The Critical Path Method
|
|
- Stephany McKenzie
- 6 years ago
- Views:
Transcription
1 The Critical Path Method Presented by Antonio Prensa, MBA, PMP, CCP, CSTE for Project Management Institute Puerto Rico Chapter June 2, 22 San Juan, Puerto Rico
2 "I believe that this nation should commit itself to achieving a goal, before this decade is out, of landing a man on the moon..." - John F. Kennedy, May 27,1961
3 On July 2, 1969, just eight years after Kennedy's speech, Apollo 11 landed two men on the moon. This achievement was possible only with careful production planning that included the critical path method. NASA used the critical path method to help determine an efficient schedule for the tasks that led to the moon landing.
4 Discussion Topics Background Some questions about the project What is the Critical Path Method (CPM)? Why the CPM? How to use the CPM? Questions and Answers
5 Background The critical path method (CPM) was invented by project managers in the early 195's. The US Navy adapted and improved it to manage the Polaris missile project in the late 195's
6 Some questions about the project How long will the entire project take to complete? Which activities determine total project time? Which activity times should be shortened, if possible, or in other words, how many resources should be allocated to each activity?
7 What is the CPM? Critical Path Method (CPM), is a procedure for using network analysis to identify those tasks which are on the critical path: ie where any delay in the completion of these tasks will lengthen the project timescale, unless action is taken. For all tasks off the critical path, a degree of tolerance is possible (eg. late start, late completion, early start, etc.). Network charts and CPM analysis used to be carried out by hand. Software is now available which requires the user only to enter the tasks, duration of each task and dependencies upon other tasks; a network chart and CPM is then automatically created.
8 Why the CPM? The CPM formally identifies tasks which must be completed on time for the whole project to be completed on time Identifies which tasks can be delayed for a while if resource needs to be reallocated to catch up on missed tasks It helps you to identify the minimum length of time needed to complete a project The CPM determines both the early start and the late start date for each activity in the schedule.
9 How to use the CPM? Project Network Diagram Any schematic display of the logical relationships of project activities
10 How to use the CPM? List List the the activities And And relationships Create Create a start start node node Draw Draw arrows arrows from from Start Start node node to to the the First First activity s node node Sequentially Arrange all all Activities from from Start Start Repeat Repeat process process from from successors for for all all activities Double Double check check for for missed missed relationships
11 How to use the CPM? Early Start (ES) Early Finish (EF) Task duration Late Start (LS) Late Finish (LF)
12 How to use the CPM? Task ID Duration Dependency A 7 B 3 C 6 A D 3 B E 3 D,F F 2 B G 3 C H 2 E,G
13 How to use the CPM? S A C G (7) (6) (3) H (2) F B D (3) (3) 6 9 E (3) 3 5 F (2)
14 How to use the CPM? S A C G (7) 7 7 (6) (3) H (2) 18 F 7 B D (3) 1 1 (3) E (3) F (2) 13
15 How to use the CPM? S 7 A B C D F G (7) 7 7 (6) (3) (3) 1 1 (3) (2) E (3) H (2) 18 F
16 Summary Critical Path Analysis is an effective and powerful method of assessing: Tasks which must be carried out Where parallel activity can be carried out The shortest time in which a project can be completed Resources needed to achieve a project The sequence of activities, scheduling, and timings involved Task priorities
17 Do you need more information? Project Management:A systems approach to Planning, Scheduling, and Controlling Harold Kerzner, Six edition. Project Management: A Managerial Approach Jack R. Meredith, Samuel J. Mantel, Fourth Edition. Web Search Engine key word: The Critical Path Method or The CPM.
18 Contact me at: Antonio Prensa / Phone: (787) ext. 3725
19 The Critical Path Method Presented by Antonio Prensa, MBA, PMP, CCP, CSTE for Project Management Institute Puerto Rico Chapter June 2, 22 San Juan, Puerto Rico
A convenient analytical and visual technique of PERT and CPM prove extremely valuable in assisting the managers in managing the projects.
