1 Program Evaluation and Review Techniques (PERT) Critical Path Method (CPM): A Rough Guide by Andrew Scouller
2 PROJECT MANAGEMENT Project Managers can use project management software to keep track of the project in real time, and use it as a tool for planning and a guide in case circumstances change. One method which time has proven to be of invaluable use to project managers is the Critical Path Method (CPM). The CPM identifies the relationships between interrelated project components and shows a clear critical path of activities that must be completed by a certain date (project deadline). This helps to create a timescale for the development of the project, allowing the project manager to plan and allocate resources more efficiently e.g. staff. UNDERSTANDING THE SYMBOLS Node this represents the end of the previous activity and the starting point of those activities to follow. à Arrow this shows the direction of the project, as activities follow on one from another. This arrow can only ever point forward on the diagram, since a project cannot go backwards. Square this will contain a number which will represent the earliest start time of this activity. Triangle this will also contain a number which will represent the latest start time of this activity. CALCULATING EARLIEST START DATE 0 A B C D To calculate, for example, the earliest start time of activity C, it is simply the number of days it takes to complete activity A i.e.. However, to calculate this for the final node (the earliest time the project could be finished), the earliest time the project could be finished would be the cumulative of the longest path in the project i.e. Path : B () + D () = Path : A () + C () =
3 CALCULATING LATEST START DATE 0 0 A B 3 C D To calculate, for example, the latest start time of activity C, it is simply the earliest start time of the previous activity less the number of days that activity takes to complete i.e. - = 3 The latest start time for the final node will always equal the same as the earliest start time. This remains true for the beginning node. THE FLOAT The float of any activity is the number of days the activity could be delayed by but still finish on time before the following activity. It is calculated using this simple formula: - - duration of activity = float So, the float for activities B and D would be 0 as they are on the critical path, but the float for activities A and C would be and repectively; A 3 0 = C = Answer to worked example below: ACTIVITY A B C D E F G H I FLOAT THE CRITICAL PATH The critical path is essentially where and are equal to each other. The significance of the critical path is that activities on this path cannot have their durations extended, and must start on time so the project is completed in the minimum time allowed. The critical path in essence shows the shortest duration possible for the project. To mark out the critical path, the arrows for the path are often drawn in a different colour, or given double lines as shown above.
4 A COMPLEX CPM EXAMPLE GANTT CHARTS & STAFFING PROFILES Gantt charts are used to illustrate a project schedule the start and finish dates of each project element. They also show the dependency relationships between activities and can compare the planned and actual progress of the project. Modern systems have a Today line to show the present progress of the project. The length of each activity is plotted on a graph as follows to show the relationship between each project element. *NOTE: there should be a float of days on activity A
5 Gantt charts can also be used to plan resources and create other charts such as staffing profiles to allocate staff to projects. The numbers in the boxes in this case are the number of staff required to complete each activity. However, there are sometimes limitations to, for example, the number of staff available at a given time, and thus certain activities may not be able to be completed on time. Staffing profiles can help to overcome this particular limitation by moving project elements within their float to satisfy these conditions. Continued example DAY Staff Required Staff Required DAY The staffing profile above shows the number of staff required to work on the project each day (black lines). However, if there was a staff restriction of a maximum of 7 staff available on any one day the Gantt chart shows the float of each activity, and allows us to see how activities can be maneuvered to fit this restriction. In this example, move activity H to start on day (see red in above graphs). DAY Staff Required Restriction
GPE engineering project management. Project Management in an Engineering Context
GPE engineering project management Project Management in an Engineering Context Network diagrams in context PM SOW CHARTER SCOPE DEFINITION WBS circulation, negotiation, translation WBS WP à activities
More informationAppendix A Decision Support Analysis
Field Manual 100-11 Appendix A Decision Support Analysis Section I: Introduction structure development, and facilities. Modern quantitative methods can greatly facilitate this Complex decisions associated
More informationProject Management Techniques (PMT)
Project Management Techniques (PMT) Critical Path Method (CPM) and Project Evaluation and Review Technique (PERT) are 2 main basic techniques used in project management. Example: Construction of a house.
