22 March 2013 MBA G523 PROJECT MANAGEMENT
|
|
- Ross Walton
- 5 years ago
- Views:
Transcription
1 22 March 2013 MBA G523 PROJECT MANAGEMENT
2 ESTIMATING PROJECT TIMES AND COSTS Some of the Whys : Estimates are needed to Support good decisions Schedule work Determine how long the project should take and its cost Develop cash flow needs Determine how well the project is progressing
3 FACTORS INFLUENCING QUALITY OF ESTIMATES Planning horizon: accuracy less for more distant phases of project Duration of project: uncertainty in estimates greater for longer duration projects People: skills of people making estimates, new people added into team due to staff turnover, people working together for first time in a project
4 FACTORS INFLUENCING QUALITY OF ESTIMATES Project structure: functional organization, dedicated project team, matrix Padding estimates: 30 minutes with 50/50 chance getting to airport on time, superfast driving in 20 minutes, to receive company president 50 minutes. Organization culture: estimation not worth the trouble, detailed estimation essential Non-project factors: equipment downtime, national holidays, vacations, etc.
5 ESTIMATING GUIDELINES FOR TIMES, COSTS, RESOURCES Responsibility: estimates by persons most familiar with task, buy-in with plan implementers ensured Use several people to estimate: consensus, realistic estimate, extremes avoided Normal conditions: 8 hour day, two-shift work day, 3 programmers for coding or two road graders for construction (normal level of resources)
6 ESTIMATING GUIDELINES FOR TIMES, COSTS, RESOURCES Time units: consistency across all tasks estimated, calendar days, workdays, workweeks, person days, single shift, hours, minutes (for medical contexts minutes more relevant) Independence: each task to be estimated individually, avoid estimation by high level managers who might aggregate multiple tasks into a single estimate, avoid simultaneous multiple task estimation
7 ESTIMATING GUIDELINES FOR TIMES, COSTS, RESOURCES Contingencies: avoid building allowances for contingencies into work package estimates most top management will include a separate contingency fund to handle unforeseen events Add risk assessment to estimate helps avoid surprises to stakeholders: optimistic and pessimistic task time
8 TOP-DOWN VERSUS BOTTOM-UP Condition Top-down estimate Bottom-up estimate Strategic decision making Cost and time important High uncertainty Internal small project Fixed-price contract Customer wants details Unstable scope X X X X X X X
9 AERIAL TRAM IN PORTLAND. OREGON Original estimate: USD 15 million Real budget: USD million Guesstimate: actual design not costed out
10 TOP-DOWN APPROACHES Consensus method Made by senior or middle managers For greater rigor: Delphi Method Experts called upon to estimate Experts tied to project being estimated One expert s feedback given to all Anonymity of experts Progressive convergence over multiple rounds At beginning of project Only an initial estimate May be off the mark
11 RATIO METHODS 2700 square USD 160 per square feet = USD 432, 000 by experience 100 days to complete
12 APPORTION METHODS Bank loan for house construction: payment to contractor Foundation: 3% Framing: 25% Electric/plumbing/heating: 15%.