Introduction Any project involves planning, scheduling and controlling a number of interrelated activities with use of limited resources, namely, men, machines, materials, money and time. The projects
More informationCHAPTER 9: PROJECT MANAGEMENT
CHAPTER 9: PROJECT MANAGEMENT The aim is to coordinate and plan a single job consisting lots of tasks between which precedence relationships exist Project planning Most popular planning tools are utilized
More informationCISC 322 Software Architecture
CISC 22 Software Architecture Project Scheduling (PERT/CPM) Ahmed E. Hassan (Edited For Course Presentation, 206) Project A project is a temporary endeavour undertaken to create a "unique" product or service
More informationProject Planning. Identifying the Work to Be Done. Gantt Chart. A Gantt Chart. Given: Activity Sequencing Network Diagrams
Project Planning Identifying the Work to Be Done Activity Sequencing Network Diagrams Given: Statement of work written description of goals work & time frame of project Work Breakdown Structure Be able
More informationProject Management. Chapter 2. Copyright 2013 Pearson Education, Inc. publishing as Prentice Hall
Project Management Chapter 2 02-0 1 What is a Project? Project An interrelated set of activities with a definite starting and ending point, which results in a unique outcome for a specific allocation of
More informationSCHEDULE CREATION AND ANALYSIS. 1 Powered by POeT Solvers Limited
SCHEDULE CREATION AND ANALYSIS 1 www.pmtutor.org Powered by POeT Solvers Limited While building the project schedule, we need to consider all risk factors, assumptions and constraints imposed on the project
More informationUNIT-II Project Organization and Scheduling Project Element
UNIT-II Project Organization and Scheduling Project Element Five Key Elements are Unique. Projects are unique, one-of-a-kind, never been done before. Start and Stop Date. Projects must have a definite
More informationProgram Evaluation and Review Techniques (PERT) Critical Path Method (CPM):
Program Evaluation and Review Techniques (PERT) Critical Path Method (CPM): A Rough Guide by Andrew Scouller PROJECT MANAGEMENT Project Managers can use project management software to keep track of the
More informationProject Management -- Developing the Project Plan
Project Management -- Developing the Project Plan Dr. Tai-Yue Wang Department of Industrial and Information Management National Cheng Kung University Tainan, TAIWAN, ROC 1 Where We Are Now 6 2 Developing
More informationInternational Journal of Advanced Engineering and Management Research Vol. 2 Issue 4, ISSN:
International Journal of Advanced Engineering and Management Research Vol. 2 Issue 4, 2017 http://ijaemr.com/ ISSN: 2456-3676 CPM AND PERT COMPARISON ANALYSIS IN PROJECT PLANNING ABSTRACT Talatu Muhammad
More informationProject Planning. Jesper Larsen. Department of Management Engineering Technical University of Denmark
Project Planning jesla@man.dtu.dk Department of Management Engineering Technical University of Denmark 1 Project Management Project Management is a set of techniques that helps management manage large-scale
More informationResearch Methods Outline
: Project Management James Gain jgain@cs.uct.ac.za Outline Introduction [] Project Management [] Experimental Computer Science [] Role of Mathematics [1] Designing User Experiments [] Qualitative Research
More informationProgramme Evaluation and Review Techniques (PERT) And Critical Path Method (CPM) By K.K. Bandyopadhyay. August 2001
Programme Evaluation and Review Techniques (PERT) And Critical Path Method (CPM) By K.K. Bandyopadhyay August 2001 Participatory Research In Asia Introduction Programme Evaluation and Review Technique
More informationPROJECT MANAGEMENT CPM & PERT TECHNIQUES
PROJECT MANAGEMENT CPM & PERT TECHNIQUES FLOW OF PRESENTATION INTRODUCTION NETWORK PLANNING ESTIMATING TIME CPM PERT Project Management Project A project is an interrelated set of activities that has a
More informationAfter complete studying this chapter, You should be able to
Chapter 10 Project Management Ch10: What Is Project Management? After complete studying this chapter, You should be able to Define key terms like Project, Project Management, Discuss the main characteristics
More informationProject Management Professional (PMP) Exam Prep Course 06 - Project Time Management
Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management Slide 1 Looking Glass Development, LLC (303) 663-5402 / (888) 338-7447 4610 S. Ulster St. #150 Denver, CO 80237 information@lookingglassdev.com
More informationIE 102 Spring Project Management
IE 102 Spring 2018 Project Management 1 Management of Projects Planning - goal setting, defining the project, team organization Scheduling - relates people, money, and supplies to specific activities and
More information6/7/2018. Overview PERT / CPM PERT/CPM. Project Scheduling PERT/CPM PERT/CPM
/7/018 PERT / CPM BSAD 0 Dave Novak Summer 018 Overview Introduce PERT/CPM Discuss what a critical path is Discuss critical path algorithm Example Source: Anderson et al., 01 Quantitative Methods for Business
More informationTextbook: pp Chapter 11: Project Management
1 Textbook: pp. 405-444 Chapter 11: Project Management 2 Learning Objectives After completing this chapter, students will be able to: Understand how to plan, monitor, and control projects with the use
More informationProject Management Chapter 13
Lecture 12 Project Management Chapter 13 Introduction n Managing large-scale, complicated projects effectively is a difficult problem and the stakes are high. n The first step in planning and scheduling
More information11/1/2018. Overview PERT / CPM. Network representation. Network representation. Project Scheduling. What is a path?
PERT / CPM BSD Dave Novak Fall Overview Introduce Discuss what a critical path is Discuss critical path algorithm Example Source: nderson et al., 1 Quantitative Methods for Business 1 th edition some slides
More informationTeori Pengambilan Keputusan. Week 12 Project Management
Teori Pengambilan Keputusan Week 1 Project Management Project Management Program Evaluation and Review Technique (PERT) Critical Path Method (CPM) PERT and CPM Network techniques Developed in 195 s CPM
More informationAppendix A Decision Support Analysis
Field Manual 100-11 Appendix A Decision Support Analysis Section I: Introduction structure development, and facilities. Modern quantitative methods can greatly facilitate this Complex decisions associated
More informationWHY ARE PROJECTS ALWAYS LATE?
WHY ARE PROJECTS ALWAYS LATE? (what can the Project Manager DO about that?) Craig Henderson, MBA, PMP ARVEST Bank Operations Introduction PM Basics FIO GID KISS (Figure it out) (Get it done) (Keep it simple,
More informationA Comparison Between the Non-Mixed and Mixed Convention in CPM Scheduling. By Gunnar Lucko 1
A Comparison Between the Non-Mixed and Mixed Convention in CPM Scheduling By Gunnar Lucko 1 1 Assistant Professor, Department of Civil Engineering, The Catholic University of America, Washington, DC 20064,
More informationINSE 6230: Assignment 1 - Winter (0% of final grade) 1. The table below provides information about a short IT project.
INSE 6230: Assignment - Winter 208 (0% of final grade). The table below provides information about a short IT project. Activity Predecessors Duration (Months) A - 2 B - 3 C A 4 D A, B 2 E D 2 F B, C, E
More informationPROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT. G.N. Sandhy Widyasthana
PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT G.N. Sandhy Widyasthana widyasthana@gmail.com 022 70702020 081 225 702020 1 2 3 Process of identifying the specific actions to be performed to produce
More informationMODULE: INTRODUCTION TO PROJECT MANAGEMENT / PROJECT MANAGEMENT
Programme BA (Hons) Fashion and Textiles (Top-Up) BA (Hons) Graphic Design with Animation (Top-Up) BA (Hons) Interior Design Cohort FDI- BFT(TP)/14B/PT FDI- BGDA(TP)/14B/PT FDI-BAID/13B/FT Examinations
More informationConstruction Management
Construction Management 1. Which one of the following represents an activity A. excavation for foundation B. curing of concrete C. setting of question paper D. preparation of breakfast 2. Pick up the incorrect
More informationIntroduction. Introduction. Six Steps of PERT/CPM. Six Steps of PERT/CPM LEARNING OBJECTIVES
Valua%on and pricing (November 5, 2013) LEARNING OBJECTIVES Lecture 12 Project Management Olivier J. de Jong, LL.M., MM., MBA, CFD, CFFA, AA www.olivierdejong.com 1. Understand how to plan, monitor, and
More informationProject Management Fundamentals
