Subject: Generator Retirement ProcedureDeactivation Process and Gap Solution Process

Size: px
Start display at page:

Download "Subject: Generator Retirement ProcedureDeactivation Process and Gap Solution Process"

Transcription

1 NEW YORK INDEPENDENT SYSTEM OPERATOR TECHNICAL BULLETIN 185 5/29/2009, revised , , recertified 9/13/11, mm/dd/16 Subject: ProcedureDeactivation Process and Gap Solution Process This Technical Bulletin explainssummarizes the process by whichnyiso s Generator Operators notifydeactivation Process and Gap Solution Process for the NYISOReliability Planning Process (RPP) as set forth in Section of their intent to retire a generator, per the New York State Public Service Commission (PSC) order in Case 05-E Proceeding on MotionAttachment Y of the Commission to Establish Policies and Procedures Regarding Generation Unit Retirements.Open Access Transmission Tariff (OATT). Details: In PSC Case No. 05-E The NYISO recently filed a Reliability Must Run (RMR) compliance filing with the Federal Energy Regulatory Commission (FERC). The compliance filing proposed revisions to the Reliability Planning Process addressing, among other things, the Generator Deactivation and Gap Solution processes and requested an effective date of October 20, This Technical Bulletin summarizes several of the principal obligations and requirements included in the revised Generator Deactivation and Gap Solution processes. Generators, Transmission Owners, Developers and Market Participants must review the relevant provisions of the Tariffs and other authority cited herein to ensure their full understanding of the NYISO processes and of their responsibilities. (1) Generator Deactivation Notice A Generator must provide the NYISO with a minimum of 365 days notice before it may be Retired or enter into a Mothball Outage. 2 The Generator must follow the instructions for submitting the Generator Deactivation Notice Form set forth in Section of Attachment Y and its submission must include the information required to satisfy the informational requirements contained in Section of Attachment Y of the Open Access Transmission Tariff (OATT). If the Generator intends to deactivate in greater than 365 days, it must specify its proposed later deactivation date in its notice. If the Generator is interested in deactivating in less than 365 days (provided that the NYISO does not identify a Reliability Need that would result from the deactivation), the Generator must indicate this interest in its notice. The 365-day period will begin to run on the Generator Deactivation Assessment Start Date, which is the date that the NYISO issues a written notice indicating that the Generator Deactivation Notice and associated informational submissions are sufficiently complete for the NYISO to commence its review. If the Initiating Generator has entered into an ICAP Ineligible Forced Outage (IIFO), the Generator Deactivation Assessment Start Date is the date that the Generator entered into the IIFO state. Such Generator must provide the NYISO with the information required by Section of Attachment Y within twenty days of entering the IIFO state, consistent with Section of the Market Administration and Control Area Service Tariff (Services Tariff). 1 NYISO s Compliance Filing to Establish Reliability Must Run (RMR) Tariff Provisions (Oct. 19, 2015) is available at: 2 Section of Attachment Y. The purpose of this Technical Bulletin is to facilitate participation in the NYISO by communicating various NYISO concepts, techniques, and processes to Market Participants before they can be formally documented in a NYISO manual. The information contained in this bulletin is subject to change as a result of a revision to the ISO Tariffs or a subsequent filed tariff with the FERC. NYISO Customer Support Page 1 of 5

2 All notices that Generator Deactivation Notices are complete will be posted to the NYISO s web page under Planning. Generators remain separately responsible for satisfying any state law or regulatory requirements concerning their deactivation, including advance notice requirements to the NYPSC and transmission and distribution utilities as set forth in Proceeding on Motion of the Commission to Establish Policies and Procedures Regarding Generation Unit Retirements, the PSC Case 05-E-0889, Order Adopting Notice Requirements for Generation Unit Retirements (issued an Order requiring that generators subject to PSC jurisdiction greater than 2 MW should provide notification of their intent to retire their generator. The PSC order states that "(g)enerators proposing to retire are required to serve their notice on our (PSC) Secretary, the NYISO, and any affected T&D utility. 3 " TheDecember 20, 2005) ( PSC Order ). Generator Owner isowners are requested to forward a copy of the respective generator's retirementany deactivation letter to the PSCsubmitted to the PSC, which differs from or is in addition to the NYISO s Generator Deactivation Notice pursuant to of Attachment Y, to the NYISO at: generator_retirement@nyiso.com. The length of the time period for notification depends upon the size of the generator. See Table 1 below for a chart of lead-time versus generator size, as defined by the PSC order: Such deactivation letters submitted to the PSC will be posted to NYISO s web page under Planning. Table 1: Notification Lead-Times Generator Size Lead Time for Notification 2 MW N/A > 2 MW, but less than 80 MW 90 Days 80 MW 180 Days The PSC Order further states that "we request that the NYISO notify its market participants of any retirement notices it receives, in order to apprise those potentially-affected parties. The NYISO is issuing this Technical Bulletin to assist Market Participants in providing their generator retirement notification to the NYISO. The NYISO is also requesting notification of generator retirements from generators pursuant to Section 3.5 of the Services Tariff, which states that: (2) "Customers shall inform the ISO, in accordance with the ISO procedures, of the Availability of Generators within the NYCA subject to a Customer s control by Energy contract, ownership or otherwise.... Suppliers will provide Generator Deactivation Assessment Following the Generator Deactivation Assessment Start Date, the NYISO will perform, in coordination with the Responsible Transmission Owner(s) (TO(s)), a Generator Deactivation Assessment to determine the impact on reliability of the Initiating Generator s deactivation as set forth in Section of Attachment Y. As a part of the Generator Deactivation Assessment, the Responsible TO(s) will perform the necessary reliability studies to review the impact on the reliability of the non- Bulk Power Transmission Facilities that are part of the New York State Transmission System. The results of the Generator Deactivation Assessment, which will identify whether a Reliability Need is expected to arise, will be posted on the NYISO s web page under Planning. 3 The Order did not apply to generators owned by the New York Power Authority (NYPA) or the Long Island Power Authority (LIPA), but NYPA and LIPA may voluntarily provide the notifications called for in the Order. NYISO Customer Support Page 2 of 5

