SECTOR ASSESSMENT (SUMMARY): CHHATTISGARH ROAD SECTOR. 1. Sector Performance, Problems, and Opportunities

Size: px
Start display at page:

Download "SECTOR ASSESSMENT (SUMMARY): CHHATTISGARH ROAD SECTOR. 1. Sector Performance, Problems, and Opportunities"

Transcription

1 Chhattisgarh State Road Sector Project (RRP IND 44427) Sector Road Map SECTOR ASSESSMENT (SUMMARY): CHHATTISGARH ROAD SECTOR 1. Sector Performance, Problems, and Opportunities 1. The state of Chhattisgarh was formed on 1 November The Chhattisgarh region was carved out of Madhya Pradesh to form the new state. Chhattisgarh state has a total area of 135,194 square kilometers (km 2 ) and a population of 21 million as of It has 27 districts. Chhattisgarh is surrounded by six states: Andhra Pradesh, Jharkhand, Madhya Pradesh, Maharashtra, Orissa, and Uttar Pradesh. Because of its location, traffic from these surrounding states passes through its state road and rail network. Railways in the state have limited coverage, comprising a total length of about 1,187 km, and serve mainly the needs of interstate traffic. Civil aviation, ports, and inland waterways have a very limited role in the state s transport services. As a result, roads are the predominant mode of transport services in the state. 2. Chhattisgarh is rich in natural resources and is a major producer of coal, iron ore, and other minerals. This has contributed to the high economic growth of the state. Chhattisgarh is a major producer of cement and steel and is a power surplus state. It also has a large agricultural base and ranks third in rice production in the country. 3. The total road network of the state was 74,434 km as of The road network managed by Chhattisgarh Public Works Department (CGPWD) is presented in Table 1. The rest of the road network is managed by village panchayats (local self-administration at the village level in India), communities, urban local bodies, and the Forest Department. Chhattisgarh Rural Road Development Authority developed 16,838 km of rural roads until 2010 under the central government funded PMGSY. 2 Road density in Chhattisgarh is well below the national average, at 55.1 km per 100 km 2 against the Indian average of 125 km per 100 km 2. This is partly because of the large forest cover (44%). Table 1: Details of Road Network under Chhattisgarh Public Works Department No. Class of Road Length (km) 1 National highways 2,226 2 State highways 5,240 3 Major district roads 10,539 4 Other district roads and rural roads 13,798 Total Length 31,803 km = kilometer. Source: Chhattisgarh Public Works Department 4. All national highways, 85% of state highways and the major district roads, and 46% of other district roads have sealed (i.e., bitumen or concrete) surfaces. Overall, 34% of the roads managed by CGPWD remain unsealed. Only a small percentage of the national highways have four-lane carriageways, increasing to 20% under capacity augmentation works in progress. Of the remaining national highway sections, about two-thirds have two-lane carriageways and the rest have single-lane carriageways. In terms of road width, 30% of the state highways have two lanes and the remaining 70% have single- or intermediate-lane carriageways. 3 Most of the major and other district roads in the state are single lanes. The majority of the state road network needs 1 Government of India, Ministry of Home Affairs, Office of Registrar General & Census Commissioner Census of India New Delhi. 2 Pradhan Mantri Gram Sadak Yojana, a rural road development program funded by the Government of India through the Ministry of Rural Development. The Asian Development Bank (ADB) is also providing funding support for this program. 3 Intermediate lane roads have a width of meters (m), which is narrower than two-lane roads (7.0 m).

2 2 widening and strengthening to cater to the increasing traffic demand. Chhattisgarh lacks an adequate road network to support the required mobility between areas with natural resources, industrial centers, and economic development zones; and to provide better access to social amenities for its population. 5. The number of motorized vehicles registered in the state increased from 0.8 million in 2001 to 2.2 million in 2010, representing an average annual increase of 12.0%. Of the 2.2 million registered motor vehicles on the road in 2010, 80.5% were two-wheelers, 4.8% were cars and jeeps, 4.9% were commercial trucks, 1.7% were buses and minibuses, and 7.2% were tractors and trailers. The average annual vehicle growth observed during was 11.7% for two-wheelers, 14.4% for cars, 13.1% for buses, and 13.5% for trucks. These growth rates are much higher than those observed nationally, especially in the case of cars, buses, and trucks owing to the higher growth of the industrial sector at 13.2% per annum during the period. 6. The Ministry of Road Transport and Highways (MORTH) is responsible for all the national highways. MORTH has delegated the development and management of the major national highway sections to the National Highway Authority of India (NHAI) and the rest of the national highways in Chhattisgarh to CGPWD. CGPWD also develops and manages all state highways and district roads, in addition to the national highway sections delegated by MORTH. District and local administrations manage rural and village roads. Chhattisgarh Rural Road Development Authority is responsible for developing rural and village roads, funded through special schemes initiated by the central government, and hands them over to district and local bodies after the development and maintenance period of 3 5 years. 7. The engineer-in-chief of CGPWD, who reports to the CGPWD principal secretary, is the technical head of department and advisor to the state government on policy and implementation related to public works. CGPWD is organized into six zones headed by chief engineers, under which 12 civil and two electrical and mechanical circle offices are headed by superintendent engineers. Superintendent engineers are responsible for 3 4 works divisions, which are the basic operating units headed by executive engineers. The 27 districts have 51 divisions. 8. Budgetary allocation and expenditure for state roads during is in Table 2. The overall budget utilization has been about 92% with a plan budget utilization of 91% and non-plan budget utilization of 95%. While the average budget allocation in these 4 years was Rs13,700 million, the budget allocation for FY rose to Rs17,316 million (a 26.6% increase over the average) and the FY allocation increased to Rs23,912 million (74.5% increase). In addition to the roadworks undertaken by CGPWD, the PMGSY scheme upgraded rural roads with total lengths of 7,714 km by 2007 and 16,838 km by The allocation for road maintenance was on average around Rs2,800 million until FY , and has been increased to Rs3,040 million in FY and Rs5,675 million in FY The budget allocation for road maintenance in FY was assessed to fully meet the maintenance needs for the state highway network and the Government of Chhattisgarh is committed to maintain a similar level of budget for road maintenance works. 9. Revenues relating to road use including registration fees and vehicle, passenger, and goods taxes were Rs5,089 million in FY in Chhattisgarh, which increased from Rs1,249 million in FY The average annual increase was 15.1%, in line with the growth in vehicle registration in the state. Chhattisgarh Transport Department has introduced online payments, making payments easier as well as increasing the efficiency of collection.

