Unit 5 Slide Lectures of 04/05/06 April 2017
|
|
- Ethan Perkins
- 5 years ago
- Views:
Transcription
1 PROJECT AND COMMUNICATION MANAGEMENT Academic Year 2016/2017 PROJECT SCHEDULING, PROJECT DURATION AND PROJECT COMMUNICATION PLAN (CH. 8-9) Unit 5 Slide Lectures of 04/05/06 April 2017
2 Overview of the Resource Scheduling Problem Resources and Priorities Project network times are not a schedule until resources have been assigned. The implicit assumption is that resources will be available in the required amounts when needed. Adding new projects requires making realistic judgments of resource availability and project durations. Cost estimates are not a budget until they have been time-phased. 8 2
3 Project Planning Process FIGURE
4 The Resource Problem (cont d) Resource Smoothing (or Leveling) Involves attempting to even out varying demands on resources by using slack (delaying noncritical activities) to manage resource utilization when resources are adequate over the life of the project. Resource-Constrained Scheduling The duration of a project may be increased by delaying the late start of some of its activities if resources are not adequate to meet peak demands. 8 4
5 Types of Project Constraints Technical or Logic Constraints Constraints related to the networked sequence in which project activities must occur. Physical Constraints Activities that cannot occur in parallel or are affected by contractual or environmental conditions. Resource Constraints The absence, shortage, or unique interrelationship and interaction characteristics of resources that require a particular sequencing of project activities Kinds of Resource Constraints People, materials, equipment 8 5
6 Constraint Examples FIGURE
7 Classification of a Scheduling Problem Classification of Problem Using a priority matrix will help determine if the project is time or resource constrained. Time-Constrained Project Must be completed by an imposed date. Time is fixed, resources are flexible: additional resources are required to ensure project meets schedule. Resource-Constrained Project Is one in which the level of resources available cannot be exceeded. Resources are fixed, time is flexible: inadequate resources will delay the project. 8 7
8 Resource Allocation Methods Limiting Assumptions Splitting activities is not allowed once an activity is start, it is carried to completion. Level of resources used for an activity cannot be changed. Risk Assumptions Activities with the most slack pose the least risk. Reduction of flexibility does not increase risk. The nature of an activity (easy, complex) doesn t increase risk. 8 8
9 Resource Allocation Methods (cont d) Time-Constrained Projects Must be completed by an imposed date. Require use of leveling techniques that focus on balancing or smoothing resource demands. Use positive slack (delaying noncritical activities) to manage resource utilization over the duration of the project. Peak resource demands are reduced. Resources over the life of the project are reduced. Fluctuation in resource demand is minimized. 8 9
10 Botanical Garden FIGURE
11 Resource Allocation Methods (cont d) Resource Demand Leveling Techniques for Time-Constrained Projects Advantages Peak resource demands are reduced. Resources over the life of the project are reduced. Fluctuation in resource demand is minimized. Disadvantages Loss of flexibility that occurs from reducing slack. Increases in the criticality of all activities. 8 11
12 Resource Allocation Methods (cont d) Resource-Constrained Projects Resources are limited in quantity or availability. Activities are scheduled using heuristics (rules-of-thumb) that focus on: 1. Minimum slack 2. Smallest (least) duration 3. Lowest activity identification number The parallel method is used to apply heuristics An iterative process starting at the first time period of the project and scheduling period-by-period the start of any activities using the three priority rules. 8 12
13 Resource-Constrained Schedule through Period 2 3 FIGURE
14 Resource-Constrained Schedule through Period 2 3 FIGURE 8.4 (cont d) 8 14
15 Resource-Constrained Schedule through Period 2 3 FIGURE 8.4 (cont d) 8 15
16 Resource-Constrained Schedule through Period 5 6 FIGURE
17 Resource-Constrained Schedule through Period 5 6 FIGURE 8.5 (cont d) 8 17
18 Resource-Constrained Schedule through Period 5 6 FIGURE 8.5 (cont d) 8 18
19 Computer Demonstration of Resource- Constrained Scheduling EMR Project The development of a handheld electronic medical reference guide to be used by emergency medical technicians and paramedics. Problem There are only eight design engineers who can be assigned to the project due to a shortage of design engineers and commitments to other projects. 8 19
20 EMR Project: Network View Schedule before Resources Leveled FIGURE
21 EMR Project before Resources Added FIGURE
22 EMR Project Time Constrained Resource Usage View, January FIGURE 8.8A 8 22
23 Resource Loading Chart for EMR Project, January FIGURE 8.8B 8 23
24 EMR Project Network View Schedule after Resources Leveled FIGURE
25 EMR Project Resources Leveled FIGURE
