Annex 8. Project Assurance Recommendations

Size: px
Start display at page:

Download "Annex 8. Project Assurance Recommendations"

Transcription

1 Annex 8 Project Assurance Recommendations Contents 1. Project Review Report 2. Recommendations and actions Taken 3. Project Board Roles and Responsibilities

2 This page is intentionally blank

3 BRT North - Project Review Report Version th July Introduction Bus Rapid Transit North Key Stage Review A Key Stage Review was conducted by Daniel Ladbury and Phil Moorcroft from Sheffield City Council on 18 th, 19 th and 22 nd July The purpose of this review was to undertake a high level assessment of the progress made to date and the readiness of the project to move into the implementation stage once funding approval has been obtained. The scope of the review, as agreed by the Project Sponsor, was as follows: Review the Project Business Case and Objectives; Review the resourcing and governance of the project including partner interfaces and reporting; Review the project risks and whether the proposed mitigations are appropriate; Review the overall readiness of the project to move into delivery. The review was undertaken through looking at project documentation provided and interviewing selected members of the project board and delivery team to provide a holistic and rounded assessment of the project status. The findings and recommendations included within this report are based solely on the information obtained through the documents provided and interviews undertaken. The documents provided in support of this review are identified at Appendix A. The people interviewed as part of this review are identified at Appendix B. 2 Delivery Confidence Assessment The overall findings of the review are that the project is in a position whereby it should: Proceed to next stage, taking into account recommended actions. Version 0.1 Page 1 of 7

4 BRT North - Project Review Report Version th July Summary of Recommended Actions Ref Recommendation Timescale 1 That the benefits and outcomes of the project are clearly identified and communicated to all parties. That a Benefits Realisation Plan is developed, identifying specific measures, owners and timescales and is monitored by the Project Board against a baseline position to ensure they are achieved as intended. 2 That the Project Sponsor ensures there is full buy in from Council Stakeholders to the Benefits Realisation Plan. 3 That the current funding position is reviewed to ensure there is an agreed position and that a single person is identified as the lead for further discussions with each of the funding organisations. 4 That the Project Sponsor reviews and revises the Purpose, Terms of Reference, Frequency and Attendance of the Project Board based on the project outcomes and risks and that these requirements are clearly documented and communicated to all relevant parties and agreed to ensure that the necessary attendance is maintained. 5 That the SYPTE, Sheffield CC and Rotherham MBC commit to provide suitable and sufficient continuity and capacity of the human resources required to deliver the project and that all key/ high risk roles are identified and regularly reviewed. It is suggested that this commitment is reflected in the Partnering Agreement. 6 That the Project Risk Register is updated to include all current and emerging risks and that this is reviewed by the Project Board to ensure there is a clear understanding of the risks together with the actions, owners and resources required to manage and mitigate these. 7 That a single audit of the procurement arrangements across all three public authorities in relation to this scheme be undertaken within a reasonable timescale to ensure that funder procurement requirements have been followed by each organisation involved in procuring works for the project. 8 That once funding has been confirmed, a single schedule is prepared identifying the funding conditions that need to be complied with and how these will be maintained. It is also suggested that the partnership of SYPTE/ SCC/ RMBC consider appointing a nominated person with experience of managing ERDF/ DfT funded schemes to act as a Funding Compliance Officer to minimise the risks of funding clawback to the project. 9 That the project team review and update the project programme to take consideration of the progress achieved to date and the remaining work packages that need to be progressed. This should include the Marketing, Communications, Branding, Quality Standard, Bus Routing and Bus Operator Agreement work packages and should identify key milestones at regular stages to enable effective progress monitoring of these workstreams to be undertaken. 10 That the Project Sponsor ensures that sufficient resource capacity is available to deliver these workstreams and that key workstream leads and stakeholders are represented at the Project Board. Within 2 months Within 2 months Within 2 weeks Within 1 month Ongoing Within 1 month Within 2 months Within 2 months Within 1 month Within 1 month 4 Review Findings 4.1 Business Case and Objectives Version 0.1 Page 2 of 7

5 BRT North - Project Review Report Version th July 2013 The scheme is being delivered by the SYPTE in partnership with Sheffield City Council and Rotherham MBC. A Business Case for the project has been established and has been set out in previous submissions to the DfT and ERDF which include the Cost-Benefit Ratio of the scheme. It is evident that there are a range of outcomes which need to be delivered which include: Providing a high quality bus link between Sheffield and Rotherham, Reducing journey times between Sheffield and Rotherham, Providing the opportunity for regeneration and the development of the Lower Don Valley, Increasing investment into the Lower Don Valley to create new jobs, Improving links to the M1 to reduce current levels of congestion. Whilst all parties are aware of the general benefits and outcomes that the scheme will deliver, there are some differing views with regards to what the key priorities and benefits are. It is possible that this is as a result of recent changes in staffing together with the different approval requirements of the main scheme funders. If not resolved within the near future, this could present a risk that the project may not fully achieve some of the key objectives which could introduce a risk of either funding claw-back or not achieving some benefits. Recommendation 1: That the benefits and outcomes of the project are clearly identified and communicated to all parties. That a Benefits Realisation Plan is developed, identifying specific measures, owners and timescales and is monitored by the Project Board against a baseline position to ensure they are achieved as intended. It was also identified that the realisation of some of the project benefits may be influenced by other parties outside of the scope of the SYPTE, for example where policies may be controlled by the Local Authorities that could have an impact on the outcomes of the scheme. Whilst the Council stakeholders are bought into the scheme and the benefits that it will deliver, there remains a risk that future policy changes could impact on the scheme outcomes. Recommendation 2: That the Project Sponsor ensures there is full buy in from Council Stakeholders to the Benefits Realisation Plan. 4.2 Project Governance and Resources The project has recently been through the SYPTE s Project Assurance Process and there is evidence of ongoing monitoring and review. The SYPTE operates robust Project Management processes and there is evidence that these are well managed and are being followed. Relevant project documentation was provided and there are clear project organisational structures in place which identify the resources required to deliver the project. The project organisation structure does not identify a clear project lead for liaising with the ERDF and DfT, which are the main funding parties and therefore key stakeholders in the project. From the interviews, it appeared that there were a number of parties engaging with these stakeholders and there appeared to be differing levels of understanding of the status of the ERDF funding approval. This needs clarifying as a matter of priority. Recommendation 3: That the current funding position is reviewed to ensure there is an agreed position and that a single person is identified as the lead for further discussions with each of the funding organisations. Version 0.1 Page 3 of 7

6 BRT North - Project Review Report Version th July 2013 Project Governance is appropriately formalised and Project Board and Delivery Team meetings have clarity of purpose and add value to the project. Project communication is effective - all interviewees were aware of the broader parameters of the project. Changes in senior staff positions within the SYPTE do not appear to have affected the project momentum. The Stakeholders interviewed are fully engaged with and supportive of the project and every stakeholder had confidence that the project will be delivered successfully, subject to existing resources being maintained. It is evident from Project Board minutes that some key attendees are not attending on a regular basis and that attendance in some instances has been delegated to Project Team members. Whilst delegation provides the benefit of operational knowledge for updates, it does present a risk that any strategic issues which arise within the organisations represented and could impact on the project are not being suitably captured and addressed. In addition to this, some of the workstreams that are essential for the successful delivery of the project are currently not attending the board regularly which means there is a risk that the focus rests on a limited number of the workstreams and does not fully integrate all of the workstreams required for the successful delivery of the project. Recommendation 4: That the Project Sponsor reviews and revises the Purpose, Terms of Reference, Frequency and Attendance of the Project Board based on the project outcomes, risks and key workstreams and that these requirements are agreed, clearly documented and communicated to all relevant parties to ensure that the necessary attendance is maintained. There is evidence from meeting records that the Project Board and Project Team meet regularly and all parties were aware of the key issues on the project and the stage that the project is at. The Project Team members have a strong team ethos and communication and information recording methods appear to be effective. The Project Team is currently resourced by skilled, knowledgeable and capable individuals. However, each of the team members is undertaking a key role within their own area and there appears to be very limited transfer of knowledge or capacity outside of the core delivery team. With emerging pressures and priorities on other projects, there is a risk that any future changes in personnel or changes to their capacity to work on the project will have an adverse impact on this project. A key area of risk is that the modelling workstream, which is necessary for funding applications and benefits realisation, appears to be the specialism of a single individual with limited understanding or capability of this function elsewhere within the organisation. Recommendation 5: That the SYPTE, Sheffield CC and Rotherham MBC commit to provide suitable and sufficient continuity and capacity of the human resources required to deliver the project and that all key/ high risk roles are identified and regularly reviewed. It is suggested that this commitment is reflected in the Partnering Agreement. 4.3 Risk Management There is evidence that robust risk management procedures are in place for the project and that mitigation measures are clearly identified with owners appointed. Given recent pressures to undertake additional, unanticipated and extensive work in an attempt to secure ERDF funding for the scheme, some of the project documentation such as the risk register and programme have not been updated recently. Whilst all parties are fully aware and in agreement of the key project risks, the risk register needs to be updated to reflect these and identify the actions required to mitigate and manage the risks to enable progress to be effectively monitored. Recommendation 6: That the Project Risk Register is updated to include all current and emerging risks and that this is reviewed by the Project Board to ensure there is a clear understanding of the risks together with the actions, owners and resources required to manage and mitigate these. Version 0.1 Page 4 of 7