More informationProject Planning. Identifying the Work to Be Done. Gantt Chart. A Gantt Chart. Given: Activity Sequencing Network Diagrams
Project Planning Identifying the Work to Be Done Activity Sequencing Network Diagrams Given: Statement of work written description of goals work & time frame of project Work Breakdown Structure Be able
More informationCHAPTER 9: PROJECT MANAGEMENT
CHAPTER 9: PROJECT MANAGEMENT The aim is to coordinate and plan a single job consisting lots of tasks between which precedence relationships exist Project planning Most popular planning tools are utilized
More informationCISC 322 Software Architecture
CISC 22 Software Architecture Project Scheduling (PERT/CPM) Ahmed E. Hassan (Edited For Course Presentation, 206) Project A project is a temporary endeavour undertaken to create a "unique" product or service
More informationProject Management. Chapter 2. Copyright 2013 Pearson Education, Inc. publishing as Prentice Hall
Project Management Chapter 2 02-0 1 What is a Project? Project An interrelated set of activities with a definite starting and ending point, which results in a unique outcome for a specific allocation of
More informationPROJECT MANAGEMENT CPM & PERT TECHNIQUES
PROJECT MANAGEMENT CPM & PERT TECHNIQUES FLOW OF PRESENTATION INTRODUCTION NETWORK PLANNING ESTIMATING TIME CPM PERT Project Management Project A project is an interrelated set of activities that has a
More informationTextbook: pp Chapter 11: Project Management
1 Textbook: pp. 405-444 Chapter 11: Project Management 2 Learning Objectives After completing this chapter, students will be able to: Understand how to plan, monitor, and control projects with the use
More informationResearch Methods Outline
: Project Management James Gain jgain@cs.uct.ac.za Outline Introduction [] Project Management [] Experimental Computer Science [] Role of Mathematics [1] Designing User Experiments [] Qualitative Research
More informationReal-World Project Management. Chapter 15
Real-World Project Chapter 15 Characteristics of Project Unique one-time focus Difficulties arise from originality Subject to uncertainties Unexplained or unplanned events often arise, affecting resources,
More informationUNIT-II Project Organization and Scheduling Project Element
UNIT-II Project Organization and Scheduling Project Element Five Key Elements are Unique. Projects are unique, one-of-a-kind, never been done before. Start and Stop Date. Projects must have a definite
More informationProject Management -- Developing the Project Plan
Project Management -- Developing the Project Plan Dr. Tai-Yue Wang Department of Industrial and Information Management National Cheng Kung University Tainan, TAIWAN, ROC 1 Where We Are Now 6 2 Developing
More informationProject Management Chapter 13
Lecture 12 Project Management Chapter 13 Introduction n Managing large-scale, complicated projects effectively is a difficult problem and the stakes are high. n The first step in planning and scheduling
More informationA convenient analytical and visual technique of PERT and CPM prove extremely valuable in assisting the managers in managing the projects.