3 (3) Generator Deactivation If the Generator Deactivation Assessment does not identify a Reliability Need, an Initiating Generator that has indicated an interest in an early deactivation in its Generator Deactivation Notice may be Retired or enter into a Mothball Outage consistent with Section of Attachment Y. Otherwise, a Generator that satisfies the requirements to be Retired or enter into a Mothball Outage may do so within 365 days of: (i) the conclusion of the 365-day notice period or (ii) the later date specified in its Generator Deactivation Notice. 4 If the Generator is not Retired or has not entered into a Mothball Outage within this time period, it must begin the Generator Deactivation process anew to be Retired or to enter into a Mothball Outage. 5 Generators are also required to provide specific data to the NYISO as set forth in Section 3.5 of the Services Tariff regarding their deactivation. They must provide, among other information: data on Generator status and output including maintenance schedules, Generator scheduled return dates (inclusive of return to service from maintenance, forced outages or partial unit outagesoutage that resulted in significant reduction in a generating unit s ability to produce Energy in any hour), and Generator machine data, in accordance with the ISO Procedures. These data shall also include Generator Incremental/Decremental Bids, operating limits, response rates, megawatt, megavar and voltage readings.". Notification provided in accordance with this Technical Bulletin will be promptly forwarded to all necessary departments within the NYISO to communicate a prospective generator retirement. If the NYISO requires additional technical information to perform the A Market Party is required reliability analyses from the generator, the respective NYISO department will contact the generator. Accordingly once communicated to the NYISO, the NYISO will also post the generator notice as received to its Planning web page at: Finally, this Technical Bulletin requires generators to to confirm the retiremententry of their unitsits Generator into a Retired or Mothball Outage state, so that the NYISO can timely update its data.market Information System. At least five business days in advance, or as soon as practicable before the actual retirement date, each generatordate that the Generator actually enters into a Retired or Mothball Outage state, each Generator shall contact its NYISO Customer Relations representative to confirm the retirementits change of the unit or units and associated changes to the NYISO s Market Information System; provided, however, that the NYISO status. The NYISO shall not be obligated to reflect the unit retirement in NYISOits systems the entry of the Generator into a Retired or Mothball Outage state on or before the date of the actual unit retirementchange of status if the notice of retirementsuch confirmation is received by the NYISO fewer than five business days in advance of the actual unit retirement. The NYISO shall as soon as practicable but not later than five business days of receiving notice of the actual unit retirement date reflect the unit retirement in NYISO systems. Once the generator is retired, the NYISO will send a final notice of retirement to its MP TIE distribution list. When a Market Participant provides notice of a generator retirement to all interested parties, the Market Participant also shall provide notice to the NYISO via the following address: generator_retirement@nyiso.com. The Market Participant shall attach to the a PDF copy of the generator retirement notification letter it provided to the PSC. The letter will be posted to the NYISO s website as described above. 4 See Section of Attachment Y. 5 Id. See also Section of Attachment Y. NYISO Customer Support Page 3 of 5

4 Nothing in this Technical Bulletin alters the responsibility of generators for all bids ingenerators to submit Bids to the extent required under the NYISO s Market Information SystemTariffs. Considerations: When retiring a generator, the Market Participant should consider the following as it proceeds in the generator retirement: 1. Day Ahead Market Bidding The Market Services Tariff sets forth certain requirements for generators to offer capacity. The NYISO Market Monitoring Unit will continue to monitor offers until the day of the respective generator s retirement. If a generator fails to comply with the Market Services Tariff, including Attachment H, the Market Participant may be subject to financial sanctions as described in the NYISO Market Services Tariff, Section , ICAP Manual, Sections 4.8 and 6, and Services Tariff Attachment H. 2. ICAP Market The NYISO ICAP Market permits generators to sell their capacity into the market many months ahead of time. When sold into the ICAP market, this capacity is a commitment from the Market Participant to the NYISO, and it is expected that the quantity of capacity will be available for the period sold. If a generator certified capacity from the unit in an ICAP Auction and it will not be available for the entire period, then the generator may be subject to an ICAP deficiency charge, as described in the NYISO Market Services Tariff, sections and A Market Participant has various options available to it to reduce its exposure to potential ICAP deficiency charges. These options include purchasing capacity in the monthly auctions or through a bilateral transaction to satisfy its obligation to provide capacity in accordance with its sale of capacity from the retired generator. (4) Commencement of Gap Solution Process In the event that a Reliability Need cannot be timely addressed through the biennial Reliability Needs Assessment (RNA) or Comprehensive Reliability Planning (CRP) processes, the NYISO will commence the Gap Solution process to address the need as set forth in Section of Attachment Y. (5) Solicitation of Gap Solution Proposals If a Reliability Need requiring a Gap Solution is identified, the NYISO will solicit proposed Gap Solutions and/or market-based solutions from Responsible TO(s) and Developers. Pursuant to Section of Attachment Y, the Responsible TO(s) must submit a Gap Solution proposal, together with a conceptual permanent solution, and any other Developer may propose a Gap Solution to address the Reliability Need. 6 In proposing a Gap Solution, Developer(s) must submit the information required in Section of Attachment Y and Attachment C of the RPP Manual. All Developers Gap Solution proposals must be submitted within thirty days of the NYISO s solicitation for solutions if the Reliability Need was identified as a result of a Generator Deactivation Assessment. 6 A Developer seeking to propose a transmission Gap solution must be determined to be qualified under Section of Attachment Y. NYISO Customer Support Page 4 of 5

5 In addition, if the NYISO determines that a Generator, which is in a Mothball Outage, an IIFO, or that has been mothballed under the pre-may 1, 2015 rules, may be capable of satisfying, in whole or in part, the identified Reliability Need, then the Generator will be notified that it is subject to review to assess whether it can satisfy the Reliability Need as a possible Gap Solution by providing service under an RMR agreement. Such a Generator shall provide the NYISO with the information required by Section of Attachment Y within twenty days of the issuance of the NYISO s notice. (6) RMR Agreements Pursuant to Sections and of Attachment Y, the NYISO may enter into an RMR Agreement with one or more Generators, if it determines such action is necessary to timely address a Reliability Need. The NYISO anticipates that the contents of this Technical Bulletin will be incorporated into the ICAPReliability Planning Process Manual during its next available recertification periodafter FERC rules on the NYISO s RMR Compliance Filing. NYISO Customer Support Page 5 of 5

Installed Capacity (ICAP) Market

Installed Capacity (ICAP) Market Installed Capacity (ICAP) Market Gina E. Craan Manager, Market Training, NYISO Market Overview Course September 13, 2018 Rensselaer, NY 12144 1 ICAP Market Module Objectives: Upon the completion of this

More information

Defining Generator Outage States DRAFT Tariff Proposed Amendments. Shaded material in blue text is updated since the 2/12/14 BIC.