Project Management Fundamentals Course No: B04-003 Credit: 4 PDH Najib Gerges, Ph.D., P.E. Continuing Education and Development, Inc. 9 Greyridge Farm Court Stony Point, NY 10980 P: (877) 322-5800 F: (877)
More informationMnDOT use of Calendars in Primavera P6
MnDOT Project Management Office Presents: MnDOT use of Calendars in Primavera P6 Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be
More informationCHAPTER 5 SCHEDULING AND TRACKING WORK IN CONSTRUCTION PROJECT MANAGEMENT. UWB10202 Effective Communication by Norazmi Danuri
CHAPTER SCHEDULING AND TRACKING WORK IN CONSTRUCTION PROJECT MANAGEMENT UWB10202 Effective Communication by Norazmi Danuri (norazmi@uthm.edu.my) Introduction Planning & Scheduling Principles Techniques
More information1 of 14 4/27/2009 7:45 AM
1 of 14 4/27/2009 7:45 AM Chapter 7 - Network Models in Project Management INTRODUCTION Most realistic projects that organizations like Microsoft, General Motors, or the U.S. Defense Department undertake
More informationProbabilistic Completion Time in Project Scheduling Min Khee Chin 1, Sie Long Kek 2, Sy Yi Sim 3, Ta Wee Seow 4
Probabilistic Completion Time in Project Scheduling Min Khee Chin 1, Sie Long Kek 2, Sy Yi Sim 3, Ta Wee Seow 4 1 Department of Mathematics and Statistics, Universiti Tun Hussein Onn Malaysia 2 Center
More informationBut is it on the critical path?
But is it on the critical path? Notes from an evening seminar held on the 12 May 2005 for the Adjudication Society Seminar in the London office of Ove Arup Speaker Peter Curtis Ladymead Projects Ltd Agenda
More informationInternational Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ
International Project Management prof.dr MILOŠ D. MILOVANČEVIĆ Project time management Project cost management Time in project management process Time is a valuable resource. It is also the scarcest. Time
More informationETSF01: Software Engineering Process Economy and Quality
ETSF01: Software Engineering Process Economy and Quality Dietmar Pfahl Lund University 1. Identify project objectives 0.Select project 2. Identify project infrastructure Project planning steps Review Lower
More informationCHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM
CHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM 6.1 Introduction Project Management is the process of planning, controlling and monitoring the activities
More informationProject planning and creating a WBS
37E01500 Project Management and Consulting Practice Project planning and creating a WBS Matti Rossi Lecture 3, Tue 28.2.2017 Learning objectives Describe the project time management planning tasks, and
More informationDecision Support Tool for Project Time-Cost Trade-off
Decision Support Tool for Project Time-Cost Trade-off Fikri Dweiri Industrial Engineering and Engineering Management Department University of Sharjah Sharjah, UAE, 27272 fdweiri@sharjah.ac.ae Abstract
More informationComparison between Deterministic and Stochastic Time Estimating Techniques
Comparison between Deterministic and Stochastic Time Estimating Techniques Daketima G. Briggs, Ph.D, PMP Management Department, Faculty of Business, University of Botswana ABSTRACT: This paper started
More informationManagement Management
Project Management Management Management in all business and organizational activities is the act of getting people together to accomplish desired goals and objectives using available resources efficiently
More informationOutline. Global Company Profile: Bechtel Group. The Importance of Project Management Project Planning Project Scheduling Project Controlling
Project Management Outline Global Company Profile: Bechtel Group The Importance of Project Management Project Planning Project Scheduling Project Controlling Outline - Continued Project Management Techniques:
More information06IP/IM74 OPERATIONS RESEARCH
06IP/IM74 OPERATIONS RESEARCH UNIT - 6: PROJECT MANAGEMENT USING NETWORK ANALYSIS (By Dr.G.N.MOHAN BABU, Prof & HOD (I&P Engg), MCE, Hassan 573 021) LEARNING OBJECTIVES OF THE MODULE: By the end of this
More informationSWEN 256 Software Process & Project Management
SWEN 256 Software Process & Project Management Plan: Identify activities. No specific start and end dates. Estimating: Determining the size & duration of activities. Schedule: Adds specific start and end
More informationACWP (actual cost of work performed) Cost of actual work performed to date on the project, plus any fixed costs.
