JORDAN DOWNS SPECIFIC PLAN DRAFT ENVIRONMENTAL IMPACT REPORT

Size: px
Start display at page:

Download "JORDAN DOWNS SPECIFIC PLAN DRAFT ENVIRONMENTAL IMPACT REPORT"

Transcription

1

2 JORDAN DOWNS SPECIFIC PLAN DRAFT ENVIRONMENTAL IMPACT REPORT STATE CLEARINGHOUSE NO ENVIRONMENTAL CASE NO. ENV EIR Prepared for CITY OF LOS ANGELES Department of City Planning Environmental Review Section 200 North Spring Street, Room 750 Los Angeles, California Prepared by TERRY A. HAYES ASSOCIATES INC National Boulevard, Suite 102 Culver City, CA November 18, 2010

3 TABLE OF CONTENTS I. EXECUTIVE SUMMARY... I-1 A Purpose of this Report...I-1 B Lead Agency...I-2 C Responsible Agencies...I-2 D Public Review and Comments...I-2 E Summary of the Proposed Project...I-3 F Summary of Potential Environmental Impacts...I-4 G Unavoidable Significant Adverse Impacts...I-36 H Summary of Alternatives...I-37 II. III. IV. PROJECT DESCRIPTION... II-1 A Introduction... II-1 B Project Objectives... II-1 C Project Location and Surrounding Uses... II-3 D Project Description... II-3 E Implementation of the Specific Plan... II-10 F Human Capital Plan... II-22 G Sustainability... II-23 H Construction Schedule and Phasing... II-24 I Required Discretionary Approvals... II-27 ENVIRONMENTAL SETTING...III-1 A Overview of Environmental Setting... III-1 B Related Projects... III-5 ENVIRONMENTAL IMPACTS... IV-1 A Aesthetics... IV.A-1 B Agricultural Resources... IV.B-1 C Air Quality... IV.C-1 D Biological Resources... IV.D-1 E Cultural Resources... IV.E-1 F Energy... IV.F-1 G Geology and Soils... IV.G-1 H Hazards and Hazardous Materials... IV.H-1 I Hydrology and Water Quality... IV.I-1 J Land Use and Planning... IV.J-1 K Mineral Resources... IV.K-1 L Noise and Vibration... IV.L-1 M Population, Housing, and Employment... IV.M-1 N Public Services... IV.N-1 O Recreation... IV.O-1 P Traffic and Transportation... IV.P-1 Q Utilities and Service Systems... IV.Q-1 i

4 TABLE OF CONTENTS (CONTINUED) V. ALTERNATIVES... V-1 A Introduction... V-1 B Project-Level Impacts... V-1 C Alternatives to the Proposed Project... V-3 D Analysis of Alternative 1 No Project Alternative... V-12 E Analysis of Alternative 2 Reduced Annexation Area Alternative... V-15 F Analysis of Alternative 3 Reduced Height Alternative... V-21 G Analysis of Alternative 4 Industrial Zone Alternative... V-25 H Environmentally Superior Alternative... V-26 VI. OTHER MANDATORY CEQA SECTIONS... V1-1 A Unavoidable and Significant Impacts... VI-1 B Reasons Why the Project is Being Proposed, Notwithstanding... VI-2 C Irreversible Adverse Environmental Changes... VI-3 D Growth-Inducing Impacts... VI-3 E Potential Secondary Effects... VI-3 F Effects Determined Not to be Significant... VI-4 VII. PERSONS AND RESOURCES CONSULTED... VII-1 APPENDICES (UNDER SEPARATE COVER) Appendix A Appendix B Appendix C Appendix D Appendix E Appendix F Appendix G Notice of Preparation and Comment Letters Air Quality Data Phase I and II Environmental Site Assessments Civil Engineering Report Noise Data Traffic Impact Study Water Supply Assessment ii

5 LIST OF FIGURES Figure II-1 Regional Location... II-4 Figure II-2 Specific Plan Area and Annexation Area... II-5 Figure II-3 Proposed Zoning Designations... II-6 Figure II-4 Proposed Building Heights... II-8 Figure II-5 Density... II-9 Figure II-6 Key Map... II-13 Figure II-7 Illustrative Site Plan... II-15 Figure II-8 Representative Residential Building Types... II-16 Figure II-9 Illustrative View of Proposed Central Park... II-19 Figure II-10 Illustrative View of Extension of Century Boulevard... II-21 Figure II-11 Construction Phase 1 and 2... II-25 Figure II-12 Construction Phase 3 and 4... II-26 Figure III-1 Aerial Photograph... III-2 Figure III-2 Jordan Downs Public Housing Complex Photographs... III-4 Figure III-3 Jordan Downs Recreation Center, Mudtown Farms, and David StarrJordan High School Photographs... III-6 Figure III-4 Annexation Area Photographs... III-7 Figure III-5 Related Projects... III-9 Figure IV.A-1 Aerial Photograph and Visual Context... IV.A-3 Figure IV.A-2 Front View of Typical Housing Units at the Jordan Downs Public Housing Complex... IV.A-4 Figure IV.A-3 Rear View of Typical Housing Units at the Jordan Downs Public Housing Complex... IV.A-5 Figure IV.A-4 Views of existing Open Space within the Specific Plan Area... IV.A-6 Figure IV.A-5 View of David Starr Jordan High School Buildings... IV.A-7 Figure IV.A-6 View of Private and HACLA-owned Properties in the Jordan Downs Annexation Area... IV.A-9 Figure IV.A-7 View of Typical Single Family Neighborhood Adjacent to the Specific Plan Area... IV.A-11 Figure IV.A-8 View Looking North and South from the Specific Plan Area... IV.A-12 Figure IV.A-9 Proposed Building Configurations and Scale... IV.A-20 Figure IV.A-10 Building Massing Along 97 th and Grape Streets... IV.A-21 Figure IV.A th Street Cross-Section... IV.A-22 Figure IV.A-12 Summer Solstice Shadows... IV.A-25 Figure IV.A-13 Winter Solstice Shadows... IV.A-26 Figure IV.A-14 Spring-Fall Equinox Shadows... IV.A-27 Figure IV.C-1 Air Monitoring Areas... IV.C-5 Figure IV.C-2 Air Quality Sensitive Receptor Locations... IV.C-7 Figure IV.C-3 South Coast Air Basin... IV.C-12 Figure IV.D-1 Existing Trees and Landscaping... IV.D-2 Figure IV.E-1 David Starr Jordan High School... IV.E-4 Figure IV.G-1 Active Faults... IV.G-3 Figure IV.H-1 Specific Plan Area Properties... IV.H-4 Figure IV.H-2 Residential Metals Diagram... IV.H-7 Figure IV.H-3 Commercial Metals Diagram... IV.H-8 Figure IV.H-4 Extractable Hydrocarbon Plan LAFD Residential Screening Level... IV.H-10 iii