Introduction Any project involves planning, scheduling and controlling a number of interrelated activities with use of limited resources, namely, men, machines, materials, money and time. The projects
More informationUNIVERSITY OF BOLTON SCHOOL OF ENGINEERING. MSc CIVIL ENGINEERING MSc CONSTRUCTION PROJECT MANAGEMENT SEMESTER ONE EXAMINATION 2017/2018
ENG026 UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING MSc CIVIL ENGINEERING MSc CONSTRUCTION PROJECT MANAGEMENT SEMESTER ONE EXAMINATION 2017/2018 PROJECT MANAGEMENT MODULE NO: CPM7002 Date: 15 January 2018
More informationProject Planning. Jesper Larsen. Department of Management Engineering Technical University of Denmark
Project Planning jesla@man.dtu.dk Department of Management Engineering Technical University of Denmark 1 Project Management Project Management is a set of techniques that helps management manage large-scale
More informationTeori Pengambilan Keputusan. Week 12 Project Management
Teori Pengambilan Keputusan Week 1 Project Management Project Management Program Evaluation and Review Technique (PERT) Critical Path Method (CPM) PERT and CPM Network techniques Developed in 195 s CPM
More informationPROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT. G.N. Sandhy Widyasthana
PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT G.N. Sandhy Widyasthana widyasthana@gmail.com 022 70702020 081 225 702020 1 2 3 Process of identifying the specific actions to be performed to produce
More informationIntroduction. Introduction. Six Steps of PERT/CPM. Six Steps of PERT/CPM LEARNING OBJECTIVES
Valua%on and pricing (November 5, 2013) LEARNING OBJECTIVES Lecture 12 Project Management Olivier J. de Jong, LL.M., MM., MBA, CFD, CFFA, AA www.olivierdejong.com 1. Understand how to plan, monitor, and
More informationAfter complete studying this chapter, You should be able to
Chapter 10 Project Management Ch10: What Is Project Management? After complete studying this chapter, You should be able to Define key terms like Project, Project Management, Discuss the main characteristics
More informationInternational Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ
International Project Management prof.dr MILOŠ D. MILOVANČEVIĆ Project time management Project cost management Time in project management process Time is a valuable resource. It is also the scarcest. Time
More informationInternational Journal of Advanced Engineering and Management Research Vol. 2 Issue 4, ISSN:
International Journal of Advanced Engineering and Management Research Vol. 2 Issue 4, 2017 http://ijaemr.com/ ISSN: 2456-3676 CPM AND PERT COMPARISON ANALYSIS IN PROJECT PLANNING ABSTRACT Talatu Muhammad
More informationOptimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur. Lecture - 18 PERT
Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur Lecture - 18 PERT (Refer Slide Time: 00:56) In the last class we completed the C P M critical path analysis
More informationConstruction Management
Construction Management 1. Which one of the following represents an activity A. excavation for foundation B. curing of concrete C. setting of question paper D. preparation of breakfast 2. Pick up the incorrect
More informationETSF01: Software Engineering Process Economy and Quality
ETSF01: Software Engineering Process Economy and Quality Dietmar Pfahl Lund University 1. Identify project objectives 0.Select project 2. Identify project infrastructure Project planning steps Review Lower
More informationCONSTRUCTION MANAGEMENT CHAPTER 3 PLANNING
CONSTRUCTION MANAGEMENT CHAPTER 3 PLANNING Planning of Works Contract Form of contract by which one party undertakes to the other to perform certain work, for a price. Corresponds to the execution of a
More informationSCHEDULE CREATION AND ANALYSIS. 1 Powered by POeT Solvers Limited
SCHEDULE CREATION AND ANALYSIS 1 www.pmtutor.org Powered by POeT Solvers Limited While building the project schedule, we need to consider all risk factors, assumptions and constraints imposed on the project
More informationPROJECT MANAGEMENT DIPLOMA COURSE
PROJECT MANAGEMENT DIPLOMA COURSE UNIT THREE PROJECT PLANNING TUTOR TALK: The Learning Outcomes for this assignment are: Describe the following: o Planning parameters o Planning quality o Developing a
More informationSCM 301 (Solo) Exam 1 Practice Exam Solutions
1. D $118,000 www.liontutors.com SCM 301 (Solo) Exam 1 Practice Exam Solutions The first thing we need to do here is use the information given in the table to create a network diagram. Once we have a network
More informationSCM 301 (Lutz) Exam 1 Practice Exam Solutions
1. D $118,000 www.liontutors.com SCM 301 (Lutz) Exam 1 Practice Exam Solutions The first thing we need to do here is use the information given in the table to create a network diagram. Once we have a network
More informationHandout 4: Deterministic Systems and the Shortest Path Problem
SEEM 3470: Dynamic Optimization and Applications 2013 14 Second Term Handout 4: Deterministic Systems and the Shortest Path Problem Instructor: Shiqian Ma January 27, 2014 Suggested Reading: Bertsekas
More informationProject Management Professional (PMP) Exam Prep Course 06 - Project Time Management
Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management Slide 1 Looking Glass Development, LLC (303) 663-5402 / (888) 338-7447 4610 S. Ulster St. #150 Denver, CO 80237 information@lookingglassdev.com
More informationINSE 6230: Assignment 1 - Winter (0% of final grade) 1. The table below provides information about a short IT project.
