Unit 5 Slide Lectures of 04/05/06 April 2017

Size: px
Start display at page:

Download "Unit 5 Slide Lectures of 04/05/06 April 2017"

Transcription

1 PROJECT AND COMMUNICATION MANAGEMENT Academic Year 2016/2017 PROJECT SCHEDULING, PROJECT DURATION AND PROJECT COMMUNICATION PLAN (CH. 8-9) Unit 5 Slide Lectures of 04/05/06 April 2017

2 Overview of the Resource Scheduling Problem Resources and Priorities Project network times are not a schedule until resources have been assigned. The implicit assumption is that resources will be available in the required amounts when needed. Adding new projects requires making realistic judgments of resource availability and project durations. Cost estimates are not a budget until they have been time-phased. 8 2

3 Project Planning Process FIGURE

4 The Resource Problem (cont d) Resource Smoothing (or Leveling) Involves attempting to even out varying demands on resources by using slack (delaying noncritical activities) to manage resource utilization when resources are adequate over the life of the project. Resource-Constrained Scheduling The duration of a project may be increased by delaying the late start of some of its activities if resources are not adequate to meet peak demands. 8 4

5 Types of Project Constraints Technical or Logic Constraints Constraints related to the networked sequence in which project activities must occur. Physical Constraints Activities that cannot occur in parallel or are affected by contractual or environmental conditions. Resource Constraints The absence, shortage, or unique interrelationship and interaction characteristics of resources that require a particular sequencing of project activities Kinds of Resource Constraints People, materials, equipment 8 5

6 Constraint Examples FIGURE

7 Classification of a Scheduling Problem Classification of Problem Using a priority matrix will help determine if the project is time or resource constrained. Time-Constrained Project Must be completed by an imposed date. Time is fixed, resources are flexible: additional resources are required to ensure project meets schedule. Resource-Constrained Project Is one in which the level of resources available cannot be exceeded. Resources are fixed, time is flexible: inadequate resources will delay the project. 8 7

8 Resource Allocation Methods Limiting Assumptions Splitting activities is not allowed once an activity is start, it is carried to completion. Level of resources used for an activity cannot be changed. Risk Assumptions Activities with the most slack pose the least risk. Reduction of flexibility does not increase risk. The nature of an activity (easy, complex) doesn t increase risk. 8 8

9 Resource Allocation Methods (cont d) Time-Constrained Projects Must be completed by an imposed date. Require use of leveling techniques that focus on balancing or smoothing resource demands. Use positive slack (delaying noncritical activities) to manage resource utilization over the duration of the project. Peak resource demands are reduced. Resources over the life of the project are reduced. Fluctuation in resource demand is minimized. 8 9

10 Botanical Garden FIGURE

11 Resource Allocation Methods (cont d) Resource Demand Leveling Techniques for Time-Constrained Projects Advantages Peak resource demands are reduced. Resources over the life of the project are reduced. Fluctuation in resource demand is minimized. Disadvantages Loss of flexibility that occurs from reducing slack. Increases in the criticality of all activities. 8 11

12 Resource Allocation Methods (cont d) Resource-Constrained Projects Resources are limited in quantity or availability. Activities are scheduled using heuristics (rules-of-thumb) that focus on: 1. Minimum slack 2. Smallest (least) duration 3. Lowest activity identification number The parallel method is used to apply heuristics An iterative process starting at the first time period of the project and scheduling period-by-period the start of any activities using the three priority rules. 8 12

13 Resource-Constrained Schedule through Period 2 3 FIGURE

14 Resource-Constrained Schedule through Period 2 3 FIGURE 8.4 (cont d) 8 14

15 Resource-Constrained Schedule through Period 2 3 FIGURE 8.4 (cont d) 8 15

16 Resource-Constrained Schedule through Period 5 6 FIGURE

17 Resource-Constrained Schedule through Period 5 6 FIGURE 8.5 (cont d) 8 17

18 Resource-Constrained Schedule through Period 5 6 FIGURE 8.5 (cont d) 8 18

19 Computer Demonstration of Resource- Constrained Scheduling EMR Project The development of a handheld electronic medical reference guide to be used by emergency medical technicians and paramedics. Problem There are only eight design engineers who can be assigned to the project due to a shortage of design engineers and commitments to other projects. 8 19

20 EMR Project: Network View Schedule before Resources Leveled FIGURE

21 EMR Project before Resources Added FIGURE

22 EMR Project Time Constrained Resource Usage View, January FIGURE 8.8A 8 22

23 Resource Loading Chart for EMR Project, January FIGURE 8.8B 8 23

24 EMR Project Network View Schedule after Resources Leveled FIGURE

25 EMR Project Resources Leveled FIGURE

26 The Impacts of Resource-Constrained Scheduling Reduces delay but reduces flexibility. Increases criticality of events. Increases scheduling complexity. May make the traditional critical path no longer meaningful. Can break sequence of events. May cause parallel activities to become sequential and critical activities with slack to become noncritical. 8 26

27 Splitting Splitting A scheduling technique for creating a better project schedule and/or increase resource utilization. Involves interrupting work on an activity to employ the resource on another activity, then returning the resource to finish the interrupted work. Is feasible when startup and shutdown costs are low. Is considered the major reason why projects fail to meet schedule. 8 27

28 Splitting Activities FIGURE

29 Benefits of Scheduling Resources Leaves time for consideration of reasonable alternatives: Cost-time tradeoffs Changes in priorities Provides information for time-phased work package budgets to assess: Impact of unforeseen events Amount of flexibility in available resources 8 29