6 LIST OF FIGURES (CONTINUED) Figure IV.H-5 Extractable Hydrocarbon Plan LARWQCB Soil Screening Level... IV.H-11 Figure IV.I-1 Existing Underground Box Culvert... IV.I-4 Figure IV.J-1 Land Use Overview... IV.J-2 Figure IV.J-2 Street-Level Views of Specific Plan Area 1... IV.J-3 Figure IV.J-3 Street-Level Views of Specific Plan Area 2... IV.J-4 Figure IV.J-4 Existing Land Uses... IV.J-7 Figure IV.J-5 Existing General Plan Land Use and Zoning Designations... IV.J-8 Figure IV.J-6 Proposed Site Plan... IV.J-16 Figure IV.J-7 Proposed Land Use and Zoning Designations... IV.J-18 Figure IV.J-8 Key Map... IV.J-19 Figure IV.J-9 Non-conforming Uses with Proposed Zoning Designations... IV.J-33 Figure IV.L-1 A-Weighted Decibel Scale... IV.L-2 Figure IV.L-2 Noise Monitoring Locations... IV.L-4 Figure IV.L-3 Noise Sensitive Receptor Locations... IV.L-6 Figure IV.N-1 Fire Stations and Police Stations... IV.N-2 Figure IV.N-2 Fire Hydrants Serving the Specific Plan Area... IV.N-6 Figure IV.N-3 LAPD Video Monitoring Infrastructure... IV.N-10 Figure IV.N-4 Security Lighting... IV.N-11 Figure IV.N-5 Public Schools and Libraries... IV.N-13 Figure IV.O-1 Parks and Recreational Facilities... IV.O-2 Figure IV.P-1 Existing Roadways and Study Intersections... IV.P-2 Figure IV.P-2 Existing Peak Hour Volumes for Study Intersections Numbers 1 to IV.P-7 Figure IV.P-3 Existing Peak Hour Volumes for Study Intersections Numbers 21 to IV.P-8 Figure IV.P-4 Existing Transit Service... IV.P-10 Figure IV.P-5 Related Projects... IV.P-20 Figure IV.P-6 Scenario 1 Peak Hour Volumes for Study Intersections Numbers 1 to IV.P-23 Figure IV.P-7 Scenario 1 Peak Hour Volumes for Study Intersections Numbers 21 to IV.P-24 Figure IV.P-8 Existing and Proposed Lane Configurations... IV.P-26 Figure IV.P-9 Scenario 2 Peak Hour Volumes for Study Intersections Numbers 1 to IV.P-27 Figure IV.P-10 Scenario 2 Peak Hour Volumes for Study Intersections Numbers 21 to IV.P-28 Figure V-1 Alternative 2 Reduced Annexation Area Alternative... V-5 Figure V-2 Alternative 3 Reduced Height Alternative... V-6 Figure V-3 Alternative 4 Industrial Zone Alternative... V-7 iv

7 LIST OF TABLES Table I-1 Specific Plan Program Summary...I-5 Table I-2 Summary of Impacts and Mitigation Measures...I-6 Table II-1 Annexation Area Properties... II-10 Table II-2 Specific Plan Program Summary... II-12 Table II-3 Existing and Proposed Land Use and Zoning Designations... II-14 Table III-1 Related Projects... III-8 Table IV.A-1 Building Height Recommendations by Building Type... IV.A-15 Table IV.A-2 Parking by Building Type... IV.A-16 Table IV.C Ambient Air Quality Data in Project Vicinity... IV.C-6 Table IV.C-2 State and National Ambient Air Quality Standards and Attainment Status for the South Coast Air Basin... IV.C-9 Table IV.C-3 SCAQMD Daily Construction Emissions Thresholds... IV.C-18 Table IV.C-4 SCAQMD Daily Operational Emissions Thresholds... IV.C-18 Table IV.C-5 Regional Construction Emissions - Unmitigated... IV.C-22 Table IV.C-6 Localized Construction Emissions - Unmitigated... IV.C-23 Table IV.C-7 Net Daily Operational Emissions... IV.C-24 Table IV.C-8 Estimated Carbon Monoxide Concentrations... IV.C-25 Table IV.C-9 Project Consistency with the Air Quality Management Plan... IV.C-27 Table IV.C-10 Estimated Annual Greenhouse Gas Emissions... IV.C-29 Table IV.C-11 Regional Construction Emissions - Mitigated... IV.C-33 Table IV.C-12 Localized Construction Emissions - Mitigated... IV.C-34 Table IV.D-1 Plant Life in the Specific Plan Area... IV.D-3 Table IV.D-2 CNDDB Quad Viewer Listing for the Southgate Quadrangle... IV.D-4 Table IV.E-1 Historic Structures within ½-Mile of the Specific Plan Area... IV.E-3 Table IV.E-2 Archeological Sites within ½-Mile of the Specific Plan Area... IV.E-5 Table IV.F-1 LADWP Power Source Mix... IV.F-2 Table IV.F-2 Estimated Electricity Usage from Existing Uses within the Specific Plan Area... IV.F-4 Table IV.F-3 Estimated Natural Gas Usage from Existing Uses within the Specific Plan Area... IV.F-5 Table IV.F-4 Estimated Electricity Usage of the Proposed Project... IV.F-9 Table IV.F-5 Estimated Natural Gas Usage of the Proposed Project... IV.F-11 Table IV.F-6 Estimated Electricity Usage of the Proposed Project and Two Related Projects... IV.F-12 Table IV.F-7 Estimated Natural Gas Usage of the Proposed Project and Nine Related Projects... IV.F-13 Table IV.G-1 Modified Mercalli Intensity Scale... IV.G-4 Table IV.H-1 Regulatory Database Research... IV.H-5 Table IV.J-1 Specific Plan Program Summary... IV.J-15 Table IV.J-2 Annexation Area Properties... IV.J-15 Table IV.J-3 Existing and Proposed Land Use and Zoning Designations... IV.J-20 Table IV.J-4 Project Consistency with Local Plans and Policies... IV.J-24 Table IV.J-5 Non-conforming Uses with Proposed Zoning Designations... IV.J-32 Table IV.J-6 Project Consistency with Regional Plans... IV.J-35 Table IV.L-1 Existing Noise Levels... IV.L-5 Table IV.L-2 Guidelines for Noise Compatible Land Use... IV.L-9 v

8 LIST OF TABLES (CONTINUED) Table IV.L-3 Maximum Noise Levels of Common Construction Machines... IV.L-11 Table IV.L-4 Outdoor Construction Noise Levels... IV.L-12 Table IV.L-5 Construction Noise Impact Unmitigated... IV.L-12 Table IV.L-6 Vibration Velocities for Construction Equipment... IV.L-14 Table IV.L-7 Estimated Mobile Source Noise Levels Proposed Project... IV.L-14 Table IV.L-8 Estimated Mobile Source Noise Levels Cumulative... IV.L-18 Table IV.L-9 Construction Noise Impact Mitigated... IV.L-20 Table IV.M-1 Existing (2010) Population Characteristics... IV.M-2 Table IV.M-2 Existing Housing Characteristics... IV.M-3 Table IV.M-3 Existing (2010) Employment in Jordan Downs Specific Plan Area... IV.M-3 Table IV.M-4 Existing (2010) Employment Characteristics... IV.M-3 Table IV.M-5 Jordan Downs Specific Plan Estimated Population and Housing Growth by Housing Type... IV.M-6 Table IV.M-6 Jordan Downs Specific Plan Proposed Job-Creating Development... IV.M-6 Table IV.M-7 SCAG Projected (2020) Population, Housing, and Employment Growth... IV.M-7 Table IV.M-8 Jordan Downs Specific Plan Estimated Population and Housing Growth Compared to SCAG Growth Projections... IV.M-7 Table IV.M-9 Related Projects and their Estimated Net Gain/Loss of Population, Housing, and/or Employment... IV.M-9 Table IV.N-1 LAFD Fire Stations Serving Specific Plan Area... IV.N-1 Table IV.N-2 LAFD Fire Station Incident Response Data of Fire Stations Serving the Specific Plan Area... IV.N-3 Table IV.N-3 LACOFD Stations Serving the Specific Plan Area... IV.N-4 Table IV.N-4 Part I Crime Offense Statistics... IV.N-8 Table IV.N-5 Current Enrollments and Capacities of LAUSD Schools Serving the Specific Plan Area... IV.N-12 Table IV.N-6 Planned Public Schools to Serve the Specific Plan Area... IV.N-14 Table IV.N-7 Proposed Project School Student Generation... IV.N-21 Table IV.N-8 Projected Enrollments and Capacities of Existing LAUSD Schools Serving the Specific Plan Area... IV.N-21 Table IV.N-9 Estimated Student Generation of the Proposed Project and Related Projects... IV.N-25 Table IV.O-1 Parks and Recreation Facilities within Two Miles of the Specific Plan Area... IV.O-3 Table IV.P-1 Study Intersections by Jurisdiction... IV.P-4 Table IV.P-2 Level of Service Definitions for Signalized Intersections... IV.P-5 Table IV.P-3 Level of Service Definitions for Unsignalized Intersections... IV.P-5 Table IV.P-4 Existing Study Signalized Intersection Peak Hour LOS... IV.P-6 Table IV.P-5 Existing Transit Service in Project Area... IV.P-13 Table IV.P-6 City of Los Angeles Significant Impact Criteria... IV.P-14 Table IV.P-7 Estimated Proposed Project Trip Generation... IV.P-18 Table IV.P-8 Related Projects and their Trip Generation... IV.P-22 Table IV.P-9 Existing and Scenario 1 Peak Hour LOS Comparison for Signalized Intersections... IV.P-22 Table IV.P-10 Scenario 1 and Scenario 2 Peak Hour LOS Comparison for Signalized Intersections... IV.P-29 Table IV.P-11 Scenario 2 Peak Hour LOS/Signal Warrant for Unsignalized Intersection (City of Los Angeles Guidelines)... IV.P-30 vi