13 APPORTION METHODS. Total project: USD 500,000 Design (20%): USD 100,000 D-1: USD 50,000 D-2: USD 50,000 Program (30%): USD 150,000 P-1: USD 100,00 P-2: USD 25,000 P-3: USD 25,000 Testing (40%): USD 200,000 (T-1, T-2, T-3) Document (5%): USD (Doc-1, Doc-2) Produce CD (5%): USD (CD-1)
14 FUNCTION POINT METHODS FOR SOFTWARE AND SYSTEM PROJECTS Element Complexity Weighting Low Average High Total # of inputs x 2 + x 3 + x 4 + = # of outputs x 3 + x 6 + x 9 + = # of inquiries x 2 + x 4 + x 6 + = # of files x 5 + x 8 + x 12 + = # of interfaces x 5 + x 10 + x 15 + = Total
15 LEARNING CURVES Output qty doubles labor hours reduced by constant rate First 100 units: 100 ours Second 100 units: 60 hours Next 200 units: 36 hours
16 CASE STUDY 4.1 (PAGE ) Manchester United Soccer Club
17 BOTTOM-UP APPROACHES Template: Historical data for similar projects: adjust for differences Parametric procedures applied for specific tasks MS Office Conversion Project: 36 workstations to be converted One person = 3 workstations/day 3 persons and 36 workstations (36/3)/3 = 4 days Wallpapering allowance in house remodeling USD 5 per square yard of wallpaper, USD 2 per yard to install, total cost = USD 7 Measure length, width, height of room area of walls known and multiply by USD 7 for total cost
18 DETAILED ESTIMATES FOR WBS WORK PACKAGES
19 A HYBRID: PHASE ESTIMATING
20 COMPARISON Top-down Estimate Bottom-up Estimate Intended Use Preparation Cost Feasibility/conceptual phase Rough time/cost estimate Fund Requirements Resource Capacity Planning 1/10 to 3/10 of a percent of total project cost Budgeting Scheduling Resource Requirements Fund Timing 3/10 of a percent to 1 % of total project cost Accuracy -20% to 60% -10% to 30% Method Consensus Ratio Apportion, FP, Learning Curves Template Parametric WBS Packages
21 LEVEL OF DETAIL For top mgt For middle mgt For first line mgrs WBS provides this flexibility 40 day task: better to break it down to multiple 5-10 day tasks, quicker corrective action and better for project control
22 TYPES OF COSTS Direct: Labor, Materials, Equipment Project (Direct) Overhead Costs: Proj Mgr Salary, temporary rental space for proj team General and Administrative (G&A) Overhead Costs: advertising, accounting, senior mgt salary (across products and projects)
23 CONTRACT BID SUMMARY COSTS Direct Costs USD Direct Overhead USD G&A Overhead (20%) USD Total Costs USD Profit (20%) USD Total Bid USD
24 PERSPECTIVES OF COSTS Committed Cost Proj Mgr months before Finance Mgr plans cash outflows Actual Cost: when budgeted cost will occur Scheduled budget: budgeted cost is charged (earned)
25 REFINING ESTIMATES Multiplying factors: why this need after so much effort in estimation Interaction costs are hidden in estimates: dependence between tasks, implementers clarification questions to design engineers, coordination meeting briefings Normal conditions do not apply: normal condition of 4 bull dozers but only 3 available Things go wrong in projects: design flaws show up later, extreme weather conditions, accidents Changes in project scope and plans: needed to hold customer from competition
26 CREATING A DATABASE FOR ESTIMATING
27 CASE STUDY 5.1 Page Sharp Printing, AG Written Answers Due 5 April 2013 Discussion on 5 April 2013
Chapter 5: Estimating Project Times and Costs 4KF3
Lecture Notes Importance of Estimates Support good decisions Schedule work o Make sure your team members can take on added work of project Determine length of project and costs o Projects can be cancelled
More informationProject and Communication Management
Project and Communication Management Chapter 5 Learning objectives: Estimating Projects Estimating The process of forecasting or approximating the time and cost of completing project deliverables. The
More informationEstimating Project Times and Costs
CHAPTER FIVE Estimating Project Times and Costs Copyright 2014 McGraw-Hill Education. All Rights Reserved. PowerPoint Presentation by Charlie Cook Where We Are Now 5 2 Estimating Estimating Projects The
More informationProject Management. Estimating Project Times and Costs. Clifford F. Gray Eric W. Larson Third Edition. Chapter 5
Project Management THE MANAGERIAL PROCESS Clifford F. Gray Eric W. Larson Third Edition Chapter 5 Estimating Project Times and Costs Copyright 2006 The McGraw-Hill Companies. All rights reserved. PowerPoint
More informationThe Project Times and Costs
The Project Times and Costs Not to underestimate the estimate Chapter 5 Defining the Project Step 1: Defining the Scope Step 2: Establishing Priorities Step 3: Creating the Work Breakdown Structure Step