30 Multiproject Resource Schedules Multiproject Scheduling Problems 1. Overall project slippage Delay on one project create delays for other projects. 2. Inefficient resource application The peaks and valleys of resource demands create scheduling problems and delays for projects. 3. Resource bottlenecks Shortages of critical resources required for multiple projects cause delays and schedule extensions. 8 30

31 Multiproject Resource Schedules (cont d) Managing Multiproject Scheduling: Create project offices or departments to oversee the scheduling of resources across projects. Use a project priority queuing system: first come, first served for resources. Centralize project management: treat all projects as a part of a megaproject. Outsource projects to reduce the number of projects handled internally. 8 31

32 Using the Resource Schedule to Develop a Project Cost Baseline Why a Time-Phased Budget Baseline Is Needed To determine if the project is on, ahead, or behind schedule and over or under its budgeted costs? To know how much work has been accomplished for the allocated money spent the project cost baseline (planned value, PV) Creating a Time-Phased Budget Assign each work package to one responsible person or department and deliverable. Compare planned schedule and costs using an integrative system called earned value. 8 32

33 Direct Labor Budget Rollup ($000) FIGURE

34 Time-Phased Work Package Budget (Labor Cost Only) FIGURE

35 Two Time-Phased Work Packages (Labor Cost Only) FIGURE

36 Patient Entry Project Network FIGURE

37 Patient Entry Time-Phased Work Packages Assigned FIGURE

38 CEBOO Project Monthly Cash Flow Statement FIGURE

39 CEBOO Project Weekly Resource Usage Schedule FIGURE

40 Key Terms Heuristic Leveling Planned value (PV) Resource-constrained projects Resource smoothing Splitting Time-constrained projects Time-phased budget baseline 8 40

41 Rationale for Reducing Project Duration Time Is Money: Cost-Time Tradeoffs Reducing the time of a critical activity usually incurs additional direct costs. Cost-time solutions focus on reducing (crashing) activities on the critical path to shorten overall duration of the project. Reasons for imposed project duration dates: Time-to-market pressures Unforeseen delays Incentive contracts (bonuses for early completion) Imposed deadlines and contract commitments Overhead and public goodwill costs Pressure to move resources to other projects 9 41

42 Options for Accelerating Project Completion Resources Not Constrained Adding resources Outsourcing project work Scheduling overtime Establishing a core project team Do it twice fast and then correctly Resources Constrained Fast-tracking Critical-chain Reducing project scope Compromise quality 9 42

43 Explanation of Project Costs Project Indirect Costs Costs that cannot be associated with any particular work package or project activity. Supervision, administration, consultants, and interest Costs that vary (increase) with time. Reducing project time directly reduces indirect costs. Project Direct Costs Normal costs that can be assigned directly to a specific work package or project activity. Labor, materials, equipment, and subcontractors Crashing activities increases direct costs. 9 43

44 Reducing Project Duration to Reduce Project Cost Identifying direct costs to reduce project time Gather information about direct and indirect costs of specific project durations. Search critical activities for lowest direct-cost activities to shorten project duration. Compute total costs for specific durations and compare to benefits of reducing project time. 9 44

45 Project Cost Duration Graph FIGURE

46 Constructing a Project Cost Duration Graph Find total direct costs for selected project durations. Find total indirect costs for selected project durations. Sum direct and indirect costs for these selected project durations. Compare additional cost alternatives for benefits. 9 46

47 Constructing a Project Cost Duration Graph Determining Activities to Shorten Shorten the activities with the smallest increase in cost per unit of time. Assumptions: The cost relationship is linear. Normal time assumes low-cost, efficient methods to complete the activity. Crash time represents a limit the greatest time reduction possible under realistic conditions. Slope represents a constant cost per unit of time. All accelerations must occur within the normal and crash times. 9 47

48 Activity Graph FIGURE

49 Cost Duration Trade-off Example FIGURE

50 Cost Duration Trade-off Example (cont d) FIGURE 9.3 (cont d) 9 50

51 Cost Duration Trade-off Example (cont d) FIGURE

52 Cost Duration Trade-off Example (cont d) FIGURE 9.4 (cont d) 9 52

53 Summary Costs by Duration FIGURE

54 Project Cost Duration Graph FIGURE

55 Practical Considerations Using the Project Cost Duration Graph Crash Times Linearity Assumption Choice of Activities to Crash Revisited Time Reduction Decisions and Sensitivity 9 55

56 What if Cost, Not Time Is the Issue? Commonly Used Options for Cutting Costs Reducing project scope Having owner take on more responsibility Outsourcing project activities or even the entire project Brainstorming cost savings options 9 56

57 Key Terms Crashing Crash point Crash time Direct costs Fast-tracking Indirect costs Outsourcing Project cost duration graph 9 57

58 Project Priority Matrix: Whitbread Project FIGURE C

Scheduling Resources and Costs

Scheduling Resources and Costs CHAPTER EIGHT Scheduling Resources and Costs Copyright 2014 McGraw-Hill Education. All Rights Reserved. PowerPoint Presentation by Charlie Cook Where We Are Now 8 2 Overview of the Resource Scheduling

More information

Reducing Project Duration

Reducing Project Duration CHAPTER NINE Reducing Project Duration McGraw-Hill/Irwin Copyright 2011 by The McGraw-Hill Companies, Inc. All rights reserved. Rationale for Reducing Project Duration Time Is Money: Cost-Time Tradeoffs