9 LIST OF TABLES (CONTINUED) Table IV.P-12 CMP Arterial Monitoring Intersection Analysis AM Peak Hour... IV.P-30 Table IV.P-13 CMP Freeway Analysis... IV.P-30 Table IV.P-14 LAMC and Specific Plan Parking Requirements... IV.P-33 Table IV.Q-1 LADWP Water Supply... IV.Q-2 Table IV.Q-2 LADWP Groundwater Extractions... IV.Q-3 Table IV.Q-3 Water Usage from Existing Uses on Specific Plan Area... IV.Q-6 Table IV.Q-4 Estimated Wastewater Generation Usage of Existing Uses on Specific Plan Area... IV.Q-7 Table IV.Q-5 Estimated Solid Waste Generation from Existing Uses on Specific Plan Area... IV.Q-8 Table IV.Q-6 Estimated Water Usage of the Proposed Project... IV.Q-17 Table IV.Q-7 Estimated Wastewater Generation of the Proposed Project... IV.Q-19 Table IV.Q-8 Estimated Solid Waste Generation of the Proposed Project Table IV.Q-9 During Demolition and Construction Phases... IV.Q-21 Estimated Solid Waste Generation During the Operation of the Proposed Project... IV.Q-22 Table IV.Q-10 Estimated Water Usage of the Proposed Project and Two Related Projects... IV.Q-23 Table IV.Q-11 Estimated Wastewater Generation of the Proposed Project and Nine Related Projects... IV.Q-24 Table V-1 Comparison of Alternatives... V-8 Table V-2 Summary of Similar Impacts Between Alternative 2 and the Proposed Project... V-15 Table V-3 Alternative 2 Estimated Electricity Usage... V-17 Table V-4 Alternative 2 Estimated Natural Gas Usage... V-17 Table V-5 Alternative 2 Job Generation... V-19 Table V-6 Alternative 2 Estimated Trip Generation... V-20 Table V-7 Alternative 2 Utility Generation Rates... V-20 Table V-8 Summary of Similar Impacts Between Alternative 3 and the Proposed Project... V-21 Table V-9 Summary of Similar Impacts Between Alternative 4 and the Proposed Project... V-22 Table V-10 Table V-11 Estimated Wastewater Generation, Water Demand, and Solid Waste Generation Under Alternative 4... V-25 Summary of Better/Worse Impacts Between All Build Alternatives and the Proposed Project... V-26 vii

Truckee Railyard Draft Master Plan EIR. Draft Environmental Impact Report Appendices A-B SCH No

Truckee Railyard Draft Master Plan EIR. Draft Environmental Impact Report Appendices A-B SCH No Truckee Railyard Draft Master Plan EIR Volume 1. Draft Environmental Impact Report Appendices A-B SCH No. 2007122092 Prepared for: Town of Truckee November 2008 TRUCKEE RAILYARD DRAFT MASTER PLAN Volume

More information

5.0 ALTERNATIVES 5.1 OVERVIEW OF ALTERNATIVES ANALYSIS

5.0 ALTERNATIVES 5.1 OVERVIEW OF ALTERNATIVES ANALYSIS 5.0 ALTERNATIVES 5.1 OVERVIEW OF ALTERNATIVES ANALYSIS According to CEQA, an EIR must describe a reasonable range of alternatives to a proposed project that could feasibly attain most of the basic project

More information

1 INTRODUCTION 1.1 PURPOSE

1 INTRODUCTION 1.1 PURPOSE 1 INTRODUCTION 1.1 PURPOSE The County of Mariposa Board of Supervisors proposes to adopt the Mariposa County General Plan. This General Plan will replace the County s current General Plan, which was prepared

More information

CHAPTER 1 INTRODUCTION

CHAPTER 1 INTRODUCTION CHAPTER 1 INTRODUCTION 1.1 PROJECT BACKGROUND This Environmental Impact Report (EIR) examines the potentially significant effects on the environment resulting from the proposed City of Citrus Heights City

More information

City of Del Mar Staff Report

City of Del Mar Staff Report LIII City of Del Mar Staff Report T: Honorable Mayor and City Council Members xt FRM: Kathleen A. Garcia, Planning and Community Development Director Via Scott W. Huth, City Manager DATE: February 6, 212

More information

NOVATO GENERAL PLAN 2035 ENVIRONMENTAL IMPACT REPORT CONSULTANT SERVICES AGREEMENT AMENDMENT

NOVATO GENERAL PLAN 2035 ENVIRONMENTAL IMPACT REPORT CONSULTANT SERVICES AGREEMENT AMENDMENT G-3 STAFF REPORT MEETING DATE: September 26, 2017 TO: FROM: City Council Steve Marshall, Planning Manager 922 Machin Avenue Novato, CA 94945 415/ 899-8900 FAX 415/ 899-8213 www.novato.org SUBJECT: NOVATO

More information

3. A CITY COUNCIL PUBLIC HEARING FEBRUARY 2, 2015 SUBJECT:

3. A CITY COUNCIL PUBLIC HEARING FEBRUARY 2, 2015 SUBJECT: CITY COUNCIL PUBLIC HEARING SUBJECT: INITIATED BY: FEBRUARY 2, 2015 APPEAL OF THE PLANNING COMMISSION'S DECISION TO APPROVE THE REHABILITATION AND RESTORATION OF A DESIGNATED CULTURAL RESOURCE, DEMOLITION

More information

OFFICE OF HISTORIC RESOURCES City Hall 200 N. Spring Street, Room 559 Los Angeles, CA 90012

OFFICE OF HISTORIC RESOURCES City Hall 200 N. Spring Street, Room 559 Los Angeles, CA 90012 City Hall 200 N. Spring Street, Room 559 Los Angeles, CA 90012 February 2, 2015 TO: Jose Huizar, Chair Planning and Land Use Management Committee FROM: Ken Bernstein, AICP Manager, Office of Historic Resources