Defining Generator Outage States DRAFT Tariff Proposed Amendments. Shaded material in blue text is updated since the 2/12/14 BIC. Defining Generator Outage States DRAFT Tariff Proposed Amendments Shaded material in blue text is updated since the 2/12/14 BIC. This version includes proposed amendments to Attachment H to the Services

More information

NYISO Posting for FERC Order 890 Describing the NYISO Planning Process

NYISO Posting for FERC Order 890 Describing the NYISO Planning Process NYISO Posting for FERC Order 890 Describing the NYISO Planning Process September 14, 2007 ` NYISO Posting for FERC Order 890 Filing DRAFT Table of Contents Section: Page No: I. Cover Memo - Draft OATT

More information

5.14 Installed Capacity Spot Market Auction and Installed Capacity Supplier Deficiencies LSE Participation in the ICAP Spot Market Auction

5.14 Installed Capacity Spot Market Auction and Installed Capacity Supplier Deficiencies LSE Participation in the ICAP Spot Market Auction 5.14 Installed Capacity Spot Market Auction and Installed Capacity Supplier Deficiencies 5.14.1 LSE Participation in the ICAP Spot Market Auction 5.14.1.1 ICAP Spot Market Auction When the ISO conducts

More information

Installed Capacity (ICAP) Market Introduction

Installed Capacity (ICAP) Market Introduction Installed Capacity (ICAP) Market Introduction Nicolé K. Grottoli Senior Market Trainer, NYISO Intermediate ICAP Course November 7-8, 2017 Rensselaer, NY 1 ICAP Market Introduction Module Objectives Upon

More information

1. MARS Base Case Model Assumptions

1. MARS Base Case Model Assumptions 1. MARS Base Case Model Assumptions 1.1 Load s Peak Load Load Shape Load Forecast Uncertainty 2014 IRM Model Assumptions October 1, 2013 forecast NYCA: 33,655 MW NYC: 11,740 MW Long Island 5,461 MW Multiple

More information

Installed Capacity (ICAP) Market

Installed Capacity (ICAP) Market Installed Capacity (ICAP) Market Amanda Carney Associate Market Design Specialist, Capacity Market Design, NYISO New York Market Orientation Course (NYMOC) October 16-19, 2018 Rensselaer, NY 1 ICAP Market

More information

NYISO 2016 Annual Report on Demand Response Programs

NYISO 2016 Annual Report on Demand Response Programs NYISO 2016 Annual Report on Demand Response Programs I. Program Descriptions The New York Independent System Operator, Inc. ( NYISO ) administers four demand response programs for the dual purposes of

More information

The cost allocation principles and methodologies in this Attachment Y cover only

The cost allocation principles and methodologies in this Attachment Y cover only 31.5 Cost Allocation and Cost Recovery 31.5.1 The Scope of Attachment Y Cost Allocation 31.5.1.1 Regulated Responses The cost allocation principles and methodologies in this Attachment Y cover only regulated

More information

BSM Enhancements. Lorenzo Seirup Supervisor, ICAP Market Mitigation & Analysis. Jonathan Newton Analyst, ICAP Market Mitigation & Analysis

BSM Enhancements. Lorenzo Seirup Supervisor, ICAP Market Mitigation & Analysis. Jonathan Newton Analyst, ICAP Market Mitigation & Analysis BSM Enhancements Lorenzo Seirup Supervisor, ICAP Market Mitigation & Analysis Jonathan Newton Analyst, ICAP Market Mitigation & Analysis Management Committee May 31, 2017, Rensselaer NY Agenda Introduction

More information

15.4 Rate Schedule 4 - Payments for Supplying Operating Reserves

15.4 Rate Schedule 4 - Payments for Supplying Operating Reserves 15.4 Rate Schedule 4 - Payments for Supplying Operating Reserves This Rate Schedule applies to payments to Suppliers that provide Operating Reserves to the ISO. Transmission Customers will purchase Operating

More information

Enhancements to Bidding Requirement

Enhancements to Bidding Requirement ICAP Spot Market Auction Enhancements to Bidding Requirement Sheri Prevratil Manager, Corporate Credit New York Independent System Operator Credit Policy Working Group March 16, 2012 KCC Conference Center

More information

Assumption Matrix. Electric System Planning Working Group April 5, 2012 Rensselaer, N.Y.

Assumption Matrix. Electric System Planning Working Group April 5, 2012 Rensselaer, N.Y. 2012 RNA Assumption Matrix Howard Tarler Manager, Long Term Planning New York Independent System Operator Electric System Planning Working Group April 5, 2012 Rensselaer, N.Y. 2012 New York Independent

More information

Enhancements to Bidding Requirement

Enhancements to Bidding Requirement ICAP Spot Market Auction Enhancements to Bidding Requirement Sheri Prevratil Manager, Corporate Credit New York Independent System Operator Credit Policy Working Group May 14, 2012 Rensselaer, NY 2012

More information

NYISO Economic Planning Process

NYISO Economic Planning Process NYISO Economic Planning Process Bryan J. Ray Market Training Group New York Independent System Operator NYISO Economic Planning Process Course October 2010 Rensselaer, NY The Roles of the NYISO Reliable

More information

Smart Grid Small Generator Interconnection Procedures for New Distributed Resources 20 MW or Less Connected in Parallel with LIPA Distribution Systems

Smart Grid Small Generator Interconnection Procedures for New Distributed Resources 20 MW or Less Connected in Parallel with LIPA Distribution Systems Smart Grid Small Generator Interconnection Procedures for New Distributed Resources 20 MW or Less Connected in Parallel with LIPA Distribution Systems -1- TABLE OF CONTENTS Section I. Application Process..