3 Table 2: Chhattisgarh Public Works Department Budget Allocation and Expenditure for Roadworks (Rs million) Item FY FY FY FY Total for 4 years A. Budget Allocation Plan Budget 10, , , , ,480.6 Non-plan Renewal and maintenance 3, , , , ,180.5 Non-plan Wages and salaries , , ,135.8 Total 14, , , , ,796.9 B. Expenditure Plan Budget 10, , , , ,921.5 Non-plan Renewal and maintenance 3, , , , ,608.8 Non-plan Wages and salaries , ,999.6 Total 14, , , , ,529.9 Note: The wages and salaries component is estimated proportionately to the budget allocation for roadworks. Source: Chhattisgarh Public Works Department. 2. Government s Sector Strategy 10. Chhattisgarh s road network is in need of capacity augmentation and upgrading as demand for road transport is increasing. The government of Chhattisgarh (GOC) formulated a road policy in 2002 for road sector development and a Master Plan for Road Sector Development for The master plan was updated in 2006 for implementation during under technical assistance provided by the Asian Development Bank (ADB). 4 Although the allocation for road maintenance was increased to Rs3,040 million in FY and Rs5,675 million in FY , maintenance is undertaken as identified at each divisional level and systematic maintenance planning is yet to be established. 11. In addition to the road upgrading by CGPWD, the state government is upgrading 1,000 km of national highway sections and 560 km of state highways with private sector participation either as Build-Operate-Transfer (BOT) project or annuity-based projects. However, a large part of the state highways as well as district roads remain in need of upgrading. The state faces capacity constraints in project implementation and delays in project preparation, and the approval process has caused the allocated budget not to be fully utilized in the past. a. Sector Institution Framework 12. The GOC has undertaken a major initiative to modernize the functioning of CGPWD, with computerization of operations, by developing an integrated organization-wide management information system with an accounts management system, works management system, establishment management system, and contractor management system. The accounts management system has been fully developed and is operational. The online payment system is expected to be operational in E-tendering for procurement of contracts has also been successfully implemented across all departments and agencies of the GOC. Implementation of other system modules such as project management, works and stores management, planning and maintenance management will enable further modernization of CGPWD operations. b. Private Sector Participation 13. The road policy adopted by the GOC in 2002 has encouraged private sector participation in road development. The state has initiated the Chhattisgarh Accelerated Road Development Program on a public private partnership basis, with an objective of developing about 1,500 km. 3 4 ADB Technical Assistance to India for the Chhattisgarh State Roads Development. Manila (TA 3995-IND).

4 4 CGPWD is pursuing feasibility studies to develop projects to be implemented as public private partnership projects. c. Road Safety 14. The road accident rate in Chhattisgarh was 12.3 fatalities per 10,000 vehicles in 2010, decreasing from 16.9 in However, fatalities increased in absolute numbers by almost 30% from 2,258 in 2005 to 2,956 in With the improvement in roads and increase in speed, potential for traffic accidents may increase unless road safety features are incorporated in the project design with increased road safety education and enforcement. Traffic safety on the state road network needs to be monitored continuously. d. Control of Overloading 15. The legal framework is in place to control overloading of vehicles, but no inspection, surveillance, and enforcement system exists to impose it. Enforcement staff inspects only a small percentage of total truck traffic and uses the goods information to assess the loading and impose fines if overloading is identified. Chhattisgarh Transport Department is establishing integrated border checkpoints on the main entry points of the national highways, with automated weighing machines. However, control of overloading on state highways is very limited. 3. ADB Sector Experience and Assistance Program 16. ADB s first involvement in Chhattisgarh s state road sector development started with project preparatory TA in 2002 (footnote 3) and with a loan in December The project, through the sector lending modality, rehabilitated 1,249 km of state roads. The road construction works were implemented under 21 civil works contracts supervised by three consulting firms. ADB also provided technical assistance for institutional strengthening and capacity building for the state roads sector management in Chhattisgarh (footnote 3). Besides introducing and building capacity in business processes, a master plan for the state roads sector was developed, which demonstrated a rational approach to road planning and provided a scientific basis for the selection and prioritization of future investment schemes in the road transport subsector. The executing agency for the project and the technical assistance was CGPWD. The project was successfully completed in July 2011 and financially closed in April Implementation of the Chhattisgarh State Road Development Sector Project faced challenges, including (i) inadequate experience of CGPWD in planning and formulating projects of similar size and complexity; and (ii) shortage of technical staff, leading to severe capacity constraints due to lack of knowledge in applying standard business procedures, (iii) delays in project implementation, and (iv) security difficulties in certain areas of the state. CGPWD improved its capacity during project implementation, with support from supervision consultants and capacity building consultants. As a result of regular policy dialogue with ADB and the state government s commitment to enhance sustainability in road sector management, CGPWD recruited about 450 engineers after several years of embargo on new recruitment for government departments. The proposed project was prepared with the improved capacity of CGPWD, and detailed design of adequate quality was prepared with the budget from CGPWD. To continue to support road sector development in Chhattisgarh and improve the capacity of CGPWD, this proposed project was included in the India country operations business plan, ADB Report and Recommendation of the President to the Board of Directors: Proposed Loan to India for the Chhattisgarh State Roads Development Sector Project. Manila (Loan 2050-IND). 6 ADB Country Operations Business Plan: India, Manila.