More information

Section 15085, the City prepared a Notice of Completion of the DEIR that was filed by mail with the State Office of

Section 15085, the City prepared a Notice of Completion of the DEIR that was filed by mail with the State Office of ENVIRONMENTAL IMPACT REPORT NO. EIR14-001 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF BUENA PARK CERTIFYING THE COMPLETION OF A FINAL ENVIRONMENTAL IMPACT REPORT AND RECIRCULATED FINAL ENVIRONMENTAL

More information

CITY OF PALM DESERT COMPREHENSIVE GENERAL PLAN

CITY OF PALM DESERT COMPREHENSIVE GENERAL PLAN Comprehensive General Plan/Administration and Implementation CITY OF PALM DESERT COMPREHENSIVE GENERAL PLAN CHAPTER II ADMINISTRATION AND IMPLEMENTATION This Chapter of the General Plan addresses the administration

More information

CHAPTER 1 Introduction

CHAPTER 1 Introduction SECTION 1.1 Introduction CHAPTER 1 Introduction 1.1 INTRODUCTION The subjects of this Environmental Impact Report (EIR) are the proposed Granada Hills Knollwood Community Plan and implementing ordinances

More information

CEQA ENVIRONMENTAL REVIEW GUIDELINES

CEQA ENVIRONMENTAL REVIEW GUIDELINES CEQA ENVIRONMENTAL REVIEW GUIDELINES Adopted by City Council on September 18, 2007 by Resolution No. 07-113 Revised by City Council on June 3, 2014 by Resolution No. 14-49 CITY OF BENICIA CEQA ENVIRONMENTAL

More information

2. Final Environmental Impact Report (EIR), dated December Findings and Statement of Overriding Considerations, dated December 2007.

2. Final Environmental Impact Report (EIR), dated December Findings and Statement of Overriding Considerations, dated December 2007. Department of Public Works Bureau of Engineering Report No. 2 May 8, 2015 CD No. 11 CONSIDERATION OF AN APPEAL OF CITY ENGINEER S APPROVAL OF COASTAL DEVELOPMENT PERMIT (CDP) 10-04 FOR THE VENICE DUAL

More information

Environmental Analysis, Chapter 4 Consequences, and Mitigation

Environmental Analysis, Chapter 4 Consequences, and Mitigation Environmental Analysis, Chapter 4 4.14 Economic and Fiscal Impacts This section evaluates potential impacts to local and regional economies during construction and operation of each project alternative.

More information

Case No.: N/A Staff Phone #: (805) Environmental Document: N/A 1.0 REQUEST

Case No.: N/A Staff Phone #: (805) Environmental Document: N/A 1.0 REQUEST SANTA BARBARA COUNTY MONTECITO PLANNING COMMISSION Staff Report/Work Program for FY 2014-2015 Long Range Planning Division Planning and Development Department Hearing Date: February 19, 2014 Staff Report

More information

GRASS VALLEY TRANSPORTATION IMPACT FEE PROGRAM NEXUS STUDY

GRASS VALLEY TRANSPORTATION IMPACT FEE PROGRAM NEXUS STUDY HEARING REPORT GRASS VALLEY TRANSPORTATION IMPACT FEE PROGRAM NEXUS STUDY Prepared for: City of Grass Valley Prepared by: Economic & Planning Systems, Inc. March 2008 EPS #17525 S A C R A M E N T O 2150

More information

1. I N T R O D U C T I O N

1. I N T R O D U C T I O N INTRODUCTION The Chico 2030 General Plan is a statement of community priorities to guide public decisionmaking. It provides a comprehensive, long-range, and internally consistent policy framework for the

More information

Planning Commission Staff Report

Planning Commission Staff Report Staff Recommendation Planning Commission Staff Report February 5, 2015 Project: Southeast Policy Area, Amendment 1 File: PL0016 and EG-13-030 Request: General Plan Amendment, Community Plan Amendment,

More information

FROM: CITY MANAGER DEPARTMENT: PLANNING AND COMMUNITY ENVIRONMENT DATE: SEPTEMBER 11, 2006 CMR: 346:06

FROM: CITY MANAGER DEPARTMENT: PLANNING AND COMMUNITY ENVIRONMENT DATE: SEPTEMBER 11, 2006 CMR: 346:06 21a TO: HONORABLE CITY COUNCIL FROM: CITY MANAGER DEPARTMENT: PLANNING AND COMMUNITY ENVIRONMENT DATE: SEPTEMBER 11, 2006 CMR: 346:06 SUBJECT: 901 SAN ANTONIO ROAD [06PLN-00031, 06PLN-00050]: REQUEST BY

More information

How to Participate in the Environmental Review Process. September 29, 2016

How to Participate in the Environmental Review Process. September 29, 2016 How to Participate in the Environmental Review Process September 29, 2016 Training for Citizen Participants Katherine Hess Community Development Administrator Eric Lee Planner Purposes De-mystify public

More information

Chapter VIII. General Plan Implementation A. INTRODUCTION B. SUBMITTAL AND APPROVAL OF SUBSEQUENT PROJECTS C. SPHERE OF INFLUENCE

Chapter VIII. General Plan Implementation A. INTRODUCTION B. SUBMITTAL AND APPROVAL OF SUBSEQUENT PROJECTS C. SPHERE OF INFLUENCE Chapter VIII General Plan Implementation A. INTRODUCTION This chapter presents a variety of tools available to the (City) to help build the physical city envisioned in Chapter III. While the Modesto provides

More information

Addendum to Environmental Impact Report

Addendum to Environmental Impact Report Lead Agency: Staff Contact: Addendum to Environmental Impact Report Addendum Date: Case No.: 2011.0558E Project Title:, EIR: 2011.0558E, certified March 27, 2014 Project Sponsor: Sean Kennedy, San Francisco

More information

CEQA Checklist for School Districts

CEQA Checklist for School Districts CEQA Checklist for School Districts (Revised March 2014) Copyright 2014 Lozano Smith For more information, please visit our website at LozanoSmith.com or call us Toll Free at 800.445.9430. CEQA Checklist

More information

Traffic Impact Analysis Guidelines Methodology

Traffic Impact Analysis Guidelines Methodology York County Government Traffic Impact Analysis Guidelines Methodology Implementation Guide for Section 154.037 Traffic Impact Analysis of the York County Code of Ordinances 11/1/2017 TABLE OF CONTENTS

More information

TO THE MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: ACTION ITEM

TO THE MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: ACTION ITEM 106 Office of the President TO THE MEMBERS OF THE COMMITTEE ON : For Meeting of ACTION ITEM AMENDMENT OF THE BUDGET FOR CAPITAL IMPROVEMENTS AND THE CAPITAL IMPROVEMENT PROGRAM, ADOPTION OF FINDINGS, AND

More information

Policy CIE The following are the minimum acceptable LOS standards to be utilized in planning for capital improvement needs:

Policy CIE The following are the minimum acceptable LOS standards to be utilized in planning for capital improvement needs: Vision Statement: Provide high quality public facilities that meet and exceed the minimum level of service standards. Goals, Objectives and Policies: Goal CIE-1. The City shall provide for facilities and

More information

DEFINITION OF REVENUE SOURCES GENERAL FUND

DEFINITION OF REVENUE SOURCES GENERAL FUND GENERAL FUND PROPERTY TAX: The valuation of property in the City is determined by the Los Angeles County Tax Assessor, except for Public Utility property, which is assessed by the State Board of Equalization.