INSE 6230: Assignment - Winter 208 (0% of final grade). The table below provides information about a short IT project. Activity Predecessors Duration (Months) A - 2 B - 3 C A 4 D A, B 2 E D 2 F B, C, E
More informationProbabilistic Completion Time in Project Scheduling Min Khee Chin 1, Sie Long Kek 2, Sy Yi Sim 3, Ta Wee Seow 4
Probabilistic Completion Time in Project Scheduling Min Khee Chin 1, Sie Long Kek 2, Sy Yi Sim 3, Ta Wee Seow 4 1 Department of Mathematics and Statistics, Universiti Tun Hussein Onn Malaysia 2 Center
More informationOutline. Global Company Profile: Bechtel Group. The Importance of Project Management Project Planning Project Scheduling Project Controlling
Project Management Outline Global Company Profile: Bechtel Group The Importance of Project Management Project Planning Project Scheduling Project Controlling Outline - Continued Project Management Techniques:
More informationProject Management. Project Mangement. ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala.
Project Mangement ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala. Page 1 of 380 26/4/2008 Syllabus 1. Total Project Management Concept, relationship with other function and other organizations,
More informationIE 102 Spring Project Management
IE 102 Spring 2018 Project Management 1 Management of Projects Planning - goal setting, defining the project, team organization Scheduling - relates people, money, and supplies to specific activities and
More informationA METHOD FOR STOCHASTIC ESTIMATION OF COST AND COMPLETION TIME OF A MINING PROJECT
A METHOD FOR STOCHASTIC ESTIMATION OF COST AND COMPLETION TIME OF A MINING PROJECT E. Newby, F. D. Fomeni, M. M. Ali and C. Musingwini Abstract The standard methodology used for estimating the cost and
More informationProgramme Evaluation and Review Techniques (PERT) And Critical Path Method (CPM) By K.K. Bandyopadhyay. August 2001
Programme Evaluation and Review Techniques (PERT) And Critical Path Method (CPM) By K.K. Bandyopadhyay August 2001 Participatory Research In Asia Introduction Programme Evaluation and Review Technique
More informationProject planning and creating a WBS
37E01500 Project Management and Consulting Practice Project planning and creating a WBS Matti Rossi Lecture 3, Tue 28.2.2017 Learning objectives Describe the project time management planning tasks, and
More informationSWEN 256 Software Process & Project Management
SWEN 256 Software Process & Project Management Plan: Identify activities. No specific start and end dates. Estimating: Determining the size & duration of activities. Schedule: Adds specific start and end
More information11/1/2018. Overview PERT / CPM. Network representation. Network representation. Project Scheduling. What is a path?