More informationEstimating Project Times and Costs
C H A P T E R F I V E Estimating Project Times Project estimation is indeed a yardstick for project cost control. And if the yardstick is faulty, you start on the wrong foot.... we exhort you not to underestimate
More informationEstimating Project Times and Costs
Estimate 5 Project networks 6 Scheduling resources/costs 8 Define project 4 Reducing project duration 9 Introduction 1 Organization 3 Managing risk 7 Monitoring progress 13 Audit and closure 14 Oversight
More informationProject Management: Cost
Project Management: Cost Cost Management the processes required to ensure that a project is completed within the approved budget Estimating cost of resources Forecasting: quantity when they are required
More informationPMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved
Project Cost Management 1 Project Cost Management Processes 1. Estimate Costs 2. Determine Budget 3. Control Costs In some projects, especially with smaller scope, cost estimation and cost budgeting are
More informationMS Project 2007 Page 1 of 18
MS Project 2007 Page 1 of 18 PROJECT MANAGEMENT (PM):- There are powerful environment forces contributed to the rapid expansion of the projects and project management approaches to the business problems
More informationProject planning and creating a WBS
37E01500 Project Management and Consulting Practice Project planning and creating a WBS Matti Rossi Lecture 3, Tue 28.2.2017 Learning objectives Describe the project time management planning tasks, and
More informationProject Management. Session 5 Budgets and Estimation Andre Samuel
Project Management Session 5 Budgets and Estimation Andre Samuel This Session Budgets and Estimation Estimation Principles Estimation Techniques Cost Estimating Estimation Principles Prediction of project
More informationFundamentals of Project Risk Management
Fundamentals of Project Risk Management Introduction Change is a reality of projects and their environment. Uncertainty and Risk are two elements of the changing environment and due to their impact on
More informationInternational Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ
International Project Management prof.dr MILOŠ D. MILOVANČEVIĆ Project time management Project cost management Time in project management process Time is a valuable resource. It is also the scarcest. Time
More informationLCS International, Inc. PMP Review. Chapter 5 Developing Project Budgets. Presented by David J. Lanners, MBA, PMP
PMP Review Chapter 5 Developing Project Budgets Presented by David J. Lanners, MBA, PMP These slides are intended to be used only in settings where each viewer has an original copy of the Sybex PMP Study
More informationPMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005
PMP Preparation Training Your key in Successful Project Management Akram Al-Najjar, PMP Cost Management Processes Chapter 7 Cost Management Slide 2 1 AGENDA What is Cost Management? Cost Management Processes
More informationChapter 8 Cost Estimating and Budgeting
Chapter 8 Cost Estimating and Budgeting Project Management for Business, Engineering, and Technology Prepared by John Nicholas, Ph.D. Loyola University Chicago Cost overrun % Cost Overruns on Projects
More informationEstimate Considerations. Estimate Considerations
Estimate Considerations Estimate Considerations Every estimate, whether it is generated in the conceptual phase of a project or at bidding time, must consider a number of issues Project Size Project Quality
More informationCMU UC Professional Master of Software Engineering
Outline The Software Estimation problem CMU UC Professional Master of Software Engineering Estimation Techniques in Software Projects Process oriented estimation techniques The WAG Wild Altogether Guess
More informationPROJECT COST MANAGEMENT
PROJECT COST MANAGEMENT For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, PMP, PMI-RMP
More informationChapter-8 Risk Management
Chapter-8 Risk Management 8.1 Concept of Risk Management Risk management is a proactive process that focuses on identifying risk events and developing strategies to respond and control risks. It is not
More information3/15/2018 CHAPTER 5. PROJECT MANAGEMENT. Prepared by: Dr. Maria Elisa Linda T. Cruz
CHAPTER 5. BUDGETING CHAPTER AND 1 INTRODUCTION COST ESTIMATION TO PROJECT MANAGEMENT Prepared by: Dr. Maria Elisa Linda T. Cruz Prepared by: Dr. Maria Elisa Linda T. Cruz 1 Chapter 5. Topics 5.1 Estimating