7 BRT North - Project Review Report Version th July 2013 The most significant risk to the project at the moment is securing the ERDF funding and obtaining this approval has required substantial input from the Project Team over recent months. At the time of undertaking this review, ERDF approval remains outstanding. Once funding approval has been obtained, there will remain a risk that funding could be clawed back should the funding conditions not be complied with. SYPTE and SCC have undertaken procurement reviews to ensure that funder procurement conditions have been complied with; however it is not clear whether Rotherham have done this. Furthermore, there will be an on-going requirement to ensure that funding conditions are not breeched as the scheme is delivered. A Partnering Agreement is currently in the process of being agreed between SYPTE/ SCC and RMBC which provides a framework for the management of the project and apportionment of funding risks across all three partner organisations. This is due to be closed out within the next few weeks. Recommendation 7: That a single audit of the procurement arrangements across all three public authorities in relation to this scheme be undertaken within a reasonable timescale to ensure that funder procurement requirements have been followed by each organisation involved in procuring works for the project. Recommendation 8: That once funding has been confirmed, a single schedule is prepared identifying the funding conditions that need to be complied with and how these will be maintained. It is also suggested that the partnership of SYPTE/ SCC/ RMBC consider appointing a nominated person with experience of managing ERDF/ DfT funded schemes to act as a Funding Compliance Officer to minimise the risks of funding clawback to the project. 4.4 Readiness to Deliver Next Phase The dominant focus of the project team s efforts in recent months has been on obtaining the funding necessary to deliver the scheme and the procurement of the highway infrastructure works. This focus is appropriate given these are currently two of the highest risk areas. It is evident that additional unplanned and substantial work has been required in order to attempt to obtain the ERDF funding and this has meant that some other workstreams, including forward planning, have not progressed at the same rate due to the focussed attentions of key team members. This needs to be accounted for in resource allocations. The project plan provided for review was last updated in May 2013 and from the interviews, it is evident that a number of workstreams on this programme have progressed or been closed out, however there are also a number of additional workstreams such as Marketing/ Communications, Bus Branding and finalising agreements with Bus Operators that are not identified in detail and do now need progressing. It is not considered that this is a critical issue that will have an adverse impact on the project at this stage; however, this does need to be addressed as soon as possible to enable works to be planned and monitored to ensure that the necessary works are delivered within the requisite timescales. Early discussions have taken place with potential commercial operators of the service. Stakeholders are confident that the route is commercially viable and that the two key operators, First Group and Stagecoach, will be able to run the route economically. Operators proposals are being fed into the final DfT submission. Further work is required to finalise the route of the service with regard to end of route loops, taking into consideration the impact of and on existing bus services, the future impact of the tram-train route that is under development and a scheme driver to achieve a modal shift from cars to public transport. Further work on the route and bus branding, communications, fares and timetable commitments needs to be progressed as the project moves into the delivery phase. Consideration should also be give to the possible value of further integrating bus operators within the project organisational structure and governance as it moves into the implementation phase. Recommendation 9: That the project team review and update the project programme to take consideration of the progress achieved to date and the remaining work packages that need to be progressed. This should include the Marketing, Communications, Branding, Bus Routing, Quality Standard and Bus Operator Agreement work packages and should identify key milestones at regular stages to enable effective progress monitoring of these workstreams to be undertaken. Recommendation 10: That the Project Sponsor ensures that sufficient resource capacity is available to deliver these workstreams and that key workstream leads and stakeholders are represented at the Project Board. Version 0.1 Page 5 of 7

8 BRT North - Project Review Report Version th July th July 2013 Daniel Ladbury, Head of Capital Delivery Service, Sheffield City Council Phil Moorcroft, Commercial Services, Sheffield City Council Version 0.1 Page 6 of 7

9 BRT North - Project Review Report Version th July 2013 Appendix A Documents Reviewed The following documents were provided as part of the review and form part of the evidence used to inform the review recommendations. BRT Project Board Roles & Responsibilities BRT Project Organogram Project Board Notes May 2013 Project Board Report June 2013 Project Assurance Review Certificate Appendix E3 Risk Register dated BRT North BAFO Volume 1 Supporting Information BRT Delivery Team minutes, 12 June 2013 BRT Project Board minutes, 13 June 2013 BRT Project Board notes, 20 June 2012 BRT Project Board notes, March 2013 BRT North Project Programme, May 2013 Appendix B Persons Interviewed The following individuals were interviewed as part of the review. Project Role Name Job Title Organisation Senior Responsible Owner Executive Senior Supplier Senior Supplier Senior Supplier Senior User BRT Project Manager David Young Peter Elliott Roy Mitchell, John Bann Tom Finnegan-Smith Julie Hurley Melanie Dei Rossi Deputy Interim Director General & Director of Customer Experience Principal Programme Delivery Manager Principal Public Transport Manager Head of Transport, Traffic and Parking Services Division Transportation Unit Manager Interim Director of Strategy Principal Project Manager SYPTE SYPTE SYPTE Sheffield City Council Rotherham MBC SYPTE SYPTE SYPTE Project Manager Ambrose White Project Manager SYPTE SCC Project Manager David Budd SCC Work Package Project Manager Sheffield City Council RMBC Project Manager Matthew Lowe RMBC Work Package Project Manager Rotherham MBC Modelling and Forecasting David Andrews Transport Economist SYPTE Version 0.1 Page 7 of 7

10 Project Assurance Recommendations And Actions Taken Ref Recommendation Timescale Actions Taken 1 That the benefits and outcomes of the project are clearly identified and communicated to all parties. That a Benefits Realisation Plan is developed, identifying specific measures, owners and timescales and is monitored by the Project Board against a baseline position to ensure they are achieved as intended. 2 That the Project Sponsor ensures there is full buy in from Council Stakeholders to the Benefits Realisation Plan. 3 That the current funding position is reviewed to ensure there is an agreed position and that a single person is identified as the lead for further discussions with each of the funding organisations. 4 That the Project Sponsor reviews and revises the Purpose, Terms of Reference, Frequency and Attendance of the Project Board based on the project outcomes and risks and that these requirements are clearly documented and communicated to all relevant parties and agreed to ensure that the necessary attendance is maintained. Within 2 months Now Complete Within 2 months Now Complete Within 2 weeks Now Complete Awaiting Full Approval Within 1 month Now Complete On-going The Realisation Plan has now been completed and attached at Annex 9 ref section 5.8 in FA form. This plan identifies benefits and outcomes. The roles of Project Board members have been updated and this includes ensuring ownership of all elements of this plan. A copy is attached below. The monitoring plan is also now complete and attached at Annex 5 ref section 5.3 of the FA form. The roles of Project Board members have been updated and this includes ensuring ownership of all elements of the benefit review plan. A copy is attached below. The Project Agreement (Appendix 1) has been revised to make clear who will be responsible for liaison with funding bodies. The Full Approval submission (when approved) will finalise the funding plan. The Project Agreement (Appendix 1) has been revised to make clear who will be responsible for liaison with funding bodies. The roles of Project Board members have been updated and this includes ensuring ownership of all elements of this plan. A copy is attached at below. Project Board meetings have been booked through to the New Year and on confirmation of Full Approval will be agreed for the duration of the Project.