5 5 PROBLEM TREE EFFECTS Limited access to economic opportunities Limited access to social services CORE PROBLEM Poor road network connectivity and road quality within Chhattisgarh CAUSES <Physical> <Non-Physical> Low quality of existing roads caused by lack of provision for proper maintenance Limited network capacity (no new investment) Limited capacity for development of projects and roads asset management Poor road safety on existing roads Interventions Financing support by proposed loan Capacity development programs supported by Technical Assistance

6 Table 2: Sector Results Framework, Chhattisgarh Transport and Communications Sector, Country Sector Outcomes Country Sector Output ADB Sector Operations Outcomes with ADB Contributions Balanced development of the road network nationwide during the 11th Five-Year Plan Improved mobility and accessibility with wider roads, better riding quality, better road safety, and world-class wayside amenities catering to the growing demand for road services Indicators with Targets and Baselines Road density in Chhattisgarh increased from 55.1 km per 100 km 2 towards the national average of 125 km per 100 km 2 The remaining 60% of one-lane state highways in Chhattisgarh are upgraded Output with ADB Contributions Building and upgrading of state highways Institutional strengthening and capacity building Indicators with Incremental Targets Chhattisgarh s state highways network of 916 km improved ADB = Asian Development Bank, km = kilometer, km 2 = square kilometer. Source: Asian Development Bank. Planned and Ongoing ADB Interventions Planned key activity areas Rural roads (50% of funds) State Roads (50% of funds) Pipeline projects with estimated amounts Chhattisgarh State Road Sector Project ($300 million) Ongoing projects with approved amounts Rural Roads Sector II Investment Program (Project 5, Chhattisgarh component: $222.2 million) Rural Connectivity Investment Program ($252 million in 5 States including about 30% of loan amount for Chhattisgarh) 6 Main Output Expected from ADB Contributions Planned key activity areas 1,335 km of rural roads constructed and improved 916 km of State Roads improved Pipeline projects 916 km of State Roads improved Ongoing projects 1,335 km of rural roads constructed and improved

SECTOR ASSESSMENT (SUMMARY): ROAD TRANSPORT (NON-URBAN)

SECTOR ASSESSMENT (SUMMARY): ROAD TRANSPORT (NON-URBAN) Second Jharkhand State Road Project (RRP IND 49125) SECTOR ASSESSMENT (SUMMARY): ROAD TRANSPORT (NON-URBAN) A. Sector Performance, Problems, and Opportunities 1. State context. The state of Jharkhand was

More information

ECONOMIC AND FINANCIAL ANALYSES FOR TRANCHE 2

ECONOMIC AND FINANCIAL ANALYSES FOR TRANCHE 2 Appendix 6 ECONOMIC AND FINANCIAL ANALYSES FOR TRANCHE 2 1. Background. The Second Rural Connectivity Investment Program will support the Government of India in improving rural connectivity through the

More information

ECONOMIC AND FINANCIAL ANALYSIS

ECONOMIC AND FINANCIAL ANALYSIS Bihar New Ganga Bridge Project (RRP IND 48373) ECONOMIC AND FINANCIAL ANALYSIS A. Introduction 1. The proposed project is to build a new six-lane bridge across the Ganges River near Patna in the state

More information

Report and Recommendation of the President to the Board of Directors

Report and Recommendation of the President to the Board of Directors Report and Recommendation of the President to the Board of Directors Sri Lanka Project Number: 41127 August 2008 Proposed Loan India: Bihar State Highways Project CURRENCY EQUIVALENTS (as of 25 August

More information

Validation Report. India: Rural Roads Sector I Project. Independent Evaluation Department

Validation Report. India: Rural Roads Sector I Project. Independent Evaluation Department Validation Report Reference Number: PVR-307 Project Number: 36320 Loan Number: 2018 May 2014 India: Rural Roads Sector I Project Independent Evaluation Department ABBREVIATIONS ADB Asian Development Bank

More information

SECTOR ASSESSMENT (SUMMARY): ROAD TRANSPORT

SECTOR ASSESSMENT (SUMMARY): ROAD TRANSPORT A. Sector Road Map Road Improvement and Institutional Development Project (RRP PHI 41076) SECTOR ASSESSMENT (SUMMARY): ROAD TRANSPORT 1. Sector Performance, Problems and Opportunities 1. Roads provide

More information

Road and Transport : Registered Motor Vehicles per 1000 Population and % Share of Registered Motor

Road and Transport : Registered Motor Vehicles per 1000 Population and % Share of Registered Motor and Transport 13.1: Surfaced & Length s in Arunachal Pradesh (A.P.) 13.2: Length of National Highways 13.3: Lane-wise Length of National Highways 13.4: and Surfaced Length of other PWD s 13.5: Length of

More information

ROAD DEVELOPMENT IN INDIA

ROAD DEVELOPMENT IN INDIA ROAD DEVELOPMENT IN INDIA - 2010 This report is the most up-to-date and comprehensive review of the Indian road sector. The report provides: The latest status of projects, programmes and policies (as on

More information

ECONOMIC AND FINANCIAL ANALYSIS

ECONOMIC AND FINANCIAL ANALYSIS South Asia Subregional Economic Cooperation Chittagong-Cox s Bazar Railway Project, Phase 1 (RRP BAN 46452-002) A. Introduction ECONOMIC AND FINANCIAL ANALYSIS 1. The proposed project will construct 102

More information

India: National Highway Sector II Project

India: National Highway Sector II Project Validation Report October 2017 India: National Highway Sector II Project Reference Number: PVR-517 Project Number: 35335-013 Loan Number: 2154 ABBREVIATIONS ADB Asian Development Bank CSC construction

More information

SECTOR ASSESSMENT (SUMMARY): TRANSPORT (ROAD TRANSPORT [NONURBAN])

SECTOR ASSESSMENT (SUMMARY): TRANSPORT (ROAD TRANSPORT [NONURBAN]) CAREC Corridors 1 and 6 Connector Road (Aktobe Makat) Reconstruction Project (RRP KAZ 48424) SECTOR ASSESSMENT (SUMMARY): TRANSPORT (ROAD TRANSPORT [NONURBAN]) 1. Sector Performance, Problems, and Opportunities

More information

Rural Road Connectivity in India

Rural Road Connectivity in India www.swaniti.in Rural Road Connectivity in India The 12th Five Year Plan (2012-17) identifies rural connectivity as one of the key priorities to achieve rural poverty alleviation and development. With over

More information

Multitranche Financing Facility India: Rural Road Sector II Investment Program (Project 1)

Multitranche Financing Facility India: Rural Road Sector II Investment Program (Project 1) Validation Report Reference Number: PVR-326 Project Number: 37066 Loan Number: 2248 October 2014 Multitranche Financing Facility India: Rural Road Sector II Investment Program (Project 1) Independent Evaluation

More information

SECTOR ASSESSMENT (SUMMARY): TRANSPORT 1

SECTOR ASSESSMENT (SUMMARY): TRANSPORT 1 Country Partnership Strategy: Viet Nam, 2012 2015 SECTOR ASSESSMENT (SUMMARY): TRANSPORT 1 Sector Road Map 1. Sector Performance, Problems, and Opportunities 1. Investment in the transport sector in Viet