More information

Chapter 9: Reducing Project Duration 4KF3

Chapter 9: Reducing Project Duration 4KF3 Lecture Notes Options for Accelerating Project Completion Unconstrained Resources o Adding resources o Outsourcing o Overtime o Core project team o Do it twice Constrained Resources o Fast-tracking o Critical-chain

More information

Allocate and Level Project Resources

Allocate and Level Project Resources Allocate and Level Project Resources Resource Allocation: Defined Resource Allocation is the scheduling of activities and the resources required by those activities while taking into consideration both

More information

Project planning and creating a WBS

Project planning and creating a WBS 37E01500 Project Management and Consulting Practice Project planning and creating a WBS Matti Rossi Lecture 3, Tue 28.2.2017 Learning objectives Describe the project time management planning tasks, and

More information

PMI - Dallas Chapter. Sample Questions. March 22, 2002

PMI - Dallas Chapter. Sample Questions. March 22, 2002 PMI - Dallas Chapter PMP Exam Sample Questions March 22, 2002 Disclaimer: These questions are intended for study purposes only. Success on these questions is not necessarily predictive of success on the

More information

SCHEDULE CREATION AND ANALYSIS. 1 Powered by POeT Solvers Limited

SCHEDULE CREATION AND ANALYSIS. 1   Powered by POeT Solvers Limited SCHEDULE CREATION AND ANALYSIS 1 www.pmtutor.org Powered by POeT Solvers Limited While building the project schedule, we need to consider all risk factors, assumptions and constraints imposed on the project

More information

Sheila Belayutham CHAPTER 6 CONTROL

Sheila Belayutham CHAPTER 6 CONTROL CHAPTER 6 CONTROL LEARNING OUTCOME Students will be able to: Understand monitoring and control in construction. Understand the monitoring and control methods in construction. MONITORING & CONTROL It s

More information

INTRODUCTION PROJECT MANAGEMENT

INTRODUCTION PROJECT MANAGEMENT CHAPTER 7. 1 RESOURCE INTRODUCTION ALLOCATION TO PROJECT MANAGEMENT Prepared by: Dr. Maria Elisa Linda T. Cruz Prepared by: Dr. Maria Elisa Linda T. Cruz 1 Chapter 7. Resource Allocation 7.1 Critical Path

More information

SWEN 256 Software Process & Project Management

SWEN 256 Software Process & Project Management SWEN 256 Software Process & Project Management Plan: Identify activities. No specific start and end dates. Estimating: Determining the size & duration of activities. Schedule: Adds specific start and end

More information

Textbook: pp Chapter 11: Project Management

Textbook: pp Chapter 11: Project Management 1 Textbook: pp. 405-444 Chapter 11: Project Management 2 Learning Objectives After completing this chapter, students will be able to: Understand how to plan, monitor, and control projects with the use

More information

Project Management Chapter 13

Project Management Chapter 13 Lecture 12 Project Management Chapter 13 Introduction n Managing large-scale, complicated projects effectively is a difficult problem and the stakes are high. n The first step in planning and scheduling

More information

Risk Video #1. Video 1 Recap

Risk Video #1. Video 1 Recap Risk Video #1 Video 1 Recap 1 Risk Video #2 Video 2 Recap 2 Risk Video #3 Risk Risk Management Process Uncertain or chance events that planning can not overcome or control. Risk Management A proactive

More information

Introduction. Introduction. Six Steps of PERT/CPM. Six Steps of PERT/CPM LEARNING OBJECTIVES

Introduction. Introduction. Six Steps of PERT/CPM. Six Steps of PERT/CPM LEARNING OBJECTIVES Valua%on and pricing (November 5, 2013) LEARNING OBJECTIVES Lecture 12 Project Management Olivier J. de Jong, LL.M., MM., MBA, CFD, CFFA, AA www.olivierdejong.com 1. Understand how to plan, monitor, and

More information

MS Project 2007 Page 1 of 18

MS Project 2007 Page 1 of 18 MS Project 2007 Page 1 of 18 PROJECT MANAGEMENT (PM):- There are powerful environment forces contributed to the rapid expansion of the projects and project management approaches to the business problems

More information

Cost Slope Analysis 1

Cost Slope Analysis 1 Cost Slope Analysis 1 Running head: Cost Slope Analysis Cost Slope Analysis Technique Summary Su-Cheng Wu Cost Slope Analysis 2 Abstract: Cost Slope Analysis considers the following: direct, indirect cost,

More information

PMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved

PMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved Project Cost Management 1 Project Cost Management Processes 1. Estimate Costs 2. Determine Budget 3. Control Costs In some projects, especially with smaller scope, cost estimation and cost budgeting are

More information

Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management

Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management Slide 1 Looking Glass Development, LLC (303) 663-5402 / (888) 338-7447 4610 S. Ulster St. #150 Denver, CO 80237 information@lookingglassdev.com

More information

Monitoring and Controlling RCC Work in Delayed Construction Projects

Monitoring and Controlling RCC Work in Delayed Construction Projects Monitoring and Controlling RCC Work in Delayed Construction s Nimesh Gujarati, Dr. B S Balapgol Post Graduate Student (Construction and Management), DYPCOE, Akurdi, Pune-44, Maharashtra, India Principal,

More information

COPYRIGHTED MATERIAL. Index

COPYRIGHTED MATERIAL. Index Index Note to the reader: Throughout this index boldfaced page numbers indicate primary discussions of a topic. Italicized page numbers indicate illustrations. A A+ certification, 28 acceptance criteria