11 Project Assurance Recommendations And Actions Taken 5 That the SYPTE, Sheffield CC and Rotherham MBC commit to provide suitable and sufficient continuity and capacity of the human resources required to deliver the project and that all key/ high risk roles are identified and regularly reviewed. It is suggested that this commitment is reflected in the Partnering Agreement. On-going The SRO will seek written assurance that all partners will continue to provide sufficient resources to ensure that the project will be delivered in line with the commitments made in the funding bids. Compliance with these assurances will be managed by the SRO and relevant project board members throughout the remaining life of the project. 6 That the Project Risk Register is updated to include all current and emerging risks and that this is reviewed by the Project Board to ensure there is a clear understanding of the risks together with the actions, owners and resources required to manage and mitigate these. Within 1 month Now Complete A Quantified Risk Assessment has been completed and a new risk register has been created using SYPTE Issue Management System. These are attached to the application for Full Approval at Annex 4 (Quantified Risk Assessment) and Annex 7 (Project Risk Register). To ensure Project Board have a clear understanding of the project risks a Project Board risk owner has been assigned to all risks in line with the Partnership leads for their respective work packages. 7 That a single audit of the procurement arrangements across all three public authorities in relation to this scheme be undertaken within a reasonable timescale to ensure that funder procurement requirements have been followed by each organisation involved in procuring works for the project. Within 2 months On going A revised ERDF funding profile has been completed in line with the revised tender prices and the required contribution from ERDF has reduced as a result of this. To minimise the exposure to ERDF clawback the profile now focuses on the remaining works and fees. All Parties have reviewed the suggested profile and have confirmed their support for this approach. This will form the basis of the response to ERDF to in response to the pre contract conditions.

12 Project Assurance Recommendations And Actions Taken 8 That once funding has been confirmed, a single schedule is prepared identifying the funding conditions that need to be complied with and how these will be maintained. It is also suggested that the partnership of SYPTE/ SCC/ RMBC consider appointing a nominated person with experience of managing ERDF/ DfT funded schemes to act as a Funding Compliance Officer to minimise the risks of funding clawback to the project. Within 2 months On going Following submission of full approval the Partners will carry out an audit of procurement arrangements in advance of entering into contract with ERDF and to inform early engagement discussions with the DCLG audit team. We are pursuing the nomination of a project team member to act as a funding compliance officer. The details of this role are currently being developed. We will also prepare a single schedule of funding conditions as recommended. 9 That the project team review and update the project programme to take consideration of the progress achieved to date and the remaining work packages that need to be progressed. This should include the Marketing, Communications, Branding, Quality Standard, Bus Routing and Bus Operator Agreement work packages and should identify key milestones at regular stages to enable effective progress monitoring of these workstreams to be undertaken. Within 1 month Now Complete An updated summary programme to reflect the Implementation stage of the project has been completed and is attached to the application for Full Approval at Annex 6 (Project Plan (Programme)) 10 That the Project Sponsor ensures that sufficient resource capacity is available to deliver these work streams and that key work stream leads and stakeholders are represented at the Project Board. Within 1 month On going As noted above the Project Board roles and attendance have been reviewed and this recommendation will be incorporated into the on-going work.

13 BRT North Project Board Roles and Responsibilities The BRT North Project Board is organised in line with PRINCE2 recommendations and is chaired by the Senior Responsible Owner: Senior Responsible Owner (SRO) David Young, Deputy Interim Director General & Director of Customer Experience, SYPTE. As SRO, Mr Young is responsible for delivering the project, and ensuring that the project meets its objectives and delivers the projected benefits. In this role Mr Young is also responsible for ensuring that sufficient resource is available to allow the project to be delivered and the benefits of the project are realised. As SRO, Mr Young receives Periodic highlight reports from the Project Manager. In his capacity as Deputy Interim Director General & Director of Customer Experience, Mr Young is appointed by the South Yorkshire Integrated Transport Authority (ITA) to lead, direct and oversee all aspects of the Executive s activities on behalf of the ITA, including the development, implementation and management of all areas of the Executive s strategy, delivery plans and associated decision-making processes in order to ensure that the organisation continuously achieves the ITA goals and objectives; this includes a strategic coordinating role in relation to the public transport element of Local Transport Plans and to manage the future development of the ITA & PTE in the context of the Government s latest proposals for Passenger Transport strategies, and the possible implications of other local developments such as City Regions. Mr Young is also a member of SYPTE s Management Board and Executive Board. The Management Board receives monthly reports on the delivery of the overall Capital Programme and on this project when required. The other members of the Project Board are as follows: Executive Peter Elliott, Principal Programme Delivery Manager, SYPTE. As Executive, Mr Elliott deputises for SRO as required and provides the interface between Management Board (represented by the SRO) and the day-to-day management of the project, ensuring delivery of the desired objectives as identified in the Business Case. In his capacity as Principal Programme Delivery Manager, Mr Elliott is responsible for the delivery of the SYPTE s Capital Programme. The Project Executive is named Project Board Risk owner for SYPTE project risks. Mr Elliott will be the project lead for funding liaison in relation to DfT funding and will oversee the liaison with DCLG for ERDF funding. Senior Suppliers The Senior Suppliers represent the interests of those involved with the design, procurement, implementation, operation, and maintenance of the services to be delivered by the project and as this project is being delivered in Partnership with Rotherham Metropolitan Borough Council (RMBC) and Sheffield City Council (SCC) this role is shared between the three parties.

14 The Senior Suppliers are named Project Board Risk Owners for their respective work package project risks. Senior Supplier - SYPTE Roy Mitchell, Principal Public Transport Manager, SYPTE As Senior Supplier, Mr Mitchell is responsible for the delivery of all SYPTE work packages and represents all contractors and suppliers appointed by SYPTE in delivering those work packages. Mr Mitchell is also responsible for ensuring the delivery of all activities identified to ensure the provision of bus services, and the realisation of the benefits of the project relating to passenger numbers (on BRT and other bus services), and the quality and capacity of the BRT service. In his capacity as Principal Public Transport Manager, Mr Mitchell is responsible for Bus Network & Development, Tram & Train Team, and External Relations teams within SYPTE. Senior Supplier - SCC John Bann, Head of Transport, Traffic and Parking Services Division, SCC. As Senior Supplier for SCC, Mr Bann is responsible for the delivery of all SCC work packages and represents all contractors and suppliers appointed by SCC in delivering those work packages. As senior supplier he receives highlight reports from the Sheffield Project Manager every two months. In his capacity as Head of Transport, Traffic and Parking Services Division, Mr Bann is responsible for the safe and efficient movement of goods and people around the City of Sheffield, and for planning, co-ordinating and regulating activities on the roads and public rights of way. Mr Bann has various Traffic and Highway Authority powers delegated from the City Council and is responsible for improving air quality in Sheffield. Mr Bann will be the project lead for funding liaison in relation to Developer Contributions (SCC) and the Growing Places funding. Senior Supplier - RMBC Tom Finnegan-Smith, Transportation and Highways Projects Manager, RMBC. As Senior Supplier for RMBC, Mr Finnegan-Smith is responsible for the delivery of all RMBC work packages and represents all contractors and suppliers appointed by RMBC in delivering those work packages. Tom discusses project progress with the Rotherham Project Manager prior to Project Board meetings and on an ad-hoc basis when issues arise. In his capacity as Transportation and Highways Projects Manager, Mr Finnegan-Smith is responsible for various Transportation and Highways issues which includes: the identification and implementation of schemes and promotion of policies that deliver the aims of the SYLTP; delivery of Road Safety ETP; Highways Development Control; Travel Planning, cycle training, Urban Traffic Control, Highway Design, Bridge Structures and Smarter Choices within Rotherham. Mr Finnegan-Smith will be the project lead for funding liaison in relation to Developer Contributions (RMBC).