26 The Impacts of Resource-Constrained Scheduling Reduces delay but reduces flexibility. Increases criticality of events. Increases scheduling complexity. May make the traditional critical path no longer meaningful. Can break sequence of events. May cause parallel activities to become sequential and critical activities with slack to become noncritical. 8 26
27 Splitting Splitting A scheduling technique for creating a better project schedule and/or increase resource utilization. Involves interrupting work on an activity to employ the resource on another activity, then returning the resource to finish the interrupted work. Is feasible when startup and shutdown costs are low. Is considered the major reason why projects fail to meet schedule. 8 27
28 Splitting Activities FIGURE
29 Benefits of Scheduling Resources Leaves time for consideration of reasonable alternatives: Cost-time tradeoffs Changes in priorities Provides information for time-phased work package budgets to assess: Impact of unforeseen events Amount of flexibility in available resources 8 29
30 Multiproject Resource Schedules Multiproject Scheduling Problems 1. Overall project slippage Delay on one project create delays for other projects. 2. Inefficient resource application The peaks and valleys of resource demands create scheduling problems and delays for projects. 3. Resource bottlenecks Shortages of critical resources required for multiple projects cause delays and schedule extensions. 8 30
31 Multiproject Resource Schedules (cont d) Managing Multiproject Scheduling: Create project offices or departments to oversee the scheduling of resources across projects. Use a project priority queuing system: first come, first served for resources. Centralize project management: treat all projects as a part of a megaproject. Outsource projects to reduce the number of projects handled internally. 8 31
32 Using the Resource Schedule to Develop a Project Cost Baseline Why a Time-Phased Budget Baseline Is Needed To determine if the project is on, ahead, or behind schedule and over or under its budgeted costs? To know how much work has been accomplished for the allocated money spent the project cost baseline (planned value, PV) Creating a Time-Phased Budget Assign each work package to one responsible person or department and deliverable. Compare planned schedule and costs using an integrative system called earned value. 8 32
33 Direct Labor Budget Rollup ($000) FIGURE
34 Time-Phased Work Package Budget (Labor Cost Only) FIGURE
35 Two Time-Phased Work Packages (Labor Cost Only) FIGURE
36 Patient Entry Project Network FIGURE
37 Patient Entry Time-Phased Work Packages Assigned FIGURE
38 CEBOO Project Monthly Cash Flow Statement FIGURE
39 CEBOO Project Weekly Resource Usage Schedule FIGURE
40 Key Terms Heuristic Leveling Planned value (PV) Resource-constrained projects Resource smoothing Splitting Time-constrained projects Time-phased budget baseline 8 40
41 Rationale for Reducing Project Duration Time Is Money: Cost-Time Tradeoffs Reducing the time of a critical activity usually incurs additional direct costs. Cost-time solutions focus on reducing (crashing) activities on the critical path to shorten overall duration of the project. Reasons for imposed project duration dates: Time-to-market pressures Unforeseen delays Incentive contracts (bonuses for early completion) Imposed deadlines and contract commitments Overhead and public goodwill costs Pressure to move resources to other projects 9 41
42 Options for Accelerating Project Completion Resources Not Constrained Adding resources Outsourcing project work Scheduling overtime Establishing a core project team Do it twice fast and then correctly Resources Constrained Fast-tracking Critical-chain Reducing project scope Compromise quality 9 42
43 Explanation of Project Costs Project Indirect Costs Costs that cannot be associated with any particular work package or project activity. Supervision, administration, consultants, and interest Costs that vary (increase) with time. Reducing project time directly reduces indirect costs. Project Direct Costs Normal costs that can be assigned directly to a specific work package or project activity. Labor, materials, equipment, and subcontractors Crashing activities increases direct costs. 9 43
44 Reducing Project Duration to Reduce Project Cost Identifying direct costs to reduce project time Gather information about direct and indirect costs of specific project durations. Search critical activities for lowest direct-cost activities to shorten project duration. Compute total costs for specific durations and compare to benefits of reducing project time. 9 44
45 Project Cost Duration Graph FIGURE
46 Constructing a Project Cost Duration Graph Find total direct costs for selected project durations. Find total indirect costs for selected project durations. Sum direct and indirect costs for these selected project durations. Compare additional cost alternatives for benefits. 9 46
47 Constructing a Project Cost Duration Graph Determining Activities to Shorten Shorten the activities with the smallest increase in cost per unit of time. Assumptions: The cost relationship is linear. Normal time assumes low-cost, efficient methods to complete the activity. Crash time represents a limit the greatest time reduction possible under realistic conditions. Slope represents a constant cost per unit of time. All accelerations must occur within the normal and crash times. 9 47
