15 TABLE OF CONTENTS

More information

PROPOSAL REQUIREMENTS AND CONDITIONS

PROPOSAL REQUIREMENTS AND CONDITIONS 1.01 QUALIFICATION OF THE BIDDERS PROPOSAL REQUIREMENTS AND CONDITIONS A. The Jurisdiction reserves the right to reject any bid that is not responsive to the proposal form or contract documents, or not

More information

Kings County Board of Education Board/Superintendent Policy

Kings County Board of Education Board/Superintendent Policy Kings County Board of Education Board/Superintendent Policy BP 3311 Business and Noninstructional Operations The county office of education shall purchase equipment, supplies and services using competitive

More information

In accordance with 61 O.S. 108 and 115, a sworn statement shall accompany any competitive bid submitted for a public construction contract.

In accordance with 61 O.S. 108 and 115, a sworn statement shall accompany any competitive bid submitted for a public construction contract. State of Oklahoma Office of Management and Enterprise Services Capital Assets Management Construction and Properties Bid Affidavits In accordance with 61 O.S. 108 and 115, a sworn statement shall accompany

More information

REQUEST FOR BIDS RENOVATION

REQUEST FOR BIDS RENOVATION REQUEST FOR BIDS RENOVATION NATASHA KIRK UNIT ADAIR COUNTY Bids Due: November 7th, 2017 @ 10:00 a.m. Housing Authority of the Cherokee Nation P.O. Box 1007 Tahlequah, OK 74465 1 (918) 456-5482 Housing

More information

REQUEST FOR BIDS MINOR REPAIRS

REQUEST FOR BIDS MINOR REPAIRS REQUEST FOR BIDS MINOR REPAIRS SOLICITATION #A10-10-17-3755 ROGERS COUNTY Bids Due: November 7, 2017 @ 5:00 P.M. Housing Authority of the Cherokee Nation P.O. Box 1007 Tahlequah, OK 74465 (918) 456-5482

More information

INSTRUCTIONS TO BIDDERS

INSTRUCTIONS TO BIDDERS INSTRUCTIONS TO BIDDERS 1. Bid Documents 1.1. Complete sets of Bid Documents shall be used in preparing Bids. Neither the Owner nor the Engineer assumes any responsibility for errors or misinterpretations

More information

GENERAL INFORMATION. CONTRACT means any contract awarded resulting from this invitation for Bids.

GENERAL INFORMATION. CONTRACT means any contract awarded resulting from this invitation for Bids. GENERAL INFORMATION 1. SCOPE: 1.1 This invitation for Bids and Specifications describes a contract for the purchase of gas directly from gas producers or gas supply companies. The direct purchase of Natural

More information

COMMISSION ADOPTED POLICY Procurement Policy

COMMISSION ADOPTED POLICY Procurement Policy Procurement Policy Adopted: December 16, 2014 Revised: N/A Page 1 of 6 1.0 Purpose and Need All procurement shall be in accordance with the Code of Virginia 2.2-4300, the Virginia Public Procurement Act,

More information

INSTRUCTIONS TO BIDDERS

INSTRUCTIONS TO BIDDERS 11/21/2011 HENNEPIN COUNTY PURCHASING INSTRUCTIONS TO BIDDERS TABLE OF CONTENTS 1. DEFINITIONS...1 2. BIDDER'S PREBID DOCUMENT REVIEW...2 2.1. Availability of Documents 2 2.2. Interpretation or Correction

More information

MULTNOMAH COUNTY GOOD FAITH EFFORT PROGRAM SUBCONTRACTOR and SELF-PERFORMED WORK LIST (FORM 1)

MULTNOMAH COUNTY GOOD FAITH EFFORT PROGRAM SUBCONTRACTOR and SELF-PERFORMED WORK LIST (FORM 1) MULTNOMAH COUNTY GOOD FAITH EFFORT PROGRAM OR and SELF-PERFORMED WORK LIST (FORM 1) NOTE: IF THE BIDDER IS NOT USING ANY ORS ON THIS PROJECT, WRITE THE WORDS SELF PERFORMING ALL WORK ON THE FORM. der :