More information

CAPITAL IMPROVEMENTS ELEMENT

CAPITAL IMPROVEMENTS ELEMENT GOALS, OBJECTIVES AND POLICIES Goal 1.0.0. To annually adopt and utilize a 5-Year Capital Improvements Program and Annual Capital Budget to coordinate the timing and to prioritize the construction and

More information

Public Works and Development Services

Public Works and Development Services City of Commerce Capital Improvement Program Prioritization Policy Public Works and Development Services SOP 101 Version No. 1.0 Effective 05/19/15 Purpose The City of Commerce s (City) Capital Improvement

More information

CITY OF LAGUNA WOODS LOCAL CALIFORNIA ENVIRONMENTAL QUALITY ACT PROCEDURES

CITY OF LAGUNA WOODS LOCAL CALIFORNIA ENVIRONMENTAL QUALITY ACT PROCEDURES CITY OF LAGUNA WOODS LOCAL CALIFORNIA ENVIRONMENTAL QUALITY ACT PROCEDURES TABLE OF CONTENTS DEFINITIONS... i I. INTRODUCTION...1 II. DELEGATION OF RESPONSIBILITY...1 A. Responsibilities of the Planning

More information

Draft West Los Angeles Transportation Improvement and Mitigation Specific Plan

Draft West Los Angeles Transportation Improvement and Mitigation Specific Plan Draft West Los Angeles Transportation Improvement and Mitigation Specific Plan City of Los Angeles Ordinance No. Effective Specific Plan Procedures Amended by Ordinance No. Specific Plan Amendment Amended

More information

Introduction P O L I C Y D O C U M E N T P A R T 1

Introduction P O L I C Y D O C U M E N T P A R T 1 P O L I C Y D O C U M E N T P A R T 1 Introduction The 2035 General Plan for San Joaquin County presents a vision for the County's future and a strategy to make that vision a reality. The Plan is the result

More information

City of Los Angeles CALIFORNIA. VMSJIs!/ rji *.i" ERIC GARCETTf MAYOR

City of Los Angeles CALIFORNIA. VMSJIs!/ rji *.i ERIC GARCETTf MAYOR DEPARTMENT OF CITY PLANNING CITY PLANNING COMMISSION DAVID H. j. AMBROZ PRESIDENT RENEE DAKE WILSON VICE-PRESIDENT ROBERT L AHN CAROLINE CHOE RICHARD KATZ JOHN W. MACK SAMANTHA MILLMAN VERONICA PADILLA-CAMPOS

More information

4.3 Economic and Fiscal Impacts

4.3 Economic and Fiscal Impacts 4.3 This section evaluates the potential economic, and fiscal impacts that could arise from the construction and long-term operation of the proposed East San Fernando Valley Transit Corridor Project. 4.3.1

More information

TABLE OF CONTENTS CHAPTER 80: AREA ZONING CODE

TABLE OF CONTENTS CHAPTER 80: AREA ZONING CODE TABLE OF CONTENTS CHAPTER 80: AREA ZONING CODE RIPLEY COUNTY, INDIANA SECTION PREAMBLE 1 80.01: SHORT TITLE 3 80.02: ESTABLISHMENT OF DISTRICTS AND ZONE MAP 3 (A) District s and Designations 3 (B) Zone

More information

CAPITAL IMPROVEMENTS ELEMENT

CAPITAL IMPROVEMENTS ELEMENT Goals, Objectives and Policies CAPITAL IMPROVEMENTS ELEMENT GOAL 9.1.: USE SOUND FISCAL POLICIES TO PROVIDE ADEQUATE PUBLIC FACILITIES TO ALL RESIDENTS WITHIN THE CITY. FISCAL POLICIES MUST PROTECT INVESTMENTS

More information

North Fair Oaks Zoning Workgroup Fair Oaks Community Center February 15, 2017

North Fair Oaks Zoning Workgroup Fair Oaks Community Center February 15, 2017 North Fair Oaks Zoning Workgroup Fair Oaks Community Center February 15, 2017 1 M e e t i n g P u r p o s e a n d O b j e c t i v e s PURPOSE: Present project timeline and next steps Present Proposed Improvements

More information

APPENDIX D PUBLIC SERVICES LETTERS AND CORRESPONDENCE

APPENDIX D PUBLIC SERVICES LETTERS AND CORRESPONDENCE LSA ASSOCIATES, INC. SEPTEBER 2016 DRAFT ENVIRONMENTAL IMPACT REPORT GENERAL PLAN LAND USE & URBAN DESIGN ELEMENTS CITY OF LONG BEACH, CALIFORNIA APPENDIX D PUBLIC SERVICES LETTERS AND CORRESPONDENCE P:\CLB1505\Preprint

More information

TABLE OF CONTENTS. Project Analysis... A-1 Project Summary Background Issues Conclusion. Findings... F-1 CEQA Findings Charter Findings

TABLE OF CONTENTS. Project Analysis... A-1 Project Summary Background Issues Conclusion. Findings... F-1 CEQA Findings Charter Findings CPC-2008-3470-SP-GPA-ZC-SUD-BL-M3 TABLE OF CONTENTS Project Analysis... A-1 Project Summary Background Issues Conclusion Findings... F-1 CEQA Findings Charter Findings Public Hearing and Communications...

More information

SAN FRANCISCO PLANNING DEPARTMENT

SAN FRANCISCO PLANNING DEPARTMENT REMARKS Addendum #2 to Environmental Impact Report Addendum Date: June 11, 2015 Case No.: 2011.0558E Project Title: Transit Effectiveness Project, Modified TTRP.5 Moderate Alternative, McAllister Street

More information

TABLE OF CONTENTS LIST OF TABLES

TABLE OF CONTENTS LIST OF TABLES TABLE OF CONTENTS A. GOALS, OBJECTIVES, AND POLICIES... 3 B. SUMMARY... 17 LIST OF TABLES Table IX 1: City of Winter Springs Five-Year Schedule of Capital Improvements (SCI) FY 2013/14-2017/18... 11 Table

More information

IV. Environmental Impact Analysis I.1. Employment

IV. Environmental Impact Analysis I.1. Employment IV. Environmental Impact Analysis I.1. Employment 1. Introduction This section of the Draft EIR analyzes the project s relationship to SCAG s 2030 employment growth forecast for the Subregion and, for

More information

RESOLUTION NO

RESOLUTION NO PO Qf sup, a1to~.' un`y` : RESOLUTION NO. 265-2006 OF THE BOARD OF SUPERVISORS OF THE COUNTY OF EL DORADO CERTIFYING THE TRAFFIC IMPACT MITIGATION FEE PROGRAM SUPPLEMENT TO THE 2004 GENERAL PLAN ENVIRONMENTAL

More information

Draft Environmental Impact Statement. Appendix G Economic Analysis Report

Draft Environmental Impact Statement. Appendix G Economic Analysis Report Draft Environmental Impact Statement Appendix G Economic Analysis Report Appendix G Economic Analysis Report Economic Analyses in Support of Environmental Impact Statement Carolina Crossroads I-20/26/126

More information

CITY OF LOS ANGELES INTER-DEPARTMENTAL CORRESPONDENCE

CITY OF LOS ANGELES INTER-DEPARTMENTAL CORRESPONDENCE CITY OF LOS ANGELES INTER-DEPARTMENTAL CORRESPONDENCE DATE: TO: Honorable City Council c/o City Clerk, Room 395, City Hall Attention: Honorable Nury Martinez, Chair, Energy and the Environment Committee

More information

HEMSON C o n s u l t i n g L t d

HEMSON C o n s u l t i n g L t d DEVELOPMENT CHARGES BACKGROUND STUDY Town of Gravenhurst C o n s u l t i n g L t d April, 2014 TABLE OF CONTENTS EXECUTIVE SUMMARY... 1 I INTRODUCTION... 7 II A TOWN-WIDE UNIFORM CHARGE APPROACH TO ALIGN

More information

Planning Commission CEQA Training A Brief Introduction to CEQA

Planning Commission CEQA Training A Brief Introduction to CEQA City of Brisbane Planning Commission CEQA Training A Brief Introduction to CEQA August 9, 2012 Presented by: Terry Rivasplata Technical Director ICF International Valerie Holcomb Community Affairs ICF

More information

Sec Transportation management special use permits Purpose and intent.