48 Activity Graph FIGURE
49 Cost Duration Trade-off Example FIGURE
50 Cost Duration Trade-off Example (cont d) FIGURE 9.3 (cont d) 9 50
51 Cost Duration Trade-off Example (cont d) FIGURE
52 Cost Duration Trade-off Example (cont d) FIGURE 9.4 (cont d) 9 52
53 Summary Costs by Duration FIGURE
54 Project Cost Duration Graph FIGURE
55 Practical Considerations Using the Project Cost Duration Graph Crash Times Linearity Assumption Choice of Activities to Crash Revisited Time Reduction Decisions and Sensitivity 9 55
56 What if Cost, Not Time Is the Issue? Commonly Used Options for Cutting Costs Reducing project scope Having owner take on more responsibility Outsourcing project activities or even the entire project Brainstorming cost savings options 9 56
57 Key Terms Crashing Crash point Crash time Direct costs Fast-tracking Indirect costs Outsourcing Project cost duration graph 9 57
58 Project Priority Matrix: Whitbread Project FIGURE C
Scheduling Resources and Costs
CHAPTER EIGHT Scheduling Resources and Costs Copyright 2014 McGraw-Hill Education. All Rights Reserved. PowerPoint Presentation by Charlie Cook Where We Are Now 8 2 Overview of the Resource Scheduling
More informationReducing Project Duration
CHAPTER NINE Reducing Project Duration McGraw-Hill/Irwin Copyright 2011 by The McGraw-Hill Companies, Inc. All rights reserved. Rationale for Reducing Project Duration Time Is Money: Cost-Time Tradeoffs
More informationChapter 9: Reducing Project Duration 4KF3
Lecture Notes Options for Accelerating Project Completion Unconstrained Resources o Adding resources o Outsourcing o Overtime o Core project team o Do it twice Constrained Resources o Fast-tracking o Critical-chain
More informationAllocate and Level Project Resources
Allocate and Level Project Resources Resource Allocation: Defined Resource Allocation is the scheduling of activities and the resources required by those activities while taking into consideration both
More informationProject planning and creating a WBS
37E01500 Project Management and Consulting Practice Project planning and creating a WBS Matti Rossi Lecture 3, Tue 28.2.2017 Learning objectives Describe the project time management planning tasks, and
More informationPMI - Dallas Chapter. Sample Questions. March 22, 2002
PMI - Dallas Chapter PMP Exam Sample Questions March 22, 2002 Disclaimer: These questions are intended for study purposes only. Success on these questions is not necessarily predictive of success on the
More informationSCHEDULE CREATION AND ANALYSIS. 1 Powered by POeT Solvers Limited
SCHEDULE CREATION AND ANALYSIS 1 www.pmtutor.org Powered by POeT Solvers Limited While building the project schedule, we need to consider all risk factors, assumptions and constraints imposed on the project
More informationSheila Belayutham CHAPTER 6 CONTROL
CHAPTER 6 CONTROL LEARNING OUTCOME Students will be able to: Understand monitoring and control in construction. Understand the monitoring and control methods in construction. MONITORING & CONTROL It s
More informationINTRODUCTION PROJECT MANAGEMENT
CHAPTER 7. 1 RESOURCE INTRODUCTION ALLOCATION TO PROJECT MANAGEMENT Prepared by: Dr. Maria Elisa Linda T. Cruz Prepared by: Dr. Maria Elisa Linda T. Cruz 1 Chapter 7. Resource Allocation 7.1 Critical Path
More informationSWEN 256 Software Process & Project Management
SWEN 256 Software Process & Project Management Plan: Identify activities. No specific start and end dates. Estimating: Determining the size & duration of activities. Schedule: Adds specific start and end
More informationTextbook: pp Chapter 11: Project Management
1 Textbook: pp. 405-444 Chapter 11: Project Management 2 Learning Objectives After completing this chapter, students will be able to: Understand how to plan, monitor, and control projects with the use
More informationProject Management Chapter 13
Lecture 12 Project Management Chapter 13 Introduction n Managing large-scale, complicated projects effectively is a difficult problem and the stakes are high. n The first step in planning and scheduling
More informationRisk Video #1. Video 1 Recap
Risk Video #1 Video 1 Recap 1 Risk Video #2 Video 2 Recap 2 Risk Video #3 Risk Risk Management Process Uncertain or chance events that planning can not overcome or control. Risk Management A proactive
More informationIntroduction. Introduction. Six Steps of PERT/CPM. Six Steps of PERT/CPM LEARNING OBJECTIVES
Valua%on and pricing (November 5, 2013) LEARNING OBJECTIVES Lecture 12 Project Management Olivier J. de Jong, LL.M., MM., MBA, CFD, CFFA, AA www.olivierdejong.com 1. Understand how to plan, monitor, and
More informationMS Project 2007 Page 1 of 18
MS Project 2007 Page 1 of 18 PROJECT MANAGEMENT (PM):- There are powerful environment forces contributed to the rapid expansion of the projects and project management approaches to the business problems
More informationCost Slope Analysis 1
Cost Slope Analysis 1 Running head: Cost Slope Analysis Cost Slope Analysis Technique Summary Su-Cheng Wu Cost Slope Analysis 2 Abstract: Cost Slope Analysis considers the following: direct, indirect cost,
More informationPMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved
Project Cost Management 1 Project Cost Management Processes 1. Estimate Costs 2. Determine Budget 3. Control Costs In some projects, especially with smaller scope, cost estimation and cost budgeting are
More informationProject Management Professional (PMP) Exam Prep Course 06 - Project Time Management
Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management Slide 1 Looking Glass Development, LLC (303) 663-5402 / (888) 338-7447 4610 S. Ulster St. #150 Denver, CO 80237 information@lookingglassdev.com
More informationMonitoring and Controlling RCC Work in Delayed Construction Projects
Monitoring and Controlling RCC Work in Delayed Construction s Nimesh Gujarati, Dr. B S Balapgol Post Graduate Student (Construction and Management), DYPCOE, Akurdi, Pune-44, Maharashtra, India Principal,
More informationCOPYRIGHTED MATERIAL. Index
Index Note to the reader: Throughout this index boldfaced page numbers indicate primary discussions of a topic. Italicized page numbers indicate illustrations. A A+ certification, 28 acceptance criteria
More informationPROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA
This section is used for projects over $1,000,000 use other section if less than $1M SECTION 01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 SCOPE A. Preliminary Contract Schedule, Contract
More informationIP-CIS : CIS Project Management
Meltem Özturan www.mis.boun.edu.tr/ozturan/mis301 1 Project Management Tools and Techniques (PMTT) Feasibility Analysis Organizational Breakdown Structure Work Breakdown Structure Scheduling Earned Value
More informationInternational Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ
International Project Management prof.dr MILOŠ D. MILOVANČEVIĆ Project time management Project cost management Time in project management process Time is a valuable resource. It is also the scarcest. Time
More information4/14/2017. Unit 7 Slide Lectures of 19/20/21 April 2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13)
PROJECT AND COMMUNICATION MANAGEMENT Academic Year 2016/2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13) Unit 7 Slide 7.2.1 Lectures of 19/20/21 April 2017 Structure of a Project Monitoring
More informationVendor: PMI. Exam Code: CA Exam Name: Certified Associate in Project Management. Version: Demo
Vendor: PMI Exam Code: CA0-001 Exam Name: Certified Associate in Project Management Version: Demo QUESTION: 1 On what is project baseline development established? A. Approved product requirements B. Estimated
More informationAppendix A Decision Support Analysis
Field Manual 100-11 Appendix A Decision Support Analysis Section I: Introduction structure development, and facilities. Modern quantitative methods can greatly facilitate this Complex decisions associated
More informationDepartment of Industrial Engineering
Department of Industrial Engineering Engineering Project Management Presented By Dr. Abed Schokry Chapter 15: Cost Control Learning Outcomes After completing this chapter students should be able to: Define
More informationProject Planning. Jesper Larsen. Department of Management Engineering Technical University of Denmark
Project Planning jesla@man.dtu.dk Department of Management Engineering Technical University of Denmark 1 Project Management Project Management is a set of techniques that helps management manage large-scale
More informationProject Management -- Developing the Project Plan
Project Management -- Developing the Project Plan Dr. Tai-Yue Wang Department of Industrial and Information Management National Cheng Kung University Tainan, TAIWAN, ROC 1 Where We Are Now 6 2 Developing
More informationAfter complete studying this chapter, You should be able to
Chapter 10 Project Management Ch10: What Is Project Management? After complete studying this chapter, You should be able to Define key terms like Project, Project Management, Discuss the main characteristics
More informationProject Planning. Planning is an important step in project execution. Planning means:
Project Planning Planning is an important step in project execution. Planning means: Thinking through future project actions Seeking and mentally inspecting the long path from the start to the finish Achieving
More informationTime and Cost Optimization Techniques in Construction Project Management
Time and Cost Optimization Techniques in Construction Project Management Mr.Bhushan V 1. Tatar and Prof.Rahul S.Patil 2 1. INTRODUCTION In the field of Construction the term project refers as a temporary
More informationUNIT-II Project Organization and Scheduling Project Element
UNIT-II Project Organization and Scheduling Project Element Five Key Elements are Unique. Projects are unique, one-of-a-kind, never been done before. Start and Stop Date. Projects must have a definite
More informationAppendix B: Glossary of Project Management Terms
Appendix B: Glossary of Project Management Terms Assumption - There may be external circumstances or events that must occur for the project to be successful (or that should happen to increase your chances
More informationCISC 322 Software Architecture
CISC 22 Software Architecture Project Scheduling (PERT/CPM) Ahmed E. Hassan (Edited For Course Presentation, 206) Project A project is a temporary endeavour undertaken to create a "unique" product or service
More informationMohammed Rafiuddin CEO and General Manager, BIOSI Biohazards Solutions Innovators