More information

Gray proposed revisions for CEE, Renewable Generator Exemption, Municipal Utilities Exemption

Gray proposed revisions for CEE, Renewable Generator Exemption, Municipal Utilities Exemption Yellow pending revisions filed 8/6/12 in ER12-2414-000 [Compliance revisions filed in response to Commission Order 139 FERC 61,244 (2012) in Docket EL11-42] Green pending revisions filed 10/11/12 in ER13-102-000

More information

CTS-New England Overview

CTS-New England Overview CTS-New England Overview William Porter Senior Market Trainer, NYISO Cheryl Mendrala Principal Engineer, ISO-NE 2000-2015 New York Independent System Operator, Inc. All Rights Reserved. DRAFT FOR DISCUSSION

More information

First Revision of Sheet No P.S.C.U. No. 50 Canceling Original Sheet No ROCKY MOUNTAIN POWER ELECTRIC SERVICE SCHEDULE NO.

First Revision of Sheet No P.S.C.U. No. 50 Canceling Original Sheet No ROCKY MOUNTAIN POWER ELECTRIC SERVICE SCHEDULE NO. First Revision of Sheet No. 38.1 P.S.C.U. No. 50 Canceling Original Sheet No. 38.1 ROCKY MOUNTAIN POWER ELECTRIC SERVICE SCHEDULE NO. 38 STATE OF UTAH Qualifying Facility Procedures PREFACE: 1. The process

More information

Qualifying Facility Avoided Cost Procedures

Qualifying Facility Avoided Cost Procedures I.P.U.C. No. 1 Original Sheet No. 38.1 ROCKY MOUNTAIN POWER ELECTRIC SERVICE SCHEDULE NO. 38 STATE OF IDAHO Qualifying Facility Avoided Cost Procedures PREFACE: 1. The process outlined in this Schedule

More information

TECHNICAL BULLETIN 27

TECHNICAL BULLETIN 27 NEW YORK INDEPENDENT SYSTEM OPERATOR TECHNICAL BULLETIN 27 12/19/2006; recertified 12/21/10, revised 7/5/11,10/19/2011,06/18/2012, mm/dd/2014 Subject: NERC E-Tags convey transaction details to Balancing

More information

Market Monitoring, Mitigation & Analysis

Market Monitoring, Mitigation & Analysis Market Monitoring, Mitigation & Analysis Ken Galarneau Supervisor, Mitigation Performance & Analysis New York Independent System Operator New York Market Orientation Course (NYMOC) October 19, 2017 Rensselaer,

More information

NYISO Administered ICAP Market Auctions

NYISO Administered ICAP Market Auctions NYISO Administered ICAP Market Auctions Mathangi Srinivasan Senior Market Trainer, NYISO Intermediate ICAP Course November 7-8, 2017 Rensselaer, NY 12144 1 Module Objectives At the conclusion of this module,

More information

Long Island Power Authority Fifth Revised Leaf No. 280 PSEG LONG ISLAND LONG ISLAND CHOICE PROGRAM TARIFF LEAVES

Long Island Power Authority Fifth Revised Leaf No. 280 PSEG LONG ISLAND LONG ISLAND CHOICE PROGRAM TARIFF LEAVES Long Island Power Authority Fifth Revised Leaf No. 280 PSEG LONG ISLAND LONG ISLAND CHOICE PROGRAM TARIFF LEAVES Long Island Power Authority Fifth Revised Leaf No. 280 IX. LONG ISLAND CHOICE PROGRAM TABLE

More information

AC TRANSMISSION PUBLIC POLICY TRANSMISSION NEEDS PROJECT SOLICITATION Response due April 29, 2016

AC TRANSMISSION PUBLIC POLICY TRANSMISSION NEEDS PROJECT SOLICITATION Response due April 29, 2016 10 Krey Boulevard Rensselaer, NY 12144 AC TRANSMISSION PUBLIC POLICY TRANSMISSION NEEDS PROJECT SOLICITATION Response due April 29, 2016 Dear NYISO Stakeholder or Interested Party: February 29, 2016 With

More information

Default Reference Price Reports / Buyer-Side Mitigation Processes (other than SCRs)

Default Reference Price Reports / Buyer-Side Mitigation Processes (other than SCRs) Default Reference Price Reports / Buyer-Side Mitigation Processes (other than SCRs) Dave Lawrence Manager, Auxiliary Market Products Esat Serhat Guney Senior Economist, Market Analysis and Mitigation New

More information

NYISO Technical Bulletins A list of retired TBs with links is at the link below

NYISO Technical Bulletins A list of retired TBs with links is at the link below NEW YORK INDEPENDENT SYSTEM OPERATOR NYISO Technical Bulletins A list of retired TBs with links is at the link below date of this document = 5/27/2011; most recent changes have dates in red TB # Version

More information

FERC Order 1000: Planning for the Right of First Refusal and Planning for Public Policy Status & Implementation in New York

FERC Order 1000: Planning for the Right of First Refusal and Planning for Public Policy Status & Implementation in New York 1 FERC Order 1000: Planning for the Right of First Refusal and Planning for Public Policy Status & Implementation in New York Henry Chao Vice President - System and Resource Planning New York Independent

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 43. Capacity Procurement Mechanism... 2 43.1 Applicability... 2 43.2 Capacity Procurement Mechanism Designation... 2 43.2.1 SC Failure to Show Sufficient Local Capacity Area Resource...