More informationSECTION PROJECT SCHEDULES (SMALL PROJECTS DESIGN/BID/BUILD)
SECTION 01 32 16.15 PROJECT SCHEDULES (SMALL PROJECTS DESIGN/BID/BUILD) PART 1- GENERAL 1.1 DESCRIPTION: A. The Contractor shall develop a Critical Path Method (CPM) plan and schedule demonstrating fulfillment
More informationProject Theft Management,
Project Theft Management, by applying best practises of Project Risk Management Philip Rosslee, BEng. PrEng. MBA PMP PMO Projects South Africa PMO Projects Group www.pmo-projects.co.za philip.rosslee@pmo-projects.com
More informationPMI PMI-SP. PMI Scheduling Professional. Download Full Version :
PMI PMI-SP PMI Scheduling Professional Download Full Version : http://killexams.com/pass4sure/exam-detail/pmi-sp QUESTION: 311 A company hires a scheduler for one of its projects. What skills should he
More informationProject Management: A Systems Approach to Planning, Scheduling, and Controlling Twelfth Edition
Project Management: A Systems Approach to Planning, Scheduling, and Controlling Twelfth Edition Chapter Thirteen Pricing and Estimating Pricing and Estimating Many managers regard this as an art! Information
More informationProject Management. A Practitioner s Guide. Steven M. Bragg
Project Management A Practitioner s Guide Steven M. Bragg Chapter 1 Overview of Project Management... 1 Learning Objectives... 1 Introduction... 1 Project Management Activities... 1 The Need for Project
More informationDOCUMENT SCHEDULING OF WORK PART 1 GENERAL 1.1 RELATED DOCUMENTS AND PROVISIONS
DOCUMENT 01 32 13 PART 1 GENERAL 1.1 RELATED DOCUMENTS AND PROVISIONS All Contract Documents should be reviewed for applicable provisions related to the provisions in this document, including without limitation:
More informationSCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016
All Rights Reserved No. of Pages - 10 No of Questions - 06 SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016 MGT 30725 Project
More informationRisk Video #1. Video 1 Recap
Risk Video #1 Video 1 Recap 1 Risk Video #2 Video 2 Recap 2 Risk Video #3 Risk Risk Management Process Uncertain or chance events that planning can not overcome or control. Risk Management A proactive
More informationLesson 7 The Project Budget
MBA, Msc, Bsc, PMP, CSM, PMI-ACP Indike Manthilake MBA, Msc, Bsc, CSM, PMI-ACP indikem@unitedmotors.lk.com Lesson 7 The Project Budget Agenda Estimate Costs and income Creating a Preliminary Budget Budget
More informationProject Integration Management
Project Integration Management Describe an overall framework for project integration management as it relates to the other PM knowledge areas and the project life cycle. Explain the strategic planning
More informationA DSS BASED METHODOLOGY FOR PROGRAMME MANAGEMENT
A DSS BASED METHODOLOGY FOR PROGRAMME MANAGEMENT P. G. IPSILANDIS, K. SIRAKOULIS, S. POLYZOS, V. GEROGIANNIS [DEPT. OF PROJECT MANAGEMENT, TECHNOLOGICAL EDUCATION INSTITUTE OF LARISSA, GREECE] ABSTRACT
More informationRisk Management Plan for the <Project Name> Prepared by: Title: Address: Phone: Last revised:
for the Prepared by: Title: Address: Phone: E-mail: Last revised: Document Information Project Name: Prepared By: Title: Reviewed By: Document Version No: Document Version Date: Review Date:
More informationu w 1.5 < 0 These two results imply that the utility function is concave.
A person with initial wealth of Rs.1000 has a 20% possibility of getting in a mischance. On the off chance that he gets in a mishap, he will lose Rs.800, abandoning him with Rs.200; on the off chance that
More informationChapter 5: Software effort estimation
Chapter 5: Software effort estimation NET481: Project Management Afnan Albahli " Topics to be covered Difficulties of Estimation Where are estimates done? Problems of over- and under- estimate Estimation
More informationProject Appraisal, Scoping and Estimation. Week 3
Project Appraisal, Scoping and Estimation Week 3 Last Week What is Project Management? Project Definition i i Stakeholder Management Organizing the Project This Week Defining the Project Project Appraisal
More informationVALLIAMMAI ENGINEERING COLLEGE
VALLIAMMAI ENGINEERING COLLEGE SRM Nagar, Kattankulathur 603 203 DEPARTMENT OF CIVIL ENGINEERING QUESTION BANK VI SEMESTER CE6005 CONSTRUCTION PLANNING AND SCHEDULING Regulation 2013 Academic Year 2017
More informationChapter 7: Project Cost Management. IT Project Management, Third Edition Chapter 7
