Activity Resource Elasticity: A New Approach to Project Crashing

Size: px
Start display at page:

Download "Activity Resource Elasticity: A New Approach to Project Crashing"

Transcription

1 Activity Resource Elasticity: A New Approach to Project Crashing Dr. Ronald S. Tibben-Lembke MGRS / 028 University of Nevada Reno, NV (775) Fax: (775) rtl@unr.edu Dr. Ted Mitchell MGRS / 028 University of Nevada Reno, NV (775) Fax: (775) mitchjt@unr.edu 1

2 Activity Resource Elasticity: A New Approach to Project Crashing August 21, 2007 Abstract Traditional project crashing methods assume that, within a given range, the time saved is a linear function of the additional resources spent. We assume the time saved is a linear function of the increase in resources used per day. As a result, we can compute how sensitive an activity s duration is to the resources made available, which we call the resource elasticity of the activity, the percentage reduction in time, divided by the percentage increase in resources. This elasticity measure is a practical, easily implemented metric that allows the manager to identify which activities duration times are more or less sensitive to daily spending rates. This metric can be used for determining which activities should be crashed, which should be slowed (if the money for crashing has to come from another activity), and for determining which activities need to be most closely monitored. Keywords: Project management, project crashing, heuristic methods 1 Introduction If a project must be sped up to meet a deadline, crashing the program or project is to speed up various activities to reduce the total time of the project, by allocating more resources to their completion. To shorten the critical path (those activities whose durations determine the total project length), it is necessary to increase the resources allocated to activities on it. This increases both the cost per day and the total cost of the activities. The duration of some activities may be 2

3 very sensitive to changes in the resources allocated to them (e.g., dollars-per-day), while others may be relatively insensitive. In the past, project managers have had metrics to help judge the total change in costs due to crashing a project They have not had a metric for judging the relative sensitivity of a duration change due to an increase in resources or cost-per-day. This paper presents resource elasticity, a metric which allows a manager to easily see which activities durations are most sensitive to increases or reductions in resources. This is useful in determining which activities are most elastic, and would be sped up the most, with increased resources, if the project needs to be crashed. Many project managers are likely faced with the reality of a finite amount of resources, whether those resources be money, programmers, engineers, welders, or something else. If one activity is to be sped up, it may result in another activity being slowed. Resource elasticity can be used to see which activities are least elastic, and the resources should be taken from them, because they will be slowed the least from the loss of resources. Finally, if an activity is very inelastic, should it fall behind schedule, a great deal of additional resources will be required to get it sped up, so these activities should be monitored closely. For example, a long project may consist of several large activities that are being executed concurrently: some of the design phase may be being finished on a software module while coding proceeds on another module. In order to help one part of the project meet a deadline, the manager may need to steal programmers from one activity to help the other. Using our results, the manager can easily determine which activities will be most affected by a loss of resources. 2 Literature Project management has received a lot of attention in the operations research literature, since the initial papers by Malcolm et al. (1959), Kelly and Walker (1959) and Kelly (1961). In their seminal paper, Kelly and Walker (1959) considered a time-cost tradeoff, with a linear time-cost relationship. They show a convex cost function, which has minimal cost at a particular duration, but as the duration increases beyond this point, costs again rise. However, as a practical matter, they are only interested in times equal to or lesser than this time, and can assume the cost function is piecewise linear and non-increasing in the time. Berman (1964) considered an upward-concave time-cost function for each activity, under certainty or uncertainty. Petrovic 3

4 (1968) approached the problem as a dynamic program, and Lamberson and Hocking (1970) applied the techniques of linear programming to the time-cost tradeoff. Elmaghraby (1977) presented methods for strictly convex and strictly concave time-cost functions. See Tavares (2002) and Herroelen (2005) for an overview of other contributions of operations research to project scheduling. Since the beginning, a great deal of research on project crashing has focused on linear programming methods, as the references in Kolisch (1995) and Hartmann (1999) indicate. LP and IP formulations assume the various time durations are known, and the cost of those durations (e.g. Boctor 1996, Hartmann 1999). Because linear programming methods can easily incorporate various resource constraints, these are the methods of preference for resource-constrained projects, as well. In the first paper on PERT, Malcolm et al. (1959) presented their well-known method for estimating the probability of completing a project at its scheduled date using the beta distribution. As Elmaghraby (1977) explains, shortcomings in the assumptions behind PERT has lead to other techniques for dealing with uncertainty, including generalized activity networks (GAN) and graphical evaluation and review technique (GERT). Most of the literature has been focused on methods for determining a schedule for the project, a priori. That is to say, given the range of times in which each activity could be completed, find the most cost-effective way to complete the project in the desired time frame. However, considerable attention has also been paid to methods for assessing and dealing with risk and uncertainty (Pich, et al. 2002). 3 Resource Elasticity The traditional time-crashing approach looks at the time-cost tradeoff from the position that completing an activity in less time will require additional resources, that is, cost is a function of time. We look at that same relationship from the opposite perspective that duration time is a function of the applied resource rate. That is to say, the higher the daily spending rate, the shorter the duration time. We approach the problem somewhat differently from much of the literature. We are interested in simple methods, which could quickly be applied by a project manager with mud on his boots. An IP formulation of the problem assumes that the decision maker has information regarding each of the possible levels of tradeoffs between time and cost for each activity. As Kelly and Walker 4

5 Activity A D C C/D Normal 200 $11,550 $57.75 Crashed 160 $12,800 $80.00 Difference 40 $1,250 $31.25 Table 1: Costs and Durations for Activities A and B. (1959, p. 164) observed, Usually in practice insufficient data is available to make more than a linear approximation. Many managers may not be able to create a full menu of all of the possible time and cost combinations, because calculating each combination requires a certain amount of time, and thus, comes at some cost. For a project manager in the field, collecting all the necessary information to formulate and solve the IP model is likely a luxury he cannot afford. 3.1 Difference of Crashing Assumptions Traditional project crashing assumes that an activity can normally be completed in D N days for a total cost C N, or crashed for a total cost C C, when it will be completed in D C days. For example, suppose activity A (summarized in Table 3.1) can be normally completed in D N = 200 days, for a cost of C N = $11,550, or crashed to D C = 160 days, for a cost of C C = $12,800. Thus, for an additional cost of C C C N = $1,250, the project can be completed D = D N D C = 40 days faster. The project manager must decide between spending an additional $1,250 to save 40 days, or $0 to save 0 days. Additionally, it is typically assumed that points in-between are possible because the time saved is linear in the amount of additional spending. Assumption 1 The time saved, D, by additional additional spending C C N, is linear in the amount of additional spending, for C N C C C. Thus, the amount of additional cost, per day to be saved, the crash cost per day (CCPD) can be computed: CCPD = C C C N D N D C. Given the CCPD for a number of activities, it would seem logical to crash first the activity on the critical path with the lowest CCPD, and when its crashing opportunities are exhausted, move to the next cheapest, etc., until the crash time reduction has been achieved, or the cost per day crashed exceeds the benefit per day. Many textbooks present some version of this. For example, 5