PERT / CPM BSD Dave Novak Fall Overview Introduce Discuss what a critical path is Discuss critical path algorithm Example Source: nderson et al., 1 Quantitative Methods for Business 1 th edition some slides
More informationProject Management Fundamentals
Project Management Fundamentals Course No: B04-003 Credit: 4 PDH Najib Gerges, Ph.D., P.E. Continuing Education and Development, Inc. 9 Greyridge Farm Court Stony Point, NY 10980 P: (877) 322-5800 F: (877)
More informationThe Critical Path Method
The Critical Path Method Presented by Antonio Prensa, MBA, PMP, CCP, CSTE for Project Management Institute Puerto Rico Chapter June 2, 22 San Juan, Puerto Rico "I believe that this nation should commit
More informationProject Planning. Planning is an important step in project execution. Planning means:
Project Planning Planning is an important step in project execution. Planning means: Thinking through future project actions Seeking and mentally inspecting the long path from the start to the finish Achieving
More informationLecture 3 Project Scheduling
B10 Lecture Project Scheduling Omar El-Anwar, PhD, PMP Network alculations The purpose of conducting network calculations is to know more about the scheduling of activities: When will each activity start?
More informationLogistics. Lecture notes. Maria Grazia Scutellà. Dipartimento di Informatica Università di Pisa. September 2015
Logistics Lecture notes Maria Grazia Scutellà Dipartimento di Informatica Università di Pisa September 2015 These notes are related to the course of Logistics held by the author at the University of Pisa.
More informationCost Reduction: Planning & Control. Impacting the Bottom Line
Cost Reduction: Planning & Control Break Even Point & Decision Tree Analysis (l.u. 4/2/11) Impacting the Bottom Line Calls for an understanding of: Variation Waste & Value Investments (time, capital, resources,
More informationSSC-JE STAFF SELECTION COMMISSION CIVIL ENGINEERING STUDY MATERIAL ESTIMATING, COSTING AND VALUATION
1 ` SSC-JE STAFF SELECTION COMMISSION CIVIL ENGINEERING STUDY MATERIAL SSC-JE Civil Engineering 2 Estimating, Costing and Valuation : Estimate, Glossary of technical terms, Analysis of rates, Methods and
More informationChapter16Project Management and. Scheduling Project management
Chapter6Project Management and Scheduling Figure 6. On completion of this chapter, you should be able to identify key components of projects and the issues associated with them, and you should be able
More informationPlan Implementation. Pushpa Lal Shakya
Plan Implementation Pushpa Lal Shakya Outline of Presentation 1. Plan Implementation: Meaning 2. Use of MTEF in Plan Implementation 3. Plan implementation Process and Implementation Modalities 4. Application
More informationChapter 11: PERT for Project Planning and Scheduling
Chapter 11: PERT for Project Planning and Scheduling PERT, the Project Evaluation and Review Technique, is a network-based aid for planning and scheduling the many interrelated tasks in a large and complex
More information1 of 14 4/27/2009 7:45 AM
1 of 14 4/27/2009 7:45 AM Chapter 7 - Network Models in Project Management INTRODUCTION Most realistic projects that organizations like Microsoft, General Motors, or the U.S. Defense Department undertake
More informationSAMPLE. DETERMINING ACTIVITY DURATIONS TCM Framework: 7.2 Schedule Planning and Development. AACE International Recommended Practice No.