Mohammed Rafiuddin CEO and General Manager, BIOSI Biohazards Solutions Innovators Profile of Mohammed Rafiuddin Mohammed is an active member of AACE International since 2006 with 30 years of experience
More informationProject Time-Cost Trade-Off
Project Time-Cost Trade-Off 7.1 Introduction In the previous chapters, duration of activities discussed as either fixed or random numbers with known characteristics. However, activity durations can often
More informationISSN: [Mali* et al., 6(3): March, 2017] Impact Factor: 4.116
IJESRT INTERNATIONAL JOURNAL OF ENGINEERING SCIENCES & RESEARCH TECHNOLOGY TIME AND COST OPTIMIZATION BY MSP SOFTWARE Mali P. A*, Lokhande A.Y, Kadam S.K, Shirole S.B, More P.N, Velhal A.J * Department
More informationKing Fahd University of Petroleum and Minerals College of Environmental Design CEM 520: Construction Contracting
King Fahd University of Petroleum and Minerals College of Environmental Design CEM 520: Construction Contracting Determination of Construction Contract Duration for Public Projects in Saudi Arabia By:
More informationManagement Services Reviewer by Ma. Elenita Balatbat-Cabrera
Course Name: Course Title: Instructors: Required Text: Course Description: XMASREV Management Services Review David, Dimalanta and Morales Management Services Reviewer by Ma. Elenita Balatbat-Cabrera This
More informationPMI PMI-SP. PMI Scheduling Professional. Download Full Version :
PMI PMI-SP PMI Scheduling Professional Download Full Version : http://killexams.com/pass4sure/exam-detail/pmi-sp QUESTION: 311 A company hires a scheduler for one of its projects. What skills should he
More informationProject Management for EPC Contracts Presented by: Dr. Jamal F. AlBahar, PMP, VMA Registered Arbitrator; Member: PMI, CMAA, AACE, AAA, PMA, CSI, SAVE
Project Management for EPC Contracts Presented by: Dr. Jamal F. AlBahar, PMP, VMA Registered Arbitrator; Member: PMI, CMAA, AACE, AAA, PMA, CSI, SAVE INTRODUCTION: Project Management for Engineering and
More informationProject Management. Project Mangement. ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala.
Project Mangement ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala. Page 1 of 380 26/4/2008 Syllabus 1. Total Project Management Concept, relationship with other function and other organizations,
More informationOutline. Global Company Profile: Bechtel Group. The Importance of Project Management Project Planning Project Scheduling Project Controlling
Project Management Outline Global Company Profile: Bechtel Group The Importance of Project Management Project Planning Project Scheduling Project Controlling Outline - Continued Project Management Techniques:
More informationPROJECT COST MANAGEMENT
PROJECT COST MANAGEMENT For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, PMP, PMI-RMP
More informationChapter 5, CVP Study Guide
Chapter 5, CVP Study Guide Chapter theme: Cost-volume-profit (CVP) analysis helps managers understand the interrelationships among cost, volume, and profit by focusing their attention on the interactions
More informationHow to arrange for financing? Cash Flow = Cash In Cash Out. = Income Expense. = Revenue - Cost
Analysis Contract How much is the total cost? How to arrange for financing? = Cash In Cash Out = Income Expense = Revenue - Cost 29/09/2016 Emad Elbeltagi 2 1 Project Expenses The project cost types: Fixed
More informationPMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005
PMP Preparation Training Your key in Successful Project Management Akram Al-Najjar, PMP Cost Management Processes Chapter 7 Cost Management Slide 2 1 AGENDA What is Cost Management? Cost Management Processes
More informationApplication of Earned Value Management (EVM) for Effective Project Control
Application of Earned Value Management (EVM) for Effective Project Control Course No: B02-012 Credit: 2 PDH Boris Shvartsberg, Ph.D., P.E., P.M.P. Continuing Education and Development, Inc. 9 Greyridge
More informationPROJECT MANAGEMENT DIPLOMA COURSE
PROJECT MANAGEMENT DIPLOMA COURSE UNIT THREE PROJECT PLANNING TUTOR TALK: The Learning Outcomes for this assignment are: Describe the following: o Planning parameters o Planning quality o Developing a
More informationOptimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur. Lecture - 18 PERT
Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur Lecture - 18 PERT (Refer Slide Time: 00:56) In the last class we completed the C P M critical path analysis
More informationResearch Methods Outline
: Project Management James Gain jgain@cs.uct.ac.za Outline Introduction [] Project Management [] Experimental Computer Science [] Role of Mathematics [1] Designing User Experiments [] Qualitative Research
More informationProject Management Fundamentals
Project Management Fundamentals Course No: B04-003 Credit: 4 PDH Najib Gerges, Ph.D., P.E. Continuing Education and Development, Inc. 9 Greyridge Farm Court Stony Point, NY 10980 P: (877) 322-5800 F: (877)
More informationGuide to Earned Value Management (EVM) Scalability for Non-Major Acquisition Implementations
Guide to Earned Value Management (EVM) for Non-Major Acquisition Implementations Prepared by the Civilian Agencies and Industry Working Group (CAIWG) March 2015 CAIWG Guide to EVM Table of Contents Introduction...