6 Crash critical activities, in order of increasing costs, as long as crashing costs do not exceed benefits (Stevenson 2002, p. 794). Under assumption 1, if total spending is C 1, the time saved is D = C 1 C N CCPD. Rearranging, under Assumption 1, to save D days, we may solve for C 1 as a function of D: C 1 ( D) = C N + D CCPD. So for activity A, if D = 10 days, C 1 (10) = $11, $31.25 = $11, In some cases, assuming that the time saved is linear in the amount of additional cost may be quite reasonable. For example, if an activity can be sped up by paying a group of welders to work overtime, paying half the amount of overtime should result in roughly half of the time savings. In this paper, we make a different assumption about linearity. For any project, the resource usage per day, R = C/D can be computed. For example, when crashed, activity A has a resource usage rate of R C = C C /D C = $12,800/160 = $80/day, and the normal usage rate is R N = C N /D N = $11,550/200 = $57.75/day. We assume that the time savings are linear in the resources used per day. Assumption 2 The time savings D, from crashing, are linear in the additional resources per day used, R R N, for R N R R C. Under assumption 2, the days saved, D, as a function of the resources spent per day, R, can be written: D 2 (R) = (R R N ) D N D C R C R N. (1) Alternatively, we may solve for the resources used per day, as a function of the days to be saved, R 2 ( D), under Assumption 2. R 2 ( D) = R N + D R C R N D N D C. (2) If D = 0, R 2 ( D) = R N. If D = D N D C, then R 2 ( D) = R C. For values of D in-between, R 2 (D) is linear in D. It is easily verified that R 2 ( D) D = R C R N D N D C. (3) Under Assumption 2, the relationship between additional resource usage and time saved is clearly linear. 6

7 Activity Duration D N D C Changing Duration Impact Resource Usage Impact R N R C Resources/Day Figure 1: Resource-Duration Combinations from Assumption 2 Under Assumption 1, the resources used per day, as a function of the days to be saved, R 1 ( D), are given by Taking the derivative with respect to D, it can be shown: R 1 ( D) = C N + D CCPD. (4) D N D R 1 ( D) D = D N CCPD + C N (D N D) 2. (5) Clearly, the resource usage per day is not linear in D under Assumption Similarity of Solutions Considered Figure 1 shows the combinations of R and D that would be available under Assumption 2. The vertical rectangle shows the total cost under normal conditions. With a width R N and height D N, it has an area of R N D N = C N. The horizontal rectangle has area of R C D C = C C. By assumption, C C > C N, and the areas of the rectangles reflects this. The straight line tangent to the two rectangles represents the crashing combinations available under Assumption 2, for resource usage rates between R N and R C. Although the traditional CCPD assumption does not result in a linear relationship between resources used per day and the days saved, as a practical matter, the relationship turns out to be nearly linear, as the following graphs demonstrate. 7

8 Project Length, D Resources / Day Figure 2: Resource-Duration Combinations from Assumption 1 Figure 2 represents the cost of crashing and normal completion. The rectangle with vertical striping represents the total cost for the regular project, because its width is R N = $57.75 per day, and its height is D N = 200 days, giving it area of R N D N = C N. The horizontal rectangle with horizontal striping represents the total cost for the crashed project, because its width is R C = $80 per day, and its height is D C = 160 days, giving it area of R C D C = C C > C N. The line connecting the upper-right corners of the two rectangles traces out the possible R, D combinations, under Assumption 1. Unfortunately, given the scale of the picture, it is difficult to see much of the tradeoff between crashing and normal operation. In Figure 3, the same points are shown, but the origin has been shifted, to better show detail. As a reference, the straight line of combinations under Assumption 2 has been drawn through the extreme points of crashing and normal. As it can be seen, although the CCPD line is not linear, it is very nearly linear. The conclusion we may draw from this is that although the two assumptions differ in their relationship between resources and project completion time, they end up considering a nearly identical set of crashing possibilities. 3.3 Elasticity as a Measure of Sensitivity Without crashing, an activity would be completed in time D N, using R N resources per day, for total cost of D N R N. With crashing, it is completed in D C, using R C resources per day, for total cost D C R C. We break the change in total costs into two factors: a savings due to faster completion, and an increase due to higher resource usage per day. 8

9 Project Length, D Resources / Day Figure 3: Assumption 1 Resource-Duration Combinations, Magnified If an activity is completed in less time, it could be argued there should be some savings, because fewer days of expense are incurred. However, more money is being spent per day, which likely more than offsets the savings from the shorter completion time. For example, if we could complete the activity in the crash time D C, but using normal resource levels, R N, the impact on total costs of changing the duration would be R N (D C D N ). However, for each of the D C days, the cost impact of increasing the resource usage rate is D C (R C R N ). Figure 1 shows these impacts graphically. For activity A, crashing increases costs by D C R C D N R N = $1,250. The impact from changing the duration is R N (D C D N ) = $57.75( ) = -$2,310. The impact from greater resource usage per day is D C (R C R N ) = 160($80 - $57.75) = $3,560, so the net impact of the change = $3,560 - $2,310 = $1,250, exactly the total cost difference. Because crashing is more expensive than the normal completion time, we know R N (D C D N ) < D C (R C R N ). If the crashing cost were the same as normal completion, the terms would be equal. If we have several activities to consider crashing, we would like to choose the activity with the least net impact, which will be the activity where the two terms are closest to being equal. We argue that taking the ratio of these two terms can tell us which activities should be crashed, and we define this ratio as E: E = Changing Duration Impact Resource Usage Impact = R N (D C D N ) D C (R C R N ). (6) This ratio is, in fact, the elasticity of completion time, with respect to resource usage. Because we have only two estimates of the relationship between resources and completion time, we must derive an arc elasticity term, instead of point elasticity. Arc elasticity has been discussed in the 9

10 economics literature by Sheldon (1986), following Gould and Ferguson (1980), Machlup (1952), and Lerner (1933). Following them, we may define: E = D/D R/R = R D D R = R N (D C D N ) D C (R C R N ). (7) From the first expression, we see that E is the ratio of percentage changes in D to percentage changes in R. By assumption, D C < D N, and R C > R N, so E < 0. For activity A, we obtain E = 2,310/3,560 = , which means a 1% decrease in resource expenditure leads to a 0.65% increase in activity duration. For any two activities, the one with the lower E value is less sensitive to changes in resource usage. If we have resources to give, the greatest percentage impact will be seen by giving resources to the activity with the highest E. If activities need to be taken away, they should be taken from the activity with the lowest E, since it is least sensitive to changes in R. Also, activities with lower elasticities must be monitored more carefully, because if they fall behind, more resources will be required to bring them back up to schedule. 3.4 Total Cost of Crashing Because of Assumption 2, within the range of R values from the crash and normal options R [R N,R C ], the relationship of duration to resource usage can be given by a straight line, shown in Figure 1: D 2 (R) = a br. (8) The term a represents a hypothetical project duration if zero resources are assigned, and is an artifact of the linearity assumption. The term b shows how duration decreases in R, a term previously derived in (1): b = (D N D C )/(R C R N ). We can then find a = D N + R N b. For activity A, b = ( )/( ) = 40/22.25 = so a = = Thus, total cost D(R) = R, and it is easily verified it returns the proper values for R = and R = 80. The total cost is given by C = R D. Substituting in D 2 (R) from (8), we obtain: C 2 (R) = R(a br) = ar br 2. (9) For A, C = 303.8R 1.798R 2, which is quadratic, as shown in Figure 4. The vertical line is at the lower range of R, R = $57.75, and the dashed vertical line is at the upper range of R, R = $80. 10