More information

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA This section is used for projects over $1,000,000 use other section if less than $1M SECTION 01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 SCOPE A. Preliminary Contract Schedule, Contract

More information

IP-CIS : CIS Project Management

IP-CIS : CIS Project Management Meltem Özturan www.mis.boun.edu.tr/ozturan/mis301 1 Project Management Tools and Techniques (PMTT) Feasibility Analysis Organizational Breakdown Structure Work Breakdown Structure Scheduling Earned Value

More information

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ International Project Management prof.dr MILOŠ D. MILOVANČEVIĆ Project time management Project cost management Time in project management process Time is a valuable resource. It is also the scarcest. Time

More information

4/14/2017. Unit 7 Slide Lectures of 19/20/21 April 2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13)

4/14/2017. Unit 7 Slide Lectures of 19/20/21 April 2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13) PROJECT AND COMMUNICATION MANAGEMENT Academic Year 2016/2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13) Unit 7 Slide 7.2.1 Lectures of 19/20/21 April 2017 Structure of a Project Monitoring

More information

Vendor: PMI. Exam Code: CA Exam Name: Certified Associate in Project Management. Version: Demo

Vendor: PMI. Exam Code: CA Exam Name: Certified Associate in Project Management. Version: Demo Vendor: PMI Exam Code: CA0-001 Exam Name: Certified Associate in Project Management Version: Demo QUESTION: 1 On what is project baseline development established? A. Approved product requirements B. Estimated

More information

Appendix A Decision Support Analysis

Appendix A Decision Support Analysis Field Manual 100-11 Appendix A Decision Support Analysis Section I: Introduction structure development, and facilities. Modern quantitative methods can greatly facilitate this Complex decisions associated

More information

Department of Industrial Engineering

Department of Industrial Engineering Department of Industrial Engineering Engineering Project Management Presented By Dr. Abed Schokry Chapter 15: Cost Control Learning Outcomes After completing this chapter students should be able to: Define

More information

Project Planning. Jesper Larsen. Department of Management Engineering Technical University of Denmark

Project Planning. Jesper Larsen. Department of Management Engineering Technical University of Denmark Project Planning jesla@man.dtu.dk Department of Management Engineering Technical University of Denmark 1 Project Management Project Management is a set of techniques that helps management manage large-scale

More information

Project Management -- Developing the Project Plan

Project Management -- Developing the Project Plan Project Management -- Developing the Project Plan Dr. Tai-Yue Wang Department of Industrial and Information Management National Cheng Kung University Tainan, TAIWAN, ROC 1 Where We Are Now 6 2 Developing

More information

After complete studying this chapter, You should be able to

After complete studying this chapter, You should be able to Chapter 10 Project Management Ch10: What Is Project Management? After complete studying this chapter, You should be able to Define key terms like Project, Project Management, Discuss the main characteristics

More information

Project Planning. Planning is an important step in project execution. Planning means:

Project Planning. Planning is an important step in project execution. Planning means: Project Planning Planning is an important step in project execution. Planning means: Thinking through future project actions Seeking and mentally inspecting the long path from the start to the finish Achieving

More information

Time and Cost Optimization Techniques in Construction Project Management

Time and Cost Optimization Techniques in Construction Project Management Time and Cost Optimization Techniques in Construction Project Management Mr.Bhushan V 1. Tatar and Prof.Rahul S.Patil 2 1. INTRODUCTION In the field of Construction the term project refers as a temporary

More information

UNIT-II Project Organization and Scheduling Project Element

UNIT-II Project Organization and Scheduling Project Element UNIT-II Project Organization and Scheduling Project Element Five Key Elements are Unique. Projects are unique, one-of-a-kind, never been done before. Start and Stop Date. Projects must have a definite

More information

Appendix B: Glossary of Project Management Terms

Appendix B: Glossary of Project Management Terms Appendix B: Glossary of Project Management Terms Assumption - There may be external circumstances or events that must occur for the project to be successful (or that should happen to increase your chances

More information

CISC 322 Software Architecture

CISC 322 Software Architecture CISC 22 Software Architecture Project Scheduling (PERT/CPM) Ahmed E. Hassan (Edited For Course Presentation, 206) Project A project is a temporary endeavour undertaken to create a "unique" product or service

More information

Mohammed Rafiuddin CEO and General Manager, BIOSI Biohazards Solutions Innovators

Mohammed Rafiuddin CEO and General Manager, BIOSI Biohazards Solutions Innovators Mohammed Rafiuddin CEO and General Manager, BIOSI Biohazards Solutions Innovators Profile of Mohammed Rafiuddin Mohammed is an active member of AACE International since 2006 with 30 years of experience

More information

Project Time-Cost Trade-Off

Project Time-Cost Trade-Off Project Time-Cost Trade-Off 7.1 Introduction In the previous chapters, duration of activities discussed as either fixed or random numbers with known characteristics. However, activity durations can often

More information

ISSN: [Mali* et al., 6(3): March, 2017] Impact Factor: 4.116

ISSN: [Mali* et al., 6(3): March, 2017] Impact Factor: 4.116 IJESRT INTERNATIONAL JOURNAL OF ENGINEERING SCIENCES & RESEARCH TECHNOLOGY TIME AND COST OPTIMIZATION BY MSP SOFTWARE Mali P. A*, Lokhande A.Y, Kadam S.K, Shirole S.B, More P.N, Velhal A.J * Department