E 32R04 SA M PL DETERMI NI NGACTI VI TY DURATI ONS AACE International Recommended Practice No. 32R-04 DETERMINING ACTIVITY DURATIONS TCM Framework: 7.2 Schedule Planning and Development Rev. Note: As AACE
More informationPROJECT MANAGEMENT. Trying to manage a project without project management is like trying to play a football game without a game plan
PROJECT MANAGEMENT Trying to manage a project without project management is like trying to play a football game without a game plan K. Tate (Past Board Member, PMI). Brad Fink 28 February 2013 Executive
More informationSchedule/Milestones. Figure 14 An example of a schedule
Schedule/Milestones The schedule shows a graphic representation of the milestones and tollgates that we defined in the project model. The purpose of the schedule and the other diagrams is to simplify and
More informationMS Project 2007 Page 1 of 18
MS Project 2007 Page 1 of 18 PROJECT MANAGEMENT (PM):- There are powerful environment forces contributed to the rapid expansion of the projects and project management approaches to the business problems
More informationMnDOT use of Calendars in Primavera P6
MnDOT Project Management Office Presents: MnDOT use of Calendars in Primavera P6 Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be
More informationNetwork Analysis Basic Components. The Other View. Some Applications. Continued. Goal of Network Analysis. RK Jana
Network nalysis RK Jana asic omponents ollections of interconnected linear forms: Lines Intersections Regions (created by the partitioning of space by the lines) Planar (streets, all on same level, vertices
More informationCHAPTER 5 SCHEDULING AND TRACKING WORK IN CONSTRUCTION PROJECT MANAGEMENT. UWB10202 Effective Communication by Norazmi Danuri
CHAPTER SCHEDULING AND TRACKING WORK IN CONSTRUCTION PROJECT MANAGEMENT UWB10202 Effective Communication by Norazmi Danuri (norazmi@uthm.edu.my) Introduction Planning & Scheduling Principles Techniques
More informationProject Time-Cost Trade-Off
Project Time-Cost Trade-Off 7.1 Introduction In the previous chapters, duration of activities discussed as either fixed or random numbers with known characteristics. However, activity durations can often
More informationImpacting the Bottom Line. Cost Reduction: Planning & Control. Bottom Line (costs) A = Costs (what we expend) B = Revenue, sales (what we generate)
Cost Reduction: Planning & Control Break Even Point & Decision Tree Analysis (l.u. 4/2/13) Impacting the Bottom Line Calls for an understanding of: Variation Waste & Value Investments (time, capital, resources,
More informationu w 1.5 < 0 These two results imply that the utility function is concave.
A person with initial wealth of Rs.1000 has a 20% possibility of getting in a mischance. On the off chance that he gets in a mishap, he will lose Rs.800, abandoning him with Rs.200; on the off chance that
More informationA Comparison Between the Non-Mixed and Mixed Convention in CPM Scheduling. By Gunnar Lucko 1
A Comparison Between the Non-Mixed and Mixed Convention in CPM Scheduling By Gunnar Lucko 1 1 Assistant Professor, Department of Civil Engineering, The Catholic University of America, Washington, DC 20064,
More informationUnit 3 Research Project. Eddie S. Jackson. Kaplan University. IT511: Information Systems Project Management
Running head: UNIT 3 RESEARCH PROJECT 1 Unit 3 Research Project Eddie S. Jackson Kaplan University IT511: Information Systems Project Management 04/06/2014 UNIT 3 RESEARCH PROJECT 2 Unit 3 Research Project
More informationDecision Support Tool for Project Time-Cost Trade-off
Decision Support Tool for Project Time-Cost Trade-off Fikri Dweiri Industrial Engineering and Engineering Management Department University of Sharjah Sharjah, UAE, 27272 fdweiri@sharjah.ac.ae Abstract
More information6/7/2018. Overview PERT / CPM PERT/CPM. Project Scheduling PERT/CPM PERT/CPM
/7/018 PERT / CPM BSAD 0 Dave Novak Summer 018 Overview Introduce PERT/CPM Discuss what a critical path is Discuss critical path algorithm Example Source: Anderson et al., 01 Quantitative Methods for Business
More informationPOLYTECHNIC OF NAMIBIA
POLYTECHNIC OF NAMIBIA SCHOOL OF MANAGEMENT SCIENCES DEPARTMENT OF MANAGEMENT PROJECT MANAGEMENT BACHELOR OF BUSINESS ADMINISTRATION 07BBMA SUBJECT CODE: PRM422S DATE: DURATION: MARKS: EXAMINERS: MODERATOR:
More informationCHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM
CHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM 6.1 Introduction Project Management is the process of planning, controlling and monitoring the activities
More informationProject orie:nta.teci pla.:n:ni:ng, scheduling a.:nci controlling technique
Project orie:nta.teci pla.:n:ni:ng, scheduling a.:nci controlling technique By Ha ilu Yemanu, Chief Engineer, Awash Valley Authority In the past several years, 1/iere has been an explosive growth of management
More informationMnDOT Project Management Office Presents: Project Reporting. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc.