11 20,000 18,000 16,000 14,000 Total Cost, C 12,000 10,000 8,000 6,000 4,000 2, Resources per Day, R Figure 4: Total Cost of Activity A as function of Resources per Day, R From first-order conditions, C(R) can be shown to reach a maximum value at R = a/2b. We can see from Figure 4, C obtains a maximum value at R = 303.8/( ) = 84.5, and a minimum value at R = 0, both of which are well outside the [70,80] range. The downward sloping portion of C for R > a/2b is also an artifact of our linearity assumption. Given a total cost amount C, we can use the quadratic formula to the find the two values of R will yield the desired value of C(R). One solution is R > a/2b, and therefore not feasible. Substituting the relevant solution into (8), we can find the resulting duration. For example, if we have $12,000 to spend on activity A, we need to solve $12,000 = 303.8R 1.798R 2 for R. From the quadratic formula, we obtain R = and R = The second, > 84.5 = a/2b, and > 80 = R max. The other value, < a/2b, and it is easily verified that C 2 (62.93) = (62.93) 1.798(62.93) 2 = 19, ,119.4 = 12,000, as desired. 4 Crashing Decisions We can use our elasticity formulas to either figure out which activities to speed up, or which activities to slow down, should that be needed. 11

12 Activity D N D C C N C C E R N R C B $11,550 $12, C $16,800 $19, Table 2: Costs and Durations for Activities A and B. 4.1 Which Activitiy to Crash We can use equation (7) to to decide which activity to crash. For example, suppose we have two activities, B and C, (listed in Table 2) and we need to decide which to crash. Activity C is more elastic, so spending on C will have a greater bang for the buck than spending on B, and should be crashed first. Suppose 4 days needed to be saved from either B or C. We can use equation (2) to see how many resources would need to be used per day to gain 4 days. For activity B, R2 B (4) = (80 70)/( ) = /5 = 78. The new cost of activity B is now C B = R D = 78 (165 4) = $12, 558. Crashing increased costs by $12,558 - $11,550= $1,008. For activity A, R2 A (4) = (90 60)/( ) = /60 = 62. The new cost of activity C is now C C = R D = 62 (280 4) = $17,112. Crashing increased costs by $17,112 - $16,800 = $312. As predicted by the elasticity, C is the better activity to crash. Another way to arrive at this same result is to look at the change in R. For activity B, to gain 4 days is a reduction of 2.42% from 165. An elasticity of means that daily resource usage must be increased by 2.42% / = 11.1% of $70, for R = $ Which Activity to Slow Down We can also use elasticity to decide which activities to slow down, and equations (8) and (9) to determine the impact of adding or withholding resources. For example, suppose that we had already decided to crash both B and C, and activity A has become delayed, and we are going to have to dedicate an additional $1,000 in resources to A, so it can be crashed. When $1,000 less is spent on B or C, it will be in a slow crash mode, where we will not spend enough to achieve the full crash benefits, but the activity will be faster than normal. B has a smaller elasticity, and is thus less sensitive to reductions in resources, so the $1,000 should be taken from it, if that is 12

13 feasible. We were planning to spend $1,250 to crash B, so it would be feasible to spend $1,000 less, giving CC B = $11,800. Solving for a and b, the cost of B is CB (R) = 200R 0.5R 2. Solving $11,800 = 200R 0.5R 2, we obtain R B = $ as the resources to devote to B in a slow-crash situation. Substituting into equation (8), the length of the slow-crash is found: D B S = (71.94) = = 164 days. Taking $1,000 from B increases its completion time by 4 days. We originally planned to spend $3,000 crashing C, so taking $1,000 from it is feasible. Computing the parameter values for B, a = 400,b = 2. Given a slow-crash cost of $18,800, we solve $18,800 = 400R 2R 2, we obtain RS C = $ Substituting into equation (9), the slow-crash length is found: DS C = 400 2(75.50) = 249 days. Taking $1,000 from C increases its completion time by 29 days. Clearly, the elasticity gave the right decision. Compared to normal, daily resource usage of $71.94 is a 2.77% increase. Multiplied by the elasticity of , the percentage change in duration is = 0.606,% compared to the normal time of 165, a reduction of 1 day. 4.3 Other Duration Times In many cases, the normal and crash times represent the extreme possibilities, and nothing faster or slower than them may be considered. In some cases, however, it may be realistic to also speak about a slow normal time, which is slower than the normal time, or a fast crash time, faster than the crash time. If the normal and crash times are the project manager s best guess, and not the result of weeks of study by a fleet of analysts, it might be quite reasonable to consider times faster than the crash time, or slower than normal. If the linear relationship between daily resource usage and duration holds for the range [R N,R C ], it is possible this relationship may also hold for points close to, but outside of this range. Figure 1 shows what the linear relationship would look like if it held for R (0,a/2b). The relationship clearly could not hold for R = 0, but it could hold for values smaller than R N, or larger than R C. If the linear assumption holds for larger or smaller R values, we can consider the possibility of further crashing of an already-crashed activity, for a fast crash time, or of slowing down a normal activity for a slow normal time. 13

14 5 Summary and Conclusions In this paper, we have presented a new method for determining which project activities to crash. The calculation of resource elasticity requires no new information, and is computed using the project manager s conventional estimates of normal and crash duration times as well as normal and crash costs. Instead of assuming a linear relationship between crash spending and time saved, we assume a linear relationship between the additional resources used per day and the time saved. This assumption allows us to compute a resource elasticity measurement that tells us which activities will respond most significantly to increases in the resources allocated to them. Resources that are highly resource elastic can easily be brought back onto schedule, should they fall behind, and highly inelastic activities would require large amounts of additional resources to speed up, should they fall behind. Therefore, highly inelastic activities need to be monitored carefully in order to make sure that they do not fall behind. If resources need to be taken away from an activity, they should be taken from the activity that will be affected the least. 6 References Berman, S Resource allocation in a PERT network under continuous time-cost functions. Management Science, 10(4) Boctor, F A new and efficient heuristic for scheduling projects with resource restrictions and multiple execution modes. European Journal of Operational Research, 90, Elmaghraby, S Activity networks: Project planning and control by network models. John Wiley Interscience: New York. Gould J., and C. Ferguson Microeconomic theory (5th ed.). Irwin: Homewood, IL. Hartmann, S Project scheduling under limited resources. Springer: Berlin. Herroelen, W Project scheduling - Theory and practice. Production and Operations Management, 14(4) Kelly, J Critical-path planning and scheduling: Mathematical basis. Operations Research, 9(3) Kelly, J., and M.R. Walker Critical path planning and scheduling. in Proc. of the eastern joint computer conference. Boston, MA, December 1-3, Kolisch, R Project scheduling under resource constraints. Physica Verlag: Kiel, Ger- 14