Chapter 7: Project Cost Management 1 Learning Objectives Understand the importance of good project cost management Explain basic project cost management principles, concepts, and terms Describe how resource
More informationPROJECT MANAGEMENT BODY OF KNOWLEDGE
A Guide to the PROJECT MANAGEMENT BODY OF KNOWLEDGE (PMBOK GUIDE ) Sixth edition Chapter 7 Project Cost Management PMBOK is a registered mark of the Project Management Institute, Inc Slide # 1 3FOLD Education
More informationCOPYRIGHTED MATERIAL. Index
Index Note to the reader: Throughout this index boldfaced page numbers indicate primary discussions of a topic. Italicized page numbers indicate illustrations. A A+ certification, 28 acceptance criteria
More informationMaking sense of Schedule Risk Analysis
Making sense of Schedule Risk Analysis John Owen Barbecana Inc. Version 2 December 19, 2014 John Owen - jowen@barbecana.com 2 5 Years managing project controls software in the Oil and Gas industry 28 years
More informationUnit 9: Risk Management (PMBOK Guide, Chapter 11)
(PMBOK Guide, Chapter 11) Some exam takers may be unfamiliar with the basic concepts of probability, expected monetary value, and decision trees. This unit will review all these concepts so that you should
More informationChapter 9 Activity-Based Costing
Chapter 9 Activity-Based Costing SUMMARY This chapter deals with the allocation of indirect costs to products. Product cost information helps managers make numerous decisions, such as pricing, keeping
More informationPMI - Dallas Chapter. Sample Questions. March 22, 2002
PMI - Dallas Chapter PMP Exam Sample Questions March 22, 2002 Disclaimer: These questions are intended for study purposes only. Success on these questions is not necessarily predictive of success on the
More informationPMP Exam Preparation Workshop Chapter 7 Project Cost Management
PMP Exam Preparation Workshop Chapter 7 Project Cost Management 1 Learning Objectives By the end of this session, you should understand: Importance of cost management for the success of a project Cost
More informationProject Management for EPC Contracts Presented by: Dr. Jamal F. AlBahar, PMP, VMA Registered Arbitrator; Member: PMI, CMAA, AACE, AAA, PMA, CSI, SAVE
Project Management for EPC Contracts Presented by: Dr. Jamal F. AlBahar, PMP, VMA Registered Arbitrator; Member: PMI, CMAA, AACE, AAA, PMA, CSI, SAVE INTRODUCTION: Project Management for Engineering and
More informationProject Management. Managing Risk. Clifford F. Gray Eric W. Larson Third Edition. Chapter 7
Project Management THE MANAGERIAL PROCESS Clifford F. Gray Eric W. Larson Third Edition Chapter 7 Managing Risk Copyright 2006 The McGraw-Hill Companies. All rights reserved. PowerPoint Presentation by
More informationOur Risk Tolerance Assessment
Our Risk Tolerance Assessment! Springwater!uses!the!services!of!a!professional!third!party!to!help!us!better!understand!your!financial! risk!tolerance!!your!attitudes,!values,!motivations,!preferences!and!experiences.!!!!
More informationContents Cloud or On-Premises Content Introduction Data Dictionary... 23
P6 Data Dictionary Version 17 July 2017 Contents Cloud or On-Premises Content... 19 Introduction... 21 Data Dictionary... 23 % Allocation... 23 Access Level... 23 Access Time... 23 Accounting Variance...
More informationBACKRGROUND INFORMATION:
The City of Sparta is seeking proposals for the following work: Statutory assessment services for three year period (2015, 2016, and 2017) beginning January 1, 2015.This will be regular annual maintenance
More informationUNIVERSITY OF TOLEDO INTERNAL AUDIT DEPARTMENT DEVELOP BUDGETS
The following control objectives provide a basis for strengthening your control environment for the process of developing budgets. When you select an objective, you will access a list of the associated
More informationPROJECT COST MANAGEMENT
PROJECT COST MANAGEMENT Planning DETERMINE BUDGET PROCESSES BY PROCESS GROUP Monitoring and Controlling 7.1 Plan Costs Management 7.4 Control Costs 7.2 Estimate Costs 7.3 Determine Budget DETERMINE BUDGET
More informationSouth Sudan Common Humanitarian Fund Allocation Process Guidelines
South Sudan Common Humanitarian Fund Allocation Process Guidelines 27 January 2012 ACRONYMS AB CAP CERF CHF HC HCT HFU ISWG NCE NGO OCHA OPS PPA PRT PUNO TOR UN UNDP Advisory Board Consolidated Appeal
More informationJune 10 th, 2015 / Ankara, Turkey
L O G I C A L F R A M E W O R K A P P R O A C H June 10 th, 2015 / Ankara, Turkey ANALYSIS PHASE 1. Problem Analysis 2. Stakeholder Analysis 3. Objective Analysis 4. Strategy Analysis PLANNING PHASE 1.