More information

King Fahd University of Petroleum and Minerals College of Environmental Design CEM 520: Construction Contracting

King Fahd University of Petroleum and Minerals College of Environmental Design CEM 520: Construction Contracting King Fahd University of Petroleum and Minerals College of Environmental Design CEM 520: Construction Contracting Determination of Construction Contract Duration for Public Projects in Saudi Arabia By:

More information

Management Services Reviewer by Ma. Elenita Balatbat-Cabrera

Management Services Reviewer by Ma. Elenita Balatbat-Cabrera Course Name: Course Title: Instructors: Required Text: Course Description: XMASREV Management Services Review David, Dimalanta and Morales Management Services Reviewer by Ma. Elenita Balatbat-Cabrera This

More information

PMI PMI-SP. PMI Scheduling Professional. Download Full Version :

PMI PMI-SP. PMI Scheduling Professional. Download Full Version : PMI PMI-SP PMI Scheduling Professional Download Full Version : http://killexams.com/pass4sure/exam-detail/pmi-sp QUESTION: 311 A company hires a scheduler for one of its projects. What skills should he

More information

Project Management for EPC Contracts Presented by: Dr. Jamal F. AlBahar, PMP, VMA Registered Arbitrator; Member: PMI, CMAA, AACE, AAA, PMA, CSI, SAVE

Project Management for EPC Contracts Presented by: Dr. Jamal F. AlBahar, PMP, VMA Registered Arbitrator; Member: PMI, CMAA, AACE, AAA, PMA, CSI, SAVE Project Management for EPC Contracts Presented by: Dr. Jamal F. AlBahar, PMP, VMA Registered Arbitrator; Member: PMI, CMAA, AACE, AAA, PMA, CSI, SAVE INTRODUCTION: Project Management for Engineering and

More information

Project Management. Project Mangement. ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala.

Project Management. Project Mangement. ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala. Project Mangement ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala. Page 1 of 380 26/4/2008 Syllabus 1. Total Project Management Concept, relationship with other function and other organizations,

More information

Outline. Global Company Profile: Bechtel Group. The Importance of Project Management Project Planning Project Scheduling Project Controlling

Outline. Global Company Profile: Bechtel Group. The Importance of Project Management Project Planning Project Scheduling Project Controlling Project Management Outline Global Company Profile: Bechtel Group The Importance of Project Management Project Planning Project Scheduling Project Controlling Outline - Continued Project Management Techniques:

More information

PROJECT COST MANAGEMENT

PROJECT COST MANAGEMENT PROJECT COST MANAGEMENT For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, PMP, PMI-RMP

More information

Chapter 5, CVP Study Guide

Chapter 5, CVP Study Guide Chapter 5, CVP Study Guide Chapter theme: Cost-volume-profit (CVP) analysis helps managers understand the interrelationships among cost, volume, and profit by focusing their attention on the interactions

More information

How to arrange for financing? Cash Flow = Cash In Cash Out. = Income Expense. = Revenue - Cost

How to arrange for financing? Cash Flow = Cash In Cash Out. = Income Expense. = Revenue - Cost Analysis Contract How much is the total cost? How to arrange for financing? = Cash In Cash Out = Income Expense = Revenue - Cost 29/09/2016 Emad Elbeltagi 2 1 Project Expenses The project cost types: Fixed

More information

PMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005

PMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005 PMP Preparation Training Your key in Successful Project Management Akram Al-Najjar, PMP Cost Management Processes Chapter 7 Cost Management Slide 2 1 AGENDA What is Cost Management? Cost Management Processes

More information

Application of Earned Value Management (EVM) for Effective Project Control

Application of Earned Value Management (EVM) for Effective Project Control Application of Earned Value Management (EVM) for Effective Project Control Course No: B02-012 Credit: 2 PDH Boris Shvartsberg, Ph.D., P.E., P.M.P. Continuing Education and Development, Inc. 9 Greyridge

More information

PROJECT MANAGEMENT DIPLOMA COURSE

PROJECT MANAGEMENT DIPLOMA COURSE PROJECT MANAGEMENT DIPLOMA COURSE UNIT THREE PROJECT PLANNING TUTOR TALK: The Learning Outcomes for this assignment are: Describe the following: o Planning parameters o Planning quality o Developing a

More information

Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur. Lecture - 18 PERT

Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur. Lecture - 18 PERT Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur Lecture - 18 PERT (Refer Slide Time: 00:56) In the last class we completed the C P M critical path analysis

More information

Research Methods Outline

Research Methods Outline : Project Management James Gain jgain@cs.uct.ac.za Outline Introduction [] Project Management [] Experimental Computer Science [] Role of Mathematics [1] Designing User Experiments [] Qualitative Research

More information

Project Management Fundamentals

Project Management Fundamentals Project Management Fundamentals Course No: B04-003 Credit: 4 PDH Najib Gerges, Ph.D., P.E. Continuing Education and Development, Inc. 9 Greyridge Farm Court Stony Point, NY 10980 P: (877) 322-5800 F: (877)

More information

Guide to Earned Value Management (EVM) Scalability for Non-Major Acquisition Implementations

Guide to Earned Value Management (EVM) Scalability for Non-Major Acquisition Implementations Guide to Earned Value Management (EVM) for Non-Major Acquisition Implementations Prepared by the Civilian Agencies and Industry Working Group (CAIWG) March 2015 CAIWG Guide to EVM Table of Contents Introduction...