15 many. Lamberson L., and R.R. Hocking Optimum time compression in project scheduling. Management Science, 16(10) Learner, A The diagrammatical representation of elasticity of demand. Review of Economic Studies, I(1) Machlup, F The economics of sellers competition: Model analysis of sellers conduct. Baltimore: Johns Hopkins press. Malcolm, D., J. Rosenbloom, C. Clark Application of a technique for research and development program evaluation. Operations Research, 7(5) Petrovic, R Optimization of resource allocation in project planning. Operations Research, 16(3) Pich, M., C. Loch, and A. De Meyer On uncertainty, ambiguity, and complexity in project management. Management Science, 48, (8) Sheldon, J A note on the teaching of arc elasticity. Journal of Economic Education, (3) Stevenson, W Production operations management. Irwin McGraw-Hill: Burr Ridge, IL. Tavares, L A review of the contribution of operational research to project management. European Journal of Operational Research, 136, Williams, T Allocation of contingency in activity duration networks. Construction Management and Economics, 17,

A Linear Programming Approach for Optimum Project Scheduling Taking Into Account Overhead Expenses and Tardiness Penalty Function

A Linear Programming Approach for Optimum Project Scheduling Taking Into Account Overhead Expenses and Tardiness Penalty Function A Linear Programming Approach for Optimum Project Scheduling Taking Into Account Overhead Expenses and Tardiness Penalty Function Mohammed Woyeso Geda, Industrial Engineering Department Ethiopian Institute

More information

2 Maximizing pro ts when marginal costs are increasing

2 Maximizing pro ts when marginal costs are increasing BEE14 { Basic Mathematics for Economists BEE15 { Introduction to Mathematical Economics Week 1, Lecture 1, Notes: Optimization II 3/12/21 Dieter Balkenborg Department of Economics University of Exeter

More information

The application of linear programming to management accounting

The application of linear programming to management accounting The application of linear programming to management accounting After studying this chapter, you should be able to: formulate the linear programming model and calculate marginal rates of substitution and

More information

1 Maximizing profits when marginal costs are increasing

1 Maximizing profits when marginal costs are increasing BEE12 Basic Mathematical Economics Week 1, Lecture Tuesday 9.12.3 Profit maximization / Elasticity Dieter Balkenborg Department of Economics University of Exeter 1 Maximizing profits when marginal costs

More information

Game Theory and Economics Prof. Dr. Debarshi Das Department of Humanities and Social Sciences Indian Institute of Technology, Guwahati

Game Theory and Economics Prof. Dr. Debarshi Das Department of Humanities and Social Sciences Indian Institute of Technology, Guwahati Game Theory and Economics Prof. Dr. Debarshi Das Department of Humanities and Social Sciences Indian Institute of Technology, Guwahati Module No. # 03 Illustrations of Nash Equilibrium Lecture No. # 02

More information

Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur. Lecture - 18 PERT

Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur. Lecture - 18 PERT Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur Lecture - 18 PERT (Refer Slide Time: 00:56) In the last class we completed the C P M critical path analysis

More information

An Application of Mathematical Model to Time-cost Trade off Problem (Case Study)

An Application of Mathematical Model to Time-cost Trade off Problem (Case Study) Australian Journal of Basic and Applied Sciences, 5(7): 208-214, 2011 ISSN 1991-8178 An Application of Mathematical Model to Time-cost Trade off Problem (ase Study) 1 Amin Zeinalzadeh 1 Tabriz Branch,

More information

False_ The average revenue of a firm can be increasing in the firm s output.

False_ The average revenue of a firm can be increasing in the firm s output. LECTURE 12: SPECIAL COST FUNCTIONS AND PROFIT MAXIMIZATION ANSWERS AND SOLUTIONS True/False Questions False_ If the isoquants of a production function exhibit diminishing MRTS, then the input choice that

More information

Chapter 19: Compensating and Equivalent Variations

Chapter 19: Compensating and Equivalent Variations Chapter 19: Compensating and Equivalent Variations 19.1: Introduction This chapter is interesting and important. It also helps to answer a question you may well have been asking ever since we studied quasi-linear

More information

ECON Micro Foundations

ECON Micro Foundations ECON 302 - Micro Foundations Michael Bar September 13, 2016 Contents 1 Consumer s Choice 2 1.1 Preferences.................................... 2 1.2 Budget Constraint................................ 3

More information

Project Time-Cost Trade-Off

Project Time-Cost Trade-Off Project Time-Cost Trade-Off 7.1 Introduction In the previous chapters, duration of activities discussed as either fixed or random numbers with known characteristics. However, activity durations can often

More information

Reducing Project Duration

Reducing Project Duration CHAPTER NINE Reducing Project Duration McGraw-Hill/Irwin Copyright 2011 by The McGraw-Hill Companies, Inc. All rights reserved. Rationale for Reducing Project Duration Time Is Money: Cost-Time Tradeoffs

More information

Problem 1 / 20 Problem 2 / 30 Problem 3 / 25 Problem 4 / 25

Problem 1 / 20 Problem 2 / 30 Problem 3 / 25 Problem 4 / 25 Department of Applied Economics Johns Hopkins University Economics 60 Macroeconomic Theory and Policy Midterm Exam Suggested Solutions Professor Sanjay Chugh Fall 00 NAME: The Exam has a total of four

More information

A Note on Ramsey, Harrod-Domar, Solow, and a Closed Form

A Note on Ramsey, Harrod-Domar, Solow, and a Closed Form A Note on Ramsey, Harrod-Domar, Solow, and a Closed Form Saddle Path Halvor Mehlum Abstract Following up a 50 year old suggestion due to Solow, I show that by including a Ramsey consumer in the Harrod-Domar

More information

Cost Slope Analysis 1

Cost Slope Analysis 1 Cost Slope Analysis 1 Running head: Cost Slope Analysis Cost Slope Analysis Technique Summary Su-Cheng Wu Cost Slope Analysis 2 Abstract: Cost Slope Analysis considers the following: direct, indirect cost,

More information

Time and Cost Optimization Techniques in Construction Project Management

Time and Cost Optimization Techniques in Construction Project Management Time and Cost Optimization Techniques in Construction Project Management Mr.Bhushan V 1. Tatar and Prof.Rahul S.Patil 2 1. INTRODUCTION In the field of Construction the term project refers as a temporary

More information

Journal of College Teaching & Learning February 2007 Volume 4, Number 2 ABSTRACT

Journal of College Teaching & Learning February 2007 Volume 4, Number 2 ABSTRACT How To Teach Hicksian Compensation And Duality Using A Spreadsheet Optimizer Satyajit Ghosh, (Email: ghoshs1@scranton.edu), University of Scranton Sarah Ghosh, University of Scranton ABSTRACT Principle

More information

Characterization of the Optimum

Characterization of the Optimum ECO 317 Economics of Uncertainty Fall Term 2009 Notes for lectures 5. Portfolio Allocation with One Riskless, One Risky Asset Characterization of the Optimum Consider a risk-averse, expected-utility-maximizing

More information

Theory of Consumer Behavior First, we need to define the agents' goals and limitations (if any) in their ability to achieve those goals.

Theory of Consumer Behavior First, we need to define the agents' goals and limitations (if any) in their ability to achieve those goals. Theory of Consumer Behavior First, we need to define the agents' goals and limitations (if any) in their ability to achieve those goals. We will deal with a particular set of assumptions, but we can modify

More information

Firm s demand for the input. Supply of the input = price of the input.

Firm s demand for the input. Supply of the input = price of the input. Chapter 8 Costs Functions The economic cost of an input is the minimum payment required to keep the input in its present employment. It is the payment the input would receive in its best alternative employment.