More informationREQUEST FOR PROPOSALS RFP #6570 EXHIBIT 3: SCOPE OF WORK
Materials Management Department 901-B Texas Street Denton, Texas 76209 REQUEST FOR PROPOSALS RFP #6570 EXHIBIT 3: SCOPE OF WORK The City of Denton is seeking the best value solution for the: SUPPLY OF
More informationExam Questions PMI-RMP
Exam Questions PMI-RMP PMI Risk Management Professional https://www.2passeasy.com/dumps/pmi-rmp/ 1. You are the project manager of a new project in your organization. You and the project team have identified
More informationStochastic Modelling: The power behind effective financial planning. Better Outcomes For All. Good for the consumer. Good for the Industry.
Stochastic Modelling: The power behind effective financial planning Better Outcomes For All Good for the consumer. Good for the Industry. Introduction This document aims to explain what stochastic modelling
More informationPersonal Financial Profiling
Personal Financial Profiling Introduction Many financial decisions are made in situations of uncertainty, and so risk is involved. Different people are comfortable with different levels of risk. Unlike,
More informationCity of Cleveland Professional Services Contracts Reimbursables Policy 01/01/2014
City of Cleveland Professional Services Contracts Reimbursables Policy 01/01/2014 The following constitutes the City of Cleveland s Reimbursables policies to be used in the City s Professional Services
More informationE. Financial Feasibility Study
E. Financial Feasibility Study 1. Overview i. Scope and Methodology The Scope of Services under the Contract calls for the Financial Feasibility Study to: Assess whether the Program will be self-sustaining.
More informationRisk Profiling System FinaMetrica
Risk Profiling System FinaMetrica The FinaMetrica risk profiling system has become an important part of the know your client process for more than 3,000 largely independent high end financial advisers
More informationManaging Project Risks. Dr. Eldon R. Larsen, Marshall University Mr. Ryland W. Musick, West Virginia Division of Highways
Managing Project Risks Dr. Eldon R. Larsen, Marshall University Mr. Ryland W. Musick, West Virginia Division of Highways Abstract Nearly all projects have risks, both known and unknown. Appropriately managing
More informationRecognizing and Mitigating Risk in Acquisition Programs
Professional Development Institute June 1-3, 2016 Recognizing and Mitigating Risk in Acquisition Programs D e b r a E. H a h n d e b b i e. h a h n @ d a u. m i l 703-805- 2830 1 Exercise 1 1. Define risk
More informationOREGON STATE UNIVERSITY CM/GC CONTRACT. (Construction Manager/General Contractor)
OREGON STATE UNIVERSITY CM/GC CONTRACT (Construction Manager/General Contractor) THE CONTRACT IS BETWEEN: OWNER: Oregon State University And CONSTRUCTION MANAGER/ GENERAL CONTRACTOR (referred to as Contractor
More informationDecommissioning Basis of Estimate Template
Decommissioning Basis of Estimate Template Cost certainty and cost reduction June 2017, Rev 1.0 2 Contents Introduction... 4 Cost Basis of Estimate... 5 What is a Basis of Estimate?... 5 When to prepare
More informationBEST FINANCIAL MANAGEMENT PRACTICES SELF-ASSESSMENT INSTRUMENT FOR FLORIDA SCHOOL DISTRICTS
REPORT NO. 97-34 BEST FINANCIAL MANAGEMENT PRACTICES SELF-ASSESSMENT INSTRUMENT FOR FLORIDA SCHOOL DISTRICTS January 1998 Florida Legislature Office of Program Policy Analysis and Government Accountability
More information1. INTRODUCTION. 5. A budget proposal for the biennium is provided separately in document CX/EXEC 16/71/7 Add. 1.
E Agenda Item 13.1 CX/CAC 18/41/14 June 2018 JOINT FAO/WHO FOOD STANDARDS PROGRAMME CODEX ALIMENTARIUS COMMISSION 41 st Session FAO Headquarters, Rome, Italy, 2 6 July 2018 CODEX BUDGETARY FINANCIAL MATTERS:
More informationProject Integration Management
Project Integration Management The Key to Overall Project Success: Good Project Integration Management Project managers must coordinate all of the other knowledge areas throughout a project s life cycle.