MnDOT Project Management Office Presents: Project Reporting Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar
More informationCOPYRIGHTED MATERIAL. Index
Index Note to the reader: Throughout this index boldfaced page numbers indicate primary discussions of a topic. Italicized page numbers indicate illustrations. A A+ certification, 28 acceptance criteria
More informationECSE 321: INTRODUCTION TO SOFTWARE ENGINEERING
ECSE 321: INTRODUCTION TO SOFTWARE ENGINEERING Software Project Management d_sinnig@cs.concordia.ca Department of Electrical and Computer Engineering 08-Jan-14 What is a project? Some dictionary definitions:
More informationPROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA
This section is used for projects over $1,000,000 use other section if less than $1M SECTION 01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 SCOPE A. Preliminary Contract Schedule, Contract
More informationCHAPTER 5 STOCHASTIC SCHEDULING
CHPTER STOCHSTIC SCHEDULING In some situations, estimating activity duration becomes a difficult task due to ambiguity inherited in and the risks associated with some work. In such cases, the duration
More informationProject Management with Brief Information regarding CPM and PERT Methods
99 INTERNATIONAL JOURNAL OF SCIENTIFIC & ENGINEERING RESEARCH, VOLUME 9, ISSUE, JULY-8 Project Management with Brief Information regarding CPM and PERT Methods Rohan Agarwal Guide: Sheetal Patel Abstract
More informationProject Management and Cost Control
Project Management and Cost Control What is Project Management Build A A Done Build B B Done Build C JAN FEB MAR APR MAY JUN C Done Build D On time! Ship Unique, one-time operations designed to accomplish
More informationACWP (actual cost of work performed) Cost of actual work performed to date on the project, plus any fixed costs.
Glossary ACWP (actual cost of work performed) Cost of actual work performed to date on the project, plus any fixed costs. ALAP (as late as possible) A constraint placed on a task s timing to make it occur
More information06IP/IM74 OPERATIONS RESEARCH
06IP/IM74 OPERATIONS RESEARCH UNIT - 6: PROJECT MANAGEMENT USING NETWORK ANALYSIS (By Dr.G.N.MOHAN BABU, Prof & HOD (I&P Engg), MCE, Hassan 573 021) LEARNING OBJECTIVES OF THE MODULE: By the end of this
More informationAppendix B: Glossary of Project Management Terms
Appendix B: Glossary of Project Management Terms Assumption - There may be external circumstances or events that must occur for the project to be successful (or that should happen to increase your chances
More informationINSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points. This is a closed book exam. Answer all the questions in the booklet.
. Surname, given names: Student Number: INSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points This is a closed book exam. Answer all the questions in the booklet. Ensure that your
More informationLine Of Balance. Dr. Ahmed Elyamany
Line Of Balance Dr. Ahmed Elyamany Intended Learning Outcomes Define the principles ofline of Balance (LOB) Demonstrate the application of LOB Understand the importanceof LOB Understand the process ofapplying
More informationQuality Project Management
Quality Project Management By James N. Salapatas, PE, PMP www.suncam.com Copyright 2014 James N. Salapatas Page 1 of 44 Table of Contents Title Page LIST OF CHARTS 2 LIST OF FIGURES 3 ABOUT THE COURSE
More informationManagement Management
Project Management Management Management in all business and organizational activities is the act of getting people together to accomplish desired goals and objectives using available resources efficiently
More informationIntroduction to Project Management. Modeling after NYS ITS
Introduction to Project Management Modeling after NYS ITS What is Project Management? Project management is the application of knowledge, skills, tools and techniques to project activities to meet project