Glossary ACWP (actual cost of work performed) Cost of actual work performed to date on the project, plus any fixed costs. ALAP (as late as possible) A constraint placed on a task s timing to make it occur
More informationLecture 3 Project Scheduling
B10 Lecture Project Scheduling Omar El-Anwar, PhD, PMP Network alculations The purpose of conducting network calculations is to know more about the scheduling of activities: When will each activity start?
More informationMnDOT Project Management Office Presents: Project Reporting. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc.
MnDOT Project Management Office Presents: Project Reporting Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar
More informationSECTION ARCHITECTURAL AND ENGINEERING CPM SCHEDULES
SECTION 01 32 16.01 ARCHITECTURAL AND ENGINEERING CPM SCHEDULES PART 1- GENERAL 1.1 DESCRIPTION: The Architect/Engineer of Record (A/E) shall develop a Critical Path Method (CPM Schedule) plan and schedule
More informationQuality Project Management
Quality Project Management By James N. Salapatas, PE, PMP www.suncam.com Copyright 2014 James N. Salapatas Page 1 of 44 Table of Contents Title Page LIST OF CHARTS 2 LIST OF FIGURES 3 ABOUT THE COURSE
More informationPROJECT MANAGEMENT. Trying to manage a project without project management is like trying to play a football game without a game plan
PROJECT MANAGEMENT Trying to manage a project without project management is like trying to play a football game without a game plan K. Tate (Past Board Member, PMI). Brad Fink 28 February 2013 Executive
More informationCrashing the Schedule An Algorithmic Approach with Caveats and Comments
ing the Schedule An Algorithmic Approach with Caveats and Comments Gilbert C. Brunnhoeffer, III PhD, P.E. and B. Gokhan Celik PhD LEED AP Roger Williams University Bristol, Rhode Island and Providence
More informationAllocate and Level Project Resources
Allocate and Level Project Resources Resource Allocation: Defined Resource Allocation is the scheduling of activities and the resources required by those activities while taking into consideration both
More informationManaging Projects As Investments: The Benefits Of Computing Critical Path Drag And Drag Cost
Managing Projects As Investments: The Benefits Of Computing Critical Path Drag And Drag Cost ***** A Presentation for PMI Westchester County Chapter by Stephen A. Devaux 6/13/2017 1 The History of PM and
More informationA UNIT BASED CRASHING PERT NETWORK FOR OPTIMIZATION OF SOFTWARE PROJECT COST PRITI SINGH, FLORENTIN SMARANDACHE, DIPTI CHAUHAN, AMIT BHAGHEL
A UNIT BASED CRASHING PERT NETWORK FOR OPTIMIZATION OF SOFTWARE PROJECT COST PRITI SINGH, FLORENTIN SMARANDACHE, DIPTI CHAUHAN, AMIT BHAGHEL Abstract: Crashing is a process of expediting project schedule
More informationGPE engineering project management. Project Management in an Engineering Context
GPE engineering project management Project Management in an Engineering Context Network diagrams in context PM SOW CHARTER SCOPE DEFINITION WBS circulation, negotiation, translation WBS WP à activities
More informationIntroduction to Project Management. Modeling after NYS ITS
Introduction to Project Management Modeling after NYS ITS What is Project Management? Project management is the application of knowledge, skills, tools and techniques to project activities to meet project
More informationProject Management and Cost Control