More informationHaeryip Sihombing 1. Risk. Risk Management
Project Management Managing Risk 7 Haeryip Sihombing Universiti Teknikal Malaysia Melaka (UTeM) BMFP 4542 1 2 Risk Management Process The Risk Event Graph Risk Uncertain or chance events that planning
More informationProject Risk Management
Project Skills Team FME www.free-management-ebooks.com ISBN 978-1-62620-986-4 Copyright Notice www.free-management-ebooks.com 2014. All Rights Reserved ISBN 978-1-62620-986-4 The material contained within
More informationAllegan County Courthouse Square
Allegan County Courthouse Square Master Plan Charrette Report Draft Executive Summary Date: August 4, 2014 Prepared By: Index to Report Executive Summary A. Introduction 1. Charrette Goals and Objectives.
More informationPMI - Dallas Chapter. PMP Exam Sample Questions
PMI - Dallas Chapter PMP Exam Sample Questions June 4, 1999 Disclaimer: These questions are intended for study purposes only. Success on these questions is not necessarily predictive of success on the
More informationDepartment of Industrial Engineering
Department of Industrial Engineering Engineering Project Management Presented By Dr. Abed Schokry Chapter 15: Cost Control Learning Outcomes After completing this chapter students should be able to: Define
More informationChange Order Guidelines: Quick Reference
ELECTRI International The Foundation for Electrical Construction, Inc. PRODUCTIVITY ENHANCEMENT Change Order Guidelines: Quick Reference ELECTRI International 3 Bethesda Metro Center, Suite 1100 Bethesda,
More informationProject Management Professional (PMP) Exam Prep Course 06 - Project Time Management
Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management Slide 1 Looking Glass Development, LLC (303) 663-5402 / (888) 338-7447 4610 S. Ulster St. #150 Denver, CO 80237 information@lookingglassdev.com
More informationSPECIAL TENDER CONDITIONS FOR THE
Page 1 SPECIAL TENDER CONDITIONS FOR THE Integrated Applications Promotion (IAP) Programme (CALL FOR PROPOSALS) FEASIBILITY STUDIES Page 2 A. INTRODUCTION The following documents are available on http://emits.esa.int/
More informationANNOUNCEMENT. This request for qualifications seeks the following type of service providers:
ANNOUNCEMENT REQUEST FOR STATEMENT OF QUALIFICATIONS NOTICE FOR ENGINEERING SERVICES BY SAN FRANCISCO UNIFIED SCHOOL DISTRICT FACILITIES DESIGN AND CONSTRUCTION The San Francisco Unified School District
More informationRequest for Fee Proposals (RFFP) Progressive Design-Build Services. New High School
Request for Fee Proposals (RFFP) Progressive Design-Build Services New High School Issaquah School District February 12, 2018 TABLE OF CONTENTS 1. INTRODUCTION 2. PROJECT OVERVIEW 3. APPLICATION OF FEE
More informationSelf-Assessment Questions for Module 07 Project Cost Management
Self-Assessment Questions for Module 07 Project Cost Management Question 1: Which of the following regarding Analogous Estimating and Parametric Estimating is incorrect? A.) Parametric Estimating uses
More informationJob Order Contracting Mandatory Pre-Bid Conference
County of Fresno Internal Services Department Job Order Contracting Mandatory Pre-Bid Conference FOR SOLICITATION OF BID 912-5020 JOB ORDER CONTRACT JANUARY 6 TH 2012 1 Agenda Part I: The Job Order Contracting
More informationWHY ARE PROJECTS ALWAYS LATE?
WHY ARE PROJECTS ALWAYS LATE? (what can the Project Manager DO about that?) Craig Henderson, MBA, PMP ARVEST Bank Operations Introduction PM Basics FIO GID KISS (Figure it out) (Get it done) (Keep it simple,
More informationTest Bank for Cost Accounting A Managerial Emphasis 15th Edition by Horngren
Test Bank for Cost Accounting A Managerial Emphasis 15th Edition by Horngren Link download full: https://testbankservice.com/download/test-bank-for-for-costaccounting-a-managerial-emphasis-15th-edition-by-horngren/
More informationREQUEST FOR PROPOSALS FOR FACILITY DESIGN SERVICES: CITY HALL & COUNCIL CHAMBERS RENOVATION & ADA COMPLIANCE PROJECT
REQUEST FOR PROPOSALS FOR FACLTY DESGN SERVCES: CTY HALL & COUNCL CHAMBERS RENOVATON & ADA COMPLANCE PROJECT Proposals must be received no later than 2:00 p.m. Friday September 4 2015 Questions with regard
More informationFINANCING AND BUDGETING POLICIES
FINANCING AND BUDGETING POLICIES LOW BUDGET Production Program FINANCING AND BUDGETING POLICIES Low Budget Production Program 1 Table of Contents Summary of fee and rate thresholds...3 A. Digital Media
More information1 Exam Prep Builder s Guide to Accounting (2)
1 Exam Prep Builder s Guide to Accounting (2) 1. All the following are normally required for a loan application except. A. an income statement B. a balance sheet C. a tax return D. retained earnings 2.