More information

1 of 14 4/27/2009 7:45 AM

1 of 14 4/27/2009 7:45 AM 1 of 14 4/27/2009 7:45 AM Chapter 7 - Network Models in Project Management INTRODUCTION Most realistic projects that organizations like Microsoft, General Motors, or the U.S. Defense Department undertake

More information

VIRGINIA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR SECTION 109 MEASUREMENT AND PAYMENT

VIRGINIA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR SECTION 109 MEASUREMENT AND PAYMENT SECTION 102.01 PREQUALIFICATION OF BIDDERS of the Specifications is amended as follows: The eighth paragraph is replaced by the following: When the Contractor's actual progress is more than 10 percent

More information

Project Management for the Professional Professional Part 3 - Risk Analysis. Michael Bevis, JD CPPO, CPSM, PMP

Project Management for the Professional Professional Part 3 - Risk Analysis. Michael Bevis, JD CPPO, CPSM, PMP Project Management for the Professional Professional Part 3 - Risk Analysis Michael Bevis, JD CPPO, CPSM, PMP What is a Risk? A risk is an uncertain event or condition that, if it occurs, has a positive

More information

Princess Nora University Computer Science and Information Faculty Information Systems Department IS321

Princess Nora University Computer Science and Information Faculty Information Systems Department IS321 Princess Nora University Computer Science and Information Faculty Information Systems Department IS321 Chapter 5 Initiating & Planning Systems Development Projects 1 Learning Objectives Describe steps

More information

Aquino, Canlas, David, Dimalanta, Manaloto and Sibug. Management Accounting by Ma. Elenita Balatbat-Cabrera

Aquino, Canlas, David, Dimalanta, Manaloto and Sibug. Management Accounting by Ma. Elenita Balatbat-Cabrera Course Name: XMGRAC1 Course Title: Managerial Accounting, Part 1 Instructors: Required Text: Course Description: Aquino, Canlas, David, Dimalanta, Manaloto and Sibug Management Accounting by Ma. Elenita

More information

CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon

CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon Abstract- Project Cost Management includes the processes involved in planning, estimating, budgeting,

More information

Activity Resource Elasticity: A New Approach to Project Crashing

Activity Resource Elasticity: A New Approach to Project Crashing Activity Resource Elasticity: A New Approach to Project Crashing Dr. Ronald S. Tibben-Lembke MGRS / 028 University of Nevada Reno, NV 89557 (775) 682-9164 Fax: (775) 784-1769 rtl@unr.edu Dr. Ted Mitchell

More information

Cumulative trends Problems and issues since last report

Cumulative trends Problems and issues since last report Project Progress Report Format Progress since last report Current status of project 1. Schedule 2. Cost 3. Scope Cumulative trends Problems and issues since last report 1. Actions and resolution of earlier

More information

PASS4TEST. IT Certification Guaranteed, The Easy Way! We offer free update service for one year

PASS4TEST. IT Certification Guaranteed, The Easy Way!  We offer free update service for one year PASS4TEST IT Certification Guaranteed, The Easy Way! \ We offer free update service for one year Exam : PMI-SP Title : PMI Scheduling Professional Vendors : PMI Version : DEMO Get Latest & Valid PMI-SP

More information

MINIMIZE TIME AND COST FOR SUCCESSFUL COMPLETION OF A LARGE SCALE PROJECT APPLYING PROJECT CRASHING METHOD

MINIMIZE TIME AND COST FOR SUCCESSFUL COMPLETION OF A LARGE SCALE PROJECT APPLYING PROJECT CRASHING METHOD International Journal of Advanced Research and Review www.ijarr.in MINIMIZE TIME AND COST FOR SUCCESSFUL COMPLETION OF A LARGE SCALE PROJECT APPLYING PROJECT CRASHING METHOD Shifat Ahmed Lecturer, Southeast

More information

GOVERNMENT ELECTRONICS AND INFORMATION TECHNOLOGY ASSOCIATION

GOVERNMENT ELECTRONICS AND INFORMATION TECHNOLOGY ASSOCIATION GEIA STANDARD ANSI/EIA-748-B-2007 Approved: September 10, 2007 EIA-748-B Earned Value Management Systems EIA-748-B JUNE 2007 GOVERNMENT ELECTRONICS AND INFORMATION TECHNOLOGY ASSOCIATION A Sector of the

More information

Intermediate Systems Acquisition Course. Integrated Baseline Reviews (IBRs)

Intermediate Systems Acquisition Course. Integrated Baseline Reviews (IBRs) Integrated Baseline Reviews (IBRs) Holding an IBR is a best practice for all programs, and it supports the implementation of an earned value management system (EVMS). EVM can be a valuable tool for controlling

More information

Project Title: INFRASTRUCTURE AND INTEGRATED TOOLS FOR PERSONALIZED LEARNING OF READING SKILL

Project Title: INFRASTRUCTURE AND INTEGRATED TOOLS FOR PERSONALIZED LEARNING OF READING SKILL Project Title: INFRASTRUCTURE AND INTEGRATED TOOLS FOR PERSONALIZED LEARNING OF READING SKILL Project Acronym: Grant Agreement number: 731724 iread H2020-ICT-2016-2017/H2020-ICT-2016-1 Subject: Dissemination

More information

SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016

SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016 All Rights Reserved No. of Pages - 10 No of Questions - 06 SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016 MGT 30725 Project

More information

Project Management. Managing Risk. Clifford F. Gray Eric W. Larson Third Edition. Chapter 7

Project Management. Managing Risk. Clifford F. Gray Eric W. Larson Third Edition. Chapter 7 Project Management THE MANAGERIAL PROCESS Clifford F. Gray Eric W. Larson Third Edition Chapter 7 Managing Risk Copyright 2006 The McGraw-Hill Companies. All rights reserved. PowerPoint Presentation by

More information

Engineering Economics and Financial Accounting

Engineering Economics and Financial Accounting Engineering Economics and Financial Accounting Unit 4: Costing Major Topics are: Job Costing Operating Costing Process Costing Standard Costing (Variance Analysis) Gross Domestic Product (GDP) Job Costing

More information

Outline. Project Management. Introduction. What is a Project?