More information1 of 14 4/27/2009 7:45 AM
1 of 14 4/27/2009 7:45 AM Chapter 7 - Network Models in Project Management INTRODUCTION Most realistic projects that organizations like Microsoft, General Motors, or the U.S. Defense Department undertake
More informationVIRGINIA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR SECTION 109 MEASUREMENT AND PAYMENT
SECTION 102.01 PREQUALIFICATION OF BIDDERS of the Specifications is amended as follows: The eighth paragraph is replaced by the following: When the Contractor's actual progress is more than 10 percent
More informationProject Management for the Professional Professional Part 3 - Risk Analysis. Michael Bevis, JD CPPO, CPSM, PMP
Project Management for the Professional Professional Part 3 - Risk Analysis Michael Bevis, JD CPPO, CPSM, PMP What is a Risk? A risk is an uncertain event or condition that, if it occurs, has a positive
More informationPrincess Nora University Computer Science and Information Faculty Information Systems Department IS321
Princess Nora University Computer Science and Information Faculty Information Systems Department IS321 Chapter 5 Initiating & Planning Systems Development Projects 1 Learning Objectives Describe steps
More informationAquino, Canlas, David, Dimalanta, Manaloto and Sibug. Management Accounting by Ma. Elenita Balatbat-Cabrera
Course Name: XMGRAC1 Course Title: Managerial Accounting, Part 1 Instructors: Required Text: Course Description: Aquino, Canlas, David, Dimalanta, Manaloto and Sibug Management Accounting by Ma. Elenita
More informationCONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon
CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon Abstract- Project Cost Management includes the processes involved in planning, estimating, budgeting,
More informationActivity Resource Elasticity: A New Approach to Project Crashing
Activity Resource Elasticity: A New Approach to Project Crashing Dr. Ronald S. Tibben-Lembke MGRS / 028 University of Nevada Reno, NV 89557 (775) 682-9164 Fax: (775) 784-1769 rtl@unr.edu Dr. Ted Mitchell
More informationCumulative trends Problems and issues since last report
Project Progress Report Format Progress since last report Current status of project 1. Schedule 2. Cost 3. Scope Cumulative trends Problems and issues since last report 1. Actions and resolution of earlier
More informationPASS4TEST. IT Certification Guaranteed, The Easy Way! We offer free update service for one year
PASS4TEST IT Certification Guaranteed, The Easy Way! \ We offer free update service for one year Exam : PMI-SP Title : PMI Scheduling Professional Vendors : PMI Version : DEMO Get Latest & Valid PMI-SP
More informationMINIMIZE TIME AND COST FOR SUCCESSFUL COMPLETION OF A LARGE SCALE PROJECT APPLYING PROJECT CRASHING METHOD
International Journal of Advanced Research and Review www.ijarr.in MINIMIZE TIME AND COST FOR SUCCESSFUL COMPLETION OF A LARGE SCALE PROJECT APPLYING PROJECT CRASHING METHOD Shifat Ahmed Lecturer, Southeast
More informationGOVERNMENT ELECTRONICS AND INFORMATION TECHNOLOGY ASSOCIATION
GEIA STANDARD ANSI/EIA-748-B-2007 Approved: September 10, 2007 EIA-748-B Earned Value Management Systems EIA-748-B JUNE 2007 GOVERNMENT ELECTRONICS AND INFORMATION TECHNOLOGY ASSOCIATION A Sector of the
More informationIntermediate Systems Acquisition Course. Integrated Baseline Reviews (IBRs)
Integrated Baseline Reviews (IBRs) Holding an IBR is a best practice for all programs, and it supports the implementation of an earned value management system (EVMS). EVM can be a valuable tool for controlling
More informationProject Title: INFRASTRUCTURE AND INTEGRATED TOOLS FOR PERSONALIZED LEARNING OF READING SKILL
Project Title: INFRASTRUCTURE AND INTEGRATED TOOLS FOR PERSONALIZED LEARNING OF READING SKILL Project Acronym: Grant Agreement number: 731724 iread H2020-ICT-2016-2017/H2020-ICT-2016-1 Subject: Dissemination
More informationSCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016
All Rights Reserved No. of Pages - 10 No of Questions - 06 SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016 MGT 30725 Project
More informationProject Management. Managing Risk. Clifford F. Gray Eric W. Larson Third Edition. Chapter 7
Project Management THE MANAGERIAL PROCESS Clifford F. Gray Eric W. Larson Third Edition Chapter 7 Managing Risk Copyright 2006 The McGraw-Hill Companies. All rights reserved. PowerPoint Presentation by
More informationEngineering Economics and Financial Accounting
Engineering Economics and Financial Accounting Unit 4: Costing Major Topics are: Job Costing Operating Costing Process Costing Standard Costing (Variance Analysis) Gross Domestic Product (GDP) Job Costing
More informationOutline. Project Management. Introduction. What is a Project?