Sec Transportation management special use permits Purpose and intent. Sec. 11-700 Transportation management special use permits. 11-701 Purpose and intent. There are certain uses of land which, by their location, nature, size and/or density, or by the accessory uses permitted

More information

CAPITAL IMPROVEMENTS ELEMENT:

CAPITAL IMPROVEMENTS ELEMENT: CAPITAL IMPROVEMENTS ELEMENT: Goals, Objectives and Policies Goal 1. The provision of needed public facilities in a timely manner, which protects investments in existing facilities, maximizes the use of

More information

IMPLEMENTATION A. INTRODUCTION C H A P T E R

IMPLEMENTATION A. INTRODUCTION C H A P T E R C H A P T E R 11 IMPLEMENTATION A. INTRODUCTION This chapter addresses implementation of the General Plan. The Plan s seven elements include 206 individual actions. 1 Many are already underway or are on-going.

More information

BUTTE COUNTY ZONING ORDINANCE CONTENTS

BUTTE COUNTY ZONING ORDINANCE CONTENTS BUTTE COUNTY ZONING ORDINANCE CONTENTS Part 1 Enactment and Applicability Article 1. Purpose and Effect of the Zoning Ordinance... 3 24-1 Title... 3 24-2 Purpose of the Zoning Ordinance... 3 24-3 Relationship

More information

CITY OF LOS ANGELES Department of Building & Safety

CITY OF LOS ANGELES Department of Building & Safety CITY OF LOS ANGELES Department of Building & Safety BUILDING PERMIT CALIFORNIA ENVIRONMENTAL QUALITY ACT (CEQA) PROCEDURE FOR HISTORICAL MONUMENTS 11/2001 TABLE OF CONTENT I. REVIEWING PROJECT AND APPLYING

More information

Agenda. Background Budget / PW General Fund Budget Streets & Infrastructure Citizen Engagement

Agenda. Background Budget / PW General Fund Budget Streets & Infrastructure Citizen Engagement 1 Agenda Background 2013-2014 Budget / PW General Fund Budget Streets & Infrastructure Citizen Engagement Sustainable Transportation Funding Dedicated Revenues Potential Rate Impact Clarification Proposed

More information

Menlo Park Fire Protection District

Menlo Park Fire Protection District Menlo Park Fire Protection District 170 Middlefield Road Menlo Park, CA 94025 Tel: 650.688.8400 Fax: 650.323.9129 Website: www.menlofire.org Email: mpfd@menlofire.org Fire Chief Harold Schapelhouman Board

More information

Population, Housing, and Employment Methodology

Population, Housing, and Employment Methodology Appendix O Population, Housing, and Employment Methodology Final EIR APPENDIX O Methodology Population, Housing, and Employment Methodology This appendix describes the data sources and methodologies employed

More information

CITY OF POMONA. Financial Update Community Meetings

CITY OF POMONA. Financial Update Community Meetings CITY OF POMONA Financial Update Community Meetings TONIGHTS PRESENTATION 1 Historical Outlook 2 2019 Operating Budget 3 UFI Recommendations 4 CIP Budget Millions POMONA S HISTORICAL OUTLOOK $110 General

More information

CANNABIS BUSINESS OPERATOR PERMIT APPLICATION Finance Department Grand Avenue, SSF CA Phone: (650)

CANNABIS BUSINESS OPERATOR PERMIT APPLICATION Finance Department Grand Avenue, SSF CA Phone: (650) CANNABIS BUSINESS OPERATOR PERMIT APPLICATION Finance Department - 400 Grand Avenue, SSF CA Phone: (650) 877-8505 In accordance with the requirements of SSFMC 20.410, no person or entity shall engage in

More information

INDEPENDENT CONSULTANT AGREEMENT FOR PROFESSIONAL SERVICES Environmental Consulting Services

INDEPENDENT CONSULTANT AGREEMENT FOR PROFESSIONAL SERVICES Environmental Consulting Services INDEPENDENT CONSULTANT AGREEMENT FOR PROFESSIONAL SERVICES Environmental Consulting Services This Independent Consultant Agreement for Professional Services ( Agreement ) is made and entered into as of

More information

Sketch Plan Alternatives: Summary of Planning Commission and Board of Supervisors Recommendations

Sketch Plan Alternatives: Summary of Planning Commission and Board of Supervisors Recommendations HUMBOLDT COUNTY GENERAL PLAN UPDATE Sketch Plan Alternatives: Summary of Planning Commission and Board of Supervisors Recommendations September 2004 Prepared by Humboldt County Department of Community

More information

Development Services Report to Council

Development Services Report to Council Development Services Report to Council File Category: File Folder: GOV.FED.HEA/PRO.DEV.ZON Marihuana Regulations/R13-021 DATE: September 23, 2013 TO: Mayor and Council FROM: Barclay Pitkethly, Deputy Director

More information

6 MONTH PLANNING CALENDAR May November 2018

6 MONTH PLANNING CALENDAR May November 2018 6 MONTH PLANNING CALENDAR May November 2018 Revised: 5/10/2018 2:59 PM CALENDAR SUBJECT TO FREQUENT CHANGES Call City Clerk s Office for up-to-date information (970) 416-2774 Council Meetings begin at

More information

Neighborhood Council of Westchester/Playa del Rey. Community Questions on the LAX Master Plan EIS/EIR QUESTIONS ON THE LAX MASTER PLAN EIS/EIR

Neighborhood Council of Westchester/Playa del Rey. Community Questions on the LAX Master Plan EIS/EIR QUESTIONS ON THE LAX MASTER PLAN EIS/EIR QUESTIONS ON THE LAX MASTER PLAN EIS/EIR 0 0. What programs or activities are the FAA and LAWA participating in or working towards creating a regional airport plan other than Ontario International Airport

More information

Plan Implementation AICP Exam Review

Plan Implementation AICP Exam Review Plan Implementation AICP Exam Review GPA Fall Conference October 9, 2013 Gary A. Cornell, FAICP Outline of AICP Exam Content Visioning and goal setting Quantitative and qualitative research methods Collecting,

More information

Malibu Middle and High School Alignment Project CEQA Consulting Services RFQ/P Questions & Answers June 14, 2018

Malibu Middle and High School Alignment Project CEQA Consulting Services RFQ/P Questions & Answers June 14, 2018 Malibu Middle and High School Alignment Project CEQA Consulting Services RFQ/P Questions & Answers June 14, 2018 1) What technical studies has the District completed to date i.e. traffic, biological, cultural,

More information

Structural Analysis of the Alaska Economy: What are the Drivers?