More information

THE SURETY & FIDELITY ASSOCIATION OF AMERICA MEMORANDUM

THE SURETY & FIDELITY ASSOCIATION OF AMERICA MEMORANDUM THE SURETY & FIDELITY ASSOCIATION OF AMERICA MEMORANDUM TO: FROM: RE: Government Affairs Advisory Committee Daniel Wanke Contract Surety Legislation DATE: June 4, 2010 There are 10 states and the District

More information

POLICY TITLE: Purchasing District Purchasing POLICY NO: 850 PAGE 1 of 11 PURCHASING POLICY 1 - DISTRICT PURCHASING

POLICY TITLE: Purchasing District Purchasing POLICY NO: 850 PAGE 1 of 11 PURCHASING POLICY 1 - DISTRICT PURCHASING POLICY TITLE: Purchasing District Purchasing POLICY NO: 850 PAGE 1 of 11 PURCHASING POLICY 1 - DISTRICT PURCHASING It is the policy of the Mountain Home School District to make purchases of goods, services,

More information

CAR 7-1 PURCHASING REGULATION CAR 7-1 OPR: Finance 4/90 (Revised 2/10)

CAR 7-1 PURCHASING REGULATION CAR 7-1 OPR: Finance 4/90 (Revised 2/10) CAR 7-1 PURCHASING REGULATION CAR 7-1 OPR: Finance 4/90 (Revised 2/10) Purpose Section I Scope II Definitions III Responsibility IV Using Department IV A Purchasing Function IV B Property Disposal V I.

More information

Introduction and Overview

Introduction and Overview Introduction to Public Contracting Procurement and Public Works Presented by Barbara R. Gadbois, Esq. and Theodore L. Senet, Esq. County Counsels Association of California March 17, 2016 2016 Gibbs Giden

More information

INSTRUCTIONS TO PROPOSERS DRAFT FOR MN/DOT REVIEW

INSTRUCTIONS TO PROPOSERS DRAFT FOR MN/DOT REVIEW PART II INSTRUCTIONS TO PROPOSERS Minnesota Department of Transportation SP 7408-29 TH 14/218 DESIGN-BUILD REQUEST FOR PROPOSALS 1 INTRODUCTION RFP and ITP. This Request for Proposals (RFP) is issued by

More information

NEW HAMPSHIRE HOUSING FINANCE AUTHORITY. Replacement Reserve and Residual Receipts Rules HFA 204

NEW HAMPSHIRE HOUSING FINANCE AUTHORITY. Replacement Reserve and Residual Receipts Rules HFA 204 NEW HAMPSHIRE HOUSING FINANCE AUTHORITY Replacement Reserve and Residual Receipts Rules HFA 204 Table of Contents HFA 204 PART ONE: Overview, Purpose, Applicability, Rulemaking 204.01 Overview and Purpose

More information

This Webcast Will Begin Shortly

This Webcast Will Begin Shortly This Webcast Will Begin Shortly If you have any technical problems with the Webcast or the streaming audio, please contact us via email at: splemoderator@smartpros.com Thank You! 1 KEY ISSUES IN NEGOTIATING

More information

CHAPTER 57 ARTICLES II & III

CHAPTER 57 ARTICLES II & III CHAPTER 57 ARTICLES II & III ARTICLE II. - MINORITY BUSINESS ENTERPRISE Sec. 57.15. - Definitions. (1) For the purposes of this Chapter, Minority Business Enterprise is defined as a business firm which

More information

East Central College

East Central College SECTION 00100 - INSTRUCTION TO BIDDERS 1. BIDDING GUIDELINES The submission of a Bid shall be deemed the Bidder's tacit acknowledgment and considered conclusive evidence that: 1. Each Bidder is responsible

More information

1 CCR PROCUREMENT RULES

1 CCR PROCUREMENT RULES Rule Changes Redlines 1 CCR 101-9 PROCUREMENT RULES ARTICLE 102 PROCUREMENT ORGANIZATION PART 2 DIVISION OF PURCHASING R-24-102-206 Contract Performance Outside the United States or Colorado R-24-102-206-01

More information

Daniel Lunghofer School District Accounting Supervisor, OSPI

Daniel Lunghofer School District Accounting Supervisor, OSPI Daniel Lunghofer School District Accounting Supervisor, OSPI 360-725-6303 daniel.lunghofer@k12.wa.us State Bid Law RCW 28A.335.190 Covers purchases of materials and supplies for school districts, except

More information

Bids must be received in the Purchasing Office by 3:00 p.m. on 11/22/16.