More informationSPECIAL CONDITIONS OF TENDER
Page 1 SPECIAL CONDITIONS OF TENDER A. INTRODUCTION The following documents are available on http://emits.esa.int/ under "Reference Documentation" --> "Administrative Documents": ESA Procurement Regulations
More informationProject Management Initial Steps
Table of Contents Table of Contents...1 Introduction...1 Basic Project Management Outline...1 Managing Resources - People, Equipment, and Material...2 Managing Time and Schedule...3 Managing Costs, Money,
More informationBrief course information Strategic planning and project selection Project integration management Project scope management
Brief course information Strategic planning and project selection Project integration management Project scope management Total Quality Project Management 2 This is an individual work. Each student prepares
More informationpm4dev, 2015 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS
pm4dev, 2015 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development
More informationKPMG Major Projects Advisory Project Leadership Series: Budgeting, Estimating, and Contingency Management for Construction Projects
KPMG Global Energy Institute KPMG International KPMG Major Projects Advisory Project Leadership Series: Budgeting, Estimating, and Contingency Management for Construction Projects Construction projects
More informationRisk Management User Guide. Prepared By: Neville Turbit Version Feb /01/2009 Risk Management User Guide Page 1 of 36
Risk Management User Guide Prepared By: Neville Turbit Version 1.0 1 Feb 09 22/01/2009 Risk Management User Guide Page 1 of 36 Table of Contents Document Origin...2 Change History...2 Risk Guidelines...
More information'!'? /~tji'wi; O}. /Y- ~I/
Republic of the Philippines DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS OFFICE OF THE SECRETARY Manila MAR 1lt 2011 '!'? /~tji'wi; O}. /Y- ~I/ DEPARTMENT 12 ORDER NO. Series of 201 (D~.If/'11 SUBJECT: PREPARATION
More informationEstimating Fallacies. Estimating Fallacies excessive detail does not help.
Estimating Fallacies 1 January 27-30, 2013 New Orleans Patrick Weaver PMP, PMI-SP A critique of the PMI Practice Standard for Estimating and the idea that 'bottom up' estimating always equals improved
More informationSWEN 256 Software Process & Project Management
SWEN 256 Software Process & Project Management Plan: Identify activities. No specific start and end dates. Estimating: Determining the size & duration of activities. Schedule: Adds specific start and end
More informationDALLAS-FORT WORTH INTERNATIONAL AIRPORT
DALLAS-FORT WORTH INTERNATIONAL AIRPORT ADDENDUM NO. 2 TO THE REQUEST FOR BIDS Contract No. 9500325 ATSAC II IN-LINE EDS BAGGAGE HANDLING SYSTEM May 6, 2008 THE REQUEST FOR BIDS (RFB) FOR THE ABOVE IS
More informationThe Productivity Imperative Corporate Real Estate Trends for Banking and Financial Services
The Productivity Imperative 2013 Corporate Real Estate Trends for Banking and Financial Services Perhaps more than any other industry, the financial services sector has been challenged by the simultaneous
More informationProject Planning Unveiled
Project Planning Unveiled Mark Norman Oxford University Computing Services 16 November 2006 1 An introduction? Me a project manager? You?? This isn't a technical course! Although we will have a look at
More informationOMDC Interactive Digital Media Fund Budgeting and Financing Guidelines For 2018 Deadlines - updated February 2018
OMDC Interactive Digital Media Fund Budgeting and Financing Guidelines For 2018 Deadlines - updated February 2018 Templates Note regarding the Budget, Summary of Related Party Transactions, Financing Plan
More informationfor Major Infrastructure Projects
for Major Infrastructure Projects Presented by: Pedram Daneshmand Senior Associate Director 4 th Annual Contract Selection and Risk for Major Projects, March 2011 Agenda Brief Introduction Project Delivery
More information