More information56:171 Operations Research Midterm Exam Solutions October 22, 1993
56:171 O.R. Midterm Exam Solutions page 1 56:171 Operations Research Midterm Exam Solutions October 22, 1993 (A.) /: Indicate by "+" ="true" or "o" ="false" : 1. A "dummy" activity in CPM has duration
More informationProject Controls Expo 16 th Nov 2016
Project Controls Expo 16 th Nov 2016 Emirates Stadium, London Introduction to Planning, Scheduling and Earned Value followed by Case Study on Data Analytics on improved Schedule Data Quality Tushar Tohan
More informationProject Management. A Practitioner s Guide. Steven M. Bragg
Project Management A Practitioner s Guide Steven M. Bragg Chapter 1 Overview of Project Management... 1 Learning Objectives... 1 Introduction... 1 Project Management Activities... 1 The Need for Project
More informationPMP032 Project Management Leadership Skills
PMP032 Project Management Leadership Skills H.H. Sheik Sultan Tower (0) Floor Corniche Street Abu Dhabi U.A.E www.ictd.ae ictd@ictd.ae Course Introduction: Countless numbers of projects undertaken by organizations
More informationTHE ACCELERATING OF DURATION AND CHANGE OF COST ON CONSTRUCTION PROJECT IMPLEMENTATION
International Journal of Civil Engineering and Technology (IJCIET) Volume 10, Issue 01, January 2019, pp. 825-832, Article ID: IJCIET_10_01_075 Available online at http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=10&itype=01
More informationUNIT 5 PROJECT ANALYSIS PERT/CPM MODULE - 2
UNIT 5 PROJECT ANALYSIS MODULE - 2 UNIT 5 PROJECT ANALYSIS Structure 5.0 Introduction 5.1 Unit Objectives 5.2 Definitions of Project and Project Management 5.3 Characteristics of a Project 5.4 Life Cycle
More informationPass PMP in 21 Days - ITTO Toolbox PROCESS MAP
PROCESS MAP 1 IntEgratIon Pass PMP in 21 Days - ITTO Toolbox InItIatIng PlannIng ExEcutIng MonItorIng & controlling closing Develop Project Charter Develop Project Management Plan Direct & Manage Project
More informationManaging Projects As Investments: The Benefits Of Computing Critical Path Drag And Drag Cost
Managing Projects As Investments: The Benefits Of Computing Critical Path Drag And Drag Cost ***** A Presentation for PMI Westchester County Chapter by Stephen A. Devaux 6/13/2017 1 The History of PM and
More informationProject Assessment Exercise
Project Assessment Exercise www.spmbook.com We have been assigned the task of assessing the project status of a project, whose Gantt chart is presented in Illustration 1, where: 1. we are currently at
More informationMODULE: INTRODUCTION TO PROJECT MANAGEMENT / PROJECT MANAGEMENT
Programme BA (Hons) Fashion and Textiles (Top-Up) BA (Hons) Graphic Design with Animation (Top-Up) BA (Hons) Interior Design Cohort FDI- BFT(TP)/14B/PT FDI- BGDA(TP)/14B/PT FDI-BAID/13B/FT Examinations
More informationEXERCISE Draw the network diagram. a. Activity Name A B C D E F G H
XRIS. What do you mean by network analysis? xplain with counter examples.. What are the basic differences between PM and PRT analysis of project work?. State the rule of constructing the network diagram..
More informationProject Management. Basic Definitions: Project and Project Plan
Project Management Basic Definitions: Project and Project Plan Software Project: All technical and managerial activities required to deliver the deliverables to the client. A software project has a specific
More informationBrown hamburger and assemble tacos (including cheese)
19.1 An Introduction to PERT PERT is an acronym for the Program Evaluation Review Technique. The Special Projects Office in the Department of the Navy created this project management tool in 1958. It was
More informationAssistance with University Projects? Research Reports? Writing Skills? We have got you covered! www.assignmentstudio.net WhatsApp: +61-424-295050 Toll Free: 1-800-794-425 Email: contact@assignmentstudio.net
More information