15 Senior User Julie Hurley, Interim Director of Strategy and Head of Policy and Planning, SYPTE. As Senior User, Ms Hurley is responsible for specifying the needs of those who will make use of the services and infrastructure delivered by the project, and representing their interests through appropriate liaison. In her capacity as Interim Director of Strategy and Head of Policy and Planning, Ms Hurley is responsible for the development of the relevant strategies and action plans to deliver the public transport and accessibility elements of the Local Transport Plan on behalf of the Transport Executive. Ms Hurley provides leadership of the SYPTE Policy and Planning Department and proactive participation in organisational strategy and decision making. Ms Hurley will be the Project representative at DCLG Performance Monitoring Board (PMB) for ERDF Funding Project Board Responsibilities In addition to the individual duties, the collective responsibility of the Project Board includes: Ownership of the Benefit Realisation Plan including actions to ensure the outcomes of the project are achievable within the local political climate; (Please see Annex 9 of the DfT Full Approval Submission for Detail) Managing identified risks; Providing overall direction and guidance; Making decisions on exceptional situations; Ensuring the project remains consistent with business plans and the external environment; Notifying the Project Manager of changes outside the project that could/will affect it; Ensuring projects remain on target for time, cost, quality and outcomes; Making decisions on changes (via RFC process). The details of the Project Board s other duties are mainly as detailed in the PRINCE2 guidance, subject to: Bus Service Operators will not be represented on the Board during the initial phase of the project as Senior Supplier SYPTE will undertake this role; but are likely to be invited as appropriate once the Service Procurement has been completed. The partners have agreed that contractors will not attend Project Board directly but will be represented by the relevant Senior Supplier.

Greater Bristol Bus Network Major Scheme Business Case. Chapter 1. Developing the Full Approval Major Scheme Business Case

Greater Bristol Bus Network Major Scheme Business Case. Chapter 1. Developing the Full Approval Major Scheme Business Case Greater Bristol Bus Network Major Scheme Business Case Chapter 1 Developing the Full Approval Major Scheme Business Case i ii 1. The Case for Full Approval INTRODUCTION 1.1.1 Bath and North East Somerset,

More information

National Productivity Investment Fund for the Local Road Network Application Form

National Productivity Investment Fund for the Local Road Network Application Form National Productivity Investment Fund for the Local Road Network Application Form The level of information provided should be proportionate to the size and complexity of the project proposed. As a guide,

More information

9 th March LGF Capital Programme Approvals. This paper includes approvals for projects which have progressed through the Appraisal Framework.

9 th March LGF Capital Programme Approvals. This paper includes approvals for projects which have progressed through the Appraisal Framework. 9 th March 2018 LGF Capital Programme Approvals Purpose of Report This paper includes approvals for projects which have progressed through the Appraisal Framework. Thematic Priority Secure investment in

More information

Edinburgh transport projects review

Edinburgh transport projects review Edinburgh transport projects review Prepared for the Auditor General for Scotland June 2007 Auditor General for Scotland The Auditor General for Scotland is the Parliament s watchdog for ensuring propriety

More information

Weston Package Phase 1 Major Scheme Business Case. The Financial Case. Scheme cost, financial risk and funding sources

Weston Package Phase 1 Major Scheme Business Case. The Financial Case. Scheme cost, financial risk and funding sources Weston Package Phase 1 Major Scheme Business Case 6 The Financial Case Scheme cost, financial risk and funding sources 6.1 Introduction This Section sets out how the council proposes to finance the Weston

More information

14 March 2017 Corporate Report Format

14 March 2017 Corporate Report Format 14 March 2017 Corporate Report Format To the Chair and Members of Cabinet APPROVAL TO ENTER INTO A FUNDING AGREEMENT WITH SHEFFIELD CITY REGION TO BE ABLE DRAW DOWN SCRIF APPROVED FUNDING FOR THE DELIVERY

More information

NOT PROTECTIVELY MARKED. Public SPA Board Meeting Date Tuesday 19 December 2017 City Suite, Apex City Quay, Dundee

NOT PROTECTIVELY MARKED. Public SPA Board Meeting Date Tuesday 19 December 2017 City Suite, Apex City Quay, Dundee Meeting Public SPA Board Meeting Date Tuesday Location City Suite, Apex City Quay, Dundee Title of Paper British Transport Police (BTP) Integration Update Item Number 7.2 Presented By Tom McMahon Recommendation

More information

Appendix J Western Corridor Regeneration Scheme. Benefits Realisation Plan & Monitoring and Evaluation Plan

Appendix J Western Corridor Regeneration Scheme. Benefits Realisation Plan & Monitoring and Evaluation Plan Appendix J Western Corridor Regeneration Scheme Benefits Realisation Plan & Monitoring and Evaluation Plan April 2014 [Final Report] Strategic Transportation Planning Torbay Council 2nd Floor Electric

More information

Travel Costs Reimbursement Policy (Replacing 078 and 096 Workforce) THIS POLICY IS CURRENTLY UNDER REVIEW WITH THE POLICY AUTHOR

Travel Costs Reimbursement Policy (Replacing 078 and 096 Workforce) THIS POLICY IS CURRENTLY UNDER REVIEW WITH THE POLICY AUTHOR (Replacing 078 and 096 Workforce) THIS POLICY IS CURRENTLY UNDER REVIEW WITH THE POLICY AUTHOR POLICY NUMBER TPWF/217 POLICY VERSION V.2 RATIFYING COMMITTEE HR Executive Group DATE RATIFIED 21 July 2015

More information

The STFC Project Management Framework

The STFC Project Management Framework The STFC Project Management Framework Version 5 June 2017 For further information contact: Tony Medland, Programmes Directorate (tony.medland@stfc.ac.uk) Matt Fletcher, National Laboratories Directorate

More information

Tariff Risk Management Plan

Tariff Risk Management Plan Tariff Risk Management Plan June 2012 Table of Contents EXECUTIVE SUMMARY... PRINCIPLES OF THE TARIFF...2 SUCCESS OF THE TARIFF...4 LEGAL REQUIREMENTS FOR DELIVERY...7 CURRENT HEADLINE TARIFF POSITION...7

More information

Tiverton EUE Access Draft Benefits Realisation Plan and Monitoring and Evaluation Plan

Tiverton EUE Access Draft Benefits Realisation Plan and Monitoring and Evaluation Plan Draft Benefits Realisation Plan and Monitoring and Evaluation Plan October 2014 Devon County Council County Hall Topsham Road Exeter Devon EX2 4QD Contents 1 Scheme Background and Context... 3 1.1 Description

More information

SHEFFIELD HALLAM UNIVERSITY

SHEFFIELD HALLAM UNIVERSITY SHEFFIELD HALLAM UNIVERSITY FEC/4/16/M FINANCE AND EMPLOYMENT COMMITTEE Minutes of the meeting held on Tuesday 21 June 2016 Present: In Attendance: Mr N MacDonald (Chair) Mr D Bradley Mr S Britland Mr

More information

ECMWF Copernicus Procurement

ECMWF Copernicus Procurement ECMWF Copernicus Procurement Invitation to Tender CLARIFICATIONS Clarifications issued 28 November 2017 ITT Ref: COP_031 ISSUED BY: ECMWF Administration Department Procurement Section We are pleased to

More information

Assets, Regeneration and Growth Committee 1 st June 2015

Assets, Regeneration and Growth Committee 1 st June 2015 Assets, Regeneration and Growth Committee 1 st June 2015 Title Community Asset Strategy Report of Chief Operating Officer Wards All Status Public Enclosures Appendix 1: Draft Community Asset Strategy Officer

More information

DIRECTORATE OF ESTATES AND FACILITIES

DIRECTORATE OF ESTATES AND FACILITIES DIRECTORATE OF ESTATES AND FACILITIES PROCEDURE AND INFORMATION MANUAL EPM PM4 Client Representative (University Project Manager) for Capital Projects Scope of Services Document Originated: April 2006

More information

BARNSLEY METROPOLITAN BOROUGH COUNCIL

BARNSLEY METROPOLITAN BOROUGH COUNCIL BARNSLEY METROPOLITAN BOROUGH COUNCIL This matter is a Key Decision within the Council s definition and has been included in the relevant Forward Plan. 1. Purpose of Report Report of the Executive Director

More information

Marsh Barton Rail Station Draft Benefits Realisation Plan and Monitoring and Evaluation Plan

Marsh Barton Rail Station Draft Benefits Realisation Plan and Monitoring and Evaluation Plan Draft Benefits Realisation Plan and Monitoring and Evaluation Plan May 2014 Devon County Council County Hall Topsham Road Exeter Devon EX2 4QD Contents 1 Scheme Background and Context... 3 1.1 Description