More information

not to be republished NCERT Chapter 2 Consumer Behaviour 2.1 THE CONSUMER S BUDGET

not to be republished NCERT Chapter 2 Consumer Behaviour 2.1 THE CONSUMER S BUDGET Chapter 2 Theory y of Consumer Behaviour In this chapter, we will study the behaviour of an individual consumer in a market for final goods. The consumer has to decide on how much of each of the different

More information

THE TRAVELING SALESMAN PROBLEM FOR MOVING POINTS ON A LINE

THE TRAVELING SALESMAN PROBLEM FOR MOVING POINTS ON A LINE THE TRAVELING SALESMAN PROBLEM FOR MOVING POINTS ON A LINE GÜNTER ROTE Abstract. A salesperson wants to visit each of n objects that move on a line at given constant speeds in the shortest possible time,

More information

Project Management and Resource Constrained Scheduling Using An Integer Programming Approach

Project Management and Resource Constrained Scheduling Using An Integer Programming Approach Project Management and Resource Constrained Scheduling Using An Integer Programming Approach Héctor R. Sandino and Viviana I. Cesaní Department of Industrial Engineering University of Puerto Rico Mayagüez,

More information

Midterm 2 - Solutions

Midterm 2 - Solutions Ecn 00 - Intermediate Microeconomic Theory University of California - Davis February 7, 009 Instructor: John Parman Midterm - Solutions You have until 3pm to complete the exam, be certain to use your time

More information

Global Financial Management

Global Financial Management Global Financial Management Bond Valuation Copyright 24. All Worldwide Rights Reserved. See Credits for permissions. Latest Revision: August 23, 24. Bonds Bonds are securities that establish a creditor

More information

3/1/2016. Intermediate Microeconomics W3211. Lecture 4: Solving the Consumer s Problem. The Story So Far. Today s Aims. Solving the Consumer s Problem

3/1/2016. Intermediate Microeconomics W3211. Lecture 4: Solving the Consumer s Problem. The Story So Far. Today s Aims. Solving the Consumer s Problem 1 Intermediate Microeconomics W3211 Lecture 4: Introduction Columbia University, Spring 2016 Mark Dean: mark.dean@columbia.edu 2 The Story So Far. 3 Today s Aims 4 We have now (exhaustively) described

More information

Chapter 6: Supply and Demand with Income in the Form of Endowments

Chapter 6: Supply and Demand with Income in the Form of Endowments Chapter 6: Supply and Demand with Income in the Form of Endowments 6.1: Introduction This chapter and the next contain almost identical analyses concerning the supply and demand implied by different kinds

More information

Reuben Gronau s Model of Time Allocation and Home Production

Reuben Gronau s Model of Time Allocation and Home Production Econ 301: Topics in Microeconomics Sanjaya DeSilva, Bard College, Spring 2008 Reuben Gronau s Model of Time Allocation and Home Production Gronau s model is a fairly simple extension of Becker s framework.

More information

Eastern Mediterranean University Faculty of Business and Economics Department of Economics Spring Semester

Eastern Mediterranean University Faculty of Business and Economics Department of Economics Spring Semester Eastern Mediterranean University Faculty of Business and Economics Department of Economics 2015 16 Spring Semester ECON101 Introduction to Economics I Second Midterm Exam Duration: 90 minutes Type A 23

More information

Unit 5 Slide Lectures of 04/05/06 April 2017

Unit 5 Slide Lectures of 04/05/06 April 2017 PROJECT AND COMMUNICATION MANAGEMENT Academic Year 2016/2017 PROJECT SCHEDULING, PROJECT DURATION AND PROJECT COMMUNICATION PLAN (CH. 8-9) Unit 5 Slide 5.2.1 Lectures of 04/05/06 April 2017 Overview of

More information

1 Asset Pricing: Bonds vs Stocks

1 Asset Pricing: Bonds vs Stocks Asset Pricing: Bonds vs Stocks The historical data on financial asset returns show that one dollar invested in the Dow- Jones yields 6 times more than one dollar invested in U.S. Treasury bonds. The return

More information

Chapter 11: Cost Minimisation and the Demand for Factors

Chapter 11: Cost Minimisation and the Demand for Factors Chapter 11: Cost Minimisation and the Demand for Factors 11.1: Introduction We assume a very simple objective for firms namely, that they want to maximise profits 1. We will explore the implications of

More information

PAPER NO.1 : MICROECONOMICS ANALYSIS MODULE NO.6 : INDIFFERENCE CURVES

PAPER NO.1 : MICROECONOMICS ANALYSIS MODULE NO.6 : INDIFFERENCE CURVES Subject Paper No and Title Module No and Title Module Tag 1: Microeconomics Analysis 6: Indifference Curves BSE_P1_M6 PAPER NO.1 : MICRO ANALYSIS TABLE OF CONTENTS 1. Learning Outcomes 2. Introduction

More information

Ecn Intermediate Microeconomics University of California - Davis July 7, 2010 Instructor: John Parman. Midterm - Solutions

Ecn Intermediate Microeconomics University of California - Davis July 7, 2010 Instructor: John Parman. Midterm - Solutions Ecn 100 - Intermediate Microeconomics University of California - Davis July 7, 2010 Instructor: John Parman Midterm - Solutions You have until 3:50pm to complete this exam. Be certain to put your name,

More information

Logistics. Lecture notes. Maria Grazia Scutellà. Dipartimento di Informatica Università di Pisa. September 2015

Logistics. Lecture notes. Maria Grazia Scutellà. Dipartimento di Informatica Università di Pisa. September 2015 Logistics Lecture notes Maria Grazia Scutellà Dipartimento di Informatica Università di Pisa September 2015 These notes are related to the course of Logistics held by the author at the University of Pisa.

More information

Math 1314 Week 6 Session Notes

Math 1314 Week 6 Session Notes Math 1314 Week 6 Session Notes A few remaining examples from Lesson 7: 0.15 Example 17: The model Nt ( ) = 34.4(1 +.315 t) gives the number of people in the US who are between the ages of 45 and 55. Note,

More information

On Repeated Myopic Use of the Inverse Elasticity Pricing Rule

On Repeated Myopic Use of the Inverse Elasticity Pricing Rule WP 2018/4 ISSN: 2464-4005 www.nhh.no WORKING PAPER On Repeated Myopic Use of the Inverse Elasticity Pricing Rule Kenneth Fjell og Debashis Pal Department of Accounting, Auditing and Law Institutt for regnskap,

More information

Chapter 1 Microeconomics of Consumer Theory

Chapter 1 Microeconomics of Consumer Theory Chapter Microeconomics of Consumer Theory The two broad categories of decision-makers in an economy are consumers and firms. Each individual in each of these groups makes its decisions in order to achieve

More information

ECO101 PRINCIPLES OF MICROECONOMICS Notes. Consumer Behaviour. U tility fro m c o n s u m in g B ig M a c s

ECO101 PRINCIPLES OF MICROECONOMICS Notes. Consumer Behaviour. U tility fro m c o n s u m in g B ig M a c s ECO101 PRINCIPLES OF MICROECONOMICS Notes Consumer Behaviour Overview The aim of this chapter is to analyse the behaviour of rational consumers when consuming goods and services, to explain how they may

More information

MINIMIZE TIME AND COST FOR SUCCESSFUL COMPLETION OF A LARGE SCALE PROJECT APPLYING PROJECT CRASHING METHOD

MINIMIZE TIME AND COST FOR SUCCESSFUL COMPLETION OF A LARGE SCALE PROJECT APPLYING PROJECT CRASHING METHOD International Journal of Advanced Research and Review www.ijarr.in MINIMIZE TIME AND COST FOR SUCCESSFUL COMPLETION OF A LARGE SCALE PROJECT APPLYING PROJECT CRASHING METHOD Shifat Ahmed Lecturer, Southeast

More information

1. [March 6] You have an income of $40 to spend on two commodities. Commodity 1 costs $10 per unit and commodity 2 costs $5 per unit.