Outline Project Management Jeffrey Pinto, Ph.D. Penn State Erie What is Project Management? Scope Management Risk Management Planning and Scheduling Project Evaluation and Control Project Termination Introduction
More informationFinancial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT. Dr. Ahmed Elyamany
1 Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT Dr. Ahmed Elyamany 2 Course Content Project financial management: Cash flow prediction, Cash flow analysis, Cost of finance
More informationPAPER 3 SECTION 1 QUESTION ONE. NJOTO Limited Product Coolo: Besto: Zedo: Shs Shs Shs Selling price:
QUESTION ONE PAPER 3 SECTION 1 NJOTO Limited Product Coolo: Besto: Zedo: Shs Shs Shs Selling price: 60 48 59 Less variable cost per unit Direct Material 15 12 14 Direct Labour 25 50 23 Variable overheads
More informationExam Questions PMI-SP
Exam Questions PMI-SP PMI Scheduling Professional Practice Test https://www.2passeasy.com/dumps/pmi-sp/ 1.CORRECT TEXT Fill in the blank with the appropriate word. When activities are logically linked,
More informationManaging Project Risk DHY
Managing Project Risk DHY01 0407 Copyright ESI International April 2007 All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any form or
More informationPMI - Dallas Chapter. PMP Exam Sample Questions
PMI - Dallas Chapter PMP Exam Sample Questions June 4, 1999 Disclaimer: These questions are intended for study purposes only. Success on these questions is not necessarily predictive of success on the
More informationProject Management. Chapter 2. Copyright 2013 Pearson Education, Inc. publishing as Prentice Hall
Project Management Chapter 2 02-0 1 What is a Project? Project An interrelated set of activities with a definite starting and ending point, which results in a unique outcome for a specific allocation of
More informationEvery project is risky, meaning there is a chance things won t turn out exactly as planned.
PMBOK 5 Ed. DEI- Every project is risky, meaning there is a chance things won t turn out exactly as planned. percent of runaway projects Did no risk management at all 38 percent did some, and 7 percent
More informationChapter 8 Cost Estimating and Budgeting
Chapter 8 Cost Estimating and Budgeting Project Management for Business, Engineering, and Technology Prepared by John Nicholas, Ph.D. Loyola University Chicago Cost overrun % Cost Overruns on Projects
More informationBraindumps.PMI-SP.323 questions
Braindumps.PMI-SP.323 questions Number: PMI-SP Passing Score: 800 Time Limit: 120 min File Version: 4.8 http://www.gratisexam.com/ PMI-SP PMI Scheduling Professional It gets you study tools online for
More informationChapter 9 Activity-Based Costing
Chapter 9 Activity-Based Costing SUMMARY This chapter deals with the allocation of indirect costs to products. Product cost information helps managers make numerous decisions, such as pricing, keeping
More informationHaeryip Sihombing 1. Risk. Risk Management
Project Management Managing Risk 7 Haeryip Sihombing Universiti Teknikal Malaysia Melaka (UTeM) BMFP 4542 1 2 Risk Management Process The Risk Event Graph Risk Uncertain or chance events that planning
More informationCrashing the Schedule An Algorithmic Approach with Caveats and Comments
ing the Schedule An Algorithmic Approach with Caveats and Comments Gilbert C. Brunnhoeffer, III PhD, P.E. and B. Gokhan Celik PhD LEED AP Roger Williams University Bristol, Rhode Island and Providence
More informationProject Management. Basic Definitions: Project and Project Plan
Project Management Basic Definitions: Project and Project Plan Software Project: All technical and managerial activities required to deliver the deliverables to the client. A software project has a specific
More informationChapter 2 Lecture Notes. I. Summary of the types of cost classifications. Cost classifications for assigning costs to cost objects
Chapter 2 Lecture Notes 1 Chapter theme: This chapter explains how managers need to rely on different cost classifications for different purposes. The four main purposes emphasized in this chapter include
More informationRISK MANAGEMENT GUIDE FOR DOD ACQUISITION
RISK MANAGEMENT GUIDE FOR DOD ACQUISITION Sixth Edition (Version 1.0) August, 2006 Department of Defense Table of Contents. Key Activity - Risk Analysis... 11.1. Purpose... 11.2. Risk Reporting Matrix...