Structural Analysis of the Alaska Economy: What are the Drivers? Structural Analysis of the Alaska Economy: What are the Drivers? by Scott Goldsmith October, 2008 Institute of Social and Economic Research University of Alaska Anchorage 3211 Providence Drive Anchorage,

More information

TAUSSIG DEVELOPMENT IMPACT FEE JUSTIFICATION STUDY CITY OF ESCALON. Public Finance Public Private Partnerships Urban Economics Clean Energy Bonds

TAUSSIG DEVELOPMENT IMPACT FEE JUSTIFICATION STUDY CITY OF ESCALON. Public Finance Public Private Partnerships Urban Economics Clean Energy Bonds DAVID TAUSSIG & ASSOCIATES, INC. DEVELOPMENT IMPACT FEE JUSTIFICATION STUDY CITY OF ESCALON B. C. SEPTEMBER 12, 2016 Public Finance Public Private Partnerships Urban Economics Clean Energy Bonds Prepared

More information

6 MONTH PLANNING CALENDAR July January 2019

6 MONTH PLANNING CALENDAR July January 2019 6 MONTH PLANNING CALENDAR July January 2019 Revised: 6/28/2018 3:22 PM CALENDAR SUBJECT TO FREQUENT CHANGES Call City Clerk s Office for up-to-date information (970) 416-2774 Council Meetings begin at

More information

4.6 POPULATION AND HOUSING

4.6 POPULATION AND HOUSING L S A A S S O C I A T E S, I N C. D R A F T E N V I R O N M E N T A L I M P A C T R E P O R T 4.6 POPULATION AND HOUSING 4.6.1 Introduction This section provides a discussion of the existing population,

More information

1. identifies the required capacity of capital improvements to serve existing and future development based on level-of-service (LOS) standards;

1. identifies the required capacity of capital improvements to serve existing and future development based on level-of-service (LOS) standards; DIVISION 4.200 CAPITAL IMPROVEMENTS ELEMENT SECTION 4.201 INTRODUCTION The purpose of the Capital Improvements Element (CIE) is to tie the capital improvement needs identified in the other elements to

More information

Honorable Mayor and Members of the City Council. Elizabeth Corpuz, Director of Planning and Building Services Jason P. Clarke, Senior Planner

Honorable Mayor and Members of the City Council. Elizabeth Corpuz, Director of Planning and Building Services Jason P. Clarke, Senior Planner Page 1 of 16 14-L TO: ATTENTION: FROM: SUBJECT: Honorable Mayor and Members of the City Council Jeffrey L. Stewart, City Manager Elizabeth Corpuz, Director of Planning and Building Services Jason P. Clarke,

More information

Notice of Request for Proposals For Ephesus Church Road/Fordham Boulevard Small Area Planning/Traffic Analysis

Notice of Request for Proposals For Ephesus Church Road/Fordham Boulevard Small Area Planning/Traffic Analysis Notice of Request for Proposals For Ephesus Church Road/Fordham Boulevard Small Area Planning/Traffic Analysis BID: Q10-62 TO: FROM: SUBJECT: ALL PROSPECTIVE BIDDERS COCO HALL, PURCHASING & CONTRACTS MANAGER

More information

Staff Report. Staff requests Commission review, discussion and determination of a policy on Unincorporated Islands and Corridors

Staff Report. Staff requests Commission review, discussion and determination of a policy on Unincorporated Islands and Corridors SONOMA LOCAL AGENCY FORMATION COMMISSION 575 ADMINISTRATION DRIVE, ROOM 104A, SANTA ROSA, CA 95403 (707) 565-2577 FAX (707) 565-3778 www.sonoma-county.org/lafco Staff Report Meeting Date: April 4, 2012

More information

Chapter CONCURRENCY

Chapter CONCURRENCY Chapter 14.28 CONCURRENCY Sections: 14.28.010 Purpose. 14.28.020 Development exempt from project concurrency review. 14.28.030 Concurrency facilities and services. 14.28.040 Project concurrency review.

More information

GENERAL INFORMATION ABOUT THE CONTENTS OF THIS FILE

GENERAL INFORMATION ABOUT THE CONTENTS OF THIS FILE GENERAL INFORMATION ABOUT THE CONTENTS OF THIS FILE Submissions by the public in compliance with the Commission Rules and Operating Procedures (ROPs), Rule 4.3, are distributed to the Commission and uploaded

More information

Nassau County 2030 Comprehensive Plan. Capital Improvements Element (CI) Goals, Objectives and Policies. Goal

Nassau County 2030 Comprehensive Plan. Capital Improvements Element (CI) Goals, Objectives and Policies. Goal (CI) Goal Based on the premise that existing taxpayers should not have to bear the financial burden of growth-related infrastructure needs, Ensure the orderly and efficient provision of infrastructure

More information

Barton Brierley, AICP, Community Development Director (Staff Contact: Tyra Hays, AICP, (707) )

Barton Brierley, AICP, Community Development Director (Staff Contact: Tyra Hays, AICP, (707) ) Agenda Item No. 8C May 10, 2016 TO: FROM: SUBJECT: Honorable Mayor and City Council Attention: Laura C. Kuhn, City Manager Barton Brierley, AICP, Community Development Director (Staff Contact: Tyra Hays,

More information

& OUTDOOR OlFTFRONT Z>

& OUTDOOR OlFTFRONT Z> / Los Angeles Advertising Coalition ClearChannel & OUTDOOR OlFTFRONT Z> DAKTRONICS SlYESCO OUTDOOR ADVERTISING media February 14, 2018 VIA FEDEX & EMAIL Planning and Land Use Management Committee City

More information

CITY PLANNING COMMISSION MINUTES March 18, 2004

CITY PLANNING COMMISSION MINUTES March 18, 2004 CITY PLANNING COMMISSION MINUTES March 18, 2004 The regular meeting of the City Planning Commission convened Thursday, March 18 at 1:37 pm in the City Council Chambers, 333 W. Ocean Boulevard. PRESENT:

More information

Sequential Flood Risk Test for Mid Sussex Neighbourhood Plans

Sequential Flood Risk Test for Mid Sussex Neighbourhood Plans Sequential Flood Risk Test for Mid Sussex Neighbourhood Plans Introduction This Sequential Test has been prepared to assess the flood risk of sites within the parish that have been identified as suitable,

More information

STAFF REPORT. Nishi Student Housing Application: Processing Directions

STAFF REPORT. Nishi Student Housing Application: Processing Directions STAFF REPORT DATE: October 17, 2017 TO: FROM: SUBJECT: City Council Mike Webb, Assistant City Manager Ashley Feeney, Assistant Director Community Development & Sustainability Katherine Hess, Community

More information

RECEIVE A REPORT AND APPROVE PROPOSED PUBLIC ENGAGEMENT POLICIES AND PRACTICES FOR THE PUBLIC

RECEIVE A REPORT AND APPROVE PROPOSED PUBLIC ENGAGEMENT POLICIES AND PRACTICES FOR THE PUBLIC J-17 STAFF REPORT MEETING DATE: October 24, 2017 TO: City Council FROM: Russ Thompson, Public Works Director PRESENTER: Russ Thompson, Public Works Director SUBJECT: RECEIVE A REPORT AND APPROVE PROPOSED

More information

CITY OF LOS ANGELES INTER-DEPARTMENTAL CORRESPONDENCE. Honorable Members of the Planning and Land Use Management Committee

CITY OF LOS ANGELES INTER-DEPARTMENTAL CORRESPONDENCE. Honorable Members of the Planning and Land Use Management Committee FORM GEN. 60 CITY OF LOS ANGELES INTER-DEPARTMENTAL CORRESPONDENCE 00-050-0000 Date: November 0, 05 To: Honorable Members of the Planning and Land Use Management Committee From: Miguel A. Santana City