1. [March 6] You have an income of $40 to spend on two commodities. Commodity 1 costs $10 per unit and commodity 2 costs $5 per unit. Spring 0 0 / IA 350, Intermediate Microeconomics / Problem Set. [March 6] You have an income of $40 to spend on two commodities. Commodity costs $0 per unit and commodity costs $5 per unit. a. Write down

More information

Answers To Chapter 6. Review Questions

Answers To Chapter 6. Review Questions Answers To Chapter 6 Review Questions 1 Answer d Individuals can also affect their hours through working more than one job, vacations, and leaves of absence 2 Answer d Typically when one observes indifference

More information

GRAPHS IN ECONOMICS. Appendix. Key Concepts. Graphing Data

GRAPHS IN ECONOMICS. Appendix. Key Concepts. Graphing Data Appendix GRAPHS IN ECONOMICS Key Concepts Graphing Data Graphs represent quantity as a distance on a line. On a graph, the horizontal scale line is the x-axis, the vertical scale line is the y-axis, and

More information

A Theory of Optimized Resource Allocation from Systems Perspectives

A Theory of Optimized Resource Allocation from Systems Perspectives Systems Research and Behavioral Science Syst. Res. 26, 289^296 (2009) Published online 6 March 2009 in Wiley InterScience (www.interscience.wiley.com).975 & Research Paper A Theory of Optimized Resource

More information

Chapter 3: Model of Consumer Behavior

Chapter 3: Model of Consumer Behavior CHAPTER 3 CONSUMER THEORY Chapter 3: Model of Consumer Behavior Premises of the model: 1.Individual tastes or preferences determine the amount of pleasure people derive from the goods and services they

More information

The Baumol-Tobin and the Tobin Mean-Variance Models of the Demand

The Baumol-Tobin and the Tobin Mean-Variance Models of the Demand Appendix 1 to chapter 19 A p p e n d i x t o c h a p t e r An Overview of the Financial System 1 The Baumol-Tobin and the Tobin Mean-Variance Models of the Demand for Money The Baumol-Tobin Model of Transactions

More information

A New Mathematical Model for Time Cost Trade-off. Problem with Budget Limitation Based on. Time Value of Money

A New Mathematical Model for Time Cost Trade-off. Problem with Budget Limitation Based on. Time Value of Money Applied Mathematical Sciences, Vol. 4, 2010, no. 63, 3107-3119 A New Mathematical Model for Time Cost Trade-off Problem with Budget Limitation Based on Time Value of Money H. Nikoomaram Dept. of management,

More information

Overall Excess Burden Minimization from a Mathematical Perspective Kong JUN 1,a,*

Overall Excess Burden Minimization from a Mathematical Perspective Kong JUN 1,a,* 016 3 rd International Conference on Social Science (ICSS 016 ISBN: 978-1-60595-410-3 Overall Excess Burden Minimization from a Mathematical Perspective Kong JUN 1,a,* 1 Department of Public Finance and

More information

We will make several assumptions about these preferences:

We will make several assumptions about these preferences: Lecture 5 Consumer Behavior PREFERENCES The Digital Economist In taking a closer at market behavior, we need to examine the underlying motivations and constraints affecting the consumer (or households).

More information

Advanced Operations Research Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology, Madras

Advanced Operations Research Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology, Madras Advanced Operations Research Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology, Madras Lecture 21 Successive Shortest Path Problem In this lecture, we continue our discussion

More information

Problem Set 5 Answers. A grocery shop is owned by Mr. Moore and has the following statement of revenues and costs:

Problem Set 5 Answers. A grocery shop is owned by Mr. Moore and has the following statement of revenues and costs: 1. Ch 7, Problem 7.2 Problem Set 5 Answers A grocery shop is owned by Mr. Moore and has the following statement of revenues and costs: Revenues $250,000 Supplies $25,000 Electricity $6,000 Employee salaries

More information

Chapter 3. A Consumer s Constrained Choice

Chapter 3. A Consumer s Constrained Choice Chapter 3 A Consumer s Constrained Choice If this is coffee, please bring me some tea; but if this is tea, please bring me some coffee. Abraham Lincoln Chapter 3 Outline 3.1 Preferences 3.2 Utility 3.3

More information

Microeconomics of Banking: Lecture 2

Microeconomics of Banking: Lecture 2 Microeconomics of Banking: Lecture 2 Prof. Ronaldo CARPIO September 25, 2015 A Brief Look at General Equilibrium Asset Pricing Last week, we saw a general equilibrium model in which banks were irrelevant.

More information

Midterm 1 - Solutions

Midterm 1 - Solutions Ecn 100 - Intermediate Microeconomics University of California - Davis April 15, 2011 Instructor: John Parman Midterm 1 - Solutions You have until 11:50am to complete this exam. Be certain to put your

More information

Calculating a Consistent Terminal Value in Multistage Valuation Models

Calculating a Consistent Terminal Value in Multistage Valuation Models Calculating a Consistent Terminal Value in Multistage Valuation Models Larry C. Holland 1 1 College of Business, University of Arkansas Little Rock, Little Rock, AR, USA Correspondence: Larry C. Holland,

More information

3Choice Sets in Labor and Financial

3Choice Sets in Labor and Financial C H A P T E R 3Choice Sets in Labor and Financial Markets This chapter is a straightforward extension of Chapter 2 where we had shown that budget constraints can arise from someone owning an endowment

More information

Lecture Notes #3 Page 1 of 15

Lecture Notes #3 Page 1 of 15 Lecture Notes #3 Page 1 of 15 PbAf 499 Lecture Notes #3: Graphing Graphing is cool and leads to great insights. Graphing Points in a Plane A point in the (x,y) plane is graphed simply by moving horizontally

More information

Economics 602 Macroeconomic Theory and Policy Problem Set 3 Suggested Solutions Professor Sanjay Chugh Spring 2012

Economics 602 Macroeconomic Theory and Policy Problem Set 3 Suggested Solutions Professor Sanjay Chugh Spring 2012 Department of Applied Economics Johns Hopkins University Economics 60 Macroeconomic Theory and Policy Problem Set 3 Suggested Solutions Professor Sanjay Chugh Spring 0. The Wealth Effect on Consumption.