Outline. Project Management. Introduction. What is a Project? Outline Project Management Jeffrey Pinto, Ph.D. Penn State Erie What is Project Management? Scope Management Risk Management Planning and Scheduling Project Evaluation and Control Project Termination Introduction

More information

Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT. Dr. Ahmed Elyamany

Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT. Dr. Ahmed Elyamany 1 Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT Dr. Ahmed Elyamany 2 Course Content Project financial management: Cash flow prediction, Cash flow analysis, Cost of finance

More information

PAPER 3 SECTION 1 QUESTION ONE. NJOTO Limited Product Coolo: Besto: Zedo: Shs Shs Shs Selling price:

PAPER 3 SECTION 1 QUESTION ONE. NJOTO Limited Product Coolo: Besto: Zedo: Shs Shs Shs Selling price: QUESTION ONE PAPER 3 SECTION 1 NJOTO Limited Product Coolo: Besto: Zedo: Shs Shs Shs Selling price: 60 48 59 Less variable cost per unit Direct Material 15 12 14 Direct Labour 25 50 23 Variable overheads

More information

Exam Questions PMI-SP

Exam Questions PMI-SP Exam Questions PMI-SP PMI Scheduling Professional Practice Test https://www.2passeasy.com/dumps/pmi-sp/ 1.CORRECT TEXT Fill in the blank with the appropriate word. When activities are logically linked,

More information

Managing Project Risk DHY

Managing Project Risk DHY Managing Project Risk DHY01 0407 Copyright ESI International April 2007 All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any form or

More information

PMI - Dallas Chapter. PMP Exam Sample Questions

PMI - Dallas Chapter. PMP Exam Sample Questions PMI - Dallas Chapter PMP Exam Sample Questions June 4, 1999 Disclaimer: These questions are intended for study purposes only. Success on these questions is not necessarily predictive of success on the

More information

Project Management. Chapter 2. Copyright 2013 Pearson Education, Inc. publishing as Prentice Hall

Project Management. Chapter 2. Copyright 2013 Pearson Education, Inc. publishing as Prentice Hall Project Management Chapter 2 02-0 1 What is a Project? Project An interrelated set of activities with a definite starting and ending point, which results in a unique outcome for a specific allocation of

More information

Every project is risky, meaning there is a chance things won t turn out exactly as planned.

Every project is risky, meaning there is a chance things won t turn out exactly as planned. PMBOK 5 Ed. DEI- Every project is risky, meaning there is a chance things won t turn out exactly as planned. percent of runaway projects Did no risk management at all 38 percent did some, and 7 percent

More information

Chapter 8 Cost Estimating and Budgeting

Chapter 8 Cost Estimating and Budgeting Chapter 8 Cost Estimating and Budgeting Project Management for Business, Engineering, and Technology Prepared by John Nicholas, Ph.D. Loyola University Chicago Cost overrun % Cost Overruns on Projects

More information

Braindumps.PMI-SP.323 questions

Braindumps.PMI-SP.323 questions Braindumps.PMI-SP.323 questions Number: PMI-SP Passing Score: 800 Time Limit: 120 min File Version: 4.8 http://www.gratisexam.com/ PMI-SP PMI Scheduling Professional It gets you study tools online for

More information

Chapter 9 Activity-Based Costing

Chapter 9 Activity-Based Costing Chapter 9 Activity-Based Costing SUMMARY This chapter deals with the allocation of indirect costs to products. Product cost information helps managers make numerous decisions, such as pricing, keeping

More information

Haeryip Sihombing 1. Risk. Risk Management

Haeryip Sihombing 1. Risk. Risk Management Project Management Managing Risk 7 Haeryip Sihombing Universiti Teknikal Malaysia Melaka (UTeM) BMFP 4542 1 2 Risk Management Process The Risk Event Graph Risk Uncertain or chance events that planning

More information

Crashing the Schedule An Algorithmic Approach with Caveats and Comments

Crashing the Schedule An Algorithmic Approach with Caveats and Comments ing the Schedule An Algorithmic Approach with Caveats and Comments Gilbert C. Brunnhoeffer, III PhD, P.E. and B. Gokhan Celik PhD LEED AP Roger Williams University Bristol, Rhode Island and Providence

More information

Project Management. Basic Definitions: Project and Project Plan

Project Management. Basic Definitions: Project and Project Plan Project Management Basic Definitions: Project and Project Plan Software Project: All technical and managerial activities required to deliver the deliverables to the client. A software project has a specific

More information

Chapter 2 Lecture Notes. I. Summary of the types of cost classifications. Cost classifications for assigning costs to cost objects

Chapter 2 Lecture Notes. I. Summary of the types of cost classifications. Cost classifications for assigning costs to cost objects Chapter 2 Lecture Notes 1 Chapter theme: This chapter explains how managers need to rely on different cost classifications for different purposes. The four main purposes emphasized in this chapter include

More information

RISK MANAGEMENT GUIDE FOR DOD ACQUISITION

RISK MANAGEMENT GUIDE FOR DOD ACQUISITION RISK MANAGEMENT GUIDE FOR DOD ACQUISITION Sixth Edition (Version 1.0) August, 2006 Department of Defense Table of Contents. Key Activity - Risk Analysis... 11.1. Purpose... 11.2. Risk Reporting Matrix...