Project Management and Cost Control What is Project Management Build A A Done Build B B Done Build C JAN FEB MAR APR MAY JUN C Done Build D On time! Ship Unique, one-time operations designed to accomplish
More informationPOLYTECHNIC OF NAMIBIA
POLYTECHNIC OF NAMIBIA SCHOOL OF MANAGEMENT SCIENCES DEPARTMENT OF MANAGEMENT PROJECT MANAGEMENT BACHELOR OF BUSINESS ADMINISTRATION 07BBMA SUBJECT CODE: PRM422S DATE: DURATION: MARKS: EXAMINERS: MODERATOR:
More informationSECTION PROJECT SCHEDULES (SMALL PROJECTS DESIGN/BID/BUILD)
SECTION 01 32 16.15 PROJECT SCHEDULES (SMALL PROJECTS DESIGN/BID/BUILD) PART 1- GENERAL 1.1 DESCRIPTION: A. The Contractor shall develop a Critical Path Method (CPM) plan and schedule demonstrating fulfillment
More informationCOST MANAGEMENT IN CONSTRUCTION PROJECTS WITH THE APPROACH OF COST-TIME BALANCING
ISSN: 0976-3104 Lou et al. ARTICLE OPEN ACCESS COST MANAGEMENT IN CONSTRUCTION PROJECTS WITH THE APPROACH OF COST-TIME BALANCING Ashkan Khoda Bandeh Lou *, Alireza Parvishi, Ebrahim Javidi Faculty Of Engineering,
More informationProject Management with Brief Information regarding CPM and PERT Methods
99 INTERNATIONAL JOURNAL OF SCIENTIFIC & ENGINEERING RESEARCH, VOLUME 9, ISSUE, JULY-8 Project Management with Brief Information regarding CPM and PERT Methods Rohan Agarwal Guide: Sheetal Patel Abstract
More informationProject Time-Cost Trade-Off
Project Time-Cost Trade-Off 7.1 Introduction In the previous chapters, duration of activities discussed as either fixed or random numbers with known characteristics. However, activity durations can often
More informationMINIMIZE TIME AND COST FOR SUCCESSFUL COMPLETION OF A LARGE SCALE PROJECT APPLYING PROJECT CRASHING METHOD
International Journal of Advanced Research and Review www.ijarr.in MINIMIZE TIME AND COST FOR SUCCESSFUL COMPLETION OF A LARGE SCALE PROJECT APPLYING PROJECT CRASHING METHOD Shifat Ahmed Lecturer, Southeast
More informationDC Program and Project Managers Meeting #2
+ Trevor Lowing Trevor.Lowing@gmail.com DC Program and Project Managers Meeting #2 Session 1: Planning projects with MS Project Session 2: Workshop: Generating Reports with MS Project and Visual Basic
More informationVALLIAMMAI ENGINEERING COLLEGE
VALLIAMMAI ENGINEERING COLLEGE SRM Nagar, Kattankulathur 603 203 DEPARTMENT OF CIVIL ENGINEERING QUESTION BANK VI SEMESTER CE6005 CONSTRUCTION PLANNING AND SCHEDULING Regulation 2013 Academic Year 2017
More informationProject Management Techniques (PMT)
Project Management Techniques (PMT) Critical Path Method (CPM) and Project Evaluation and Review Technique (PERT) are 2 main basic techniques used in project management. Example: Construction of a house.
More informationNetwork Analysis Basic Components. The Other View. Some Applications. Continued. Goal of Network Analysis. RK Jana
Network nalysis RK Jana asic omponents ollections of interconnected linear forms: Lines Intersections Regions (created by the partitioning of space by the lines) Planar (streets, all on same level, vertices
More informationCOPYRIGHT AND CITATION CONSIDERATIONS FOR THIS THESIS/ DISSERTATION
COPYRIGHT AND CITATION CONSIDERATIONS FOR THIS THESIS/ DISSERTATION o Attribution You must give appropriate credit, provide a link to the license, and indicate if changes were made. You may do so in any
More informationOutline. Project Management. Introduction. What is a Project?