More information

B.29[17d] Medium-term planning in government departments: Four-year plans

B.29[17d] Medium-term planning in government departments: Four-year plans B.29[17d] Medium-term planning in government departments: Four-year plans Photo acknowledgement: mychillybin.co.nz Phil Armitage B.29[17d] Medium-term planning in government departments: Four-year plans

More information

with the National Rural Support Programme (NRSP) for the Islamic Republic of Pakistan 13 November 2015 NDA Strengthening & Country Programming

with the National Rural Support Programme (NRSP) for the Islamic Republic of Pakistan 13 November 2015 NDA Strengthening & Country Programming with the National Rural Support Programme (NRSP) for the Islamic Republic of Pakistan 13 November 2015 NDA Strengthening & Country Programming READINESS AND PREPARATORY SUPPORT PROPOSAL PAGE 1 OF 10 Country

More information

Ebbsfleet Development Corporation

Ebbsfleet Development Corporation Title of paper Finance and Operations Report as at 31 March 2018 Presented by Sub-committee Gerard Whiteman, Director of Finance Not applicable Purpose of Paper and Executive Summary An update on EDC budgets,

More information

Air Partner plc (the Company ) Terms of reference for the Audit and Risk Committee (the Committee )

Air Partner plc (the Company ) Terms of reference for the Audit and Risk Committee (the Committee ) P a g e 1 1. Membership Air Partner plc (the Company ) Terms of reference for the Audit and Risk Committee (the Committee ) 1.1 The Committee shall comprise at least three members including, where possible,

More information

INVITATION TO TENDER

INVITATION TO TENDER INVITATION TO TENDER To undertake an ex-ante assessment of the case for 2014-20 ERDF investment by Cheshire and Warrington and Stoke-on-Trent and Staffordshire LEPs into a new Urban Development Fund established

More information

UCISA TOOLKIT. Major Project Governance Assessment. version 1.0

UCISA TOOLKIT. Major Project Governance Assessment. version 1.0 UCISA TOOLKIT Major Project Governance Assessment version 1.0 Contents Introduction 1 Roles and responsibilities 2 Definition of a Major Project 3 Guidance for using the Toolkit 4 Governance elements 4

More information

CABINET ENVIRONMENTAL SERVICES CONTRACTS

CABINET ENVIRONMENTAL SERVICES CONTRACTS Report No: 65/2016 PUBLIC REPORT CABINET 15 March 2016 ENVIRONMENTAL SERVICES CONTRACTS Report of the Director for Places (Environment, Planning & Transport) Strategic Aim: Meeting the health & wellbeing

More information

THE CORPORATION OF THE CITY OF WINDSOR POLICY

THE CORPORATION OF THE CITY OF WINDSOR POLICY THE CORPORATION OF THE CITY OF WINDSOR POLICY Service Area: Office of the Chief Administrative Officer Policy No.: CR252/2014 Department: Approval Date: October 6, 2014 Division: Corporate Initiatives

More information

HISTORIC ENVIRONMENT SCOTLAND MINUTES OF HES BOARD MEETING HELD ON 22 FEBRUARY Conference Room, Longmore House

HISTORIC ENVIRONMENT SCOTLAND MINUTES OF HES BOARD MEETING HELD ON 22 FEBRUARY Conference Room, Longmore House HISTORIC ENVIRONMENT SCOTLAND MINUTES OF HES BOARD MEETING HELD ON 22 FEBRUARY 2018 Present: Jane Ryder, Chair Janet Brennan Ian Brennan Trudi Craggs Coinneach Maclean Fiona McLean Paul Stollard Ken Thomson

More information

Norwich Northern Distributor Road Promoter: Norfolk County Council. Full Business Case Summary Tables September 2015

Norwich Northern Distributor Road Promoter: Norfolk County Council. Full Business Case Summary Tables September 2015 Norwich Northern Distributor Road Promoter: Norfolk County Council. Full Business Case Summary Tables September 2015 Introduction Scheme Name Norwich Northern Distributor Road Date 2/9/2015 Scheme Description

More information

Brunel Pension Partnership Questions & Answers

Brunel Pension Partnership Questions & Answers A A1 Full Business Case approval Is the business case dependent on all 10 authorities signing, how many need to sign for the pool to proceed? The 10 funds have been working together on the pool since 2015

More information

Developing Transition Agreements between PCTs and Local Authorities in South Yorkshire and Bassetlaw

Developing Transition Agreements between PCTs and Local Authorities in South Yorkshire and Bassetlaw Developing Transition Agreements between PCTs and Local Authorities in South Yorkshire and Bassetlaw Board Meeting 16 April 2012 Author(s)/Presenter and title Sponsor Director South Yorkshire and Bassetlaw

More information

Section 4 Governors Guidance notes on the Management of School Finances

Section 4 Governors Guidance notes on the Management of School Finances Section 4 Governors Guidance notes on the Management of School Finances 1. Introduction Governors should be aware of their roles and responsibilities, accountability for public money and the school s model

More information

BARNSLEY METROPOLITAN BOROUGH COUNCIL

BARNSLEY METROPOLITAN BOROUGH COUNCIL BARNSLEY METROPOLITAN BOROUGH COUNCIL This matter is not a Key Decision within the Council s definition and has not been included in the relevant Forward Plan 1. Purpose of report Superfast Broadband Phase

More information

Strategic Orientation for the Future of the PMR Proposal on Modality for Funding Additional Activities under the PMR

Strategic Orientation for the Future of the PMR Proposal on Modality for Funding Additional Activities under the PMR Strategic Orientation for the Future of the PMR Proposal on Modality for Funding Additional Activities under the PMR Mr. Adrien de Bassompierre PMR Secretariat Thirteenth Meeting of the Partnership Assembly

More information

Solent NHS Trust Shadow Historical Due Diligence Paper for Trust Board June 2011

Solent NHS Trust Shadow Historical Due Diligence Paper for Trust Board June 2011 Solent NHS Trust Shadow Historical Due Diligence Paper for Trust Board June 2011 Summary This paper sets out the programme for shadow due diligence in July. Board members are asked to note the timetable,

More information

Strategic Policy Transport Levy

Strategic Policy Transport Levy Strategic Policy Transport Levy Corporate Plan reference: An outstanding organisation A high performing customer-focussed organisation marked by great people, good governance and regional leadership 5.3

More information

Internal Audit Report

Internal Audit Report Internal Audit Report Community Infrastructure Levy (CIL) and Section 106 (S106) Phase II, Expenditure, January 2018 To: From: Deputy Chief Executive, LBB Strategic Director - Environment, LBB Director

More information

Guidance for Member States on Integrated Sustainable Urban Development (Article 7 ERDF Regulation)

Guidance for Member States on Integrated Sustainable Urban Development (Article 7 ERDF Regulation) EUROPEAN COMMISSION European Structural and Investment Funds Guidance for Member States on Integrated Sustainable Urban Development (Article 7 ERDF Regulation) p10 addition of 3 bullet points for specific

More information

NIRS 2: Contract extension. REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 355 Session : 14 November 2001

NIRS 2: Contract extension. REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 355 Session : 14 November 2001 NIRS 2: Contract extension REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 355 Session 2001-2002: 14 November 2001 The National Audit Office scrutinises public spending on behalf of Parliament. The Comptroller

More information

UNIVERSITY OF CAMBRIDGE INFORMATION SERVICES COMMITTEE PROJECT AND PROGRAMME GOVERNANCE: DECISION MAKING PROCESS

UNIVERSITY OF CAMBRIDGE INFORMATION SERVICES COMMITTEE PROJECT AND PROGRAMME GOVERNANCE: DECISION MAKING PROCESS UNIVERSITY OF CAMBRIDGE INFORMATION SERVICES COMMITTEE PROJECT AND PROGRAMME GOVERNANCE: DECISION MAKING PROCESS Document Status: Approving Body: Last Update: Author: Approved Information Services Committee

More information

CABINET GROUNDS MAINTENANCE CONTRACT

CABINET GROUNDS MAINTENANCE CONTRACT Report No: 9/2017 PUBLIC REPORT CABINET 17 January 2017 GROUNDS MAINTENANCE CONTRACT Report of the Director for Places (Environment, Planning & Transport) Strategic Aim: Sustainable Growth Key Decision:

More information

Financial viability of the social housing sector: introducing the Affordable Homes Programme

Financial viability of the social housing sector: introducing the Affordable Homes Programme Department for Communities and Local Government Financial viability of the social housing sector: introducing the Affordable Homes Programme Detailed methodology JULY 2012 2 Financial viability of the

More information

Integrated Risk Management Framework Sept Page 1 of 17

Integrated Risk Management Framework Sept Page 1 of 17 Integrated Risk Management Framework 2017-2018 Sept 2017 Page 1 of 17 Reference: Title: Author/Nominated Lead: Approval Date: Approving Committee: Review Date: Target Audience: Circulation List: Cross

More information

NHS Fleet Travel & Expenses Policy

NHS Fleet Travel & Expenses Policy NHS Fleet Travel & Expenses Policy January 2009 Contents Section 1 Travel Policy Paragraph Introduction 1.00 Scope 1.30 General Principles 2.00 Health & Safety at Work 2.10 Drivers responsibility 2.30

More information

Councillor Dean Cohen, Chairman Environment Committee

Councillor Dean Cohen, Chairman Environment Committee Environment Committee 14 March 2018 Title Report of Wards Status Urgent Key Enclosures Officer Contact Details 2018/19 Local Implementation Plan (LIP) Work Programme Councillor Dean Cohen, Chairman Environment

More information

Procedure for Post Contract Progress And Cost Control. Procedure No. 012

Procedure for Post Contract Progress And Cost Control. Procedure No. 012 Procedure for Post Contract Progress And Cost Control Procedure No. 012 Print Name Title Date Prepared by J.G. MacNamara Section Officer / T.S.O. 01/03/05 Reviewed by Clodagh Hanratty C.A.T.S.O. 01/03/05

More information

Travel, Subsistence and Expenses Policy

Travel, Subsistence and Expenses Policy Travel, Subsistence and Expenses Policy Bournemouth Primary Multi Academy Trust Policy Approved By Board Signed Date Signed Chair of Board Date Signed Executive Head Date Chief Financial Officer Reviewed

More information

SCOTTISH FUNDING COUNCIL CAPITAL PROJECTS DECISION POINT PROCESS

SCOTTISH FUNDING COUNCIL CAPITAL PROJECTS DECISION POINT PROCESS SCOTTISH FUNDING COUNCIL CAPITAL PROJECTS DECISION POINT PROCESS Incorporating amendments by Scottish Futures Trust (Proposals for Decision Points 2 5 Only) Executive summary... 1 Section 1: Introduction

More information

Policy on Budget Management

Policy on Budget Management Policy on Budget Management Status: Approved Custodian: Directorate: Finance and Administration Date approved: 2013-12-04 Decision No: SAQA 07102/13 Implementation date: 2013-12-05 Due for review: 2016.12-03

More information

Apologies for absence were received from Councillor L Rose OBE, H Bowen, D Bunton, J Miller, D Swaine, E Walker and N Knowles

Apologies for absence were received from Councillor L Rose OBE, H Bowen, D Bunton, J Miller, D Swaine, E Walker and N Knowles SHEFFIELD CITY REGION COMBINED AUTHORITY THE AMP TECHNOLOGY CENTRE, WAVERLEY, ROTHERHAM, S60 5WG MINUTES OF THE MEETING HELD ON 29 JANUARY 2018 PRESENT: Councillor Chris Read, Rotherham MBC (Chair) Councillor

More information

a. Options for managing any equity shares the Government takes in projects through the Fund

a. Options for managing any equity shares the Government takes in projects through the Fund implementation of the Fund (e.g. to reflect potential changes in the role of Senior Regional Officials). I also recommend that the RED Delegated Ministers be similarly authorised to make small scale changes

More information

AMTRAK PURSUING PRIVATE INVESTMENT TO SUPPORT NORTHEAST CORRIDOR HIGH-SPEED RAIL PLANS

AMTRAK PURSUING PRIVATE INVESTMENT TO SUPPORT NORTHEAST CORRIDOR HIGH-SPEED RAIL PLANS FOR IMMEDIATE RELEASE May 19, 2011 ATK-11-076a Contact: Media Relations 202 906.3860 AMTRAK PURSUING PRIVATE INVESTMENT TO SUPPORT NORTHEAST CORRIDOR HIGH-SPEED RAIL PLANS WASHINGTON Amtrak is developing

More information

SPAIN Zaragoza Tramway SUMMARY OVERVIEW ZARAGOZA TRAMWAY. Location Zaragoza, Aragón, Spain

SPAIN Zaragoza Tramway SUMMARY OVERVIEW ZARAGOZA TRAMWAY. Location Zaragoza, Aragón, Spain SPAIN Zaragoza Tramway Image: Tramway through Plaza Lanuza in Zaragoza by Thierry Llansades / CC BY-NC-ND 2.0 OVERVIEW Location Zaragoza, Aragón, Spain Sector Transport Rail Procuring Authority Municipality

More information

Terms of Reference for the Solvency II Project of the Groupe Consultatif

Terms of Reference for the Solvency II Project of the Groupe Consultatif Terms of Reference for the Solvency II Project of the Groupe Consultatif 1. Project Overview At its meetings of 2 October 2003 and 25 March 2004, the Insurance Committee of the Groupe Consultatif has established

More information

Cumbria Local Enterprise Partnership CENTRAL ASSURANCE FRAMEWORK

Cumbria Local Enterprise Partnership CENTRAL ASSURANCE FRAMEWORK Cumbria Local Enterprise Partnership CENTRAL ASSURANCE FRAMEWORK February 2017 PART ONE: LEP GOVERNANCE AND DECISION MAKING 1.1 Name The purpose of the Cumbria LEP Central Assurance Framework is to put

More information

NHS HIGHLAND STRATEGIC RISK REGISTER ADULT SOCIAL CARE SERVICES AND CHILDREN S SERVICES

NHS HIGHLAND STRATEGIC RISK REGISTER ADULT SOCIAL CARE SERVICES AND CHILDREN S SERVICES Highland NHS Board 14 August Item 4.3 NHS HIGHLAND STRATEGIC RISK REGISTER ADULT SOCIAL CARE SERVICES AND CHILDREN S SERVICES Report by Jan Baird, Care and Lesley Anne Smith, Quality on behalf of Elaine

More information

Assurance Approach Delivery assurance activities for Retail Market Release April 2019

Assurance Approach Delivery assurance activities for Retail Market Release April 2019 Assurance Approach Delivery assurance activities for Retail Market Release April 2019 Schema V12.00.00 23 August 2018 Version 0.8 Draft for Consultation Contents Change History... 3 Document Controls...

More information

2. The BCPP collaboration encompasses 13 Funds with combined assets of 36bn (fund valuations at 31 March 2015).

2. The BCPP collaboration encompasses 13 Funds with combined assets of 36bn (fund valuations at 31 March 2015). Introduction 1. We, the administering authorities for the following Local Government Pension Scheme (LGPS) Funds, are pleased to have the opportunity to submit to the Department for Communities and Local

More information

CENTRAL MANCHESTER UNIVERSITY HOSPITALS NHS FOUNDATION TRUST

CENTRAL MANCHESTER UNIVERSITY HOSPITALS NHS FOUNDATION TRUST CENTRAL MANCHESTER UNIVERSITY HOSPITALS NHS FOUNDATION TRUST Agenda Item 8.3 Report of: Paper prepared by: Executive Director of Human & Corporate Resources Margot Johnson Director of Corporate Services

More information

3.0 SERVICE AIMS AND OBJECTIVES The Corporate Plan (ref. 3)

3.0 SERVICE AIMS AND OBJECTIVES The Corporate Plan (ref. 3) 3.0 SERVICE AIMS AND OBJECTIVES 3.1. The Corporate Plan (ref. 3) 3.1.1. s Corporate Plan was adopted in February 2002. It outlines the aims, objectives and immediate priorities of the Council for the 3

More information

Having regard to the Treaty on the Functioning of the European Union, and in particular Article 291 thereof,

Having regard to the Treaty on the Functioning of the European Union, and in particular Article 291 thereof, L 244/12 COMMISSION IMPLEMTING REGULATION (EU) No 897/2014 of 18 August 2014 laying down specific provisions for the implementation of cross-border cooperation programmes financed under Regulation (EU)