More information

Dr. Pramod Kumar Anand JS (RC) & DG, NRRDA : : : D.O. # P-10021/1/2010/P-III August 4, 2010

Dr. Pramod Kumar Anand JS (RC) & DG, NRRDA : : : D.O. # P-10021/1/2010/P-III August 4, 2010 Dr. Pramod Kumar Anand JS (RC) & DG, NRRDA : 23383553 : 23388207 : anandpk@nic.in D.O. # P-10021/1/2010/P-III August 4, 2010 Dear Shri As you are aware, Government of India launched the Pradhan Mantri

More information

SECTOR ASSESSMENT (SUMMARY): TRANSPORT

SECTOR ASSESSMENT (SUMMARY): TRANSPORT SECTOR ASSESSMENT (SUMMARY): TRANSPORT 1 Sector Road Map 1. Sector Performance, Problems, and Opportunities 1. Myanmar is the largest country in the Greater Mekong Subregion (GMS) with a total land area

More information

People s Republic of Bangladesh: Updating the Road Master Plan

People s Republic of Bangladesh: Updating the Road Master Plan South Asia Subregional Economic Cooperation Dhaka Northwest Corridor Road Project, Phase 2 (RRP BAN 40540) Technical Assistance Report Project Number: 40540-016 Transaction Technical Assistance (TRTA)

More information

SECTOR ASSESSMENT (SUMMARY): FINANCE

SECTOR ASSESSMENT (SUMMARY): FINANCE Country Partnership Strategy: Bhutan, 2014 2018 SECTOR ASSESSMENT (SUMMARY): FINANCE Sector Road Map 1. Sector Performance, Problems, and Opportunities 1. Bhutan s finance sector developed steadily during

More information

India: Public Private Partnerships in Highways Sector

India: Public Private Partnerships in Highways Sector India: Public Private Partnerships in Highways Sector Prepared by World Bank as input for IDA paper, 2008 (provided by Tarun Sankar, PPIAF office, South Asia) India s transport program is one of the most

More information

Presentation at Asian Highways Investment Forum. Performance based Maintenance Contracts for Highways

Presentation at Asian Highways Investment Forum. Performance based Maintenance Contracts for Highways Presentation at Asian Highways Investment Forum Bangkok, 8-9, October 2013 United Nations Economic & Social Commission For Asia & The Pacific Performance based Maintenance Contracts for Highways By Atul

More information

Bangladesh: Road Maintenance and Improvement Project

Bangladesh: Road Maintenance and Improvement Project Performance Evaluation Report Bangladesh: Road Maintenance and Improvement Project Independent Evaluation Performance Evaluation Report December 2014 Bangladesh: Road Maintenance and Improvement Project

More information

THE ROAD TO ECONOMIC GROWTH

THE ROAD TO ECONOMIC GROWTH THE ROAD TO ECONOMIC GROWTH Introduction 1. As in many countries, the road sector accounts for the major share of domestic freight and inter-urban passenger land travel in Indonesia, playing a crucial

More information

Development, Govt. of India, and 40% funded by Govt. Madhya Pradesh.

Development, Govt. of India, and 40% funded by Govt. Madhya Pradesh. MADHYA PRADESH RURAL ROAD DEVELOPMENT AUTHORITY (AN AGENCY OF PANCHYAT & RURAL DEVELOPMENT DEPARTMENT, GOVT. OF M.P.) 5 th Floor, Block-II, Paryavas Bhawan, BHOPAL M.P. 462 011 PRADHANMANTRI GRAM SADAK

More information

Investment in Infrastructure

Investment in Infrastructure 14 Investment in Infrastructure INTRODUCTION 14.1 The Eleventh Plan emphasized the importance of investment in infrastructure for achieving a sustainable and inclusive growth of 9 to 10 per cent in GDP

More information

COST BENEFIT ANALYSIS OF CHENNAI PERIPHERAL ROAD

COST BENEFIT ANALYSIS OF CHENNAI PERIPHERAL ROAD COST BENEFIT ANALYSIS OF CHENNAI PERIPHERAL ROAD 1 Introduction The objective of the cost benefit economic analysis is to identify and quantify the benefits and costs associated with the project. This

More information

ECONOMIC AND FINANCIAL ANALYSIS

ECONOMIC AND FINANCIAL ANALYSIS Additional Financing of National Motorway M-4 Gojra Shorkot Khanewal Section Project (RRP PAK 48402) ECONOMIC AND FINANCIAL ANALYSIS A. General 1. Roads are the main mode of transport in Pakistan, accounting

More information

Report and Recommendation of the President to the Board of Directors

Report and Recommendation of the President to the Board of Directors Report and Recommendation of the President to the Board of Directors Project Number: 40423 June 2012 Proposed Multitranche Financing Facility, Technical Assistance, and Administration of Technical Assistance

More information

ECONOMIC ANALYSIS. A. Introduction

ECONOMIC ANALYSIS. A. Introduction Bridge Replacement for Improved Rural Access Sector Project (RRP PNG 43200) ECONOMIC ANALYSIS A. Introduction 1. The economic analysis of the proposed project has been carried out in accordance with ADB

More information

Economic Analysis Concepts

Economic Analysis Concepts Economic Analysis Concepts Questions & Decisions (1) Is the project justified?- Are benefits greater than costs? Which is the best investment if we have a set of mutually exclusive alternatives? If funds

More information

SECTOR ASSESSMENT (SUMMARY): FINANCE 1

SECTOR ASSESSMENT (SUMMARY): FINANCE 1 Policy-Based Loan for Subprogram 3 of the Third Financial Sector Program (RRP CAM 42305) SECTOR ASSESSMENT (SUMMARY): FINANCE 1 1. Sector Performance, Problems, and Opportunities 1. Overall finance sector.