More information

PART 5 OPERATING PROCEDURES

PART 5 OPERATING PROCEDURES PART 5 OPERATING PROCEDURES LONG ISLAND CHOICE OPERATING PROCEDURES TABLE OF CONTENTS 1.0 INTRODUCTION...1 1.1 Purpose...1 1.2 Incorporation by Reference...1 2.0 DEFINITIONS...3 2.1 Authority...3 2.2 Bundled

More information

Assessment of the Buyer-Side Mitigation Exemption Test for the Hudson Transmission Partners Project

Assessment of the Buyer-Side Mitigation Exemption Test for the Hudson Transmission Partners Project Assessment of the Buyer-Side Mitigation Exemption Test for the Hudson Transmission Partners Project by: Potomac Economics, Ltd. November 6, 2012, revised January 16, 2014 revised February 21, 2014 Table

More information

Smart Grid Small Generator Interconnection Procedures For Distributed Generators Less than 10 MW Connected in Parallel with LIPA s Radial

Smart Grid Small Generator Interconnection Procedures For Distributed Generators Less than 10 MW Connected in Parallel with LIPA s Radial Smart Grid Small Generator Interconnection Procedures For Distributed Generators Less than 10 MW Connected in Parallel with LIPA s Radial Distribution Systems Revised January 1, 2017 TABLE OF CONTENTS

More information

Planning in a competitive market environment

Planning in a competitive market environment Planning in a competitive market environment The New York Story Rana Mukerji Senior Vice President - Market Structures New York Independent System Operator Harvard Electricity Policy Group 74 th Plenary

More information

Assessment of the Buyer-Side Mitigation Exemption Test for the Hudson Transmission Partners Project

Assessment of the Buyer-Side Mitigation Exemption Test for the Hudson Transmission Partners Project Assessment of the Buyer-Side Mitigation Exemption Test for the Hudson Transmission Partners Project by: Potomac Economics, Ltd. November 6, 2012 Table of Contents I. Introduction and Summary... 2 II. Part

More information

TRANSMISSION OWNER ZONAL PLACEMENT PROCESS

TRANSMISSION OWNER ZONAL PLACEMENT PROCESS TRANSMISSION OWNER ZONAL PLACEMENT PROCESS Published July 2017 CONTENTS Section 1: Introduction, Scope & Steps... 1 Subsection A: Introduction To Zonal Placement... 1 Subsection B: Scope... 1 Subsection

More information

California Independent System Operator Corporation Fifth Replacement Tariff. Appendix H. Grandfathered Metering & Settlement Provisions

California Independent System Operator Corporation Fifth Replacement Tariff. Appendix H. Grandfathered Metering & Settlement Provisions Grandfathered Metering & Settlement Provisions FOR TRADING DAYS PRIOR TO NOVEMBER 1, 2009 1. Grandfathering of Metering and Settlement Provisions for Trading Days Prior to November 1, 2009. Notwithstanding

More information

Historic Fixed Price TCC Extensions

Historic Fixed Price TCC Extensions Historic Fixed Price TCC Extensions Gregory R. Williams MANAGER, TCC MARKET OPERATIONS Business Issues Committee Meeting June 20, 2018, Rensselaer, NY Agenda Historic Fixed Price TCC (HFPTCC) Overview

More information

ISO Rules Part 300 System Reliability and Operations Division 306 Outages and Disturbances Section Generation Outage Reporting and Coordination

ISO Rules Part 300 System Reliability and Operations Division 306 Outages and Disturbances Section Generation Outage Reporting and Coordination Applicability 1 Section 306.5 applies to: (a) a pool participant with a generating source asset with a maximum capability of five (5) MW or higher; (b) a legal owner of a source asset described in subsection

More information

LONG ISLAND POWER AUTHORITY

LONG ISLAND POWER AUTHORITY LONG ISLAND POWER AUTHORITY TARIFF FOR ELECTRIC SERVICE Applicable in Fifth Ward, Borough of Queens, City of New York, and Cities, Towns and Villages in Nassau and Suffolk Counties, State of New York Effective

More information

Proposal Concerning Modification to Smart Grid Small Generator Interconnection Procedures Appended to LIPA s Tariff for Electric Service

Proposal Concerning Modification to Smart Grid Small Generator Interconnection Procedures Appended to LIPA s Tariff for Electric Service Proposal Concerning Modification to Smart Grid Small Generator Interconnection Procedures Appended to LIPA s Tariff for Electric Service Requested Action: The Long Island Power Authority ( LIPA or the

More information

7.3 Auction Procedures Role of the Office of the Interconnection.

7.3 Auction Procedures Role of the Office of the Interconnection. 7.3 Auction Procedures. 7.3.1 Role of the Office of the Interconnection. Financial Transmission Rights auctions shall be conducted by the Office of the Interconnection in accordance with standards and

More information

new. york. independent. system. operator

new. york. independent. system. operator new. york. independent. system. operator nyiso Day-Ahead Demand Response Program Manual revised: 05. 1821. 2001 1 nyiso Day-Ahead Demand Reduction Program Manual (Rev. 5/1821/2001) 1.0 Definitions and

More information

Stakeholder Comments Template

Stakeholder Comments Template Stakeholder Comments Template Submitted by Company Date Submitted Xian Ming Cindy Li Patrick Cunningham Patrick.cunningham@cpuc.ca.gov 415-703-1993 Public Advocates Office California Public Utilities Commission

More information

NYISO 2009 Comprehensive Reliability Plan (CRP)

NYISO 2009 Comprehensive Reliability Plan (CRP) NYISO 2009 Comprehensive Reliability Plan (CRP) John P. Buechler NYISO Executive Regulatory Policy Advisor NPCC Governmental & Regulatory Affairs Advisory Group Meeting May 21, 2009 NYC Overview: 2009

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 36. Congestion Revenue Rights... 3 36.1 Overview Of CRRs And Procurement Of CRRs... 3 36.2 Types Of CRR Instruments... 3 36.2.1 CRR Obligations... 3 36.2.2 CRR Options... 3 36.2.3 Point-To-Point

More information

Operating Agreement Redlines

Operating Agreement Redlines Option J1 Proposed OA and OATT Revisions for FTR Defaults Operating Agreement Redlines OPERATING AGREEMENT, SCHEDULE 1 PJM INTERCHANGE ENERGY MARKET 7.3 Auction Procedures. 7.3.1 Role of the Office of

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: June 14, 2018 Re: Decision on congestion

More information

Emergency Demand Response Program Manual

Emergency Demand Response Program Manual MANUAL 7 Emergency Demand Response Program Manual December 2010 Version: 6.2 Revision Date: 12/02/2010 Committee Acceptance: mm/dd/2010 Recertification Date: 05/05/2010 This document was prepared by: NYISO

More information

Overview of the New ICAP In-City Mitigation Rules

Overview of the New ICAP In-City Mitigation Rules Overview of the New ICAP In-City Mitigation Rules New York Independent System Operator NYISO Market Participant Training April 10, 11 & 15, 2008 DRAFT for Discussion Purposes Only Training Session Overview