More information

Major Project Authority Integrated Assurance

Major Project Authority Integrated Assurance Major Project Authority Integrated Assurance March 2012 Major Project Authority Integrated Assurance March 2012 Official versions of this document are printed on 100% recycled paper. When you have finished

More information

GREATER MANCHESTER PENSION FUND - PENSIONS ADMINISTRATION WORKING GROUP. 19 January 2018

GREATER MANCHESTER PENSION FUND - PENSIONS ADMINISTRATION WORKING GROUP. 19 January 2018 GREATER MANCHESTER PENSION FUND - PENSIONS ADMINISTRATION WORKING GROUP 19 January 2018 Commenced: 9.00 am Terminated: 10.05 am Present: Councillors J Lane (Chair), Patrick, S Quinn, Andrews, Brett, Grimshaw

More information

Risk Management Strategy Draft Copy

Risk Management Strategy Draft Copy Risk Management Strategy 2017 Draft Copy FOREWORD Welcome to the Council s Strategic & Operational Risk Management Strategy, refreshed in May 2017. The aim of the Strategy is to improve strategic and operational

More information

JOB DESCRIPTION. Head of Partnering and Financial Management. Leeds (with regular travel to London and regional offices)

JOB DESCRIPTION. Head of Partnering and Financial Management. Leeds (with regular travel to London and regional offices) JOB DESCRIPTION Job Title: Head of Partnering and Financial Management Department: Finance Location: Leeds (with regular travel to London and regional offices) Reports To: Assistant Director of Finance

More information

Risk Management Plan PURPOSE: SCOPE:

Risk Management Plan PURPOSE: SCOPE: Management Plan Authority Source: Vice-Chancellor Approval Date: 16/05/2018 Publication Date: 17/05/2018 Review Date: 17/05/2021 Effective Date: 16/05/2018 Custodian: General Counsel and University Secretary

More information

Scheme Decision Sought Scheme Description Rail Park and Ride Programme Garforth Rail Station Car Park Project Leeds Scheme

Scheme Decision Sought Scheme Description Rail Park and Ride Programme Garforth Rail Station Car Park Project Leeds Scheme Report to: West Yorkshire & York Investment Committee Date: 21 March 2018 Subject: Director(s): Author(s): Capital Spending and Project Approvals Melanie Corcoran, Director of Delivery Caroline Coy 1 Purpose

More information

NIRS 2: Contract extension

NIRS 2: Contract extension NIRS 2: Contract extension REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 355 Session 2001-2002: 14 November 2001 LONDON: The Stationery Office 0.00 Ordered by the House of Commons to be printed on 12

More information

WEST CLIFF PRIMARY SCHOOL BUDGET MANAGEMENT POLICY

WEST CLIFF PRIMARY SCHOOL BUDGET MANAGEMENT POLICY WEST CLIFF PRIMARY SCHOOL BUDGET MANAGEMENT POLICY MISSION STATEMENT Caring, Happy, Inspiring and Achieving Document Status Date of policy creation/review Reasons for review Date of adoption by the Governing

More information

SOUTH CAMBRIDGESHIRE DISTRICT COUNCIL. TO: Leader and Cabinet 14 April 2005 Development Services Director LETTINGS POLICY REVIEW

SOUTH CAMBRIDGESHIRE DISTRICT COUNCIL. TO: Leader and Cabinet 14 April 2005 Development Services Director LETTINGS POLICY REVIEW SOUTH CAMBRIDGESHIRE DISTRICT COUNCIL TO: Leader and Cabinet 14 April 2005 AUTHOR: Development Services Director Purpose LETTINGS POLICY REVIEW 1. To consider a project framework including a Member level

More information

SUSTAINABLE URBAN MOBILITY PLAN TRAINING WORKSHOP. Module 6 Implementation Plan

SUSTAINABLE URBAN MOBILITY PLAN TRAINING WORKSHOP. Module 6 Implementation Plan SUSTAINABLE URBAN MOBILITY PLAN TRAINING WORKSHOP Module 6 Implementation Plan Sustainable Urban Mobility Plans: Delivery & Implementation Plans Identifying phased approach to delivery and programming

More information

Title Aggregated Procurement

Title Aggregated Procurement Policy and Resources Committee 02 September 2016 Title Aggregated Procurement Report of Chief Operating Officer Wards All Status Public Urgent No Key Yes Enclosures None Officer Contact Details Chris Smith

More information

Chairman of the Policy and Resources Committee. Appendix 1 - Draft Local Implementation Plan Enclosures. Summary

Chairman of the Policy and Resources Committee. Appendix 1 - Draft Local Implementation Plan Enclosures. Summary Policy & Resources Committee 23 October 2018 Title Report of Wards Status Urgent Key Local Implementation Plan submission of draft to TfL and public consultation Chairman of the Policy and Resources Committee

More information

SOUTH EAST LOCAL ENTERPRISE PARTNERSHIP ASSURANCE FRAMEWORK

SOUTH EAST LOCAL ENTERPRISE PARTNERSHIP ASSURANCE FRAMEWORK SOUTH EAST LOCAL ENTERPRISE PARTNERSHIP ASSURANCE FRAMEWORK Last Date Approved: Friday 17 th February 2017 Revised date: 1 Contents Description Page no: 1. Overview 4 2. Governance and Decision Making

More information

Adults and Safeguarding Commissioning Plan /17 addendum. Commissioning Director Adults and Health. Summary

Adults and Safeguarding Commissioning Plan /17 addendum. Commissioning Director Adults and Health. Summary Adults and Safeguarding Committee 7th March 2016 Title Report of Wards Status Urgent Key Enclosures Officer Contact Details Adults and Safeguarding Commissioning Plan - 2016/17 addendum Commissioning Director

More information

Report of Housing and Environment Lead Commissioner

Report of Housing and Environment Lead Commissioner Performance and Contract Management Committee 11 June 2014 Title NSL Contract Performance and other parking related issues Report of Housing and Environment Lead Commissioner Wards All Status Public Enclosures

More information

The Economic Impact of Housing Organisations on the North

The Economic Impact of Housing Organisations on the North The Economic Impact of Housing Organisations on the North Draft Case Study Report Stockport Homes Ltd Author(s): Chris Dayson Paul Lawless Ian Wilson January 2013 Contents 1. Introduction: Background and

More information

1 Executive summary 1. 2 Existing evaluation frameworks 7. 3 Case study evaluations Wider economic impacts Evaluation programmes 24

1 Executive summary 1. 2 Existing evaluation frameworks 7. 3 Case study evaluations Wider economic impacts Evaluation programmes 24 Important notice This Report, An economic evaluation of local bus infrastructure investment ( Report ) has been prepared by KPMG LLP solely for Greener Journeys in accordance with specific terms of reference

More information

Preparatory Phase II Project

Preparatory Phase II Project Euro BioImaging Preparatory Phase II Project Quality Assurance and Risk Management Plan established Project N. 688945 Project Title Euro-BioImaging Preparatory Phase II Project Acronym EuBI PPII Associated

More information

Metz Way to Abbeymead Avenue Improvements: Full Business Case and Due Diligence Assessment Report

Metz Way to Abbeymead Avenue Improvements: Full Business Case and Due Diligence Assessment Report Capability Gloucestershire County Council August, 2016 Metz Way to Abbeymead Avenue Improvements: Full Business Case and Due Diligence Assessment Report Prepared by:... Checked by:... Stephen Payne Nick

More information

Report To: GREATER MANCHESTER PENSION FUND LOCAL PENSIONS BOARD

Report To: GREATER MANCHESTER PENSION FUND LOCAL PENSIONS BOARD Report To: GREATER MANCHESTER PENSION FUND LOCAL PENSIONS BOARD Date: 14 December 2017 Reporting Officer: Subject: Report Summary Recommendations: Policy Implications: Financial Implications: (Authorised

More information

MODALITY FOR FUNDING ADDITIONAL ACTIVITIES UNDER THE PMR: DRAFT PROPOSAL FOR DISCUSSION. PMR Note PA

MODALITY FOR FUNDING ADDITIONAL ACTIVITIES UNDER THE PMR: DRAFT PROPOSAL FOR DISCUSSION. PMR Note PA MODALITY FOR FUNDING ADDITIONAL ACTIVITIES UNDER THE PMR: DRAFT PROPOSAL FOR DISCUSSION PMR Note PA13 2015-4 October 14, 2015 I. INTRODUCTION 1. In an effort to further facilitate discussions on the PMR