More information

ROLE OF INFRASTRUCTURE IN PROMOTING ECONOMIC GROWTH IN INDIA

ROLE OF INFRASTRUCTURE IN PROMOTING ECONOMIC GROWTH IN INDIA Volume 5, Issue 3 (March, 2016) Online ISSN-2277-1166 Published by: Abhinav Publication Abhinav National Monthly Refereed Journal of Research in ROLE OF INFRASTRUCTURE IN PROMOTING ECONOMIC GROWTH IN INDIA

More information

ECONOMIC ANALYSIS. Table 1: Total Cost Estimate (Economic Costs) (CNY million)

ECONOMIC ANALYSIS. Table 1: Total Cost Estimate (Economic Costs) (CNY million) Jiangxi Ji an Sustainable Urban Transport Project (RRP PRC 45022) ECONOMIC ANALYSIS A. Project Costs 1. This chapter outlines the methodology and results of the economic analysis for the project, comprising

More information

NORTH LUZON, PHILIPPINES. Case Study (Transportation) Project Summary:

NORTH LUZON, PHILIPPINES. Case Study (Transportation) Project Summary: NORTH LUZON, PHILIPPINES Case Study (Transportation) Project Summary: The Republic of the Philippines is an archipelagic nation in Southeast Asia comprised of 7,107 islands. The Philippines is home to

More information

Development, Govt. of India, and 40% funded by Govt. Madhya Pradesh.

Development, Govt. of India, and 40% funded by Govt. Madhya Pradesh. MADHYA PRADESH RURAL ROAD DEVELOPMENT AUTHORITY (AN AGENCY OF PANCHYAT & RURAL DEVELOPMENT DEPARTMENT, GOVT. OF M.P.) 5 th Floor, Block-II, Paryavas Bhawan, BHOPAL M.P. 462 011 PRADHANMANTRI GRAM SADAK

More information

ASIAN DEVELOPMENT BANK RRP: IND 34420

ASIAN DEVELOPMENT BANK RRP: IND 34420 ASIAN DEVELOPMENT BANK RRP: IND 34420 REPORT AND RECOMMENDATION OF THE PRESIDENT TO THE BOARD OF DIRECTORS ON A PROPOSED LOAN TO INDIA FOR THE NATIONAL HIGHWAY CORRIDOR (SECTOR) I PROJECT November 2003

More information

Presentation Structure

Presentation Structure Enabling Access Presentation Structure Housing & Housing Finance About DHFL Aadhar A New Initiative Potential Challenge The Business Model Road Map Importance of Housing Role of Housing Finance Even in

More information

SECTOR ASSESSMENT (SUMMARY): FINANCE

SECTOR ASSESSMENT (SUMMARY): FINANCE Inclusive Financial Sector Development Program, Subprogram 1 (RRP CAM 44263 013) SECTOR ASSESSMENT (SUMMARY): FINANCE 1. Sector Performance, Problems, and Opportunities a. Sector Context and Performance

More information

Experience of Implementing Transportation PPPs in India. Abhijit Bhaumik August 6, 2015

Experience of Implementing Transportation PPPs in India. Abhijit Bhaumik August 6, 2015 Experience of Implementing Transportation PPPs in India Abhijit Bhaumik August 6, 2015 Experience of Implementing PPPs in India India has witnessed successful PPPs across several infrastructure sectors

More information

ROAD SECTOR ROAD MAP (Central Asia Regional Economic Cooperation Corridor 2 Road Investment Program)

ROAD SECTOR ROAD MAP (Central Asia Regional Economic Cooperation Corridor 2 Road Investment Program) ROAD SECTOR ROAD MAP (Central Asia Regional Economic Cooperation Corridor 2 Road Investment Program) A. Road Sector Road Map 1. Strategic Objective 1. The strategic objective of the National Road Development

More information

ALL Counties. ALL Districts

ALL Counties. ALL Districts TEXAS TRANSPORTATION COMMISSION ALL Counties rhnute ORDER Page of ALL Districts The Texas Transportation Commission (commission) finds it necessary to propose amendments to. and., relating to Transportation

More information

Technical Assistance Report

Technical Assistance Report Technical Assistance Report Project Number: 51360-002 Transaction Technical Assistance Facility (F-TRTA) April 2018 Turkmenistan: Preparing the Central Asia Regional Economic Cooperation Corridors 2, 3

More information

15 th International Road Federation World Meeting

15 th International Road Federation World Meeting 15 th International Road Federation World Meeting Bangkok, June 2005 Guang Z. Chen Sector Manager, Transport South Asia Region The World Bank Today s Presentation Principles of Road User Charges Objectives

More information

SRI LANKA ROAD SECTOR POLICY REVIEW NOTE

SRI LANKA ROAD SECTOR POLICY REVIEW NOTE SRI LANKA ROAD SECTOR POLICY REVIEW NOTE December 4, 2003 EXECUTIVE SUMMARY 1. Context. This policy note aims to: (i) facilitate the sector reform dialogue with the Government of Sri Lanka (GOSL); and

More information

HIGHWAY ENGINEERING MODULE-IV

HIGHWAY ENGINEERING MODULE-IV HIGHWAY ENGINEERING MODULE-IV 1 HIGHWAY DRAINAGE. 2 HILL ROAD 3 ROADSIDE DEVELOPMENT. 4 ROAD ADMINISTRATION AND FINANCE Prof. Ujjval J. Solanki DEPARTMENT OF CIVIL ENGINEERING, DARSHAN INSTITUTE OF ENGINEERING

More information

ECONOMIC ANALYSIS. Table 1: Vehicle Fleet Characteristics Four- Medium Car. Light Bus. Wheel Drive

ECONOMIC ANALYSIS. Table 1: Vehicle Fleet Characteristics Four- Medium Car. Light Bus. Wheel Drive Western Regional Road Corridor Investment Program (RRP MON 41193) A. Project Costs and Benefits ECONOMIC ANALYSIS 1. Project Costs. The project s capital costs include the costs of the road works, design,

More information

Contents. Alamo Area Metropolitan Planning Organization. Introduction S. St. Mary s Street San Antonio, Texas 78205

Contents. Alamo Area Metropolitan Planning Organization. Introduction S. St. Mary s Street San Antonio, Texas 78205 Contents Introduction 1 Alamo Area Metropolitan Planning Organization Tel 210.227.8651 Fax 210.227.9321 825 S. St. Mary s Street San Antonio, Texas 78205 www.alamoareampo.org aampo@alamoareampo.org Pg.