More information

BUYER SIDE MITIGATION NARRATIVE AND NUMERICAL EXAMPLE

BUYER SIDE MITIGATION NARRATIVE AND NUMERICAL EXAMPLE BUYER SIDE MITIGATION NARRATIVE AND NUMERICAL EXAMPLE NEW YORK INDEPENDENT SYSTEM OPERATOR MARKET MITIGATION AND ANALYSIS ISSUED: AUGUST 7, 2012 UPDATED: MARCH 29, 2013 UPDATED: SEPTEMBER 3, 2013 MARCH

More information

Short Term Improvements to Transmission Planning Processes

Short Term Improvements to Transmission Planning Processes Short Term Improvements to Transmission Planning Processes Yachi Lin Senior Manager, Transmission Planning ESPWG April 30, 2018 Agenda Background Objectives Issues to be Addressed in 2018 Tariff Amendments

More information

Bidding Rules for the Auctions Under the Competitive Bidding Process of Ohio Power Company

Bidding Rules for the Auctions Under the Competitive Bidding Process of Ohio Power Company Bidding Rules for the Auctions Under the Competitive Bidding Process of Ohio Power Company CBP Rules Contents Contents Contents... i ARTICLE I. Introduction...1 I.1. Background...1 I.2. Overview...1 ARTICLE

More information

New York Independent System Operator. Billing Cycle Assessment. Report to. Regarding. March 15, 2004

New York Independent System Operator. Billing Cycle Assessment. Report to. Regarding. March 15, 2004 Report to New York Independent System Operator Regarding March 15, 2004 Disclaimer: This report was prepared by R. J. Rudden Associates at the request of the NYISO. Notwithstanding anything stated in the

More information

Attachment G. Glossary for Duke Energy Ohio, Inc. s Competitive Bidding Process Auctions

Attachment G. Glossary for Duke Energy Ohio, Inc. s Competitive Bidding Process Auctions Attachment G Glossary for Duke Energy Ohio, Inc. s Competitive Bidding Process Auctions GLOSSARY In the event of a conflict between this Glossary and the Master SSO Supply Agreement with respect to the

More information

Manual 05. NYISO Day-Ahead Demand Response Program Manual

Manual 05. NYISO Day-Ahead Demand Response Program Manual Manual 05 NYISO Day-Ahead Demand Response Program Manual Issued: December, 2018 Version: 4.0 Effective Date: 12/03/2018 Committee Acceptance: 11/14/2018 BIC Prepared by: NYISO Distributed Resources Operations

More information

UNITED STATES OF AMERICA 96 FERC 61,147 FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA 96 FERC 61,147 FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA 96 FERC 61,147 FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Curt Hébert, Jr., Chairman; William L. Massey, Linda Breathitt, Pat Wood, III and Nora Mead Brownell.

More information

(Blackline) VOLUME NO. III Page No. 878 SCHEDULING PROTOCOL

(Blackline) VOLUME NO. III Page No. 878 SCHEDULING PROTOCOL VOLUME NO. III Page No. 878 SCHEDULING PROTOCOL VOLUME NO. III Page No. 879 SCHEDULING PROTOCOL Table of Contents SP 1 SP 1.1 OBJECTIVES, DEFINITIONS AND SCOPE Objectives SP 1.2 Definitions SP 1.2.1 Master

More information

Two-Tier Allocation of Bid Cost Recovery

Two-Tier Allocation of Bid Cost Recovery Two-Tier Allocation of Bid Cost Recovery Jordan Curry Market Design & Regulatory Policy Developer December 21, 2015 Agenda Time Topic Presenter 1:00 1:05 Introduction Kim Perez 1:05 2:00 Purpose and Background

More information

Transmission Congestion Contracts (TCCs) Provide Transmission Price Certainty

Transmission Congestion Contracts (TCCs) Provide Transmission Price Certainty Transmission Congestion Contracts (TCCs) Provide Transmission Price Certainty Arthur L. Desell Manager Resource Reliability New York Power Pool 1999 PICA Conference Santa Clara May 20, 1999 Locational

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents Appendix F Rate Schedules... 2 Schedule 1... 2 Grid Management Charge... 2 Part A Monthly Calculation of Grid Management Charge (GMC)... 2 Part B Quarterly Adjustment, If Required...

More information

Delisting: Exit of capacity resources from the market. Eligibility WG October 24, 2017

Delisting: Exit of capacity resources from the market. Eligibility WG October 24, 2017 Delisting: Exit of capacity resources from the market Eligibility WG October 24, 2017 Overview SAM3.0: Directional Indication - How will the capacity market manage the exit of capacity resources? Overview

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 43A. Capacity Procurement Mechanism... 2 43A.1 Applicability... 2 43A.2 Capacity Procurement Mechanism Designation... 2 43A.2.1 SC Failure to Show Sufficient Local Capacity Area Resources...

More information

5.2 Transmission Congestion Credit Calculation Eligibility.

5.2 Transmission Congestion Credit Calculation Eligibility. 5.2 Transmission Congestion Credit Calculation. 5.2.1 Eligibility. (a) Except as provided in Section 5.2.1(b), each FTR Holder shall receive as a Transmission Congestion Credit a proportional share of

More information

9. RELATIONSHIP BETWEEN ISO AND PARTICIPATING TOs. Each Participating TO shall enter into a Transmission Control Agreement with the

9. RELATIONSHIP BETWEEN ISO AND PARTICIPATING TOs. Each Participating TO shall enter into a Transmission Control Agreement with the First Revised Sheet No. 121 ORIGINAL VOLUME NO. I Replacing Original Sheet No. 121 9. RELATIONSHIP BETWEEN ISO AND PARTICIPATING TOs. 9.1 Nature of Relationship. Each Participating TO shall enter into

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) California Independent System ) Docket Nos. ER06-615-000 Operator Corporation ) ER07-613-000 ) ) (not consolidated) ) STATUS REPORT

More information

FERC Order 741-A: Credit Reforms in Organized Wholesale Electric Markets Update

FERC Order 741-A: Credit Reforms in Organized Wholesale Electric Markets Update FERC Order 741-A: Credit Reforms in Organized Wholesale Electric Markets Update Sheri Prevratil Manager, Corporate Credit New York Independent System Operator Credit Policy Working Group July 22, 2011

More information

MEMORANDUM The FERC Order on Proposed Changes to ISO-NE s Forward Capacity Market

MEMORANDUM The FERC Order on Proposed Changes to ISO-NE s Forward Capacity Market MEMORANDUM The FERC Order on Proposed Changes to ISO-NE s Forward Capacity Market The Federal Energy Regulatory Commission s April 13, 2011 Order is a culmination of the paper hearing on proposed changes

More information

EIPC Roll-Up Report & Scenarios

EIPC Roll-Up Report & Scenarios EIPC Roll-Up Report & Scenarios Zach Smith Director, Transmission Planning New York Independent System Operator IPTF/EGCWG/ESPWG Meeting January 6, 2014 2013 New York Independent System Operator, Inc.