More information

MMZG 523 PROJECT MANAGEMENT

MMZG 523 PROJECT MANAGEMENT MMZG 523 PROJECT MANAGEMENT BITS Pilani Pilani Campus ARUN MAITY BITS Pilani Pilani Campus PROGRESS & PERFORMANCE MANAGEMENT AND EVALUATION CHAPTER NO 13 TEXTBOOK T1 Need Control holds people accountable

More information

Pass PMP in 21 Days - ITTO Toolbox PROCESS MAP

Pass PMP in 21 Days - ITTO Toolbox PROCESS MAP PROCESS MAP 1 IntEgratIon Pass PMP in 21 Days - ITTO Toolbox InItIatIng PlannIng ExEcutIng MonItorIng & controlling closing Develop Project Charter Develop Project Management Plan Direct & Manage Project

More information

Chapter 11: PERT for Project Planning and Scheduling

Chapter 11: PERT for Project Planning and Scheduling Chapter 11: PERT for Project Planning and Scheduling PERT, the Project Evaluation and Review Technique, is a network-based aid for planning and scheduling the many interrelated tasks in a large and complex

More information

Costing and Budgeting. From cost to value: methods and techniques to set the right cost to software

Costing and Budgeting. From cost to value: methods and techniques to set the right cost to software Costing and Budgeting From cost to value: methods and techniques to set the right cost to software Goals of the Unit Questions you might face: How much does the development of the software cost? Is the

More information

Topic 3: An introduction to cost terms and concepts

Topic 3: An introduction to cost terms and concepts Topic 3: An introduction to cost terms and concepts Ana Mª Arias Alvarez University of Oviedo Department of Accounting amarias@uniovi.es School of Business Administration Course: Financial Statement Analysis

More information

SECTION PROJECT SCHEDULE 08/08

SECTION PROJECT SCHEDULE 08/08 SECTION 01 32 01.00 10 PROJECT SCHEDULE 08/08 PART 1 GENERAL 1.1 REFERENCES The publications listed below form a part of this specification to the extent referenced. The publications are referred to within

More information

Association for Project Management 2008

Association for Project Management 2008 Contents List of tables vi List of figures vii Foreword ix Acknowledgements x 1. Introduction 1 2. Understanding and describing risks 4 3. Purposes of risk prioritisation 12 3.1 Prioritisation of risks

More information

Solutions to the Fall 2015 CAS Exam 5

Solutions to the Fall 2015 CAS Exam 5 Solutions to the Fall 2015 CAS Exam 5 (Only those questions on Basic Ratemaking) There were 25 questions worth 55.75 points, of which 12.5 were on ratemaking worth 28 points. The Exam 5 is copyright 2015

More information

Project Management Resource Scheduling Eng. Giorgio Locatelli

Project Management Resource Scheduling Eng. Giorgio Locatelli Resource scheduling Project Management Resource Scheduling ng. Giorgio Locatelli Mauro Mancini Mauro Mancini Resource Scheduling Project Management: The planning, monitoring and control of all aspects

More information

THE INSTITUTE OF CHARTERED ACCOUNTANTS (GHANA)

THE INSTITUTE OF CHARTERED ACCOUNTANTS (GHANA) THE INSTITUTE OF CHARTERED ACCOUNTANTS (GHANA) MAY 22 EXAMINATIONS (PROFESSIONAL) PART 2 QUANTITATIVE TOOLS IN BUSINESS (Paper 2.) Attempt five (5) Questions in ALL TIME ALLOWED: Reading & Planning - 5

More information

Earned Value Management. Danielle Kellogg. Hodges University

Earned Value Management. Danielle Kellogg. Hodges University Earned Value Management 1 EARNED VALUE MANAGEMENT Earned Value Management Danielle Kellogg Hodges University Earned Value Management 2 Abstract Earned Value Management has been used with enterprise-level

More information

11/1/2018. Overview PERT / CPM. Network representation. Network representation. Project Scheduling. What is a path?

11/1/2018. Overview PERT / CPM. Network representation. Network representation. Project Scheduling. What is a path? PERT / CPM BSD Dave Novak Fall Overview Introduce Discuss what a critical path is Discuss critical path algorithm Example Source: nderson et al., 1 Quantitative Methods for Business 1 th edition some slides

More information

Principles of Accounting, Tenth Edition

Principles of Accounting, Tenth Edition Principles of Accounting, Tenth Edition Answers to Stop, Review, and Apply Questions Chapter 14 The Corporate Income Statement and the Statement of Stockholders Equity 1-1. Quality of earnings refers to

More information

Systems Engineering. Engineering 101 By Virgilio Gonzalez

Systems Engineering. Engineering 101 By Virgilio Gonzalez Systems Engineering Engineering 101 By Virgilio Gonzalez Systems process What is a System? What is your definition? A system is a construct or collection of different elements that together produce results

More information