Outline Project Management Jeffrey Pinto, Ph.D. Penn State Erie What is Project Management? Scope Management Risk Management Planning and Scheduling Project Evaluation and Control Project Termination Introduction
More informationAssistance with University Projects? Research Reports? Writing Skills? We have got you covered! www.assignmentstudio.net WhatsApp: +61-424-295050 Toll Free: 1-800-794-425 Email: contact@assignmentstudio.net
More informationProject Controls Expo 16 th Nov 2016
Project Controls Expo 16 th Nov 2016 Emirates Stadium, London Introduction to Planning, Scheduling and Earned Value followed by Case Study on Data Analytics on improved Schedule Data Quality Tushar Tohan
More informationSECTION PROJECT SCHEDULE 08/08
SECTION 01 32 01.00 10 PROJECT SCHEDULE 08/08 PART 1 GENERAL 1.1 REFERENCES The publications listed below form a part of this specification to the extent referenced. The publications are referred to within
More informationSystems Engineering. Engineering 101 By Virgilio Gonzalez
Systems Engineering Engineering 101 By Virgilio Gonzalez Systems process What is a System? What is your definition? A system is a construct or collection of different elements that together produce results
More informationCONSTRUCTION MANAGEMENT CHAPTER 3 PLANNING
CONSTRUCTION MANAGEMENT CHAPTER 3 PLANNING Planning of Works Contract Form of contract by which one party undertakes to the other to perform certain work, for a price. Corresponds to the execution of a
More informationPROJECT MANAGEMENT IN PRACTICE
PROJECT MANAGEMENT IN PRACTICE Fourth Edition Samuel J. Mantel, Jr. University of Cincinnati Jack R. Meredith Wake Forest University Scott M. Shafer Wake Forest University Margaret M. Sutton button Associates
More informationECSE 321: INTRODUCTION TO SOFTWARE ENGINEERING
ECSE 321: INTRODUCTION TO SOFTWARE ENGINEERING Software Project Management d_sinnig@cs.concordia.ca Department of Electrical and Computer Engineering 08-Jan-14 What is a project? Some dictionary definitions:
More informationTechniques to Assist Delivery of Projects
Techniques to Assist Delivery of Projects 1 Introduction Who am I? Ian Bell Where am I from? Adept Knowledge Management Ltd Based at 5 Carden Place Aberdeen AB10 1UT +44 (0) 1224 251015 2 Introduction
More informationProject Management. Project Mangement. ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala.
Project Mangement ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala. Page 1 of 380 26/4/2008 Syllabus 1. Total Project Management Concept, relationship with other function and other organizations,
More informationSSC-JE STAFF SELECTION COMMISSION CIVIL ENGINEERING STUDY MATERIAL ESTIMATING, COSTING AND VALUATION
1 ` SSC-JE STAFF SELECTION COMMISSION CIVIL ENGINEERING STUDY MATERIAL SSC-JE Civil Engineering 2 Estimating, Costing and Valuation : Estimate, Glossary of technical terms, Analysis of rates, Methods and
More informationIns. Luay Dwaikat Fall 2013/2014
An-Najah National University Faculty of Engineering Civil/Building Engineering Dept. Construction Management - 6147 Ins. : Luay Dwaikat Course Outline Introduction to project management Project Work breakdown
More informationMICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR CRITICAL PATH METHOD NETWORK SCHEDULE
MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR CRITICAL PATH METHOD NETWORK SCHEDULE C&T:JTL 1 of 6 C&T:APPR:JDC:PAL:07-24-02 FHWA:APPR:06-01-11 a. Description. In addition to the progress
More informationUNIT 5 PROJECT ANALYSIS PERT/CPM MODULE - 2
UNIT 5 PROJECT ANALYSIS MODULE - 2 UNIT 5 PROJECT ANALYSIS Structure 5.0 Introduction 5.1 Unit Objectives 5.2 Definitions of Project and Project Management 5.3 Characteristics of a Project 5.4 Life Cycle
More informationVALUE MANAGEMENT INTERNATIONAL RESEARCH JOURNAL OF ENGINEERING AND TECHNOLOGY (IRJET) E-ISSN: Snehal Salunke
VALUE MANAGEMENT Snehal Salunke Post Graduate Student, Civil Engg. Department, SSJCET, Asangaon, Thane -----------------------------------------------------------------------------***------------------------------------------------------------------