More information

RENEWABLE MARKET ADJUSTING TARIFF POWER PURCHASE AGREEMENT

RENEWABLE MARKET ADJUSTING TARIFF POWER PURCHASE AGREEMENT [This contract has been approved by the California Public Utilities Commission in Decision 13-05-034. Modification of the terms and conditions of this contract will result in the need to obtain additional

More information

REQUEST FOR PROPOSALS FOR LONG-TERM CONTRACTS FOR RENEWABLE ENERGY PROJECTS

REQUEST FOR PROPOSALS FOR LONG-TERM CONTRACTS FOR RENEWABLE ENERGY PROJECTS REQUEST FOR PROPOSALS FOR LONG-TERM CONTRACTS FOR RENEWABLE ENERGY PROJECTS Issuance Date: July 1, 2013 The Narragansett Electric Company d/b/a National Grid i Table of Contents I. Introduction and Overview...1

More information

ICAP Demand Curve. Zachary T. Smith Supervisor, ICAP Market Operations, NYISO. Intermediate ICAP Course. November 7-8, 2017 Rensselaer, NY 12144

ICAP Demand Curve. Zachary T. Smith Supervisor, ICAP Market Operations, NYISO. Intermediate ICAP Course. November 7-8, 2017 Rensselaer, NY 12144 ICAP Demand Curve Zachary T. Smith Supervisor, ICAP Market Operations, NYISO Intermediate ICAP Course November 7-8, 2017 Rensselaer, NY 12144 1 Objectives Upon the completion of this module, trainees should

More information

ROCKLAND ELECTRIC COMPANY PROPOSAL FOR BASIC GENERATION SERVICE REQUIREMENTS TO BE PROCURED EFFECTIVE JUNE 1, 2018

ROCKLAND ELECTRIC COMPANY PROPOSAL FOR BASIC GENERATION SERVICE REQUIREMENTS TO BE PROCURED EFFECTIVE JUNE 1, 2018 STATE OF NEW JERSEY BOARD OF PUBLIC UTILITIES IN THE MATTER OF THE PROVISION OF BASIC GENERATION SERVICE FOR THE PERIOD BEGINNING JUNE 1, 2018 Docket No. ER17040335 ROCKLAND ELECTRIC COMPANY PROPOSAL FOR

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. ) ISO New England Inc. ) Docket No. ER )

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. ) ISO New England Inc. ) Docket No. ER ) UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ISO New England Inc. ) Docket No. ER19-291-000 ) LIMITED PROTEST OF THE NEW ENGLAND STATES COMMITTEE ON ELECTRICITY Pursuant to

More information

Transmission Congestion Contacts

Transmission Congestion Contacts Transmission Congestion Contacts Horace Horton Senior Market Trainer, Market Training, NYISO New York Market Orientation Course (NYMOC) March 20-23, 2018 Rensselaer, NY 12144 1 Transmission Congestion

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 39. Market Power Mitigation Procedures... 2 39.1 Intent Of CAISO Mitigation Measures; Additional FERC Filings... 2 39.2 Conditions For The Imposition Of Mitigation Measures... 2 39.2.1

More information

150 FERC 61,116 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

150 FERC 61,116 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 150 FERC 61,116 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Cheryl A. LaFleur, Chairman; Philip D. Moeller, Tony Clark, Norman C. Bay, and Colette D. Honorable.

More information

165 FERC 61,140 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER ACCEPTING COMPLIANCE FILING SUBJECT TO CONDITION

165 FERC 61,140 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER ACCEPTING COMPLIANCE FILING SUBJECT TO CONDITION 165 FERC 61,140 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Neil Chatterjee, Chairman; Cheryl A. LaFleur and Richard Glick. California Independent System Operator

More information

LSE Perspective on FTR and ARR Surplus Funds. Jeff Whitehead Direct Energy

LSE Perspective on FTR and ARR Surplus Funds. Jeff Whitehead Direct Energy LSE Perspective on FTR and ARR Surplus Funds Jeff Whitehead Direct Energy Congestion Revenue Entitlement Transmission Customers paid and continue to pay the embedded cost of the transmission system Transmission

More information

SCHEDULE 72 INTERCONNECTIONS TO NON-UTILITY GENERATION

SCHEDULE 72 INTERCONNECTIONS TO NON-UTILITY GENERATION Idaho Power Company Second Revised Sheet No. 72-1 I.P.U.C. No. 29, Tariff No. 101 First Revised Sheet No. 72-1 PUBLIC UTILITIES COMMISSION AVAILABILITY Service under this schedule is available throughout

More information

BEFORE THE WYOMING PUBLIC SERVICE COMMISSION ROCKY MOUNTAIN POWER. Rebuttal Testimony of Joelle R. Steward

BEFORE THE WYOMING PUBLIC SERVICE COMMISSION ROCKY MOUNTAIN POWER. Rebuttal Testimony of Joelle R. Steward Docket No. 0000--ER-1 Witness: Joelle R. Steward BEFORE THE WYOMING PUBLIC SERVICE COMMISSION ROCKY MOUNTAIN POWER Rebuttal Testimony of Joelle R. Steward September 01 11 1 1 1 1 1 1 1 1 0 1 Q. Are you

More information

January 25, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.