More informationMMZG 523 PROJECT MANAGEMENT
MMZG 523 PROJECT MANAGEMENT BITS Pilani Pilani Campus ARUN MAITY BITS Pilani Pilani Campus PROGRESS & PERFORMANCE MANAGEMENT AND EVALUATION CHAPTER NO 13 TEXTBOOK T1 Need Control holds people accountable
More informationPass PMP in 21 Days - ITTO Toolbox PROCESS MAP
PROCESS MAP 1 IntEgratIon Pass PMP in 21 Days - ITTO Toolbox InItIatIng PlannIng ExEcutIng MonItorIng & controlling closing Develop Project Charter Develop Project Management Plan Direct & Manage Project
More informationChapter 11: PERT for Project Planning and Scheduling
Chapter 11: PERT for Project Planning and Scheduling PERT, the Project Evaluation and Review Technique, is a network-based aid for planning and scheduling the many interrelated tasks in a large and complex
More informationCosting and Budgeting. From cost to value: methods and techniques to set the right cost to software
Costing and Budgeting From cost to value: methods and techniques to set the right cost to software Goals of the Unit Questions you might face: How much does the development of the software cost? Is the
More informationTopic 3: An introduction to cost terms and concepts
Topic 3: An introduction to cost terms and concepts Ana Mª Arias Alvarez University of Oviedo Department of Accounting amarias@uniovi.es School of Business Administration Course: Financial Statement Analysis
More informationSECTION PROJECT SCHEDULE 08/08
SECTION 01 32 01.00 10 PROJECT SCHEDULE 08/08 PART 1 GENERAL 1.1 REFERENCES The publications listed below form a part of this specification to the extent referenced. The publications are referred to within
More informationAssociation for Project Management 2008
Contents List of tables vi List of figures vii Foreword ix Acknowledgements x 1. Introduction 1 2. Understanding and describing risks 4 3. Purposes of risk prioritisation 12 3.1 Prioritisation of risks
More informationSolutions to the Fall 2015 CAS Exam 5
Solutions to the Fall 2015 CAS Exam 5 (Only those questions on Basic Ratemaking) There were 25 questions worth 55.75 points, of which 12.5 were on ratemaking worth 28 points. The Exam 5 is copyright 2015
More informationProject Management Resource Scheduling Eng. Giorgio Locatelli
Resource scheduling Project Management Resource Scheduling ng. Giorgio Locatelli Mauro Mancini Mauro Mancini Resource Scheduling Project Management: The planning, monitoring and control of all aspects
More informationTHE INSTITUTE OF CHARTERED ACCOUNTANTS (GHANA)
THE INSTITUTE OF CHARTERED ACCOUNTANTS (GHANA) MAY 22 EXAMINATIONS (PROFESSIONAL) PART 2 QUANTITATIVE TOOLS IN BUSINESS (Paper 2.) Attempt five (5) Questions in ALL TIME ALLOWED: Reading & Planning - 5
More informationEarned Value Management. Danielle Kellogg. Hodges University
Earned Value Management 1 EARNED VALUE MANAGEMENT Earned Value Management Danielle Kellogg Hodges University Earned Value Management 2 Abstract Earned Value Management has been used with enterprise-level
More information11/1/2018. Overview PERT / CPM. Network representation. Network representation. Project Scheduling. What is a path?
PERT / CPM BSD Dave Novak Fall Overview Introduce Discuss what a critical path is Discuss critical path algorithm Example Source: nderson et al., 1 Quantitative Methods for Business 1 th edition some slides
More informationPrinciples of Accounting, Tenth Edition
Principles of Accounting, Tenth Edition Answers to Stop, Review, and Apply Questions Chapter 14 The Corporate Income Statement and the Statement of Stockholders Equity 1-1. Quality of earnings refers to
More informationSystems Engineering. Engineering 101 By Virgilio Gonzalez
Systems Engineering Engineering 101 By Virgilio Gonzalez Systems process What is a System? What is your definition? A system is a construct or collection of different elements that together produce results
More information