Bids must be received in the Purchasing Office by 3:00 p.m. on 11/22/16. Tennessee Technological University Date: 10/25/2016 Purchasing Office Contact: Emily Vaughn P. O. Box 5144, 1 William L. Jones Dr., Ste. 301 Phone: 931-372-3566 Cookeville, TN 38505-0001 Email: evaughn@tntech.edu

More information

Quote A written or verbal price a supplier can provide for material or services for a specified period of time.

Quote A written or verbal price a supplier can provide for material or services for a specified period of time. METROPOLITAN DOMESTIC WATER IMPROVEMENT DISTRICT PROCUREMENT POLICY NOVEMBER 14, 2018 PURPOSE The purpose of the Procurement Policy is to ensure the prudent and economical use of public monies in the best

More information

Public School Bidding Legal Citations

Public School Bidding Legal Citations LEGAL CITATI Public School Bidding Legal Citations 1. Who has the authority to bid? N.J.S.A. 18A:18A~2(b) The Purchasing Agent assumes full control over preparing bid advertisements and sending the legal

More information

CHAPTER 57 ARTICLES II & III

CHAPTER 57 ARTICLES II & III CHAPTER 57 ARTICLES II & III ARTICLE II. MINORITY BUSINESS ENTERPRISE Sec. 57.15. Definitions. (1) For the purposes of this Chapter, Minority Business Enterprise is defined as a business firm which is

More information

INSTRUCTIONS TO BIDDERS

INSTRUCTIONS TO BIDDERS INSTRUCTIONS TO BIDDERS Jefferson County School District No. R-1, State of Colorado, hereinafter called the "Owner", has advertised for bids to be submitted for the construction work specified in the advertisement.

More information

DISADVANTAGED BUSINESS ENTERPRISE (DBE) PROGRAM FOR

DISADVANTAGED BUSINESS ENTERPRISE (DBE) PROGRAM FOR DISADVANTAGED BUSINESS ENTERPRISE (DBE) PROGRAM FOR 2006 2007 This Program is in accordance with Title 49 of the Code of Federal Regulations Part 26 Local Assistance Procedures Manual EXHIBIT 9-A DBE Race-Neutral

More information

REQUEST FOR BIDS MODERNIZATION

REQUEST FOR BIDS MODERNIZATION REQUEST FOR BIDS MODERNIZATION 3 MODERNIZATION UNITS LOCATED IN SEQUOYAH COUNTY Bids Due: January 15th, 2019 @ 10:00 a.m. Housing Authority of the Cherokee Nation P.O. Box 1007 Tahlequah, OK 74465 1 (918)

More information

City of Charlotte Uniform Guidance Procurement Policy

City of Charlotte Uniform Guidance Procurement Policy City of Charlotte Uniform Guidance Procurement Policy I. Objective The objective of this Policy is to establish guidelines that meet or exceed the procurement requirements for purchases of goods (apparatus,

More information

DISADVANTAGED BUSINESS ENTERPRISE RACE-NEUTRAL IMPLEMENTATION AGREEMENT FOR HUMBOLDT COUNTY

DISADVANTAGED BUSINESS ENTERPRISE RACE-NEUTRAL IMPLEMENTATION AGREEMENT FOR HUMBOLDT COUNTY DISADVANTAGED BUSINESS ENTERPRISE RACE-NEUTRAL IMPLEMENTATION AGREEMENT FOR HUMBOLDT COUNTY L:\projects\_DBE Program\Fed FY 2007-08\0708 Exhibit 9A.doc June 1, 2006 Page 1 of 9 DISADVANTAGED BUSINESS ENTERPRISE

More information

The Colorado Procurement Code and these rules do not apply to the following procurements:

The Colorado Procurement Code and these rules do not apply to the following procurements: CodeofCol or adoregul at i ons Sec r et ar yofst at e St at eofcol or ado DEPARTMENT OF PERSONNEL AND ADMINISTRATION PROCUREMENT RULES 1 CCR 101-9 [Editor s Notes follow the text of the rules at the end

More information

PART INSTRUCTIONS TO BIDDERS

PART INSTRUCTIONS TO BIDDERS [ ] [ ] [ ] Date [Date] [ ] [] PART 1 - INSTRUCTIONS TO BIDDERS CLAUSE 1 - DOCUMENTS 1 DOCUMENTS Carefully examine the following information. Failure to follow these instructions may result in bid disqualification.