More information

SANTA BARBARA COUNTY PLANNING COMMISSION Staff Report/Work Program for FY Long Range Planning Division Planning and Development Department

SANTA BARBARA COUNTY PLANNING COMMISSION Staff Report/Work Program for FY Long Range Planning Division Planning and Development Department SANTA BARBARA COUNTY PLANNING COMMISSION Staff Report/Work Program for FY 2016-2017 Long Range Planning Division Planning and Development Department Hearing Date: February 24, 2016 Staff Report Date: February

More information

CITY OF SASKATOON COUNCIL POLICY

CITY OF SASKATOON COUNCIL POLICY ORIGIN/AUTHORITY Planning and Operations Committee Reports 2-2013 and 13-2013 ADOPTED BY: City Council CITY FILE NO. CK. 230-3 1 of 20 1. PURPOSE 1.1 To establish a policy that is consistent with Industry

More information

CAPITAL IMPROVEMENTS ELEMENT GOALS, OBJECTIVES AND POLICIES. Goal 1: [CI] (EFF. 7/16/90)

CAPITAL IMPROVEMENTS ELEMENT GOALS, OBJECTIVES AND POLICIES. Goal 1: [CI] (EFF. 7/16/90) CAPITAL IMPROVEMENTS ELEMENT GOALS, OBJECTIVES AND POLICIES Goal 1: [CI] (EFF. 7/16/90) To use sound fiscal policies to provide adequate public facilities concurrent with, or prior to development in order

More information

Regulations Regarding Preliminary Flood Risk Assessment, Flood Maps and Flood Risk Management Plan

Regulations Regarding Preliminary Flood Risk Assessment, Flood Maps and Flood Risk Management Plan Text consolidated by Valsts valodas centrs (State Language Centre) with amending regulations of: 20 March 2012 [shall come into force from 23 March 2012]. If a whole or part of a paragraph has been amended,

More information

COMPREHENSIVE PLAN UPDATE EXECUTIVE SUMMARY. Plan Abstract

COMPREHENSIVE PLAN UPDATE EXECUTIVE SUMMARY. Plan Abstract Village of Swansea, Illinois 10/26/2017 Executive Summary COMPREHENSIVE PLAN UPDATE EXECUTIVE SUMMARY A Plan Abstract The following are excerpts from Swansea s 2017 Comprehensive Plan Update Comprehensive

More information

City Services Appendix

City Services Appendix Technical vices 1.0 Introduction... 1 1.1 The Capital Facilities Plan... 1 1.2 Utilities Plan... 2 1.3 Key Principles Guiding Bremerton s Capital Investments... 3 1.4 Capital Facilities and Utilities Addressed

More information

Rule GREENHOUSE GAS FEE

Rule GREENHOUSE GAS FEE Eastern Kern Air Pollution Control District Rule 301.4 GREENHOUSE GAS FEE STAFF REPORT October 25, 2011 Prepared by Jeremiah Cravens Air Quality Specialist II David L. Jones Air Pollution Control Officer

More information

Value for Money Analysis: Choosing the Best Project Delivery Method. Ken L. Smith, PE, CVS -HDR Engineering, Inc.

Value for Money Analysis: Choosing the Best Project Delivery Method. Ken L. Smith, PE, CVS -HDR Engineering, Inc. Value for Money Analysis: Choosing the Best Project Delivery Method Ken L. Smith, PE, CVS -HDR Engineering, Inc. 1 Overview What is a VfM analysis Why is it used Key VfM components and principles Life

More information

INITIAL STUDY APPLICATION

INITIAL STUDY APPLICATION DEPARTMENT OF PUBLIC WORKS AND PLANNING STEVEN E. WHITE, DIRECTOR INITIAL STUDY APPLICATION INSTRUCTIONS Answer all questions completely. An incomplete form may delay processing of your application. Use

More information

Expenditures & Revenue Summary by Category

Expenditures & Revenue Summary by Category Expenditures & Revenue Summary by Category Expenditure & Revenue Summary by Category 2011 2012 2013 $ Change Over Actual Forecast 2012 Expenditures by Category Salaries, Wages & Benefits 1,276,441 1,279,528

More information

STAFF REPORT. PURPOSE OF REPORT: Information only Discussion Commission Action

STAFF REPORT. PURPOSE OF REPORT: Information only Discussion Commission Action CITY OF LAKEPORT PLANNING COMMISSION STAFF REPORT RE: GPA 09-01/City of Lakeport 2025 General Plan: Recommended changes to the Draft General Plan Planning Commission Resolution #76 Planning Commission

More information

City of Ocoee Quarterly Report First Quarter Fiscal Year

City of Ocoee Quarterly Report First Quarter Fiscal Year City of Ocoee Quarterly Report First Quarter Fiscal Year 2008-2009 Prepared by the Finance Department February 2009 TABLE OF CONTENTS Quarterly Overview...i-iii General Fund... 1 Revenue Comparison Graph...

More information

RE: PROPOSED MANAWATU DISTRICT PLAN CHANGE 55 HEARINGS

RE: PROPOSED MANAWATU DISTRICT PLAN CHANGE 55 HEARINGS 30 November 2016 File: 13/134 DDI: 09 917 4305 Email: kblair@burtonconsultants.co.nz Manawatu District Council Private Bag 10 001 FEILDING 4743 Attention: Hearing Committee: Plan Change 55 By email only:

More information

Proposed Menlo Gateway Project Development Agreement Term Sheet

Proposed Menlo Gateway Project Development Agreement Term Sheet Proposed Menlo Gateway Project Development Agreement Term Sheet Presentation to City Council April 6, 2010 Availability of Final Environmental Impact Report (FEIR) and Fiscal Impact Analysis More Information.

More information

CITY OF LANCASTER FISCAL BUDGET REVENUE SOURCES

CITY OF LANCASTER FISCAL BUDGET REVENUE SOURCES CITY OF LANCASTER FISCAL 2006-07 BUDGET REVENUE SOURCES TAXES The tax raising authority of cities has been severely limited for the past 25 years. Proposition 13 enacted in 1978 amended the California

More information

Metro EXECUTIVE MANAGEMENT AND AUDIT COMMITTEE CONSTRUCTION COMMITTEE JULY 21, 2011 SUBJECT: GREEN CONSTRUCTION POLICY

Metro EXECUTIVE MANAGEMENT AND AUDIT COMMITTEE CONSTRUCTION COMMITTEE JULY 21, 2011 SUBJECT: GREEN CONSTRUCTION POLICY Metro 43 Los Angeles County One Gateway Plaza Metropolitan Transportation Authority Los Angeles, CA 90012-2952 EXECUTIVE MANAGEMENT AND AUDIT COMMITTEE CONSTRUCTION COMMITTEE JULY 21, 2011 SUBJECT: GREEN

More information

CITY OF SIGNAL HILL. California state law requires that each city adopt a General Plan. The General Plan must include:

CITY OF SIGNAL HILL. California state law requires that each city adopt a General Plan. The General Plan must include: CITY OF SIGNAL HILL 2175 Cherry Avenue Signal Hill, CA 90755-3799 AGENDA ITEM TO: FROM: HONORABLE CHAIR AND MEMBERS OF THE CITY COUNCIL SCOTT CHARNEY DIRECTOR OF COMMUNITY DEVELOPMENT SUBJECT: 2014 GENERAL

More information

Planning Commission 101:

Planning Commission 101: : The Nuts and Bolts of Planning March 6, 2019 Panelists» David Early, AICP, Senior Advisor, PlaceWorks» Marc Roberts, City Manager, City of Livermore» Bill Anderson, Director of City and Regional Planning,

More information