More information

Mobility / Other Modes Roger Nober Executive Vice President Law and Secretary BNSF Railway

Mobility / Other Modes Roger Nober Executive Vice President Law and Secretary BNSF Railway Mobility / Other Modes Roger Nober Executive Vice President Law and Secretary BNSF Railway Today s Discussion Urban Mobility Rural Mobility and Safety Other Modes: Mass Transportation Freight and Intercity

More information

ECONOMIC AND FINANCIAL ANALYSIS

ECONOMIC AND FINANCIAL ANALYSIS Khyber Pakhtunkhwa Provincial Roads Improvement Project (RRP PAK 47360) A. Background ECONOMIC AND FINANCIAL ANALYSIS 1. The province of Khyber Pakhtunkhwa in northwest Pakistan covers almost six degrees

More information

DEVELOPING A LOCAL GOVERNMENT TRANSPORT MASTERPLAN: CASE STUDY

DEVELOPING A LOCAL GOVERNMENT TRANSPORT MASTERPLAN: CASE STUDY DEVELOPING A LOCAL GOVERNMENT TRANSPORT MASTERPLAN: CASE STUDY Objectives of the case study J. Lebo, World Bank (1999) National or state rural planning processes are often top down, technically sophisticated

More information

Post and Telecommunications

Post and Telecommunications Post and Telecommunications This section presents operating and financial data relating to the different branches of the Department of Posts including the Post Office Savings Banks. It comprises statistics

More information

Nepal: Road Connectivity Sector I Project

Nepal: Road Connectivity Sector I Project Validation Report October 2017 Nepal: Road Connectivity Sector I Project Reference Number: PVR-523 Project Number: 37266-032 Grant Number: 0051 ABBREVIATIONS ADB Asian Development Bank DOR Department of

More information

ROADS For updated information, please visit June 2018

ROADS For updated information, please visit   June 2018 ROADS June 2018 Table of Content Executive Summary...3 Advantage India.....4 Market Overview...6 Growth Drivers...15 Key Industry Associations.....23 Useful Information....25 EXECUTIVE SUMMARY One of the

More information

SUBSCRIBE to H.G. Infra Engineering Ltd. Strong player in government s renewed focus sector

SUBSCRIBE to H.G. Infra Engineering Ltd. Strong player in government s renewed focus sector SUBSCRIBE to H.G. Infra Engineering Ltd. Strong player in government s renewed focus sector 19 th Feb. 2018 Salient features of the IPO: H.G. Infra Engineering Ltd. (HGIEL) is an infrastructure construction,

More information

Pakistan: National Highway Development Sector Investment Program Tranche 2

Pakistan: National Highway Development Sector Investment Program Tranche 2 Validation Report December 2017 Pakistan: National Highway Development Sector Investment Program Tranche 2 Reference Number: PVR-521 MFF Number: 0002 Project Number: 37559-023, 37559-033, and 37559-043

More information

CBA of transport infrastructure projects in Germany

CBA of transport infrastructure projects in Germany CBA of transport infrastructure projects in Germany Dr. Catharina Horn Federal Transport Infrastructure Planning, Investment Policy Paris, 27th of February 2014 www.bmvi.de 1. The Federal Transport Infrastructure

More information

Table 1 the Road Network of Mozambique (in kilometers)

Table 1 the Road Network of Mozambique (in kilometers) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project Name PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: AB2867 Roads

More information

Public Private Partnership in Highway Sector in Punjab, India

Public Private Partnership in Highway Sector in Punjab, India Public Private Partnership in Highway Sector in Punjab, India Infrastructure Governance Roundtable March 24 th, 2006 Kulwinder Singh Rao Deputy Project Director Punjab Roads & Bridges Development Board

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK TAR:NEP 37266 TECHNICAL ASSISTANCE (Financed by the Japan Special Fund) TO THE KINGDOM OF NEPAL FOR PREPARING THE TRANSPORT CONNECTIVITY SECTOR PROJECT June 2004 CURRENCY EQUIVALENTS

More information

Welcome to Presentation of Twelfth Five Year Plan and Annual Plan Proposal Madhya Pradesh. May 11, 2012

Welcome to Presentation of Twelfth Five Year Plan and Annual Plan Proposal Madhya Pradesh. May 11, 2012 Welcome to Presentation of Twelfth Five Year Plan and Annual Plan Proposal Madhya Pradesh May 11, 2012 1 ACHIEVEMENTS OF ELEVENTH PLAN (ECONOMY) Targets and Achievement Sector Target for Growth Expected

More information

Islamic Republic of Pakistan National Motorway M-4 (Shorkot-Khanewal Section) Project

Islamic Republic of Pakistan National Motorway M-4 (Shorkot-Khanewal Section) Project PD 00001-PAK June 6, 2016 PROJECT DOCUMENT Islamic Republic of Pakistan National Motorway M-4 (Shorkot-Khanewal Section) Project This document has a restricted distribution and may be used by recipients

More information

India: Bihar State Highways Project

India: Bihar State Highways Project Completion Report Project Number: 41127-013 Loan Number: 2443 Technical Assistance Number: 7130 August 2018 India: Bihar State Highways Project This document is being disclosed to the public in accordance

More information

ACHIEVEMENT OF TECHNICAL ASSISTANCE OUTCOMES

ACHIEVEMENT OF TECHNICAL ASSISTANCE OUTCOMES Timor-Leste: CPS 2011 2015 Final Review Validation, Linked Document 7 ACHIEVEMENT OF TECHNICAL ASSISTANCE OUTCOMES Road Transport TA 7698 - Supporting Road Network Development Outcome: The Ministry of

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK TAR:ETM 34402 TECHNICAL ASSISTANCE (Financed from the Japan Special Fund) TO EAST TIMOR FOR TRANSPORT SECTOR IMPROVEMENT October 2001 ABBREVIATIONS ADB Asian Development Bank ETTA

More information

ROADS For updated information, please visit July 2018

ROADS For updated information, please visit   July 2018 ROADS July 2018 Table of Content Executive Summary.3 Advantage India......4 Market Overview..6 Growth Drivers...15 Key Industry Associations.......23 Useful Information... 25 EXECUTIVE SUMMARY One of the

More information

Prioritising bridge replacements

Prioritising bridge replacements Prioritising bridge replacements Andrew Sonnenberg, National Bridge Engineering Manager, Pitt&Sherry ABSTRACT Road and Rail managers own a variety of assets which are aging and will need replacement. There