More informationUnit 3 Research Project. Eddie S. Jackson. Kaplan University. IT511: Information Systems Project Management
Running head: UNIT 3 RESEARCH PROJECT 1 Unit 3 Research Project Eddie S. Jackson Kaplan University IT511: Information Systems Project Management 04/06/2014 UNIT 3 RESEARCH PROJECT 2 Unit 3 Research Project
More informationProject Theft Management,
Project Theft Management, by applying best practises of Project Risk Management Philip Rosslee, BEng. PrEng. MBA PMP PMO Projects South Africa PMO Projects Group www.pmo-projects.co.za philip.rosslee@pmo-projects.com
More informationChapter 2 The PERT/CPM Technique
Chapter The PERT/CPM Technique Abstract Completing a project on time and within budget is not an easy task. The project scheduling phase plays a central role in predicting both the time and cost aspects
More informationMS Project 2007 Page 1 of 18
MS Project 2007 Page 1 of 18 PROJECT MANAGEMENT (PM):- There are powerful environment forces contributed to the rapid expansion of the projects and project management approaches to the business problems
More informationOptimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur. Lecture - 18 PERT
Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur Lecture - 18 PERT (Refer Slide Time: 00:56) In the last class we completed the C P M critical path analysis
More informationFinal: Total 200 points (3-hour exam)
Final: Total 200 points (3-hour exam) [Engineering Economics] IRR Calculation [15 points] One alternative for improving a company s operations is to do nothing for the next 2 years and then spend $10,000
More informationPlan Implementation. Pushpa Lal Shakya
Plan Implementation Pushpa Lal Shakya Outline of Presentation 1. Plan Implementation: Meaning 2. Use of MTEF in Plan Implementation 3. Plan implementation Process and Implementation Modalities 4. Application
More informationCOPYRIGHTED MATERIAL. Index
Index Note to the reader: Throughout this index boldfaced page numbers indicate primary discussions of a topic. Italicized page numbers indicate illustrations. A A+ certification, 28 acceptance criteria
More informationNavigation: PeopleSoft Menu > Set up HCM > Product Related > Commitment Accounting > UC Customizations > Funding Entry
-By- Guide UCLA UCPATH Update Funding for Positions Use this task to Update funding for an unfilled of filled position. NOTE: Refer to the job aid called Update Funding for Positions with Salary Caps or
More informationNETWORK ANALYSIS QUESTION BANK
NETWORK ANALYSIS QUESTION BANK 1. Explain the terms : Total elapsed time, idle time. 2. What do you mean by dummy activity and successor activity. 3. Write four advantages of network analysis. 4. Explain
More informationExpense: Workflow Cost Object Approval
Expense: Workflow Cost Object Approval Setup Guide Applies to these SAP Concur solutions: Expense Professional/Premium edition Standard edition Travel Professional/Premium edition Standard edition Invoice
More informationTHE ACCELERATING OF DURATION AND CHANGE OF COST ON CONSTRUCTION PROJECT IMPLEMENTATION
International Journal of Civil Engineering and Technology (IJCIET) Volume 10, Issue 01, January 2019, pp. 825-832, Article ID: IJCIET_10_01_075 Available online at http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=10&itype=01
More informationChapter 18. Indebtedness
Chapter 18 Indebtedness This Page Left Blank Intentionally CTAS User Manual 18-1 Indebtedness: Introduction The Indebtedness Module is designed to track an entity s indebtedness. By entering the principal
More informationProject Network Analysis Model to Dredging Operations In Niger Delta
American Journal of Engineering Research (AJER) E-ISSN: 2320-0847 p-issn: 2320-0936 Volume-7, Issue-12, pp-150-165 www.ajer.org Research Paper Open Access Project Network Analysis Model to Dredging Operations
More information[Project Name] Project Schedule Management Plan. [Sub-Project, phase, etc.] [Company] [Company Address] Marc Arnecke, PMP
[Company] [Company Address] Tel: Fax: [Company Phone] [Company Fax] [Company E-mail] May 16, 2015 [Ref. number] Marc Arnecke, PMP [Project Name] [Sub-Project, phase, etc.] The project schedule management
More information