More information

520 - Purchasing Policy

520 - Purchasing Policy 520 - Purchasing Policy Table of Contents 1.0 Purpose... 2 2.0 General Responsibilities... 2 2.1 General Authority... 2 2.2 Written Contracts / When Required... 2 3.0 Open Market Purchases... 2 3.1 General

More information

AIA Document A101 TM 2007

AIA Document A101 TM 2007 AIA Document A101 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum AS MODIFIED BY OWNER AGREEMENT made as of the day of in the year (In words,

More information

PUBLIC WORKS PROJECT REQUEST FOR BIDS

PUBLIC WORKS PROJECT REQUEST FOR BIDS PUBLIC WORKS PROJECT REQUEST FOR BIDS PIERCE COUNTY FIRE PROTECTION DISTRICT #22 18421 OLD BUCKLEY HIGHWAY BONNEY LAKE, WA 98391 (253) 863-1800 (253) 863-1848 (FAX) Date Bid Requested: 9/22/2010 Date Bid

More information

Contract Administration Final Exam

Contract Administration Final Exam Contract Administration Final Exam 1. You want to solicit bids for a one year contract for concrete to support your roadway construction work. At this time, prices are fluctuating due to high demand and

More information

APPLICATION FOR PAYMENT PROCEDURE SUBCONTRACT EXHIBIT F

APPLICATION FOR PAYMENT PROCEDURE SUBCONTRACT EXHIBIT F Subcontract No.: Enter Number Cost Code: Enter Code TOCCI BUILDING CORPORATION Vendor No.: Enter Number APPLICATION FOR PAYMENT PROCEDURE SUBCONTRACT EXHIBIT F To standardize the Application for Payment

More information

CALIFORNIA DEPARTMENT OF TRANSPORTATION DISADVANTAGED BUSINESS ENTERPRISE IMPLEMENTATION AGREEMENT

CALIFORNIA DEPARTMENT OF TRANSPORTATION DISADVANTAGED BUSINESS ENTERPRISE IMPLEMENTATION AGREEMENT CALIFORNIA DEPARTMENT OF TRANSPORTATION DISADVANTAGED BUSINESS ENTERPRISE IMPLEMENTATION AGREEMENT For the County of San Mateo, hereinafter referred to as "RECIPIENT." I Definition of Terms The terms used

More information

PROCUREMENT FEDERAL GRANTS/FUNDS

PROCUREMENT FEDERAL GRANTS/FUNDS BRADFORD ACADEMY 6325/page 1 of 6 PROCUREMENT FEDERAL GRANTS/FUNDS Reference: 2 C.F.R. 200.317 -.326 Procurement of all supplies, materials, equipment, and services paid for from Federal funds or Academy

More information

Acknowledgment Form - page 1 of 2

Acknowledgment Form - page 1 of 2 Acknowledgment Form - page 1 of 2 RFQu - Construction Services for Josiah Henson Park The Proposer must include this signed acknowledgment that the Proposer has reviewed all the terms and conditions of

More information

ARCHIVED - MAY 20, 2014

ARCHIVED - MAY 20, 2014 TEXAS POLICY In Texas, organizations contracting directly with the Texas Department of Agriculture (TDA) to operate nutrition programs federally funded through the United States Department of Agriculture

More information

Nicole Janes DESIGN HOME REPAIR KNOW YOUR CONSUMER RIGHTS

Nicole Janes DESIGN HOME REPAIR KNOW YOUR CONSUMER RIGHTS HOME REPAIR ILLINOIS HOME REPAIR AND REMODELING ACT As you prepare for your home repair / improvement project, it is important to ask the right questions in order to protect your investment. The tips in

More information

The term Government in clauses and/or provisions shall mean Concho Valley Council of Governments (CVCOG) unless otherwise specified.