More information

Foundational Preliminaries: Answers to Within-Chapter-Exercises

Foundational Preliminaries: Answers to Within-Chapter-Exercises C H A P T E R 0 Foundational Preliminaries: Answers to Within-Chapter-Exercises 0A Answers for Section A: Graphical Preliminaries Exercise 0A.1 Consider the set [0,1) which includes the point 0, all the

More information

ECONOMICS SOLUTION BOOK 2ND PUC. Unit 2

ECONOMICS SOLUTION BOOK 2ND PUC. Unit 2 ECONOMICS SOLUTION BOOK N PUC Unit I. Choose the correct answer (each question carries mark). Utility is a) Objective b) Subjective c) Both a & b d) None of the above. The shape of an indifference curve

More information

Problem Set #2. Intermediate Macroeconomics 101 Due 20/8/12

Problem Set #2. Intermediate Macroeconomics 101 Due 20/8/12 Problem Set #2 Intermediate Macroeconomics 101 Due 20/8/12 Question 1. (Ch3. Q9) The paradox of saving revisited You should be able to complete this question without doing any algebra, although you may

More information

Mean Variance Analysis and CAPM

Mean Variance Analysis and CAPM Mean Variance Analysis and CAPM Yan Zeng Version 1.0.2, last revised on 2012-05-30. Abstract A summary of mean variance analysis in portfolio management and capital asset pricing model. 1. Mean-Variance

More information

Module 2 THEORETICAL TOOLS & APPLICATION. Lectures (3-7) Topics

Module 2 THEORETICAL TOOLS & APPLICATION. Lectures (3-7) Topics Module 2 THEORETICAL TOOLS & APPLICATION 2.1 Tools of Public Economics Lectures (3-7) Topics 2.2 Constrained Utility Maximization 2.3 Marginal Rates of Substitution 2.4 Constrained Utility Maximization:

More information

Equalities. Equalities

Equalities. Equalities Equalities Working with Equalities There are no special rules to remember when working with equalities, except for two things: When you add, subtract, multiply, or divide, you must perform the same operation

More information

Problem 1 / 25 Problem 2 / 25 Problem 3 / 25 Problem 4 / 25

Problem 1 / 25 Problem 2 / 25 Problem 3 / 25 Problem 4 / 25 Department of Economics Boston College Economics 202 (Section 05) Macroeconomic Theory Midterm Exam Suggested Solutions Professor Sanjay Chugh Fall 203 NAME: The Exam has a total of four (4) problems and

More information

PORTFOLIO OPTIMIZATION AND EXPECTED SHORTFALL MINIMIZATION FROM HISTORICAL DATA

PORTFOLIO OPTIMIZATION AND EXPECTED SHORTFALL MINIMIZATION FROM HISTORICAL DATA PORTFOLIO OPTIMIZATION AND EXPECTED SHORTFALL MINIMIZATION FROM HISTORICAL DATA We begin by describing the problem at hand which motivates our results. Suppose that we have n financial instruments at hand,

More information

= quantity of ith good bought and consumed. It

= quantity of ith good bought and consumed. It Chapter Consumer Choice and Demand The last chapter set up just one-half of the fundamental structure we need to determine consumer behavior. We must now add to this the consumer's budget constraint, which

More information

Optimal Portfolio Selection

Optimal Portfolio Selection Optimal Portfolio Selection We have geometrically described characteristics of the optimal portfolio. Now we turn our attention to a methodology for exactly identifying the optimal portfolio given a set

More information

Lesson 10: Interpreting Quadratic Functions from Graphs and Tables

Lesson 10: Interpreting Quadratic Functions from Graphs and Tables : Interpreting Quadratic Functions from Graphs and Tables Student Outcomes Students interpret quadratic functions from graphs and tables: zeros ( intercepts), intercept, the minimum or maximum value (vertex),

More information

BOND ANALYTICS. Aditya Vyas IDFC Ltd.

BOND ANALYTICS. Aditya Vyas IDFC Ltd. BOND ANALYTICS Aditya Vyas IDFC Ltd. Bond Valuation-Basics The basic components of valuing any asset are: An estimate of the future cash flow stream from owning the asset The required rate of return for

More information

Textbook: pp Chapter 11: Project Management

Textbook: pp Chapter 11: Project Management 1 Textbook: pp. 405-444 Chapter 11: Project Management 2 Learning Objectives After completing this chapter, students will be able to: Understand how to plan, monitor, and control projects with the use

More information

The Duration Derby: A Comparison of Duration Based Strategies in Asset Liability Management

The Duration Derby: A Comparison of Duration Based Strategies in Asset Liability Management The Duration Derby: A Comparison of Duration Based Strategies in Asset Liability Management H. Zheng Department of Mathematics, Imperial College London SW7 2BZ, UK h.zheng@ic.ac.uk L. C. Thomas School

More information

Project Management Chapter 13

Project Management Chapter 13 Lecture 12 Project Management Chapter 13 Introduction n Managing large-scale, complicated projects effectively is a difficult problem and the stakes are high. n The first step in planning and scheduling

More information

Probability and Stochastics for finance-ii Prof. Joydeep Dutta Department of Humanities and Social Sciences Indian Institute of Technology, Kanpur

Probability and Stochastics for finance-ii Prof. Joydeep Dutta Department of Humanities and Social Sciences Indian Institute of Technology, Kanpur Probability and Stochastics for finance-ii Prof. Joydeep Dutta Department of Humanities and Social Sciences Indian Institute of Technology, Kanpur Lecture - 07 Mean-Variance Portfolio Optimization (Part-II)

More information

Chapter 11: PERT for Project Planning and Scheduling

Chapter 11: PERT for Project Planning and Scheduling Chapter 11: PERT for Project Planning and Scheduling PERT, the Project Evaluation and Review Technique, is a network-based aid for planning and scheduling the many interrelated tasks in a large and complex

More information

Eco 300 Intermediate Micro

Eco 300 Intermediate Micro Eco 300 Intermediate Micro Instructor: Amalia Jerison Office Hours: T 12:00-1:00, Th 12:00-1:00, and by appointment BA 127A, aj4575@albany.edu A. Jerison (BA 127A) Eco 300 Spring 2010 1 / 27 Review of

More information

THEORETICAL TOOLS OF PUBLIC FINANCE

THEORETICAL TOOLS OF PUBLIC FINANCE Solutions and Activities for CHAPTER 2 THEORETICAL TOOLS OF PUBLIC FINANCE Questions and Problems 1. The price of a bus trip is $1 and the price of a gallon of gas (at the time of this writing!) is $3.

More information

LINES AND SLOPES. Required concepts for the courses : Micro economic analysis, Managerial economy.

LINES AND SLOPES. Required concepts for the courses : Micro economic analysis, Managerial economy. LINES AND SLOPES Summary 1. Elements of a line equation... 1 2. How to obtain a straight line equation... 2 3. Microeconomic applications... 3 3.1. Demand curve... 3 3.2. Elasticity problems... 7 4. Exercises...