More information

India: Enhancing Capacity of State Utilities in Preparing Energy Sector Projects

India: Enhancing Capacity of State Utilities in Preparing Energy Sector Projects Technical Assistance Report Project Number: 51308-002 Transaction Technical Assistance Facility (F-TRTA) December 2017 India: Enhancing Capacity of State Utilities in Preparing Energy Sector Projects Distribution

More information

SECTOR ASSESSMENT (SUMMARY): PUBLIC SECTOR MANAGEMENT

SECTOR ASSESSMENT (SUMMARY): PUBLIC SECTOR MANAGEMENT Country Partnership Strategy: Papua New Guinea, 2016 2020 Sector Road Map SECTOR ASSESSMENT (SUMMARY): PUBLIC SECTOR MANAGEMENT 1. Sector Performance, Problems, and Opportunities 1. Strengthening public

More information

ECONOMIC AND FINANCIAL ANALYSIS

ECONOMIC AND FINANCIAL ANALYSIS Railway Rolling Stock Project (RRP BAN 49094) ECONOMIC AND FINANCIAL ANALYSIS A. Introduction 1. The project involves procurement of 214 meter gauge (MG) passenger carriages, 50 broad gauge (BG) passenger

More information

People s Republic of China: Emergency Assistance for Wenchuan Earthquake Reconstruction Project

People s Republic of China: Emergency Assistance for Wenchuan Earthquake Reconstruction Project Validation Report Reference Number: PVR-462 Project Number: 42496-013 Loan Number: 2508 December 2016 People s Republic of China: Emergency Assistance for Wenchuan Earthquake Reconstruction Project Independent

More information

SECTOR ASSESSMENT (SUMMARY): PUBLIC SECTOR MANAGEMENT 1

SECTOR ASSESSMENT (SUMMARY): PUBLIC SECTOR MANAGEMENT 1 Country Partnership Strategy: Cambodia, 2014 2018 Sector Road Map SECTOR ASSESSMENT (SUMMARY): PUBLIC SECTOR MANAGEMENT 1 1. Sector Performance, Problems, and Opportunities 1. Lagging public sector management

More information

India: Madhya Pradesh Power Sector Development Program

India: Madhya Pradesh Power Sector Development Program Evaluation Study Reference Number: PPE: IND 2011-03 Project Numbers: 29473 Loans 1868/1869 Program Performance Evaluation Report February 2011 India: Madhya Pradesh Power Sector Development Program Independent

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK TAR:PHI 29226 ASIAN DEVELOPMENT BANK Li TECHNICAL ASSISTANCE TO THE REPUBLIC OF ThE PHILIPPINES FOR PREPARATION OF A NATIONAL TRANSPORT STRATEGY November 1995 CURRENCY EQUIVALENTS (as of 15 October 1995)

More information

1,07,758 cr GoI allocations for Ministry of Rural Development (MoRD) in FY

1,07,758 cr GoI allocations for Ministry of Rural Development (MoRD) in FY BUDGET BRIEFS Vol 10/ Issue 8 Pradhan Mantri Awaas Yojana Gramin (PMAY G) GoI, 2017-18 Pradhan Mantri Awaas Yojana - Gramin (PMAY - G) ) is Government of India s (GoI) flagship Housing for All scheme.

More information

National Rural Roads Development Agency. Ministry of Rural Development, Govt. of India

National Rural Roads Development Agency. Ministry of Rural Development, Govt. of India National Rural Roads Development Agency Ministry of Rural Development, Govt. of India Minutes of the sixth meeting of the General Body of National Rural Roads Development Agency held on 28 th September

More information

Odisha Budget Analysis

Odisha Budget Analysis -6.7% -0.4% 4.4% 1.3% 3.1% 1.8% 4.7% 5.4% 7.8% 7.8% 8.1% 9.3% 11. 10.7% 12.4% 8.2% 10.4% 7.1% 15. 15.1% Budget Analysis The Finance Minister of, Mr. Sashibhusan Behera, presented the Budget for financial

More information

Project Administration Memorandum. Project Number: Loan Number: 2181 July PRC: Central Sichuan Roads Development Project

Project Administration Memorandum. Project Number: Loan Number: 2181 July PRC: Central Sichuan Roads Development Project Project Administration Memorandum Project Number: 34174 Loan Number: 2181 July 2006 PRC: Central Sichuan Roads Development Project CURRENCY EQUIVALENTS (as of 31 August 2005) Currency Unit yuan (CNY) CNY1.00

More information

Pakistan: Road Sector Development Program

Pakistan: Road Sector Development Program Validation Report Reference Number: PCV: PAK 2010-69 Project Number: 32058 Loan Number: 1891 December 2010 Pakistan: Road Sector Development Program Independent Evaluation Department ABBREVIATIONS ADB

More information

Accessing the Indian Market

Accessing the Indian Market Accessing the Indian Market India is the sixth largest economy in the world with a gross domestic product (GDP) of US$2.602 trillion (2017 current prices); the third largest economy based on its purchasing-power-parity

More information

Scaling up investment in Infrastructure: The Indian experience

Scaling up investment in Infrastructure: The Indian experience Scaling up investment in Infrastructure: The Indian experience - Gajendra Haldea November 30, 2010 IMF, Washington Infrastructure Deficit Power 14% peaking deficit and 11% energy shortage; 27% T&D losses;

More information

ADB Support to Public Resource Management in India

ADB Support to Public Resource Management in India Evaluation Study Reference Number: SST: REG 2007-22 Special Evaluation Study September 2007 ADB Support to Public Resource Management in India Operations Evaluation Department ABBREVIATIONS ADB Asian Development

More information

MFF - Bihar Urban Development Investment Program (Facility Concept)

MFF - Bihar Urban Development Investment Program (Facility Concept) India: MFF - Bihar Urban Development Investment Program (Facility Concept) Project Name Project Number 41603-013 Country Project Status Project Type / Modality of Assistance Source of Funding / Amount

More information

Implementation Status & Results India Assam State Roads Project (P096018)

Implementation Status & Results India Assam State Roads Project (P096018) Public Disclosure Authorized Public Disclosure Authorized Implementation Status & Results India Assam State Roads Project (P096018) Operation Name: Assam State Roads Project (P096018) Project Stage: Implementation