The term Government in clauses and/or provisions shall mean Concho Valley Council of Governments (CVCOG) unless otherwise specified. The term Government in clauses and/or provisions shall mean Concho Valley Council of Governments (CVCOG) unless otherwise specified. 1. Prohibition on Contracting with Inverted Domestic Corporations-Representation.

More information

The BASICS of CONSTRUCTION ACCOUNTING Workshop GLOSSARY

The BASICS of CONSTRUCTION ACCOUNTING Workshop GLOSSARY The BASICS of CONSTRUCTION ACCOUNTING Workshop GLOSSARY From Financial Management & Accounting for the Construction Industry, CFMA. Accounts Payable Obligations to pay for goods and services that have

More information

DES MOINES PUBLIC SCHOOLS WRIGHT ELEMENTARY SCHOOL KITCHEN RENOVATION BID NO. B8183 APRIL 9, 2018 ADDENDUM NO. 1

DES MOINES PUBLIC SCHOOLS WRIGHT ELEMENTARY SCHOOL KITCHEN RENOVATION BID NO. B8183 APRIL 9, 2018 ADDENDUM NO. 1 DES MOINES PUBLIC SCHOOLS WRIGHT ELEMENTARY SCHOOL KITCHEN RENOVATION BID B8183 APRIL 9, 2018 ADDENDUM 1 Bidders shall recognize the receipt of this addenda by noting it on the Bid Form in the space designated.

More information

DOING BUSINESS WITH NEWPORT NEWS PUBLIC SCHOOLS... A VENDOR S GUIDE TO UNDERSTANDING NNPS PROCUREMENT PRACTICES

DOING BUSINESS WITH NEWPORT NEWS PUBLIC SCHOOLS... A VENDOR S GUIDE TO UNDERSTANDING NNPS PROCUREMENT PRACTICES DOING BUSINESS WITH NEWPORT NEWS PUBLIC SCHOOLS.... A VENDOR S GUIDE TO UNDERSTANDING NNPS PROCUREMENT PRACTICES July 2014 NEWPORT NEWS PUBLIC SCHOOLS (NNPS) PURCHASING DEPARTMENT The following Purchasing

More information

AN ANALYSIS OF ARIZONA PROMPT PAYMENT STATUTES

AN ANALYSIS OF ARIZONA PROMPT PAYMENT STATUTES AN ANALYSIS OF ARIZONA PROMPT PAYMENT STATUTES GUY W. BLUFF, ESQ. I. ARIZONA S PROMPT PAYMENT STATUTES 3 A. The General Rule 4 B. Objections Must be In Writing and Specific 6 II. SUMMARY OF STATUTORY AND

More information

PROCUREMENT PLAN FOR CHILD NUTRITION PROGRAMS

PROCUREMENT PLAN FOR CHILD NUTRITION PROGRAMS PROPOSED (EFC) PROCUREMENT PLAN FOR CHILD NUTRITION PROGRAMS Muskogee Public Schools, A School Food Authority (SFA) will purchase food and other items for use in the Child Nutrition Programs (CNP in compliance

More information

Construction Management Contract This agreement is made by (Contractor) and (Owner) on the date written beside our signatures.

Construction Management Contract This agreement is made by (Contractor) and (Owner) on the date written beside our signatures. Construction Management Contract This agreement is made by (Contractor) and (Owner) on the date written beside our signatures. Contractor Address Address City, Zip Work Phone Number: Cell Phone Number:

More information

Lead Agency Procurement Self-Certification March 2017

Lead Agency Procurement Self-Certification March 2017 Lead Agency Procurement Self-Certification March 2017 Uniform Grant Guidance 200.324 200.317 Procurements By States When procuring property and services under a Federal award, a state must follow the same

More information

LAFOURCHE PARISH GOVERNMENT PURCHASING POLICIES AND PROCEDURES

LAFOURCHE PARISH GOVERNMENT PURCHASING POLICIES AND PROCEDURES LAFOURCHE PARISH GOVERNMENT PURCHASING POLICIES AND PROCEDURES The mission of Lafourche Parish Government Department of Finance is to develop and implement sound procurement practices in accordance with