January 25, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. California Independent System Operator Corporation January 25, 2008 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: One Hundred

More information

Organization of MISO States Response to the Midwest ISO October Hot Topic on Pricing

Organization of MISO States Response to the Midwest ISO October Hot Topic on Pricing Organization of MISO States Response to the Midwest ISO October Hot Topic on Pricing I. Day Ahead and Real Time Energy and Ancillary Services Pricing Prices that Accurately Reflect the Marginal Cost of

More information

Stakeholder Comments Template

Stakeholder Comments Template Stakeholder Comments Template Submitted by Company Date Submitted Jaime Rose Gannon jrg@cpuc.ca.gov 415-846-4365 California Public Utilities Commission 3/11/2019 Please use this template to provide your

More information

Capacity Procurement Mechanism Risk-of-Retirement Process Enhancements. Straw Proposal

Capacity Procurement Mechanism Risk-of-Retirement Process Enhancements. Straw Proposal Capacity Procurement Mechanism Risk-of-Retirement Process Enhancements June 20, 2017 Market & Infrastructure Policy Table of Contents 1. Executive Summary... 3 2. Plan for Stakeholder Engagement... 4 3.

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: March 14, 2018 Re: Decision on congestion

More information

IESO to NYISO Installed Capacity (ICAP) Memorandum of Understanding

IESO to NYISO Installed Capacity (ICAP) Memorandum of Understanding IESO to NYISO Installed Capacity (ICAP) Memorandum of Understanding THIS MEMORAUNDUM OF UNDERSTANDING ("MOU") is dated as of the 25th day of August, 2016 (the "Effective Date") between the Independent

More information

Business Practice Manual For. Generator Management. Version 76

Business Practice Manual For. Generator Management. Version 76 Business Practice Manual For Generator Management Version 76 Revision Date: April 30, 3015June 1, 2015 Approval History Approval Date: February, 2014 Effective Date: March, 2014 BPM Owner: Deb Le Vine

More information

Business Practice Manual For. Generator Management. Version 8

Business Practice Manual For. Generator Management. Version 8 Business Practice Manual For Generator Management Version 8 Revision Date: June 30, 2015 Approval History Approval Date: February, 2014 Effective Date: March, 2014 BPM Owner: Deb Le Vine BPM Owner s Title:

More information

5.2 Transmission Congestion Credit Calculation Eligibility.

5.2 Transmission Congestion Credit Calculation Eligibility. 5.2 Transmission Congestion culation. 5.2.1 Eligibility. (a) Except as provided in Section 5.2.1(b), each FTR Holder shall receive as a Transmission Congestion Credit a proportional share of the total

More information

The tariff leaves have an effective date of December 1, Background

The tariff leaves have an effective date of December 1, Background Orange and Rockland Utilities, Inc. 4 Irving Place New York NY 10003-0987 www.oru.com August 1, 2016 Honorable Kathleen H. Burgess Secretary State of New York Public Service Commission Three Empire State

More information

Capacity Procurement Mechanism Replacement. Second Revised Draft Straw Proposal

Capacity Procurement Mechanism Replacement. Second Revised Draft Straw Proposal Capacity Procurement Mechanism Replacement Second Revised Draft September 25, 2014 Table of Contents 1. Document change tracking... 4 2. Executive summary... 5 3. CPUC Joint Reliability Plan Proceeding...

More information

December 23, By etariff Filing Hon. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426

December 23, By etariff Filing Hon. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 December 23, 2014 By etariff Filing Hon. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 Re: Nevada Power Company and Sierra Pacific Power Company,

More information

Capacity Procurement Mechanism Risk-of-Retirement Process Enhancements. Issue Paper

Capacity Procurement Mechanism Risk-of-Retirement Process Enhancements. Issue Paper Capacity Procurement Mechanism Risk-of-Retirement Process Enhancements May 10, 2017 Market & Infrastructure Policy Table of Contents 1. Executive Summary... 3 2. Plan for Stakeholder Engagement... 3 3.

More information

ROCKLAND ELECTRIC COMPANY PROPOSAL FOR BASIC GENERATION SERVICE REQUIREMENTS TO BE PROCURED EFFECTIVE JUNE 1, 2016

ROCKLAND ELECTRIC COMPANY PROPOSAL FOR BASIC GENERATION SERVICE REQUIREMENTS TO BE PROCURED EFFECTIVE JUNE 1, 2016 STATE OF NEW JERSEY BOARD OF PUBLIC UTILITIES IN THE MATTER OF THE PROVISION OF BASIC GENERATION SERVICE FOR THE PERIOD BEGINNING JUNE 1, 2016 Docket No. ER15040482 ROCKLAND ELECTRIC COMPANY PROPOSAL FOR

More information

Congestion revenue rights auction efficiency

Congestion revenue rights auction efficiency Congestion revenue rights auction efficiency Track 1 draft final proposal Perry Servedio Sr. Market Design Policy Developer February 13, 2018 Three tracks for addressing auction efficiency Track 0: Process

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 39. Market Power Mitigation Procedures... 2 39.1 Intent Of CAISO Mitigation Measures; Additional FERC Filings... 2 39.2 Conditions For The Imposition Of Mitigation Measures... 2 39.2.1

More information

FERC Order 1000 Compliance Initiative. Straw Proposal (regional requirements), posted May 22, 2012

FERC Order 1000 Compliance Initiative. Straw Proposal (regional requirements), posted May 22, 2012 Stakeholder Comments Template FERC Order 1000 Compliance Initiative Straw Proposal (regional requirements), posted May 22, 2012 Please submit comments (in MS Word) to fo1k@caiso.com no later than the close

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 33 Hour-Ahead Scheduling Process (HASP)... 2 33.1 Submission Of Bids For The HASP And RTM... 2 33.2 The HASP Optimization... 3 33.3 Treatment Of Self-Schedules In HASP... 3 33.4 MPM For

More information

83C Questions and Answers

83C Questions and Answers 83C Questions and Answers (2) Section 1.7.4.1 Can the Evaluation Team provide guidance on the scope and amount of information that could be requested from ISO-NE, and the expected magnitude of any associated

More information

We Energies. Request for Proposal Renewable Energy Supply 2014

We Energies. Request for Proposal Renewable Energy Supply 2014 We Energies Request for Proposal Renewable Energy Supply 2014 Page 2 of 12 I. Introduction A. Summary of Request for Proposals Wisconsin Electric Power Company (We Energies) requests proposals (Proposals)

More information