More information

PROGRAM EXPENDITURE AND FINANCING ASSESSMENT

PROGRAM EXPENDITURE AND FINANCING ASSESSMENT Supporting National Urban Health Mission (RRP IND 47354) PROGRAM EXPENDITURE AND FINANCING ASSESSMENT 1. The Supporting National Urban Health Program will support the implementation of the National Urban

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK RRP: PRC 33470 REPORT AND RECOMMENDATION OF THE PRESIDENT TO THE BOARD OF DIRECTORS ON A PROPOSED LOAN TO THE PEOPLE S REPUBLIC OF CHINA FOR THE GANSU ROADS DEVELOPMENT PROJECT November

More information

Q2 FY 12 INVESTOR PRESENTATION

Q2 FY 12 INVESTOR PRESENTATION Q2 FY 12 INVESTOR PRESENTATION PERFORMANCE HIGHLIGHTS Profitability Measure ROA 1.34 1.15 1.44 11.48% 11.28% 14.29% Shareholder Value Measure ROE 38.60% 38.91% Efficiency Measure COST-INCOME 33.90% 0.68

More information

RAJYA SABHA List of Questions for ORAL ANSWERS

RAJYA SABHA List of Questions for ORAL ANSWERS RAJYA SABHA List of Questions for ORAL ANSWERS to be asked at a sitting of the Rajya Sabha to be held on Monday, July 30, 2018/Shravana 8, 1940 (Saka) (Ministries: Defence; Drinking Water Sanitation; Earth

More information

SECTOR ASSESSMENT (SUMMARY): PUBLIC SECTOR MANAGEMENT (PUBLIC EXPENDITURE AND FISCAL MANAGEMENT) Sector Performance, Problems, and Opportunities

SECTOR ASSESSMENT (SUMMARY): PUBLIC SECTOR MANAGEMENT (PUBLIC EXPENDITURE AND FISCAL MANAGEMENT) Sector Performance, Problems, and Opportunities Improving Public Expenditure Quality Program, SP1 (RRP VIE 50051-001) SECTOR ASSESSMENT (SUMMARY): PUBLIC SECTOR MANAGEMENT (PUBLIC EXPENDITURE AND FISCAL MANAGEMENT) 1 Sector Road Map 1. Sector Performance,

More information

People's Republic of China: Ganzhou Longyan Railway Project

People's Republic of China: Ganzhou Longyan Railway Project Validation Report Reference Number: PCV: PRC 2009-22 Project Number: 33442 Loan Number: 1850 December 2009 People's Republic of China: Ganzhou Longyan Railway Project Independent Evaluation Department

More information

Financial Snapshot October 2014

Financial Snapshot October 2014 Financial Snapshot October 2014 Financial Snapshot About the Financial Snapshot The Financial Snapshot provides answers to frequently asked questions regarding MoDOT s finances. This document provides

More information

Highlights of Union Budget

Highlights of Union Budget Highlights of Union Budget 2017-18 The Budget broadly focussed on 10 themes viz. farming sector, rural population, the youth, the poor to name a few. The 2017 Union Budget, presented by Finance Minister

More information

IDA assisted ICDS Systems Strengthening and Nutrition Improvement Project (ISSNIP)

IDA assisted ICDS Systems Strengthening and Nutrition Improvement Project (ISSNIP) IDA assisted ICDS Systems Strengthening and Nutrition Improvement Project (ISSNIP) Background The World Bank had been supporting the Government of India to improve nutritional status of children through

More information

Investor Presentation Q3 FY 12

Investor Presentation Q3 FY 12 Investor Presentation Q3 FY 12 Performance Highlights Profitability Measure ROA 1.30 1.44 1.41 11.37 14.29 14.56 Shareholder Value Measure ROE 37.30 38.91 37.13 Efficiency Measure COST-INCOME 0.81 0.58

More information

National Rural Roads Development Agency (Ministry of Rural Development, GoI)

National Rural Roads Development Agency (Ministry of Rural Development, GoI) National Rural Roads Development Agency (Ministry of Rural Development, GoI) ACTION PLAN FOR 2007-08 Pradhan Mantri Gram Sadak Yojana(PMGSY) # Item Functionary Activity 1 DRRP & Core Network Director Tech

More information

Republic of the Maldives: Preparing Business Strategy for Port Development

Republic of the Maldives: Preparing Business Strategy for Port Development Technical Assistance Report Project Number: 47283 Capacity Development Technical Assistance (CDTA) November 2013 Republic of the Maldives: Preparing Business Strategy for Port Development The views expressed

More information

Madhya Pradesh Budget Analysis

Madhya Pradesh Budget Analysis Madhya Pradesh Budget Analysis The Finance Minister of Madhya Pradesh, Mr. Jayant Malaiya, presented the Budget for financial year on February 28, 2018. Budget Highlights The Gross State Domestic Product

More information

PROGRAM FIDUCIARY SYSTEMS ASSESSMENT

PROGRAM FIDUCIARY SYSTEMS ASSESSMENT Sustainable Transport Infrastructure Improvement Program (RRP SOL 46499) A. Background and Information Sources PROGRAM FIDUCIARY SYSTEMS ASSESSMENT 1. Under the proposed program, country public financial

More information

Farmers and rural population

Farmers and rural population MARCH YOJANA Budget Union Budget, this year, was presented amidst a host of uncertainties. Demonetisation drive and imminent GST drive, new administration in U.S etc. made the whole exercise very challenging.

More information

EXPLANATORY NOTES ON DATA SOURCE AND METHODOLOGY

EXPLANATORY NOTES ON DATA SOURCE AND METHODOLOGY EXPLANATORY NOTES ON DATA SOURCE AND METHODOLOGY Data Sources The data on State Government Finances are based on the receipts and expenditure data presented in the Budget documents of the State Governments

More information

Improving Public Expenditure Efficiency in Infrastructure Development Lao PDR Case

Improving Public Expenditure Efficiency in Infrastructure Development Lao PDR Case Ministry of Public Works and Transports Improving Public Expenditure Efficiency in Infrastructure Development Lao PDR Case Department of Planning and Cooperation Dr. Oulay PHADOUANGDETH 30 Aug 2017 Outline

More information

INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT

INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT Public Disclosure Authorized CONFORMED COPY LOAN NUMBER 4860-IN Public Disclosure Authorized Loan Agreement (Himachal Pradesh State Roads Project) between Public Disclosure Authorized INDIA and INTERNATIONAL

More information