More information

RULES FOR CONSTRUCTING PROJECTS UNDER THE GEORGIA LOCAL GOVERNMENT PUBLIC WORKS CONSTRUCTION LAW

RULES FOR CONSTRUCTING PROJECTS UNDER THE GEORGIA LOCAL GOVERNMENT PUBLIC WORKS CONSTRUCTION LAW 1075 Peachtree Street, N.E. Suite 2500 Atlanta, GA 30309-3962 (404) 885-1500 Fax (404) 892-7056 http:/www.seyfarth.com/ 404.888.1883 direct 404.892.7056 fax danmcrae@mindspring.com dmcrae@seyfarth.com

More information

Pittsburgh, PA 15213

Pittsburgh, PA 15213 The Board of Public Education of the School District of Pittsburgh Administration Building, 341 South Bellefield Avenue Pittsburgh, PA 15213 Inquiry Number 8796 Sealed bids for material listed herein will

More information

The Toler Firm LLC A Construction Law Firm Timothy N. Toler September 23, 2015

The Toler Firm LLC A Construction Law Firm Timothy N. Toler September 23, 2015 The Toler Firm LLC A Construction Law Firm Timothy N. Toler September 23, 2015 Negotiating 8 Key Contract Clauses from the Contractor s Perspective (Part 1 of 2) 1 This is the first of a two-part overview

More information

Lessons Learned: Construction Bidding & Procurement Item D.1

Lessons Learned: Construction Bidding & Procurement Item D.1 Lessons Learned: Construction Bidding & Procurement Item D.1 Facilities Subcommittee Meeting February 28, 2017 Bid Limits The District must competitively bid any contract involving an expenditure of: Bid

More information

L/L September 8, 2014

L/L September 8, 2014 * Roll Call Number Agenda Item Number L/L September 8, 2014 Date APPROVING CITY OF DES MOINES TAXPAYER QUALITY ASSURANCE POLICY WHEREAS, Iowa Code 26.9 requires that contracts for public improvements be

More information

CALIFORNIA UNIFORM PUBLIC CONSTRUCTION COST ACCOUNTING ACT. FREQUENTLY ASKED QUESTIONS (FAQs)

CALIFORNIA UNIFORM PUBLIC CONSTRUCTION COST ACCOUNTING ACT. FREQUENTLY ASKED QUESTIONS (FAQs) CALIFORNIA UNIFORM PUBLIC CONSTRUCTION COST ACCOUNTING ACT FREQUENTLY ASKED QUESTIONS (FAQs) 1. What is the? A program created in 1983 which allows local agencies to perform public project work up to $45,000

More information

REQUEST FOR QUOTATION SUBMIT BID TO PURCHASING DIVISION SHAWNEE COUNTY COURTHOUSE Room 201 Topeka, Kansas THIS IS NOT AN ORDER

REQUEST FOR QUOTATION SUBMIT BID TO PURCHASING DIVISION SHAWNEE COUNTY COURTHOUSE Room 201 Topeka, Kansas THIS IS NOT AN ORDER REQUEST FOR QUOTATION SUBMIT BID TO PURCHASING DIVISION SHAWNEE COUNTY COURTHOUSE Room 201 Topeka, Kansas 66603 QUOTATION NO. 018-18 VENDOR ADDRESS PHONE THIS IS NOT AN ORDER 1. In communications, always

More information

OFFICE OF STATE AID ROAD CONSTRUCTION MISSISSIPPI DEPARTMENT OF TRANSPORTATION

OFFICE OF STATE AID ROAD CONSTRUCTION MISSISSIPPI DEPARTMENT OF TRANSPORTATION OFFICE OF STATE AID ROAD CONSTRUCTION MISSISSIPPI DEPARTMENT OF TRANSPORTATION NOTICE TO BIDDERS NO. 4 DATE: 10/25/2002 SUBJECT: DISADVANTAGED BUSINESS ENTERPRISES IN FEDERAL-AID HIGHWAY CONSTRUCTION This

More information