More information

Chapter 4 UTILITY MAXIMIZATION AND CHOICE

Chapter 4 UTILITY MAXIMIZATION AND CHOICE Chapter 4 UTILITY MAXIMIZATION AND CHOICE 1 Our Consumption Choices Suppose that each month we have a stipend of $1250. What can we buy with this money? 2 What can we buy with this money? Pay the rent,

More information

CHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM

CHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM CHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM 6.1 Introduction Project Management is the process of planning, controlling and monitoring the activities

More information

Comment Does the economics of moral hazard need to be revisited? A comment on the paper by John Nyman

Comment Does the economics of moral hazard need to be revisited? A comment on the paper by John Nyman Journal of Health Economics 20 (2001) 283 288 Comment Does the economics of moral hazard need to be revisited? A comment on the paper by John Nyman Åke Blomqvist Department of Economics, University of

More information

Problem Set 1 Answer Key. I. Short Problems 1. Check whether the following three functions represent the same underlying preferences

Problem Set 1 Answer Key. I. Short Problems 1. Check whether the following three functions represent the same underlying preferences Problem Set Answer Key I. Short Problems. Check whether the following three functions represent the same underlying preferences u (q ; q ) = q = + q = u (q ; q ) = q + q u (q ; q ) = ln q + ln q All three

More information

ECON 2100 Principles of Microeconomics (Fall 2018) Consumer Choice Theory

ECON 2100 Principles of Microeconomics (Fall 2018) Consumer Choice Theory ECON 21 Principles of Microeconomics (Fall 218) Consumer Choice Theory Relevant readings from the textbook: Mankiw, Ch 21 The Theory of Consumer Choice Suggested problems from the textbook: Chapter 21

More information

Optimization Methods in Management Science

Optimization Methods in Management Science Optimization Methods in Management Science MIT 15.053, Spring 013 Problem Set (Second Group of Students) Students with first letter of surnames I Z Due: February 1, 013 Problem Set Rules: 1. Each student

More information

Making Hard Decision. ENCE 627 Decision Analysis for Engineering. Identify the decision situation and understand objectives. Identify alternatives

Making Hard Decision. ENCE 627 Decision Analysis for Engineering. Identify the decision situation and understand objectives. Identify alternatives CHAPTER Duxbury Thomson Learning Making Hard Decision Third Edition RISK ATTITUDES A. J. Clark School of Engineering Department of Civil and Environmental Engineering 13 FALL 2003 By Dr. Ibrahim. Assakkaf

More information

Name: Class: Date: in general form.

Name: Class: Date: in general form. Write the equation in general form. Mathematical Applications for the Management Life and Social Sciences 11th Edition Harshbarger TEST BANK Full clear download at: https://testbankreal.com/download/mathematical-applications-management-life-socialsciences-11th-edition-harshbarger-test-bank/

More information

8 POSSIBILITIES, PREFERENCES, AND CHOICES. Chapter. Key Concepts. The Budget Line

8 POSSIBILITIES, PREFERENCES, AND CHOICES. Chapter. Key Concepts. The Budget Line Chapter 8 POSSIBILITIES, PREFERENCES, AND CHOICES Key Concepts FIGURE 8. The Budget Line Consumption Possibilities The budget shows the limits to a household s consumption. Figure 8. graphs a budget ;

More information

Corporate Finance, Module 21: Option Valuation. Practice Problems. (The attached PDF file has better formatting.) Updated: July 7, 2005

Corporate Finance, Module 21: Option Valuation. Practice Problems. (The attached PDF file has better formatting.) Updated: July 7, 2005 Corporate Finance, Module 21: Option Valuation Practice Problems (The attached PDF file has better formatting.) Updated: July 7, 2005 {This posting has more information than is needed for the corporate

More information

Solutions to Extra Business Problems

Solutions to Extra Business Problems Solutions to Extra Business Problems 5/28/11 1. (a).taking the derivative of C(q), we find that MC(q) = 12q + 14. Thus MC(5) = 74 - the marginal cost at a production level of 5 is 74 thousand dollars/unit.

More information

2. Find the equilibrium price and quantity in this market.

2. Find the equilibrium price and quantity in this market. 1 Supply and Demand Consider the following supply and demand functions for Ramen noodles. The variables are de ned in the table below. Constant values are given for the last 2 variables. Variable Meaning

More information

1 Supply and Demand. 1.1 Demand. Price. Quantity. These notes essentially correspond to chapter 2 of the text.

1 Supply and Demand. 1.1 Demand. Price. Quantity. These notes essentially correspond to chapter 2 of the text. These notes essentially correspond to chapter 2 of the text. 1 Supply and emand The rst model we will discuss is supply and demand. It is the most fundamental model used in economics, and is generally

More information

Chapter 15: Dynamic Programming

Chapter 15: Dynamic Programming Chapter 15: Dynamic Programming Dynamic programming is a general approach to making a sequence of interrelated decisions in an optimum way. While we can describe the general characteristics, the details

More information

Perfect Competition. Profit-Maximizing Level of Output. Profit-Maximizing Level of Output. Profit-Maximizing Level of Output.

Perfect Competition. Profit-Maximizing Level of Output. Profit-Maximizing Level of Output. Profit-Maximizing Level of Output. erfect Competition Chapter 14-2. rofit Maximizing and Shutting Down rofit-maximizing Level of The goal of the firm is to maximize profits. rofit is the difference between total revenue and total cost.

More information

Power functions of the Shewhart control chart

Power functions of the Shewhart control chart Journal of Physics: Conference Series Power functions of the Shewhart control chart To cite this article: M B C Khoo 013 J. Phys.: Conf. Ser. 43 01008 View the article online for updates and enhancements.

More information

Product Di erentiation: Exercises Part 1

Product Di erentiation: Exercises Part 1 Product Di erentiation: Exercises Part Sotiris Georganas Royal Holloway University of London January 00 Problem Consider Hotelling s linear city with endogenous prices and exogenous and locations. Suppose,

More information

Chapter 6 Firms: Labor Demand, Investment Demand, and Aggregate Supply

Chapter 6 Firms: Labor Demand, Investment Demand, and Aggregate Supply Chapter 6 Firms: Labor Demand, Investment Demand, and Aggregate Supply We have studied in depth the consumers side of the macroeconomy. We now turn to a study of the firms side of the macroeconomy. Continuing

More information

Elasticity. McGraw-Hill/Irwin. Copyright 2012 by The McGraw-Hill Companies, Inc. All rights reserved.

Elasticity. McGraw-Hill/Irwin. Copyright 2012 by The McGraw-Hill Companies, Inc. All rights reserved. 04 Elasticity McGraw-Hill/Irwin Copyright 2012 by The McGraw-Hill Companies, Inc. All rights reserved. LO1 4-2 Price Elasticity of Demand Measures buyers responsiveness to price changes Elastic demand

More information

Midterm 2 (Group A) U (x 1 ;x 2 )=3lnx 1 +3 ln x 2

Midterm 2 (Group A) U (x 1 ;x 2 )=3lnx 1 +3 ln x 2 Econ 301 Midterm 2 (Group A) You have 70 minutes to complete the exam. The midterm consists of 4 questions (25,30,25 and 20 points). Problem 1 (25p). (Uncertainty and insurance) You are an owner of a luxurious

More information

1 Consumption and saving under uncertainty

1 Consumption and saving under uncertainty 1 Consumption and saving under uncertainty 1.1 Modelling uncertainty As in the deterministic case, we keep assuming that agents live for two periods. The novelty here is that their earnings in the second

More information

LECTURE 1 : THE INFINITE HORIZON REPRESENTATIVE AGENT. In the IS-LM model consumption is assumed to be a

LECTURE 1 : THE INFINITE HORIZON REPRESENTATIVE AGENT. In the IS-LM model consumption is assumed to be a LECTURE 1 : THE INFINITE HORIZON REPRESENTATIVE AGENT MODEL In the IS-LM model consumption is assumed to be a static function of current income. It is assumed that consumption is greater than income at

More information