More information

DRAFT TRANSPORT ACT The Tyne and Wear Quality Contracts Scheme for Buses [date] ARRANGEMENT OF THE SCHEME ARTICLE

DRAFT TRANSPORT ACT The Tyne and Wear Quality Contracts Scheme for Buses [date] ARRANGEMENT OF THE SCHEME ARTICLE DRAFT TRANSPORT ACT 2000 The Tyne and Wear Quality Contracts Scheme for Buses [date] Made [date] ARRANGEMENT OF THE SCHEME ARTICLE 1. CITATION AND COMMENCEMENT 2. INTERPRETATION 3. THE QCS AREA 4. DESIGNATION

More information

Outline Capital Investment Strategy

Outline Capital Investment Strategy Outline Capital Investment Strategy INDEX FOREWORD 1. INTRODUCTION 2. PURPOSE 3. SUMMARY 4. INFLUENCES ON CAPITAL INVESTMENT 5. CURRENT CAPITAL EXPENDITURE 6. COMMERCIAL PROPERTY INVESTMENT STRATEGY 7.

More information

CROSS BOUNDARY BUS COLLABORATION AGREEMENT HEADS OF TERMS

CROSS BOUNDARY BUS COLLABORATION AGREEMENT HEADS OF TERMS CROSS BOUNDARY BUS COLLABORATION AGREEMENT HEADS OF TERMS Between Tyne and Wear Integrated Transport Authority, Northumberland and Durham County Councils and Hartlepool Borough Council. 1. Introduction

More information

PROJECT RISK REGISTER Guidance Notes

PROJECT RISK REGISTER Guidance Notes PROJECT RISK REGISTER Guidance Notes The Risk Register is a tool to assist Project Managers in identifying likely sources of risk and the impact they may have on achieving Objective 2 target expenditure.

More information

Name of GSO Paul Frost. Date 15/03/2013. Date 19/03/2013. Name of Res. Officer. Date. Date 15/03/2013 Name of Legal officer.

Name of GSO Paul Frost. Date 15/03/2013. Date 19/03/2013. Name of Res. Officer. Date. Date 15/03/2013 Name of Legal officer. DELEGATED POWERS REPORT NO. SUBJECT: To award of contract for Frankham Consultancy Group Ltd to undertake asbestos surveys within designated Council owned buildings Control sheet All of the following actions

More information

York North Yorkshire & East Riding Local Enterprise Partnership. Infrastructure & Joint Assets Board Meeting

York North Yorkshire & East Riding Local Enterprise Partnership. Infrastructure & Joint Assets Board Meeting York North Yorkshire & East Riding Local Enterprise Partnership Infrastructure & Joint Assets Board Meeting Minutes of the Meeting held on Wednesday 14 June 2017 At 2.00pm in the De Grey Building Room

More information

Local Pinch Point Fund Application Form

Local Pinch Point Fund Application Form Greater Manchester Scheme Reference: 02 Local Pinch Point Fund Application Form Guidance on the Application Process is available at: https://www.gov.uk/government/organisations/department-for-transport/series/local-pinch-pointfund

More information

CWM TAF UNIVERSITY HEALTH BOARD CONFIRMED MINUTES OF THE MEETING OF THE AUDIT COMMITTEE HELD ON 5 OCTOBER 2015 AT YNYSMEURIG HOUSE, ABERCYNON

CWM TAF UNIVERSITY HEALTH BOARD CONFIRMED MINUTES OF THE MEETING OF THE AUDIT COMMITTEE HELD ON 5 OCTOBER 2015 AT YNYSMEURIG HOUSE, ABERCYNON CWM TAF UNIVERSITY HEALTH BOARD CONFIRMED MINUTES OF THE MEETING OF THE AUDIT COMMITTEE HELD ON 5 OCTOBER 2015 AT YNYSMEURIG HOUSE, ABERCYNON PRESENT Mr G Bell - Independent Member (Chair) Dr C Turner

More information

Executive Summary (in one page)

Executive Summary (in one page) Kenya 2015.10.28 PAGE 1 OF 6 (Please submit completed form to countries@gcfund.org) Executive Summary (in one page) Country (or region) Kenya Submission Date 28/10/2015 NDA or Focal Point Contact Point

More information

REPORT FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT AND THE COUNCIL

REPORT FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT AND THE COUNCIL EUROPEAN COMMISSION Brussels, 20.12.2011 COM(2011) 907 final REPORT FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT AND THE COUNCIL PROGRESS REPORT ON THE DEVELOPMENT OF THE SECOND GENERATION SCHENGEN INFORMATION

More information

Worcestershire County Council: Use of External Consultants

Worcestershire County Council: Use of External Consultants Worcestershire County Council: Use of External Consultants Risk and Assurance Services Providing assurance on the management of risks Report status Final Report date 30th November 2015 Prepared by Christopher

More information

Cost reduction in central government: summary of progress

Cost reduction in central government: summary of progress REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 1788 SESSION 2010 2012 2 FEBRUARY 2012 Cabinet Office and HM Treasury Cost reduction in central government: summary of progress 4 Key facts Cost reduction

More information

In Confidence. Office of the Minister for Regional Economic Development. Chair, Cabinet THE PROVINCIAL GROWTH FUND. Purpose

In Confidence. Office of the Minister for Regional Economic Development. Chair, Cabinet THE PROVINCIAL GROWTH FUND. Purpose In Confidence Office of the Minister for Regional Economic Development Chair, Cabinet THE PROVINCIAL GROWTH FUND Purpose This paper sets the broad parameters for the Provincial Growth Fund. This will enable

More information

Code Subsidiary Document No. 0007: Business Continuity Management

Code Subsidiary Document No. 0007: Business Continuity Management Code Subsidiary Document No. 0007: Change History Version Number Date of Issue Reason For Change Change Control Reference Sections Affected Version 1.0 Page 2 of 28 Table of Contents 1. Introduction...

More information

CABINET FUTURE DELIVERY OF FACILITY MANAGEMENT SERVICES

CABINET FUTURE DELIVERY OF FACILITY MANAGEMENT SERVICES Report No: 172/2017 PUBLIC REPORT CABINET 19 th September 2017 FUTURE DELIVERY OF FACILITY MANAGEMENT SERVICES Report of the Director for Places Strategic Aim: Sound financial planning and workforce planning

More information

Report to the Sutton Clinical Commissioning Group Board

Report to the Sutton Clinical Commissioning Group Board Sutton and Merton Borough Teams Sutton Clinical Commissioning Group Report to the Sutton Clinical Commissioning Group Board Date of Meeting: Wednesday, 3 rd April 2013 Agenda No: 6.1 Attachment: 06 Title

More information

3 Key Results Areas. claims as may be allocated from time to time by the Senior Claims Officer and/or the Claims Officer.

3 Key Results Areas. claims as may be allocated from time to time by the Senior Claims Officer and/or the Claims Officer. Sub-section Content 1 Preliminaries - Post title: Claims Assistant - Reports to: Senior Claims Officer - Pay grade / salary: xxx - Organisation Sector / Service Area: xxx 2 Job Purpose - To undertake the

More information

CHARNGES TO THE ARRANGEMENTS FOR THE APPOINTMENT OF EXTERNAL AUDITORS

CHARNGES TO THE ARRANGEMENTS FOR THE APPOINTMENT OF EXTERNAL AUDITORS p 17 th November, 2016 To the Chair and Members of the AUDIT COMMITTEE CHARNGES TO THE ARRANGEMENTS FOR THE APPOINTMENT OF EXTERNAL AUDITORS EXECUTIVE SUMMARY 1. This report summarises the changes to the

More information

The Annual Audit Letter for Wigan Metropolitan Borough Council

The Annual Audit Letter for Wigan Metropolitan Borough Council The Annual Audit Letter for Wigan Metropolitan Borough Council Year ended 31 March 2015 26 October 2015 2015 Grant Thornton UK LLP Annual Audit Letter 2014/15 Contents Section Page 1. Key messages 3-5

More information